Anda di halaman 1dari 22

KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT

DIREKTORAT JENDERAL SUMBER DAYA AIR


BALAI BESAR WILAYAH SUNGAI BRANTAS
SNVT PEMBANGUNAN BENDUNGAN BBWS BRANTAS
Jln. Jayengkusuma No 123 Tulungagung – Jawa Timur Telp. 0355-321013 / Fax. 0355-321014

LAPORAN PROGRES MINGGUAN


01 Oktober 2019
s.d
07 Oktober 2019

PEMBANGUNAN SPILLWAY BENDUNGAN TUGU


DI KAB. TRENGGALEK (MYC)

NOMOR KONTRAK : IK.02.04-Am.10.2/SP.02/2018


TANGGAL KONTRAK : 27 Desember 2018

NINDYA MINARTA KSO


Jl. Letjen Haryono MT Kav 22 - Jakarta
TELP.021-8093126, 8094647 , FAX. 021-8007920
NINDYA MINARTA KSO
FM-RKP-50
No. Revisi : 0.1

DATA PROYEK : Unit Kerja : Wilayah II


( Form : RKP-50 ) No.Proyek :

01. a. JENIS PEKERJAAN :


b. NAMA PEKERJAAN :

c. TGL.PEMASUKAN TENDER :
d. TGL.PENETAPAN PEMENANG :
e. STATUS PEKERJAAN :

f. LINGKUP PEKERJAAN I 2,634,465,000.00


II
2.1
2.1.1 87,994,306,083.63
2.1.2 253,970,252,853.58
2.1.3 7,147,865,090.00
2.1.4 109,771,920,143.82
2.1.8 2,695,000,000.00

d. BAGIAN PROYEK :

LOKASI PEKERJAAN / KOTA :


02. a. PEMBERI TUGAS :

b. PEJABAT PEMBUAT KOMITMEN :

c. KONSULTAN PENGAWAS :

03. a. NOMOR KONTRAK :


b. TANGGAL KONTRAK ::
04. a. HARGA KONTRAK (+) PPN :
b. HARGA KONTRAK ( - ) PPN :
05. SUMBER DANA PROYEK
a. DARI …………… SBSN 2018 : = Rp -
b. DARI …………… SBSN 2019 = Rp 155,805,466,000.00
c. DARI …………… SBSN 2020 = Rp 238,730,252,000.00
d. DARI …………… SBSN 2021 = Rp 134,543,282,000.00
529,079,000,000.00
06. a. WAKTU PELAKSANAAN : HARI
b. SERAH TERIMA - I / PHO :
b. SERAH TERIMA - II / FHO :
07. a. UANG MUKA ( ada , besarnya ) : % = Rp 69,632,071,375.65
b. TERMIN ( prestasi / bulanan ) :
c. RETENSI ( ada , besarnya ) : % = Rp 23,210,690,458.55
08. a. JAMINAN PELAKSANAAN : % = Rp 23,210,690,458.55
b. ASURANSI PEKERJAAN : % = Rp 2,356,363,637.79
c. DENDA - MINIMAL : % = Rp 464,213,809.17
- MAKSIMAL : % = Rp 23,210,690,458.55
09. a. SIFAT KONTRAK :
b. MANAJEMEN PELAKSANAAN :
LAPORAN PROGRES MINGGUAN
PEKERJAAN PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB.TRENGGALEK (MYC)

PROYEK : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC)


PEMILIK : BBWS BRANTAS SNVT PEMBANGUNAN BENDUNGAN
NOMOR KONTRAK : IK.02.04-Am.10.2/SP.02/2018
TANGGAL KONTRAK : 27 Desember 2018
KONTRAKTOR : NINDYA MINARTA KSO
LAPORAN TANGGAL : Trenggalek, 01 Oktober 2019 s/d 07 Oktober 2019
RENCANA PEKERJAAN : 10.472 %
REALISASI PEKERJAAN : 7.764 %
DEVIASI : -2.709 %
MINGGU KE : 00036 35

Harga Satuan Total Total Biaya


No. Jenis Pekerjaan Sat Volume Volume ADD-1 BOBOT ADD-1 (%) S/D Minggu Lalu Minggu ini S/D Minggu ini
(Rp) Biaya (Rp) ADD-1 (Rp)
(1) (2). (3) (4) (4) (4) (4) (5) (7) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan konstruksi Ls 1.000 603,015,000.00 ### 603,015,000.00 1.00 0.128% 0.500 0.064% - 0.000% 0.500 0.064%
1.2 Penyelenggaraan K3 Konstruksi Ls 1.000 2,031,450,000.00 ### 2,031,450,000.00 1.00 0.431% 0.250 0.108% 0.005 0.002% 0.255 0.110%
SUB TOTAL 2.1.1 ### ### 20.035% 0.172% 0.002% 0.174%
II PEKERJAAN SIPIL/KONSTRUKSI
2.1 BANGUNAN PELIMPAH
2.1.1 Pekerjaan Tanah :
a. Pembersihan m2 44,052.86 5,104.00 ### 321,321,809.60 62,954.90 0.068% 45,200.00 0.049% 0.000% 45,200.000 0.049%
b. Galian Tanah m3 1,358,345.07 25,715.00 ### ### 747,694.40 4.080% 563,882.78 3.077% 6,313.00 0.034% 570,195.781 3.111%
c. Galian Batu Lapuk (Stockpile) m3 128,247.24 60,991.00 ### 7,821,927,414.84 128,247.24 1.660% 128,247.24 1.660% 0.000% 128,247.240 1.660%
c.c. Galian Batu Lapuk (Stockpile) m3 34,400.00 9,655,923,136.00 280,695.44 2.052% 61,781.64 0.451% 0.000% 61,781.640 0.451%
d. Penggalian Batu Keras (dengan peledakan) m3 421,214.78 101,005.00 ### ### 538,841.05 11.539% 63,283.98 1.356% 8,430.464 0.181% 71,714.445 1.537%
e. Urugan Kembali (dipadatkan dan free draining) m3 60,548.26 11,740.00 ### 1,053,719,004.00 89,754.60 0.224% - 0.000% - 0.000% - 0.000%
f. Batang angker/anchor bars D25 (L=2m) termasuk boring dan air semen bh 3,173.00 174,890.00 ### 650,765,690.00 3,721.00 0.138% - 0.000% - 0.000% - 0.000%
g. Drainase Pipa PVC (perforated) dia. 6" m 2,600.00 464,280.00 ### 1,207,128,000.00 2,600.00 0.256% - 0.000% - 0.000% - 0.000%
g.g. Drainase Pipa PVC (perforated) dia. 6" 211,000.00 87,292,810.00 413.71 0.019% - 0.000% 0.000% - 0.000%

SUB TOTAL 2.1.1 ### ### 20.035% 6.593% 0.215% 6.808%

2.1.2 Pekerjaan Beton :


a. Beton K-225 m3 43,489.72 1,401,030.00 ### ### 36,250.22 10.360% 264.56 0.079% 127.00 0.038% 391.56 0.116%
b. Beton K-350 m3 24,585.21 1,530,823.00 ### ### 17,503.39 5.686% - 0.000% - 0.000% - 0.000%
c. Tulangan Beton (pemotongan, pembengkokan dan
ton 5,773.81 20,630,445.00 ### ### 2,169.17 9.422% 13.88 0.061% 6.90 0.030% 20.78 0.091%
pemasangan)
d. Bekisting tipe expose F2 (termasuk perancah dan
m2 26,370.27 159,663.00 ### 4,372,727,303.49 27,387.23 0.928% - 0.000% - 0.000% - 0.000%
pembongkaran
e. Bekisting tipe) non expose F1 (termasuk perancah dan
m2 13,421.75 181,492.00 ### 3,599,625,211.84 19,833.52 0.715% 992.19 0.038% 469.00 0.018% 1,461.19 0.056%
pembongkaran
f. Bekisting tipe )expose F4 (termasuk perancah dan
m2 537.97 240,516.00 ### 394,220,154.96 1,639.06 0.084% - 0.000% - 0.000% - 0.000%
pembongkaran )
g. Shotcrete t = 10 cm (termasuk wiremesh) m2 25,682.72 671,011.00 ### ### 79,167.74 11.272% - 0.000% - 0.000% - 0.000%
h. Plat baja dan aksesorisnya bh 3,616.00 162,800.00 ### 1,336,099,600.00 8,207.00 0.284% - 0.000% - 0.000% - 0.000%
i. Pipa PVC Perforated dia. 50 mm ( termasuk Geotekstile
bh 5,426.00 13,096.00 ### 71,058,896.00 5,426.00 0.015% - 0.000% - 0.000% - 0.000%
dan
i.i pemasangan
Pipa )
PVC Perforated dia. 50 mm ( termasuk Geotekstile
bh 11,800.00 127,180,400.00 10,778.00 0.027% 0.000% 0.000% 0.000%
dan pemasangan )
j. Pemboran Anchor Shotcrete m 5,455.00 280,132.00 ### 2,299,043,324.00 8,207.00 0.488% - 0.000% - 0.000% - 0.000%
k. Pemboran Rock bolt m 21,696.00 285,124.00 ### ### 49,242.00 2.979% - 0.000% - 0.000% - 0.000%
l. Pemboran Pipa PVC Perforated m 1,899.10 292,951.00 ### 1,661,442,301.40 5,671.40 0.353% - 0.000% - 0.000% - 0.000%
m. Tulangan Beton Anchor Shotcrete(Pemotongan,
ton 93.87 20,630,445.00 ### 4,236,255,576.30 205.34 0.899% - 0.000% - 0.000% - 0.000%
Pembengkokan dan Pemasangan)
n. Beton K-175 m3 1,200.00 1,176,720.00 ### 1,412,064,000.00 1,200.00 0.300% - 0.000% - 0.000% - 0.000%
o. Grouting termasuk material dan peralatan ton 3,000,000.00 696,120,000.00 232.04 0.148% - 0.000% - 0.000% - 0.000%
p. Dowel Bar bh 183,799.00 2,347,113,230.00 12,770.00 0.498% - 0.000% - 0.000% - 0.000%
q. Joint Sealant m 151,500.00 380,916,450.00 2,514.30 0.081% - 0.000% - 0.000% - 0.000%

