REKAPITULASI

ENGINEER ESTIMATE (EE)


KEGIATAN :

PEKERJAAN :

LOKASI :
T.A :

KODE JUMLAH HARGA

A PEKERJAAN PERSIAPAN Rp -

B PEKERJAAN TANAH DAN PONDASI Rp -

C PEKERJAAN PASANGAN DAN PLASTERAN Rp -

D PEKERJAAN BETON BERTULANG Rp -

E PEKERJAAN LANTAI Rp -

F PEKERJAAN TANGGA Rp -

G PEKERJAAN PINTU, JENDELA DAN KUNCI Rp -

H PEKERJAAN INSTALASI LISTRIK Rp -

I PEKERJAAN SANITASI DALAM DAN LUAR GEDUNG Rp -

J PEKERJAAN PLAFOND dan ATAP Rp -

K PEKERJAAN PENGECATAN Rp -

JUMLAH Rp -
PPN 10% Rp -
JUMLAH TOTAL Rp -
DIBULATKAN Rp -

Terbilang :

Disusun Oleh,
Konsultan Perencana,
PT. ARISTA GEMILANG KONSULINDO

( …........................................)
Team Leader
PT. ARISTA GEMILANG KONSULINDO

KODE ( …........................................)
JUMLAH HARGA
Team Leader
ENGINEER ESTIMATE (EE)

KEGIATAN :

PEKERJAAN :
LOKASI :
T.A :

JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SAT. KODE ANALISA HARGA SATUAN
SATUAN
1 2 3 4 5 6 7=3x6

A PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan/Lokasi m2 Rp -
2 Pengukuran / Pemasangan Bouplank m1 Rp -

SUB JUMLAH PEKERJAAN PERSIAPAN Rp -


B PEKERJAAN TANAH DAN PONDASI
1 a Galian Tanah Pondasi Foot Plat m3 Rp -
b Urugan Kembali Galian Foot Plat m3 Rp -
c Lapisan Pasir Urug Bawah Pondasi m3 Rp -

2 a Pengerjaan 1 titik pancang ulin 10/10 dan kalang ulin ttk Rp -

3 a Galian Tanah Pondasi Menerus m3 Rp -


b Urugan Kembali Galian Pondasi Menerus m3 Rp -
c Lapisan Pasir Urug Bawah Pondasi m3 Rp -
d Pas. Batu Kosong / Aanstamping m3 Rp -
e Pas. Pondasi Batu Gunung 1 : 4 m3 Rp -

SUB JUMLAH PEKERJAAN TANAH DAN PONDASI Rp -


C PEKERJAAN PASANGAN DAN PLASTERAN
a Pasangan batu bata 1 : 2 1 PC : 2 PP m2 Rp -
b Plasteran batu bata 1 : 2 1 PC : 2 PP m2 Rp -
c Pasangan batu bata 1 : 4 1 PC : 4 PP m2 Rp -
d Plasteran batu bata 1 : 4 1 PC : 4 PP m2 Rp -
f Acian Dinding m2 Rp -

SUB JUMLAH PEKERJAAN PASANGAN DAN PLASTERAN Rp -


D PEKERJAAN BETON BERTULANG
1 Pekerjaan Pondasi Foot Plat 1,20 x 1,20
- Beton K-250 m3 Rp -
- Besi Tulangan Pokok D16 -150 kg Rp -
- Bekisting + Perawatan Beton m2 Rp -

2 Pekerjaan Sloof 30/40


- Beton K-250 m3 Rp -
- Besi Tulangan Pokok D16 kg Rp -
- Tul pinggang ø 12 kg Rp -
- Besi Tulangan Sengkang ø 8 - 10 cm kg Rp -
- Bekisting + Perawatan Beton m2 Rp -

3 Pekerjaan Kolom K1 40/40


- Beton K-250 m3 Rp -
- Besi Tulangan Pokok D16 kg Rp -
- Besi Tulangan Sengkang ø 8 - 15 cm kg Rp -
- Bekisting + Perawatan Beton m2 Rp -

4 Pekerjaan Balok Lantai 30/40


- Beton K-250 m3 Rp -
- Besi Tulangan Pokok D16 kg Rp -
- Tul pinggang ø 12 kg Rp -
- Besi Tulangan Sengkang ø 8 - 15 cm kg Rp -
- Bekisting + Perawatan Beton m2 Rp -

5 Pekerjaan Kolom K2 13/13


- Beton K-175 m3 Rp -
- Besi Tulangan Pokok ø 12 kg Rp -
- Besi Tulangan Sengkang ø 8 - 15 cm kg Rp -
- Bekisting + Perawatan Beton m2 Rp -

6 Pekerjaan Balok Ringbalk 13/20


- Beton K-175 m3 Rp -
- Besi Tulangan Pokok ø 12 kg Rp -
- Besi Tulangan Sengkang ø 6 - 15 cm kg Rp -
- Bekisting + Perawatan Beton m2 Rp -

7 Pekerjaan Plat Lantai


- Beton K-250 m3 Rp -
- Besi Tulangan Pokok ø 10 kg Rp -
- Bekisting + Perawatan Beton m2 Rp -

SUB JUMLAH PEKERJAAN BETON BERTULANG Rp -


JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SAT. KODE ANALISA HARGA SATUAN
SATUAN
1 2 3 4 5 6 7=3x6

E PEKERJAAN LANTAI
1 Timbunan Tanah Bawah Lantai m3 Rp -
2 Urugan Pasir Bawah Lantai m3 Rp -
3 Lantai Granite Tile 60 x 60 cm m2 Rp -
4 Keramik Uk. 20 x 20 cm (Km/Wc) m2 Rp -
5 Keramik Uk. 20 x 25 cm (Dinding Km/Wc) m2 Rp -
6 Keramik Uk. 40 x 40 cm (Meja Pantry) m2 Rp -
7 Keramik Uk. 40 x 40 cm (Tangga) m2 Rp -

