Subtotal B 12,334.30
C MAINTENANCE COST
c.1. Preventive Maintenance Ls 1 1,113.89 1,113.89
c.2. Maintenance Ls 1 9,468.33 9,468.33
Subtotal C 10,582.22
D OTHER
d.1. Safety Ls 1 767.69 767.69
d.2. Cleaning Services Ls 2 75.00 150.00
d.3. Communication Ls 1 138.89 138.89
d.4. Biaya Lain Ls 1 55.56 55.56
d.5. Risk [ 0.5% x (Sub Tot A+B+C)] Ls 1 179.18 179.18
Subtotal D 1,291.31
Page 2 of 9
Analisa Harga Satuan-Potable Water
Code No. : A.II.3.b.
Subjek : Material & Consumable
Sub Objek : Chemical
Lokasi : WTP Sangatta Baru & WTP Tj. Bara
Kebutuhan Bahan Kimia per Bulan $6,704.34
Harga Satuan Jumlah Harga
No. Uraian Satuan Jumlah
( USD ) ( USD )
a. Aluminium Sulfat Sak 58 28.00 1,624.00
b. Soda Ash Sak 44.4 35.00 1,554.00
c. Ph Paper Box 18 20.88 375.84
d. Polymer Sak 2.72 365.00 992.80
e. Chlorine 70% Can 9.4 210.00 1,974.00
f. Analisa Alum
- Aluver 3 Al Bag 0.5 170.00 85.00
- Ascorbat acid Bag 0.5 98.70 49.35
- Bleaching 3 Bag 0.5 98.70 49.35
Sub Total Chemical 6,704.34
Page 4 of 9
Salary Operator Analisa Harga Satuan-Potable Water
4
- Basic Bln 1 1,750,000.00 1,750,000.00 194.44
- Tunjangan Shift III : Rp. 25.000,-/hari Bln 1 150,000.00 150,000.00 16.67
Jumlah hari Shift III : 6 Hari
- Tunjangan Hari Raya Bln 1 145,833.33 145,833.33 16.20
- Uang Makan : Rp. 15.000/hari Bln 1 15,000.00 15,000.00 1.67
- Uang Transport : Rp. Bln 1 - -
(dari rumah ke Kantor)
- Jamsostek : Rp. 30.000,-/bln Bln 1 30,000.00 30,000.00 3.33
- PPh : 3% dari Basic Bln 1 52,500.00 52,500.00 5.83
- Over Time (Jam/bln) : 70 Bln 1 505,780.35 505,780.35 56.20
Jumlah Personal : 12 Orang
294.35
5 Salary Roving Bln 1 2,200,000.00 2,200,000.00
- Tunjangan Jabatan : Rp. Bln 650,000.00 -
- Tunjangan Hari Raya : Rp. Bln 1 183,333.33 183,333.33
- Uang Makan : Rp. 12.500/hari Org 1 325,000.00 325,000.00
- Uang Transport : Rp. 7.000.- Bln 1 182,000.00 182,000.00
- Jamsostek : Rp. 50.000,-/bln Bln 1 60,000.00 60,000.00
- PPh : 3% dari Basic Bln 1 66,000.00 66,000.00
Jumlah Personal : 10 Orang
3,016,333.33 335.15
Estimate Biaya
Estimate Satuan Harga Satuan
No. U R A I A N
Vol / Qtt Jumlah USD
IDR
1 Preventive Maintenance
- Lubrication (Grease) 1 x/Bln 750,000.00 750,000.00
- Peminyakan 1 x/Bln 250,000.00 250,000.00
- Check setting 1 x/Bln 350,000.00 350,000.00
- Pengukuran Tegangan, Arus beban dan Tahanan Isolasi. 4 x/Bln 125,000.00 500,000.00
- Perawatan jalan inspeksi pipa 0.6 x/Bln 5,000,000.00 3,000,000.00
- Pembersihan Filter, Clarifier & Treated Water 0.6 x/Bln 7,500,000.00 4,500,000.00
