Rp 700,000.00 Rp 700,000.00
Rp -
Rp 1,948,000.00 Rp 1,948,000.00
Rp 2,648,000.00
Rp 6,500.00 Rp 292,500.00
Rp 52,000.00 Rp 364,000.00
Rp 15,000.00 Rp 120,000.00
Rp -
Rp - Rp -
Rp 25,000.00 Rp 3,328,500.00
Rp 60,000.00 Rp 480,000.00
Rp 30,000.00 Rp 510,000.00
Rp 900,000 Rp -
Rp 380,000 Rp 190,000.00
Rp 1,250,000 Rp 1,250,000.00
Rp 380,000 Rp 570,000.00
Rp 380,000 Rp 380,000.00
Rp 15,000 Rp 7,500.00
Rp 95,000 Rp 95,000.00
Rp 82,000 Rp 328,000.00
Rp 10,000 Rp 20,000.00
Rp 12,500 Rp 12,500.00
Rp 6,000 Rp 12,000.00
Rp 20,000 Rp 40,000.00
Rp 10,000 Rp 50,000.00
Rp 55,000 Rp 110,000.00
Rp 55,000 Rp 110,000.00
Rp 8,000 Rp 24,000.00
Rp 7,500 Rp 22,500.00
Rp 5,000 Rp 5,000.00
Rp 1,350,000 Rp -
Rp 150,000 Rp 150,000.00
Rp 71,429 Rp -
Rp 74,000 Rp 1,554,000.00 Rp 8,279,500.00
Rp 78,500 Rp 1,177,500.00
Rp 87,500 Rp 875,000.00
Rp 1,500 Rp 9,000.00
Rp 22,000 Rp 4,664,000.00
Rp 55,000.00 Rp -
Rp - Rp -
Rp 850,000.00 Rp 850,000.00
Rp 800,000.00 Rp 1,600,000.00
Rp 800,000.00 Rp 800,000.00
Rp 400,000.00 Rp 400,000.00
Rp 400,000.00 Rp 1,600,000.00
Rp 450,000.00 Rp 1,800,000.00 Rp 9,000,000.00
Rp 550,000.00 Rp 1,100,000.00
Rp 550,000.00 Rp 550,000.00
Rp - Rp -
Rp 50,000.00 Rp 300,000.00
Rp - Rp -
Rp 76,000.00 Rp 1,672,000.00
Rp 35,000.00 Rp 875,000.00
Rp 8,500.00 Rp 4,080,000.00
Rp 18,000.00 Rp 1,296,000.00
Rp 250.00 Rp 250,000.00
Rp 45,000.00 Rp 495,000.00
Rp 74,500.00 Rp 74,500.00 Rp 8,793,500.00
Rp 8,000.00 Rp 8,000.00
Rp 24,250.00 Rp 24,250.00
Rp 37,500.00 Rp 18,750.00 Rp 105,000.00
Rp 1,600,000.00 Rp -
Rp 150,000.00 Rp 105,000.00
Rp 125,000.00 Rp -
Rp 3,200.00 Rp 38,400.00
Rp 600.00 Rp 21,600.00
Rp 2,800.00 Rp 33,600.00
Rp 14,000.00 Rp 14,000.00
Rp 18,000.00 Rp 18,000.00
Rp 73,000.00 Rp 182,500.00
Rp 73,000.00 Rp 109,500.00
Rp 105,000.00 Rp 840,000.00
Rp 145,000.00 Rp 435,000.00
Rp 7,000.00 Rp 14,000.00 Rp 1,930,600.00
Rp 27,000.00 Rp 135,000.00
Rp 20,500.00 Rp 41,000.00
Rp 12,000.00 Rp 48,000.00
Rp 12,500.00 Rp -
Rp - Rp -
Rp 140,000.00 Rp 3,669,166.67 Rp 4,626,666.67
Rp 50,000.00 Rp 544,500.00
Rp 200,000.00 Rp 363,000.00
Rp 12,500.00 Rp 50,000.00
Rp - Rp -
Rp - Rp -
Rp 58,000.00 Rp 883,920.00
Rp 56,000.00 Rp 151,200.00
Rp 200,000.00 Rp 27,000.00
Rp 49,000.00 Rp 39,690.00
Rp 1,100,000.00 Rp 1,100,000.00
Rp 60,000.00 Rp 60,000.00
Rp 60,000.00 Rp 60,000.00
Rp 12,500.00 Rp 12,500.00
Rp 5,000.00 Rp 10,000.00
Rp 18,000.00 Rp 54,000.00
Rp 3,500.00 Rp 21,000.00
Rp 3,500.00 Rp 10,500.00
Rp 45,000.00 Rp 112,500.00
Rp 6,000.00 Rp 18,000.00
Rp 70,000.00 Rp 140,000.00
Rp 15,000.00 Rp 30,000.00
Rp 60,000.00 Rp 60,000.00
Rp 85,000.00 Rp 1,360,000.00
