RAB - 4 - JULI
RAB - 4 - JULI
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
11,000.00
15,000.00
1,800.00
925.00
28,725.00 alt. Pakai upah bouwplank
10,500.00
3,625.00
65,268.00
1,328.51
3,110.94
1,310.40
19,845.00
104,987.85
-
-
133,712.85
20,056.93 15%
153,769.78
11,000.00
15,000.00
1,800.00
925.00
28,725.00
32,760.00
436.80
22,050.00
55,246.80
-
-
83,971.80
12,595.77 15%
96,567.57
110,000.00 2.000
300,000.00 2.000
150,000.00 1.000
36,000.00 0.300
9,250.00 0.050
605,250.00 alt. Pakai upah pembuatan gudang
10,500.00
288,000.00
1,747.20
11,797.50
50,750.00
39,855.38
26,570.25
51,849.00
25,200.00
9,791.25
41,600.00
9,200.00
9,750.00
4,365.90
58,275.00
639,251.48 belum dimasukan atap seng
-
-
1,244,501.48
186,675.22 15%
1,431,176.70
110,000.00
300,000.00
36,000.00
9,250.00
455,250.00
14,280.00
491,400.00 koefisien samakan dengan pembuatan kantor
6,552.00
15,225.00
7,971.08
17,283.00
58,275.00
9,791.25
620,777.33
-
-
1,076,027.33
161,404.10 15%
1,237,431.42
110,000.00
300,000.00
36,000.00
9,250.00
455,250.00
10,500.00
297,600.00
6,552.00
26,100.00
7,971.08
17,283.00
58,275.00
358,698.38
782,979.45
-
-
1,238,229.45
185,734.42 15%
1,423,963.87
11,000.00
9,250.00
20,250.00
-
-
-
-
20,250.00
3,037.50 15%
23,287.50
27,500.00 1
2,550.00 2
360.00 0.2
2,405.00 0.05
32,815.00
47,500.00
7,068.00
-
54,568.00
-
-
87,383.00
13,107.45 15%
100,490.45
Jumlah Harga (Rp)
45,000.00
5,400.00
50,400.00
94,500.00
29,400.00
1,747.20
-
125,647.20
-
-
176,047.20
26,407.08 15%
202,454.28
1,466,740.00
123,210.00
1,589,950.00
-
-
-
-
1,589,950.00
238,492.50 15%
1,828,442.50
733,370.00
61,605.00
794,975.00
-
-
-
-
794,975.00
119,246.25 15%
914,221.25
4,620.00
600.00
360.00
7,770.00
13,350.00
27,876.96
27,876.96
-
-
41,226.96
6,184.04 15%
47,411.00
27,500.00
2,550.00
360.00
2,405.00
32,815.00
45,000.00
-
45,000.00
-
-
77,815.00
11,672.25 15%
89,487.25
2.3.1. HARGA SATUAN PEKERJAAN TANAH
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
6. Pembuangan 1 m3 tanah sejauh 30 meter
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.330 110,000.00
Mandor L.04 OH 0.010 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
* pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
DIV. 2.3.1 - 2
8. Pemadatan tanah 1 m3 tanah (per 20 cm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.500 110,000.00
Mandor L.04 OH 0.050 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 10% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
82,500.00
4,625.00
87,125.00
-
-
-
-
87,125.00
13,068.75 15%
100,193.75
99,000.00
8,325.00
107,325.00
-
-
-
-
107,325.00
16,098.75 15%
123,423.75
110,000.00
5,920.00
115,920.00
-
-
-
-
115,920.00
17,388.00 15%
133,308.00
132,000.00
8,325.00
140,325.00
-
-
-
-
140,325.00
21,048.75 15%
161,373.75
5,500.00
925.00
6,425.00
-
-
-
-
6,425.00
963.75 15%
7,388.75
Jumlah Harga (Rp)
36,300.00
1,850.00
38,150.00
-
-
-
-
38,150.00
5,722.50 15%
43,872.50
27,500.00
4,625.00
32,125.00
-
-
-
-
32,125.00
4,818.75 15%
36,943.75
kerjaan galian
55,000.00
9,250.00
64,250.00
-
-
-
-
64,250.00
9,637.50 15%
73,887.50
33,000.00
1,850.00
34,850.00
318,843.00
-
318,843.00
-
-
353,693.00
53,053.95 15%
406,746.95
27,500.00
4,625.00
32,125.00
318,843.00
318,843.00
-
-
350,968.00
52,645.20 15%
403,613.20
27,500.00
4,625.00
32,125.00
334,593.00
334,593.00
-
-
366,718.00
55,007.70 15%
421,725.70
3.2.1. HARGA SATUAN PEKERJAAN PONDASI
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
3. Pemasangan 1 m3 pondasi batu bata (8x8x16) cm campuran 1 SP: 3 PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 2.025 110,000.00
Tukang Batu L.02 OH 0.675 150,000.00
Kepala Tukang L.03 OH 0.068 180,000.00
Mandor L.04 OH 0.101 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Batu bata bh 726.000 840.00
Sement Portland kg 170.022 1,450.00
Pasir Pasang m3 0.470 265,702.50
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 3.2.1 - 1
4. Pemasangan 1 m3 pondasi batu bata (8x8x16) cm campuran 1 SP: 4 PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 2.025 110,000.00
Tukang Batu L.02 OH 0.675 150,000.00
Kepala Tukang L.03 OH 0.068 180,000.00
Mandor L.04 OH 0.101 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Batu bata bh 726.000 840.00
Sement Portland kg 136.998 1,450.00
Pasir Pasang m3 0.480 265,702.50
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
5. 1 m2 pasang cerucup gelam untuk pondasi (p.1,5m-20 cm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 110,000.00
Tukang Batu L.02 OH 150,000.00
Kepala Tukang L.03 OH 0.030 180,000.00
Mandor L.04 OH 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Gelam dia.6-8 btg 6.000 8,400.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% x D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
165,000.00
112,500.00
13,500.00
13,875.00
304,875.00
470,799.00
292,900.00
128,865.71
892,564.71
-
-
1,197,439.71
179,615.96 15%
1,377,055.67
165,000.00
112,500.00
13,500.00
13,875.00
304,875.00
470,799.00
236,350.00
138,165.30
845,314.30
-
-
1,150,189.30
172,528.40 15%
1,322,717.70
Jumlah Harga (Rp)
222,750.00
101,250.00
12,150.00
18,731.25
354,881.25
609,840.00
246,531.90
124,763.27
981,135.17
-
-
1,336,016.42
200,402.46 15%
1,536,418.88
222,750.00
101,250.00
12,150.00
18,731.25
354,881.25
609,840.00
198,647.10
127,505.32
935,992.42
-
-
1,290,873.67
193,631.05 15%
1,484,504.72
Jumlah Harga (Rp)
33,000.00
-
5,400.00
-
38,400.00
50,400.00
50,400.00
-
-
88,800.00
13,320.00 15%
102,120.00
33,000.00
5,550.00
38,550.00
780,000.00
138,075.00
918,075.00
124,800.00
-
124,800.00
1,081,425.00
162,213.75 15%
1,243,638.75
4.1.1. HARGA SATUAN PEKERJAAN BETON
1. Membuat 1 m3 beton mutu F'c=9,8 Mpa (K125), slump (12±2) cm, w/c=0,78
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 110,000.00
Tukang Batu L.02 OH 0.275 150,000.00
Kepala Tukang L.03 OH 0.028 180,000.00
Mandor L.04 OH 0.083 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 276.000 1,450.00
Pasir Beton kg 828.000 189.79
Kerikil (Maks. 30mm) kg 1012.000 452.04
Air Liter 215.000 66.60
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
2. Membuat 1 m3 lantai kerja beton mutu F'c=7,4 Mpa (K100) slump (3-6)cm, w/c=0,87
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.200 110,000.00
Tukang Batu L.02 OH 0.200 150,000.00
Kepala Tukang L.03 OH 0.020 180,000.00
Mandor L.04 OH 0.060 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 230.000 1,450.00
Pasir Beton kg 893.000 189.79
Kerikil (Maks. 30mm) kg 1027.000 452.04
Air Liter 200.000 66.60
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
3. Membuat 1 m3 beton mutu F'c=14,5 Mpa (K175), slump (12±2) cm, w/c=0,66
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 110,000.00
Tukang Batu L.02 OH 0.275 150,000.00
Kepala Tukang L.03 OH 0.028 180,000.00
Mandor L.04 OH 0.083 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 326.000 1,450.00
Pasir Beton kg 760.000 189.79
Kerikil (Maks. 30mm) kg 1029.000 452.04
Air Liter 215.000 66.60
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
4. Membuat 1 m3 beton mutu F'c=19,3 Mpa (K225), slump (12±2) cm, w/c=0,58
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 110,000.00
Tukang Batu L.02 OH 0.275 150,000.00
Kepala Tukang L.03 OH 0.028 180,000.00
Mandor L.04 OH 0.083 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 371.000 1,450.00
Pasir Beton kg 698.000 189.79
Kerikil (Maks. 30mm) kg 1047.000 452.04
Air Liter 215.000 66.60
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
5. Membuat 1 m3 beton mutu F'c=21,7 Mpa (K250), slump (12±2) cm, w/c=0,56
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 110,000.00
Tukang Batu L.02 OH 0.275 150,000.00
Kepala Tukang L.03 OH 0.028 180,000.00
Mandor L.04 OH 0.083 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 384.000 1,450.00
Pasir Beton kg 692.000 189.79
Kerikil (Maks. 30mm) kg 1039.000 452.04
Air Liter 215.000 66.60
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
6. Membuat 1 m3 beton mutu F'c=26,4 Mpa (K300), slump (12±2) cm, w/c=0,52
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 110,000.00
Tukang Batu L.02 OH 0.275 150,000.00
Kepala Tukang L.03 OH 0.028 180,000.00
Mandor L.04 OH 0.083 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 413.000 1,450.00
Pasir Beton kg 681.000 189.79
Kerikil (Maks. 30mm) kg 1021.000 452.04
Air Liter 215.000 66.60
JUMLAH TENAGA BAHAN
C. PERALATAN
7. Membuat 1 m3 beton mutu F'c=31,2 Mpa (K350), slump (12±2) cm, w/c=0,48
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 2.100 110,000.00
Tukang Batu L.02 OH 0.350 150,000.00
Kepala Tukang L.03 OH 0.035 180,000.00
Mandor L.04 OH 0.105 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 448.000 1,450.00
Pasir Beton kg 667.000 189.79
Kerikil (Maks. 30mm) kg 1000.000 452.04
Air Liter 215.000 66.60
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
1 kg
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
1 kg
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
11. Pemasangan 1 m2 bekesting untuk sloof
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.520 110,000.00
Tukang Kayu L.02 OH 0.260 150,000.00
Kepala Tukang L.03 OH 0.026 180,000.00
Mandor L.04 OH 0.026 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kayu m3 0.045 1,600,000.00
Paku 5-10 cm kg 0.300 21,840.00
Minyak bekesting Liter 0.100 44,100.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
32 Membuat 1 m3 beton mutu F'c=21,7 Mpa (K250), slump (12±2) cm, w/c=0,56 menggunakan molen
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.323 110,000.00
Tukang Batu L.02 OH 0.189 150,000.00
Kepala Tukang L.03 OH 0.019 180,000.00
Mandor L.04 OH 0.1320 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 384.00 1,450.00
Pasir beton kg 692.00 189.79
Kerikil (maks. 30mm) kg 1,039.00 452.04
Air Liter 215.00 66.60
JUMLAH TENAGA BAHAN
C. PERALATAN
Molen sewa/hari 0.25 600,000.00
JUMLAH TENAGA ALAT
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
33 Membuat 1 m3 beton mutu F'c=21,7 Mpa (K250), slump (12±2) cm, w/c=0,56 Untuk perkerasan jalan
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.323 110,000.00
Tukang Batu L.02 OH 0.189 150,000.00
Kepala Tukang L.03 OH 0.019 180,000.00
Mandor L.04 OH 0.1320 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 384.00 1,450.00
Pasir beton kg 692.00 189.79
Kerikil (maks. 30mm) kg 1,039.00 452.04
Air Liter 215.00 66.60
JUMLAH TENAGA BAHAN
C. PERALATAN
Batching plan E43 Jam 0.1004 433,012.93
Truck mixer E49 Jam 0.2369 786,400.89
Water Tank trucE23 Jam 0.0422 327,347.63
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
78
Jumlah Harga (Rp)
181,500.00
41,250.00
5,040.00
15,355.00
243,145.00
400,200.00
157,144.05
457,468.98
14,319.00
1,029,132.03
-
-
1,272,277.03
190,841.55 15%
1,463,118.58
m, w/c=0,87
Jumlah Harga (Rp)
132,000.00
30,000.00
3,600.00
11,100.00
176,700.00
333,500.00
169,480.24
464,249.64
13,320.00
980,549.88
-
-
1,157,249.88
173,587.48 15%
1,330,837.36
181,500.00
41,250.00
5,040.00
15,355.00
243,145.00
472,700.00
144,238.50
465,153.73
14,319.00
1,096,411.23
-
-
1,339,556.23
200,933.44 15%
1,540,489.67
181,500.00
41,250.00
5,040.00
15,355.00
243,145.00
537,950.00
132,471.68
473,290.53
14,319.00
1,158,031.21
-
-
1,401,176.21
210,176.43 15%
1,611,352.64
181,500.00
41,250.00
5,040.00
15,355.00
243,145.00
556,800.00
131,332.95
469,674.18
14,319.00
1,172,126.13
-
-
1,415,271.13
212,290.67 15%
1,627,561.80
181,500.00
41,250.00
5,040.00
15,355.00
243,145.00
598,850.00
129,245.29
461,537.38
14,319.00
1,203,951.67
-
-
1,447,096.67
217,064.50 15%
1,664,161.17
231,000.00
52,500.00
6,300.00
19,425.00
309,225.00
649,600.00
126,588.26
452,044.44
14,319.00
1,242,551.71
-
-
1,551,776.71
232,766.51 15%
1,784,543.21
7,700.00
10,500.00
1,260.00
740.00
20,200.00
164,850.00
3,841.11
168,691.11
-
-
188,891.11
28,333.67 15%
217,224.78
21,722.48
2,750.00
3,750.00
4,500.00
185.00
11,185.00
179,742.16
1,280.37
181,022.53
-
-
192,207.53
28,831.13 15%
221,038.65
22,103.87
57,200.00
39,000.00
4,680.00
4,810.00
105,690.00
64,000.00
6,552.00
4,410.00
74,962.00
-
-
180,652.00
27,097.80 15%
207,749.80
Jumlah Harga (Rp)
57,200.00
39,000.00
4,680.00
4,810.00
105,690.00
72,000.00
6,552.00
4,410.00
82,962.00
-
-
188,652.00
28,297.80 15%
216,949.80
216,949.80
32,542.47 15%
249,492.27
72,600.00
49,500.00
5,940.00
6,105.00
134,145.00
64,000.00
8,736.00
8,820.00
40,950.00
49,796.25
24,000.00
196,302.25
-
-
330,447.25
49,567.09 15%
380,014.34
72,600.00
49,500.00
5,940.00
6,105.00
134,145.00
64,000.00
8,736.00
8,820.00
49,140.00
49,796.25
24,000.00
204,492.25
-
-
338,637.25
50,795.59 15%
389,432.84
72,600.00
49,500.00
5,940.00
6,105.00
134,145.00
109,200.00
8,736.00
8,820.00
40,950.00
49,796.25
72,000.00
289,502.25
-
-
423,647.25
63,547.09 15%
487,194.34
72,600.00
49,500.00
5,940.00
6,105.00
134,145.00
94,500.00
8,736.00
2,400.00
54,600.00
49,796.25
36,000.00
33,600.00
279,632.25
-
-
413,777.25
62,066.59 15%
475,843.84
72,600.00
49,500.00
5,940.00
6,105.00
134,145.00
94,500.00
8,736.00
6,615.00
40,950.00
49,796.25
24,000.00
224,597.25
-
-
358,742.25
53,811.34 15%
412,553.59
16,500.00
7,500.00
900.00
1,480.00
26,380.00
83,160.00
13,104.00
6,000.00
102,264.00
-
-
128,644.00
19,296.60 15%
147,940.60
583,000.00
41,250.00
195,000.00
157,500.00
47,160.00
49,025.00
1,072,935.00
630,000.00
32,760.00
17,640.00
2,472,750.00
57,616.65
487,200.00
143,479.35
494,310.60
4,335,756.60
-
-
5,408,691.60
811,303.74 15%
6,219,995.34
621,500.00
41,250.00
234,000.00
210,000.00
58,140.00
52,355.00
1,217,245.00
850,500.00
43,680.00
26,460.00
3,297,000.00
76,822.20
487,200.00
143,479.35
494,310.60
5,419,452.15
-
-
6,636,697.15
995,504.57 15%
7,632,201.72
775,500.00
41,250.00
247,500.00
315,000.00
72,540.00
65,305.00
1,517,095.00
1,260,000.00
87,360.00
88,200.00
4,945,500.00
115,233.30
487,200.00
143,479.35
366.16
409,500.00
497,962.50
240,000.00
8,274,801.31
-
-
9,791,896.31
1,468,784.45 15%
11,260,680.75
698,500.00
41,250.00
247,500.00
210,000.00
59,940.00
58,830.00
1,316,020.00
1,008,000.00
69,888.00
70,560.00
3,297,000.00
76,822.20
487,200.00
143,479.35
366.16
382,200.00
398,370.00
192,000.00
6,125,885.71
-
-
7,441,905.71
1,116,285.86 15%
8,558,191.56
583,000.00
41,250.00
195,000.00
157,500.00
47,700.00
49,025.00
1,073,475.00
1,008,000.00
69,888.00
70,560.00
2,472,750.00
57,616.65
487,200.00
143,479.35
366.16
327,600.00
398,370.00
384,000.00
5,419,830.16
-
-
6,493,305.16
973,995.77 15%
7,467,300.93
583,000.00
41,250.00
195,000.00
157,500.00
47,160.00
49,025.00
1,072,935.00
756,000.00
69,888.00
70,560.00
2,472,750.00
57,616.65
487,200.00
143,479.35
366.16
436,800.00
398,370.00
288,000.00
5,181,030.16
-
-
6,253,965.16
938,094.77 15%
7,192,059.93
49,796.25
43,680.00
3,276.00
96,752.25
-
-
141,467.25
21,220.09 15%
162,687.34
19,800.00
3,000.00
3,000.00
3,000.00
1,080.00
1,665.00
31,545.00
5,460.00
21.84
4,410.00
47,100.00
11,523.33
5,800.00
1,594.22
5,492.34
81,401.73
-
-
112,946.73
16,942.01 15%
129,888.73
32,670.00
4,950.00
4,950.00
450.00
1,800.00
2,775.00
47,595.00
8,190.00
436.80
4,410.00
56,520.00
1,280.37
7,975.00
2,391.32
9,153.90
90,357.39
-
-
137,952.39
20,692.86 15%
158,645.25
-
-
1,405,600.50
210,840.08 15%
1,616,440.58
-
-
1,267,450.50
190,117.58 15%
1,457,568.08
-
-
2,162,950.50
324,442.58
2,487,393.08
-
-
67,281.00
10,092.15 15%
77,373.15
24,200.00
16,500.00
1,980.00
2,035.00
44,715.00
49,796.25
43,680.00
3,276.00
96,752.25
-
-
141,467.25
21,220.09 15%
162,687.34
56 menggunakan molen
Jumlah Harga (Rp)
145,530.00
28,350.00
3,420.00
24,420.00
201,720.00
556,800.00
131,332.95
469,674.18
14,319.00
1,172,126.13
150,000.00
150,000.00
1,523,846.13
228,576.92 15%
1,752,423.05
145,530.00
28,350.00
3,420.00
24,420.00
201,720.00
556,800.00
131,332.95
469,674.18
14,319.00
1,172,126.13
43,474.50
186,298.37
13,814.07
243,586.94
1,617,433.07
242,614.96 15%
1,860,048.03
4.2.1. HARGA SATUAN PEKERJAAN BESI & ALUMINIUM
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
4. Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 110,000.00
Tukang Las Biasa L.02 OH 0.275 150,000.00
Kepala Tukang L.03 OH 0.028 180,000.00
Mandor L.04 OH 0.083 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Besi siku L 30.30.3 kg 15.000 10,725.00
