REKAPITULASI BOBOT KEMAJUAN PEKERJAAN BULANAN

PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 21 November S/D 25 Desember 2022
VOLUME : 1 (SATU) PAKET BULAN KE : Satu
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 NOMOR KONTRAK : CV. MEGA KONSULTAN

S/D Bulan Lalu Bulan Ini S/D Bulan Ini


NO. URAIAN DAN JENIS PEKERJAAN JUMLAH HARGA Bobot (%) Bobot Bobot Bobot Bobot Bobot Bobot
Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga
(%) g(%) (%) g(%) (%) g(%)
1 2 3 4 5 6 7 8 9 10 11 12 13

I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 - - - 100.00 2.86 5,050,000.00 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 - - - 100.00 25.47 44,922,952.70 100.00 25.47 44,922,952.70
III. PEKERJAAN BETON 61,763,489.27 35.02 - - - 100.00 35.02 61,763,489.27 100.00 35.02 61,763,489.27
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 - - - 100.00 29.08 51,289,901.30 100.00 29.08 51,289,901.30
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - 100.00 7.56 13,325,558.76 100.00 7.56 13,325,558.76

A REAL COST 176,351,902.03 100.00 - - 100.00 176,351,902.03 100.00 176,351,902.03


B PPn ( 11% ) 19,398,709.22 - 19,398,709.22 19,398,709.22
C TOTAL HARGA 195,750,611.26 - 195,750,611.26 195,750,611.26
D DIBULATKAN 195,750,000.00 - 195,750,000.00 195,750,000.00

Welala, 25 Desember 2022


Mengetahui / Menyetujui :
Pejabat Pembuat Komitmen (PPK) Dibuat Oleh
Rumah Sakit Umum Daerah (RSUD) Konsultan Pengawas
Kab. Kolaka Timur CV. MEGA KONSULTAN

DR. ABDUL MUNIR ABUBAKAR SYAMSUL ALAM, ST


Nip. 19830324 201001 1 001 Direktur
BOBOT KEMAJUAN PEKERJAAN BULANAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 21 November S/D 25 Desember 2022
VOLUME : 1 (SATU) PAKET BULAN KE : Satu
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 KONSULTAN PENGAWAS : CV. MEGA KONSULTAN

S/D Bulan Lalu Bulan Ini S/D Bulan Ini

NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)

1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09

Jumlah 5,050,000.00 2.86 - - 5,050,000.00 2.86 5,050,000.00 2.86


II. PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi M3 38.85 85,937.00 3,338,652.45 1.89 - - - - 38.85 100.00 3,338,652.45 1.89 38.85 100.00 3,338,652.45 1.89
2 Pek. Batu Kosong (Aanstamping) M3 11.66 541,084.00 6,306,334.02 3.58 - - - - 11.66 100.00 6,306,334.02 3.58 11.66 100.00 6,306,334.02 3.58
3 Pek. Pondasi Batu Gunung camp. 1Pc 5Psr M3 29.14 974,990.00 28,408,771.13 16.11 - - - - 29.14 100.00 28,408,771.13 16.11 29.14 100.00 28,408,771.13 16.11
4 Pek. Urugan kembali bekas Galian tanah M3 7.28 30,937.00 225,356.71 0.13 - - - - 7.28 100.00 225,356.71 0.13 7.28 100.00 225,356.71 0.13
5 Pek. Plesteran Pondasi camp. 1Pc : 3Psr M2 88.80 74,818.00 6,643,838.40 3.77 - - - - 88.80 100.00 6,643,838.40 3.77 88.80 100.00 6,643,838.40 3.77

Jumlah 44,922,952.70 25.47 - - 44,922,952.70 25.47 44,922,952.70 25.47


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
III. PEKERJAAN BETON
1 Pek. Sloef Beton 15 x 20 cm (SF)
- Cor Beton M3 2.22 1,095,378.00 2,426,716.63 1.38 - - - - 2.22 100.00 2,426,716.63 1.38 2.22 100.00 2,426,716.63 1.38
- Besi Beton Kg 448.44 18,841.90 8,449,461.64 4.79 - - - - 448.44 100.00 8,449,461.64 4.79 448.44 100.00 8,449,461.64 4.79
- Bekisting M2 30.30 203,379.00 6,162,383.70 3.49 - - - - 30.30 100.00 6,162,383.70 3.49 30.30 100.00 6,162,383.70 3.49
2 Pek. Kolom Pagar 25x25 cm (T=180)
- Cor Beton M3 1.61 1,095,378.00 1,760,031.46 1.00 - - - - 1.61 100.00 1,760,031.46 1.00 1.61 100.00 1,760,031.46 1.00
- Besi Beton Kg 126.48 18,841.90 2,383,040.98 1.35 - - - - 126.48 100.00 2,383,040.98 1.35 126.48 100.00 2,383,040.98 1.35
- Kolom Pagar Jadi Bh 138.00 70,000.00 9,660,000.00 5.48 - - - - 138.00 100.00 9,660,000.00 5.48 138.00 100.00 9,660,000.00 5.48
- Kepala Kolom Pagar Jadi Bh 23.00 70,000.00 1,610,000.00 0.91 - - - - 23.00 100.00 1,610,000.00 0.91 23.00 100.00 1,610,000.00 0.91
3 Pek. Kolom Gerbang 25x25 cm (T=150)
- Cor Beton M3 0.23 1,095,378.00 248,636.20 0.14 - - - - 0.23 100.00 248,636.20 0.14 0.23 100.00 248,636.20 0.14
- Besi Beton Kg 18.33 18,841.90 345,368.26 0.20 - - - - 18.33 100.00 345,368.26 0.20 18.33 100.00 345,368.26 0.20
- Kolom Pagar Jadi Bh 20.00 70,000.00 1,400,000.00 0.79 - - - - 20.00 100.00 1,400,000.00 0.79 20.00 100.00 1,400,000.00 0.79
4 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 1.00 1,095,378.00 1,092,256.81 0.62 - - - - 1.00 100.00 1,092,256.81 0.62 1.00 100.00 1,092,256.81 0.62
- Besi Beton Kg 120.58 18,841.90 2,271,943.11 1.29 - - - - 120.58 100.00 2,271,943.11 1.29 120.58 100.00 2,271,943.11 1.29
- Bekisting ( 3 x Pakai ) M2 21.60 119,968.67 2,591,323.20 1.47 - - - - 21.60 100.00 2,591,323.20 1.47 21.60 100.00 2,591,323.20 1.47
5 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 0.07 1,095,378.00 79,577.46 0.05 - - - - 0.07 100.00 79,577.46 0.05 0.07 100.00 79,577.46 0.05
- Besi Beton Kg 17.53 18,841.90 330,309.81 0.19 - - - - 17.53 100.00 330,309.81 0.19 17.53 100.00 330,309.81 0.19
- Bekisting ( 3 x Pakai ) M2 1.87 119,968.67 224,581.34 0.13 - - - - 1.87 100.00 224,581.34 0.13 1.87 100.00 224,581.34 0.13
6 Pek. Kolom Pagar 12x12 cm
- Cor Beton M3 0.37 1,095,378.00 402,164.85 0.23 - - - - 0.37 100.00 402,164.85 0.23 0.37 100.00 402,164.85 0.23
- Besi Beton Kg 90.91 18,841.90 1,712,963.35 0.97 - - - - 90.91 100.00 1,712,963.35 0.97 90.91 100.00 1,712,963.35 0.97
- Bekisting ( 3 x Pakai ) M2 9.47 119,968.67 1,135,863.34 0.64 - - - - 9.47 100.00 1,135,863.34 0.64 9.47 100.00 1,135,863.34 0.64
7 Pek. Ring Balok 12x12 cm
- Cor Beton M3 0.64 1,095,378.00 702,146.13 0.40 - - - - 0.64 100.00 702,146.13 0.40 0.64 100.00 702,146.13 0.40
- Besi Beton Kg 168.05 18,841.90 3,166,326.53 1.80 - - - - 168.05 100.00 3,166,326.53 1.80 168.05 100.00 3,166,326.53 1.80
- Bekisting (3 x Pakai ) M2 11.04 123,488.67 1,363,314.88 0.77 - - - - 11.04 100.00 1,363,314.88 0.77 11.04 100.00 1,363,314.88 0.77
8 Pek. Balok latei 12x12 cm
- Cor Beton M3 0.95 1,095,378.00 1,041,741.87 0.59 - - - - 0.95 100.00 1,041,741.87 0.59 0.95 100.00 1,041,741.87 0.59
- Besi Beton Kg 232.57 18,841.90 4,382,110.17 2.48 - - - - 232.57 100.00 4,382,110.17 2.48 232.57 100.00 4,382,110.17 2.48
- Bekisting (3 x Pakai ) M2 16.34 123,488.67 2,018,298.77 1.14 - - - - 16.34 100.00 2,018,298.77 1.14 16.34 100.00 2,018,298.77 1.14
9 Pek. Plat Gerbang 390x50x7 cm
- Cor Beton M3 0.54 1,095,378.00 594,356.93 0.34 - - - - 0.54 100.00 594,356.93 0.34 0.54 100.00 594,356.93 0.34
- Besi Beton Kg 55.90 18,841.90 1,053,347.63 0.60 - - - - 55.90 100.00 1,053,347.63 0.60 55.90 100.00 1,053,347.63 0.60
- Bekisting ( 2 x Pakai ) M2 10.34 179,953.00 1,861,145.91 1.06 - - - - 10.34 100.00 1,861,145.91 1.06 10.34 100.00 1,861,145.91 1.06
10 Pek. Plat Papan Nama 580x50x7 cm
- Cor Beton M3 0.20 1,095,378.00 219,471.88 0.12 - - - - 0.20 100.00 219,471.88 0.12 0.20 100.00 219,471.88 0.12
- Besi Beton Kg 20.72 18,841.90 390,497.12 0.22 - - - - 20.72 100.00 390,497.12 0.22 20.72 100.00 390,497.12 0.22
- Bekisting ( 2 x Pakai ) M2 3.80 179,953.00 684,109.32 0.39 - - - - 3.80 100.00 684,109.32 0.39 3.80 100.00 684,109.32 0.39

