NO MATERIAL SATUAN
VOLUME
1 PERSIAPAN
2 PAS 1/2 BATA 1 PC : 5 PS
Batu Bata 70 Buah
PC. Merk Tiga Roda (50 Kg) 0.194 Zak
Pasir pasang 0.045 m3
TENAGA KERJA
Pekerja
Tukang Batu
Kepala Tukang
Mandor
TENAGA KERJA
Pekerja
Tukang Batu
Kepala Tukang
Mandor
TENAGA KERJA
Pekerja
Tukang Batu
Kepala Tukang
Mandor
TENAGA KERJA
Pekerja
Tukang Batu
Kepala Tukang
Mandor
TENAGA KERJA
Pekerja
Tukang Batu
Kepala Tukang
Mandor
TENAGA KERJA
Pekerja
Tukang Batu
Kepala Tukang
Mandor
TENAGA KERJA
Pekerja
Tukang Batu
Kepala Tukang
Mandor
TENAGA KERJA
Pekerja
Tukang Batu
Kepala Tukang
Mandor
TENAGA KERJA
Pekerja
Tukang Batu
Kepala Tukang
Mandor
12 BEKISTING
TRIPLEK 6 MM
KAYU USUK 5/7 6 M 39
PAKU 5 CM
PAKU 3 CM
PAPAN (20 x 2 x 600 )
13 PERPIPAAN
PIPA PVC 2 "
PIPA PVC 1/2"
KERAN 1/2 "
KNEE 2 "
KNEE 1/2 "
keran 2 "
STOP KRAN
SELANG PLASTIK 1/2 "
KNEE L 1/2 "
TEE 1/2 "
lem pipa
PEKERJA 48 m
Pembantu tukang
Tukang batu
kepala tukang
mandor
14 TANAH URUG
TANAH URUG
pekerja
mandor
15 GAJI TUKANG
PEMASANGAN MINIATUR DAN ASESORIS 2
16 ELEKTRONIK
arduino mega 2560
KEYPAD TTP 229
LCD 20X4 + I2C
SENSOR GP2Y0A21
DRIVER MOTOR L298N
MOTOR DC 12V
KABEL PELANGI 20 WARNA(KABEL)
IC BUFFER 74LS07
KABEL SOKET 24 PCS
POWER SUPLAY 5V 2A
POWER SUPLAY 12V 2A
PCB BOLONG
PC ALL IN ONE
UPS
USB HUB
MESIN POMPA AIR OTOMATIS
PINTU
ORNAMEN
CAT AQUAPROF
HARGA BIAYA BIAYA TUKANG
VOLUME SATUAN
SATUAN ( Rp ) (Rp)
Rp 500,000.0
Rp 1,650,991.6
15.105 M2 Rp 800.0 Rp 845,880.0
10.6 Rp 85,250.0 Rp 249,814.0
Rp 150,000.0 Rp 101,958.8
Rp 1,127,449.3
12.084 M2 Rp 800.0 Rp 483,360.0
Rp 85,250.0 Rp 199,851.2
Rp 150,000.0 Rp 81,567.0
Rp 1,632,427.6
38.16 M2 Rp 85,250.0 Rp 338,326.6
Rp 150,000.0 Rp 148,824.0
Rp 516,935.4
12.084 M2 Rp 85,250.0 Rp 107,136.7
Rp 150,000.0 Rp 47,127.6
Rp 9,639,381.2
3.6 M3 Rp 85,250.0 Rp 2,277,198.0
Rp 175,000.0 Rp 314,100.0
Rp 338,030.0 Rp 943,779.8
Rp 60.0 Rp -
58 LONJOR Rp 95,037.0 Rp 5,512,146.0
2 KG Rp 27,300.0 Rp 54,600.0
Rp 1,323,178.2
0.477 M3 Rp 85,250.0 Rp 301,728.7
Rp 175,000.0 Rp 41,618.3
Rp 338,030.0 Rp 125,050.8
Rp 60.0 Rp -
6 LONJOR Rp 95,037.0 Rp 570,222.0
4 LONJOR Rp 53,333.0 Rp 213,332.0
Rp 1,431,679.1
0.35775 M3 Rp 85,250.0 Rp 226,296.6
Rp 175,000.0 Rp 31,213.7
Rp 338,030.0 Rp 93,788.1
Rp 60.0 Rp -
8 LONJOR Rp 95,037.0 Rp 760,296.0
5 LONJOR Rp 53,333.0 Rp 266,665.0
Rp 1,145,442.3
0.151875 M3 Rp 85,250.0 Rp 96,069.3
Rp 175,000.0 Rp 13,251.1
Rp 338,030.0 Rp 39,815.7
Rp 60.0 Rp -
8 LONJOR Rp 95,037.0 Rp 760,296.0
4 LONJOR Rp 53,333.0 Rp 213,332.0
1.65 OH Rp 70,000.0 Rp 17,541.6
0.275 OH Rp 85,000.0 Rp 3,550.1
0.028 OH Rp 90,000.0 Rp 382.7
0.083 OH Rp 95,500.0 Rp 1,203.8 Rp 22,678.2
Rp 771,382.5
3.249 M3 Rp 85,250.0 Rp 276,977.3
Rp 150,000.0 Rp 9,259.7
Rp 11,141,975.0
26 M2 Rp 95,150.0 Rp 2,473,900.0
Rp 85,250.0 Rp 2,216,500.0
Rp 150,000.0 Rp 3,900,000.0
Rp 16,500.0 Rp 429,000.0
Rp 5,955,731.4
15 LEMBAR Rp 105,950.0 Rp 1,589,250.0
0.819 BATANG Rp 3,025,000.0 Rp 2,477,475.0
3 KG Rp 23,000.0 Rp 69,000.0
3 KG Rp 24,100.0 Rp 72,300.0
0.2688 M3 Rp 3,630,000.0 Rp 975,744.0
Rp 3,243,536.0
1 BH Rp 93,750.0 Rp 562,500.0
7 BH Rp 6,300.0 Rp 264,600.0
1 BH Rp 63,500.0 Rp 63,500.0
3 BH Rp 97,500.0 Rp 292,500.0
5 BH Rp 7,050.0 Rp 35,250.0
1 BH Rp 640,450.0 Rp 640,450.0
10 BH Rp 63,500.0 Rp 635,000.0
8M Rp 15,000.0 Rp 120,000.0
4 BH Rp 3,100.0 Rp 12,400.0
5 BH Rp 7,600.0 Rp 38,000.0
5 bh Rp 7,500.0 Rp 37,500.0
Rp 375,000.0
2 M3 Rp 150,000.0 Rp 300,000.0
0.375 oh Rp 90,000.0 Rp 67,500.0
0.025 oh Rp 150,000.0 Rp 7,500.0 Rp 75,000.0
Rp 1,250,000.0
5 hari Rp 250,000.0 Rp 1,250,000.0 Rp 1,250,000.0
Rp 26,020,000.0
2 BH Rp 600,000.0 Rp 1,200,000.0
6 BH Rp 120,000.0 Rp 720,000.0
12 BH Rp 150,000.0 Rp 1,800,000.0
10 BH Rp 215,000.0 Rp 2,150,000.0 Rp 8,255,358.6
6 BH Rp 30,000.0 Rp 180,000.0
6 BH Rp 170,000.0 Rp 1,020,000.0
40 METER Rp 20,000.0 Rp 800,000.0
6 BH Rp 100,000.0 Rp 600,000.0
12 BH Rp 50,000.0 Rp 600,000.0
10 BH Rp 100,000.0 Rp 1,000,000.0
6 BH Rp 150,000.0 Rp 900,000.0
6 BH Rp 20,000.0 Rp 120,000.0
1 BH Rp 8,000,000.0 Rp 8,000,000.0
1 BH Rp 1,500,000.0 Rp 1,500,000.0
1 BH Rp 100,000.0 Rp 100,000.0
1 BH Rp 1,000,000.0 Rp 1,000,000.0
12 BH Rp 250,000.0 Rp 3,000,000.0
1 LS Rp 1,000,000.0 Rp 1,000,000.0
2 KALENG 4KG Rp 165,000.0 Rp 330,000.0
Total Rp 67,725,109.43
Ppn 10 % Rp 6,772,510.94
Rp 74,497,620.37###
Rp 109,301.0
1800
3600
540
Rp 93,301.0
Rp 42,778.5
Rp 42,778.5
Rp 2,773,958.4
Rp 4,001,898.3
Rp 7,542,006.9
Rp 237,421.5
Rp 428,537.5
Rp 183,309.7
Rp 67,573.7
Rp 187,500.0
Rp 1,250,000.0
Rp 26,020,000.0
kerikil
1350
DAFTAR KUANTITAS DAN HARGA
Pekerjaan :
MODEL TES HIDROLIK ALOKASI AIR
Lokasi Pekerjaan : ALOKASI AIR
Tahun Anggaran : 2018
Terbilang : #NAME?
