PEMBANGUNAN RUMAH
IBU ENDANG
SUMUT
A. PEKERJAAN PERSIAPAN
TOTAL A Rp 6.500.000,00
B. LANTAI 1
II PEKERJAAN BETON
1 Footplat, besi d8-100
Pembesian 41,79 kg Rp 13.720 Rp 573.372,52
Beton 6,00 m³ Rp 988.470 Rp 5.930.820,00
Total Harga Footplat Rp 6.504.192,52
2 Sloof S1 15x30
Pembesian 1163,37 kg Rp 13.720 Rp 15.961.394,55
Bekisting 78,81 m² Rp 149.970 Rp 11.819.135,70
Beton 5,91 m³ Rp 988.470 Rp 5.842.599,05
Total Harga Sloof Rp 33.623.129,31
3 Kolom Kp 15x15 cm
Pembesian 324,31 kg Rp 13.720 Rp 4.449.529,08
Bekisting 34,65 m² Rp 181.130 Rp 6.276.154,50
Beton 1,30 m³ Rp 988.470 Rp 1.284.393,21
Total Harga Kolom Rp 12.010.076,79
4 Kolom Kp 15x15 cm (pagar)
Pembesian 13,53 kg Rp 13.720 Rp 185.584,40
Bekisting 14,40 m² Rp 181.130 Rp 2.608.272,00
Beton 0,54 m³ Rp 988.470 Rp 533.773,80
Total Harga Kolom Rp 3.327.630,20
5 Kolom K1 25x25 cm
Pembesian 35,89 kg Rp 13.720 Rp 492.361,68
Bekisting 37,80 m² Rp 181.130 Rp 6.846.714,00
Beton 2,84 m³ Rp 988.470 Rp 2.802.312,45
Total Harga Kolom Rp 10.141.388,13
6 Kolom K1 25x25 cm
Pembesian 35,89 kg Rp 13.720 Rp 492.361,68
Bekisting 31,50 m² Rp 181.130 Rp 5.705.595,00
Beton 1,97 m³ Rp 988.470 Rp 1.946.050,31
Total Harga Kolom Rp 8.144.006,99
7 Kolom K2 15x30 cm
Pembesian 107,52 kg Rp 13.720 Rp 1.475.188,67
Bekisting 103,95 m² Rp 181.130 Rp 18.828.463,50
Beton 5,20 m³ Rp 988.470 Rp 5.137.572,83
Total Harga Kolom Rp 25.441.224,99
8 Balok B1 20x40 cm
Pembesian 20,01 kg Rp 13.720 Rp 274.493,30
Bekisting 13,20 m² Rp 184.130 Rp 2.430.516,00
Beton 1,32 m³ Rp 988.470 Rp 1.304.780,40
Total Harga Balok Rp 4.009.789,70
9 Balok B2 15x30 cm
Pembesian 64,27 kg Rp 13.720 Rp 881.802,78
Bekisting 34,02 m² Rp 184.130 Rp 6.264.102,60
Beton 2,55 m³ Rp 988.470 Rp 2.522.081,21
Total Harga Balok Rp 9.667.986,59
10 Balok B2/RB 15x25 cm
Pembesian 51,25 kg Rp 13.720 Rp 703.185,49
Bekisting 40,18 m² Rp 184.130 Rp 7.397.422,75
Beton 3,01 m³ Rp 988.470 Rp 2.978.383,67
Total Harga Balok Rp 11.078.991,91
11 Balok Latei 15x15 cm
Pembesian 57,28 kg Rp 13.720 Rp 785.816,66
Bekisting 29,10 m² Rp 184.130 Rp 5.358.183,00
Beton 2,18 m³ Rp 988.470 Rp 2.157.335,78
Total Harga Balok Rp 8.301.335,43
12 Plat Lantai Dag Cor t 12cm
Pembesian 12,45 kg Rp 13.720 Rp 170.819,49
Bekisting 49,25 m² Rp 374.270 Rp 18.432.797,50
Beton 5,91 m³ Rp 988.470 Rp 5.841.857,70
Total Harga Plat Rp 24.445.474,69
Subtotal Rp 156.695.227,26
IV PEKERJAAN LANTAI
1 Pas. Keramik Tile 30x30 Ex. Asia Tile Kamar Mandi 8,25 m² Rp 169.120 Rp 1.395.240,00
2 Pas. Keramik Granite Tile 60x60 96,75 m² Rp 212.390 Rp 20.548.732,50