Rp 6,000.00 Rp 12,000.00
Rp 200,000.00 Rp 200,000.00
Rp 4,500.00 Rp 13,500.00
Rp - Rp -
Rp 160,000.00 Rp 160,000.00 Rp 5,754,010.00
Rp 55,000.00 Rp 783,200.00
Rp 50,000.00 Rp 135,000.00
Rp 150,000.00 Rp 150,000.00 Rp -
Rp 150,000.00 Rp 150,000.00
Rp - Rp -
Rp - Rp -
Rp 40,000.00 Rp 200,000.00
Rp 25,000.00 Rp 125,000.00
Rp 200,000.00 Rp 200,000.00
Rp 67,000.00 Rp 804,000.00
Rp 550.00 Rp 110,000.00 Rp 2,211,000.00
Rp 50,000.00 Rp 200,000.00
Rp 240,000.00 Rp 192,000.00
Rp 25,000.00 Rp 300,000.00 Rp 1,650,000.00
Rp 50,000.00 Rp 80,000.00 Rp 44,998,276.67
Rp 1,650,000.00 Rp 1,650,000.00
NO URAIAN UPAH SATUAN
1 Pekerja Orang
2 Tukang Orang
3 Kepala Tukang Orang
4 Mandor Orang
Rp 815,850.00
Rp 509,906.25
Rp70,067.00
Rp 314,000.00
Rp 6,500,000.00
Rp 40,000.00
Rp 30,500.00
Rp 850,000.00
Rp 28,000.00
Rp 5,000.00
Rp 160,000.00
Rp 17,000.00
Rp 336,000.00
Rp 60,000.00
Rp 65,000.00
Rp 9,000.00
Rp 38,000.00
Rp 67,500.00
Rp 500.00
Rp 55,000.00
Rp 125,000.00
Rp 3,200
Rp 600
Rp 2,800
Rp 14,000
Rp 18,000
Rp 73,000
Rp 73,000
Rp 105,000
Rp 145,000
Rp 7,000
Rp 27,000
Rp 20,500
Rp 12,000
Rp 12,500
Rp 60,000.00
Rp 3,750,000.00
Rp 25,000.00
Rp 69,900.00
Rp 40,000.00
Rp 40,000.00
Rp 71,500.00
Rp 1,000,000.00
Rp 85,000.00
Rp 145,000.00
Rp 45,000.00
Rp 35,000.00
Rp 185,000.00
Rp 235,000.00
Rp 1,600.00
Rp 6,000.00
Rp 1,600,000.00
Rp 40,000.00
Rp 83,000.00
Harga Satuan (Rp)
No Jenis Pekerjaan
Sat Indeks Bahan
III PEKERJAAN PONDASI
6.6 1 m³ Pasang Pondasi Batu Belah 1 PC : 4 Ps
SNI 03-2835-2002 Bahan
Batu belah 15 - 20 (cm) m³ 1.1 Rp 288,489.00
Semen PC @ 50 kg kg 163 Rp 1,969.00
Pasir pasang m³ 0.52 Rp 248,418.00
Tenaga
Pekerja Oh 2
Tukang batu Oh 0.35
Kepala tukang Oh 0.035
Mandor Oh 1
Sub Total
1 m³ Galian Tanah biasa Sedalam 1 m (dengan tenaga)
Rp 317,337.90
Rp 320,947.00
Rp 129,177.36
Rp 106,925.00 Rp 213,850.00
Rp 150,000.00 Rp 52,500.00
Rp 160,388.00 Rp 5,613.58
Rp 187,119.00 Rp 187,119.00
Rp 1,226,544.84
Rp 106,925.00 Rp 42,770.00
Rp 187,119.00 Rp 7,484.76
Rp 50,254.76
Rp 376,800.00
Rp 106,925.00 Rp 32,077.50
Rp 187,119.00 Rp 1,871.19
Rp 410,748.69
Rp 85,800.00
Rp 106,925.00 Rp 32,077.50
Rp 98,450.00 Rp 984.50
Rp 118,862.00
Rp 3,493,958.58
Pondasi 1/2 Batu
La Lb t v
0.3 0.6 0.7 0.315
Kebutuhan Material
Pondasi 1 Batu
La Lb t v
0.25 0.45 0.6 0.21
No Pekerjaan Volume
1 Membuat Pondasi 35
0,2
0,75
0,8
0,5
0,6
MT
-0. 70
0,1
0,15
0,25
0,45
No Pekerjaan Volume
1 Membuat Pondasi 35
0,25
0,75
0,85
0,5
0,6
MT
-0.75
0,25
0,75
0,85
0,5
0,6
MT
-0.75
0,1
0,15
0,25
0,45
Recap
Vtotal (m ) 3 V 1/2 Batu (m )
3
V 1 Batu (m3)
#VALUE! #REF! #REF!
