HARGA
NO URAIAN SAT VOLUME UPAH & BAHAN
(Rp)
(Rp)
1 PEK. TANAH LANTAI 1
- Galian Tanah Untuk Poer Plat M3 53.760 Rp 4,838,400.00
Tenaga
Pekerja OH 48.38 Rp 100,000.00 Rp 4,838,400.00
- Bekisting
- Bekisting 2x Pakai M2 24.36 Rp 3,343,454.48
Tenaga
Pekerja OH 16.08 Rp 100,000.00 Rp 1,607,760.00
Tukang OH 8.04 Rp 150,000.00 Rp 1,205,820.00
Bahan
Kayu kelas III m3 0.97 Rp 1,747,591.30 Rp 1,702,852.96
Paku 5 cm – 12 cm kg 9.74 Rp 26,000.00 Rp 253,344.00
Balok kayu kelas II m3 0.37 Rp 2,000,000.00 Rp 730,800.00
Tripleks tebal 6 mm Lbr 8.53 Rp 82,000.00 Rp 699,132.00
Dolken kayu φ8-10cm-pjg 4 m Batang 48.72 Rp 10,000.00 Rp 487,200.00
- Bekisting
- Bekisting 2x Pakai M2 67.20 Rp 9,223,322.71
Tenaga
Pekerja OH 44.35 Rp 100,000.00 Rp 4,435,200.00
Tukang OH 22.18 Rp 150,000.00 Rp 3,326,400.00
Bahan
Kayu kelas III m3 2.69 Rp 1,747,591.30 Rp 4,697,525.41
Paku 5 cm – 12 cm kg 26.88 Rp 26,000.00 Rp 698,880.00
Balok kayu kelas II m3 1.01 Rp 2,000,000.00 Rp 2,016,000.00
Tripleks tebal 6 mm Lbr 23.52 Rp 82,000.00 Rp 1,928,640.00
Dolken kayu φ8-10cm-pjg 4 m Batang 134.40 Rp 10,000.00 Rp 1,344,000.00
- Bekisting
- Bekisting 2x Pakai M2 9.60 Rp 1,317,617.53
Tenaga
Pekerja OH 6.34 Rp 100,000.00 Rp 633,600.00
Tukang OH 3.17 Rp 150,000.00 Rp 475,200.00
Bahan
Kayu kelas III m3 0.38 Rp 1,747,591.30 Rp 671,075.06
Paku 5 cm – 12 cm kg 3.84 Rp 26,000.00 Rp 99,840.00
Balok kayu kelas II m3 0.14 Rp 2,000,000.00 Rp 288,000.00
Tripleks tebal 6 mm Lbr 3.36 Rp 82,000.00 Rp 275,520.00
Dolken kayu φ8-10cm-pjg 4 m Batang 19.20 Rp 10,000.00 Rp 192,000.00
- Bekisting
Bekisting 2x Pakai M2 112.813 Rp 15,483,721.62
Tenaga
Pekerja OH 74.46 Rp 100,000.00 Rp 7,445,625.00
Tukang OH 37.23 Rp 150,000.00 Rp 5,584,218.75
Bahan
Kayu kelas III m3 4.51 Rp 1,747,591.30 Rp 7,886,005.74
Paku 5 cm – 12 cm kg 45.13 Rp 26,000.00 Rp 1,173,250.00
Balok kayu kelas II m3 1.69 Rp 2,000,000.00 Rp 3,384,375.00
Tripleks tebal 6 mm Lbr 39.48 Rp 82,000.00 Rp 3,237,718.75
Dolken kayu φ8-10cm-pjg 4 m Batang 225.63 Rp 10,000.00 Rp 2,256,250.00
- Bekisting
- Bekisting 2x Pakai M2 52.43 Rp 7,196,113.24
Tenaga
Pekerja OH 34.60 Rp 100,000.00 Rp 3,460,380.00
Tukang OH 17.30 Rp 150,000.00 Rp 2,595,285.00
Bahan
Kayu kelas III m3 2.10 Rp 1,747,591.30 Rp 3,665,048.47
Paku 5 cm – 12 cm kg 20.97 Rp 26,000.00 Rp 545,272.00
Balok kayu kelas II m3 0.79 Rp 2,000,000.00 Rp 1,572,900.00
Tripleks tebal 6 mm Lbr 18.35 Rp 82,000.00 Rp 1,504,741.00
Dolken kayu φ8-10cm-pjg 4 m Batang 104.86 Rp 10,000.00 Rp 1,048,600.00
5 PEK. DINDING
- Lantai 1
- Pek. Rangka Dinding Baja Ringan Tasso 7.5x7.5 M2 179.00 Rp 22,192,420.00
Tenaga
Pekerja OH 35.80 Rp 100,000.00 Rp 3,580,000.00
Tukang OH 80.55 Rp 150,000.00 Rp 12,082,500.00
Bahan
C-75 , 0.8 M' 44.39 Rp 85,000.00 Rp 3,773,320.00
Baut (screw driver) Bh 5012.00 Rp 350.00 Rp 1,754,200.00
Dynabolt Bh 286.40 Rp 3,500.00 Rp 1,002,400.00
- Lantai 2
- Pek. Rangka Dinding Baja Ringan Tasso 7.5x7.5 M2 94.50 Rp 11,716,110.00
Tenaga
Pekerja OH 18.90 Rp 100,000.00 Rp 1,890,000.00
Tukang OH 42.53 Rp 150,000.00 Rp 6,378,750.00
Bahan
C-75 , 0.8 M' 23.44 Rp 85,000.00 Rp 1,992,060.00
Baut (screw driver) Bh 2646.00 Rp 350.00 Rp 926,100.00
Dynabolt Bh 151.20 Rp 3,500.00 Rp 529,200.00
7 PLESTERAN
- Kolom M2 76.80 Rp 4,079,056.90
Tenaga
Pekerja OH 23.04 Rp 100,000.00 Rp 2,304,000.00
Tukang OH 7.68 Rp 150,000.00 Rp 1,152,000.00
Bahan
Semen Portlan Kg 6.64 Rp 74,800.00 Rp 496,336.90
Pasir Pasang M3 0.46 Rp 275,000.00 Rp 126,720.00
8 PENGECETAN
- Kolom M2 76.80 Rp 2,080,512.00
Tenaga
Pekerja OH 1.54 Rp 100,000.00 Rp 153,600.00
Tukang OH 4.84 Rp 150,000.00 Rp 725,760.00
Bahan
Plamuur Kg 7.68 Rp 16,000.00 Rp 122,880.00
Cat Dasar Kg 7.68 Rp 39,000.00 Rp 299,520.00
Cat Penutup Kg 19.97 Rp 39,000.00 Rp 778,752.00
11 PEKERJAAN LISPLANK
- Pemasangan Rangka Hollow 40.40 mm M2 15.06 Rp 1,816,738.00
Tenaga
Pekerja OH 5.27 Rp 100,000.00 Rp 527,100.00
Tukang OH 5.27 Rp 150,000.00 Rp 790,650.00
Bahan
Hollow 40.40 mm M' 10.04 Rp 35,000.00 Rp 351,400.00
Baut (screw driver) Bh 421.68 Rp 350.00 Rp 147,588.00