Besi plat baja kg 32.800 10,725.00
Kawat las kg 0.050 69,037.50
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
12. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60x120cm, dinding partisi
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 110,000.00
Tukang Besi L.02 OH 0.250 150,000.00
Kepala Tukang L.03 OH 0.025 180,000.00
Mandor L.04 OH 0.013 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Rangka metal hollow 40.40.2 mm m' 3.500 5,375.00
Assesoris (perkuatan, las dll) Ls 100%xrangka
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
14. Pemasangan 1 bh pintu KM/WC Aluminium warna lengkap (kusen, kunci engsel setara dekson) -
No. frame louver
Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 110,000.00
Tukang L.03 OH 0.500 150,000.00
Kepala Tukang L.03 OH 0.050 180,000.00
Mandor L.04 OH 0.0030 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pintu Aluminium - frame louver unit 1.000 2,450,000.00
Sealent tube 0.432 28,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
15. Pemasangan 1 bh pintu Aluminium warna lengkap (kusen, kunci engsel setara dekson) - ice glass
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 110,000.00
Tukang L.03 OH 0.500 150,000.00
Kepala Tukang L.03 OH 0.050 180,000.00
Mandor L.04 OH 0.0030 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pintu Aluminium - ice glass unit 1.000 3,750,000.00
Sealent tube 0.432 28,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
16. Pemasangan 1 bh pintu KM/WC Aluminium warna urat kayu lengkap (kusen, kunci engsel setara
No. dekson)Uraian
- frame louver Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 110,000.00
Tukang L.03 OH 0.500 150,000.00
Kepala Tukang L.03 OH 0.050 180,000.00
Mandor L.04 OH 0.0030 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pintu Aluminium - frame louver unit 1.000 3,600,000.00
Sealent tube 0.432 28,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
17. Pemasangan 1 bh pintu Aluminium warna urat kayu lengkap (kusen, kunci engsel setara dekson)
No. ice glass
Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 110,000.00
Tukang L.03 OH 0.500 150,000.00
Kepala Tukang L.03 OH 0.050 180,000.00
Mandor L.04 OH 0.0030 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pintu Aluminium - ice glass unit 1.000 4,300,000.00
Sealent tube 0.432 28,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
6,600.00
9,000.00
1,080.00
555.00
17,235.00
18,055.00
18,055.00
-
-
35,290.00
5,293.50 15%
40,583.50
6,600.00
9,000.00
1,080.00
555.00
17,235.00
42,262.50
42,262.50
-
-
59,497.50
8,924.63 15%
68,422.13
16,986.52
23,066.69
40,053.21
5,360.00
5,360.00
72,518.21
10,877.73 15%
83,395.94
181,500.00
41,250.00
5,040.00
15,355.00
243,145.00
160,875.00
351,780.00
3,451.88
516,106.88
-
-
759,251.88
113,887.78 15%
873,139.66
4,400.00
3,000.00
360.00
370.00
8,130.00
1,139.00
1,139.00
26,353.13
3,952.97 15%
30,306.10
48,400.00
66,000.00
7,920.00
4,070.00
126,390.00
828,345.00
828,345.00
-
-
954,735.00
143,210.25 15%
1,097,945.25
4,730.00
6,450.00
774.00
388.50
12,342.50
178,750.00
330.00
1,680.00
180,760.00
-
-
193,102.50
28,965.38 15%
222,067.88 1,065,925.80
9,350.00
12,750.00
1,530.00
777.00
24,407.00
715,000.00
674,520.00
1,389,520.00
-
-
1,413,927.00
212,089.05 0.15
1,626,016.05 2,276,422.47
9,350.00
12,750.00
1,620.00
925.00
24,645.00
-
-
1,586,205.00
237,930.75 0.15
1,824,135.75 3,064,548.06
183,700.00
250,500.00
30,060.00
15,355.00
479,615.00
66,248.33
82,068.92
148,317.25
-
-
627,932.25
94,189.84 0.15
722,122.09
22,000.00
30,000.00
3,600.00
185.00
55,785.00
41,123.25
327.60
59,850.00
101,300.85
-
-
157,085.85
23,562.88 0.15
180,648.73
m, dinding partisi
Jumlah Harga (Rp)
27,500.00
37,500.00
4,500.00
2,405.00
71,905.00
18,812.50
5,375.00
24,187.50
-
-
96,092.50
14,413.88 0.15
110,506.38
38,500.00
52,500.00
6,300.00
3,330.00
100,630.00
21,500.00
5,375.00
26,875.00
-
-
127,505.00
19,125.75 0.15
146,630.75
5,500.00
75,000.00
9,000.00
555.00
90,055.00
2,450,000.00
12,096.00
2,462,096.00
-
-
2,552,151.00
382,822.65 0.15
2,934,973.65 4,108,963.11
5,500.00
75,000.00
9,000.00
555.00
90,055.00
3,750,000.00
12,096.00
3,762,096.00
-
-
3,852,151.00
577,822.65 0.15
4,429,973.65 6,201,963.11
5,500.00
75,000.00
9,000.00
555.00
90,055.00
3,600,000.00
12,096.00
3,612,096.00
-
-
3,702,151.00
555,322.65 0.15
4,257,473.65 5,960,463.11
5,500.00
75,000.00
9,000.00
555.00
90,055.00
4,300,000.00
12,096.00
4,312,096.00
-
-
4,402,151.00
660,322.65 0.15
5,062,473.65 7,087,463.11
4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
3. Pemasangan 1 m2 dinding bata lobang (8x8x16) cm tebal 1/2 batu campuran 1 SP:3PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 110,000.00
Tukang Batu L.02 OH 0.100 150,000.00
Kepala Tukang L.03 OH 0.010 180,000.00
Mandor L.04 OH 0.015 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Bata merah bh 66.000 840.00
Semen Portland kg 7.832 1,450.00
Pasir pasang m3 0.022 265,702.50
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 4.4.1 - 1
4. Pemasangan 1 m2 dinding bata lubang (8x8x16) cm tebal 1/2 batu campuran 1 SP:4PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 110,000.00
Tukang Batu L.02 OH 0.100 150,000.00
Kepala Tukang L.03 OH 0.010 180,000.00
Mandor L.04 OH 0.015 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Bata merah bh 66.000 840.00
Semen Portland kg 6.268 1,450.00
Pasir pasang m3 0.023 265,702.50
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
5. Pemasangan 1 m2 dinding terawang (roster) 10x12x20 campuran 1SP : 4PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 110,000.00
Tukang Batu L.02 OH 0.100 150,000.00
Kepala Tukang L.03 OH 0.010 180,000.00
Mandor L.04 OH 0.015 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Bata rooster bh 45.000 12,500.00
Roster terawang kg 11.000 7,455.00
Pasir pasang m3 0.035 265,702.50
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
7. Pemasangan 1 m2 dinding roster keramik 20x20 campuran 1SP : 4PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 110,000.00
Tukang Batu L.02 OH 0.100 150,000.00
Kepala Tukang L.03 OH 0.010 180,000.00
Mandor L.04 OH 0.015 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Rooster keramik 20x20cm bh 25.000 50,400.00
Semen Portland kg 11.000 1,450.00
Pasir pasang m3 0.035 265,702.50
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
tu campuran 1 SP:3PP 50.00 m2 pasangan dinding batu bata
Jumlah Harga (Rp)
- 32.95 zak
-
10 0.015 0.15
ampuran 1 SP:4PP 11 0.08 0.88
Jumlah Harga (Rp) 1.03 1.0609
66,000.00
30,000.00
3,600.00
5,550.00
105,150.00
101,640.00
25,408.35
16,308.82
143,357.17
-
-
248,507.17
37,276.08 15%
285,783.24
batu campuran 1 SP:3PP
Jumlah Harga (Rp)
33,000.00
15,000.00
1,800.00
2,775.00
52,575.00
125,163.21
18,774.48 15%
143,937.69
33,000.00
15,000.00
1,800.00
2,775.00
52,575.00
55,440.00
9,087.88
6,226.74
70,754.61
-
-
123,329.61
18,499.44 15%
141,829.06
ran 1SP : 4PP
Jumlah Harga (Rp)
33,000.00
15,000.00
1,800.00
2,775.00
52,575.00
706,379.59
105,956.94 15%
812,336.53
33,000.00
15,000.00
1,800.00
2,775.00
52,575.00
760,256.34
114,038.45 15%
874,294.79
Jumlah Harga (Rp)
33,000.00
15,000.00
1,800.00
2,775.00
52,575.00
1,337,824.59
200,673.69 15%
1,538,498.28
33,000.00
15,000.00
1,800.00
2,775.00
52,575.00
734,580.00
15,950.00
9,299.59
759,829.59
812,404.59
121,860.69 15%
934,265.28
waktu (hari)
5
6
2
0.2
0.3
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
3. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 110,000.00
Tukang Ba L.02 OH 0.150 150,000.00
Kepala Tu L.03 OH 0.015 180,000.00
Mandor L.04 OH 0.015 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 6.240 1,450.00
Pasir pasang m3 0.024 265,702.50
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 4.4.2 - 1
4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 20 mm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.260 110,000.00
Tukang Ba L.02 OH 0.200 150,000.00
Kepala Tu L.03 OH 0.020 180,000.00
Mandor L.04 OH 0.013 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 8.320 1,450.00
Pasir pasang m3 0.032 265,702.50
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
9. Pemasangan 1 m2 acian
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.200 110,000.00
Tukang Ba L.02 OH 0.100 150,000.00
Kepala Tu L.03 OH 0.010 180,000.00
Mandor L.04 OH 0.010 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland kg 3.250 1,450.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
33,000.00
22,500.00
2,700.00
2,775.00
60,975.00
11,275.20
6,111.16
17,386.36
-
-
78,361.36
11,754.20 15%
90,115.56
28,600.00
30,000.00
3,600.00
2,405.00
64,605.00
15,033.60
8,236.78
23,270.38
-
-
87,875.38
13,181.31 15%
101,056.68
Jumlah Harga (Rp)
33,000.00
22,500.00
2,700.00
2,775.00
60,975.00
9,048.00
6,376.86
15,424.86
-
-
76,399.86
11,459.98 15%
87,859.84
28,600.00
30,000.00
3,600.00
2,405.00
64,605.00
12,064.00
8,502.48
20,566.48
-
-
85,171.48
12,775.72 15%
97,947.20
7,516.80
6,908.27
14,425.07
-
-
45,095.07
6,764.26 15%
51,859.32
8,800.00
60,000.00
7,200.00
740.00
76,740.00
725.00
3,454.13
4,179.13
-
-
80,919.13
12,137.87 15%
93,057.00
33,000.00
15,000.00
1,800.00
2,775.00
52,575.00
6,264.00
1,594.22
7,858.22
-
-
60,433.22
9,064.98 15%
69,498.20
puran 1 SP : 2 PP
Jumlah Harga (Rp)
33,000.00
22,500.00
2,700.00
2,775.00
60,975.00
9,193.00
3,188.43
12,381.43
-
-
73,356.43
11,003.46 15%
84,359.89
22,000.00
15,000.00
1,800.00
1,850.00
40,650.00
4,712.50
4,712.50
-
-
45,362.50
6,804.38 15%
52,166.88
4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 4.4.3 - 1
4. Pemasangan 1 m2 lantai keramik putih ukuran 40cm x 40cm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 110,000.00
Tukang Ba L.02 OH 0.125 150,000.00
Kepala Tu L.03 OH 0.013 180,000.00
Mandor L.04 OH 0.013 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Keramik 40x40 (putih) bh 6.630 17,570.00
Semen Portland kg 10.000 1,450.00
Pasir pasang kg 0.045 189.79
Semen warna kg 1.500 16,500.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 4.4.3 - 2
7. Pemasangan 1 m2 lantai keramik warna ukuran 40cm x 40cm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 110,000.00
Tukang Ba L.02 OH 0.125 150,000.00
Kepala Tu L.03 OH 0.013 180,000.00
Mandor L.04 OH 0.013 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Keramik 40x40 warna bh 6.630 17,570.00
Semen Portland kg 10.000 1,450.00
Pasir pasang kg 0.045 189.79
Semen warna kg 1.500 16,500.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 4.4.3 - 3
10. Pemasangan 1 m' plint Granite Tile ukuran 10 cm x 60 cm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.090 110,000.00
Tukang Ba L.02 OH 0.090 150,000.00
Kepala Tu L.03 OH 0.035 180,000.00
Mandor L.04 OH 0.005 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Plint granite tile bh 1.760 12,900.00
Semen Portland kg 1.140 1,450.00
Pasir pasang kg 0.003 189.79
Semen warna kg 0.050 16,500.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 4.4.3 - 4
13. Pemasangan 1 m2 lantai lantai karpet t. 4-5 mm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.170 110,000.00
Tukang Ba L.02 OH 0.170 150,000.00
Kepala Tu L.03 OH 0.017 180,000.00
Mandor L.04 OH 0.009 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Karpet m2 1.050 87,500.00
Lem kg 0.350 51,580.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 4.4.3 - 6
19. Pemasangan 1 m2 dinding batu tempel hitam
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.700 110,000.00
Tukang Ba L.02 OH 0.350 150,000.00
Kepala Tu L.03 OH 0.035 180,000.00
Mandor L.04 OH 0.035 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Batu tempel m2 1.100 130,000.00
Semen Portland kg 11.750 1,450.00
Pasir pasang kg 0.035 189.79
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 4.4.3 - 8
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
AN PENUTUP DINDING
27,500.00
18,750.00
2,340.00
2,405.00
50,995.00
236,070.00
11,875.50
8.54
26,730.00
274,684.04
-
-
325,679.04
48,851.86 15%
374,530.90
27,500.00
18,750.00
2,340.00
2,405.00
50,995.00
569,162.88
11,875.50
8.54
26,730.00
607,776.92
-
-
658,771.92
98,815.79 15%
757,587.71
27,500.00
18,750.00
2,340.00
2,405.00
50,995.00
60,164.71
14,500.00
8.54
24,750.00
99,423.25
-
-
150,418.25
22,562.74 15%
172,980.99
27,500.00
18,750.00
2,340.00
2,405.00
50,995.00
116,489.10
14,500.00
8.54
24,750.00
155,747.64
-
-
206,742.64
31,011.40 15%
237,754.04
29,700.00
20,250.00
2,520.00
2,590.00
55,060.00
82,250.70
15,080.00
8.54
26,730.00
124,069.24
-
-
179,129.24
26,869.39 15%
205,998.63
27,500.00
18,750.00
2,340.00
2,405.00
50,995.00
60,164.71
14,500.00
8.54
24,750.00
99,423.25
-
-
150,418.25
22,562.74 15%
172,980.99
27,500.00
18,750.00
2,340.00
2,405.00
50,995.00
116,489.10
14,500.00
8.54
24,750.00
155,747.64
-
-
206,742.64
31,011.40 15%
237,754.04
9,900.00
13,500.00
6,300.00
925.00
30,625.00
5,638.37
1,653.00
0.57
825.00
8,116.94
-
-
38,741.94
5,811.29 15%
44,553.23
9,900.00
13,500.00
6,300.00
925.00
30,625.00
11,593.75
1,653.00
0.57
825.00
14,072.32
-
-
44,697.32
6,704.60 15%
51,401.92
9,900.00
13,500.00
6,300.00
925.00
30,625.00
22,704.00
1,653.00
0.57
825.00
25,182.57
-
-
55,807.57
8,371.14 15%
64,178.70
9,900.00
13,500.00
6,300.00
925.00
30,625.00
54,934.50
1,653.00
0.57
825.00
57,413.07
-
-
88,038.07
13,205.71 15%
101,243.78
77,000.00
52,500.00
6,300.00
6,475.00
142,275.00
1,855,000.00
11,875.50
8.54
10,725.00
1,877,609.04
-
-
2,019,884.04
302,982.61 15%
2,322,866.65
18,700.00
25,500.00
3,060.00
1,665.00
48,925.00
91,875.00
18,053.00
109,928.00
-
-
158,853.00
23,827.95 15%
182,680.95
77,000.00
52,500.00
6,300.00
6,475.00
142,275.00
255,402.00
30,948.00
286,350.00
-
-
428,625.00
64,293.75 15%
492,918.75
20,625.00
56,250.00
8,100.00
3,478.00
88,453.00
68,283.60
13,485.00
3.42
32,010.00
113,782.02
-
-
202,235.02
30,335.25 15%
232,570.27
20,625.00
56,250.00
8,100.00
3,478.00
88,453.00
97,713.00
13,485.00
3.42
32,010.00
143,211.42
-
-
231,664.42
34,749.66 15%
266,414.08
143,000.00
97,500.00
11,700.00
6,475.00
258,675.00
1,855,000.00
18,038.00
4.74
10,725.00
66,175.20
1,949,942.94
-
-
2,208,617.94
331,292.69 15%
2,539,910.64
77,000.00
52,500.00
6,300.00
6,475.00
142,275.00
187,000.00
17,037.50
6.64
204,044.14
-
-
346,319.14
51,947.87 15%
398,267.01
77,000.00
52,500.00
6,300.00
6,475.00
142,275.00
143,000.00
17,037.50
6.64
160,044.14
-
-
302,319.14
45,347.87 15%
347,667.01
38,500.00
26,250.00
3,060.00
370.00
68,180.00
55,000.00
12,895.00
67,895.00
-
-
136,075.00
20,411.25 15%
156,486.25
13,200.00
18,000.00
2,160.00
1,110.00
34,470.00
22,500.00
22,500.00
-
-
56,970.00
8,545.50 15%
65,515.50
77,000.00
52,500.00
6,300.00
6,475.00
142,275.00
231,000.00
17,037.50
6.64
248,044.14
-
-
390,319.14
58,547.87 15%
448,867.01
4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
2. Pemasangan 1 m2 langit-langit plywood ukuran (120 x 240) cm (tebal 3 mm, 4 mm, 6 mm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 110,000.00
Tukang Ba L.02 OH 0.100 150,000.00
Kepala Tu L.03 OH 0.010 180,000.00
Mandor L.04 OH 0.005 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Plywood 4mm Lembar 0.375 72,765.00
Paku tripleks kg 0.030 22,890.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
3. Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm (tebal 9 mm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 110,000.00
Tukang Ba L.02 OH 0.050 150,000.00
Kepala Tu L.03 OH 0.005 180,000.00
Mandor L.04 OH 0.005 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Gypsum board Lembar 0.364 72,870.00
Paku skrup kg 0.110 60,000.00
Cornis kg 0.300 4,872.00
Lakban gypsum roll 0.070 15,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
LAFOND)
, 5 mm, 6 mm)
Jumlah Harga (Rp)
3,300.00
10,500.00
1,260.00
740.00
15,800.00
24,826.39
228.90
25,055.29
-
-
40,855.29
6,128.29 15%
46,983.58
11,000.00
15,000.00
1,800.00
925.00
28,725.00
27,286.88
686.70
27,973.58
-
-
56,698.58
8,504.79 15%
65,203.36
0 x 240 x 9) mm (tebal 9 mm)
Jumlah Harga (Rp)
11,000.00
7,500.00
900.00
925.00
20,325.00
26,524.68
6,600.00
1,461.60
1,050.00
35,636.28
-
-
55,961.28
8,394.19 15%
64,355.47
5,500.00
7,500.00
900.00
555.00
14,455.00
115,762.50