SUB JUMLAH PEKERJAAN LANTAI Rp -


F PEKERJAAN TANGGA
1 Plat Tangga
- Beton K-250 m3 Rp -
- Besi Tulangan Pokok ø 12 kg Rp -
- Bekisting + Perawatan Beton m2 Rp -

2 Anak Tangga
- Beton K-250 m3 Rp -
- Besi Tulangan Pokok ø 12 kg Rp -
- Bekisting + Perawatan Beton m2 Rp -

3 Plat Bordes
- Beton K-250 m3 Rp -
- Besi Tulangan Pokok ø 12 kg Rp -
- Bekisting + Perawatan Beton m2 Rp -

4 Relling Tangga
- Besi Hollow m1 Rp -

SUB JUMLAH PEKERJAAN TANGGA Rp -


G PEKERJAAN PINTU, JENDELA DAN KUNCI
1 Pas. Pintu P1
- Kusen Pintu m3 Rp -
- Daun Pintu m2 Rp -
- Kusen Ventilasi m3 Rp -
- Papan Ventilasi/Jelusi m3 Rp -
- Kunci Pintu (Standar) Buah Rp -
- Engsel Pintu Buah Rp -

2 Pas. Pintu P2 (Km/Wc)


- Kusen Pintu m3 Rp -
- Daun Pintu m2 Rp -
- Kusen Ventilasi m3 Rp -
- Papan Ventilasi/Jelusi m3 Rp -
- Kunci Pintu (Km/Wc) Buah Rp -
- Engsel Pintu Buah Rp -

3 Pas. Jendela J1
Kusen Jendela m3 Rp -
Daun Jendela m2 Rp -
Kaca 5 mm m2 Rp -
Hak Angin Buah Rp -
Engsel Jendela Buah Rp -
Grendel Jendela Buah Rp -

4 Jendela J2
- Kusen Jendela m3 Rp -
- Daun Jendela m2 Rp -
- Kaca 5 mm m2 Rp -
- Hak Angin Buah Rp -
- Engsel Jendela Buah Rp -
- Grendel Jendela Buah Rp -

SUB JUMLAH PEKERJAAN PINTU, JENDELA DAN KUNCI Rp -


H PEKERJAAN INSTALASI LISTRIK
1 Intalasi Listrik Ttk Rp -
2 Lampu Saving Energi 18 Watt Bh Rp -
3 Saklar Tunggal Bh Rp -
4 Saklar Ganda Bh Rp -
5 Stop Kontak Bh Rp -
6 Pasang Box KWH Meter Unit Rp -

SUB JUMLAH PEKERJAAN INSTALASI LISTRIK Rp -


JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SAT. KODE ANALISA HARGA SATUAN
SATUAN
1 2 3 4 5 6 7=3x6

I PEKERJAAN SANITASI DALAM DAN LUAR GEDUNG


1 Pemasangan Closet Duduk Buah Rp -
2 Pemasangan Wastafel Set Rp -
3 Pemasangan Kran Air Buah Rp -
4 Pemasangan Floor Drain Buah Rp -
5 Pemasangan Instalasi Air Bersih Ls Rp -
6 Pemasangan Instalasi Air Kotor Ls Rp -
7 Septic Tank dan Peresapan Unit Rp -

SUB JUMLAH PEKERJAAN SANITASI DALAM DAN LUAR GEDUNG Rp -


J PEKERJAAN PLAFOND dan ATAP
1 Rangka Plafond hollow 1x40.40.2mm, modul 60 x 60 cm m2 Rp -
2 Plafon Gypsum 9 mm m2 Rp -
3 List Plafond Gypsum m1 Rp -
4 Plafond lambrisering kayu, tebal 9 mm (Area Luar) m2 Rp -
5 List Kayu Profil m1 Rp -
6 Pasang Kuda - Kuda Baja Ringan m2 Rp -
7 Pemasangan Genteng Aspal Bitumen m2 Rp -
8 Pasang Nok/Bubungan m1 Rp -
9 Pasang Talang Jurai m1 Rp -
10 Pasang Listplank m1 Rp -

SUB JUMLAH PEKERJAAN PLAFOND dan ATAP Rp -


K PEKERJAAN PENGECATAN
1 Cat Dinding Luar m2 Rp -
2 Cat Dinding Dalam m2 Rp -
3 Cat Plafond - m2 Rp -
4 Cat Kusen, Daun Pintu / Jendela / Papan Jelusi m2 Rp -

SUB JUMLAH PEKERJAAN PENGECATAN Rp -


BACK UP DATA VOLUME
0
NO PERHITUNGAN VOLUME VOLUME SAT. REFFERENSI GAMBAR

A. PEKERJAAN PERSIAPAN
1. Pembersihan Lapangan
Lebar = 14.00 m
Panjang = 12.00 m
Luas = (PxL)
= ( 14 x 12 ) 168.00 M²

2. Pemasangan Bouwplank
Lebar = 16.00 m
Panjang = 14.00 m
Keliling = 2 (P + L )
= 2 x ( 16 + 14 ) 60.00 M

B. PEKERJAAN TANAH DAN PONDASI


1.a Galian Tanah Pondasi Foot Palt
Tinggi = 0.60 m
Lebar = 1.20 m
Panjang = 1.20 m
Jumlah = 16.00 unit