SUB TOTAL 2.1.2 ### ### 43.811% 0.178% 0.086% 0.264%

2.1.3 Drilling dan Grouting :


a. Pemboran lubang Curtain Grouting m 1,340.00 442,516.00 ### 592,971,440.00 1,340.00 0.126% - 0.000% - 0.000% - 0.000%
b. Pemboran Sub Curtain Grouting m 590.00 283,635.00 ### 167,344,650.00 590.00 0.036% - 0.000% - 0.000% - 0.000%
c. Grouting termasuk material dan peralatan ton 1,913.56 3,000,000.00 ### 5,740,680,000.00 1,913.56 1.218% - 0.000% - 0.000% - 0.000%
f. Single Water Presure test test 358.00 290,000.00 ### 103,820,000.00 358.00 0.022% - 0.000% - 0.000% - 0.000%
g. Double Water Presure test test 28.00 390,000.00 ### 10,920,000.00 28.00 0.002% - 0.000% - 0.000% - 0.000%
h. Pemasangan Pipa pelindung m 157.50 39,000.00 ### 6,142,500.00 157.50 0.001% - 0.000% - 0.000% - 0.000%
i. Penutupan Lubang Grouting ton 4.47 1,950,000.00 ### 8,716,500.00 4.47 0.002% - 0.000% - 0.000% - 0.000%
j. Redrilling m 203.00 590,000.00 ### 119,770,000.00 203.00 0.025% - 0.000% - 0.000% - 0.000%
k. Pemboran inti untuk Pilot & Check Hole m 100.00 575,000.00 ### 57,500,000.00 100.00 0.012% - 0.000% - 0.000% - 0.000%
l. Investigasi Geologi dan Mekanika Tanah (termasuk Tes Lab. Mektan & Batuan ) Ls 1.000 340,000,000.00 ### 340,000,000.00 1.00 0.072% 1.000 0.072% - 0.000% 1.000 0.072%

SUB TOTAL 2.1.3 ### ### 1.517% 0.072% 0.000% 0.072%

2.1.4 Pekerjaan Perbaikan Pondasi :


a. Bronjong m3 9,403.39 782,320.00 ### 8,536,143,862.40 10,911.32 1.985% 247.00 0.041% 266.00 0.044% 513.00 0.085%
b. Geotekstile m2 28,457.54 51,816.00 ### 1,575,073,751.04 30,397.44 0.337% 1,616.50 0.018% 495.75 0.005% 2,112.25 0.023%
c. Pasangan Batu Kali (1Pc : 3Ps) m3 218.93 1,065,724.00 ### 233,318,955.32 218.93 0.050% - 0.000% - 0.000% - 0.000%
Harga Satuan Total Total Biaya
No. Jenis Pekerjaan Sat Volume Volume ADD-1 BOBOT ADD-1 (%) S/D Minggu Lalu Minggu ini S/D Minggu ini
(Rp) Biaya (Rp) ADD-1 (Rp)
(1) (2). (3) (4) (4) (4) (4) (5) (7) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
e. Joint Filler m2 5,231.62 175,000.00 ### 816,781,000.00 4,667.32 0.173% - 0.000% - 0.000% - 0.000%
f. PVC Waterstop, l=300 mm m 2,253.00 272,639.00 ### 614,255,667.00 2,253.00 0.130% - 0.000% - 0.000% - 0.000%
f.f. PVC Waterstop, l=300 mm m 140,700.00 153,298,278.00 1,089.54 0.033% 0.000% 0.000% 0.000%
g. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m 5,780.00 1,561,129.00 ### ### 8,101.20 3.220% - 0.000% 0.000% - 0.000%
h. Pengeboran Batu untuk Bore Pile dia. 80 cm m 8,670.00 2,574,504.00 ### ### 12,151.80 7.965% - 0.000% - 0.000% - 0.000%
i. Beton K-225 m3 13,931.00 1,401,030.00 ### ### 11,338.26 3.975% - 0.000% 0.000% - 0.000%
j. Tulangan Beton (pemotongan, pembengkokan dan
ton 1,916.04 20,630,445.00 ### ### 2,324.46 12.208% - 0.000% 0.000% - 0.000%
pemasangan)
k. Bekisting tipe expose F2 (termasuk perancah dan
m2 16,825.65 159,663.00 ### 139,379,412.48 872.96 0.030% - 0.000% - 0.000% - 0.000%
pembongkaran)
l. Riprap m3 852.20 291,459.00 ### 219,471,541.59 753.01 0.047% - 0.000% - 0.000% - 0.000%
m. Pengadaan dan Pemasangan U-Ditch uk 50 x 50 cm
m 3,746.43 761,057.00 ### 3,052,097,329.38 4,010.34 0.648% - 0.000% - 0.000% - 0.000%
(Pabrikasi
n. Pengadaan dan Pemasangan U-Ditch uk 120 x 120 cm
m 1,084.00 2,768,406.00 ### 3,267,023,604.66 1,180.11 0.693% - 0.000% - 0.000% - 0.000%
(Pabrikasi

SUB TOTAL 2.1.4 ### ### 31.492% 0.059% 0.050% 0.108%

2.1.5 Pekerjaan Jembatan (2 unit) :


a. Beton K-225 m3 151.98 1,401,030.00 ### 368,064,591.30 262.71 0.141% 172.96 0.051% 18.87 0.006% 191.83 0.057%
b. Tulangan Beton (pemotongan, pembengkokan dan
ton 38.68 20,630,445.00 ### 2,303,595,488.70 111.66 0.196% 37.45 0.164% 3.00 0.013% 40.45 0.177%
pemasangan)
c. Bekisting tipe expose F2 (termasuk perancah dan
m2 686.92 159,663.00 ### 110,929,062.51 694.77 0.037% - 0.000% - 0.000% - 0.000%
pembongkaran
d. Bekisting tipe) non expose F1 (termasuk perancah dan
m2 61.76 181,492.00 ### 127,944,600.32 704.96 0.003% - 0.000% - 0.000% - 0.000%
pembongkaran)
e. Elastomer bh 8.00 600,000.00 ### 6,000,000.00 10.00 0.001% - 0.000% - 0.000% - 0.000%
f. Hand rail m 195.20 595,000.00 ### 84,728,000.00 142.40 0.025% - 0.000% - 0.000% - 0.000%
g. Pipa Drainasi PVC Ø 4" m 44.00 180,000.00 ### 70,884,000.00 393.80 0.002% - 0.000% - 0.000% - 0.000%
h. Expansion Joint m 28.00 2,400,000.00 ### 57,600,000.00 24.00 0.014% - 0.000% - 0.000% - 0.000%
i. Pasangan Batu kali (1PC : 4Ps) m3 12.20 929,729.00 ### 9,641,289.73 10.37 0.002% - 0.000% - 0.000% - 0.000%
j. Plesteran t=1.5cm (1PC : 3Ps) m2 15.72 35,429.00 556,943.88 1,002,994.99 28.31 0.000% - 0.000% - 0.000% - 0.000%
k. Siaran (1PC : 2Ps) m2 36.96 59,281.00 ### 1,441,713.92 24.32 0.001% - 0.000% - 0.000% - 0.000%
l. Timbunan Tanah dipadatkan kembali m3 3,842.00 15,072.00 ### 31,333,934.40 2,078.95 0.026% - 0.000% - 0.000% - 0.000%
m. Lapis penetrasi hotmix, t = 5cm m3 250.00 228,171.00 ### 73,852,107.57 323.67 0.011% - 0.000% - 0.000% - 0.000%
n. Beton K-350 m3 1,530,823.00 1,228,470,149.27 802.49 0.261% - 0.000% - 0.000% - 0.000%
o. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m 1,561,129.00 499,561,280.00 320.00 0.106% 312.00 0.103% 0.000% 312.00 0.103%
p. Pengadaan PC I-Girder L = 35 m (H = 1,7 m; CTC = 2,3 m) Unit 410,572,800.00 1,231,718,400.00 3.00 0.261% - 0.000% - 0.000% - 0.000%
q. Beton Diafragma K-350 termasuk pekerjaan penegangan setelah pengecoran (post tension) Unit 15,382,842.00 215,359,788.00 14.00 0.046% - 0.000% - 0.000% - 0.000%
r. Plat Deck K-350 Unit 1,019,700.00 73,418,400.00 72.00 0.016% - 0.000% - 0.000% - 0.000%
s. Erection PC I-Girder L = 35 m (H = 1,7 m; CTC = 2,3 m) Unit 176,365,602.00 529,096,806.00 3.00 0.112% - 0.000% - 0.000% - 0.000%
t. Kansteen pracetak m 218,851.00 26,087,039.20 119.20 0.006% - 0.000% - 0.000% - 0.000%
u. dowel bar bh 183,799.00 8,822,352.00 48.00 0.002% - 0.000% - 0.000% - 0.000%

SUB TOTAL 2.1.5 ### ### 0.459% 0.319% 0.019% 0.337%


Harga Satuan Total Total Biaya
No. Jenis Pekerjaan Sat Volume Volume ADD-1 BOBOT ADD-1 (%) S/D Minggu Lalu Minggu ini S/D Minggu ini
(Rp) Biaya (Rp) ADD-1 (Rp)
(1) (2). (3) (4) (4) (4) (4) (5) (7) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

