ITEM PEMBAYARAN NO. : 1.

2
JENIS PEKERJAAN : MOBILISASI

% TERHADAP TOTAL BIAYA PROYEK = #REF! %


Lembar 1.2-1
HARGA JUMLAH
No. URAIAN SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

A. Sewa Tanah M2 2.500,00 20.000 50.000.000

B. PERALATAN
Periksa lembar 1.2-2 355.600.000

C. Kantor Lapangan dan Fasilitas 1,00 0


1 Base Camp M2 100,00 500.000 50.000.000
2 Kantor M2 50,00 500.000 25.000.000
3 Barak M2 50,00 250.000 12.500.000
4 Bengkel M2 200,00 56.000 11.200.000
5 Gudang, dan lain-lain M2 1.000,00 50.000 50.000.000
6 Papan Nama Proyek Buah 2,00 1.000.000 2.000.000

D. MOBILISASI FASILITAS LABORATORIUM set 1,00 124.000.000 124.000.000


1 Ruang Laboratorium (sesuai Gambar)

2 Soil & Aggregate Testing


Compaction Test
CBR Test
Specific Gravity
Atterberg Limits
Grain Size Analysis
Field Density Test by Sand Cone Methode
Moisture Content
Abrasion of Aggregate by Los Angeles Machine

3 Bituminous Testing
Marshall Asphalt Test
Extraction Test, Centrifuge/Refflux Method
Specific Gravity for Coarse Aggregate
Specific Gravity for Fine Aggregate
Mix Air Viod Content (Accurate Method)
Core Drill
Metal Thermometer
Accessories and Tolls
Penetration Test
Softening Point
Refusal Density Compactor

4 Concrete Testing
Slump Cone
Cylinder Mould for Compressive Strength
Beam Mould for Flexural Strength (RIGID)
Crushing Machine

5 Pendukung (Periksa Fasilitas Laboratorium)

6 Operasional (Periksa Fasilitas Laboratorium)

* Fasilitas Kantor Direksi


- Sewa Kendaraan Roda 4 (3 Unit) Bln 39,00 7.000.000,00 273.000.000
- Sewa Kendaraan Roda 2 (3 Unit) Bln 39,00 1.500.000,00 58.500.000
E. MOBILISASI PERSONIL
E.I. Personil Sesuai Struktur Organisasi LS 0
1 General Superintendent (GS)
2 Tenaga Ahli Jalan
3 Tenaga Ahli Jembatan . . . .
4 Para Asisten Tenaga Ahli Jalan . . . .
5 Para Asisten Tenaga Ahli Jembatan . . . .
6 Para Surveyor & Teknisi . . . .

E.II. Personil Lainnya Set 0


1 Koordinator Manajemen dan Keselamatan Lalu Lintas (KMKL)
....
2 Manajer Kendali Mutu ....
3 Ahli K3 Muda min.3 tahun ....
4 Staf KMKL (2 orang) ....
5 Para Staf Pendukung Manajemen Mutu ....
6 Para Staf Pendukung K3 ....

F. Manajemen dan Keselamatan lalu lintas LS 0

G. DEMOBILISASI LS 1,00 143.880.000 143.880.000

E TOTAL BIAYA MANAJEMEN DAN KESELAMATAN LALU LINTAS 1.155.680.000


F OVERHEAD & PROFIT 10,00 % x D 115.568.000,00
G HARGA SATUAN PEKERJAAN ( E + F ) 1.271.248.000,00
Catatan : Harga Satuan Personil tersebut sudah termasuk seluruh pajak dan bea (kecuali PPN),
Asuransi Tenaga Kerja dan pengeluaran lainnya.
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : MOBILISASI
Lembar 1.2-2
KODE HARGA JUMLAH
No. JENIS ALAT ALAT SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

B. PERALATAN

1 ASPHALT FINISHER E02 Unit 2,00 10.000.000 20.000.000,00


2 BULLDOZER 100-150 HP E04 Unit 2,00 10.000.000 20.000.000,00
3 COMPRESSOR 4000-6500 L\M E05 Unit 2,00 1.000.000 2.000.000,00
4 CONCRETE MIXER 0.3-0.6 M3 E06 Unit 4,00 1.500.000 6.000.000,00
5 CRANE 10-15 TON E07 Unit 1,00 10.000.000 10.000.000,00
6 DUMP TRUCK 4 TON E08 Unit 12,00 1.250.000 15.000.000,00
7 DUMP TRUCK 7 TON E09 Unit 20,00 1.250.000 25.000.000,00
8 EXCAVATOR 80-140 HP E10 Unit 8,00 10.000.000 80.000.000,00
9 FLAT BED TRUCK 4 TON E11 Unit 2,00 500.000 1.000.000,00
10 GENERATOR SET E12 Unit 2,00 1.000.000 2.000.000,00
11 MOTOR GRADER >100 HP E13 Unit 2,00 10.000.000 20.000.000,00
12 TRACK LOADER 75-100 HP E14 Unit 2,00 10.000.000 20.000.000,00
13 WHEEL LOADER 1.0-1.6 M3 E15 Unit 2,00 10.000.000 20.000.000,00
14 TANDEM ROLLER 6-8 T. E17 Unit 2,00 10.000.000 20.000.000,00
15 TIRE ROLLER 8-10 T. E18 Unit 2,00 10.000.000 20.000.000,00
16 VIBRATORY ROLLER 5-8 T. E19 Unit 2,00 10.000.000 20.000.000,00
17 CONCRETE VIBRATOR E20 Unit 4,00 250.000 1.000.000,00
18 WATER PUMP 70-100 mm E22 Unit 1,00 250.000 250.000,00
19 WATER TANKER 3000-4500 L. E23 Unit 2,00 1.000.000 2.000.000,00
20 TAMPER E25 Unit 4,00 250.000 1.000.000,00
21 JACK HAMMER E26 Unit 1,00 250.000 250.000,00
22 WELDING SET E32 Unit 1,00 100.000 100.000,00
23 ROCK DRILL BREAKER E36 Unit 1,00 10.000.000 10.000.000,00
24 ASPHALT DISTRIBUTOR E41 Unit 2,00 2.500.000 5.000.000,00
25 SHOTCRETE MACHINE Unit 1,00 25.000.000 25.000.000,00
26 SHEEP FOOT ROLLER Unit 1,00 10.000.000 10.000.000,00

Total untuk Item B pada Lembar 1 355.600.000,00