DEVIASI BOBOT
BOBOT RENCANA MINGGUAN 0.700% 6.630% 6.950% 4.140% 5.050% 9.320% 5.220% 8.640% 9.420% 3.010% 1.890% 1.060% 0.880% 1.250% 2.040% 2.040% %
RENCANA KOMULATIF MINGGUAN 0.700% 7.330% 14.280% 18.420% 23.470% 32.790% 38.010% 46.650% #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
100
80
60
40
20
BOBOT REALISASI MINGGUAN 0.000% 7.441% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
BOBOT REALISASI KUMULATIF MINGGUAN 0.000% 7.441%
DEVIASI BOBOT -0.700% 0.111%
Keterangan
: Rencana
: Realisasi
Dibuat Oleh
Disetujui Oleh, CV. MEGA GEMILANG
CV. CALVINDAM JAYA EC
M. RAPIK
DEDI ROSPIAN, ST Pelaksana Lapangan
Inspector
PEKERJAAN : PENGGANTIAN TULISAN NAMA JALAN DI KOTA TEMBILAHAN KECAMATAN TEMBILAHAN
KONTRAKTOR PELAKSANA : CV. MEGA GEMILANG
KONSULTAN PENGAWAS : CV. CALVINDAM JAYA EC SERTIFIKAT : BULAN AGUSTUS
JANGKA WAKTU PELAKSANAAN : 30 HARI KALENDER ( 21 AGUSTUS S/D 19 SEPTEMBER 2017) TANGGAL : 31 Agustus 2017
REKAPITULASI
KONTRAK PROSENTASE PEMBAYARAN ( % )
NILAI PEKERJAAN YG DIBAYAR
NO URAIAN NILAI BOBOT S/D BULAN BULAN S/D BULAN
( Rp ) LALU INI INI ( Rp )
DINAS PERHUBUNGAN PENGGANTIAN TULISAN NAMA JALAN DI KOTA TEMBILAHAN KECAMATAN TEMBILAHAN CV. CALVINDAM JAYA EC
LAPORAN MINGGUAN
JL. Pangeran Diponegoro No. 744 Tlp/Faks. (0768) 22195 KONTRAKTOR PELAKSANA
TANGGAL S/D TANGGAL
Email : disbubinhil@gmail.com MINGGU KE : I ( SATU )
21 Agustus 2017 27 Agustus 2017 CV. MEGA GEMILANG
TEMBILAHAN
PROSENTASE TERHADAP
KONTRAK ASLI REALISASI VOLUME
BAGIAN PEKERJAAN (%) REALISASI
NO URAIAN PEKERJAAN VOLUME BOBOT (%) S/D
KONTRAK HARGA SATUAN MINGGU S/D MINGGU MINGGU INI MINGGU S/D MINGGU MINGGU INI
(Rp) JUMLAH HARGA (Rp) BOBOT % MINGGU INI LALU INI LALU INI
1 2 3 4 5 6 7 8 9 10 11 12 13
I PEKERJAAN PENDAHULUAN
1 Pek. Pembongkaran Papan Nama Lama 1.00 Ls 2,100,000.00 2,100,000.00 4.63% 1.00 - 1.00 100% 0% 100% 4.63%
2 Pek. Papan Nama Kegiatan 1.00 Ls 250,000.00 250,000.00 0.55% 1.00 - 1.00 100% 0% 100% 0.55%
Sub Total 2,350,000.00 5.18% 5.18%
II PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi 1.05 M3 27,200.00 28,560.00 0.06% 1.05 - 1.05 100% 0% 100% 0.06%
2 Pek. Urugan Paisr 10 cm 0.15 M3 232,969.45 34,945.42 0.08% 0.15 - 0.15 100% 0% 100% 0.08%
3 Pek. Pemasangan Cerucuk Bakau Pj 5 m 30.00 M1 5,612.13 168,363.97 0.37% 30.00 - 30.00 100% 0% 100% 0.37%
4 Pek. Cor Lantai Kerja Camp 1:3:5 0.72 M3 1,099,306.14 791,500.42 1.75% 0.72 - 0.72 100% 0% 100% 1.75%
Sub Total 1,023,369.80 2.26% 2.26%
III PEKERJAAN NAMA TYPE I (BUAT BARU 3 BUAH)
1 Pek. Pembuatan Tulisan Nama Jalan Type I