- Pembersihan Lingkungan 1 x/Bln 675,000.00 675,000.00
10,025,000.00 1,113.89
2 Perbaikan / Penggantian Komponen
- Electromotor pompa 1 x/Bln 5,500,000.00 5,500,000.00
- Komponen panel kontrol pompa 1 x/Bln 1,250,000.00 1,250,000.00
- Valve & Accessories lain 1 x/Bln 3,500,000.00 3,500,000.00
- Pompa Fire & Hydrant & lainya 1.00 x/Bln 15,000,000.00 15,000,000.00
- Water Meter 1 x/Bln 1,500,000.00 1,500,000.00
- Pipa Distribusi 5 x/Bln 9,500,000.00 47,500,000.00
- Bearing pompa centrifugal 0.6 x/Bln 2,275,000.00 1,365,000.00
- Mechanical seal pompa centrifugal 0.6 x/Bln 2,250,000.00 1,350,000.00
- Pompa kimia (dozing pump) 0.6 x/Bln 7,500,000.00 4,500,000.00
- Cubicle box Panel Control 0.6 x/Bln 6,250,000.00 3,750,000.00
85,215,000.00 9,468.33
3 Other
- Telekomunikasi 1 Ls 1,250,000.00 1,250,000.00
- Lain-lain 1 Ls 500,000.00 500,000.00
1,750,000.00
Page 5 of 9
Analisa Harga Satuan-Potable Water
Code No. : A.II.3.e.
Subjek : Safety Equipment
Sub Objek : Personal Safety Equipment
Lokasi : OFFICE, STP & SWIMMING POOL
PPE per bulan $767.69
Harga Satuan Jumlah Harga
No. Uraian Satuan Jumlah
( Rp. ) ( Rp. ) ( USD )
1 Operator Org 12 125,833.33 1,510,000.00 167.78
- Seragam Kerja : 2 x/thn @ Rp.400.000,-
- Sepatu Safety : 2x/thn @ Rp. 325.000,-
- Kaca Mata : 1x / 6 bulan @Rp. 30.000,-
Jumlah : 125,833.33
2 WTP (Sangatta Baru & Tj. Bara) Bln 1 282,500.00 282,500.00 31.39
- Helmet safety : 1x / 1 tahun @ 150.000 x 3 Org
- Sarung Tangan karet : 1x / 3 bulan @ Rp. 160.000,-
- Life Jacket : 2x / thn @ Rp. 225.000,- x 3 Org
- Jas Hujan : 2 x (2x / thn) @ Rp. 75.000 x 3 Org
- P3K : 1 box / tahun @ Rp. 250.000,-
Jumlah : 282,500.00
3 Leading Hand & Helper Org 10 336,666.67 3,366,666.67 374.07
- Seragam Kerja : 2 x/thn @ Rp.400.000,-
- Sepatu Safety : 2x/thn @ Rp. 325.000,-
- Helmet safety : 1x / 1 tahun @ 150.000
- Sarung Tangan : 1x / 3 bulan @ Rp. 160.000,-
- Jas Hujan : 2 x /thn @ Rp. 75.000
- Kaca Mata : 1x / 6 bulan @Rp. 30.000,-
- Rompi : 2x/thn @ Rp. 250.000,-
- Life Jacket : 2x / thn @ Rp. 225.000,-
- Sepatu Boot : 1x / 6 bulan @ Rp. 2.400.000,-
Jumlah : 336,666.67
4 Roving Org 10 175,000.00 1,750,000.00 194.44
- Seragam Kerja : 2 x/thn @ Rp.400.000,-
- Sepatu Safety : 2x/thn @ Rp. 325.000,-
- Helmet safety
- Sarung Tangan
- Jas Hujan : 2 x /thn @ Rp. 75.000
- Kaca Mata
- Rompi : 2x/thn @ Rp. 250.000,-
- Life Jacket
- Sepatu Boot
Jumlah : 175,000.00
Sub Total PPE 6,909,166.67 767.69
Page 6 of 9
Tabel
NILAI DEPRESIASI BARANG / PERALATAN