Subtotal Rp 21.943.972,50
V PEKERJAAN LANGIT-LANGIT
1 Plafond Gypsum Board 9mm Finish. Cat ex Catylac + Rangka Hollow 117,90 m² Rp 166.710 19655109
Subtotal Rp 19.655.109,00
b SANITASI
1 Instalasi Air Bersih pipa 1/2" Ex. Rucika Aw 60,00 m' Rp 21.490 Rp 1.289.400,00
2 Instalasi Air Kotor pipa 3" Ex. Rucika Aw 55,00 m' Rp 60.800 Rp 3.344.000,00
3 Instalasi Mainline Kotoran Padat pipa 4" Rucika Aw 40,00 m' Rp 90.100 Rp 3.604.000,00
4 Saluran Buangan Air Kotor Buis beton 30cm 2,00 bh Rp 568.528 Rp 1.137.056,00
5 Kran Air Ex. Onda / Setara 5,00 bh Rp 35.000 Rp 175.000,00
6 Wastafel/Bak Cuci 1,00 bh Rp 709.150 Rp 709.150,00
c SEPTICTANK
1 Galian tanah 14,00 m³ Rp 70.000 Rp 980.000,00
2 Pas. Dinding Bata 32,00 m² Rp 119.950 Rp 3.838.400,00
3 Pek. Plester & Acian 32,00 m² Rp 77.110 Rp 2.467.520,00
4 Pas. Buis Beton D100 4,00 m' Rp 285.000 Rp 1.140.000,00
5 Pek. Rabat Beton 2,80 m³ Rp 988.470 Rp 2.767.716,00
6 Pek. Beton Penutup 4,60 m³ Rp 684.320 Rp 3.147.872,00
7 Urugan Sirtu 3,00 m³ Rp 197.800 Rp 593.400,00
8 Ijuk 2,40 kg Rp 40.000 Rp 96.000,00
Subtotal Rp 33.884.366,50
C. LANTAI 2
I PEKERJAAN BETON
1 Kolom Kp 15x15 cm
Pembesian 9,45 kg Rp 13.720 Rp 129.596,92
Bekisting 10,08 m² Rp 181.130 Rp 1.825.790,40
Beton 0,38 m³ Rp 988.470 Rp 373.641,66
Total Harga Kolom Rp 2.329.028,98
2 Kolom K2 15x30 cm
Pembesian 22,48 kg Rp 13.720 Rp 308.371,54
Bekisting 22,68 m² Rp 181.130 Rp 4.108.028,40
Beton 1,13 m³ Rp 988.470 Rp 1.120.924,98
Total Harga Kolom Rp 5.537.324,92
3 Balok RB 15x25 cm
Pembesian 15,63 kg Rp 13.720 Rp 214.412,50
Bekisting 12,25 m² Rp 184.130 Rp 2.255.592,50
Beton 0,92 m³ Rp 988.470 Rp 908.156,81
Total Harga Balok Rp 3.378.161,81
4 Balok Latei 15x15 cm
Pembesian 14,47 kg Rp 13.720 Rp 198.479,47
Bekisting 7,35 m² Rp 184.130 Rp 1.353.355,50
Beton 0,55 m³ Rp 988.470 Rp 544.894,09
Total Harga Balok Rp 2.096.729,05
5 Plat Lantai Dag Cor t 12cm
Pembesian 2,28 kg Rp 13.720 Rp 31.215,74
Bekisting 9,00 m² Rp 374.270 Rp 3.368.430,00
Beton 1,08 m³ Rp 988.470 Rp 1.067.547,60
Total Harga Plat Rp 4.467.193,34
Subtotal Rp 17.808.438,12
IV PEKERJAAN LANGIT-LANGIT
1 Plafond Gypsum Board 9mm Finish. Cat ex Catylac + Rangka Hollow 9,00 m² Rp 166.710 1500390
Subtotal Rp 1.500.390,00
b SANITASI
1 Instalasi Air Bersih pipa 1/2" Ex. Rucika Aw 12,00 m' Rp 21.490 Rp 257.880,00
2 Instalasi Air Kotor pipa 3" Ex. Rucika Aw 12,00 m' Rp 60.800 Rp 729.600,00
3 Kran Air Ex. Onda / Setara 1,00 bh Rp 35.000 Rp 35.000,00
Subtotal Rp 1.070.380,00
..................................
