Laporan Konsultan Pagar
Laporan Konsultan Pagar
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 21 November S/D 25 Desember 2022
VOLUME : 1 (SATU) PAKET BULAN KE : Satu
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 NOMOR KONTRAK : CV. MEGA KONSULTAN
I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 - - - 100.00 2.86 5,050,000.00 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 - - - 100.00 25.47 44,922,952.70 100.00 25.47 44,922,952.70
III. PEKERJAAN BETON 61,763,489.27 35.02 - - - 100.00 35.02 61,763,489.27 100.00 35.02 61,763,489.27
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 - - - 100.00 29.08 51,289,901.30 100.00 29.08 51,289,901.30
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - 100.00 7.56 13,325,558.76 100.00 7.56 13,325,558.76
NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)
1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09
I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 100.00 2.86 5,050,000.00 - - - 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 85.21 21.71 38,279,114.30 14.79 3.77 6,643,838.40 100.00 25.47 44,922,952.70
III. PEKERJAAN BETON 61,763,489.27 35.02 100.00 35.02 61,763,489.27 - - - 100.00 35.02 61,763,489.27
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 71.80 20.88 36,827,597.71 28.20 8.20 14,462,303.59 100.00 29.08 51,289,901.30
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - 100.00 7.56 13,325,558.76 100.00 7.56 13,325,558.76
A REAL COST 176,351,902.03 100.00 80.48 141,920,201.28 19.52 34,431,700.75 100.00 176,351,902.03
B PPn ( 11% ) 19,398,709.22 15,611,222.14 3,787,487.08 19,398,709.22
C TOTAL HARGA 195,750,611.26 157,531,423.43 38,219,187.83 195,750,611.26
D DIBULATKAN 195,750,000.00 157,530,000.00 38,210,000.00 195,750,000.00
NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)
1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09
I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 100.00 2.86 5,050,000.00 - - - 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 85.21 21.71 38,279,114.30 - - - 85.21 21.71 38,279,114.30
III. PEKERJAAN BETON 61,763,489.27 35.02 100.00 35.02 61,763,489.27 - - - 100.00 35.02 61,763,489.27
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 26.08 7.58 13,374,797.94 45.73 13.30 23,452,799.77 71.80 20.88 36,827,597.71
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - - - - - - -
A REAL COST 176,351,902.03 100.00 67.18 118,467,401.51 13.30 23,452,799.77 80.48 141,920,201.28
B PPn ( 11% ) 19,398,709.22 13,031,414.17 2,579,807.97 15,611,222.14
C TOTAL HARGA 195,750,611.26 131,498,815.68 26,032,607.74 157,531,423.43
D DIBULATKAN 195,750,000.00 131,490,000.00 26,030,000.00 157,530,000.00
NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)
1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09
I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 100.00 2.86 5,050,000.00 - - - 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 85.21 21.71 38,279,114.30 - - - 85.21 21.71 38,279,114.30
III. PEKERJAAN BETON 61,763,489.27 35.02 53.55 18.75 33,074,468.94 46.45 16.27 28,689,020.33 100.00 35.02 61,763,489.27
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 9.53 2.77 4,889,015.67 16.54 4.81 8,485,782.26 26.08 7.58 13,374,797.94
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - - - - - - -
A REAL COST 176,351,902.03 100.00 46.10 81,292,598.92 21.08 37,174,802.59 67.18 118,467,401.51
B PPn ( 11% ) 19,398,709.22 8,942,185.88 4,089,228.29 13,031,414.17
C TOTAL HARGA 195,750,611.26 90,234,784.80 41,264,030.88 131,498,815.68
D DIBULATKAN 195,750,000.00 90,230,000.00 41,260,000.00 131,490,000.00
NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)
1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09
I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 100.00 2.86 5,050,000.00 - - - 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 85.21 21.71 38,279,114.30 - - - 85.21 21.71 38,279,114.30
III. PEKERJAAN BETON 61,763,489.27 35.02 - - - 53.55 18.75 33,074,468.94 53.55 18.75 33,074,468.94
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 - - - 9.53 2.77 4,889,015.67 9.53 2.77 4,889,015.67
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - - - - - - -
A REAL COST 176,351,902.03 100.00 24.57 43,329,114.30 21.53 37,963,484.62 46.10 81,292,598.92
B PPn ( 11% ) 19,398,709.22 4,766,202.57 4,175,983.31 8,942,185.88
C TOTAL HARGA 195,750,611.26 48,095,316.88 42,139,467.92 90,234,784.80
D DIBULATKAN 195,750,000.00 48,090,000.00 42,130,000.00 90,230,000.00
NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)
1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09
I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 - - - 100.00 2.86 5,050,000.00 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 - - - 85.21 21.71 38,279,114.30 85.21 21.71 38,279,114.30
III. PEKERJAAN BETON 61,763,489.27 35.02 - - - - - - - - -
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 - - - - - - - - -
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - - - - - - -
NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)
1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09