TIME LINE

Rehabilitasi Gedung Serbaguna Stadion Kadrie Oening Sempaja


CV. SHANZA PUJAKA
Tanggal Mulai Proyek Senin Februari 2024 Tampilan Minggu 1 Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 5 Minggu 6 Minggu 7 Minggu 8 Minggu 9 Minggu 10 Minggu 11 Minggu 12 Minggu 13 Minggu 14 Minggu 15 Minggu 16 Minggu 17 Minggu 18 Minggu 19 Minggu 20 Minggu 21 Minggu 22
26 Feb 2024 4 Mar 2024 11 Mar 2024 18 Mar 2024 25 Mar 2024 1 Apr 2024 8 Apr 2024 15 Apr 2024 22 Apr 2024 29 Apr 2024 6 May 2024 13 May 2024 20 May 2024 27 May 2024 3 Jun 2024 10 Jun 2024 17 Jun 2024 24 Jun 2024 1 Jul 2024 8 Jul 2024 15 Jul 2024 22 Jul 2024
26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Durasi Hari
No. Uraian Pekerjaan Mulai Akhir Waktu % Selesai
Kerja
Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min

I. DIVISI PERSIAPAN LAPANGAN SITE WORK


I.A PELAKSANAAN KESELAMATAN DAN KESEHATAN KERJA (K3)
Penyiapan RKK 29 Maret 2024 09 Mei 2024 42 0% 30
Pembuatan dokumen RKK (1 Set) 15 April 2024 23 Juni 2024 70 0% 50
a. Pembuatan Prosedur dan Instruksi Kerja .
b. Pembuatan Formulir Ijin Kerja dan Formulir Lainnya
Sosialisasi dan Promosi
a. Spanduk (Banner ) (3 bh)
b. Poster K3 (3 bh)
c. Papan Informasi K3 (3 bh)
Alat Pelindung Kerja dan Alat Pelindung Diri
a. Pembatas Area (Restricted Area) (3 bh)
b. Helm Pelindung (safety helmet) (30 bh)
c. Pelindung Mata (Goggles, Spectacles) (10 psg)
d. Helm Pengelasan (Welding Helmet) (5 bh)
e. Sarung Tangan Las Merah (Safety Gloves) (5 bh)
f. Sepatu Keselamatan (Safety Shoes) (30 psg)
g. Rompi Keselamatan (Safety Vest) (30 psg)
Asuransi
BPJS Ketenagakerjaan Dan Kesehatan Kerja
Personel Keselamatan Konstruksi
Petugas K3 Konstruksi (10 Ob)
Fasilitas alat kesehatan
Peralatan P3K (Kotak P3K, Perban, Obat, Masker dll) (3 Set)
Rambu rambu yang diperlukan
a. Rambu Petunjuk (5 bh)
b. Rambu Larangan (5 bh)
c. Rambu Peringatan (5 bh)
d. Rambu Kewajiban (5 bh)
e. Rambu Informasi (5 bh)
f. Rambu pekerjaan sementara (5 bh)
Konsultasi dengan Ahli Terkait Keselamatan Konstruksi
Ahli K3 Konstruksi (3 Ob)
Kegiatan dan Peralatan terkait Pengendalian Resiko Keselamatan Konstruksi
Alat Pemadam Api Ringan (APAR) 3 Kg (2 Bh)
Bendera K3 (2 Bh)
Pembuatan Kartu Identitas Pekerja (KIP) (30 bh)
II PEKERJAAN KONSTRUKSI
I.A PEKERJAAN REVETMEN
1 Injeksi Bocor Dak Struktur dengan Zat Aditif Lantai 1 sd Atap
2 Pekerjaan Pancang Kayu Ulin 10x10x400cm
3 Galian Tanah
4 Buang Tanah Galian
5 Urugan Kembali
6 Urugan Pasir
7 Lantai Kerja
8 Bongkar Struktur Eksisting
9 Pekerjaan Pile Cap
- Cor Beton Site Mix
- Besi Beton
- Bekisting
10 Pekerjaan Pedestal
- Cor Beton Site Mix
- Besi Beton
- Bekisting
11 Pekerjaan Tie Beam
- Cor Beton Site Mix
- Besi Beton
- Bekisting
12 Pekerjaan Plat Lantai
- Cor Beton Site Mix
- Besi Beton
- Bekisting
III DIVISI PEKERJAAN ARSITEKTUR
III.A LANTAI 01