Recap
Vtotal (m3) V 1/2 Batu (m )
3
V 1 Batu (m3)
#REF! #VALUE! #VALUE!
m³ Rp 3,493,958.58 1
Pas Hebel 7cm 11,15
La + Lb /2 x T 0,78 0,8 2 4
Sloof 15x20cm
besid 10 mm) 0,56
0,2
9
11,14 4
0,8
0,5
0,6
2
0,8
0,1 0,78
0,78 0,8 2 4
11,15
m³ Rp 3,493,958.58 2
Pas Hebel 7 cm
Pas Bata 1/2
Sloof 15x25 cm
(besi d 10 mm)
La + Lb /2 x T
Pondasi Batu Gunung
Luas Trapesium 0.21
0,25
0,85
0,5
0,6
MT
-0.75
0,25
0,85
0,5
0,6
MT
-0.75
0,1
Unit
#REF!
0.21
Unit La + Lb /2 x T
#REF! Luas Trapesium
Total Harga
Rp 122,288,550.30
11,15
8
0,78 0,8 2 4 2 0,8 0,78
0,56 0,56
1 1
2 2
9 9
11,14 4 4 11,14
2 2
0,8 0,8
0,78 0,78
11,15
Total Harga
Rp 122,288,550.30
Rp 244,577,100.60
NO PEKERJAAN / MATERIAL BYK SAT
ONGKOS KERJA
HARGA
TOTAL HARGA NO PEKERJAAN / MATERIAL
SATUAN
PEKERJAAN BESI STRUKTUR
Rp 540,000 Rp 540,000 1 Upah
Rp 540,000 TOTAL
BYK SAT HARGA SATUAN TOTAL HARGA
I STRUKTUR
22 Btg Rp 72,670 Rp 1,598,740
17 Btg Rp 74,926 Rp 1,273,742
10 Btg Rp 81,875 Rp 818,750
6 Btg Rp 93,125 Rp 558,750
235 Bh Rp 1,500 Rp 352,500
5 Kg Rp 22,000 Rp 110,000
Rp 4,712,482
ONGKOS KERJA
BYK SAT HARGA SATUAN TOTAL HARGA
I STRUKTUR
1 Ls Rp 675,000 Rp 675,000
Rp 675,000
Uraian Jenis
No. Sat. Koeff.
Pekerjaan
1 2 3 4
M.19 1 M2 PASANGAN LANTAI KERAMIK , UK.
40x
Bahan40 CM: PUTIH POLOS
Keramik, uk. 40 x Bh 6.5000
40 cm
Semen Portland Kg 8.1900
Pasir Pasang M3 0.0450
Semen Warna Kg 1.6200
( putih )
Tenaga Kerja :
Pekerja Oh 0.7000
Tukang Batu Oh 0.3500
Kepala Tukang Batu Oh 0.0350
Mandor Oh 0.0350
Jumlah
Keuntungan maksimal 10%
Jumlah
Dibulatkan
Harga Sat. Jumlah Harga Jumlah Harga Bahan +
Bahan / Upah Bahan Upah Upah
Rp. Rp. Rp. Rp.
5 6 7 8
Rp 8,000.00 Rp 52,000.00
Rp 1,125.00 Rp 9,213.75
Rp 210,000.00 Rp 9,450.00
Rp 7,400.00 Rp 11,988.00
Rp 125,000.00 Rp 87,500.00
Rp 139,000.00 Rp 48,650.00
Rp 153,000.00 Rp 5,355.00
Rp 167,000.00 Rp 5,845.00
Rp 82,651.75 Rp 147,350.00 Rp 230,001.75
Rp 23,000.18
Rp 253,001.93
Rp 253,000.00
No Pekerjaan Volume Satuan Harga Satuan Total Harga
Luas Lantai 72 0
Luas Keramik 0.96 0
II PEKERJAAN PONDASI BATU KALI
Gambar Penampang Pondasi Batu Kali
Lantai Keramik 40X40 Pas Hebel 7cm
Beton Cor 1:3:5 Sloof 15x25cm
Pasir Urug (besi d 10mm)
Tanah Urug Pondasi BatuGunung
+0.00
0,15
0,25
0,75
1
0,35
MT
-0.75 0,6
0,25
0,15
0,25
0,45
Panjang Rencana Pondasi :
Arah Horizontal = 43.20 m =
Arah Vertikal = 43.60 m
Panjang total pondasi = 86.80 m
t Keterangan
Skala 1 : 10 1. Ukuran : 15 x 25
0.15 2. Bahan : Beton Bertulang
Besi polos 2 Ø 10 mm
3. Beton : K-225
Begel Ø6 - 150
4. Tulangan : Besi Polos Ø 10
Besi polos 2 Ø 10 mm
0.25 - Tulangan Utama : Besi Polos 2 Ø 10
Besi polos 2 Ø 10 mm - Tulangan Sengkang : : Ø6 - 150
5. Selimut Beton : 2,5 cm
Pekerjaan Sloof Uk 15 x 30 cm
Bentang L m 4 x 4 = 16
Bentang L m 2 x 8 = 16
Bentang L m 1 x 2 = 2
Bentang L m 0.8 x 6 = 4.8
Total Panjang Sloof 38.8
Detail Keterangan
Skala 1 : 10 1. Ukuran : 15 x 20
0.15
2. Bahan : Beton Bertulang
3. Beton : K-225
Besi polos 2 Ø 10 mm
Besi polos 2 Ø 10 mm