Jumlah 61,763,489.27 35.02 - - 61,763,489.27 35.02 61,763,489.27 35.02


IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN
1 Pas. Dinding Bata tebal batu camp. 1PC 5PP M2 76.71 127,465.00 9,778,031.35 5.54 - - - - 76.71 100.00 9,778,031.35 5.54 76.71 100.00 9,778,031.35 5.54
2 Pek. Plesteran Dinding Biasa camp. 1Pc 5Psr M2 202.04 71,209.00 14,387,066.36 8.16 - - - - 202.04 100.00 14,387,066.36 8.16 202.04 100.00 14,387,066.36 8.16
3 Pek. Pas. Dinding Granit 60x60 untuk Papan Nama M2 4.25 423,982.00 1,799,803.59 1.02 - - - - 4.25 100.00 1,799,803.59 1.02 4.25 100.00 1,799,803.59 1.02
4 Pek. Profil Beton Kolom Teras Camp. 1PC 2Psr M' 150.00 35,500.00 5,325,000.00 3.02 - - - - 150.00 100.00 5,325,000.00 3.02 150.00 100.00 5,325,000.00 3.02
5 Pek. Pas. Besi Holow Bh 20.00 1,000,000.00 20,000,000.00 11.34 - - - - 20.00 100.00 20,000,000.00 11.34 20.00 100.00 20,000,000.00 11.34

Jumlah 51,289,901.30 29.08 - - 51,289,901.30 29.08 51,289,901.30 29.08


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
V. PEKERJAAN PENGECETAN & PEMBERSIHAN
1 Pek. Pengecatan Dinding, Kolom, Sloef, dan Dak M2 340.34 20,621.00 7,018,171.76 3.98 - - - - 340.34 100.00 7,018,171.76 3.98 340.34 100.00 7,018,171.76 3.98
2 Pek. Huruf Acrilk Lapis Spond ( RSUD KOLAKA TIMUR ) Cm 375.00 7,000.00 2,625,000.00 1.49 - - - - 375.00 100.00 2,625,000.00 1.49 375.00 100.00 2,625,000.00 1.49
3 Pek. Huruf Acrilk Lapis Spond ( PEMERINTAH KOLAKA M2 340.34 7,000.00 2,382,387.00 1.35 - - - - 340.34 100.00 2,382,387.00 1.35 340.34 100.00 2,382,387.00 1.35
4 Pek. Logo Acrilik 60 x 70 Bh 1.00 800,000.00 800,000.00 0.45 - - - - 1.00 100.00 800,000.00 0.45 1.00 100.00 800,000.00 0.45
5 Pek. Pembersihan Akhir Sisa - Sisa Pekerjaan Ls 1.00 500,000.00 500,000.00 0.28 - - - - 1.00 100.00 500,000.00 0.28 1.00 100.00 500,000.00 0.28

Jumlah 13,325,558.76 7.56 - - 13,325,558.76 7.56 13,325,558.76 7.56


A REAL COST 176,351,902.0 100.0 - - 176,351,902.0 100.0 176,351,902.0 100.0
B PPn ( 11% ) 19,398,709.2 - 19,398,709.2 19,398,709.2
C TOTAL HARGA 195,750,611.3 - 195,750,611.3 195,750,611.3
D DIBULATKAN 195,750,000.0 - 195,750,000.0 195,750,000.0
REKAPITULASI BOBOT KEMAJUAN PEKERJAAN MINGGUAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 19 Desember S/D 25 Desember 2022
VOLUME : 1 (SATU) PAKET MINGGU KE : Lima
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 NOMOR KONTRAK : CV. MEGA KONSULTAN

S/D Minggu Lalu Minggu Ini S/D Minggu Ini


NO. URAIAN DAN JENIS PEKERJAAN JUMLAH HARGA Bobot (%) Bobot Bobot Bobot Bobot Bobot Bobot
Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga
(%) g(%) (%) g(%) (%) g(%)
1 2 3 4 5 6 7 8 9 10 11 12 13

I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 100.00 2.86 5,050,000.00 - - - 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 85.21 21.71 38,279,114.30 14.79 3.77 6,643,838.40 100.00 25.47 44,922,952.70
III. PEKERJAAN BETON 61,763,489.27 35.02 100.00 35.02 61,763,489.27 - - - 100.00 35.02 61,763,489.27
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 71.80 20.88 36,827,597.71 28.20 8.20 14,462,303.59 100.00 29.08 51,289,901.30
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - 100.00 7.56 13,325,558.76 100.00 7.56 13,325,558.76

A REAL COST 176,351,902.03 100.00 80.48 141,920,201.28 19.52 34,431,700.75 100.00 176,351,902.03
B PPn ( 11% ) 19,398,709.22 15,611,222.14 3,787,487.08 19,398,709.22
C TOTAL HARGA 195,750,611.26 157,531,423.43 38,219,187.83 195,750,611.26
D DIBULATKAN 195,750,000.00 157,530,000.00 38,210,000.00 195,750,000.00

Welala, 25 Desember 2022


Mengetahui / Menyetujui :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Dibuat Oleh
Rumah Sakit Umum Daerah (RSUD) Konsultan Pengawas
Kab. Kolaka Timur CV. MEGA KONSULTAN

NUR QOMAR, S.Km ISMAIL, ST


Nip. 19780610 200701 1 020 Konsultan Pengawas
BOBOT KEMAJUAN PEKERJAAN MINGGUAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 19 Desember S/D 25 Desember 2022
VOLUME : 1 (SATU) PAKET MINGGU KE : Lima
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 KONSULTAN PENGAWAS : CV. MEGA KONSULTAN

S/D Minggu Lalu Minggu Ini S/D Minggu Ini

NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)

1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09

Jumlah 5,050,000.00 2.86 5,050,000.00 2.86 - - 5,050,000.00 2.86


II. PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi M3 38.85 85,937.00 3,338,652.45 1.89 38.85 100.00 3,338,652.45 1.89 - - - - 38.85 100.00 3,338,652.45 1.89
2 Pek. Batu Kosong (Aanstamping) M3 11.66 541,084.00 6,306,334.02 3.58 11.66 100.00 6,306,334.02 3.58 - - - - 11.66 100.00 6,306,334.02 3.58
3 Pek. Pondasi Batu Gunung camp. 1Pc 5Psr M3 29.14 974,990.00 28,408,771.13 16.11 29.14 100.00 28,408,771.13 16.11 - - - - 29.14 100.00 28,408,771.13 16.11
4 Pek. Urugan kembali bekas Galian tanah M3 7.28 30,937.00 225,356.71 0.13 7.28 100.00 225,356.71 0.13 - - - - 7.28 100.00 225,356.71 0.13
5 Pek. Plesteran Pondasi camp. 1Pc : 3Psr M2 88.80 74,818.00 6,643,838.40 3.77 - - - - 88.80 100.00 6,643,838.40 3.77 88.80 100.00 6,643,838.40 3.77

Jumlah 44,922,952.70 25.47 38,279,114.30 21.71 6,643,838.40 3.77 44,922,952.70 25.47