Konsultan Individu
Alokasi Air
Ahmad, ST
NIP : -
DATA ASLI
LUAS KAPASITAS DIMENSI (LEBAR)
NO NAMA HW
LAHAN QD (Q) m3 SPILL INTAKE
1 B TEMUSIK 628 879.2 12 1
2 B TERARA 255 357 12 1.2
3 B/S RUTUS 2360 3304
4 BD PANDANDURI
5 B/S PANDANDURI 1111 1555.4 14.7 2
6 B SUWANGI 3151 4411.4 25 4.5
7 INTAKE SUPLESI 6
8
Ha
1 10000
DATA GAMBAR
LUAS KOORDINAT KAPASITAS DIMENSI (LEBAR)
NO NAMA HW
LAHAN (Q) m3 SPILL INTAKE
1 B TEMUSIK 628 879.2 3
2 B TERARA 255 357 3.6
3 B/S RUTUS 2360 3304
4 BD PANDANDURI 0
5 B/S PANDANDURI 1111 1555.4 6
6 B SUWANGI 3151 4411.4 9
7 INTAKE SUPLESI 6
8
bak 0.25
SLI
DIMENSI (LEBAR) DIMENSI SALURAN LEBAR skala 1 :100 skala 1 : 10000
PENGURAS B B' H SUNGAI m2 cm
1.25 1.8 2.7 0.8 14 6280000 2506 50.12 2512
1.3 1.9 3.1 1.5 14 2550000 1597 31.94 1020
23600000 4858 97.16 9440
- - -
1.5 2 - 1.5 17.6 11110000 3333 66.66 4444
2.5 2.75 3.85 1 28.5 31510000 5613 112.27 12604
1 4.32 1.66 0
216
$ 2,050,000 7
$ 55,000,000 223
$ 457,150,000
MBAR $ 512,150,000
DIMENSI (LEBAR) DIMENSI SALURAN LEBAR
PENGURAS B B' H SUNGAI
3.75 5.4 8.1 2.4 1700000
3.9 5.7 9.3 4.5 5
340000
4.5 6 4.5
5 5.5 7.7 2
3 12.96 4.98
No Nama Nominal tanda tangan
2 M. Fauzi, ST Rp 450,000.0
Rp 1,700,000.0
HARGA BESI
Nama
Diameter Panjang Berat HARGA /KG PERLONJOR
Produk
Besi Beton
Polos
6 mm 12 meter 2.66 Kg Rp 20,050.0 Rp 53,333.0
Besi Beton
Polos
7 mm 12 meter 3.63 Kg Rp 20,050.0 Rp 72,781.5
Besi Beton
Polos
8 mm 12 meter 4.74 Kg Rp 20,050.0 Rp 95,037.0
Besi Beton
Polos
9 mm 12 meter 6 Kg Rp 20,050.0 Rp 120,300.0
Besi Beton
Polos
10 mm 12 meter 7.4 Kg Rp 20,050.0 Rp 148,370.0
Besi Beton
Polos
11 mm 12 meter 8.95 Kg Rp 20,050.0 Rp 179,447.5
Besi Beton
Polos
12 mm 12 meter 10.7 Kg Rp 20,050.0 Rp 214,535.0
Besi Beton
Polos
16 mm 12 meter 19 Kg Rp 20,050.0 Rp 380,950.0
Besi Beton
Polos
19 mm 12 meter 26.8 Kg Rp 20,050.0 Rp 537,340.0
Besi Beton
Polos
22 mm 12 meter 35.8 Kg Rp 20,050.0 Rp 717,790.0
Besi Beton
Polos
25 mm 12 meter 46.2 Kg Rp 20,050.0 Rp 926,310.0
Besi Beton
Polos
28 mm 12 meter 58 Kg Rp 20,050.0 Rp 1,162,900.0
Besi Beton
Polos
32 mm 12 meter 75.72 Kg Rp 20,050.0 Rp 1,518,186.0
BH BH BERAT
7 18.62 Rp 373,331.0
3.6
58 274.92 76.366667 9 42.66 Rp 855,333.0
m m m
0.003 0.19 6 0.00785 2.6847E-05
Februari
KALEND
Maret
Minggu senin Selasa Rabu Kamis Jumat Sabtu Minggu senin Selasa Rabu Kamis
1 2 3 1
4 5 6 7 8 9 10 4 5 6 7 8
11 12 13 14 15 16 17 11 12 13 14 15
18 19 20 21 22 23 24 18 19 20 21 22
25 26 27 28 25 26 27 28 29
Juni Juli
Minggu senin Selasa Rabu Kamis Jumat Sabtu Minggu senin Selasa Rabu Kamis
1 2 1 2 3 4 5
3 4 5 6 7 8 9 8 9 10 11 12
10 11 12 13 14 15 16 15 16 17 18 19
17 18 19 20 21 22 23 22 23 24 25 26
24 25 26 27 28 29 30 29 30 31
Oktober November
Minggu senin Selasa Rabu Kamis Jumat Sabtu Minggu senin Selasa Rabu Kamis
1 2 3 4 5 6 1
7 8 9 10 11 12 13 4 5 6 7 8
14 15 16 17 18 19 20 11 12 13 14 15
21 22 23 24 25 26 27 18 19 20 21 22
28 29 30 31 25 26 27 28 29
KALENDER 2018 April Mei
Jumat Sabtu Minggu senin Selasa Rabu Kamis Jumat Sabtu Minggu senin Selasa Rabu Kamis
2 3 1 2 3 4 5 6 7 1 2 3
9 10 8 9 10 11 12 13 14 6 7 8 9 10
16 17 15 16 17 18 19 20 21 13 14 15 16 17
23 24 22 23 24 25 26 27 28 20 21 22 23 24
30 31 29 30 27 28 29 30 31
Agustus September
Jumat Sabtu Minggu senin Selasa Rabu Kamis Jumat Sabtu Minggu senin Selasa Rabu Kamis
6 7 1 2 3 4
13 14 5 6 7 8 9 10 11 2 3 4 5 6
20 21 12 13 14 15 16 17 18 9 10 11 12 13
27 28 19 20 21 22 23 24 25 16 17 18 19 20