218.40
115,980.90
-
-
130,435.90
19,565.39 15%
150,001.29
Jumlah Harga (Rp)
5,500.00
7,500.00
900.00
555.00
14,455.00
27,794.12
600.00
487.20
28,881.32
-
-
43,336.32
6,500.45 15%
49,836.77
11,000.00
7,500.00
900.00
925.00
20,325.00
27,709.50
6,600.00
1,461.60
1,050.00
36,821.10
-
-
57,146.10
8,571.92 15%
65,718.02
4.6.1 HARGA SATUAN PEKERJAAN KAYU
1. Pembuatan dan Pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 6.000 110,000.00
Tukang Ka L.02 OH 18.000 150,000.00
Kepala Tu L.03 OH 1.800 180,000.00
Mandor L.04 OH 0.300 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Balok kayu klas II m3 1.200 2,730,000.00
Paku 10 cm kg 1.250 21,840.00
Lem kayu kg 1.000 16,590.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
3. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.800 110,000.00
Tukang Ka L.02 OH 2.400 150,000.00
Kepala Tu L.03 OH 0.240 180,000.00
Mandor L.04 OH 0.040 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan kayu klas III m3 0.024 2,625,000.00
Lem kayu kg 0.300 16,590.00
Kaca polos 5 mm m2 1.000 115,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
4. Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas III tertutup (lebar sampai 90 cm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.700 110,000.00
Tukang Ka L.02 OH 2.100 150,000.00
Kepala Tu L.03 OH 0.210 180,000.00
Mandor L.04 OH 0.035 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan kayu klas III m3 0.025 2,625,000.00
Paku 1 cm - 2,5 cm kg 0.030 21,840.00
Lem kayu kg 0.500 16,590.00
Plywood tebal 4 mm Lembar 1.000 72,765.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
5. Pemasangan 1 m2 jalusi kusen, kayu kelas II
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.670 110,000.00
Tukang Ka L.02 OH 2.000 150,000.00
Kepala Tu L.03 OH 0.200 180,000.00
Mandor L.04 OH 0.335 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Papan kayu klas II m3 0.060 3,150,000.00
Paku 1 cm - 2,5 cm kg 0.150 21,840.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
14. Pemasangan 1 m2 rangka dinding pemisah plywood rangkap, rangka kayu kelas III
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.028 110,000.00
Tukang Ka L.02 OH 0.150 150,000.00
Kepala Tu L.03 OH 0.860 180,000.00
Mandor L.04 OH 0.560 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Balok kayu klas III, 6x m3 0.0280 2,100,000.00
Paku kg 0.1500 21,840.00
Plywood 4 mm, 120x2 Lembar 0.8600 72,765.00
Lem kayu kg 0.560 16,590.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 4.6.1 - 5
16. Pemasangan 1 m2 dinding lambrisering dari plywood ukuran (120x240) cm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.025 110,000.00
Tukang Ka L.02 OH 0.075 150,000.00
Kepala Tu L.03 OH 0.008 180,000.00
Mandor L.04 OH 0.001 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Plywod 4 mm m3 0.4000 72,765.00
Paku 1' dan 2,5' kg 0.0500 21,840.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
n jendela, kayu kelas II
Jumlah Harga (Rp)
660,000.00
2,700,000.00
324,000.00
55,500.00
3,739,500.00
3,276,000.00
27,300.00
16,590.00
3,319,890.00
-
-
7,059,390.00
1,058,908.50 15%
8,118,298.50 0.036 292,258.75
110,000.00
450,000.00
54,000.00
9,250.00
623,250.00
105,000.00
8,295.00
113,295.00
-
-
736,545.00
110,481.75 15%
847,026.75 1.722 1,458,580.06
Jumlah Harga (Rp)
88,000.00
360,000.00
43,200.00
7,400.00
498,600.00
63,000.00
4,977.00
115,000.00
182,977.00
-
-
681,577.00
102,236.55 15%
783,813.55
77,000.00
315,000.00
37,800.00
6,475.00
436,275.00
65,625.00
655.20
8,295.00
72,765.00
147,340.20
-
-
583,615.20
87,542.28 15%
671,157.48
Jumlah Harga (Rp)
73,700.00
300,000.00
36,000.00
61,975.00
471,675.00
189,000.00
3,276.00
192,276.00
-
-
663,951.00
99,592.65 15%
763,543.65
440,000.00
1,800,000.00
216,000.00
37,000.00
2,493,000.00
3,003,000.00
160,875.00
122,304.00
3,286,179.00
-
-
5,779,179.00
866,876.85 15%
6,646,055.85
Jumlah Harga (Rp)
737,000.00
3,015,000.00
361,800.00
61,975.00
4,175,775.00
737,000.00
3,015,000.00
361,800.00
4,113,800.00
-
-
8,289,575.00
1,243,436.25 15%
9,533,011.25
11,000.00
15,000.00
1,800.00
925.00
28,725.00
29,400.00
75,600.00
5,460.00
110,460.00
-
-
139,185.00
20,877.75 15%
160,062.75
32,340.00
4,368.00
36,708.00
-
-
117,483.00
17,622.45 15%
135,105.45
22,000.00
45,000.00
5,400.00
1,850.00
74,250.00
34,230.00
5,460.00
39,690.00
-
-
113,940.00
17,091.00 15%
131,031.00
11,000.00
30,000.00
3,600.00
925.00
45,525.00
34,020.00
2,184.00
36,204.00
-
-
81,729.00
12,259.35 15%
93,988.35
11,000.00
30,000.00
3,600.00
925.00
45,525.00
34,650.00
1,092.00
35,742.00
-
-
81,267.00
12,190.05 15%
93,457.05
16,500.00
67,500.00
8,100.00
1,480.00
93,580.00
58,800.00
3,276.00
62,076.00
-
-
155,656.00
23,348.40 15%
179,004.40
3,080.00
22,500.00
154,800.00
103,600.00
283,980.00
58,800.00
3,276.00
62,577.90
9,290.40
133,944.30
-
-
417,924.30
62,688.65 15%
480,612.95
66,000.00
270,000.00
32,400.00
5,550.00
373,950.00
22,050.00
2,184.00
3,276.00
27,510.00
-
-
401,460.00
60,219.00 15%
461,679.00
uran (120x240) cm
Jumlah Harga (Rp)
2,750.00
11,250.00
1,440.00
185.00
15,625.00
29,106.00
1,092.00
30,198.00
-
-
45,823.00
6,873.45 15%
52,696.45
11,000.00
30,000.00
3,600.00
925.00
45,525.00
16,800.00
2,184.00
18,984.00
-
-
64,509.00
9,676.35 15%
74,185.35
4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
DIV. 4.6.2 - 3
11 Pemasangan 1 buah Door handle
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 110,000.00
Tukang Ka L.02 OH 0.500 150,000.00
Kepala Tu L.03 OH 0.050 180,000.00
Mandor L.04 OH 0.0030 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Door handle bh 1.000 450,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
1,100.00
75,000.00
9,000.00
925.00
86,025.00
65,000.00
65,000.00
-
-
151,025.00
22,653.75 15%
173,678.75
1,100.00
75,000.00
9,000.00
925.00
86,025.00
238,000.00
175,000.00
413,000.00
-
-
499,025.00
74,853.75 15%
573,878.75
150,000.00
150,000.00
-
-
235,105.00
35,265.75 15%
270,370.75
1,650.00
22,500.00
2,700.00
148.00
26,998.00
22,050.00
22,050.00
49,048.00
7,357.20 15%
56,405.20
1,650.00
22,500.00
2,700.00
148.00
26,998.00
22,050.00
22,050.00
-
-
49,048.00
7,357.20 15%
56,405.20
1,100.00
15,000.00
1,800.00
92.50
17,992.50
16,590.00
16,590.00
-
-
34,582.50
5,187.38 15%
39,769.88
1,650.00
22,500.00
2,700.00
1,480.00
28,330.00
72,345.00
72,345.00
-
-
100,675.00
15,101.25 15%
115,776.25
72,345.00
72,345.00
-
-
100,675.00
15,101.25 15%
115,776.25
5,500.00
75,000.00
9,000.00
555.00
90,055.00
500,000.00
500,000.00
-
-
590,055.00
88,508.25 15%
678,563.25
2,200.00
30,000.00
3,600.00
185.00
35,985.00
22,050.00
22,050.00
-
-
58,035.00
8,705.25 15%
66,740.25
5,500.00
75,000.00
9,000.00
555.00
90,055.00
450,000.00
450,000.00
-
-
540,055.00
81,008.25 15%
621,063.25
1,100.00
15,000.00
1,800.00
925.00
18,825.00
130,000.00
130,000.00
-
-
148,825.00
22,323.75 15%
171,148.75
1,650.00
22,500.00
2,700.00
148.00
26,998.00
126,500.00
-
126,500.00
-
-
153,498.00
23,024.70 15%
176,522.70
1,870.00
25,500.00
3,060.00
166.50
30,596.50
385,000.00
1,960.00
386,960.00
-
-
417,556.50
62,633.48 15%
480,189.98
2,750.00
37,500.00
4,500.00
240.50
44,990.50
605,000.00
1,960.00
606,960.00
-
-
651,950.50
97,792.58 15%
749,743.08
8,250.00
22,500.00
2,700.00
740.00
34,190.00
2,200,000.00
1,400.00
2,201,400.00
-
-
2,235,590.00
335,338.50 15%
2,570,928.50
4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
2. 1 m2 Pengecatan bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.070 110,000.00
Tukang cat L.02 OH 0.009 150,000.00
Kepala tukang L.03 OH 0.006 180,000.00
Mandor L.04 OH 0.003 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Cat menie kg 0.200 44,100.00
Plamir kg 0.150 44,100.00
Cat dasar kg 0.170 31,000.00
Cat penutup kg 0.260 68,460.00
Kuas bh 0.010 11,025.00
Pengencer kg 0.030 29,820.00
Amplas Lbr 0.200 11,025.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
3. Pelaburan 1 m2 bidang kayu dengan teak oil
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.040 110,000.00
Tukang cat L.02 OH 0.063 150,000.00
Kepala tukang L.03 OH 0.063 180,000.00
Mandor L.04 OH 0.003 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Teak oil L 0.360 55,125.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
7. Pengecatan 1 m2 tembok baru untuk interior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.020 110,000.00
Tukang cat L.02 OH 0.063 150,000.00
Kepala tukang L.03 OH 0.0063 180,000.00
Mandor L.04 OH 0.003 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Plamir L 0.100 44,100.00
Cat dasar Kg 0.100 48,000.00
Cat penutup ex. Vinilex kg 0.260 33,025.10
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
10. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.060 110,000.00
Tukang cat L.02 OH 0.060 150,000.00
Kepala tukang L.03 OH 0.0120 180,000.00
Mandor L.04 OH 0.0030 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Cat kg 0.300 60,690.00
Kuas bh 0.010 11,025.00
Pengencer L 0.010 29,820.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
11. Pengecatan 1 m2 tembok baru untuk exterior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.020 110,000.00
Tukang cat L.02 OH 0.063 150,000.00
Kepala tukang L.03 OH 0.0063 180,000.00
Mandor L.04 OH 0.003 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Plamir L 0.100 44,100.00
Cat dasar Kg 0.100 33,025.10
Cat penutup ex. Dulux L 0.260 48,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
16,500.00
555.00
17,055.00
1,380.75
1,380.75
-
-
18,435.75
2,765.36 15%
21,201.11
7,700.00
1,350.00
1,080.00
555.00
10,685.00
8,820.00
6,615.00
5,270.00
17,799.60
110.25
894.60
2,205.00
41,714.45
-
-
52,399.45
7,859.92 15%
60,259.37
Jumlah Harga (Rp)
4,400.00
9,450.00
11,340.00
555.00
25,745.00
19,845.00
19,845.00
-
-
45,590.00
6,838.50 15%
52,428.50
4,400.00
9,000.00
2,880.00
555.00
16,835.00
10,253.25
30,779.28
22,050.00
63,082.53
-
-
79,917.53
11,987.63 15%
91,905.16
Jumlah Harga (Rp)
11,000.00
1,110.00
12,110.00
15,435.00
15,435.00
-
-
27,545.00
4,131.75 15%
31,676.75
17,600.00
24,000.00
2,880.00
555.00
45,035.00
5,465.25
465.00
1,102.50
7,032.75
-
-
52,067.75
7,810.16 15%
59,877.91
2,200.00
9,450.00
1,134.00
555.00
13,339.00
4,410.00
4,800.00
8,586.53
17,796.53
-
-
31,135.53
4,670.33 15%
35,805.85
3,080.00
6,300.00
756.00
555.00
10,691.00
5,760.00
5,944.52
11,704.52
-
-
22,395.52
3,359.33 15%
25,754.85
6,600.00
9,000.00
2,160.00
555.00
18,315.00
4,410.00
110.25
4,520.25
-
-
22,835.25
3,425.29 15%
26,260.54
6,600.00
9,000.00
2,160.00
555.00
18,315.00
18,207.00
110.25
298.20
18,615.45
-
-
36,930.45
5,539.57 15%
42,470.02
2,200.00
9,450.00
1,134.00
555.00
13,339.00
4,410.00
3,302.51
12,480.00
20,192.51
-
-
33,531.51
5,029.73 15%
38,561.24
3,080.00
6,300.00
756.00
555.00
10,691.00
5,944.52
5,944.52
-
-
16,635.52
2,495.33 15%
19,130.85
3,080.00
6,300.00
756.00
555.00
10,691.00
44,100.00
44,100.00
-
-
54,791.00
8,218.65 15%
63,009.65
5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
3. Pemasangan 1 buah urinoir (setara AmStand)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.000 110,000.00
Tukang batu L.02 OH 1.000 150,000.00
Kepala Tukang L.03 OH 0.100 180,000.00
Mandor L.04 OH 0.050 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Urinoir unit 1.000 2,694,405.00
Semen Portland kg 6.000 1,450.00
Pasir pasang m3 0.010 265,702.50
Perlengkapan 30%xurinoir
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
7. Pemasangan 1 buah bak cuci piring stainlessteel
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.030 110,000.00
Tukang batu L.02 OH 0.300 150,000.00
Kepala Tukang L.03 OH 0.030 180,000.00
Mandor L.04 OH 0.015 185,000.00
JUMLAH TENAGA KERJA
B BAHAN
Bak cuci piring stainless Ste unit 1.000 717,045.00
Waterdrain unit 1.000 88,000.00
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
15% E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)
363,000.00
165,000.00
1,800.00
29,600.00
559,400.00
3,639,825.00
218,389.50
3,858,214.50
-
-
4,417,614.50
662,642.18
5,080,256.68
110,000.00
45,000.00
27,000.00
9,250.00
191,250.00
497,700.00
8,700.00
1.90
5,880.00
512,281.90
-
-
703,531.90
105,529.78
809,061.68
Jumlah Harga (Rp)
110,000.00
150,000.00
18,000.00
9,250.00
287,250.00
2,694,405.00
8,700.00
2,657.03
808,321.50
3,514,083.53
-
-
3,801,333.53
570,200.03
4,371,533.55
132,000.00
217,500.00
27,000.00
11,100.00
387,600.00
828,240.00
8,700.00
2,657.03
621,225.00
1,460,822.03
-
-
1,848,422.03
277,263.30
2,125,685.33
8,250.00
112,500.00
13,500.00
555.00
134,805.00
9,179,835.00
1,835,967.00
11,015,802.00
-
-
11,150,607.00
1,672,591.05
12,823,198.05
33,000.00
67,500.00
8,100.00
2,775.00
111,375.00
331,170.00
39,740.40
370,910.40
-
-
482,285.40
72,342.81
554,628.21
Jumlah Harga (Rp)
3,300.00
45,000.00
5,400.00
2,775.00
56,475.00
717,045.00
88,000.00
805,045.00
-
-
861,520.00
129,228.00
990,748.00
1,100.00
15,000.00
1,800.00
925.00
18,825.00
74,970.00
74,970.00
-
-
93,795.00
14,069.25
107,864.25
28,000.00
8,166.67
28,000.00
-
-
54,055.00
8,108.25
62,163.25
1,100.00
15,000.00
7,200.00
925.00
24,225.00
57,500.00
125.00
57,625.00
-
-
81,850.00
12,277.50
94,127.50
5,940.00
13,500.00
1,620.00
4,995.00
26,055.00
38,000.00
11,083.33
49,083.33
-
-
75,138.33
11,270.75
86,409.08
3,960.00
9,000.00
1,080.00
370.00
14,410.00
13,682.34
3,990.68
17,673.02
-
-
32,083.02
4,812.45
36,895.48
3,960.00
9,000.00
1,080.00
370.00
14,410.00
16,857.54
4,916.78
21,774.32
-
-
36,184.32
5,427.65
41,611.97
8,910.00
20,250.00
2,430.00
740.00
32,330.00
13,230.00
3,858.75
17,088.75
-
-
49,418.75
7,412.81
56,831.56
8,910.00
20,250.00
2,430.00
740.00
32,330.00
21,620.34
6,305.93
27,926.27
-
-
60,256.27
9,038.44
69,294.71
8,910.00
20,250.00
2,430.00
740.00
32,330.00
16,857.54
4,916.78
21,774.32
-
-
54,104.32
8,115.65
62,219.97
8,910.00
20,250.00
2,430.00
740.00
32,330.00
16,857.54
4,916.78
21,774.32
-
-
54,104.32
8,115.65
62,219.97
41,800.00
28,500.00
3,420.00
3,515.00
77,235.00
495,000.00
462.00
14,935.00
16,207.85
13.10
526,617.95
-
-
603,852.95
90,577.94
694,430.89
ANALISA TAKSIR PINTU DAN JENDELA
No Kode Item
Bentuk
5
5 160 5
1 TYPE P1
KACA BIRU KACA BIRU
8 MM 8 MM
K AC A 8 M M
K AC A 8 M M
604200
108720
108720
108720
108720
108720
108720
275000
162720
350000
5 160 5
No Kode Item
Bentuk
5
5 180 5
2 TYPE P2
KACA BIRU KACA BIRU
8 MM 8 MM
KACA BIRU KACA BIRU
8 MM 8 MM
5 180 5
No Kode Item
Bentuk
5 90 5
3 TYPE P3
KACA BIRU
8 MM
A 8 M M
KACA 8 M M
8 Remote Wired - unit ### -
0
0
0
9
5 90 5
No Kode Item
Bentuk
5 90 5
K AC A 8 M M
4 TYPE P4
5 80 5
No Kode Item
Bentuk
Pintu UPVC 80
5 70 5
5 TYPE P-5 5 5
5 70 5
80
No Kode Item
Bentuk
5 60 5
Cubicle 2 Pintu
7 TYPE P6'
PINTU
PINTU
CUBICLE
No Kode Item
Bentuk
5 60 5
Cubicle 3 Pintu
8 TYPE P6"
PINTU
CUBICLE
5 80 5
No Kode Item
Bentuk
5
5 150 5
9 TYPE P7
5 150 5
No Kode Item
Bentuk
10 TYPE PJ-1 540
5 60 5 60 5 64 5 64 5 64 5 64 5 60 5 60 5
5 5
50 KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU 50
8 MM 8 MM 8 MM 8 MM 8 MM 8 MM 8 MM 8 MM
5 5
40 GRANIT 40X40 CM 40
5 5
315 315
KACA KACA
210 KACA BIRU KACA BIRU TEMPERED TEMPERED KACA BIRU KACA BIRU 210
8 MM 8 MM 12 MM 12 MM 8 MM 8 MM
KACA KACA
210 KACA BIRU KACA BIRU TEMPERED TEMPERED KACA BIRU KACA BIRU 210
8 MM 8 MM 12 MM 12 MM 8 MM 8 MM
5 60 5 60 5 40 5 90 90 5 40 5 60 5 60 5
540
No Kode Item
Bentuk
5 95 5 64 5 64 5 64 5 64 5 95 5
5 5
50 KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU 50
8 MM 8 MM 8 MM 8 MM 8 MM 8 MM
5 5
40 GRANIT 40X40 CM 40
5 5
315 315
KACA KACA
210 KACA BIRU TEMPERED TEMPERED KACA BIRU 210
8 MM 12 MM 12 MM 8 MM
5 95 5 40 5 90 90 5 40 5 95 5
480
No Kode Item
Bentuk
5 70 5 88 5 88 5 70 5
5 5
5 5
40 40
5 5
CA 8 MM
CA 8 MM
315 315
5 5
40 40
5 5
KACA 8 MM
KACA 8 MM
315 315
5 70 5 90 90 5 70 5
340
No Kode Item
Bentuk
340
13 TYPE PJ-4 5 88 5 88 5 70 5 70 5
5 5
5 5
40 40
5 5
315 315
210 KACA BIRU KACA BIRU KACA BIRU KACA BIRU 210
8 MM 8 MM 8 MM 8 MM
5 90 90 5 70 5 70 5
340
No Kode Item
Bentuk
120 355
5 5 5
5 5 5
40 40 40
5 5 5
315 315
KACA BIRU KACA BIRU K
125
8 MM 8 MM
KACA KACA
210 TEMPERED BIRU 210
12 MM 8 MM
5
80
5 80 5 25 5 5 80 5 80 5
120 355
No Kode Item
Bentuk
120 355
5
15110TYPE PJ-6
5 5 80 5 80 5 80 5 90 5
5 5 5 5
50 KACA BIRU 50 50 KACA BIRU KACA BIRU KACA BIRU KACA BIRU 50
8 MM 8 MM 8 MM 8 MM 8 MM