2.1.6 Pekerjaan Jalan Inspeksi


a. Lapis penetrasi hotmix, t = 5cm m2 6,000.00 228,171.00 ### 1,402,621,898.04 6,147.24 0.298% - 0.000% - 0.000% - 0.000%
b. Lapis Pondasi Atas / Base Course, t = 20 cm m3 2,200.00 519,023.00 ### 1,141,850,600.00 2,200.00 0.242% - 0.000% - 0.000% - 0.000%
b.b. Lapis Pondasi Atas / Base Course, t = 20 cm m3 288,300.00 594,953,178.00 2,063.66 0.126% 0.000% 0.000% 0.000%
c. Lapis Pondasi Bawah / Sub-Base Course, t = 30 m3 3,300.00 493,042.00 ### 1,627,038,600.00 3,300.00 0.345% - 0.000% - 0.000% - 0.000%
c.c. Lapis Pondasi Bawah / Sub-Base Course, t = 30 m3 284,500.00 880,666,905.00 3,095.49 0.187% 0.000% 0.000% 0.000%
d. Beton K-225 m3 218.16 1,401,030.00 ### 367,854,436.80 262.56 0.078% - 0.000% - 0.000% - 0.000%
e. Tulangan Beton (pemotongan, pembengkokan dan
ton 15.27 20,630,445.00 ### 379,187,579.10 18.38 0.080% - 0.000% - 0.000% - 0.000%
pemasangan)
f. Bekisting tipe expose F2 (termasuk perancah dan
m2 473.52 159,663.00 ### 168,257,659.29 1,053.83 0.036% - 0.000% - 0.000% - 0.000%
pembongkaran)

SUB TOTAL 2.1.6 ### ### 1.392% - 0.000% - 0.000% - 0.000%

2.1.7 Pekerjaan Helipad


a. Lapis penetrasi hotmix, t = 5cm m2 1,600.00 228,171.00 ### 365,073,600.00 1,600.00 0.077% - 0.000% - 0.000% - 0.000%
b. Lapis Pondasi Atas / Base Course, t = 20 cm m3 320.00 519,023.00 ### 166,087,360.00 320.00 0.035% - 0.000% - 0.000% - 0.000%
c. Lapis Pondasi Bawah / Sub-Base Course, t = 30 m3 480.00 493,042.00 ### 236,660,160.00 480.00 0.050% - 0.000% - 0.000% - 0.000%

SUB TOTAL 2.1.7 ### ### 0.163% - 0.000% - 0.000% - 0.000%

2.1.8 Pekerjaan Lain-lain


a. Alat Pencatat Gempa Terintegrasi Dengan Jaringan BMKG Unit 1.00 2,695,000,000.00 ### 2,695,000,000.00 1.00 0.572% - 0.000% - 0.000% - 0.000%

SUB TOTAL 2.1.8 ### ### 0.572% - 0.000% - 0.000% - 0.000%

2.1.9 Pekerjaan Jalan Akses Nglinggis -


a. Pembersihan m2 5,104.00 9,632,881.28 1,887.32 0.002% - 0.000% - 0.000% - 0.000%
b. Galian Tanah m3 25,715.00 91,999,784.05 3,577.67 0.020% - 0.000% - 0.000% - 0.000%
c. Urugan Kembali m3 11,740.00 42,503,143.80 3,620.37 0.009% - 0.000% - 0.000% - 0.000%
d. Timbunan Tanah dari Material Setempat pilihan m3 33,241.00 149,969,098.37 4,511.57 0.032% - 0.000% - 0.000% - 0.000%
e. Beton K-225 m3 1,401,030.00 2,034,617,796.90 1,452.23 0.432% - 0.000% - 0.000% - 0.000%
f. Tulangan Beton (pemotongan, pembengkokan dan pemasangan) ton 20,630,445.00 4,041,710,479.95 195.91 0.858% - 0.000% - 0.000% - 0.000%
g. Bekisting tipe non expose F1 (termasuk perancah dan pembongkaran) m2 181,492.00 869,914,749.96 4,793.13 0.185% - 0.000% - 0.000% - 0.000%
h. Pengadaan dan Pemasangan U-Ditch uk 50 x 50 cm (Pabrikasi dan Pemasangan) m' 761,057.00 490,881,765.00 645.00 0.104% - 0.000% - 0.000% - 0.000%
i. Lapis penetrasi hotmix, t = 5cm m2 228,171.00 1,581,480,581.52 6,931.12 0.336% - 0.000% - 0.000% - 0.000%
j. Lapis Pondasi Atas / Base Course, t = 20 cm m3 519,023.00 846,931,350.94 1,631.78 0.180% - 0.000% - 0.000% - 0.000%
k. Lapis Pondasi Bawah / Sub-Base Course, t = 30 m3 493,042.00 987,119,388.20 2,002.10 0.209% - 0.000% - 0.000% - 0.000%

SUB TOTAL 2.1.9 ### 0.572% - 0.000% - 0.000% - 0.000%

TOTAL II ### ### 99.441% 7.220% 0.370% 7.590%

TOTAL LANGSUNG / KONSTRUKSI ( I + II ) ### ### 100.000% 7.392% 0.372% 7.764%


7.764

DIPERIKSA
DI SETUJUI & DIPERIKSA, KONSULTAN SUPERVISI DIBUAT OLEH,
SNVT PEMBANGUNAN BENDUNGAN BBWS BRANTAS PT. Innako Internasional Konsultindo NINDYA MINARTA KSO
BALAI WILAYAH SUNGAI BRANTAS KSO PT. Bina Karya

Hery Suyono Ir. Hartono, MT Edi Purnomo


Pengawas Utama Team Leader Site Manager
LAPORAN PROGRES MINGGUAN
PEKERJAAN PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB.TRENGGALEK (MYC)

PROYEK : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC)


PEMILIK : BBWS BRANTAS SNVT PEMBANGUNAN BENDUNGAN
NOMOR KONTRAK : IK.02.04-Am.10.2/SP.02/2018
TANGGAL KONTRAK : 27 Desember 2018
KONTRAKTOR : NINDYA MINARTA KSO
LAPORAN TANGGAL : Trenggalek, 01 Oktober 2019 s/d 07 Oktober 2019
RENCANA PEKERJAAN : 10.472 %
REALISASI PEKERJAAN : 7.788 %
DEVIASI : -2.684 %
MINGGU KE : 000 35

Volume BOBOT ADD-1


No. Jenis Pekerjaan Sat Volume BOBOT (%) S/D Minggu Lalu Minggu ini S/D Minggu ini
ADD-1 (%)
(1) (2). (3) (4) (5) (6) (7) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan konstruksi Ls 1.000 1.00 0.128% 0.128% 0.500 0.064% - 0.000% 0.500 0.064%
1.2 Penyelenggaraan K3 Konstruksi Ls 1.000 1.00 0.431% 0.431% 0.250 0.108% 0.005 0.002% 0.255 0.110%
SUB TOTAL 2.1.1 18.672% 20.035% 0.172% 0.002% 0.174%
II PEKERJAAN SIPIL/KONSTRUKSI
2.1 BANGUNAN PELIMPAH
2.1.1 Pekerjaan Tanah :
a. Pembersihan m2 44,052.86 62,954.90 0.048% 0.068% 45,200.00 0.049% 0.000% 45,200.000 0.049%
b. Galian Tanah m3 1,358,345.07 747,694.40 7.412% 4.080% 559,891.44 3.055% 6,313.00 0.034% 566,204.444 3.089%
c. Galian Batu Lapuk (Stockpile) m3 128,247.24 128,247.24 1.660% 1.660% 128,247.24 1.660% 0.000% 128,247.240 1.660%
c.c. Galian Batu Lapuk (Stockpile) m3 281,143.76 2.052% 61,781.64 0.451% 0.000% 61,781.640 0.451%
d. Penggalian Batu Keras (dengan peledakan) m3 421,214.78 538,392.72 9.028% 11.539% 64,300.14 1.378% 8,430.464 0.181% 72,730.604 1.559%
e. Urugan Kembali (dipadatkan dan free draining) m3 60,548.26 89,754.60 0.151% 0.224% - 0.000% - 0.000% - 0.000%
f. Batang angker/anchor bars D25 (L=2m) termasuk boring dan air semen bh 3,173.00 3,721.00 0.118% 0.138% - 0.000% - 0.000% - 0.000%
g. Drainase Pipa PVC (perforated) dia. 6" m 2,600.00 2,600.00 0.256% 0.256% - 0.000% - 0.000% - 0.000%
g.g. Drainase Pipa PVC (perforated) dia. 6" 413.71 0.019% - 0.000% 0.000% - 0.000%

SUB TOTAL 2.1.1 18.672% 20.035% 6.593% 0.215% 6.808%

2.1.2 Pekerjaan Beton :


a. Beton K-225 m3 43,489.72 34,850.00 12.929% 10.360% 264.56 0.079% 127.00 0.038% 391.56 0.116%
b. Beton K-350 m3 24,585.21 17,503.39 7.986% 5.686% - 0.000% - 0.000% - 0.000%
c. Tulangan Beton (pemotongan, pembengkokan dan
ton 5,773.81 2,152.33 25.275% 9.422% 13.88 0.061% 6.90 0.030% 20.78 0.091%
pemasangan)
d. Bekisting tipe expose F2 (termasuk perancah dan
m2 26,370.27 27,387.23 0.893% 0.928% - 0.000% - 0.000% - 0.000%
pembongkaran
e. Bekisting tipe) non expose F1 (termasuk perancah dan
m2 13,421.75 18,572.57 0.517% 0.715% 992.19 0.038% 469.00 0.018% 1,461.19 0.056%
pembongkaran
f. Bekisting tipe )expose F4 (termasuk perancah dan
m2 537.97 1,639.06 0.027% 0.084% - 0.000% - 0.000% - 0.000%
pembongkaran )
g. Shotcrete t = 10 cm (termasuk wiremesh) m2 25,682.72 79,167.74 3.657% 11.272% - 0.000% - 0.000% - 0.000%
h. Plat baja dan aksesorisnya bh 3,616.00 8,207.00 0.125% 0.284% - 0.000% - 0.000% - 0.000%
i. Pipa PVC Perforated dia. 50 mm ( termasuk Geotekstile
bh 5,426.00 5,426.00 0.015% 0.015% - 0.000% - 0.000% - 0.000%
dan
i.i pemasangan
Pipa )
PVC Perforated dia. 50 mm ( termasuk Geotekstile
bh 10,778.00 0.027% 0.000% 0.000% 0.000%
dan pemasangan )
j. Pemboran Anchor Shotcrete m 5,455.00 8,207.00 0.324% 0.488% - 0.000% - 0.000% - 0.000%
k. Pemboran Rock bolt m 21,696.00 49,242.00 1.313% 2.979% - 0.000% - 0.000% - 0.000%
l. Pemboran Pipa PVC Perforated m 1,899.10 5,671.40 0.118% 0.353% - 0.000% - 0.000% - 0.000%
m. Tulangan Beton Anchor Shotcrete(Pemotongan,
ton 93.87 205.34 0.411% 0.899% - 0.000% - 0.000% - 0.000%
Pembengkokan dan Pemasangan)
n. Beton K-175 m3 1,200.00 1,200.00 0.300% 0.300% - 0.000% - 0.000% - 0.000%