0.15
Besi polos 2 Ø 10 mm
4. Tulangan : Besi Polos Ø 10
Begel Ø6 - 150 - Tulangan Utama : Besi Polos 2 Ø 10
0.20
- Tulangan Sengkang : Ø6 - 150
Besi polos 2 Ø 10 mm 5. Selimut Beton : 2,5 cm
Detail Keterangan
Skala 1 : 10 1. Ukuran : 15 x 20
0.15 2. Bahan : Beton Bertulang
Besi polos 2 Ø 10 mm 3. Beton : K-225
4. Tulangan : Besi Polos Ø 10
0.20 Begel Ø6 - 150 - Tulangan Utama : Besi Polos 2 Ø 10
- Tulangan Sengkang : Ø6 - 150
Besi polos 2 Ø 10 mm 5. Selimut Beton : 2,5 cm
Detail Keterangan
Skala 1 : 10 1. Ukuran : 25 x 25
0.25 2. Bahan : Beton Bertulang
Besi Ulir 3 Ø 16 mm 3. Beton : K-200
4. Tulangan : Besi Ulir Ø 16
Begel Ø8 - 150 - Tulangan Utama : Besi Ulir 3 Ø 16
0.25
Besi Ulir 2 Ø 16 mm - Tulangan Utama : Besi Ulir 2 Ø 16
- Tulangan Sengkang : Ø8 - 150
Besi Ulir 3 Ø 16 mm
5. Selimut Beton : 2,5 cm
=
Keterangan
Skala 1 : 10 1. Ukuran : 15 x 15
0.15 2. Bahan : Beton Bertulang
Besi polos 2 Ø 10 mm 3. Beton : K-200
4. Tulangan : Besi Polos 2 Ø 10
0.15 Begel Ø6 - 150
- Tulangan Utama : Besi Polos3 Ø6 - 150
Besi polos 2 Ø 10 mm - Tulangan Sengkang : Ø6 - 150
5. Selimut Beton : 2,5 cm
Totalnya =
4 Pek. Ring Balok Uk. 15 x 30 Cm
Detail Keterangan
Skala 1 : 10 1. Ukuran : 15 x 30
0.15 2. Bahan : Beton Bertulang
Besi polos 2 Ø 10 mm
3. Beton : K-200
Begel Ø6 - 150
4. Tulangan : Besi Polos Ø 10
Besi polos 2 Ø 10 mm
0.30 - Tulangan Utama : Besi Polos 2 Ø 10
- Tulangan Sengkang : Ø6 - 150
Besi polos 2 Ø 10 mm
5. Selimut Beton : 2,5 cm
Detail Keterangan
Skala 1 : 10 1. Ukuran : 15 x 20
2. Bahan : Beton Bertulang
0.15
3. Beton : K-200
Besi polos 2 Ø 10 mm
4. Tulangan : Besi Polos 2 Ø 10
0.20 Begel Ø6 - 150 - Tulangan Utama : Besi Polos 2 Ø 10
Besi polos 2 Ø 10 mm
- Tulangan Sengkang : Ø6 - 150
5. Selimut Beton : 2,5 cm
V PEKERJAAN DINDING KUSEN DAN PINTU
11,15
8
0,78 0,8 2 4 2 0,8 0,78
0,56 0,56
1
1 1
2
2 2
9 MUSHALLA
9
EL.±0.00
11,14 4 4 11,14
A A
2
2 2
9 MUSHALLA
9
EL.±0.00
11,14 4 4 11,14
A A
2 2
1 1
3 89.5 3 90 90
375
5
0,8 0,8
15
1 1
0,78 0,78 3 89.5 3 90 90
375
11,15
V PEKERJAAN ATAP
0,4
Gording zincalumunium45 mm
0,4
Sokong zincalumunium60mm 0,4
0,4
Bint zincalumunium60mm
0,4
0,4
0,4
0,4
7,98
1. Pek. Galian Tanah Biasa Sedalam 1 m
Luas penampang
Volume
Volume
Volume
Volume
Volume
Volume
Volume
Volume
1. Bekisting Sloof
Bentang L = 4 m
Lebar Bekisting = 1 x
= 0.02 m
Luas bekisting = 0.02 x
= 0.32 m2
Bentang L = 2.00 m
Lebar Bekisting = 1 x
= 0.02 m
Luas bekisting = 0.02 x
= 0.32 m2
Bentang L = 1.00 m
Lebar Bekisting = 1 x
= 0.02 m
Luas bekisting = 0.02 x
= 0.04 m2
Bentang L = 0.80 m
Lebar Bekisting = 1 x
= 0.016 m
Luas bekisting = 0.02 x
= 0.08 m2
Total Bekisting
= 0.32 +
= 0.76 m2
b. Pembesian
Bentang L = 4.00 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 4.00 m
Jumlah sloof = 4.00 bh
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
b. Tulangan Sengkang/begel ( Ø 6 mm )
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
Bentang L = 2.00 m
= 0.15 m
= 0.20 m
= 2.00 m
= 8.00 bh
