SNI 2835:2008 S.C.

3 Galian tanah biasa sedalam ≤1m (Manual)


Tenaga Kerja
0.02500 MD Mandor 188,473 #VALUE!
0.75000 MD Pekerja 140,651 #VALUE!
Biaya / m³ (m kubik) 0

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN N: A.2.2.1.4 AHSP - A.2.2.1


KODE/ JENIS PEKERJ : Pengukuran dan Pemasangan Bouwplank
SATUAN PEMBAYARA: 1 M1

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.100 102,510.00 10,251.00
Tukang Kayu L.02 Org/Hari 0.100 143,916.00 14,391.60
Kepala Tukang L.03 Org/Hari 0.010 165,624.00 1,656.24
Mandor L.04 Org/Hari 0.005 122,208.00 611.04
JUMLAH TENAGA KERJA 26,909.88
B. BAHAN :
Kayu 5/7 Kelas III/ Da - M3 0.012 1,811,010.00 21,732.12
Paku Biasa 2" - 3" - Kg 0.020 23,517.00 470.34
Kayu Papan 2/30 - M1 0.007 1,656.24 11.59
JUMLAH HARGA BAHAN 22,214.05
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 49,123.93
E. Overhead & Profit 10% x D 4,912.39
F. Harga Satuan Pekerjaan(D + E) 54,036.33

S.D.2 1 m³ Pondasi batu kali / belah campuran 1 PC : 4 PP


Bahan/ Peralatan
1.20000 m³ Batu Kali Belah 15/20 c 267,145 #VALUE! #VALUE!
163.00000 kg Portland Cement 1,656 #VALUE! #VALUE!
0.52000 m³ Pasir PasanPasir Pasang 248,687 #VALUE! #VALUE!
Tenaga Kerja
1.50000 MD Pekerja 140,651 #VALUE! #VALUE!
0.75000 MD Tukang Batu 161,749 #VALUE! #VALUE!
0.07500 MD Kepala Tukang Batu 177,221 #VALUE! #VALUE!
0.07500 MD Mandor 188,473 #VALUE! #VALUE!
Biaya / m³ (m kubik) 719,867 359,715

S.E.38 1m² plesteran 1 PC : 4 PP, tebal 15mm


Bahan/ Peralatan
6.24000 kg Portland Cement 1,656 #VALUE! #VALUE!
0.02400 m³ Pasir PasanPasir Pasang 248,687 #VALUE! #VALUE!
Tenaga Kerja
0.01500 MD Mandor 188,473 #VALUE! #VALUE!
0.01500 MD Kepala Tukang Batu 177,221 #VALUE! #VALUE!
0.15000 MD Tukang Batu 161,749 #VALUE! #VALUE!
0.30000 MD Pekerja 140,651 #VALUE! #VALUE!
Biaya / m² (m persegi) 16,304 71,943

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN N: A.2.3.1.14.a AHSP - A.2.3.1


KODE/ JENIS PEKERJ : Pengurugan Tanah Timbunan
SATUAN PEMBAYARA: M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.250 120,000.00 30,000.00
Mandor L.04 Org/Hari 0.025 150,000.00 3,750.00
JUMLAH TENAGA KERJA 33,750.00
B. BAHAN :
Tanah Timbunan - M3 1.200 200,000.00 240,000.00
JUMLAH HARGA BAHAN 240,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 273,750.00
E. Overhead & Profit 10% x D 27,375.00
F. Harga Satuan Pekerjaan(D + E) 301,125.00

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN N: T.14.b1 T - 14


KODE/ JENIS PEKERJ : Pemadatan Tanah
SATUAN PEMBAYARA: M3
HARGA SATUAN JUMLAH HARGA
No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.500 102,510.00 51,255.00
Mandor L.04 Org/Hari 0.050 122,208.00 6,110.40
JUMLAH TENAGA KERJA 57,365.40
B. BAHAN :
- - - - -
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 57,365.40
E. Overhead & Profit 10% x D 5,736.54
F. Harga Satuan Pekerjaan(D + E) 63,101.94

S.G.18 Pembesian kolom, balok, ring balk dan sloof untuk besi beton ⌀ ≤ 12mm

Bahan/ Peralatan
1.05000 kg Besi Beton Polos 11,407 #VALUE! #VALUE!
0.02800 kg Kawat Beton 21,372 #VALUE! #VALUE!
Tenaga Kerja
0.00160 MD Mandor 188,473 #VALUE! #VALUE!
0.00160 MD Kepala Tukang Batu 177,221 #VALUE! #VALUE!
0.01600 MD Tukang Besi I (konstruksi) 161,749 #VALUE! #VALUE!
0.01600 MD Pekerja 140,651 #VALUE! #VALUE!
Biaya /Kg 12,576 5,424

SNI 7394:2008 S.G.5 Beton cor f'c = 14,5 Mpa, K 175, Slump 12 + 2 cm, w/c 0,66
Bahan/ Peralatan
326.00000 kg Portland Cement 1,656 #VALUE!
0.54286 m³ Pasir Beton 248,687 #VALUE!
0.76222 m³ Batu Koral/ Kerikil/ Bat 374,002 #VALUE!
0.21500 m³ Air tawar 26,423 #VALUE!
Tenaga Kerja
0.08300 MD Mandor 188,473 #VALUE!
0.02800 MD Kepala Tukang Batu 177,221 #VALUE!
0.27500 MD Tukang Batu 161,749 #VALUE!
1.65000 MD Pekerja 140,651 #VALUE!
Biaya / m³ ( m kubik) 965,708