26 27 28 29 30 31 23 24 25 26 27
30
Desember
Jumat Sabtu Minggu senin Selasa Rabu Kamis Jumat Sabtu
2 3 1
9 10 2 3 4 5 6 7 8
16 17 9 10 11 12 13 14 15
23 24 16 17 18 19 20 21 22
30 23 24 25 26 27 28 29
30 31
Jumat Sabtu
4 5
11 12
18 19
25 26
Jumat Sabtu
1
7 8
14 15
21 22
28 29
RAB PROTOTYPE 2
HARGA BIAYA
NO MATERIAL VOLUME SATUAN
SATUAN ( Rp )
1 Selang 1/2 " 2.5 M Rp 7,500.0 Rp 18,750.0
2 Acrilik 5 Mm 1.2 X 2.4 2 Lbr Rp 1,320,000.0 Rp 2,640,000.0
3 Ember Plastik Menengah 1 Bh Rp 20,000.0 Rp 20,000.0
4 Selang 1" 6 M Rp 15,000.0 Rp 90,000.0
5 Sim900A v4 1 Bh Rp 215,000.0 Rp 215,000.0
6 LCD + I2C module 6 bh Rp 85,000.0 Rp 510,000.0
7 Sensor Ultrasonic HC-SR05 12 bh Rp 30,000.0 Rp 360,000.0
8 Keran 1/2 " 3 Bh Rp 12,000.0 Rp 36,000.0
9 Kawat Anti Karat 0.5 Kg Rp 27,500.0 Rp 13,750.0
10 Lem Tembak 40 Bh Rp 1,200.0 Rp 48,000.0
11 Lem Besi 3 Bh Rp 16,000.0 Rp 48,000.0
12 Mata gergaji triplek 5 bh Rp 3,000.0 Rp 15,000.0
13 Mata Gergaji tangan 12 " 1 bh Rp 13,000.0 Rp 13,000.0
14 Adaptor 2A-5V 6 Bh Rp 30,000.0 Rp 180,000.0
15 Kabel pelangi 20 Warna 6 m Rp 18,000.0 Rp 108,000.0
16 Semprotan Standar 1 Bh Rp 30,000.0 Rp 30,000.0
17 Jasa Potong Acrilik 1 Rp 500,000.0 Rp 500,000.0
18 Jasa Ongkir (Belanja OnLine ) 1 Rp 200,000.0 Rp 200,000.0
19 Alat Bor 1 Bh Rp 290,000.0 Rp 290,000.0
20 Mata Bor 1 Set Rp 127,000.0 Rp 127,000.0
21 Palu 1 Bh Rp 65,000.0 Rp 65,000.0
22 Mata Gerinda Besi 2 Bh Rp 10,000.0 Rp 20,000.0
23 Plat Besi Strip 3 mm 5.5 m 3 Batang Rp 150,000.0 Rp 450,000.0
24 Baut 10 mm (Murting ) 30 Bh Rp 5,000.0 Rp 150,000.0
25 Pilox Dop 2 Bh Rp 30,000.0 Rp 60,000.0
26 Karton 3 mm 2 Lbr Rp 20,000.0 Rp 40,000.0
27 Klem 7/8 " 5 Bh Rp 7,500.0 Rp 37,500.0
28 Kunci L 1 Set Rp 80,000.0 Rp 80,000.0
29 Cableties 1 Bungkus Rp 59,000.0 Rp 59,000.0
30 Jasa tukang plat 1 Rp 150,000.0 Rp 150,000.0
31 Acrilik siku 5 mm , 120 cm 2 bh Rp 8,000.0 Rp 16,000.0
32 Lem Acrilic 85 ml 10 bh Rp 45,000.0 Rp 450,000.0
33 Alat Lem Acrilik 1 bh Rp 35,000.0 Rp 35,000.0
34 Kabel jumpel male to female 10 Set Rp 8,000.0 Rp 80,000.0
35 Motor DC 6-12v dengan gearbox 4 bh Rp 45,000.0 Rp 180,000.0
36 Arduino Mega 2560 1 bh Rp 180,000.0 Rp 180,000.0
37 Mesin Air Amara AA106 1 bh Rp 395,000.0 Rp 395,000.0
38 Baut ɸ 5 mm 2 Cm 6 bh Rp 500.0 Rp 3,000.0
39 Baut ɸ 5 mm 9 Cm 3 bh Rp 4,000.0 Rp 12,000.0
40 Ember Besar 3 bh Rp 50,000.0 Rp 150,000.0
41 Keran kompresor 1/4 " 2 Bh Rp 30,000.0 Rp 60,000.0
42 Teakblok 1.2 x 2.4 tebal 19 mm 3 Bh Rp 250,000.0 Rp 750,000.0
43 Kayu usuk 4/6 kelas 2 65 m Rp 15,000.0 Rp 975,000.0
44 Triplek 5 mm 2 Lbr Rp 70,000.0 Rp 140,000.0
45 paku Triplek 1 kg Rp 25,000.0 Rp 25,000.0
46 paku 12 cm 2 kg Rp 23,000.0 Rp 46,000.0
47 Printer bekas (gear Printer) 3 bh Rp 100,000.0 Rp 300,000.0
48 tukang kayu / Acrilic 20 hari Rp 150,000.0 Rp 3,000,000.0
49 fernis 1 kg Rp 70,000.0 Rp 70,000.0
50 seltip kecil 11 bh Rp 3,500.0 Rp 38,500.0
51 Stang gergaji triplek 1 Bh Rp 25,000.0 Rp 25,000.0
52 stop keran 1.5 " 3 Bh Rp 32,000.0 Rp 96,000.0
53 Mur Tandon + drat luar 1.5 " 6 Bh Rp 30,000.0 Rp 180,000.0
54 Pipa Pvc 1,5 " 4 m Rp 38,500.0 Rp 154,000.0
55 Mur Tandon + drat luar 1 " 2 Bh Rp 21,000.0 Rp 42,000.0
56 Lem pipa 1 bh Rp 12,500.0 Rp 12,500.0
57 stop keran 3/4 " 3 bh Rp 26,250.0 Rp 78,750.0
58 Uang Transportasi 1 Rp 150,000.0 Rp 150,000.0
59 Catok C wipro 1 " 1 Bh Rp 13,000.0 Rp 13,000.0
Jumlah Rp 14,230,750.0
Dibulatkan Rp 14,231,000.0
Terbilang #NAME?