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
b. Tulangan Sengkang/begel ( Ø 6 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
Total Volume Tulangan
Bentang L = 1.00 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 1.00 m
Jumlah sloof = 2.00 bh
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
b. Tulangan Sengkang/begel ( Ø 6 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
Bentang L = 0.80 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 0.80 m
Jumlah sloof = 6.00 bh
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
b. Tulangan Sengkang/begel ( Ø 6 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
c. Beton K-200
Bentang L = 4.00 m
Lebar sloof = 0.15
Tinggi sloof = 0.20
Panjang sloof = 4.00
Jumlah sloof = 4.00
Bentang L = 2.00 m
Lebar sloof = 0.15
Tinggi sloof = 0.20
Panjang sloof = 2.00
Jumlah sloof = 8.00
Bentang L = 1.00 m
Lebar sloof = 0.15
Tinggi sloof = 0.20
Panjang sloof = 1.00
Jumlah sloof = 2.00
Bentang L = 0.80 m
Lebar sloof = 0.15
Tinggi sloof = 0.20
Panjang sloof = 0.80
Jumlah sloof = 6.00
Bentang L = 0.80 m
Lebar sloof = 0.15 m
Tinggi sloof = 0.20 m
Panjang sloof = 0.80 m
Jumlah sloof = 6.00 bh
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
b. Tulangan Sengkang/begel ( Ø 6 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
Total Pembesian
= 4,141.14 Kg
c. Beton K-225
Bentang L = 4.00 m
- Lebar sloof = 0.15
- Tinggi sloof = 0.20
- Panjang sloof = 4.00
- Jumlah sloof = 4.00
Bentang L = 2.00 m
- Lebar sloof = 0.15
- Tinggi sloof = 0.20
- Panjang sloof = 2.00
- Jumlah sloof = 8.00
Bentang L = 1.00 m
- Lebar sloof 0.15 0.15
- Tinggi sloof = 0.20
- Panjang sloof = 1.00
- Jumlah sloof = 2.00
a. Bekisting Kolom
Tinggi T = = 3.95
Lebar 01 = 0.25
Lebar 02 = 0.25
Tinggi kolom = 3.95
Jumlah kolom = 8.00
Bentang L = 3.95 m
Lebar 01 = 0.25
Lebar 02 = 0.25
Tinggi kolom = 3.95
Jumlah kolom = 8.00
a. Tulangan Pokok ( Ø 16 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
b. Tulangan Sengkang/begel ( Ø 8 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
- Volume tulangan
b. Tulangan Sengkang/begel ( Ø 8 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
b. Tulangan Sengkang/begel ( Ø 8 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
b. Pembesian
Bentang L = 0.40 m
Lebar 01 = 0.15
Lebar 02 = 0.15
Tinggi kolom = 0.40
Jumlah kolom = 3.00
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
b. Tulangan Sengkang/begel ( Ø 8 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
b. Pembesian
Bentang L = 0.30 m
Lebar 01 = 0.15
Lebar 02 = 0.15
Tinggi kolom = 0.30
Jumlah kolom = 4.00
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
b. Tulangan Sengkang/begel ( Ø 8 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
b. Pembesian
Bentang L = 0.15 m
Lebar 01 = 0.15
Lebar 02 = 0.15
Tinggi kolom = 0.15
Jumlah kolom = 3.00
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
b. Tulangan Sengkang/begel ( Ø 8 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Selimut beton
