2
ITEM PENGERJAAN
NO
A 5
B 10
C 8
D 5
E 6
F 5
G 4
H 5
I 3
J 2
(JAM)
19 20 21 22 23 24 25 26 27 28 29 30
ITEM PENGERJAAN
NO
REALISASI
DEVIASI
WAKTU
KODE HARGA SATUAN BOBOT (%)
(JAM)
1 2 3 4
A 5 5,000 0.0609607412826 0.012 0.012 0.012 0.012
B 10 3,000,000 36.576444769568
C 8 40,000 0.4876859302609
D 5 3,000,000 36.576444769568
E 6 1,200,000 14.630577907827
F 5 132,000 1.609363569861
G 4 500,000 6.0960741282614
H 5 40,000 0.4876859302609
I 3 270,000 3.2918800292612
J 2 15,000 0.1828822238478
8,202,000 100 0.012 0.012 0.012 0.012
0 0.012 0.024 0.037 0.049
0.012 0.024 0.037 0.049
0 0.012 0.037 0.073 0.122
0 -0.012 -0.037 -0.073
WAKTU (JAM)
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
0.012
3.658 3.658 3.658 3.658 3.658 3.658 3.658 3.658 3.658 3.658
0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061
7.315 7.315 7.315 7.315 7.315
2.438 2.438 2.438 2.438 2.438
0.322 0.322 0.322 0.322 0.322
0.012 3.719 3.719 3.719 3.719 3.719 3.719 3.719 3.719 3.658 3.658 10.08 10.08 10.08 10.08 10.08
0.061 3.78 7.498 11.22 14.94 18.65 22.37 26.09 29.81 33.47 37.13 47.2 57.28 67.35 77.43 87.5
0.061 2.78 2.78 2.78 2.78 2.78 2.78
0.183 2.963 5.743 8.523 11.3 14.08 16.86
-0.122 0.817 1.755 2.694 3.632 4.571 5.51
21 22 23 24 25 26 27 28 29 30
2.438
A 4 5 6 A 4
B 9 10 14 B 9
C 7 8 9 C 7
D 4 5 6 D 4
E 5 6 13 E 5
F 4 5 6 F 4
G 3 4 11 G 3
H 4 5 6 H 4
I 2 3 7 I 2
J 1 2 3 J 1
WAKTU
Realistis Pesimis
Te S V(te)
4 (m) (b)
5 6 5 0.333333 0.166667
10 14 10.5 0.833333 0.416667
8 9 8 0.333333 0.166667
5 6 5 0.333333 0.166667
6 13 7 1.333333 0.666667
5 6 5 0.333333 0.166667
4 11 5 1.333333 0.666667
5 6 5 0.333333 0.166667
3 7 3.5 0.833333 0.416667
2 3 2 0.333333 0.166667
∑ 56 6.333333 3.166667