- Pek. Pengedaan ACP ( Alumunium Komposit Panel 3 mm ) 4.50 M2 1,000,000.00 4,500,000.00 9.93% - - - 0% 0% 0% 0.00%
- Pek. Pengecatan 4.50 M2 46,611.23 209,750.53 0.46% - - - 0% 0% 0% 0.00%
- Pek. Pengadaan dan Pemasangan Baut 18.00 Bh 5,000.00 90,000.00 0.20% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 6.00 Bh 910,000.00 5,460,000.00 12.04% - - - 0% 0% 0% 0.00%
- Pek. Pemasangan Mahkota Tiang 6.00 Bh 34,000.00 204,000.00 0.45% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Tiang Nama Jalan +Pemasangan Pipa Dia 4" dan 2,5" Galpanis Tebal 1,5 mm 3.00 Bh 3,000,000.00 9,000,000.00 19.85% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Bingkai Papan Nama Besi UNP 10 6.00 Bh 1,200,000.00 7,200,000.00 15.88% - - - 0% 0% 0% 0.00%
Sub Total 26,663,750.53 58.81% 0.00%
IV PEKERJAAN NAMA TYPE II (PENGGANTIAN TULISAN NAMA JALAN 6 BUAH)
1 Pek. Pembuatan Tulisan Nama Jalan Type I
- Pek. Pengecatan 9.00 M2 46,611.23 419,501.07 0.93% - - - 0% 0% 0% 0.00%
- Pek. Pengadaan dan Pemasangan Baut 36.00 Bh 5,000.00 180,000.00 0.40% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 12.00 Bh 910,000.00 10,920,000.00 24.09% - - - 0% 0% 0% 0.00%
- Pek. Pemasangan Mahkota Tiang 12.00 Bh 34,000.00 408,000.00 0.90% - - - 0% 0% 0% 0.00%
2 Pek. Pembuatan Papan Tulisan Tulisan Nama Jalan Type II
- Pek. Pengedaan ACP ( Alumunium Komposit Panel 3 mm ) 1.20 M2 1,000,000.00 1,200,000.00 2.65% - - - 0% 0% 0% 0.00%
- Pek. Pengecatan 0.48 M2 46,611.23 22,373.39 0.05% - - - 0% 0% 0% 0.00%
- Pek. Pengadaan dan Pemasangan Baut 8.00 Bh 5,000.00 40,000.00 0.09% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 4.00 Bh 455,000.00 1,820,000.00 4.01% - - - 0% 0% 0% 0.00%
- Pek. Pemasangan Mahkota Tiang 2.00 Bh 34,000.00 68,000.00 0.15% - - - 0% 0% 0% 0.00%
Sub Total 15,077,874.46 33.26% 0.00%
V PEKERJAAN LAIN-LAIN
1 Pek. Pembersihan Akhir 1.00 Ls 220,100.00 220,100.00 0.49% - - - 0% 0% 0% 0.00%
Sub Total 220,100.00 0.49% 0.00%
JUMLAH 45,335,094.79 BOBOT S/D MINGGU INI 7.44%
PPN 10% 4,533,509.48 BOBOT MINGGU INI 7.44%
100.00%
TOTAL JUMLAH 49,868,604.27 BOBOT MINGGU LALU 0.00%
DIBULATKAN 49,869,000.00
1 2 3 4 5 6 7 8 9 10 11 12 13
DEDI ROSPIAN, ST M. RAPIK
Inspector Pelaksana Lapangan
PEMERINTAH KABUPATEN INDRAGIRI HILIR PEKERJAAN KONSULTAN PENGAWAS
DINAS PERHUBUNGAN PENGGANTIAN TULISAN NAMA JALAN DI KOTA TEMBILAHAN KECAMATAN TEMBILAHAN CV. CALVINDAM JAYA EC
LAPORAN MINGGUAN
JL. Pangeran Diponegoro No. 744 Tlp/Faks. (0768) 22195 KONTRAKTOR PELAKSANA
TANGGAL S/D TANGGAL
Email : disbubinhil@gmail.com MINGGU KE : II ( DUA)
28 Agustus 2017 31 Agustus 2017 CV. MEGA GEMILANG
TEMBILAHAN