- Jarak spasi tulangan
- Volume tulangan
Total Pembesian
a. Bekisting Balok
Bentang L = 2.80 m
Lebar RB 01 = 0.15
Tinggi RB 01 = 0.30
Panjang RB 01 = 1.00
Lebar RB 02 = 0.15
Tinggi RB 02 = 0.20
Panjang RB 02 = 0.00
Jumlah RB 01 = 27.00
Jumlah RB 02 = 9.00
3
6 Total bekisting = 17.28
= 21.24
Bentang L= 4.00 m
Lebar RB 01 = 0.15
Tinggi RB 01 = 0.30
Panjang RB 01 = 4.00
Jumlah RB 01 = 9.00
Bentang L= 2.00 m
Lebar RB 01 = 0.15
Tinggi RB 01 = 0.30
Panjang RB 01 = 2.00
Jumlah RB 01 = 16.00
Bentang L= 1.00 m
Lebar RB 01 = 0.15
Tinggi RB 01 = 0.30
Panjang RB 01 = 1.00
Jumlah RB 01 = 2.00
Bentang L= 4.00 m
Lebar RB 02 = 0.15
Tinggi RB 02 = 0.20
Panjang RB 02 = 4.00
Jumlah RB 02 = 3.00
Lebar bekisting = 1.00
= 0.55
Luas bekisting = 0.55
= 6.60
Bentang L= 0.80 m
Lebar RB 02 = 0.15
Tinggi RB 02 = 0.20
Panjang RB 02 = 4.00
Jumlah RB 02 = 6.00
Total Bekisting
= 27.00
= 52.50
b. Pembesian
Bentang L = 4.00 m
Lebar RB 01 = 0.15
Tinggi RB 01 = 0.30
Panjang RB 01 = 4.00
Jumlah RB 01 = 9.00
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
- Volume tulangan
Pembesian
Bentang L = 2.00 m
Lebar RB 01 = 0.15
Tinggi RB 01 = 0.30
Panjang RB 01 = 2.00
Jumlah RB 01 = 16.00
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
- Volume tulangan
Pembesian
Bentang L = 1.00 m
Lebar RB 01 = 0.15
Tinggi RB 01 = 0.30
Panjang RB 01 = 1.00
Jumlah RB 01 = 2.00
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
Pembesian
Bentang L = 4.00 m
Lebar RB 02 = 0.15
Tinggi RB 02 = 0.20
Panjang RB 02 = 4.00
Jumlah RB 02 = 3.00
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
- Volume tulangan
a. Tulangan Pokok ( Ø 10 mm )
- Diameter tulangan (Ø)
- Panjang besi per-batang
- Berat besi per-batang
- Berat besi per-1 m'
- Jumlah tulangan pokok
- Overlap untuk sambungan (40d)
- Volume tulangan
- Volume tulangan
Total Pembesian
=
=
c. Beton K-200
Bentang L = 4.00 m
Lebar RB 01 =
Tinggi RB 01 =
Panjang RB 01 =
Jumlah RB 01 =
Volume Beton =
=
Bentang L = 2.00 m
Lebar RB 01 =
Tinggi RB 01 =
Panjang RB 01 =
Jumlah RB 01 =
Volume Beton =
=
Bentang L = 1.00 m
Lebar RB 01 =
Tinggi RB 01 =
Panjang RB 01 =
Jumlah RB 01 =
Volume Beton =
=
Bentang L = 4.00 m
Lebar RB 01 =
Tinggi RB 01 =
Panjang RB 01 =
Jumlah RB 01 =
Volume Beton =
72 80
117 - 18
170 330
250
1
31
170 330
31
Kebutuhan Bata Ringan
1
70
Luas Dinding : Panjang Bata Ringan
13
96.2076 : 0.6
1 1 1
89.5 3 90 90 3 89.5 3
375
= 801.73 bh
89.5
1
3 90 90 3
1
89.5
1
3 Dibulatkan 802 bh
375
Tipe 01 0.72 x
Tipe 02 0.7 x
Tipe 03 1.7 x
Volume Pintu = 10
= 18
Kebutuhan Hebel / m3
1 : 0.009
Dibulatkan
Sehingga ,
7.16071428571429 m3
Dibulatkan 8 m3
= 6.012975
Dibulatkan = 7
Menghitung Kuda - Kuda
399
2,9
Nilai tangen 30
399
B = Panjang kemiringan
399
Nilai cos 30
399
Overstack
587.179487179
= 1.00 x 0.45
= 0.45 m2
= 0.45 x 86.80
= 39.06 m3
= 0.03 x 0.85
= 0.03 m2
= 0.03 x 86.80
= 2.21 m3
= 1.00 x 0.45
= 0.45 m2
= 0.45 x 0.00
= 0.00 m3
= 0.04 x 0.85
= 0.03 m2
= 0.03 x 0.00