5 5 5 5
40 40 40 40
5 5 5 5
KACA KACA
210 TEMPERED BIRU 210 KACA BIRU 210
12 MM 8 MM 8 MM
80
5 80 5 25 5 5 80 5 80 5 80 5 90 5
120 355
12 MM 8 MM 8 MM
80
5 80 5 25 5 5 80 5 80 5 80 5 90 5
120 355
No Kode Item
Bentuk
260
5 80 5 80 5 80 5
16 TYPE PJ-7 5 5
5 5
40 40
5 5
315 315
KACA BIRU KACA BIRU
125 125
8 MM 8 MM
KACA BIRU
8 MM
5 5
80 80
5 80 5 80 5 80 5
260
No Kode Item
Bentuk
5 5 5
5 5 5
40 40
5 5
290 290
310 190 KACA BIRU KACA BIRU
8 MM 8 MM
5 5
290 290
310 190 KACA BIRU KACA BIRU
8 MM 8 MM
5 70 5 70 5
5
155
5 60 5 60 5
135
No Kode Item
Bentuk
JENDELA
135
5 60 5 60 5
5 18 TYPE J-2 5 5
5 5 5
40
290
310 190 KACA BIRU KACA BIRU 190 310
8 MM 8 MM
180
5 5
5 5
5 60 5 60 5
135
KUSEN TYPE J2
SKALA 1 : 20
No Kode Item
Bentuk
JENDELA
230 200
5 70 5 70 5 70 5 5 60 5 60 5 60 5
19 TYPE J-3 5 5 5 5
KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU
50 50 50 50
8 MM 8 MM 8 MM 8 MM 8 MM 8 MM
5 5 5 5
40 40
5 5
235
310 190 KACA BIRU KACA BIRU KACA BIRU 190 310
8 MM 8 MM 8 MM 125 125
KACA BIRU KACA BIRU KACA BIRU
8 MM 8 MM 8 MM
5 5
5 60 5 60 5 60 5
5 5
200
5 5
5 70 5 70 5 70 5
230
No Kode Item
Bentuk
20 TYPE J-4 5 5 5
KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU
8 MM 8 MM 50 50 8 MM 8 MM 8 MM 50
5 5 5
40 40
5 5
235 235
5 5
5 60 5 60 5 60 5
5
200
5 5
5 60 5 60 5 60 5
5
200
70 5 70 5
230
No Kode Item
Bentuk
260 175
5 80 5 80 5 80 5 5 80 5 80 5
21 TYPE J-5 5 5 5 5
KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU
50 8 MM 8 MM 8 MM 50 50 8 MM 8 MM 50
5 5 5 5
310 190 KACA BIRU KACA BIRU KACA BIRU 190 310 310 190 KACA BIRU KACA BIRU 190 310
8 MM 8 MM 8 MM 8 MM 8 MM
5 5 5 5
KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU
50 50 50 50
8 MM 8 MM 8 MM 8 MM 8 MM
5 5 5 5
5 80 5 80 5 80 5 5 80 5 80 5
260 175
No Kode Item
Bentuk
260 175
5 80 5 80 5 5 80 5 80 5
5 5 5
22 TYPE J-6
KACA BIRU KACA BIRU KACA BIRU KACA BIRU
50 50 50
8 MM 8 MM 8 MM 8 MM
5 5 5
KACA BIRU KACA BIRU 190 310 310 190 KACA BIRU KACA BIRU 190 310
8 MM 8 MM 8 MM 8 MM
5 5 5
5 5 5
5 80 5 80 5 5 80 5 80 5
260 175
5 5 5
5 5 5
5 80 5 80 5 5 80 5 80 5
260 175
No Kode Item
Bentuk
5 5 5
5 5 5
40 40
5 5
235 235
5 5
5 55 5 55 5
5
125
KACA BIRU
50
8 MM
5 100 5
No Kode Item
Bentuk
KUSEN TYPE J7
SKALA 1 : 20
5 5 5
5 5 5
40
5
125 320
5 55 5 5 100 5 100 5 100 5
5 5 5
5 5 5
40
235
310 190 KACA BIRU KACA BIRU KACA BIRU 190 310
8 MM 8 MM 8 MM
IRU KACA BIRU 125
M 8 MM
5 55 5
5 5
125
5 5
No Kode Item
Bentuk
25 TYPE J-9
123 111
5 54 5 54 5 5 48 5 48 5
5 5 5
5 5 5
310 190 KACA BIRU KACA BIRU 190 310 310 190 KACA BIRU KACA BIRU
8 MM 8 MM 8 MM 8 MM
5 5 5
5 5 5
5 54 5 54 5 5 48 5 48 5
123 111
123 111
5 54 5 5 48 5 48 5
5 5 5
U KACA BIRU
26 TYPE J-10 KACA BIRU KACA BIRU
50 50 50
8 MM 8 MM 8 MM
5 5 5
U KACA BIRU 190 310 310 190 KACA BIRU KACA BIRU 190 310
8 MM 8 MM 8 MM
5 5 5
5 5 5
5 54 5 5 48 5 48 5
123 111
No Kode Item
Bentuk
125 260
5 55 5 55 5 5 80 5 80 5
5 5 5
27 TYPE J-11
KACA BIRU KACA BIRU KACA BIRU KACA BIRU KA
50 8 MM 8 MM 50 50 8 MM 8 MM
5 5 5
40
235
310 190 KACA BIRU KACA BIRU 190 310 105 KACA BIRU KACA BIRU KA
8 MM 8 MM
8 MM 8 MM
5
15
5
5 80 5 80 5
5 5
260
5 5
5 55 5 55 5
125
5 5
5 55 5 55 5
125
No Kode Item
Bentuk
28 TYPE J-12
125 260
5 55 5 55 5 5 80 5 80 5 80 5
5 5 5 5
KACA BIRU KACA BIRU KACA BIRU KACA BIRU KACA BIRU
50 50 50 50
8 MM 8 MM 8 MM 8 MM 8 MM
5 5 5 5
40 40
5 5
235 235
310 190 KACA BIRU KACA BIRU 190 310 105 105
KACA BIRU KACA BIRU KACA BIRU
8 MM 8 MM
8 MM 8 MM 8 MM
5 5
15 15
5 5
5 80 5 80 5 80 5
5 5
260
5 5
5 55 5 55 5
125
No Kode Item
KUSEN TYPE J11 KUSEN TYPE J12 Bentuk
SKALA 1 : 20 SKALA 1 : 20
125
29 TYPE J-13 5 55 5 55 5
5 5
5 5
99
40 40
5 42 5 42 5
5 5 5 5
310 310
KACA KACA
190 180 180 190
BIRU BIRU
200 KACA BIRU KACA BIRU 200 8 MM 8 MM
8 MM 8 MM
40 40
5 42 5 42 5
5 5 5 5
310 310
KACA KACA
190 180 180 190
BIRU BIRU
200 KACA BIRU KACA BIRU 200 8 MM 8 MM
8 MM 8 MM
5 5
5 42 5 42 5
5 5
99
5 55 5 55 5
BIRU
50
No Kode Item
M
Bentuk
5
99
40
5 42 5 42 5
5 30 TYPE J-14 5 5
310
KACA KACA
190 180 180 190
BIRU BIRU
BIRU 200 8 MM 8 MM
M
5 5
5 42 5 42 5
5
99
5
No Kode Item
Bentuk
BOUVENLIGHT (BV)
70
31 TYPE BV - 1 5 60 5 5
5 5 5
60 50 KACA 50 60 60 50
BIRU
8 MM
5 5 5
5 60 5 5
70
5 60 5 5
5 5 5
60 50 KACA 50 60 60 50
BIRU
8 MM
5 5 5
5 60 5 5
70
0 135
0 5 32 TYPE BV - 2 5 60 5 60 5
5 5 5
CA 50 60 60 50 KACA KACA 50 60
RU BIRU BIRU
M 8 MM 8 MM
5 5 5
0 5 5 60 5 60 5
0 135
135 200
5 60 5 60 5 5 60 5 60 5 6
33 TYPE BV - 2"
5 5 5
KACA KACA
60 50 BIRU BIRU 50 60 60 50 KACA KACA KA
8 MM 8 MM BIRU BIRU BI
8 MM 8 MM 8M
5 5 5
5 60 5 60 5 5 60 5 60 5 6
135 200
No Kode Item
Bentuk
135 200
34 TYPE BV - 3
5 60 5 5 60 5 60 5 60 5
5 5 5
KACA
BIRU 50 60 60 50 KACA KACA KACA 50 60
8 MM BIRU BIRU BIRU
8 MM 8 MM 8 MM
5 5 5
5 60 5 5 60 5 60 5 60 5
135 200
5 5
200
5 60 5 60 5 60 5
5 5
5 5
5 60 5 60 5 60 5
200
KACA KACA
60 50 BIRU BIRU 50 60
8 MM 8 MM
5 5
5 55 5 55 5
125
5 60 5 60 5 60 5 60 5
265
No Kode Item
Bentuk
5 50 50 5
5 KACA KACA
5
37 TYPE JP - 1 50 BIRU BIRU 50
8 MM 8 MM
5 5
KACA KACA
190 BIRU BIRU 190
8 MM 8 MM
5 KACA KACA
5
50 BIRU BIRU 50
8 MM 8 MM
5 5
KACA KACA
90 BIRU BIRU 90
8 MM 8 MM
5 KACA KACA
5
50 BIRU BIRU 50
8 MM 8 MM
5 5
1055 1055
KACA KACA
190 BIRU BIRU 190
8 MM 8 MM
5 KACA KACA
5
50 BIRU BIRU 50
8 MM 8 MM
5 5
1055 1055
KACA KACA
190 BIRU BIRU 190
8 MM 8 MM
5 KACA KACA
5
50 BIRU BIRU 50
8 MM 8 MM
5 5
KACA KACA
90 BIRU BIRU 90
8 MM 8 MM
5 KACA KACA
5
50 BIRU BIRU 50
8 MM 8 MM
5 5
KACA KACA
190 BIRU BIRU 190
8 MM 8 MM
5 5
5 50 50 5
115
No Kode Item
Bentuk
200
38 TYPE JP - 2 5 60 60 60 5
5 KACA KACA KACA
5
50 BIRU BIRU BIRU 50
8 MM 8 MM 8 MM
5 5
65 5
1 Unit Kusen BV Atas Pintu Coating Putih 4.90 m' 205,000 1,004,500 Kaca Reflektif
Kaca Biru (Reflektif) BV 0.96 m2 747,500 717,600
50 Sealant 1.73 tube 63,000 109,200 Kusen Alexindo
Ongkos Pasang 1.02 m2 175,000 178,500
Per-unit 2,009,800
5
40
Jumlah 9,287,785
Overhead & Profit = 15% 1,393,168
10,680,952
Dibulatkan 10,681,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
65 5
1 Unit Kusen BV Atas Pintu Coating Putih 5.30 m' 205,000 1,086,500
50
Kaca Biru (Reflektif) BV 8 mm 1.08 m2 747,500 807,300
50 Sealant 1.87 tube 63,000 117,600
Ongkos Pasang 1.14 m2 175,000 199,500
Per-unit 2,210,900
5
Kaca Reflektif
40
Kusen Alexindo
Jumlah 13,133,970
Overhead & Profit = 15% 1,970,096
15,104,066
Dibulatkan 15,104,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
65 5
1 Unit Kusen BV Atas Pintu Coating Putih 3.50 m' 205,000 717,500 Kaca Reflektif
Kaca Biru (Reflektif) BV 0.54 m2 747,500 403,650
50 Sealant 0.93 tube 63,000 58,800 Kusen Alexindo
Ongkos Pasang 1.02 m2 175,000 178,500
Per-unit 1,358,450
5
40
40
Jumlah 5,621,319
Overhead & Profit = 15% 843,198
6,464,516
Dibulatkan 6,465,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Kaca Reflektif
5 1 Unit Kusen Pintu Coating Putih 5.10 m1 205,000 1,045,500
Daun Pintu Plywood 9 mm 3.87 m2 142,275 550,604 Kusen Alexindo
Kaca Biru (Reflektif) Pintu 0.14 m2 747,500 101,660 EngselPintu
HPL 3.87 m2 83,983 325,013 Engsel Jendela
Engsel Pintu 3.00 bh 44,100 132,300
Kunci Pintu 1.00 set 350,000 350,000
Grendel Tanam 1.00 set 220,000 220,000
Handle Pintu 1.00 set 238,000 238,000
Door Closer 1.00 set 500,000 500,000
Sealant 0.67 tube 63,000 42,000
Ongkos Pasang 3.87 m2 200,000 774,000
210
Per-unit 4,279,078
Jumlah 4,279,078
Overhead & Profit = 15% 641,862
Sub Total 4,920,939
Dibulatkan 4,921,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 4,500,000
175
Overhead & Profit = 15% 675,000
Sub Total 5,175,000
Dibulatkan 5,175,000
Total Harga 1 Unit Type P-5 Rp. 5,175,000
15
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
175
Per-unit 18,717,300
Jumlah 18,717,300
Overhead & Profit = 15% 2,807,595
Sub Total 21,524,895
Dibulatkan 21,525,000
15
Total Harga 1 Unit Cubicle 2 Pintu Rp. 21,525,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
175
Per-unit 33,407,900
Jumlah 33,407,900
Overhead & Profit = 15% 5,011,185
Sub Total 38,419,085
Dibulatkan 38,419,000
15
Total Harga 1 Unit Cubicle 2 Pintu Rp. 38,419,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 10,615,570
Overhead & Profit = 15% 1,592,336
Sub Total 12,207,906
Dibulatkan 12,208,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Pintu Coating Putih 15.30 m' 205,000 3,136,500 Kaca Reflektif
Kaca Biru (Reflektif) BV 2.86 m2 747,500 2,137,850
Sealant 5.87 tube 63,000 369,600 Kusen Alexindo
Ongkos Pasang 3.24 m2 175,000 567,000
Per-unit 6,210,950
EngselPintu
1 Unit Pintu Kaca Temperet (lengkap+Kunci Tanam) Per-unit 19,500,000 Engsel Jendela
Jumlah 35,096,900
Overhead & Profit = 15% 5,264,535
Sub Total 40,361,435
Dibulatkan 40,361,000
Total Harga 1 Unit Pintu Type PJ - 1 Rp. 40,361,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Pintu Coating Putih 13.10 m' 205,000 2,685,500
Kaca Biru (Reflektif) BV 2.62 m2 747,500 1,956,955
Sealant 5.87 tube 63,000 369,600
Ongkos Pasang 3.24 m2 175,000 567,000
Per-unit 5,579,055
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Pintu Coating Putih 9.30 m' 205,000 1,906,500
Kaca Biru (Reflektif) BV 1.85 m2 747,500 1,381,380
Sealant 3.43 tube 63,000 216,300
Ongkos Pasang 3.24 m2 110,000 356,400
Per-unit 3,860,580
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Pintu Coating Putih 9.30 m' 205,000 1,906,500
Kaca Biru (Reflektif) BV 8 mm 1.85 m2 747,500 1,381,380
Sealant 3.43 tube 63,000 216,300
Ongkos Pasang 1.14 m2 175,000 199,500
Per-unit 3,703,680
1 Unit Kusen Pintu/Jendela Coating Putih 13.35 m' 205,000 2,736,750
Frame Pintu, 10. 6,6 12.00 m' 210,000 2,520,000
Kaca Biru (Reflektif) Pintu 8 mm 5.81 m2 747,500 4,342,975
Fisher 10.00 bh 1,500 15,000
Engsel Pintu 6.00 bh 44,100 264,600
Kunci Pintu - set 350,000 -
Grendel Tanam 1.00 set 220,000 220,000
Handle Pintu 2.00 set 238,000 476,000
Door Closer 2.00 set 500,000 1,000,000
Sealant 1.41 tube 63,000 88,620
Ongkos Pasang 12.00 m2 200,000 2,400,000
Per-unit 14,063,945
Jumlah 17,767,625
Overhead & Profit = 15% 2,665,144
Sub Total 20,432,769
Dibulatkan 20,433,000
1 Unit Kusen BV Atas Pintu Coating Putih 3.40 m' 205,000 697,000
Kaca Biru (Reflektif) BV 0.63 m2 747,500 472,794
Sealant 1.07 tube 63,000 67,200
Ongkos Pasang 3.24 m2 175,000 567,000
Per-unit 1,803,994
Jumlah 14,248,869
Overhead & Profit = 15% 2,137,330
Sub Total 16,386,199
Dibulatkan 16,386,000
Total Harga 1 Unit Pintu Type PJ-5 Rp. 16,386,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Pintu Coating Putih 9.60 m' 205,000 1,968,000
Kaca Biru (Reflektif) BV 8 mm 1.91 m2 747,500 1,430,715
Sealant 3.53 tube 63,000 222,600
Ongkos Pasang 2.13 m2 175,000 372,750
Per-unit 3,994,065
1 Unit Kusen Pintu/Jendela Coating Putih 14.10 m' 205,000 2,890,500
Frame Pintu, 10. 6,6 6.00 m' 210,000 1,260,000
Kaca Biru (Reflektif) Pintu 8 mm 4.99 m2 747,500 3,731,894
Fisher 10.00 bh 1,500 15,000
Engsel Pintu 3.00 bh 63,000 189,000
Kunci Pintu 1.00 set 350,000 350,000
Grendel Tanam 1.00 set 220,000 220,000
Handle Pintu 1.00 set 238,000 238,000
Door Closer 1.00 set 500,000 500,000
Sealant 1.41 tube 63,000 88,620
Ongkos Pasang 5.32 m2 200,000 1,063,000
Per-unit 10,546,014
Jumlah 14,540,079
Overhead & Profit = 15% 2,181,012
Sub Total 16,721,091
Dibulatkan 16,721,000
Total Harga 1 Unit Pintu Type PJ - 6 Rp. 16,721,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Pintu Coating Putih 7.20 m' 205,000 1,476,000
Kaca Biru (Reflektif) BV 8 mm 1.40 m2 747,500 1,048,369
Sealant 2.60 tube 63,000 163,800
Ongkos Pasang 1.56 m2 175,000 273,000
Per-unit 2,961,169
1 Unit Kusen Pintu/Jendela Coating Putih 11.00 m' 205,000 2,255,000
Frame Pintu, 10. 6,6 5.80 m' 210,000 1,218,000
Kaca Biru (Reflektif) Pintu 8 mm 3.74 m2 747,500 2,795,650
Fisher 10.00 bh 1,500 15,000
Engsel Pintu 3.00 bh 63,000 189,000
Kunci Pintu 1.00 set 350,000 350,000
Grendel Tanam 1.00 set 220,000 220,000
Handle Pintu 1.00 set 238,000 238,000
Door Closer 1.00 set 500,000 500,000
Sealant 1.41 tube 63,000 88,620
Ongkos Pasang 3.91 m2 200,000 782,000
Per-unit 8,651,270
Jumlah 11,612,439
Overhead & Profit = 15% 1,741,866
Sub Total 13,354,305
Dibulatkan 13,354,000
Total Harga 1 Unit Pintu Type PJ - 7 Rp. 13,354,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Jendela Coating Putih 4.60 m' 205,000 943,000
Kaca Biru (Reflektif) BV 8 mm 0.83 m2 747,500 616,688
Sealant 1.60 tube 63,000 100,800
Ongkos Pasang 0.93 m2 175,000 162,750
Per-unit 1,823,238
1 Unit Kusen Jendela Coating Putih 8.50 m' 205,000 1,742,500
Kaca Biru (Reflektif) Pintu 8 mm 2.78 m2 747,500 2,074,313
Fisher 10.00 bh 1,500 15,000
Sealant 1.41 tube 63,000 88,620
Ongkos Pasang 2.95 m2 200,000 589,000
Per-unit 4,509,433
Jumlah 6,332,670
Overhead & Profit = 15% 949,901
Sub Total 7,282,571
Dibulatkan 7,283,000
Total Harga 1 Unit Jendela Type J - 1 Rp. 7,283,000
6,567,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 7,053,750
Overhead & Profit = 15% 1,058,063
Sub Total 8,111,813
Dibulatkan 8,112,000
Total Harga 1 Unit Jendela Type J - 2 Rp. 8,112,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen Jendela Coating Putih 21.60 m' 205,000 4,428,000
Kaca Biru (Reflektif) Pintu 8 mm 5.85 m2 747,500 4,372,875
Fisher 10.00 bh 1,500 15,000
Sealant 7.10 tube 63,000 447,300
Ongkos Pasang 7.13 m2 200,000 1,426,000
Per-unit 10,689,175
Jumlah 10,689,175
Overhead & Profit = 15% 1,603,376
Sub Total 12,292,551
Dibulatkan 12,293,000
Total Harga 1 Unit Jendela Type J - 3 Rp. 12,293,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Jendela Coating Putih 6.00 m' 205,000 1,230,000
Kaca Biru (Reflektif) BV 8 mm 1.07 m2 747,500 801,694
Sealant 2.20 tube 63,000 138,600
Ongkos Pasang 1.20 m2 175,000 210,000
Per-unit 2,380,294
Jumlah 6,908,306
Overhead & Profit = 15% 1,036,246
Sub Total 7,944,552
Dibulatkan 7,945,000
Total Harga 1 Unit Jendela Type J - 4 Rp. 7,945,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 12,599,781
Overhead & Profit = 15% 1,889,967
Sub Total 14,489,748
Dibulatkan 14,490,000
Total Harga 1 Unit Jendela Type J - 5 Rp. 14,490,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 8,596,050
Overhead & Profit = 15% 1,289,408
Sub Total 9,885,458
Dibulatkan 9,885,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Jendela Coating Putih 4.00 m' 205,000 820,000
Kaca Biru (Reflektif) BV 8 mm 0.66 m2 747,500 493,350
Sealant 1.40 tube 63,000 88,200
Ongkos Pasang 0.75 m2 175,000 131,250
Per-unit 1,532,800
Jumlah 4,490,150
Overhead & Profit = 15% 673,523
Sub Total 5,163,673
Dibulatkan 5,164,000
Total Harga 1 Unit Jendela Type J - 7 Rp. 5,164,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 14,901,006
Overhead & Profit = 15% 2,235,151
Sub Total 17,136,157
Dibulatkan 17,136,000
Total Harga 1 Unit Jendela Type J - 8 Rp. 17,136,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 6,508,525
Overhead & Profit = 15% 976,279
Sub Total 7,484,804
Dibulatkan 7,485,000
Total Harga 1 Unit Jendela Type J - 9 Rp. 7,485,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 6,060,475
Overhead & Profit = 15% 909,071
Sub Total 6,969,546
Dibulatkan 6,970,000
Total Harga 1 Unit Jendela Type J - 10 Rp. 6,970,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 6,583,200
Overhead & Profit = 15% 987,480
Sub Total 7,570,680
Dibulatkan 7,571,000
Total Harga 1 Unit Jendela Type J - 11 Rp. 7,571,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Jendela Coating Putih 7.20 m' 205,000 1,476,000
Kaca Biru (Reflektif) BV 8 mm 1.40 m2 747,500 1,048,369
Sealant 2.60 tube 63,000 163,800
Ongkos Pasang 1.56 m2 175,000 273,000
Per-unit 2,961,169
Jumlah 8,539,006
Overhead & Profit = 15% 1,280,851
Sub Total 9,819,857
Dibulatkan 9,820,000
Total Harga 1 Unit Jendela Type J - 12 Rp. 9,820,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
1 Unit Kusen BV Atas Jendela Coating Putih 4.00 m' 205,000 820,000
Kaca Biru (Reflektif) BV 8 mm 0.66 m2 747,500 493,350
Sealant 1.40 tube 63,000 88,200
Ongkos Pasang 0.75 m2 175,000 131,250
Per-unit 1,532,800
1 Unit Kusen Jendela Coating Putih 8.50 m' 205,000 1,742,500
Kaca Biru (Reflektif) Pintu 8 mm 2.46 m2 747,500 1,838,850
Fisher 10.00 bh 1,500 15,000
Sealant 3.40 tube 63,000 214,200
Ongkos Pasang 2.63 m2 200,000 525,000
Per-unit 4,335,550
Jumlah 5,868,350
Overhead & Profit = 15% 880,253
Sub Total 6,748,603
