Analisa Pengukuran
Analisa Pengukuran
2 Upah
U.14 Juru Ukur org-hari 2.00 100,000.00 200,000.00
U.13 Pekerja org-hari 4.00 100,000.00 400,000.00
Upah 600,000.00
3 Alat
A.8 Waterpass Hari 2.00 2,845,303.75 5,690,607.50
A.20 Theodilite Hari 1.00 3,989,794.02 3,989,794.02
A.21 Alat Survey (GPS & Echosounder) Hari 1.00 24,836,840.00 24,836,840.00
A.41 Alat Bantu Pengukuran ls 1.00 1,114.18 1,114.18
Upah 34,518,355.70
Jumlah 35,118,355.70