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
III. PEKERJAAN BETON
1 Pek. Sloef Beton 15 x 20 cm (SF)
- Cor Beton M3 2.22 1,095,378.00 2,426,716.63 1.38 2.22 100.00 2,426,716.63 1.38 - - - - 2.22 100.00 2,426,716.63 1.38
- Besi Beton Kg 448.44 18,841.90 8,449,461.64 4.79 448.44 100.00 8,449,461.64 4.79 - - - - 448.44 100.00 8,449,461.64 4.79
- Bekisting M2 30.30 203,379.00 6,162,383.70 3.49 30.30 100.00 6,162,383.70 3.49 - - - - 30.30 100.00 6,162,383.70 3.49
2 Pek. Kolom Pagar 25x25 cm (T=180)
- Cor Beton M3 1.61 1,095,378.00 1,760,031.46 1.00 1.61 100.00 1,760,031.46 1.00 - - - - 1.61 100.00 1,760,031.46 1.00
- Besi Beton Kg 126.48 18,841.90 2,383,040.98 1.35 126.48 100.00 2,383,040.98 1.35 - - - - 126.48 100.00 2,383,040.98 1.35
- Kolom Pagar Jadi Bh 138.00 70,000.00 9,660,000.00 5.48 138.00 100.00 9,660,000.00 5.48 - - - - 138.00 100.00 9,660,000.00 5.48
- Kepala Kolom Pagar Jadi Bh 23.00 70,000.00 1,610,000.00 0.91 23.00 100.00 1,610,000.00 0.91 - - - - 23.00 100.00 1,610,000.00 0.91
3 Pek. Kolom Gerbang 25x25 cm (T=150)
- Cor Beton M3 0.23 1,095,378.00 248,636.20 0.14 0.23 100.00 248,636.20 0.14 - - - - 0.23 100.00 248,636.20 0.14
- Besi Beton Kg 18.33 18,841.90 345,368.26 0.20 18.33 100.00 345,368.26 0.20 - - - - 18.33 100.00 345,368.26 0.20
- Kolom Pagar Jadi Bh 20.00 70,000.00 1,400,000.00 0.79 20.00 100.00 1,400,000.00 0.79 - - - - 20.00 100.00 1,400,000.00 0.79
4 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 1.00 1,095,378.00 1,092,256.81 0.62 1.00 100.00 1,092,256.81 0.62 - - - - 1.00 100.00 1,092,256.81 0.62
- Besi Beton Kg 120.58 18,841.90 2,271,943.11 1.29 120.58 100.00 2,271,943.11 1.29 - - - - 120.58 100.00 2,271,943.11 1.29
- Bekisting ( 3 x Pakai ) M2 21.60 119,968.67 2,591,323.20 1.47 21.60 100.00 2,591,323.20 1.47 - - - - 21.60 100.00 2,591,323.20 1.47
5 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 0.07 1,095,378.00 79,577.46 0.05 0.07 100.00 79,577.46 0.05 - - - - 0.07 100.00 79,577.46 0.05
- Besi Beton Kg 17.53 18,841.90 330,309.81 0.19 17.53 100.00 330,309.81 0.19 - - - - 17.53 100.00 330,309.81 0.19
- Bekisting ( 3 x Pakai ) M2 1.87 119,968.67 224,581.34 0.13 1.87 100.00 224,581.34 0.13 - - - - 1.87 100.00 224,581.34 0.13
6 Pek. Kolom Pagar 12x12 cm
- Cor Beton M3 0.37 1,095,378.00 402,164.85 0.23 0.37 100.00 402,164.85 0.23 - - - - 0.37 100.00 402,164.85 0.23
- Besi Beton Kg 90.91 18,841.90 1,712,963.35 0.97 90.91 100.00 1,712,963.35 0.97 - - - - 90.91 100.00 1,712,963.35 0.97
- Bekisting ( 3 x Pakai ) M2 9.47 119,968.67 1,135,863.34 0.64 9.47 100.00 1,135,863.34 0.64 - - - - 9.47 100.00 1,135,863.34 0.64
7 Pek. Ring Balok 12x12 cm
- Cor Beton M3 0.64 1,095,378.00 702,146.13 0.40 0.64 100.00 702,146.13 0.40 - - - - 0.64 100.00 702,146.13 0.40
- Besi Beton Kg 168.05 18,841.90 3,166,326.53 1.80 168.05 100.00 3,166,326.53 1.80 - - - - 168.05 100.00 3,166,326.53 1.80
- Bekisting (3 x Pakai ) M2 11.04 123,488.67 1,363,314.88 0.77 11.04 100.00 1,363,314.88 0.77 - - - - 11.04 100.00 1,363,314.88 0.77
8 Pek. Balok latei 12x12 cm
- Cor Beton M3 0.95 1,095,378.00 1,041,741.87 0.59 0.95 100.00 1,041,741.87 0.59 - - - - 0.95 100.00 1,041,741.87 0.59
- Besi Beton Kg 232.57 18,841.90 4,382,110.17 2.48 232.57 100.00 4,382,110.17 2.48 - - - - 232.57 100.00 4,382,110.17 2.48
- Bekisting (3 x Pakai ) M2 16.34 123,488.67 2,018,298.77 1.14 16.34 100.00 2,018,298.77 1.14 - - - - 16.34 100.00 2,018,298.77 1.14
9 Pek. Plat Gerbang 390x50x7 cm
- Cor Beton M3 0.54 1,095,378.00 594,356.93 0.34 0.54 100.00 594,356.93 0.34 - - - - 0.54 100.00 594,356.93 0.34
- Besi Beton Kg 55.90 18,841.90 1,053,347.63 0.60 55.90 100.00 1,053,347.63 0.60 - - - - 55.90 100.00 1,053,347.63 0.60
- Bekisting ( 2 x Pakai ) M2 10.34 179,953.00 1,861,145.91 1.06 10.34 100.00 1,861,145.91 1.06 - - - - 10.34 100.00 1,861,145.91 1.06
10 Pek. Plat Papan Nama 580x50x7 cm
- Cor Beton M3 0.20 1,095,378.00 219,471.88 0.12 0.20 100.00 219,471.88 0.12 - - - - 0.20 100.00 219,471.88 0.12
- Besi Beton Kg 20.72 18,841.90 390,497.12 0.22 20.72 100.00 390,497.12 0.22 - - - - 20.72 100.00 390,497.12 0.22
- Bekisting ( 2 x Pakai ) M2 3.80 179,953.00 684,109.32 0.39 3.80 100.00 684,109.32 0.39 - - - - 3.80 100.00 684,109.32 0.39

Jumlah 61,763,489.27 35.02 61,763,489.27 35.02 - - 61,763,489.27 35.02


IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN
1 Pas. Dinding Bata tebal batu camp. 1PC 5PP M2 76.71 127,465.00 9,778,031.35 5.54 76.71 100.00 9,778,031.35 5.54 - - - - 76.71 100.00 9,778,031.35 5.54
2 Pek. Plesteran Dinding Biasa camp. 1Pc 5Psr M2 202.04 71,209.00 14,387,066.36 8.16 202.04 100.00 14,387,066.36 8.16 - - - - 202.04 100.00 14,387,066.36 8.16
3 Pek. Pas. Dinding Granit 60x60 untuk Papan Nama M2 4.25 423,982.00 1,799,803.59 1.02 - - - - 4.25 100.00 1,799,803.59 1.02 4.25 100.00 1,799,803.59 1.02
4 Pek. Profil Beton Kolom Teras Camp. 1PC 2Psr M' 150.00 35,500.00 5,325,000.00 3.02 75.00 50.00 2,662,500.00 1.51 75.00 50.00 2,662,500.00 1.51 150.00 100.00 5,325,000.00 3.02
5 Pek. Pas. Besi Holow Bh 20.00 1,000,000.00 20,000,000.00 11.34 10.00 50.00 10,000,000.00 5.67 10.00 50.00 10,000,000.00 5.67 20.00 100.00 20,000,000.00 11.34

Jumlah 51,289,901.30 29.08 36,827,597.71 20.88 14,462,303.59 8.20 51,289,901.30 29.08


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
V. PEKERJAAN PENGECETAN & PEMBERSIHAN
1 Pek. Pengecatan Dinding, Kolom, Sloef, dan Dak M2 340.34 20,621.00 7,018,171.76 3.98 - - - - 340.34 100.00 7,018,171.76 3.98 340.34 100.00 7,018,171.76 3.98
2 Pek. Huruf Acrilk Lapis Spond ( RSUD KOLAKA TIMUR ) Cm 375.00 7,000.00 2,625,000.00 1.49 - - - - 375.00 100.00 2,625,000.00 1.49 375.00 100.00 2,625,000.00 1.49
3 Pek. Huruf Acrilk Lapis Spond ( PEMERINTAH KOLAKA M2 340.34 7,000.00 2,382,387.00 1.35 - - - - 340.34 100.00 2,382,387.00 1.35 340.34 100.00 2,382,387.00 1.35
4 Pek. Logo Acrilik 60 x 70 Bh 1.00 800,000.00 800,000.00 0.45 - - - - 1.00 100.00 800,000.00 0.45 1.00 100.00 800,000.00 0.45
5 Pek. Pembersihan Akhir Sisa - Sisa Pekerjaan Ls 1.00 500,000.00 500,000.00 0.28 - - - - 1.00 100.00 500,000.00 0.28 1.00 100.00 500,000.00 0.28

Jumlah 13,325,558.76 7.56 - - 13,325,558.76 7.56 13,325,558.76 7.56


A REAL COST 176,351,902.0 100.0 141,920,201.3 80.48 34,431,700.8 19.52 176,351,902.0 100.0
B PPn ( 11% ) 19,398,709.2 15,611,222.1 3,787,487.1 19,398,709.2
C TOTAL HARGA 195,750,611.3 157,531,423.4 38,219,187.8 195,750,611.3
D DIBULATKAN 195,750,000.0 157,530,000.0 38,210,000.0 195,750,000.0
REKAPITULASI BOBOT KEMAJUAN PEKERJAAN MINGGUAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 12 Desember S/D 18 Desember 2022
VOLUME : 1 (SATU) PAKET MINGGU KE : Empat
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 NOMOR KONTRAK : CV. MEGA KONSULTAN

S/D Minggu Lalu Minggu Ini S/D Minggu Ini


NO. URAIAN DAN JENIS PEKERJAAN JUMLAH HARGA Bobot (%) Bobot Bobot Bobot Bobot Bobot Bobot
Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga
(%) g(%) (%) g(%) (%) g(%)
1 2 3 4 5 6 7 8 9 10 11 12 13

I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 100.00 2.86 5,050,000.00 - - - 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 85.21 21.71 38,279,114.30 - - - 85.21 21.71 38,279,114.30
III. PEKERJAAN BETON 61,763,489.27 35.02 100.00 35.02 61,763,489.27 - - - 100.00 35.02 61,763,489.27
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 26.08 7.58 13,374,797.94 45.73 13.30 23,452,799.77 71.80 20.88 36,827,597.71
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - - - - - - -

A REAL COST 176,351,902.03 100.00 67.18 118,467,401.51 13.30 23,452,799.77 80.48 141,920,201.28
B PPn ( 11% ) 19,398,709.22 13,031,414.17 2,579,807.97 15,611,222.14
C TOTAL HARGA 195,750,611.26 131,498,815.68 26,032,607.74 157,531,423.43
D DIBULATKAN 195,750,000.00 131,490,000.00 26,030,000.00 157,530,000.00