PROSENTASE TERHADAP
KONTRAK ASLI REALISASI VOLUME
BAGIAN PEKERJAAN (%) REALISASI
NO URAIAN PEKERJAAN VOLUME BOBOT (%) S/D
KONTRAK HARGA SATUAN MINGGU S/D MINGGU MINGGU INI MINGGU S/D MINGGU MINGGU INI
(Rp) JUMLAH HARGA (Rp) BOBOT % MINGGU INI LALU INI LALU INI
1 2 3 4 5 6 7 8 9 10 11 12 13
I PEKERJAAN PENDAHULUAN
1 Pek. Pembongkaran Papan Nama Lama 1.00 Ls 2,100,000.00 2,100,000.00 4.63% - 1.00 1.00 0% 100% 100% 4.63%
2 Pek. Papan Nama Kegiatan 1.00 Ls 250,000.00 250,000.00 0.55% - 1.00 1.00 0% 100% 100% 0.55%
Sub Total 2,350,000.00 5.18% 5.18%
II PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi 1.05 M3 27,200.00 28,560.00 0.06% - 1.05 1.05 0% 100% 100% 0.06%
2 Pek. Urugan Paisr 10 cm 0.15 M3 232,969.45 34,945.42 0.08% - 0.15 0.15 0% 100% 100% 0.08%
3 Pek. Pemasangan Cerucuk Bakau Pj 5 m 30.00 M1 5,612.13 168,363.97 0.37% - 30.00 30.00 0% 100% 100% 0.37%
4 Pek. Cor Lantai Kerja Camp 1:3:5 0.72 M3 1,099,306.14 791,500.42 1.75% - 0.72 0.72 0% 100% 100% 1.75%
Sub Total 1,023,369.80 2.26% 2.26%
III PEKERJAAN NAMA TYPE I (BUAT BARU 3 BUAH)
1 Pek. Pembuatan Tulisan Nama Jalan Type I
- Pek. Pengedaan ACP ( Alumunium Komposit Panel 3 mm ) 4.50 M2 1,000,000.00 4,500,000.00 9.93% 4.50 - 4.50 100% 0% 100% 9.93%
- Pek. Pengecatan 4.50 M2 46,611.23 209,750.53 0.46% 4.50 - 4.50 100% 0% 100% 0.46%
- Pek. Pengadaan dan Pemasangan Baut 18.00 Bh 5,000.00 90,000.00 0.20% 18.00 - 18.00 100% 0% 100% 0.20%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 6.00 Bh 910,000.00 5,460,000.00 12.04% - - - 0% 0% 0% 0.00%
- Pek. Pemasangan Mahkota Tiang 6.00 Bh 34,000.00 204,000.00 0.45% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Tiang Nama Jalan +Pemasangan Pipa Dia 4" dan 2,5" Galpanis Tebal 1,5 mm 3.00 Bh 3,000,000.00 9,000,000.00 19.85% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Bingkai Papan Nama Besi UNP 10 6.00 Bh 1,200,000.00 7,200,000.00 15.88% - - - 0% 0% 0% 0.00%
Sub Total 26,663,750.53 58.81% 10.59%
IV PEKERJAAN NAMA TYPE II (PENGGANTIAN TULISAN NAMA JALAN 6 BUAH)
1 Pek. Pembuatan Tulisan Nama Jalan Type I
- Pek. Pengecatan 9.00 M2 46,611.23 419,501.07 0.93% - - - 0% 0% 0% 0.00%
- Pek. Pengadaan dan Pemasangan Baut 36.00 Bh 5,000.00 180,000.00 0.40% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 12.00 Bh 910,000.00 10,920,000.00 24.09% - - - 0% 0% 0% 0.00%
- Pek. Pemasangan Mahkota Tiang 12.00 Bh 34,000.00 408,000.00 0.90% - - - 0% 0% 0% 0.00%
2 Pek. Pembuatan Papan Tulisan Tulisan Nama Jalan Type II
- Pek. Pengedaan ACP ( Alumunium Komposit Panel 3 mm ) 1.20 M2 1,000,000.00 1,200,000.00 2.65% - - - 0% 0% 0% 0.00%