RAB PROTOTYPE 1
total semua
Rp 8,600,000.0
Rp 7,500,000.0
total Rp 16,100,000.0
total Rp 3,206,000.0
.000.000 (ke Tiga) RINCIAN PENGGUNAAN U
ONGKIR TANGGAL NO MATERIAL VOLUME
Rp 40,000.0 23/10/2018 1 Parkir 1
29/10/2018 2 bensin 3
14/11/2018 3 akrilik 3 mm 1.2 x 2.4 1
Rp 46,587.0 19/12/2018 4 jajan 1
Rp 45,790.0 22/11/2018 5 masker 50
23/11/2018 6 isi kater 1
Rp 11,580.0 22/11/2018 7 isolsai kertas 2
22/11/2018 8 lem stik kertas 1
Rp 36,044.0
22/11/2018 9 ariel (elektronik) 1
22/11/2018 10 DP maket indokaria 1
22/11/2018 11
22/11/2018 12
22/11/2018 13
Rp 51,652.0 22/11/2018 14
22/11/2018 15
22/11/2018 16
22/11/2018 17
22/11/2018 18
Rp 46,890.0 29/11/2018 19
27/11/2018 20
27/11/2018 21
27/11/2018 22
27/11/2018 23
27/11/2018 24
27/11/2018 25
27/11/2018 26
27/11/2018 27
27/11/2018 28
27/11/2018 29
27/11/2018 30
27/11/2018 31
27/11/2018 32
Rp 25,800.0
27/11/2018 33
27/11/2018 34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
Total
Rp 12,500,000.0
RINCIAN PENGGUNAAN UANG RP 12.500.000 (ke empat) 17/12/2018
HARGA BIAYA
SATUAN ONGKIR TANGGAL
SATUAN ( Rp )
kali Rp 1,000.0 Rp 1,000.0
kali Rp 10,000.0 Rp 30,000.0
lbr Rp 852,500.0 Rp 852,500.0 17/12/2018
kali Rp 15,000.0 Rp 15,000.0 17/12/2018
bh Rp 965.0 Rp 48,250.0 18/12/2018
kotak Rp 9,500.0 Rp 9,500.0 18/12/2018
bh Rp 6,300.0 Rp 12,600.0 18/12/2018
bh Rp 5,400.0 Rp 5,400.0 18/12/2018
Rp 7,500,000.0 Rp 7,500,000.0 17/12/2018
Rp 4,000,000.0 Rp 4,000,000.0 19/12/2018
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Total Rp 12,474,250.0
sisa Rp 25,750.0
keb Asli di tambah
4). Belanja bahan pembuatan model tes Hidrolik Alokasi Air
Acrilik 2 mm 1 x 1 m 6 7 6
Acrilik 3 Mm 1 X 2 m 4 2 4
Acrilik 5 Mm 1.2 X 2.4 m 18 18 18
Acrilik 10 Mm 1.2 X 2.4 m 12 12 12
Acrilik siku 5 mm 120 92 120
Adaptor 2A-5V 20 20 20
Alat Glue gun 1 1 1
Alat Lem Acrilik 8 5 8
Alat Lem Silikon 1 1 1
Amplas no 100, 240 50 25 50
Arduino Mega 2560 Rev 3 Original 12 12 12
Baut 10 mm (Murting ) 500 500 500
Baut sPandek 6 4 6
Baut ɸ 12 mm panjang 100 mm 20 20 20
Baut ɸ 12 mm panjang 80 mm 21 50 21
Baut ɸ 5 mm 9 Cm 16 16 16
Baut ɸ 5 mm 3 Cm 45 40 45
Besi Hollow 40 x 40 x 2 mm, 6 m 13 12 13
Besi Hollow 50 x 50 x 2 mm, 6 m 60 52 60
Besi plat 1.2 x 2.4 2 mm 46 46 46
BESI siku 2 x 2 3 mm 16 16 16
Cableties 3 1 3
Cat besi hollow 100 84 100
Cat meja teakblok 63 42 63
Catok C 10 10 10
COK LISTRIK 6 6 6
Dempul 8 2 8
drat dalam pipa 1 " 20 16 20
drat dalam pipa 1.5 " 15 11 15
drat dalam pipa 3/4 " 9 7 9
drat dalam pipa 2 " 4 1 4
Driver Motor 12 12 12
Gergaji triplek 2 2 2
Gerinda Besi 1 1 1
Isolasi Kertas 100 30 100
Isoprofil alkohol 95 % 1 L 26 8 26
Jangka Sorong 1 1 1
Kabel jumper female to female 33 15 33
Kabel jumper male to female 33 15 33
Kabel jumper male to male 33 15 33
kabel NYMH PUTIH 2 x 0.75 40 34 40
Kabel pelangi 20 Warna 45 45 45
Kacamata Safety 6 6 6
Kawat ikat beton 2 0.5 2
kawat las 7 5 7
Keran 1/2" 12 12 12
Klem 7/8 " 13 13 13
klem gantung pipa 1 " 10 8 10
klem gantung pipa 1.5 " 10 10 10
klem gantung pipa 1/2 " 5 5 5
knee 1 " 27 22 27
knee 3/4 " 6 6 6
knee 1.5 " 16 16 16
Knee 1/2 " 15 15 15
knee 2 " 2 2 2
Kuas 8 8 8
Kunci Pipa 18 " 1 1 1
Kunci T 8, 10, 12, 14 4 4 4
LCD + I2C module Ori 20 20 20
Lem Acrilic 85 ml 95 60 95
Lem besi 18 16 18
Lem G 45 14 45
Lem pipa 20 10 20
Lem Tembak 100 42 100
Lem Silikon 50 5 50
Masker 10 5 10
Mata bor 4 1 4
mata gergai triplek 27 10 27
Mata gerinda amplas 20 10 20
Mata Gerinda Besi 50 40 50
Mata Gerinda potong 8 2 8
Mesin Air Amara AA106 6 5 6
Mesin bor 1 1 1
Mesin stand bor 1 1 1
Modem 1 1 1
Motor DC 6-12v dengan gearbox 10 10 10
Mur Tandon 1 " 16 16 16
Mur Tandon 1.5 " 11 11 11
Mur Tandon 2 " 1 1 1
Penggaris plastik 12 13 12
Penggaris besi 30 cm 3 3 3
Pilox Dop 16 8 16
Pipa 1/2 " 18 18 18
Pipa pvc 1" 28 28 28
Pipa Pvc 1,5 " 30 30 30
Pipa pvc 3/4 " 16 16 16
Pipa pvc AW 2 " 16 16 16
Plat Besi Strip 5 mm 6 m 156 156 156
Sarung tangan tahan panas & tidak kaku 6 6 6
Scroll Machine (Scroll Saw 16") 1 1 1
selotip 75 45 75
semprot WD (pelumas ) 2 2 2
