ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2002

PEKERJAAN PERSIAPAN

6 Analisa Biaya Konstruksi Pekerjaan Persiapan


6.1 1 m Pagar sementara dari kayu tinggi 2 meter
6.1.1 Bahan
Dolken kayu Ø 8-10/400 cm 1.250 Btg
Semen Portland 2.500 Kg
Pasir Beton 0.005 m3
Koral Beton 0.009 m3
Kayu 5/7 0.072 m3
Paku biasa 2" - 5" 0.060 Kg
Residu 0.400 Lt

6.1.2 Tenaga
Tukang kayu 0.200 Oh
Pekerja 0.400 Oh
Kepala tukang 0.020 Oh
Mandor 0.020 Oh

6.2 1 m Pagar sementara dari seng gelombang tinggi 2 meter


6.2.1 Bahan
Dolken kayu Ø 8-10/400 cm 1.250 Btg
Semen Portland 2.500 Kg
Seng gelombnag 3" - 5" 1.200 Lbr
Pasir Beton 0.005 m3
Koral Beton 0.009 m3
Kayu 5/7 0.072 m3
Paku biasa 2" - 5" 0.060 Kg
Meni besi 0.450 Kg

6.2.2 Tenaga
Tukang kayu 0.200 Oh
Pekerja 0.400 Oh
Kepala tukang 0.020 Oh
Mandor 0.020 Oh
6.3 1 m Pagar sementara dari kawat duri tinggi 1.8 meter
6.3.1 Bahan
Dolken kayu Ø 8-10/400 cm 1.000 Btg
Semen Portland 2.000 Kg
Kawat duri 25.000 Kg
Pasir Beton 0.005 m3
Koral Beton 0.009 m3
Paku biasa 2" - 5" 0.060 m3

6.3.2 Tenaga
Tukang kayu 0.200 Oh
Pekerja 0.300 Oh
Kepala tukang 0.020 Oh
Mandor 0.020 Oh

6.4 1 m' Pengukuran dan pemasangan bowplank


6.4.1 Bahan
Kayu 5/7 0.012 m3
Paku biasa 2" - 5" 0.020 Kg
Kayu papan 3/20 0.007 m3

6.4.2 Tenaga
Tukang kayu 0.100 Oh
Pekerja 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.005 Oh

6.5 1 m2 Pembuatan kantor sementara dengan lantai plesteran


6.5.1 Bahan
Dolken kayu Ø 8-10/400 cm 1.250 Btg
Kayu 0.180 Kg
Kayu biasa 0.850 Kg
Besi strip 1.100 Kg
Semen Portland 35.000 Kg
Pasir pasang 0.150 m3
Pasir Beton 0.100 m3
Koral Beton 0.150 m3
Bata merah 30.000 bh
Seng plat 0.250 Lbr
Jendela nako 2.000 bh
Kaca polos 0.080 m2
Kunci tanam 0.150 bh
Plywood 4 mm 0.060 Lbr

6.5.2 Tenaga
Tukang kayu 2.000 Oh
Tukang batu 1.000 Oh
Pekerja 2.000 Oh
Kepala tukang 0.300 Oh
Mandor 0.050 Oh

6.6 1 m2 Pembuatan gudang semen dan alat-alat


6.6.1 Bahan
Dolken kayu Ø 8-10/400 cm 1.700 Btg
Kayu 0.210 Kg
Paku biasa 0.300 m3
Semen Portland 10.500 Kg
Pasir Beton 0.030 m3
Koral Beton 0.050 m3
Seng gelombang bljs 32 1.500 Lbr

6.6.2 Tenaga
Tukang kayu 2.000 Oh
Pekerja 1.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.050 Oh

6.7 1 m2 Pembuatan rumah jaga/konstruksi kayu


6.7.1 Bahan
Dolken kayu Ø 8-10/400 cm 3.000 Kg
Kayu 0.276 m3
Paku biasa 0.700 Kg
Seng gelombang bljs 32 1.500 Lbr
6.7.2 Tenaga
Tukang kayu 1.500 Oh
Pekerja 1.000 Oh
Kepala tukang 0.150 Oh
Mandor 0.050 Oh

6.8 1 m2 Membersihkan lapangan dan peralatan


6.8.1 Tenaga
Pekerja 1.000 Oh
Mandor 0.050 Oh

6.9 Pembuatan bedeng buruh


6.9.1 Bahan
Dolken kayu Ø 8-10/400 cm 1.250 Kg
Kayu 0.019 m3
Paku biasa 0.300 Kg
Semen Portland 18.000 Kg
Pasir Beton 0.030 m3
Koral Beton 0.050 m3
Seng gelombang bljs 32 1.500 Lbr
Plywood 4 mm 1.350 Lbr

6.9.2 Tenaga
Tukang kayu 2.000 Oh
Pekerja 1.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.050 Oh

6.10 1 m2 Pembuatan bak adukan ukuran (40x50x20)cm


6.10.1 Bahan
Kayu terenteng 0.036 m3
Paku biasa 0.080 Kg
Kaso 5/7 1.000 Btg

6.10.2 Tenaga
Tukang kayu 0.300 Oh
Mandor 0.002 Oh

6.11 1 m2 Pembuatan Stegger dari bambu, ukuran (40x50x20) cm


6.11.1 Bahan
Bambu Ø6 - 8 /600 cm 1.000 Btg
Tali ijuk 0.250 Kg

6.11.2 Tenaga
Tukang kayu 0.017 Oh
Pekerja 0.002 Oh
Kepala tukang 0.250 Oh
Mandor 0.013 Oh

6.12 1 m2 Pembuatan jalan sementara


6.12.1 Bahan
Batu belah 15/20 0.150 m3
Batu Pecah 5/7 0.090 m3
Batu pasang 0.010 m3

6.12.2 Tenaga
Pekerja 1.000 Oh
Mandor 0.050 Oh

6.13 Bongkaran beton bertulang


6.13.1 Tenaga
Pekerja 6.667 Oh
Mandor 0.333 Oh

6.14 Bongkaran dinding tembok bata merah


6.14.1 Tenaga
Pekerja 6.667 Oh
Mandor 0.333 Oh
6.15 1 m Pasang pagar kawat jaring galvanis, tinggi 1 meter
6.15.1 Bahan
Pagar kawat jaring 0.434 Lbr

6.15.2 Tenaga
Pekerja 0.042 Oh
Kepala tukang 0.004 Oh
Tukang 0.042 Oh
Mandor 0.002 Oh

6.16 1 m Pasang pagar pracetak (5x50x213)cm


6.16.1 Bahan
Panel beton pracetak 0.986 Lbr
Kolom beton pracetak 0.525 Btg
Pasir Beton 0.074 m3
Koral 2/3 0.146 m3
Semen abu-abu 45.000 Kg

6.16.2 Tenaga
Tukang batu 0.125 Oh
Pekerja 0.375 Oh
Kepala tukang 0.012 Oh
Tukang 0.019 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PEKERJAAN TANAH

6 Analisa Biaya Pekerjaan Tanah


6.1 1 m3 Galian tanah biasa sedalam 1 m
6.1.1 Tenaga
Pekerja 0.400 Oh
Tukang gali
Kepala tukang
Mandor 0.040 Oh
6.2 1 m3 Galian tanah biasa sedalam 2 m
6.2.1 Tenaga
Pekerja 0.526 Oh
Tukang gali
Kepala tukang
Mandor 0.052 Oh

6.3 1 m3 Galian tanah biasa sedalam 3 m


6.3.1 Tenaga
Pekerja 0.735 Oh
Tukang gali
Kepala tukang
Mandor 0.073 Oh

6.4 1 m3 Galian tanah Keras sedalam 1 m


6.4.1 Tenaga
Pekerja 0.625 Oh
Tukang gali
Kepala tukang
Mandor 0.062 Oh

6.5 1 m3 Galian tanah cadas sedalam 1 m


6.5.1 Tenaga
Pekerja 1.250 Oh
Tukang gali
Kepala tukang
Mandor 0.125 Oh

6.6 1 m3 Galian tanah lumpur sedalam 1 m


6.6.1 Tenaga
Pekerja 0.823 Oh
Tukang gali
Kepala tukang
Mandor 0.083 Oh

6.7 1 m2 Pekerjaan stripping setinggi 1 m


6.7.1 Tenaga
Pekerja 0.050 Oh
Tukang gali
Kepala tukang
Mandor 0.005 Oh
6.8 1 m3 Pembuangan tanah sejauh 150 m
6.8.1 Tenaga
Pekerja 0.518 Oh
Tukang gali
Kepala tukang
Mandor 0.050 Oh

6.9 1 m3 Urugan kembali


6.9.1 Tenaga
Pekerja 0.192 Oh
Tukang gali
Kepala tukang
Mandor 0.019 Oh

6.10 1 m3 Pemadatan tanah


6.10.1 Tenaga
Pekerja 0.500 Oh
Tukang gali
Kepala tukang
Mandor 0.050 Oh

6.11 1 m3 Urugan pasir


6.11.1 Bahan
Pasir urug 1.200 m3

6.11.2 Tenaga
Pekerja 0.300 Oh
Tukang gali
Kepala tukang
Mandor 0.010 Oh

6.12 1 m3 Lapisan pudel campuran 1 Kp : 3 Ps : 7 TL


6.12.1 Bahan
Pasir urug 0.330 m3
Kapur padam 0.109 m3
Tanah Liat 0.763 m3

6.12.1 Tenaga
Pekerja 0.833 Oh
Tukang batu 0.416 Oh
Kepala tukang 0.040 Oh
Mandor 0.083 Oh

6.13 1 m3 Lapisan pudel campuran 1 Kp : 5 TL


6.13.1 Bahan
Kapur padam 0.200
Tanah Liat 1.000

6.13.2 Tenaga
Pekerja 0.833 Oh
Tukang batu 0.416 Oh
Kepala tukang 0.041 Oh
Mandor 0.081 Oh

6.14 1 m3 Pemasangan lapisan ijuk


6.14.1 Bahan
Ijuk 1.200 m3

6.14.2 Tenaga
Pekerja 0.150 Oh
Tukang batu
Kepala tukang
Mandor 0.015 Oh

6.15 1 m3 Urugan sirtu


6.15.1 Bahan
Sirtu 1.200 m3

Tenaga
Pekerja 0.250 Oh
Tukang gali
Kepala tukang
Mandor 0.025 Oh
6.16 1 m3 Pembuatan jalan sementara, tebal 25 cm
6.16.1 Bahan
Batu belah 0.275 m3
Kerikil 0.030 m3
Pasir 0.050 m3

6.16.2 Tenaga
Pekerja 1.000 Oh
Tukang gali
Kepala tukang
Mandor 0.100 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PEKERJAAN PONDASI

6 Analisa Biaya Pekerjaan Pondasi


6.1 1 m3 Pasang pondasi batu kali, 1 Pc : 1 Ps
6.1.1 Bahan
Batu belah 15/20 cm 1.100 m3
Semen Portland 392.000 Kg
Pasir pasang 0.314 m3

6.1.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.2 1 m3 Pasang pondasi batu kali, 1 Pc : 2 Ps


6.2.1 Bahan
Batu belah 15/20 cm 1.100 m3
Semen Portland 267.000 Kg
Pasir pasang 0.427 m3
6.2.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.3 1 m3 Pasang pondasi batu kali, 1 Pc : 2.5 Ps


6.3.1 Bahan
Batu belah 15/20 cm 1.100 m3
Semen Portland 392.000 Kg
Pasir pasang 0.314 m3

6.3.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.4 1 m3 Pasang pondasi batu kali, 1 Pc : 3 Ps


6.4.1 Bahan
Batu belah 15/20 cm 1.100 m3
Semen Portland 202.000 Kg
Pasir pasang 0.485 m3

6.4.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.5 1 m3 Pasang pondasi batu kali, 1 Pc : 4 Ps


6.5.1 Bahan
Batu belah 15/20 cm 1.100 m3
Semen Portland 163.000 Kg
Pasir pasang 0.520 m3

6.5.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.6 1 m3 Pasang pondasi batu kali, 1 Pc : 5 Ps


6.6.1 Bahan
Batu belah 15/20 cm 1.100 m3
Semen Portland 136.000 Kg
Pasir pasang 0.544 m3

6.6.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.7 1 m3 Pasang pondasi batu kali, 1 Pc : 6 Ps


6.7.1 Bahan
Batu belah 15/20 cm 1.100 m3
Semen Portland 117.000 Kg
Pasir pasang 0.561 m3

6.7.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.8 1 m3 Pasang pondasi batu kali, 1 Pc : 8 Ps


6.8.1 Bahan
Batu belah 15/20 cm 1.100 m3
Semen Portland 91.000 Kg
Pasir pasang 0.561 m3

6.8.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.9 1 m3 Pasang pondasi batu kali, 1 Kp : 1 Sm :1 Ps


6.9.1 Bahan
Batu belah 15/20 cm 1.100 m3
Kapur pasang 0.229 Kg
Semen merah 0.229 Kg
Pasir pasang 0.544 m3

6.9.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.10 1 m3 Pasang pondasi batu kali, 1 Kp : 1 Sm :1 Ps


6.10.1 Bahan
Batu belah 15/20 cm 1.100 Kg
Kapur pasang 0.229 Kg
Semen merah 0.229 Kg
Pasir pasang 0.544 m3

6.10.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh
6.11 1 m3 Pasang pondasi batu kali, 1 Pc : 1/4 Kp :4 Ps
6.11.1 Bahan
Batu belah 15/20 cm 1.100 Kg
Semen Portland 156.000 Kg
Kapur pasang 0.032 Kg
Pasir pasang 0.584 m3

6.11.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.12 1 m3 Pasang pondasi batu kali, 1 Pc : 3 Kp : 10 Ps


6.12.1 Bahan
Batu belah 15/20 cm 1.100 Kg
Semen Portland 61.000 Kg
Kapur pasang 0.147 Kg
Pasir pasang 0.492 m3

6.12.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.13 1 m3 Pasang pondasi batu kali, 1/4 Pc : 1 Kp : 4 Ps


6.13.1 Bahan
Batu belah 15/20 cm 1.100 Kg
Semen Portland 41.000 Kg
Kapur pasang 0.131 Kg
Pasir pasang 0.523 m3

6.13.2 Tenaga
Pekerja 1.500 Oh
Tukang Batu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.075 Oh

6.14 1 m3 Pasang pondasi batu kosong


6.14.1 Bahan
Batu belah 15/20 cm 1.200 Kg
Pasir urug 0.300 m3

6.14.2 Tenaga
Pekerja 0.780 Oh
Tukang Batu 0.390 Oh
Kepala tukang 0.039 Oh
Mandor 0.039 Oh

6.15 1 m3 Pasang pondasi siklop 40% batu kali


6.15.1 Bahan
Besi beton 75.000 Kg
Semen Portland 202.000 Kg
Pasir beton 0.320 m3
Koral beton 0.490 m3
Kawat beton 0.800 Kg

6.15.2 Tenaga
Pekerja 3.000 Oh
Tukang Batu 0.850 Oh
Kepala tukang 0.085 Oh
Mandor 0.150 Oh

6.16 1 m3 Pasang pondasi sumuran diameter 100cm


6.16.1 Bahan
Batu belah 15/20 cm 0.450 Kg
Semen Portland 280.000 Kg
Pasir beton 0.450 m3
Koral beton 0.670 m3

6.16.2 Tenaga
Pekerja 2.300 Oh
Tukang Batu 0.300 Oh
Kepala tukang 0.030 Oh
Mandor 0.080 Oh

6.17 Pembuatan tiang pancang (40x40) cm beton bertulang


6.17.1 Bahan
Pasir urug darat 0.019 m3
Pasir beton 0.094 m3
Koral beton 0.150 m3
Semen Portland 60.500 Kg
Besi beton 45.000 Kg
Kawat beton 0.900 Kg
Kayu kaso 5/7 0.032 m3
Paku 0.120 Kg
Minyak bekisting 0.090 Kg
Plamur tembok 0.240 Kg

6.17.2 Tenaga
Pekerja 1.000 Oh
Tukang Batu 0.670 Oh
Kepala tukang 0.067 Oh
Mandor 0.050 Oh

6.18 Pembuatan tiang pancang (35x35) cm beton bertulang


6.18.1 Bahan
Pasir urug darat 0.016 Oh
Pasir beton 0.080 Oh
Koral beton 0.125 Oh
Semen Portland 49.000 m3
Besi beton 34.500 m3
Kawat beton 0.700 m3
Kayu kaso 5/7 0.027 Oh
Paku 0.120 m3
Minyak bekisting 0.090 Kg
Plamur tembok 0.200 Kg

6.18.2 Tenaga
Pekerja 0.800 Oh
Tukang Batu 0.500 Oh
Kepala tukang 0.050 Oh
Mandor 0.040 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PEKERJAAN DINDING

6 Analisa Biaya Pekerjaan Dinding


6.1 1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 1 Ps
6.1.1 Bahan
Bata merah 5x11x22 cm 140.000 bh
Semen Portland 64.030 Kg
Pasir pasang 0.059 m3

6.1.2 Tenaga
Pekerja 0.650 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.030 Oh

6.2 1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 2 Ps


6.2.1 Bahan
Bata merah 5x11x22 cm 140.000 bh
Semen Portland 43.500 Kg
Pasir pasang 0.080 m3

6.2.2 Tenaga
Pekerja 0.650 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.030 Oh
6.3 1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 3 Ps
6.3.1 Bahan
Bata merah 5x11x22 cm 140.000 bh
Semen Portland 32.950 Kg
Pasir pasang 0.091 m3

6.3.2 Tenaga
Pekerja 0.650 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.030 Oh

6.4 1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 4 Ps


6.4.1 Bahan
Bata merah 5x11x22 cm 140.000 bh
Semen Portland 26.550 Kg
Pasir pasang 0.093 m3

6.4.2 Tenaga
Pekerja 0.650 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.030 Oh

6.5 1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 5 Ps


6.5.1 Bahan
Bata merah 5x11x22 cm 140.000 bh
Semen Portland 22.200 Kg
Pasir pasang 0.102 m3

6.5.2 Tenaga
Pekerja 0.650 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.030 Oh

6.6 1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 6 Ps


6.6.1 Bahan
Bata merah 5x11x22 cm 140.000 bh
Semen Portland 22.200 Kg
Pasir pasang 0.102 m3

6.6.2 Tenaga
Pekerja 0.650 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.030 Oh

6.7 1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 3 Kp : 10 Ps


6.7.1 Bahan
Bata merah 5x11x22 cm 140.000 bh
Semen Portland 10.080 Kg
Pasir pasang 0.093 m3
Kapur pasang 0.028 m3

6.7.2 Tenaga
Pekerja 0.650 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.030 Oh

6.8 1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 1 Ps


6.8.1 Bahan
Bata merah 5x11x22 cm 70.000 bh
Semen Portland 27.800 Kg
Pasir pasang 0.028 m3
6.8.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.9 1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 2 Ps


6.9.1 Bahan
Bata merah 5x11x22 cm 70.000 bh
Semen Portland 18.950 Kg
Pasir pasang 0.038 m3

6.9.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.10 1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 3 Ps


6.10.1 Bahan
Bata merah 5x11x22 cm 70.000 bh
Semen Portland 14.370 Kg
Pasir pasang 0.040 m3

6.10.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.11 1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 4 Ps


6.11.1 Bahan
Bata merah 5x11x22 cm 70.000 bh
Semen Portland 11.500 Kg
Pasir pasang 0.043 m3

6.11.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.12 1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 5 Ps


6.12.1 Bahan
Bata merah 5x11x22 cm 70.000 bh
Semen Portland 9.680 Kg
Pasir pasang 0.045 m3

6.12.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.13 1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 6 Ps


6.13.1 Bahan
Bata merah 5x11x22 cm 70.000 bh
Semen Portland 8.320 Kg
Pasir pasang 0.049 m3

6.13.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.14 1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 8 Ps


6.14.1 Bahan
Bata merah 5x11x22 cm 70.000 bh
Semen Portland 6.500 Kg
Pasir pasang 0.050 m3

6.14.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.15 1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 3 Kp : 10 Ps


6.15.1 Bahan
Bata merah 5x11x22 cm 70.000 bh
Semen Portland 4.500 Kg
Pasir pasang 0.050 m3
Kapur padam 0.015 m3

6.15.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.16 1 m2 Pasangan batu bata tebal 1/2 bata. 1 Kp : 1 Sm : 1 Ps


6.16.1 Bahan
Bata merah 5x11x22 cm 70.000 bh
Semen Portland 0.018 Kg
Pasir pasang 0.018 m3
Kapur padam 0.018 m3

6.16.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh
6.17 1 m2 Pasangan batu bata tebal 1/2 bata. 1 Kp : 1 Sm : 2 Ps
6.17.1 Bahan
Bata merah 5x11x22 cm 70.000 bh
Semen Portland 0.014 Kg
Pasir pasang 0.028 m3
Kapur padam 0.014 m3

6.17.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.18 1 m2 Pasangan dinding Hollowblock (HB.20)


6.18.1 Bahan
Hollow block (HB.20) 12.500 bh
Semen Portland 13.500 Kg
Pasir pasang 0.048 m3
Besi beton polos 1.950 Kg

6.18.2 Tenaga
Pekerja 0.350 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.017 Oh

6.19 1 m2 Pasangan dinding Hollowblock (HB.15)


6.19.1 Bahan
Hollow block (HB.15) 12.500 bh
Semen Portland 10.450 Kg
Pasir pasang 0.038 m3
Besi beton polos 1.950 Kg

6.19.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.015 Oh

6.20 1 m2 Pasangan dinding Hollowblock (HB.10)


6.20.1 Bahan
Hollow block (HB.10) 12.500 bh
Semen Portland 7.500 Kg
Pasir pasang 0.027 m3
Besi beton polos 1.950 Kg

6.20.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.015 Oh

6.21 1 m2 Pasangan dinding Conblock (CB.20)


6.21.1 Bahan
Concrete block (CB. 20) 12.500 bh
Semen Portland 14.050 Kg
Pasir beton 0.004 m3
Pasir pasang 0.042 m3
Besi beton polos 3.870 Kg
Paku biasa 2" - 5" 0.006 Kg
Kayu terenteng 0.001 Kg
Kawat beton 0.030 Kg
koral beton 0.005 Kg

6.21.2 Tenaga
Pekerja 0.370 Oh
Tukang Batu 0.157 Oh
Tukang besi 0.007 Oh
Kepala tukang 0.016 Oh
Mandor 0.019 Oh
6.22 1 m2 Pasangan dinding Conblock (CB.15)
6.22.1 Bahan
Concrete block (CB. 20) 12.500 bh
Semen Portland 10.460 Kg
Pasir beton 0.003 m3
Pasir pasang 0.032 m3
Besi beton polos 0.870 Kg
Paku biasa 2" - 5" 0.004 Kg
Kayu terenteng 0.001 Kg
Kawat beton 0.020 Kg
koral beton 0.004 Kg

6.22.2 Tenaga
Pekerja 0.340 Oh
Tukang Batu 0.130 Oh
Tukang besi 0.007 Oh
Kepala tukang 0.014 Oh
Mandor 0.017 Oh

6.23 1 m2 Pasangan dinding Conblock (CB.10)


6.23.1 Bahan
Concrete block (CB. 20) 12.500 bh
Semen Portland 7.200 Kg
Pasir beton 0.002 m3
Pasir pasang 0.021 m3
Besi beton polos 2.540 Kg
Paku biasa 2" - 5" 0.003 Kg
Kayu terenteng 0.001 Kg
Kawat beton 0.015 Kg
koral beton 0.003 Kg

6.23.2 Tenaga
Pekerja 0.340 Oh
Tukang Batu 0.107 Oh
Tukang besi 0.007 Oh
Kepala tukang 0.011 Oh
Mandor 0.017 Oh
6.24 1 m2 Pasangan dinding lantai
6.24.1 Bahan
Bondbearn 40x20x20 cm 2.500 bh
Semen Portland 5.100 Kg
Pasir beton 0.080 m3
Besi beton polos 1.500 Kg
koral beton 0.150 m3

6.24.2 Tenaga
Pekerja 0.100 Oh
Tukang Batu 0.030 Oh
Tukang besi 0.030 Oh
Kepala tukang 0.006 Oh
Mandor 0.005 Oh

6.25 1 m2 Pasangan dinding roster/terawang (12X11x24) cm


6.25.1 Bahan
Roster/terawang 36.000 bh
Semen Portland 12.800 Kg
Pasir pasang 0.035 m3

6.25.2 Tenaga
Pekerja 0.300 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.26 1 m2 Pasangan bata berongga ukuran (5x11x24) cm


6.26.1 Bahan
Bata berongga 80.000 bh
Semen Portland 23.650 Kg
Pasir pasang 0.570 m3

6.26.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.015 Oh

6.27 1 m2 Pasangan anyaman bambu, rangka kayu


6.27.1 Bahan
Bilik bambu 1.500 m2
Kayu 5/7 0.014 m3
Paku 0.012 Kg
List kayu 2/4 0.003 m3

6.27.2 Tenaga
Pekerja 0.100 Oh
Tukang Batu 0.050 Oh
Kepala tukang 0.005 Oh
Mandor 0.002 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PEKERJAAN PLESTERAN

6 Analisa Biaya Pekerjaan Plesteran


6.1 1 m2 Plesteran 1 Pc : 1 Ps , tebal 15 mm
6.1.1 Bahan
Semen Portland 12.920 Kg
Pasir pasang 0.013 m3

6.1.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.2 1 m2 Plesteran 1 Pc : 2 Ps , tebal 15 mm


6.2.1 Bahan
Semen Portland 8.520 Kg
Pasir pasang 0.017 m3

6.2.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.3 1 m2 Plesteran 1 Pc : 3 Ps , tebal 15 mm


6.3.1 Bahan
Semen Portland 6.480 Kg
Pasir pasang 0.019 m3

6.3.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.4 1 m2 Plesteran 1 Pc : 4 Ps , tebal 15 mm


6.4.1 Bahan
Semen Portland 5.200 Kg
Pasir pasang 0.020 m3

6.4.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.5 1 m2 Plesteran 1 Pc : 5 Ps , tebal 15 mm


6.5.1 Bahan
Semen Portland 4.320 Kg
Pasir pasang 0.022 m3

6.5.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.6 1 m2 Plesteran 1 Pc : 6 Ps , tebal 15 mm


6.6.1 Bahan
Semen Portland 3.800 Kg
Pasir pasang 0.023 m3

6.6.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.7 1 m2 Plesteran 1 Pc : 8 Ps , tebal 15 mm


6.7.1 Bahan
Semen Portland 2.880 Kg
Pasir pasang 0.024 m3

6.7.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.8 1 m2 Plesteran 1 Pc : 0.5 Kp : 3 Ps , tebal 15 mm


6.8.1 Bahan
Semen Portland 5.760 Kg
Kapur padam 0.003 m3
Pasir pasang 0.013 m3

6.8.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.9 1 m2 Plesteran 1 Pc : 3 Kp : 10 Ps , tebal 15 mm


6.9.1 Bahan
Semen Portland 1.840 Kg
Kapur padam 0.006 m3
Pasir pasang 0.014 m3

6.9.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.10 1 m2 Plesteran 0.5 Pc : 1 Kp : 4 Ps , tebal 15 mm


6.10.1 Bahan
Semen Portland 3.000 Kg
Kapur padam 0.005 m3
Pasir pasang 0.019 m3

6.10.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.11 1 m2 Plesteran 1 Kp : 1 Sm : 1 Ps , tebal 15 mm


6.11.1 Bahan
Semen merah 0.009 Kg
Kapur padam 0.009 m3
Pasir pasang 0.009 m3

6.11.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.12 1 m2 Plesteran 1 Kp : 1 Sm : 2 Ps , tebal 15 mm


6.12.1 Bahan
Semen merah 0.007 Kg
Kapur padam 0.007 m3
Pasir pasang 0.015 m3

6.12.2 Tenaga
Pekerja 0.200 Oh
Tukang Batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.010 Oh

6.13 1 m2 Plesteran 1 Pc : 2 Ps , tebal 20 mm


6.13.1 Bahan
Semen Portland 14.280 Kg
Pasir pasang 0.023 m3

6.13.2 Tenaga
Pekerja 0.250 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh

6.14 1 m2 Plesteran 1 Pc : 3 Ps , tebal 20 mm


6.14.1 Bahan
Semen Portland 10.800 Kg
Pasir pasang 0.026 m3

6.14.2 Tenaga
Pekerja 0.250 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh

6.15 1 m2 Plesteran 1 Pc : 4 Ps , tebal 20 mm


6.15.1 Bahan
Semen Portland 8.680 Kg
Pasir pasang 0.028 m3

6.15.2 Tenaga
Pekerja 0.250 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh

6.16 1 m2 Plesteran 1 Pc : 5 Ps , tebal 20 mm


6.16.1 Bahan
Semen Portland 7.290 Kg
Pasir pasang 0.028 m3

6.16.2 Tenaga
Pekerja 0.250 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh

6.17 1 m2 Plesteran 1 Pc : 6 Ps , tebal 20 mm


6.17.1 Bahan
Semen Portland 6.240 Kg
Pasir pasang 0.030 m3

6.17.2 Tenaga
Pekerja 0.250 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh

6.18 1 m2 Plesteran 1 Kp : 1 Sm : 2 Ps , tebal 20 mm


6.18.1 Bahan
Semen merah 0.009 Kg
Kapur padam 0.009 m3
Pasir pasang 0.018 m3

6.18.2 Tenaga
Pekerja 0.250 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh

6.19 1 m2 Plesteran 1 Pc : 2 Ps , tebal 25 mm


6.19.1 Bahan
Semen Portland 15.500 Kg
Pasir pasang 0.013 m3

6.19.2 Tenaga
Pekerja 0.300 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh
6.20 1 m2 Plesteran 1 Pc : 3 Ps , tebal 25 mm
6.20.1 Bahan
Semen Portland 11.750 Kg
Pasir pasang 0.035 m3

6.20.2 Tenaga
Pekerja 0.300 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh

6.21 1 m2 Plesteran 1 Pc : 4 Ps , tebal 25 mm


6.21.1 Bahan
Semen Portland 9.480 Kg
Pasir pasang 0.038 m3

6.21.2 Tenaga
Pekerja 0.300 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh

6.22 1 m2 Plesteran 1 Pc : 5 Ps , tebal 25 mm


6.22.1 Bahan
Semen Portland 7.940 Kg
Pasir pasang 0.039 m3

6.22.2 Tenaga
Pekerja 0.300 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh
6.23 1 m2 Plesteran 1 Pc : 2 Ps , tebal 30 mm
6.23.1 Bahan
Semen Portland 18.650 Kg
Pasir pasang 0.035 m3

6.23.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.015 Oh

6.24 1 m2 Plesteran 1 Pc : 3 Ps , tebal 30 mm


6.24.1 Bahan
Semen Portland 14.150 Kg
Pasir pasang 0.039 m3

6.24.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.015 Oh

6.25 1 m2 Plesteran 1 Pc : 4 Ps , tebal 30 mm


6.25.1 Bahan
Semen Portland 11.380 Kg
Pasir pasang 0.042 m3

6.25.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.015 Oh
6.26 1 m2 Plesteran 1 Pc : 5 Ps , tebal 30 mm
6.26.1 Bahan
Semen Portland 8.190 Kg
Pasir pasang 0.045 m3

6.26.2 Tenaga
Pekerja 0.320 Oh
Tukang Batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.015 Oh

6.27 1 m2 Berapen 1 Pc : 3 Ps , tebal 30 mm


6.27.1 Bahan
Semen Portland 7.070 Kg
Pasir pasang 0.021 m3

6.27.2 Tenaga
Pekerja 0.150 Oh
Tukang Batu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.008 Oh

6.28 1 m2 Berapen 1 Pc : 5 Ps , tebal 15 mm


6.28.1 Bahan
Semen Portland 5.670 Kg
Pasir pasang 0.023 m3

6.28.2 Tenaga
Pekerja 0.150 Oh
Tukang Batu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.008 Oh
6.29 1 m2 Berapen 1 Pc : 2 Ps , tebal 15 mm
6.29.1 Bahan
Semen Portland 9.300 Kg
Pasir pasang 0.018 m3

6.29.2 Tenaga
Pekerja 0.260 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh

6.30 1 m2 Berapen 1 Pc : 3 Ps , tebal 15 mm


6.30.1 Bahan
Semen Portland 7.070 Kg
Pasir pasang 0.021 m3

6.30.2 Tenaga
Pekerja 0.260 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.013 Oh

6.31 1 m2 Plesteran Skoning 1 Pc : 2 Ps


6.31.1 Bahan
Semen Portland 0.500 Kg
Pasir pasang 0.002 m3

6.31.2 Tenaga
Pekerja 0.057 Oh
Tukang Batu 0.038 Oh
Kepala tukang 0.038 Oh
Mandor 0.002 Oh

6.32 1 m2 Plesteran Granito, 1 Pc warna : 2 Granito, tebal 10 mm


6.32.1 Bahan
PC warna 0.144 Kg
Batu Granito 15.000 m3

6.32.2 Tenaga
Pekerja 0.050 Oh
Tukang Batu 0.020 Oh
Kepala tukang 0.002 Oh
Mandor 0.005 Oh

6.33 1 m2 Plesteran Granito, 1 Pc warna : 2 Batu teraso, tebal 10 mm


6.33.1 Bahan
PC warna 0.440 Kg
Batu Teraso 11.500 m3

6.33.2 Tenaga
Pekerja 0.450 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.025 Oh

6.34 1 m2 Plesteran Ciprat, 1 Pc warna : 2 Ps


6.34.1 Bahan
Semen Portland 4.320 Kg
Pasir pasang 0.016 m3

6.34.2 Tenaga
Pekerja 0.250 Oh
Tukang Batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.015 Oh

6.35 1 m2 Plesteran Siar, 1 Pc warna : 2 Ps


6.35.1 Bahan
Semen Portland 4.320 Kg
Pasir pasang 0.016 m3

6.35.2 Tenaga
Pekerja 0.150 Oh
Tukang Batu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.008 Oh

6.36 1 m2 Plesteran waterproof batacote 3 lapis


6.36.1 Bahan
Semen Portland 0.500 Kg
Batacote 2.900 Kg
Pasir pasang 0.006 m3

6.36.2 Tenaga
Pekerja 0.300 Oh
Tukang Batu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.015 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2002


PEKERJAAN KAYU
6 Analisa Biaya Pekerjaan Kayu
6.1 1 m2 Pasang kusen pintu dan jendela kayu
6.1.1 Bahan
Kayu Jati, balok 1.100 m3

6.1.2 Tenaga
Pekerja 6.000 Oh
Tukang Kayu 20.000 Oh
Kepala tukang 2.000 Oh
Mandor 0.300 Oh

6.2 1 m2 Pasang kusen pintu dan jendela kayu kamper


6.2.1 Bahan
Kayu kamper, balok 1.200 m3

6.2.2 Tenaga
Pekerja 6.000 Oh
Tukang Kayu 18.000 Oh
Kepala tukang 2.000 Oh
Mandor 0.300 Oh

6.3 1 m2 Pasang kusen pintu dan jendela kayu borneo


6.3.1 Bahan
Kayu borneo, balok 1.200 m3

6.3.2 Tenaga
Pekerja 6.000 Oh
Tukang Kayu 18.000 Oh
Kepala tukang 2.000 Oh
Mandor 0.300 Oh
6.4 1 m2 Pasang kusen pintu dan jendela kayu damar laut
6.4.1 Bahan
Kayu damar laut, damar laut, balok 1.200 m3

6.4.2 Tenaga
Pekerja 6.000 Oh
Tukang Kayu 18.000 Oh
Kepala tukang 2.000 Oh
Mandor 0.300 Oh

6.5 1 m2 Pasang pintu klamp kayu kamper


6.5.1 Bahan
Kayu Kamper, papan 0.036 m3
Paku biasa 2" - 5" 0.050 Kg

6.5.2 Tenaga
Pekerja 0.350 Oh
Tukang Kayu 1.050 Oh
Kepala tukang 0.105 Oh
Mandor 0.018 Oh

6.6 1 m2 Pasang pintu klamp kayu borneo


6.6.1 Bahan
Kayu borneo, papan 0.036 m3
Paku biasa 2" - 5" 0.050 Kg

6.6.2 Pekerja 0.350 Oh


Tukang Kayu 1.050 Oh
Kepala tukang 0.105 Oh
Mandor 0.018 Oh
6.7 1 m2 Pasang pintu panel kayu jati
6.7.1 Bahan
Kayu jati, papan 0.040 m3

6.7.2 Tenaga
Pekerja 1.000 Oh
Tukang Kayu 2.500 Oh
Kepala tukang 0.250 Oh
Mandor 0.050 Oh

6.8 1 m2 Pasang pintu panel kayu kamper


6.8.1 Bahan
Kayu Kamper, papan 0.040 m3

6.8.2 Tenaga
Pekerja 1.000 Oh
Tukang Kayu 2.500 Oh
Kepala tukang 0.250 Oh
Mandor 0.050 Oh

6.9 1 m2 Pasang pintu dan jendela kaca kayu jati


6.9.1 Bahan
Kayu jati, papan 0.035 m3

6.9.2 Tenaga
Pekerja 0.800 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.040 Oh
6.10 1 m2 Pasang pintu dan jendela kaca kayu kamper
6.10.1 Bahan
Kayu Kamper, papan 0.035 m3

6.10.2 Tenaga
Pekerja 0.800 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.040 Oh

6.11 1 m2 Pasang pintu dan jendela kaca kayu borneo


6.11.1 Bahan
Kayu borneo, papan 0.035 m3

6.11.2 Tenaga
Pekerja 0.800 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.040 Oh

6.12 1 m2 Pasang pintu dan jendela jalusi kayu jati


6.12.1 Bahan
Kayu jati, papan 0.064 m3

6.12.2 Tenaga
Pekerja 1.000 Oh
Tukang Kayu 3.000 Oh
Kepala tukang 0.300 Oh
Mandor 0.300 Oh
6.13 1 m2 Pasang pintu dan jendela jalusi kayu kamper
6.13.1 Bahan
Kayu Kamper, papan 0.064 m3

6.13.2 Tenaga
Pekerja 1.000 Oh
Tukang Kayu 3.000 Oh
Kepala tukang 0.300 Oh
Mandor 0.500 Oh

6.14 1 m2 Pasang pintu plywood rangkap, rangka kayu jati


6.14.1 Bahan
Kayu jati, papan 0.020 m3
Paku biasa 1/2" - 1" 0.030 Kg
Lem kayu 0.300 Ltr
Plywood 4' x 3' x 4 mm 1.000 Lbr

6.14.2 Tenaga
Pekerja 0.600 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.030 Oh

6.15 1 m2 Pasang pintu plywood rangkap, rangka kayu kamper


6.15.1 Bahan
Kayu Kamper, papan 0.020 m3
Paku biasa 1/2" - 1" 0.030 Kg
Lem kayu 0.300 Ltr
Plywood 4' x 3' x 4 mm 1.000 Lbr
6.15.2 Tenaga
Pekerja 0.600 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.030 Oh

6.16 1 m2 Pasang jalusi mati kusen kayu jati


6.16.1 Bahan
Kayu jati, papan 0.060 m3
Paku biasa 1/2" - 1" 0.150 Kg

6.16.2 Tenaga
Pekerja 0.500 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.025 Oh

6.17 1 m2 Pasang jalusi mati kusen kayu kamper


6.17.1 Bahan
Kayu Kamper, papan 0.060 m3
Paku biasa 1/2" - 1" 0.150 Kg

6.17.2 Tenaga
Pekerja 0.500 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.025 Oh

6.18 1 m2 Pasang jalusi mati kusen kayu borneo


6.18.1 Bahan
Kayu borneo, papan 0.020 m3
Paku biasa 1/2" - 1" 0.030 Kg
Lem kayu 0.300 Ltr
Plywood 4' x 3' x 4 mm 1.000 Lbr

6.18.2 Tenaga
Pekerja 0.600 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.030 Oh

6.19 1 m2 Pasang pintu teakwood rangkap, rangka kayu jati


6.19.1 Bahan
Kayu jati, papan 0.020 m3
Paku biasa 1/2" - 1" 0.030 Kg
Lem kayu 0.300 Ltr
Teakwood 4' x 8' x 4 mm 1.000 Lbr

6.19.2 Tenaga
Pekerja 0.600 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.030 Oh

6.20 1 m2 Pasang pintu teakwood rangkap, rangka kayu kamper


6.20.1 Bahan
Kayu Kamper, papan 0.020 m3
Paku biasa 1/2" - 1" 0.300 Kg
Lem kayu 0.300 Ltr
Teakwood 4' x 8' x 4 mm 1.000 Lbr
6.20.2 Tenaga
Pekerja 0.600 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.030 Oh

6.21 1 m2 Pasang pintu plywood & formika, rangka kayu jati


6.21.1 Bahan
Kayu jati, papan 0.020 m3
Paku biasa 1/2" - 1" 0.300 Kg
Lem kayu 0.800 Ltr
Plywood 4'x8'x4mm 1.000 Lbr
Formika 0.500 Lbr

6.21.2 Tenaga
Pekerja 0.600 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.030 Oh

6.22 1 m2 Pasang pintu plywood & formika, rangka kayu kamper


6.22.1 Bahan
Kayu Kamper, papan 0.020 m3
Paku biasa 1/2" - 1" 0.300 Kg
Lem kayu 0.800 Ltr
Plywood 4'x8'x4mm 1.000 Lbr
Formika 4'x8' 0.500 Lbr

6.22.2 Tenaga
Pekerja 0.600 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.030 Oh

6.23 1 m2 Pasang pintu teakwood & formika, rangka kayu jati


6.23.1 Bahan
Kayu Kamper, papan 0.020 m3
Paku biasa 1/2" - 1" 0.300 Kg
Lem kayu 0.800 Ltr
Teakwood 4' x 8' x 4 mm 0.500 Lbr
Formika 4'x8' 0.500 Lbr

6.23.2 Tenaga
Pekerja 0.600 Oh
Tukang Kayu 2.000 Oh
Kepala tukang 0.200 Oh
Mandor 0.030 Oh

6.24 1 m2 Pasang pintu teakwood & formika, rangka kayu kamper (divernis)
6.24.1 Bahan
Kayu Kamper, papan 0.020 m3
Paku biasa 1/2" - 1" 0.300 Kg
Lem kayu 0.800 Ltr
Teakwood 4' x 8' x 4 mm 0.500 Lbr
Vernis 0.500 Ltr
Formika 4'x8' 0.500 Lbr

