BACK UP DATA

(Urugan Tanah Pilihan Penimbunan Lahan)

INSTANSI/SKPD : DINAS PERUMAHAN DAN KAWASAN PERMUKIMAN


PEKERJAAN : PENIMBUNAN DAN PEMATANGAN LAHAN KANTOR DPRD KABUPATEN KOLAKA
NOMOR KONTRAK : 19.2/K-APBD/DPKP/KLK/IV/2023
TANGGAL MULAI : 05 MEI 2023
SUMBER DANA : APBD TA.2023
WAKTU PELAKSANAAN : 120 (SERATUS DUA PULUH) HARI KALENDER
NILAI KONTRAK : Rp. 1.425.368.000,-

SKETSA GAMBAR

KODE STA LUAS (M2) LUAS RATA-RATA PANJANG (M') VOLUME (M3)

a b c d f g

P0 0+000 40.04
57.70 10.00 577.00
P1 0+010 75.36
98.84 10.00 988.40
P2 0+020 122.32
123.68 10.00 1236.80
P3 0+030 125.04
125.64 10.00 1256.35
P4 0+040 126.23
125.46 10.00 1254.60
P5 0+050 124.69
117.94 10.00 1179.40
P6 0+060 111.19
101.26 10.00 1012.60
P7 0+070 91.33
52.44 10.00 524.37
P7 0+070 70.98
44.66 11.00 491.24
P8 0+080 51.61
38.08 12.00 456.93
P9 0+090 41.85
33.57 13.00 436.37
P10 0+100 33.65
29.43 14.00 411.95
P11 0+110 25.20
25.20 15.00 378.00

VOLUME REALISASI M3 10204.00


VOLUME KONTRAK M3 9830.00
DEVIASI (-/+) M3 374.00

Kolaka, Juli 2023


Mengetahui/Menyetujui Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Konsultan Pengawas Kontraktor Pelaksana
DINAS PERUMAHAN DAN KAWASAN PERMUKIMAN CV. ALL DESIGN CONSULTANT CV. RINAMBO KONSTRUKSI

ADHI PRATAMA, S.T SUARDIN, S.T TRISNO ABIWAHYU RAMADHAN


NIP. 19820910 200901 1 001 Direktur Direktur