PENYEBAB TIDAK TERCAPAINYA PRODUKSI KLINKER

Target 8,000 t/h

Penyebab Action Dampak


Operasional
Tanggal Production Note Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production

1-Jul-18 8,019.0 ok Lancar 19.00


2-Jul-18 8,101.0 ok Lancar 101.00
3-Jul-18 8,163.0 ok Lancar 163.00
4-Jul-18 8,165.8 ok Lancar 165.80
5-Jul-18 8,158.7 ok Lancar 158.70
6-Jul-18 8,164.9 ok Lancar 164.90
7-Jul-18 8,165.2 ok Lancar 165.20
Perbaikan pendulum valave B54IDserta
Pressure after fan max 2
penggantian kanvas air 1:22 2:06 0:44
8-Jul-18 5,389.0 slide 6W1A14 yang bocor (2611.00)
16:58 0:00

9-Jul-18 4,687.0 Kiln feeding jam 07:33 7:33 14:35 (3313.00)


10-Jul-18 7,914.0 Gangguan pembakaran / coating jatuh (86.00)
11-Jul-18 8,175.0 ok lancar 175.00
12-Jul-18 8,235.9 ok lancar 235.90
13-Jul-18 7,688.4 ok Feed 480-560 tph flutuasi karena LSF Raw Mix tinggi (311.60)
Feed 400-570 tph flutuasi karena LSF Raw Mix tinggi + turun
14-Jul-18 7,670.0 (330.00)
feeding karena menstop V23 untuk perbaikan pipa yang bocor
15-Jul-18 8,066.0 gangguan power Gi PLN teluk siri 2:05 2:54 0:49 66.00
16-Jul-18 7,070.0 6W1W02 vibrasi max 11:07 11:31 0:24 (930.00)
17-Jul-18 7,862.0 feeding tidak max karena SIM kiln feed >1,5 (138.00)
18-Jul-18 6,676.0 LSF fluktuasi dari 99-105,4 (1324.00)
10:06 10:49 0:43
19-Jul-18 7,119.0 6W1A08Z1 runtime (881.00)
15:11 16:43 1:32
20-Jul-18 8,202.4 ok lancar 202.40
21-Jul-18 7,940.1 ok lancar (59.90)
22-Jul-18 7,658.4 ok LSF Kilnfeed tinggi (341.60)
23-Jul-18 6,946.9 ok LSF Kilnfeed tinggi & nox rendah (1053.10)
24-Jul-18 7,777.0 nok feeding berfluktuasi karena LSF kiln feed tinggi (223.00)
25-Jul-18 8,132.0 ok 23:30 132.00
26-Jul-18 stop perbaikan cooler (8000.00)
27-Jul-18 stop perbaikan cooler (8000.00)
28-Jul-18 stop perbaikan cooler (8000.00)
29-Jul-18 stop perbaikan cooler (8000.00)
30-Jul-18 stop perbaikan cooler
31-Jul-18 1,014.8 ok 19:39 (6985.20)
190146.7 Total Produksi
195000 RKAP Bulan Ini
-4853.3
248000 RKAP Int Bulan Ini
-57853.3

Agustus 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
1-Aug-18 8251 ok 251.00
2-Aug-18 8158 ok 158.00
3-Aug-18 6071 6W1K41 sealing air ganti motor dengan motor fan JPF 6U1P72 0:50 5:54 5:04 (1929.00)
fan motor short phase dengan body.
4-Aug-18 7569 W1V22 coriolis multi cell terganjal/stop sehingga kiln turun feeding longgarkan baut penutup 16:51 3:11 10:20 (431.00)
5-Aug-18 7205.2 Feeding berfluktuasi karena LSF kiln feed tinggi (794.80)
6-Aug-18 7610.9 LSF Kilnfeed tinggi & nox rendah (389.10)
7-Aug-18 7715.5 LSF Kilnfeed tinggi & nox rendah (284.50)
butterfly LSF Kilnfeed tinggi & nox rendah + coriolis v23 stop dari 03:27 sd
8-Aug-18 7716.2 6W1V44 cek sensor.ganti fuse dan eratkan koneksi kabel sensor (283.80)
valve 04:56 karena valve V44 runtime
9-Aug-18 8341 ok 341.00
10-Aug-18 8238 ok 238.00
11-Aug-18 7590 LSF raw mix fluktuatif dari 101-106 (410.00)
12-Aug-18 8711 ok 711.00
13-Aug-18 6196 Feeding ditahan 400 tpd CF Silo kritis (1804.00)
14-Aug-18 7000 Feeding ditahan 470 tpd CF Silo kritis (1000.00)
15-Aug-18 8034.2 ok keterbatasan power dari GI 34.20
16-Aug-18 8123.5 ok 123.50
17-Aug-18 7740 free lime sering > 1,5 turunkan feeding kiln sampai 500 t/h (260.00)
18-Aug-18 6435.1 Feeding ditahan 400 tpd CF Silo kritis (1564.90)
19-Aug-18 7424.4 lsf KF berfluasi tinggi. cek exstraksi silo (575.60)
20-Aug-18 8154.1 ok 154.10
21-Aug-18 8377 ok 377.00
22-Aug-18 8581 ok 581.00
23-Aug-18 8427.7 ok 427.70
gangguan tegangan di GI 16:28 17:13 0:45 (614.00)
24-Aug-18 7386
kiln turun feed s/d 400 tph karena W1V23 STOP (tertahan) 20:30
7006 kiln turun feed s/d 400 tph karena W1V23 STOP (tertahan) MEbuka down pipe mullticore serta bantu putar dengan chain (994.00)
25-Aug-18 sampai jam 10:50 block
7892 kiln turun feed s/d 400 tph karena W1V23 STOP (tertahan) jam ME buka down pipe mullticore dan putar dengan chain block (108.00)
26-Aug-18 22.30 serta bantu distart local oleh EL
27-Aug-18 7762 W1V23 STOP +Rhino 22:30 1:18 (238.00)
28-Aug-18 7573 rhino dan clogging bersihkan rino clongging (427.00)
29-Aug-18 8213.4 rhino dan clogging bersihkan rino clongging 213.40
30-Aug-18 8306.5 Lancar 306.50
31-Aug-18 8340.5 Lancar 340.50
240149.2 Total Produksi
226200 RKAP Bulan Ini
13949.2
248000 RKAP Int Bulan Ini
-7850.8

September 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
1-Sep-18 8512.9 ok Lancar 512.90
6R1U05Z1 alarm limit drifting serta membuat 6W1A08Z1Y01
7999.7
alarm dan limit lifting dan menyetop feeding kiln.
jalankan elevator stand by 6R1U17 13:08 13:42 0:34 (0.30)
2-Sep-18
3-Sep-18 7461.6 Pembakaran keras dimana LSF klinker >96 sesuaikan feeding kiln untuk operasional (538.40)
4-Sep-18 7848.6 LSF tinggi + red spot di m.5.2 (151.40)
5-Sep-18 7431.4 Tahan feeding untuk antisipasi red spot di m 5.2 (568.60)
6-Sep-18 7426.1 Tahan feeding untuk antisipasi red spot di m 5.2 (573.90)
7-Sep-18 7506 Tahan feeding untuk antisipasi red spot di m 5.2 (494.00)
8-Sep-18 7020.3 Tahan feeding untuk antisipasi red spot di m 5.2 (979.70)
9-Sep-18 6891.6 Tahan feeding untuk antisipasi red spot di m 5.2 (1108.40)
10-Sep-18 6036.5 Tahan feeding untuk antisipasi red spot di m 5.2 (1963.50)
kiln stop patching 20:35
11-Sep-18 kiln stop patching (8000.00)
12-Sep-18 kiln stop patching (8000.00)
13-Sep-18 kiln stop patching (8000.00)
14-Sep-18 kiln stop patching (8000.00)
15-Sep-18 kiln stop patching (8000.00)
16-Sep-18 3196.6 kiln feeding 13:22 13:22 (4803.40)
6W1V21A02/6W1V
kiln coal dan calsiner coal purge air system return fault ME bersihkan saringan udara setelah tanki yang di BHF 10:48 11:30 0:42
17-Sep-18 6729.1 22A02 (1270.90)
fine coal kritis. coal mill stop temperatur bhf tinggi 20:31
19-Sep-18 4785.9 kiln feeding 9:13 (3214.10)
20-Sep-18 8802.3 802.30
21-Sep-18 8146.7 146.70
22-Sep-18 8010.1 10.10
23-Sep-18 8334.8 334.80
24-Sep-18 8101.5 101.50
Lepaskan coupling motor, tes motor ok,cekbearing ok, cek
25-Sep-18 5713.2 6W1B17 Rotary feeder over current blade rotary feeder ditemukan ada satu posisi yg bengkok lau 1:38 8:29 6:51 (2286.80) atasi cloaging inlet
di gerinda ok, test running lagi ok current 37%
26-Sep-18 8139.4 139.40
27-Sep-18 8092.6 92.60
28-Sep-18 7901.5 (98.50)
29-Sep-18 8156.1 156.10
30-Sep-18 8101.7 101.70
176346.2 Total Produksi
226200 RKAP Bulan Ini
-49853.8
240000 RKAP Int Bulan Ini
-63653.8

Oktober 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
1-Oct-18 7820.3 Lancar
2-Oct-18 8011.6
3-Oct-18 8153.8
korek cloging dan jengger serta sesuaikan feeding untuk
4-Oct-18 7826.2 lancar[ { nox rendah serta pressure inlet tinggi } menjaga kualitas klinker.
5-Oct-18 8007.2
6-Oct-18 7404.6 elevator A12 bus fault 3:43 4:40 0:57
7-Oct-18 7062 elevator A12 bus fault 18:55 19:58 1:03
8-Oct-18 8077.5 Lancar
9-Oct-18 8149.5 Lancar
korek cloging dan jengger serta sesuaikan feeding untuk
10-Oct-18 7717.3 lancar[ { nox rendah serta pressure inlet tinggi } menjaga kualitas klinker.
korek cloging dan jengger serta sesuaikan feeding untuk
11-Oct-18 7377 lancar[ { nox rendah.freelime tinggi dan lsf tinggi } menjaga kualitas klinker.
12-Oct-18 7985 Lancar
13-Oct-18 8230.9 Lancar
klinker crusher trip 10:25 12:32 2:07
14-Oct-18 6308
klinker crusher trip 16:08 18:14 2:06
15-Oct-18 7919 Feed diturunkan karena 6U1J03 block
16-Oct-18 7440.8 Temp . fluid coupling 6R1U17 alarm Pindah feeding ke Elevator Kiln 12:03 13:22 1:19
6W1M01A02 Klinker Crusher Trip Check dan pastikan kondisi Crusher 9:35 12:30 2:55
17-Oct-18 6069.5
Tegangan GI Turun 15:46 17:20 1:34
18-Oct-18 8129.3 Lancar
19-Oct-18 7298
20-Oct-18 7650 Feeding tidak max karena LSF klinker > 95 koordinasi sama labor untuk turunkan target lsf raw mix
feeding kiln tidak max karena free lime >1.5 serta antisipasi chute
21-Oct-18 7760.7 J04 block [ jalan satu PAN conv J03 ]
22-Oct-18 8014 lancar
23-Oct-18 8134 lancar
24-Oct-18 8127 Lancar
25-Oct-18 7808.5 Feeding tidak max karena LSF klinker > 95 sesuaikan feeding untuk menjaga kualitas klinker.
26-Oct-18 8232.7
27-Oct-18 7929
28-Oct-18 8344 Lancar
29-Oct-18 8160 Lancar
30-Oct-18 8162 lancar
31-Oct-18 8062 lancar
241371.4 Total Produksi
226200 RKAP Bulan Ini
15171.4
248000 RKAP Int Bulan Ini
-6628.6