6.24.2 Tenaga
Pekerja 0.800 Oh
Tukang Kayu 2.500 Oh
Kepala tukang 0.250 Oh
Mandor 0.040 Oh
6.25 1 m2 Pasang pintu formika double, rangka kayu jati
6.25.1 Bahan
Kayu jati, papan 0.020 m3
Paku biasa 1/2" - 1" 0.300 Kg
Lem kayu 1.200 Ltr
Plywood 4'x8'x4mm 1.000 Lbr
Formika 4'x8' 1.000 Lbr

6.25.2 Tenaga
Pekerja 1.000 Oh
Tukang Kayu 2.600 Oh
Kepala tukang 0.260 Oh
Mandor 0.050 Oh

6.26 1 m2 Pasang pintu formika double, rangka kayu kamper


6.26.1 Bahan
Kayu Kamper, papan 0.020 m3
Paku biasa 1/2" - 1" 0.300 Kg
Lem kayu 1.200 Ltr
Plywood 4'x8'x4mm 1.000 Lbr
Formika 4'x8' 1.000 Lbr

6.26.2 Tenaga
Pekerja 1.000 Oh
Tukang Kayu 2.600 Oh
Kepala tukang 0.260 Oh
Mandor 0.050 Oh

6.27 1 m3 Pasang konstruksi kuda-kuda kayu jati


6.27.1 Bahan
Kayu jati, balok 1.100 m3
Besi strip 15.000 Kg
Paku biasa 2" - 5" 0.800 Kg

6.27.2 Tenaga
Pekerja 4.000 Oh
Tukang Kayu 12.000 Oh
Kepala tukang 1.200 Oh
Mandor 0.200 Oh

6.28 1 m3 Pasang konstruksi kuda-kuda kayu kamper


6.28.1 Bahan
Kayu kamper, balok 1.100 m3
Besi strip 15.000 Kg
Paku biasa 2" - 5" 0.800 Kg

6.28.2 Tenaga
Pekerja 4.000 Oh
Tukang Kayu 12.000 Oh
Kepala tukang 1.200 Oh
Mandor 0.200 Oh

6.29 1 m3 Pasang konstruksi kuda-kuda kayu borneo


6.29.1 Bahan
Kayu borneo, balok 1.100 m3
Besi strip 15.000 Kg
Paku biasa 2" - 5" 0.800 Kg

6.29.2 Tenaga
Pekerja 4.000 Oh
Tukang Kayu 12.000 Oh
Kepala tukang 1.200 Oh
Mandor 0.200 Oh
6.30 1 m3 Pasang konstruksi kuda-kuda kayu kruing
6.30.1 Bahan
Kayu kruing, balok 1.100 m3
Besi strip 15.000 Kg
Paku biasa 2" - 5" 0.800 Kg

6.30.2 Tenaga
Pekerja 4.000 Oh
Tukang Kayu 12.000 Oh
Kepala tukang 1.200 Oh
Mandor 0.200 Oh

6.31 1 m3 Pasang kaso + reng genteng kodok kayu kamper


6.31.1 Bahan
Kayu kamper, balok 0.012 m3
Paku biasa 2" - 5" 0.150 Kg

6.31.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.005 Oh

6.32 1 m3 Pasang kaso + reng genteng kodok kayu borneo


6.32.1 Bahan
Kayu borneo, balok 0.012 m3
Paku biasa 2" - 5" 0.150 Kg

6.32.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.005 Oh

6.33 1 m3 Pasang kaso + reng genteng monier kayu jati


6.33.1 Bahan
Kayu jati, balok 0.014 m3
Paku biasa 2" - 5" 0.150 Kg

6.33.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.005 Oh

6.34 1 m3 Pasang kaso + reng genteng monier kayu kamper


6.34.1 Bahan
Kayu kamper, balok 0.014 m3
Paku biasa 2" - 5" 0.150 Kg

6.34.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.005 Oh

6.35 1 m3 Pasang kaso + reng genteng beton kayu borneo


6.35.1 Bahan
Kayu borneo, balok 0.014 m3
Paku biasa 2" - 5" 0.150 Kg
6.35.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.005 Oh

6.36 1 m3 Pasang kaso + reng atap sirap kayu kamper


6.36.1 Bahan
Kayu kamper, balok 0.165 m3
Paku biasa 2" - 5" 0.200 Kg

6.36.2 Tenaga
Pekerja 0.120 Oh
Tukang Kayu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.006 Oh

6.37 1 m3 Pasang kaso + reng atap sirap kayu borneo


6.37.1 Bahan
Kayu borneo, balok 0.165 m3
Paku biasa 2" - 5" 0.200 Kg

6.37.2 Tenaga
Pekerja 0.120 Oh
Tukang Kayu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.006 Oh
6.38 1 m2 Pasang rangka langit-langit ( 1 x 1 ) m, kayu jati
6.38.1 Bahan
Kayu jati, balok 0.012 m3
Paku biasa 2" - 5" 0.100 Kg

6.38.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.075 Oh

6.39 1 m2 Pasang rangka langit-langit ( 1 x 1 ) m, kayu kamper


6.39.1 Bahan
Kayu kamper, balok 0.012 m3
Paku biasa 2" - 5" 0.100 Kg

6.39.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.075 Oh

6.40 1 m2 Pasang rangka langit-langit ( 1 x 1 ) m, kayu borneo


6.40.1 Bahan
Kayu borneo, balok 0.012 m3
Paku biasa 2" - 5" 0.100 Kg

6.40.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.075 Oh

6.41 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu jati


6.41.1 Bahan
Kayu jati, balok 0.023 m3
Paku biasa 2" - 5" 0.150 Kg

6.41.2 Tenaga
Pekerja 0.200 Oh
Tukang Kayu 0.300 Oh
Kepala tukang 0.030 Oh
Mandor 0.010 Oh

6.42 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu kamper


6.42.1 Bahan
Kayu kamper, balok 0.023 m3
Paku biasa 2" - 5" 0.150 Kg

6.42.2 Tenaga
Pekerja 0.200 Oh
Tukang Kayu 0.300 Oh
Kepala tukang 0.030 Oh
Mandor 0.010 Oh

6.43 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu borneo


6.43.1 Bahan
Kayu borneo, balok 0.023 m3
Paku biasa 2" - 5" 0.150 Kg
6.43.2 Tenaga
Pekerja 0.200 Oh
Tukang Kayu 0.300 Oh
Kepala tukang 0.030 Oh
Mandor 0.010 Oh

6.44 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu jati


6.44.1 Bahan
Kayu jati, balok 0.027 m3
Paku biasa 2" - 5" 0.200 Kg

6.44.2 Tenaga
Pekerja 0.250 Oh
Tukang Kayu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.013 Oh

6.45 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu kamper


6.45.1 Bahan
Kayu kamper, balok 0.027 m3
Paku biasa 2" - 5" 0.200 Kg

6.45.2 Tenaga
Pekerja 0.250 Oh
Tukang Kayu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.013 Oh
6.46 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu borneo
6.46.1 Bahan
Kayu borneo, balok 0.027 m3
Paku biasa 2" - 5" 0.200 Kg

6.46.2 Tenaga
Pekerja 0.250 Oh
Tukang Kayu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.013 Oh

6.47 1 m Pasang listplank ( 3 x 20 ) cm, kayu jati


6.47.1 Bahan
Kayu jati, papan 0.007 m3
Paku biasa 2" - 5" 0.050 Kg

6.47.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.005 Oh

6.48 1 m Pasang listplank ( 3 x 20 ) cm, kayu kamper


6.48.1 Bahan
Kayu Kamper, papan 0.007 m3
Paku biasa 2" - 5" 0.050 Kg

6.48.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.005 Oh
6.49 1 m Pasang listplank ( 3 x 20 ) cm, kayu jati
6.49.1 Bahan
Kayu jati, papan 0.011 m3
Paku biasa 2" - 5" 0.050 Kg

6.49.2 Tenaga
Pekerja 0.110 Oh
Tukang Kayu 0.220 Oh
Kepala tukang 0.022 Oh
Mandor 0.005 Oh

6.50 1 m Pasang listplank ( 3 x 30 ) cm, kayu kamper


6.50.1 Bahan
Kayu Kamper, papan 0.011 m3
Paku biasa 2" - 5" 0.050 Kg

6.50.2 Tenaga
Pekerja 0.110 Oh
Tukang Kayu 0.220 Oh
Kepala tukang 0.022 Oh
Mandor 0.005 Oh

6.51 1 m Pasang listplank 2 x ( x 30 ) cm, kayu kamper


6.51.1 Bahan
Kayu Kamper, papan 0.015 m3
Paku biasa 2" - 5" 0.060 Kg
6.51.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.075 Oh

6.52 1 m Pasang listplank 2 x ( 3 x 30 ) cm, kayu kamper


6.52.1 Bahan
Kayu Kamper, papan 0.009 m3
Paku biasa 2" - 5" 0.060 Kg

6.52.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.050 Oh

6.53 1 m Pasang listplank 2 x ( 2 x 30 ) cm, kayu borneo


6.53.1 Bahan
Kayu borneo, papan 0.009 m3
Paku biasa 2" - 5" 0.060 Kg

6.53.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.050 Oh
6.54 1 m2 Pasang rangka dinding pemisah kayu kamper
6.54.1 Bahan
Kayu kamper, balok 0.020 m3
Kayu Kamper, papan 0.007 m3
Paku biasa 2" - 5" 0.100 Kg

6.54.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.075 Oh

6.55 1 m2 Pasang rangka dinding pemisah kayu borneo


6.55.1 Bahan
Kayu borneo, balok 0.020 m3
Kayu borneo, papan 0.007 m3
Paku biasa 2" - 5" 0.100 Kg

6.55.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.075 Oh

6.56 1 m2 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper


6.56.1 Bahan
Kayu kamper, balok 0.020 m3
Kayu Kamper, papan 0.007 m3
Paku biasa 2" - 5" 0.100 Kg

6.56.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.075 Oh

6.57 1 m2 Pasang dinding pemisah plywood rangkap, rangka kayu kamper


6.57.1 Bahan
Kayu kamper, balok 0.020 m3
Kayu Kamper, papan 0.007 m3
Paku biasa 2" - 5" 0.100 Kg
Lem kayu 0.560 Lt
Plywood 4'x8'x4mm 1.000 Lbr

6.57.2 Tenaga
Pekerja 0.200 Oh
Tukang Kayu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.010 Oh

6.58 1 m2 Pasang dinding lambriziring dari papan jati


6.58.1 Bahan
Kayu jati, balok 0.007 m3
Paku biasa 2" - 5" 0.100 Kg
Paku skrup 0.150 Kg

6.58.2 Tenaga
Pekerja 0.600 Oh
Tukang Kayu 10.800 Oh
Kepala tukang 0.180 Oh
Mandor 0.030 Oh
6.59 1 m2 Pasang plywood tebal 4 mm, untuk diding
6.59.1 Bahan
Plywood 4'x8'x4mm 0.400 Lbr
Paku biasa 1/2" - 1" 0.050 Kg

6.59.2 Tenaga
Pekerja 0.025 Oh
Tukang Kayu 0.075 Oh
Kepala tukang 0.008 Oh
Mandor 0.001 Oh

6.60 1 m Pasang list plafond kayu profil


6.60.1 Bahan
kayu profil 1.050 m3

6.60.2 Tenaga
Pekerja 0.021 Oh
Tukang Kayu 0.021 Oh
Kepala tukang 0.002 Oh
Mandor 0.001 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PEKERJAAN BETON

Analisa Biaya Pekerjaan Beton


6.1 1 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr
6.1.1 Bahan
Semen Portland 218.000 Kg
Pasir beton 0.520 m3
Koral beton 0.870 m3
6.1.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh

6.2 1 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 6 Kr


6.2.1 Bahan
Semen Portland 197.000 Kg
Pasir beton 0.470 m3
Koral beton 0.940 m3

6.2.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh

6.3 1 m3 Membuat beton tumbuk, 1 Pc : 4 Ps : 6 Kr


6.3.1 Bahan
Semen Portland 173.000 Kg
Pasir beton 0.570 m3
Koral beton 0.870 m3

6.3.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh
6.4 1 m3 Membuat lantai kerja beton tumbuk, 1 Pc : 3 Ps : 5 Kr
6.4.1 Bahan
Semen Portland 10.000 Kg
Pasir beton 0.260 m3
Koral beton 0.044 m3

6.4.2 Tenaga
Pekerja 1.150 Oh
Tukang batu 0.020 Oh
Kepala tukang 0.002 Oh
Mandor 0.006 Oh

6.5 1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr


6.5.1 Bahan
Semen Portland 232.000 Kg
Pasir beton 0.520 m3
Koral beton 0.780 m3

6.5.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh

6.6 1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 4 Kr


6.6.1 Bahan
Semen Portland 280.000 Kg
Pasir beton 0.450 m3
Koral beton 0.900 m3

6.6.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh

6.7 1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 2.5 Kr


6.7.1 Bahan
Semen Portland 352.000 Kg
Pasir beton 0.560 m3
Koral beton 0.700 m3

6.7.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh

6.8 1 m3 Membuat beton bertulang, 1 Pc : 1.5 Ps : 3 Kr


6.8.1 Bahan
Semen Portland 357.000 Kg
Pasir beton 0.420 m3
Koral beton 0.540 m3

6.8.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh
6.9 1 m3 Membuat beton bertulang, 1 Pc : 1.5 Ps : 2.5 Kr
6.9.1 Bahan
Semen Portland 386.000 Kg
Pasir beton 0.470 m3
Koral beton 0.780 m3

6.9.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh

6.10 1 m3 Membuat beton bertulang, 1 Pc : 1 Ps : 2 Kr


6.10.1 Bahan
Semen Portland 479.000 Kg
Pasir beton 0.370 m3
Koral beton 0.740 m3

6.10.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh

6.11 1 m3 Membuat tiang pancang pretressed beton


6.11.1 Bahan
Semen Portland 440.000 Kg
Pasir beton 0.500 m3
Koral beton 0.800 m3
Rapidrant 4.460 Gln
6.11.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh

6.12 1 m3 Membuat beton dengan puzzith 100 XR


6.12.1 Bahan
Semen Portland 336.000 Kg
Pasir beton 0.540 m3
Koral beton 0.810 m3
Rapidrant 1.000 Gln

6.12.2 Tenaga
Pekerja 1.650 Oh
Tukang batu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.080 Oh

6.13 1 m3 Membuat beton bertulang 1 Pc : 2 Ps : 3 Kr


6.13.1 Bahan
Semen Portland 336.000 Kg
Pasir beton 0.540 m3
Koral beton 0.810 m3

6.13.2 Tenaga
Pekerja 2.000 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 1.000 Oh
6.14 1 m3 Membuat beton bertulang 1 Pc : 2 Ps : 4 Kr
6.14.1 Bahan
Semen Portland 291.000 Kg
Pasir beton 0.470 m3
Koral beton 0.930 m3

6.14.2 Tenaga
Pekerja 2.000 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 1.000 Oh

6.15 1 m3 Membuat beton bertulang 1 Pc : 1.5 Ps : 3 Kr


6.15.1 Bahan
Semen Portland 367.000 Kg
Pasir beton 0.440 m3
Koral beton 0.880 m3

6.15.2 Tenaga
Pekerja 2.000 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 1.000 Oh

6.16 1 m3 Membuat beton bertulang 1 Pc : 1.5 Ps : 2.5 Kr


6.16.1 Bahan
Semen Portland 400.000 Kg
Pasir beton 0.480 m3
Koral beton 0.800 m3

6.16.2 Tenaga
Pekerja 2.000 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 1.000 Oh

6.17 1 m3 Membuat beton bertulang 1 Pc : 1 Ps : 1 Kr


6.17.1 Bahan
Semen Portland 615.000 Kg
Pasir beton 0.520 m3
Koral beton 0.520 m3

6.17.2 Tenaga
Pekerja 2.000 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 1.000 Oh

6.18 1 m3 Membuat beton kedap air dengan storox - 100


6.18.1 Bahan
Semen Portland 400.000 Kg
Pasir beton 0.480 m3
Koral beton 2/3 0.800 m3
Storox - 100 1.200 Kg

6.18.2 Tenaga
Pekerja 2.000 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 1.000 Oh
6.19 1 m3 Memasang waterstop lebar 150 mm
6.19.1 Bahan
Waterstop lebar 150 mm 1.050 m

6.19.2 Tenaga
Pekerja 0.050 Oh
Tukang batu 0.030 Oh
Kepala tukang 0.003 Oh
Mandor 0.002 Oh

6.20 1 m3 Memasang waterstop lebar 200 mm


6.20.1 Bahan
Waterstop lebar 200 mm 1.050 m

6.20.2 Tenaga
Pekerja 0.050 Oh
Tukang batu 0.030 Oh
Kepala tukang 0.003 Oh
Mandor 0.002 Oh

6.21 1 m3 Memasang waterstop lebar 230 mm


6.21.1 Bahan
Waterstop lebar 230 mm 1.050 m

6.21.2 Tenaga
Pekerja 0.550 Oh
Tukang batu 0.035 Oh
Mandor 0.003 Oh
6.22 1 m3 Memasang waterstop lebar 250 mm
6.22.1 Bahan
Waterstop lebar 250 mm 1.050 m

6.22.2 Tenaga
Pekerja 0.550 Oh
Tukang batu 0.035 Oh
Mandor 0.003 Oh

6.23 1 m3 Memasang waterstop lebar 300 mm


6.23.1 Bahan
Waterstop lebar 300 mm 1.050 m

6.23.2 Tenaga
Pekerja 0.550 Oh
Tukang batu 0.035 Oh
Mandor 0.003 Oh

6.24 1 m3 Memasang waterstop lebar 320 mm


6.24.1 Bahan
Waterstop lebar 320 mm 1.050 m

6.24.2 Tenaga
Pekerja 0.550 Oh
Tukang batu 0.035 Oh
Mandor 0.003 Oh
6.25 1 Kg pembesian dengan besi polos atau besi ulir
6.25.1 Bahan
Besi beton(polos/ulir) 1.050 Kg
Kawat beton 0.015 m3

6.25.2 Tenaga
Pekerja 0.007 Oh
Tukang batu 0.007 Oh
Kepala tukang 0.001 Oh
Mandor 0.000 Oh

6.26 1 Kg Kabel presstressed polos/strands


6.26.1 Bahan
Besi presstressed polos 1.050 Kg
Kawat beton 0.010 Kg

6.26.2 Tenaga
Pekerja 0.005 Oh
Tukang batu 0.005 Oh
Kepala tukang 0.001 Oh
Mandor 0.000 Oh

6.27 1 Kg Jaring kawat baja


6.27.1 Bahan
Besi jaring kawat baja 1.020 Kg
Kawat beton 0.805 Kg

6.27.2 Tenaga
Pekerja 0.025 Oh
Tukang batu 0.025 Oh
Kepala tukang 0.003 Oh
Mandor 0.002 Oh

6.28 1 m2 Pasang bekisting untuk pondasi


6.28.1 Bahan
Kayu terenteng 0.040 m3
Paku biasa 2" - 5" 0.300 Kg
Minyak bekisting 0.100 Lt

6.28.2 Tenaga
Pekerja 0.300 Oh
Tukang Kayu 0.260 Oh
Kepala tukang 0.026 Oh
Mandor 0.005 Oh

6.29 1 m2 Pasang bekisting untuk sloof


6.29.1 Bahan
Kayu terenteng 0.045 m3
Paku biasa 2" - 5" 0.300 Kg
Minyak bekisting 0.100 Lt

6.29.2 Tenaga
Pekerja 0.300 Oh
Tukang Kayu 0.260 Oh
Kepala tukang 0.026 Oh
Mandor 0.005 Oh

6.30 1 m2 Pasang bekisting untuk kolom


6.30.1 Bahan
Kayu terenteng 0.040 m3
Paku biasa 2" - 5" 0.400 Kg
Minyak bekisting 0.200 Lt
Balok kayu borneo 0.015 m3
Plywood tebal 9 mm 0.350 Lbr
Dolken kayu galam dia 8 - 10/4 m 2.000 Btg

6.30.2 Tenaga
Pekerja 0.300 Oh
Tukang Kayu 0.300 Oh
Kepala tukang 0.033 Oh
Mandor 0.006 Oh

6.31 1 m2 Pasang bekisting untuk balok


6.31.1 Bahan
Kayu terenteng 0.040 m3
Paku biasa 2" - 5" 0.400 Kg
Minyak bekisting 0.200 Lt
Balok kayu borneo 0.200 m3
Plywood tebal 9 mm 0.350 Lbr
Dolken kayu galam dia 8 - 10/4 m 2.000 Btg

6.31.2 Tenaga
Pekerja 0.320 Oh
Tukang Kayu 0.330 Oh
Kepala tukang 0.033 Oh
Mandor 0.006 Oh

6.32 1 m2 Pasang bekisting untuk lantai


6.32.1 Bahan
Kayu terenteng 0.040 m3
Paku biasa 2" - 5" 0.400 Kg
Minyak bekisting 0.200 Lt
Balok kayu borneo 0.200 m3
Plywood tebal 9 mm 0.350 Lbr
Dolken kayu galam dia 8 - 10/4 m 6.000 Btg

6.32.2 Tenaga
Pekerja 0.320 Oh
Tukang Kayu 0.330 Oh
Kepala tukang 0.033 Oh
Mandor 0.006 Oh

6.33 1 m2 Pasang bekisting untuk dinding


6.33.1 Bahan
Kayu terenteng 0.030 m3
Paku biasa 2" - 5" 0.400 Kg
Minyak bekisting 0.200 Lt
Balok kayu borneo 0.020 m3
Plywood tebal 9 mm 0.350 Lbr
Dolken kayu galam dia 8 - 10/4 m 3.000 Btg
Formtie penjaga jarak bekisting/spacer 4.000 Bh

6.33.2 Tenaga
Pekerja 0.320 Oh
Tukang Kayu 0.330 Oh
Kepala tukang 0.033 Oh
Mandor 0.006 Oh

6.34 1 m2 Pasang bekisting untuk tangga


6.34.1 Bahan
Kayu terenteng 0.030 m3
Paku biasa 2" - 5" 0.400 Kg
Minyak bekisting 0.150 Lt
Balok kayu borneo 0.015 m3
Plywood tebal 9 mm 0.350 Lbr
Dolken kayu galam dia 8 - 10/4 m 2.000 Btg

6.34.2 Tenaga
Pekerja 0.320 Oh
Tukang Kayu 0.330 Oh
Kepala tukang 0.033 Oh
Mandor 0.006 Oh

6.35 1 m3 membuat beton dengan mutu K 225


6.35.1 Bahan
Semen Portland 388.000 Kg
Pasir beton 0.650 m3
Koral beton 0.650 m3

6.35.2 Tenaga
Pekerja 6.000 Oh
Tukang batu 1.000 Oh
Kepala tukang 0.100 Oh
Mandor 0.300 Oh

6.36 1 m3 membuat beton dengan mutu K 275


6.36.1 Bahan
Semen Portland 400.000 Kg
Pasir beton 0.400 m3
Koral beton 0.820 m3

6.36.2 Tenaga
Pekerja 6.000 Oh
Tukang batu 1.000 Oh
Kepala tukang 0.100 Oh
Mandor 0.300 Oh
6.37 1 m2 Pasang jembatan cor
6.37.1 Bahan
Kayu terenteng 0.026 m3
Paku biasa 2" - 5" 0.600 Kg
Dolken kayu galam dia 8 - 10/4 m 0.500 Btg

6.37.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.050 Oh
Kepala tukang 0.005 Oh
Mandor 0.007 Oh

6.38 1 m3 Membuat pondasi beton bertulang (150 kg besi + bekisting)


6.38.1 Bahan
Kayu terenteng 0.200 m3
Paku biasa 2" - 5" 1.500 Kg
Minyak bekisting 0.400 Lt
Besi beton polos 150.000 Kg
Kawat beton 2.250 Kg
Semen Portland 323.000 Kg
Pasir beton 0.520 m3
Koral beton 0.780 m3

6.38.2 Tenaga
Pekerja 3.900 Oh
Tukang Kayu 0.350 Oh
Tukang batu 1.040 Oh
Tukang besi 11.050 Oh
Kepala tukang 0.245 Oh
Mandor 0.165 Oh
6.39 1 m3 Membuat pondasi beton bertulang (200 kg besi + bekisting)
6.39.1 Bahan
Kayu terenteng 0.200 m3
Paku biasa 2" - 5" 1.500 Kg
Minyak bekisting 0.400 Lt
Besi beton polos 150.000 Kg
Kawat beton 2.250 Kg
Semen Portland 323.000 Kg
Pasir beton 0.520 m3
Koral beton 0.780 m3

6.39.2 Tenaga
Pekerja 3.900 Oh
Tukang Kayu 0.350 Oh
Tukang batu 1.040 Oh
Tukang besi 11.050 Oh
Kepala tukang 0.245 Oh
Mandor 0.165 Oh

6.40 1 m3 Membuat kolom beton bertulang (300 kg besi + bekisting)


6.40.1 Bahan
Kayu terenteng 0.400 m3
Paku biasa 2" - 5" 4.000 Kg
Minyak bekisting 2.000 Lt
Besi beton polos 300.000 Kg
Kawat beton 4.500 Kg
Semen Portland 323.000 Kg
Pasir beton 0.520 m3
Koral beton 0.780 m3
Balok kayu borneo 0.150 m3
Plywood tebal 9 mm 3.500 Lbr
Dolken kayu galam dia 8 - 10/4 m 20.000 Btg

6.40.2 Tenaga
Pekerja 7.300 Oh
Tukang Kayu 0.350 Oh
Tukang batu 3.300 Oh
Tukang besi 2.100 Oh
Kepala tukang 0.570 Oh
Mandor 0.250 Oh

6.41 1 m3 Membuat balok beton bertulang (200 kg besi + bekisting)


6.41.1 Bahan
Kayu terenteng 0.320 m3
Paku biasa 2" - 5" 3.200 Kg
Minyak bekisting 1.600 Lt
Besi beton polos 200.000 Kg
Kawat beton 3.000 Kg
Semen Portland 323.000 Kg
Pasir beton 0.520 m3
Koral beton 0.780 m3
Balok kayu borneo 0.140 m3
Plywood tebal 9 mm 2.800 Lbr
Dolken kayu galam dia 8 - 10/4 m 16.000 Btg

6.41.2 Tenaga
Pekerja 5.960 Oh
Tukang Kayu 0.350 Oh
Tukang batu 2.800 Oh
Tukang besi 1.400 Oh
Kepala tukang 0.455 Oh
Mandor 0.208 Oh

6.42 1 m3 Membuat balok beton bertulang (150 kg besi + bekisting)


6.42.1 Bahan
Kayu terenteng 0.320 m3
Paku biasa 2" - 5" 3.200 Kg
Minyak bekisting 1.600 Lt
Besi beton polos 150.000 Kg
Kawat beton 2.250 Kg
Semen Portland 323.000 Kg
Pasir beton 0.520 m3
Koral beton 0.780 m3
Balok kayu borneo 0.140 m3
Plywood tebal 9 mm 2.800 Lbr
Dolken kayu galam dia 8 - 10/4 m 32.000 Btg

6.42.2 Tenaga
Pekerja 5.800 Oh
Tukang Kayu 0.350 Oh
Tukang batu 2.800 Oh
Tukang besi 1.050 Oh
Kepala tukang 0.420 Oh
Mandor 0.185 Oh

6.43 1 m3 Membuat dinding beton bertulang (150 kg besi + bekisting)


6.43.1 Bahan
Kayu terenteng 0.320 m3
Paku biasa 2" - 5" 3.200 Kg
Minyak bekisting 1.600 Lt
Besi beton polos 150.000 Kg
Kawat beton 2.250 Kg
Semen Portland 323.000 Kg
Pasir beton 0.520 m3
Koral beton 0.780 m3
Balok kayu borneo 0.160 m3
Plywood tebal 9 mm 2.800 Lbr
Dolken kayu galam dia 8 - 10/4 m 24.000 Btg

6.43.2 Tenaga
Pekerja 5.600 Oh
Tukang Kayu 0.350 Oh
Tukang batu 2.640 Oh
Tukang besi 1.050 Oh
Kepala tukang 0.400 Oh
Mandor 0.193 Oh

6.44 1 m3 Membuat tangga beton bertulang (200 kg besi + bekisting)


6.44.1 Bahan
Kayu terenteng 0.250 m3
Paku biasa 2" - 5" 3.000 Kg
Minyak bekisting 1.200 Lt
Besi beton polos 200.000 Kg
Kawat beton 3.000 Kg
Semen Portland 323.000 Kg
Pasir beton 0.520 m3
Koral beton 0.780 m3
Balok kayu borneo 0.105 m3
Plywood tebal 9 mm 2.500 Lbr
Dolken kayu galam dia 8 - 10/4 m 14.000 Btg

6.44.2 Tenaga
Pekerja 5.600 Oh
Tukang Kayu 0.350 Oh
Tukang batu 2.300 Oh
Tukang besi 1.400 Oh
Kepala tukang 0.405 Oh
Mandor 0.202 Oh

6.45 1 m' Membuat kolom penguat beton bertulang (11 x 11) cm


6.45.1 Bahan
Kayu terenteng 0.002 m3
Paku biasa 2" - 5" 0.010 Kg
Besi beton polos 3.000 Kg
Kawat beton 0.450 Kg
Semen Portland 4.000 Kg
Pasir beton 0.006 m3
Koral beton 0.009 m3
6.45.2 Tenaga
Pekerja 5.600 Oh
Tukang Kayu 0.350 Oh
Tukang batu 2.300 Oh
Tukang besi 1.400 Oh
Kepala tukang 0.405 Oh
Mandor 0.202 Oh

6.46 1 m' Membuat ring balok beton bertulang (10 x 15) cm


6.46.1 Bahan
kayu albasiah 0.003 m3
Paku biasa 2" - 5" 0.020 Kg
Besi beton polos 3.600 Kg
Kawat beton 0.050 Kg
Semen Portland 5.500 Kg
Pasir beton 0.009 m3
Koral beton 0.015 m3

6.46.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.033 Oh
Tukang batu 0.033 Oh
Tukang besi 0.033 Oh
Kepala tukang 0.010 Oh
Mandor 0.005 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PEKERJAAN PENUTUP ATAP

Analisa Biaya Konstruksi Pekerjaan Penutup Atap


6.1 1 m2 Pasang atap genteng palentong kecil
6.1.1 Bahan
Genteng palentong 25.000 Bh
6.1.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.075 Oh
Kepala tukang 0.008 Oh
Mandor 0.008 Oh

6.2 1 m2 Pasang atap genteng kodok/glazzur


6.2.1 Bahan
Genteng kodok 25.000 Bh

6.2.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.075 Oh
Kepala tukang 0.008 Oh
Mandor 0.008 Oh

6.3 1 m2 Pasang atap genteng palentong super / besar


6.3.1 Bahan
Genteng palentong super 12.000 Bh

6.3.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.075 Oh
Kepala tukang 0.008 Oh
Mandor 0.008 Oh

6.4 1 m2 Pasang genteng bubung palentong


6.4.1 Bahan
Genteng bubung palentong 5.000 Bh
Semen Portland 8.000 Kg
Pasir pasang 0.032 m3

6.4.2 Tenaga
Pekerja 0.400 Oh
Tukang Kayu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.002 Oh

6.5 1 m Pasang bubung genteng kodok glazuur


6.5.1 Bahan
Genteng bubung kodok 5.000 Bh
Semen Portland 8.000 Kg
Pasir pasang 0.032 m3

6.5.2 Tenaga
Pekerja 0.400 Oh
Tukang Kayu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.002 Oh

6.6 1 m Pasang bubung genteng palentong besar


6.6.1 Bahan
Genteng bubung palentong 4.000 Bh
Semen Portland 8.000 Kg
Pasir pasang 0.032 m3
6.6.2

Tenaga
Pekerja 0.400 Oh
Tukang Kayu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.002 Oh
6.7 1 m2 Pasang roof light fibreglass ( 180 x 90 ) cm
6.7.1 Bahan
Roof light fibreglass 0.600 Lbr
Paku biasa 1/2" x 1" 0.050 Kg

6.7.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.067 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.8 1 m2 Pasang atap asbes gelombang ( 2.5 x 0.92 m ) x 5 mm


6.8.1 Bahan
Asbes gelombang 0.500 Lbr
Paku pancing 60 x 230 0.120 Kg

6.8.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.075 Oh
Kepala tukang 0.008 Oh
Mandor 0.008 Oh

6.9 1 m2 Pasang atap asbes gelombang ( 2.25 x 0.92 m ) x 5 mm


6.9.1 Bahan
Asbes gelombang 0.600 Lbr
Paku pancing 60 x 230 0.120 Kg

6.9.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.075 Oh
Kepala tukang 0.008 Oh
Mandor 0.008 Oh

6.10 1 m2 Pasang atap asbes gelombang ( 2.00 x 0.92 m ) x 5 mm


6.10.1 Bahan
Asbes gelombang 0.600 Lbr
Paku pancing 60 x 230 0.120 Kg

6.10.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.11 1 m2 Pasang atap asbes gelombang ( 1.80 x 0.92 m ) x 5 mm


6.11.1 Bahan
Asbes gelombang 0.700 Lbr
Paku pancing 60 x 230 0.120 Kg

6.11.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.12 1 m2 Pasang atap asbes gelombang ( 3.00 x 1.05 m ) x 4 mm


6.12.1 Bahan
Asbes gelombang 0.350 Lbr
Paku pancing 60 x 230 0.120 Kg

6.12.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.13 1 m2 Pasang atap asbes gelombang ( 2.70 x 1.05 m ) x 4 mm


6.13.1 Bahan
Asbes gelombang 0.420 Lbr
Paku pancing 60 x 230 0.120 Kg

6.13.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.14 1 m2 Pasang atap asbes gelombang ( 2.40 x 1.05 m ) x 4 mm


6.14.1 Bahan
Asbes gelombang 0.440 Lbr
Paku pancing 60 x 230 0.120 Kg

6.14.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.067 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh
6.15 1 m2 Pasang atap asbes gelombang ( 2.10 x 1.05 m ) x 4 mm
6.15.1 Bahan
Asbes gelombang 0.510 Lbr
Paku pancing 60 x 230 0.120 Kg

6.15.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.067 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.16 1 m2 Pasang atap asbes gelombang ( 1.5 x 1.05 m ) x 4 mm


6.16.1 Bahan
Asbes gelombang 0.800 Lbr
Paku pancing 60 x 230 0.120 Kg

6.16.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.067 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.17 1 m2 Pasang atap asbes gelombang ( 3.00 x 1.08 m ) x 6 mm


6.17.1 Bahan
Asbes gelombang 0.700 Lbr
Paku pancing 60 x 230 0.120 Kg
6.17.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.067 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.18 1 m2 Pasang atap asbes gelombang ( 2.70 x 1.08 m ) x 6 mm


6.18.1 Bahan
Asbes gelombang 0.380 Lbr
Paku pancing 60 x 230 0.120 Kg

6.18.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.067 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.19 1 m2 Pasang atap asbes gelombang ( 2.40 x 1.08 m ) x 6 mm


6.19.1 Bahan
Asbes gelombang 0.460 Lbr
Paku pancing 60 x 230 0.120 Kg

6.19.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.067 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh
6.20 1 m2 Pasang atap asbes gelombang ( 2.10 x 1.08 m ) x 6 mm
6.20.1 Bahan
Asbes gelombang 0.490 Lbr
Paku pancing 60 x 230 0.120 Kg

6.20.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.067 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.21 1 m2 Pasang atap asbes gelombang (1.80x 1.08 m ) x 6 mm


6.21.1 Bahan
Asbes gelombang 0.570 Lbr
Paku pancing 60 x 230 0.120 Kg

6.21.2 Tenaga
Pekerja 0.140 Oh
Tukang Kayu 0.067 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.22 1 m' Pasang bubung stel gelombang 0.92 m


6.22.1 Bahan
Bubung Stel gelombang 2.400 Lbr
Paku sekrup 3.5 " 6.000 Kg

6.22.2 Tenaga
Pekerja 0.080 Oh
Tukang Kayu 0.125 Oh
Kepala tukang 0.013 Oh
Mandor 0.004 Oh
6.23 1 m' Pasang nok stel gelombang 1.05 m
6.23.1 Bahan
Nok Stel gelombang 2.100 Lbr
Paku sekrup 3.5 " 6.000 Kg

6.23.2 Tenaga
Pekerja 0.080 Oh
Tukang Kayu 0.125 Oh
Kepala tukang 0.013 Oh
Mandor 0.004 Oh

6.24 1 m' Pasang nok stel gelombang 1.08 m


6.24.1 Bahan
Nok Stel gelombang 2.050 Lbr
Paku sekrup 3.5 " 6.000 Kg

6.24.2 Tenaga
Pekerja 0.080 Oh
Tukang Kayu 0.125 Oh
Kepala tukang 0.013 Oh
Mandor 0.004 Oh

6.25 1 m' Pasang nok paten 0.92 m


6.25.1 Bahan
Nok paten 1.200 Lbr
Paku sekrup 3.5 " 6.000 Kg

6.25.2 Tenaga
Pekerja 0.084 Oh
Tukang Kayu 0.125 Oh
Kepala tukang 0.013 Oh
Mandor 0.004 Oh

6.26 1 m' Pasang nok paten 1.05 m


6.26.1 Bahan
Nok paten 1.200 Lbr
Paku sekrup 3.5 " 6.000 Kg

6.26.2 Tenaga
Pekerja 0.084 Oh
Tukang Kayu 0.125 Oh
Kepala tukang 0.013 Oh
Mandor 0.004 Oh

6.27 1 m' Pasang nok paten 1.08 m


6.27.1 Bahan
Nok paten 1.200 Lbr
Paku sekrup 3.5 " 6.000 Kg

6.27.2 Tenaga
Pekerja 0.084 Oh
Tukang Kayu 0.125 Oh
Kepala tukang 0.013 Oh
Mandor 0.004 Oh

6.28 1 m' Pasang nok stel rata 0.92 m


6.28.1 Bahan
Nok stel rata 1.100 Lbr
Paku sekrup 3.5 " 6.000 Kg

6.28.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.150 Oh
Kepala tukang 0.013 Oh
Mandor 0.004 Oh

6.29 1 m' Pasang nok stel rata 1.05 m


6.29.1 Bahan
Nok stel rata 1.100 Lbr
Paku sekrup 3.5 " 6.000 Kg

6.29.2 Tenaga
Pekerja 0.084 Oh
Tukang Kayu 0.125 Oh
Kepala tukang 0.013 Oh
Mandor 0.004 Oh

6.30 1 m2 Pasang atap genteng beton


6.30.1 Bahan
Genteng beton 11.000 Bh
Paku biasa 2" -5" 0.030 Kg

6.30.2 Tenaga
Pekerja 0.200 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.010 Oh
6.31 1 m2 Pasang atap genteng aspal
6.31.1 Bahan
Genteng aspal 6.900 Lbr
Plywood 4" x 8" x 6 mm 0.350 Lbr
Paku biasa 1/2" - 1" 0.030 Kg
Plastic aerator 0.500 Bh

6.31.2 Tenaga
Pekerja 0.200 Oh
Tukang Kayu 0.300 Oh
Kepala tukang 0.003 Oh
Mandor 0.010 Oh

6.32 1 m2 Pasang atap genteng metal


6.32.1 Bahan
Genteng metal 1.020 Lbr
Paku biasa 2" -5" 0.200 Kg

6.32.2 Tenaga
Pekerja 0.200 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.001 Oh

6.33 1 m2 Pasang atap sirap


6.33.1 Bahan
genteng sirap 60.000 Bh
Paku biasa 1/2" - 1" 0.200 Kg
6.33.2 Tenaga
Pekerja 0.166 Oh
Tukang Kayu 0.250 Oh
Kepala tukang 0.008 Oh
Mandor 0.250 Oh

6.34 1 m' Pasang nok genteng beton


6.34.1 Bahan
Nok genteng beton 3.500 Lbr
Paku biasa 2" -5" 0.005 Kg
Semen abu-abu 10.800 m3
Pasir pasang 0.032 m3
Semen warna 1.000 Kg

6.34.2 Tenaga
Pekerja 0.400 Oh
Tukang Kayu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.020 Oh

6.35 1 m' Pasang nok genteng aspal


6.35.1 Bahan
Genteng aspal 2.000 Lbr
Paku biasa 1/2" - 1" 0.050 Kg
Kayu borneo, balok 0.004 m3

6.35.2 Tenaga
Pekerja 0.125 Oh
Tukang Kayu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.006 Oh
6.36 1 m' Pasang nok genteng metal
6.36.1 Bahan
Genteng decra bond 1.100 Lbr
Paku biasa 1/2" - 1" 0.050 Kg

6.36.2 Tenaga
Pekerja 0.250 Oh
Tukang Kayu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.013 Oh

6.37 1 m' Pasang nok `sirap


6.37.1 Bahan
Seng plat 3" x 6" bjls 28 0.400 Lbr
Paku biasa 1/2" - 1" 0.060 Kg
Paku biasa 2" -5" 0.050 Kg
Kayu borneo, papan tebal 3 cm 0.004 m3

6.37.2 Tenaga
Pekerja 0.125 Oh
Tukang Kayu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.006 Oh

6.38 1 m2 Pasang atap seng gelombang


6.38.1 Bahan
Seng gelombang 3" x 6 " bjls 28 0.700 Lbr
Paku biasa 1/2" - 1" 0.020 Kg

6.38.2 Tenaga
Pekerja 0.120 Oh
Tukang Kayu 0.060 Oh
Kepala tukang 0.006 Oh
Mandor 0.006 Oh

6.39 1 m2 Pasang atap nok seng


6.39.1 Bahan
Seng plat 3" x 6 " bjls 28 0.300 Lbr
Paku biasa 1/2" - 1" 0.040 Kg

6.39.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.070 Oh
Kepala tukang 0.008 Oh
Mandor 0.006 Oh

6.40 1 m2 Pasang atap aluminium


6.40.1 Bahan
Atap alumunium gelombang tebal 0.55 1.050 Lbr
Paku hak panjang 15 cm 0.002 Kg

6.40.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.070 Oh
Kepala tukang 0.008 Oh
Mandor 0.006 Oh

