no item qty satuan harga satuan harga


A Kebutuhan 2 stage 19mm
1 Besi 19 mm SNI 3 btg 400,000 1,200,000
2 Besi 10 mm SNI 4 btg 95,000 380,000

B Kebutuhan 7 stage 16mm


1 Besi 16 mm SNI 7 btg 280,000 1,960,000
2 Besi 10 mm SNI 16 btg 95,000 1,520,000

C Kebutuhan 6 stage 13mm


1 Besi 13 mm SNI 6 btg 175,000 1,050,000
2 Besi 10 mm SNI 12 btg 95,000 1,140,000
3 Besi 8 mm SNI 4 btg 90,000 360,000
4 Besi siku 4x4 7 btg 150,000 1,050,000
8,660,000
D Jasa
Tukang Las 15 stg 300,000 4,500,000
angkur Pondasi Tengah 1 set 100,000 100,000
angkur Pondasi pancang 3 Set 175,000 525,000
Mounting 2 set 125,000 250,000
Cat 8 kaleng 75,000 600,000
Tiner 30 ltr 23,000 690,000
15,325,000
1,021,667
1 btg
90 126 105
10 11 31
900 1386 3255
5.425

40 40 40 40 40 40 40 40 40 40

supir 150,000
mobil 350,000
minyak 400,000
900,000 4,500,000
RAB Pembuatan Tower 60 meter

No Item Qty Satuan Harga Satuan Harga


A Tower 60 meter @15 Stage
1 Stage Tower Triangle 15 stage 1,100,000 16,500,000
Besi 19 mm diameter 30x30 ( 2 )
Besi 16 mm Diameter 30x30 ( 7 )
Besi 13 mm Diameter 30x30 (6 )

B Bahan Pondasi
Pasir 1 Lot 250,000 250,000
Batu Split 1 Lot 250,000 250,000
Semen 6 sak 70,000 420,000

C Bahan Pendukung Tower


Kawat No 10 3 Roll 1,100,000 3,300,000
Baut Nomor 14 Pendek 100 pcs 2,000 200,000
jarum keras no 12 45 pcs 24,000 1,080,000

D Jasa Pendirian Tower


Jasa Pendirian Tower 15 stage 300,000 4,500,000
Jasa Transportasi akomodasi 1 Lot 7,000,000 7,000,000

33,500,000