- Pek. Pengecatan 0.48 M2 46,611.23 22,373.39 0.05% - - - 0% 0% 0% 0.00%
- Pek. Pengadaan dan Pemasangan Baut 8.00 Bh 5,000.00 40,000.00 0.09% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 4.00 Bh 455,000.00 1,820,000.00 4.01% - - - 0% 0% 0% 0.00%
- Pek. Pemasangan Mahkota Tiang 2.00 Bh 34,000.00 68,000.00 0.15% - - - 0% 0% 0% 0.00%
Sub Total 15,077,874.46 33.26% 0.00%
V PEKERJAAN LAIN-LAIN
1 Pek. Pembersihan Akhir 1.00 Ls 220,100.00 220,100.00 0.49% - - - 0% 0% 0% 0.00%
Sub Total 220,100.00 0.49% 0.00%
JUMLAH 45,335,094.79 BOBOT S/D MINGGU INI 18.03%
PPN 10% 4,533,509.48 BOBOT MINGGU INI 10.59%
100.00%
TOTAL JUMLAH 49,868,604.27 BOBOT MINGGU LALU 7.44%
DIBULATKAN 49,869,000.00
1 2 3 4 5 6 7 8 9 10 11 12 13
DEDI ROSPIAN, ST M. RAPIK
Inspector Pelaksana Lapangan
PEKERJAAN : PENGGANTIAN TULISAN NAMA JALAN DI KOTA TEMBILAHAN KECAMATAN TEMBILAHAN
KONTRAKTOR PELAKSANA : CV. MEGA GEMILANG
KONSULTAN PENGAWAS : CV. CALVINDAM JAYA EC SERTIFIKAT : BULAN SEPTEMBER
JANGKA WAKTU PELAKSANAAN : 30 HARI KALENDER ( 21 AGUSTUS S/D 19 SEPTEMBER 2017) TANGGAL : 17 September 2017
REKAPITULASI
KONTRAK PROSENTASE PEMBAYARAN ( % )
NILAI PEKERJAAN YG DIBAYAR
NO URAIAN NILAI BOBOT S/D BULAN BULAN S/D BULAN
( Rp ) LALU INI INI ( Rp )
Terbilang : Empat Puluh Sembilan Juta Delapan Ratus Enam Puluh Delapan Ribu Rupiah
DINAS PERHUBUNGAN PENGGANTIAN TULISAN NAMA JALAN DI KOTA TEMBILAHAN KECAMATAN TEMBILAHAN CV. CALVINDAM JAYA EC
LAPORAN MINGGUAN
JL. Pangeran Diponegoro No. 744 Tlp/Faks. (0768) 22195 KONTRAKTOR PELAKSANA
TANGGAL S/D TANGGAL
Email : disbubinhil@gmail.com MINGGU KE : I ( SATU )
01 September 2017 03 September 2017 CV. MEGA GEMILANG
TEMBILAHAN
PROSENTASE TERHADAP
KONTRAK ASLI REALISASI VOLUME
BAGIAN PEKERJAAN (%) REALISASI
NO URAIAN PEKERJAAN VOLUME BOBOT (%) S/D
KONTRAK HARGA SATUAN MINGGU S/D MINGGU MINGGU INI MINGGU S/D MINGGU MINGGU INI
(Rp) JUMLAH HARGA (Rp) BOBOT % MINGGU INI LALU INI LALU INI
1 2 3 4 5 6 7 8 9 10 11 12 13
I PEKERJAAN PENDAHULUAN
1 Pek. Pembongkaran Papan Nama Lama 1.00 Ls 2,100,000.00 2,100,000.00 4.63% - 1.00 1.00 0% 100% 100% 4.63%
2 Pek. Papan Nama Kegiatan 1.00 Ls 250,000.00 250,000.00 0.55% - 1.00 1.00 0% 100% 100% 0.55%
Sub Total 2,350,000.00 5.18% 5.18%
II PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi 1.05 M3 27,200.00 28,560.00 0.06% - 1.05 1.05 0% 100% 100% 0.06%
2 Pek. Urugan Paisr 10 cm 0.15 M3 232,969.45 34,945.42 0.08% - 0.15 0.15 0% 100% 100% 0.08%
3 Pek. Pemasangan Cerucuk Bakau Pj 5 m 30.00 M1 5,612.13 168,363.97 0.37% - 30.00 30.00 0% 100% 100% 0.37%