Dibulatkan 6,749,000
Total Harga 1 Unit Jendela Type J - 13 Rp. 6,749,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 3,387,483
Overhead & Profit = 15% 508,122
Sub Total 3,895,605
Dibulatkan 3,896,000
Total Harga 1 Unit Jendela Type J - 14 Rp. 3,896,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 20,783,875
Overhead & Profit = 15% 3,117,581
Sub Total 23,901,456
Dibulatkan 23,901,000
Total Harga 1 Unit Jendela Type JP - 1 Rp. 23,901,000
Qty PERINCIAN
Bahan / Material Volume HASAT JUMLAH
Jumlah 28,102,769
Overhead & Profit = 15% 4,215,415
Sub Total 32,318,184
Dibulatkan 32,318,000
Total Harga 1 Unit Jendela Type JP - 2 Rp. 32,318,000
8 mm 910,000.0
6 mm
4"
2.2 jt
/m'
/m'
83,983 kpg
/m' 60,000.00
/m'
270,000.0
8 mm
6 mm
4"
24,600.00
18,200.00
/m'
/m'
/m'
/m'
8 mm 910,000.0
6 mm
4"
2.2 jt
/m'
/m'
83,983 kpg
/m' 60,000.00
/m'
270,000.0
8 mm 910,000.0 2.2 jt
6 mm
4"
24,600.00
18,200.00
/m'
/m'
83,983 kpg
/m' 60,000.00
/m'
270,000.0
6 mm
4" 2.2 jt
24,600.00
18,200.00
/m'
/m'
83,983
/m' 60,000.00
kpg
/m'
270,000.0
6 mm
4" 2.2 jt
24,600.00
18,200.00
/m'
/m'
83,983
/m' 60,000.00
kpg
/m'
270,000.0
6 mm
4" 2.2 jt
24,600.00
18,200.00
/m'
/m'
83,983
/m' 60,000.00
kpg
/m'
270,000.0
24,600.00
18,200.00
/m'
/m'
/m'
/m'
8 mm 910,000.0
6 mm
4"
2.2 jt
24,600.00
18,200.00
/m'
/m'
83,983 kpg
/m' 60,000.00
/m'
270,000.0
No URAIAN PEKERJAAN URAIAN PERHITUNGAN
I. PEKERJAAN PERSIAPAN
A PEKERJAAN PERSIAPAN DAN LAIN LAIN
1 Survei, Pengukuran site dan Bouplank
Panjang = 75
Lebar = 15
Luas = 1125
2 Bongkar Bangunan Lama
jumlah = 274.80
Volume = 103.68
2 Pek. Galian Tanah Pondasi menerus Batu Bata 1:4
Panjang = 106.84
Lebar = 0.40
tinggi = 0.70
Volume = 29.92
3 Pek. Urugan pasir bawah pile cap
panjang = 1.30
lebar = 2.50
tinggi = 0.10
jumlah = 58.00
Volume = 18.85
4 Cor lantai kerja
panjang = 1.30
lebar = 2.50
tinngi = 0.05
jumlah = 58.00
Volume = 9.43
B PEKERJAAN PONDASI
1 Pek. Mobilisasi dan Demobilisasi
jumlah = 1.00
2 Pek. Pengadaan Tiang Pancang 40 x 40 cm
panjang = 6.00
Jumlah pilr cap = 58.00
jumlah = 2.00
Volume = 696.00
3 Pek. Pemotongan Tiang Pancang
jumlah titik = 58.00
4 Pek. Pas Bekisting pile cap
panjang = 1.30
lebar = 2.50
tinggi = 0.50
jumlah = 58.00
Luas = 220.40
5 Pek. Pas Pembesian pile cap
jumlah pile cap = 58.00
tinggi tulangan = 0.40
panjang tul atas = 2.40
panjang tul total = 5.75
jumlah tul pokok D19-200 (atas) = 9.00
berat besi D19 = 2.23
Berat tul total = 6693.35
tinggi tul bawah = 0.36
panjang tul bawah = 1.20
panjang tul total = 3.27
jumlah tul pokok D19-200
(bawah)
= 17.00
berat tul total = 7198.81
berat seluruh tul = 13892.15
6 Pek. Beton pile cap mutu k-350
jumlah = 58.00
panjang = 2.50
lebar = 1.30
tebal = 0.50
volume = 78.65
7 Pek. Pondasi Batu bata menerus ad 1:4 toilet dan selasar
Panjang = 106.84
lebar = 0.20
tinggi = 0.60
=
volume 12.82
8 Pek. Urugan Pasir dibawah pondasi batu bata menerus
Panjang = 106.84
lebar = 0.20
tinggi = 0.10
volume = 2.14
9 Pek. Lantai Kerja dibawah pondasi batu bata menerus
Panjang = 106.84
lebar = 0.20
tinggi = 0.05
volume = 1.07
C PEKERJAAN KONSTRUKSI BETON BERTULANG s/d Pelat Lantai 2
1 Pek. Lantai Kerja Dibawah Sloof uk 30/50 cm
Panjang = 444.00
lebar = 0.30
tinggi = 0.05
volume = 6.66
2 Pek. Lantai Kerja Dibawah Sloof uk 15/25 cm
Panjang = 106.84
lebar = 0.15
tinggi = 0.05
volume = 0.80
3 Pek. Bekisting Sloof uk 30/50 cm
tinggi = 0.50
panjang memanjang = 288.00
panjang melintang = 156.00
=
luas 444.00
4 Pek. Bekisting Sloof uk 15/25 cm
tinggi = 0.25
panjang = 106.84
=
luas 53.42
5 Pek. Pembesian Sloof uk 30/50 cm
Memanjang Panjang = 288.00
jumlah tulangan = 7.00
berat besi = 2.23
berat tulangan total = 4495.68
Sengkang D10-200
panjang = 1.60
jumlah tulangan = 1440.00
berat besi = 0.62
=
volume 66.60
8 Pek. Beton Sloof uk 15/25 cm mutu K-300
Panjang = 106.84
lebar = 0.15
tinggi = 0.25
=
volume 4.01
9 Pek. Bekisting Kolom uk 50/50 cm
Panjang = 0.50
lebar = 0.50
tinggi = 4.50
Jumlah = 58.00
volume = 522.00
10 Pek. Pembesian Kolom uk 50/50 cm
Panjang = 4.50
berat besi D19 = 2.23
banyak tulangan 16.00
Jumlah = 58.00
berat total = 9312.48
11 Pek. Beton Kolom uk 50/50 cm
Panjang = 4.00
lebar = 0.50
tinggi 0.50
Jumlah = 58.00
berat total = 58.00
12 Pek. Kolom praktis uk 12/12 cm
Panjang = 4.00
lebar = 12.00
tinggi 0.12
Jumlah = 70.00
=
berat total 280.00
13 Pek. Bekisting Balok (B1) uk 30/50 cm
Arah X (Memanjang)
Panjang = 288.00
lebar = 0.30
tinggi 0.50
berat total = 288.30
Arah Y (Melintang)
Panjang = 140.00
lebar = 0.30
tinggi 0.50
berat total = 140.30
14 Pek. Bekisting Balok (B2) uk 20/40 cm
Arah Y (Melintang)
Panjang = 140.00
lebar = 0.20
tinggi 0.40
=
berat total 112.20
15 Pek. Pembesian Balok (B1) uk 30/50 cm
Arah X (Memanjang)
Panjang = 288.00
Jumlah besi = 7.00
Berat besi D19 2.23
berat total = 4495.68
Sengkang D10-200
Panjang = 1.43
Jumlah Tulangan = 1440.00
Berat besi D10 0.62
berat total = 1270.53
Arah Y (Melintang)
Panjang = 140.00
Jumlah besi = 4.00
Berat besi D19 2.23
berat total = 1248.80
Sengkang D10-200
Panjang = 1.43
Jumlah Tulangan = 700.00
Berat besi D10 0.62
berat total = 617.62
16 Pek. Pembesian Balok (B2) uk 20/40 cm
Arah Y (Melintang)
Panjang = 140.00
Jumlah besi = 4.00
Berat besi D19 2.23
berat total = 1248.80
Sengkang D10-200
Panjang = 1.03
Jumlah Tulangan = 700.00
Berat besi D10 0.62
berat total = 444.86
Volume = 7.84
19 Pek. Bekisting Pelat lantai 1
Panjang = 72.00
lebar = 12.00
tinggi = 0.12
jumlah = 1.00
Luas = 864.00
Dikurangi Void
Panjang = 18.00
Lebar = 4.00
Jumlah = 1.00
Luas = -72.00
Tangga
Panjang = 3.00
lebar = 4.00
Jumlah = 2.00
Luas = -24.00
20 Pek. Pembesian Pelat Lantai 1
Ly = 4.00
Lx = 3.00
jumlah panel = 64.00
berat tul D8-150 = 0.390
Jarak tulangan = 0.15
Lapangan =
jml tul lapangan x = 27.00
Panjang tul lapangan x = 1.50
Panjang total tul = 40.50
jml tul lap y = 20.00
Panjang tul lap y = 2.00
Panjang total tul = 40.00
Tumpuan =
jumlah tul tumpuan x = 27.00
Panjang tul tumpuan x = 1.50
Panjang tul tumpuan y 40.50
jumlah tul tumpuan y = 20.00
Panjang tul tumpuan y = 2.00
Panjang total tul = 40.00
panjang seluruh tul = 161.00
berat seluruh tul = 4018.56
21 Pek. Beton Pelat lantai 1
Panjang = 72.00
lebar = 12.00
tinggi = 0.12
jumlah = 1.00
Volume = 103.68
Dikurangi Void
Panjang = 18.00
Lebar = 4.00
Jumlah = 1.00
Volume = -72.00
tangga
Panjang = 3.00
lebar = 4.00
Jumlah = 2.00
Volume = -2.88
D PEKERJAAN KONSTRUKSI TANGGA UTAMA KIRI&KANAN
1 Pek. Bekisting tangga utama
Anak tangga Anak tangga
lebar = 0.20
jumlah = 1.40
jumlah anak tangga = 19.00
jumlah tangga = 2.00
Luas = 10.64
Cetakan bawah Pelat Tangga
Lebar = 1.40
Panjang = 2.77
Jumlah = 2.00
Jumlah tangga = 2.00
Luas = 15.51
Cetakan samping Pelat Tangga
Panjang = 2.77
Lebar = 0.28
Jumlah = 4.00
Jumlah tangga = 2.00
Luas = 6.20
Pelat Bordes Tangga Pelat Tangga
lebar = 1.00
panjang = 3.00
tinggi = 0.12
Jumlah tangga = 2.00
Luas = 6.99
Balok Bordes 20/30 Panjang = 3.00
Lebar = 0.20
Jumlah tangga = 2.00
Luas = 1.20
2 Pek. Pembesian tangga utama
Tulangan Utama D10
Panjang = 2.77
Jumlah Tulangan = 16.00
Jumlah Lapis = 2.00
Jumlah Tangga = 2.00
Berat besi D10 = 0.62
Berat Tulangan total = 109.38
Tulangan Pembagi D10
Panjang = 1.55
Jumlah Tulangan = 7.00
Jumlah Lapis = 2.00
Jumlah Tangga = 2.00
Berat Tulangan total = 43.40
Tulangan anak tangga melintang D10
Panjang = 0.65
Jumlah tulangan = 4.00
jumlah anak tangga = 19.00
Berat besi D10 = 0.62
Jumlah tangga = 2.00
Berat Tulangan total = 60.96
Tulangan anak tangga memanjang D10
Panjang = 1.42
Jumlah tulangan = 3.00
jumlah anak tangga = 19.00
Berat besi D10 = 0.62
Jumlah tangga = 2.00
Berat Tulangan total = 99.53
Pelat Bordes Tulangan Utama D13
Panjang = 3.00
Jumlah Tulangan = 20.00
Jumlah Lapis = 1.00
Jumlah Tangga = 2.00
Berat besi D10 = 0.62
Berat Tulangan total = 74.04
Tulangan Utama D10
Panjang = 3.00
Jumlah Tulangan = 10.00
Jumlah Lapis = 1.00
Jumlah Tangga = 2.00
Berat besi D10 = 0.62
Berat Tulangan total = 37.02
Balok Bordes 20/30 Tulangan Utama D13
Panjang = 4.00
jumlah tulangan = 6.00
Jumlah Tangga = 2.00
Berat besi D13 = 1.04
Berat Tulangan total = 49.92
Tulangan Sengkang D10
Panjang = 0.83
Jumlah Tulangan = 17.00
Jumlah Lapis = 1.00
Jumlah Tangga = 2.00
Berat besi D10 = 1.04
Berat Tulangan total = 29.35
3 Pek. Beton tangga utama
Anak Tangga Optride = 0.20
Antride = 0.30
Lebar = 1.40
jumlah anak tangga = 19.00
Jumlah tangga = 2.00
Berat Tulangan total = 3.19
Pelat Tangga Lebar = 2.80
Panjang = 2.77
Tebal = 0.12
Jumlah Tangga = 2.00
= 1.86
Volume
Pelat Bordes Tangga Lebar = 1.00
Panjang = 3.00
Tebal = 0.12
Jumlah anak tangga = 19.00
Volume = 6.84
Balok Bordes 20/30 Lebar = 0.20
Panjang = 3.00
Tinggi = 0.18
Jumlah Tangga = 2.00
Volume = 0.22
H PEKERJAAN CAT
1 Cat Dinding Eksterior
Volume = 1024.87
2 Cat Dinding Interior
Volume = 1024.87
3 Cat Plafond Kalsiboard
Luas = 47.20
B PEKERJAAN PLUMBING
1 Pipa tegak Air Bersih suplai Ø 1" (dari sumber ke Tanki Dag)
Jumlah = 70.00
2 Pipa PVC AW Ø 1" distribusi air Bersih dari dag ke lantai 1
Jumlah = 150.00
3 Pipa PVC AW Ø 3/4" (distribusi ke sanitair )
Jumlah = 120.00
4 Pipa PVC AW Ø 2" (pipa dari wastafel ke saluran)
Jumlah = 70.00
5 Pipa PVC AW 3"(Pipa dari Floor Drain ke saluran)
Jumlah = 43.00
6 Pipa PVC AW 4" (pipa dari Kloset ke septictank)
Jumlah = 66.00
7 Gate Valve Pipa Ø1" suplay air bersih (dekat pintu dalam Shaft )
Jumlah = 10.00
B PEKERJAAN PLUMBING
1 Pipa PVC AW Ø 1" distribusi air Bersih dari dag ke lantai 2
Jumlah = 125.00
2 Pipa PVC AW Ø 3/4" (distribusi ke sanitair )
Jumlah = 142.00
3 Pipa PVC AW Ø 2" (pipa dari wastafel ke saluran)
Jumlah = 165.00
4 Pipa PVC AW 3"(Pipa dari Floor Drain ke saluran)
Jumlah = 67.00
5 Pipa PVC AW 4" (pipa dari Kloset ke septictank)
Jumlah = 98.00
6 Gate Valve Pipa Ø1" suplay air bersih (dekat pintu dalam Shaft )
Jumlah = 10.00
B PEKERJAAN PLUMBING
1 Pipa PVC AW Ø 1" distribusi air Bersih dari dag ke lantai 3
Jumlah = 125.00
2 Pipa PVC AW Ø 3/4" (distribusi ke sanitair )
Jumlah = 142.00
3 Pipa PVC AW Ø 2" (pipa dari wastafel ke saluran)
Jumlah = 165.00
4 Pipa PVC AW 3"(Pipa dari Floor Drain ke saluran)
Jumlah = 67.00
5 Pipa PVC AW 4" (pipa dari Kloset ke septictank)
Jumlah = 98.00
6 Gate Valve Pipa Ø1" suplay air bersih (dekat pintu dalam Shaft )
Jumlah = 10.00
GAN Volume
m
m 1125 m2
m2
m3
274.80 m3
bh
1.00 bh
m
m
18.00 m2
m2
m
m
24.00 m2
m2
Ls 1.00 Ls
ls 1.00 ls
m
m
m 103.68 m3
bh
m3
m
m
29.92 m3
29.92 m3
m
m3
m
m
m 18.85 m3
bh
m3
m
m
m 9.43 m3
bh
m3
Ls 1.00 Ls
m
m
696.00 m'
bh
m'
bh 58.00 bh
m
m
m 220.40 m2
bh
m2
m
m
m
bh
bh
kg/m
kg/m 13892.15 kg
bh
kg/m
m
m
m 78.65 m3
bh
m2
m
m
m 12.82 m3
m2
m
m
2.14 m3
m
m2
m
m
1.07 m3
m
m2
i2
m
m
6.66 m3
m
m2
m
m
0.80 m3
m
m2
m
m
m 444.00 m2
m2
m
53.42 m2
m 53.42 m2
m2
m
bh
kg/m
kg
m
bh
kg/m
kg 7498.46 kg
m
bh
kg/m
kg
m
bh
kg/m
kg
m
bh
kg/m
kg
605.57 kg
m
bh
kg/m
kg
m
m
m 66.60 m3
m3
m
m
m 4.01 m3
4.01 m3
m3
m
m
m 522.00 m3
bh
m3
m
m
bh 9312.48 kg
bh
kg
m
m
bh 58.00 m3
bh
m3
m
m
bh
280.00 m
bh
m
m
m
m3
428.60 m2
m
m
m
m2
m
m
112.20 m2
m
m2
m
m
m
m3
m
m
m
kg
7632.62 kg
m
m
m
m3
m
m
m
kg
m
m
kg/m
kg
1693.66 kg
m
m
kg/m
kg
m
m
m
m3
48.79 m3
m
m
m
m3
m
m 7.84 m3
m
m3
m
m
m
bh
m2
m
m 768.00 m2
bh
m2
m
m
bh
m2
m
m
bh
kg/m
m
m
m
m
m
m 4018.56 kg
m
m
m
m
m
m
m
m
kg
m
m
m
bh
m3
m
m 28.80 m2
bh
m2
m
m
bh
m2
m
m
bh
bh
m2
m
m
bh
bh
m2
m
40.55 m2
m
bh
bh
m2
m
m
bh
bh
m2
m
m
bh
m2
m
m
bh
bh
kg/m
kg
m
m
bh
bh
kg
m
m
bh
kg/m
bh
kg
m
m
bh
kg/m
bh
kg
503.60 kg
m
m
bh
bh
kg/m
kg
m
m
bh
bh
kg/m
kg
m
m
bh
kg/m
kg
m
m
bh
bh
kg/m
kg
m
m
m
bh
bh
m3
m
m
bh
m3 12.11 m3
m
m
m
bh
m3
m
m
m
bh
m3
NTAI 3
m
m
m 522.00 m3
bh
m3
m
m
9312.48 kg
bh
9312.48 kg
bh
kg
m
m
bh
58.00 m3
bh
m3
m
m
m
bh
m3
444.60 m2
m
m
m
bh
m2
m
m
125.00 m2
m
bh
m2
m
m
m
bh
m3
m
m
m
bh
kg
10704.61 kg
10704.61 kg
m
m
m
bh
m3
m
m
m
bh
kg
m
m
kg/m
bh
kg
1887.22 kg
m
m
kg/m
bh
kg
m
m
m
bh
m3
50.62 m3
m
m
m
bh
m3
m
m
8.06 m3
m
bh
m3
m
m
bh
280.00 m
bh
m
m
m
bh
m2
840.00 m2
m
m
bh
m2
m
m
bh
kg/m
m
m
m
m
m
m 4395.30 kg
m
m
m
m
m
m
m
m
kg
m
m
m
bh
100.80 m2
m2
100.80 m2
m
m
bh
m2
m
m
bh
bh
m2
m
m
bh
bh
m2
m
40.55 m2
m
bh
bh
m2
m
m
bh
bh
m2
m
m
bh
m2
m
m
bh
bh
kg/m
kg
m
m
bh
bh
kg
m
m
bh
kg/m
bh
kg
m
m
bh
kg/m
bh
kg
503.60 kg
m
m
bh
bh
kg/m
kg
m
m
bh
bh
kg/m
kg
m
m
bh
kg/m
kg
m
m
bh
bh
kg/m
kg
m
m
m
bh
bh
m3
m
m
bh
m3 12.11 m3
m
m
m
bh
m3
m
m
m
bh
m3
m
m
m 522.00 m3
bh
m3
m
m
bh
9312.48 kg
bh
kg
m
m
bh
58.00 m3
bh
58.00 m3
m3
m
m
bh
280.00 m
bh
m
m
m
bh
m3
444.60 m2
m
m
m
bh
m2
m
m
125.00 m2
m
bh
m2
m
m
m
bh
m3
m
m
m
bh
kg
9420.13 kg
m
m
m
bh
m3
m
m
m
bh
kg
m
m
kg/m
bh
kg
1887.22 kg
m
m
kg/m
bh
kg
m
m
m
bh
m3
50.62 m3
m
m
m
bh
m3
m
m
8.06 m3
m
bh
m3
m
m
840.00 m2
m
bh
m2
840.00 m2
m
m
bh
m2
m
m
bh
kg/m
m
m
m
m
m
m 4395.30 kg
m
m
m
m
m
m
m
m
kg
m
m
m
bh
m2
100.80 m2
m
m
bh
m2
m
m
bh
bh
m2
m
m
bh
bh
m2
m
23.98 m2
m
bh
bh
m2
m
m
bh
bh
m2
m
m
bh
m2
m
m
bh
bh
kg/m
kg
m
m
bh
bh
m2
m
m
bh
kg/m
bh
kg
m
m
bh
kg/m
bh
kg
244.89 kg
m
m
bh
bh
kg/m
kg
m
m
bh
bh
kg/m
kg
m
m
bh
kg/m
kg
m
m
bh
bh
kg/m
kg
m
m
m
bh
bh
m3
9.47 m3
m
m
bh
m3 9.47 m3
m
m
m
bh
m3
m
m
m
bh
m3
m
m
bh 672.00 m2
m
m
bh 299.81 m2
m
m
bh 280.00 m2
m
m
bh -37.80 m2
m
m
bh -60.48 m2
m
m
bh -7.98 m2
m
m
bh -28.56 m2
m
m
bh -16.80 m2
m
m
bh -14.70 m2
m
m
bh -2.80 m2
m
m
bh -1.82 m2
m
m
bh -56.00 m2
1024.87 m2
m2 2049.74 m2
m2 1024.87 m2
m
m
304.5 m2
m
m2
m2 10.00 m2
m
m
m
bh 432.00 m2
m
m
m
bh 432.00 m2
m
m
m
bh 86.40 m2
m
m
m
bh 43.20 m2
m
m
m
bh 864.00 m2
m
m
bh -48.00 m2
816.00 m2
m2 47.20 m2
m2 160.00 m2
m
m 27.30 m2
m
m 24.00 m2
m 26.40 m
m 19.40 m
m2 916.00 m2
m2 47.20 m2
m2 47.20 m2
m 70.00 m
m2 1024.87 m2
m2 1024.87 m2
m2 47.20 m2
m 39.60 m
m 29.70 m
m 47.52 m
m 47.52 m
m 7.92 m
m 158.40 m
m 8.52 m
m2 10.80 m2
kg 110.88 kg
m3 1.01 m3
m
m
bh 672.00 m2
m
m
bh 299.81 m2
m
m
bh 280.00 m2
m
m
bh -57.60 m2
m
m
bh -83.16 m2
m
m
bh -17.85 m2
m
m
bh -16.80 m2
m
m
bh -14.70 m2
m
m
bh -136.00 m2
m
m
bh -184.00 m2
m
m
bh -160.00 m2
m
m
bh -24.00 m2
m
m
bh -16.00 m2
m
m
bh -64.00 m2
m
m
bh -8.40 m2
m
m
bh -4.20 m2
465.10 m2
m2 930.20 m2
m2 465.10 m2
m
m
304.5 m2
m
m2
m2 10.00 m2
m
m
m
bh 864.00 m2
m
m
bh -48.00 m2
816.00 m2
m2 105.60 m2
m2 320.00 m2
m
m 27.30 m2
m
m 24.00 m2
m 26.40 m
m 19.40 m
m2 916.00 m2
m2 47.20 m2
m2 47.20 m2
m 70.00 m
m2 1024.87 m2
m2 1024.87 m2
m2 47.20 m2
m
m
bh 672.00 m2
m
m
bh 299.81 m2
m
m
bh 280.00 m2
m
m
bh -57.60 m2
m
m
bh -90.72 m2
m
m
bh -21.42 m2
m
m
bh -16.80 m2
m
m
bh -14.70 m2
m
m
bh -136.00 m2
m
m
bh -184.00 m2
m
m
bh -160.00 m2
m
m
bh -24.00 m2
m
m
bh -8.40 m2
m
m
bh -4.20 m2
533.97 m2
m2 1067.94 m2
m2 533.97 m2
m
m
304.5 m2
m
m2
m2 10.00 m2
m
m
m
bh 864.00 m2
m
m
bh -48.00 m2
816.00 m2
m2 105.60 m2
m2 320.00 m2
m
m 13.65 m2
m
m 12.00 m2
m 26.40 m
m 19.40 m
m2 916.00 m2
m2 105.60 m2
m2 105.60 m2
m 70.00 m
m2 1024.87 m2
m2 1024.87 m2
m2 47.20 m2
bh 121.00 bh
bh 14.00 bh
bh 16.00 bh
bh 1.00 bh
bh 60.00 bh
bh 30.00 bh
bh 6.00 bh
bh 15.00 bh
bh 45.00 bh
bh 2.00 bh
bh 3.00 bh
bh 6.00 bh
bh 10.00 bh
bh 143.00 bh
bh 12.00 bh
bh 2.00 bh
bh 100.00 bh
bh 28.00 bh
bh 8.00 bh
bh 20.00 bh
bh 80.00 bh
bh 4.00 bh
bh 10.00 bh
bh 143.00 bh
bh 12.00 bh
bh 2.00 bh
bh 100.00 bh
bh 23.00 bh
bh 8.00 bh
bh 20.00 bh
bh 80.00 bh
bh 4.00 bh
bh 1.00 bh
bh 1.00 bh
bh 1.00 bh
bh 10.00 bh
DIV. NO.
2.2.1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10 .
11 .
12 .
2.3.1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10 .
11 .
3.2.1
1
2
3
4
5.
4.1.1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10 .
11 .
12 .
13 .
14 .
15 .
16 .
17 .
18 .
19 .
20 .
21 .
22 .
23 .
24 .
25 .
26 .
27 .
28 .
29 .
30 .
31 .
32 .
33 .
4.2.1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10 .
11 .
12 .
13 .
14
.
15 .
16 .
17 .
4.4.1
1.
2.
3.
4.
5.
6.
7
8.
4.4.2
1.
2.
3.
4.
5.
6.
7.
8.
9.
4.4.3
1.
2
3.
4.
5.
6.
7.
8.
9
10 .
11 .
12 .
13
14 .
15 .
16
17 .
18
19 .
20 .
21
22
4.5.1
1.
2.
3.
4.
5.
6.
4.5.1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10 .
11 .
12 .
13 .
14 .
15 .
16 .
17 .
4.6.2
1.
2.
3.
4.
5.
6.
7.
8.
9.
10 .
11 .
12 .
13 .
14 .
15 .
16 .
4.7.1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10 .
11 .
12 .
13 .
5.1.1
1.
2.
3.
4.
5.
6.
7.
8.
9.
10 .
11 .
12 .
13 .
13.a .
13.b .
14 .
15 .
16 .
Taksir
1.
2.
3
4.
5
6.
7.
8.
9.
10 .
11 .
12 .
13 .
14 .
14.a .
15 .
16 .
17 .