6.41 1 m2 Pasang nok aluminium


6.41.1 Bahan
Nok standar 40 cm swg 22 1.200 Lbr
Paku hak panjang 15 cm 0.040 Kg

6.41.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 1.000 Oh
Kepala tukang 0.010 Oh
Mandor 0.010 Oh

6.42 1 m2 Pasang nok aluminium foil sisalation


6.42.1 Bahan
Nok standar 40 cm swg 22 1.050 Lbr

6.42.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.050 Oh
Kepala tukang 0.005 Oh
Mandor 0.008 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PEKERJAAN LANGIT - LANGIT

Analisa Biaya Pekerjaan Langit-langit


6.1 1 m2 Langit - langit asbes ( 1.00 x 1.00 ) m, tebal 6 mm
6.1.1 Bahan
Pelat asbes tebal 6 mm 1.100 Lbr
Paku 0.010 Kg

6.1.2 Tenaga
Pekerja 0.030 Oh
Tukang Kayu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.002 Oh
6.2 1 m2 Langit - langit asbes ( 1.00 x 1.00 ) m, tebal 5 mm
6.2.1 Bahan
Pelat asbes tebal 5 mm 1.100 Lbr
Paku 0.010 Kg

6.2.2 Tenaga
Pekerja 0.030 Oh
Tukang Kayu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.002 Oh

6.3 1 m2 Langit - langit asbes ( 1.00 x 1.00 ) m, tebal 4 mm


6.3.1 Bahan
Pelat asbes tebal 4 mm 1.100 Lbr
Paku 0.010 Kg

6.3.2 Tenaga
Pekerja 0.030 Oh
Tukang Kayu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.002 Oh

6.4 1 m2 Langit - langit asbes ( 1.00 x 1.00 ) m, tebal 3.5 mm


6.4.1 Bahan
Pelat asbes tebal 3.5 mm 1.100 Lbr
Paku 0.010 Kg

6.4.2 Tenaga
Pekerja 0.030 Oh
Tukang Kayu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.002 Oh
6.5 1 m2 Langit - langit akustik ( 30 x 30 ) cm
6.5.1 Bahan
Akustik ( 30 x 30 ) cm 11.500 Lbr
Paku 0.050 Kg

6.5.2 Tenaga
Pekerja 0.060 Oh
Tukang Kayu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.003 Oh

6.6 1 m2 Langit - langit akustik ( 30 x 60 ) cm


6.6.1 Bahan
Akustik ( 30 x 60 ) cm 5.800 Lbr
Paku 0.050 Kg

6.6.2 Tenaga
Pekerja 0.060 Oh
Tukang Kayu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.003 Oh

6.7 1 m2 Langit - langit akustik ( 60 x 120 ) cm


6.7.1 Bahan
Akustik arm strong ( 60 x 120 ) cm 1.500 Lbr
Paku 0.050 Kg

6.7.2 Tenaga
Pekerja 0.060 Oh
Tukang Kayu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.003 Oh

6.8 1 m2 Langit - langit plywood ( 30 x 60 ) cm, tebal 4 mm


6.8.1 Bahan
Plywood 4" x 8" x 4 mm 0.360 Lbr
Paku 0.030 Kg

6.8.2 Tenaga
Pekerja 0.070 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.004 Oh

6.9 1 m2 Langit - langit plywood ( 30 x 60 ) cm, tebal 6 mm


6.9.1 Bahan
Plywood 4" x 8" x 6 mm 0.360 Lbr
Paku 0.030 Kg

6.9.2 Tenaga
Pekerja 0.070 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.004 Oh

6.10 1 m2 Langit - langit plywood ( 60 x 120 ) cm, tebal 4 mm


6.10.1 Bahan
Plywood 4" x 8" x 4 mm 0.375 Lbr
Paku 0.030 Kg
6.10.2 Pekerja 0.070 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.004 Oh

6.11 1 m2 Langit - langit plywood ( 60 x 120 ) cm, tebal 6 mm


6.11.1 Bahan
Plywood 4" x 8" x 6 mm 0.375 Lbr
Paku 0.030 Kg

6.11.2 Tenaga
Pekerja 0.070 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.004 Oh

6.12 1 m2 Langit - langit teakwood ( 30 x 60 ) cm, tebal 4 mm


6.12.1 Bahan
Teakwood 4" x 8" x 4 mm 0.360 Lbr
Paku 0.030 Kg

6.12.2 Tenaga
Pekerja 0.070 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.004 Oh
6.13 1 m2 Langit - langit teakwood ( 60 x 120 ) cm, tebal 4 mm
6.13.1 Bahan
Teakwood 4" x 8" x 4 mm 0.375 Lbr
Paku 0.030 Kg

6.13.2 Tenaga
Pekerja 0.070 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.004 Oh

6.14 1 m2 Langit - langit lat kayu jati


6.14.1 Bahan
Kayu jati,papan 0.024 Lbr
Paku 0.010 Kg
Paku sekrup 0.050 Kg

6.14.2 Tenaga
Pekerja 0.200 Oh
Tukang Kayu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.010 Oh

6.15 1 m2 Langit - langit lat kayu ramin


6.15.1 Bahan
Kayu ramin 0.024 Lbr
Paku 0.010 Kg
Paku sekrup 0.050 Kg
6.15.2 Tenaga
Pekerja 0.200 Oh
Tukang Kayu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.010 Oh

6.16 1 m2 Langit - langit lat kayu kamper


6.16.1 Bahan
Kayu kamper, papan 0.024 Lbr
Paku 0.010 Kg
Paku sekrup 0.050 Kg

6.16.2 Tenaga
Pekerja 0.200 Oh
Tukang Kayu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.010 Oh

6.17 1 m2 Langit - langit soft board


6.17.1 Bahan
Soft board 4' x 8' x 4 mm 0.350 Lbr
Paku biasa 0.030 Kg

6.17.2 Tenaga
Pekerja 0.600 Oh
Tukang Kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.003 Oh
6.18 1 m2 Langit - langit akustik 60 x 120 cm + rangka alumunium
6.18.1 Bahan
Profil alumunium "T" 3.600 Lbr
Kawat seng polos 0.150 Kg
Ramset/dina bolt 1.000 Bh
Akustik arm strong 60 x120 cm 1.500 Lbr

6.18.2 Tenaga
Pekerja 0.150 Oh
Tukang Kayu 0.500 Oh
Kepala tukang 0.050 Oh
Mandor 0.008 Oh

6.19 1 m' List Langit - langit kayu profil


6.19.1 Bahan
List kayu profil 1.100 m
Paku 0.010 Kg

6.19.2 Tenaga
Pekerja 0.050 Oh
Tukang Kayu 0.050 Oh
Kepala tukang 0.005 Oh
Mandor 0.005 Oh

6.20 1 m2 Langit - langit asbes (1.00 x 1.00) m, tebal 3.2 mm, rangka kayu borneo
6.20.1 Bahan
Kayu borneo, balok 0.012 m3
Paku 0.060 Kg
Asbes 1.00 x 1.00 m 1.100 Lbr
6.20.2 Tenaga
Tenaga 0.180 Oh
Pekerja 0.320 Oh
Tukang Kayu 0.032 Oh
Kepala tukang 0.009 Oh

6.21 1 m2 Langit - langit plywood 4 mm + rangka kayu borneo


6.21.1 Bahan
Kayu borneo, balok 0.012 m3
Paku biasa 0.060 Kg
Plywood 4" x 8" x 4 mm 1.100 Lbr

6.21.2 Tenaga
Pekerja 0.270 Oh
Tukang Kayu 0.400 Oh
Kepala tukang 0.040 Oh
Mandor 0.014 Oh

6.22 1 m2 Langit - langit akustik (30 x 60) cm + rangka kayu borneo


6.22.1 Bahan
Kayu borneo, balok 0.023 m3
Paku biasa 0.060 Kg
Akustik 30 x 60 cm 5.800 Lbr

6.22.2 Tenaga
Pekerja 0.260 Oh
Tukang Kayu 0.400 Oh
Kepala tukang 0.040 Oh
Mandor 0.014 Oh
6.23 1 m2 Langit - langit akustik (30 x 30) cm + rangka kayu borneo
6.23.1 Bahan
Kayu borneo, balok 0.027 m3
Paku biasa 0.060 Kg
Akustik 30 x 30 cm 11.500 Lbr

6.23.2 Tenaga
Pekerja 0.310 Oh
Tukang Kayu 0.470 Oh
Kepala tukang 0.047 Oh
Mandor 0.016 Oh

6.24 1 m2 Langit - langit gypsum board, tebal 9 mm


6.24.1 Bahan
Gypsum Board (120x240x9) mm 0.364 Lbr
Paku sekrup 0.110 Kg

6.24.2 Tenaga
Pekerja 0.100 Oh
Tukang Kayu 0.050 Oh
Kepala tukang 0.005 Oh
Mandor 0.005 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PEKERJAAN SANITASI

Analisa Biaya Pekerjaan Sanitasi


6.1 Memasang 1 buah kloset duduk/monoblok
6.1.1 Bahan
Kloset duduk/monoblok 1.000 Bh
Perlengkapan
6.1.2 Tenaga
Pekerja 3.300 Oh
Tukang batu 1.100 Oh
Kepala tukang 0.001 Oh
Mandor 0.160 Oh

6.2 Memasang 1 buah kloset jongkok porselen


6.2.1 Bahan
Kloset jongkok porselen 1.000 Bh
Semen Portland 6.000 Kg
Pasir Pasang 0.010 m3

6.2.2 Tenaga
Pekerja 1.000 Oh
Tukang batu 1.500 Oh
Kepala tukang 1.500 Oh
Mandor 0.160 Oh

6.3 Memasang 1 buah kloset jongkok teraso


6.3.1 Bahan
Kloset jongkok porselen 1.000 Bh
Bata Merah 5x11x22 cm 7.000 Kg
Semen Portland 6.000 Kg
Pasir Pasang 0.010 m3

6.3.2 Tenaga
Pekerja 1.000 Oh
Tukang batu 1.500 Oh
Kepala tukang 0.300 Oh
Mandor 0.110 Oh
6.4 Memasang 1 buah urinoir
6.4.1 Bahan
Urinoir 1.000 Bh
Perlengkapan
Semen Portland 6.000 Kg
Pasir Pasang 0.010 m3

6.4.2 Tenaga
Pekerja 1.000 Oh
Tukang batu 1.000 Oh
Kepala tukang 0.100 Oh
Mandor 0.010 Oh

6.5 Memasang 1 buah wastafel


6.5.1 Bahan
Wastafel 1.000 Bh
Perlengkapan
Semen Portland 6.000 Kg
Pasir Pasang 0.010 m3

6.5.2 Tenaga
Pekerja 1.200 Oh
Tukang batu 1.450 Oh
Kepala tukang 0.150 Oh
Mandor 0.100 Oh

6.6 Memasang 1 buah bak mandi teraso volume 0.30 m3


6.6.1 Bahan
Bak teraso 1.000 Bh
Semen Portland 6.000 Kg
Pasir Pasang 0.010 m3
6.6.2 Tenaga
Pekerja 2.100 Oh
Tukang batu 0.750 Oh
Kepala tukang 0.070 Oh
Mandor 0.110 Oh

6.7 Memasang 1 buah bak mandi fibreglass volume 0.30 m3


6.7.1 Bahan
Bak fibreglass 1.000 Bh
Perlengkapan Kg

6.7.2 Tenaga
Pekerja 1.800 Oh
Tukang batu 2.700 Oh
Kepala tukang 0.540 Oh
Mandor 0.110 Oh

6.8 Memasang 1 buah bak mandi batu bata volume 0.30 m3


6.8.1 Bahan
Batu bata 0.400 m3
Semen Portland 12.000 Kg
Pasir Pasang 0.300 m3
Porselen (11x11) cm 36.000 m2
Semen nat 6.000 Kg

6.8.2 Tenaga
Pekerja 6.000 Oh
Tukang batu 3.000 Oh
Kepala tukang 0.300 Oh
Mandor 0.300 Oh
6.9 Memasang 1 buah badkip porselen
6.9.1 Bahan
Batu bata 1.000 m3
Perlengkapan

6.9.2 Tenaga
Pekerja 0.000 Oh
Tukang batu 0.075 Oh
Kepala tukang 0.750 Oh
Mandor 0.250 Oh

6.10 Memasang 1 buah bak beton volume 1 m3 air


6.10.1 Bahan
Beton 1 : 1.5 : 2.5 0.900 m3
Besi beton 18.000 Kg
Kayu cetakan 0.080 m3
Ubin porselen 5.000 m2
Perlengkapan

6.10.2 Tenaga
Pekerja 6.000 Oh
Tukang batu 3.000 Oh
Kepala tukang 0.300 Oh
Mandor 0.300 Oh

6.11 Memasang 1 buah bak fibreglass volume 1 m3 air


6.11.1 Bahan
Bak fibreglass 1.000 Bh
Perlengkapan
6.11.2 Tenaga
Pekerja 1.800 Oh
Tukang batu 2.700 Oh
Kepala tukang 0.540 Oh
Mandor 0.110 Oh

6.12 Memasang 1 m' pipa penyalur air limbah jenis pipa tanah, diameter 15 cm
6.12.1 Bahan
Pipa tanah 1.600 m3
Semen Portland 0.680 Kg
Pasir Pasang 0.013 m3
Pasir urug 0.011 Kg

6.12.2 Tenaga
Pekerja 0.060 Oh
Tukang batu 0.030 Oh
Kepala tukang 0.003 Oh
Mandor 0.003 Oh

6.13 Memasang 1 m' pipa penyalur air limbah jenis pipa tanah, diameter 20 cm
6.13.1 Bahan
Pipa tanah 1.600 m3
Semen Portland 0.870 Kg
Pasir Pasang 0.014 m3
Pasir urug 0.014 Kg

6.13.2 Tenaga
Pekerja 0.080 Oh
Tukang batu 0.040 Oh
Kepala tukang 0.004 Oh
Mandor 0.007 Oh
6.14 Memasang 1 m' pipa beton, diameter 15 - 20 cm
6.14.1 Bahan
Pipa beton 1.100 m3
Batu bata 0.027 m3
Semen Portland 3.920 Kg
Pasir Pasang 0.056 m3
Pasir urug 0.024 Kg

6.14.2 Tenaga
Pekerja 0.140 Oh
Tukang batu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.15 Memasang 1 m' pipa beton, diameter 30 - 100 cm


6.15.1 Bahan
Pipa beton 1.100 m3
Batu bata 0.027 m3
Semen Portland 3.920 Kg
Pasir Pasang 0.056 m3
Pasir urug 0.024 Kg

6.15.2 Tenaga
Pekerja 0.140 Oh
Tukang batu 0.070 Oh
Kepala tukang 0.007 Oh
Mandor 0.007 Oh

6.16 Memasang 1 buah bak kontrol pasangan batu bata ukuran (30x30), tinggi 35 cm
6.16.1 Bahan
Batu bata 0.145 m3
Semen Portland 44.000 Kg
Pasir Pasang 0.070 m3
Batu kerikil 0.070 m3
Besi beton 1.600 Kg
Pasir beton 0.060 m3

6.16.2 Tenaga
Pekerja 3.200 Oh
Tukang batu 1.015 Oh
Kepala tukang 0.002 Oh
Mandor 0.016 Oh

6.17 Memasang 1 buah bak kontrol pasangan batu bata ukuran (45x45), tinggi 50 cm
6.17.1 Bahan
Batu bata 0.250 m3
Semen Portland 77.000 Kg
Pasir Pasang 0.013 m3
Batu kerikil 0.020 m3
Besi beton 2.600 Kg
Pasir beton 0.090 m3

6.17.2 Tenaga
Pekerja 1.420 Oh
Tukang batu 0.473 Oh
Kepala tukang 0.047 Oh
Mandor 0.071 Oh

6.18 Memasang 1 buah bak kontrol pasangan batu bata ukuran (60x60), tinggi 65 cm
6.18.1 Bahan
Batu bata 0.371 m3
Semen Portland 114.000 Kg
Pasir Pasang 0.184 m3
Batu kerikil 0.033 m3
Besi beton 4.850 Kg
Pasir beton 0.120 m3

6.18.2 Tenaga
Pekerja 2.160 Oh
Tukang batu 0.720 Oh
Kepala tukang 0.072 Oh
Mandor 0.108 Oh
Tukang gali 0.100 Oh

6.19 Memasang 1 m' pipa galvanis diameter 1/2 "


6.19.1 Bahan
Pipa galvanis 1.200 m'
Perlengkapan

6.19.2 Tenaga
Pekerja 0.054 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.027 Oh

6.20 Memasang 1 m' pipa galvanis diameter 3/4 "


6.20.1 Bahan
Pipa galvanis 1.200 m'
Perlengkapan

6.20.2 Tenaga
Pekerja 0.054 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.027 Oh
6.21 Memasang 1 m' pipa galvanis diameter 1 "
6.21.1 Bahan
Pipa galvanis 1.200 m'
Perlengkapan

6.21.2 Tenaga
Pekerja 0.054 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.027 Oh

6.22 Memasang 1 m' pipa galvanis diameter 1.5 "


6.22.1 Bahan
Pipa galvanis 1.200 m'
Perlengkapan

6.22.2 Tenaga
Pekerja 0.054 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.027 Oh

6.23 Memasang 1 m' pipa galvanis diameter 3 "


6.23.1 Bahan
Pipa galvanis 1.200 m'
Perlengkapan

6.23.2 Tenaga
Pekerja 0.108 Oh
Tukang batu 0.180 Oh
Kepala tukang 0.018 Oh
Mandor 0.005 Oh
6.24 Memasang 1 m' pipa galvanis diameter 4"
6.24.1 Bahan
Pipa galvanis 1.200 m'
Perlengkapan

6.24.2 Tenaga
Pekerja 0.135 Oh
Tukang batu 0.225 Oh
Kepala tukang 0.023 Oh
Mandor 0.007 Oh

6.25 Memasang 1 m' pipa PVC tipe AW diameter 1/2"


6.25.1 Bahan
Pipa PVC 1.200 m'
Perlengkapan

6.25.2 Tenaga
Pekerja 0.036 Oh
Tukang batu 0.060 Oh
Kepala tukang 0.006 Oh
Mandor 0.002 Oh

6.26 Memasang 1 m' pipa PVC tipe AW diameter 3/4"


6.26.1 Bahan
Pipa PVC 1.200 m'
Perlengkapan
6.26.2 Tenaga
Pekerja 0.036 Oh
Tukang batu 0.060 Oh
Kepala tukang 0.006 Oh
Mandor 0.002 Oh

6.27 Memasang 1 m' pipa PVC tipe AW diameter 1"


6.27.1 Bahan
Pipa PVC 1.200 m'
Perlengkapan

6.27.2 Tenaga
Pekerja 0.036 Oh
Tukang batu 0.060 Oh
Kepala tukang 0.006 Oh
Mandor 0.002 Oh

6.28 Memasang 1 m' pipa PVC tipe AW diameter 1.5"


6.28.1 Bahan
Pipa PVC 1.200 m'
Perlengkapan

6.28.2 Tenaga
Pekerja 0.036 Oh
Tukang batu 0.060 Oh
Kepala tukang 0.006 Oh
Mandor 0.002 Oh

6.29 Memasang 1 m' pipa PVC tipe AW diameter 2"


6.29.1 Bahan
Pipa PVC 1.200 m'
Perlengkapan

6.29.2 Tenaga
Pekerja 0.054 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.003 Oh

6.30 Memasang 1 m' pipa PVC tipe AW diameter 2.5"


6.30.1 Bahan
Pipa PVC 1.200 m'
Perlengkapan

6.30.2 Tenaga
Pekerja 0.036 Oh
Tukang batu 0.060 Oh
Kepala tukang 0.006 Oh
Mandor 0.002 Oh

6.31 Memasang 1 m' pipa PVC tipe AW diameter 3"


6.31.1 Bahan
Pipa PVC 1.200 m'
Perlengkapan

6.31.2 Tenaga
Pekerja 0.081 Oh
Tukang batu 0.135 Oh
Kepala tukang 0.014 Oh
Mandor 0.004 Oh
6.32 Memasang 1 m' pipa PVC tipe AW diameter 4"
6.32.1 Bahan
Pipa PVC 1.200 m'
Perlengkapan

6.32.2 Tenaga
Pekerja 0.081 Oh
Tukang batu 0.135 Oh
Kepala tukang 0.014 Oh
Mandor 0.004 Oh

6.33 Memasang 1 buah bak cuci piring stainless steel


6.33.1 Bahan
Bak cuci piring stainless steel 1.000 bh
Water drain + asesories 1.000 set

6.33.2 Tenaga
Pekerja 0.030 Oh
Tukang batu 0.300 Oh
Kepala tukang 0.030 Oh
Mandor 0.002 Oh

6.34 Memasang 1 buah bak cuci piring teraso


6.34.1 Bahan
Bak cuci piring teraso 1.000 bh
Water drain + asesories 1.000 set
Semen Portland 20.000 Kg
Pasir Pasang 0.050 m3

6.34.2 Tenaga
Pekerja 0.050 Oh
Tukang batu 0.500 Oh
Kepala tukang 0.050 Oh
Mandor 0.003 Oh

6.35 Memasang 1 buah kran diameter 3/4" atau 1/2"


6.35.1 Bahan
Kran air 1.000 bh
Seal tape 0.025 bh

6.35.2 Tenaga
Pekerja 0.010 Oh
Tukang batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.005 Oh

6.36 Memasang 1 buah floor drain


6.36.1 Bahan
Kran air 1.000 bh

6.36.2 Tenaga
Pekerja 0.010 Oh
Tukang batu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.005 Oh
ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2
PEKERJAAN BESI DAN ALUMINIUM

Analisa Biaya Konstruksi Pekerjaan Besi dan Aluminium


6.1 1 Kg Pasang rangka atap baja
6.1.1 Bahan
Besi profil WF 1.100 kg
Meni besi 0.080 kg

6.1.2 Tenaga
Tukang besi 0.006 Oh
Pekerja 0.060 Oh
Kepala tukang 0.006 Oh
Mandor 0.000 Oh

6.2 1 m2 Pasang pintu besi baja


6.2.1 Bahan
Pintu besi baja 1.000 m2

6.2.2 Tenaga
Tukang besi konstruksi 0.650 Oh
Pekerja 0.650 Oh
Kepala tukang 0.065 Oh
Mandor 0.032 Oh

6.3 1 m2 Pasang jendela besi


6.3.1 Bahan
Jendela besi 1.000 m2

6.3.2 Tenaga
Tukang besi konstruksi 1.050 Oh
Pekerja 0.105 Oh
Kepala tukang 0.105 Oh
Mandor 0.00525 Oh

6.4 1 m2 Pasang jendela besi tahan api


6.4.1 Bahan
Jendela besi tahan api 1.000 m2

6.4.2 Tenaga
Tukang besi konstruksi 1.200 Oh
Pekerja 1.022 Oh
Kepala tukang 0.120 Oh
Mandor 0.006 Oh

6.5 1 m2 Pasang pintu gulung besi


6.5.1 Bahan
Pintu gulung besi 1.000 m2

6.5.2 Tenaga
Tukang besi konstruksi 1.200 Oh
Pekerja 1.200 Oh
Kepala tukang 0.120 Oh
Mandor 0.006 Oh

6.6 1 m2 Pasang pintu lipat


6.6.1 Bahan
Pintu lipat 1.000 m2
6.6.2 Tenaga
Tukang besi konstruksi 1.060 Oh
Pekerja 0.105 Oh
Kepala tukang 0.105 Oh
Mandor 0.0052 Oh

6.7 1 m2 Pasang pintu sunscreen aluminium


6.7.1 Bahan
Sunscreen aluminium 1.000 m2

6.7.2 Tenaga
Tukang besi konstruksi 0.800 Oh
Pekerja 0.080 Oh
Kepala tukang 0.080 Oh
Mandor 0.004 Oh

6.8 1 m2 Pasang rolling door


6.8.1 Bahan
Rooling door 1.000 m2

6.8.2 Tenaga
Tukang besi konstruksi 1.500 Oh
Pekerja 1.050 Oh
Kepala tukang 0.105 Oh
Mandor 0.004 Oh

6.9 1 m2 Pasang pintu alluminium


6.9.1 Bahan
Pintu alluminium 1.000 m2
6.9.2 Tenaga
Tukang besi konstruksi 1.050 Oh
Pekerja 1.050 Oh
Kepala tukang 0.105 Oh
Mandor 0.0052 Oh

6.10 1 m2 Pasang venetions blinds


6.10.1 Bahan
Venetions blinds 1.000 m2

6.10.2 Tenaga
Tukang kayu 0.350 Oh
Pekerja 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.00175 Oh

6.11 1 m2 Pasang vertikals blinds


6.11.1 Bahan
Vertikals blind 1.000 m2

6.11.2 Tenaga
Tukang kayu 0.350 Oh
Pekerja 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.00175 Oh

6.12 1 m2 Pasang terali besi


6.12.1 Bahan
Besi strip 2x3 11.000 m2

6.12.2 Tenaga
Tukang las 1.200 Oh
Pekerja 1.200 Oh
Kepala tukang 0.012 Oh
Mandor 0.0006 Oh

6.13 1 m2 Pasang kawat harmonika


6.13.1 Bahan
Kawat harmonika 1.100 m2
Paku biasa 1/2" - 1" 0.020 kg
Kayu kamper, papan 0.0018 m3

6.13.2 Tenaga
Pekerja 0.100 Oh
Tukang kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.0005 Oh

6.14 1 m2 Pasang kawat nyamuk


6.14.1 Bahan
Kawat nyamuk 1.100 m2
Paku biasa 1/2" - 1" 0.020 kg
Kayu kamper, papan 0.0018 m3

6.14.2 Tenaga
Pekerja 0.100 Oh
Tukang kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.0005 Oh
6.15 1 m2 Pasang kawat kassa
6.15.1 Bahan
Kawat kassa 1.100 m2
Paku biasa 1/2" - 1" 0.020 kg
Kayu kamper, papan 0.0018 m3

6.15.2 Tenaga
Pekerja 0.100 Oh
Tukang kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.0005 Oh

6.16 1 m2 Pasang kawat burung


6.16.1 Bahan
Kawat burung 1.100 m2
Paku biasa 1/2" - 1" 0.020 kg
Kayu kamper, papan 0.0018 m3

6.16.2 Tenaga
Pekerja 0.100 Oh
Tukang kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.0005 Oh

6.17 1 m2 Pasang jendela nako dan teralis


6.17.1 Bahan
Kaca Nako 1.100 m2
Paku biasa 1/2" - 1" 0.020 kg
Kayu kamper, papan 0.025 m3

6.17.2 Tenaga
Pekerja 0.200 Oh
Tukang kayu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.001 Oh

6.18 1 m2 Pasang talang datar, seng bjls 28


6.18.1 Bahan
Seng plat 3' x 6' bjls 28 0.500 lbr
Paku biasa 1/2" - 1" 0.015 kg
Kayu borneo, papan 0.0096 m3
Flincote/meni besi 0.250 kg

6.18.2 Tenaga
Pekerja 0.150 Oh
Tukang kayu 0.400 Oh
Kepala tukang 0.025 Oh
Mandor 0.00125 Oh

6.19 1 m2 Pasang talang miring, seng bjls 28


6.19.1 Bahan
Seng plat 3' x 6' bjls 28 0.500 lbr
Paku biasa 1/2" - 1" 0.015 kg
Kayu borneo, papan 0.019 m3
Flincote/meni besi 0.300 kg

6.19.2 Tenaga
Pekerja 0.040 Oh
Tukang kayu 0.400 Oh
Kepala tukang 0.025 Oh
Mandor 0.00125 Oh

6.20 1 m' Pasang talang 1/2 lingkaran D-10 cm, seng bjls 28
6.20.1 Bahan
Seng plat 3' x 6' bjls 28 0.300 lbr
Paku biasa 1/2" - 1" 0.100 kg
Kayu borneo, papan 0.019 m3
Besi strip 0.500 kg

6.20.2 Tenaga
Pekerja 0.150 Oh
Tukang kayu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.00125 Oh

6.21 1 m' Pasang talang 1/2 lingkaran D-10 cm, seng bjls 24
6.21.1 Bahan
Seng plat 3' x 6' bjls 28 0.300 lbr
Paku biasa 1/2" - 1" 0.100 kg
Kayu borneo, papan 0.019 m3
Besi strip 0.500 kg

6.21.2 Tenaga
Pekerja 0.150 Oh
Tukang kayu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.00125 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PEKERJAAN KUNCI DAN KACA

6.1 1 buah kunci tanam antik


6.1.1 Bahan
Kunci tanam antik 1.000 Bh

6.1.2 Tenaga
Pekerja 0.060 Oh
Tukang kayu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.003 Oh

6.2 1 buah kunci tanam biasa


6.2.1 Bahan
Kunci tanam biasa 1.000 Bh

6.2.2 Tenaga
Pekerja 0.010 Oh
Tukang kayu 0.500 Oh
Kepala tukang 0.010 Oh
Mandor 0.005 Oh

6.3 1 buah kunci tanam kamar mandi


6.3.1 Bahan
Kunci tanam kamar mandi 1.000 Bh

6.3.2 Tenaga
Pekerja 0.050 Oh
Tukang kayu 0.500 Oh
Kepala tukang 0.005 Oh
Mandor 0.0025 Oh
6.4 1 buah pasang kunci silinder
6.4.1 Bahan
Kunci silinder 1.000 Bh

6.4.2 Tenaga
Pekerja 0.050 Oh
Tukang kayu 0.500 Oh
Kepala tukang 0.005 Oh
Mandor 0.00025 Oh

6.5 1 buah pasang engsel pintu


6.5.1 Bahan
Engsel pintu 1.000 Bh

6.5.2 Tenaga
Pekerja 0.015 Oh
Tukang kayu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.00075 Oh

6.6 1 buah pasang engsel jendela kupu-kupu


6.6.1 Bahan
Engsel jendela 1.000 Bh

6.6.2 Tenaga
Pekerja 0.010 Oh
Tukang kayu 0.100 Oh
Kepala tukang 0.010 Oh
Mandor 0.0005 Oh

6.7 1 buah pasang engsel angin


6.7.1 Bahan
Engsel angin 1.000 Bh

6.7.2 Tenaga
Pekerja 0.020 Oh
Tukang kayu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.010 Oh

6.8 1 buah pasang spring knip


6.8.1 Bahan
Spring knip 1.000 Bh

6.8.2 Tenaga
Pekerja 0.015 Oh
Tukang kayu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.00075 Oh

6.9 1 buah pasang kait angin


6.9.1 Bahan
Kait angin 1.000 Bh
6.9.2 Tenaga
Pekerja 0.015 Oh
Tukang kayu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.00075 Oh

6.10 1 buah pasang door closer


6.10.1 Bahan
Door closer 1.000 Bh

6.10.2 Tenaga
Pekerja 0.050 Oh
Tukang kayu 0.500 Oh
Kepala tukang 0.050 Oh
Mandor 0.0025 Oh

6.11 1 buah pasang kunci selot


6.11.1 Bahan
Kunci selot 1.000 Bh

6.11.2 Tenaga
Pekerja 0.020 Oh
Tukang kayu 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.001 Oh

6.12 1 buah pasang pegangan pintu/door holder


6.12.1 Bahan
Door holder 1.000 Bh

6.12.2 Tenaga
Pekerja 0.050 Oh
Tukang kayu 0.500 Oh
Kepala tukang 0.050 Oh
Mandor 0.0025 Oh

6.13 1 buah pasang door stop


6.13.1 Bahan
Door stop 1.000 Bh

6.13.2 Tenaga
Pekerja 0.010 Oh
Tukang kayu 0.010 Oh
Kepala tukang 0.010 Oh
Mandor 0.0005 Oh

6.14 1 buah pasang rel pintu dorong


6.14.1 Bahan
Rel pintu dorong 1.000 Bh

6.14.2 Tenaga
Pekerja 0.060 Oh
Tukang kayu 0.600 Oh
Kepala tukang 0.060 Oh
Mandor 0.003 Oh
6.15 1 buah pasang kunci lemari
6.15.1 Bahan
Kunci lemari 1.000 Bh

6.15.2 Tenaga
Pekerja 0.025 Oh
Tukang kayu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.00125 Oh

6.16 1 m2 pasang kaca, tebal 3 mm


6.16.1 Bahan
Kaca polos 1.100 m2

6.16.2 Tenaga
Pekerja 0.015 Oh
Tukang kayu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.00075 Oh

6.17 1 m2 pasang kaca, tebal 5 mm


6.17.1 Bahan
Kaca polos 1.100 m2

6.17.2 Tenaga
Pekerja 0.015 Oh
Tukang kayu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.00075 Oh
6.18 1 m2 pasang kaca, tebal 8 mm
6.18.1 Bahan
Kaca polos 1.1 m2

6.18.2 Tenaga
Pekerja 0.0165 Oh
Tukang kayu 0.165 Oh
Kepala tukang 0.0165 Oh
Mandor 0.0008 Oh

6.19 1 m2 pasang kaca, tebal 12mm


6.19.1 Bahan
Kaca buram 1.100 m2
Sealent 0.050 kg

6.19.2 Tenaga
Pekerja 0.025 Oh
Tukang kayu 0.250 Oh
Kepala tukang 0.025 Oh
Mandor 0.00125 Oh

6.20 1 m2 pasang kaca cermin, tebal 5 mm


6.20.1 Bahan
Kaca cermin 1.100 m2

6.20.2 Tenaga
Pekerja 0.015 Oh
Tukang kayu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.00075 Oh
6.21 1 m2 pasang kaca cermin, tebal 6 mm
6.21.1 Bahan
Kaca cermin 1.100 m2

6.21.2 Tenaga
Pekerja 0.015 Oh
Tukang kayu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.00075 Oh

6.22 1 m2 pasang kaca cermin, tebal 8 mm


6.22.1 Bahan
Kaca cermin 1.100 m2

6.22.2 Tenaga
Pekerja 0.0165 Oh
Tukang kayu 0.165 Oh
Kepala tukang 0.017 Oh
Mandor 0.0008 Oh

6.23 1 m2 pasang kaca "wireglass" tebal 5 mm


6.23.1 Bahan
Kaca wireglass 1.1 m2

6.23.2 Tenaga
Pekerja 0.015 Oh
Tukang kayu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.00075 Oh
6.24 1 m2 pasang kaca patri tebal 5 mm
6.24.1 Bahan
Kaca patri 1.100 m2

6.24.2 Tenaga
Pekerja 0.015 Oh
Tukang kayu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.00075 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PENUTUP LANTAI

6.1 1 m2 Pasang lantai ubin pc abu-abu ukuran 40 x 40 cm


6.1.1 Bahan
Ubin abu-abu ukuran 40 x 40 cm 6.630 bh
Semen portland 9.800 kg
Pasir pasang 0.0215 m3

6.1.2 Tenaga
Pekerja 0.250 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.0125 Oh

6.2 1 m2 Pasang lantai ubin pc abu-abu ukuran 30 x 30 cm


6.2.1 Bahan
Ubin abu-abu ukuran 30 x 30 cm 11.87 bh
Semen portland 10 kg
Pasir pasang 0.0215 m3

6.2.2 Tenaga
Pekerja 0.260 Oh
Tukang batu 0.125 Oh
Kepala tukang 0.0125 Oh
Mandor 0.013 Oh

6.3 1 m2 Pasang lantai ubin pc abu-abu ukuran 20 x20 cm


6.3.1 Bahan
Ubin abu-abu ukuran 20 x 20 cm 26.500 bh
Semen portland 10.400 kg
Pasir pasang 0.0135 m3

6.3.2 Tenaga
Pekerja 0.270 Oh
Tukang batu 0.130 Oh
Kepala tukang 0.013 Oh
Mandor 0.0135 Oh

6.4 1 m2 Pasang lantai ubin warna ukuran 40 x 40 cm


6.4.1 Bahan
Ubin warna ukuran 40 x 40 cm 6.630 bh
Semen portland 8.160 kg
Pasir pasang 0.023 m3
Semen warna 0.900 kg

6.4.2 Tenaga
Pekerja 0.250 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.0125 Oh

6.5 1 m2 Pasang lantai ubin warna ukuran 30 x 30 cm


6.5.1 Bahan
Ubin warna ukuran 30 x 30 cm 11.700 bh
Semen portland 8.360 kg
Pasir pasang 0.023 m3
Semen warna 0.900 kg

6.5.2 Tenaga
Pekerja 0.250 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.0125 Oh

6.6 1 m2 Pasang lantai ubin warna ukuran 20 x 20 cm


6.6.1 Bahan
Ubin warna ukuran 20 x 20 cm 26.500 bh
Semen portland 8.760 kg
Pasir pasang 0.023 m3
Semen warna 0.900 kg

6.6.2 Tenaga
Pekerja 0.27 Oh
Tukang batu 0.13 Oh
Kepala tukang 0.013 Oh
Mandor 0.0135 Oh
6.7 1 m2 Pasang lantai ubin teraso ukuran 40 x 40 cm
6.7.1 Bahan
Ubin teraso ukuran 40 x 40 cm 6.250 bh
Semen portland 8.800 kg
Pasir pasang 0.022 m3
Semen warna 0.900 kg

6.7.2 Tenaga
Pekerja 0.250 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.0125 Oh

6.8 1 m2 Pasang lantai ubin teraso ukuran 30 x 30 cm


6.8.1 Bahan
Ubin teraso ukuran 30 x 30 cm 6.250 bh
Semen portland 8.800 kg
Pasir pasang 0.022 m3
Semen warna 0.900 kg

6.8.2 Tenaga
Pekerja 0.250 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.0125 Oh

6.9 1 m2 Pasang lantai ubin granito ukuran 40 x 40 cm


6.9.1 Bahan
Ubin granito ukuran 40 x 40 cm 6.930 bh
Semen portland 9.800 kg
Pasir pasang 0.022 m3
Semen warna 1.300 kg

6.9.2 Tenaga
Pekerja 0.250 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.0125 Oh

6.10 1 m2 Pasang lantai ubin granito ukuran 30 x 30 cm


6.10.1 Bahan
Ubin granito ukuran 30 x 30 cm 11.870 bh
Semen portland 10.000 kg
Pasir pasang 0.0215 m3
Semen warna 1.500 kg

6.10.2 Tenaga
Pekerja 0.260 Oh
Tukang batu 0.125 Oh
Kepala tukang 0.0125 Oh
Mandor 0.013 Oh

6.11 1 m2 Pasang lantai ubin teralux ukuran 40 x 40 cm


6.11.1 Bahan
Ubin teralux ukuran 40 x 40 cm 6.250 bh
Semen portland 8.800 kg
Pasir pasang 0.0215 m3
Semen warna 1.300 kg

6.11.2 Tenaga
Pekerja 0.250 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.0125 Oh

6.12 1 m2 Pasang lantai ubin teralux ukuran 30 x 30 cm


6.12.1 Bahan
Ubin teralux ukuran 30 x 30 cm 11.87 bh
Semen portland 10 kg
Pasir pasang 0.0215 m3
Semen warna 1.125 kg

6.12.2 Tenaga
Pekerja 0.25 Oh
Tukang batu 0.12 Oh
Kepala tukang 0.012 Oh
Mandor 0.0125 Oh

6.13 1 m2 Pasang lantai ubin teralux marmer ukuran 60 x 60 cm


6.13.1 Bahan
Ubin teralux marmer ukuran 60 x 60 cm 5.600 bh
Semen portland 8.190 kg
Pasir pasang 0.045 m3
Semen warna 1.000 kg

6.13.2 Tenaga
Pekerja 0.250 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.0125 Oh

6.14 1 m2 Pasang lantai ubin teralux marmer ukuran 40 x 40 cm


6.14.1 Bahan
Ubin teralux marmer ukuran 40 x 40 cm 6.250 bh
Semen portland 8.800 kg
Pasir pasang 0.022 m3
Semen warna 1.300 kg

6.14.2 Tenaga
Pekerja 0.672 Oh
Tukang batu 0.224 Oh
Kepala tukang 0.022 Oh
Mandor 0.034 Oh

6.15 1 m2 Pasang lantai ubin teralux marmer ukuran 30 x30 cm


6.15.1 Bahan
Ubin teralux marmer ukuran 30 x 30 cm 11.870 bh
Semen portland 10.000 kg
Pasir pasang 0.022 m3
Semen warna 1.500 kg

6.15.2 Tenaga
Pekerja 0.700 Oh
Tukang batu 0.340 Oh
Kepala tukang 0.034 Oh
Mandor 0.035 Oh

6.16 1 m' Pasang plint ubin pc abu-abu ukuran 15 x 20 cm


6.16.1 Bahan
Plint ubin pc abu-abu ukuran 15 x 20 cm 5.300 bh
Semen portland 1.560 kg
Pasir pasang 0.004 m3

6.16.2 Tenaga
Pekerja 0.060 Oh
Tukang batu 0.030 Oh
Kepala tukang 0.003 Oh
Mandor 0.003 Oh

6.17 1 m' Pasang plint ubin pc abu-abu ukuran 10 x 30 cm


6.17.1 Bahan
Plint ubin pc abu-abu ukuran 10 x 30 cm 3.500 bh
Semen portland 1.560 kg
Pasir pasang 0.003 m3

6.17.2 Tenaga
Pekerja 0.060 Oh
Tukang batu 0.030 Oh
Kepala tukang 0.003 Oh
Mandor 0.003 Oh

6.18 1 m' Pasang plint ubin pc abu-abu ukuran 10 x 40 cm


6.18.1 Bahan
Plint ubin pc abu-abu ukuran 10 x 40 cm 2.650 bh
Semen portland 1.560 kg
Pasir pasang 0.003 m3

6.18.2 Tenaga
Pekerja 0.060 Oh
Tukang batu 0.030 Oh
Kepala tukang 0.003 Oh
Mandor 0.003 Oh

6.19 1 m' Pasang plint ubin pc warna ukuran 10 x 20 cm


6.19.1 Bahan
Plint ubin pc warna ukuran 10 x 20 cm 5.300 bh
Semen portland 1.200 kg
Pasir pasang 0.003 m3
Semen warna 0.190 kg