Sensor Ultrasonic HC-SR04 Ori 20 20 20
Serbet 12 5 12
Sim Card 12 12 12
Sim900A v4 ori 11 11 11
Spacer 300 225 300
stop keran 1 " 16 16 16
stop keran 1.5 " 11 11 11
stop keran 2 " 1 1 1
stop keran 3/4 " 7 7 7
Stop watch 7 7 7
Teakblok 1.2 x 2.4 tebal 19 mm 12 10 12
Tee 1/2 " 4 4 4
TERMINAL KUNINGAN 4 LUBANG 6 6 6
Tinner A 5 Liter 8 4 8
Toolbox 1 1 1
Vernis 8 8 8
B Upah tukang
Tukang Acrilik 2 org 30 hari 60 60
Tukang las 2 org 21 hari 42 42
Tukang Cat hollow 1 org 16 hari 16 16
Tukang cat meja teakblok 1 org 4 hari 4 4
Tukang Plat besi 2 org 10 hari 20 20
143,562,720.00
142,934,500 128,181,000 143,563,000
lbr 215,000 1,290,000 1,505,000 628,500
lbr 577,000 2,308,000 1,154,000
m2 544,000 9,792,000 9,792,000
m2 993,000 11,916,000 11,916,000
m 11,000 1,320,000 1,012,000
Bh 30,000 600,000 600,000
bh 68,500 68,500 68,500
bh 35,000 280,000 175,000
bh 60,000 60,000 60,000
lembar 4,500 225,000 112,500
bh 770,000 9,240,000 9,240,000
Bh 5,000 2,500,000 2,500,000
kg 60,000 360,000 240,000
bh 14,500 290,000 290,000
bh 12,500 262,500 625,000
bh 4,000 64,000 64,000
bh 4,000 180,000 160,000
Batang 145,000 1,885,000 1,740,000
Batang 225,000 13,500,000 11,700,000
Kg 22,000 1,012,000 1,012,000
Kg 22,000 352,000 352,000
Bungkus 59,000 177,000 59,000
m2 4,000 400,000 336,000
m2 44,500 2,803,500 1,869,000
bh 125,000 1,250,000 1,250,000
bh 17,500 105,000 105,000
Kg 70,000 560,000 140,000
bh 6,000 120,000 96,000
bh 8,000 120,000 88,000
bh 5,000 45,000 35,000
bh 13,000 52,000 13,000
bh 60,000 720,000 720,000
bh 25,000 50,000 50,000
bh 750,000 750,000 750,000
bh 7,500 750,000 225,000
bh 79,000 2,054,000 632,000
bh 75,000 75,000 75,000
Set 8,000 264,000 120,000
Set 8,000 264,000 120,000
Set 8,000 264,000 120,000
m 8,000 320,000 272,000
m 18,000 810,000 810,000
bh 108,000 648,000 648,000
Kg 28,000 56,000 14,000
Kg 40,000 280,000 200,000
Bh 34,000 408,000 408,000
Bh 7,500 97,500 97,500
bh 18,000 180,000 144,000
bh 23,000 230,000 230,000
bh 12,000 60,000 60,000
bh 9,000 243,000 198,000
bh 5,000 30,000 30,000
bh 22,500 360,000 360,000
bh 3,500 52,500 52,500
bh 52,500 105,000 105,000
bh 11,500 92,000 92,000
bh 202,500 202,500 202,500
bh 47,000 188,000 188,000
bh 140,000 2,800,000 2,800,000
bh 45,000 4,275,000 2,700,000
bh 16,000 288,000 256,000
bh 8,500 382,500 119,000
bh 12,000 240,000 120,000
Bh 3,000 300,000 126,000
bh 40,000 2,000,000 200,000
kotak 50,000 500,000 250,000
Set 127,000 508,000 127,000
bh 2,500 67,500 25,000
bh 20,000 400,000 200,000
bh 10,000 500,000 400,000
bh 50,000 400,000 100,000
bh 395,000 2,370,000 1,975,000
bh 825,000 825,000 825,000
bh 250,000 250,000 250,000
Bh 170,000 170,000 170,000
bh 45,000 450,000 450,000
bh 30,000 480,000 480,000
Bh 30,000 330,000 330,000
bh 55,000 55,000 55,000
bh 3,000 36,000 39,000
bh 6,000 18,000 18,000
Bh 30,000 480,000 240,000
M 6,500 117,000 117,000
M 12,500 350,000 350,000
m 38,000 1,140,000 1,140,000
m 8,000 128,000 128,000
m 93,500 1,496,000 1,496,000
Kg 22,000 3,432,000 3,432,000
bh 127,000 762,000 762,000
bh 2,695,000 2,695,000 2,695,000
bh 3,000 225,000 135,000
botol 65,000 130,000 130,000
bh 375,000 7,500,000 7,500,000
bh 10,000 120,000 50,000
Bh 10,000 120,000 120,000
Bh 297,000 3,267,000 3,267,000
Bh 2,000 600,000 450,000
bh 240,000 3,840,000 3,840,000
Bh 432,000 4,752,000 4,752,000
bh 640,500 640,500 640,500
bh 97,000 679,000 679,000
BH 50,000 350,000 350,000
Bh 387,500 4,650,000 3,875,000
bh 7,500 30,000 30,000
bh 35,000 210,000 210,000
kaleng 85,000 680,000 340,000
bh 250,000 250,000 250,000
Liter 43,500 348,000 348,000
13,607,000 13,607,000
129,327,500
No Uraian Kegiatan Volume Pekerjaan
A Bahan-Maket
1 Acrilik 2 mm 1 x 1 m 6 lbr
2 Acrilik 3 Mm 1 X 2 m 4 lbr
3 Acrilik 5 Mm 1.2 X 2.4 m 18 m2
4 Acrilik 10 Mm 1.2 X 2.4 m 12 m2
5 Acrilik siku 5 mm 120 m
6 Adaptor 2A-5V 20 Bh
7 Alat Glue gun 1 bh
8 Alat Lem Acrilik 8 bh
9 Alat Lem Silikon 1 bh
10 Amplas no 100, 240 50 lembar
12 Arduino Mega 2560 Rev 3 Original 12 bh
13 Baut 10 mm (Murting ) 500 Bh
14 Baut sPandek 6 kg