= 0.00 m3
0.04 x 2 x 0.25
4.00 x 4.00
0.04 x 2 x 0.25
2.00 x 8.00
0.04 x 2 x 0.25
1.00 x 2.00
0.04 x 2 x 0.20
0.80 x 6.00
= 10.00 mm
= 12.00 m
= 7.38 kg
= 0.62 kg
= 6.00 bh
= 0.40 m
= 6.00 mm
= 12.00 m
= 2.66 kg
= 0.22 kg
= 0.025 m
= 0.15 m
= 0.10 m =
= 0.15 m
= 0.075 m
= 0.65 m
= 4.00 / 0.15
= 26.67 bh Pembulatan = 27
= 27.00 x 0.65 x 0.22
= 3.89 kg
= 3.89 x 27.00
= 105.04 kg
= 10.00 mm
= 12.00 m
= 7.38 kg
= 6.54 kg
= 6.00 bh
= 0.40 m
= 6.00 mm
= 12.00 m
= 2.66 kg
= 0.22 kg
= 0.025 m
= 0.15 m
= 0.10 m =
= 0.15 m
= 0.075 m
= 0.65 m
= 2.00 / 0.15
= 13.33 bh Pembulatan = 14
= 14.00 x 0.65 x 0.22
= 2.02 kg
= 2.02 x 14.00
= 28.24 kg
= 10.00 mm
= 12.00 m
= 7.38 kg
= 6.54 kg
= 4.00 bh
= 0.40 m
= 6.00 mm
= 12.00 m
= 2.66 kg
= 0.22 kg
= 0.025 m
= 0.15 m
= 0.10 m =
= 0.15 m
= 0.075 m
= 0.65 m
= 1.00 / 0.15
= 6.67 bh Pembulatan = 7
= 7.00 x 0.65 x 0.22
= 1.01 kg
= 1.01 x 7.00
= 7.06
= 10.00 mm
= 12.00 m
= 7.38 kg
= 6.54 kg
= 4.00 bh
= 0.40 m
= 6.00 mm
= 12.00 m
= 2.66 kg
= 0.22 kg
= 0.025 m
= 0.15 m
= 0.10 m =
= 0.15 m
= 0.075 m
= 0.65 m
= 0.80 / 0.15
= 5.33 bh Pembulatan = 6
= 6.00 x 0.65 x 0.22
= 0.86 kg
= 0.86 x 6.00
= 5.19
m
m
m
bh
m
m
m
bh
m
m
m
bh
= 10.00 mm
= 12.00 m
= 7.38 kg
= 6.54 kg
= 4.00 bh
= 0.40 m
= 6.00 mm
= 12.00 m
= 2.66 kg
= 0.22 kg
= 0.025 m
= 0.15 m
= 0.10 m =
= 0.15 m
= 0.075 m
= 0.65 m
= 0.80 / 0.15
= 5.33 bh Pembulatan = 6
= 6.00 x 0.65 x 0.22
= 0.86 kg
= 0.86 x 6.00
= 5.19 kg
m
m
m
bh
m
m
m
bh
m
m
m
bh
m
m
m
bh
= 16.00 mm
= 12.00 m
= 18.89 kg
= 1.57 kg
= 6.00 bh
= 0.64 m
= 68.77 kg
= 8.00 mm
= 12.00 m
= 4.74 kg
= 0.40 kg
= 0.025 m
= 0.15 m
= 0.25 m
= 0.20 m
= 0.075 m
= 1.05 m
= 3.95 / 0.15
= 26.33 bh Pembulatan = 27
= 27.00 x 1.05 x 0.40
= 11.20 kg
= 11.20 x 27.00
= 302.35 kg
m
m
m
bh
= 11.81 kg
= 8.00 mm
= 12.00 m
= 4.74 kg
= 0.40 kg
= 0.025 m
= 0.15 m
= 0.15 m
= 0.00 m
= 0.075 m
= 0.45 m
= 0.80 / 0.15
= 5.33 bh Pembulatan = 6
= 6.00 x 0.45 x 0.40
= 1.07 kg
= 1.07 x 6.00
= 6.40 kg
m
m
m
bh
= 10.00 mm
= 12.00 m
= 7.38 kg
= 0.62 kg
= 4.00 bh
= 0.40 m
= 11.81 kg
= 8.00 mm
= 12.00 m
= 4.74 kg
= 0.40 kg
= 0.025 m
= 0.15 m
= 0.15 m
= 0.73 m
= 0.075 m
= 1.91 m
= 0.73 / 0.15
= 4.87 bh Pembulatan = 5
= 5.00 x 1.91 x 0.40
= 3.77 kg
= 3.77 x 5.00
= 18.86 kg
= 11.81 kg
= 8.00 mm
= 12.00 m
= 4.74 kg
= 0.40 kg
= 0.025 m
= 0.15 m
= 0.15 m
= 0.40 m
= 0.075 m
= 1.25 m
= 0.40 / 0.15
= 2.67 bh Pembulatan = 3
= 3.00 x 1.25 x 0.40
= 1.48 kg
= 1.48 x 3.00
= 4.44 kg
= 10.00 mm
= 12.00 m
= 7.38 kg
= 0.62 kg
= 4.00 bh
= 0.40 m
= 11.81 kg
= 8.00 mm
= 12.00 m
= 4.74 kg
= 0.40 kg
= 0.025 m
= 0.15 m
= 0.15 m
= 0.30 m
= 0.075 m
= 1.05 m
= 0.30 / 0.15
= 2.00 bh Pembulatan = 2
= 2.00 x 1.05 x 0.40
= 0.83 kg
= 0.83 x 2.00
= 1.66 kg
= 10.00 mm
= 12.00 m
= 7.38 kg
= 0.62 kg
= 4.00 bh
= 0.40 m
= 11.81 kg
= 8.00 mm
= 12.00 m
= 4.74 kg
= 0.40 kg
= 0.025 m
= 0.15 m
= 0.15 m
= 0.15 m
= 0.075 m
= 0.75 m
= 0.15 / 0.15
= 1.00 bh Pembulatan = 1
= 1.00 x 0.75 x 0.40
= 0.30 kg
= 0.30 x 1.00
= 0.30 kg
m
m
m
m
m
m
bh
bh
+ 3.96
m2