6.19.2 Tenaga
Pekerja 0.060 Oh
Tukang batu 0.030 Oh
Kepala tukang 0.003 Oh
Mandor 0.003 Oh
6.20 1 m' Pasang plint ubin pc warna ukuran 10 x 30 cm
6.20.1 Bahan
Plint ubin pc warna ukuran 10 x 30 cm 3.300 bh
Semen portland 4.650 kg
Pasir pasang 0.0032 m3
Semen warna 0.100 kg

6.20.2 Tenaga
Pekerja 0.060 Oh
Tukang batu 0.030 Oh
Kepala tukang 0.003 Oh
Mandor 0.003 Oh

6.21 1 m' Pasang plint ubin pc warna ukuran 10 x 40 cm


6.21.1 Bahan
Plint ubin pc warna ukuran 10 x 30 cm 2.650 bh
Semen portland 1.200 kg
Pasir pasang 0.003 m3
Semen warna 0.100 kg

6.21.2 Tenaga
Pekerja 0.080 Oh
Tukang batu 0.040 Oh
Kepala tukang 0.004 Oh
Mandor 0.004 Oh

6.22 1 m' Pasang plint ubin teraso ukuran 10 x 30 cm


6.22.1 Bahan
Plint ubin teraso ukuran 10 x 30 cm 3.500 bh
Semen portland 1.560 kg
Pasir pasang 0.003 m3
Semen warna 0.190 kg
6.22.2 Tenaga
Pekerja 0.080 Oh
Tukang batu 0.040 Oh
Kepala tukang 0.004 Oh
Mandor 0.004 Oh

6.23 1 m' Pasang plint ubin teraso ukuran 10 x 40 cm


6.23.1 Bahan
Plint ubin teraso ukuran 10 x 40 cm 2.650 bh
Semen portland 1.200 kg
Pasir pasang 0.003 m3
Semen warna 0.100 kg

6.23.2 Tenaga
Pekerja 0.080 Oh
Tukang batu 0.040 Oh
Kepala tukang 0.004 Oh
Mandor 0.004 Oh

6.24 1 m' Pasang plint ubin granito ukuran 10 x 40 cm


6.24.1 Bahan
Plint ubin granito ukuran 10 x 40 cm 2.650 bh
Semen portland 1.200 kg
Pasir pasang 0.003 m3
Semen warna 0.100 kg

6.24.2 Tenaga
Pekerja 0.060 Oh
Tukang batu 0.030 Oh
Kepala tukang 0.003 Oh
Mandor 0.100 Oh
6.25 1 m' Pasang plint ubin granito ukuran 10 x 30 cm
6.25.1 Bahan
Plint ubin granito ukuran 10 x 30 cm 3.330 bh
Semen portland 1.650 kg
Pasir pasang 0.003 m3
Semen warna 0.100 kg

6.25.2 Tenaga
Pekerja 0.900 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.26 1 m' Pasang plint ubin teralux kerang ukuran 10 x 40 cm


6.26.1 Bahan
Plint ubin teralux kerang ukuran 10 x 40 cm 2.500 bh
Semen portland 1.650 kg
Pasir pasang 0.0032 m3
Semen warna 0.100 kg

6.26.2 Tenaga
Pekerja 0.900 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.27 1 m' Pasang plint ubin teralux kerang ukuran 10 x 30 cm


6.27.1 Bahan
Plint ubin teralux kerang ukuran 10 x 30 cm 3.330 bh
Semen portland 1.650 kg
Pasir pasang 0.0032 m3
Semen warna 0.100 kg

6.27.2 Tenaga
Pekerja 0.900 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.28 1 m' Pasang plint ubin teralux marmer ukuran 10 x 60 cm


6.28.1 Bahan
Plint ubin teralux marmer ukuran 10 x 60 cm 1.700 bh
Semen portland 1.650 kg
Pasir pasang 0.0032 m3
Semen warna 0.100 kg

6.28.2 Tenaga
Pekerja 0.900 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.29 1 m' Pasang plint ubin teralux marmer ukuran 10 x 40 cm


6.29.1 Bahan
Plint ubin teralux marmer ukuran 10 x 40 cm 2.500 bh
Semen portland 1.650 kg
Pasir pasang 0.0032 m3
Semen warna 0.100 kg

6.29.2 Tenaga
Pekerja 0.900 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.30 1 m' Pasang plint ubin teralux marmer ukuran 10 x 30 cm


6.30.1 Bahan
Plint ubin teralux marmer ukuran 10 x 30 cm 3.300 bh
Semen portland 1.650 kg
Pasir pasang 0.0032 m3
Semen warna 0.100 kg

6.30.2 Tenaga
Pekerja 0.900 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.31 1 m2 Pasang teraso cor di tempat


6.31.1 Bahan
Bahan teraso cor 0.0036 m3

6.31.2 Tenaga
Pekerja 0.900 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.32 1 m2 Pasang teralux cor di tempat, tebal 3 cm


6.32.1 Bahan
Bahan cor teralux 0.0036 m3

6.32.2 Tenaga
Pekerja 0.900 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.33 1 m2 Pasang ubin tahan asam


6.33.1 Bahan
Ubin tahan asam 3.3 bh
Semen tahan asam 1.65 kg
Pasir pasang 0.0032 m3

6.33.2 Tenaga
Pekerja 0.9 Oh
Tukang batu 0.09 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.34 1 m2 Pasang lantai keramik artistik 10 x 20 cm


6.34.1 Bahan
Ubin keramik artistik 10 x 20 cm 50.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 1.500 kg

6.34.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.35 1 m2 Pasang lantai keramik artistik 10 x 10 cm


6.35.1 Bahan
Ubin keramik artistik 10 x 10 cm 50.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 2.000 kg

6.35.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh
6.36 1 m2 Pasang lantai keramik artistik 5 x 20 cm
6.36.1 Bahan
Ubin keramik artistik 5 x 20 cm 100.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 1.500 kg

6.36.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.37 1 m' Pasang plint keramik artistik 10 x 20 cm


6.37.1 Bahan
Plint keramik artistik 10 x 200 cm 5.000 bh
Semen portland 1.650 kg
Pasir pasang 0.0032 m3
Semen warna 0.120 kg

6.37.2 Tenaga
Pekerja 0.090 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.38 1 m' Pasang plint keramik artistik 10 x 10 cm


6.38.1 Bahan
Plint keramik artistik 10 x 10 cm 10.000 bh
Semen portland 1.650 kg
Pasir pasang 0.0032 m3
Semen warna 0.120 kg

6.38.2 Tenaga
Pekerja 0.090 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.39 1 m' Pasang plint keramik artistik 50 x 20 cm


6.39.1 Bahan
Plint keramik artistik 50 x 20 cm 5.000 bh
Semen portland 0.850 kg
Pasir pasang 0.0022 m3
Semen warna 0.080 kg

6.39.2 Tenaga
Pekerja 0.090 Oh
Tukang batu 0.090 Oh
Kepala tukang 0.009 Oh
Mandor 0.0045 Oh

6.40 1 m' Pasang internal cove artistik (5 x 5 x 20) cm


6.40.1 Bahan
Internal cove artistik (5 x 5 x 20) cm 10.000 bh
Semen portland 1.415 kg
Pasir pasang 0.039 m3
Semen warna 1.200 kg

6.40.2 Tenaga
Pekerja 0.750 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.0375 Oh

6.41 1 m' Pasang plint vinyil tanpa adukan


6.41.1 Bahan
Lt vinyil karet 30 x 30 kwl 3.500 bh
Lem vinyil 0.080 kg

6.41.2 Tenaga
Pekerja 0.080 Oh
Tukang batu 0.080 Oh
Kepala tukang 0.008 Oh
Mandor 0.004 Oh

6.42 1 m2 Pasang lantai keramik 10 x 20 cm


6.42.1 Bahan
Ubin keramik artistik 10 x 20 cm 50.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 1.500 kg

6.42.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.43 1 m2 Pasang lantai keramik 15 x 15 cm


6.43.1 Bahan
Ubin keramik artistik 15 x 15 cm 44.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 1.500 kg

6.43.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh
6.44 1 m2 Pasang lantai keramik 20 x 20 cm
6.44.1 Bahan
Ubin keramik artistik 20 x 20 cm 25.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 1.500 kg

6.44.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.45 1 m2 Pasang lantai keramik 25 x 25cm


6.45.1 Bahan
Ubin keramik artistik 25 x 25 cm 16.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 1.500 kg

6.45.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.46 1 m2 Pasang lantai keramik 15 x 20 cm


6.46.1 Bahan
Ubin keramik artistik 15 x 20 cm 35.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 1.500 kg

6.46.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.47 1 m2 Pasang lantai keramik 33 x 33 cm


6.47.1 Bahan
Ubin keramik artistik 33 x 33 cm 10.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 1.500 kg

6.47.2 Tenaga
Pekerja 0.620
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.48 1 m2 Pasang lantai keramik 33 x 33 cm anti slip


6.48.1 Bahan
Ubin keramik artistik 33 x 33 cm anti slip 10.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 1.500 kg

6.48.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.49 1 m2 Pasang lantai keramik 10 x 33 cm


6.49.1 Bahan
Ubin keramik 10 x 33 cm 33.000 bh
Semen portland 11.380 kg
Pasir pasang 0.042 m3
Semen warna 1.500 kg

6.49.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.50 1 m2 Pasang lantai mosaik 30 x 30 cm, ex lokal


6.50.1 Bahan
Ubin keramik 30 x 30 cm 12.000 bh
Semen portland 14.150 kg
Pasir pasang 0.039 m3
Semen warna 2.000 kg

6.50.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.51 1 m2 Pasang lantai marmer


6.51.1 Bahan
Marmer 1.052 bh
Semen portland 14.150 kg
Pasir pasang 0.039 m3
Semen warna 2.000 kg

6.51.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh
6.52 1 m2 Pasang lantai karpet 100% wool
6.52.1 Bahan
Feltex carpet 100 % wool T-21 1.050 m2
Lem vinyl 0.350 kg

6.52.2 Tenaga
Pekerja 0.170 Oh
Tukang batu 0.170 Oh
Kepala tukang 0.017 Oh
Mandor 0.0085 Oh

6.53 1 m2 Pasang lantai karpet 80% wool, 20% nylon


6.53.1 Bahan
Karpet 80% wool, 20% nylon 1.050 m2
Lem vinyl 0.350 kg

6.53.2 Tenaga
Pekerja 0.170 Oh
Tukang batu 0.170 Oh
Kepala tukang 0.017 Oh
Mandor 0.0085 Oh

6.54 1 m2 Pasang underlyer, tebal 6 mm


6.54.1 Bahan
Underlyer tebal 6 mm / rubber corrugated 1.050 m2

6.54.2 Tenaga
Pekerja 0.120 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.006 Oh
6.55 1 m2 Pasang lantai karpet
6.55.1 Bahan
Karpet 1.050 m2
Lem vinyl 0.350 kg

6.55.2 Tenaga
Pekerja 0.170 Oh
Tukang batu 0.170 Oh
Kepala tukang 0.017 Oh
Mandor 0.0085 Oh

6.56 1 m2 Pasang lantai parquet jati


6.56.1 Bahan
Parquet jati 1.050 m2
Lem vinyl 0.600 kg

6.56.2 Tenaga
Pekerja 0.650
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.0325 Oh

6.57 1 m2 Pasang gymfloor


6.57.1 Bahan
Gymfloor 1.050 m2
Lem vinyl 0.600 kg

6.57.2 Tenaga
Pekerja 0.650 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.0325 Oh

6.58 1 m2 Pasang dinding porselin 11 x 11 cm, putih


6.58.1 Bahan
Porselin 11 x 11 cm 83.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.58.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.500 Oh
Kepala tukang 0.050 Oh
Mandor 0.030 Oh

6.59 1 m2 Pasang dinding porselin 11 x 11 cm, warna


6.59.1 Bahan
Porselin 11 x 11 cm warna 83.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.59.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.500 Oh
Kepala tukang 0.050 Oh
Mandor 0.030 Oh

6.60 1 m2 Pasang dinding porselin 15 x 15 cm, putih


6.60.1 Bahan
Porselin 15 x 15 cm putih 45.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.60.2 Tenaga
Pekerja 0.600 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.030 Oh

6.61 1 m2 Pasang dinding porselin 15 x 15 cm, warna


6.61.1 Bahan
Porselin 15 x 15 cm warna 45.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.61.2 Tenaga
Pekerja 0.600 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.030 Oh

6.62 1 m2 Pasang dinding porselin 10 x 20 cm, warna


6.62.1 Bahan
Porselin 10 x 20 cm warna 50.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.62.2 Tenaga
Pekerja 0.600 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.030 Oh
6.63 1 m2 Pasang dinding porselin 20 x 20 cm, warna
6.63.1 Bahan
Porselin 20 x 20 cm warna 25.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.63.2 Tenaga
Pekerja 0.600 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.030 Oh

6.64 1 m2 Pasang dinding keramik artistik 10 x 20 cm


6.64.1 Bahan
Keramik 10 x 20 cm warna 100.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.64.2 Tenaga
Pekerja 0.600 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.030 Oh

6.65 1 m2 Pasang dinding keramik artistik 5 x 20 cm


6.65.1 Bahan
Keramik 5 x 20 cm warna 100.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg
6.65.2 Tenaga
Pekerja 0.600 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.030 Oh

6.66 1 m2 Pasang dinding keramik 10 x 20 cm


6.66.1 Bahan
Keramik 10 x 20 cm warna 50.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.66.2 Tenaga
Pekerja 0.600 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.030 Oh

6.67 1 m2 Pasang dinding keramik 15 x 15 cm


6.67.1 Bahan
Keramik 15 x 15 cm warna 45.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.67.2 Tenaga
Pekerja 0.600 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.030 Oh
6.68 1 m2 Pasang dinding keramik 20 x 20 cm
6.68.1 Bahan
Keramik 20 x 20 cm warna 25.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.68.2 Tenaga
Pekerja 0.600 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.030 Oh

6.69 1 m2 Pasang dinding keramik artistik 10 x 20 cm


6.69.1 Bahan
Keramik 10 x 20 cm warna 100.000 Bh
Semen abu-abu 9.300 Kg
Pasir pasang 0.018 m3
Semen warna 1.500 Kg

6.69.2 Tenaga
Pekerja 0.600 Oh
Tukang batu 0.450 Oh
Kepala tukang 0.045 Oh
Mandor 0.030 Oh

6.70 1 m2 Pasang dinding marmer


6.70.1 Bahan
Marmer 1.020 M2
Pacu Pancing 60 x 230 2.000 Bh
Semen Abu-abu 12.440 Kg
Pasir pasang 0.025 M3
Semen Warna 1.500 Kg

6.70.2 Tenaga
Pekerja 0.720 Oh
Tukang batu 0.650 Oh
Kepala tukang 0.065 Oh
Mandor 0.035 Oh

6.71 1 m2 Pasang dinding bata pelapis 7 x 3 x24 cm


6.71.1 Bahan
Bata Pelapis Dinding 60.000 Bh
Semen Abu-abu 12.440 Kg
Pasir pasang 0.025 M3

6.71.2 Tenaga
Pekerja 0.650 Oh
Tukang batu 0.500 Oh
Kepala tukang 0.050 Oh
Mandor 0.030 Oh

6.72 1 m2 Pasang dinding bata klinker 5 x 5 x24 cm


6.72.1 Bahan
Bata Pelapis Klinker 60.000 Bh
Semen Abu-abu 12.440 Kg
Pasir pasang 0.025 M3

6.72.2 Tenaga
Pekerja 0.650 Oh
Tukang batu 0.500 Oh
Kepala tukang 0.050 Oh
Mandor 0.030 Oh

6.73 1 m2 Pasang dinding bata paros


6.73.1 Bahan
Batu paros 1.050 m2
Semen Abu-abu 11.750 Kg
Pasir pasang 0.035 M3

6.73.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.74 1 m2 Pasang dinding batu tempel hitam


6.74.1 Bahan
Batu tempel hitam 1.050 m2
Semen Abu-abu 11.750 Kg
Pasir pasang 0.035 M3

6.74.2 Tenaga
Pekerja 0.620 Oh
Tukang batu 0.350 Oh
Kepala tukang 0.035 Oh
Mandor 0.030 Oh

6.75 1 m2 Pasang lantai vinyl karet 30 x 30 cm KL I


6.75.1 Bahan
Vinyl karet 30 x 30 cm KL I 11.050 Bh
Lem vinyl 0.035 Kg

6.75.2 Tenaga
Pekerja 0.150 Oh
Tukang batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.0075 Oh
6.76 1 m2 Pasang lantai vinyl karet 30 x 30 cm KL II
6.76.1 Bahan
Vinyl karet 30 x 30 cm KL II 11.050 Bh
Lem vinyl 0.035 Kg

6.76.2 Tenaga
Pekerja 0.150 Oh
Tukang batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.008 Oh

6.77 1 m2 Pasang lantai vinyl asbes 30 x 30 cm


6.77.1 Bahan
Vinyl asbes 30 x 30 cm 11.050 Bh
Lem vinyl 0.035 Kg

6.77.2 Tenaga
Pekerja 0.150 0
Tukang batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.0075 Oh

6.78 1 m2 Pasang lantai vinyl motif kembang 30 x 30 cm


6.78.1 Bahan
Vinyl motif kembang 30 x 30 cm ex DN 11.05 Bh
Lem vinyl 0.035 Kg

6.78.2 Tenaga
Pekerja 0.150 Oh
Tukang batu 0.150 Oh
Kepala tukang 0.015 Oh
Mandor 0.0075 Oh
6.79 1 m2 Pasang wall covering lebar 50 cm
6.79.1 Bahan
Vinyl wall covering, lebar 50 cm 1.100 m2
Lem vinyl 0.255 Kg

6.79.2 Tenaga
Pekerja 0.750 Oh
Tukang batu 0.175 Oh
Kepala tukang 0.017 Oh
Mandor 0.0085 Oh

6.80 1 m2 Floor hardener ferrovax


6.80.1 Bahan
Floor hardener ferrovax 3.000 Kg

6.80.2 Tenaga
Pekerja 0.120 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.006 Oh

6.81 1 m2 Floor hardener mastercron


6.81.1 Bahan
Mastercron "S" 5.000 Kg

6.81.2 Tenaga
Pekerja 0.120 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.006 Oh
6.82 1 m2 Floor hardener mastercron
6.82.1 Bahan
Kayu jati, papan 0.002 m3
Paku skrup 3.5" 0.050 Kg

6.82.2 Tenaga
Pekerja 0.120 Oh
Tukang batu 0.120 Oh
Kepala tukang 0.012 Oh
Mandor 0.006 Oh

ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN SNI 2


PEKERJAAN CAT

6.1 1 m2 Mengikis / mengerok permukaan cat tembok lama


6.1.1 Bahan
Soda api 0.050 Kg

6.1.2 Tenaga
Pekerja 0.150 Oh
Tukang cat
Kepala tukang
Mandor 0.0025 Oh

6.2 1 m2 Mencuci bidang permukaan tembok yang pernah di cat


6.2.1 Bahan
Sabun 0.05 Kg

6.2.2 Tenaga
Pekerja 0.150 Oh
Tukang cat
Kepala tukang
Mandor 0.0025 Oh

6.3 1 m2 Mengerok karat cat lama permukaan baja dengan cara manual
6.3.1 Bahan
Sabun 0.05 Kg

6.3.2 Tenaga
Pekerja 0.15 Oh
Tukang cat
Kepala tukang
Mandor 0.0025 Oh

6.4 1 m2 Menyabun permukaan tembok lama


6.4.1 Bahan
Sabun 0.05 Kg

6.4.2 Tenaga
Pekerja 0.15 Oh
Tukang cat
Kepala tukang
Mandor 0.0025 Oh

6.5 1 m2 Mengerok karat atau cat lama permukaan baja dengan panca pasir (sanblasting) dgn tingkat
kebersihan Sa 2.5
6.5.1 Bahan
Sabun 40.000 Kg
BBM 10.000 Ltr

6.5.2 Peralatan
Kompreso, blasting Pot, selang & nozzle Per hari

6.5.3 Tenaga
Pekerja 1.600 Oh
Tukang cat 1.600 Oh
Kepala tukang 0.800 Oh
Mandor 0.500 Oh

6.6 1 m2 Mendempul dan menggosok kayu


6.6.1 Bahan
Dempul jadi 0.080 Kg
Minyak cat 0.020 Kg
batu apung 0.010 Kg

6.6.2 Tenaga
Pekerja 0.040 Oh
Tukang cat 0.040 Oh
Kepala tukang 0.004 Oh
Mandor 0.0025 Oh

6.7 1 m2 Pengecatan bidang kayu lama


6.7.1 Bahan
Plamir 0.150 Kg
Cat dasar 0.170 Kg
Cat penutup 0.170 Kg

6.7.2 Tenaga
Pekerja 0.070 Oh
Tukang cat 0.075 Oh
Kepala tukang 0.0075 Oh
Mandor 0.0025 Oh

6.8 1 m2 Pengecatan bidang kayu baru(1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
6.8.1 Bahan
Cat meni 0.200 Kg
Plamir 0.150 Kg
Cat dasar 0.170 Kg
Cat penutup 0.260 Kg

6.8.2 Tenaga
Pekerja 0.070 Oh
Tukang cat 0.009 Oh
Kepala tukang 0.006 Oh
Mandor 0.0025 Oh

6.9 1 m2 Pengecatan bidang kayu baru(1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
6.9.1 Bahan
Cat meni 0.200 Kg
Plamir 0.150 Kg
Cat dasar 0.170 Kg
Cat penutup 0.350 Kg

6.9.2 Tenaga
Pekerja 0.070 Oh
Tukang cat 0.105 Oh
Kepala tukang 0.004 Oh
Mandor 0.0025 Oh

6.10 1 m2 Pelaburan bidang kayu dengan teak oil


6.10.1 Bahan
Teak oil 0.360 Ltr

6.10.2 Tenaga
Pekerja 0.040 Oh
Tukang cat 0.063 Oh
Kepala tukang 0.063 Oh
Mandor 0.0025 Oh
6.11 1 m2 Pelaburan bidang kayu dengan politur
6.11.1 Bahan
Politur 0.150 Ltr
Politur jadi 0.372 Ltr
Ampelas 2.000 Lbr

6.11.2 Tenaga
Pekerja
Tukang cat 0.060 Oh
Kepala tukang 0.016 Oh
Mandor 0.0025 Oh

6.12 1 m2 Pelaburan bidang kayu dengan cat residu dan ter


6.12.1 Bahan
Residu atau ter 0.350 Ltr

6.12.2 Tenaga
Pekerja 0.100 Oh
Tukang cat
Kepala tukang
Mandor 0.006 Oh

6.13 1 m2 Pelaburan bidang kayu dengan vernis


6.13.1 Bahan
Vernis 0.150 Ltr
Dempul 0.050 Kg
Ampelas 0.100 Lbr
Kuas 0.010 Bh

6.13.2 Tenaga
Pekerja 0.160 Oh
Tukang cat 0.160 Oh
Kepala tukang 0.016 Oh
Mandor 0.0025 Oh
6.14 1 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
6.14.1 Bahan
Plamir 0.100 Kg
Cat dasar 0.100 Kg
Cat penutup 0.260 Kg

6.14.2 Tenaga
Pekerja 0.020 Oh
Tukang cat 0.063 Oh
Kepala tukang 0.006 Oh
Mandor 0.0025 Oh

6.15 1 m2 Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup)
6.15.1 Bahan
Cat dasar 0.120 Kg
Cat penutup 0.180 Kg

6.15.2 Tenaga
Pekerja 0.028 Oh
Tukang cat 0.042 Oh
Kepala tukang 0.004 Oh
Mandor 0.0025 Oh

6.16 1 m2 melabur tembok dengan kalkarium


6.16.1 Bahan
Kalkarium 0.100 Kg

6.16.2 Tenaga
Pekerja 0.028 Oh
Tukang cat 0.042 Oh
Kepala tukang 0.0042 Oh
Mandor 0.0025 Oh

6.17 1 m2 melabur tembok dengan kapur sirih


6.17.1 Bahan
Ampelas 0.100 Lbr
Alang-alang 0.250 Ikat
Perancah kayu 0.002 m3
Kapur sirih 0.150 Kg

6.17.2 Tenaga
Pekerja 0.150 Oh
Tukang cat 0.001 Oh
Kepala tukang 0.0001 Oh
Mandor 0.0025 Oh

6.18 1 m2 melabur tembok dengan kapur sirih (untuk pemeliharaan


6.18.1 Bahan
Perancah kayu 0.002 m3
Kapur sirih 0.300 Kg

6.18.2 Tenaga
Pekerja 0.040 Oh
Tukang cat 0.005 Oh
Kepala tukang 0.0005 Oh
Mandor 0.0025 Oh

6.19 1 m2 Pemasangan wall paper


6.19.1 Bahan
Wall paper 1.200 m3
Perekat 0.200 Kg

6.19.2 Tenaga
Pekerja 0.020 Oh
Tukang cat 0.200 Oh
Kepala tukang 0.002 Oh
Mandor 0.0025 Oh

6.20 1 m2 Pengecatan permukaan baja dengan meni besi


6.20.1 Bahan
Meni besi 0.100 Kg
Kuas 0.010 Bh

6.20.2 Tenaga
Pekerja 0.020 Oh
Tukang cat 0.200 Oh
Kepala tukang 0.020 Oh
Mandor 0.010 Oh

6.21 1 m2 Pengecatan permukaan baja dengan meni besi


6.21.1 Bahan
Meni besi 0.100 Kg
Meni besi 0.010 Bh
Perancah kayu 0.020 m3

6.21.2 Tenaga
Pekerja 0.250 Oh
Tukang cat 0.025 Oh
Kepala tukang 0.0225 Oh
Mandor 0.0075 Oh
6.22 1 m2 Pengecatan permukaan baja lapis seng (galbani) secara manual sistem 4 lapis cat konvensional
dengan tebal 200 um
6.22.1 Bahan
Meni (read lead) A 0.100 Kg
Meni (read lead) A 0.100 Kg
Aluminium C 0.040 Kg
Aluminium B 0.040 Kg
Pengencer 0.010 Ltr
Perancah kayu 0.002 m3

6.22.2 Tenaga
Pekerja 0.006 Oh
Tukang cat 0.006 Oh
Kepala tukang 0.0225 Oh
Mandor 0.0075 Oh

6.23 1 m2 Pengecatan permukaan baja lapis seng (galbani) secara manual sistem 1 lapis cat mutakhir
dengan tebal 200 um
6.23.1 Bahan
Cat 0.300 Kg

6.23.2 Tenaga
Pekerja 0.006 Oh
Tukang cat 0.060 Oh
Kepala tukang 0.012 Oh
Mandor 0.006 Oh

6.24 1 m2 Pengecatan permukaan baja lapis seng (galbani) secara manual sistem 3 lapis cat konvensional
dengan tebal 200 um
6.24.1 Bahan
Cat dasar 0.110 Kg
Cata antara 0.170 Kg
Cat penutup 0.080 Kg
6.24.2 Tenaga
Pekerja 0.500 Oh
Tukang cat 0.800 Oh
Kepala tukang 0.300 Oh
Mandor 0.200 Oh

6.25 1 m2 Pengecatan permukaan baja lapis seng (galbani) secara semprot (airless spray) sistem 1 lapis c
6.25.1 dengan tebal 200 um
Bahan
Cat dasar 0.300 Kg

6.25.2 Tenaga
Pekerja 0.400 Oh
Tukang cat 0.700 Oh
Kepala tukang 0.200 Oh
Mandor 0.200 Oh
DAN PERUMAHAN SNI 2002

Rp 102,130.00 = Rp 127,662.50
Rp 1,502.00 = Rp 3,755.00
Rp 144,180.00 = Rp 720.90
Rp 177,220.00 = Rp 1,594.98
Rp 6,367,950.00 = Rp 458,492.40
Rp 24,630.00 = Rp 1,477.80
Rp 25,230.00 = Rp 10,092.00
Jumlah (1) = Rp 603,795.58

Rp 88,910.00 = Rp 17,782.00
Rp 59,470.00 = Rp 23,788.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 45,703.20
Jumlah (1) + (2) = Rp 649,498.78
Dibulatkan = Rp 649,500.00

Rp 102,130.00 = Rp 127,662.50
Rp 1,502.00 = Rp 3,755.00
Rp 73,890.00 = Rp 88,668.00
Rp 144,180.00 = Rp 720.90
Rp 177,220.00 = Rp 1,594.98
Rp 6,367,950.00 = Rp 458,492.40
Rp 24,630.00 = Rp 1,477.80
Rp 22,830.00 = Rp 10,273.50
Jumlah (1) = Rp 692,645.08

Rp 88,910.00 = Rp 17,782.00
Rp 59,470.00 = Rp 23,788.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 45,703.20
Jumlah (1) + (2) = Rp 738,348.28
Dibulatkan = Rp 738,300.00
Rp 102,130.00 = Rp 102,130.00
Rp 1,502.00 = Rp 3,004.00
Rp - = Rp -
Rp 144,180.00 = Rp 720.90
Rp 177,220.00 = Rp 1,594.98
Rp 24,630.00 = Rp 1,477.80
Jumlah (1) = Rp 108,927.68

Rp 88,910.00 = Rp 17,782.00
Rp 59,470.00 = Rp 17,841.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 39,756.20
Jumlah (1) + (2) = Rp 148,683.88
Dibulatkan = Rp 148,700.00

Rp 6,367,950.00 = Rp 76,415.40
Rp 24,630.00 = Rp 492.60
Rp 6,367,950.00 = Rp 44,575.65
Jumlah (1) = Rp 121,483.65

Rp 88,910.00 = Rp 8,891.00
Rp 59,470.00 = Rp 5,947.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 16,387.95
Jumlah (1) + (2) = Rp 137,871.60
Dibulatkan = Rp 137,900.00

Rp 102,130.00 = Rp 127,662.50
Rp 6,367,950.00 = Rp 1,146,231.00
Rp 6,367,950.00 = Rp 5,412,757.50
Rp 38,445.00 = Rp 42,289.50
Rp 1,502.00 = Rp 52,570.00
Rp 144,180.00 = Rp 21,627.00
Rp 144,180.00 = Rp 14,418.00
Rp 177,220.00 = Rp 26,583.00
Rp 840.00 = Rp 25,200.00
Rp 177,150.00 = Rp 44,287.50
Rp 4,930.00 = Rp 9,860.00
Rp 158,600.00 = Rp 12,688.00
Rp 52,270.00 = Rp 7,840.50
Rp 127,960.00 = Rp 7,677.60
Jumlah (1) = Rp 6,951,692.10

Rp 88,910.00 = Rp 177,820.00
Rp 88,910.00 = Rp 88,910.00
Rp 59,470.00 = Rp 118,940.00
Rp 103,330.00 = Rp 30,999.00
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 421,835.50
Jumlah (1) + (2) = Rp 7,373,527.60
Dibulatkan = Rp 7,373,500.00

Rp 102,130.00 = Rp 173,621.00
Rp 6,367,950.00 = Rp 1,337,269.50
Rp 24,630.00 = Rp 7,389.00
Rp 1,502.00 = Rp 15,771.00
Rp 144,180.00 = Rp 4,325.40
Rp 177,220.00 = Rp 8,861.00
Rp 177,150.00 = Rp 265,725.00
Jumlah (1) = Rp 1,812,961.90

Rp 88,910.00 = Rp 177,820.00
Rp 59,470.00 = Rp 59,470.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 263,122.50
Jumlah (1) + (2) = Rp 2,076,084.40
Dibulatkan = Rp 2,076,100.00

Rp 102,130.00 = Rp 306,390.00
Rp 6,367,950.00 = Rp 1,757,554.20
Rp 24,630.00 = Rp 17,241.00
Rp 177,150.00 = Rp 265,725.00
Jumlah (1) = Rp 2,346,910.20

Rp 88,910.00 = Rp 133,365.00
Rp 59,470.00 = Rp 59,470.00
Rp 103,330.00 = Rp 15,499.50
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 213,501.00
Jumlah (1) + (2) = Rp 2,560,411.20
Dibulatkan = Rp 2,560,400.00

Rp 59,470.00 = Rp 59,470.00
Rp 103,330.00 = Rp 5,166.50
Jumlah = Rp 64,636.50

Rp 102,130.00 = Rp 127,662.50
Rp 6,367,950.00 = Rp 118,443.87
Rp 24,630.00 = Rp 7,389.00
Rp 1,502.00 = Rp 27,036.00
Rp 144,180.00 = Rp 4,325.40
Rp 177,220.00 = Rp 8,861.00
Rp 177,150.00 = Rp 265,725.00
Rp 127,960.00 = Rp 172,746.00
Jumlah (1) = Rp 732,188.77

Rp 88,910.00 = Rp 177,820.00
Rp 59,470.00 = Rp 59,470.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 263,122.50
Jumlah (1) + (2) = Rp 995,311.27
Dibulatkan = Rp 995,300.00

Rp 6,367,950.00 = Rp 229,246.20
Rp 24,630.00 = Rp 1,970.40
Rp - = Rp -
Jumlah (1) = Rp 231,216.60
Rp 88,910.00 = Rp 26,673.00
Rp 103,330.00 = Rp 155.00
Jumlah (2) = Rp 26,828.00
Jumlah (1) + (2) = Rp 258,044.60
Dibulatkan = Rp 258,000.00

Rp 84,110.00 = Rp 84,110.00
Rp - = Rp -
Jumlah (1) = Rp 84,110.00

Rp 88,910.00 = Rp 1,511.47
Rp 59,470.00 = Rp 118.94
Rp 103,330.00 = Rp 25,832.50
Rp 103,330.00 = Rp 1,343.29
Jumlah (2) = Rp 28,806.20
Jumlah (1) + (2) = Rp 112,916.20
Dibulatkan = Rp 112,900.00

Rp 303,380.00 = Rp 45,507.00
Rp 291,960.00 = Rp 26,276.40
Rp 291,960.00 = Rp 2,919.60
Jumlah (1) = Rp 300,519.20

Rp 59,470.00 = Rp 59,470.00
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 64,636.50
Jumlah (1) + (2) = Rp 365,155.70
Dibulatkan = Rp 365,200.00

Rp 59,470.00 = Rp 396,486.49
Rp 103,330.00 = Rp 34,408.89
Jumlah = Rp 430,895.38

Rp 59,470.00 = Rp 396,486.49
Rp 103,330.00 = Rp 34,408.89
Jumlah = Rp 430,895.38
= Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 2,497.74
Rp 103,330.00 = Rp 413.32
Rp 88,910.00 = Rp 3,734.22
Rp 103,330.00 = Rp 206.66
Jumlah (2) = Rp 6,851.94
Jumlah (1) + (2) = Rp 6,851.94
Dibulatkan = Rp 6,900.00

Rp - = Rp -
Rp - = Rp -
Rp 144,180.00 = Rp 10,669.32
Rp 177,220.00 = Rp 25,874.12
Rp 1,502.00 = Rp 67,590.00
Jumlah (1) = Rp 104,133.44

Rp 88,910.00 = Rp 11,113.75
Rp 59,470.00 = Rp 22,301.25
Rp 103,330.00 = Rp 1,239.96
Rp 88,910.00 = Rp 1,689.29
Jumlah (2) = Rp 36,344.25
Jumlah (1) + (2) = Rp 140,477.69
Dibulatkan = Rp 140,500.00

N GEDUNG DAN PERUMAHAN SNI 2002


TANAH

Rp 59,470.00 = Rp 23,788.00
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 4,133.20
Jumlah = Rp 27,921.20
Rp 59,470.00 = Rp 31,281.22
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 5,373.16
Jumlah = Rp 36,654.38

Rp 59,470.00 = Rp 43,710.45
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 7,543.09
Jumlah = Rp 51,253.54

Rp 59,470.00 = Rp 37,168.75
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 6,406.46
Jumlah = Rp 43,575.21

Rp 59,470.00 = Rp 74,337.50
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 12,916.25
Jumlah = Rp 87,253.75

Rp 59,470.00 = Rp 48,943.81
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 8,576.39
Jumlah = Rp 57,520.20

Rp 59,470.00 = Rp 2,973.50
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 516.65
Jumlah = Rp 3,490.15
Rp 59,470.00 = Rp 30,805.46
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 5,166.50
Jumlah = Rp 35,971.96

Rp 59,470.00 = Rp 11,418.24
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 1,963.27
Jumlah = Rp 13,381.51

Rp 59,470.00 = Rp 29,735.00
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 5,166.50
Jumlah = Rp 34,901.50

Rp 106,930.00 = Rp 128,316.00
Jumlah (1) = Rp 128,316.00

Rp 59,470.00 = Rp 17,841.00
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 18,874.30
Jumlah (1) + (2) = Rp 147,190.30
Dibulatkan = Rp 147,200.00

Rp 106,930.00 = Rp 35,286.90
Rp - = Rp -
Rp 97,320.00 = Rp 74,255.16
Jumlah (1) = Rp 109,542.06

Rp 59,470.00 = Rp 49,538.51
Rp 88,910.00 = Rp 36,986.56
Rp 103,330.00 = Rp 4,133.20
Rp 103,330.00 = Rp 8,576.39
Jumlah (2) = Rp 99,234.66
Jumlah (1) + (2) = Rp 208,776.72
Dibulatkan = Rp 208,800.00

Rp - = Rp -
Rp 97,320.00 = Rp 97,320.00
Jumlah (1) = Rp 97,320.00

Rp 59,470.00 = Rp 49,538.51
Rp 88,910.00 = Rp 36,986.56
Rp 103,330.00 = Rp 4,236.53
Rp 103,330.00 = Rp 8,369.73
Jumlah (2) = Rp 99,131.33
Jumlah (1) + (2) = Rp 196,451.33
Dibulatkan = Rp 196,500.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,920.50
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 1,549.95
Jumlah (2) = Rp 10,470.45
Jumlah (1) + (2) = Rp 10,470.45
Dibulatkan = Rp 10,500.00

Rp 164,010.00 = Rp 196,812.00
Jumlah (1) = Rp 196,812.00

Rp 59,470.00 = Rp 14,867.50
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 2,583.25
Jumlah (2) = Rp 17,450.75
Jumlah (1) + (2) = Rp 214,262.75
Dibulatkan = Rp 214,300.00

Rp 303,380.00 = Rp 83,429.50
Rp 164,010.00 = Rp 4,920.30
Rp 144,180.00 = Rp 7,209.00
Jumlah (1) = Rp 95,558.80

Rp 59,470.00 = Rp 59,470.00
Rp - = Rp -
Rp - = Rp -
Rp 103,330.00 = Rp 10,333.00
Jumlah (2) = Rp 69,803.00
Jumlah (1) + (2) = Rp 165,361.80
Dibulatkan = Rp 165,400.00

N GEDUNG DAN PERUMAHAN SNI 2002


PONDASI

Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 588,784.00
Rp 144,180.00 = Rp 45,272.52
Jumlah (1) = Rp 828,998.52

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 53,346.00
Rp 103,330.00 = Rp 6,199.80
Rp 103,330.00 = Rp 7,749.75
Jumlah (2) = Rp 156,500.55
Jumlah (1) + (2) = Rp 985,499.07
Dibulatkan = Rp 985,500.00

Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 401,034.00
Rp 144,180.00 = Rp 61,564.86
Jumlah (1) = Rp 657,540.86

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 948,308.66
Dibulatkan = Rp 948,300.00

Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 588,784.00
Rp 144,180.00 = Rp 45,272.52
Jumlah (1) = Rp 828,998.52

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 1,119,766.32
Dibulatkan = Rp 1,119,800.00

Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 303,404.00
Rp 144,180.00 = Rp 69,927.30
Jumlah (1) = Rp 568,273.30

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 859,041.10
Dibulatkan = Rp 859,000.00

Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 244,826.00
Rp 144,180.00 = Rp 74,973.60
Jumlah (1) = Rp 514,741.60

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 805,509.40
Dibulatkan = Rp 805,500.00

Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 204,272.00
Rp 144,180.00 = Rp 78,433.92
Jumlah (1) = Rp 477,647.92

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 768,415.72
Dibulatkan = Rp 768,400.00

Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 175,734.00
Rp 144,180.00 = Rp 80,884.98
Jumlah (1) = Rp 451,560.98

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 742,328.78
Dibulatkan = Rp 742,300.00
Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 136,682.00
Rp 144,180.00 = Rp 80,884.98
Jumlah (1) = Rp 412,508.98

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 703,276.78
Dibulatkan = Rp 703,300.00

Rp 177,220.00 = Rp 194,942.00
Rp 2,400.00 = Rp 549.60
Rp 3,439.25 = Rp 787.59
Rp 144,180.00 = Rp 78,433.92
Jumlah (1) = Rp 274,713.11

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 565,480.91
Dibulatkan = Rp 565,500.00

Rp 177,220.00 = Rp 194,942.00
Rp 2,400.00 = Rp 549.60
Rp 3,439.25 = Rp 787.59
Rp 144,180.00 = Rp 78,433.92
Jumlah (1) = Rp 274,713.11

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 565,480.91
Dibulatkan = Rp 565,500.00

Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 234,312.00
Rp 3,439.25 = Rp 110.06
Rp 144,180.00 = Rp 84,201.12
Jumlah (1) = Rp 513,565.18

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 804,332.98
Dibulatkan = Rp 804,300.00

Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 91,622.00
Rp 3,439.25 = Rp 505.57
Rp 144,180.00 = Rp 70,936.56
Jumlah (1) = Rp 358,006.13

Rp 59,470.00 = Rp 89,205.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 290,767.80
Jumlah (1) + (2) = Rp 648,773.93
Dibulatkan = Rp 648,800.00

Rp 177,220.00 = Rp 194,942.00
Rp 1,502.00 = Rp 61,582.00
Rp 3,439.25 = Rp 450.54
Rp 144,180.00 = Rp 75,406.14
Jumlah (1) = Rp 332,380.68
Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 61,998.00
Rp 103,330.00 = Rp 6,199.80
Jumlah (2) = Rp 201,562.80
Jumlah (1) + (2) = Rp 533,943.48
Dibulatkan = Rp 533,900.00

Rp 177,220.00 = Rp 212,664.00
Rp 106,930.00 = Rp 32,079.00
Jumlah (1) = Rp 244,743.00

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 69,349.80
Rp 103,330.00 = Rp 40,298.70
Rp 103,330.00 = Rp 4,029.87
Jumlah (2) = Rp 113,678.37
Jumlah (1) + (2) = Rp 358,421.37
Dibulatkan = Rp 358,400.00