Volume = ( P x L x T ) x Unit
= (1.20 x 1.20 x 0.6) x 16 13.82 M³

1.b Urugan Kembali Pondasi Foot Plat


Volume = 3/4 x Volume Galian Tapak
= 3/4 x Vol. Galian 10.37 M³

1.c Lapisan Pasir / Pasir Alas


Tinggi = 0.05 m
Lebar = 1.20 m
Panjang = 1.20 m
Jumlah = 12.00 Unit

Volume = ( P x L x T ) x Unit
= ( 1,2 x 1,2 x 0,05 ) x 12 Unit 0.86 M³

2.a Pengerjaan 1 titik pancang ulin 10/10 dan kalang ulin


Jumlah per FP = 9 ttk
Jumlah FP = 12 buah

Volume = Jumlah Per FP x Jumlah FP 108.00 Ttk

3.a. Galian Pondasi Menerus


Tinggi = 0.85 m
Lebar = 0.80 m
Panjang = 74.40 m

Volume = (PxLxT)
= (40.80 x 0.80 x 0.85) 50.59 M³

3.b. Urugan Kembali Pondasi Menerus


Volume = 1/4 x Volume Galian Menerus
= 1/4 x 50.59 12.65 M³

3.c. Lapisan Pasir / Pasir Alas


Tinggi = 0.05 m
Lebar = 1.00 m
Panjang = 74.40 m

Volume = (PxLxT)
= ( 74.40 x 1,00 x 0,05 ) 3.72 M³

3.d. Aanstamping
Tinggi = 0.10 m
Lebar = 1.00 m
Panjang = 74.40 m

Volume = (PxLxT)
= ( 74.40 x 1,00 x 0,1) 7.44 M³
NO PERHITUNGAN VOLUME VOLUME SAT. REFFERENSI GAMBAR

3.e. Pas. Batu Gunung


Tinggi = 0.80 m
Lebar a = 0.30 m
Lebar b = 0.80 m
Panjang = 74.40 m

Volume = (( a + b )/2 x P x T ))
= (( 0,30 + 0,80)/2 x 74.40 x 0,80) 32.74 M³

C. PEKERJAAN PASANGAN DAN PLASTERAN


a Pas. Dinding Bata 1 : 2
Tinggi = 0.50 m
Panjang = 53.02 m

Luas = (PxT)
= ( 53.02 x 0.40 ) 26.51 M²

b Plesteran Dinding Bata 1 : 2


= ( Vol. Pas Bata 1:2 ) x 2 53.02 M²

c Pas. Dinding Bata 1 : 4


Tinggi = 3.10 m
Panjang = 43.60 m

Luas = (PxT )
= (53.02 x 3.20 ) 135.16 M²

b Plesteran Dinding Bata 1 : 2


= ( Vol. Pas Bata 1:4 ) x 2 270.32 M²

D. PEKERJAAN BETON BERTULANG


BETON
Foot Plat 1,2 x 1,2
Tinggi = 0.60 m
Lebar = 1.20 m
Panjang = 1.20 m
Jumlah = 16.00 Unit

Volume = (PxLxT)
= ( 1.20 x 1.20 x 0.60 ) x 16 13.82 M³

Sloof (30/40)
Tinggi = 0.40 m
Lebar = 0.30 m
Panjang = 75.36 m

Volume = (PxLxT)
= ( 60.00 x 0.30 x 0.40 ) 9.04 M³

Kolom K1 (40/40)
Tinggi = 3.60 m
Lebar = 0.40 m
Panjang = 0.40 m
Jumlah = 16.00 Unit

Volume = ( P x L x T ) x Unit
= ( 0.40 x 0.40 x 3.60 ) x 16 9.22 M³

Balok Lantai (30/40)


Tinggi = 0.40 m
Lebar = 0.30 m
Panjang = 75.36 m

Volume = (PxLxT)
= ( 75.36 x 0.30 x 0.40 ) 9.04 M³

Kolom KP (13/13)
Tinggi = 3.60 m
Lebar = 0.13 m
Panjang = 0.13 m
Jumlah = 18.00 Unit

Volume = ( P x L x T ) x Unit
= ( 0.13 x 0.13 x 3.60 ) x 18 1.10 M³
NO PERHITUNGAN VOLUME VOLUME SAT. REFFERENSI GAMBAR

Balok RB (13/20)
Tinggi = 0.20 m
Lebar = 0.13 m
Panjang = 75.36 m

Volume = (PxLxT)
= ( 75.36 x 0.13 x 0.20 ) 1.96 M³

Plat Lantai
Tinggi = 0.12 m
Lebar = 10.00 m
Panjang = 12.00 m

Volume = (PxLxT)
= ( 12 x 10 x 0.12 ) 14.40 M³

E PEKERJAAN LANTAI
1 Tanah timbunan dibawah lantai dalam ruangan
Tinggi = 0.40 m
Lebar = 8.98 m
Panjang = 12.00 m
Jumlah = 1.00 Unit