III.A.1 PEKERJAN DINDING
1 Pekerjaan Pasangan Dinding
2 Perbaikan Dinding Retak (Lebar Perbaikan 20cm,bobok plesteran,kawat nyamuk,plaster & Aci)
3 Pekerjaan Finishing Interior
4 Cat Interior Dinding
III.A.2 PEKERJAN LANTAI
1 Granite Tile 600x600 Unpolished (Toilet & Ruang Ganti)
2 Granite Tile 600x600 Unpolished + Anti Slip (Tangga)
3 Granite Tile 600X600 Polished (Hall,Lobby dan koridor utama)
4 Pengecatan Lantai dengan Cat Lapangan (Gelanggang)
III.A.3 PEKERJAN PLAFOND
1 Plafond Gypsum 9mm Rangka Hollow 40x40 comb 40x20mm Tebal 0.4mm
2 Plafond Calsi Silicate board 4mm Rangka Hollow 40x40 comb 40x20mm Tebal 0.4mm
3 List Plafond Shadowline
4 Cat Plafond Interior
III.A.4 PEKERJAN PINTU DAN JENDELA
1 Daun Pintu Enggeneering Door Double Lumbercol 18mm Lapis HPL
2 Engsel 4( 1 Pintu 3 Engsel )
3 Door closer
4 Bodi kunci lock case pelor Aluminium, Cylinder, Lever hadle
5 Pengecatan Ulang Pintu Besi
III.A.5 PEKERJAN LAIN - LAIN
1 Pembersihan \/ Pengupasan cat dinding Eksisting
2 Pembongkaran Plafond Eksisting & Buang Puing Bongkaran
3 Pembongkaran Pelapir Lantai Exsisting & Buang Puing Bongkaran
4 Pengecatan Ulang Railling tangga darurar dan tangga Utama
III.B LANTAI 02
III.B.1 PEKERJAN DINDING
1 Pekerjaan Pasangan Dinding
2 Perbaikan Dinding Retak (Lebar Perbaikan 20cm,bobok plesteran,kawat nyamuk,plaster & Aci)
3 Pekerjaan Finishing Interior
4 Cat Interior Dinding
III.B.2 PEKERJAN LANTAI
1 Granite Tile 600x600 Unpolished (Ruang Utilitas gedung)
III.B.3 PEKERJAN PLAFOND
1 Plafond Gypsum 9mm Rangka Hollow 40x40 comb 40x20mm Tebal 0.4mm
2 List Plafond Shadowline
3 Cat Plafond Interior
III.B.4 PEKERJAN PINTU DAN JENDELA
1 Daun Pintu Enggeneering Door Multipleks Lapis HPL + List Aluminium 10mm + Rangka + Honeycom
2 Engsel 4( 1 Pintu 3 Engsel )
3 Door closer
4 Bodi kunci lock case pelor Aluminium, Cylinder, Lever hadle
III.B.5 PEKERJAN LAIN - LAIN
1 Pembersihan \/ Pengupasan cat dinding Eksisting
2 Pembongkaran Plafond Eksisting & Buang Puing Bongkaran
3 Pembongkaran Pelapir Lantai Exsisting & Buang Puing Bongkaran
4 Pengecatan Ulang Railling tangga darurar dan tangga Utama
III.C LANTAI ATAP
III.C1 PEKERJAAN PASANGAN DINDING
1 Perbaikan Dinding Retak (Lebar Perbaikan 20cm,bobok plesteran,kawat nyamuk,plaster & Aci)
2 Pekerjaan Finishing Interior
3 Cat Dinding Exsterior
III.C2 PEKERJAN LANTAI
Water Profing Coating
1 Acian Pelindung
III.C3 PEKERJAN LAIN - LAIN
1 Pembersihan Dak Atap
2 Pembersihan \/ Pengupasan cat dinding Eksisting
3 Perbaikan Kebocoran Atap
4 Penggantian Talang Air Hujan Dengan Pipa Air PVC AW 6 Include TEE perjarak 4m dan LBOW pada 2 sisi Ujung
5 Pembersihan dan Pengecatan Ulang Atap sisi luar Dengan Sistem Sprayer \/ Semprot 3 Lapis
III.D FASADE
III.D.1 TAMPAK DEPAN
1 Pembersihan \/ Pengupasan cat dinding Eksisting
2 Perbaikan Dinding Retak (Lebar Perbaikan 20cm,bobok plesteran,kawat nyamuk,plaster & Aci)