November 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
1-Nov-18 8093.2 Lancar
2-Nov-18 5319 perbaikan cooler 18:03
3-Nov-18 0 perbaikan cooler
4-Nov-18 2023.4 perbaikan cooler 15:55
5-Nov-18 7995.4 Lancar
6-Nov-18 8194 Lancar
7-Nov-18 6998.6 6W1A54N01T01 fuse problem+ cf silo kritis 10:51 11:24 0:33
8-Nov-18 7948.1 LSF raw mix fluktuasi
9-Nov-18 7782.8 LSF raw mix fluktuasi
10-Nov-18 8026.4 Lancar
11-Nov-18 7944 Lancar
12-Nov-18 8240.3 Lancar
13-Nov-18 8521 Lancar
14-Nov-18 8137.7 Lancar
15-Nov-18 8144 Lancar
16-Nov-18 7385 tahan feedinguntuk naikkan isi CF sio
17-Nov-18 4568.1 6W1M01A02 Cruhser Trip terganjal patahan Crossbar Ambil Crossbar yang patah 6:21 8:53 2:32
18-Nov-18 7128.5 6W1V22 Cariolis trip alarm not ready.
19-Nov-18 8025.2 Lancar
20-Nov-18 8031

21-Nov-18 4016 chute pan conv 6j1U04 block oleh plate serta J03 keluar dari rel 7:36 16:49 9:13

7528 proses speed up [ feeding tertahan 530-500 t/h free lime >1.5
22-Nov-18 karena SIM KF >2.6 serta pan conv jalan satu J04
23-Nov-18 8036
7681
24-Nov-18 stop lonjakan tegangan PLN (transmisi PLN ombilin ada gangguan) 11:00 11:32 0:32
7351 free lime sering > 1,5 karena SIM Kiln feed tinggi sehingga
25-Nov-18 pembakaran sulit dan terpaksa turun feeding.
7255.8 free lime sering > 1,5 karena SIM Kiln feed tinggi sehingga
26-Nov-18 pembakaran sulit dan terpaksa turun feeding.
27-Nov-18 6578 6W1M01A02 Klinker Crusher Trip not ready 5:19 6:23 1:04
28-Nov-18 7545 tahan feeding untuk jaga isi CF sio
29-Nov-18 7290.4 tahan feeding 500 t/h untuk jaga isi CF sio
30-Nov-18 7290 tahan feeding 500 t/h untuk jaga isi CF sio
209076.9 Total Produksi
226200 RKAP Bulan Ini
-17123.1
240000 RKAP Int Bulan Ini
-30923.1

Desember 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
1-Dec-18 6562 tahan feeding 450 t/h untuk jaga isi CF sio
2-Dec-18 6561 tahan feeding 450 t/h untuk jaga isi CF sio
3-Dec-18 6113.6 tahan feeding 400 t/h untuk jaga isi CF silo, RM PMC
4-Dec-18
5-Dec-18
6-Dec-18
7-Dec-18
8-Dec-18
9-Dec-18
10-Dec-18
11-Dec-18
12-Dec-18
13-Dec-18
14-Dec-18
15-Dec-18
16-Dec-18
17-Dec-18
18-Dec-18
19-Dec-18
20-Dec-18
21-Dec-18
22-Dec-18
23-Dec-18
24-Dec-18
25-Dec-18
26-Dec-18
27-Dec-18
28-Dec-18
29-Dec-18
30-Dec-18
31-Dec-18
19236.6 Total Produksi
218400 RKAP Bulan Ini
-199163.4
248000 RKAP Int Bulan Ini
-228763.4
PENYEBAB TIDAK TERCAPAINYA PRODUKSI FINE COAL
Target 1,920 t/h

Penyebab Action Dampak


Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
6K1A03 Rotary air lock Over Current terganjal batu Bebaskan material yang nyangkut 1:14 1:38 0:24
1-Jun-18 2,086.0 Bin FC L11 dan L22 penuh 14:47 16:32 1:45 166
6K1A03 Rotary air lock Over Current terganjal batu Bebaskan material yang nyangkut 19:04 19:25 0:21
Bin FC L11 dan L22 penuh 4:29 5:32 1:03
2-Jun-18 1,937.0 Bin FC L11 dan L22 penuh 15:09 16:07 0:58 17
Bin FC L11 dan L22 penuh 20:33 21:46 1:13
6K1A03 Rotary air lock Over Current terganjal batu Bebaskan material yang nyangkut 3:27 3:51 0:24
3-Jun-18 2,065.4 145
Bin FC L11 dan L22 penuh 12:21 13:37 1:16
6K1A03 Rotary air lock Over Current terganjal batu Bebaskan material yang nyangkut 3:35 4:14 0:39
4-Jun-18 1,954.4 34
Bin FC L11 dan L22 penuh 18:20 19:41 1:21
6K1A03 Rotary air lock Over Current terganjal batu Bebaskan material yang nyangkut 12:28 13:44 1:16
5-Jun-18 1,950.0 product trasport stop langsug ready 14:35 15:50 1:15 30
6K1A03 Rotary air lock Over Current terganjal batu Bebaskan material yang nyangkut 16:10 16:29 0:19
6K1A03 Rotary air lock Over Current terganjal batu Bebaskan material yang nyangkut 4:10 4:34 0:24
stel bukaan angin regulator masuk bhf serta
buka valve angin manual [regulator
6-Jun-18 2,122.0 pressure BHF tinggi
anginmacet atau rusak serta sudah diketahui
4:46 5:25 0:39 202
mekanik]
Over Current terganjal batu Bebaskan material yang nyangkut 20:02 20:29 0:27
Over Current terganjal batu Bebaskan material yang nyangkut 8:00 8:22 0:22
Bebaskan material yang nyangkut pada A03
6K1A03 dan A03 over current terganjal batu serta mill fan kondisi stop tapi serta block emergency motor sesaat [ EL akan
13:41 15:40 1:59
6K1P25M01 KW terbaca sehingga delay stop tidak terbaca ganti switch gear apabila mill sudah bisa
7-Jun-18 2,051.00 stop / isi BIN FC cukup] 131
A03 bebaskan material yang menyankut serta
6K1A03 dan stel bukaan angin regulator masuk bhf serta
A03 over Current terganjal batu serta pressure inlet Bhf tinggi 19:16 19:56 0:40
6K1P11A01P02 buka valve angin manual [regulator yg rusak
sudah diketahui mekanik]
product transport trip ready kan oleh elinst 11:54 12:20 0:26
8-juni-18 2,159.0 239
kiln stop 13:57 15:33 1:36
6K1M04 not ready di reset langsung ready 6:59 7:36 0:37
6K1P11 perbaikan ME perbaiki regulator 9:36 10:45 1:09
9-juni-18 2,027.0 107
6K1J06 unit fault di reset langsung ready 18:33 19:13 0:40
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 21:02 21:20 0:18
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 2:14 2:33 0:19
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 2:52 3:24 0:32
10-juni-18 2,306.9 387
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 10:25 10:44 0:19
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 13:51 14:13 0:22
6K1A03+6K1M0 Bebaskan material yang nyangkut dan
Over Current terganjal batu&6K1M05 pressure low 10:32 12:57 2:25
5 bersihkan air filter, atasi kebocoran
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 13:33 13:51 0:18
11-juni-18 1,956.2 36
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 14:04 14:22 0:18
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 18:30 19:00 0:30
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 20:36 21:01 0:25
6K1M01 PMC 7:35 12:21 4:46
12-Jun-18 1,761.9 6K1M03 ups alarm unit fault 13:13 15:00 1:47 (158)
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 17:56 18:14 0:18
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 8:04 8:24 0:20
13-Jun-18 2,363.2 6K1M07 temperatur low 8:44 9:11 0:27 443
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 20:05 20:23 0:18
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 1:16 1:36 0:20
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 4:20 5:24 1:04
14-Jun-18 2,276.0 356
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 7:44 8:04 0:20
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 20:28 20:51 0:23
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 3:55 4:13 0:18
6K1M03 kiln stop 6:04 14:02 7:58
15-Jun-18 1,533.0 (387)
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 14:21 14:44 0:23
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 22:31 22:48 0:17
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 1:14 1:33 0:19
K1M04E1 NOT READY 7:12 7:30 0:18
16-juni-18 2,054.0 K1A02 belt terkelupas lem belt yang terkelupas 9:43 11:45 2:02 134
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 14:15 14:34 0:19
K1M01Z1 reject tersumbat bebaskan yang menyumbat 16:17 17:08 0:51
transport FC MD (putaran agak tertahan) reset 7:56 8:14 0:18
transport FC MD (putaran agak tertahan) reset 8:56 9:21 0:25
17-juni-18 2,273.00 353
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 10:36 10:54 0:18
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 11:44 12:03 0:19
18-juni-18 2,199.30 6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 23:00 23:18 0:18 279
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 9:22 9:43 0:21
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 10:20 10:41 0:21
19-juni-18 2,141.90 6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 15:11 15:30 0:19 222
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 15:53 16:23 0:30
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 21:03 21:23 0:20
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 6:31 7:00 0:29
20-juni-18 2,266.50 6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 18:00 18:20 0:20 347
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 22:14 22:37 0:23
6K1M04 TRIP low pressure di reset langsung ready 12:47 13:14 0:27
6K1M04 TRIP low pressure di reset langsung ready 17:12 17:50 0:38
6K1M04 TRIP low pressure di reset langsung ready 18:35 19:18 0:43
21-juni-18 2,031.60 di check ME dan akan dibersihkan saringan 112
0:27
6K1M04 TRIP low pressure apabila mill stop 20:48 21:15
Bebaskan material yang nyangkut serta Me
6K1A03 Over Current terganjal batu 0:38
bersihkan saringan M04 21:46 22:24
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 1:50 2:08 0:18 343
22-juni-18 2,263.30 6K1M04 TRIP low pressure di reset langsung ready 4:21 4:50 0:29
6K1M04 TRIP low pressure Bersihkan saringan 6:02 6:34 0:32
L11 dan L21 Bin FC L11 dan L22 penuh 7:20 8:32 1:12 133
23-juni-18 2,053.00 kiln stop 9:56 11:37 1:41
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 18:00 18:19 0:19
6K1M04 TRIP low pressure di reset langsung ready 7:02 7:21 0:19 258
24-juni-18 2,178.00
6K1M04 TRIP low pressure Bersihkan saringan 14:25 15:02 0:37
Bin FC L11 dan L22 penuh 9:23 10:31 1:08 59
6K1M04 TRIP low pressure Bersihkan saringan 14:45 15:06 0:21
25-juni-18 1,979.00 6K1P17 Rotary Air Lock Alarm MD di reset langsung ready 16:26 16:44 0:18
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 19:19 19:38 0:19
6K1M04 TRIP low pressure di reset langsung ready 23:23 23:50 0:27
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 3:20 3:42 0:22
26-juni-18 2,103.00 Coal Mill Stop RawCoal Kritis 12:50 13:58 1:08 183
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 15:18 15:39 0:21
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 2:30 3:06 0:36
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 12:54 13:20 0:26
27-juni-18 1,859.00 (61)
kiln stop 19:54 21:51 1:57
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 22:32 22:50 0:18
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 5:31 5:51 0:20
28-juni-18 2,164.70 6K1M04 NOT ready 15:25 16:26 1:01 245
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 19:01 19:22 0:21
kiln stop 4:20 7:34 3:14
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 10:40 10:58 0:18
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 11:18 11:36 0:18
29-juni-18 1,907.60 6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 19:54 20:13 0:19 (12)
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 20:47 21:06 0:19
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 22:02 22:22 0:20
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 23:28 23:48 0:20
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 8:17 8:43 0:26
30-juni-18 2281
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 8:43 9:02 0:19