VOLUME PEKERJAAN
A. PEKERJAAN PERSIAPAN
TOTAL A
B. PEKERJAAN LANTAI 1
2 Galian Pondasi
V2 = L. muka x p. pondasi
= 1,1 m2 x 131,4 m'
= 144,485 m3
Vtotal = 144,485 m3 144,49 m³
3 Urugan Kembali
V = 1
x V. galian total
3
V = 1
x 144,485
3
V = 48,1617 m3 48,16 m³
Subtotal
II PEKERJAAN BETON
1 Footplat, besi d8-100
Pembesian
p besi : 2,3 m'
W Ø 8/m : 4,74 / 12 = 0,395 kg
d8 - 100 : 23 bh
Berat besi = p x W x 23
= 2,30 x 0,40 x 23
= 20,8955 kg/m3
Total berat = 20,8955 x 20 bh (jmlh footplat)
= 417,91 kg/m3
Berat per 10 kg
= 41,791 10kg/m3 41,79 kg
Volume Beton
V = 0,3 x 1 x 1 = 0,3 m3
V total = 0,3 x 20 = 6 m3 6,00 m³
2 Sloof S1 15x30
Pembesian
p tul. pokok : 131,35 m' x 6 bh = 788,1 m'
p tul. begel : 0,66 m'
W d13/m : 12,5 / 12 = 1,042 kg
W Ø 8/m : 4,74 / 12 = 0,395 kg
Ø8 - 100 : 1313,5 bh
Berat besi tul pokok
= p x W
= 788 x 1,04
= 820,94 kg/m3
Berat besi tul sengkang
= p x W x 1313,5
= 0,66 x 0,40 x 1313,5
= 342,43 kg/m3 gg4
Total Berat
= 1163,37 kg/m3
Berat per 10 kg
= 116,337 10kg/m3 116,34 kg
Volume Beton
V = 0,15 x 0,3 x 131,35 = 5,91075 m3 5,91 m³
Luas Bekisting
L = 2 x 0,3 x 131,35
= 78,81 m2 78,81 m²
3 Kolom Kp 15x15 cm
Pembesian
p tul. pokok : 5,25 m' x 4 bh = 21 m'
p tul. begel : 0,36 m'
W d13/m : 12,5 / 12 = 1,042 kg
W Ø 8/m : 4,74 / 12 = 0,395 kg
Ø8 - 100 : 53,5 bh
Berat besi tul pokok
= p x W
= 21,0 x 1,04
= 21,88 kg/m3
Berat besi tul sengkang
= p x W x 53,5
= 0,36 x 0,40 x 53,5
= 7,61 kg/m3
Total Berat = 29,5 x 11 bh (jmlh kolom )
= 324,31 kg/m3
Berat per 10 kg
= 32,431 10kg/m3 32,43 kg
Volume Beton
V = 0,15 x 0,15 x 5,25 = 0,11813 m3
V total = 0,11813 x 11 = 1,29938 m3 1,30 m³
Luas Bekisting
L = 0,6 x 5,25 x 11
= 34,65 m2 34,65 m²
5 Kolom K1 25x25 cm
Pembesian
p tul. pokok : 5,25 m' x 8 bh = 42 m'
p tul. begel : 0,76 m'
W d13/m : 12,5 / 12 = 1,042 kg
W Ø 8/m : 4,74 / 12 = 0,395 kg
Ø8 - 100 : 53,5 bh
Berat besi tul pokok
= p x W
= 42,0 x 1,04
= 43,75 kg/m3
Berat besi tul sengkang
= p x W x 53,5
= 0,76 x 0,40 x 53,5
= 16,06 kg/m3