Rp 17,420.00 = Rp 1,306,500.00
Rp 1,502.00 = Rp 303,404.00
Rp 144,180.00 = Rp 46,137.60
Rp 177,220.00 = Rp 86,837.80
Rp 24,030.00 = Rp 19,224.00
Jumlah (1) = Rp 1,762,103.40

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 266,730.00
Rp 103,330.00 = Rp 87,830.50
Rp 103,330.00 = Rp 8,783.05
Jumlah (2) = Rp 363,343.55
Jumlah (1) + (2) = Rp 2,125,446.95
Dibulatkan = Rp 2,125,400.00

Rp 177,220.00 = Rp 79,749.00
Rp 1,502.00 = Rp 420,560.00
Rp 144,180.00 = Rp 64,881.00
Rp 177,220.00 = Rp 118,737.40
Jumlah (1) = Rp 683,927.40

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 204,493.00
Rp 103,330.00 = Rp 30,999.00
Rp 103,330.00 = Rp 3,099.90
Jumlah (2) = Rp 238,591.90
Jumlah (1) + (2) = Rp 922,519.30
Dibulatkan = Rp 922,500.00

Rp 106,930.00 = Rp 2,031.67
Rp 144,180.00 = Rp 13,552.92
Rp 177,220.00 = Rp 26,583.00
Rp 1,502.00 = Rp 90,871.00
Rp 17,420.00 = Rp 783,900.00
Rp 24,030.00 = Rp 21,627.00
Rp 6,367,950.00 = Rp 203,774.40
Rp 24,630.00 = Rp 2,955.60
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp 1,145,295.59

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 88,910.00
Rp 103,330.00 = Rp 69,231.10
Rp 103,330.00 = Rp 6,923.11
Jumlah (2) = Rp 165,064.21
Jumlah (1) + (2) = Rp 1,310,359.80
Dibulatkan = Rp 1,310,400.00

Rp 106,930.00 = Rp 1,710.88
Rp 144,180.00 = Rp 11,534.40
Rp 177,220.00 = Rp 22,152.50
Rp 1,502.00 = Rp 73,598.00
Rp 17,420.00 = Rp 600,990.00
Rp 24,030.00 = Rp 16,821.00
Rp 6,367,950.00 = Rp 171,934.65
Rp 24,630.00 = Rp 2,955.60
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp 901,697.03

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 71,128.00
Rp 103,330.00 = Rp 51,665.00
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 127,959.50
Jumlah (1) + (2) = Rp 1,029,656.53
Dibulatkan = Rp 1,029,700.00

N GEDUNG DAN PERUMAHAN SNI 2002


DINDING

Rp 840.00 = Rp 117,600.00
Rp 1,502.00 = Rp 96,173.06
Rp 144,180.00 = Rp 8,506.62
Jumlah (1) = Rp 222,279.68

Rp 59,470.00 = Rp 38,655.50
Rp 88,910.00 = Rp 57,791.50
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 119,179.60
Jumlah (1) + (2) = Rp 341,459.28
Dibulatkan = Rp 341,500.00

Rp 840.00 = Rp 117,600.00
Rp 1,502.00 = Rp 65,337.00
Rp 144,180.00 = Rp 11,534.40
Jumlah (1) = Rp 194,471.40

Rp 59,470.00 = Rp 38,655.50
Rp 88,910.00 = Rp 57,791.50
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 119,179.60
Jumlah (1) + (2) = Rp 313,651.00
Dibulatkan = Rp 313,700.00

Rp 840.00 = Rp 117,600.00
Rp 1,502.00 = Rp 49,490.90
Rp 144,180.00 = Rp 13,120.38
Jumlah (1) = Rp 180,211.28

Rp 59,470.00 = Rp 38,655.50
Rp 88,910.00 = Rp 57,791.50
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 119,179.60
Jumlah (1) + (2) = Rp 299,390.88
Dibulatkan = Rp 299,400.00

Rp 840.00 = Rp 117,600.00
Rp 1,502.00 = Rp 39,878.10
Rp 144,180.00 = Rp 13,408.74
Jumlah (1) = Rp 170,886.84

Rp 59,470.00 = Rp 38,655.50
Rp 88,910.00 = Rp 57,791.50
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 119,179.60
Jumlah (1) + (2) = Rp 290,066.44
Dibulatkan = Rp 290,100.00

Rp 840.00 = Rp 117,600.00
Rp 1,502.00 = Rp 33,344.40
Rp 144,180.00 = Rp 14,706.36
Jumlah (1) = Rp 165,650.76

Rp 59,470.00 = Rp 38,655.50
Rp 88,910.00 = Rp 57,791.50
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 119,179.60
Jumlah (1) + (2) = Rp 284,830.36
Dibulatkan = Rp 284,800.00

Rp 840.00 = Rp 117,600.00
Rp 1,502.00 = Rp 33,344.40
Rp 144,180.00 = Rp 14,706.36
Jumlah (1) = Rp 165,650.76

Rp 59,470.00 = Rp 38,655.50
Rp 88,910.00 = Rp 57,791.50
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 119,179.60
Jumlah (1) + (2) = Rp 284,830.36
Dibulatkan = Rp 284,800.00

Rp 840.00 = Rp 117,600.00
Rp 1,502.00 = Rp 15,140.16
Rp 144,180.00 = Rp 13,336.65
Rp 2,400.00 = Rp 66.00
Jumlah (1) = Rp 146,142.81

Rp 59,470.00 = Rp 38,655.50
Rp 88,910.00 = Rp 57,791.50
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 119,179.60
Jumlah (1) + (2) = Rp 265,322.41
Dibulatkan = Rp 265,300.00

Rp 840.00 = Rp 58,800.00
Rp 1,502.00 = Rp 41,755.60
Rp 144,180.00 = Rp 4,037.04
Jumlah (1) = Rp 104,592.64
Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 58,847.90
Jumlah (1) + (2) = Rp 163,440.54
Dibulatkan = Rp 163,400.00

Rp 840.00 = Rp 58,800.00
Rp 1,502.00 = Rp 28,462.90
Rp 144,180.00 = Rp 5,478.84
Jumlah (1) = Rp 92,741.74

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 39,817.50
Jumlah (1) + (2) = Rp 132,559.24
Dibulatkan = Rp 132,600.00

Rp 840.00 = Rp 58,800.00
Rp 1,502.00 = Rp 21,583.74
Rp 144,180.00 = Rp 5,767.20
Jumlah (1) = Rp 86,150.94

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 39,817.50
Jumlah (1) + (2) = Rp 125,968.44
Dibulatkan = Rp 126,000.00

Rp 840.00 = Rp 58,800.00
Rp 1,502.00 = Rp 17,273.00
Rp 144,180.00 = Rp 6,199.74
Jumlah (1) = Rp 82,272.74

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 39,817.50
Jumlah (1) + (2) = Rp 122,090.24
Dibulatkan = Rp 122,100.00

Rp 840.00 = Rp 58,800.00
Rp 1,502.00 = Rp 14,539.36
Rp 144,180.00 = Rp 6,488.10
Jumlah (1) = Rp 79,827.46

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 39,817.50
Jumlah (1) + (2) = Rp 119,644.96
Dibulatkan = Rp 119,600.00

Rp 840.00 = Rp 58,800.00
Rp 1,502.00 = Rp 12,496.64
Rp 144,180.00 = Rp 7,064.82
Jumlah (1) = Rp 78,361.46

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 39,817.50
Jumlah (1) + (2) = Rp 118,178.96
Dibulatkan = Rp 118,200.00
Rp 840.00 = Rp 58,800.00
Rp 1,502.00 = Rp 9,763.00
Rp 144,180.00 = Rp 7,209.00
Jumlah (1) = Rp 75,772.00

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 39,817.50
Jumlah (1) + (2) = Rp 115,589.50
Dibulatkan = Rp 115,600.00

Rp 840.00 = Rp 58,800.00
Rp 1,502.00 = Rp 6,759.00
Rp 144,180.00 = Rp 7,209.00
Rp - = Rp -
Jumlah (1) = Rp 72,768.00

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 58,847.90
Jumlah (1) + (2) = Rp 131,615.90
Dibulatkan = Rp 131,600.00

Rp 840.00 = Rp 58,800.00
Rp 1,502.00 = Rp 27.04
Rp 144,180.00 = Rp 2,595.24
Rp - = Rp -
Jumlah (1) = Rp 61,422.28

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 39,817.50
Jumlah (1) + (2) = Rp 101,239.78
Dibulatkan = Rp 101,200.00

Rp 840.00 = Rp 58,800.00
Rp 1,502.00 = Rp 21.03
Rp 144,180.00 = Rp 4,037.04
Rp - = Rp -
Jumlah (1) = Rp 62,858.07

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 39,817.50
Jumlah (1) + (2) = Rp 102,675.57
Dibulatkan = Rp 102,700.00

Rp - = Rp -
Rp 1,502.00 = Rp 20,277.00
Rp 144,180.00 = Rp 6,920.64
Rp 17,420.00 = Rp 33,969.00
Jumlah (1) = Rp 61,166.64

Rp 59,470.00 = Rp 20,814.50
Rp 88,910.00 = Rp 31,118.50
Rp 103,330.00 = Rp 15,499.50
Rp 103,330.00 = Rp 1,549.95
Jumlah (2) = Rp 68,982.45
Jumlah (1) + (2) = Rp 130,149.09
Dibulatkan = Rp 130,100.00

Rp - = Rp -
Rp 1,502.00 = Rp 15,695.90
Rp 144,180.00 = Rp 5,478.84
Rp 17,420.00 = Rp 33,969.00
Jumlah (1) = Rp 55,143.74

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 12,399.60
Rp 103,330.00 = Rp 1,239.96
Jumlah (2) = Rp 61,121.16
Jumlah (1) + (2) = Rp 116,264.90
Dibulatkan = Rp 116,300.00

Rp - = Rp -
Rp 1,502.00 = Rp 11,265.00
Rp 144,180.00 = Rp 3,892.86
Rp 17,420.00 = Rp 33,969.00
Jumlah (1) = Rp 49,126.86

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 12,399.60
Rp 103,330.00 = Rp 1,239.96
Jumlah (2) = Rp 61,121.16
Jumlah (1) + (2) = Rp 110,248.02
Dibulatkan = Rp 110,200.00

= Rp -
Rp 1,502.00 = Rp 21,103.10
Rp 144,180.00 = Rp 576.72
Rp 144,180.00 = Rp 6,055.56
Rp 17,420.00 = Rp 67,415.40
Rp 24,630.00 = Rp 147.78
Rp 6,367,950.00 = Rp 6,367.95
Rp 24,030.00 = Rp 720.90
Rp 177,220.00 = Rp 886.10
Jumlah (1) = Rp 103,273.51

Rp 59,470.00 = Rp 22,003.90
Rp 88,910.00 = Rp 32,896.70
Rp 88,910.00 = Rp 13,958.87
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 1,694.61
Jumlah (2) = Rp 71,277.39
Jumlah (1) + (2) = Rp 174,550.90
Dibulatkan = Rp 174,600.00

Rp - = Rp -
Rp 1,502.00 = Rp 15,710.92
Rp 144,180.00 = Rp 432.54
Rp 144,180.00 = Rp 4,613.76
Rp 17,420.00 = Rp 15,155.40
Rp 24,630.00 = Rp 98.52
Rp 6,367,950.00 = Rp 6,367.95
Rp 24,030.00 = Rp 480.60
Rp 177,220.00 = Rp 708.88
Jumlah (1) = Rp 43,568.57

Rp 59,470.00 = Rp 20,219.80
Rp 88,910.00 = Rp 30,229.40
Rp 88,910.00 = Rp 11,558.30
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 1,415.62
Jumlah (2) = Rp 64,146.43
Jumlah (1) + (2) = Rp 107,715.00
Dibulatkan = Rp 107,700.00

Rp - = Rp -
Rp 1,502.00 = Rp 10,814.40
Rp 144,180.00 = Rp 288.36
Rp 144,180.00 = Rp 3,027.78
Rp 17,420.00 = Rp 44,246.80
Rp 24,630.00 = Rp 73.89
Rp 6,367,950.00 = Rp 6,367.95
Rp 24,030.00 = Rp 360.45
Rp 177,220.00 = Rp 531.66
Jumlah (1) = Rp 65,711.29

Rp 59,470.00 = Rp 20,219.80
Rp 88,910.00 = Rp 30,229.40
Rp 88,910.00 = Rp 9,513.37
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 1,177.96
Jumlah (2) = Rp 61,863.84
Jumlah (1) + (2) = Rp 127,575.13
Dibulatkan = Rp 127,600.00

Rp - = Rp -
Rp 1,502.00 = Rp 7,660.20
Rp 144,180.00 = Rp 11,534.40
Rp 17,420.00 = Rp 26,130.00
Rp 177,220.00 = Rp 26,583.00
Jumlah (1) = Rp 71,907.60

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 2,667.30
Rp 88,910.00 = Rp 2,667.30
Rp 103,330.00 = Rp 619.98
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 12,418.23
Jumlah (1) + (2) = Rp 84,325.83
Dibulatkan = Rp 84,300.00

Rp - = Rp -
Rp 1,502.00 = Rp 19,225.60
Rp 144,180.00 = Rp 5,046.30
Jumlah (1) = Rp 24,271.90

Rp 59,470.00 = Rp 17,841.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 1,549.95
Jumlah (2) = Rp 29,315.25
Jumlah (1) + (2) = Rp 53,587.15
Dibulatkan = Rp 53,600.00

Rp 960.00 = Rp 76,800.00
Rp 1,502.00 = Rp 35,522.30
Rp 144,180.00 = Rp 82,182.60
Jumlah (1) = Rp 194,504.90
Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,549.95
Jumlah (2) = Rp 35,466.80
Jumlah (1) + (2) = Rp 229,971.70
Dibulatkan = Rp 230,000.00

Rp - = Rp -
Rp 6,367,950.00 = Rp 89,151.30
Rp 24,630.00 = Rp 295.56
Rp - = Rp -
Jumlah (1) = Rp 89,446.86

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 4,445.50
Rp 103,330.00 = Rp 516.65
Rp 103,330.00 = Rp 206.66
Jumlah (2) = Rp 11,115.81
Jumlah (1) + (2) = Rp 100,562.67
Dibulatkan = Rp 100,600.00

N GEDUNG DAN PERUMAHAN SNI 2002


LESTERAN

Rp 1,502.00 = Rp 19,405.84
Rp 144,180.00 = Rp 1,874.34
Jumlah (1) = Rp 21,280.18

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 49,093.93
Dibulatkan = Rp 49,100.00
Rp 1,502.00 = Rp 12,797.04
Rp 144,180.00 = Rp 2,451.06
Jumlah (1) = Rp 15,248.10

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 43,061.85
Dibulatkan = Rp 43,100.00

Rp 1,502.00 = Rp 9,732.96
Rp 144,180.00 = Rp 2,739.42
Jumlah (1) = Rp 12,472.38

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 40,286.13
Dibulatkan = Rp 40,300.00

Rp 1,502.00 = Rp 7,810.40
Rp 144,180.00 = Rp 2,883.60
Jumlah (1) = Rp 10,694.00

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 38,507.75
Dibulatkan = Rp 38,500.00
Rp 1,502.00 = Rp 6,488.64
Rp 144,180.00 = Rp 3,171.96
Jumlah (1) = Rp 9,660.60

Rp 59,470.00 = Rp 892.05
Rp 88,910.00 = Rp 889.10
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 4,364.40
Jumlah (1) + (2) = Rp 14,025.00
Dibulatkan = Rp 14,000.00

Rp 1,502.00 = Rp 5,707.60
Rp 144,180.00 = Rp 3,316.14
Jumlah (1) = Rp 9,023.74

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 36,837.49
Dibulatkan = Rp 36,800.00

Rp 1,502.00 = Rp 4,325.76
Rp 144,180.00 = Rp 3,460.32
Jumlah (1) = Rp 7,786.08

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 35,599.83
Dibulatkan = Rp 35,600.00
Rp 1,502.00 = Rp 8,651.52
Rp - = Rp -
Rp 144,180.00 = Rp 1,874.34
Jumlah (1) = Rp 10,525.86

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 38,339.61
Dibulatkan = Rp 38,300.00

Rp 1,502.00 = Rp 2,763.68
Rp - = Rp -
Rp 144,180.00 = Rp 2,018.52
Jumlah (1) = Rp 4,782.20

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 32,595.95
Dibulatkan = Rp 32,600.00

Rp 1,502.00 = Rp 4,506.00
Rp - = Rp -
Rp 144,180.00 = Rp 2,739.42
Jumlah (1) = Rp 7,245.42

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 35,059.17
Dibulatkan = Rp 35,100.00
Rp 3,439.25 = Rp 30.95
Rp - = Rp -
Rp 144,180.00 = Rp 1,297.62
Jumlah (1) = Rp 1,328.57

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 29,142.32
Dibulatkan = Rp 29,100.00

Rp 3,439.25 = Rp 24.07
Rp - = Rp -
Rp 144,180.00 = Rp 2,162.70
Jumlah (1) = Rp 2,186.77

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 27,813.75
Jumlah (1) + (2) = Rp 30,000.52
Dibulatkan = Rp 30,000.00

Rp 1,502.00 = Rp 21,448.56
Rp 144,180.00 = Rp 3,316.14
Jumlah (1) = Rp 24,764.70

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 36,007.73
Jumlah (1) + (2) = Rp 60,772.43
Dibulatkan = Rp 60,800.00

Rp 1,502.00 = Rp 16,221.60
Rp 144,180.00 = Rp 3,748.68
Jumlah (1) = Rp 19,970.28

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 36,007.73
Jumlah (1) + (2) = Rp 55,978.01
Dibulatkan = Rp 56,000.00

Rp 1,502.00 = Rp 13,037.36
Rp 144,180.00 = Rp 4,037.04
Jumlah (1) = Rp 17,074.40

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 36,007.73
Jumlah (1) + (2) = Rp 53,082.13
Dibulatkan = Rp 53,100.00

Rp 1,502.00 = Rp 10,949.58
Rp 144,180.00 = Rp 4,037.04
Jumlah (1) = Rp 14,986.62

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,291.63
Jumlah (1) + (2) = Rp 36,007.73
Dibulatkan = Rp 50,994.35
Dibulatkan = Rp 51,000.00
Rp 1,502.00 = Rp 9,372.48
Rp 144,180.00 = Rp 4,325.40
Jumlah (1) = Rp 13,697.88

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,291.63
Dibulatkan = Rp 36,007.73
Dibulatkan = Rp 49,705.61
Dibulatkan = Rp 49,700.00

Rp 3,439.25 = Rp 30.95
Rp - = Rp -
Rp 144,180.00 = Rp 2,595.24
Jumlah (1) = Rp 2,626.19

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 36,007.73
Jumlah (1) + (2) = Rp 38,633.92
Dibulatkan = Rp 38,600.00

Rp 1,502.00 = Rp 23,281.00
Rp 144,180.00 = Rp 1,874.34
Jumlah (1) = Rp 25,155.34

Rp 59,470.00 = Rp 17,841.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 38,981.23
Jumlah (1) + (2) = Rp 64,136.57
Dibulatkan = Rp 64,100.00
Rp 1,502.00 = Rp 17,648.50
Rp 144,180.00 = Rp 5,046.30
Jumlah (1) = Rp 22,694.80

Rp 59,470.00 = Rp 17,841.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 38,981.23
Jumlah (1) + (2) = Rp 61,676.03
Dibulatkan = Rp 61,700.00

Rp 1,502.00 = Rp 14,238.96
Rp 144,180.00 = Rp 5,478.84
Jumlah (1) = Rp 19,717.80

Rp 59,470.00 = Rp 17,841.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 38,981.23
Jumlah (1) + (2) = Rp 58,699.03
Dibulatkan = Rp 58,700.00

Rp 1,502.00 = Rp 11,925.88
Rp 144,180.00 = Rp 5,623.02
Jumlah (1) = Rp 17,548.90

Rp 59,470.00 = Rp 17,841.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 38,981.23
Jumlah (1) + (2) = Rp 56,530.13
Dibulatkan = Rp 56,500.00

Rp 1,502.00 = Rp 28,012.30
Rp 144,180.00 = Rp 5,046.30
Jumlah (1) = Rp 33,058.60

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 1,549.95
Jumlah (2) = Rp 45,391.10
Jumlah (1) + (2) = Rp 78,449.70
Dibulatkan = Rp 78,400.00

Rp 1,502.00 = Rp 21,253.30
Rp 144,180.00 = Rp 5,623.02
Jumlah (1) = Rp 26,876.32

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 1,549.95
Jumlah (2) = Rp 45,391.10
Jumlah (1) + (2) = Rp 72,267.42
Dibulatkan = Rp 72,300.00

Rp 1,502.00 = Rp 17,092.76
Rp 144,180.00 = Rp 6,055.56
Jumlah (1) = Rp 23,148.32

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 1,549.95
Jumlah (2) = Rp 45,391.10
Jumlah (1) + (2) = Rp 68,539.42
Dibulatkan = Rp 68,500.00

Rp 1,502.00 = Rp 12,301.38
Rp 144,180.00 = Rp 6,488.10
Jumlah (1) = Rp 18,789.48

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 1,549.95
Jumlah (2) = Rp 45,391.10
Jumlah (1) + (2) = Rp 64,180.58
Dibulatkan = Rp 64,200.00

Rp 1,502.00 = Rp 10,619.14
Rp 144,180.00 = Rp 3,027.78
Jumlah (1) = Rp 13,646.92

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 826.64
Jumlah (2) = Rp 16,694.15
Jumlah (1) + (2) = Rp 30,341.07
Dibulatkan = Rp 30,300.00

Rp 1,502.00 = Rp 8,516.34
Rp 144,180.00 = Rp 3,316.14
Jumlah (1) = Rp 11,832.48

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 826.64
Jumlah (2) = Rp 16,694.15
Jumlah (1) + (2) = Rp 28,526.63
Dibulatkan = Rp 28,500.00

Rp 1,502.00 = Rp 13,968.60
Rp 144,180.00 = Rp 2,595.24
Jumlah (1) = Rp 16,563.84

Rp 59,470.00 = Rp 15,462.20
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,343.29
Jumlah (2) = Rp 36,654.09
Jumlah (1) + (2) = Rp 53,217.93
Dibulatkan = Rp 53,200.00

Rp 1,502.00 = Rp 10,619.14
Rp 144,180.00 = Rp 3,027.78
Jumlah (1) = Rp 13,646.92

Rp 59,470.00 = Rp 15,462.20
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,343.29
Jumlah (2) = Rp 36,654.09
Jumlah (1) + (2) = Rp 50,301.01
Dibulatkan = Rp 50,300.00

Rp 1,502.00 = Rp 751.00
Rp 144,180.00 = Rp 288.36
Jumlah (1) = Rp 1,039.36

Rp 59,470.00 = Rp 3,389.79
Rp 88,910.00 = Rp 3,378.58
Rp 103,330.00 = Rp 3,926.54
Rp 103,330.00 = Rp 206.66
Jumlah (2) = Rp 10,901.57
Jumlah (1) + (2) = Rp 11,940.93
Dibulatkan = Rp 11,900.00

Rp 3,439.25 = Rp 495.25
Rp - = Rp -
Jumlah (1) = Rp 495.25

Rp 59,470.00 = Rp 2,973.50
Rp 88,910.00 = Rp 1,778.20
Rp 103,330.00 = Rp 206.66
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 5,475.01
Jumlah (1) + (2) = Rp 5,970.26
Dibulatkan = Rp 6,000.00

Rp 3,439.25 = Rp 1,513.27
Rp - = Rp -
Jumlah (1) = Rp 1,513.27

Rp 59,470.00 = Rp 26,761.50
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 2,583.25
Jumlah (2) = Rp 49,193.35
Jumlah (1) + (2) = Rp 50,706.62
Dibulatkan = Rp 50,700.00

Rp 1,502.00 = Rp 6,488.64
Rp 144,180.00 = Rp 2,306.88
Jumlah (1) = Rp 8,795.52

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 1,549.95
Jumlah (2) = Rp 26,341.75
Jumlah (1) + (2) = Rp 35,137.27
Dibulatkan = Rp 35,100.00

Rp 1,502.00 = Rp 6,488.64
Rp 144,180.00 = Rp 2,306.88
Jumlah (1) = Rp 8,795.52

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 826.64
Jumlah (2) = Rp 16,694.15
Jumlah (1) + (2) = Rp 25,489.67
Dibulatkan = Rp 25,500.00

Rp 1,502.00 = Rp 751.00
Rp - = Rp -
Rp 144,180.00 = Rp 865.08
Jumlah (1) = Rp 1,616.08

Rp 59,470.00 = Rp 17,841.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 1,549.95
Jumlah (2) = Rp 39,239.55
Jumlah (1) + (2) = Rp 40,855.63
Dibulatkan = Rp 40,900.00

DAN PERUMAHAN SNI 2002


Rp 7,809,750.00 = Rp 8,590,725.00
Jumlah (1) = Rp 8,590,725.00

Rp 59,470.00 = Rp 356,820.00
Rp 88,910.00 = Rp 1,778,200.00
Rp 103,330.00 = Rp 206,660.00
Rp 103,330.00 = Rp 30,999.00
Jumlah (2) = Rp 2,372,679.00
Jumlah (1) + (2) = Rp 10,963,404.00
Dibulatkan = Rp 10,963,400.00

Rp 6,367,950.00 = Rp 7,641,540.00
Jumlah (1) = Rp 7,641,540.00

Rp 59,470.00 = Rp 356,820.00
Rp 88,910.00 = Rp 1,600,380.00
Rp 103,330.00 = Rp 206,660.00
Rp 103,330.00 = Rp 30,999.00
Jumlah (2) = Rp 2,194,859.00
Jumlah (1) + (2) = Rp 9,836,399.00
Dibulatkan = Rp 9,836,400.00

Rp 6,367,950.00 = Rp 7,641,540.00
Jumlah (1) = Rp 7,641,540.00

Rp 59,470.00 = Rp 356,820.00
Rp 88,910.00 = Rp 1,600,380.00
Rp 103,330.00 = Rp 206,660.00
Rp 103,330.00 = Rp 30,999.00
Jumlah (2) = Rp 2,194,859.00
Jumlah (1) + (2) = Rp 9,836,399.00
Dibulatkan = Rp 9,836,400.00
Rp 11,414,250.00 = Rp 13,697,100.00
Jumlah (1) = Rp 13,697,100.00

Rp 59,470.00 = Rp 1,070,460.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 30,999.00
Rp 103,330.00 = Rp -
Jumlah (2) = Rp 1,279,279.00
Jumlah (1) + (2) = Rp 14,976,379.00
Dibulatkan = Rp 14,976,400.00

Rp 6,367,950.00 = Rp 229,246.20
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 230,477.70

Rp 59,470.00 = Rp 20,814.50
Rp 88,910.00 = Rp 93,355.50
Rp 103,330.00 = Rp 10,849.65
Rp 103,330.00 = Rp 1,859.94
Jumlah (2) = Rp 126,879.59
Jumlah (1) + (2) = Rp 357,357.29
Dibulatkan = Rp 357,400.00

Rp 6,367,950.00 = Rp 229,246.20
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 230,477.70

Rp 59,470.00 = Rp 20,814.50
Rp 88,910.00 = Rp 93,355.50
Rp 103,330.00 = Rp 10,849.65
Rp 103,330.00 = Rp 1,859.94
Jumlah (2) = Rp 126,879.59
Jumlah (1) + (2) = Rp 357,357.29
Dibulatkan = Rp 357,400.00
Rp 12,615,750.00 = Rp 504,630.00
Jumlah (1) = Rp 504,630.00

Rp 59,470.00 = Rp 59,470.00
Rp 88,910.00 = Rp 222,275.00
Rp 103,330.00 = Rp 25,832.50
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 312,744.00
Jumlah (1) + (2) = Rp 817,374.00
Dibulatkan = Rp 817,400.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 59,470.00
Rp 88,910.00 = Rp 222,275.00
Rp 103,330.00 = Rp 25,832.50
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 312,744.00
Jumlah (1) + (2) = Rp 312,744.00
Dibulatkan = Rp 312,700.00

Rp 12,615,750.00 = Rp 441,551.25
Jumlah (1) = Rp 441,551.25

Rp 59,470.00 = Rp 47,576.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 4,133.20
Jumlah (2) = Rp 250,195.20
Jumlah (1) + (2) = Rp 691,746.45
Dibulatkan = Rp 691,700.00

Rp 6,367,950.00 = Rp 222,878.25
Jumlah (1) = Rp 222,878.25

Rp 59,470.00 = Rp 47,576.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 4,133.20
Jumlah (2) = Rp 250,195.20
Jumlah (1) + (2) = Rp 473,073.45
Dibulatkan = Rp 473,100.00

Rp 6,367,950.00 = Rp 222,878.25
Jumlah (1) = Rp 222,878.25

Rp 59,470.00 = Rp 47,576.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 4,133.20
Jumlah (2) = Rp 250,195.20
Jumlah (1) + (2) = Rp 473,073.45
Dibulatkan = Rp 473,100.00

Rp 12,615,750.00 = Rp 807,408.00
Jumlah (1) = Rp 807,408.00

Rp 59,470.00 = Rp 59,470.00
Rp 88,910.00 = Rp 266,730.00
Rp 103,330.00 = Rp 30,999.00
Rp 103,330.00 = Rp 30,999.00
Jumlah (2) = Rp 388,198.00
Jumlah (1) + (2) = Rp 1,195,606.00
Dibulatkan = Rp 1,195,600.00

Rp 6,367,950.00 = Rp 407,548.80
Jumlah (1) = Rp 407,548.80

Rp 59,470.00 = Rp 59,470.00
Rp 88,910.00 = Rp 266,730.00
Rp 103,330.00 = Rp 30,999.00
Rp 103,330.00 = Rp 51,665.00
Jumlah (2) = Rp 408,864.00
Jumlah (1) + (2) = Rp 816,412.80
Dibulatkan = Rp 816,400.00

Rp 12,615,750.00 = Rp 247,268.70
Rp 24,630.00 = Rp 738.90
Rp - = Rp -
Rp 127,960.00 = Rp 127,960.00
Jumlah (1) = Rp 375,967.60

Rp 59,470.00 = Rp 35,682.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 3,099.90
Jumlah (2) = Rp 237,267.90
Jumlah (1) + (2) = Rp 613,235.50
Dibulatkan = Rp 613,200.00

Rp 6,367,950.00 = Rp 124,811.82
Rp 24,630.00 = Rp 738.90
Rp - = Rp -
Rp 127,960.00 = Rp 127,960.00
Jumlah (1) = Rp 253,510.72
Rp 59,470.00 = Rp 35,682.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 3,099.90
Jumlah (2) = Rp 237,267.90
Jumlah (1) + (2) = Rp 490,778.62
Dibulatkan = Rp 490,800.00

Rp 12,615,750.00 = Rp 756,945.00
Rp 24,630.00 = Rp 3,694.50
Jumlah (1) = Rp 760,639.50

Rp 59,470.00 = Rp 29,735.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 2,583.25
Jumlah (2) = Rp 230,804.25
Jumlah (1) + (2) = Rp 991,443.75
Dibulatkan = Rp 991,400.00

Rp 6,367,950.00 = Rp 382,077.00
Rp 24,630.00 = Rp 3,694.50
Jumlah (1) = Rp 385,771.50

Rp 59,470.00 = Rp 29,735.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 2,583.25
Jumlah (2) = Rp 230,804.25
Jumlah (1) + (2) = Rp 616,575.75
Dibulatkan = Rp 616,600.00
Rp 6,367,950.00 = Rp 124,811.82
Rp 24,630.00 = Rp 738.90
Rp - = Rp -
Rp 127,960.00 = Rp 127,960.00
Jumlah (1) = Rp 253,510.72

Rp 59,470.00 = Rp 35,682.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 3,099.90
Jumlah (2) = Rp 237,267.90
Jumlah (1) + (2) = Rp 490,778.62
Dibulatkan = Rp 490,800.00

Rp 12,615,750.00 = Rp 247,268.70
Rp 24,630.00 = Rp 738.90
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp 248,007.60

Rp 59,470.00 = Rp 35,682.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 3,099.90
Jumlah (2) = Rp 237,267.90
Jumlah (1) + (2) = Rp 485,275.50
Dibulatkan = Rp 485,300.00

Rp 6,367,950.00 = Rp 124,811.82
Rp 24,630.00 = Rp 7,389.00
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp 132,200.82
Rp 59,470.00 = Rp 35,682.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 3,099.90
Jumlah (2) = Rp 237,267.90
Jumlah (1) + (2) = Rp 369,468.72
Dibulatkan = Rp 369,500.00

Rp 12,615,750.00 = Rp 247,268.70
Rp 24,630.00 = Rp 7,389.00
Rp - = Rp -
Rp 127,960.00 = Rp 127,960.00
Rp - = Rp -
Jumlah (1) = Rp 382,617.70

Rp 59,470.00 = Rp 35,682.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 3,099.90
Jumlah (2) = Rp 237,267.90
Jumlah (1) + (2) = Rp 619,885.60
Dibulatkan = Rp 619,900.00

Rp - = Rp -
Rp 24,630.00 = Rp 7,389.00
Rp - = Rp -
Rp 127,960.00 = Rp 127,960.00
Rp - = Rp -
Jumlah (1) = Rp 135,349.00

Rp 59,470.00 = Rp 35,682.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 3,099.90
Jumlah (2) = Rp 237,267.90
Jumlah (1) + (2) = Rp 372,616.90
Dibulatkan = Rp 372,600.00

Rp 6,367,950.00 = Rp 124,811.82
Rp 24,630.00 = Rp 7,389.00
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp 132,200.82

Rp 59,470.00 = Rp 35,682.00
Rp 88,910.00 = Rp 177,820.00
Rp 103,330.00 = Rp 20,666.00
Rp 103,330.00 = Rp 3,099.90
Jumlah (2) = Rp 237,267.90
Jumlah (1) + (2) = Rp 369,468.72
Dibulatkan = Rp 369,500.00

er (divernis)

Rp 6,367,950.00 = Rp 124,811.82
Rp 24,630.00 = Rp 7,389.00
Rp - = Rp -
Rp - = Rp -
Rp 37,850.00 = Rp 18,925.00
Rp - = Rp -
Jumlah (1) = Rp 151,125.82

Rp 59,470.00 = Rp 47,576.00
Rp 88,910.00 = Rp 222,275.00
Rp 103,330.00 = Rp 25,832.50
Rp 103,330.00 = Rp 4,133.20
Jumlah (2) = Rp 299,816.70
Jumlah (1) + (2) = Rp 450,942.52
Dibulatkan = Rp 450,900.00
Rp 12,615,750.00 = Rp 247,268.70
Rp 24,630.00 = Rp 7,389.00
Rp - = Rp -
Rp 127,960.00 = Rp 127,960.00
Rp - = Rp -
Jumlah (1) = Rp 382,617.70

Rp 59,470.00 = Rp 59,470.00
Rp 88,910.00 = Rp 231,166.00
Rp 103,330.00 = Rp 26,865.80
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 322,668.30
Jumlah (1) + (2) = Rp 705,286.00
Dibulatkan = Rp 705,300.00

Rp 6,367,950.00 = Rp 124,811.82
Rp 24,630.00 = Rp 7,389.00
Rp - = Rp -
Rp 127,960.00 = Rp 127,960.00
Rp - = Rp -
Jumlah (1) = Rp 260,160.82

Rp 59,470.00 = Rp 59,470.00
Rp 88,910.00 = Rp 231,166.00
Rp 103,330.00 = Rp 26,865.80
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 322,668.30
Jumlah (1) + (2) = Rp 582,829.12
Dibulatkan = Rp 582,800.00

Rp 11,414,250.00 = Rp 12,555,675.00
Rp 38,445.00 = Rp 576,675.00
Rp 24,630.00 = Rp 19,704.00
Jumlah (1) = Rp 13,152,054.00

Rp 59,470.00 = Rp 237,880.00
Rp 88,910.00 = Rp 1,066,920.00
Rp 103,330.00 = Rp 123,996.00
Rp 103,330.00 = Rp 20,666.00
Jumlah (2) = Rp 1,449,462.00
Jumlah (1) + (2) = Rp 14,601,516.00
Dibulatkan = Rp 14,601,500.00

Rp - = Rp -
Rp 38,445.00 = Rp 576,675.00
Rp 24,630.00 = Rp 19,704.00
Jumlah (1) = Rp 596,379.00

Rp 59,470.00 = Rp 237,880.00
Rp 88,910.00 = Rp 1,066,920.00
Rp 103,330.00 = Rp 123,996.00
Rp 103,330.00 = Rp 20,666.00
Jumlah (2) = Rp 1,449,462.00
Jumlah (1) + (2) = Rp 2,045,841.00
Dibulatkan = Rp 2,045,800.00

Rp 6,367,950.00 = Rp 7,004,745.00
Rp 38,445.00 = Rp 576,675.00
Rp 24,630.00 = Rp 19,704.00
Jumlah (1) = Rp 7,601,124.00

Rp 59,470.00 = Rp 237,880.00
Rp 88,910.00 = Rp 1,066,920.00
Rp 103,330.00 = Rp 123,996.00
Rp 103,330.00 = Rp 20,666.00
Jumlah (2) = Rp 1,449,462.00
Jumlah (1) + (2) = Rp 9,050,586.00
Dibulatkan = Rp 9,050,600.00

Rp 6,367,950.00 = Rp 7,004,745.00
Rp 38,445.00 = Rp 576,675.00
Rp 24,630.00 = Rp 19,704.00
Jumlah (1) = Rp 7,601,124.00

Rp 59,470.00 = Rp 237,880.00
Rp 88,910.00 = Rp 1,066,920.00
Rp 103,330.00 = Rp 123,996.00
Rp 103,330.00 = Rp 20,666.00
Jumlah (2) = Rp 1,449,462.00
Jumlah (1) + (2) = Rp 9,050,586.00
Dibulatkan = Rp 9,050,600.00

Rp 6,367,950.00 = Rp 76,415.40
Rp 24,630.00 = Rp 3,694.50
Jumlah (1) = Rp 80,109.90

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 16,387.95
Jumlah (1) + (2) = Rp 96,497.85
Dibulatkan = Rp 96,500.00

Rp 6,367,950.00 = Rp 76,415.40
Rp 24,630.00 = Rp 3,694.50
Jumlah (1) = Rp 80,109.90

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 16,387.95
Jumlah (1) + (2) = Rp 96,497.85
Dibulatkan = Rp 96,500.00

Rp 11,414,250.00 = Rp 159,799.50
Rp 24,630.00 = Rp 3,694.50
Jumlah (1) = Rp 163,494.00

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 16,387.95
Jumlah (1) + (2) = Rp 179,881.95
Dibulatkan = Rp 179,900.00

Rp 6,367,950.00 = Rp 89,151.30
Rp 24,630.00 = Rp 3,694.50
Jumlah (1) = Rp 92,845.80

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 16,387.95
Jumlah (1) + (2) = Rp 109,233.75
Dibulatkan = Rp 109,200.00

Rp 6,367,950.00 = Rp 89,151.30
Rp 24,630.00 = Rp 3,694.50
Jumlah (1) = Rp 92,845.80

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 16,387.95
Jumlah (1) + (2) = Rp 109,233.75
Dibulatkan = Rp 109,200.00

Rp 6,367,950.00 = Rp 1,050,711.75
Rp 24,630.00 = Rp 4,926.00
Jumlah (1) = Rp 1,055,637.75

Rp 59,470.00 = Rp 7,136.40
Rp 88,910.00 = Rp 10,669.20
Rp 103,330.00 = Rp 1,239.96
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 19,665.54
Jumlah (1) + (2) = Rp 1,075,303.29
Dibulatkan = Rp 1,075,300.00

Rp 6,367,950.00 = Rp 1,050,711.75
Rp 24,630.00 = Rp 4,926.00
Jumlah (1) = Rp 1,055,637.75

Rp 59,470.00 = Rp 7,136.40
Rp 88,910.00 = Rp 10,669.20
Rp 103,330.00 = Rp 1,239.96
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 19,665.54
Jumlah (1) + (2) = Rp 1,075,303.29
Dibulatkan = Rp 1,075,300.00
Rp 11,414,250.00 = Rp 136,971.00
Rp 24,630.00 = Rp 2,463.00
Jumlah (1) = Rp 139,434.00

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 7,749.75
Jumlah (2) = Rp 41,481.00
Jumlah (1) + (2) = Rp 180,915.00
Dibulatkan = Rp 180,900.00

Rp - = Rp -
Rp 24,630.00 = Rp 2,463.00
Jumlah (1) = Rp 2,463.00

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 7,749.75
Jumlah (2) = Rp 41,481.00
Jumlah (1) + (2) = Rp 43,944.00
Dibulatkan = Rp 43,900.00

Rp 6,367,950.00 = Rp 76,415.40
Rp 24,630.00 = Rp 2,463.00
Jumlah (1) = Rp 78,878.40

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 7,749.75
Jumlah (2) = Rp 41,481.00
Jumlah (1) + (2) = Rp 120,359.40
Dibulatkan = Rp 120,400.00

Rp 11,414,250.00 = Rp 262,527.75
Rp 24,630.00 = Rp 3,694.50
Jumlah (1) = Rp 266,222.25

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 26,673.00
Rp 103,330.00 = Rp 3,099.90
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 42,700.20
Jumlah (1) + (2) = Rp 308,922.45
Dibulatkan = Rp 308,900.00

Rp 6,367,950.00 = Rp 146,462.85
Rp 24,630.00 = Rp 3,694.50
Jumlah (1) = Rp 150,157.35

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 26,673.00
Rp 103,330.00 = Rp 3,099.90
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 42,700.20
Jumlah (1) + (2) = Rp 192,857.55
Dibulatkan = Rp 192,900.00

Rp 6,367,950.00 = Rp 146,462.85
Rp 24,630.00 = Rp 3,694.50
Jumlah (1) = Rp 150,157.35

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 26,673.00
Rp 103,330.00 = Rp 3,099.90
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 42,700.20
Jumlah (1) + (2) = Rp 192,857.55
Dibulatkan = Rp 192,900.00

Rp 11,414,250.00 = Rp 308,184.75
Rp 24,630.00 = Rp 4,926.00
Jumlah (1) = Rp 313,110.75

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 31,118.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 50,894.18
Jumlah (1) + (2) = Rp 364,004.93
Dibulatkan = Rp 364,000.00