18
19
JENIS PEKERJAAN SATUAN
HARGA SATUAN PEKERJAAN PERSIAPAN
Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter m2
Pengukuran dan Pemasangan 1 m' Bouwplank m
Pembuatan 1 m2 kantor sementara lantai plesteran m2
Pembuatan 1 m2 gudang semen dan peralatan m2
Pembuatan 1 m2 bedeng pekerja m2
Pembersihan dan perataan lapangan 1 m2 m2
Pembuatan 1 m2 Steger/perancah dari bambu m2
Pembuatan 1 buah kotak adukan ukuran 40cm x 50cm x 25cm bh
Pembongkaran 1m3 beton bertulang m3
Pembongkaran 1m3 dinding tembok bata m3
Pembuatan 1 m2 pagar kawat jaring galvanis panjang 240 cm m2
Pemasangan 1 unit scafolding (sewa) unit
Pemasangan 1 m2 dinding bata lubang (8x8x16) cm tebal 1/2 batu campuran 1 SP:4PP m2
153,769.78
96,567.57
1,431,176.70
1,237,431.42
1,423,963.87
23,287.50
100,490.45
202,454.28
1,828,442.50
914,221.25
47,411.00
89,487.25
100,193.75
123,423.75
133,308.00
161,373.75
7,388.75
43,872.50
36,943.75
73,887.50
406,746.95
403,613.20
421,725.70
1,377,055.67
1,322,717.70
1,536,418.88
1,484,504.72
102,120.00
1,463,118.58
1,330,837.36
1,540,489.67
1,611,352.64
1,627,561.80
1,664,161.17
1,784,543.21
217,224.78
22,103.87
207,749.80
249,492.27
380,014.34
389,432.84
487,194.34
475,843.84
412,553.59
147,940.60
6,219,995.34
7,632,201.72
11,260,680.75
8,558,191.56
7,467,300.93
7,192,059.93
162,687.34
129,888.73
158,645.25
1,616,440.58
1,457,568.08
2,487,393.08
77,373.15
162,687.34
1,752,423.05
1,860,048.03
40,583.50
68,422.13
83,395.94
873,139.66
30,306.10
1,097,945.25
222,067.88
1,626,016.05
1,824,135.75
722,122.09
180,648.73
110,506.38
146,630.75
2,934,973.65
4,429,973.65
4,257,473.65
5,062,473.65
292,423.43
285,783.24
143,937.69
141,829.06
812,336.53
874,294.79
1,538,498.28
934,265.28
90,115.56
101,056.68
87,859.84
97,947.20
51,859.32
93,057.00
69,498.20
84,359.89
52,166.88
374,530.90
757,587.71
172,980.99
237,754.04
205,998.63
172,980.99
237,754.04
44,553.23
51,401.92
64,178.70
101,243.78
2,322,866.65
182,680.95
492,918.75
232,570.27
266,414.08
2,539,910.64
398,267.01
347,667.01
156,486.25
65,515.50
448,867.01
46,983.58
65,203.36
64,355.47
150,001.29
49,836.77
65,718.02
8,118,298.50
847,026.75
783,813.55
671,157.48
763,543.65
6,646,055.85
9,533,011.25
160,062.75
135,105.45
131,031.00
93,988.35
93,457.05
179,004.40
480,612.95
461,679.00
52,696.45
74,185.35
173,678.75
573,878.75
270,370.75
56,405.20
56,405.20
39,769.88
115,776.25
115,776.25
678,563.25
66,740.25
621,063.25
171,148.75
176,522.70
480,189.98
749,743.08
2,570,928.50
21,201.11
60,259.37
52,428.50
91,905.16
31,676.75
59,877.91
35,805.85
25,754.85
26,260.54
42,470.02
38,561.24
19,130.85
63,009.65
5,080,256.68
809,061.68
4,371,533.55
2,125,685.33
12,823,198.05
554,628.21
990,748.00
107,864.25
62,163.25
94,127.50
86,409.08
36,895.48
41,611.97
56,831.56
69,294.71
62,219.97
62,219.97
694,430.89
249,320.92
353,461.41
409,121.41
310,353.66
365,668.66
353,055.75
450,863.25
30,528.61
991,186.15
1,637,140.00
1,803,775.00
7,883.54
48,046.14
1,457,420.96
1,744,920.96
1,295,194.28
1,056,197.64
373,608.51
679,080.75
518,491.44
No URAIAN
a b
I PEKERJAAN PERSIAPAN
II PEKERJAAN STRUKTUR LANTAI 1
A PEKERJAAN TANAH DAN URUGAN
B PEKERJAAN PONDASI
C PEKERJAAN KONSTRUKSI BETON BERTULANG s/d Pelat Lantai 2
D PEKERJAAN KONSTRUKSI TANGGA UTAMA KIRI&KANAN
III PEKERJAAN STRUKTUR LANTAI 2
A PEKERJAAN KONSTRUKSI BETON BERTULANG s/d PELAT LANTAI 3
B PEKERJAAN KONSTRUKSI TANGGA UTAMA KIRI&KANAN
IV PEKERJAAN STRUKTUR LANTAI 3
A PEKERJAAN KONSTRUKSI BETON BERTULANG s/d PELAT DAK ATAP
B PEKERJAAN KONSTRUKSI TANGGA UTAMA KIRI&KANAN
V PEKERJAAN ARSITEKTUR LANTAI 1
A PEKERJAAN PLESTERAN
B PEKERJAAN PINTU DAN JENDELA
C PEKERJAAN FINISHING LANTAI & DINDING
D PEKERJAAN FINISHING LANTAI & DINDING TOILET
E PEKERJAAN FINISHING TANGGA KANAN & KIRI
F PEKERJAAN PLAFOND RUANG
G PEKERJAAN PLAFOND Toilet
H PEKERJAAN SELASAR DAN SALURAN
I PEKERJAAN SELASAR DAN SALURAN
VI PEKERJAAN ARSITEKTUR LANTAI 2
A PEKERJAAN PLESTERAN
B PEKERJAAN PINTU DAN JENDELA
C PEKERJAAN FINISHING LANTAI & DINDING
D PEKERJAAN FINISHING LANTAI & DINDING TOILET
E PEKERJAAN FINISHING TANGGA KANAN & KIRI
F PEKERJAAN PLAFOND RUANG
G PEKERJAAN PLAFOND Toilet
H Cat Dinding Eksterior
VII PEKERJAAN ARSITEKTUR LANTAI 3
A PEKERJAAN PLESTERAN
B PEKERJAAN PINTU DAN JENDELA
C PEKERJAAN FINISHING LANTAI & DINDING
D PEKERJAAN FINISHING LANTAI & DINDING TOILET
E PEKERJAAN FINISHING TANGGA KANAN & KIRI
F PEKERJAAN PLAFOND RUANG
G PEKERJAAN PLAFOND Toilet
H Cat Dinding Eksterior
VIII PEKERJAAN ELEKTRIKAL DAN PLUMBING LANTAI 1
A PEKERJAAN ELEKTRIKAL
B PEKERJAAN PLUMBING
IX PEKERJAAN ELEKTRIKAL DAN PLUMBING LANTAI 3
A PEKERJAAN ELEKTRIKAL
B PEKERJAAN PLUMBING
X PEKERJAAN ELEKTRIKAL DAN PLUMBING LANTAI 3
A PEKERJAAN ELEKTRIKAL
B PEKERJAAN PLUMBING
XI PEKERJAAN LAIN-LAIN
A PEKERJAAN PEMBERSIHAN AKHIR
JUMLAH TOTAL
PPN 11%
PPH 3 %
TOTAL SELURUH
KONTRAK
Jumlah Harga Bobot
(Rp) (%)
c d
544,813,522.09 2.73
33,595,225.27 0.17
1,027,726,152.08 5.15
2,016,128,708.09 10.11
49,468,523.66 0.25
1,835,226,026.05 9.20
49,468,523.66 0.25
1,806,834,052.90 9.06
59,389,546.13 0.30
1,796,384,924.39 9.01
451,925,000.00 2.27
922,821,531.76 4.63
201,113,700.28 1.01
34,258,237.29 0.17
870,200,000.00 4.36
11,806,364.78 0.06
77,373,280.62 0.39
102,202,158.15 0.51
835,314,292.84 4.19
947,966,000.00 4.75
618,191,570.14 3.10
218,505,340.05 1.10
34,258,237.29 0.17
870,200,000.00 4.36
11,806,364.78 0.06
77,373,280.62 0.39
953,557,382.68 4.78
779,037,000.00 3.91
618,191,570.14 3.10
176,183,721.77 0.88
27,070,118.64 0.14
870,200,000.00 4.36
22,097,869.15 0.11
77,373,280.62 0.39
241,490,243.43 1.21
53,281,834.04 0.27
256,082,302.55 1.28
68,798,517.62 0.34
212,427,001.65 1.07
68,798,517.62 0.34
15,000,000.00 0.08
19,943,939,922.82 100
1,994,393,992.28
598,318,197.68
22,536,652,112.79
No URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
a b c d e
I PEKERJAAN PERSIAPAN
A PEKERJAAN PERSIAPAN DAN LAIN LAIN
1 Survei, Pengukuran site dan Bouplank
2 Bongkar Bangunan Lama
3 Papan Nama Proyek
4 Pembuatan Gudang bahan dan Peralatan
5 Penyediaan listrik kerja
6 Penyediaan listrik kerja
7 Tes PDA
8 K3
II PEKERJAAN STRUKTUR LANTAI 1
A PEKERJAAN TANAH DAN URUGAN
1 Pek. Mobilisasi dan Demobilisasi
2 Pek. Pengadaan Tiang Pancang 40 x 40 cm
3 Pek. Pemotongan Tiang Pancang
4 Pek. Pas Bekisting pile cap
B PEKERJAAN PONDASI
1 Pek. Mobilisasi dan Demobilisasi
2 Pek. Pengadaan Tiang Pancang 40 x 40 cm
3 Pek. Pemotongan Tiang Pancang
4 Pek. Pas Bekisting pile cap
5 Pek. Pas Pembesian pile cap
6 Pek. Beton pile cap mutu k-350
7 Pek. Pondasi Batu bata menerus ad 1:4 toilet dan selasar
8 Pek. Urugan Pasir dibawah pondasi batu bata menerus
9 Pek. Lantai Kerja dibawah pondasi batu bata menerus
C PEKERJAAN KONSTRUKSI BETON BERTULANG s/d Pelat Lantai 2
1 Pek. Lantai Kerja Dibawah Sloof uk 30/50 cm
2 Pek. Lantai Kerja Dibawah Sloof uk 15/25 cm
3 Pek. Bekisting Sloof uk 30/50 cm
4 Pek. Bekisting Sloof uk 15/25 cm
5 Pek. Pembesian Sloof uk 30/50 cm
6 Pek. Pembesian Sloof uk 15/25 cm
7 Pek. Beton Sloof uk 30/50 cm mutu K-300
8 Pek. Beton Sloof uk 15/25 cm mutu K-300
9 Pek. Bekisting Kolom uk 50/50 cm
10 Pek. Pembesian Kolom uk 50/50 cm
11 Pek. Beton Kolom uk 50/50 cm
12 Pek. Kolom praktis uk 12/12 cm
13 Pek. Bekisting Balok (B1) uk 30/50 cm
14 Pek. Bekisting Balok (B2) uk 20/40 cm
15 Pek. Pembesian Balok (B1) uk 30/50 cm
16 Pek. Pembesian Balok (B2) uk 20/40 cm
17 Pek. Beton Balok (B1) uk 30/50 cm
18 Pek. Beton Balok (B2) uk 20/40 cm
19 Pek. Bekisting Pelat lantai 1
20 Pek. Pembesian Pelat Lantai 1
21 Pek. Beton Pelat lantai 1
D PEKERJAAN KONSTRUKSI TANGGA UTAMA KIRI&KANAN
1 Pek. Bekisting tangga utama
2 Pek. Pembesian tangga utama
3 Pek. Beton tangga utama
III PEKERJAAN STRUKTUR LANTAI 2
A PEKERJAAN KONSTRUKSI BETON BERTULANG s/d PELAT LANTAI 3
1 Pek. Bekisting Kolom uk. 50/50 cm
2 Pek. Pembesian Kolom uk 50/50 cm
3 Pek. Beton Kolom uk 50/50 cm
4 Pek. Bekisting Balok (B1) uk 30/50 cm
5 Pek. Bekisting Balok (B2) uk 20/40 cm
6 Pek. Pembesian Balok (B1) uk 30/50 cm
7 Pek. Pembesian Balok (B2) uk 20/40 cm
8 Pek. Beton Balok (B1) uk 30/50 cm
9 Pek. Beton Balok (B2) uk 20/40 cm
10 Pek. Kolom praktis uk 12/12 cm
11 Pek. Bekisting Pelat lantai 2
12 Pek. Pembesian Pelat Lantai 2
13 Pek. Beton Pelat lantai 2
B PEKERJAAN KONSTRUKSI TANGGA UTAMA KANAN&KIRI
1 Pek. Bekisting tangga utama
2 Pek. Pembesian tangga utama
3 Pek. Beton tangga utama
IV PEKERJAAN STRUKTUR LANTAI 3
A PEKERJAAN KONSTRUKSI BETON BERTULANG s/d PELAT LANTAI ATAP (DAK ATAP)
1 Pek. Bekisting Kolom uk. 50/50 cm
2 Pek. Pembesian Kolom uk 50/50 cm
3 Pek. Beton Kolom uk 50/50 cm
4 Pek. Kolom praktis uk 12/12 cm
5 Pek. Bekisting Balok (B1) uk 30/50 cm
6 Pek. Bekisting Balok (B2) uk 20/40 cm
7 Pek. Pembesian Balok (B1) uk 30/50 cm
8 Pek. Pembesian Balok (B2) uk 20/40 cm
9 Pek. Beton Balok (B1) uk 30/50 cm
10 Pek. Beton Balok (B2) uk 20/40 cm
11 Pek. Bekisting Pelat lantai 2
12 Pek. Pembesian Pelat Lantai 2
13 Pek. Beton Pelat lantai 2
B PEKERJAAN KONSTRUKSI TANGGA UTAMA KANAN&KIRI
1 Pek. Bekisting tangga Samping
2 Pek. Pembesian tangga utama
3 Pek. Beton tangga utama
V PEKERJAAN ARSITEKTUR LANTAI 1
A PEKERJAAN PLESTERAN
1 Pek. Pasangan Dinding Batu Bata 1/2 ad 1:4
2 Pek. Plesteran ad, 1:4 (T 15 mm)/dinding luar, dalam, toilet
3 Pek. Acian (Dinding luar)
4 Pek. Plesteran Kolom
5 Pek. Pasangan Glass block di ruang shaft dan toilet pria (12 bh)
B PEKERJAAN PINTU DAN JENDELA
1 Pek. Pintu Type P-1
2 Pek. Pintu Type P-2
3 Pek. Pintu Type P-3
4 Pek. Pintu Type P-4
5 Pek. Pintu jendela Type PJ1
6 Pek. Pintu jendela Type PJ3
7 Pek. Pintu jendela Type PJ5
8 Pek. Jendela Type J-8
9 Pek. Jendela Type J-13
10 Pek. Bounvenligth Type BV-1
11 Pek. Bounvenligth Type BV-2
C PEKERJAAN FINISHING LANTAI & DINDING
1 Pek. Timbunan Peninggian Lantai
2 Pek. Pemadatan Tanah Timbunan per 20 cm
3 Pek. Urug Pasir diatas Timbunan
4 Pek. Cor Rabat Beton diatas Pasir Urug
5 Pek. Pas Lantai Granit Tile, 80 x 80 cm
D PEKERJAAN FINISHING LANTAI & DINDING TOILET
1 Pek. Pas Lantai Keramik 40 x 40 cm Toilet Pria warna
2 Pek. Pas Dinding Keramik 20 X 25 toilet pria
3 Kloset duduk ex.Amstand(berikut Asesories)
4 Shower Spray ex Amstand(berikut Asesories)
5 Kloset Jongkok ex Amstand
6 Wastafel + Assesories terpasang
7 Kran Wastafel ex Amstand + Assesories terpasang
8 Floor Drain Staim;esstee;
9 Kran Dinding
10 Biotank kap. 4,8 M3
E PEKERJAAN FINISHING TANGGA KANAN & KIRI
1 Pas Granit Untrade 60 x 60 cm
2 Pas Granit Oftrade (ketinggian lihat gambar/ diambil uk 30x30
3 Gores Step Nousing
4 Pasang Railling Tangga Utama (bahan Stainles)
F PEKERJAAN PLAFOND RUANG
1 Penutup Plafond Akuistik
G PEKERJAAN PLAFOND Toilet
1 Rangka Plafond Hollow Galvanis 2/4, 4/4
2 Penutup Plafond Kalsiboard tbl. 3,5 mm
3 Pasang List Plafond Kecil
H PEKERJAAN CAT
1 Cat Dinding Eksterior
2 Cat Dinding Interior
3 Cat Plafond Kalsiboard
I PEKERJAAN SELASAR DAN SALURAN
1 Galian Ris Selasar
2 Pasangan Ris Bata
3 Timbunan Tanah Selasar, T=45 cm
4 Pemadatan Tanah Timbunan (Pemadatan Per 20 cm)
5 Urugan Pasir T=10 cm
6 Berapen Ris Bata ad,1:5
7 Cor Rabat Beton T=8cm Keliling Selasar
8 Beton Bertulang Pelat Diatas Saluran T=10 cm,
VI PEKERJAAN ARSITEKTUR LANTAI 2
A PEKERJAAN PLESTERAN
1 Pek. Pasangan Dinding Batu Bata 1/2 ad 1:4
2 Pek. Plesteran ad, 1:4 (T 15 mm)/dinding luar, dalam, toilet
3 Pek. Acian (Dinding luar)
4 Pek. Plesteran Kolom
5 Pek. Pasangan Glass block di ruang shaft dan toilet pria (12 bh)
B PEKERJAAN PINTU DAN JENDELA
1 Pek. Pintu Type P-1
2 Pek. Pintu Type P-3
3 Pek. Pintu Type P-6
4 Pek. jendela Type J1
5 Pek. jendela Type J6
6 Pek. jendela Type J8
7 Pekerjaan Bounvenligth Type BV3
8 Pekerjaan Bounvenligth Type BV3"
9 Pekerjaan Bounvenligth Type BV4
C PEKERJAAN FINISHING LANTAI & DINDING
1 Pek. Pas Lantai Granit Tile, 80 x 80 cm
D PEKERJAAN FINISHING LANTAI & DINDING TOILET
1 Pek. Pas Lantai Keramik 40 x 40 cm Toilet Pria warna
2 Pek. Pas Dinding Keramik 20 X 25 toilet pria
3 Kloset duduk ex.Amstand(berikut Asesories)
4 Shower Spray ex Amstand(berikut Asesories)
5 Wastafel + Assesories terpasang
6 Kran Wastafel ex Amstand + Assesories terpasang
7 Floor Drain Staim;esstee;
8 Septictank kap. 9m3
E PEKERJAAN FINISHING TANGGA KANAN & KIRI
1 Pas Granit Untrade 30x60
2 Pas Granit Oftrade (ketinggian lihat gambar/ diambil uk 30x30
3 Gores Step Nousing
4 Pasang Railling Tangga Utama (bahan Stainles)
F PEKERJAAN PLAFOND RUANG
1 Penutup Plafond Akuistik
G PEKERJAAN PLAFOND Toilet
1 Rangka Plafond Hollow Galvanis 2/4, 4/4
2 Penutup Plafond Kalsiboard tbl. 3,5 mm
3 Pasang List Plafond Kecil
H PEKERJAAN CAT
1 Cat Dinding Eksterior
2 Cat Dinding Interior
3 Cat Plafond Kalsiboard
VII PEKERJAAN ARSITEKTUR LANTAI 3
A PEKERJAAN PLESTERAN
1 Pek. Pasangan Dinding Batu Bata 1/2 ad 1:4
2 Pek. Plesteran ad, 1:4 (T 15 mm)/dinding luar, dalam, toilet
3 Pek. Acian (Dinding luar)
4 Pek. Plesteran Kolom
5 Pek. Pasangan Glass block di ruang shaft dan toilet pria (12 bh)
B PEKERJAAN PINTU DAN JENDELA
1 Pek. Pintu Type P-1
2 Pek. Pintu Type P-3
3 Pek. Pintu Type P-6
4 Pek. jendela Type J3
5 Pek. jendela Type J4
6 Pek. jendela Type J7
7 Pekerjaan Bounvenligth Type BV3
8 Pekerjaan Bounvenligth Type BV3"
C PEKERJAAN FINISHING LANTAI & DINDING
RENCANA (OH) KAPASITAS PEKERJA/HARI DURASI
f g=1/c h=fxg i=d/h
TAI ATAP (DAK ATAP)
I PEKERJAAN PERSIAPAN
H PEKERJAAN CAT
1 Cat Dinding Eksterior 1,024.87 m2
2 Cat Dinding Interior 1,024.87 m2
3 Cat Plafond Kalsiboard 47.20 m
B PEKERJAAN PLUMBING
1 Pipa tegak Air Bersih suplai Ø 1" (dari sumber ke Tanki Dag) 70.00 m'
2 Pipa PVC AW Ø 1" distribusi air Bersih dari dag ke lantai 1 150.00 m'
3 Pipa PVC AW Ø 3/4" (distribusi ke sanitair ) 120.00 m'
4 Pipa PVC AW Ø 2" (pipa dari wastafel ke saluran) 70.00 m'
5 Pipa PVC AW 3"(Pipa dari Floor Drain ke saluran) 43.00 m'
6 Pipa PVC AW 4" (pipa dari Kloset ke septictank) 66.00 m'
7 Gate Valve Pipa Ø1" suplay air bersih (dekat pintu dalam Shaft ) 10.00 m'
B PEKERJAAN PLUMBING
1 Pipa PVC AW Ø 1" distribusi air Bersih dari dag ke lantai 2 125.00 m'
2 Pipa PVC AW Ø 3/4" (distribusi ke sanitair ) 142.00 m'
3 Pipa PVC AW Ø 2" (pipa dari wastafel ke saluran) 165.00 m'
4 Pipa PVC AW 3"(Pipa dari Floor Drain ke saluran) 67.00 m'
5 Pipa PVC AW 4" (pipa dari Kloset ke septictank) 98.00 m'
6 Gate Valve Pipa Ø1" suplay air bersih (dekat pintu dalam Shaft ) 10.00 m'
B PEKERJAAN PLUMBING
1 Pipa PVC AW Ø 1" distribusi air Bersih dari dag ke lantai 3 125.00 m'
2 Pipa PVC AW Ø 3/4" (distribusi ke sanitair ) 142.00 m'
3 Pipa PVC AW Ø 2" (pipa dari wastafel ke saluran) 165.00 m'
4 Pipa PVC AW 3"(Pipa dari Floor Drain ke saluran) 67.00 m'
5 Pipa PVC AW 4" (pipa dari Kloset ke septictank) 98.00 m'
6 Gate Valve Pipa Ø1" suplay air bersih (dekat pintu dalam Sha 10.00 bh
XI PEKERJAAN LAIN-LAIN
1 PEKERJAAN PEMBERSIHAN AKHIR 1.00 Ls
JUMLAH TOTAL
Harga Satuan Jumlah Harga
Bobot %
(Rp) (Rp)
e f=(c x e) g
3
380,014.34 198,367,484.18 0.99
22,103.87 205,841,805.30 1.03
1,784,543.21 103,503,506.35 0.52
389,432.84 173,141,839.55 0.87
389,432.84 48,679,104.69 0.24
22,103.87 236,613,317.03 1.19
22,103.87 41,714,808.40 0.21
1,784,543.21 90,326,439.27 0.45
1,784,543.21 14,390,556.47 0.07
129,888.73 36,368,845.45 0.18
487,194.34 409,243,243.50 2.05
22,103.87 97,153,119.99 0.49
1,784,543.21 179,881,955.87 0.90
beton s/d lantai 2 1,835,226,026.05 9.20
AP
380,014.34 198,367,484.18 0.99
22,103.87 205,841,805.30 1.03
1,784,543.21 103,503,506.35 0.52
129,888.73 36,368,845.45 0.18
389,432.84 173,141,839.55 0.87
389,432.84 48,679,104.69 0.24
22,103.87 208,221,343.89 1.04
22,103.87 41,714,808.40 0.21
1,784,543.21 90,326,439.27 0.45
1,784,543.21 14,390,556.47 0.07
487,194.34 409,243,243.50 2.05
22,103.87 97,153,119.99 0.49
1,784,543.21 179,881,955.87 0.90
beton s/d lantai Atap 1,806,834,052.90 9.06
2 Kabel ladder
16,400,250.00
6 Instalasi TV
1,050,000.00
18 Outled TV
255,000.00
1 4,844,189.94
Pipa tegak Air Bersih suplai Ø 1" (dari sumber ke Tanki Dag)
2 10,380,407.01
Pipa PVC AW Ø 1" distribusi air Bersih dari dag ke lantai 1
3 4,987,916.51
Pipa PVC AW Ø 3/4" (distribusi ke sanitair )
4 7,003,951.61
Pipa PVC AW Ø 2" (pipa dari wastafel ke saluran)
5 14,926,495.23
Pipa PVC AW 3"(Pipa dari Floor Drain ke saluran)
6 6,888,873.75
Pipa PVC AW 4" (pipa dari Kloset ke septictank)
7 4,250,000.00
Gate Valve Pipa Ø1" suplay air bersih (dekat pintu dalam Shaft )
7 53,281,834.04
IX PEKERJAAN ELEKTRIKAL DAN PLUMBING LANTAI 2
A PEKERJAAN ELEKTRIKAL
15 256,082,302.55
B PEKERJAAN PLUMBING
1 8,650,339.17
Pipa PVC AW Ø 1" distribusi air Bersih dari dag ke lantai 2
2 5,902,367.86
Pipa PVC AW Ø 3/4" (distribusi ke sanitair )
3 16,509,314.50
Pipa PVC AW Ø 2" (pipa dari wastafel ke saluran)
4 23,257,562.34
Pipa PVC AW 3"(Pipa dari Floor Drain ke saluran)
5 10,228,933.75
Pipa PVC AW 4" (pipa dari Kloset ke septictank)
6 4,250,000.00
Gate Valve Pipa Ø1" suplay air bersih (dekat pintu dalam Shaft )
7 68,798,517.62
X PEKERJAAN ELEKTRIKAL DAN PLUMBING LANTAI 3
A PEKERJAAN ELEKTRIKAL
16 Adaptor 12 V 1,000,000.00
10 212,427,001.65
B PEKERJAAN PLUMBING
1 8,650,339.17
Pipa PVC AW Ø 1" distribusi air Bersih dari dag ke lantai 3
2 5,902,367.86
Pipa PVC AW Ø 3/4" (distribusi ke sanitair )
3 16,509,314.50
Pipa PVC AW Ø 2" (pipa dari wastafel ke saluran)