Welala, 18 Desember 2022


Mengetahui / Menyetujui :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Dibuat Oleh
Rumah Sakit Umum Daerah (RSUD) Konsultan Pengawas
Kab. Kolaka Timur CV. MEGA KONSULTAN

NUR QOMAR, S.Km ISMAIL, ST


Nip. 19780610 200701 1 020 Konsultan Pengawas
BOBOT KEMAJUAN PEKERJAAN MINGGUAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 12 Desember S/D 18 Desember 2022
VOLUME : 1 (SATU) PAKET MINGGU KE : Empat
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 KONSULTAN PENGAWAS : CV. MEGA KONSULTAN

S/D Minggu Lalu Minggu Ini S/D Minggu Ini

NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)

1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09

Jumlah 5,050,000.00 2.86 5,050,000.00 2.86 - - 5,050,000.00 2.86


II. PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi M3 38.85 85,937.00 3,338,652.45 1.89 38.85 100.00 3,338,652.45 1.89 - - - - 38.85 100.00 3,338,652.45 1.89
2 Pek. Batu Kosong (Aanstamping) M3 11.66 541,084.00 6,306,334.02 3.58 11.66 100.00 6,306,334.02 3.58 - - - - 11.66 100.00 6,306,334.02 3.58
3 Pek. Pondasi Batu Gunung camp. 1Pc 5Psr M3 29.14 974,990.00 28,408,771.13 16.11 29.14 100.00 28,408,771.13 16.11 - - - - 29.14 100.00 28,408,771.13 16.11
4 Pek. Urugan kembali bekas Galian tanah M3 7.28 30,937.00 225,356.71 0.13 7.28 100.00 225,356.71 0.13 - - - - 7.28 100.00 225,356.71 0.13
5 Pek. Plesteran Pondasi camp. 1Pc : 3Psr M2 88.80 74,818.00 6,643,838.40 3.77 - - - - - - - - - - - -

Jumlah 44,922,952.70 25.47 38,279,114.30 21.71 - - 38,279,114.30 21.71


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
III. PEKERJAAN BETON
1 Pek. Sloef Beton 15 x 20 cm (SF)
- Cor Beton M3 2.22 1,095,378.00 2,426,716.63 1.38 2.22 100.00 2,426,716.63 1.38 - - - - 2.22 100.00 2,426,716.63 1.38
- Besi Beton Kg 448.44 18,841.90 8,449,461.64 4.79 448.44 100.00 8,449,461.64 4.79 - - - - 448.44 100.00 8,449,461.64 4.79
- Bekisting M2 30.30 203,379.00 6,162,383.70 3.49 30.30 100.00 6,162,383.70 3.49 - - - - 30.30 100.00 6,162,383.70 3.49
2 Pek. Kolom Pagar 25x25 cm (T=180)
- Cor Beton M3 1.61 1,095,378.00 1,760,031.46 1.00 1.61 100.00 1,760,031.46 1.00 - - - - 1.61 100.00 1,760,031.46 1.00
- Besi Beton Kg 126.48 18,841.90 2,383,040.98 1.35 126.48 100.00 2,383,040.98 1.35 - - - - 126.48 100.00 2,383,040.98 1.35
- Kolom Pagar Jadi Bh 138.00 70,000.00 9,660,000.00 5.48 138.00 100.00 9,660,000.00 5.48 - - - - 138.00 100.00 9,660,000.00 5.48
- Kepala Kolom Pagar Jadi Bh 23.00 70,000.00 1,610,000.00 0.91 23.00 100.00 1,610,000.00 0.91 - - - - 23.00 100.00 1,610,000.00 0.91
3 Pek. Kolom Gerbang 25x25 cm (T=150)
- Cor Beton M3 0.23 1,095,378.00 248,636.20 0.14 0.23 100.00 248,636.20 0.14 - - - - 0.23 100.00 248,636.20 0.14
- Besi Beton Kg 18.33 18,841.90 345,368.26 0.20 18.33 100.00 345,368.26 0.20 - - - - 18.33 100.00 345,368.26 0.20
- Kolom Pagar Jadi Bh 20.00 70,000.00 1,400,000.00 0.79 20.00 100.00 1,400,000.00 0.79 - - - - 20.00 100.00 1,400,000.00 0.79
4 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 1.00 1,095,378.00 1,092,256.81 0.62 1.00 100.00 1,092,256.81 0.62 - - - - 1.00 100.00 1,092,256.81 0.62
- Besi Beton Kg 120.58 18,841.90 2,271,943.11 1.29 120.58 100.00 2,271,943.11 1.29 - - - - 120.58 100.00 2,271,943.11 1.29
- Bekisting ( 3 x Pakai ) M2 21.60 119,968.67 2,591,323.20 1.47 21.60 100.00 2,591,323.20 1.47 - - - - 21.60 100.00 2,591,323.20 1.47
5 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 0.07 1,095,378.00 79,577.46 0.05 0.07 100.00 79,577.46 0.05 - - - - 0.07 100.00 79,577.46 0.05
- Besi Beton Kg 17.53 18,841.90 330,309.81 0.19 17.53 100.00 330,309.81 0.19 - - - - 17.53 100.00 330,309.81 0.19
- Bekisting ( 3 x Pakai ) M2 1.87 119,968.67 224,581.34 0.13 1.87 100.00 224,581.34 0.13 - - - - 1.87 100.00 224,581.34 0.13
6 Pek. Kolom Pagar 12x12 cm
- Cor Beton M3 0.37 1,095,378.00 402,164.85 0.23 0.37 100.00 402,164.85 0.23 - - - - 0.37 100.00 402,164.85 0.23
- Besi Beton Kg 90.91 18,841.90 1,712,963.35 0.97 90.91 100.00 1,712,963.35 0.97 - - - - 90.91 100.00 1,712,963.35 0.97
- Bekisting ( 3 x Pakai ) M2 9.47 119,968.67 1,135,863.34 0.64 9.47 100.00 1,135,863.34 0.64 - - - - 9.47 100.00 1,135,863.34 0.64
7 Pek. Ring Balok 12x12 cm
- Cor Beton M3 0.64 1,095,378.00 702,146.13 0.40 0.64 100.00 702,146.13 0.40 - - - - 0.64 100.00 702,146.13 0.40
- Besi Beton Kg 168.05 18,841.90 3,166,326.53 1.80 168.05 100.00 3,166,326.53 1.80 - - - - 168.05 100.00 3,166,326.53 1.80
- Bekisting (3 x Pakai ) M2 11.04 123,488.67 1,363,314.88 0.77 11.04 100.00 1,363,314.88 0.77 - - - - 11.04 100.00 1,363,314.88 0.77
8 Pek. Balok latei 12x12 cm
- Cor Beton M3 0.95 1,095,378.00 1,041,741.87 0.59 0.95 100.00 1,041,741.87 0.59 - - - - 0.95 100.00 1,041,741.87 0.59
- Besi Beton Kg 232.57 18,841.90 4,382,110.17 2.48 232.57 100.00 4,382,110.17 2.48 - - - - 232.57 100.00 4,382,110.17 2.48
- Bekisting (3 x Pakai ) M2 16.34 123,488.67 2,018,298.77 1.14 16.34 100.00 2,018,298.77 1.14 - - - - 16.34 100.00 2,018,298.77 1.14
9 Pek. Plat Gerbang 390x50x7 cm
- Cor Beton M3 0.54 1,095,378.00 594,356.93 0.34 0.54 100.00 594,356.93 0.34 - - - - 0.54 100.00 594,356.93 0.34
- Besi Beton Kg 55.90 18,841.90 1,053,347.63 0.60 55.90 100.00 1,053,347.63 0.60 - - - - 55.90 100.00 1,053,347.63 0.60
- Bekisting ( 2 x Pakai ) M2 10.34 179,953.00 1,861,145.91 1.06 10.34 100.00 1,861,145.91 1.06 - - - - 10.34 100.00 1,861,145.91 1.06
10 Pek. Plat Papan Nama 580x50x7 cm
- Cor Beton M3 0.20 1,095,378.00 219,471.88 0.12 0.20 100.00 219,471.88 0.12 - - - - 0.20 100.00 219,471.88 0.12
- Besi Beton Kg 20.72 18,841.90 390,497.12 0.22 20.72 100.00 390,497.12 0.22 - - - - 20.72 100.00 390,497.12 0.22
- Bekisting ( 2 x Pakai ) M2 3.80 179,953.00 684,109.32 0.39 3.80 100.00 684,109.32 0.39 - - - - 3.80 100.00 684,109.32 0.39

Jumlah 61,763,489.27 35.02 61,763,489.27 35.02 - - 61,763,489.27 35.02


IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN
1 Pas. Dinding Bata tebal batu camp. 1PC 5PP M2 76.71 127,465.00 9,778,031.35 5.54 76.71 100.00 9,778,031.35 5.54 - - - - 76.71 100.00 9,778,031.35 5.54
2 Pek. Plesteran Dinding Biasa camp. 1Pc 5Psr M2 202.04 71,209.00 14,387,066.36 8.16 50.51 25.00 3,596,766.59 2.04 151.53 75.00 10,790,299.77 6.12 202.04 100.00 14,387,066.36 8.16
3 Pek. Pas. Dinding Granit 60x60 untuk Papan Nama M2 4.25 423,982.00 1,799,803.59 1.02 - - - - - - - - - - - -
4 Pek. Profil Beton Kolom Teras Camp. 1PC 2Psr M' 150.00 35,500.00 5,325,000.00 3.02 - - - - 75.00 50.00 2,662,500.00 1.51 75.00 50.00 2,662,500.00 1.51
5 Pek. Pas. Besi Holow Bh 20.00 1,000,000.00 20,000,000.00 11.34 - - - - 10.00 50.00 10,000,000.00 5.67 10.00 50.00 10,000,000.00 5.67