4 Pek. Cor Lantai Kerja Camp 1:3:5 0.72 M3 1,099,306.14 791,500.42 1.75% - 0.72 0.72 0% 100% 100% 1.75%
Sub Total 1,023,369.80 2.26% 2.26%
III PEKERJAAN NAMA TYPE I (BUAT BARU 3 BUAH)
1 Pek. Pembuatan Tulisan Nama Jalan Type I
- Pek. Pengedaan ACP ( Alumunium Komposit Panel 3 mm ) 4.50 M2 1,000,000.00 4,500,000.00 9.93% - 4.50 4.50 0% 100% 100% 9.93%
- Pek. Pengecatan 4.50 M2 46,611.23 209,750.53 0.46% - 4.50 4.50 0% 100% 100% 0.46%
- Pek. Pengadaan dan Pemasangan Baut 18.00 Bh 5,000.00 90,000.00 0.20% - 18.00 18.00 0% 100% 100% 0.20%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 6.00 Bh 910,000.00 5,460,000.00 12.04% 6.00 - 6.00 100% 0% 100% 12.04%
- Pek. Pemasangan Mahkota Tiang 6.00 Bh 34,000.00 204,000.00 0.45% 6.00 - 6.00 100% 0% 100% 0.45%
- Pek. Pembuatan Tiang Nama Jalan +Pemasangan Pipa Dia 4" dan 2,5" Galpanis Tebal 1,5 mm 3.00 Bh 3,000,000.00 9,000,000.00 19.85% 3.00 - 3.00 100% 0% 100% 19.85%
- Pek. Pembuatan Bingkai Papan Nama Besi UNP 10 6.00 Bh 1,200,000.00 7,200,000.00 15.88% 6.00 - 6.00 100% 0% 100% 15.88%
Sub Total 26,663,750.53 58.81% 58.81%
IV PEKERJAAN NAMA TYPE II (PENGGANTIAN TULISAN NAMA JALAN 6 BUAH)
1 Pek. Pembuatan Tulisan Nama Jalan Type I
- Pek. Pengecatan 9.00 M2 46,611.23 419,501.07 0.93% - - - 0% 0% 0% 0.00%
- Pek. Pengadaan dan Pemasangan Baut 36.00 Bh 5,000.00 180,000.00 0.40% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 12.00 Bh 910,000.00 10,920,000.00 24.09% - - - 0% 0% 0% 0.00%
- Pek. Pemasangan Mahkota Tiang 12.00 Bh 34,000.00 408,000.00 0.90% - - - 0% 0% 0% 0.00%
2 Pek. Pembuatan Papan Tulisan Tulisan Nama Jalan Type II
- Pek. Pengedaan ACP ( Alumunium Komposit Panel 3 mm ) 1.20 M2 1,000,000.00 1,200,000.00 2.65% - - - 0% 0% 0% 0.00%
- Pek. Pengecatan 0.48 M2 46,611.23 22,373.39 0.05% - - - 0% 0% 0% 0.00%
- Pek. Pengadaan dan Pemasangan Baut 8.00 Bh 5,000.00 40,000.00 0.09% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 4.00 Bh 455,000.00 1,820,000.00 4.01% - - - 0% 0% 0% 0.00%
- Pek. Pemasangan Mahkota Tiang 2.00 Bh 34,000.00 68,000.00 0.15% - - - 0% 0% 0% 0.00%
Sub Total 15,077,874.46 33.26% 0.00%
V PEKERJAAN LAIN-LAIN
1 Pek. Pembersihan Akhir 1.00 Ls 220,100.00 220,100.00 0.49% - - - 0% 0% 0% 0.00%
Sub Total 220,100.00 0.49% 0.00%
JUMLAH 45,335,094.79 BOBOT S/D MINGGU INI 66.26%
PPN 10% 4,533,509.48 BOBOT MINGGU INI 48.23%
100.00%
TOTAL JUMLAH 49,868,604.27 BOBOT MINGGU LALU 18.03%
DIBULATKAN 49,869,000.00
1 2 3 4 5 6 7 8 9 10 11 12 13
DEDI ROSPIAN, ST M. RAPIK
Inspector Pelaksana Lapangan
PEMERINTAH KABUPATEN INDRAGIRI HILIR PEKERJAAN KONSULTAN PENGAWAS
