KURVA S PEKERJAAN ARSITEKTUR

KLINIK KARSA HUSADA GARUT


FEBRUARI MARET APRIL MEI JUNI JULI
NO PEKERJAAN ARSITEKTUR BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 KET
01-09 10-16 17-23 24-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03 04-10 11-17 18-24 25-31 01-07 08-14 15-21 22-28 29-05 06-12 13-19 20-26 27-31
1 PEKERJAAN PASANGAN DAN PELAPIS DINDING 5,433% 14-15
1. Dinding bata ringan 600x200x100 mm 1,682% 0,561 0,561 0,561 Februari
2. Plesteran semen mortar 1,340% 0,335 0,335 0,335 0,335 2024
3. Acian semen mortar 0,438% 0,219 0,219 Libur
4. Acian beton ekspose (mortar) 0,010% 0,003 0,003 0,003 PEMILU,
5. Opening pintu & jendela 0,032% 0,011 0,011 0,011 10-11
6. Balok praktis uk. 10x15 cm - Besi 4Ø10, Ø8-150 0,141% 0,047 0,047 0,047 Maret
7. Kolom praktis uk. 11x11 cm - Besi 4Ø10, Ø8-200 0,599% 0,200 0,200 0,200 2024
8. Dinding keramik tile 30 x 60 cm Polished 0,579% 0,193 0,193 0,193 Libur
9. Dinding batu granit polish finish (granit slab) 0,309% 0,103 0,103 0,103 Awal,
10. Plint homogeneous 10 x 60 cm (cutting size) 0,017% 0,009 0,009 Puasa 9-
11. Hospital plint homogeneous tile t. 10 cm 0,287% 0,287 14 April
2 PEKERJAAN PASANGAN PELAPIS LANTAI 3,373% 2024
1 Lantai homogenous tile 60 x 60 cm polished 1,896% 0,474 0,474 0,474 0,474 Libur Idul
2 Lantai homogenous tile 60 x 60 cm unpolished 0,084% 0,021 0,021 0,021 0,021 Fitri,
3 Step nosing homogeneous tile 30 x 60 cm 0,153% 0,077 0,077 sehingga
4 Lantai homogenous tile 20 x 60 cm (cutting size) 0,068% 0,034 0,034 Rencana
5 Lantai kayu polish finish (timber flooring) 1,055% 0,528 0,528 Progress
6 Lantai floor hardener t. 1,5 mm 0,008% 0,008 Mingguan
7 Screed beton t. 3 cm 0,108% 0,054 0,054 akan
3 PEKERJAAN PASANGAN PLAFOND 2,296% menyesua
1 Plafond gypsum tebal 9 mm (metal furing system) 0,593% 0,148 0,148 0,148 0,148 ikan.
2 Plafond moisture proof gypsum tebal 9 mm (metal furing system) 1,333% 0,333 0,333 0,333 0,333
3 Drop ceiling gypsum board tinggi 40 cm tebal 9 mm 0,098% 0,025 0,025 0,025 0,025
4 Plafond eksposed acian semen 0,017% 0,004 0,004 0,004 0,004
5 List profil gypsum 9 cm 0,255% 0,064 0,064 0,064 0,064
4 PEKERJAAN PASANGAN PINTU DAN JENDELA 5,003%
KUSEN DAN PINTU TIPE : 2,639%
1 D1 0,588% 0,588
2 D2 0,365% 0,365
3 D2-A 0,286% 0,286
4 SHF 0,480% 0,480
5 SD1 0,144% 0,144
6 TOI 0,312% 0,156 0,156
7 TOI-A 0,465% 0,233 0,233
KUSEN DAN JENDELA TIPE : 2,363%
1 FR1-E 0,857% 0,429 0,429
2 FR2-E 1,447% 0,724 0,724
3 LV-2E 0,060% 0,030 0,030
5 PEKERJAAN PASANGAN SANITAIR 1,441%
1 Kloset duduk lengkap dengan aksesoris 0,334% 0,167 0,167
2 Wastafel gantung + Kran lengkap dgn aksesoris 0,196% 0,098 0,098
3 Jet washer / Shower spray lengkap dengan aksesoris 0,035% 0,018 0,018
4 Service sink+kran lengkap dengan aksesoris 0,500% 0,250 0,250
5 Slop sink+kran lengkap dengan aksesoris 0,182% 0,091 0,091
6 Floor drain 0,043% 0,022 0,022
7 Tissue Holder 0,036% 0,018 0,018
8 Cove ligth wastafel MDF board fin. cat duco 0,037% 0,050 0,050
9 Kaca cermin 5 mm 0,078% 0,039 0,039
6 PEKERJAAN PENGECATAN 1,113%
1 Cat dinding acrylic emulsion paint 0,234% 0,117 0,117
2 Cat dinding antibacterial acrylic emulsion paint 0,285% 0,143 0,143
3 Cat plafond acrylic emulsion paint 0,041% 0,021 0,021