4 23,257,562.34
Pipa PVC AW 3"(Pipa dari Floor Drain ke saluran)
5 10,228,933.75
Pipa PVC AW 4" (pipa dari Kloset ke septictank)
6 4,250,000.00
Gate Valve Pipa Ø1" suplay air bersih (dekat pintu dalam Shaft )
7 68,798,517.62
XI PEKERJAAN LAIN-LAIN
1 PEKERJAAN PEMBERSIHAN AKHIR 7 15,000,000.00
19,937,929,634.32
RENCANA KEMAJUAN PEKERJAAN
KOMULATIF RENCANA PEKERJAAN
Bobot %
1 2
1 2 3 4 5 6 7 8 9 10
0.05 0.003
0.02
0.04
0.06
0.38 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
2.16 0.11 0.11 0.11 0.11 0.11 0.11 0.11
0.04 0.003 0.003
0.23
1.54
0.70
0.10
0.00
0.01
0.04
0.01
0.56
0.07
0.83
0.07
0.56
0.03
0.99
1.03
0.52
0.23
0.84
0.22
0.85
0.19
0.44
0.07
1.88
0.45
0.26
0.08
0.06
0.11
0.99
1.03
0.52
0.87
0.24
1.19
0.21
0.45
0.07
0.18
2.05
0.49
0.90
0.08
0.06
0.11
0.99
1.03
0.52
0.18
0.87
0.24
1.04
0.21
0.45
0.07
2.05
0.49
0.90
0.01
0.20
0.09
7.63
0.93
0.27
0.14
0.05
0.43
0.15
0.26
0.20
0.20
0.37
0.16
0.26
0.20
0.01
0.02
2.27
0.87
0.16
0.18
0.32
3.10
0.06
0.21
0.13
0.01
0.02
0.26
0.03
0.01
0.00
0.28
1.01
0.05
0.02
0.01
0.09
0.17
4.36
4.36
0.03
0.02
0.02
0.06
0.20
0.18
0.01
0.39
0.02
0.23
0.10
0.02
0.02
0.04
0.06
-
0.01
0.01
0.01
0.51
3.46
0.42
0.12
0.14
0.05
4.19
0.83
0.16
0.21
2.43
0.17
0.17
0.07
0.64
0.08
4.75
3.10
0.13
0.43
0.20
0.01
0.20
0.02
0.00
0.00
0.09
1.10
0.05
0.02
0.01
0.09
0.17
4.36
0.03
0.02
0.02
0.06
0.20
0.18
0.01
0.39
3.98
0.48
0.14
0.14
0.05
4.78
0.91
0.19
0.21
1.05
0.92
0.52
0.10
0.01
3.91
3.10
0.13
0.43
0.20
0.01
0.10
0.01
0.00
0.00
0.88
0.03
0.01
0.01
0.09
0.14
4.36
0.06
0.03
0.02
0.11
0.20
0.18
0.01
0.39
0.29
0.08
0.27
0.14
0.10
0.01
0.02
0.13
0.01
0.02
0.00
0.03
0.02
0.03
0.01
0.03
0.00
0.00
0.02
1.21
0.02
0.05
0.03
0.04
0.07
0.03
0.02
0.27
0.29
0.28
0.23
0.10
0.01
0.15
0.01
0.00
0.08
0.02
0.05
0.01
0.05
0.02
1.28
0.04
0.03
0.08
0.12
0.05
0.02
0.35
0.02
0.28
0.23
0.08
0.01
0.15
0.01
0.00
0.08
0.01
0.05
0.01
0.05
0.02
0.04
0.01
0.03
1.07
0.04
0.03
0.08
0.12
0.05
0.02
0.35
0.08
104.47
0.153 0.258 0.303 0.411 0.411 0.412 0.450 0.411 0.298 0.302
0.153 0.41 0.71 1.12 1.54 1.95 2.40 2.81 3.11 3.41
BULAN KE-1
2 3
11 12 13 14 15 16 17 18 19 20 21 22
0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003
0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002
0.005 0.005 0.005 0.005 0.005
0.01 0.01 0.01 0.01 0.01
0.11 0.11 0.11 0.11 0.11 0.11 0.1 0.11 0.11 0.11 0.11 0.11
0.003 0.003 0.003 0.003 0.003 0.003 0.0 0.003 0.003 0.003 0.003 0.003
0.02 0.02 0.0 0.02 0.02 0.02 0.02 0.02
0.08 0.08 0.1 0.08 0.08 0.08 0.08 0.08
0.264 0.264 0.257 0.136 0.208 0.208 0.208 0.224 0.224 0.224 0.224 0.224
3.67 3.94 4.19 4.33 4.54 4.74 4.95 5.18 5.40 5.62 5.85 6.07
4 5
23 24 25 26 27 28 1 2 3 4 5 6 7
0.003 0.003
0.002 0.002
0.005 0.005
0.01
0.11
0.003
0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.001 0.001 0.001 0.001 0.001
0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
0.011 0.011
0.003 0.003
0.06
0.224 0.170 0.159 0.159 0.159 0.159 0.159 0.143 0.143 0.143 0.143 0.156 0.135
6.30 6.47 6.62 6.78 6.94 7.10 7.26 7.40 7.55 7.69 7.83 7.99 8.13
BULAN KE-2
6 7
8 9 10 11 12 13 14 15 16 17 18 19 20
0.01 0.01
0.01 0.01
0.12
10 11
6 7 8 9 10 11 12 13 14 15 16 17 18
0.10
0.09 0.09
0.07 0.07
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
0.04 0.04 0.04 0.04 0.04
0.12 0.12 0.12 0.12 0.12 0.12
0.04 0.04 0.04 0.04 0.04
0.06 0.06 0.06 0.06 0.06 0.06 0.06
0.01 0.01 0.01 0.01 0.01
0.19 0.19 0.19 0.19 0.19
0.06
0.03
0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
0.03 0.03 0.03 0.03 0.03
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
13 14 15
4 5 6 7 8 9 10 11 12 13 14 15 16
0.10 0.10 0.10 0.10 0.10
0.10 0.10 0.10 0.10 0.10
0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
0.05 0.05 0.05 0.05 0.05
0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.06 0.06 0.06 0.06
0.02 0.02 0.02 0.02
0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
0.06 0.06 0.06
15 16
17 18 19 20 21 22 23 24 25 26 27 28 1
0.06 0.06 0.06
0.10
0.10
0.03
0.02
0.05 0.05 0.05 0.05 0.05 0.05 0.05
0.281 0.281 0.281 0.216 0.216 0.178 0.178 0.178 0.178 0.178 0.178 0.178 0.248
40.42 40.70 40.98 41.20 41.41 41.59 41.77 41.95 42.13 42.31 42.48 42.66 42.91
BUL
17 18
2 3 4 5 6 7 8 9 10 11 12
0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.03 0.03 0.03 0.03 0.03 0.03
0.11
0.05
0.13
0.04
0.60
0.68 0.68 0.68 0.68 0.68 0.68 0.68
0.02 0.02 0.02 0.02 0.02 0.02
0.248 0.248 0.248 1.002 1.002 1.002 0.956 0.956 0.956 0.753 0.928
43.16 43.41 43.65 44.66 45.66 46.66 47.62 48.57 49.53 50.28 51.21
BULAN KE-5
19 20
13 14 15 16 17 18 19 20 21 22 23
0.11 0.11 0.11 0.11 0.11 0.11 0.11
0.05 0.05 0.05 0.05
0.13 0.13 0.13 0.13 0.13 0.13 0.13
0.04 0.04 0.04 0.04
0.09 0.09 0.09 0.09 0.09
0.02 0.02 0.02
0.14 0.14 0.14 0.14
0.60 0.60 0.60 0.60 0.60 0.60
0.03 0.03
0.05 0.05 0.05 0.05 0.05 0.05 0.05
0.978 0.978 0.978 0.978 1.002 1.002 0.403 0.227 0.227 0.171 0.171
52.19 53.16 54.14 55.12 56.12 57.12 57.53 57.75 57.98 58.15 58.32
20 21
24 25 26 27 28 1 2 3 4 5
0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
0.06 0.06 0.06 0.06 0.06 0.06 0.06
0.03 0.03 0.03
0.171 0.171 0.171 0.198 0.198 0.198 0.198 0.198 0.198 0.198
58.49 58.67 58.84 59.03 59.23 59.43 59.63 59.83 60.02 60.22
BULAN KE-6
22
6 7 8 9 10 11 12 13 14 15
0.14
0.06
0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
0.003
0.03
0.32
0.26
0.09
0.11
0.198 0.113 0.113 0.113 0.113 0.113 0.113 0.113 0.113 0.802
60.42 60.53 60.64 60.76 60.87 60.98 61.10 61.21 61.32 62.12
23 24
16 17 18 19 20 21 22 23 24 25 26 27
0.003 0.003 0.003 0.003
0.03 0.03 0.03 0.03 0.03 0.03
0.02 0.02 0.02 0.02 0.02
0.29 0.29 0.29 0.29 0.29
0.21 0.21 0.21 0.21 0.21 0.21
0.32 0.32 0.32 0.32 0.32 0.32 0.32 0.32 0.32 0.32 0.32 0.32
0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26
0.32 0.32
0.26 0.26
0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21
27 28
13 14 15 16 17 18 19 20 21 22 23 24
0.01 0.01 0.01 0.01 0.01
0.02 0.02
0.223 0.223 0.641 0.434 0.434 0.434 0.434 0.423 0.423 0.378 0.378 0.378
92.84 93.06 93.71 94.14 94.57 95.01 95.44 95.87 96.29 96.67 97.04 97.42
28
25 26 27 28
0.31 0.31 0.31 0.31
0
M1 = 2
BULAN KE-2 BULAN KE-3
6 7 8 9 10 11 12 13
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5
0.001 0.026
0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450 0.450
0.101 0.101 0.101 0.101 0.101 0.101 0.101 0.101 0.101 0.101
0.081 0.081 0.081 0.081 0.081 0.081 0.081 0.081 0.081 0.081 0.081 0.081 0.081 0.081 0.081
0.208 0.194 0.194 0.194 0.194 0.083 0.155 0.155 0.155 0.143 0.143 0.143 0.262 0.299 0.246 0.246 0.246 0.320 0.792 0.775 0.775 0.896 0.896 0.969 0.990 0.952 0.952 0.952 0.778 0.778 0.980 0.980 0.980 0.896 0.859 0.782 0.782 0.782 0.383 0.303 0.115 0.052 0.052 0.526 0.526 0.526 0.526 0.526 0.759 0.932
8.974 9.169 9.363 9.557 9.751 9.834 9.989 10.144 10.298 10.442 10.585 10.728 10.991 11.289 11.536 11.782 12.028 12.348 13.140 13.915 14.690 15.586 16.482 17.451 18.442 19.394 20.346 21.298 22.076 22.854 23.834 24.813 25.793 26.689 27.547 28.330 29.112 29.894 30.278 30.581 30.696 30.747 30.799 31.325 31.852 32.378 32.904 33.431 34.189 35.122
BULAN KE-4 BULAN KE-5
14 15 16 17 18 19 20
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099
0.103 0.103 0.103 0.103 0.103 0.103 0.103 0.103 0.103 0.103
0.074 0.074 0.074 0.074 0.074 0.074 0.074
0.026 0.026 0.026 0.026 0.026 0.026 0.026
0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109
0.049 0.049 0.049 0.049 0.049
0.131 0.131 0.131 0.131 0.131 0.131 0.131 0.131
0.042 0.042 0.042 0.042 0.042
0.091 0.091 0.091 0.091 0.091
0.009 0.009 0.009
0.137 0.137 0.137 0.137 0.137 0.137 0.137 0.137
0.061
0.638 0.775 0.775 0.524 0.524 0.451 0.343 0.247 0.308 0.308 0.298 0.280 0.280 0.280 0.216 0.216 0.178 0.178 0.178 0.178 0.178 0.178 0.178 0.248 0.248 0.248 0.248 1.001 1.001 1.001 0.956 0.956 0.956 0.753 0.928 0.977 0.977 0.977 0.977 0.986 0.986 0.388 0.227 0.227 0.171 0.171 0.171 0.171 0.171 0.198
35.760 36.535 37.310 37.834 38.358 38.809 39.152 39.399 39.708 40.016 40.315 40.595 40.876 41.156 41.372 41.588 41.766 41.944 42.122 42.300 42.478 42.656 42.834 43.083 43.331 43.579 43.827 44.828 45.829 46.831 47.787 48.742 49.698 50.451 51.379 52.357 53.334 54.311 55.288 56.275 57.261 57.649 57.876 58.103 58.275 58.446 58.617 58.788 58.959 59.157
BULAN KE-6 BULAN KE-7
21 22 23 24 25 26 27
28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
0.137 0.137 0.137 0.137 0.137 0.137 0.137
0.061 0.061 0.061 0.061 0.061 0.061 0.061
0.113 0.113 0.113 0.113 0.113 0.113 0.113 0.113
0.308 0.308 0.308 0.308 0.308 0.308 0.308 0.308 0.308 0.308 0.308 0.308 0.308 0.308 0.308
0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291
0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207
0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110
0.319 0.319 0.319 0.319 0.319 0.319 0.319 0.319 0.319 0.319 0.319 0.319 0.319 0.319 0.319
0.260 0.260 0.260 0.260 0.260 0.260 0.260 0.260 0.260 0.260 0.260 0.260 0.260 0.260 0.260
0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207 0.207
0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291
0.086 0.086 0.086 0.086 0.086 0.086 0.086 0.086 0.086 0.086 0.086 0.086 0.086 0.086 0.086
0.107 0.107 0.107 0.107 0.107 0.107 0.107 0.107 0.107 0.107
0.198 0.307 0.307 0.307 0.307 0.307 0.307 0.222 0.222 0.222 0.222 0.113 0.113 0.113 0.113 0.802 0.802 0.802 0.802 0.802 0.799 0.799 1.595 1.886 1.886 1.779 1.779 1.762 1.762 2.066 1.402 1.402 1.402 1.402 1.402 1.402 1.429 0.623 0.234 0.234 0.234 0.222 0.222 0.641 0.434 0.434 0.434 0.434 0.423 0.423
59.355 59.662 59.969 60.276 60.584 60.891 61.198 61.420 61.643 61.865 62.087 62.200 62.313 62.425 62.538 63.340 64.142 64.944 65.746 66.548 67.347 68.146 69.741 71.627 73.513 75.292 77.072 78.833 80.595 82.661 84.063 85.465 86.866 88.268 89.670 91.071 92.501 93.124 93.358 93.593 93.827 94.050 94.272 94.913 95.347 95.782 96.216 96.650 97.073 97.495
28
22 23 24 25 26 27 28
0.312 0.312 0.312 0.312 0.312 0.312 0.312
8
Jasa upah titik 0.01 Rp 65,000.00 Rp 650.00
8
Pipa conduit m¹ 1 Rp 4,000.00 Rp 4,000.00
Rp 20,050.00
11% Overhead + profit Rp 2,205.50
STOP KONTAK pcs 1 Rp 25,700.00 Rp 25,700.00
Jasa upah titik 1 Rp 65,000.00 Rp 65,000.00
Bobokan m¹ 3 Rp -
9 NYM 3 x 2,5 mm m¹ 15 Rp -
Embedos pcs 1 Rp 7,513.00 Rp 7,513.00
Rp 98,213.00
11% Overhead + profit Rp 10,803.43
STOP KONTAK AC pcs 1 Rp 55,000.00 Rp 55,000.00
Jasa upah titik 1 Rp 65,000.00 Rp 65,000.00
Bobokan m¹ 3 Rp -
10 NYM 3 x 2,5 mm m¹ 7 Rp - Rp -
Box pcs 1 Rp 7,513.00 Rp 7,513.00
Rp 127,513.00
11% Overhead + profit Rp 14,026.43
STOP KONTAK PORTEBEL isi 2 pcs 1 Rp 45,000.00 Rp 45,000.00
Jasa upah titik 1 Rp 65,000.00 Rp 65,000.00
Bobokan m¹ 3 Rp -
11
NYM 3x2,5 mm m¹ 15 Rp -
Rp 110,000.00
10% Overhead + profit Rp 11,000.00
MODUL DATA pcs 2 Rp 85,000.00 Rp 170,000.00
FRAME GANDA pcs 1 Rp 7,500.00 Rp 7,500.00
COVER pcs 1 Rp 7,500.00 Rp 7,500.00
Jasa upah titik 1 Rp 65,000.00 Rp 65,000.00
12 Bobokan m¹ 3 Rp - Rp -
Kabel m¹ 15 Rp 11,000.00 Rp 165,000.00
Box pcs 1 Rp 7,513.00 Rp 7,513.00
Rp 422,513.00
10% Overhead + profit Rp 42,251.30
SAKLAR SERI pcs 2 Rp 45,000.00 Rp 90,000.00
FRAME GANDA pcs 1 Rp 7,500.00 Rp 7,500.00
COVER pcs 1 Rp 7,500.00 Rp 7,500.00
Jasa upah titik 0.1 Rp 65,000.00 Rp 6,500.00
13 Bobokan m¹ 3 Rp - Rp -
NYM 3 x 2,5 mm m¹ 0 Rp - Rp -
Box pcs 1 Rp 7,513.00 Rp 7,513.00
Rp 119,013.00
11% Overhead + profit Rp 13,091.43
SAKLAR TUNGGAL pcs 1 Rp 45,000.00 Rp 45,000.00
FRAME GANDA pcs 1 Rp 7,500.00 Rp 7,500.00
COVER pcs 1 Rp 7,500.00 Rp 7,500.00
14
Jasa upah titik 0.1 Rp 65,000.00 Rp 6,500.00
14 Bobokan m¹ 3 Rp - Rp -
NYM 3 x 2,5 mm m¹ 0 Rp - Rp -
Box pcs 1 Rp 7,513.00 Rp 7,513.00
Rp 74,013.00
11% Overhead + profit Rp 8,141.43
Saklar 2 arah seri pcs 2 Rp 45,000.00 Rp 90,000.00
FRAME GANDA pcs 1 Rp 7,500.00 Rp 7,500.00
COVER pcs 1 Rp 7,500.00 Rp 7,500.00
Jasa upah titik 0.1 Rp 65,000.00 Rp 6,500.00
15 Bobokan m¹ 3 Rp - Rp -
NYM 3 x 2,5 mm m¹ 30 Rp - Rp -
Box pcs 1 Rp 7,513.00 Rp 7,513.00
Rp 119,013.00
11% Overhead + profit Rp 13,091.43
Saklar 2 arah tunggal pcs 1 Rp 45,000.00 Rp 45,000.00
FRAME GANDA pcs 1 Rp 7,500.00 Rp 7,500.00
COVER pcs 1 Rp 7,500.00 Rp 7,500.00
Jasa upah titik 0.1 Rp 65,000.00 Rp 6,500.00
16 Bobokan m¹ 3 Rp - Rp -
NYM 3 x 2,5 mm m¹ 15 Rp - Rp -
Box pcs 1 Rp 7,513.00 Rp 7,513.00
Rp 74,013.00
11% Overhead + profit Rp 8,141.43
Downhligt NNP 74666 pcs 1 Rp 121,000.00 Rp 121,000.00
Jasa upah titik 1 Rp 65,000.00 Rp 65,000.00
17 NYM 3 x 2,5 mm m¹ 15 Rp -
Rp 186,000.00
11% Overhead + profit Rp 20,460.00
Downhligt NNP 74566 pcs 1 Rp 93,000.00 Rp 93,000.00
Jasa upah titik 1 Rp 65,000.00 Rp 65,000.00
18 NYM 3 x 2,5 mm m¹ 7 Rp -
Rp 158,000.00
11% Overhead + profit Rp 17,380.00
Downhligt NNP 72266 pcs 1 Rp 84,000.00 Rp 84,000.00
Jasa upah titik 1 Rp 65,000.00 Rp 65,000.00
19 NYM 3 x 2,5 mm m¹ 15 Rp -
Rp 149,000.00
11% Overhead + profit Rp 16,390.00
Downhligt NNP 5/3 watt pcs 1 Rp 55,000.00 Rp 55,000.00
Alat bantu ls 0.1 Rp 55,000.00 Rp 5,500.00
Jasa upah titik 1 Rp 65,000.00 Rp 65,000.00
20
NYM 3 x 2,5 mm m¹ 15 Rp -
Rp 125,500.00
11% Overhead + profit Rp 13,805.00
LAMPU BARET pcs 1 Rp 200,000.00 Rp 200,000.00
Jasa upah titik 1 Rp 65,000.00 Rp 65,000.00
21 NYM 3 x 2,5 mm m¹ 15 Rp - Rp -
Rp 265,000.00
11% Overhead + profit Rp 29,150.00
LAMPU EXIT pcs 1 Rp 65,000.00 Rp 65,000.00
Jasa upah titik 1 Rp 87,500.00 Rp 87,500.00
22 NYM 3 x 2,5 mm m¹ 15 Rp - Rp -
Rp 152,500.00
11% Overhead + profit Rp 16,775.00
PANEL MDP pcs 1 Rp 3,500,000.00 Rp 3,500,000.00
Alat bantu ls 10% Rp 350,000.00 Rp 350,000.00
MCCB 250 A 3P pcs 1 Rp 6,750,000.00 Rp 6,750,000.00
MCCB 100 A 3P pcs 1 Rp 4,333,000.00 Rp 4,333,000.00
MCCB 160 A 3P pcs 1 Rp 2,777,000.00 Rp 2,777,000.00
MCCB 60 A 3p pcs 1 Rp 2,101,000.00 Rp 2,101,000.00
MCB 2 A pcs 3 Rp 65,000.00 Rp 195,000.00
Jasa upah titik 1 Rp 500,000.00 Rp 500,000.00
CT 50/5A pcs 3 Rp 65,000.00 Rp 195,000.00
23
Ampere meter 50/5A pcs 3 Rp 85,000.00 Rp 255,000.00
volt-meter 0-500 volt pcs 1 Rp 85,000.00 Rp 85,000.00
volt selector swit pcs 1 Rp 65,000.00 Rp 65,000.00
indicator lamp pcs 1 Rp 10,000.00 Rp 10,000.00
accessories ls 1 Rp 200,000.00 Rp 200,000.00
rel 3 Fase m¹ 1 Rp 220,000.00 Rp 220,000.00
Bobokan unit 1 Rp -
Rp 21,536,000.00
11% Overhead + profit Rp 2,368,960.00
BOX PANEL LT.1 pcs 1 Rp 1,500,000.00 Rp 1,500,000.00
Alat bantu ls 10% Rp 150,000.00 Rp 150,000.00
MCB 2/4/6 A pcs 10 Rp 77,700.00 Rp 777,000.00
MCB 10/16 A pcs 24 Rp 61,050.00 Rp 1,465,200.00
MCB 2 A pcs 3 Rp 77,700.00 Rp 233,100.00
MCB 25 A 3P pcs 2 Rp 581,000.00 Rp 1,162,000.00
MCB 50 A 3P pcs 1 Rp 873,000.00 Rp 873,000.00
MCCB 100 A 3P pcs 1 Rp 2,896,500.00 Rp 2,896,500.00
Jasa upah titik 1 Rp 500,000.00 Rp 500,000.00
24 CT 50/5A pcs 3 Rp 65,000.00 Rp 195,000.00
Ampere meter 50/5A pcs 3 Rp 85,000.00 Rp 255,000.00
volt-meter 0-500 volt pcs 1 Rp 85,000.00 Rp 85,000.00
volt selector swit pcs 1 Rp 65,000.00 Rp 65,000.00
indicator lamp pcs 1 Rp 10,000.00 Rp 10,000.00
accessories ls 1 Rp 200,000.00 Rp 200,000.00
rel 3 Fase m¹ 1 Rp 220,000.00 Rp 220,000.00
Bobokan unit 1 Rp -
Rp 10,586,800.00
11% Overhead + profit Rp 1,164,548.00
BOX PANEL LT.2 pcs 1 Rp 1,500,000.00 Rp 1,500,000.00
Alat bantu ls 10% Rp 150,000.00 Rp 150,000.00
MCB 2/4/6 A pcs 10 Rp 77,700.00 Rp 777,000.00
MCB 10/16 A pcs 34 Rp 61,050.00 Rp 2,075,700.00
MCB 20/25 A pcs 2 Rp 95,000.00 Rp 190,000.00
MCB 2 A pcs 3 Rp 77,700.00 Rp 233,100.00
MCB 25 A 3P pcs 1 Rp 581,000.00 Rp 581,000.00
MCB 63 A 3P pcs 1 Rp 873,000.00 Rp 873,000.00
MCCB 160 A 3P pcs 1 Rp 2,896,500.00 Rp 2,896,500.00
Jasa upah titik 1 Rp 500,000.00 Rp 500,000.00
25
CT 50/5A pcs 3 Rp 65,000.00 Rp 195,000.00
Ampere meter 50/5A pcs 3 Rp 85,000.00 Rp 255,000.00
volt-meter 0-500 volt pcs 1 Rp 85,000.00 Rp 85,000.00
volt selector swit pcs 1 Rp 65,000.00 Rp 65,000.00
indicator lamp pcs 1 Rp 10,000.00 Rp 10,000.00
accessories ls 1 Rp 200,000.00 Rp 200,000.00
rel 3 Fase m¹ 1 Rp 220,000.00 Rp 220,000.00
Bobokan unit 1 Rp -
Rp 10,806,300.00
11% Overhead + profit Rp 1,188,693.00
BOX PANEL LT.3 pcs 1 Rp 1,500,000.00 Rp 1,500,000.00
Alat bantu ls 10% Rp 150,000.00 Rp 15,000.00
MCB 2/4/6 A pcs 11 Rp 77,700.00 Rp 854,700.00
MCB 10/16 A pcs 11 Rp 61,050.00 Rp 671,550.00
MCB 25 A 3 p pcs 2 Rp 581,000.00 Rp 1,162,000.00
MCCB 60 A 3p pcs 1 Rp 937,000.00 Rp 937,000.00
Jasa upah titik 1 Rp 500,000.00 Rp 500,000.00
CT 50/5A pcs 3 Rp 65,000.00 Rp 195,000.00
26 Ampere meter 50/5A pcs 3 Rp 85,000.00 Rp 255,000.00
volt-meter 0-500 volt pcs 1 Rp 85,000.00 Rp 85,000.00
volt selector swit pcs 1 Rp 65,000.00 Rp 65,000.00
indicator lamp pcs 1 Rp 10,000.00 Rp 10,000.00
accessories ls 1 Rp 200,000.00 Rp 200,000.00
rel 3 Fase m¹ 1 Rp 220,000.00 Rp 220,000.00
Bobokan unit 1 Rp - Rp -
Rp 6,670,250.00
11% Overhead + profit Rp 733,727.50
MCB 2/4/6 A pcs 1 Rp 70,000.00 Rp 70,000.00
Alat bantu ls 10% Rp -
Jasa upah titik 1 Rp -
27
NYM 3 x 2,5 mm m¹ 3 Rp -
Rp 70,000.00
11% Overhead + profit Rp 7,700.00
MCB 10/16 A pcs 1 Rp 55,000.00 Rp 55,000.00
Alat bantu ls 10% Rp -
Jasa upah titik 3 Rp -
28
NYM 3 x 2,5 mm m¹ 3 Rp -
Rp 55,000.00
11% Overhead + profit Rp 6,050.00
Exausfan mvf pcs 1 Rp 950,000.00 Rp 950,000.00
Alat bantu ls 10% Rp 95,000.00 Rp 9,500.00
Jasa upah titik 1 Rp 65,000.00 Rp 65,000.00
29
NYM 3 x 2,5 mm m¹ 1 #VALUE! #VALUE!