Luas = ( P x L x T ) x unit
= ( 8.98 x 12.00 x 0.10 ) x 1 43.10 M³

2 Urugan Pasir Bawah dalam Ruangan


Tinggi = 0.10 m
Lebar = 8.98 m
Panjang = 12.00 m
Jumlah = 1.00 Unit

Luas = ( P x L x T ) x unit
= ( 8.98 x 12.00 x 0.10 ) x 1 10.78 M³

3 Pas. Lantai Granite Tile 60 x 60 cm dalam Ruangan Lt 1 & 2


Lebar = 8.98 m
Panjang = 12.00 m
Jumlah = 1.00 Unit

Luas = ( P x L) x unit
= ( 8.98 x 12.00 ) x 1 107.76 M²

3 Pas. Lantai Granite Tile 60 x 60 cm Lt. 2 (Overllap)


Lebar = 1.00 m
Panjang = 8.00 m

Luas = (PxL)
= (8x1) 8.00 M²

7 Pas. Keramik 40/40 tangga


Lebar = 1.89 m
Panjang = 3.87 m

Luas = ( P x L)
= ( 3.87 x 1.89) 7.31 M²

4 Pas. Keramik Lantai 20 x 20 (Km/Wc)


Lebar = 2.00 m
Panjang = 2.00 m
Jumlah = 3.00 Unit

Luas = ( P x L) x unit
= ( 2.00 x 2.00 ) x 3 12.00 M²

5 Pas. Keramik Dinding 20 x 25 (Km/Wc)


Lebar = 2.00 m
Panjang = 2.00 m
Jumlah = 12.00 Sisi

Luas = ( P x L) x unit
= ( 2.00 x 2.00 ) x 12 48.00 M²
NO PERHITUNGAN VOLUME VOLUME SAT. REFFERENSI GAMBAR

6 Pas. Keramik Meja Pantry 40 x 40


Lebar = 0.48 m
Panjang = 1.46 m
Jumlah = 6.00 Unit

Luas = ( P x L) x unit
= ( 1.46 x 0.48 ) x 6 4.20 M²

F PEKERJAAN TANGGA
Plat Tangga
Tinggi = 0.12 m
Lebar = 2.00 m
Panjang = 4.87 m

Volume = (PxLxT)
= ( 2 x 4.87 x 0.12 ) 1.17 M³

Anak Tangga Tangga


Tinggi = 0.12 m
Lebar = 0.40 m
Panjang = 1.00 m
Jumlah = 30.00 Buah

Volume = (PxLxT)
= ( 1.00 x 0.40 x 0.12 ) x 30 1.44 M³

Plat Bordes
Tinggi = 0.12 m
Lebar = 1.11 m
Panjang = 2.00 m

Volume = (PxLxT)
= ( 2 x 1.11 x 0.12 ) 0.27 M³

Railing Tangga
Volume = (4.82 x 2) + (3.77 x 2) + 2.10 19.28 M

PEKERJAAN PINTU, JENDELA DAN KUNCI


Kusen Untuk Lantai 1
Kusen Pintu P1
Panjang = 5.36 m
Lebar = 0.13 m
Tinggi = 0.06 m
Jumlah = 3.00 unit

Luas = ( P x L x T ) x unit
= ( 5,36 x 0,13 x 0,06 ) x 3 0.13 M³

Daun Pintu P1
Panjang = 2.10 m
Lebar = 0.80 m
Jumlah = 3.00 unit

Luas = ( P x L ) x unit
= ( 2.10 x 0.80 ) x 4 5.04 M²

Engsel Pintu P1
Buah = 3.00 Bh
Jumlah = 3.00 unit

Luas = ( Bh ) x unit
= (3)x4 9.00 Bh

Kunci Pintu P1
Buah = 1.00 Bh
Jumlah = 3.00 unit

Luas = ( Bh ) x unit
= (1)x3 3.00 Bh

Kusen Ventilasi P1
Panjang = 3.08 m
Lebar = 0.13 m
Tinggi = 0.06 m
Jumlah = 3.00 unit

Luas = ( P x L x T ) x unit
= ( 3.08 x 0,13 x 0,06 ) x 3 0.07 M³
NO PERHITUNGAN VOLUME VOLUME SAT. REFFERENSI GAMBAR

Papan Ventilasi P1
Panjang = 6.24 m
Lebar = 0.13 m
Tinggi = 0.02 m
Jumlah = 3.00 unit

Luas = ( P x L x T ) x unit
= ( 6.24 x 0,13 x 0,02 ) x 3 0.05 M³

Kusen Pintu P2
Panjang = 5.27 m
Lebar = 0.13 m
Tinggi = 0.06 m
Jumlah = 3.00 unit

Luas = ( P x L x T ) x unit
= ( 5,27 x 0,13 x 0,06 ) x 3 0.12 M³

Daun Pintu P2
Panjang = 2.10 m
Lebar = 0.70 m
Jumlah = 3.00 unit

Luas = ( P x L ) x unit
= ( 2.10 x 0.80 ) x 4 4.41 M²

Engsel Pintu P2
Buah = 3.00 Bh
Jumlah = 3.00 unit

Luas = ( Bh ) x unit
= (3)x4 9.00 Bh

Kunci Pintu P2
Buah = 1.00 Bh
Jumlah = 3.00 unit

Luas = ( Bh ) x unit
= (1)x3 3.00 Bh

Kusen Ventilasi Km/WC


Panjang = 2.70 m
Lebar = 0.13 m
Tinggi = 0.06 m
Jumlah = 3.00 unit

Luas = ( P x L x T ) x unit
= ( 2.7 x 0,13 x 0,06 ) x 3 0.06 M³

Papan Ventilasi Km/Wc


Panjang = 4.16 m
Lebar = 0.13 m
Tinggi = 0.02 m
Jumlah = 3.00 unit

Luas = ( P x L x T ) x unit
= ( 4.16 x 0,13 x 0,02 ) x 3 0.03 M³

Kusen Jendela J1
Panjang = 5.20 m
Lebar = 0.13 m
Tinggi = 0.06
Jumlah = 3.00 unit