4 Cat plafond antibacterial acrylic emulsion paint 0,194% 0,097 0,097
5 Cat plafond weathershield 0,329% 0,165 0,165
6 Cat list plafond acrylic profil gypsum emulsion paint 0,005% 0,003 0,003
7 Cat list plafond antibacterial acrylic profil gypsum emulsion paint 0,012% 0,006 0,006
8 Cat list plafond weathershield 0,013% 0,007 0,007
9 Plint Cat int. semi gloss t. 10 cm 0,001% 0,001 0,001
7 PEKERJAAN RAILLING DAN HAND RAILLING 0,149%
1 Handrailing Ø 50 mm Stainless Steel Handrail W/. Satin Polished Finish 0,149% 0,149
8 PEKERJAAN FASADE 63,493%
1 Pemasangan dinding batu andesit fin. Coating 0,719% 0,360 0,360
2 Cat weathershield (eksterior) 0,140% 0,070 0,070
3 Acian beton eksposed 0,020% 0,010 0,010
4 ACP PVDF thick Top & bottom 4 mm, skin 0,5 mm Alloy 3003 (Beckers/PPG) Easy Clean 55,537% 4,628 4,628 4,628 4,628 4,628 4,628 4,628 4,628 4,628 4,628 4,628 4,628
5 ACP PVDF thick Top & bottom 4 mm, skin 0,5 mm Alloy 3003 (Beckers/PPG) (CNC Cutting Pervorated) 4,873% 0,812 0,812 0,812 0,812 0,812 0,812
6 Signage Tulisan :
- Signage Lamp Tulisan ""KLINIK PRATAMA KARSA HUSADA"" Tinggi = 60 cm 1,574% 0,787 0,787
- Signage Lamp Tulisan ""UNIT GAWAT DARURAT"" Tinggi = 30 cm" 0,630% 0,315 0,315
9 PEKERJAAN INTERIOR MELEKAT 0,333%
1 Meja Nurse Station, P=4,1 m
- Teakwood fin. Clear stained finish 0,269% 0,135 0,135
2 Signage toilet bahan stainless steel satin polish finish" 0,064% 0,032 0,032
10 PEKERJAAN PEMATANGAN LAHAN 5,185%
a. Pekerjaan pembersihan lahan 0,564% 0,282 0,282
b. Pekerjaan galian tanah menggunakan alat berat (cutting) 0,325% 0,163 0,163
c. Urugan tanah dari luar site + pemadatan CBR Test 4,296% 0,859 0,859 0,859 0,8592 0,859
11 PEKERJAAN JALAN DAN PARKIR 10,258%
1. Lapisan pondasi bawah (LPB), t = 30 cm 2,425% 0,606 0,606 0,606 0,606
2. Lapisan pondasi atas (LPA), t = 20 cm 1,632% 0,816 0,816
3. Pemadatan CBR test dengan alat berat 0,203% 0,102 0,102
4. Lapisan pengikat aspal 0,302% 0,151 0,151
5. Pekerjaan lapis permukaan aspal t= 5 cm 2,947% 0,982 0,982 0,982
6. Pemasangan Kansteen beton uk. 60/28/15 cm
- Kansteen beton uk. 60/28/15 cm 1,372% 0,686 0,686
- Plesteran 1PC : 4 PP 0,265% 0,133 0,133
- Acian semen 0,270% 0,135 0,135
- Pengecatan Kansteen 0,243% 0,122 0,122
7. Urugan tanah humus 0,179% 0,090 0,090
8. Penanaman rumput gajah mini 0,421% 0,211 0,211
12 PEKERJAAN SALURAN DRAINASE 1,923%
1. Galian tanah 0,061% 0,031 0,031
2. Urugan tanah kembali 0,006% 0,003 0,003
3. Saluran U-dict :
- Saluran U-Ditch uk. 30 x 40 cm 1,274% 0,637 0,637
- Tutup U-dict 50 cm" 0,581% 0,291 0,291
JUMLAH 100%
RENCANA PROGRES MINGGUAN (%) 0,81 0,81 1,15 1,13 1,47 2,71 1,95 2,34 2,20 1,71 1,33 1,48 1,63 4,63 4,63 4,63 5,07 5,07 5,49 6,88 9,74 8,96 7,89 6,13 7,78 2,46
KOMULATIF RENCANA PROGRES MINGGUAN (%) 0,81 1,62 2,77 3,89 5,37 8,08 10,03 12,37 14,57 16,28 17,61 19,09 20,72 25,34 29,97 34,60 39,67 44,74 50,23 57,11 66,86 75,81 83,70 89,83 97,60 100
REALISASI RENCANA PROGRES MINGGUAN (%) 1,25 0,90
REALISASI KOMULATIF RENCANA PROGRES MINGGUAN (%) 1,25 2,15
DEVIASI (%) 0,44 0,53

KETUA PEMBINA KETUA UMUM PENGURUS PELAKSANA LAPANGAN


YAYASAN DHARMA HUSADA INSANI GARUT YAYASAN DHARMA HUSADA INSANI GARUT

Dr. H. HADIAT, MA. H. SURYADI, S.E., M.Si. ADE SUKMA IRAWAN, S.Ars.