Jumlah 51,289,901.30 29.08 13,374,797.94 7.58 23,452,799.77 13.30 36,827,597.71 20.88


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
V. PEKERJAAN PENGECETAN & PEMBERSIHAN
1 Pek. Pengecatan Dinding, Kolom, Sloef, dan Dak M2 340.34 20,621.00 7,018,171.76 3.98 - - - - - - - - - - - -
2 Pek. Huruf Acrilk Lapis Spond ( RSUD KOLAKA TIMUR ) Cm 375.00 7,000.00 2,625,000.00 1.49 - - - - - - - - - - - -
3 Pek. Huruf Acrilk Lapis Spond ( PEMERINTAH KOLAKA M2 340.34 7,000.00 2,382,387.00 1.35 - - - - - - - - - - - -
4 Pek. Logo Acrilik 60 x 70 Bh 1.00 800,000.00 800,000.00 0.45 - - - - - - - - - - - -
5 Pek. Pembersihan Akhir Sisa - Sisa Pekerjaan Ls 1.00 500,000.00 500,000.00 0.28 - - - - - - - - - - - -

Jumlah 13,325,558.76 7.56 - - - - - -


A REAL COST 176,351,902.0 100.0 118,467,401.5 67.18 23,452,799.8 13.30 141,920,201.3 80.5
B PPn ( 11% ) 19,398,709.2 13,031,414.2 2,579,808.0 15,611,222.1
C TOTAL HARGA 195,750,611.3 131,498,815.7 26,032,607.7 157,531,423.4
D DIBULATKAN 195,750,000.0 131,490,000.0 26,030,000.0 157,530,000.0
REKAPITULASI BOBOT KEMAJUAN PEKERJAAN MINGGUAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 05 Desember S/D 11 Desember 2022
VOLUME : 1 (SATU) PAKET MINGGU KE : Tiga
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 NOMOR KONTRAK : CV. MEGA KONSULTAN

S/D Minggu Lalu Minggu Ini S/D Minggu Ini


NO. URAIAN DAN JENIS PEKERJAAN JUMLAH HARGA Bobot (%) Bobot Bobot Bobot Bobot Bobot Bobot
Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga
(%) g(%) (%) g(%) (%) g(%)
1 2 3 4 5 6 7 8 9 10 11 12 13

I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 100.00 2.86 5,050,000.00 - - - 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 85.21 21.71 38,279,114.30 - - - 85.21 21.71 38,279,114.30
III. PEKERJAAN BETON 61,763,489.27 35.02 53.55 18.75 33,074,468.94 46.45 16.27 28,689,020.33 100.00 35.02 61,763,489.27
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 9.53 2.77 4,889,015.67 16.54 4.81 8,485,782.26 26.08 7.58 13,374,797.94
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - - - - - - -

A REAL COST 176,351,902.03 100.00 46.10 81,292,598.92 21.08 37,174,802.59 67.18 118,467,401.51
B PPn ( 11% ) 19,398,709.22 8,942,185.88 4,089,228.29 13,031,414.17
C TOTAL HARGA 195,750,611.26 90,234,784.80 41,264,030.88 131,498,815.68
D DIBULATKAN 195,750,000.00 90,230,000.00 41,260,000.00 131,490,000.00

Welala, 11 Desember 2022


Mengetahui / Menyetujui :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Dibuat Oleh
Rumah Sakit Umum Daerah (RSUD) Konsultan Pengawas
Kab. Kolaka Timur CV. MEGA KONSULTAN

NUR QOMAR, S.Km ISMAIL, ST


Nip. 19780610 200701 1 020 Konsultan Pengawas
BOBOT KEMAJUAN PEKERJAAN MINGGUAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 05 Desember S/D 11 Desember 2022
VOLUME : 1 (SATU) PAKET MINGGU KE : Tiga
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 KONSULTAN PENGAWAS : CV. MEGA KONSULTAN

S/D Minggu Lalu Minggu Ini S/D Minggu Ini

NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)

1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09

Jumlah 5,050,000.00 2.86 5,050,000.00 2.86 - - 5,050,000.00 2.86


II. PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi M3 38.85 85,937.00 3,338,652.45 1.89 38.85 100.00 3,338,652.45 1.89 - - - - 38.85 100.00 3,338,652.45 1.89
2 Pek. Batu Kosong (Aanstamping) M3 11.66 541,084.00 6,306,334.02 3.58 11.66 100.00 6,306,334.02 3.58 - - - - 11.66 100.00 6,306,334.02 3.58
3 Pek. Pondasi Batu Gunung camp. 1Pc 5Psr M3 29.14 974,990.00 28,408,771.13 16.11 29.14 100.00 28,408,771.13 16.11 - - - - 29.14 100.00 28,408,771.13 16.11
4 Pek. Urugan kembali bekas Galian tanah M3 7.28 30,937.00 225,356.71 0.13 7.28 100.00 225,356.71 0.13 - - - - 7.28 100.00 225,356.71 0.13
5 Pek. Plesteran Pondasi camp. 1Pc : 3Psr M2 88.80 74,818.00 6,643,838.40 3.77 - - - - - - - - - - - -

Jumlah 44,922,952.70 25.47 38,279,114.30 21.71 - - 38,279,114.30 21.71


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
III. PEKERJAAN BETON
1 Pek. Sloef Beton 15 x 20 cm (SF)
- Cor Beton M3 2.22 1,095,378.00 2,426,716.63 1.38 2.22 100.00 2,426,716.63 1.38 - - - - 2.22 100.00 2,426,716.63 1.38
- Besi Beton Kg 448.44 18,841.90 8,449,461.64 4.79 448.44 100.00 8,449,461.64 4.79 - - - - 448.44 100.00 8,449,461.64 4.79
- Bekisting M2 30.30 203,379.00 6,162,383.70 3.49 30.30 100.00 6,162,383.70 3.49 - - - - 30.30 100.00 6,162,383.70 3.49
2 Pek. Kolom Pagar 25x25 cm (T=180)
- Cor Beton M3 1.61 1,095,378.00 1,760,031.46 1.00 - - - - 1.61 100.00 1,760,031.46 1.00 1.61 100.00 1,760,031.46 1.00
- Besi Beton Kg 126.48 18,841.90 2,383,040.98 1.35 126.48 100.00 2,383,040.98 1.35 - - - - 126.48 100.00 2,383,040.98 1.35
- Kolom Pagar Jadi Bh 138.00 70,000.00 9,660,000.00 5.48 - - - - 138.00 100.00 9,660,000.00 5.48 138.00 100.00 9,660,000.00 5.48
- Kepala Kolom Pagar Jadi Bh 23.00 70,000.00 1,610,000.00 0.91 - - - - 23.00 100.00 1,610,000.00 0.91 23.00 100.00 1,610,000.00 0.91
3 Pek. Kolom Gerbang 25x25 cm (T=150)
- Cor Beton M3 0.23 1,095,378.00 248,636.20 0.14 - - - - 0.23 100.00 248,636.20 0.14 0.23 100.00 248,636.20 0.14
- Besi Beton Kg 18.33 18,841.90 345,368.26 0.20 18.33 100.00 345,368.26 0.20 - - - - 18.33 100.00 345,368.26 0.20
- Kolom Pagar Jadi Bh 20.00 70,000.00 1,400,000.00 0.79 - - - - 20.00 100.00 1,400,000.00 0.79 20.00 100.00 1,400,000.00 0.79
4 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 1.00 1,095,378.00 1,092,256.81 0.62 - - - - 1.00 100.00 1,092,256.81 0.62 1.00 100.00 1,092,256.81 0.62
- Besi Beton Kg 120.58 18,841.90 2,271,943.11 1.29 120.58 100.00 2,271,943.11 1.29 - - - - 120.58 100.00 2,271,943.11 1.29
- Bekisting ( 3 x Pakai ) M2 21.60 119,968.67 2,591,323.20 1.47 - - - - 21.60 100.00 2,591,323.20 1.47 21.60 100.00 2,591,323.20 1.47
5 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 0.07 1,095,378.00 79,577.46 0.05 - - - - 0.07 100.00 79,577.46 0.05 0.07 100.00 79,577.46 0.05
- Besi Beton Kg 17.53 18,841.90 330,309.81 0.19 17.53 100.00 330,309.81 0.19 - - - - 17.53 100.00 330,309.81 0.19
- Bekisting ( 3 x Pakai ) M2 1.87 119,968.67 224,581.34 0.13 - - - - 1.87 100.00 224,581.34 0.13 1.87 100.00 224,581.34 0.13
6 Pek. Kolom Pagar 12x12 cm
- Cor Beton M3 0.37 1,095,378.00 402,164.85 0.23 - - - - 0.37 100.00 402,164.85 0.23 0.37 100.00 402,164.85 0.23
- Besi Beton Kg 90.91 18,841.90 1,712,963.35 0.97 90.91 100.00 1,712,963.35 0.97 - - - - 90.91 100.00 1,712,963.35 0.97
- Bekisting ( 3 x Pakai ) M2 9.47 119,968.67 1,135,863.34 0.64 - - - - 9.47 100.00 1,135,863.34 0.64 9.47 100.00 1,135,863.34 0.64
7 Pek. Ring Balok 12x12 cm
- Cor Beton M3 0.64 1,095,378.00 702,146.13 0.40 - - - - 0.64 100.00 702,146.13 0.40 0.64 100.00 702,146.13 0.40
- Besi Beton Kg 168.05 18,841.90 3,166,326.53 1.80 168.05 100.00 3,166,326.53 1.80 - - - - 168.05 100.00 3,166,326.53 1.80
- Bekisting (3 x Pakai ) M2 11.04 123,488.67 1,363,314.88 0.77 - - - - 11.04 100.00 1,363,314.88 0.77 11.04 100.00 1,363,314.88 0.77
8 Pek. Balok latei 12x12 cm
- Cor Beton M3 0.95 1,095,378.00 1,041,741.87 0.59 - - - - 0.95 100.00 1,041,741.87 0.59 0.95 100.00 1,041,741.87 0.59
- Besi Beton Kg 232.57 18,841.90 4,382,110.17 2.48 232.57 100.00 4,382,110.17 2.48 - - - - 232.57 100.00 4,382,110.17 2.48
- Bekisting (3 x Pakai ) M2 16.34 123,488.67 2,018,298.77 1.14 - - - - 16.34 100.00 2,018,298.77 1.14 16.34 100.00 2,018,298.77 1.14
9 Pek. Plat Gerbang 390x50x7 cm
- Cor Beton M3 0.54 1,095,378.00 594,356.93 0.34 - - - - 0.54 100.00 594,356.93 0.34 0.54 100.00 594,356.93 0.34
- Besi Beton Kg 55.90 18,841.90 1,053,347.63 0.60 55.90 100.00 1,053,347.63 0.60 - - - - 55.90 100.00 1,053,347.63 0.60
- Bekisting ( 2 x Pakai ) M2 10.34 179,953.00 1,861,145.91 1.06 - - - - 10.34 100.00 1,861,145.91 1.06 10.34 100.00 1,861,145.91 1.06
10 Pek. Plat Papan Nama 580x50x7 cm
- Cor Beton M3 0.20 1,095,378.00 219,471.88 0.12 - - - - 0.20 100.00 219,471.88 0.12 0.20 100.00 219,471.88 0.12
- Besi Beton Kg 20.72 18,841.90 390,497.12 0.22 20.72 100.00 390,497.12 0.22 - - - - 20.72 100.00 390,497.12 0.22
- Bekisting ( 2 x Pakai ) M2 3.80 179,953.00 684,109.32 0.39 - - - - 3.80 100.00 684,109.32 0.39 3.80 100.00 684,109.32 0.39