Total Berat = 59,8 x 6 bh (jmlh kolom )
= 358,86 kg/m3
Berat per 10 kg
= 35,886 10kg/m3 35,89 kg
Volume Beton
V = 0,3 x 0,3 x 5,25 = 0,4725 m3
V total = 0,4725 x 6 = 2,835 m3 2,84 m³
Luas Bekisting
L = 1,2 x 5,25 x 6
= 37,8 m2 37,80 m²
6 Kolom K1 25x25 cm
Pembesian
p tul. pokok : 5,25 m' x 8 bh = 42 m'
p tul. begel : 0,76 m'
W d13/m : 12,5 / 12 = 1,042 kg
W Ø 8/m : 4,74 / 12 = 0,395 kg
Ø8 - 100 : 53,5 bh
Berat besi tul pokok
= p x W
= 42,0 x 1,04
= 43,75 kg/m3
Berat besi tul sengkang
= p x W x 53,5
= 0,76 x 0,40 x 53,5
= 16,06 kg/m3
Total Berat = 59,8 x 6 bh (jmlh kolom )
= 358,86 kg/m3
Berat per 10 kg
= 35,886 10kg/m3 35,89 kg
Volume Beton
V = 0,25 x 0,25 x 5,25 = 0,32813 m3
V total = 0,32813 x 6 = 1,96875 m3 1,97 m³
Luas Bekisting
L = 1 x 5,25 x 6
= 31,5 m2 31,50 m²
7 Kolom K2 15x30 cm
Pembesian
p tul. pokok : 5,25 m' x 6 bh = 31,5 m'
p tul. begel : 0,76 m'
W d13/m : 12,5 / 12 = 1,042 kg
W Ø 8/m : 4,74 / 12 = 0,395 kg
Ø8 - 100 : 53,5 bh
Berat besi tul pokok
= p x W
= 31,5 x 1,04
= 32,81 kg/m3
Berat besi tul sengkang
= p x W x 53,5
= 0,76 x 0,40 x 53,5
= 16,06 kg/m3
Total Berat = 48,9 x 22 bh (jmlh kolom )
= 1075,21 kg/m3
Berat per 10 kg
= 107,521 10kg/m3 107,52 kg
Volume Beton
V = 0,15 x 0,3 x 5,25 = 0,23625 m3
V total = 0,23625 x 22 = 5,1975 m3 5,20 m³
Luas Bekisting
L = 0,9 x 5,25 x 22
= 103,95 m2 103,95 m²
8 Balok B1 20x40 cm
Pembesian
p tul. pokok : 16,50 m' x 8 bh = 132 m'
p tul. begel : 0,96 m'
W d13/m : 12,5 / 12 = 1,042 kg
W Ø 8/m : 4,74 / 12 = 0,395 kg
Ø8 - 100 : 165 bh
Berat besi tul pokok
= p x W
= 132 x 1,04
= 137,50 kg/m3
Berat besi tul sengkang
= p x W x 165
= 0,96 x 0,40 x 165
= 62,57 kg/m3
Total Berat
= 200,07 kg/m3
Berat per 10 kg
= 20,007 10kg/m3 20,01 kg
Volume Beton
V = 0,2 x 0,4 x 16,5 = 1,32 m3 1,32 m³
Luas Bekisting
L = 2 x 0,4 x 16,5
= 13,2 m2 13,20 m²
9 Balok B2 15x30 cm
Pembesian
p tul. pokok : 56,70 m' x 8 bh = 453,6 m'
p tul. begel : 0,76 m'
W d13/m : 12,5 / 12 = 1,042 kg
W Ø 8/m : 4,74 / 12 = 0,395 kg
Ø8 - 100 : 567 bh
Berat besi tul pokok