Luas = ( P x L x T ) x unit
= ( 4,60 x 0,13 x 0,06 ) x 3 0.12 M²

Daun Jendela J1
Panjang = 1.80 m
Lebar = 0.60 m
Jumlah = 3.00 unit

Luas = ( P x L ) x unit
= ( 1.80 x 0.60 ) x 8 3.24 M²
NO PERHITUNGAN VOLUME VOLUME SAT. REFFERENSI GAMBAR

Kaca Jendela J1
Panjang = 1.68 m
Lebar = 0.57 m
Jumlah = 3.00 unit

Luas = ( P x L ) x unit
= ( 1.68 x 0.57 ) x 3 2.87 M²

Engsel Jendela J1
Buah = 4.00 Bh
Jumlah = 3.00 unit

Luas = ( Bh ) x unit
= (4)x4 12.00 Bh
Grendel Jendela J1
Buah = 2.00 Bh
Jumlah = 3.00 unit

Luas = ( Bh ) x unit
= (2)x3 6.00 Bh

Hak Angin J1
Buah = 2.00 Bh
Jumlah = 3.00 unit

Luas = ( Bh ) x unit
= (2)x3 6.00 Bh

Kusen Ventilasi J1
Panjang = 4.50 m
Lebar = 0.13 m
Tinggi = 0.06
Jumlah = 4.00 unit

Luas = ( P x L x T ) x unit
= ( 4.50x 0,13 x 0,06 ) x 4 0.14 M³

Papan Ventilasi J1
Panjang = 8.32 m
Lebar = 0.13 m
Tinggi = 0.02 m
Jumlah = 4.00 unit

Luas = ( P x L x T ) x unit
= ( 8.32 x 0,13 x 0,02 ) x 4 0.09 M³

Kusen Jendela J2
Panjang = 6.72 m
Lebar = 0.13 m
Tinggi = 0.06 m
Jumlah = 3.00 unit

Luas = ( P x L x T ) x unit
= ( 6.72 x 0,13 x 0,06 ) x 3 0.16 M²

Daun Jendela J2
Panjang = 1.70 m
Lebar = 0.70 m
Jumlah = 6.00 unit

Luas = ( P x L ) x unit
= (1.70 x 0.70 ) x 6 7.14 M²

Kaca Jendela J2
Panjang = 1.50 m
Lebar = 0.50 m
Jumlah = 6.00 unit

Luas = ( P x L ) x unit
= ( 1.50 x 0.50 ) x 6 4.50 M²

Engsel Jendela J2
Buah = 2.00 Bh
Jumlah = 6.00 unit

Luas = ( Bh ) x unit
= (6)x4 12.00 Bh
NO PERHITUNGAN VOLUME VOLUME SAT. REFFERENSI GAMBAR

Grendel Jendela J2
Buah = 1.00 Bh
Jumlah = 6.00 unit

Luas = ( Bh ) x unit
= (1)x6 6.00 Bh

Hak Angin
Buah = 2.00 Bh
Jumlah = 6.00 unit

Luas = ( Bh ) x unit
= (2)x6 12.00 Bh

J PEKERJAAN ATAP DAN PLAFOND


PEKERJAAN ATAP
1 Rangka Kuda-kuda Baja Ringan C-75
Panjang = 14.00 m
Lebar = 3.85 m
Jumlah = 2.00 Unit

Volume = (PxL)
= ( 14.00 x 3.85 ) x 2 107.80 M2

2 Penutup Atap Genteng Aspal Bitumen


Panjang = 14.00 m
Lebar = 4.02 m
Jumlah = 2.00 Unit

Volume = (PxL)
= ( 14 x 4.02 ) x 2 112.56 M2

3 Bubungan
Panjang = 14.00 m
Jumlah = 1.00 Unit

Volume = (PxU)
= ( 20 ) x 1 14.00 M¹

4 Talang Jurai
Panjang = 3.20 m
Jumlah = 4.00 Unit

Volume = (PxU)
= ( 3.45 x 4) 12.80 M¹

5 Papan Listplank Uk. 3/30 cm


Panjang = 88.10 m
Jumlah = 1.00 Unit

Volume = (PxU)
= ( 55 ) x 1 88.10 M¹

PEKERJAAN PLAFOND
1 Rangka Plafond hollow 1x40.40.2mm, modul 60 x 60 cm
Bangunan Utama
Panjang = 6.00 m
Lebar = 3.60 m
Jumlah = 3.00 Unit

Volume = ( P x L ) x unit
= ( 6.00 x 3.60 ) x 3 64.80 M²

Teras
Panjang = 8.00 m
Lebar = 4.00 m
Jumlah = 1.00 Unit

Volume = ( P x L ) x unit
= ( 8.00 x 4.00 ) x 1 32.00 M²

Tritisan
Panjang = 14.00 m
Lebar = 12.00 m
Jumlah = 2.00 Unit

Volume = ( P x L ) x unit
= ( 8.00 + 4.00 ) x 1 52.00 M²
Volume Total Rangka Palfond 148.80 M²
NO PERHITUNGAN VOLUME VOLUME SAT. REFFERENSI GAMBAR

3 List Plafond Gypsum


Panjang = 28.00 m
Jumlah = 3.00 Unit
Volume = ( P ) x Unit
= ( 18.40 ) x 4 84.00 M²