15 Baut ɸ 12 mm panjang 100 mm 20 bh
16 Baut ɸ 12 mm panjang 80 mm 21 bh
17 Baut ɸ 5 mm 9 Cm 16 bh
18 Baut ɸ 5 mm 3 Cm 45 bh
19 Besi Hollow 40 x 40 x 2 mm, 6 m 13 Batang
20 Besi Hollow 50 x 50 x 2 mm, 6 m 60 Batang
21 Besi plat 1.2 x 2.4 2 mm 46 Kg
22 BESI siku 2 x 2 3 mm 16 Kg
23 Cableties 3 Bungkus
24 Cat besi hollow 100 m2
25 Cat meja teakblok 63 m2
26 Catok C 10 bh
27 COK LISTRIK 6 bh
28 Dempul 8 Kg
29 drat dalam pipa 1 " 20 bh
30 drat dalam pipa 1.5 " 15 bh
31 drat dalam pipa 3/4 " 9 bh
32 drat dalam pipa 2 " 4 bh
33 Driver Motor 12 bh
34 Gergaji triplek 2 bh
35 Gerinda Besi 1 bh
36 Isolasi Kertas 100 bh
37 Isoprofil alkohol 95 % 1 L 26 bh
38 Jangka Sorong 1 bh
39 Kabel jumper female to female 33 Set
40 Kabel jumper male to female 33 Set
41 Kabel jumper male to male 33 Set
42 kabel NYMH PUTIH 2 x 0.75 40 m
43 Kabel pelangi 20 Warna 45 m
44 Kacamata Safety 6 bh
45 Kawat ikat beton 2 Kg
46 kawat las 7 Kg
47 Keran 1/2" 12 Bh
48 Klem 7/8 " 13 Bh
49 klem gantung pipa 1 " 10 bh
50 klem gantung pipa 1.5 " 10 bh
51 klem gantung pipa 1/2 " 5 bh
52 knee 1 " 27 bh
53 knee 3/4 " 6 bh
54 knee 1.5 " 16 bh
55 Knee 1/2 " 15 bh
56 knee 2 " 2 bh
57 Kuas 8 bh
58 Kunci Pipa 18 " 1 bh
59 Kunci T 8, 10, 12, 14 4 bh
60 LCD + I2C module Ori 20 bh
61 Lem Acrilic 85 ml 95 bh
62 Lem besi 18 bh
63 Lem G 45 bh
64 Lem pipa 20 bh
65 Lem Tembak 100 Bh
66 Lem Silikon 50 bh
67 Masker 10 kotak
68 Mata bor 4 Set
69 mata gergai triplek 27 bh
70 Mata gerinda amplas 20 bh
71 Mata Gerinda Besi 50 bh
72 Mata Gerinda potong 8 bh
73 Mesin Air Amara AA106 6 bh
74 Mesin bor 1 bh
75 Mesin stand bor 1 bh
76 Modem 1 Bh
77 Motor DC 6-12v dengan gearbox 10 bh
78 Mur Tandon 1 " 16 bh
79 Mur Tandon 1.5 " 11 Bh
80 Mur Tandon 2 " 1 bh
81 Penggaris plastik 12 bh
82 Penggaris besi 30 cm 3 bh
83 Pilox Dop 16 Bh
84 Pipa 1/2 " 18 M
85 Pipa pvc 1" 28 M
86 Pipa Pvc 1,5 " 30 m
87 Pipa pvc 3/4 " 16 m
88 Pipa pvc AW 2 " 16 m
89 Plat Besi Strip 5 mm 6 m 156 Kg
90 Sarung tangan tahan panas & tidak kaku 6 bh
91 Scroll Machine (Scroll Saw 16") 1 bh
92 selotip 75 bh
93 semprot WD (pelumas ) 2 botol
94 Sensor Ultrasonic HC-SR04 Ori 20 bh
95 Serbet 12 bh
96 Sim Card 12 Bh
97 Sim900A v4 ori 11 Bh
98 Spacer 300 Bh
99 stop keran 1 " 16 bh
100 stop keran 1.5 " 11 Bh
101 stop keran 2 " 1 bh
102 stop keran 3/4 " 7 bh
103 Stop watch 7 BH
104 Teakblok 1.2 x 2.4 tebal 19 mm 12 Bh
105 Tee 1/2 " 4 bh
106 TERMINAL KUNINGAN 4 LUBANG 6 bh
107 Tinner A 5 Liter 8 kaleng
108 Toolbox 1 bh
109 Vernis 8 Liter
B Upah tukang
103 Tukang Acrilik 60 OH
104 Tukang las 42 OH
105 Tukang Cat hollow 16 OH
106 Tukang cat meja tealblok 4 OH
107 Tukang Plat besi 20 OH
TOTAL
Rp 362,500.0
Biaya Satuan Jumlah Biaya Penarikan pertama Penarikan Kedua
(Rp) (Rp) Volume pekerjaan Jumlah Volume pekerjaan
Rp 99,000.0 Rp 5,940,000.0 OH Rp - OH
Rp 93,500.0 Rp 3,927,000.0 OH Rp - OH
Rp 93,500.0 Rp 1,496,000.0 OH Rp - OH
Rp 93,500.0 Rp 374,000.0 OH Rp - OH
Rp 93,500.0 Rp 1,870,000.0 OH Rp - OH
Rp 142,934,500.0 Rp 49,256,500.0
Penarikan Kedua Penarikan Ketiga
Jumlah Volume pekerjaan Jumlah jumlah
Rp - OH Rp - 0 Belum Beres
Rp - OH Rp - 0 Belum Beres
Rp - OH Rp - 0 Belum Beres
Rp - OH Rp - 0 Belum Beres
Rp - OH Rp - 0 Belum Beres
Rp 49,728,000.0 Rp 30,708,500.0 Rp 129,693,000.0
Biaya Satuan
No Uraian Kegiatan Volume Pekerjaan
(Rp)
A Bahan-Maket
1 Acrilik 2 mm 1 x 1 m 2 lbr 215,000
2 Acrilik 3 Mm 1 X 2 m 2 lbr 577,000
3 Acrilik 5 Mm 1.2 X 2.4 m 15 m2 544,000
4 Adaptor 2A-5V 10 Bh 30,000
5 Alat Glue gun 1 bh 68,500
6 Alat Lem Acrilik 5 bh 35,000
7 Amplas no 100, 240 10 lembar 4,500
8 Arduino Mega 2560 Rev 3 Original 7 bh 770,000
9 Baut 10 mm (Murting ) 50 Bh 5,000
10 Baut ɸ 12 mm panjang 100 mm 10 bh 14,500
11 Baut ɸ 12 mm panjang 80 mm 50 bh 12,500
12 Baut ɸ 5 mm 9 Cm 16 bh 4,000
13 Besi Hollow 40 x 40 x 2 mm, 6 m 12 Batang 145,000
14 Besi Hollow 50 x 50 x 2 mm, 6 m 48 Batang 225,000
15 Besi plat 1.2 x 2.4 2 mm 20 Kg 22,000
16 Cableties 1 Bungkus 59,000
17 Cat besi hollow 50 m2 4,000
18 Cat meja teakblok 21 m2 44,500