#VALUE!
10% Overhead + profit #VALUE!
TRAY 200x100x2400 pcs 1 Rp 230,000.00 Rp 230,000.00
Alat bantu ls 20% Rp 230,000.00 Rp 46,000.00
30 Jasa upah titik 0.3 Rp 65,000.00 Rp 19,500.00
Rp 295,500.00
11% Overhead + profit Rp 32,505.00
ELEKTRIKAL
#VALUE!
#VALUE!
84915
Rp 62,659.50 Rp 149,517.00
Rp 119,047.50
446109
Rp 419,635.50
Rp 26,473.50
Rp 30,469.50
Rp 22,255.50
Rp 109,016.43
Rp 141,539.43
Rp 121,000.00
Rp 464,764.30
Rp 132,104.43
Rp 82,154.43
Rp 132,104.43
Rp 82,154.43
Rp 206,460.00
Rp 175,380.00
Rp 165,390.00
Rp 139,305.00
Rp 294,150.00
Rp 169,275.00
Rp 23,904,960.00
Rp 11,751,348.00
Rp 11,994,993.00
Rp 7,403,977.50
Rp 77,700.00
Rp 61,050.00
#VALUE!
Rp 328,005.00
HARGA SATUAN PEKERJAAN LAIN-LAIN
D. Jumlah (A+B+C)
### E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
### E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
### E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
TAKSIR - 1
4. Pemasangan 1 m2 paving blok segienam t. 8 cm mutu K200
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 110,000.00
Tukang L.02 OH -
Kepala Tukang L.03 OH -
Mandor L.04 OH 0.018 165,000.00
JUMLAH TENAGA KERJA
B BAHAN
Paving blok segienam t. 8 cm bh 37.000 5,457.16
Pasir m3 0.100 265,702.50
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
### E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
### E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
### E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
TAKSIR - 2
7. Pemasangan 1 titik nyala stop kontak
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH
Tukang L.02 OH 0.1350 150,000.00
Kepala Tukang L.03 OH 0.0135 180,000.00
Mandor L.04 OH 0.0050 165,000.00
JUMLAH TENAGA KERJA
B BAHAN
NYM 3 x 2,5 mm2 m 15.000 18,200.00
Perlengkapan ( 35% harga conduit,klem,isolasi )
JUMLAH TENAGA BAHAN
C. PERALATAN
D. Jumlah (A+B+C)
### E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
8. 1 m2 labur aspal + labur pasir
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.006 110,000.00
Tukang Batu L.02 OH 150,000.00
Kepala Tukang L.03 OH 180,000.00
Mandor L.04 OH 0.00042 165,000.00
JUMLAH TENAGA KERJA
B BAHAN
Aspal bitumen kg 1.208 17,441.96
Pasir pasang m3 0.018 265,702.50
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
TAKSIR - 3
10. Pemasangan 100 m2 karung goni basah untuk curing beton
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.800 110,000.00
Tukang Batu L.02 OH 150,000.00
Kepala Tukang L.03 OH 180,000.00
Mandor L.04 OH 0.0800 165,000.00
JUMLAH TENAGA KERJA
B BAHAN
Karung goni lbr 102.000 9,700.00
Air liter 5000.000 66.60
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
.
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
TAKSIR - 4
13. Pemasangan 1 m2 geotekstil untuk timbunan
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 110,000.00
Tukang Batu L.02 OH 0.020 150,000.00
Kepala Tukang L.03 OH 180,000.00
Mandor L.04 OH 0.0100 165,000.00
JUMLAH TENAGA KERJA
B BAHAN
Geotekstil m2 1.05 24,885.00
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
14.a Pemasangan 1 m2 ACP +Cutting Laser + rangka besi siku mm, modul 100x100cm eksterior
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 110,000.00
Tukang Besi L.02 OH 0.275 150,000.00
Kepala Tukang L.03 OH 0.028 180,000.00
Mandor L.04 OH 0.083 165,000.00
JUMLAH TENAGA KERJA
B BAHAN
Rangka besi siku 40.40.4mm m' 11.200 18,055.00
Alimunium Composite m2 1.118 575,000.00
sealent m' 2.000 5,600.00
Assesoris (perkuatan, las dll) cm 56.000 3,026.01
JUMLAH TENAGA BAHAN
C. PERALATAN
Upah Cutingg m2 1.000 250,000.00
JUMLAH TENAGA ALAT
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
16. Lapisan Pondasi 1 m3 Agregat Kls. B Untuk Pek. Rutin
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A. TENAGA
Pekerja L.01 OH 0.028 110,000.00
Mandor L.04 OH 0.0019 165,000.00
JUMLAH TENAGA KERJA
B BAHAN
Agregat B m3 1.000 741,378.75
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
D. Jumlah (A+B+C)
### E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
A. TENAGA
Pekerja L.01 oh 0.5000 Rp 110,000.00
Tukang L.02 oh 0.5000 Rp 150,000.00
Kepala tukang L.03 oh 0.0500 Rp 180,000.00
Mandor L.04 oh 0.0250 Rp 165,000.00
B. Bahan:
Plafond Akustik 60 x 120 cm lbr 1.5152 Rp 102,000.00
Menti (Profil Alumunium "T") m 4.0000 Rp 9,166.67
Crossti (Profil Alumunium "T") m 1.2000 Rp 21,000.00
L Clip bh 4.0000 Rp 12,000.00
Wall angle m' 1.2000 Rp 22,000.00
Gantungan m 4.0000 Rp 3,750.00
Paku ramset+misiu kg 0.1100 Rp 17,500.00
C. PERALATAN
Scapolding
JUMLAH TENAGA ALAT
D. Jumlah (A+B+C)
E. Overhead & Profit 15% X D
F. Harga Satuan Pekerjaan (D+E)
Bahan:
Lantai vynil anti bacteri m² 1.1000 Rp 675,000.00
Semen kg 8.0000 Rp 1,450.00
Self leveling floor 3-10 mm zak 0.0720 Rp 270,000.00
Lem/adhesive kg 0.4500 Rp 51,580.00
Jumlah
Overhead & Profit 15% X D
Harga Satuan Pekerjaan
TAKSIR - 5
Jumlah Harga (Rp)
22,000.00
67,500.00
1,800.00 4 m 145 rb
8,250.00 6 m 225rb
99,550.00
33,480.00
35,488.80
34,776.00
6,270.00
2,400.00
4,836.00
117,250.80
-
-
216,800.80
32,520.12 15%
249,320.92
38,500.00
-
-
2,887.50
41,387.50
239,400.00
26,570.25
265,970.25
-
-
307,357.75
46,103.66
353,461.41
287,800.00
26,570.25
314,370.25
-
-
355,757.75
53,363.66
409,121.41
38,500.00
-
-
2,887.50
41,387.50
201,915.00
26,570.25
228,485.25
-
-
269,872.75
40,480.91
310,353.66
38,500.00
-
-
2,887.50
41,387.50
250,015.00
26,570.25
276,585.25
-
-
317,972.75
47,695.91
365,668.66
-
20,250.00
2,430.00
825.00
23,505.00
210,000.00
73,500.00
283,500.00
-
-
307,005.00
46,050.75
353,055.75
-
20,250.00
2,430.00
825.00
23,505.00
273,000.00
95,550.00
368,550.00
-
-
392,055.00
58,808.25
450,863.25
Jumlah Harga (Rp) 2400
641.67
-
-
68.75
710.42
21,075.70
4,760.50
25,836.20
-
-
26,546.62
3,981.99 15%
30,528.61
5,500.00
75,000.00
9,000.00
495.00
89,995.00
759,810.00
12,096.00
771,906.00
-
-
861,901.00
129,285.15 15%
991,186.15
989,400.00
333,000.00
1,322,400.00
-
-
1,423,600.00
213,540.00 15%
1,637,140.00
220,000.00
-
-
16,500.00
236,500.00
1,332,000.00
1,332,000.00
-
-
1,568,500.00
235,275.00 15%
1,803,775.00
880.00
-
-
132.00
1,012.00
5,843.25
5,843.25
-
-
6,855.25
1,028.29 15%
7,883.54
11,000.00
3,000.00
-
1,650.00
15,650.00
26,129.25
26,129.25
-
-
41,779.25
6,266.89 15%
48,046.14
181,500.00
41,250.00
5,040.00
13,695.00
241,485.00
1,267,322.57
190,098.39 0.15
1,457,420.96
0x100cm eksterior
Jumlah Harga (Rp)
181,500.00
41,250.00
5,040.00
13,695.00
241,485.00
250,000.00
250,000.00
1,517,322.57
227,598.39 0.15
1,744,920.96
2,784.57
167.36
2,951.93
949,625.42
949,625.42
-
163,248.39
5,828.90
4,601.27
-
-
173,678.55
1,126,255.90
168,938.38 15%
1,295,194.28
Jumlah Harga (Rp)
3,069.00
306.43
3,375.43
741,378.75
741,378.75
-
163,248.39
5,828.90
4,601.27
-
173,678.55
918,432.73
137,764.91 15%
1,056,197.64
27,500.00
18,750.00
2,340.00
2,145.00
50,735.00
247,685.36
14,500.00
11,956.61
-
274,141.97
-
-
324,876.97
48,731.55 15%
373,608.51
-
20,250.00
2,430.00
825.00
23,505.00
420,000.00
147,000.00
567,000.00
-
-
590,505.00
88,575.75
679,080.75
Rp 55,000.00 130000
Rp 75,000.00 150000
Rp 9,000.00 170000
Rp 4,125.00 180000
Rp 143,125.00
Rp 154,545.45 85000
Rp 36,666.67 19840
Rp 25,200.00 19840
Rp 48,000.00
Rp 26,400.00
Rp 15,000.00 3300
Rp 1,925.00 14500
Rp 307,737.12
-
-
Rp 450,862.12
Rp 67,629.32
Rp 518,491.44
Rp 49,500.00
Rp 67,500.00
Rp 20,700.00
Rp 2,970.00
Rp 140,670.00
Rp 742,500.00
Rp 11,600.00
Rp 19,440.00
Rp 23,211.00
Rp 961,091.00
Rp 144,163.65
Rp 1,105,254.65
Rp 27,500,000.00
Rp 3,000,000.00
Rp 5,000,000.00
Rp 5,000,000.00
Rp 7,000,000.00
Rp 10,000,000.00
Rp 8,000,000.00
Rp 65,500,000.00
Rp 9,825,000.00
Rp 75,325,000.00
Muara
2. PASIR
3. BATU KALI
4. BATU BATA
5. TANAH
6. LAIN-LAIN
2. ASBES
3. GENTENG KERAMIK
4. GENTENG METAL
6. POLYCARBONATE
7. ATAP ZINCALUME
8. ATAP BITUMEN
9. LAIN-LAIN
III BAHAN KAYU
1. MERAWAN, KULIM
2. MERANTI
4. RACUK
3. LAIN-LAIN
2. KERAMIK
WARNA/TEKSTUR
3. GRANITE TILE
4. BATU ALAM
5. LAIN-LAIN
V BAHAN CETAK
1. BUIS BETON
2. ROSTER
3. GLASS BLOK
4. PAGAR BETON
5. PAVING BLOK
6. KANSTEIN
7. BATACO BETON
8. JENDELA UPVC
2. BAJA
3. ALUMINIUM
4. BAJA RINGAN
5. PINTU BESI
6. PEGANGAN TANGGA
STAINLESS
7. LAIN-LAIN
VII. BAHAN PIPA
1. PIPA PVC
2. PIPA GALVANIS
3. LAIN-LAIN
VIII. BAHAN LANGIT-LANGIT
1. PLYWOOD
2. SOFT BOARD
3. HARD BOARD
4. PLAFOND PVC
5. LIST PLAFOND
6. LAIN-LAIN
2. BESI
3. TEMBOK
4. THINNER
5. LAIN-LAIN
X. BAHAN KACA
1. KACA POLOS
2. KACA RYBEN/HITAM
3. LAIN-LAIN
XI BAHAN INSTALASI LISTRIK
1. KABEL LISTRIK
2. SAKELAR
3. STOP KONTAK
4. LAMPU
5. LAIN-LAIN
XII. BAHAN PENGUNCI DAN PENGGANTUNG
1. KUNCI TANAM
2. ENGSEL/GRENDEL
3. LAIN-LAIN
2. JET SHOWER
3. KRAN TEMBOK
4. WASTAFEL
5. URINOIR
6. BATHUBE
7. PENAMPUNG AIR
8. LAIN-LAIN
2. LEM
XV. LAIN-LAIN
1 Amplas Biasa
Amplas Niken
2 Diamond wheel
3 Tali Ijuk
4 Air
5 Minyak Bekesting
6 Minyak Pelumas
7 Minyak Bensin
8 Minyak Tanah
9 Solar
10 Soda api
11 Sewa alat las
12 Sewa scafolding
13 Sewa molen
14 Karung goni
15 Plastik
16 Geotekstil
HARGA
JENIS BAHAN SATUAN
DASAR (Rp)
Semen PC kg 1,450.00
Floor hardener kg 7,500.00
Semen instan Zak 157,700.00
Aspal kg 17,441.96
Seng gelombang uk. 5' kpg 38,850.00
Seng gelombang uk. 7' kpg 54,390.00
Seng gelombang uk. 10' kpg 77,700.00
Seng polos m 39,165.00
Polycarbonate m2 90,800.00
Papan m3 3,150,000.00
Balok kayu m3 2,730,000.00
Papan m3 2,625,000.00
Balok kayu m3 2,100,000.00
Papan m3 1,890,000.00
Balok kayu m3 1,600,000.00
Papan racuk t.20 cm kpg 35,000.00
DING/LANTAI
20 x 25 kotak 88,830.00
buah 4,441.50
20 x 25 kotak 77,805.00
buah 3,890.25
30 x 30 kotak 57,225.00
buah 5,202.27
40 x 40 kotak 105,000.00
buah 17,500.00
40 x 40 kotak 55,545.00
buah 9,257.50
50x50 kotak 105,420.00
buah 26,355.00
20 x 25 kotak 88,830.00
bh 4,441.50
20 x 20 kotak 77,595.00
bh 3,103.80
20 x 20 kotak 66,780.00
bh 2,671.20
30 x 30 kotak 55,755.00
bh 5,068.64
30 x 30 kotak 52,710.00
bh 4,791.82
33,5x33,5 kotak 105,000.00
bh 13,125.00
40 x 40 kotak 105,420.00
bh 17,570.00
40 x 40 kotak 55,755.00
bh 9,292.50
50x50 kotak 105,420.00
bh 26,355.00
50x50 kotak 93,555.00
bh 23,388.75
30x60 ktk 173,460.00
bh 34,692.00
60 x 60 kotak 309,600.00
bh 77,400.00
60 x 60 (tekstur) kotak 533,000.00
bh 133,250.00
80 x 80 kotak 663,360.00
bh 331,680.00
80 x 80 (tekstur) kotak 838,000.00
bh 419,000.00
Granite Pola uk. 1,2 x 1,2 m ls 2,550,000.00
Step nosing 30 x 60 bh 92,600.00
Step nosing 20 x 60 bh 58,700.00
Tegel Difabel m2 229,531.50
bh 20,866.50
flaxiwall m2 210,000.00
Pegangan tangga stainless kombinasi acylic (3/4", 1" & 2") m' 317,000.00
bh 3,600,000.00
Pintu KM/WC Aluminium warna urat kayu - frame louver (incl.
kusen, lever handle stainless steel, engsel aluminium)
Pintu Aluminium warna urat kayu - 5 mm ice glass (incl. kusen, bh 4,300,000.00
lever handle stainless steel, engsel aluminium)
Menie kg 44,100.00
Cat penutup liter 60,690.00
Thinner kg 29,820.00
Thinner kg 16,065.00
N PENGGANTUNG
Kunci tanam stainless bh 279,000.00
Kunci tanam biasa bh 159,000.00
Kunci tanam kecil bh 65,000.00
Kunci bulat (KM/WC) bh 150,000.00
Handle pintu stainless steel bh 238,000.00
Cylinder kunci bh 175,000.00
Kunci Pintu Alumunium Kualitas Baik bh 27,615.00
Kunci Pintu Alumunium Kualitas Biasa bh 33,075.00
Kunci Pintu Besar Kualitas Baik bh 275,625.00
Kunci Pintu Besar Kualitas Biasa bh 137,865.00
Kunci Pintu Kecil Kualitas Baik bh 137,865.00
Kunci Pintu Kecil Kualitas Biasa bh 99,225.00
Urinoir bh 2,694,405.00
Pembatas Urinoir bh 552,000.00
lbr 11,025.00
bh 6,615.00
bh 130,000.00
kg 38,000.00
ltr 66.60
ltr 44,100.00
ltr 230,666.88
ltr 10,831.80
ltr 18,036.52
ltr 16,986.52
kg 27,615.00
jam 6,700.00
unit 45,000.00
unit/hari 600,000.00
lbr 9,700.00
m2 5,565.00
m2 24,885.00
OH 110,000.00
OH 150,000.00
OH 180,000.00
OH 185,000.00
jam 110,668.90
00 - 4500 ltr jam 327,347.63
jam 526,464.02
jam 433,012.93
jam 786,400.89
jam 600,000.00
jam 600,000.00
jam 650,000.00
Keterangan
BJ 1400 kg/m3
BJ 1400 kg/m3
BJ 1350 kg/m3
BJ 1350 kg/m3
lebar 105 cm
panjang 105 cm; satu pasang
setara Kanmuri; 1m 2 @ 14 bh
setara Kanmuri; 1m 2 @ 14 bh
setara Kanmuri; 1m @ 3,9 bh
setara Kanmuri; 1m @ 3,9 bh
1 m2 @ 17,5 bh
1 m @ 3,5 bh
uk.lebar 105 cm
uk.lebar 105 cm
uk. Lebar 105 cm
uk. 300x60
Kayu Klas II
Kayu Klas II
Kayu klas
uk 2/25
p. 6 m
Mutu A
Mutu B
Mutu B
Mutu A
Mutu B
Mutu A
Mutu A
Mutu A
Mutu B
Mutu A
Mutu B
Mutu B
Mutu A
Mutu B
Mutu A
setara Indecor
setara granito
setara granito
1 m2 @ 11,87 kpg
uk. 15x30
setara AM
interior ; uk. 1,22 m x 2,44 m
Doff; uk. 1,22 m x 2,44 m
Glossy; uk. 1,22 m x 2,44 m
Metalic; uk. 1,22 m x 2,44 m
setara Trisensa
setara Trisensa
uk. 10x20
uk. 25x25
setara KIG
uk. 50x240
uk. 40x240
uk. 16x17
1 m2 @ 37 bh; K 200
1 m2 @ 44 bh; K200
1 m2 @ 37 bh; K 200
1 m2 @ 44 bh; K200
1 m2 @ 37 bh; K 200
1 m2 @ 44 bh; K200
1 m2 @ 37 bh; K 200
1 m2 @ 44 bh; K200
1 batang @ 12 m
p. 10 mm
panjang 6 m
setara star
setara star
uk. 2,4 m x 3 m
1 rol @ 60m
Aluminium 0,75mm ; coating powder
60 micron; uk. 80cm x 200cm; setara
solidoor-starmas
Akuminium 0,75mm ; coating powder
60 micron; uk. 90cm x 215cm; setara
solidoor-starmas
Aluminium 0,75mm ; coating powder
60 micron; uk. 80cm x 200cm; setara
solidoor-starmas
Akuminium 0,75mm ; coating powder
60 micron; uk. 90cm x 215cm; setara
solidoor-starmas
1 btg @ 6m
1 btg @ 6m
1 btl @ 60 gram
530,099.29
926,561.79
uk. 1,2 x 2,4 m
Setara Kangbang
Setara Shunda
Setara Kangbang
1 batang @ 3,8 m
1 batang @ 3,8 m
1 batang @ 1,7 m
1 batang @ 1,7 m
1 batang @ 4 m
1 kotak @ 1000
1 btg @ 4 m
1 btg @ 4 m
setara prima
setara prima
setara prima
setara ace
setara ace
setara ace
NN
setara AM 152
Setara Propan Stone care
Setara Glotek
Setara Tennekote
setara Asahimas
setara Asahimas
setara Asahimas
setara Asahimas
setara Asahimas
setara Asahimas
setara Asahimas
list kuningan
u. 60x120
setara Asahimas
setara Clipsal
setara Clipsal
setara Broko
setara Broko
1 bks @ 50 pcs
setara panasonic
setara Dekkson
setara Hampton
setara Dekkson
setara Gradino, Solid
setara paloma
paloma
setara paloma
setara Paloma
setara Paloma
setara Hampton
setara Dolomite
setara paloma
setara San-Ei
setara Onda
setara Toto
setara Amstand
setara zehn
setara Amstand
setara san-ei
Setara Alco
Setara Ciator
Setara Teka
Setara Teka
setara Onda
NN
setara muriko
setara san-ei
setara san-ei
1 ktk @ 50 buah
p. 70 mm
setara Bosch
1 bulan
uk. 75 cm x 110 cm
1 roll @ 20m x 1,2m