Rp - = Rp -
Rp 24,630.00 = Rp 4,926.00
Jumlah (1) = Rp 4,926.00

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 31,118.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 50,894.18
Jumlah (1) + (2) = Rp 55,820.18
Dibulatkan = Rp 55,800.00
Rp 6,367,950.00 = Rp 171,934.65
Rp 24,630.00 = Rp 4,926.00
Jumlah (1) = Rp 176,860.65

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 31,118.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 1,291.63
Jumlah (2) = Rp 50,894.18
Jumlah (1) + (2) = Rp 227,754.83
Dibulatkan = Rp 227,800.00

Rp 12,615,750.00 = Rp 90,833.40
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 92,064.90

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 26,312.25
Jumlah (1) + (2) = Rp 118,377.15
Dibulatkan = Rp 118,400.00

Rp 6,367,950.00 = Rp 45,849.24
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 47,080.74

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 26,312.25
Jumlah (1) + (2) = Rp 73,392.99
Dibulatkan = Rp 73,400.00

Rp 12,615,750.00 = Rp 138,773.25
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 140,004.75

Rp 59,470.00 = Rp 6,541.70
Rp 88,910.00 = Rp 19,560.20
Rp 103,330.00 = Rp 2,273.26
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 28,891.81
Jumlah (1) + (2) = Rp 168,896.56
Dibulatkan = Rp 168,900.00

Rp 6,367,950.00 = Rp 70,047.45
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 71,278.95

Rp 59,470.00 = Rp 6,541.70
Rp 88,910.00 = Rp 19,560.20
Rp 103,330.00 = Rp 2,273.26
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 28,891.81
Jumlah (1) + (2) = Rp 100,170.76
Dibulatkan = Rp 100,200.00

Rp 6,367,950.00 = Rp 92,335.28
Rp 24,630.00 = Rp 1,477.80
Jumlah (1) = Rp 93,813.08
Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 7,749.75
Jumlah (2) = Rp 41,481.00
Jumlah (1) + (2) = Rp 135,294.08
Dibulatkan = Rp 135,300.00

Rp 6,367,950.00 = Rp 54,764.37
Rp 24,630.00 = Rp 1,477.80
Jumlah (1) = Rp 56,242.17

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 21,037.80
Jumlah (1) + (2) = Rp 77,279.97
Dibulatkan = Rp 77,300.00

Rp 6,367,950.00 = Rp 56,037.96
Rp 24,630.00 = Rp 1,477.80
Jumlah (1) = Rp 57,515.76

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 5,166.50
Jumlah (2) = Rp 21,037.80
Jumlah (1) + (2) = Rp 78,553.56
Dibulatkan = Rp 78,600.00
Rp 6,367,950.00 = Rp 124,175.03
Rp 6,367,950.00 = Rp 44,575.65
Rp 24,630.00 = Rp 2,463.00
Jumlah (1) = Rp 171,213.68

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 40,009.50
Rp 103,330.00 = Rp 4,649.85
Rp 103,330.00 = Rp 7,749.75
Jumlah (2) = Rp 61,329.60
Jumlah (1) + (2) = Rp 232,543.28
Dibulatkan = Rp 232,500.00

Rp 6,367,950.00 = Rp 124,175.03
Rp 6,367,950.00 = Rp 44,575.65
Rp 24,630.00 = Rp 2,463.00
Jumlah (1) = Rp 171,213.68

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 40,009.50
Rp 103,330.00 = Rp 4,649.85
Rp 103,330.00 = Rp 7,749.75
Jumlah (2) = Rp 61,329.60
Jumlah (1) + (2) = Rp 232,543.28
Dibulatkan = Rp 232,500.00

yu kamper

Rp 6,367,950.00 = Rp 124,175.03
Rp 6,367,950.00 = Rp 44,575.65
Rp 24,630.00 = Rp 2,463.00
Jumlah (1) = Rp 171,213.68

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 40,009.50
Rp 103,330.00 = Rp 4,649.85
Rp 103,330.00 = Rp 7,749.75
Jumlah (2) = Rp 61,329.60
Jumlah (1) + (2) = Rp 232,543.28
Dibulatkan = Rp 232,500.00

u kamper

Rp 6,367,950.00 = Rp 124,175.03
Rp 6,367,950.00 = Rp 44,575.65
Rp 24,630.00 = Rp 2,463.00
Rp - = Rp -
Rp 127,960.00 = Rp 127,960.00
Jumlah (1) = Rp 299,173.68

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 53,346.00
Rp 103,330.00 = Rp 6,199.80
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 72,473.10
Jumlah (1) + (2) = Rp 371,646.78
Dibulatkan = Rp 371,600.00

Rp 11,414,250.00 = Rp 79,899.75
Rp 24,630.00 = Rp 2,463.00
Rp 28,000.00 = Rp 4,200.00
Jumlah (1) = Rp 86,562.75

Rp 59,470.00 = Rp 35,682.00
Rp 88,910.00 = Rp 960,228.00
Rp 103,330.00 = Rp 18,599.40
Rp 103,330.00 = Rp 3,099.90
Jumlah (2) = Rp 1,017,609.30
Jumlah (1) + (2) = Rp 1,104,172.05
Dibulatkan = Rp 1,104,200.00
Rp 127,960.00 = Rp 51,184.00
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 52,415.50

Rp 59,470.00 = Rp 1,486.75
Rp 88,910.00 = Rp 6,668.25
Rp 103,330.00 = Rp 774.98
Rp 103,330.00 = Rp 134.33
Jumlah (2) = Rp 9,064.30
Jumlah (1) + (2) = Rp 61,479.80
Dibulatkan = Rp 61,500.00

Rp 6,367,950.00 = Rp 6,686,347.50
Jumlah (1) = Rp 6,686,347.50

Rp 59,470.00 = Rp 1,248.87
Rp 88,910.00 = Rp 1,867.11
Rp 103,330.00 = Rp 206.66
Rp 103,330.00 = Rp 103.33
Jumlah (2) = Rp 3,425.97
Jumlah (1) + (2) = Rp 6,689,773.47
Dibulatkan = Rp 6,689,800.00

N GEDUNG DAN PERUMAHAN SNI 2002


BETON

Rp 1,502.00 = Rp 327,436.00
Rp 144,180.00 = Rp 74,973.60
Rp 177,220.00 = Rp 154,181.40
Jumlah (1) = Rp 556,591.00
Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 687,793.65
Dibulatkan = Rp 687,800.00

Rp 1,502.00 = Rp 295,894.00
Rp 144,180.00 = Rp 67,764.60
Rp 177,220.00 = Rp 166,586.80
Jumlah (1) = Rp 530,245.40

Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 661,448.05
Dibulatkan = Rp 661,400.00

Rp 1,502.00 = Rp 259,846.00
Rp 144,180.00 = Rp 82,182.60
Rp 177,220.00 = Rp 154,181.40
Jumlah (1) = Rp 496,210.00

Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 627,412.65
Dibulatkan = Rp 627,400.00
Rp 1,502.00 = Rp 15,020.00
Rp 144,180.00 = Rp 37,486.80
Rp 177,220.00 = Rp 7,797.68
Jumlah (1) = Rp 60,304.48

Rp 59,470.00 = Rp 68,390.50
Rp 88,910.00 = Rp 1,778.20
Rp 103,330.00 = Rp 206.66
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 70,995.34
Jumlah (1) + (2) = Rp 131,299.82
Dibulatkan = Rp 131,300.00

Rp 1,502.00 = Rp 348,464.00
Rp 144,180.00 = Rp 74,973.60
Rp 177,220.00 = Rp 138,231.60
Jumlah (1) = Rp 561,669.20

Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 692,871.85
Dibulatkan = Rp 692,900.00

Rp 1,502.00 = Rp 420,560.00
Rp 144,180.00 = Rp 64,881.00
Rp 177,220.00 = Rp 159,498.00
Jumlah (1) = Rp 644,939.00
Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 776,141.65
Dibulatkan = Rp 776,100.00

Rp 1,502.00 = Rp 528,704.00
Rp 144,180.00 = Rp 80,740.80
Rp 177,220.00 = Rp 124,054.00
Jumlah (1) = Rp 733,498.80

Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 864,701.45
Dibulatkan = Rp 864,700.00

Rp 1,502.00 = Rp 536,214.00
Rp 144,180.00 = Rp 60,555.60
Rp 177,220.00 = Rp 95,698.80
Jumlah (1) = Rp 692,468.40

Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 823,671.05
Dibulatkan = Rp 823,700.00
Rp 1,502.00 = Rp 579,772.00
Rp 144,180.00 = Rp 67,764.60
Rp 177,220.00 = Rp 138,231.60
Jumlah (1) = Rp 138,231.60

Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 269,434.25
Dibulatkan = Rp 269,400.00

Rp 1,502.00 = Rp 719,458.00
Rp 144,180.00 = Rp 53,346.60
Rp 177,220.00 = Rp 131,142.80
Jumlah (1) = Rp 131,142.80

Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 262,345.45
Dibulatkan = Rp 262,300.00

Rp 1,502.00 = Rp 660,880.00
Rp 144,180.00 = Rp 72,090.00
Rp 177,220.00 = Rp 88,610.00
Rp - = Rp -
Jumlah (1) = Rp 821,580.00
Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 952,782.65
Dibulatkan = Rp 952,800.00

Rp 1,502.00 = Rp 504,672.00
Rp 144,180.00 = Rp 77,857.20
Rp 177,220.00 = Rp 95,698.80
Rp - = Rp -
Jumlah (1) = Rp 678,228.00

Rp 59,470.00 = Rp 98,125.50
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 8,266.40
Jumlah (2) = Rp 131,202.65
Jumlah (1) + (2) = Rp 809,430.65
Dibulatkan = Rp 809,400.00

Rp 1,502.00 = Rp 504,672.00
Rp 144,180.00 = Rp 77,857.20
Rp 177,220.00 = Rp 143,548.20
Jumlah (1) = Rp 726,077.40

Rp 59,470.00 = Rp 118,940.00
Rp 88,910.00 = Rp 31,118.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 103,330.00
Jumlah (2) = Rp 257,005.05
Jumlah (1) + (2) = Rp 983,082.45
Dibulatkan = Rp 983,100.00
Rp 1,502.00 = Rp 437,082.00
Rp 144,180.00 = Rp 67,764.60
Rp 177,220.00 = Rp 164,814.60
Jumlah (1) = Rp 669,661.20

Rp 59,470.00 = Rp 118,940.00
Rp 88,910.00 = Rp 31,118.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 103,330.00
Jumlah (2) = Rp 257,005.05
Jumlah (1) + (2) = Rp 926,666.25
Dibulatkan = Rp 926,700.00

Rp 1,502.00 = Rp 551,234.00
Rp 144,180.00 = Rp 63,439.20
Rp 177,220.00 = Rp 155,953.60
Jumlah (1) = Rp 155,953.60

Rp 59,470.00 = Rp 118,940.00
Rp 88,910.00 = Rp 31,118.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 103,330.00
Jumlah (2) = Rp 257,005.05
Jumlah (1) + (2) = Rp 412,958.65
Dibulatkan = Rp 413,000.00

Rp 1,502.00 = Rp 600,800.00
Rp 144,180.00 = Rp 69,206.40
Rp 177,220.00 = Rp 141,776.00
Jumlah (1) = Rp 141,776.00
Rp 59,470.00 = Rp 118,940.00
Rp 88,910.00 = Rp 31,118.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 103,330.00
Jumlah (2) = Rp 257,005.05
Jumlah (1) + (2) = Rp 398,781.05
Dibulatkan = Rp 398,800.00

Rp 1,502.00 = Rp 923,730.00
Rp 144,180.00 = Rp 74,973.60
Rp 177,220.00 = Rp 92,154.40
Jumlah (1) = Rp 92,154.40

Rp 59,470.00 = Rp 118,940.00
Rp 88,910.00 = Rp 31,118.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 103,330.00
Jumlah (2) = Rp 257,005.05
Jumlah (1) + (2) = Rp 349,159.45
Dibulatkan = Rp 349,200.00

Rp 1,502.00 = Rp 600,800.00
Rp 144,180.00 = Rp 69,206.40
Rp 177,220.00 = Rp 141,776.00
Rp - = Rp -
Jumlah (1) = Rp 811,782.40

Rp 59,470.00 = Rp 118,940.00
Rp 88,910.00 = Rp 31,118.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 103,330.00
Jumlah (2) = Rp 257,005.05
Jumlah (1) + (2) = Rp 1,068,787.45
Dibulatkan = Rp 1,068,800.00
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 2,973.50
Rp 88,910.00 = Rp 2,667.30
Rp 103,330.00 = Rp 309.99
Rp 103,330.00 = Rp 206.66
Jumlah (2) = Rp 6,157.45
Jumlah (1) + (2) = Rp 6,157.45
Dibulatkan = Rp 6,200.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 2,973.50
Rp 88,910.00 = Rp 2,667.30
Rp 103,330.00 = Rp 309.99
Rp 103,330.00 = Rp 206.66
Jumlah (2) = Rp 6,157.45
Jumlah (1) + (2) = Rp 6,157.45
Dibulatkan = Rp 6,200.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 32,708.50
Rp 88,910.00 = Rp 3,111.85
Rp 103,330.00 = Rp 309.99
Jumlah (2) = Rp 36,130.34
Jumlah (1) + (2) = Rp 36,130.34
Dibulatkan = Rp 36,100.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 32,708.50
Rp 88,910.00 = Rp 3,111.85
Rp 103,330.00 = Rp 309.99
Jumlah (2) = Rp 36,130.34
Jumlah (1) + (2) = Rp 36,130.34
Dibulatkan = Rp 36,100.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 32,708.50
Rp 88,910.00 = Rp 3,111.85
Rp 103,330.00 = Rp 309.99
Jumlah (2) = Rp 36,130.34
Jumlah (1) + (2) = Rp 36,130.34
Dibulatkan = Rp 36,100.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 32,708.50
Rp 88,910.00 = Rp 3,111.85
Rp 103,330.00 = Rp 309.99
Jumlah (2) = Rp 36,130.34
Jumlah (1) + (2) = Rp 36,130.34
Dibulatkan = Rp 36,100.00
Rp 17,420.00 = Rp 18,291.00
Rp 24,030,000.00 = Rp 360,450.00
Jumlah (1) = Rp 378,741.00

Rp 59,470.00 = Rp 416.29
Rp 88,910.00 = Rp 622.37
Rp 103,330.00 = Rp 72.33
Rp 103,330.00 = Rp 31.00
Jumlah (2) = Rp 1,141.99
Jumlah (1) + (2) = Rp 379,882.99
Dibulatkan = Rp 379,900.00

Rp - = Rp -
Rp 24,030.00 = Rp 240.30
Jumlah (1) = Rp 240.30

Rp 59,470.00 = Rp 297.35
Rp 88,910.00 = Rp 444.55
Rp 103,330.00 = Rp 51.67
Rp 103,330.00 = Rp 31.00
Jumlah (2) = Rp 824.56
Jumlah (1) + (2) = Rp 1,064.86
Dibulatkan = Rp 1,100.00

Rp - = Rp -
Rp 24,030.00 = Rp 19,344.15
Jumlah (1) = Rp 19,344.15

Rp 59,470.00 = Rp 1,486.75
Rp 88,910.00 = Rp 2,222.75
Rp 103,330.00 = Rp 258.33
Rp 103,330.00 = Rp 155.00
Jumlah (2) = Rp 4,122.82
Jumlah (1) + (2) = Rp 23,466.97
Dibulatkan = Rp 23,500.00

Rp 6,367,950.00 = Rp 254,718.00
Rp 24,630.00 = Rp 7,389.00
Rp - = Rp -
Jumlah (1) = Rp 262,107.00

Rp 59,470.00 = Rp 17,841.00
Rp 88,910.00 = Rp 23,116.60
Rp 103,330.00 = Rp 2,686.58
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 44,160.83
Jumlah (1) + (2) = Rp 306,267.83
Dibulatkan = Rp 306,300.00

Rp 6,367,950.00 = Rp 286,557.75
Rp 24,630.00 = Rp 7,389.00
Rp - = Rp -
Jumlah (1) = Rp 293,946.75

Rp 59,470.00 = Rp 17,841.00
Rp 88,910.00 = Rp 23,116.60
Rp 103,330.00 = Rp 2,686.58
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 44,160.83
Jumlah (1) + (2) = Rp 338,107.58
Dibulatkan = Rp 338,100.00
Rp 6,367,950.00 = Rp 254,718.00
Rp 24,630.00 = Rp 9,852.00
Rp - = Rp -
Rp 6,367,950.00 = Rp 95,519.25
Rp 207,860.00 = Rp 72,751.00
Rp 102,130.00 = Rp 20,426.00
Jumlah (1) = Rp 453,266.25

Rp 59,470.00 = Rp 17,841.00
Rp 88,910.00 = Rp 26,673.00
Rp 103,330.00 = Rp 3,409.89
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 48,543.87
Jumlah (1) + (2) = Rp 501,810.12
Dibulatkan = Rp 501,800.00

Rp 6,367,950.00 = Rp 254,718.00
Rp 24,630.00 = Rp 9,852.00
Rp - = Rp -
Rp 6,367,950.00 = Rp 1,273,590.00
Rp 207,860.00 = Rp 72,751.00
Rp 102,130.00 = Rp 20,426.00
Jumlah (1) = Rp 1,631,337.00

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 29,340.30
Rp 103,330.00 = Rp 3,409.89
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 52,400.57
Jumlah (1) + (2) = Rp 1,683,737.57
Dibulatkan = Rp 1,683,700.00

Rp 6,367,950.00 = Rp 254,718.00
Rp 24,630.00 = Rp 9,852.00
Rp - = Rp -
Rp 6,367,950.00 = Rp 1,273,590.00
Rp 207,860.00 = Rp 72,751.00
Rp 102,130.00 = Rp 20,426.00
Jumlah (1) = Rp 1,631,337.00

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 29,340.30
Rp 103,330.00 = Rp 3,409.89
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 52,400.57
Jumlah (1) + (2) = Rp 1,683,737.57
Dibulatkan = Rp 1,683,700.00

Rp 6,367,950.00 = Rp 191,038.50
Rp 24,630.00 = Rp 9,852.00
Rp - = Rp -
Rp 6,367,950.00 = Rp 127,359.00
Rp 207,860.00 = Rp 72,751.00
Rp 102,130.00 = Rp 306,390.00
Rp - = Rp -
Jumlah (1) = Rp 707,390.50

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 29,340.30
Rp 103,330.00 = Rp 3,409.89
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 52,400.57
Jumlah (1) + (2) = Rp 759,791.07
Dibulatkan = Rp 759,800.00

Rp 6,367,950.00 = Rp 191,038.50
Rp 24,630.00 = Rp 9,852.00
Rp - = Rp -
Rp 6,367,950.00 = Rp 95,519.25
Rp 207,860.00 = Rp 72,751.00
Rp 102,130.00 = Rp 204,260.00
Jumlah (1) = Rp 573,420.75

Rp 59,470.00 = Rp 19,030.40
Rp 88,910.00 = Rp 29,340.30
Rp 103,330.00 = Rp 3,409.89
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 52,400.57
Jumlah (1) + (2) = Rp 625,821.32
Dibulatkan = Rp 625,800.00

Rp 1,502.00 = Rp 582,776.00
Rp 144,180.00 = Rp 93,717.00
Rp 177,220.00 = Rp 115,193.00
Jumlah (1) = Rp 791,686.00

Rp 59,470.00 = Rp 356,820.00
Rp 88,910.00 = Rp 88,910.00
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 30,999.00
Jumlah (2) = Rp 487,062.00
Jumlah (1) + (2) = Rp 1,278,748.00
Dibulatkan = Rp 1,278,700.00

Rp 1,502.00 = Rp 600,800.00
Rp 144,180.00 = Rp 57,672.00
Rp 177,220.00 = Rp 145,320.40
Jumlah (1) = Rp 803,792.40

Rp 59,470.00 = Rp 356,820.00
Rp 88,910.00 = Rp 88,910.00
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 30,999.00
Jumlah (2) = Rp 487,062.00
Jumlah (1) + (2) = Rp 1,290,854.40
Dibulatkan = Rp 1,290,900.00

Rp 6,367,950.00 = Rp 168,113.88
Rp 24,630.00 = Rp 14,778.00
Rp 102,130.00 = Rp 51,065.00
Jumlah (1) = Rp 233,956.88

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 4,445.50
Rp 103,330.00 = Rp 516.65
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 14,605.96
Jumlah (1) + (2) = Rp 248,562.84
Dibulatkan = Rp 248,600.00

Rp 6,367,950.00 = Rp 1,273,590.00
Rp 24,630.00 = Rp 36,945.00
Rp - = Rp -
Rp 17,420.00 = Rp 2,613,000.00
Rp 24,030.00 = Rp 54,067.50
Rp 1,502.00 = Rp 485,146.00
Rp 144,180.00 = Rp 74,973.60
Rp 177,220.00 = Rp 138,231.60
Jumlah (1) = Rp 4,675,953.70

Rp 59,470.00 = Rp 231,933.00
Rp 88,910.00 = Rp 31,118.50
Rp 88,910.00 = Rp 92,466.40
Rp 88,910.00 = Rp 982,455.50
Rp 103,330.00 = Rp 25,315.85
Rp 103,330.00 = Rp 17,049.45
Jumlah (2) = Rp 1,380,338.70
Jumlah (1) + (2) = Rp 6,056,292.40
Dibulatkan = Rp 6,056,300.00
Rp 6,367,950.00 = Rp 1,273,590.00
Rp 24,630.00 = Rp 36,945.00
Rp - = Rp -
Rp 17,420.00 = Rp 2,613,000.00
Rp 24,030.00 = Rp 54,067.50
Rp 1,502.00 = Rp 485,146.00
Rp 144,180.00 = Rp 74,973.60
Rp 177,220.00 = Rp 138,231.60
Jumlah (1) = Rp 4,675,953.70

Rp 59,470.00 = Rp 231,933.00
Rp 88,910.00 = Rp 31,118.50
Rp 88,910.00 = Rp 92,466.40
Rp 88,910.00 = Rp 982,455.50
Rp 103,330.00 = Rp 25,315.85
Rp 103,330.00 = Rp 17,049.45
Jumlah (2) = Rp 1,380,338.70
Jumlah (1) + (2) = Rp 6,056,292.40
Dibulatkan = Rp 6,056,300.00

Rp 6,367,950.00 = Rp 2,547,180.00
Rp 24,630.00 = Rp 98,520.00
Rp - = Rp -
Rp 17,420.00 = Rp 5,226,000.00
Rp 24,030.00 = Rp 108,135.00
Rp 1,502.00 = Rp 485,146.00
Rp 144,180.00 = Rp 74,973.60
Rp 177,220.00 = Rp 138,231.60
Rp 6,367,950.00 = Rp 955,192.50
Rp 207,860.00 = Rp 727,510.00
Rp 102,130.00 = Rp 2,042,600.00
Jumlah (1) = Rp 12,403,488.70
Rp 59,470.00 = Rp 434,131.00
Rp 88,910.00 = Rp 31,118.50
Rp 88,910.00 = Rp 293,403.00
Rp 88,910.00 = Rp 186,711.00
Rp 103,330.00 = Rp 58,898.10
Rp 103,330.00 = Rp 25,832.50
Jumlah (2) = Rp 1,030,094.10
Jumlah (1) + (2) = Rp 13,433,582.80
Dibulatkan = Rp 13,433,600.00

Rp 6,367,950.00 = Rp 2,037,744.00
Rp 24,630.00 = Rp 78,816.00
Rp - = Rp -
Rp 17,420.00 = Rp 3,484,000.00
Rp 24,030.00 = Rp 72,090.00
Rp 1,502.00 = Rp 485,146.00
Rp 144,180.00 = Rp 74,973.60
Rp 177,220.00 = Rp 138,231.60
Rp 6,367,950.00 = Rp 891,513.00
Rp 207,860.00 = Rp 582,008.00
Rp 102,130.00 = Rp 1,634,080.00
Jumlah (1) = Rp 9,478,602.20

Rp 59,470.00 = Rp 354,441.20
Rp 88,910.00 = Rp 31,118.50
Rp 88,910.00 = Rp 248,948.00
Rp 88,910.00 = Rp 124,474.00
Rp 103,330.00 = Rp 47,015.15
Rp 103,330.00 = Rp 21,492.64
Jumlah (2) = Rp 827,489.49
Jumlah (1) + (2) = Rp 10,306,091.69
Dibulatkan = Rp 10,306,100.00

Rp 6,367,950.00 = Rp 2,037,744.00
Rp 24,630.00 = Rp 78,816.00
Rp - = Rp -
Rp 17,420.00 = Rp 2,613,000.00
Rp 24,030.00 = Rp 54,067.50
Rp 1,502.00 = Rp 485,146.00
Rp 144,180.00 = Rp 74,973.60
Rp 177,220.00 = Rp 138,231.60
Rp 6,367,950.00 = Rp 891,513.00
Rp 207,860.00 = Rp 582,008.00
Rp 102,130.00 = Rp 3,268,160.00
Jumlah (1) = Rp 10,223,659.70

Rp 59,470.00 = Rp 344,926.00
Rp 88,910.00 = Rp 31,118.50
Rp 88,910.00 = Rp 248,948.00
Rp 88,910.00 = Rp 93,355.50
Rp 103,330.00 = Rp 43,398.60
Rp 103,330.00 = Rp 19,116.05
Jumlah (2) = Rp 780,862.65
Jumlah (1) + (2) = Rp 11,004,522.35
Dibulatkan = Rp 11,004,500.00

Rp 6,367,950.00 = Rp 2,037,744.00
Rp 24,630.00 = Rp 78,816.00
Rp - = Rp -
Rp 17,420.00 = Rp 2,613,000.00
Rp 24,030.00 = Rp 54,067.50
Rp 1,502.00 = Rp 485,146.00
Rp 144,180.00 = Rp 74,973.60
Rp 177,220.00 = Rp 138,231.60
Rp 6,367,950.00 = Rp 1,018,872.00
Rp 207,860.00 = Rp 582,008.00
Rp 102,130.00 = Rp 2,451,120.00
Jumlah (1) = Rp 9,533,978.70

Rp 59,470.00 = Rp 333,032.00
Rp 88,910.00 = Rp 31,118.50
Rp 88,910.00 = Rp 234,722.40
Rp 88,910.00 = Rp 93,355.50
Rp 103,330.00 = Rp 41,332.00
Rp 103,330.00 = Rp 19,942.69
Jumlah (2) = Rp 753,503.09
Jumlah (1) + (2) = Rp 10,287,481.79
Dibulatkan = Rp 10,287,500.00

Rp 6,367,950.00 = Rp 1,591,987.50
Rp 24,630.00 = Rp 73,890.00
Rp - = Rp -
Rp 17,420.00 = Rp 3,484,000.00
Rp 24,030.00 = Rp 72,090.00
Rp 1,502.00 = Rp 485,146.00
Rp 144,180.00 = Rp 74,973.60
Rp 177,220.00 = Rp 138,231.60
Rp 6,367,950.00 = Rp 668,634.75
Rp 207,860.00 = Rp 519,650.00
Rp 102,130.00 = Rp 1,429,820.00
Jumlah (1) = Rp 8,538,423.45

Rp 59,470.00 = Rp 333,032.00
Rp 88,910.00 = Rp 31,118.50
Rp 88,910.00 = Rp 204,493.00
Rp 88,910.00 = Rp 124,474.00
Rp 103,330.00 = Rp 41,848.65
Rp 103,330.00 = Rp 20,872.66
Jumlah (2) = Rp 755,838.81
Jumlah (1) + (2) = Rp 9,294,262.26
Dibulatkan = Rp 9,294,300.00

Rp 6,367,950.00 = Rp 12,735.90
Rp 24,630.00 = Rp 246.30
Rp - = Rp -
Rp 17,420.00 = Rp 7,839.00
Rp 24,030.00 = Rp 96,120.00
Rp 1,502.00 = Rp 9.01
Rp 144,180.00 = Rp 1,297.62
Jumlah (1) = Rp 118,247.83
Rp 59,470.00 = Rp 333,032.00
Rp 88,910.00 = Rp 31,118.50
Rp 88,910.00 = Rp 204,493.00
Rp 88,910.00 = Rp 124,474.00
Rp 103,330.00 = Rp 41,848.65
Rp 103,330.00 = Rp 20,872.66
Jumlah (2) = Rp 755,838.81
Jumlah (1) + (2) = Rp 874,086.64
Dibulatkan = Rp 874,100.00

Rp 6,367,950.00 = Rp 19,103.85
Rp 24,630.00 = Rp 492.60
Rp - = Rp -
Rp 17,420.00 = Rp 871.00
Rp 24,030.00 = Rp 132,165.00
Rp 1,502.00 = Rp 13.52
Rp 144,180.00 = Rp 2,162.70
Jumlah (1) = Rp 154,808.67

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 2,934.03
Rp 88,910.00 = Rp 2,934.03
Rp 88,910.00 = Rp 2,934.03
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 16,299.04
Jumlah (1) + (2) = Rp 171,107.71
Dibulatkan = Rp 171,100.00

N GEDUNG DAN PERUMAHAN SNI 2002


NUTUP ATAP

= Rp -
Jumlah (1) = Rp -
Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 6,668.25
Rp 103,330.00 = Rp 826.64
Rp 103,330.00 = Rp 826.64
Jumlah (2) = Rp 17,242.03
Jumlah (1) + (2) = Rp 17,242.03
Dibulatkan = Rp 17,200.00

= Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 6,668.25
Rp 103,330.00 = Rp 826.64
Rp 103,330.00 = Rp 826.64
Jumlah (2) = Rp 17,242.03
Jumlah (1) + (2) = Rp 17,242.03
Dibulatkan = Rp 17,200.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 6,668.25
Rp 103,330.00 = Rp 826.64
Rp 103,330.00 = Rp 826.64
Jumlah (2) = Rp 17,242.03
Jumlah (1) + (2) = Rp 17,242.03
Dibulatkan = Rp 17,200.00

Rp - = Rp -
Rp 1,502.00 = Rp 12,016.00
Rp 144,180.00 = Rp 4,613.76
Jumlah (1) = Rp 16,629.76

Rp 59,470.00 = Rp 23,788.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 206.66
Jumlah (2) = Rp 43,843.26
Jumlah (1) + (2) = Rp 60,473.02
Dibulatkan = Rp 60,500.00

Rp - = Rp -
Rp 1,502.00 = Rp 12,016.00
Rp 144,180.00 = Rp 4,613.76
Jumlah (1) = Rp 16,629.76

Rp 59,470.00 = Rp 23,788.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 206.66
Jumlah (2) = Rp 43,843.26
Jumlah (1) + (2) = Rp 60,473.02
Dibulatkan = Rp 60,500.00

Rp - = Rp -
Rp 1,502.00 = Rp 12,016.00
Rp 144,180.00 = Rp 4,613.76
Jumlah (1) = Rp 16,629.76

Rp 59,470.00 = Rp 23,788.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 206.66
Jumlah (2) = Rp 43,843.26
Jumlah (1) + (2) = Rp 60,473.02
Dibulatkan = Rp 60,500.00

Rp - = Rp -
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 1,231.50

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 5,956.97
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,729.39
Jumlah (1) + (2) = Rp 16,960.89
Dibulatkan = Rp 17,000.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 6,668.25
Rp 103,330.00 = Rp 826.64
Rp 103,330.00 = Rp 826.64
Jumlah (2) = Rp 16,647.33
Jumlah (1) + (2) = Rp 16,647.33
Dibulatkan = Rp 16,600.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 6,668.25
Rp 103,330.00 = Rp 826.64
Rp 103,330.00 = Rp 826.64
Jumlah (2) = Rp 16,647.33
Jumlah (1) + (2) = Rp 16,647.33
Dibulatkan = Rp 16,600.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,996.12
Jumlah (1) + (2) = Rp 15,996.12
Dibulatkan = Rp 16,000.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,996.12
Jumlah (1) + (2) = Rp 15,996.12
Dibulatkan = Rp 16,000.00
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,996.12
Jumlah (1) + (2) = Rp 15,996.12
Dibulatkan = Rp 16,000.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,996.12
Jumlah (1) + (2) = Rp 15,996.12
Dibulatkan = Rp 16,000.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 5,956.97
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,729.39
Jumlah (1) + (2) = Rp 15,729.39
Dibulatkan = Rp 15,700.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 5,956.97
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,729.39
Jumlah (1) + (2) = Rp 15,729.39
Dibulatkan = Rp 15,700.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 5,956.97
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,729.39
Jumlah (1) + (2) = Rp 15,729.39
Dibulatkan = Rp 15,700.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -
Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 5,956.97
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,729.39
Jumlah (1) + (2) = Rp 15,729.39
Dibulatkan = Rp 15,700.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 5,956.97
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,729.39
Jumlah (1) + (2) = Rp 15,729.39
Dibulatkan = Rp 15,700.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 5,956.97
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,729.39
Jumlah (1) + (2) = Rp 15,729.39
Dibulatkan = Rp 15,700.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 5,956.97
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,729.39
Jumlah (1) + (2) = Rp 15,729.39
Dibulatkan = Rp 15,700.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 5,956.97
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,729.39
Jumlah (1) + (2) = Rp 15,729.39
Dibulatkan = Rp 15,700.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 4,757.60
Rp 88,910.00 = Rp 11,113.75
Rp 103,330.00 = Rp 1,343.29
Rp 103,330.00 = Rp 413.32
Jumlah (2) = Rp 17,627.96
Jumlah (1) + (2) = Rp 17,627.96
Dibulatkan = Rp 17,600.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 4,757.60
Rp 88,910.00 = Rp 11,113.75
Rp 103,330.00 = Rp 1,343.29
Rp 103,330.00 = Rp 413.32
Jumlah (2) = Rp 17,627.96
Jumlah (1) + (2) = Rp 17,627.96
Dibulatkan = Rp 17,600.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 4,757.60
Rp 88,910.00 = Rp 11,113.75
Rp 103,330.00 = Rp 1,343.29
Rp 103,330.00 = Rp 413.32
Jumlah (2) = Rp 17,627.96
Jumlah (1) + (2) = Rp 17,627.96
Dibulatkan = Rp 17,600.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -
Rp 59,470.00 = Rp 4,995.48
Rp 88,910.00 = Rp 11,113.75
Rp 103,330.00 = Rp 1,343.29
Rp 103,330.00 = Rp 413.32
Jumlah (2) = Rp 17,865.84
Jumlah (1) + (2) = Rp 17,865.84
Dibulatkan = Rp 17,900.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 4,995.48
Rp 88,910.00 = Rp 11,113.75
Rp 103,330.00 = Rp 1,343.29
Rp 103,330.00 = Rp 413.32
Jumlah (2) = Rp 17,865.84
Jumlah (1) + (2) = Rp 17,865.84
Dibulatkan = Rp 17,900.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 4,995.48
Rp 88,910.00 = Rp 11,113.75
Rp 103,330.00 = Rp 1,343.29
Rp 103,330.00 = Rp 413.32
Jumlah (2) = Rp 17,865.84
Jumlah (1) + (2) = Rp 17,865.84
Dibulatkan = Rp 17,900.00
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,343.29
Rp 103,330.00 = Rp 413.32
Jumlah (2) = Rp 21,040.11
Jumlah (1) + (2) = Rp 21,040.11
Dibulatkan = Rp 21,000.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 4,995.48
Rp 88,910.00 = Rp 11,113.75
Rp 103,330.00 = Rp 1,343.29
Rp 103,330.00 = Rp 413.32
Jumlah (2) = Rp 17,865.84
Jumlah (1) + (2) = Rp 17,865.84
Dibulatkan = Rp 17,900.00

Rp 11,410.00 = Rp 125,510.00
Rp 24,630.00 = Rp 738.90
Jumlah (1) = Rp 126,248.90

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 22,851.60
Jumlah (1) + (2) = Rp 149,100.50
Dibulatkan = Rp 149,100.00

Rp - = Rp -
Rp 168,210.00 = Rp 58,873.50
Rp 24,630.00 = Rp 738.90
Rp - = Rp -
Jumlah (1) = Rp 59,612.40

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 26,673.00
Rp 103,330.00 = Rp 309.99
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 39,910.29
Jumlah (1) + (2) = Rp 99,522.69
Dibulatkan = Rp 99,500.00

Rp 54,070.00 = Rp 55,151.40
Rp 24,630.00 = Rp 4,926.00
Jumlah (1) = Rp 60,077.40

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 103.33
Jumlah (2) = Rp 21,921.63
Jumlah (1) + (2) = Rp 81,999.03
Dibulatkan = Rp 82,000.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -
Rp 59,470.00 = Rp 9,872.02
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 826.64
Rp 103,330.00 = Rp 25,832.50
Jumlah (2) = Rp 58,758.66
Jumlah (1) + (2) = Rp 58,758.66
Dibulatkan = Rp 58,800.00

Rp - = Rp -
Rp 24,630.00 = Rp 123.15
Rp 1,502.00 = Rp 16,221.60
Rp 144,180.00 = Rp 4,613.76
Rp 3,439.25 = Rp 3,439.25
Jumlah (1) = Rp 24,397.76

Rp 59,470.00 = Rp 23,788.00
Rp 88,910.00 = Rp 17,782.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 2,066.60
Jumlah (2) = Rp 45,703.20
Jumlah (1) + (2) = Rp 70,100.96
Dibulatkan = Rp 70,100.00

Rp - = Rp -
Rp 24,630.00 = Rp 1,231.50
Rp 6,367,950.00 = Rp 22,287.83
Jumlah (1) = Rp 23,519.33

Rp 59,470.00 = Rp 7,433.75
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 32,864.48
Jumlah (1) + (2) = Rp 56,383.81
Dibulatkan = Rp 56,400.00

Rp - = Rp -
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 1,231.50

Rp 59,470.00 = Rp 14,867.50
Rp 88,910.00 = Rp 13,336.50
Rp 103,330.00 = Rp 1,549.95
Rp 103,330.00 = Rp 1,343.29
Jumlah (2) = Rp 31,097.24
Jumlah (1) + (2) = Rp 32,328.74
Dibulatkan = Rp 32,300.00

Rp 73,890.00 = Rp 29,556.00
Rp 24,630.00 = Rp 1,477.80
Rp 24,630.00 = Rp 1,231.50
Rp 6,367,950.00 = Rp 25,471.80
Jumlah (1) = Rp 57,737.10

Rp 59,470.00 = Rp 7,433.75
Rp 88,910.00 = Rp 22,227.50
Rp 103,330.00 = Rp 2,583.25
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 32,864.48
Jumlah (1) + (2) = Rp 90,601.58
Dibulatkan = Rp 90,600.00

Rp 43,250.00 = Rp 30,275.00
Rp 24,630.00 = Rp 492.60
Jumlah (1) = Rp 30,767.60
Rp 59,470.00 = Rp 7,136.40
Rp 88,910.00 = Rp 5,334.60
Rp 103,330.00 = Rp 619.98
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 13,710.96
Jumlah (1) + (2) = Rp 44,478.56
Dibulatkan = Rp 44,500.00

Rp 73,890.00 = Rp 22,167.00
Rp 24,630.00 = Rp 985.20
Jumlah (1) = Rp 23,152.20

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 826.64
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 16,590.82
Jumlah (1) + (2) = Rp 39,743.02
Dibulatkan = Rp 39,700.00

Rp 163,400.00 = Rp 171,570.00
Rp - = Rp -
Jumlah (1) = Rp 171,570.00

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 826.64
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 16,590.82
Jumlah (1) + (2) = Rp 188,160.82
Dibulatkan = Rp 188,200.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 88,910.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 99,897.10
Jumlah (1) + (2) = Rp 99,897.10
Dibulatkan = Rp 99,900.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 4,445.50
Rp 103,330.00 = Rp 516.65
Rp 103,330.00 = Rp 826.64
Jumlah (2) = Rp 14,709.29
Jumlah (1) + (2) = Rp 14,709.29
Dibulatkan = Rp 14,700.00

N GEDUNG DAN PERUMAHAN SNI 2002


GIT - LANGIT

Rp - = Rp -
Rp 24,630.00 = Rp 246.30
Jumlah (1) = Rp 246.30

Rp 59,470.00 = Rp 1,784.10
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 155.00
Jumlah (2) = Rp 8,886.11
Jumlah (1) + (2) = Rp 9,132.41
Dibulatkan = Rp 9,100.00
Rp - = Rp -
Rp 24,630.00 = Rp 246.30
Jumlah (1) = Rp 246.30

Rp 59,470.00 = Rp 1,784.10
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 155.00
Jumlah (2) = Rp 8,886.11
Jumlah (1) + (2) = Rp 9,132.41
Dibulatkan = Rp 9,100.00

Rp - = Rp -
Rp 24,630.00 = Rp 246.30
Jumlah (1) = Rp 246.30

Rp 59,470.00 = Rp 1,784.10
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 155.00
Jumlah (2) = Rp 8,886.11
Jumlah (1) + (2) = Rp 9,132.41
Dibulatkan = Rp 9,100.00

Rp - = Rp -
Rp 24,630.00 = Rp 246.30
Jumlah (1) = Rp 246.30

Rp 59,470.00 = Rp 1,784.10
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 155.00
Jumlah (2) = Rp 8,886.11
Jumlah (1) + (2) = Rp 9,132.41
Dibulatkan = Rp 9,100.00

Rp - = Rp -
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 1,231.50

Rp 59,470.00 = Rp 3,568.20
Rp 88,910.00 = Rp 10,669.20
Rp 103,330.00 = Rp 1,239.96
Rp 103,330.00 = Rp 309.99
Jumlah (2) = Rp 15,787.35
Jumlah (1) + (2) = Rp 17,018.85
Dibulatkan = Rp 17,000.00

Rp - = Rp -
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 1,231.50

Rp 59,470.00 = Rp 3,568.20
Rp 88,910.00 = Rp 10,669.20
Rp 103,330.00 = Rp 1,239.96
Rp 103,330.00 = Rp 309.99
Jumlah (2) = Rp 15,787.35
Jumlah (1) + (2) = Rp 17,018.85
Dibulatkan = Rp 17,000.00

Rp - = Rp -
Rp 24,630.00 = Rp 1,231.50
Jumlah (1) = Rp 1,231.50

Rp 59,470.00 = Rp 3,568.20
Rp 88,910.00 = Rp 10,669.20
Rp 103,330.00 = Rp 1,239.96
Rp 103,330.00 = Rp 309.99
Jumlah (2) = Rp 15,787.35
Jumlah (1) + (2) = Rp 17,018.85
Dibulatkan = Rp 17,000.00