3 Cat Dinding Exsterior
4 Alumunium Composite Panel PVDF 0.5 mm Alloy 5005 Corrugated Includ Rangka dan Perkuatan yang Diperlukan
5 Pencucian ACP dengan cairan pembersih Khusus ACP
III.D.2 TAMPAK BELAKANG
1 Pembersihan \/ Pengupasan cat dinding Eksisting
2 Perbaikan Dinding Retak (Lebar Perbaikan 20cm,bobok plesteran,kawat nyamuk,plaster & Aci)
3 Cat Dinding Exsterior
4 Pencucian ACP dengan cairan pembersih Khusus ACP
III.D.3 TAMPAK SAMPING KANAN
1 Pembersihan \/ Pengupasan cat dinding Eksisting
2 Perbaikan Dinding Retak (Lebar Perbaikan 20cm,bobok plesteran,kawat nyamuk,plaster & Aci)
3 Cat Dinding Exsterior
4 Pencucian ACP dengan cairan pembersih Khusus ACP
III.D.4 TAMPAK SAMPING KIRI
1 Pembersihan \/ Pengupasan cat dinding Eksisting
2 Perbaikan Dinding Retak (Lebar Perbaikan 20cm,bobok plesteran,kawat nyamuk,plaster & Aci)
3 Cat Dinding Exsterior
4 Pencucian ACP dengan cairan pembersih Khusus ACP
IV. PEKERJAAN POMPA AIR BERSIH ,PIPA PLUMBING & SANITAIR
IV.A PEKERJAAN INSTALASI AIR BERSIH DAN POMPA
IV.A1 Pekerjaan Pengadaan & Pemasangan Peralatan Utama Pompa Air Bersih,Intalasi, termasuk Hanger \/ Support Sesuai dengan Gambar , Spesifikasi Teknis Dan Testcomissioning
1 Pompa boster
Item Booster Pump
Type Vertical Multistage Booster Pump
Pump model Helix FIRST V 1005-5\/16\/E\/S\/400-50(B-ck1)-E
Capacity 10 m3\/h
Head 35 m
Speed 2825 rpm
Shaft Power 1.66 kW
Motor 2.2 kW\/ 3 400V 50Hz
Suction size G 1, PN 16
Discharge size G 1, PN 16
Pump material
Casing Stainless Steel
Impeller Stainless Steel
Shaft Stainless Steel
Sealing Mechanical Seal
Scope of supply Pump c\/w motor and control panel VSD (1 panel for 2 pumps)
Pekerjaan Pengadaan dan Pemasangan Instalasi Pipa tranfer
2 Pipa Ppr pn 10 63 mm
3 Header 100 mm
4 Gate Valve 32 mm
5 Strainer 32 mm
6 Check Valve 32 mm
7 Flexible Joint 32 mm
8 Pressure Gauge
9 Pressure Switch
10 Intalasi Water Level Control (WLC)
11 Floating Level Valve 32 mm
12 Foot Valve 32 mm
IV.A.2 INSTALASI PIPA PLUMBING & SANITAIR LANTAI 1
1 Instalasi pemipaan cabang dan toilet dengan pipa Ppr pn 10 termasuk fitting dan aksesories
IV.A.3 INSTALASI PIPA AIR BERSIH
1 Pipa Ppr pn 10 63 mm
2 Pipa Ppr pn 10 50 mm
3 Pipa Ppr pn 10 40 mm
4 Pipa Ppr pn 10 32 mm
5 Pipa Ppr pn 10 20 mm
IV.B PERBAIKAN PIPA AIR KOTOR
IV.B.1 PERBAIKAN PIPA AIR KOTOR
1 PIPA PVC dia 100 mm
2 PIPA PVC dia 80 mm
IV.B.2 INSTALASI PIPA AIR KOTOR
1 PIPA PVC dia 100 mm
2 PIPA PVC dia 80 mm
3 PIPA PVC dia 65 mm
4 PIPA PVC dia 50 mm
5 PIPA PVC dia 40 mm
6 PIPA PVC dia 32 mm
IV.C PEKERJAAN TATA UDARA
Harga satuan pekerjaan sudah termasuk pengadaan , pemasangan, material serta material bantu
yang diperlukan,Testcomissioning sehingga pekerjaan tersebut dinyatakan tercapai dengan baik.
Pekerjaan harus dilaksanakan sesuai dengan spesifikasi teknis dan gambar.