JULI 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 7:06 8:10 1:04
1- juli-2018 2108 188
6K1M04 TRIP low pressure di reset langsung ready 21:37 22:09 0:32
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 0:55 1:15 0:20
2-juli-2018 2326 6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 4:24 5:02 0:38 406
6K1M04 TRIP low pressure di reset langsung ready 16:37 17:02 0:25
6K1A03 Over Current terganjal batu + penggantian CT di GI Bebaskan material yang nyangkut 13:35 16:01 2:26
3-juli-2018 2110 190
J1U05 R1U07 stop dan menstop J1U05 21:59 22:24 0:25
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 1:20 1:34 0:14
4-juli-2018 2231 6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 7:54 8:20 0:26 311
6K1A01 Set Point tidak terbaca Reset dipanel lapangan 16:39 17:45 1:06
6K1M04 6K1M04 not ready 2:10 2:37 0:27
5-juli-2018 2126.4 Pengujian CO2 ke bin Indarung V 10:41 12:12 1:31 206
6K1M04 6K1M04 not ready 21:42 22:01 0:19
6K1M04 6K1M04 not ready 8:21 8:56 0:35
6-juli-2018 2119.9 6K1J03Z1 run time 15:58 16:26 0:28 200
6K1M04 6K1M04 not ready 18:18 18:44 0:26
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 2:15 2:33 0:18
6K1M04 6K1M04 not ready 10:42 11:39 0:57
7-juli-2018 2248 328
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 13:09 13:27 0:18
6K1M04 6K1M04 not ready 15:49 16:06 0:17
6K1J03Z1 run time 1:16 3:23 2:07
6K1J03Z1 run time 4:17 4:44 0:27
8-juli-2018 1348 6K1M04 6K1M04 not ready 8:42 9:02 0:20 (572)
8-juli-2018 1348 (572)
6K1M05 6K1M05 not ready 16:01 16:21 0:20
kiln stop 16:46 0:00
10:56 17:56
6K1A03 Over Current terganjal batu 11:12 11:34 0:22
9-juli-2018 1171 6K1M04 6K1M04 not ready 17:40 18:06 0:26 (749)
6K1A03 Over Current terganjal batu 20:16 20:36 0:20
6K1A03 Over Current terganjal batu 21:11 21:30 0:19
6K1A03 Over Current terganjal batu 12:50 13:08 0:18
10-juli-18 2361 441
6K1A03 Over Current terganjal batu 21:48 22:11 0:23
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 4:12 4:35 0:23
6K1M04 TRIP low pressure di reset langsung ready 6:42 7:07 0:25
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 7:18 7:35 0:17
11-juli-18 2378 458
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 11:55 12:13 0:18
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 14:59 15:17 0:18
6K1M04 TRIP low pressure di reset langsung ready 23:54 0:00
0:24 0:30
Bin FC L11 dan L22 penuh 10:02 11:00 0:58
12-juli-2018 2185 265
6K1M04 TRIP low pressure di reset langsung ready 13:08 13:24 0:16
6K1M01 Keluarkan Plat dari Chute Reject 13:48 14:11 0:23
6K1M04 TRIP low pressure di reset langsung ready 2:32 3:30 0:58
13- juli-2018 2204 284
0:56
13:14 14:10
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 8:21 8:38 0:17
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 9:42 10:01 0:19
14-juli-2018 2063 143
product transport trip 13:00 13:20 0:20
6K1M04 TRIP low pressure di reset langsung ready 15:44 16:03 0:19
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 4:01 4:21 0:20
15- juli-2018 2087 6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 9:44 10:03 0:19 167
6K1M04 TRIP low pressure di reset langsung ready 21:26 21:44 0:18
gangguan power 2:05 3:40 1:35
16-juli-18 2088 168
kiln stop 11:08 11:36 0:28
17- juli-2018 2351 6K1A03 Over Current terganjal batu 8:20 8:39 0:19 431
bin full 9:15 10:39 1:24
18-juli-2018 1734 bin full 15:58 17:14 1:16 (186)
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 23:25 0:24 0:59
K1A02 belt K1A02 terkelupas lem belt yang terkelupas 2:31 3:36 1:05
6K1A03 Over Current terganjal batu + kiln stop Bebaskan material yang nyangkut 9:46 11:10 1:24
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 11:25 11:47 0:22
19-juli-18 1892 (28)
kiln stop 15:13 16:05 0:47
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 19:45 20:11 0:36
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 22:15 22:35 0:20
6K1A03 Over Current terganjal batu + kiln stop Bebaskan material yang nyangkut 0:12 1:10 1:20
6K1A03 Over Current terganjal batu + kiln stop Bebaskan material yang nyangkut 3:06 3:25 2:20
6K1A03 Over Current terganjal batu + kiln stop Bebaskan material yang nyangkut 9:18 9:50 3:20
20- juli-2018 2094.9 175
6K1M04 TRIP low pressure di reset langsung ready 15:31 15:50 4:20
6K1A03 Over Current terganjal batu + kiln stop Bebaskan material yang nyangkut 17:25 17:43 5:20
6K1A03 Over Current terganjal batu + kiln stop Bebaskan material yang nyangkut 20:44 21:04 6:20
6K1M04 TRIP low pressure di reset langsung ready 3:58 5:17 7:20
6K1M04 TRIP low pressure di reset langsung ready 10:28 10:46 8:20
21-juli-2018 2072 152
6K1A03 Over Current terganjal batu + kiln stop Bebaskan material yang nyangkut 18:31 18:50 9:20
6K1A03 Over Current terganjal batu + kiln stop Bebaskan material yang nyangkut 21:14 21:38 10:20
Bin FC L11 dan L22 penuh 7:56 9:10 1:14
22-juli-2018 1956 6K1M03 perbaiki seal hydraulic yg bocor 19:10 20:16 1:06 36
6K1M04 TRIP low pressure di reset langsung ready 23:20 23:41 0:21
PMC 7:36 14:10 6:34
23-juli-2018 1863
6K1M06 6K1M06 not ready ganti power suply 21:32 22:44 1:12
24-juli-18 2192 6K1A03 Over Current terganjal batu 2:03 2:22 0:19
6K1A03 Over Current terganjal batu 2:34 2:55 0:21
L11 dan L21 Bin FC L11 dan L22 penuh 11:29 13:41 2:12
25-juli-18 L11 dan L21 Bin FC L11 dan L22 penuh 1:20 2:20 1:00
6K1A03 Over Current terganjal batu 3:10 3:32 0:22
26-juli-18 1396 6K1M04 TRIP low pressure 7:43 8:11 0:28 524
6K1A03 Over Current terganjal batu 9:30 9:50 0:20
L11 dan L21 Bin FC L11 dan L22 penuh 15:39 17:04 1:25
27- juli-2018 kiln stop perbaikan cooler 17:50
28- juli-2018 kiln stop perbaikan cooler 0:00
29- juli-2018 kiln stop perbaikan cooler 0:00
30- juli-2018 kiln stop perbaikan cooler 0:00
20:42 20:42
31- juli-2018 257
6K1M01 vibrasi bodi mill tinggi. cek sensor oleh elints 21:39 22:21 0:42

Agustus 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
1- agustus-2018 2385 6K1A02 scraper kurang rapat perbaikan scraper serta gate material 15:05 16:14 1:09
6K1P51 JPF ducting tersumbat atasi ducting yang tersumbat 15:14 17:17 2:03
2- agustus-2018 2062
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 22:18 22:49 0:31
kiln stop 0:50 7:12 6:22
3- agustus-2018 1727
Bin FC L11 dan L22 penuh 23:23 0:09 0:46
Bin FC L11 dan L22 penuh 8:25 10:57 2:32
4- agustus-2018 1938
Bin FC L11 dan L22 penuh 22:18 0:19 1:01
Bin FC L11 dan L22 penuh 9:40 10:55 1:15
5- agustus-2019 2061
Bin FC L11 dan L22 penuh 22:40 0:06 1:26
6K1M01 reject tersumbat bebaskan yang menyumbat 1:30 1:52 0:22
6- agustus-2020 2023
Bin FC L11 dan L22 penuh 9:45 11:11 1:26
Bin FC L11 dan L22 penuh 2:49 4:03 1:14
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 4:24 4:41 0:17
7- agustus-2020 2006
6K1M05 v belt pecah2 ganti v-belt 8:28 9:15 0:47
6K1A03 Over Current terganjal batu + bin FC penuh Bebaskan material yang nyangkut 22:04 23:13 1:09
8- agustus-2018 2133 Bin FC L11 dan L22 penuh 16:28 17:19 0:51
Bin FC L11 dan L22 penuh 3:35 4:34 0:59
9- agustus-2019 2045
Bin FC L11 dan L22 penuh 15:02 16:52 1:50
6K1M04 TRIP low pressure di reset langsung ready 9:04 9:59 0:55
10- agustus-2020 2158 6K1M04 temp alarm di reset langsung ready 12:31 13:09 0:38
6K1M04 TRIP low pressure di reset langsung ready 14:57 15:20 0:23
11-agustus-2018 Bin FC L11 dan L22 penuh 14:56 16:31 1:35
12-agustus-2018 2139 lancar
Bin FC L11 dan L22 penuh 0:54 3:39 2:45
13-agustus-2019 1514 Bin FC L11 dan L22 penuh 9:34 11:24 1:50
6K1A03 Over Current terganjal batu Bebaskan material yang nyangkut 12:19 12:41 0:22
Bin FC L11 dan L22 penuh 7:28 8:44 1:16
14-agustus-2019 1789 6K1M04 TRIP low pressure di reset langsung ready 13:01 14:06 1:05
Bin FC L11 dan L22 penuh 20:24 22:11 1:47
Bin FC L11 dan L22 penuh 7:25 8:15 0:50
15- agustus-2019
Bin FC L11 dan L22 penuh 13:39 14:44 1:05
16-agustus-2018 Bin FC L11 dan L22 penuh 16:28 17:18 0:50
17-agustus-2018 1962 Bin FC L11 dan L22 penuh 16:15 18:42 2:27
Bin FC L11 dan L22 penuh 4:47 6:04 1:17
6K1M04 TRIP low pressure di reset langsung ready 8:39 9:41 1:02
18-agustus-2018 1601
Bin FC L11 dan L22 penuh 13:39 15:36 1:57
Bin FC L11 dan L22 penuh 20:50 22:02 1:12
Bin FC L11 dan L22 penuh 6:00 7:43 1:43
19-agustus-2018 1860
Bin FC L11 dan L22 penuh 17:46 19:27 1:41
1806 Bin FC L11 dan L22 penuh 3:22 4:48 1:26
20- agustus-2018
Bin FC L11 dan L22 penuh 21:37 23:12 1:35
1913 Bin FC L11 dan L22 penuh 10:12 11:44 1:32
21- agustus-2018
Bin FC L11 dan L22 penuh 21:19 22:40 1:21
22- agustus-2018 2013 Bin FC L11 dan L22 penuh 8:09 11:03 2:54
Bin FC L11 dan L22 penuh 3:04 4:14 1:10
23- agustus-2018 Bin FC L11 dan L22 penuh 9:28 11:15 1:47
Bin FC L11 dan L22 penuh 22:05 23:32 1:27
Over Current terganjal batu + bin FC penuh Bebaskan material yang nyangkut 1:58 2:15 0:17
24- agustus-2018 1844 Bin FC L11 dan L22 penuh 7:47 10:30 2:43
kiln stop 16:28 18:00 1:32
Bin FC L11 dan L22 penuh 1:42 3:27 1:45
25- agustus-2018 1591 Bin FC L11 dan L22 penuh 6:43 9:34 2:51
Bin FC L11 dan L22 penuh 18:10 20:22 2:12
Bin FC L11 dan L22 penuh 3:28 5:14 1:46
26- agustus-2018 1861 Bin FC L11 dan L22 penuh 11:35 13:00 1:25
Bin FC L11 dan L22 penuh 3:25 5:14 1:49
Bin FC L11 dan L22 penuh 1:13 2:15 1:02
27- agustus-2018 1994
6K1A03 Over Current terganjal batu + bin FC penuh Bebaskan material yang nyangkut 12:00 12:18 0:18
28-agustus-2018 1929 Bin FC L11 dan L22 penuh 14:26 16:22 1:56
PMC 7:52 11:56 4:04
29-agustus-2018 1909
Bin FC L11 dan L22 penuh 21:25 22:04 0:39
30- agustus-2018 2030 PMC 8:03 11:12 3:09
31- agustus-2018 2012 Bin FC L11 dan L22 penuh 13:56 16:11 2:15