SUB TOTAL 2.1.2 53.890% 43.811% 0.178% 0.086% 0.264%

2.1.3 Drilling dan Grouting :


a. Pemboran lubang Curtain Grouting m 1,340.00 1,340.00 0.126% 0.126% - 0.000% - 0.000% - 0.000%
b. Pemboran Sub Curtain Grouting m 590.00 590.00 0.036% 0.036% - 0.000% - 0.000% - 0.000%
c. Grouting termasuk material dan peralatan ton 1,913.56 1,913.56 1.218% 1.218% - 0.000% - 0.000% - 0.000%
f. Single Water Presure test test 358.00 358.00 0.022% 0.022% - 0.000% - 0.000% - 0.000%
g. Double Water Presure test test 28.00 28.00 0.002% 0.002% - 0.000% - 0.000% - 0.000%
h. Pemasangan Pipa pelindung m 157.50 157.50 0.001% 0.001% - 0.000% - 0.000% - 0.000%
i. Penutupan Lubang Grouting ton 4.47 4.47 0.002% 0.002% - 0.000% - 0.000% - 0.000%
j. Redrilling m 203.00 203.00 0.025% 0.025% - 0.000% - 0.000% - 0.000%
k. Pemboran inti untuk Pilot & Check Hole m 100.00 100.00 0.012% 0.012% - 0.000% - 0.000% - 0.000%
l. Investigasi Geologi dan Mekanika Tanah (termasuk Tes Lab. Mektan & Batuan ) Ls 1.000 1.00 0.072% 0.072% 1.000 0.072% 0.000% 1.000 0.072%

SUB TOTAL 2.1.3 1.517% 1.517% 0.072% 0.000% 0.072%

2.1.4 Pekerjaan Perbaikan Pondasi :


a. Bronjong m3 9,403.39 11,956.78 1.561% 1.985% 247.00 0.041% 266.00 0.044% 513.00 0.085%
b. Geotekstile m2 28,457.54 30,641.92 0.313% 0.337% 1,616.50 0.018% 495.75 0.006% 2,112.25 0.023%
c. Pasangan Batu Kali (1Pc : 3Ps) m3 218.93 218.93 0.050% 0.050% - 0.000% - 0.000% - 0.000%
e. Joint Filler m2 5,231.62 4,667.32 0.194% 0.173% - 0.000% - 0.000% - 0.000%
f. PVC Waterstop, l=300 mm m 2,253.00 2,253.00 0.130% 0.130% - 0.000% - 0.000% - 0.000%
f.f. PVC Waterstop, l=300 mm m 1,089.54 0.033% 0.000% 0.000% 0.000%
g. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m 5,780.00 9,719.60 1.915% 3.220% 312.00 0.103% - 0.000% 312.00 0.103%
h. Pengeboran Batu untuk Bore Pile dia. 80 cm m 8,670.00 14,579.40 4.736% 7.965% - 0.000% - 0.000% - 0.000%
i. Beton K-225 m3 13,931.00 13,370.97 4.141% 3.975% 156.83 0.047% 18.87 0.006% 175.70 0.052%
j. Tulangan Beton (pemotongan, pembengkokan dan
ton 1,916.04 2,788.73 8.388% 12.208% 37.45 0.164% - 0.000% 37.45 0.164%
pemasangan)
k. Bekisting tipe expose F2 (termasuk perancah dan
m2 16,825.65 872.96 0.570% 0.030% - 0.000% - 0.000% - 0.000%
pembongkaran)
l. Riprap m3 852.20 753.01 0.053% 0.047% - 0.000% - 0.000% - 0.000%
m. Pengadaan dan Pemasangan U-Ditch uk 50 x 50 cm
m 3,746.43 4,010.34 0.605% 0.648% - 0.000% - 0.000% - 0.000%
(Pabrikasi
n. Pengadaan dan Pemasangan U-Ditch uk 120 x 120 cm
m 1,084.00 1,180.11 0.637% 0.693% - 0.000% - 0.000% - 0.000%
(Pabrikasi

SUB TOTAL 2.1.4 23.293% 31.492% 0.373% 0.055% 0.428%

2.1.5 Pekerjaan Jembatan (2 unit) :


a. Beton K-225 m3 151.98 474.71 0.045% 0.141% 16.13 0.005% 127.00 0.038% 143.13 0.043%
b. Tulangan Beton (pemotongan, pembengkokan dan
ton 38.68 44.70 0.169% 0.196% - 0.000% - 0.000% - 0.000%
pemasangan)
c. Bekisting tipe expose F2 (termasuk perancah dan
m2 686.92 1,094.07 0.023% 0.037% - 0.000% - 0.000% - 0.000%
pembongkaran
d. Bekisting tipe) non expose F1 (termasuk perancah dan
m2 61.76 81.26 0.002% 0.003% - 0.000% - 0.000% - 0.000%
pembongkaran)
e. Elastomer bh 8.00 8.00 0.001% 0.001% - 0.000% - 0.000% - 0.000%
f. Hand rail m 195.20 198.40 0.025% 0.025% - 0.000% - 0.000% - 0.000%
g. Pipa Drainasi PVC Ø 4" m 44.00 48.00 0.002% 0.002% - 0.000% - 0.000% - 0.000%
h. Expansion Joint m 28.00 28.00 0.014% 0.014% - 0.000% - 0.000% - 0.000%
i. Pasangan Batu kali (1PC : 4Ps) m3 12.20 12.22 0.002% 0.002% - 0.000% - 0.000% - 0.000%
j. Plesteran t=1.5cm (1PC : 3Ps) m2 15.72 19.44 0.000% 0.000% - 0.000% - 0.000% - 0.000%
k. Siaran (1PC : 2Ps) m2 36.96 52.00 0.000% 0.001% - 0.000% - 0.000% - 0.000%
l. Timbunan Tanah dipadatkan kembali m3 3,842.00 8,272.21 0.012% 0.026% - 0.000% - 0.000% - 0.000%
m. Lapis penetrasi hotmix, t = 5cm m3 250.00 220.08 0.012% 0.011% - 0.000% - 0.000% - 0.000%

SUB TOTAL 2.1.5 0.309% 0.459% 0.005% 0.038% 0.043%


2.1.6 Pekerjaan Jalan Inspeksi
a. Lapis penetrasi hotmix, t = 5cm m2 6,000.00 6,147.24 0.290% 0.298% - 0.000% - 0.000% - 0.000%
b. Lapis Pondasi Atas / Base Course, t = 20 cm m3 2,200.00 2,200.00 0.242% 0.242% - 0.000% - 0.000% - 0.000%
b.b. Lapis Pondasi Atas / Base Course, t = 20 cm m3 2,063.66 0.126% 0.000% 0.000% 0.000%
c. Lapis Pondasi Bawah / Sub-Base Course, t = 30 m3 3,300.00 3,300.00 0.345% 0.345% - 0.000% - 0.000% - 0.000%
c.c. Lapis Pondasi Bawah / Sub-Base Course, t = 30 m3 3,095.49 0.187% 0.000% 0.000% 0.000%
d. Beton K-225 m3 218.16 262.56 0.065% 0.078% - 0.000% - 0.000% - 0.000%
e. Tulangan Beton (pemotongan, pembengkokan dan
ton 15.27 18.38 0.067% 0.080% - 0.000% - 0.000% - 0.000%
pemasangan)
f. Bekisting tipe expose F2 (termasuk perancah dan
m2 473.52 1,053.83 0.016% 0.036% - 0.000% - 0.000% - 0.000%
pembongkaran)

SUB TOTAL 2.1.6 1.026% 1.392% - 0.000% - 0.000% - 0.000%

2.1.7 Pekerjaan Helipad


a. Lapis penetrasi hotmix, t = 5cm m2 1,600.00 1,600.00 0.077% 0.077% - 0.000% - 0.000% - 0.000%
b. Lapis Pondasi Atas / Base Course, t = 20 cm m3 320.00 320.00 0.035% 0.035% - 0.000% - 0.000% - 0.000%
c. Lapis Pondasi Bawah / Sub-Base Course, t = 30 m3 480.00 480.00 0.050% 0.050% - 0.000% - 0.000% - 0.000%

SUB TOTAL 2.1.7 0.163% 0.163% - 0.000% - 0.000% - 0.000%

2.1.8 Pekerjaan Lain-lain


a. Alat Pencatat Gempa Terintegrasi Dengan Jaringan BMKG Unit 1.00 1.00 0.572% 0.572% - 0.000% - 0.000% - 0.000%

SUB TOTAL 2.1.8 0.572% 0.572% - 0.000% - 0.000% - 0.000%

TOTAL II 99.441% 99.441% 7.220% 0.394% 7.614%

TOTAL LANGSUNG / KONSTRUKSI ( I + II ) 100.000% 100.000% 7.392% 0.397% 7.7884%

DIPERIKSA
DI SETUJUI & DIPERIKSA, KONSULTAN SUPERVISI DIBUAT OLEH,
SNVT PEMBANGUNAN BENDUNGAN BBWS BRANTAS PT. Inakko Internasional Konsulindo NINDYA MINARTA KSO
BALAI WILAYAH SUNGAI BRANTAS KSO PT. Bina Karya

Hery Suyono Carsa Kusumaatmaja Edi Purnomo


Pengawas Utama TA Quantity Surveyor Deputy Project Manager
LAPORAN PROGRES MINGGUAN
PEKERJAAN PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB.TRENGGALEK (MYC)

PROYEK : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC)