19 Catok C 10 bh 125,000
20 Dempul 2 Kg 70,000
21 Gergaji triplek 2 bh 25,000
22 Gerinda Besi 1 bh 750,000
23 Isolasi Kertas 10 bh 7,500
24 Isoprofil alkohol 95 % 1 L 4 bh 79,000
25 Jangka Sorong 1 bh 75,000
26 Kacamata Safety 6 bh 108,000
27 kawat las 6 Kg 40,000
28 LCD + I2C module Ori 5 bh 140,000
29 Lem Acrilic 85 ml 15 bh 45,000
30 Lem besi 5 bh 16,000
31 Lem Besi 5 Bh 16,000
32 Lem G 14 bh 8,500
33 Lem pipa 6 bh 12,000
34 Lem Tembak 42 Bh 3,000
35 Mata bor 1 Set 127,000
36 mata gergai triplek 5 bh 2,500
37 Mata gerinda amplas 10 bh 20,000
38 Mata Gerinda Besi 40 bh 10,000
39 Mata Gerinda potong 2 bh 50,000
40 Mesin Air Amara AA106 2 bh 395,000
41 Mesin bor 1 bh 825,000
42 Modem 1 Bh 170,000
43 Motor DC 6-12v dengan gearbox 10 bh 45,000
44 Penggaris plastik 13 bh 3,000
45 Sarung tangan tahan panas & tidak kaku 6 bh 127,000
46 Scroll Machine (Scroll Saw 16") 1 bh 2,695,000
47 selotip 20 bh 3,000
48 Serbet 5 bh 10,000
49 Sim Card 5 Bh 10,000
50 Sim900A v4 ori 5 Bh 297,000
51 Spacer 100 Bh 2,000
52 Teakblok 1.2 x 2.4 tebal 19 mm 10 Bh 387,500
53 Tinner A 5 Liter 4 kaleng 85,000
54 Toolbox 1 bh 250,000
Jumlah Biaya
(Rp)
430,000
1,154,000
8,160,000
300,000
68,500
175,000
45,000
5,390,000
250,000
145,000
625,000
64,000
1,740,000
10,800,000
440,000
59,000
200,000
934,500
1,250,000
140,000
50,000
750,000
75,000
316,000
75,000
648,000
240,000
700,000
675,000
80,000
80,000
119,000
72,000
126,000
127,000
12,500
200,000
400,000
100,000
790,000
825,000
170,000
450,000
39,000
762,000
2,695,000
60,000
50,000
50,000
1,485,000
200,000
3,875,000
340,000
250,000
Rp 49,256,500.0
Biaya Satuan
No Uraian Kegiatan Volume Pekerjaan
(Rp)
A Bahan-Maket
1 Acrilik 2 mm 1 x 1 m 4 lbr Rp 215,000.0
2 Acrilik 5 Mm 1.2 X 2.4 m 3 m2 Rp 544,000.0
3 Acrilik 10 Mm 1.2 X 2.4 m 12 m2 Rp 993,000.0
4 Acrilik siku 5 mm 120 m Rp 11,000.0
5 Adaptor 2A-5V 10 Bh Rp 30,000.0
6 Alat Lem Silikon 1 bh Rp 60,000.0
7 Amplas no 100, 240 40 lembar Rp 4,500.0
8 Baut 10 mm (Murting ) 450 Bh Rp 5,000.0
9 Baut sPandek 6 kg Rp 60,000.0
10 Baut ɸ 12 mm panjang 100 mm 10 bh Rp 14,500.0
11 Baut ɸ 5 mm 3 Cm 40 bh Rp 4,000.0
12 Besi Hollow 50 x 50 x 2 mm, 6 m 4 Batang Rp 225,000.0
13 Besi plat 1.2 x 2.4 2 mm 26 Kg Rp 22,000.0
14 BESI siku 2 x 2 3 mm 16 Kg Rp 22,000.0
15 Cableties 1 Bungkus Rp 59,000.0
16 Cat besi hollow 50 m2 Rp 4,000.0
17 Cat meja teakblok 42 m2 Rp 44,500.0
18 Dempul 6 Kg Rp 70,000.0
19 drat dalam pipa 1 " 16 bh Rp 6,000.0
20 drat dalam pipa 1.5 " 11 bh Rp 8,000.0
21 drat dalam pipa 3/4 " 7 bh Rp 5,000.0
22 drat dalam pipa 2 " 1 bh Rp 13,000.0
23 Isolasi Kertas 90 bh Rp 7,500.0
24 Isoprofil alkohol 95 % 1 L 16 bh Rp 79,000.0
25 Kawat ikat beton 1 Kg Rp 28,000.0
26 kawat las 1 Kg Rp 40,000.0
27 Keran 1/2" 12 Bh Rp 34,000.0
28 Klem 7/8 " 13 Bh Rp 7,500.0
29 klem gantung pipa 1 " 10 bh Rp 18,000.0
30 klem gantung pipa 1.5 " 10 bh Rp 23,000.0
31 klem gantung pipa 1/2 " 5 bh Rp 12,000.0
32 knee 1 " 27 bh Rp 9,000.0
33 knee 3/4 " 6 bh Rp 5,000.0
34 knee 1.5 " 16 bh Rp 22,500.0
35 Knee 1/2 " 15 bh Rp 3,500.0
36 knee 2 " 2 bh Rp 52,500.0
37 Kuas 8 bh Rp 11,500.0
38 Kunci Pipa 18 " 1 bh Rp 202,500.0
39 Kunci T 8, 10, 12, 14 4 bh Rp 47,000.0
40 Lem Acrilic 85 ml 30 bh Rp 45,000.0
41 Lem besi 6 bh Rp 16,000.0
42 Lem G 31 bh Rp 8,500.0
43 Masker 10 kotak Rp 50,000.0
44 Mata bor 1 Set Rp 127,000.0
45 mata gergai triplek 5 bh Rp 2,500.0
46 Mata gerinda amplas 5 bh Rp 20,000.0
47 Mata Gerinda Besi 10 bh Rp 10,000.0
48 Mata Gerinda potong 4 bh Rp 50,000.0
49 Mesin Air Amara AA106 1 bh Rp 395,000.0
50 Mesin stand bor 1 bh Rp 250,000.0
51 Mur Tandon 1 " 16 bh Rp 30,000.0
52 Mur Tandon 1.5 " 11 Bh Rp 30,000.0
53 Mur Tandon 2 " 1 bh Rp 55,000.0
54 Penggaris besi 30 cm 3 bh Rp 6,000.0
55 Pilox Dop 12 Bh Rp 30,000.0
56 Plat Besi Strip 5 mm 6 m 100 Kg Rp 22,000.0
57 selotip 55 bh Rp 3,000.0
58 semprot WD (pelumas ) 2 botol Rp 65,000.0
59 Sensor Ultrasonic HC-SR04 Ori 20 bh Rp 375,000.0
60 Serbet 7 bh Rp 10,000.0
61 Spacer 200 Bh Rp 2,000.0