September 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
bin full 4:21 6:15 1:54
1-Sep-18 2014 6K1A06 terganjal batu 9:35 9:59 0:24
bin full 13:11 14:45 1:34
bin full 1:53 2:55 1:02
2-Sep-18 1885 bin full 13:09 14:27 1:18
bin full 17:31 19:10 1:39
bin full 0:56 2:26 1:30
3-Sep-18 1781 bin full 6:13 7:43 1:30
bin full 15:35 16:39 1:04
4-Sep-18 1988 bin full 22:38 0:17 1:39
Low Pressure 6K1M04 5:06 6:22 1:16
5-Sep-18 1835
6K1A03 Over Current terganjal batu 22:35 22:53 0:18
6K1A03 Over Current terganjal batu 4:46 5:17 0:31
6-Sep-18 1888 6K1M04 TRIP low pressure 7:13 7:44 0:31
Mill distop menjaga isi bin tetap rendah, antisipasi red spot kiln. 15:23 17:03 1:40
7-Sep-18 1997 Bin FC L11 dan L22 penuh 11:57 12:55 0:58
Mill distop menjaga isi bin tetap rendah, antisipasi red spot kiln. 1:36 2:58 1:22
6K1M04 Low Pressure 6K1M04 6:47 8:53 2:06
8-Sep-18 1558
Mill distop menjaga isi bin tetap rendah, antisipasi red spot kiln. 16:10 17:18 1:08
Mill distop menjaga isi bin tetap rendah, antisipasi red spot kiln. 20:56 22:16 1:20
Mill distop menjaga isi bin tetap rendah, antisipasi red spot kiln. 4:35 5:52 1:17
6K1M04 Low Pressure 6K1M04 9:31 9:49 0:18
Mill distop menjaga isi bin tetap rendah, antisipasi red spot kiln. 11:45 13:10 1:25
9-Sep-18 1738
6K1M04 Low Pressure 6K1M04 17:12 17:50 0:38
6K1M04 Low Pressure 6K1M04 18:10 18:20 0:10
Mill distop menjaga isi bin tetap rendah, antisipasi red spot kiln. 23:38 1:05 1:27
10-Sep-18 Mill distop menjaga isi bin tetap rendah, antisipasi red spot kiln. 7:47 9:14 1:27
proses pengosongan isi BIN [ kiln stop patching] 18:00
11-Sep-18 kiln stop patching
12-Sep-18 kiln stop patching
13-Sep-18 kiln stop patching
14-Sep-18 kiln stop patching
15-Sep-18 kiln stop patching
14:57
16-Sep-18 827 vibrasi max 16:11 16:48 0:37
6K1A03 Over Current terganjal batu 23:36 23:55 0:19
Bin FC L11 dan L22 penuh 2:37 4:07 1:30
Bin FC L11 dan L22 penuh + mekanik tightening bolt + kiln stop 7:55 12:13 4:18
17-Sep-18 947
untuk operasional coal mill maka sieving dibuat 24-26% serta TM 14-
6K1M01N02P01 coal mill inlet press ext low2 + temperatur chamber 2 bhf tinggi 15:58 16%
19-Sep-18 1374 10:13
19-Sep-18 6K1A03 Over Current terganjal batu 17:30 17:49 0:19
20-Sep-18 1941 Bin FC L11 dan L22 penuh 4:12 5:21 1:09
Bin FC L11 dan L22 penuh 2:04 2:47 0:43
21-Sep-18
1828 Bin FC L11 dan L22 penuh 14:57 16:09 1:12
22-Sep-18 1891
23-Sep-18 1946 Bin FC L11 dan L22 penuh 11:31 12:41 1:10
24-Sep-18 1915 Bin FC L11 dan L22 penuh 10:26 11:30 1:04
25-Sep-18 1504 kiln stop 1:38 9:28 7:50
26-Sep-18 1899 Bin FC L11 dan L22 penuh 8:30 10:22 1:52
6K1A03 Over Current terganjal batu 13:33 13:53 0:20
27-Sep-18 1779 Bin FC L11 dan L22 penuh 4:21 5:31 1:10
Bin FC L11 dan L22 penuh 19:17 20:18 1:01
28-Sep-18 1836 Bin FC L11 dan L22 penuh 8:59 10:15 1:16
6K1P24 damper mill fan menutup sendiri cek dan test ulang open closenya 16:56 17:23 0:27
6K1A03 terganjal batu 21:58 22:17 0:19
29-Sep-18 1942
30-Sep-18 1938 6K1A03 Over Current terganjal batu 9:42 10:02 0:20

Oktober 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
6K1J03Z1 Produk Alarm > 2menit menyetop Filter Fan di reset langsung ready 20:11 20:45 0:34 Mohon interlock alat transport ke truk jika produk transport sudah
1-Oct-18 1728
6K1J03Z1 Transport di reset langsung ready 23:16 23:39 0:23 mengarah kesistem dihilangkan saja.
6K1J03Z1 produk transport di reset langsung ready 9:37 10:01 0:24
2-Oct-18 2098
6K1J03Z1 produk transport di reset langsung ready 17:02 17:25 0:23
6K1A03 Over Current terganjal batu 11:53 13:09 1:16
3-Oct-18 2002 6K1A03 Over Current terganjal batu 15:56 16:14 0:18
6K1A03 Over Current terganjal batu 16:22 16:40 0:18
jalur reject tersumbat 1:33 2:03 0:30
4-Oct-18 1972
6K1M07 not ready di reset langsung ready 23:28 23:45 0:17
Bin FC L11 dan L22 penuh 7:09 8:12 1:03
5-Oct-18 1943 6K1A03 Over Current terganjal batu 15:29 15:53 0:24
6K1A03 Over Current terganjal batu 17:31 17:54 0:23
6K1A03 Over Current terganjal batu 2:48 3:19 0:31
kiln stop 3:45 5:12 1:27
6-Oct-18 1907 6K1A03 Over Current terganjal batu 5:24 5:45 0:21
6K1A03 Over Current terganjal batu 22:23 22:42 0:19
6K1A03 Over Current terganjal batu 23:56 0:29 0:33
6K1A03 Over Current terganjal batu 2:17 2:36 0:19
6K1A03 Over Current terganjal batu 4:39 5:00 0:21
7-Oct-18 1879
reject tersumbat 5:28 5:52 0:24
kiln stop 18:56 21:28 2:32
6K1A03 Over Current terganjal batu 1:05 1:31 0:26
8-Oct-18 2152 6K1A02 Belt Conveyot Bus Fault 6:02 6:26 0:24
6K1A03 Over Current terganjal batu 22:58 23:19 0:21
6K1A03 Over Current terganjal batu 4:31 6:00 1:29
9-Oct-18 2161
6K1Mo5 Sealing Air Fan low Pressure Ketok2 saringan Inlet Fan 11:51 12:25 0:34
10-Oct-18 2280 Lancar
11-Oct-18 2255 6K1A03 Over Current terganjal batu 22:03 22:22 0:19
12-Oct-18 2158 6K1T01 bus fault di reset langsung ready 5:29 5:54 0:25
6K1A03 Over Current terganjal batu 18:26 18:47 0:21
6K1A03 Over Current terganjal batu 23:39 23:59 0:20
6K1A03 Over Current terganjal batu 13:01 13:18 0:17
13-Oct-18 2256 6K1A03 Over Current terganjal batu 17:10 17:26 0:16
6K1A03 Over Current terganjal batu 20:27 20:47 0:20
kiln stop 10:25 14:15 3:50
14/10/2018 1659 6K1A03 Over Current terganjal batu 14:43 15:02 0:19
kiln stop 16:08 19:08 3:00
15/10/2018 2406 6K1A03 Over Current terganjal batu 18:49 19:24 0:35
16/10/2018 2070 kiln stop 12:03 14:28 2:25
6K1A03 Over Current terganjal batu 2:20 2:44 0:24
6K1S22 Motion detector di reset langsung ready 4:13 4:35 0:22
17/10/2018 1718
kiln stop 9:34 13:24 3:50
kiln stop 15:48 18:01 2:13
6K1A03 Over Current terganjal batu 7:15 7:34 0:19
6K1A03 Over Current terganjal batu 8:07 8:27 0:20
18/10/2018 2281
6K1A03 Over Current terganjal batu 12:47 13:06 0:19
6K1A03 Over Current terganjal batu 17:09 17:28 0:19
6K1M03 coal mill drive mcb trip 20:10 20:29 0:19
19/10/2018
2018 6K1A03 Over Current terganjal batu 23:28 23:56 0:28
20/10/2018 2160 Over Current terganjal batu 8:45 9:05 0:20
Over Current terganjal batu 18:03 18:25 0:22
Over Current terganjal batu 22:49 23:08 0:19
21/10/2018 2313 Over Current terganjal batu 5:51 6:09 0:18
Over Current terganjal batu 7:48 8:07 0:19
Over Current terganjal batu 2:48 3:30 0:42
22/10/2018 2145 K1M01N02P01 inlet pressure open loop 16:15 17:25 1:10
20:50 21:08 0:18
23-oktober-2018 2296 6K1A03 Over Current terganjal batu 6:58 7:17 0:19
24-oktober-2018 1868 6K1A03 5:43 6:07 0:24
pmc 13:17 17:39 4:22
25-oktober-2018 Over Current terganjal batu 1:32 1:52 0:20
Over Current terganjal batu 8:16 8:33 0:17
Over Current terganjal batu 11:17 11:35 0:18
Over Current terganjal batu 17:50 18:09 0:19
26-oktober-2018 2045 pmc 7:48 10:45 2:57
27-oktober-2018 2311 Over Current terganjal batu 9:43 10:04 0:21
Over Current terganjal batu 12:46 13:08 0:22
28-oktober-2018 2182 Over Current terganjal batu 2:43 3:12 0:29
Over Current terganjal batu 20:45 21:29 0:44
Over Current terganjal batu 22:58 23:23 0:25
29-oktober-2018 2187 6K1M04 temp alarm di reset langsung ready 2:03 2:23 0:20
Over Current terganjal batu 2:45 3:04 0:19
Over Current terganjal batu 13:38 13:59 0:21
Over Current terganjal batu 21:37 22:20 0:43
blok di chute K1AO2 1:25 2:20 0:55
6K1A03 Over Current terganjal batu 5:30 5:48 0:18
30-oktober-2018 2057
6K1A03 Over Current terganjal batu 7:15 7:32 0:17
6K1A03 Over Current terganjal batu 16:19 17:04 0:45
6K1A03 Over Current terganjal batu 12:31 13:11 0:40
6K1A03 Over Current terganjal batu 13:48 14:07 0:19
31-oktober-2018 1897
6K1A03 Over Current terganjal batu + mekanik men cek kopleng 16:56 19:03 2:07
6K1A03 Over Current terganjal batu 22:47 23:05 0:18