PEMILIK : BBWS BRANTAS SNVT PEMBANGUNAN BENDUNGAN
NOMOR KONTRAK : IK.02.04-Am.10.2/SP.02/2018
TANGGAL KONTRAK : 27 Desember 2018
KONTRAKTOR : NINDYA MINARTA KSO
LAPORAN TANGGAL : Trenggalek, 01 Oktober 2019 s/d 07 Oktober 2019
RENCANA PEKERJAAN : 55.491 %
REALISASI PEKERJAAN : 41.272 %
DEVIASI : -14.219 %
MINGGU KE : 000 35

Harga Satuan
No. Jenis Pekerjaan Sat Volume Volume ADD-1 Total Biaya (Rp) Total Biaya ADD-1(Rp) BOBOT (%) S/D Minggu Lalu Minggu ini S/D Minggu ini
(Rp)
(1) (2). (3) (4) (4) (5) (6) (7) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan konstruksi Ls 0.956 0.600 603,015,000.00 576,246,243.00 361,809,000.00 0.407% 0.500 0.339% - 0.000% 0.500 0.339%
1.2 Penyelenggaraan K3 Konstruksi Ls 0.531 0.333 2,031,450,000.00 1,078,483,795.16 677,150,000.00 0.761% 0.250 0.571% 0.005 0.012% 0.255 0.583%

TOTAL I 1,654,730,038.16 1,038,959,000.00 1.168% 0.910% 0.012% 0.922%

II PEKERJAAN SIPIL/KONSTRUKSI
2.1 BANGUNAN PELIMPAH
2.1.1 Pekerjaan Tanah :
a. Pembersihan m2 100,267.060 62,954.900 5,104.00 511,763,072.71 321,321,809.60 0.361% 45,200.000 0.259% - 0.000% 45,200.000 0.259%
b. Galian Tanah m3 1,190,838.501 747,694.397 25,715.00 30,622,412,047.43 19,226,961,416.47 21.620% 559,891.444 16.189% 6,313.000 0.183% 566,204.444 16.372%
c. Galian Batu Lapuk (Stockpile) m3 204,256.915 128,247.240 60,991.00 12,457,833,513.78 7,821,927,414.84 8.795% 128,247.240 8.795% - 0.000% 128,247.240 8.795%
c.c. Galian Batu Lapuk (Stockpile) m3 281,143.760 34,400.00 9,671,345,344.00 10.875% 61,781.640 2.390% - 0.000% 61,781.640 2.390%
d. Penggalian Batu Keras (dengan peledakan) m3 511,809.020 321,350.659 101,005.00 51,695,270,106.38 32,458,023,300.38 36.497% 64,300.140 7.303% 8,430.464 0.958% 72,730.604 8.260%
e. Urugan Kembali (dipadatkan dan free draining) m3 - - 11,740.00 - - 0.000% - - -
f. Batang angker/anchor bars D25 (L=2m) termasuk boring dan air semen bh 658.485 413.444 174,890.00 115,162,445.73 72,307,298.89 0.081% - 0.000% - 0.000% - 0.000%
g. Drainase Pipa PVC (perforated) dia. 6" m 207.049 130.000 464,280.00 96,128,478.67 60,356,400.00 0.068% - 0.000% - 0.000% - 0.000%
g.g. Drainase Pipa PVC (perforated) dia. 6" m 20.686 211,000.00 4,364,640.50 0.005% - 0.000% - 0.000% - 0.000%

SUB TOTAL 2.1.1 95,498,569,664.70 69,636,607,624.68 78.303% 34.937% 1.140% 36.077%

2.1.2 Pekerjaan Beton :


a. Beton K-225 m3 4,826.515 3,030.435 1,401,030.00 6,762,092,668.59 4,245,730,043.48 4.774% 264.565 0.417% 127.000 0.200% 391.565 0.617%
b. Beton K-350 m3 - - 1,530,823.00 - - 0.000% - - -
c. Tulangan Beton (pemotongan, pembengkokan dan
ton 77.909 48.917 20,630,445.00 1,607,287,323.93 1,009,171,038.34 1.135% 13.877 0.322% 6.900 0.160% 20.777 0.482%
pemasangan)
d. Bekisting tipe expose F2 (termasuk perancah dan
m2 - - 159,663.00 - - 0.000% - - -
pembongkaran
e. Bekisting tipe) non expose F1 (termasuk perancah dan
m2 672.277 422.104 181,492.00 122,012,845.36 76,608,474.42 0.086% 992.186 0.202% 469.000 0.096% 1,461.186 0.298%
pembongkaran
f. Bekisting tipe )expose F4 (termasuk perancah dan
m2 - - 240,516.00 - - 0.000% - - -
pembongkaran )
g. Shotcrete t = 10 cm (termasuk wiremesh) m2 - - 671,011.00 - - 0.000% - - -
h. Plat baja dan aksesorisnya bh - - 162,800.00 - - 0.000% - - -
i. Pipa PVC Perforated dia. 50 mm ( termasuk Geotekstile
bh - - 13,096.00 - - 0.000% - - -
dan
i.i pemasangan
Pipa )
PVC Perforated dia. 50 mm ( termasuk Geotekstile
bh - - 0.000% - - -
dan pemasangan )
j. Pemboran Anchor Shotcrete m - - 280,132.00 - - 0.000% - - -
k. Pemboran Rock bolt m - - 285,124.00 - - 0.000% - - -
l. Pemboran Pipa PVC Perforated m - - 292,951.00 - - 0.000% - - -
m. Tulangan Beton Anchor Shotcrete(Pemotongan,
ton - - 20,630,445.00 - - 0.000% - - -
Pembengkokan dan Pemasangan)
n. Beton K-175 m3 - - 1,176,720.00 - - 0.000% - - -

SUB TOTAL 2.1.2 8,491,392,837.87 5,331,509,556.23 5.995% 0.941% 0.456% 1.397%

2.1.3 Drilling dan Grouting :


a. Pemboran lubang Curtain Grouting m - - 442,516.00 - - 0.000% - - -
b. Pemboran Sub Curtain Grouting m - - 283,635.00 - - 0.000% - - -
c. Grouting termasuk material dan peralatan ton - - 3,000,000.00 - - 0.000% - - -
f. Single Water Presure test test - - 290,000.00 - - 0.000% - - -
g. Double Water Presure test test - - 390,000.00 - - 0.000% - - -
h. Pemasangan Pipa pelindung m - - 39,000.00 - - 0.000% - - -
i. Penutupan Lubang Grouting ton - - 1,950,000.00 - - 0.000% - - -
j. Redrilling m - - 590,000.00 - - 0.000% - - -
k. Pemboran inti untuk Pilot & Check Hole m - - 575,000.00 - - 0.000% - - -
l. Investigasi Geologi dan Mekanika Tanah (termasuk Tes Lab. Mektan & Batuan Ls 1.593 1.000 340,000,000.00 541,511,467.70 340,000,000.00 0.382% 1.000 0.382% - 0.000% 1.000 0.382%

SUB TOTAL 2.1.3 541,511,467.70 340,000,000.00 0.382% 0.382% 0.000% 0.382%

2.1.4 Pekerjaan Perbaikan Pondasi :


a. Bronjong m3 8,243.337 5,175.762 782,320.00 6,448,927,239.48 4,049,102,174.55 4.553% 247.000 0.217% 266.000 0.234% 513.000 0.451%
b. Geotekstile m2 16,267.599 10,213.973 51,816.00 842,921,914.48 529,247,242.24 0.595% 1,616.500 0.094% 495.750 0.029% 2,112.250 0.123%
c. Pasangan Batu Kali (1Pc : 3Ps) m3 - - 1,065,724.00 - - 0.000% - - -
e. Joint Filler m2 337.889 212.151 175,000.00 59,130,518.46 37,126,409.09 0.042% - 0.000% - 0.000% - 0.000%
f. PVC Waterstop, l=300 mm m 163.105 102.409 272,639.00 44,468,781.79 27,920,712.14 0.031% - 0.000% - 0.000% - 0.000%
f.f. PVC Waterstop, l=300 mm m 49.525 - 0.000% - - -
g. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m 1,290.018 809.967 1,561,129.00 2,013,885,054.23 1,264,462,452.37 1.422% 312.000 0.548% - 0.000% 312.000 0.548%
h. Pengeboran Batu untuk Bore Pile dia. 80 cm m 1,161.017 728.970 2,574,504.00 2,989,041,658.24 1,876,736,180.88 2.110% - 0.000% - 0.000% - 0.000%
i. Beton K-225 m3 1,064.784 668.548 1,401,030.00 1,491,794,819.80 936,656,504.95 1.053% 156.828 0.247% 18.868 0.030% 175.696 0.277%
j. Tulangan Beton (pemotongan, pembengkokan dan
ton 222.078 139.437 20,630,445.00 4,581,564,552.59 2,876,637,044.24 3.235% 37.455 0.869% - 0.000% 37.455 0.869%
pemasangan)
k. Bekisting tipe expose F2 (termasuk perancah dan
m2 - - 159,663.00 - - 0.000% - - -
pembongkaran)
l. Riprap m3 - - 291,459.00 - - 0.000% - - -
m. Pengadaan dan Pemasangan U-Ditch uk 50 x 50 cm
m - - 761,057.00 - - 0.000% - - -
(Pabrikasi
n. Pengadaan dan Pemasangan U-Ditch uk 120 x 120 cm
m - - 2,768,406.00 - - 0.000% - - -
(Pabrikasi