4 List Kayu
Panjang = 76.00 m
Jumlah = 4.00 Unit
Volume = ( P ) x Unit
= ( 18.40 ) x 4 304.00 M²

H PEKERJAAN INSTALASI LISTRIK


Lampu Saving Energi 18 Watt 24.00 Bh

Saklar Tunggal 9.00 Bh

Saklar dauble 3.00 Bh

Stop Kontak 12.00 Bh

K PEKERJAAN PENGECATAN
Cat Dinding Bata Luar 84.00 M²

Cat Kolom Lt 1
Panjang = 3.60 m
Lebar = 0.40 m
Jumlah = 11.00 Unit

Volume = ( P x L ) x Unit
= ( 3,60 x 0,40 ) x 11 15.84 M²

Cat Balok Lantai


Panjang = 25.60 m
Lebar = 0.30 m
Jumlah = 10.00 Unit

Volume = ( P x L ) x Unit
= ( 25,60 x 0,30 ) x 10 76.80 M²

Total Volume Pengecatan Luar 176.64 M²

Cat Dinding Bata Dalam 84.00 M²

Cat Kolom Dalam


Panjang = 3.60 m
Lebar = 2.60 m
Jumlah = 12.00 Unit

Volume = ( P x L ) x Unit
= ( 7,20 x 0,40 ) x 12 112.32 M²

Cat Plafond
Panjang = m
Lebar = m
Jumlah = Unit

Volume = ( P x L ) x Unit
= - M²

Total Volume Pengecatan Dalam 196.32 M²

Cat Kusen
Cat Kusen Pintu P1
Panjang = 5.24 m
Lebar = 0.25 m
Jumlah = 4.00 unit

Luas = ( P x L) x unit
= ( 5,24 x 0,25 ) x 4 5.24 M²

Cat Daun Pintu P1


Panjang = 4.20 m
Lebar = 1.60 m
Jumlah = 4.00 unit

Luas = ( P x L) x unit
= ( 4.20 x 1.60) x 4 26.88 M²
NO PERHITUNGAN VOLUME VOLUME SAT. REFFERENSI GAMBAR

Cat Kusen Ventilasi P1


Panjang = 2.84 m
Lebar = 0.25 m
Jumlah = 4.00 unit

Luas = ( P x L) x unit
= ( 2.84 x 0.25) x 4 2.84 M²

Cat Papan Ventilasi P1


Panjang = 6.24 m
Lebar = 0.17 m
Jumlah = 4.00 unit

Luas = ( P x L ) x unit
= ( 6.24 x 0,17) x 4 4.24 M²

Cat Kusen Jendela J1


Panjang = 5.08 m
Lebar = 0.25 m
Jumlah = 4.00 unit

Luas = ( P x L) x unit
= ( 5,08 x 0,25 ) x 4 5.08 M²

Cat Daun Jendela J1


Panjang = 3.40 m
Lebar = 0.22 m
Jumlah = 4.00 unit

Luas = ( P x L) x unit
= ( 2.80 x 0,22 ) x 4 2.99 M²

Cat Kusen Ventilasi J1


Panjang = 4.26 m
Lebar = 0.25 m
Jumlah = 4.00 unit

Luas = ( P x L) x unit
= ( 4.26 x 0,25 ) x 4 4.26 M²

Cat Papan Ventilasi J1


Panjang = 8.32 m
Lebar = 0.17 m
Jumlah = 4.00 unit

Luas = ( P x L) x unit
= ( 8.32 x 0.17) x 4 5.66 M²

Cat Kusen Jendela J2


Panjang = 7.28 m
Lebar = 0.25 m
Jumlah = 4.00 unit

Luas = ( P x L) x unit
= ( 7.28 x 0,25 ) x 4 7.28 M²

Cat Daun Jendela J2


Panjang = 4.00 m
Lebar = 0.22 m
Jumlah = 4.00 unit

Luas = ( P x L) x unit
= ( 2.80 x 0,22 ) x 4 3.52 M²

Cat Kusen Ventilasi J2


Panjang = m
Lebar = m
Jumlah = unit

Luas = ( P x L) x unit
= ( 4.76 x 0,25 ) x 4 - M²

Cat Papan Ventilasi J2


Panjang = m
Lebar = m
Jumlah = unit

Luas = ( P x L) x unit
= ( 12.48 x 0.17) x 4 - M²
Total Volume Cat Kusen, Pintu, Jendela dan Ventilasi Lt 1 67.99 M²
NO PERHITUNGAN VOLUME VOLUME SAT. REFFERENSI GAMBAR
PERHITUNGAN BESI DAN BEKISTING
0
NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

PERHITUNGAN Panjang balok untuk 1 m3


Sloof SL ( 0.30 x 0.40 ) M = 1/( b x h)
= 8.333 m'
Jumlah Tul. Pokok = 6.00 Batang a. Pembesian untuk 1 m beton adalah
3

Ø Tul. Pokok = 16.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 2.00 Batang Berat besi Ø 16, = 78.9120 kg
Ø Tul. Pinggang = 12.00 mm
Ø Tul. Begel = 8.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.150 M Berat besi Ø 12, = 14.796 kg
Luas Permukaan Papan = 0.80 M2
3. Tulangan Begel Besi Ø 8,
Panjang begel = 1.250 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 55.56 ± -------> 55.00 Btg
56 btg
40
Berat besi Ø 8, = Byk begel x Pjg begel x 0.006165 x dia.2
= 27.619 kg
30
4. Papan mal = Pjg balok untuk 1 m3 beton x luas permukaan papan
Sloof 30/ 40 = 6.667 m2

Total Berat Besi = 121.33 Kg/M3


Papan mal 1 x Pakai = 6.667 M2/M3

PERHITUNGAN Panjang balok untuk 1 m3


Balok Lantai ( 0.30 x 0.40 ) M = 1/( b x h)
= 8.333 m'
Jumlah Tul. Pokok = 6.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 16.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 2.00 Batang Berat besi Ø 16, = 78.9120 kg
Ø Tul. Pinggang = 12.00 mm
Ø Tul. Begel = 8.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.100 M Berat besi Ø 12, = 14.796 kg
Luas Permukaan Papan = 0.86 M2
3. Tulangan Begel Besi Ø 8,
Panjang begel = 1.250 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 83.33 ± -------> 83.00 Btg
84 btg