Oktober 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production
6K1A03 Over Current terganjal batu 6:46 7:06 0:20
1-Nov-18 2293 6K1A03 Over Current terganjal batu 9:14 9:39 0:25
6K1A03 Over Current terganjal batu 17:28 17:52 0:24
2-Nov-18 kiln stop
3-Nov-18 kiln stop
4-Nov-18 585 6K1M01 vibrasi max 19:37 19:55 0:18
5-Nov-18 2257 6K1A03 Over Current terganjal batu 0:25 0:43 0:18
5-Nov-18 6K1A02 Block 2:16 2:43 0:27
5-Nov-18 6K1A03 Over Current terganjal batu 16:05 16:26 0:21
5-Nov-18 6K1A03 Over Current terganjal batu 17:02 17:22 0:20
6K1A03 Over Current terganjal batu 2:20 2:39 0:19
6-Nov-18 6K1A03 Over Current terganjal batu 8:13 8:33 0:20
2085 6K1A03 Over Current terganjal batu 9:51 10:13 0:22
bin full 9:22 10:02 0:40
kiln stop 10:53 12:10 1:17
7-Nov-18 1862
6K1A03 Over Current terganjal batu 13:24 13:43 0:19
bin full 19:33 20:46 1:13
6K1P17 Over Current terganjal plat 23:55 0:40 0:45
8-Nov-18 2114 6K1M05 dp rendah 4:36 4:59 0:23
PMC 8:19 9:35 1:16
6K1A03 Over Current terganjal batu 4:09 4:28 0:19
6K1A03 Over Current terganjal batu 13:37 13:56 0:19
9-Nov-18 1963
6K1A03 Over Current terganjal batu 14:32 14:57 0:25
6K1A03 Over Current terganjal batu 23:07 0:15 1:12
6K1A03 Over Current terganjal batu 7:36 7:54 0:18
6K1A03 Over Current terganjal batu 12:09 12:28 0:19
10-Nov-18 2144 6K1A03 Over Current terganjal batu 15:48 16:07 0:19
6K1A03 Over Current terganjal batu 21:12 21:30 0:18
6K1A03 Over Current terganjal batu 22:54 23:12 0:18
6K1A03 Over Current terganjal batu 9:22 9:42 0:20
6K1A03 Over Current terganjal batu 10:33 10:50 0:17
11-Nov-18 2080
6K1A03 Over Current terganjal batu 16:46 17:03 0:17
6K1A03 Over Current terganjal batu 18:24 18:49 0:25
6K1A03 Over Current terganjal batu 11:52 12:13 0:21
6K1A03 Over Current terganjal batu 12:39 12:57 0:18
6K1A03 Over Current terganjal batu 13:06 13:24 0:18
12-Nov-18
6K1A03 Over Current terganjal batu 13:25 13:43 0:18
6K1A03 Over Current terganjal batu 18:11 18:31 0:20
6K1A03 Over Current terganjal batu 21:29 21:51 0:22
6K1M04 thrust pad lw press [ di reset langsung ready] 7:22 7:44 0:22
13-Nov-18 2137 6K1A03 Over Current terganjal batu 11:36 11:52 0:16
6K1M07 trip di reset langsung ready 14:43 15:13 0:30
14-Nov-18 2335 6K1A03 Over Current terganjal batu 9:32 9:51 0:19
6K1A03 Over Current terganjal batu 2:03 2:24 0:21
6K1A03 Over Current terganjal batu 2:37 2:54 0:17
6K1A03 Over Current terganjal batu 4:55 5:19 0:24
15-Nov-18 2186 6K1A03 Over Current terganjal batu 5:42 6:01 0:19
6K1M04 temp alarm di reset langsung ready 9:22 9:41 0:19
6K1A03 Over Current terganjal batu 14:47 15:04 0:17
6K1A03 Over Current terganjal batu 22:25 22:45 0:20
6K1A03 Over Current terganjal batu 2:43 3:03 0:20
6K1A03 Over Current terganjal batu 12:18 12:36 0:18
16-Nov-18 2216 6K1A03 Over Current terganjal batu 14:15 14:33 0:18
6K1A03 Over Current terganjal batu 14:38 14:57 0:19
6K1A03 Over Current terganjal batu 15:55 16:14 0:19
kiln stop 6:21 10:41 4:20
6K1A03 Over Current terganjal batu 12:44 13:16 0:32
17-Nov-18 1078 6K1A03 Over Current terganjal batu 14:34 15:27 0:53
bin full 17:44 22:55 5:11
6K1A03 Over Current terganjal batu 23:15 23:33 0:18
6K1A03 Over Current terganjal batu 19:15 19:45 0:30
18-Nov-18 1997
6K1A03 Over Current terganjal batu 23:22 23:41 0:19
6K1A03 Over Current terganjal batu 2:47 3:06 0:19
6K1A02 blok di chute 3:43 4:23 0:40
6K1A03 Over Current terganjal batu 5:45 6:03 0:18
19-Nov-18 2123
6K1A03 Over Current terganjal batu 10:04 10:21 0:17
6K1A03 Over Current terganjal batu 15:52 16:12 0:20
6K1A03 Over Current terganjal batu 19:37 19:59 0:22
2171 6K1A03 Over Current terganjal batu 8:16 8:31 0:15
6K1A03 Over Current terganjal batu 8:49 9:11 0:22
20-Nov-18 6K1A03 Over Current terganjal batu 16:22 16:53 0:31
6K1A03 Over Current terganjal batu 17:31 17:45 0:14
6K1A03 Over Current terganjal batu 19:36 19:55 0:19
1148 kiln stop 7:35 18:03 10:28
6K1M01 vibrasi max diperbaiki el 18:17 18:42 0:25
21-Nov-18
6K1M01 vibrasi max diperbaiki el 18:50 19:12 0:22
6K1A03 Over Current terganjal batu 23:03 23:42 0:39
2172 6K1A03 Over Current terganjal batu 9:19 9:39 0:20
6K1A03 Over Current terganjal batu 13:07 13:25 0:18
22-Nov-18
6K1A03 Over Current terganjal batu 18:19 18:38 0:19
6K1A03 Over Current terganjal batu 22:06 22:33 0:27
product transport run time 7:39 7:59 0:20
Over Current terganjal batu + mekanik perbaikan K1M06
6K1A03 (bocor) 10:46 12:02 1:16
23-Nov-18 2116 6K1A03 Over Current terganjal batu 13:35 13:55 0:20
6K1A03 Over Current terganjal batu 14:56 15:15 0:19
6K1A03 Over Current terganjal batu 15:30 15:49 0:19
6K1A03 Over Current terganjal batu 20:19 20:37 0:18
6K1A03 Over Current terganjal batu 7:58 8:13 0:15
6K1A01 bus fault 10:33 10:51 0:18
24-Nov-18 2042 kiln stop 11:01 12:15 1:14
6K1A03 Over Current terganjal batu 13:38 13:57 0:19
6K1A03 Over Current terganjal batu 21:21 21:37 0:16
6K1A03 Over Current terganjal batu 0:34 0:58 0:24
6K1A03 Over Current terganjal batu 1:33 2:33 1:00
6K1A03 Over Current terganjal batu 4:55 5:13 0:18
25-Nov-18 2027
6K1A03 Over Current terganjal batu 5:16 5:35 0:19
6K1A03 Over Current terganjal batu 6:05 6:22 0:17
6K1A03 Over Current terganjal batu 8:47 9:26 0:39
6K1P11 Indikasi DP Tinggi 17:39 18:52 1:13
6K1P11 Indikasi DP Tinggi Reset Panel Lokal Di BHF baru Ok 19:17 19:35 0:18
26-Nov-18 2102
6K1A03 Over Current terganjal batu 19:59 20:17 0:18
6K1A03 Over Current terganjal batu 20:28 20:46 0:18
kiln stop 5:18 7:47 2:29
27-Nov-18 2093 6K1A03 Over Current terganjal batu 8:47 9:36 0:49
6K1A03 Over Current terganjal batu 0:50 1:09 0:19
6K1A03 Over Current terganjal batu 1:32 1:53 0:21
28-Nov-18 2165 6K1A03 Over Current terganjal batu 3:10 3:30 0:20
6K1A03 Over Current terganjal batu 5:15 5:34 0:19
6K1A03 Over Current terganjal batu 15:33 16:43 1:10
29-Nov-18 2303 6K1A03 Over Current terganjal batu 10:07 10:26 0:19
6K1A03 Over Current terganjal batu 12:19 12:44 0:25
6K1A03 Over Current terganjal batu 16:35 16:54 0:19
30-Nov-18 2181 6K1A03 Over Current terganjal batu 13:38 13:59 0:21
6K1A03 Over Current terganjal batu 18:07 18:34 0:27
6K1A03 Over Current terganjal batu 20:27 21:11 0:44

Desember 2018
Penyebab Action Dampak
Tanggal Production Note Operasional Inisiatif Ke Depan
Nomenclature Alat Permasalahan/ Issue Action Pada Saat Kejadian Dampak lain
Stop Start Durasi Loss Of Production

6K1A03 Over Current terganjal batu 0:06 0:27 0:21


1/12/2018 2122 mekanik ganti seal pipa hidrolik (bocor) 8:27 10:25 1:58
6K1A03 Over Current terganjal batu 16:14 16:36 0:22
6K1A03 Over Current terganjal batu 2:15 2:32 0:17
6K1A03 Over Current terganjal batu 9:50 10:08 0:18
2/12/2018 2169
6K1A03 Over Current terganjal batu 19:44 20:05 0:21
6K1A03 Over Current terganjal batu 22:31 22:49 0:18
6K1A03 Over Current terganjal batu 10:37 11:54 1:17
3/12/2018 1972
6K1A03 Over Current terganjal batu 12:07 12:27 0:20
bin full 0:46 4:27 3:41
4/12/2018
6K1A03 Over Current terganjal batu 4:55 5:14 0:19
6K1A03 Over Current terganjal batu 5:17 5:36 0:19
AFTAR ABNORMALITAS AREA KILN DAN COAL MILL

Periode : Agustus 2018


Check List
Shift (I, Status
Tanggal Nama Ka. Urusan Area Nama Personil Jam Dinas Personil No Equipment Nama Peralatan Abnormalitas Personil Mekanikal Personil Elinst Due Date Keterangan
II, III) (Ada/Tida (Open/Close)
k Ada)