IV.C.1 PERALATAN UTAMA


PEKERJAAN TATA UDARA
1 Pekerjaan AC Split duct Type split duct Mounted Kapasitas 150.000 BTU\/H
2 Kabel Control 4x2,5mm
3 Pipa Refregerant c\/w isolasi t = 19 mm, vinil, klem
4 Pipa Drainage PVC AW 1 c\/w isolasi armaflex t = 13mm, klem
5 Pekerjaan AC Single Wall Deluxe Model CS\/CU-PN18WKJ Kapasitas 18.000 BTU\/H
6 Kabel Power & Control
- Kabel Power (Nym 3x2.5mm)
- Kabel Control Nym 3x2,5mm
7 Pipa Refregerant c\/w isolasi t Ukuran (1\/2 & 1\/4 Inch)
8 Pipa Drainage PVC AW 3\/4 c\/w isolasi armaflex t = 13mm, klem
9 Extra Carge Refrigerant R32
10 Kabel Power Dari Panel AC ke Outdoor Unit
- Kabel NYY 4 x 16 mm2
- Kabel NYY 4 x 4 mm2
Tanggal Mulai Proyek Senin Februari 2024 Tampilan Minggu 1 Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 5 Minggu 6 Minggu 7 Minggu 8 Minggu 9 Minggu 10 Minggu 11 Minggu 12 Minggu 13 Minggu 14 Minggu 15 Minggu 16 Minggu 17 Minggu 18 Minggu 19 Minggu 20 Minggu 21 Minggu 22
26 Feb 2024 4 Mar 2024 11 Mar 2024 18 Mar 2024 25 Mar 2024 1 Apr 2024 8 Apr 2024 15 Apr 2024 22 Apr 2024 29 Apr 2024 6 May 2024 13 May 2024 20 May 2024 27 May 2024 3 Jun 2024 10 Jun 2024 17 Jun 2024 24 Jun 2024 1 Jul 2024 8 Jul 2024 15 Jul 2024 22 Jul 2024
26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Durasi Hari
No. Uraian Pekerjaan Mulai Akhir Waktu % Selesai
Kerja
Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min
Rehabilitasi Gedung Serbaguna Stadion Kadrie Oening Sempaja
CV. SHANZA PUJAKA
Tanggal Mulai Proyek Senin Februari 2024 Tampilan Minggu 2 Minggu 2 Minggu 3 Minggu 4 Minggu 5 Minggu 6 Minggu 7 Minggu 8 Minggu 9 Minggu 10 Minggu 11 Minggu 12 Minggu 13 Minggu 14 Minggu 15 Minggu 16 Minggu 17 Minggu 18 Minggu 19 Minggu 20 Minggu 21 Minggu 22 Minggu 23
4 Mar 2024 11 Mar 2024 18 Mar 2024 25 Mar 2024 1 Apr 2024 8 Apr 2024 15 Apr 2024 22 Apr 2024 29 Apr 2024 6 May 2024 13 May 2024 20 May 2024 27 May 2024 3 Jun 2024 10 Jun 2024 17 Jun 2024 24 Jun 2024 1 Jul 2024 8 Jul 2024 15 Jul 2024 22 Jul 2024 29 Jul 2024
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
Durasi Hari
No. Uraian Bahan/Material Mulai Akhir Waktu % Selesai
Kerja
Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min Sen Sel Rab Kam Jum Sab Min