SUB TOTAL 2.1.4 18,471,734,539.08 11,597,888,720.46 13.041% 1.975% 0.293% 2.268%

2.1.5 Pekerjaan Jembatan (2 unit) :


a. Beton K-225 m3 378.031 237.355 1,401,030.00 529,632,419.27 332,541,475.65 0.374% 16.130 0.025% 127.000 0.200% 143.130 0.226%
b. Tulangan Beton (pemotongan, pembengkokan dan
ton 35.596 22.350 20,630,445.00 734,369,894.18 461,090,445.75 0.518% - 0.000% - 0.000% - 0.000%
pemasangan)
c. Bekisting tipe expose F2 (termasuk perancah dan
m2 871.252 547.035 159,663.00 139,106,729.55 87,341,249.21 0.098% - 0.000% - 0.000% - 0.000%
pembongkaran
d. Bekisting tipe) non expose F1 (termasuk perancah dan
m2 64.711 40.630 181,492.00 11,744,459.92 7,374,019.96 0.008% - 0.000% - 0.000% - 0.000%
pembongkaran)
e. Elastomer bh 6.371 4.000 600,000.00 3,822,433.89 2,400,000.00 0.003% - 0.000% - 0.000% - 0.000%
f. Hand rail m 157.994 99.200 595,000.00 94,006,390.79 59,024,000.00 0.066% - 0.000% - 0.000% - 0.000%
g. Pipa Drainasi PVC Ø 4" m 38.224 24.000 180,000.00 6,880,381.00 4,320,000.00 0.005% - 0.000% - 0.000% - 0.000%
h. Expansion Joint m 22.298 14.000 2,400,000.00 53,514,074.46 33,600,000.00 0.038% - 0.000% - 0.000% - 0.000%
i. Pasangan Batu kali (1PC : 4Ps) m3 - - 929,729.00 - - 0.000% - - -
j. Plesteran t=1.5cm (1PC : 3Ps) m2 - - 35,429.00 - - 0.000% - - -
k. Siaran (1PC : 2Ps) m2 - - 59,281.00 - - 0.000% - - -
l. Timbunan Tanah dipadatkan kembali m3 - - 15,072.00 - - 0.000% - - -
m. Lapis penetrasi hotmix, t = 5cm m3 - - 228,171.00 - - 0.000% - - -

SUB TOTAL 2.1.5 1,573,076,783.06 987,691,190.57 1.111% 0.025% 0.200% 0.226%

2.1.6 Pekerjaan Jalan Inspeksi


a. Lapis penetrasi hotmix, t = 5cm m2 - - 228,171.00 - - 0.000% - - -
b. Lapis Pondasi Atas / Base Course, t = 20 cm m3 - - 519,023.00 - - 0.000% - - -
b.b. Lapis Pondasi Atas / Base Course, t = 20 cm m3 - - 0.000% - - -
c. Lapis Pondasi Bawah / Sub-Base Course, t = 30 m3 - - 493,042.00 - - 0.000% - - -
c.c. Lapis Pondasi Bawah / Sub-Base Course, t = 30 m3 - - 0.000% - - -
d. Beton K-225 m3 - - 1,401,030.00 - - 0.000% - - -
e. Tulangan Beton (pemotongan, pembengkokan dan
ton - - 20,630,445.00 - - 0.000% - - -
pemasangan)
f. Bekisting tipe expose F2 (termasuk perancah dan
m2 - - 159,663.00 - - 0.000% - - -
pembongkaran)

SUB TOTAL 2.1.6 - - 0.000% 0.000% 0.000% 0.000%

2.1.7 Pekerjaan Helipad


a. Lapis penetrasi hotmix, t = 5cm m2 - - 228,171.00 - - 0.000% - - -
b. Lapis Pondasi Atas / Base Course, t = 20 cm m3 - - 519,023.00 - - 0.000% - - -
c. Lapis Pondasi Bawah / Sub-Base Course, t = 30 m3 - - 493,042.00 - - 0.000% - - -

SUB TOTAL 2.1.7 - - 0.000% 0.000% 0.000% 0.000%

2.1.8 Pekerjaan Lain-lain


a. Alat Pencatat Gempa Terintegrasi Dengan Jaringan BMKG Unit - - 2,695,000,000.00 - - 0.000% - - -

SUB TOTAL 2.1.8 - - 0.000% 0.000% 0.000% 0.000%

TOTAL II 124,576,285,292.41 87,893,697,091.94 98.832% 431,539.00 38.261% 8,126.99 2.089% 439,665.99 40.350%

TOTAL LANGSUNG / KONSTRUKSI ( I + II ) 141,641,332,727.00 88,932,656,091.94 100.000% 431,539.377 39.171% 8,126.994 2.101% 439,666.371 41.272%

PEJABAT PEMBUAT KOMITMEN KONSULTAN SUPERVISI DIBUAT OLEH,


SNVT PEMBANGUNAN BENDUNGAN BBWS BRANTAS PT. Inakko Internasional Konsulindo NINDYA MINARTA KSO
BALAI WILAYAH SUNGAI BRANTAS KSO PT. Bina Karya

YUDHATANTRA AHMADI, ST.MT. Chandra Adriawan, ST.MT Edi Purnomo


Kuasa KSO Team Leader Deputy Project Manager
LAPORAN HARIAN

Pekerjaan : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC) Hari ke : 273
Nomor Kontrak : IK.02.04-Am.10.2/SP.02/2018 Hari : Selasa
Tanggak Kontrak : 27 Desember 2018 Tanggal : 01 Oktober 2019
Penyedia Jasa : NINDYA-MINARTA KSO

Pekerjaan yang dikerjakan hari ini Tenaga Kerja Bahan bangunan Peralatan
No. Volume Jenis bahan Jumlah bahan Keterangan
Uraian Pekerjaan Keahlian Jumlah Jenis Jumlah
Pekerjaan yang digunakan yang digunakan

I PEKERJAAN PERSIAPAN - Site Manager 1.00 orang - batu kali 58.5 m3 - Water Pass 1.00 unit
1.1 Mobilisasi dan Demobilisasi Peralatan konstruksi - Ls - Pelaksana 2.00 orang - beton k-225 89.748 m3 - Total Station 2.00 unit
1.2 Penyelenggaraan K3 Konstruksi 0.001 Ls - Administrasi 1.00 orang - besi beton 3 ton - Excavator 13.00 unit
- Logistik 3.00 orang - Buldoser 3.00 unit
II PEKERJAAN SIPIL/KONSTRUKSI - Keamanan 3.00 orang - Dump truck 7.00 unit
2 BANGUNAN PELIMPAH - Juru Ukur 2.00 orang - Tronton 17.00 unit
2.1.1 Pekerjaan Tanah : - Pembantu Juru Ukur 4.00 orang - Excavator breaker 1.00 unit
a. Pembersihan m2 - Sopir 15.00 orang
b. Galian Tanah m3
d. Penggalian Batu Keras (dengan peledakan) 1,204.352 m3
2.1.4 Pekerjaan Perbaikan Pondasi :
a. Bronjong 45.000 m3
b. Geotekstile m2
2.1.5 Pekerjaan Jembatan (2 unit) :
o. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m
h. Pengeboran Batu untuk Bore Pile dia. 80 cm m
a. Beton K-225 18.868 m3
b. Tulangan Beton (pemotongan, pembengkokan dan pemasangan) Ton
2.1.2 Pekerjaan Beton :
a. Beton K-225 m3
c. Tulangan Beton (pemotongan, pembengkokan dan
ton
pemasangan)
e. Bekisting tipe non expose F1 (termasuk perancah dan
m2
pembongkaran )
2.1.5 Pekerjaan Jembatan (2 unit) :
a. Beton K-225 89.748 m3
b. Tulangan Beton (pemotongan, pembengkokan dan
3.000 Ton
pemasangan)
Jumlah 31 orang

Pekerjaan dimulai jam : 07:00 s/d 16:00 WIB Catatan Tentang Pekerjaan :
Kondisi cuaca : Cerah Belum adanya review design perkuatan lereng, galian belum bisa dilaksanakan.
Mendung Desain slope yang dilandaikan dari PKK Perencana belum keluar
Hujan Gerimis Kurangnya Lahan disposal
Hujan Lebat Galian terganggu karena Batcing Plant Paket 1 belum di bongkar

Diperiksa oleh, Diketahui Dibuat oleh


Direksi Pekerjaan Konsultan Supervisi

JEFRIANTO
KOORDINATOR PENGAWAS _______________________ FARID BUDIYANTO
INSPECTOR PELAKSANA
LAPORAN HARIAN

Pekerjaan : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC) Hari ke : 274
Nomor Kontrak : IK.02.04-Am.10.2/SP.02/2018 Hari : Rabu
Tanggak Kontrak : 27 Desember 2018 Tanggal : 02 Oktober 2019
Penyedia Jasa : NINDYA-MINARTA KSO

Pekerjaan yang dikerjakan hari ini Tenaga Kerja Bahan bangunan Peralatan
No. Volume Jenis bahan Jumlah bahan Keterangan
Uraian Pekerjaan Keahlian Jumlah Jenis Jumlah
Pekerjaan yang digunakan yang digunakan

I PEKERJAAN PERSIAPAN - Site Manager 1.00 orang - batu kali 70.20 m3 - Water Pass 1.00 unit
1.1 Mobilisasi dan Demobilisasi Peralatan konstruksi - Ls
- Pelaksana 2.00 orang - Geotextile 165.25 m2 - Total Station 2.00 unit
1.2 Penyelenggaraan K3 Konstruksi 0.001 Ls
- Administrasi 1.00 orang - Beton k-225 31.75 m3 - Excavator 13.00 unit
- Logistik 3.00 orang - besi beton 1.73 ton - Buldoser 3.00 unit
II PEKERJAAN SIPIL/KONSTRUKSI - Keamanan 3.00 orang - Multiplek 18 mm 15.61 Lbr - Dump truck 7.00 unit
2 BANGUNAN PELIMPAH - Juru Ukur 2.00 orang - Kayu Kelas III 1.17 m3 - Tronton 17.00 unit
2.1.1 Pekerjaan Tanah : - Pembantu Juru Ukur 4.00 orang - Paku 5-12 cm 15.63 kg - Excavator breaker 1.00 unit
a. Pembersihan m2 - Sopir 11.00 orang - Minyak Bekisting 23.45 ltr
b. Galian Tanah m3 - Kayu kelas II 0.78 m3
d. Penggalian Batu Keras (dengan peledakan) 1,204.352 m3 - Pipe Support 52.11 set
2.1.4 Pekerjaan Perbaikan Pondasi :
a. Bronjong 54.000 m3
b. Geotekstile 165.250 m2
2.1.5 Pekerjaan Jembatan (2 unit) :
o. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m
h. Pengeboran Batu untuk Bore Pile dia. 80 cm m
a. Beton K-225 m3
b. Tulangan Beton (pemotongan, pembengkokan dan pemasangan) Ton
2.1.2 Pekerjaan Beton :
a. Beton K-225 31.750 m3
c. Tulangan Beton (pemotongan, pembengkokan dan
1.725 ton
pemasangan)
e. Bekisting tipe non expose F1 (termasuk perancah dan
117.250 m2
pembongkaran )
2.1.5 Pekerjaan Jembatan (2 unit) :
a. Beton K-225 m3