62 stop keran 1 " 10 bh Rp 240,000.0
63 stop keran 1.5 " 5 Bh Rp 432,000.0
64 stop keran 2 " 1 bh Rp 640,500.0
65 stop keran 3/4 " 7 bh Rp 97,000.0
66 Tee 1/2 " 4 bh Rp 7,500.0
67 Tinner A 5 Liter 4 kaleng Rp 85,000.0
68 Vernis 8 Liter Rp 43,500.0
Jumlah Biaya
(Rp)
Rp 860,000.0
Rp 1,632,000.0
Rp 11,916,000.0
Rp 1,320,000.0
Rp 300,000.0
Rp 60,000.0
Rp 180,000.0
Rp 2,250,000.0
Rp 360,000.0
Rp 145,000.0
Rp 160,000.0
Rp 900,000.0
Rp 572,000.0
Rp 352,000.0
Rp 59,000.0
Rp 200,000.0
Rp 1,869,000.0
Rp 420,000.0
Rp 96,000.0
Rp 88,000.0
Rp 35,000.0
Rp 13,000.0
Rp 675,000.0
Rp 1,264,000.0
Rp 14,000.0
Rp 40,000.0
Rp 408,000.0
Rp 97,500.0
Rp 180,000.0
Rp 230,000.0
Rp 60,000.0
Rp 243,000.0
Rp 30,000.0
Rp 360,000.0
Rp 52,500.0
Rp 105,000.0
Rp 92,000.0
Rp 202,500.0
Rp 188,000.0
Rp 1,350,000.0
Rp 96,000.0
Rp 263,500.0
Rp 500,000.0
Rp 127,000.0
Rp 12,500.0
Rp 100,000.0
Rp 100,000.0
Rp 200,000.0
Rp 395,000.0
Rp 250,000.0
Rp 480,000.0
Rp 330,000.0
Rp 55,000.0
Rp 18,000.0
Rp 360,000.0
Rp 2,200,000.0
Rp 165,000.0
Rp 130,000.0
Rp 7,500,000.0
Rp 70,000.0
Rp 400,000.0
Rp 2,400,000.0
Rp 2,160,000.0
Rp 640,500.0
Rp 679,000.0
Rp 30,000.0
Rp 340,000.0
Rp 348,000.0
Rp 49,728,000.0
Biaya Satuan
No Uraian Kegiatan Volume Pekerjaan
(Rp)
A Bahan-Maket
1 Acrilik 3 Mm 1 X 2 m 2 lbr Rp 577,000.0
2 Alat Lem Acrilik 3 bh Rp 35,000.0
3 Arduino Mega 2560 Rev 3 Original 5 bh Rp 770,000.0
4 Baut ɸ 5 mm 3 Cm 5 bh Rp 4,000.0
5 Besi Hollow 40 x 40 x 2 mm, 6 m 1 Batang Rp 145,000.0
6 Besi Hollow 50 x 50 x 2 mm, 6 m 8 Batang Rp 225,000.0
7 Cableties 1 Bungkus Rp 59,000.0
8 COK LISTRIK 6 bh Rp 17,500.0
9 drat dalam pipa 1 " 4 bh Rp 6,000.0
10 drat dalam pipa 1.5 " 4 bh Rp 8,000.0
11 drat dalam pipa 3/4 " 2 bh Rp 5,000.0
12 drat dalam pipa 2 " 3 bh Rp 13,000.0
13 Driver Motor 12 bh Rp 60,000.0
14 Isoprofil alkohol 95 % 1 L 6 bh Rp 79,000.0
15 Kabel jumper female to female 33 Set Rp 8,000.0
16 Kabel jumper male to female 33 Set Rp 8,000.0
17 Kabel jumper male to male 33 Set Rp 8,000.0
18 kabel NYMH PUTIH 2 x 0.75 40 m Rp 8,000.0
19 Kabel pelangi 20 Warna 45 m Rp 18,000.0
20 Kawat ikat beton 2 Kg Rp 28,000.0
21 LCD + I2C module Ori 15 bh Rp 140,000.0
22 Lem Acrilic 85 ml 50 bh Rp 45,000.0
23 Lem besi 2 bh Rp 16,000.0
24 Lem pipa 14 bh Rp 12,000.0
58 25 Lem Tembak 55 Bh Rp 3,000.0
26 Lem Silikon 50 bh Rp 40,000.0
27 Mata bor 2 Set Rp 127,000.0
28 mata gergai triplek 17 bh Rp 2,500.0
29 Mata gerinda amplas 5 bh Rp 20,000.0
30 Mata Gerinda potong 2 bh Rp 50,000.0
31 Mesin Air Amara AA106 3 bh Rp 395,000.0
32 Pilox Dop 4 Bh Rp 30,000.0
33 Pipa 1/2 " 18 M Rp 6,500.0
34 Pipa pvc 1" 28 M Rp 12,500.0
30 35 Pipa Pvc 1,5 " 28 m Rp 38,000.0
36 Pipa pvc 3/4 " 16 m Rp 8,000.0
16 37 Pipa pvc AW 2 " 13 m Rp 93,500.0
38 Plat Besi Strip 5 mm 6 m 56 Kg Rp 22,000.0
39 Sim Card 7 Bh Rp 10,000.0
40 Sim900A v4 ori 6 Bh Rp 297,000.0
41 stop keran 1 " 6 bh Rp 240,000.0
42 stop keran 1.5 " 6 Bh Rp 432,000.0
43 Stop watch 7 BH Rp 50,000.0
44 Teakblok 1.2 x 2.4 tebal 19 mm 2 Bh Rp 387,500.0
45 TERMINAL KUNINGAN 4 LUBANG 6 bh Rp 35,000.0
Jumlah Biaya
(Rp)
Rp 1,154,000.0
Rp 105,000.0
Rp 3,850,000.0
Rp 20,000.0
Rp 145,000.0
Rp 1,800,000.0
Rp 59,000.0
Rp 105,000.0
Rp 24,000.0
Rp 32,000.0
Rp 78,000.0
Rp 39,000.0
Rp 720,000.0
Rp 474,000.0
Rp 264,000.0
Rp 264,000.0
Rp 264,000.0
Rp 320,000.0
Rp 810,000.0
Rp 42,000.0
Rp 2,100,000.0
Rp 2,250,000.0
Rp 32,000.0
Rp 168,000.0
Rp 165,000.0
Rp 2,000,000.0
Rp 254,000.0
Rp 42,500.0
Rp 100,000.0
Rp 100,000.0
Rp 1,185,000.0
Rp 120,000.0
Rp 117,000.0
Rp 350,000.0
Rp 1,064,000.0
Rp 128,000.0
Rp 1,215,500.0
Rp 1,232,000.0
Rp 70,000.0
Rp 1,782,000.0
Rp 1,440,000.0
Rp 2,592,000.0
Rp 350,000.0
Rp 775,000.0
Rp 210,000.0
Rp 30,411,000.0 Rp 49,256,500.0 Rp 49,728,000.0 Rp 129,395,500.0 Rp 129,693,000.0
Rp 129,327,500.0 Rp 129,327,500.0
Rp 30,776,500.0 Rp 68,000.0 Rp 365,500.0
Rp 362,500.0
Acrilik 5 Mm 1.2 X 2.4 m 9,792,000
Tukang Acrilik 8,100,000
Tukang las 5,100,000
Tukang Cat hollow 1,800,000
Tukang cat meja tealblok 300,000
Tukang Plat besi 1,500,000
26,592,000