DINAS PERHUBUNGAN PENGGANTIAN TULISAN NAMA JALAN DI KOTA TEMBILAHAN KECAMATAN TEMBILAHAN CV. CALVINDAM JAYA EC
LAPORAN MINGGUAN
JL. Pangeran Diponegoro No. 744 Tlp/Faks. (0768) 22195 KONTRAKTOR PELAKSANA
TANGGAL S/D TANGGAL
Email : disbubinhil@gmail.com MINGGU KE : II ( DUA)
04 September 2017 10 September 2017 CV. MEGA GEMILANG
TEMBILAHAN
PROSENTASE TERHADAP
KONTRAK ASLI REALISASI VOLUME
BAGIAN PEKERJAAN (%) REALISASI
NO URAIAN PEKERJAAN VOLUME BOBOT (%) S/D
KONTRAK HARGA SATUAN MINGGU S/D MINGGU MINGGU INI MINGGU S/D MINGGU MINGGU INI
(Rp) JUMLAH HARGA (Rp) BOBOT % MINGGU INI LALU INI LALU INI
1 2 3 4 5 6 7 8 9 10 11 12 13
I PEKERJAAN PENDAHULUAN
1 Pek. Pembongkaran Papan Nama Lama 1.00 Ls 2,100,000.00 2,100,000.00 4.63% - 1.00 1.00 0% 100% 100% 4.63%
2 Pek. Papan Nama Kegiatan 1.00 Ls 250,000.00 250,000.00 0.55% - 1.00 1.00 0% 100% 100% 0.55%
Sub Total 2,350,000.00 5.18% 5.18%
II PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi 1.05 M3 27,200.00 28,560.00 0.06% - 1.05 1.05 0% 100% 100% 0.06%
2 Pek. Urugan Paisr 10 cm 0.15 M3 232,969.45 34,945.42 0.08% - 0.15 0.15 0% 100% 100% 0.08%
3 Pek. Pemasangan Cerucuk Bakau Pj 5 m 30.00 M1 5,612.13 168,363.97 0.37% - 30.00 30.00 0% 100% 100% 0.37%
4 Pek. Cor Lantai Kerja Camp 1:3:5 0.72 M3 1,099,306.14 791,500.42 1.75% - 0.72 0.72 0% 100% 100% 1.75%
Sub Total 1,023,369.80 2.26% 2.26%
III PEKERJAAN NAMA TYPE I (BUAT BARU 3 BUAH)
1 Pek. Pembuatan Tulisan Nama Jalan Type I
- Pek. Pengedaan ACP ( Alumunium Komposit Panel 3 mm ) 4.50 M2 1,000,000.00 4,500,000.00 9.93% - 4.50 4.50 0% 100% 100% 9.93%
- Pek. Pengecatan 4.50 M2 46,611.23 209,750.53 0.46% - 4.50 4.50 0% 100% 100% 0.46%
- Pek. Pengadaan dan Pemasangan Baut 18.00 Bh 5,000.00 90,000.00 0.20% - 18.00 18.00 0% 100% 100% 0.20%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 6.00 Bh 910,000.00 5,460,000.00 12.04% - 6.00 6.00 0% 100% 100% 12.04%
- Pek. Pemasangan Mahkota Tiang 6.00 Bh 34,000.00 204,000.00 0.45% - 6.00 6.00 0% 100% 100% 0.45%
- Pek. Pembuatan Tiang Nama Jalan +Pemasangan Pipa Dia 4" dan 2,5" Galpanis Tebal 1,5 mm 3.00 Bh 3,000,000.00 9,000,000.00 19.85% - 3.00 3.00 0% 100% 100% 19.85%
- Pek. Pembuatan Bingkai Papan Nama Besi UNP 10 6.00 Bh 1,200,000.00 7,200,000.00 15.88% - 6.00 6.00 0% 100% 100% 15.88%
Sub Total 26,663,750.53 58.81% 58.81%
IV PEKERJAAN NAMA TYPE II (PENGGANTIAN TULISAN NAMA JALAN 6 BUAH)
1 Pek. Pembuatan Tulisan Nama Jalan Type I
- Pek. Pengecatan 9.00 M2 46,611.23 419,501.07 0.93% 9.00 - 9.00 100% 0% 100% 0.93%