Jumlah 27 orang

Pekerjaan dimulai jam : 07:00 s/d 16:00 WIB Catatan Tentang Pekerjaan :
Kondisi cuaca : Cerah Belum adanya review design perkuatan lereng belum bisa dilaksanakan.
Mendung Desain slope yang dilandaikan dari PKK Perencana belum keluar
Hujan Gerimis Kurangnya Lahan disposal
Hujan Lebat Galian terganggu karena Batcing Plant Paket 1 belum di bongkar

Diperiksa oleh, Diketahui Dibuat oleh


Direksi Pekerjaan Konsultan Supervisi

JEFRIANTO
KOORDINATOR PENGAWAS
JEFRIANTO
KOORDINATOR PENGAWAS _______________________ FARID BUDIYANTO
INSPECTOR PELAKSANA
LAPORAN HARIAN

Pekerjaan : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC) Hari ke : 275
Nomor Kontrak : IK.02.04-Am.10.2/SP.02/2018 Hari : Kamis
Tanggak Kontrak : 27 Desember 2018 Tanggal : 03 Oktober 2019
Penyedia Jasa : NINDYA-MINARTA KSO

Pekerjaan yang dikerjakan hari ini Tenaga Kerja Bahan bangunan Peralatan
No. Volume Jenis bahan Jumlah bahan Keterangan
Uraian Pekerjaan Keahlian Jumlah Jenis Jumlah
Pekerjaan yang digunakan yang digunakan

I PEKERJAAN PERSIAPAN - Site Manager 1.00 orang - batu kali 42.90 m3 - Water Pass 1.00 unit
1.1 Mobilisasi dan Demobilisasi Peralatan konstruksi - Ls - Pelaksana 2.00 orang - Geotextile 165.25 m2 - Total Station 2.00 unit
1.2 Penyelenggaraan K3 Konstruksi 0.001 Ls - Administrasi 1.00 orang - Beton k-225 31.75 m3 - Excavator 13.00 unit
- Logistik 3.00 orang - besi beton 1.73 ton - Buldoser 3.00 unit
II PEKERJAAN SIPIL/KONSTRUKSI - Keamanan 3.00 orang - Multiplek 18 mm 15.61 Lbr - Dump truck 7.00 unit
2 BANGUNAN PELIMPAH - Juru Ukur 2.00 orang - Kayu Kelas III 1.17 m3 - Tronton 17.00 unit
2.1.1 Pekerjaan Tanah : - Pembantu Juru Ukur 4.00 orang - Paku 5-12 cm 15.63 kg - Excavator breaker 1.00 unit
a. Pembersihan m2 - Sopir - orang - Minyak Bekisting 23.45 ltr
b. Galian Tanah m3 - Kayu kelas II 0.78 m3
d. Penggalian Batu Keras (dengan peledakan) 1,204.352 m3 - Pipe Support 52.11 set
2.1.4 Pekerjaan Perbaikan Pondasi :
a. Bronjong 33.000 m3
b. Geotekstile 165.250 m2
2.1.5 Pekerjaan Jembatan (2 unit) :
o. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m
h. Pengeboran Batu untuk Bore Pile dia. 80 cm m
a. Beton K-225 m3
b. Tulangan Beton (pemotongan, pembengkokan dan pemasangan) Ton
2.1.2 Pekerjaan Beton :
a. Beton K-225 31.750 m3
c. Tulangan Beton (pemotongan, pembengkokan dan
1.725 ton
pemasangan)
e. Bekisting tipe non expose F1 (termasuk perancah dan
117.250 m2
pembongkaran )
2.1.5 Pekerjaan Jembatan (2 unit) :
a. Beton K-225 m3
c. Tulangan Beton (pemotongan, pembengkokan dan
pemasangan)
Jumlah 16 orang

Pekerjaan dimulai jam : 07:00 s/d 16:00 WIB Catatan Tentang Pekerjaan :
Kondisi cuaca : Cerah Belum adanya review design perkuatan lereng belum bisa dilaksanakan.
Mendung Desain slope yang dilandaikan dari PKK Perencana belum keluar
Hujan Gerimis Kurangnya Lahan disposal
Hujan Lebat Galian terganggu karena Batcing Plant Paket 1 belum di bongkar

Diperiksa oleh, Diketahui Dibuat oleh


Direksi Pekerjaan Konsultan Supervisi

JEFRIANTO
KOORDINATOR PENGAWAS
JEFRIANTO
KOORDINATOR PENGAWAS _______________________ FARID BUDIYANTO
INSPECTOR PELAKSANA
LAPORAN HARIAN

Pekerjaan : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC) Hari ke : 276
Nomor Kontrak : IK.02.04-Am.10.2/SP.02/2018 Hari : Jumat
Tanggak Kontrak : 27 Desember 2018 Tanggal : 04 Oktober 2019
Penyedia Jasa : NINDYA-MINARTA KSO

Pekerjaan yang dikerjakan hari ini Tenaga Kerja Bahan bangunan Peralatan
No. Volume Jenis bahan Jumlah bahan Keterangan
Uraian Pekerjaan Keahlian Jumlah Jenis Jumlah
Pekerjaan yang digunakan yang digunakan

I PEKERJAAN PERSIAPAN - Site Manager 1.00 orang - batu kali 31.20 m3 - Water Pass 1.00 unit
1.1 Mobilisasi dan Demobilisasi Peralatan konstruksi - Ls - Pelaksana 2.00 orang - Geotextile 165.25 m2 - Total Station 2.00 unit
1.2 Penyelenggaraan K3 Konstruksi 0.001 Ls - Administrasi 1.00 orang - Beton k-225 31.75 m3 - Excavator 13.00 unit
- Logistik 3.00 orang - besi beton 1.73 ton - Buldoser 3.00 unit
II PEKERJAAN SIPIL/KONSTRUKSI - Keamanan 3.00 orang - Multiplek 18 mm 15.61 Lbr - Dump truck 7.00 unit
2 BANGUNAN PELIMPAH - Juru Ukur 2.00 orang - Kayu Kelas III 1.17 m3 - Tronton 17.00 unit
2.1.1 Pekerjaan Tanah : - Pembantu Juru Ukur 4.00 orang - Paku 5-12 cm 15.63 kg - Excavator breaker 1.00 unit
a. Pembersihan m2 - Sopir 11.00 orang - Minyak Bekisting 23.45 ltr
b. Galian Tanah m3 - Kayu kelas II 0.78 m3
d. Penggalian Batu Keras (dengan peledakan) 1,204.352 m3 - Pipe Support 52.11 set
2.1.4 Pekerjaan Perbaikan Pondasi :
a. Bronjong 24.000 m3
b. Geotekstile 165.250 m2
2.1.5 Pekerjaan Jembatan (2 unit) :
o. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m
h. Pengeboran Batu untuk Bore Pile dia. 80 cm m
a. Beton K-225 m3
b. Tulangan Beton (pemotongan, pembengkokan dan pemasangan) Ton
2.1.2 Pekerjaan Beton :
a. Beton K-225 31.750 m3
c. Tulangan Beton (pemotongan, pembengkokan dan
1.725 ton
pemasangan)
e. Bekisting tipe non expose F1 (termasuk perancah dan
117.250 m2
pembongkaran )
2.1.5 Pekerjaan Jembatan (2 unit) :
a. Beton K-225 m3

Jumlah 27 orang

Pekerjaan dimulai jam : 07:00 s/d 16:00 WIB Catatan Tentang Pekerjaan :
Kondisi cuaca : Cerah Belum adanya review design perkuatan lereng belum bisa dilaksanakan.
Mendung Desain slope yang dilandaikan dari PKK Perencana belum keluar
Hujan Gerimis Kurangnya Lahan disposal
Hujan Lebat Galian terganggu karena Batcing Plant Paket 1 belum di bongkar

Diperiksa oleh, Diketahui Dibuat oleh


Direksi Pekerjaan Konsultan Supervisi

JEFRIANTO
KOORDINATOR PENGAWAS
JEFRIANTO
KOORDINATOR PENGAWAS _______________________ FARID BUDIYANTO
INSPECTOR PELAKSANA
LAPORAN HARIAN

Pekerjaan : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC) Hari ke : 277
Nomor Kontrak : IK.02.04-Am.10.2/SP.02/2018 Hari : Sabtu
Tanggak Kontrak : 27 Desember 2018 Tanggal : 05 Oktober 2019
Penyedia Jasa : NINDYA-MINARTA KSO

Pekerjaan yang dikerjakan hari ini Tenaga Kerja Bahan bangunan Peralatan
No. Volume Jenis bahan Jumlah bahan Keterangan
Uraian Pekerjaan Keahlian Jumlah Jenis Jumlah
Pekerjaan yang digunakan yang digunakan