Rp 127,960.00 = Rp 46,065.60
Rp 24,630.00 = Rp 738.90
Jumlah (1) = Rp 46,804.50

Rp 59,470.00 = Rp 4,162.90
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 361.66
Jumlah (2) = Rp 14,448.86
Jumlah (1) + (2) = Rp 61,253.36
Dibulatkan = Rp 61,300.00

Rp 168,210.00 = Rp 60,555.60
Rp 24,630.00 = Rp 738.90
Jumlah (1) = Rp 61,294.50

Rp 59,470.00 = Rp 4,162.90
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 361.66
Jumlah (2) = Rp 14,448.86
Jumlah (1) + (2) = Rp 75,743.36
Dibulatkan = Rp 75,700.00

Rp 127,960.00 = Rp 47,985.00
Rp 24,630.00 = Rp 738.90
Jumlah (1) = Rp 48,723.90
Rp 59,470.00 = Rp 4,162.90
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 361.66
Jumlah (2) = Rp 14,448.86
Jumlah (1) + (2) = Rp 63,172.76
Dibulatkan = Rp 63,200.00

Rp 168,210.00 = Rp 63,078.75
Rp 24,630.00 = Rp 738.90
Jumlah (1) = Rp 63,817.65

Rp 59,470.00 = Rp 4,162.90
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 361.66
Jumlah (2) = Rp 14,448.86
Jumlah (1) + (2) = Rp 78,266.51
Dibulatkan = Rp 78,300.00

Rp - = Rp -
Rp 24,630.00 = Rp 738.90
Jumlah (1) = Rp 738.90

Rp 59,470.00 = Rp 4,162.90
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 361.66
Jumlah (2) = Rp 14,448.86
Jumlah (1) + (2) = Rp 15,187.76
Dibulatkan = Rp 15,200.00

Rp - = Rp -
Rp 24,630.00 = Rp 738.90
Jumlah (1) = Rp 738.90

Rp 59,470.00 = Rp 4,162.90
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 361.66
Jumlah (2) = Rp 14,448.86
Jumlah (1) + (2) = Rp 15,187.76
Dibulatkan = Rp 15,200.00

Rp 12,615,750.00 = Rp 302,778.00
Rp 24,630.00 = Rp 246.30
Rp - = Rp -
Jumlah (1) = Rp 303,024.30

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 53,346.00
Rp 103,330.00 = Rp 6,199.80
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 72,473.10
Jumlah (1) + (2) = Rp 375,497.40
Dibulatkan = Rp 375,500.00

Rp 6,367,950.00 = Rp 152,830.80
Rp 24,630.00 = Rp 246.30
Rp - = Rp -
Jumlah (1) = Rp 153,077.10
Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 53,346.00
Rp 103,330.00 = Rp 6,199.80
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 72,473.10
Jumlah (1) + (2) = Rp 225,550.20
Dibulatkan = Rp 225,600.00

Rp 6,367,950.00 = Rp 152,830.80
Rp 24,630.00 = Rp 246.30
Rp - = Rp -
Jumlah (1) = Rp 153,077.10

Rp 59,470.00 = Rp 11,894.00
Rp 88,910.00 = Rp 53,346.00
Rp 103,330.00 = Rp 6,199.80
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 72,473.10
Jumlah (1) + (2) = Rp 225,550.20
Dibulatkan = Rp 225,600.00

Rp - = Rp -
Rp 24,630.00 = Rp 738.90
Jumlah (1) = Rp 738.90

Rp 59,470.00 = Rp 35,682.00
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 309.99
Jumlah (2) = Rp 45,916.29
Jumlah (1) + (2) = Rp 46,655.19
Dibulatkan = Rp 46,700.00
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,920.50
Rp 88,910.00 = Rp 44,455.00
Rp 103,330.00 = Rp 5,166.50
Rp 103,330.00 = Rp 774.98
Jumlah (2) = Rp 59,316.98
Jumlah (1) + (2) = Rp 59,316.98
Dibulatkan = Rp 59,300.00

Rp - = Rp -
Rp 24,630.00 = Rp 246.30
Jumlah (1) = Rp 246.30

Rp 59,470.00 = Rp 2,973.50
Rp 88,910.00 = Rp 4,445.50
Rp 103,330.00 = Rp 516.65
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 8,452.30
Jumlah (1) + (2) = Rp 8,698.60
Dibulatkan = Rp 8,700.00

gka kayu borneo

Rp 6,367,950.00 = Rp 76,415.40
Rp 24,630.00 = Rp 1,477.80
Rp - = Rp -
Jumlah (1) = Rp 77,893.20
Rp 59,470.00 = Rp 10,704.60
Rp 88,910.00 = Rp 28,451.20
Rp 103,330.00 = Rp 3,306.56
Rp 103,330.00 = Rp 929.97
Jumlah (2) = Rp 43,392.33
Jumlah (1) + (2) = Rp 121,285.53
Dibulatkan = Rp 121,300.00

Rp 6,367,950.00 = Rp 76,415.40
Rp 24,630.00 = Rp 1,477.80
Rp 127,960.00 = Rp 140,756.00
Jumlah (1) = Rp 218,649.20

Rp 59,470.00 = Rp 16,056.90
Rp 88,910.00 = Rp 35,564.00
Rp 103,330.00 = Rp 4,133.20
Rp 103,330.00 = Rp 1,394.96
Jumlah (2) = Rp 57,149.06
Jumlah (1) + (2) = Rp 275,798.26
Dibulatkan = Rp 275,800.00

Rp 6,367,950.00 = Rp 146,462.85
Rp 24,630.00 = Rp 1,477.80
Rp - = Rp -
Jumlah (1) = Rp 147,940.65

Rp 59,470.00 = Rp 15,462.20
Rp 88,910.00 = Rp 35,564.00
Rp 103,330.00 = Rp 4,133.20
Rp 103,330.00 = Rp 1,394.96
Jumlah (2) = Rp 56,554.36
Jumlah (1) + (2) = Rp 204,495.01
Dibulatkan = Rp 204,500.00
Rp 6,367,950.00 = Rp 171,934.65
Rp 24,630.00 = Rp 1,477.80
Rp - = Rp -
Jumlah (1) = Rp 173,412.45

Rp 59,470.00 = Rp 18,435.70
Rp 88,910.00 = Rp 41,787.70
Rp 103,330.00 = Rp 4,856.51
Rp 103,330.00 = Rp 1,601.62
Jumlah (2) = Rp 66,681.53
Jumlah (1) + (2) = Rp 240,093.98
Dibulatkan = Rp 240,100.00

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 5,947.00
Rp 88,910.00 = Rp 4,445.50
Rp 103,330.00 = Rp 516.65
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 11,425.80
Jumlah (1) + (2) = Rp 11,425.80
Dibulatkan = Rp 11,400.00

N GEDUNG DAN PERUMAHAN SNI 2002


SANITASI

Rp 2,403,000.00 = Rp 2,403,000.00
Rp 144,180.00 = Rp 144,180.00 6% x harga kloset
Jumlah (1) = Rp 2,547,180.00
Rp 59,470.00 = Rp 196,251.00
Rp 88,910.00 = Rp 97,801.00
Rp 103,330.00 = Rp 103.33
Rp 103,330.00 = Rp 16,532.80
Jumlah (2) = Rp 310,688.13
Jumlah (1) + (2) = Rp 2,857,868.13
Dibulatkan = Rp 2,857,900.00

Rp 1,740,220.00 = Rp 1,740,220.00
Rp 1,502.00 = Rp 9,012.00
Rp 144,180.00 = Rp 1,441.80
Jumlah (1) = Rp 1,750,673.80

Rp 59,470.00 = Rp 59,470.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 154,995.00
Rp 103,330.00 = Rp 16,532.80
Jumlah (2) = Rp 364,362.80
Jumlah (1) + (2) = Rp 2,115,036.60
Dibulatkan = Rp 2,115,000.00

Rp 1,740,220.00 = Rp 1,740,220.00
Rp 840.00 = Rp 5,880.00
Rp 1,502.00 = Rp 9,012.00
Rp 144,180.00 = Rp 1,441.80
Jumlah (1) = Rp 1,756,553.80

Rp 59,470.00 = Rp 59,470.00
Rp 88,910.00 = Rp 133,365.00
Rp 103,330.00 = Rp 30,999.00
Rp 103,330.00 = Rp 11,366.30
Jumlah (2) = Rp 235,200.30
Jumlah (1) + (2) = Rp 1,991,754.10
Dibulatkan = Rp 1,991,800.00

Rp 823,030.00 = Rp 823,030.00
Rp 246,909.000 = Rp 246,909.00 30% x harga urinoir
Rp 1,502.00 = Rp 9,012.00
Rp 144,180.00 = Rp 1,441.80
Jumlah (1) = Rp 1,080,392.80

Rp 59,470.00 = Rp 59,470.00
Rp 88,910.00 = Rp 88,910.00
Rp 103,330.00 = Rp 10,333.00
Rp 103,330.00 = Rp 1,033.30
Jumlah (2) = Rp 159,746.30
Jumlah (1) + (2) = Rp 1,240,139.10
Dibulatkan = Rp 1,240,100.00

Rp 510,640.00 = Rp 510,640.00
Rp 61,276.80 = Rp 61,276.80 125 x harga wastafel
Rp 1,502.00 = Rp 9,012.00
Rp 144,180.00 = Rp 1,441.80
Jumlah (1) = Rp 582,370.60

Rp 59,470.00 = Rp 71,364.00
Rp 88,910.00 = Rp 128,919.50
Rp 103,330.00 = Rp 15,499.50
Rp 103,330.00 = Rp 10,333.00
Jumlah (2) = Rp 226,116.00
Jumlah (1) + (2) = Rp 808,486.60
Dibulatkan = Rp 808,500.00

Rp - = Rp -
Rp 1,502.00 = Rp 9,012.00
Rp 144,180.00 = Rp 1,441.80
Jumlah (1) = Rp 10,453.80

Rp 59,470.00 = Rp 124,887.00
Rp 88,910.00 = Rp 66,682.50
Rp 103,330.00 = Rp 7,233.10
Rp 103,330.00 = Rp 11,366.30
Jumlah (2) = Rp 210,168.90
Jumlah (1) + (2) = Rp 220,622.70
Dibulatkan = Rp 220,600.00

Rp 456,570.00 = Rp 456,570.00
Rp 82,182.60 = Rp 82,182.60 18% x harga bak fibreglass
Jumlah (1) = Rp 538,752.60

Rp 59,470.00 = Rp 107,046.00
Rp 88,910.00 = Rp 240,057.00
Rp 103,330.00 = Rp 55,798.20
Rp 103,330.00 = Rp 11,366.30
Jumlah (2) = Rp 414,267.50
Jumlah (1) + (2) = Rp 953,020.10
Dibulatkan = Rp 953,000.00

Rp 58,800.00 = Rp 23,520.00 17.5


Rp 1,502.00 = Rp 18,024.00
Rp 144,180.00 = Rp 43,254.00
Rp - = Rp -
Rp 3,439.25 = Rp 20,635.50
Jumlah (1) = Rp 105,433.50

Rp 59,470.00 = Rp 356,820.00
Rp 88,910.00 = Rp 266,730.00
Rp 103,330.00 = Rp 30,999.00
Rp 103,330.00 = Rp 30,999.00
Jumlah (2) = Rp 685,548.00
Jumlah (1) + (2) = Rp 790,981.50
Dibulatkan = Rp 791,000.00

Rp 58,800.00 = Rp 58,800.00
Rp 11,760.00 = Rp 11,760.00 20% X Harga batu bata
Jumlah (1) = Rp 70,560.00

Rp 59,470.00 = Rp -
Rp 88,910.00 = Rp 6,668.25
Rp 103,330.00 = Rp 77,497.50
Rp 103,330.00 = Rp 25,832.50
Jumlah (2) = Rp 109,998.25
Jumlah (1) + (2) = Rp 180,558.25
Dibulatkan = Rp 180,600.00

Rp - = Rp -
Rp 17,420.00 = Rp 313,560.00
Rp 6,367,950.00 = Rp 509,436.00
Rp - = Rp -
= Rp - 10% x harga total bahan
Jumlah (1) = Rp 822,996.00

Rp 59,470.00 = Rp 356,820.00
Rp 88,910.00 = Rp 266,730.00
Rp 103,330.00 = Rp 30,999.00
Rp 103,330.00 = Rp 30,999.00
Jumlah (2) = Rp 685,548.00
Jumlah (1) + (2) = Rp 1,508,544.00
Dibulatkan = Rp 1,508,500.00

Rp 456,570.00 = Rp 456,570.00
Rp 54,788.40 = Rp 54,788.40 12% x harga bak
Jumlah (1) = Rp 511,358.40
Rp 59,470.00 = Rp 107,046.00
Rp 88,910.00 = Rp 240,057.00
Rp 103,330.00 = Rp 55,798.20
Rp 103,330.00 = Rp 11,366.30
Jumlah (2) = Rp 414,267.50
Jumlah (1) + (2) = Rp 925,625.90
Dibulatkan = Rp 925,600.00

diameter 15 cm

Rp - = Rp -
Rp 1,502.00 = Rp 1,021.36
Rp 144,180.00 = Rp 1,874.34
Rp 106,930.00 = Rp 1,176.23
Jumlah (1) = Rp 4,071.93

Rp 59,470.00 = Rp 3,568.20
Rp 88,910.00 = Rp 2,667.30
Rp 103,330.00 = Rp 309.99
Rp 103,330.00 = Rp 258.33
Jumlah (2) = Rp 6,803.82
Jumlah (1) + (2) = Rp 10,875.75
Dibulatkan = Rp 10,900.00

diameter 20 cm

Rp - = Rp -
Rp 1,502.00 = Rp 1,306.74
Rp 144,180.00 = Rp 2,018.52
Rp 106,930.00 = Rp 1,497.02
Jumlah (1) = Rp 4,822.28

Rp 59,470.00 = Rp 4,757.60
Rp 88,910.00 = Rp 3,556.40
Rp 103,330.00 = Rp 413.32
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 9,450.63
Jumlah (1) + (2) = Rp 14,272.91
Dibulatkan = Rp 14,300.00

Rp - = Rp -
Rp 58,800.00 = Rp 1,587.60
Rp 1,502.00 = Rp 5,887.84
Rp 144,180.00 = Rp 8,074.08
Rp 106,930.00 = Rp 2,566.32
Jumlah (1) = Rp 18,115.84

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,996.12
Jumlah (1) + (2) = Rp 34,111.96
Dibulatkan = Rp 34,100.00

Rp - = Rp -
Rp 58,800.00 = Rp 1,587.60
Rp 1,502.00 = Rp 5,887.84
Rp 144,180.00 = Rp 8,074.08
Rp 106,930.00 = Rp 2,566.32
Jumlah (1) = Rp 18,115.84

Rp 59,470.00 = Rp 8,325.80
Rp 88,910.00 = Rp 6,223.70
Rp 103,330.00 = Rp 723.31
Rp 103,330.00 = Rp 723.31
Jumlah (2) = Rp 15,996.12
Jumlah (1) + (2) = Rp 34,111.96
Dibulatkan = Rp 34,100.00

30x30), tinggi 35 cm
Rp 58,800.00 = Rp 8,526.00
Rp 1,502.00 = Rp 66,088.00
Rp 144,180.00 = Rp 10,092.60
Rp 164,010.00 = Rp 11,480.70
Rp 17,420.00 = Rp 27,872.00
Rp 144,180.00 = Rp 8,650.80
Jumlah (1) = Rp 132,710.10

Rp 59,470.00 = Rp 190,304.00
Rp 88,910.00 = Rp 90,243.65
Rp 103,330.00 = Rp 155.00
Rp 103,330.00 = Rp 1,653.28
Jumlah (2) = Rp 282,355.93
Jumlah (1) + (2) = Rp 415,066.03
Dibulatkan = Rp 415,100.00

45x45), tinggi 50 cm

Rp 58,800.00 = Rp 14,700.00
Rp 1,502.00 = Rp 115,654.00
Rp 144,180.00 = Rp 1,874.34
Rp 164,010.00 = Rp 3,280.20
Rp 17,420.00 = Rp 45,292.00
Rp 144,180.00 = Rp 12,976.20
Jumlah (1) = Rp 193,776.74

Rp 59,470.00 = Rp 84,447.40
Rp 88,910.00 = Rp 42,054.43
Rp 103,330.00 = Rp 4,887.51
Rp 103,330.00 = Rp 7,336.43
Jumlah (2) = Rp 138,725.77
Jumlah (1) + (2) = Rp 332,502.51
Dibulatkan = Rp 332,500.00

60x60), tinggi 65 cm

Rp 58,800.00 = Rp 21,814.80
Rp 1,502.00 = Rp 171,228.00
Rp 144,180.00 = Rp 26,529.12
Rp 164,010.00 = Rp 5,412.33
Rp 17,420.00 = Rp 84,487.00
Rp 144,180.00 = Rp 17,301.60
Jumlah (1) = Rp 326,772.85

Rp 59,470.00 = Rp 128,455.20
Rp 88,910.00 = Rp 64,015.20
Rp 103,330.00 = Rp 7,439.76
Rp 103,330.00 = Rp 11,159.64
Rp 88,910.00 = Rp 8,891.00
Jumlah (2) = Rp 219,960.80
Jumlah (1) + (2) = Rp 546,733.65
Dibulatkan = Rp 546,700.00

Rp 73,290.00 = Rp 87,948.00
Rp 25,651.50 = Rp 25,651.50 35% x harga pipa
Jumlah (1) = Rp 113,599.50

Rp 59,470.00 = Rp 3,211.38
Rp 88,910.00 = Rp 8,001.90
Rp 103,330.00 = Rp 929.97
Rp 103,330.00 = Rp 2,789.91
Jumlah (2) = Rp 14,933.16
Jumlah (1) + (2) = Rp 128,532.66
Dibulatkan = Rp 128,500.00

Rp 96,120.00 = Rp 115,344.00
Rp 33,642.00 = Rp 33,642.00 35% x harga pipa
Jumlah (1) = Rp 148,986.00

Rp 59,470.00 = Rp 3,211.38
Rp 88,910.00 = Rp 8,001.90
Rp 103,330.00 = Rp 929.97
Rp 103,330.00 = Rp 2,789.91
Jumlah (2) = Rp 14,933.16
Jumlah (1) + (2) = Rp 163,919.16
Dibulatkan = Rp 163,900.00

Rp 120,150.00 = Rp 144,180.00
Rp 42,052.50 = Rp 42,052.50 35% x harga pipa
Jumlah (1) = Rp 186,232.50

Rp 59,470.00 = Rp 3,211.38
Rp 88,910.00 = Rp 8,001.90
Rp 103,330.00 = Rp 929.97
Rp 103,330.00 = Rp 2,789.91
Jumlah (2) = Rp 14,933.16
Jumlah (1) + (2) = Rp 201,165.66
Dibulatkan = Rp 201,200.00

Rp 180,230.00 = Rp 216,276.00
Rp 63,080.50 = Rp - 35% x harga pipa
Jumlah (1) = Rp 216,276.00

Rp 59,470.00 = Rp 3,211.38
Rp 88,910.00 = Rp 8,001.90
Rp 103,330.00 = Rp 929.97
Rp 103,330.00 = Rp 2,789.91
Jumlah (2) = Rp 14,933.16
Jumlah (1) + (2) = Rp 231,209.16
Dibulatkan = Rp 231,200.00

Rp - = Rp -
Rp - = Rp - 35% x harga pipa
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 6,422.76
Rp 88,910.00 = Rp 16,003.80
Rp 103,330.00 = Rp 1,859.94
Rp 103,330.00 = Rp 557.98
Jumlah (2) = Rp 24,844.48
Jumlah (1) + (2) = Rp 24,844.48
Dibulatkan = Rp 24,800.00

Rp - = Rp -
Rp - = Rp - 35% x harga pipa
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 8,028.45
Rp 88,910.00 = Rp 20,004.75
Rp 103,330.00 = Rp 2,324.93
Rp 103,330.00 = Rp 702.64
Jumlah (2) = Rp 31,060.77
Jumlah (1) + (2) = Rp 31,060.77
Dibulatkan = Rp 31,100.00

Rp 66,100.00 = Rp 79,320.00
Rp 23,135.00 = Rp 23,135.00 35% x harga pipa
Jumlah (1) = Rp 102,455.00

Rp 59,470.00 = Rp 2,140.92
Rp 88,910.00 = Rp 5,334.60
Rp 103,330.00 = Rp 619.98
Rp 103,330.00 = Rp 185.99
Jumlah (2) = Rp 8,281.49
Jumlah (1) + (2) = Rp 110,736.49
Dibulatkan = Rp 110,700.00

Rp 69,110.00 = Rp 82,932.00
Rp 24,188.50 = Rp 24,188.50 35% x harga pipa
Jumlah (1) = Rp 107,120.50
Rp 59,470.00 = Rp 2,140.92
Rp 88,910.00 = Rp 5,334.60
Rp 103,330.00 = Rp 619.98
Rp 103,330.00 = Rp 185.99
Jumlah (2) = Rp 8,281.49
Jumlah (1) + (2) = Rp 115,401.99
Dibulatkan = Rp 115,400.00

Rp 132,200.00 = Rp 158,640.00
Rp 46,270.00 = Rp 46,270.00 35% x harga pipa
Jumlah (1) = Rp 204,910.00

Rp 59,470.00 = Rp 2,140.92
Rp 88,910.00 = Rp 5,334.60
Rp 103,330.00 = Rp 619.98
Rp 103,330.00 = Rp 185.99
Jumlah (2) = Rp 8,281.49
Jumlah (1) + (2) = Rp 213,191.49
Dibulatkan = Rp 213,200.00

Rp 1.00 = Rp 1.20
Rp 0.35 = Rp 0.35 35% x harga pipa
Jumlah (1) = Rp 1.55

Rp 59,470.00 = Rp 2,140.92
Rp 88,910.00 = Rp 5,334.60
Rp 103,330.00 = Rp 619.98
Rp 103,330.00 = Rp 185.99
Jumlah (2) = Rp 8,281.49
Jumlah (1) + (2) = Rp 8,283.04
Dibulatkan = Rp 8,300.00
Rp 264,300.00 = Rp 317,160.00
Rp 92,505.00 = Rp 92,505.00 35% x harga pipa
Jumlah (1) = Rp 409,665.00

Rp 59,470.00 = Rp 3,211.38
Rp 88,910.00 = Rp 8,001.90
Rp 103,330.00 = Rp 929.97
Rp 103,330.00 = Rp 278.99
Jumlah (2) = Rp 12,422.24
Jumlah (1) + (2) = Rp 422,087.24
Dibulatkan = Rp 422,100.00

Rp 1.00 = Rp 1.20
Rp 0.35 = Rp - 35% x harga pipa
Jumlah (1) = Rp 1.20

Rp 59,470.00 = Rp 2,140.92
Rp 88,910.00 = Rp 5,334.60
Rp 103,330.00 = Rp 619.98
Rp 103,330.00 = Rp 185.99
Jumlah (2) = Rp 8,281.49
Jumlah (1) + (2) = Rp 8,282.69
Dibulatkan = Rp 8,300.00

Rp 396,500.00 = Rp 475,800.00
Rp 138,775.00 = Rp 138,775.00 35% x harga pipa
Jumlah (1) = Rp 614,575.00

Rp 59,470.00 = Rp 4,817.07
Rp 88,910.00 = Rp 12,002.85
Rp 103,330.00 = Rp 1,394.96
Rp 103,330.00 = Rp 423.65
Jumlah (2) = Rp 18,638.53
Jumlah (1) + (2) = Rp 633,213.53
Dibulatkan = Rp 633,200.00

Rp 528,660.00 = Rp 634,392.00
Rp 185,031.00 = Rp 185,031.00 35% x harga pipa
Jumlah (1) = Rp 819,423.00

Rp 59,470.00 = Rp 4,817.07
Rp 88,910.00 = Rp 12,002.85
Rp 103,330.00 = Rp 1,394.96
Rp 103,330.00 = Rp 423.65
Jumlah (2) = Rp 18,638.53
Jumlah (1) + (2) = Rp 838,061.53
Dibulatkan = Rp 838,100.00

Rp 348,440.00 = Rp 348,440.00
Rp - = Rp -
Jumlah (1) = Rp 348,440.00

Rp 59,470.00 = Rp 1,784.10
Rp 88,910.00 = Rp 26,673.00
Rp 103,330.00 = Rp 3,099.90
Rp 103,330.00 = Rp 155.00
Jumlah (2) = Rp 31,712.00
Jumlah (1) + (2) = Rp 380,152.00
Dibulatkan = Rp 380,200.00

Rp - = Rp -
Rp - = Rp -
Rp 1,502.00 = Rp 30,040.00
Rp 144,180.00 = Rp 7,209.00
Jumlah (1) = Rp 37,249.00
Rp 59,470.00 = Rp 2,973.50
Rp 88,910.00 = Rp 44,455.00
Rp 103,330.00 = Rp 5,166.50
Rp 103,330.00 = Rp 258.33
Jumlah (2) = Rp 52,853.33
Jumlah (1) + (2) = Rp 90,102.33
Dibulatkan = Rp 90,100.00

Rp 45,660.00 = Rp 45,660.00
Rp - = Rp -
Jumlah (1) = Rp 45,660.00

Rp 59,470.00 = Rp 594.70
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 11,035.65
Jumlah (1) + (2) = Rp 56,695.65
Dibulatkan = Rp 56,700.00

Rp 22,830.00 = Rp 22,830.00
Jumlah (1) = Rp 22,830.00

Rp 59,470.00 = Rp 594.70
Rp 88,910.00 = Rp 8,891.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 516.65
Jumlah (2) = Rp 11,035.65
Jumlah (1) + (2) = Rp 33,865.65
Dibulatkan = Rp 33,900.00
N GEDUNG DAN PERUMAHAN SNI 2002
AN ALUMINIUM

Rp 23,430.00 = Rp 25,773.00
Rp - = Rp -
Jumlah (1) = Rp 25,773.00

Rp 88,910.00 = Rp 533.46
Rp 59,470.00 = Rp 3,568.20
Rp 103,330.00 = Rp 619.98
Rp 103,330.00 = Rp 31.00
Jumlah (2) = Rp 4,752.64
Jumlah (1) + (2) = Rp 30,525.64
Dibulatkan = Rp 30,500.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 88,910.00 = Rp 57,791.50
Rp 59,470.00 = Rp 38,655.50
Rp 103,330.00 = Rp 6,716.45
Rp 103,330.00 = Rp 3,306.56
Jumlah (2) = Rp 106,470.01
Jumlah (1) + (2) = Rp 106,470.01
Dibulatkan = Rp 106,500.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 88,910.00 = Rp 93,355.50
Rp 59,470.00 = Rp 6,244.35
Rp 103,330.00 = Rp 10,849.65
Rp 103,330.00 = Rp 542.48
Jumlah (2) = Rp 110,991.98
Jumlah (1) + (2) = Rp 110,991.98
Dibulatkan = Rp 111,000.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 88,910.00 = Rp 106,692.00
Rp 59,470.00 = Rp 60,778.34
Rp 103,330.00 = Rp 12,399.60
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 180,489.92
Jumlah (1) + (2) = Rp 180,489.92
Dibulatkan = Rp 180,500.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 88,910.00 = Rp 106,692.00
Rp 59,470.00 = Rp 71,364.00
Rp 103,330.00 = Rp 12,399.60
Rp 103,330.00 = Rp 619.98
Jumlah (2) = Rp 191,075.58
Jumlah (1) + (2) = Rp 191,075.58
Dibulatkan = Rp 191,100.00

Rp - = Rp -
Jumlah (1) = Rp -
Rp 88,910.00 = Rp 94,244.60
Rp 59,470.00 = Rp 6,244.35
Rp 103,330.00 = Rp 10,849.65
Rp 103,330.00 = Rp 537.32
Jumlah (2) = Rp 111,875.92
Jumlah (1) + (2) = Rp 111,875.92
Dibulatkan = Rp 111,900.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 88,910.00 = Rp 71,128.00
Rp 59,470.00 = Rp 4,757.60
Rp 103,330.00 = Rp 8,266.40
Rp 103,330.00 = Rp 413.32
Jumlah (2) = Rp 84,565.32
Jumlah (1) + (2) = Rp 84,565.32
Dibulatkan = Rp 84,600.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 88,910.00 = Rp 133,365.00
Rp 59,470.00 = Rp 62,443.50
Rp 103,330.00 = Rp 10,849.65
Rp 103,330.00 = Rp 413.32
Jumlah (2) = Rp 207,071.47
Jumlah (1) + (2) = Rp 207,071.47
Dibulatkan = Rp 207,100.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 88,910.00 = Rp 93,355.50
Rp 59,470.00 = Rp 62,443.50
Rp 103,330.00 = Rp 10,849.65
Rp 103,330.00 = Rp 537.32
Jumlah (2) = Rp 167,185.97
Jumlah (1) + (2) = Rp 167,185.97
Dibulatkan = Rp 167,200.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 88,910.00 = Rp 31,118.50
Rp 59,470.00 = Rp 20,814.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 180.83
Jumlah (2) = Rp 55,730.38
Jumlah (1) + (2) = Rp 55,730.38
Dibulatkan = Rp 55,700.00

Rp - = Rp -
Jumlah (1) = Rp -

Rp 88,910.00 = Rp 31,118.50
Rp 59,470.00 = Rp 20,814.50
Rp 103,330.00 = Rp 3,616.55
Rp 103,330.00 = Rp 180.83
Jumlah (2) = Rp 55,730.38
Jumlah (1) + (2) = Rp 55,730.38
Dibulatkan = Rp 55,700.00
Rp 300,375.00 = Rp 3,304,125.00
Jumlah (1) = Rp 3,304,125.00

Rp 88,910.00 = Rp 106,692.00
Rp 59,470.00 = Rp 71,364.00
Rp 103,330.00 = Rp 1,239.96
Rp 103,330.00 = Rp 62.00
Jumlah (2) = Rp 179,357.96
Jumlah (1) + (2) = Rp 3,483,482.96
Dibulatkan = Rp 3,483,500.00

Rp 44,450.00 = Rp 48,895.00
Rp 24,630.00 = Rp 492.60
Rp 6,367,950.00 = Rp 11,462.31
Jumlah (1) = Rp 60,849.91

Rp 88,910.00 = Rp 8,891.00
Rp 59,470.00 = Rp 5,947.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 51.67
Jumlah (2) = Rp 15,922.97
Jumlah (1) + (2) = Rp 76,772.88
Dibulatkan = Rp 76,800.00

Rp 21,620.00 = Rp 23,782.00
Rp 24,630.00 = Rp 492.60
Rp 6,367,950.00 = Rp 11,462.31
Jumlah (1) = Rp 35,736.91

Rp 88,910.00 = Rp 8,891.00
Rp 59,470.00 = Rp 5,947.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 51.67
Jumlah (2) = Rp 15,922.97
Jumlah (1) + (2) = Rp 51,659.88
Dibulatkan = Rp 51,700.00

Rp - = Rp -
Rp 24,630.00 = Rp 492.60
Rp 6,367,950.00 = Rp 11,462.31
Jumlah (1) = Rp 11,954.91

Rp 88,910.00 = Rp 8,891.00
Rp 59,470.00 = Rp 5,947.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 51.67
Jumlah (2) = Rp 15,922.97
Jumlah (1) + (2) = Rp 27,877.88
Dibulatkan = Rp 27,900.00

Rp - = Rp -
Rp 24,630.00 = Rp 492.60
Rp 6,367,950.00 = Rp 11,462.31
Jumlah (1) = Rp 11,954.91

Rp 88,910.00 = Rp 8,891.00
Rp 59,470.00 = Rp 5,947.00
Rp 103,330.00 = Rp 1,033.30
Rp 103,330.00 = Rp 51.67
Jumlah (2) = Rp 15,922.97
Jumlah (1) + (2) = Rp 27,877.88
Dibulatkan = Rp 27,900.00

Rp 158,600.00 = Rp 174,460.00
Rp 24,630.00 = Rp 492.60
Rp 6,367,950.00 = Rp 159,198.75
= Rp 334,151.35

Rp 88,910.00 = Rp 17,782.00
Rp 59,470.00 = Rp 11,894.00
Rp 103,330.00 = Rp 2,066.60
Rp 103,330.00 = Rp 103.33
Jumlah (2) = Rp 31,845.93
Jumlah (1) + (2) = Rp 365,997.28
Dibulatkan = Rp 366,000.00

Rp - = Rp -
Rp 24,630.00 = Rp 369.45
Rp 6,367,950.00 = Rp 61,132.32
Rp - = Rp -
Jumlah (1) = Rp 61,501.77

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp 61,501.77
Dibulatkan = Rp 61,500.00

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

N GEDUNG DAN PERUMAHAN SNI 2002


CI DAN KACA

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

N GEDUNG DAN PERUMAHAN SNI 2002


ANTAI

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

N GEDUNG DAN PERUMAHAN SNI 2002


N CAT

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -

Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -

Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -

Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

n panca pasir (sanblasting) dgn tingkat

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Jumlah (2) = Rp -
Rp - = Rp -

Rp - = Rp -
Jumlah (3) = Rp -
Jumlah (1)+(2)+(3) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

at dasar, 2 lapis cat penutup

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

at dasar, 3 lapis cat penutup

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -

Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
sar, 2 lapis cat penutup)

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
a manual sistem 4 lapis cat konvensional

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

a manual sistem 1 lapis cat mutakhir

Rp - = Rp -
Jumlah (1) = Rp -

Rp 59,470.00 = Rp 356.82
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp 356.82
Jumlah (1) + (2) = Rp 356.82
Dibulatkan = Rp 400.00

a manual sistem 3 lapis cat konvensional

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (1) = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -

a semprot (airless spray) sistem 1 lapis cat mutakhir

Rp - = Rp -
Jumlah (1) = Rp -

Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Rp - = Rp -
Jumlah (2) = Rp -
Jumlah (1) + (2) = Rp -
Dibulatkan = Rp -
DAFTAR DAN UPAH BAHAN BANGUNAN
DINAS PERUMAHAN DAN PEMUKIMAN KOTA MEDAN
TAHUN ANGGARAN 2002

No Nama Bahan Harga Satuan

A DAFTAR PEKERJA
1 Pekerja Rp 59,470.00 Hari
2 Mandor Rp 103,330.00 Hari
3 Tukang Kayu Rp 88,910.00 Hari
4 Tukang Batu, Cat, Besi Rp 88,910.00 Hari
5 Kepala Tukang Rp 103,330.00 Hari

B DAFTAR BAHAN
1. GALIAN
1 Tanah timbun/Merah Rp 97,320.00 m3
2 Pasir timbun Rp 106,930.00 m3
3 Pasir pasang Rp 144,180.00 m3
4 Sirtu / Kerikil kotor Rp 164,010.00 m3
5 Batu kerikil (A) Cor Rp 291,960.00 m3
6 Batu mangga Rp 214,470.00 m3
7 Batu koral 15 - 20 cm Rp 177,220.00 m3
8 Batu pecah 1 -2 cm Rp 303,380.00 m3
9 Batu bata besar (jumbo) Rp 840.00 Bh
10 Batu bata mesin Rp 960.00 Bh
11 Batu krawang 10 x 20 cm Rp 5,410.00 Bh
12 Semen PC @ 40 kg Rp 60,080.00 Zak
13 Semen Putih @ 40 kg Rp 137,570.00 Zak
14 Kapur pasang Rp 2,400.00 Kg
15 Kapur basah / Dinding Rp - Kg

2. KAYU
16 Broti / papan kayu sembarang Rp 6,367,950.00 Ton
17 Broti kayu meranti Rp 7,809,750.00 Ton
18 Broti kayu damar laut Rp 11,414,250.00 Ton
19 Papan kayu meranti Rp 8,410,500.00 Ton
20 Papan kayu meranti batu Rp 12,615,750.00 Ton
21 Papan kayu damar laut Rp 12,615,750.00 Btg
22 Kayu buta-buta / Kayu api Ø 2" - 3" Pj 3 - 4 m Rp 84,110.00 Btg
23 Kayu buta-buta / Kayu api Ø 3" - 4" Pj 3 - 4 m Rp 99,120.00 Btg
24 Kayu buta-buta / Kayu api Ø 4" - 5" Pj 3 - 4 m Rp 102,130.00 Btg
25 Kayu lat asbes ketam Rp 12,620.00 Btg
26 Kayu lat asbes tidak ketam Rp 9,610.00 Btg
27 Listplank motif bungan 14 x 40 cm Rp 22,230.00 Btg
28 Jalusi motif bunga 18 x 60 cm Rp 25,230.00 Bh
29 Profil gypsum Rp 67,280.00 Bh
30 Profil gypsum uk 120 x 240 cm Rp 144,180.00 Lbr
31 Triplek Sungkai # 3 mm uk 120 x 240 cm Rp 132,170.00 Lbr
32 Triplek Jati # 3 mm uk 120 x 240 cm Rp 91,070.00 Lbr
33 Triplek # 4 mm uk 120 x 240 cm Rp 127,960.00 Lbr
34 Triplek # 6 mm uk 120 x 240 cm Rp 168,210.00 Lbr
35 Triplek # 9 mm uk 120 x 240 cm Rp 207,860.00 Lbr
36 Triplek # 12 mm uk 120 x 240 cm Rp 264,330.00 Lbr
37 Triplek # 18 mm uk 120 x 240 cm Rp 87,710.00 Lbr
38 Shop board # 12 mm uk 120 x 240 cm Rp 21,550.00 Lbr
39 Asbes lokal 1 x 1 m Rp 26,330.00 Lbr
40 Asbes astrisc 1 x 1 m

3. BESI / KAWAT
41 Paku biasa Rp 24,630.00 Kg
42 Paku seng Rp 31,840.00 Kg
43 Paku sumbat Rp 450.00 Bh
44 Paku seng + Ring karet Rp 510.00 Bh
45 Baut seng + Ring karet Rp 1,500.00 Bh
46 Sekrup Rp 2,800.00 Bh
47 Besi beton Rp 17,420.00 Kg
48 Besi strip 12.2 mm Rp 38,445.00 Kg
49 Besi profil Rp 23,430.00 Btg
50 Jerjak besi Rp 300,375.00 m2
51 Pagar besi strip Rp 300,375.00 m2
52 Pintu paga r besi Rp 841,050.00 m2
53 Pintu harmonika Rp 1,441,800.00 m2
54 Tiang bendera besi Ø 3" T = 6 m Rp 841,050.00 Bh
55 Kawat beton Rp 24,030.00 Kg
56 Kawat las Rp 9,010.00 Kg
57 Kawat licin Rp 16,820.00 Kg
58 Kawat harmonika Rp 44,450.00 m2
59 kawat nyamuk lokal Rp 21,620.00 m2
60 Kawat duri Rp - m
61 Rangka jendela nako 8 daun standart Rp 40,500.00 Set
62 Profil aluminium Rp 14,420.00 m
63 bahab patri Rp 6,600.00 m2
64 Rangka atap baja ringan atap seng Rp 186,230.00 m2
65 Rangka atap baja ringan atap genteng metal Rp 213,270.00 m2
66 Rangka atap baja ringan atap genteng keramik / beton Rp 240,300.00 m2
67 Rangka furing Rp 83,750.00 m2
4. ATAP
68 Rabung seng BJLS 20 L = 30 cm Rp 25,230.84 Lbr
69 Rabung genteng warna Rp 8,410.00 Bh
70 Rabung genteng keramik Rp 16,220.00 Bh
71 Rabung genteng asbes (fiber cement) Rp 24,030.00 Bh
72 Rabung asbes gelombang Rp 12,620.00 Bh
73 Rabung genteng metal # 0.25 Rp 34,840.00 Bh
74 Plat Alumunium # 0.5 mm Rp 163,400.00 Lbr
75 Seng plat BLJS 35 Rp 177,150.00 Lbr
76 Seng plat BLJS 20 Rp 73,890.00 Lbr
77 Seng gelombang BJLS 35 Rp 73,890.00 Lbr
78 Seng gelombang BJLS 20 Rp 43,250.00 Lbr
79 Genteng warna Rp 28,840.00 Lbr
80 Genteng keramik Rp 7,810.00 Bh
81 Genteng asbes (fiber cement) Rp 11,410.00 Bh
82 Genteng metal # 0.25 (16 daun) Rp 54,070.00 Lbr
83 Genteng warna Rp 79,900.00 Lbr

5. CAT & AMPELAS


84 Cat minyak/perak (setara bee brand) Rp 49,260.00 Kg
85 cat kilat ICI Rp 48,060.00 Kg
86 Minyak cat Rp 18,620.00 Ltr
87 tepung dempul Rp 8,410.00 Kg
88 Dempul jadi Rp 18,620.00 Kg
89 Cat tembok (setara vinilex) Rp 23,430.00 Kg
90 Cat tembok (setara paragon) Rp 16,820.00 Kg
91 Cat tembok ICI Rp - Kg
92 Cat vernis jadi Rp 37,850.00 Kg
93 Cat meni Rp 22,830.00 Kg
94 Kertas pasir Rp 4,210.00 Lbr
95 Residu ( Colter) Rp 25,230.00 Kg
96 Tepung Gypsum Rp 81,700.00 Zak
97 Tepung pelitur Rp 18,620.00 Kg
98 Serlak keripik Rp 79,300.00 Kg
99 Serlak putih Rp 46,260.00 Ltr
100 Tinner Rp 16,820.00 Ltr
101 Spiritus putih Rp 10,210.00 Ltr
102 Minyak tanah Rp 6,730.00 Ltr

6. KACA
103 Kaca bening # = 5 mm Rp 158,600.00 m2
104 Kaca ryben # = 5 mm Rp 193,440.00 m2
105 Kaca Es # 5 mm Rp 170,610.00 m2
106 Kaca blok Rp 25,230.00 Bh
107 Kaca nako bening # 5 mm standart Rp 4,930.00 Lbr
108 Kaca nako ryben # 5 mm standart Rp 4,810.00 Lbr