Jumlah 61,763,489.27 35.02 33,074,468.94 18.75 28,689,020.33 16.27 61,763,489.27 35.02


IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN
1 Pas. Dinding Bata tebal batu camp. 1PC 5PP M2 76.71 127,465.00 9,778,031.35 5.54 38.36 50.00 4,889,015.67 2.77 38.36 50.00 4,889,015.67 2.77 76.71 100.00 9,778,031.35 5.54
2 Pek. Plesteran Dinding Biasa camp. 1Pc 5Psr M2 202.04 71,209.00 14,387,066.36 8.16 - - - - 50.51 25.00 3,596,766.59 2.04 50.51 25.00 3,596,766.59 2.04
3 Pek. Pas. Dinding Granit 60x60 untuk Papan Nama M2 4.25 423,982.00 1,799,803.59 1.02 - - - - - - - - - - - -
4 Pek. Profil Beton Kolom Teras Camp. 1PC 2Psr M' 150.00 35,500.00 5,325,000.00 3.02 - - - - - - - - - - - -
5 Pek. Pas. Besi Holow Bh 20.00 1,000,000.00 20,000,000.00 11.34 - - - - - - - - - - - -

Jumlah 51,289,901.30 29.08 4,889,015.67 2.77 8,485,782.26 4.81 13,374,797.94 7.58


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
V. PEKERJAAN PENGECETAN & PEMBERSIHAN
1 Pek. Pengecatan Dinding, Kolom, Sloef, dan Dak M2 340.34 20,621.00 7,018,171.76 3.98 - - - - - - - - - - - -
2 Pek. Huruf Acrilk Lapis Spond ( RSUD KOLAKA TIMUR ) Cm 375.00 7,000.00 2,625,000.00 1.49 - - - - - - - - - - - -
3 Pek. Huruf Acrilk Lapis Spond ( PEMERINTAH KOLAKA M2 340.34 7,000.00 2,382,387.00 1.35 - - - - - - - - - - - -
4 Pek. Logo Acrilik 60 x 70 Bh 1.00 800,000.00 800,000.00 0.45 - - - - - - - - - - - -
5 Pek. Pembersihan Akhir Sisa - Sisa Pekerjaan Ls 1.00 500,000.00 500,000.00 0.28 - - - - - - - - - - - -

Jumlah 13,325,558.76 7.56 - - - - - -


A REAL COST 176,351,902.0 100.0 81,292,598.9 46.10 37,174,802.6 21.08 118,467,401.5 67.18
B PPn ( 11% ) 19,398,709.2 8,942,185.9 4,089,228.3 13,031,414.2
C TOTAL HARGA 195,750,611.3 90,234,784.8 41,264,030.9 131,498,815.7
D DIBULATKAN 195,750,000.0 90,230,000.0 41,260,000.0 131,490,000.0
REKAPITULASI BOBOT KEMAJUAN PEKERJAAN MINGGUAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 28 November S/D 04 Desember 2022
VOLUME : 1 (SATU) PAKET MINGGU KE : Dua
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 NOMOR KONTRAK : CV. MEGA KONSULTAN

S/D Minggu Lalu Minggu Ini S/D Minggu Ini


NO. URAIAN DAN JENIS PEKERJAAN JUMLAH HARGA Bobot (%) Bobot Bobot Bobot Bobot Bobot Bobot
Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga
(%) g(%) (%) g(%) (%) g(%)
1 2 3 4 5 6 7 8 9 10 11 12 13

I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 100.00 2.86 5,050,000.00 - - - 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 85.21 21.71 38,279,114.30 - - - 85.21 21.71 38,279,114.30
III. PEKERJAAN BETON 61,763,489.27 35.02 - - - 53.55 18.75 33,074,468.94 53.55 18.75 33,074,468.94
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 - - - 9.53 2.77 4,889,015.67 9.53 2.77 4,889,015.67
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - - - - - - -

A REAL COST 176,351,902.03 100.00 24.57 43,329,114.30 21.53 37,963,484.62 46.10 81,292,598.92
B PPn ( 11% ) 19,398,709.22 4,766,202.57 4,175,983.31 8,942,185.88
C TOTAL HARGA 195,750,611.26 48,095,316.88 42,139,467.92 90,234,784.80
D DIBULATKAN 195,750,000.00 48,090,000.00 42,130,000.00 90,230,000.00

Welala, 04 Desember 2022


Mengetahui / Menyetujui :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Dibuat Oleh
Rumah Sakit Umum Daerah (RSUD) Konsultan Pengawas
Kab. Kolaka Timur CV. MEGA KONSULTAN

NUR QOMAR, S.Km ISMAIL, ST


Nip. 19780610 200701 1 020 Konsultan Pengawas
BOBOT KEMAJUAN PEKERJAAN MINGGUAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 28 November S/D 04 Desember 2022
VOLUME : 1 (SATU) PAKET MINGGU KE : Dua
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 KONSULTAN PENGAWAS : CV. MEGA KONSULTAN

S/D Minggu Lalu Minggu Ini S/D Minggu Ini

NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)

1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09

Jumlah 5,050,000.00 2.86 5,050,000.00 2.86 - - 5,050,000.00 2.86


II. PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi M3 38.85 85,937.00 3,338,652.45 1.89 38.85 100.00 3,338,652.45 1.89 - - - - 38.85 100.00 3,338,652.45 1.89
2 Pek. Batu Kosong (Aanstamping) M3 11.66 541,084.00 6,306,334.02 3.58 11.66 100.00 6,306,334.02 3.58 - - - - 11.66 100.00 6,306,334.02 3.58
3 Pek. Pondasi Batu Gunung camp. 1Pc 5Psr M3 29.14 974,990.00 28,408,771.13 16.11 29.14 100.00 28,408,771.13 16.11 - - - - 29.14 100.00 28,408,771.13 16.11
4 Pek. Urugan kembali bekas Galian tanah M3 7.28 30,937.00 225,356.71 0.13 7.28 100.00 225,356.71 0.13 - - - - 7.28 100.00 225,356.71 0.13
5 Pek. Plesteran Pondasi camp. 1Pc : 3Psr M2 88.80 74,818.00 6,643,838.40 3.77 - - - - - - - - - - - -