1 PEK. PENGECATAN - -
a Cat Dinding Exsterior 29 Maret 2024 09 Mei 2024 42 0% 30
b Cat Dinding Interior 15 April 2024 23 Juni 2024 70 0% 50
2 PEK. PAS KERAMIK LANTAI - `
a Keramik Lantai 1 22 April 2024 16 Juni 2024 56 0% 40
b Keramik Lantai 2 22 April 2024 19 Mei 2024 28 0% 20
3 PEK. PLAFOND -
a Plafond LT. 1 15 April 2024 23 Juni 2024 70 0% 50
b Plafond LT. 2 20 April 2024 14 Juni 2024 56 0% 40
-
10 Februari 2018 13 Februari 2018 4 0% 2
14 Februari 2018 16 Februari 2018 3 0% 3
14 Februari 2018 16 Februari 2018 3 0% 3
17 Februari 2018 22 Februari 2018 6 0% 4
23 Februari 2018 25 Februari 2018 3 0% 1
- -
29 Januari 2018 29 Januari 2018 1 0% 1
30 Januari 2018 30 Januari 2018 1 0% 1
31 Januari 2018 31 Januari 2018 1 0% 1
01 Februari 2018 01 Februari 2018 1 0% 1
02 Februari 2018 02 Februari 2018 1 0% 1
-
-
Gantt Chart Template Pro

Gantt Chart Template Pro is similar to this free version, but


it is more feature-packed. It also comes with other bonus content.

Learn About Gantt Chart Template Pro


https://www.vertex42.com/ExcelTemplates/excel-gantt-chart.html

The following link is a blog post that talks specifically about the
Pro version for Excel Online.

Gantt Chart Template Pro for Excel Online

Benefits and Features of Gantt Chart Template Pro

Simple Color-Coding
The Pro version includes a column for specifying the color of bars in the chart. For example,
you could change the color based on urgency or task lead.

Daily, Weekly, or Monthly View


The Pro version includes a drop-down next to the Display Week that lets you choose to display
the columns in the chart area as days, weeks, or months.

Use Work Days as an Input


By default, the Pro version is set up to have you enter Work Days instead of Calendar Days.
The expanded set of template rows provides more options for defining the Start date, End date,
and Duration of tasks. Define a task based on …
- Start date and End date
- Start date and Work days
- Start date and Calendar days

Easily Create Task Dependencies


Though you can still use your own formulas for creating task dependencies, the Pro version
includes template rows that calculate the Start date based on the WBS number that you enter
in the Predecessor column.

Exclude Holidays from Work Days


List holidays and other specific non-working days that you want to exclude from work days.

Customize Your Work Week


The versions designed for Excel 2010+ use the WORKDAY.INTL() and NETWORKDAYS.INTL()
functions that allow you define the work week as something other than Monday-Friday.

Learn More About Gantt Chart Template Pro

Anda mungkin juga menyukai