S.G.21 1m² Bekisting untuk sloof


Bahan/ Peralatan
0.04500 m³ Kayu Kelas III 2,842,418 #VALUE! #VALUE!
0.30000 kg Paku 5cm dan 7cm 15,543 #VALUE! #VALUE!
0.10000 ltr Minyak Bekisting 19,429 #VALUE! #VALUE!
Tenaga Kerja
0.02600 MD Mandor 188,473 #VALUE! #VALUE!
0.02600 MD Kepala Tuk Kepala Tukang 177,221 #VALUE! #VALUE!
0.26000 MD Tukang Kayu
Tukang Kayu 140,651 #VALUE! #VALUE!
0.52000 MD Pekerja 140,651 #VALUE! #VALUE!
Biaya per m² (m persegi) 134,515 119,216

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN N: A.3.2.1.9 AHSP - A.3.2.1


KODE/ JENIS PEKERJ : Pemasangan Batu Kosong (Aanstamping)
SATUAN PEMBAYARA: M3

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.780 120,000.00 93,600.00
Tukang Batu L.02 Org/Hari 0.390 150,000.00 58,500.00
Kepala Tukang L.03 Org/Hari 0.039 150,000.00 5,850.00
Mandor L.04 Org/Hari 0.039 150,000.00 5,850.00
JUMLAH TENAGA KERJA 163,800.00
B. BAHAN :
Batu Kali/ Batu Gunun - M3 1.200 303,510.00 364,212.00
Pasir Urug - M3 0.432 278,385.00 120,262.32
JUMLAH HARGA BAHAN 484,474.32
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 648,274.32
E. Overhead & Profit 10% x D 64,827.43
F. Harga Satuan Pekerjaan(D + E) 713,101.75

S.G.21 1m² Bekisting untuk sloof


Bahan/ Peralatan
0.04500 m³ Kayu Kelas III 2,842,418 #VALUE! #VALUE!
0.30000 kg Paku 5cm dan 7cm 15,543 #VALUE! #VALUE!
0.10000 ltr Minyak Bekisting 19,429 #VALUE! #VALUE!
Tenaga Kerja
0.02600 MD Mandor 188,473 #VALUE! #VALUE!
0.02600 MD Kepala Tuk Kepala Tukang 177,221 #VALUE! #VALUE!
0.26000 MD Tukang Kayu
Tukang Kayu 140,651 #VALUE! #VALUE!
0.52000 MD Pekerja 140,651 #VALUE! #VALUE!
Biaya per m² (m persegi) 134,515 119,216
#VALUE!
#VALUE!
110,200
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
297,161
RENCANA ANGGARAN BIAYA
( RAB )
Pekerjaan : Pekerjaan Pemindahan Pipa & Pembuatan Jalan
Lokasi : Fuel Teminal Banggai
Tahun : 2024
HARGA SATUAN
NO VOL SAT
JASA
A PEKERJAAN PERSIAPAN
1 Mobilisasi Pekerja 1 Ls 1,000,000.00
2 Mobilisasi Peralatan 1 Ls 1,000,000.00
3 Direksi Keet 1 Ls 1,000,000.00
4 Perlengkapan K3 Safety 7 Ls
5 Drawing Engginer , Desain Interior & Managament Proye 1 Ls 3,000,000.00
SUB TOTAL A
B PEKERJAAN PONDASI TALUD
1 Pek. Bwoiplank 31 m1 26,909.88
2 Pek. Anstamping 6.08 m3 163,800.00
3 Pek. Galian Tanah 64.75 m3 110,200.21
4 Pek. Susunan Pondasi Talud 1 : 4 31.2 m3 359,715.43
5 Pek. Plesteran Kasar Pondasi Talud 64 m2 16,303.78
SUB TOTAL B
C PEKERJAAN JALAN , BOX COVER & PEMBONGKARAN PONDASI
1 Pek. Box Cover
a Pengecoran K175 1.17 m3 297,160.81
b Pembesian B 10 34.5 kg 5,423.51
c Bakesting 12 m2 119,215.95
2 Pek. Pengecoran Jalan
a Pek. GO tanah 30.6 m3 115,000.00
b Pek. Timbunan Jalan 40.8 m3 33,750.00
c Pek. Pemadatan Jalan Menggunakan Stamper 40.8 m3 63,101.94
d Pek. Pembesian 8 1069 kg 5,423.51
e Pek. Pengecoran K175 40.8 m3 297,160.81
f Pek. Bakesting 41.7 m2 119,215.95
g Pek. Vibrator 1 Ls 3,500,000.00
H Pek. Pembongkaran Pondasi 1 Ls 2,000,000.00
SUB TOTAL C
D PEKERJAAN PEMINDAHAN PIPA & PENGADAAN PIPA
BIAYA

HARGA SATUAN JUMLAH


MATERIAL JASA MATERIAL

1,000,000.00
1,000,000.00
2,000,000.00 1,000,000.00 2,000,000.00
295,000.00 2,065,000.00
3,000,000.00
SUB TOTAL A 6,000,000.00 4,065,000.00

22,214.05 834,206.28 688,635.66


484,474.32 995,904.00 2,945,603.87
7,135,463.60
719,867.02 11,223,121.33 22,459,850.98
71,943.09 1,043,441.97 4,604,357.47
SUB TOTAL B 21,232,137.17 30,698,447.97

965,707.95 347,678.15 1,129,878.30


12,575.75 187,111.10 433,863.24
134,514.55 1,430,591.42 1,614,174.54

3,519,000.00
240,000.00 1,377,000.00 9,792,000.00
2,574,559.15
12,575.75 5,797,732.21 13,443,472.57
965,707.95 12,124,161.00 39,400,884.37
134,514.55 4,971,305.18 5,609,256.54
3,500,000.00
2,000,000.00
SUB TOTAL C 37,829,138.21 71,423,529.56 171,248,252.92