7. KERAMIK & BETON CETAK


109 Plint keramik 15 x 30 cm Rp 3,725.00 Bh
110 Plint keramik 10 x 30 cm Rp 2,640.00 Bh
111 Plint keramik 15 x 40 cm Rp 4,570.00 Bh
112 Keramik 10 x 30 cm Rp 960.00 Bh
113 Keramik 20 x 20 cm Rp 2,400.00 Bh
114 Keramik 20 x 25 cm Rp 2,760.00 Bh
115 Keramik 30 x 30 cm Rp 6,010.00 Bh
116 Keramik 40 x 40 cm Rp 10,810.00 Bh
117 Keramik granito 40 x 40 cm Rp 51,060.00 Bh
118 Keramik ezenza 20 x 20 cm Rp 63,080.00 Bh
119 Siku keramik (bon-bon) Rp 10,210.00 m'
120 Tempat sabun keramik 10 x 20 cm Rp 40,850.00 Bh
121 Closed jongkok keramik Rp 1,740,220.00 Bh
122 Closet duduk standard Rp 2,403,000.00 Bh
123 Wastafel komplet standard Rp 510,640.00 unit
124 Urinoir komplet standard Rp 823,030.00 unit
125 Bak cuci piring 1 lobang stainless steel komplet standar Rp 348,440.00 unit
126 Bak cuci piring 2 lobang stainless steel komplet standar Rp 841,050.00 unit
127 Bak cuci piring trasso komplet Rp - unit
128 Bak air fibre glass Rp 456,570.00 Bh
129 Riol beton 1/2 Ø 15 cm P = 1 m Rp 45,060.00 Bh
130 Riol beton 1/2 Ø 20 cm P = 1 m Rp 45,660.00 Bh
131 Riol beton 1/2 Ø 30 cm P = 1 m Rp 46,260.00 Bh
132 Riol beton Ø 15 cm P = 1 m Rp 46,350.00 Bh
133 Riol beton Ø 20 cm P = 1 m Rp 47,460.00 Bh
134 Riol beton Ø 30 cm P = 1 m Rp 71,490.00 Bh
135 Riol beton Ø 80 cm P = 1 m Rp 252,320.00 Bh
136 Riol beton Ø 100 cm P = 1 m Rp 288,360.00 Bh
137 Batu con blok K 125 Rp 1,680.00 Bh
138 Batu con blok K 175 Rp 2,100.00 Bh
139 Con blok type HOLAN DISH warna merah # 6 cm Rp 2,400.00 Bh
140 Con blok type HOLAN DISH warna merah # 8 cm Rp 3,120.00 Bh
141 Con blok type UNI PAVE warna merah # 6 cm Rp 2,100.00 Bh
142 Con blok type UNI PAVE warna merah # 8 cm Rp 3,120.00 Bh
143 Con blok type DOSEX SIX warna merah # 6 cm Rp 2,400.00 Bh
144 Con blok type DOSEX SIX warna merah # 8 cm Rp 3,120.00 Bh
145 Con blok type HEXAGON warna merah # 6 cm Rp 2,100.00 Bh
146 Con blok type HEXAGON warna merah # 8 cm Rp 1,340.00 Bh
147 Kastin uk. 15 x 30 x 40 cm Rp 25,230.00 Bh
148 Batu bataco Rp - Bh

8. PIPA PVC DAN BESI


149 Pipa PVC (Paralon) kwalitet AW Ø 1/2" Rp 66,100.00 Btg
150 Pipa PVC (Paralon) kwalitet AW Ø 3/4" Rp 69,110.00 Btg
151 Pipa PVC (Paralon) kwalitet AW Ø 1" Rp 132,200.00 Btg
152 Pipa PVC (Paralon) kwalitet AW Ø 2" Rp 264,300.00 Btg
153 Pipa PVC (Paralon) kwalitet AW Ø 3" Rp 396,500.00 Btg
154 Pipa PVC (Paralon) kwalitet AW Ø 4" Rp 528,660.00 Btg
155 Pipa PVC (Paralon) kwalitet AW Ø 8" Rp 1,063,300.00 Btg
156 Pipa PVC (Paralon) listrik Rp 7,650.00 Btg
157 Pipa besi GIP Ø 1/2" Rp 73,290.00 Btg
158 Pipa besi GIP Ø 3/4" Rp 96,120.00 Btg
159 Pipa besi GIP Ø 1" Rp 120,150.00 Btg
160 Pipa besi GIP Ø 1 1/4" Rp 156,200.00 Btg
161 Pipa besi GIP Ø 1 1/2" Rp 180,230.00 Btg
162 Pipa besi GIP Ø 2" Rp 246,310.00 Btg
163 Pompa tangan (Dragon sejenis) Rp 570,710.00 Bh
164 Mesin pompa air (Daff sejenis) Rp 612,770.00 Bh
165 Mesin pompa air (Sanyo sejenis) Rp 901,130.00 Bh
166 Sumur bor dangkal Rp 1,441,800.00 m'
167 Pintu fiber Glass kamar mandi Rp 408,510.00 Bh

9. LISTRIK
168 Kabel listrik NYA Golden Livers / Sejenis 1.5 mm Rp 252,315.00 Roll
169 Kabel listrik NYA Golden Livers / Sejenis 2.5 mm Rp 328,470.00 Roll
170 Kabel listrik NYM Golden Livers / Sejenis 2 x 1.5 mm Rp 342,430.00 Roll
171 Kabel listrik NYM Golden Livers / Sejenis 2 x 2.5 mm Rp 503,430.00 Roll
172 Kabel listrik NYM Golden Livers / Sejenis 2 x 4 mm Rp 699,280.00 Roll
173 Instalasi listrik stop kontak Rp 103,490.00 Ttk
174 Instalasi listrik stop nyala Rp 103,490.00 Ttk
175 Lampu TL 1 x 40 watt (komplet) Rp 67,400.00 Set
176 Lampu TL 1 x 20 watt (komplet) Rp 52,210.00 Set
177 Lampu pijar 40 watt Rp 3,700.00 Bh
178 Lampu SL 23 watt Rp 34,360.00 Bh
179 Lampu SL 18 watt Rp 24,030.00 Bh
180 Saklar enkle timbul Rp 15,260.00 Bh
181 Saklar seri timbul Rp 18,980.00 Bh
182 Stopp kontak timbul Rp 14,900.00 Bh
183 Saklar triple timbul Rp 19,830.00 Bh
184 Saklar enkle tanam Rp 15,620.00 Bh
185 Saklar seri tanam Rp 19,100.00 Bh
186 Saklar triple tanam Rp 19,830.00 Bh
187 Stop kontak tanam Rp 16,060.00 Set
188 Box Zekering 1 group Rp 9,010.00 Set
189 Box Zekering 2 group Rp 24,030.00 Bh
190 MCB 2 Ampre Rp 18,020.00 Bh
191 MCB 4 Ampre Rp 18,020.00 Bh

10. SANITAIR
192 Kran air lokal uk 1/2 " Rp 22,830.00 Bh
193 Kran air bebek lokal uk 1/2 " Rp 45,660.00 Bh
194 Kran air San Ei uk 1/2 " Rp 112,940.00 Bh
195 Kran air bebek San Ei uk 1/2 " Rp 144,180.00 Bh
196 Stop kran uk 1/2" Rp 42,050.00 Bh
197 Stop kran uk 3/4" Rp 62,480.00 Bh
198 Instalasi air bersih Rp 103,930.00 Ttk
199 Saringan air kamar mandi (floor drain) Rp 17,420.00 Bh
200 Pipa kuras pembuangan bak Rp 8,410.00 Bh
201 Septic tank kapasitas 3 m3 Rp 3,063,830.00 Bh

11. PENGUNCI DAN PENGGANTUNG


202 Kunci tanam besar Union (sejenis) Rp 112,340.00 Bh
203 Kunci tanam kecil Union (sejenis) Rp 52,270.00 Bh
204 Kunci Silinder Rp 88,910.00 Bh
205 Engsel pintu cabut uk 5 " Rp 8,410.00 Set
206 Engsel pintu Nilon uk 4 " Rp 12,020.00 Set
207 Engsel jendela cabuk uk 3 " Rp 4,810.00 Set
208 Engsel jendela Nilon uk 3 " Rp 7,210.00 Set
209 Engsel Milano uk 18 " Rp 88,910.00 Set
210 Engsel Milano uk 16 " Rp 68,490.00 Set
211 Engsel pintu lipat (gudang) Rp 31,240.00 Set
212 Engsel panjang Rp 6,610.00 m'
213 Grendel pintu Rp 5,410.00 Bh
214 Grendel jendela Rp 4,810.00 Bh
215 Hak angin Rp 6,610.00 Bh
216 Espagnolet Rp 103,330.00 Set

12. ASSECORIES
217 Wall paper Falcon Rp 68,490.00 m2
218 Wall paper Kingston Rp 88,910.00 m2
219 Wall paper Duraport Rp 104,530.00 m2
REKAPITULASI ANALISA BIAYA KONSTRUKSI
BANGUNAN GEDUNG DAN PERUMAHAN SNI 2002

Analisa Biaya Konstruksi Pekerjaan Persiapan

No Kode Analisa

1 6.1
2 6.2
3 6.3
4 6.4
5 6.5
6 6.6
7 6.7
8 6.8
9 6.9
10 6.10
11 6.11
12 6.12
13 6.13
14 6.14
15 6.15
16 6.16

Analisa Biaya Pekerjaan Tanah

No Kode Analisa

17 6.1
18 6.2
19 6.3
20 6.4
21 6.5
22 6.6
23 6.7
24 6.8
25 6.9
26 6.10
27 6.11
28 6.12
29 6.13
30 6.14
31 6.15
32 6.16
Analisa Biaya Pekerjaan Pondasi

No Kode Analisa

33 6.1
34 6.2
35 6.3
36 6.4
37 6.5
38 6.6
39 6.7
40 6.8
41 6.9
42 6.10
43 6.11
44 6.12
45 6.13
46 6.14
47 6.15
48 6.16
49 6.17
50 6.18

Analisa Biaya Pekerjaan Dinding

No Kode Analisa

51 6.1
52 6.2
53 6.3
54 6.4
55 6.5
56 6.6
57 6.7
58 6.8
59 6.9
60 6.10
61 6.11
62 6.12
63 6.13
64 6.14
65 6.15
66 6.16
67 6.17
68 6.18
69 6.19
70 6.20
71 6.21
72 6.22
73 6.23
74 6.24
75 6.25
76 6.26
77 6.27

Analisa Biaya Pekerjaan Plesteran

No Kode Analisa

78 6.1
79 6.2
80 6.3
81 6.4
82 6.5
83 6.6
84 6.7
85 6.8
86 6.9
87 6.10
88 6.11
89 6.12
90 6.13
91 6.14
92 6.15
93 6.16
94 6.17
95 6.18
96 6.19
97 6.20
98 6.21
99 6.22
100 6.23
101 6.24
102 6.25
103 6.26
104 6.27
105 6.28
106 6.29
107 6.30
108 6.31
109 6.32
110 6.33
111 6.34
112 6.35
113 6.36

Analisa Biaya Pekerjaan Kayu

No Kode Analisa

114 6.1
115 6.2
116 6.3
117 6.4
118 6.5
119 6.6
120 6.7
121 6.8
122 6.9
123 6.10
124 6.11
125 6.12
126 6.13
127 6.14
128 6.15
129 6.16
130 6.17
131 6.18
132 6.19
133 6.20
134 6.21
135 6.22
136 6.23
137 6.24
138 6.25
139 6.26
140 6.27
141 6.28
142 6.29
143 6.30
144 6.31
145 6.32
146 6.33
147 6.34
148 6.35
149 6.36
150 6.37
151 6.38
152 6.39
153 6.40
154 6.41
155 6.42
156 6.43
157 6.44
158 6.45
159 6.46
160 6.47
161 6.48
162 6.49
163 6.50
164 6.51
165 6.52
166 6.53
167 6.54
168 6.55
169 6.56
170 6.57
171 6.58
172 6.59
173 6.60

Analisa Biaya Pekerjaan Beton

174 6.1
175 6.2
176 6.3
177 6.4
178 6.5
179 6.6
180 6.7
181 6.8
182 6.9
183 6.10
184 6.11
185 6.12
186 6.13
187 6.14
188 6.15
189 6.16
190 6.17
191 6.18
192 6.19
193 6.20
194 6.21
195 6.22
196 6.23
197 6.24
198 6.25
199 6.26
200 6.27
201 6.28
202 6.29
203 6.30
204 6.31
205 6.32
206 6.33
207 6.34
208 6.35
209 6.36
210 6.37
211 6.38
212 6.39
213 6.40
214 6.41
215 6.42
216 6.43
217 6.44
218 6.45
219 6.46

Analisa Biaya Konstruksi Pekerjaan Penutup Atap

220 6.1
221 6.2
222 6.3
223 6.4
224 6.5
225 6.6
226 6.7
227 6.8
228 6.9
229 6.10
230 6.11
231 6.12
232 6.13
233 6.14
234 6.15
235 6.16
236 6.17
237 6.18
238 6.19
239 6.20
240 6.21
241 6.22
242 6.23
243 6.24
244 6.25
245 6.26
246 6.27
247 6.28
248 6.29
249 6.30
250 6.31
251 6.32
252 6.33
253 6.34
254 6.35
255 6.36
256 6.37
257 6.38
258 6.39
259 6.40
260 6.41
261 6.42

Analisa Biaya Pekerjaan Langit-langit

262 6.1
263 6.2
264 6.3
265 6.4
266 6.5
267 6.6
268 6.7
269 6.8
270 6.9
271 6.10
272 6.11
273 6.12
274 6.13
275 6.14
276 6.15
277 6.16
278 6.17
279 6.18
280 6.19
281 6.20
282 6.21
283 6.22
284 6.23
285 6.24

Analisa Biaya Pekerjaan Sanitasi

286 6.1
287 6.2
288 6.3
289 6.4
290 6.5
291 6.6
292 6.7
293 6.8
294 6.9
295 6.10
296 6.11
297 6.12
298 6.13
299 6.14
300 6.15
301 6.16
302 6.17
303 6.18
304 6.19
305 6.20
306 6.21
307 6.22
308 6.23
309 6.24
310 6.25
311 6.26
312 6.27
313 6.28
314 6.29
315 6.30
316 6.31
317 6.32
318 6.33
319 6.34
320 6.35
321 6.36

Analisa Biaya Konstruksi Pekerjaan Besi dan Aluminium

322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
REKAPITULASI ANALISA BIAYA KONSTRUKSI
BANGUNAN GEDUNG DAN PERUMAHAN SNI 2002

truksi Pekerjaan Persiapan

Uraian Harga

1 m Pagar sementara dari kayu tinggi 2 meter Rp 649,500.00


1 m Pagar sementara dari seng gelombang tinggi 2 meter Rp 738,300.00
1 m Pagar sementara dari kawat duri tinggi 1.8 meter Rp 148,700.00
1 m' Pengukuran dan pemasangan bowplank Rp 137,900.00
1 m2 Pembuatan kantor sementara dengan lantai plesteran Rp 7,373,500.00
1 m2 Pembuatan gudang semen dan alat-alat Rp 2,076,100.00
1 m2 Pembuatan rumah jaga/konstruksi kayu Rp 2,560,400.00
1 m2 Membersihkan lapangan dan peralatan Rp 64,636.50
Pembuatan bedeng buruh Rp 995,300.00
1 m2 Pembuatan bak adukan ukuran (40x50x20)cm Rp 258,000.00
1 m2 Pembuatan Stegger dari bambu, ukuran (40x50x20) cm Rp 112,900.00
1 m2 Pembuatan jalan sementara Rp 365,200.00
Bongkaran beton bertulang Rp 430,895.38
Bongkaran dinding tembok bata merah Rp 430,895.38
1 m Pasang pagar kawat jaring galvanis, tinggi 1 meter Rp 6,900.00
1 m Pasang pagar pracetak (5x50x213)cm Rp 140,500.00

Uraian Harga

1 m3 Galian tanah biasa sedalam 1 m Rp 27,921.20


1 m3 Galian tanah biasa sedalam 2 m Rp 36,654.38
1 m3 Galian tanah biasa sedalam 3 m Rp 51,253.54
1 m3 Galian tanah Keras sedalam 1 m Rp 43,575.21
1 m3 Galian tanah cadas sedalam 1 m Rp 87,253.75
1 m3 Galian tanah lumpur sedalam 1 m Rp 57,520.20
1 m2 Pekerjaan stripping setinggi 1 m Rp 3,490.15
1 m3 Pembuangan tanah sejauh 150 m Rp 35,971.96
1 m3 Urugan kembali Rp 13,381.51
1 m3 Pemadatan tanah Rp 34,901.50
1 m3 Urugan pasir Rp 147,200.00
1 m3 Lapisan pudel campuran 1 Kp : 3 Ps : 7 TL Rp 208,800.00
1 m3 Lapisan pudel campuran 1 Kp : 5 TL Rp 196,500.00
1 m3 Pemasangan lapisan ijuk Rp 10,500.00
1 m3 Urugan sirtu Rp 214,300.00
1 m3 Pembuatan jalan sementara, tebal 25 cm Rp 165,400.00
aan Pondasi

Uraian Harga

1 m3 Pasang pondasi batu kali, 1 Pc : 1 Ps Rp 985,500.00


1 m3 Pasang pondasi batu kali, 1 Pc : 2 Ps Rp 948,300.00
1 m3 Pasang pondasi batu kali, 1 Pc : 2.5 Ps Rp 1,119,800.00
1 m3 Pasang pondasi batu kali, 1 Pc : 3 Ps Rp 859,000.00
1 m3 Pasang pondasi batu kali, 1 Pc : 4 Ps Rp 805,500.00
1 m3 Pasang pondasi batu kali, 1 Pc : 5 Ps Rp 768,400.00
1 m3 Pasang pondasi batu kali, 1 Pc : 6 Ps Rp 742,300.00
1 m3 Pasang pondasi batu kali, 1 Pc : 8 Ps Rp 703,300.00
1 m3 Pasang pondasi batu kali, 1 Kp : 1 Sm :1 Ps Rp 565,500.00
1 m3 Pasang pondasi batu kali, 1 Kp : 1 Sm :1 Ps Rp 565,500.00
1 m3 Pasang pondasi batu kali, 1 Pc : 1/4 Kp :4 Ps Rp 804,300.00
1 m3 Pasang pondasi batu kali, 1 Pc : 3 Kp : 10 Ps Rp 648,800.00
1 m3 Pasang pondasi batu kali, 1/4 Pc : 1 Kp : 4 Ps Rp 533,900.00
1 m3 Pasang pondasi batu kosong Rp 358,400.00
1 m3 Pasang pondasi siklop 40% batu kali Rp 2,125,400.00
1 m3 Pasang pondasi sumuran diameter 100cm Rp 922,500.00
Pembuatan tiang pancang (40x40) cm beton bertulang Rp 1,310,400.00
Pembuatan tiang pancang (35x35) cm beton bertulang Rp 1,029,700.00

aan Dinding

Uraian Harga

1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 1 Ps Rp 341,500.00


1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 2 Ps Rp 313,700.00
1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 3 Ps Rp 299,400.00
1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 4 Ps Rp 290,100.00
1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 5 Ps Rp 284,800.00
1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 6 Ps Rp 284,800.00
1 m2 Pasangan batu bata tebal 1 bata. 1 Pc : 3 Kp : 10 Ps Rp 265,300.00
1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 1 Ps Rp 163,400.00
1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 2 Ps Rp 132,600.00
1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 3 Ps Rp 126,000.00
1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 4 Ps Rp 122,100.00
1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 5 Ps Rp 119,600.00
1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 6 Ps Rp 118,200.00
1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 8 Ps Rp 115,600.00
1 m2 Pasangan batu bata tebal 1/2 bata. 1 Pc : 3 Kp : 10 Ps Rp 131,600.00
1 m2 Pasangan batu bata tebal 1/2 bata. 1 Kp : 1 Sm : 1 Ps Rp 101,200.00
1 m2 Pasangan batu bata tebal 1/2 bata. 1 Kp : 1 Sm : 2 Ps Rp 102,700.00
1 m2 Pasangan dinding Hollowblock (HB.20) Rp 130,100.00
1 m2 Pasangan dinding Hollowblock (HB.15) Rp 116,300.00
1 m2 Pasangan dinding Hollowblock (HB.10) Rp 110,200.00
1 m2 Pasangan dinding Conblock (CB.20) Rp 174,600.00
1 m2 Pasangan dinding Conblock (CB.15) Rp 107,700.00
1 m2 Pasangan dinding Conblock (CB.10) Rp 127,600.00
1 m2 Pasangan dinding lantai Rp 84,300.00
1 m2 Pasangan dinding roster/terawang (12X11x24) cm Rp 53,600.00
1 m2 Pasangan bata berongga ukuran (5x11x24) cm Rp 230,000.00
1 m2 Pasangan anyaman bambu, rangka kayu Rp 100,600.00

aan Plesteran

Uraian Harga

1 m2 Plesteran 1 Pc : 1 Ps , tebal 15 mm Rp 49,100.00


1 m2 Plesteran 1 Pc : 2 Ps , tebal 15 mm Rp 43,100.00
1 m2 Plesteran 1 Pc : 3 Ps , tebal 15 mm Rp 40,300.00
1 m2 Plesteran 1 Pc : 4 Ps , tebal 15 mm Rp 38,500.00
1 m2 Plesteran 1 Pc : 5 Ps , tebal 15 mm Rp 14,000.00
1 m2 Plesteran 1 Pc : 6 Ps , tebal 15 mm Rp 36,800.00
1 m2 Plesteran 1 Pc : 8 Ps , tebal 15 mm Rp 35,600.00
1 m2 Plesteran 1 Pc : 0.5 Kp : 3 Ps , tebal 15 mm Rp 38,300.00
1 m2 Plesteran 1 Pc : 3 Kp : 10 Ps , tebal 15 mm Rp 32,600.00
1 m2 Plesteran 0.5 Pc : 1 Kp : 4 Ps , tebal 15 mm Rp 35,100.00
1 m2 Plesteran 1 Kp : 1 Sm : 1 Ps , tebal 15 mm Rp 29,100.00
1 m2 Plesteran 1 Kp : 1 Sm : 2 Ps , tebal 15 mm Rp 30,000.00
1 m2 Plesteran 1 Pc : 2 Ps , tebal 20 mm Rp 60,800.00
1 m2 Plesteran 1 Pc : 3 Ps , tebal 20 mm Rp 56,000.00
1 m2 Plesteran 1 Pc : 4 Ps , tebal 20 mm Rp 53,100.00
1 m2 Plesteran 1 Pc : 5 Ps , tebal 20 mm Rp 51,000.00
1 m2 Plesteran 1 Pc : 6 Ps , tebal 20 mm Rp 49,700.00
1 m2 Plesteran 1 Kp : 1 Sm : 2 Ps , tebal 20 mm Rp 38,600.00
1 m2 Plesteran 1 Pc : 2 Ps , tebal 25 mm Rp 64,100.00
1 m2 Plesteran 1 Pc : 3 Ps , tebal 25 mm Rp 61,700.00
1 m2 Plesteran 1 Pc : 4 Ps , tebal 25 mm Rp 58,700.00
1 m2 Plesteran 1 Pc : 5 Ps , tebal 25 mm Rp 78,400.00
1 m2 Plesteran 1 Pc : 2 Ps , tebal 30 mm Rp 78,400.00
1 m2 Plesteran 1 Pc : 3 Ps , tebal 30 mm Rp 72,300.00
1 m2 Plesteran 1 Pc : 4 Ps , tebal 30 mm Rp 68,500.00
1 m2 Plesteran 1 Pc : 5 Ps , tebal 30 mm Rp 64,200.00
1 m2 Berapen 1 Pc : 3 Ps , tebal 30 mm Rp 30,300.00
1 m2 Berapen 1 Pc : 5 Ps , tebal 15 mm Rp 28,500.00
1 m2 Berapen 1 Pc : 2 Ps , tebal 15 mm Rp 53,200.00
1 m2 Berapen 1 Pc : 3 Ps , tebal 15 mm Rp 50,300.00
1 m2 Plesteran Skoning 1 Pc : 2 Ps Rp 11,900.00
1 m2 Plesteran Granito, 1 Pc warna : 2 Granito, tebal 10 mm Rp 6,000.00
1 m2 Plesteran Granito, 1 Pc warna : 2 Batu teraso, tebal 10 mm Rp 50,700.00
1 m2 Plesteran Ciprat, 1 Pc warna : 2 Ps Rp 35,100.00
1 m2 Plesteran Siar, 1 Pc warna : 2 Ps Rp 25,500.00
1 m2 Plesteran waterproof batacote 3 lapis Rp 40,900.00

Uraian Harga

1 m2 Pasang kusen pintu dan jendela kayu Rp 10,963,400.00


1 m2 Pasang kusen pintu dan jendela kayu kamper Rp 9,836,400.00
1 m2 Pasang kusen pintu dan jendela kayu borneo Rp 9,836,400.00
1 m2 Pasang kusen pintu dan jendela kayu damar laut Rp 14,976,400.00
1 m2 Pasang pintu klamp kayu kamper Rp 357,400.00
1 m2 Pasang pintu klamp kayu borneo Rp 357,400.00
1 m2 Pasang pintu panel kayu jati Rp 817,400.00
1 m2 Pasang pintu panel kayu kamper Rp 312,700.00
1 m2 Pasang pintu dan jendela kaca kayu jati Rp 691,700.00
1 m2 Pasang pintu dan jendela kaca kayu kamper Rp 473,100.00
1 m2 Pasang pintu dan jendela kaca kayu borneo Rp 473,100.00
1 m2 Pasang pintu dan jendela jalusi kayu jati Rp 1,195,600.00
1 m2 Pasang pintu dan jendela jalusi kayu kamper Rp 816,400.00
1 m2 Pasang pintu plywood rangkap, rangka kayu jati Rp 613,200.00
1 m2 Pasang pintu plywood rangkap, rangka kayu kamper Rp 490,800.00
1 m2 Pasang jalusi mati kusen kayu jati Rp 991,400.00
1 m2 Pasang jalusi mati kusen kayu kamper Rp 616,600.00
1 m2 Pasang jalusi mati kusen kayu borneo Rp 490,800.00
1 m2 Pasang pintu teakwood rangkap, rangka kayu jati Rp 485,300.00
1 m2 Pasang pintu teakwood rangkap, rangka kayu kamper Rp 369,500.00
1 m2 Pasang pintu plywood & formika, rangka kayu jati Rp 619,900.00
1 m2 Pasang pintu plywood & formika, rangka kayu kamper Rp 372,600.00
1 m2 Pasang pintu teakwood & formika, rangka kayu jati Rp 369,500.00
1 m2 Pasang pintu teakwood & formika, rangka kayu kamper (divernis) Rp 450,900.00
1 m2 Pasang pintu formika double, rangka kayu jati Rp 705,300.00
1 m2 Pasang pintu formika double, rangka kayu kamper Rp 582,800.00
1 m3 Pasang konstruksi kuda-kuda kayu jati Rp 14,601,500.00
1 m3 Pasang konstruksi kuda-kuda kayu kamper Rp 2,045,800.00
1 m3 Pasang konstruksi kuda-kuda kayu borneo Rp 9,050,600.00
1 m3 Pasang konstruksi kuda-kuda kayu kruing Rp 9,050,600.00
1 m3 Pasang kaso + reng genteng kodok kayu kamper Rp 96,500.00
1 m3 Pasang kaso + reng genteng kodok kayu borneo Rp 96,500.00
1 m3 Pasang kaso + reng genteng monier kayu jati Rp 179,900.00
1 m3 Pasang kaso + reng genteng monier kayu kamper Rp 109,200.00
1 m3 Pasang kaso + reng genteng beton kayu borneo Rp 109,200.00
1 m3 Pasang kaso + reng atap sirap kayu kamper Rp 1,075,300.00
1 m3 Pasang kaso + reng atap sirap kayu borneo Rp 1,075,300.00
1 m2 Pasang rangka langit-langit ( 1 x 1 ) m, kayu jati Rp 180,900.00
1 m2 Pasang rangka langit-langit ( 1 x 1 ) m, kayu kamper Rp 43,900.00
1 m2 Pasang rangka langit-langit ( 1 x 1 ) m, kayu borneo Rp 120,400.00
1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu jati Rp 308,900.00
1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu kamper Rp 192,900.00
1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu borneo Rp 192,900.00
1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu jati Rp 364,000.00
1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu kamper Rp 55,800.00
1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu borneo Rp 227,800.00
1 m Pasang listplank ( 3 x 20 ) cm, kayu jati Rp 118,400.00
1 m Pasang listplank ( 3 x 20 ) cm, kayu kamper Rp 73,400.00
1 m Pasang listplank ( 3 x 20 ) cm, kayu jati Rp 168,900.00
1 m Pasang listplank ( 3 x 30 ) cm, kayu kamper Rp 100,200.00
1 m Pasang listplank 2 x ( x 30 ) cm, kayu kamper Rp 135,300.00
1 m Pasang listplank 2 x ( 3 x 30 ) cm, kayu kamper Rp 77,300.00
1 m Pasang listplank 2 x ( 2 x 30 ) cm, kayu borneo Rp 78,600.00
1 m2 Pasang rangka dinding pemisah kayu kamper Rp 232,500.00
1 m2 Pasang rangka dinding pemisah kayu borneo Rp 232,500.00
1 m2 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper Rp 232,500.00
1 m2 Pasang dinding pemisah plywood rangkap, rangka kayu kamper Rp 371,600.00
1 m2 Pasang dinding lambriziring dari papan jati Rp 1,104,200.00
1 m2 Pasang plywood tebal 4 mm, untuk diding Rp 61,500.00
1 m Pasang list plafond kayu profil Rp 6,689,800.00

1 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr Rp 687,800.00


1 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 6 Kr Rp 687,800.00
1 m3 Membuat beton tumbuk, 1 Pc : 4 Ps : 6 Kr Rp 627,400.00
1 m3 Membuat lantai kerja beton tumbuk, 1 Pc : 3 Ps : 5 Kr Rp 131,300.00
1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr Rp 692,900.00
1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 4 Kr Rp 776,100.00
1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 2.5 Kr Rp 864,700.00
1 m3 Membuat beton bertulang, 1 Pc : 1.5 Ps : 3 Kr Rp 823,700.00
1 m3 Membuat beton bertulang, 1 Pc : 1.5 Ps : 2.5 Kr Rp 269,400.00
1 m3 Membuat beton bertulang, 1 Pc : 1 Ps : 2 Kr Rp 262,300.00
1 m3 Membuat tiang pancang pretressed beton Rp 952,800.00
1 m3 Membuat beton dengan puzzith 100 XR Rp 809,400.00
1 m3 Membuat beton bertulang 1 Pc : 2 Ps : 3 Kr Rp 983,100.00
1 m3 Membuat beton bertulang 1 Pc : 2 Ps : 4 Kr Rp 926,700.00
1 m3 Membuat beton bertulang 1 Pc : 1.5 Ps : 3 Kr Rp 413,000.00
1 m3 Membuat beton bertulang 1 Pc : 1.5 Ps : 2.5 Kr Rp 398,800.00
1 m3 Membuat beton bertulang 1 Pc : 1 Ps : 1 Kr Rp 349,200.00
1 m3 Membuat beton kedap air dengan storox - 100 Rp 1,068,800.00
1 m3 Memasang waterstop lebar 150 mm Rp 6,200.00
1 m3 Memasang waterstop lebar 200 mm Rp 6,200.00
1 m3 Memasang waterstop lebar 230 mm Rp 36,100.00
1 m3 Memasang waterstop lebar 250 mm Rp 36,100.00
1 m3 Memasang waterstop lebar 300 mm Rp 36,100.00
1 m3 Memasang waterstop lebar 320 mm Rp 36,100.00
1 Kg pembesian dengan besi polos atau besi ulir Rp 379,900.00
1 Kg Kabel presstressed polos/strands Rp 1,100.00
1 Kg Jaring kawat baja Rp 23,500.00
1 m2 Pasang bekisting untuk pondasi Rp 306,300.00
1 m2 Pasang bekisting untuk sloof Rp 338,100.00
1 m2 Pasang bekisting untuk kolom Rp 501,800.00
1 m2 Pasang bekisting untuk balok Rp 1,683,700.00
1 m2 Pasang bekisting untuk lantai Rp 1,683,700.00
1 m2 Pasang bekisting untuk dinding Rp 759,800.00
1 m2 Pasang bekisting untuk tangga Rp 625,800.00
1 m3 membuat beton dengan mutu K 225 Rp 1,278,700.00
1 m3 membuat beton dengan mutu K 275 Rp 1,290,900.00
1 m2 Pasang jembatan cor Rp 248,600.00
1 m3 Membuat pondasi beton bertulang (150 kg besi + bekisting) Rp 6,056,300.00
1 m3 Membuat pondasi beton bertulang (200 kg besi + bekisting) Rp 6,056,300.00
1 m3 Membuat kolom beton bertulang (300 kg besi + bekisting) Rp 13,433,600.00
1 m3 Membuat balok beton bertulang (200 kg besi + bekisting) Rp 10,306,100.00
1 m3 Membuat balok beton bertulang (150 kg besi + bekisting) Rp 11,004,500.00
1 m3 Membuat dinding beton bertulang (150 kg besi + bekisting) Rp 10,287,500.00
1 m3 Membuat tangga beton bertulang (200 kg besi + bekisting) Rp 9,294,300.00
1 m' Membuat kolom penguat beton bertulang (11 x 11) cm Rp 874,100.00
1 m' Membuat ring balok beton bertulang (10 x 15) cm Rp 171,100.00

uksi Pekerjaan Penutup Atap

1 m2 Pasang atap genteng palentong kecil Rp 17,200.00


1 m2 Pasang atap genteng kodok/glazzur Rp 17,200.00
1 m2 Pasang atap genteng palentong super / besar Rp 17,200.00
1 m2 Pasang genteng bubung palentong Rp 60,500.00
1 m Pasang bubung genteng kodok glazuur Rp 60,500.00
1 m Pasang bubung genteng palentong besar Rp 60,500.00
1 m2 Pasang roof light fibreglass ( 180 x 90 ) cm Rp 17,000.00
1 m2 Pasang atap asbes gelombang ( 2.5 x 0.92 m ) x 5 mm Rp 16,600.00
1 m2 Pasang atap asbes gelombang ( 2.25 x 0.92 m ) x 5 mm Rp 16,600.00
1 m2 Pasang atap asbes gelombang ( 2.00 x 0.92 m ) x 5 mm Rp 16,000.00
1 m2 Pasang atap asbes gelombang ( 1.80 x 0.92 m ) x 5 mm Rp 16,000.00
1 m2 Pasang atap asbes gelombang ( 3.00 x 1.05 m ) x 4 mm Rp 16,000.00
1 m2 Pasang atap asbes gelombang ( 2.70 x 1.05 m ) x 4 mm Rp 16,000.00
1 m2 Pasang atap asbes gelombang ( 2.40 x 1.05 m ) x 4 mm Rp 15,700.00
1 m2 Pasang atap asbes gelombang ( 2.10 x 1.05 m ) x 4 mm Rp 15,700.00
1 m2 Pasang atap asbes gelombang ( 1.5 x 1.05 m ) x 4 mm Rp 15,700.00
1 m2 Pasang atap asbes gelombang ( 3.00 x 1.08 m ) x 6 mm Rp 15,700.00
1 m2 Pasang atap asbes gelombang ( 2.70 x 1.08 m ) x 6 mm Rp 15,700.00
1 m2 Pasang atap asbes gelombang ( 2.40 x 1.08 m ) x 6 mm Rp 15,700.00
1 m2 Pasang atap asbes gelombang ( 2.10 x 1.08 m ) x 6 mm Rp 15,700.00
1 m2 Pasang atap asbes gelombang (1.80x 1.08 m ) x 6 mm Rp 15,700.00
1 m' Pasang bubung stel gelombang 0.92 m Rp 17,600.00
1 m' Pasang nok stel gelombang 1.05 m Rp 17,600.00
1 m' Pasang nok stel gelombang 1.08 m Rp 17,600.00
1 m' Pasang nok paten 0.92 m Rp 17,900.00
1 m' Pasang nok paten 1.05 m Rp 17,900.00
1 m' Pasang nok paten 1.08 m Rp 17,900.00
1 m' Pasang nok stel rata 0.92 m Rp 21,000.00
1 m' Pasang nok stel rata 1.05 m Rp 17,900.00
1 m2 Pasang atap genteng beton Rp 149,100.00
1 m2 Pasang atap genteng aspal Rp 99,500.00
1 m2 Pasang atap genteng metal Rp 82,000.00
1 m2 Pasang atap sirap Rp 58,800.00
1 m' Pasang nok genteng beton Rp 70,100.00
1 m' Pasang nok genteng aspal Rp 56,400.00
1 m' Pasang nok genteng metal Rp 32,300.00
1 m' Pasang nok `sirap Rp 90,600.00
1 m2 Pasang atap seng gelombang Rp 44,500.00
1 m2 Pasang atap nok seng Rp 39,700.00
1 m2 Pasang atap aluminium Rp 188,200.00
1 m2 Pasang nok aluminium Rp 99,900.00
1 m2 Pasang nok aluminium foil sisalation Rp 14,700.00

aan Langit-langit

1 m2 Langit - langit asbes ( 1.00 x 1.00 ) m, tebal 6 mm Rp 9,100.00


1 m2 Langit - langit asbes ( 1.00 x 1.00 ) m, tebal 5 mm Rp 9,100.00
1 m2 Langit - langit asbes ( 1.00 x 1.00 ) m, tebal 4 mm Rp 9,100.00
1 m2 Langit - langit asbes ( 1.00 x 1.00 ) m, tebal 3.5 mm Rp 9,100.00
1 m2 Langit - langit akustik ( 30 x 30 ) cm Rp 17,000.00
1 m2 Langit - langit akustik ( 30 x 60 ) cm Rp 17,000.00
1 m2 Langit - langit akustik ( 60 x 120 ) cm Rp 17,000.00
1 m2 Langit - langit plywood ( 30 x 60 ) cm, tebal 4 mm Rp 61,300.00
1 m2 Langit - langit plywood ( 30 x 60 ) cm, tebal 6 mm Rp 75,700.00
1 m2 Langit - langit plywood ( 60 x 120 ) cm, tebal 4 mm Rp 63,200.00
1 m2 Langit - langit plywood ( 60 x 120 ) cm, tebal 6 mm Rp 78,300.00
1 m2 Langit - langit teakwood ( 30 x 60 ) cm, tebal 4 mm Rp 15,200.00
1 m2 Langit - langit teakwood ( 60 x 120 ) cm, tebal 4 mm Rp 15,200.00
1 m2 Langit - langit lat kayu jati Rp 375,500.00
1 m2 Langit - langit lat kayu ramin Rp 225,600.00
1 m2 Langit - langit lat kayu kamper Rp 225,600.00
1 m2 Langit - langit soft board Rp 46,700.00
1 m2 Langit - langit akustik 60 x 120 cm + rangka alumunium Rp 59,300.00
1 m' List Langit - langit kayu profil Rp 8,700.00
1 m2 Langit - langit asbes (1.00 x 1.00) m, tebal 3.2 mm, rangka kayu borneo Rp 121,300.00
1 m2 Langit - langit plywood 4 mm + rangka kayu borneo Rp 275,800.00
1 m2 Langit - langit akustik (30 x 60) cm + rangka kayu borneo Rp 204,500.00
1 m2 Langit - langit akustik (30 x 30) cm + rangka kayu borneo Rp 240,100.00
1 m2 Langit - langit gypsum board, tebal 9 mm Rp 11,400.00

Memasang 1 buah kloset duduk/monoblok Rp 2,857,900.00


Memasang 1 buah kloset jongkok porselen Rp 2,115,000.00
Memasang 1 buah kloset jongkok teraso Rp 1,991,800.00
Memasang 1 buah urinoir Rp 1,240,100.00
Memasang 1 buah wastafel Rp 808,500.00
Memasang 1 buah bak mandi teraso volume 0.30 m3 Rp 220,600.00
Memasang 1 buah bak mandi fibreglass volume 0.30 m3 Rp 953,000.00
Memasang 1 buah bak mandi batu bata volume 0.30 m3 Rp 791,000.00
Memasang 1 buah badkip porselen Rp 180,600.00
Memasang 1 buah bak beton volume 1 m3 air Rp 1,508,500.00
Memasang 1 buah bak fibreglass volume 1 m3 air Rp 925,600.00
Memasang 1 m' pipa penyalur air limbah jenis pipa tanah, diameter 15 cm Rp 10,900.00
Memasang 1 m' pipa penyalur air limbah jenis pipa tanah, diameter 20 cm Rp 14,300.00
Memasang 1 m' pipa beton, diameter 15 - 20 cm Rp 34,100.00
Memasang 1 m' pipa beton, diameter 30 - 100 cm Rp 34,100.00
Memasang 1 buah bak kontrol pasangan batu bata ukuran (30x30), tinggi 35 cm Rp 415,100.00
Memasang 1 buah bak kontrol pasangan batu bata ukuran (45x45), tinggi 50 cm Rp 332,500.00
Memasang 1 buah bak kontrol pasangan batu bata ukuran (60x60), tinggi 65 cm Rp 546,700.00
Memasang 1 m' pipa galvanis diameter 1/2 " Rp 128,500.00
Memasang 1 m' pipa galvanis diameter 3/4 " Rp 163,900.00
Memasang 1 m' pipa galvanis diameter 1 " Rp 201,200.00
Memasang 1 m' pipa galvanis diameter 1.5 " Rp 231,200.00
Memasang 1 m' pipa galvanis diameter 3 " Rp 24,800.00
Memasang 1 m' pipa galvanis diameter 4" Rp 31,100.00
Memasang 1 m' pipa PVC tipe AW diameter 1/2" Rp 110,700.00
Memasang 1 m' pipa PVC tipe AW diameter 3/4" Rp 115,400.00
Memasang 1 m' pipa PVC tipe AW diameter 1" Rp 213,200.00
Memasang 1 m' pipa PVC tipe AW diameter 1.5" Rp 8,300.00
Memasang 1 m' pipa PVC tipe AW diameter 2" Rp 422,100.00
Memasang 1 m' pipa PVC tipe AW diameter 2.5" Rp 8,300.00
Memasang 1 m' pipa PVC tipe AW diameter 3" Rp 633,200.00
Memasang 1 m' pipa PVC tipe AW diameter 4" Rp 838,100.00
Memasang 1 buah bak cuci piring stainless steel Rp 380,200.00
Memasang 1 buah bak cuci piring teraso Rp 90,100.00