= p x W
= 454 x 1,04
= 472,50 kg/m3
Berat besi tul sengkang
= p x W x 567
= 0,76 x 0,40 x 567
= 170,21 kg/m3
Total Berat
= 642,71 kg/m3
Berat per 10 kg
= 64,271 10kg/m3 64,27 kg
Volume Beton
V = 0,15 x 0,3 x 56,7 = 2,5515 m3 2,55 m³
Luas Bekisting
L = 2 x 0,3 x 56,7
= 34,02 m2 34,02 m²
Subtotal
IV PEKERJAAN LANTAI
1 Pas. Keramik Tile 30x30 Ex. Asia Tile Kamar Mandi
L = 8,25 m2 8,25 m²
2 Pas. Keramik Granite Tile 60x60
L = 96,75 m2 96,75 m²
Subtotal
V PEKERJAAN LANGIT-LANGIT
1 Plafond Gypsum Board 9mm Finish. Cat ex Catylac + Rangka Hollow
L = 117,9 m2 117,90 m²
Subtotal
b SANITASI
1 Instalasi Air Bersih pipa 1/2" Ex. Rucika Aw 60,00 m'
2 Instalasi Air Kotor pipa 3" Ex. Rucika Aw 55,00 m'
3 Instalasi Mainline Kotoran Padat pipa 4" Rucika Aw 40,00 m'
4 Saluran Buangan Air Kotor Buis beton 30cm 2,00 bh
5 Kran Air Ex. Onda / Setara 5,00 bh
6 Wastafel/Bak Cuci 1,00 bh
c SEPTICTANK
1 Galian tanah 14,00 m³
2 Pas. Dinding Bata 32,00 m²
3 Pek. Plester & Acian 32,00 m²
4 Pas. Buis Beton D100 4,00 m'
5 Pek. Rabat Beton 2,80 m³
6 Pek. Beton Penutup 4,60 m³
7 Urugan Sirtu 3,00 m³
8 Ijuk 2,40 kg
Subtotal
TOTAL B
C. PEKERJAAN LANTAI 2
I PEKERJAAN BETON
1 Kolom Kp 15x15 cm
Pembesian
p tul. pokok : 4,2 m' x 4 bh = 16,8 m'
p tul. begel : 0,36 m'
W d13/m : 12,5 / 12 = 1,042 kg
W Ø 8/m : 4,74 / 12 = 0,395 kg
Ø8 - 100 : 43 bh
Berat besi tul pokok
= p x W
= 16,8 x 1,04
= 17,50 kg/m3
Berat besi tul sengkang
= p x W x 43
= 0,36 x 0,40 x 43
= 6,11 kg/m3
Total Berat = 23,6 x 4 bh (jmlh kolom )
= 94,46 kg/m3
Berat per 10 kg
= 9,446 10kg/m3 9,45 kg
Volume Beton
V = 0,15 x 0,15 x 4,2 = 0,0945 m3
V total = 0,0945 x 4 = 0,378 m3 0,38 m³
Luas Bekisting
L = 0,6 x 4,2 x 4
= 10,08 m2 10,08 m²
2 Kolom K2 15x30 cm
Pembesian
p tul. pokok : 4,2 m' x 6 bh = 25,2 m'
p tul. begel : 0,66 m'
W d13/m : 12,5 / 12 = 1,042 kg
W Ø 8/m : 4,74 / 12 = 0,395 kg
Ø8 - 100 : 43 bh
Berat besi tul pokok
= p x W
= 25,2 x 1,04
= 26,25 kg/m3
Berat besi tul sengkang
= p x W x 43
= 0,66 x 0,40 x 43
= 11,21 kg/m3