m
m
m
bh
m
m
m
bh
m
m
m
bh
m
m
m
bh
x 0.15 + 2.00 x 0.20
m
x 4.00 x 3.00
m2
m
m
m
bh
= 10.00 mm
= 12.00 m
= 7.38 kg
= 0.62 kg
= 4.00 bh
= 0.40 m
= 6.00 mm
= 12.00 m
= 2.66 kg
= 0.22 kg
= 0.025 m
= 0.15 m
= 0.10 m
= 0.25 m
= 0.075 m
= 0.85 m
= 4.00 / 0.15
= 26.67 bh Pembulatan =
= 27.00 x 0.85 x 0.22
= 5.08 kg
= 5.08 x 9.00
= 45.73 kg
= 10.00 mm
= 12.00 m
= 7.38 kg
= 0.62 kg
= 4.00 bh
= 0.40 m
= 6.00 mm
= 12.00 m
= 2.66 kg
= 0.22 kg
= 0.025 m
= 0.15 m
= 0.10 m
= 0.25 m
= 0.075 m
= 0.85 m
= 2.00 / 0.15
= 13.33 bh Pembulatan =
= 14.00 x 0.85 x 0.22
= 2.63 kg
= 2.63 x 16.00
= 42.15 kg
= 10.00 mm
= 12.00 m
= 7.38 kg
= 0.62 kg
= 4.00 bh
= 0.40 m
= 6.00 mm
= 12.00 m
= 2.66 kg
= 0.22 kg
= 0.025 m
= 0.15 m
= 0.10 m
= 0.25 m
= 0.075 m
= 0.85 m
= 1.00 / 0.15
= 6.67 bh Pembulatan =
= 7.00 x 0.85 x 0.22
= 1.32 kg
= 1.32 x 2.00
= 2.63 kg
= 10.00 mm
= 12.00 m
= 7.38 kg
= 0.62 kg
= 4.00 bh
= 0.40 m
= 6.00 mm
= 12.00 m
= 2.66 kg
= 0.22 kg
= 0.025 m
= 0.15 m
= 0.10 m
= 0.15 m
= 0.075 m
= 0.65 m
= 4.00 / 0.15
= 26.67 bh Pembulatan =
= 27.00 x 0.65 x 0.22
= 3.89 kg
= 3.89 x 3.00
= 11.66 kg
Total volume pembesian =
m
m
m
bh
= 10.00 mm
= 12.00 m
= 7.38 kg
= 0.62 kg
= 4.00 bh
= 0.40 m
= 6.00 mm
= 12.00 m
= 2.66 kg
= 0.22 kg
= 0.025 m
= 0.15 m
= 0.10 m
= 0.15 m
= 0.075 m
= 0.65 m
= 0.80 / 0.15
= 5.33 bh Pembulatan =
= 6.00 x 0.65 x 0.22
= 0.86 kg
= 0.86 x 6.00
= 5.18 kg
0.15 m
0.30 m
2.00 m
16.00 bh
0.15 m
0.30 m
1.00 m
2.00 bh
0.15 m
0.20 m
4.00 m
0.00 bh
117 m
- Volume Jendela
- 2.7924
m2
x 0.2
Jml;
0.895 = 0.6444 m2 2 bh
0.895 = 0.6265 m2 2 bh
0.895 = 1.5215 m2 2 bh
2.7924 m2
x 1.8 Jml
2 bh
m2
0.6 x 0.075
0.009 m3
= 111.111111111111 bh
112 bh
zak
sak
ghitung Kuda - Kuda
gi Kuda - Kuda
x tan 35 = 280 cm
x tan 35 280 cm
= 0.700
x 0.700
279.3 cm
anjang kemiringan
: cos 35 = 487 cm
= 0.819
: 0.819
= 487.179487179487
= 100
39.06 M3
2.21 M3
11.72 M3
5.47 M3
0.60
0.00 M3
0.00 M3
0.00 M3
0.00 M3
0.60
0.76 m2
kg
bh
bh
bh
bh
0.48 m2
0.48 m2
0.06 m2
0.14 m2
kg
bh
371.12 kg
bh
18.21 kg
bh
30.67 kg
bh
16.25 kg
bh
13.47 kg
bh
12.10 kg
bh
+ 13.47 + 12.10
0.00 M2
0.00 Kg
152.00 kg
27.00 bh
152.36 kg
14.00 bh
11.49 kg
7.00 bh
47.08 kg
27.00 bh
28.80 kg
6.00 bh
0.20 M3
= 0.12 m2
Vidio Tutorial : https://youtu.be/uxxyfdSUXpM
ANALISA PONDASI BATU KALI MENERUS
qn >= P/A
qn = daya dukung tanah di bagi safty factor
P = Beban Aksial dari kolom
A = luas pondasi
Safty factor = 3
BEBAN BEBAN
Berat rangka atap dan penutup atap = 2,010.00 kg/m
Berat Plafound & ME = 84.00 kg/m
Berat Dinding = 1,050.00 kg/m
Berat Lain lain = - kg/m
Berat Pondasi = 440.00 kg/m
Total Beban = 3,584.00 kg/m
qu = 2.50 kg/cm2
Safty factor = 3.00 2,200.00
qn = 0.83 kg/cm2
KESIMPULAN
Type Pondasi = Batu Kali Menerus
Lebar Atas = 30.00 cm
Lebar Dasar = 50.00 cm
Kedalaman = 50.00 cm
Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp)
17 m³ Rp 288,489.00 Rp 4,904,313.00
45 zak Rp 98,450.00 Rp 4,430,250.00
7 m³ Rp 248,418.00 Rp 1,738,926.00
bh
bh
Volume Type Berat (Kg)/btg