PROYEK PHONSKA V

PAKET PEKERJAAN GUDANG BUFFER 1X25.000 TON


PEKERJAAN SIPIL & STRUKTUR
ID WBS Task Name Duration Start Year 2
09 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12
1 kan PEMBANGUNAN GUDANG BUFFER & CONVEYOR 450 days 01/10/22
2 1.1 PEKERJAAN PERSIAPAN 36 days 01/10/22
3 1.1.1 Mobilisasi Demobilisasi (Peralatan, Manusia dll) 7 days 01/10/22
4 1.1.2 Pekerjaan Engineering (Survering, Soil Investigation, Detail Design) 29 days 01/10/22
5 1.1.3 Temporary Facilities (Laydown area, dsb) 14 days 08/10/22
6 1.1.4 Direksi keet (Kantor & Toilet) 14 days 11/10/22
7 1.1.5 Perijinan (PBG & SLF) 7 days 01/10/22
8 1.1.6 Pembongkaran fasilitas eksisting terdampak proyek 21 days 16/10/22
9 1.2 PEKERJAAN GUDANG BUFFER 25.000 TON 280 days 30/10/22
10 1.2.1 PEKERJAAN BETON 130 days 30/10/22
11 1.2.1.1 PEKERJAAN PONDASI 40 days 30/10/22
12 1.2.1.2 PEKERJAAN LANTAI BETON 90 days 09/12/22
13 1.2.1.3 PEKERJAAN DINDING BETON 60 days 08/01/23
14 1.2.2 PEKERJAAN BETON AREA HOPPER (39.D-651-A & 39.D-651-B) 60 days 09/12/22
15 1.2.2.1 PEKERJAAN PONDASI & LANTAI BETON 60 days 09/12/22
16 1.2.3 PEKERJAAN STRUKTUR BAJA & PENUTUP (GUDANG & AREA HOPPER) 180 days 07/02/23
17 1.3 PEKERJAAN CONVEYOR 179 days 07/02/23
18 1.3.1 PEKERJAAN TRANSFER TOWER (39-TP-01) 74 days 07/02/23
19 1.3.1.1 PEKERJAAN PONDASI 30 days 07/02/23
20 1.3.1.2 PEKERJAAN STRUKTUR BAJA & PENUTUP 60 days 21/02/23
21 1.3.2 PEKERJAAN TRANSFER TOWER (39-TP-02) 67 days 23/02/23
22 1.3.2.1 PEKERJAAN PONDASI 30 days 23/02/23
23 1.3.2.2 PEKERJAAN STRUKTUR BAJA & PENUTUP 60 days 02/03/23
24 1.3.3 PEKERJAAN TRANSFER TOWER (39-TP-03) 67 days 11/03/23
25 1.3.3.1 PEKERJAAN PONDASI 30 days 11/03/23
26 1.3.3.2 PEKERJAAN STRUKTUR BAJA & PENUTUP 60 days 18/03/23
27 1.3.4 PEKERJAAN MODIFIKASI TRANSFER TOWER EKSISTING (TP.2-2(M)) 67 days 27/03/23
28 1.3.4.1 PEKERJAAN PONDASI 30 days 27/03/23
29 1.3.4.2 PEKERJAAN STRUKTUR BAJA & PENUTUP 60 days 03/04/23
30 1.3.5 PEKERJAAN SUPPORT CONVEYOR (TIPE TERBUKA) 39-M-601 45 days 26/04/23
31 1.3.5.1 PEKERJAAN STRUKTUR BAJA 45 days 26/04/23
32 1.3.6 PEKERJAAN SUPPORT CONVEYOR (TIPE TERBUKA) 39-M-653 45 days 03/05/23
33 1.3.6.1 PEKERJAAN STRUKTUR BAJA 45 days 03/05/23
34 1.3.7 PEKERJAAN SUPPORT CONVEYOR (TIPE TERBUKA) 39-M-602 52 days 10/05/23
35 1.3.7.1 PEKERJAAN PONDASI 21 days 10/05/23
36 1.3.7.2 PEKERJAAN STRUKTUR BAJA 45 days 17/05/23
37 1.3.8 PEKERJAAN SUPPORT CONVEYOR (TIPE TERBUKA) 39-M-652 45 days 17/05/23
38 1.3.8.1 PEKERJAAN STRUKTUR BAJA 45 days 17/05/23
39 1.3.9 PEKERJAAN SUPPORT CONVEYOR (TIPE TERBUKA) 39-M-651 52 days 31/05/23
40 1.3.9.1 PEKERJAAN PONDASI 21 days 31/05/23
41 1.3.9.2 PEKERJAAN STRUKTUR BAJA 45 days 07/06/23
42 1.3.10 PEKERJAAN MODIFIKASI CONVEYOR (03-M-7101-3 & 29-M-7003) (M) 45 days 21/06/23
43 1.3.10.1 PEKERJAAN STRUKTUR BAJA & PENUTUP 45 days 21/06/23
44 1.4 PEKERJAAN JALAN & DRAINASE 127 days 06/08/23
45 1.4.1 PEKERJAAN JALAN BETON (L=6m, T=20cm) 120 days 06/08/23
46 1.4.2 PEKERJAAN SALURAN AIR DRAINASE 90 days 12/09/23
47 1.5 PEKERJAAN KANTOR & UTILITAS 120 days 06/08/23
48 1.5.1 PEKERJAAN SUBSTATION (12m x 8m x 2 lantai) 120 days 06/08/23
49 1.5.2 PEKERJAAN BARAK OPERATOR & KANTOR 90 days 05/09/23
50 1.6 PEKERJAAN PEMBERSIHAN 14 days 11/12/23
51 1.6.1 Pekerjaan Pembersihan kembali area Kerja 14 days 11/12/23

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Project1
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: 02/09/22
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress

Page 1