- Pek. Pengadaan dan Pemasangan Baut 36.00 Bh 5,000.00 180,000.00 0.40% 36.00 - 36.00 100% 0% 100% 0.40%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 12.00 Bh 910,000.00 10,920,000.00 24.09% 12.00 - 12.00 100% 0% 100% 24.09%
- Pek. Pemasangan Mahkota Tiang 12.00 Bh 34,000.00 408,000.00 0.90% - - - 0% 0% 0% 0.00%
2 Pek. Pembuatan Papan Tulisan Tulisan Nama Jalan Type II
- Pek. Pengedaan ACP ( Alumunium Komposit Panel 3 mm ) 1.20 M2 1,000,000.00 1,200,000.00 2.65% - - - 0% 0% 0% 0.00%
- Pek. Pengecatan 0.48 M2 46,611.23 22,373.39 0.05% - - - 0% 0% 0% 0.00%
- Pek. Pengadaan dan Pemasangan Baut 8.00 Bh 5,000.00 40,000.00 0.09% - - - 0% 0% 0% 0.00%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 4.00 Bh 455,000.00 1,820,000.00 4.01% - - - 0% 0% 0% 0.00%
- Pek. Pemasangan Mahkota Tiang 2.00 Bh 34,000.00 68,000.00 0.15% - - - 0% 0% 0% 0.00%
Sub Total 15,077,874.46 33.26% 25.41%
V PEKERJAAN LAIN-LAIN
1 Pek. Pembersihan Akhir 1.00 Ls 220,100.00 220,100.00 0.49% - - - 0% 0% 0% 0.00%
Sub Total 220,100.00 0.49% 0.00%
JUMLAH 45,335,094.79 BOBOT S/D MINGGU INI 91.67%
PPN 10% 4,533,509.48 BOBOT MINGGU INI 25.41%
100.00%
TOTAL JUMLAH 49,868,604.27 BOBOT MINGGU LALU 66.26%
DIBULATKAN 49,869,000.00
1 2 3 4 5 6 7 8 9 10 11 12 13
DEDI ROSPIAN, ST M. RAPIK
Inspector Pelaksana Lapangan
PEMERINTAH KABUPATEN INDRAGIRI HILIR PEKERJAAN KONSULTAN PENGAWAS
DINAS PERHUBUNGAN PENGGANTIAN TULISAN NAMA JALAN DI KOTA TEMBILAHAN KECAMATAN TEMBILAHAN CV. CALVINDAM JAYA EC
LAPORAN MINGGUAN
JL. Pangeran Diponegoro No. 744 Tlp/Faks. (0768) 22195 KONTRAKTOR PELAKSANA
TANGGAL S/D TANGGAL
Email : disbubinhil@gmail.com MINGGU KE : III (TIGA)
11 September 2017 17 September 2017 CV. MEGA GEMILANG
TEMBILAHAN
PROSENTASE TERHADAP
KONTRAK ASLI REALISASI VOLUME
BAGIAN PEKERJAAN (%) REALISASI
NO URAIAN PEKERJAAN VOLUME BOBOT (%) S/D
KONTRAK HARGA SATUAN MINGGU S/D MINGGU MINGGU INI MINGGU S/D MINGGU MINGGU INI
(Rp) JUMLAH HARGA (Rp) BOBOT % MINGGU INI LALU INI LALU INI
1 2 3 4 5 6 7 8 9 10 11 12 13
I PEKERJAAN PENDAHULUAN
1 Pek. Pembongkaran Papan Nama Lama 1.00 Ls 2,100,000.00 2,100,000.00 4.63% - 1.00 1.00 0% 100% 100% 4.63%
2 Pek. Papan Nama Kegiatan 1.00 Ls 250,000.00 250,000.00 0.55% - 1.00 1.00 0% 100% 100% 0.55%
Sub Total 2,350,000.00 5.18% 5.18%
II PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi 1.05 M3 27,200.00 28,560.00 0.06% - 1.05 1.05 0% 100% 100% 0.06%
2 Pek. Urugan Paisr 10 cm 0.15 M3 232,969.45 34,945.42 0.08% - 0.15 0.15 0% 100% 100% 0.08%
3 Pek. Pemasangan Cerucuk Bakau Pj 5 m 30.00 M1 5,612.13 168,363.97 0.37% - 30.00 30.00 0% 100% 100% 0.37%
4 Pek. Cor Lantai Kerja Camp 1:3:5 0.72 M3 1,099,306.14 791,500.42 1.75% - 0.72 0.72 0% 100% 100% 1.75%