Jumlah 44,922,952.70 25.47 38,279,114.30 21.71 - - 38,279,114.30 21.71


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
III. PEKERJAAN BETON
1 Pek. Sloef Beton 15 x 20 cm (SF)
- Cor Beton M3 2.22 1,095,378.00 2,426,716.63 1.38 - - - - 2.22 100.00 2,426,716.63 1.38 2.22 100.00 2,426,716.63 1.38
- Besi Beton Kg 448.44 18,841.90 8,449,461.64 4.79 - - - - 448.44 100.00 8,449,461.64 4.79 448.44 100.00 8,449,461.64 4.79
- Bekisting M2 30.30 203,379.00 6,162,383.70 3.49 - - - - 30.30 100.00 6,162,383.70 3.49 30.30 100.00 6,162,383.70 3.49
2 Pek. Kolom Pagar 25x25 cm (T=180)
- Cor Beton M3 1.61 1,095,378.00 1,760,031.46 1.00 - - - - - - - - - - - -
- Besi Beton Kg 126.48 18,841.90 2,383,040.98 1.35 - - - - 126.48 100.00 2,383,040.98 1.35 126.48 100.00 2,383,040.98 1.35
- Kolom Pagar Jadi Bh 138.00 70,000.00 9,660,000.00 5.48 - - - - - - - - - - - -
- Kepala Kolom Pagar Jadi Bh 23.00 70,000.00 1,610,000.00 0.91 - - - - - - - - - - - -
3 Pek. Kolom Gerbang 25x25 cm (T=150)
- Cor Beton M3 0.23 1,095,378.00 248,636.20 0.14 - - - - - - - - - - - -
- Besi Beton Kg 18.33 18,841.90 345,368.26 0.20 - - - - 18.33 100.00 345,368.26 0.20 18.33 100.00 345,368.26 0.20
- Kolom Pagar Jadi Bh 20.00 70,000.00 1,400,000.00 0.79 - - - - - - - - - - - -
4 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 1.00 1,095,378.00 1,092,256.81 0.62 - - - - - - - - - - - -
- Besi Beton Kg 120.58 18,841.90 2,271,943.11 1.29 - - - - 120.58 100.00 2,271,943.11 1.29 120.58 100.00 2,271,943.11 1.29
- Bekisting ( 3 x Pakai ) M2 21.60 119,968.67 2,591,323.20 1.47 - - - - - - - - - - - -
5 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 0.07 1,095,378.00 79,577.46 0.05 - - - - - - - - - - - -
- Besi Beton Kg 17.53 18,841.90 330,309.81 0.19 - - - - 17.53 100.00 330,309.81 0.19 17.53 100.00 330,309.81 0.19
- Bekisting ( 3 x Pakai ) M2 1.87 119,968.67 224,581.34 0.13 - - - - - - - - - - - -
6 Pek. Kolom Pagar 12x12 cm
- Cor Beton M3 0.37 1,095,378.00 402,164.85 0.23 - - - - - - - - - - - -
- Besi Beton Kg 90.91 18,841.90 1,712,963.35 0.97 - - - - 90.91 100.00 1,712,963.35 0.97 90.91 100.00 1,712,963.35 0.97
- Bekisting ( 3 x Pakai ) M2 9.47 119,968.67 1,135,863.34 0.64 - - - - - - - - - - - -
7 Pek. Ring Balok 12x12 cm
- Cor Beton M3 0.64 1,095,378.00 702,146.13 0.40 - - - - - - - - - - - -
- Besi Beton Kg 168.05 18,841.90 3,166,326.53 1.80 - - - - 168.05 100.00 3,166,326.53 1.80 168.05 100.00 3,166,326.53 1.80
- Bekisting (3 x Pakai ) M2 11.04 123,488.67 1,363,314.88 0.77 - - - - - - - - - - - -
8 Pek. Balok latei 12x12 cm
- Cor Beton M3 0.95 1,095,378.00 1,041,741.87 0.59 - - - - - - - - - - - -
- Besi Beton Kg 232.57 18,841.90 4,382,110.17 2.48 - - - - 232.57 100.00 4,382,110.17 2.48 232.57 100.00 4,382,110.17 2.48
- Bekisting (3 x Pakai ) M2 16.34 123,488.67 2,018,298.77 1.14 - - - - - - - - - - - -
9 Pek. Plat Gerbang 390x50x7 cm
- Cor Beton M3 0.54 1,095,378.00 594,356.93 0.34 - - - - - - - - - - - -
- Besi Beton Kg 55.90 18,841.90 1,053,347.63 0.60 - - - - 55.90 100.00 1,053,347.63 0.60 55.90 100.00 1,053,347.63 0.60
- Bekisting ( 2 x Pakai ) M2 10.34 179,953.00 1,861,145.91 1.06 - - - - - - - - - - - -
10 Pek. Plat Papan Nama 580x50x7 cm
- Cor Beton M3 0.20 1,095,378.00 219,471.88 0.12 - - - - - - - - - - - -
- Besi Beton Kg 20.72 18,841.90 390,497.12 0.22 - - - - 20.72 100.00 390,497.12 0.22 20.72 100.00 390,497.12 0.22
- Bekisting ( 2 x Pakai ) M2 3.80 179,953.00 684,109.32 0.39 - - - - - - - - - - - -

Jumlah 61,763,489.27 35.02 - - 33,074,468.94 18.75 33,074,468.94 18.75


IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN
1 Pas. Dinding Bata tebal batu camp. 1PC 5PP M2 76.71 127,465.00 9,778,031.35 5.54 - - - - 38.36 50.00 4,889,015.67 2.77 38.36 50.00 4,889,015.67 2.77
2 Pek. Plesteran Dinding Biasa camp. 1Pc 5Psr M2 202.04 71,209.00 14,387,066.36 8.16 - - - - - - - - - - - -
3 Pek. Pas. Dinding Granit 60x60 untuk Papan Nama M2 4.25 423,982.00 1,799,803.59 1.02 - - - - - - - - - - - -
4 Pek. Profil Beton Kolom Teras Camp. 1PC 2Psr M' 150.00 35,500.00 5,325,000.00 3.02 - - - - - - - - - - - -
5 Pek. Pas. Besi Holow Bh 20.00 1,000,000.00 20,000,000.00 11.34 - - - - - - - - - - - -

Jumlah 51,289,901.30 29.08 - - 4,889,015.67 2.77 4,889,015.67 2.77


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
V. PEKERJAAN PENGECETAN & PEMBERSIHAN
1 Pek. Pengecatan Dinding, Kolom, Sloef, dan Dak M2 340.34 20,621.00 7,018,171.76 3.98 - - - - - - - - - - - -
2 Pek. Huruf Acrilk Lapis Spond ( RSUD KOLAKA TIMUR ) Cm 375.00 7,000.00 2,625,000.00 1.49 - - - - - - - - - - - -
3 Pek. Huruf Acrilk Lapis Spond ( PEMERINTAH KOLAKA M2 340.34 7,000.00 2,382,387.00 1.35 - - - - - - - - - - - -
4 Pek. Logo Acrilik 60 x 70 Bh 1.00 800,000.00 800,000.00 0.45 - - - - - - - - - - - -
5 Pek. Pembersihan Akhir Sisa - Sisa Pekerjaan Ls 1.00 500,000.00 500,000.00 0.28 - - - - - - - - - - - -

Jumlah 13,325,558.76 7.56 - - - - - -


A REAL COST 176,351,902.0 100.0 43,329,114.3 24.57 37,963,484.6 21.53 81,292,598.9 46.10
B PPn ( 11% ) 19,398,709.2 4,766,202.6 4,175,983.3 8,942,185.9
C TOTAL HARGA 195,750,611.3 48,095,316.9 42,139,467.9 90,234,784.8
D DIBULATKAN 195,750,000.0 48,090,000.0 42,130,000.0 90,230,000.0
REKAPITULASI BOBOT KEMAJUAN PEKERJAAN MINGGUAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 21 November S/D 27 November 2022
VOLUME : 1 (SATU) PAKET MINGGU KE : Satu
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 NOMOR KONTRAK : CV. MEGA KONSULTAN

S/D Minggu Lalu Minggu Ini S/D Minggu Ini


NO. URAIAN DAN JENIS PEKERJAAN JUMLAH HARGA Bobot (%) Bobot Bobot Bobot Bobot Bobot Bobot
Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga Tercapai Tertimban Total Harga
(%) g(%) (%) g(%) (%) g(%)
1 2 3 4 5 6 7 8 9 10 11 12 13

I. PEKERJAAN PERSIAPAN 5,050,000.00 2.86 - - - 100.00 2.86 5,050,000.00 100.00 2.86 5,050,000.00
II. PEKERJAAN PONDASI 44,922,952.70 25.47 - - - 85.21 21.71 38,279,114.30 85.21 21.71 38,279,114.30
III. PEKERJAAN BETON 61,763,489.27 35.02 - - - - - - - - -
IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN 51,289,901.30 29.08 - - - - - - - - -
V. PEKERJAAN PENGECETAN & PEMBERSIHAN 13,325,558.76 7.56 - - - - - - - - -

A REAL COST 176,351,902.03 100.00 - - 24.57 43,329,114.30 24.57 43,329,114.30


B PPn ( 11% ) 19,398,709.22 - 4,766,202.57 4,766,202.57
C TOTAL HARGA 195,750,611.26 - 48,095,316.88 48,095,316.88
D DIBULATKAN 195,750,000.00 - 48,090,000.00 48,090,000.00

Welala, 27 November 2022


Mengetahui / Menyetujui :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Dibuat Oleh
Rumah Sakit Umum Daerah (RSUD) Konsultan Pengawas
Kab. Kolaka Timur CV. MEGA KONSULTAN

NUR QOMAR, S.Km ISMAIL, ST


Nip. 19780610 200701 1 020 Konsultan Pengawas
BOBOT KEMAJUAN PEKERJAAN MINGGUAN
PEKERJAAN : BELANJA PEKERJAAN PAGAR RSUD PERIODE TANGGAL : 21 November S/D 27 November 2022
VOLUME : 1 (SATU) PAKET MINGGU KE : Satu
LOKASI : RSUD Kolaka Timur KONTRAKTOR PELAKSANA : CV. PRISMA ARCHI
THN. ANGGARAN : 2022 KONSULTAN PENGAWAS : CV. MEGA KONSULTAN