40 Berat besi Ø 8, = Byk begel x Pjg begel x 0.006165 x dia.2


= 41.429 kg

30 4. Papan mal = Pjg balok untuk 1 m3 beton x luas permukaan papan


= 7.167 m2
Balok Lt-2 30/ 40
Total Berat Besi = 135.14 Kg/M3
Papan mal 1 x Pakai = 7.167 M2/M3

PERHITUNGAN Panjang balok untuk 1 m3


Kolom K1 ( 0.30 x 0.30 ) M = 1/( b x h)
= 11.11 m'
Jumlah Tul. Pokok = 12.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 16.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = - Batang Berat besi Ø 16, = 210.4320 kg
Ø Tul. Pinggang = - mm
Ø Tul. Begel = 8.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.120 M Berat besi Ø 0, = - kg
Luas Permukaan Papan = 1.20 M2
3. Tulangan Begel Besi Ø 8,
Panjang begel = 1.050 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 92.59 ± -------> 92.00 Btg
93 btg

30 Berat besi Ø 8, = Byk begel x Pjg begel x 0.006165 x dia.2


= 38.5288 kg

30 4. Papan mal = Pjg balok untuk 1 m3 beton x luas permukaan papan


= 13.33 m2
Kolom30/ 30
Total Berat Besi = 248.96 Kg
Papan mal 1 x Pakai = 13.333 M2
NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3
PERHITUNGAN Panjang balok untuk 1 m3
Kolom K2 ( 0.13 x 0.13 ) M = 1/( b x h)
= 59.17 m'
Jumlah Tul. Pokok = 4.00 Batang a. Pembesian untuk 1 m beton adalah
3

Ø Tul. Pokok = 12.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = - Batang Berat besi Ø 12, = 210.1207 kg
Ø Tul. Pinggang = - mm
Ø Tul. Begel = 6.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.150 M Berat besi Ø 0, = - kg
Luas Permukaan Papan = 0.52 M2
3. Tulangan Begel Besi Ø 6,
Panjang begel = 0.370 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 394.48 ± -------> 394.00 Btg
395 btg
13
Berat besi Ø 6, = Byk begel x Pjg begel x 0.006165 x dia.2
13 = 32.4365 kg
Kolom13/ 13
4. Papan mal = Pjg balok untuk 1 m3 beton x luas permukaan papan
= 30.77 m2 -------> 50%

Total Berat Besi = 242.56 Kg


Papan mal 2 x Pakai = 15.385 M2

PERHITUNGAN Panjang balok untuk 1 m3


Balok RB ( 0.13 x 0.20 ) M = 1/( b x h)
= 38.46 m'
Jumlah Tul. Pokok = 4.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 12.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = - Batang Berat besi Ø 12, = 136.5785 kg
Ø Tul. Pinggang = - mm
Ø Tul. Begel = 6.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.150 M Berat besi Ø 0, = - kg
Luas Permukaan Papan = 0.53 M2
3. Tulangan Begel Besi Ø 6,
Panjang begel = 0.510 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 256.41 ± -------> 257.00 Btg
257 btg

Berat besi Ø 6, = Byk begel x Pjg begel x 0.006165 x dia.2


= 29.0897 kg

4. Papan mal = Pjg balok untuk 1 m3 beton x luas permukaan papan


= 20.38 m2 -------> 50%

Total Berat Besi = 165.67 Kg


Papan mal 2 x Pakai = 10.192 M2

PERHITUNGAN Panjang balok untuk 1 m3


Balok Bordes ( 0.15 x 0.20 ) M = 1/( b x h)
= 33.33 m'
Jumlah Tul. Pokok = 4.00 Batang a. Pembesian untuk 1 m beton adalah
3

Ø Tul. Pokok = 12.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = - Batang Berat besi Ø 12, = 118.3680 kg
Ø Tul. Pinggang = - mm
Ø Tul. Begel = 8.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.100 M Berat besi Ø 0, = - kg
Luas Permukaan Papan = 0.55 M2
3. Tulangan Begel Besi Ø 8,
Panjang begel = 0.550 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 333.33 ± -------> 334.00 Btg
334 btg
20
Berat besi Ø 8, = Byk begel x Pjg begel x 0.006165 x dia.2
15 = 72.4807 kg

4. Papan mal = Pjg balok untuk 1 m3 beton x luas permukaan papan


Balok Bordes 15/ 20 = 18.33 m2 -------> 50%

Total Berat Besi = 190.85 Kg


Papan mal 2 x Pakai = 9.167 M2
NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3
PERHITUNGAN 1. Untuk Bidang 16,50 Meter
Plat Lantai = 12 cm Panjang Besi (Pjb) = 10.00 M
Jumlah Baris Besi (Jb) = 80.00 M
Bidang X = 12.00 M Jumlah Lapis (Jl) = 2.00 Lapis
Bidang Y = 10.00 M Diameter Besi (d) = 10.00 mm
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.15 M = 985.920 Kg

2. Untuk Bidang 4,65 Meter


Panjang Besi (Pjb) = 12.00 M
Jumlah Baris Besi (Jb) = 66.67 M
Jumlah Lapis (Jl) = 2.00 Lapis
Diameter Besi (d) = 10.00 mm
Ø12-150 Ø12-150 Ø12-150
30