Sub Total 1,023,369.80 2.26% 2.26%
III PEKERJAAN NAMA TYPE I (BUAT BARU 3 BUAH)
1 Pek. Pembuatan Tulisan Nama Jalan Type I
- Pek. Pengedaan ACP ( Alumunium Komposit Panel 3 mm ) 4.50 M2 1,000,000.00 4,500,000.00 9.93% - 4.50 4.50 0% 100% 100% 9.93%
- Pek. Pengecatan 4.50 M2 46,611.23 209,750.53 0.46% - 4.50 4.50 0% 100% 100% 0.46%
- Pek. Pengadaan dan Pemasangan Baut 18.00 Bh 5,000.00 90,000.00 0.20% - 18.00 18.00 0% 100% 100% 0.20%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 6.00 Bh 910,000.00 5,460,000.00 12.04% - 6.00 6.00 0% 100% 100% 12.04%
- Pek. Pemasangan Mahkota Tiang 6.00 Bh 34,000.00 204,000.00 0.45% - 6.00 6.00 0% 100% 100% 0.45%
- Pek. Pembuatan Tiang Nama Jalan +Pemasangan Pipa Dia 4" dan 2,5" Galpanis Tebal 1,5 mm 3.00 Bh 3,000,000.00 9,000,000.00 19.85% - 3.00 3.00 0% 100% 100% 19.85%
- Pek. Pembuatan Bingkai Papan Nama Besi UNP 10 6.00 Bh 1,200,000.00 7,200,000.00 15.88% - 6.00 6.00 0% 100% 100% 15.88%
Sub Total 26,663,750.53 58.81% 58.81%
IV PEKERJAAN NAMA TYPE II (PENGGANTIAN TULISAN NAMA JALAN 6 BUAH)
1 Pek. Pembuatan Tulisan Nama Jalan Type I
- Pek. Pengecatan 9.00 M2 46,611.23 419,501.07 0.93% - 9.00 9.00 0% 100% 100% 0.93%
- Pek. Pengadaan dan Pemasangan Baut 36.00 Bh 5,000.00 180,000.00 0.40% - 36.00 36.00 0% 100% 100% 0.40%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 12.00 Bh 910,000.00 10,920,000.00 24.09% - 12.00 12.00 0% 100% 100% 24.09%
- Pek. Pemasangan Mahkota Tiang 12.00 Bh 34,000.00 408,000.00 0.90% 12.00 - 12.00 100% 0% 100% 0.90%
2 Pek. Pembuatan Papan Tulisan Tulisan Nama Jalan Type II
- Pek. Pengedaan ACP ( Alumunium Komposit Panel 3 mm ) 1.20 M2 1,000,000.00 1,200,000.00 2.65% 1.20 - 1.20 100% 0% 100% 2.65%
- Pek. Pengecatan 0.48 M2 46,611.23 22,373.39 0.05% 0.48 - 0.48 100% 0% 100% 0.05%
- Pek. Pengadaan dan Pemasangan Baut 8.00 Bh 5,000.00 40,000.00 0.09% 8.00 - 8.00 100% 0% 100% 0.09%
- Pek. Pembuatan Tulisan Skotlet (depan belakang) 4.00 Bh 455,000.00 1,820,000.00 4.01% 4.00 - 4.00 100% 0% 100% 4.01%
- Pek. Pemasangan Mahkota Tiang 2.00 Bh 34,000.00 68,000.00 0.15% 2.00 - 2.00 100% 0% 100% 0.15%
Sub Total 15,077,874.46 33.26% 33.26%
V PEKERJAAN LAIN-LAIN
1 Pek. Pembersihan Akhir 1.00 Ls 220,100.00 220,100.00 0.49% 1.00 - 1.00 100% 0% 100% 0.49%
Sub Total 220,100.00 0.49% 0.49%
JUMLAH 45,335,094.79 BOBOT S/D MINGGU INI 100.00%
PPN 10% 4,533,509.48 BOBOT MINGGU INI 8.33%
100.00%
TOTAL JUMLAH 49,868,604.27 BOBOT MINGGU LALU 91.67%
DIBULATKAN 49,869,000.00
1 2 3 4 5 6 7 8 9 10 11 12 13
DEDI ROSPIAN, ST M. RAPIK
Inspector Pelaksana Lapangan
PHO TGL 18 SEPTEMBER