I PEKERJAAN PERSIAPAN - Site Manager 1.00 orang - batu kali 46.80 m3 - Water Pass 1.00 unit
1.1 Mobilisasi dan Demobilisasi Peralatan konstruksi - Ls - Pelaksana 2.00 orang - Geotextile 165.25 m2 - Total Station 2.00 unit
1.2 Penyelenggaraan K3 Konstruksi 0.001 Ls - Administrasi 1.00 orang - Beton k-225 31.75 m3 - Excavator 13.00 unit
- Logistik 3.00 orang - besi beton 1.73 ton - Buldoser 3.00 unit
II PEKERJAAN SIPIL/KONSTRUKSI - Keamanan 3.00 orang - Multiplek 18 mm 15.61 Lbr - Dump truck 7.00 unit
2 BANGUNAN PELIMPAH - Juru Ukur 2.00 orang - Kayu Kelas III 1.17 m3 - Tronton 17.00 unit
2.1.1 Pekerjaan Tanah : - Pembantu Juru Ukur 4.00 orang - Paku 5-12 cm 15.63 kg - Excavator breaker 1.00 unit
a. Pembersihan m2 - Sopir 11.00 orang - Minyak Bekisting 23.45 ltr
b. Galian Tanah m3 - Kayu kelas II 0.78 m3
d. Penggalian Batu Keras (dengan peledakan) 1,204.352 m3 - Pipe Support 52.11 set
2.1.4 Pekerjaan Perbaikan Pondasi :
a. Bronjong 36.000 m3
b. Geotekstile 165.250 m2
2.1.5 Pekerjaan Jembatan (2 unit) :
o. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m
h. Pengeboran Batu untuk Bore Pile dia. 80 cm m
a. Beton K-225 m3
b. Tulangan Beton (pemotongan, pembengkokan dan pemasangan) Ton
2.1.2 Pekerjaan Beton :
a. Beton K-225 31.750 m3
c. Tulangan Beton (pemotongan, pembengkokan dan
1.725 ton
pemasangan)
e. Bekisting tipe non expose F1 (termasuk perancah dan
117.250 m2
pembongkaran )
2.1.5 Pekerjaan Jembatan (2 unit) :
a. Beton K-225 m3

Jumlah 27 orang

Pekerjaan dimulai jam : 07:00 s/d 16:00 WIB Catatan Tentang Pekerjaan :
Kondisi cuaca : Cerah Belum adanya review design perkuatan lereng belum bisa dilaksanakan.
Mendung Desain slope yang dilandaikan dari PKK Perencana belum keluar
Hujan Gerimis Kurangnya Lahan disposal
Hujan Lebat Galian terganggu karena Batcing Plant Paket 1 belum di bongkar

Diperiksa oleh, Diketahui Dibuat oleh


Direksi Pekerjaan Konsultan Supervisi

JEFRIANTO
KOORDINATOR PENGAWAS _______________________ FARID BUDIYANTO
INSPECTOR PELAKSANA
LAPORAN HARIAN

Pekerjaan : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC) Hari ke : 278
Nomor Kontrak : IK.02.04-Am.10.2/SP.02/2018 Hari : Minggu
Tanggak Kontrak : 27 Desember 2018 Tanggal : 06 Oktober 2019
Penyedia Jasa : NINDYA-MINARTA KSO

Pekerjaan yang dikerjakan hari ini Tenaga Kerja Bahan bangunan Peralatan
No. Volume Jenis bahan Jumlah bahan Keterangan
Uraian Pekerjaan Keahlian Jumlah Jenis Jumlah
Pekerjaan yang digunakan yang digunakan

I PEKERJAAN PERSIAPAN - Site Manager 1.00 orang - batu kali 57.20 m3 - Water Pass 1.00 unit
1.1 Mobilisasi dan Demobilisasi Peralatan konstruksi - Ls - Pelaksana 2.00 orang - Total Station 2.00 unit
1.2 Penyelenggaraan K3 Konstruksi 0.001 Ls - Administrasi 1.00 orang - Excavator 13.00 unit
- Logistik 3.00 orang - Buldoser 3.00 unit
II PEKERJAAN SIPIL/KONSTRUKSI - Keamanan 3.00 orang - Dump truck 7.00 unit
2 BANGUNAN PELIMPAH - Juru Ukur 2.00 orang - Tronton 17.00 unit
2.1.1 Pekerjaan Tanah : - Pembantu Juru Ukur 4.00 orang - Excavator breaker 1.00 unit
a. Pembersihan m2 - Sopir 11.00 orang
b. Galian Tanah 5,102.00 m3
d. Penggalian Batu Keras (dengan peledakan) 1,204.352 m3
2.1.4 Pekerjaan Perbaikan Pondasi :
a. Bronjong 44.000 m3
b. Geotekstile m2
2.1.5 Pekerjaan Jembatan (2 unit) :
o. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m
h. Pengeboran Batu untuk Bore Pile dia. 80 cm m
a. Beton K-225 m3
b. Tulangan Beton (pemotongan, pembengkokan dan pemasangan) Ton
2.1.2 Pekerjaan Beton :
a. Beton K-225 m3
c. Tulangan Beton (pemotongan, pembengkokan dan
ton
pemasangan)
e. Bekisting tipe non expose F1 (termasuk perancah dan
m2
pembongkaran )
2.1.5 Pekerjaan Jembatan (2 unit) :
a. Beton K-225 m3

Jumlah 27 orang

Pekerjaan dimulai jam : 07:00 s/d 16:00 WIB Catatan Tentang Pekerjaan :
Kondisi cuaca : Cerah Belum adanya review design perkuatan lereng belum bisa dilaksanakan.
Mendung Desain slope yang dilandaikan dari PKK Perencana belum keluar
Hujan Gerimis Kurangnya Lahan disposal
Hujan Lebat Galian terganggu karena Batcing Plant Paket 1 belum di bongkar

Diperiksa oleh, Diketahui Dibuat oleh


Direksi Pekerjaan Konsultan Supervisi

JEFRIANTO
KOORDINATOR PENGAWAS
JEFRIANTO
KOORDINATOR PENGAWAS _______________________ FARID BUDIYANTO
INSPECTOR PELAKSANA
LAPORAN HARIAN

Pekerjaan : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC) Hari ke : 279
Nomor Kontrak : IK.02.04-Am.10.2/SP.02/2018 Hari : Senin
Tanggak Kontrak : 27 Desember 2018 Tanggal : 07 Oktober 2019
Penyedia Jasa : NINDYA-MINARTA KSO

Pekerjaan yang dikerjakan hari ini Tenaga Kerja Bahan bangunan Peralatan
No. Volume Jenis bahan Jumlah bahan Keterangan
Uraian Pekerjaan Keahlian Jumlah Jenis Jumlah
Pekerjaan yang digunakan yang digunakan

I PEKERJAAN PERSIAPAN - Site Manager 1.00 orang - batu kali 39.00 m3 - Water Pass 1.00 unit
1.1 Mobilisasi dan Demobilisasi Peralatan konstruksi - Ls - Pelaksana 2.00 orang - Total Station 2.00 unit
1.2 Penyelenggaraan K3 Konstruksi 0.001 Ls - Administrasi 1.00 orang - Excavator 13.00 unit
- Logistik 3.00 orang - Buldoser 3.00 unit
II PEKERJAAN SIPIL/KONSTRUKSI - Keamanan 3.00 orang - Dump truck 7.00 unit
2 BANGUNAN PELIMPAH - Juru Ukur 2.00 orang - Tronton 17.00 unit
2.1.1 Pekerjaan Tanah : - Pembantu Juru Ukur 4.00 orang - Excavator breaker 1.00 unit
a. Pembersihan m2 - Sopir 11.00 orang
b. Galian Tanah 1,211.00 m3
d. Penggalian Batu Keras (dengan peledakan) 1,204.352 m3
2.1.4 Pekerjaan Perbaikan Pondasi :
a. Bronjong 30.000 m3
b. Geotekstile m2
2.1.5 Pekerjaan Jembatan (2 unit) :
o. Pengeboran Tanah Untuk Bore Pile dia. 80 cm m
h. Pengeboran Batu untuk Bore Pile dia. 80 cm m
a. Beton K-225 m3
b. Tulangan Beton (pemotongan, pembengkokan dan pemasangan) Ton
2.1.2 Pekerjaan Beton :
a. Beton K-225 m3
c. Tulangan Beton (pemotongan, pembengkokan dan
ton
pemasangan)
e. Bekisting tipe non expose F1 (termasuk perancah dan
m2
pembongkaran )
2.1.5 Pekerjaan Jembatan (2 unit) :
a. Beton K-225 m3

Jumlah 27 orang

Pekerjaan dimulai jam : 07:00 s/d 16:00 WIB Catatan Tentang Pekerjaan :
Kondisi cuaca : Cerah Belum adanya review design perkuatan lereng belum bisa dilaksanakan.
Mendung Desain slope yang dilandaikan dari PKK Perencana belum keluar
Hujan Gerimis Kurangnya Lahan disposal
Hujan Lebat Galian terganggu karena Batcing Plant Paket 1 belum di bongkar

Diperiksa oleh, Diketahui Dibuat oleh


Direksi Pekerjaan Konsultan Supervisi

JEFRIANTO
KOORDINATOR PENGAWAS
JEFRIANTO
KOORDINATOR PENGAWAS _______________________ FARID BUDIYANTO
INSPECTOR PELAKSANA
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
DIREKTORAT JENDERAL SUMBER DAYA AIR
BALAI BESAR WILAYAH SUNGAI BRANTAS LAPORAN CUACA

SNVT PEMBANGUNAN BENDUNGAN BBWS BRANTAS


Jln. Jayengkusuma No 123 Tulungagung – Jawa Timur Telp. 0355-321013 / Fax. 0355-321014

PEKERJAAN : PEMBANGUNAN SPILLWAY BENDUNGAN TUGU DI KAB. TRENGGALEK (MYC)


KONTRAKTOR : NINDYA MINARTA KSO Minggu ke : 36
NO. KONTRAK : IK.02.04-Am.10.2/SP.02/2018
TANGGAL KONTRAK : 27 Desember 2018
HARI KERJA : 1083 Hari Tanggal :
01 Oktober 2019
S/D
07 Oktober 2019
J A M
TANGGAL CUACA
1 2 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
01 Oktober 2019 cerah
02 Oktober 2019 cerah
03 Oktober 2019 cerah
04 Oktober 2019 cerah
05 Oktober 2019 cerah
06 Oktober 2019 cerah
07 Oktober 2019 cerah

Trenggalek, 07 Oktober 2019


Keterangan :
Cerah Hujan = Hujan Ringan = Banjir
MENGETAHUI/MENYETUJUI, MENGETAHUI, DIBUAT OLEH :
DIREKSI PEKERJAAN KONSULTAN SUPERVISI PENYEDIA JASA
PT. Inakko Internasional Konsulindo KSO PT. Bina Karya NINDYA MINARTA KSO

Hery Suyono Ir.Hartono, MT Edi Purnomo


Pengawas Utama Team Leader Site Manager

Anda mungkin juga menyukai