S/D Minggu Lalu Minggu Ini S/D Minggu Ini

NO. URAIAN DAN JENIS PEKERJAAN SAT. VOL HARGA JUMLAH HARGA Bobot Bobot Bobot Bobot Bobot Bobot Bobot
SATUAN (%) Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg Volume Trcp Jumlah Harga Ttbg
(%) (%) (%) (%) (%) (%)

1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

I. PEKERJAAN PERSIAPAN
1. Pek. Pembongkaran Pagar Lama Ls 1.00 2,500,000.00 2,500,000.00 1.42 - - - - 1.00 100.00 2,500,000.00 1.42 1.00 100.00 2,500,000.00 1.42
2. Pek. Pengukuran dan Pasang Bouwplank Ls 1.00 400,000.00 400,000.00 0.23 - - - - 1.00 100.00 400,000.00 0.23 1.00 100.00 400,000.00 0.23
3. Peralatan Kesehatan dan Keselamatan Kerja (K3) Ls 1.00 1,000,000.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57
4. Administrasi dan Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00 0.57 - - - - 1.00 100.00 1,000,000.00 0.57 1.00 100.00 1,000,000.00 0.57
5. Papan Nama Proyek Ls 1.00 150,000.00 150,000.00 0.09 - - - - 1.00 100.00 150,000.00 0.09 1.00 100.00 150,000.00 0.09

Jumlah 5,050,000.00 2.86 - - 5,050,000.00 2.86 5,050,000.00 2.86


II. PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi M3 38.85 85,937.00 3,338,652.45 1.89 - - - - 38.85 100.00 3,338,652.45 1.89 38.85 100.00 3,338,652.45 1.89
2 Pek. Batu Kosong (Aanstamping) M3 11.66 541,084.00 6,306,334.02 3.58 - - - - 11.66 100.00 6,306,334.02 3.58 11.66 100.00 6,306,334.02 3.58
3 Pek. Pondasi Batu Gunung camp. 1Pc 5Psr M3 29.14 974,990.00 28,408,771.13 16.11 - - - - 29.14 100.00 28,408,771.13 16.11 29.14 100.00 28,408,771.13 16.11
4 Pek. Urugan kembali bekas Galian tanah M3 7.28 30,937.00 225,356.71 0.13 - - - - 7.28 100.00 225,356.71 0.13 7.28 100.00 225,356.71 0.13
5 Pek. Plesteran Pondasi camp. 1Pc : 3Psr M2 88.80 74,818.00 6,643,838.40 3.77 - - - - - - - - - - - -

Jumlah 44,922,952.70 25.47 - - 38,279,114.30 21.71 38,279,114.30 21.71


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
III. PEKERJAAN BETON
1 Pek. Sloef Beton 15 x 20 cm (SF)
- Cor Beton M3 2.22 1,095,378.00 2,426,716.63 1.38 - - - - - - - - - - - -
- Besi Beton Kg 448.44 18,841.90 8,449,461.64 4.79 - - - - - - - - - - - -
- Bekisting M2 30.30 203,379.00 6,162,383.70 3.49 - - - - - - - - - - - -
2 Pek. Kolom Pagar 25x25 cm (T=180)
- Cor Beton M3 1.61 1,095,378.00 1,760,031.46 1.00 - - - - - - - - - - - -
- Besi Beton Kg 126.48 18,841.90 2,383,040.98 1.35 - - - - - - - - - - - -
- Kolom Pagar Jadi Bh 138.00 70,000.00 9,660,000.00 5.48 - - - - - - - - - - - -
- Kepala Kolom Pagar Jadi Bh 23.00 70,000.00 1,610,000.00 0.91 - - - - - - - - - - - -
3 Pek. Kolom Gerbang 25x25 cm (T=150)
- Cor Beton M3 0.23 1,095,378.00 248,636.20 0.14 - - - - - - - - - - - -
- Besi Beton Kg 18.33 18,841.90 345,368.26 0.20 - - - - - - - - - - - -
- Kolom Pagar Jadi Bh 20.00 70,000.00 1,400,000.00 0.79 - - - - - - - - - - - -
4 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 1.00 1,095,378.00 1,092,256.81 0.62 - - - - - - - - - - - -
- Besi Beton Kg 120.58 18,841.90 2,271,943.11 1.29 - - - - - - - - - - - -
- Bekisting ( 3 x Pakai ) M2 21.60 119,968.67 2,591,323.20 1.47 - - - - - - - - - - - -
5 Pek. Kolom 15x50 (T=225)
- Cor Beton M3 0.07 1,095,378.00 79,577.46 0.05 - - - - - - - - - - - -
- Besi Beton Kg 17.53 18,841.90 330,309.81 0.19 - - - - - - - - - - - -
- Bekisting ( 3 x Pakai ) M2 1.87 119,968.67 224,581.34 0.13 - - - - - - - - - - - -
6 Pek. Kolom Pagar 12x12 cm
- Cor Beton M3 0.37 1,095,378.00 402,164.85 0.23 - - - - - - - - - - - -
- Besi Beton Kg 90.91 18,841.90 1,712,963.35 0.97 - - - - - - - - - - - -
- Bekisting ( 3 x Pakai ) M2 9.47 119,968.67 1,135,863.34 0.64 - - - - - - - - - - - -
7 Pek. Ring Balok 12x12 cm
- Cor Beton M3 0.64 1,095,378.00 702,146.13 0.40 - - - - - - - - - - - -
- Besi Beton Kg 168.05 18,841.90 3,166,326.53 1.80 - - - - - - - - - - - -
- Bekisting (3 x Pakai ) M2 11.04 123,488.67 1,363,314.88 0.77 - - - - - - - - - - - -
8 Pek. Balok latei 12x12 cm
- Cor Beton M3 0.95 1,095,378.00 1,041,741.87 0.59 - - - - - - - - - - - -
- Besi Beton Kg 232.57 18,841.90 4,382,110.17 2.48 - - - - - - - - - - - -
- Bekisting (3 x Pakai ) M2 16.34 123,488.67 2,018,298.77 1.14 - - - - - - - - - - - -
9 Pek. Plat Gerbang 390x50x7 cm
- Cor Beton M3 0.54 1,095,378.00 594,356.93 0.34 - - - - - - - - - - - -
- Besi Beton Kg 55.90 18,841.90 1,053,347.63 0.60 - - - - - - - - - - - -
- Bekisting ( 2 x Pakai ) M2 10.34 179,953.00 1,861,145.91 1.06 - - - - - - - - - - - -
10 Pek. Plat Papan Nama 580x50x7 cm
- Cor Beton M3 0.20 1,095,378.00 219,471.88 0.12 - - - - - - - - - - - -
- Besi Beton Kg 20.72 18,841.90 390,497.12 0.22 - - - - - - - - - - - -
- Bekisting ( 2 x Pakai ) M2 3.80 179,953.00 684,109.32 0.39 - - - - - - - - - - - -

Jumlah 61,763,489.27 35.02 - - - - - -


IV. PEKERJAAN PASANGAN DINDING DAN PLESTERAN
1 Pas. Dinding Bata tebal batu camp. 1PC 5PP M2 76.71 127,465.00 9,778,031.35 5.54 - - - - - - - - - - - -
2 Pek. Plesteran Dinding Biasa camp. 1Pc 5Psr M2 202.04 71,209.00 14,387,066.36 8.16 - - - - - - - - - - - -
3 Pek. Pas. Dinding Granit 60x60 untuk Papan Nama M2 4.25 423,982.00 1,799,803.59 1.02 - - - - - - - - - - - -
4 Pek. Profil Beton Kolom Teras Camp. 1PC 2Psr M' 150.00 35,500.00 5,325,000.00 3.02 - - - - - - - - - - - -
5 Pek. Pas. Besi Holow Bh 20.00 1,000,000.00 20,000,000.00 11.34 - - - - - - - - - - - -

Jumlah 51,289,901.30 29.08 - - - - - -


1 2 4 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
V. PEKERJAAN PENGECETAN & PEMBERSIHAN
1 Pek. Pengecatan Dinding, Kolom, Sloef, dan Dak M2 340.34 20,621.00 7,018,171.76 3.98 - - - - - - - - - - - -
2 Pek. Huruf Acrilk Lapis Spond ( RSUD KOLAKA TIMUR ) Cm 375.00 7,000.00 2,625,000.00 1.49 - - - - - - - - - - - -
3 Pek. Huruf Acrilk Lapis Spond ( PEMERINTAH KOLAKA M2 340.34 7,000.00 2,382,387.00 1.35 - - - - - - - - - - - -
4 Pek. Logo Acrilik 60 x 70 Bh 1.00 800,000.00 800,000.00 0.45 - - - - - - - - - - - -
5 Pek. Pembersihan Akhir Sisa - Sisa Pekerjaan Ls 1.00 500,000.00 500,000.00 0.28 - - - - - - - - - - - -

Jumlah 13,325,558.76 7.56 - - - - - -


A REAL COST 176,351,902.0 100.0 - - 43,329,114.3 24.57 43,329,114.3 24.57
B PPn ( 11% ) 19,398,709.2 - 4,766,202.6 4,766,202.6
C TOTAL HARGA 195,750,611.3 - 48,095,316.9 48,095,316.9
D DIBULATKAN 195,750,000.0 - 48,090,000.0 48,090,000.0