Thursday, August 16, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada Blaster No 7 Blaster Tidak menembak (angin tidak masuk) Close mekanik ganti regulator
Thursday, August 16, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6W1A53 Cyclone Jalur ke kiln riser ducting masih blok Close diatasi pada saat kiln stop
Section 1,2,3 dan 4 String A dan Section 2 string B aeration box berisi
Thursday, August 16, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6W1A14M01 Air Slide Close
material
pengecekan hanya dapat dilakukan pada saat kiln stop
Thursday, August 16, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6W1A10 Air Slide Section 1 aeration box berisi material Close
Thursday, August 16, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6W1A07M2 Air Slide Section 1,2 aeration box berisi material Close
Thursday, August 16, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6J1U05M01 Drag chain perlu tambahan greess Close dilumasi ME
Thursday, August 16, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6j1U04M01 Drag chain perlu tambahan greess Close dilumasi ME
Thursday, August 16, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6W1B52Z1A01 Diverter gate Motor tidak ada Close diverter gate tidak dipergunakan lagi
Thursday, August 16, 2018 Novian Helmi, SE LP 643 Jafri 07:00 s/d 19:00 Ada 6W1W14M01 Lubrication unit Ada sedikit rembesan pada sambungan valve Close
Thursday, August 16, 2018 Novian Helmi, SE LP 661 Elfis Presley 07:00 s/d 19:00 Ada CO2 Injection Pembacaan pada layar tidak jelas Open Roni Safrianton Akan dillakukan penggantian panel oleh EL saat kiln stop
Thursday, August 16, 2018 Rahman Sudjana, ST LM 642 Zaiful Amran 19:00 s/d 07:00 Ada Blaster No 7 Blaster oil reguletor kosong sehinnga blaster tidak aktif Close mekanik ganti regulator
Thursday, August 16, 2018 Rahman Sudjana, ST LM 643 Jufri Ramadhan 19:00 s/d 07:00 Ada 6W1W14M01 Lubrication unit Ada sedikit rembesan pada sambungan valve Close
Thursday, August 16, 2018 Rahman Sudjana, ST LM 662 Hilman Rosman 19:00 s/d 07:00 Ada
Friday, August 17, 2018 Amrullah LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada Blaster No 7 Blaster Tidak menembak (angin tidak masuk) Close mekanik ganti regulator
Friday, August 17, 2018 Amrullah LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6W1A53 Cyclone Jalur ke kiln riser ducting masih blok Close diatasi pada saat bricking
Friday, August 17, 2018 Amrullah LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6W1A07M2 Air Slide Section 1,2 aeration box berisi material Close
Friday, August 17, 2018 Amrullah LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6J1U05M01 Drag chain perlu tambahan greess Close
Friday, August 17, 2018 Amrullah LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6j1U04M01 Drag chain perlu tambahan greess Close
Friday, August 17, 2018 Amrullah LP 643 Jafri 07:00 s/d 19:00 Ada 6W1W14M01 Lubrication unit Ada sedikit rembesan pada sambungan valve Close
Friday, August 17, 2018 Amrullah LP 661 Elfis Presley 07:00 s/d 19:00 Ada 6K1A01 Belt Feeder Sambungan belt robek Close di lem ME
Friday, August 17, 2018 Indra bahar LM 642 Eri Kurniadi 19:00 s/d 07:00 Ada Blaster No 7 Blaster Tidak menembak (angin tidak masuk) Close mekanik ganti regulator
Friday, August 17, 2018 Indra bahar LM 642 Eri Kurniadi 19:00 s/d 07:00 Ada 6J1U05M01 Drag chain perlu tambahan greess Close
Friday, August 17, 2018 Indra bahar LM 642 Eri Kurniadi 19:00 s/d 07:00 Ada 6j1U04M01 Drag chain perlu tambahan greess Close
Friday, August 17, 2018 Indra bahar LM 642 Eri Kurniadi 19:00 s/d 07:00 Ada 6H1H02 Rotary Blower dalam perbaikan ME Close ME tunggu spare
hoisting damper ditahan dengan taka [ daun damper sudah habis
Friday, August 17, 2018 Indra bahar LM 643 jafri 19:00 s/d 07:00 ada 6W1A72M01 Hosting Damper Open akan dilakuan perbaikan daun hoisting saat kiln breaking
sebahagian]
Friday, August 17, 2018 Indra bahar LM 661 Toni Ismanto 19:00 s/d 07:00 Ada 6K1A01 Belt Feeder Sambungan belt robek Close di lem ME
Friday, August 17, 2018 Indra bahar LM 662 Juldani 19:00 s/d 07:00 ada
Saturday, August 18, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada Blaster No 7 Blaster Tidak menembak (angin tidak masuk) Close mekanik ganti regulator
Saturday, August 18, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6J1U05M01 Drag chain perlu tambahan greess Close
Saturday, August 18, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6j1U04M01 Drag chain perlu tambahan greess Close
Saturday, August 18, 2018 Novian Helmi, SE LP 642 Roy Denny Zain 07:00 s/d 19:00 Ada 6H1H02 Rotary Blower Masih ada kebocoran Close
Saturday, August 18, 2018 Novian Helmi, SE LP 643 Jafri 07:00 s/d 19:00 Ada 6W1W14M01 Lubrication unit Ada sedikit rembesan pada sambungan valve Close
Saturday, August 18, 2018 Novian Helmi, SE LP 661 Elfis Presley 07:00 s/d 19:00 Ada 6K1A01 Belt Feeder Sambungan belt robek Close di tambah lem oleh ME
Sunday, August 19, 2018 Rahman Sujana, ST LP 662 Hilman Rosman 07:00 s/d 19:00 Ada
Sunday, August 19, 2018 Rahman Sujana, ST LP 642 Zaiful Amran 07:00 s/d 19:00 Ada
Sunday, August 19, 2018 Rahman Sujana, ST LP 643 Jufri Ramadhan 07:00 s/d 19:00 Ada 6W1W14M01 Lubrication unit Ada sedikit rembesan pada sambungan valve Close
Sunday, August 19, 2018 Novian Helmi, SE LM 642 Roy Denny Zain 19:00 s/d 07:00 Ada 6J1U05M01 Drag chain perlu tambahan greess Close dilumasi ME
Sunday, August 19, 2018 Novian Helmi, SE LM 642 Roy Denny Zain 19:00 s/d 07:00 Ada 6j1U04M01 Drag chain perlu tambahan greess Close dilumasi ME
Sunday, August 19, 2018 Novian Helmi, SE LM 643 Jafri 19:00 s/d 07:00 Ada 6W1W14M01 Lubrication unit Ada sedikit rembesan pada sambungan valve Close
Sunday, August 19, 2018 Novian Helmi, SE LM 661 Elfis Presley 19:00 s/d 07:00 Ada 6K1A01 Belt Feeder Sambungan belt robek Close di lem ME
Sunday, August 19, 2018 Novian Helmi, SE LM 662 Deswardi 19:00 s/d 07:00 Ada
Monday, August 20, 2018 Rahman Sujana, ST LP 662 Hilman Rosman 07:00 s/d 19:00 Ada
Monday, August 20, 2018 Rahman Sujana, ST LP 642 Zaiful Amran 07:00 s/d 19:00 Ada
Monday, August 20, 2018 Novian Helmi, SE LM 642 Roy Denny Zain 19:00 s/d 07:00 Ada 6J1U05M01 Drag chain perlu tambahan greess Close dilumasi ME
Monday, August 20, 2018 Novian Helmi, SE LM 642 Roy Denny Zain 19:00 s/d 07:00 Ada 6j1U04M01 Drag chain perlu tambahan greess Close dilumasi ME
Monday, August 20, 2018 Novian Helmi, SE LM 643 Jafri 19:00 s/d 07:00 Ada 6W1W14M01 Lubrication unit Ada sedikit rembesan pada sambungan valve Close
Monday, August 20, 2018 Novian Helmi, SE LM 661 Elfis Presley 19:00 s/d 07:00 Ada 6K1A01 Belt Feeder Sambungan belt robek Close
Tuesday, August 21, 2018 Rahman Sudjana, ST LP 642 Yudhi 19:00 s/d 15:00 Ada 6R1U05M01 Air Slide Aeration box berisi material Close
Tuesday, August 21, 2018 Rahman Sudjana, ST LP 642 Yudhi 19:00 s/d 15:00 Ada 6W1A07M1 Air Slide Aeration box berisi material Close
Tuesday, August 21, 2018 Indra bahar Shift II 642 Zaiful Amran 15:00 s/d 22:00 Ada 6R1U05M01 Air Slide Aeration box berisi material Close
Tuesday, August 21, 2018 Indra bahar Shift III 642 Eri Kurniadi 22:00 s/d 07:00 Ada 6R1U05M01 Air Slide Aeration box berisi material Close
Tuesday, August 21, 2018 Indra bahar Shift III 642 Eri Kurniadi 22:00 s/d 07:00 Ada 6W1A09 Air Slide Aeration box berisi material Close
Tuesday, August 21, 2018 Indra bahar Shift III 661/661 22:00 s/d 07:00 Ada 6K1M01 atox mill double plat pengaman grease yg dibelakang roller lepas Close ME minta stop 2 jam setelah isi bin penuh
Wednesday, August 22, 2018 Rahman Sudjana, ST Shift I 642 Yudhi 19:00 s/d 15:00 Ada 6R1U05M01 Air Slide Aeration box berisi material Close
Wednesday, August 22, 2018 Indra bahar Shift III Eri Kurniadi 15:00 s/d 22:00 Ada 6W1A14M01 Air Slide Aeration box berisi material Close
pengecekan hanya dapat dilakukan pada saat kiln stop
Wednesday, August 22, 2018 Indra bahar Shift III Eri Kurniadi 15:00 s/d 22:00 Ada 6R1U05M01 Air Slide Aeration box berisi material Close
Wednesday, August 22, 2018 Indra bahar Shift III Eri Kurniadi 15:00 s/d 22:00
Wednesday, August 22, 2018 Indra bahar Shift III 661/662 Toni Ismanto/Hilman
Thursday, August 23, 2018 Novian Helmi, SE Shift I 642 Roy Denny Zain 19:00 s/d 15:00 Ada 6W1B54 Cyclone Pendulum ducting bottom masih belum ada Close jamilus akan dipasang pada saat kiln breaking
Thursday, August 23, 2018 Novian Helmi, SE Shift I 642 Roy Denny Zain 19:00 s/d 15:00 Ada 6J1U05M01 Drag chain perlu tambahan greess Close
Thursday, August 23, 2018 Novian Helmi, SE Shift I 642 Roy Denny Zain 19:00 s/d 15:00 Ada 6j1U04M01 Drag chain perlu tambahan greess Close