Total Berat = 37,5 x 6 bh (jmlh kolom )
= 224,76 kg/m3
Berat per 10 kg
= 22,476 10kg/m3 22,48 kg
Volume Beton
V = 0,15 x 0,3 x 4,2 = 0,189 m3
V total = 0,189 x 6 = 1,134 m3 1,13 m³
Luas Bekisting
L = 0,9 x 4,2 x 6
= 22,68 m2 22,68 m²
3 Balok RB 15x25 cm
Pembesian
p tul. pokok : 24,50 m' x 4 bh = 98 m'
p tul. begel : 0,56 m'
W d13/m : 12,5 / 12 = 1,042 kg
W Ø 8/m : 4,74 / 12 = 0,395 kg
Ø8 - 100 : 245 bh
Berat besi tul pokok
= p x W
= 98 x 1,04
= 102,08 kg/m3
Berat besi tul sengkang
= p x W x 245
= 0,56 x 0,40 x 245
= 54,19 kg/m3
Total Berat
= 156,28 kg/m3
Berat per 10 kg
= 15,628 10kg/m3 15,63 kg
Volume Beton
V = 0,15 x 0,25 x 24,5 = 0,91875 m3 0,92 m³
Luas Bekisting
L = 2 x 0,25 x 24,5
= 12,25 m2 12,25 m²
Subtotal
Subtotal
iV PEKERJAAN LANGIT-LANGIT
1 Plafond Gypsum Board 9mm Finish. Cat ex Catylac + Rangka Hollow
L = 9,0 m2 9,00 m²
Subtotal
b SANITASI
1 Instalasi Air Bersih pipa 1/2" Ex. Rucika Aw 12,00 m'
2 Instalasi Air Kotor pipa 3" Ex. Rucika Aw 12,00 m'
3 Kran Air Ex. Onda / Setara 1,00 bh
Subtotal
TOTAL C
D. PEKERJAAN ATAP
1 Waterproof 58,25 m²
2 Rangka Atap Baja Ringan 98,84 m²
3 Atap Spandek 98,84 m²
4 Alumunium Foil 98,84 m²
5 Triplek 3mm 98,84 m²
6 Kanopi Rangka Hollow 19,25 m²
7 Tangga Putar 1,00 set
8 Listplank 54,00 m'
TOTAL D
DAFTAR UPAH TENAGA
Dokumen Perencanaan Teknis
16 1 m2 Pek. Acian
Bahan
PC Kg 3,1080 Rp 900,00 Rp 2.797,20
Pekerja -
Pekerja OH 0,1500 Rp 90.000,00 Rp 13.500,00
Tukang Batu OH 0,0750 Rp 90.000,00 Rp 6.750,00
Kepala Tukang OH 0,0080 Rp 95.000,00 Rp 760,00
Mandor OH 0,0080 Rp 100.000,00 Rp 800,00
Jumlah Rp 24.607,20
Dibulatkan Rp 24.600,00
40 1 m2 Pasang Kaca Es 5 mm
Bahan
Kaca Es 5 mm m2 1,1000 Rp 162.300,00 Rp 178.530,00
Pekerja -
Pekerja OH 0,1600 Rp 90.000,00 Rp 14.400,00
Tukang Kayu OH 0,1600 Rp 90.000,00 Rp 14.400,00
Kepala Tukang OH 0,0160 Rp 95.000,00 Rp 1.520,00
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
1 2 3 4 5 6
Mandor OH 0,0080 Rp 100.000,00 Rp 800,00
Jumlah Rp 209.650,00
Dibulatkan Rp 209.650,00