Berat besi Ø 10, = Pjg*Jb*Jl*0.006162*d*d


40
= 985.920 Kg
100 200 100
400 Total Berat Besi = 1,971.84 Kg

Berat Besi Untuk 1 m3 Beton = 136.93 Kg / M3 Beton

Luas Bekisting Untuk 1 m3 Beton = 8.333 M2 / M3 Beton

PERHITUNGAN 1. Untuk Bidang 1.00 Meter


12 Plat Tangga = 12 cm Panjang Besi (Pjb) = 4.87 M
Jumlah Baris Besi (Jb) = 6.67 M
Bidang X = 1.00 M Jumlah Lapis (Jl) = 2.00 Lapis
Bidang Y = 4.87 M Diameter Besi (d) = 10.00 mm
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.15 M = 40.012 Kg

2. Untuk Bidang 6.49 Meter


Panjang Besi (Pjb) = 1.00 M
Jumlah Baris Besi (Jb) = 32.47 M
Jumlah Lapis (Jl) = 2.00 Lapis
Diameter Besi (d) = 10.00 mm

Berat besi Ø 10, = Pjg*Jb*Jl*0.006162*d*d


= 40.012 Kg

Total Berat Besi = 80.02 Kg

Berat Besi Untuk 1 m3 Beton = 136.93 Kg / M3 Beton

Luas Bekisting Untuk 1 m3 Beton = 8.333 M2 / M3 Beton

PERHITUNGAN 1. Untuk Bidang 1.30 Meter


13 Plat bordes = 12 cm Panjang Besi (Pjb) = 2.00 M
Jumlah Baris Besi (Jb) = 7.40 M
Bidang X = 1.11 M Jumlah Lapis (Jl) = 2.00 Lapis
Bidang Y = 2.00 M Diameter Besi (d) = 10.00 mm
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.15 M = 18.240 Kg

2. Untuk Bidang 2.00 Meter


Panjang Besi (Pjb) = 1.11 M
Jumlah Baris Besi (Jb) = 13.33 M
Jumlah Lapis (Jl) = 2.00 Lapis
Diameter Besi (d) = 10.00 mm

Berat besi Ø 10, = Pjg*Jb*Jl*0.006162*d*d


= 18.240 Kg

Total Berat Besi = 36.48 Kg

Berat Besi Untuk 1 m3 Beton = 136.93 Kg / M3 Beton

Luas Bekisting Untuk 1 m3 Beton = 8.333 M2 / M3 Beton

PERHITUNGAN 1. Untuk Bidang 1.30 Meter


14 Anak Tangga = 12 cm Panjang Besi (Pjb) = 0.40 M
Jumlah Baris Besi (Jb) = 1.33 M
Bidang X = 0.20 M Jumlah Lapis (Jl) = 2.00 Lapis
Bidang Y = 0.40 M Diameter Besi (d) = 10.00 mm
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.15 M = 0.657 Kg

2. Untuk Bidang 2.00 Meter


Panjang Besi (Pjb) = 0.20 M
Jumlah Baris Besi (Jb) = 2.67 M
Jumlah Lapis (Jl) = 2.00 Lapis
Diameter Besi (d) = 10.00 mm

Berat besi Ø 10, = Pjg*Jb*Jl*0.006162*d*d


= 0.657 Kg

Total Berat Besi = 1.31 Kg

Berat Besi Untuk 1 m3 Beton = 136.93 Kg / M3 Beton


NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3

Luas Bekisting Untuk 1 m3 Beton = 8.333 M2 / M3 Beton


NO. BENTUK / DIMENSI / UKURAN PERHITUNGAN VOLUME

1 2 3
PERHITUNGAN 1. Untuk Bidang 1.20 Meter
15 Pondasi Foot Plat ( tinggi ) = 60.0 cm Panjang Besi (Pjb) = 1.20 M
Jumlah Baris Besi (Jb) = 8.00 M
Bidang X = 1.20 M Jumlah Lapis (Jl) = 2.00 Lapis
Bidang Y = 1.20 M Diameter Besi (d) = 16.00 mm
Tebal Pengecoran = 0.60 M
Diameter Besi = 16.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.15 M = 30.287 Kg

2. Untuk Bidang 1.20 Meter


Panjang Besi (Pjb) = 1.20 M
D14 - 150
Jumlah Baris Besi (Jb) = 8.00 M
Jumlah Lapis (Jl) = 2.00 Lapis
D14 - 150
Diameter Besi (d) = 16.00 mm

Berat besi Ø 16, = Pjg*Jb*Jl*0.006162*d*d


D14-150

D14-150

D14-150
8-D16-150 30 120 = 30.287 Kg

30 Total Berat Besi = 60.57 Kg

D14 - 150
Berat Besi Untuk 1 m3 Beton = 70.11 Kg / M3 Beton

Luas Bekisting Untuk 1 m3 Beton = 1.667 M2 / M3 Beton


120

PERHITUNGAN Panjang balok untuk 1 m3


Pedestal Pondasi Foot
16 ( 0.30 x 0.30 ) M = 1/( b x h)
Plat
= 11.11 m'
Jumlah Tul. Pokok = 8.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 14.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = - Batang Berat besi Ø 14, = 107.4080 kg
Ø Tul. Pinggang = - mm
Ø Tul. Begel = 8.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.10 M Berat besi Ø 0, = - kg
Luas Permukaan Papan = 1.20 M2
3. Tulangan Begel Besi Ø 8,
Panjang begel = 1.050 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 111.11 ± -------> 111.00 Btg
112 btg

Berat besi Ø 8, = Byk begel x Pjg begel x 0.006165 x dia.2


115
= 46.4003 kg
140
4. Papan mal = Pjg balok untuk 1 m3 beton x luas permukaan papan
8 - Ø14 = 13.33 m2 -------> 50%
Ø8 - 100
5 Total Berat Besi = 153.81 Kg
8 Ø14 - 150
20 Papan mal 2 x Pakai = 6.667 M2