Thursday, August 23, 2018 Novian Helmi, SE Shift I 642 Roy Denny Zain 19:00 s/d 15:00 Ada 6W1B52Z1A01 Diverter gate Motor tidak ada close Diverter gate tidak dipergunakan lagi
Thursday, August 23, 2018 Novian Helmi, SE Shift I 643 Jafri 19:00 s/d 15:00 Ada 6W1W14M01 Lubrication unit Ada sedikit rembesan pada sambungan valve Close sudah diperbaiki ME
Thursday, August 23, 2018 Novian Helmi, SE Shift I 661 Elfis Presley 19:00 s/d 15:00 Ada 6K1A01 Belt Feeder Sambungan belt robek Close di tambah lem oleh ME
Thursday, August 23, 2018 Rahman Sudjana, ST Shift I 642 Yudhi 15:00 s/d 22:00 Ada 6R1U05M01 Air Slide Aeration box berisi material Close
pengecekan hanya dapat dilakukan pada saat kiln stop
Thursday, August 23, 2018 Rahman Sudjana, ST Shift I 642 Yudhi 15:00 s/d 22:00 Ada 6W1A10 Air Slide Aeration box berisi material Close
Thursday, August 23, 2018 Rahman Sudjana, ST Shift III 642 Zaiful Amran 22:00 s/d 07:00 Ada
Thursday, August 23, 2018 Rahman Sudjana, ST Shift III 643 Jufri Ramadhan 22:00 s/d 07:00 Ada 6U1P22 Fan Bearing Abnormal Close akan di cek ME shift pagi
642 Roy Denny Zain
bearing rusak serta akan diganti ME[ sedang cek stok bearing di
Friday, August 24, 2018 Indra bahar Shift I 643 Jafri 19:00 s/d 15:00 Ada 6U1P22 Fan Bearing Abnormal Close Sabrimen 25-Aug-18
gudang ]
661/662 Deswardi
Novian Helmi, SE Shift III 642 Zaiful Amran 22:00 s/d 07:00 Ada
Friday, August 24, 2018 Novian Helmi, SE Shift III 643 Jufri Ramadhan 22:00 s/d 07:00 Ada 6U1P22 Fan Bearing Abnormal Close akan di cek ME shift pagi
Saturday, August 25, 2018 Amrullah Shift I 642 Eri Kurniadi 19:00 s/d 15:00 Ada 6H1H05Z01 Discharge Gate Tidak mau membuka Close On progress perbaikan
Saturday, August 25, 2018 Amrullah Shift I 643 Andi Warsah 19:00 s/d 15:00 Ada 6U1P22 Fan Bearing Abnormal Close akan di cek ME shift pagi
Discharge Gate segmen
Saturday, August 25, 2018 Shift II 642 Roy Denny Zain 15:00 s/d 22:00 Ada 6H1H05Z01 Tidak mau membuka Close akan dilakukan pengecekan atuator oleh ME pagi/ harian
A
Saturday, August 25, 2018 Shift II 643 Jafri 15:00 s/d 22:00 Ada 6U1P22 Fan Bearing Abnormal Close akan dilakukan penggantian bearing oleh ME
Saturday, August 25, 2018 Indra bahar LM 661/662 Toni Ismanto/Deswardi 19:00 s/d 07:00 Ada
Discharge Gate segmen
Saturday, August 25, 2018 Shift III 642 Yudhi 22:00 s/d 07:00 Ada 6H1H05Z01 Tidak mau membuka Close Arif Rusman Fajri Hakim akan dilakukan pengecekan atuator oleh ME pagi/ harian
A
Saturday, August 25, 2018 Shift III 643 Dasril 22:00 s/d 07:00 Ada 6U1P22 Fan Bearing Abnormal Close akan dilakukan penggantian bearing oleh ME
Sunday, August 26, 2018 Amrullah Shift I 642 Roy Denny Zain 19:00 s/d 15:00 Ada 6H1H05Z01 Discharge Gate Tidak mau membuka Close actuator masih dicek mekanik
Sunday, August 26, 2018 Amrullah Shift I 643 Andi Warsah 19:00 s/d 15:00 Ada 6U1P22 Fan Bearing Abnormal Close akan di cek ME shift pagi
Sunday, August 26, 2018 Novian Helmi, SE Shift II 642 Roy Denny Zain 15:00 s/d 22:00 Ada 6H1H05Z01 Discharge Gate Tidak mau membuka Close actuator masih dicek mekanik
Sunday, August 26, 2018 Novian Helmi, SE Shift II 643 Jafri 15:00 s/d 22:00 Ada 6U1P22 Fan Bearing Abnormal Close akan di cek ME shift pagi
Sunday, August 26, 2018 Shift II 643 Jafri 15:00 s/d 22:00 Ada 6U1P22 Fan Bearing Abnormal Close akan dilakukan penggantian bearing oleh ME
LM 661/662 Toni Ismanto/Deswardi 19:00 s/d 07:00 Ada
Discharge Gate segmen
Sunday, August 26, 2018 Indra bahar Shift III 642 Yudhi 22:00 s/d 07:00 Ada 6H1H05Z01 Tidak mau membuka Close Arif Rusman Ahmad Ilham akan dilakukan pengecekan atuator oleh ME pagi/ harian
A
Shift III 643 Dasril 22:00 s/d 07:00 Ada 6U1P22 Fan Bearing Abnormal Close akan dilakukan penggantian bearing oleh ME
Tuesday, August 28, 2018 Amrullah Shift II 642 Eri Kurniadi 15:00 s/d 22:00 Ada 6H1H05Z01 Discharge Gate Tidak mau membuka Close actuator masih dicek mekanik
Tuesday, August 28, 2018 Amrullah Shift II 643 Jufri/Jafri 15:00 s/d 22:00 Ada 6U1P22 Fan Bearing Abnormal Close akan di cek ME shift pagi
Tuesday, August 28, 2018 Novian Helmi, SE Shift III 642 Roy Denny Zain 22:00 s/d 07:00 Ada 6H1H05Z01 Discharge Gate Tidak mau membuka Close actuator masih dicek mekanik
Tuesday, August 28, 2018 Novian Helmi, SE Shift III 643 Jafri 22:00 s/d 07:00 Ada 6U1P22 Fan Bearing Abnormal Close akan di cek ME shift pagi
actuator dibawa mekanik ke bawah untuk pengecekan seal
642 Yudhi 19:00 s/d 15:00 6H1H05Z01 Discharge Gate Tidak mau membuka Close
indikasi bocor.
Wednesday, August 29, 2018 Indra bahar Shift I Ada
643 Dasril 07:00 s/d 19:00 6U1P22 Fan Bearing Abnormal Close Arif Rusman Ahmad Ilham 27-Aug-18 ME ganti bearing
661/662 Ricardo/Deswardi 07:00 s/d 19:00
actuator dibawa mekanik ke bawah untuk pengecekan seal
642 Yudhi 19:00 s/d 15:00 6H1H05Z01 Discharge Gate Tidak mau membuka Close
indikasi bocor.
Wednesday, August 29, 2018 Indra bahar Shift I Ada
643 Dasril 07:00 s/d 19:00 Arif Rusman Ahmad Ilham
661/662 Ricardo/Deswardi 07:00 s/d 19:00
actuator dibawa mekanik ke bawah untuk pengecekan seal
642 Zaiful Amran 15:00 s/d 22:00 6H1H05Z01 Discharge Gate Tidak mau membuka Close
indikasi bocor.
Wednesday, August 29, 2018 Rahman Sudjana, ST Shift II Ada
643 Jufri Ramadhan 19:00 s/d 07:00 6U1P22 Fan Bearing Abnormal Close Arif Rusman Ahmad Ilham 27-Aug-18 ME ganti bearing
661/662 Tri Febrianto/ Juldani 19:00 s/d 07:00
Thursday, August 30, 2018 Amrullah Shift III 642 Eri Kurniadi 22:00 s/d 07:00
Sering terbentuk Jengger di ujung burner (Sekarang Intensitas Sudah
Thursday, August 30, 2018 Amrullah Shift III 643 Jufri Ramadhan 19:00 s/d 07:00 Ada 6W1V95M01 Burner Carriage Close akan dillakukan modifikasi pada burner saat kiln stop
berkurang)
Thursday, August 30, 2018 Novian Helmi, SE Shift I 642 yudhi 07:00 s/d 19:00 Ada 6H1H05Z01 Discharge Gate Tidak mau membuka Close Sabrimen penyebab karena posisi as terbalik
Thursday, August 30, 2018 643 Jafri 07:00 s/d 19:00 Arif Rusman Ahmad Ilham
Indra bahar Shift II Ada
Thursday, August 30, 2018 661/662 Ricardo/Hilman 07:00 s/d 19:00
642 Zaiful Amran 19:00 s/d 07:00 Ada
Friday, August 31, 2018 Rahman Sudjana, ST LM
643 Deswardi 19:00 s/d 07:00 Ada Arif Rusman Ahmad Ilham
tidak maximal menarik debu jatuhan klinker dari crusher ke pan conv
643 Jafri 07:00 s/d 19:00 6U1P01 JPF Close arif rusman rencana upgrade JPF
J03 dan J04
Indra bahar Shift II 642 Yudhi 07:00 s/d 19:00 Ada
Saturday, September 1, 2018
661/662 Elfis/Hilman 07:00 s/d 19:00 Ada
642 Zaiful Amran 19:00 s/d 07:00 Ada
Saturday, September 1, 2018 Rahman Sudjana, ST LM 643 Deswardi 19:00 s/d 07:00 Arif Rusman Ahmad Ilham
Ada
661/662 Tri Febrianto/ Juldani 19:00 s/d 07:00 6W1V33M01 Rotary Blower spare rotor belum ada Close 31-Dec-18 ME tunggu spare
Sunday, September 2, 2018 Shift III 642 Yudhi 22:00 s/d 07:00 Ada
Indra bahar 643 Jafri 07:00 s/d 19:00 Ada Arif Rusman M.torik
661/662 Ricardo/Hilman 07:00 s/d 19:00 Ada
Monday, September 3, 2018 Amrullah Shift I 642 Eri Kurniadi 07:00 s/d 15:00 Ada Ferizal Dedi M Daris
Monday, September 3, 2018 Amrullah LP 643 Andi Warsah 07:00 s/d 19:00 Ada
Monday, September 3, 2018 Amrullah LP 661/662 Toni Isman/Juldani 07:00 s/d 19:00 Ada
642 Yudhi 22:00 s/d 07:00 Ada Arif Rusman ahmad ilham
Tuesday, September 4, 2018 Indra bahar Shift III 643 Dasril 19:00 s/d 07:00 Ada Arif Rusman ahmad ilham
661/662 Ricardo/Hilman 19:00 s/d 07:00 Ada Arif Rusman ahmad ilham
Tuesday, September 4, 2018 Rahman Sujana, ST Shift I 661/662 Toni Isman/Jufri Ramadhan 07:00 s/d 19:00 Ada 6W1V33M01 Rotary Blower spare rotor belum ada Close Sabrimen 31-Dec-18 On progress, expert supervisi sudah datang
642 Zaiful Amran 19:00 s/d 07:00 Ada
643 Andi Warsah 07:00 s/d 19:00 Ada 6U1P02M01 Fan Vibrasi dan Penggantian V-Belt Close Erik
Thursday, August 30, 2018 Novian Helmi, SE Shift III 643 Jafri 22:00 s/d 07:00 Ada 6W1 Sheel Kiln Red Spot Close Red spot meteran 4,5 & 6
Tuesday, September 18, 2018 Indra bahar Shift III 19:00 s/d 07:00 6K1P14 screw conv daunnya ada yang bengkok Open jamilus Akan dikerjakan saat kiln stop breaking
Monday, September 24, 2018 Amrullah Shift III 661 19:00 s/d 07:00 6K1J05Z1 Slide gate Daunnya tidak bisa membuka/menutup sempurna Close Sabrimen Roni Safrianton bersihkan jalur udara untuk selenoit valve
penambahan chek hole sejajar sliding inlet kiln 2 buah dan modifikasi
Sunday, October 7, 2018 Novian Helmi, SE 642 Roy Denny Zain check hole inlet kiln 2 buah check hole di samping sliding inlet kiln untuk mengatasi Open jamilus akan dikerjakan waktu kiln stop
clogging yang sering muncul
pemindahan letak sensor ke posisi sebelah agar posisi letak sensor
Sunday, October 7, 2018 Novian Helmi, SE 643 Jafri 6W1K02 temp. udara sekunder Open sabrimen Roni Safrianton akan dikerjakan waktu kiln stop
sekarang bisa digunakan untuk membersihkan jengger

modifikasi ducting hisap JPF 6K1P51 dari bin 6K1L21 menjadi lebih
curam, karena kondisi sekarang ducting sering tersumbat FC (bahkan
ducting hisap JPF dari
Sunday, October 7, 2018 Novian Helmi, SE 661 Elfis Presley 6K1P51 hingga 1 kali 24 jam jika tak dibersihkan bisa tersumbat). ditambah Open sabrimen akan dikerjakan waktu kiln stop
bin 6K1P51
lagi kadar air FC yang dinaikkan hinnga 15% sehingga potensi
tersumbat semakin besar.

compensator vibrating
Monday, October 8, 2018 Indra bahar 642 Zaiful Amran 07:00 s/d 15:00 6J1Ko1 bocor Open efdiresmen akan dikerjakan waktu kiln stop
gct section B
Saringan diketok pressure naiik sedikit.ME shift pagi tgl 09-10-
Tuesday, October 9, 2018 Amrullah 661 Toni Ismanto 19:00 s/d 07:00 6K1M05 Sealing air fan Pressure rendah dan menyetop Mill < 18 mBar Close sabrimen
2018 lanjut bersihkan saringan { pressure sudah terbaca 24 mbar}
Thursday, October 18, 2018 Indra bahar 642 Yudhi 15:00 s/d 22:00 6J1Ko1 Kompensator gct Kompensator puncak gct bagian timur bocor Open efdiresmen akan dikerjakan waktu kiln stop
Thursday, October 18, 2018 Rahman Sujana, ST Shift III 661/662 Tri Febrianto/ Dasril 19:00 s/d 07:00 Ada - - - - -
Shift III 642 Zaiful Amran 22:00 s/d 07:00 Ada - -
19:00 s/d 07:00 Ada 6U1P01 JPF Bag filter sobek Open
Shift III 643 Jufri Ramadhan 6U1P11 JPF Bag filter sobek Open
6U1P21 JPF Bag filter sobek Open
Saturday, October 20, 2018 Indra bahar Shift III 643 Andi Warsah 19:00 s/d 07:00 Ada plat segment outlet kiln banyak yang lepas Open Sabrimen akan dikerjakan waktu kiln stop
usulan untuk membuat sliding plat yang diarahkan ke silo klinker dari
bawah chute U1JO3/U1JO4 arah timur agar bila seandainya terjadi
Monday, October 22, 2018 Novian Helmi, SE Shift III 643 japri 19:00 s/d 07:00 Ada 6U1J03 dan 6U1J04 pan conveyor open sabrimen bisa dikerjakan tidak waktu kiln stop
block, maka material akan masuk ke dalam silo (tidak melimpah
keluar)
Saturday, October 27, 2018 Indra bahar Shift II 661 Toni Ismanto 19:00 s/d 07:00 Ada 6K1j05Z1 slide gate selenoid valve bocor sehingga tidak kuat untuk buka gate Close Arif Rusman akan di cek ME harian senen [ senen diperbaiki ME]
Sunday, October 28, 2018 Amrullah Shift I 07:00 s/d 15:00 Ada
Sunday, October 28, 2018 Novian Helmi Shift II 15:00 s/d 22:00 Ada
Sunday, October 28, 2018 Indra Bahar Shift III 22:00 s/d 07:00 Ada
Monday, October 29, 2018 Amrullah Shift I 07:00 s/d 15:00 Ada
Monday, October 29, 2018 Novian Helmi Shift II 15:00 s/d 22:00 Ada
Monday, October 29, 2018 Indra Bahar Shift III 22:00 s/d 07:00 Ada
Tuesday, October 30, 2018 Rahman Sudjana Shift I 07:00 s/d 15:00 Ada
Tuesday, October 30, 2018 Amrullah Shift II 15:00 s/d 22:00 Ada
Tuesday, October 30, 2018 Novian Helmi Shift III 22:00 s/d 07:00 Ada
Wednesday, October 31, 2018 Rahman Sudjana Shift I 07:00 s/d 15:00 Ada
Wednesday, October 31, 2018 Amrullah Shift II 15:00 s/d 22:00 Ada
Wednesday, October 31, 2018 Novian Helmi Shift III 22:00 s/d 07:00 Ada
Thursday, November 1, 2018 Indra Bahar Shift I 07:00 s/d 15:00 Ada
Thursday, November 1, 2018 Rahman Sudjana Shift II 15:00 s/d 22:00 Ada
Thursday, November 1, 2018 Amrullah Shift III 22:00 s/d 07:00 Ada
Friday, November 2, 2018 Indra Bahar Shift I 07:00 s/d 15:00 Ada
Friday, November 2, 2018 Rahman Sudjana Shift II 15:00 s/d 22:00 Ada
Friday, November 2, 2018 Amrullah Shift III 22:00 s/d 07:00 Ada
Saturday, November 3, 2018 Novian Helmi Shift I 07:00 s/d 15:00 Ada
Saturday, November 3, 2018 Indra Bahar Shift II 15:00 s/d 22:00 Ada
Saturday, November 3, 2018 Rahman Sudjana Shift III 22:00 s/d 07:00 Ada
Sunday, November 4, 2018 Novian Helmi Shift I 07:00 s/d 15:00 Ada
Sunday, November 4, 2018 Indra Bahar Shift II 15:00 s/d 22:00 Ada
Sunday, November 4, 2018 Rahman Sudjana Shift III 22:00 s/d 07:00 Ada
Monday, November 5, 2018 Amrullah Shift I 07:00 s/d 15:00 Ada
Monday, November 5, 2018 Novian Helmi Shift II 15:00 s/d 22:00 Ada
Monday, November 5, 2018 Indra Bahar Shift III 22:00 s/d 07:00 Ada
Tuesday, November 6, 2018 Amrullah Shift I 07:00 s/d 15:00 Ada 6K1J05Z1 Slide gate shell piston bocor CLOSE
Tuesday, November 6, 2018 Novian Helmi Shift II 15:00 s/d 22:00 Ada
Tuesday, November 6, 2018 Indra Bahar Shift III 22:00 s/d 07:00 Ada
Wednesday, November 7, 2018 Rahman Sudjana Shift I 07:00 s/d 15:00 Ada
Wednesday, November 7, 2018 Amrullah Shift II 15:00 s/d 22:00 Ada
Wednesday, November 7, 2018 Novian Helmi Shift III 22:00 s/d 07:00 Ada
Thursday, November 8, 2018 Rahman Sudjana Shift I 07:00 s/d 15:00 Ada
Thursday, November 8, 2018 Amrullah Shift II 15:00 s/d 22:00 Ada
Thursday, November 8, 2018 Novian Helmi Shift III 22:00 s/d 07:00 Ada
Friday, November 9, 2018 Indra Bahar Shift I 07:00 s/d 15:00 Ada
Friday, November 9, 2018 Rahman Sudjana Shift II 15:00 s/d 22:00 Ada
Friday, November 9, 2018 Amrullah Shift III 22:00 s/d 07:00 Ada
Saturday, November 10, 2018 Indra Bahar Shift I 07:00 s/d 15:00 Ada
Saturday, November 10, 2018 Rahman Sudjana Shift II 15:00 s/d 22:00 Ada
Saturday, November 10, 2018 Amrullah Shift III 22:00 s/d 07:00 Ada
Tuesday, November 13, 2018 Amrullah Shift I 07:00 s/d 15:00 Ada
Tuesday, November 13, 2018 Amrullah Shift II 15:00 s/d 22:00 Ada
Tuesday, November 13, 2018 Indra bahar Shift III 22:00 s/d 07:00 Ada
Wednesday, November 14, 2018 Amrullah Shift I 07:00 s/d 15:00 Ada
Wednesday, November 14, 2018 Novian Helmi Shift II 15:00 s/d 22:00 Ada
Wednesday, November 14, 2018 Indra bahar Shift III 22:00 s/d 07:00 Ada
Thursday, November 15, 2018 Rahman Sudjana Shift I 07:00 s/d 15:00 Ada
Thursday, November 15, 2018 Amrullah Shift II 15:00 s/d 22:00 Ada
Thursday, November 15, 2018 Novian Helmi Shift III 22:00 s/d 07:00 Ada
Friday, November 16, 2018 Rahman Sudjana Shift I 07:00 s/d 15:00 Ada
Friday, November 16, 2018 Amrullah Shift II 15:00 s/d 22:00 Ada
Friday, November 16, 2018 Novian Helmi Shift III 22:00 s/d 07:00 Ada
Saturday, November 17, 2018 Indra bahar Shift I 07:00 s/d 15:00 Ada
Saturday, November 17, 2018 Rahman Sudjana Shift II 15:00 s/d 22:00 Ada
Saturday, November 17, 2018 Amrullah Shift III 22:00 s/d 07:00 Ada
Sunday, November 18, 2018 Indra bahar Shift I 07:00 s/d 15:00 Ada
Sunday, November 18, 2018 Rahman Sudjana Shift II 15:00 s/d 22:00 Ada
Sunday, November 18, 2018 Amrullah Shift III 22:00 s/d 07:00 Ada
Monday, November 19, 2018 Novian Helmi Shift I 07:00 s/d 15:00 Ada
Monday, November 19, 2018 Indra bahar Shift II 15:00 s/d 22:00 Ada
Monday, November 19, 2018 Rahman Sudjana Shift III 22:00 s/d 07:00 Ada
Tuesday, November 20, 2018 Novian Helmi Shift I 07:00 s/d 15:00 Ada
Tuesday, November 20, 2018 Indra bahar Shift II 15:00 s/d 22:00 Ada
Tuesday, November 20, 2018 Rahman Sudjana Shift III 22:00 s/d 07:00 Ada
Wednesday, November 21, 2018 Amrullah Shift I 07:00 s/d 15:00 Ada
Wednesday, November 21, 2018 Novian Helmi Shift II 15:00 s/d 22:00 Ada
Wednesday, November 21, 2018 Indra bahar Shift III 22:00 s/d 07:00 Ada
Thursday, November 22, 2018 Amrullah Shift I 07:00 s/d 15:00 Ada
Thursday, November 22, 2018 Novian Helmi Shift II 15:00 s/d 22:00 Ada
Thursday, November 22, 2018 Indra bahar Shift III 22:00 s/d 07:00 Ada
Friday, November 23, 2018 Rahman Sudjana Shift I 07:00 s/d 15:00 Ada
Friday, November 23, 2018 Amrullah Shift II 15:00 s/d 22:00 Ada
Friday, November 23, 2018 Novian Helmi Shift III 22:00 s/d 07:00 Ada
Saturday, November 24, 2018 Rahman Sudjana Shift I 07:00 s/d 15:00 Ada
Saturday, November 24, 2018 Amrullah Shift II 15:00 s/d 22:00 Ada
Saturday, November 24, 2018 Novian Helmi Shift III 22:00 s/d 07:00 Ada
Sunday, November 25, 2018 Indra bahar Shift I 07:00 s/d 15:00 Ada
Sunday, November 25, 2018 Rahman Sudjana Shift II 15:00 s/d 22:00 Ada
Sunday, November 25, 2018 Amrullah Shift III 22:00 s/d 07:00 Ada
Monday, November 26, 2018 Indra bahar Shift I 07:00 s/d 15:00 Ada
Monday, November 26, 2018 Rahman Sudjana Shift II 15:00 s/d 22:00 Ada
Monday, November 26, 2018 Amrullah Shift III 22:00 s/d 07:00 Ada
Tuesday, November 27, 2018 Novian Helmi Shift I 07:00 s/d 15:00 Ada
Tuesday, November 27, 2018 Indra bahar Shift II 15:00 s/d 22:00 Ada
Tuesday, November 27, 2018 Rahman Sudjana Shift III 22:00 s/d 07:00 Ada
Wednesday, November 28, 2018 Novian Helmi Shift I 07:00 s/d 15:00 Ada
Wednesday, November 28, 2018 Indra bahar Shift II 15:00 s/d 22:00 Ada
Wednesday, November 28, 2018 Rahman Sudjana Shift III 22:00 s/d 07:00 Ada
Thursday, November 29, 2018 Amrullah Shift I 07:00 s/d 15:00 Ada
Thursday, November 29, 2018 Novian Helmi Shift II 15:00 s/d 22:00 Ada
Thursday, November 29, 2018 Indra bahar Shift III 22:00 s/d 07:00 Ada