Rab Blank Me RSGW
Rab Blank Me RSGW
PEKERJAAN ELEKTRIKAL
1 TOTAL PEKERJAAN PANEL TM DAN TRANSFORMATOR 626,250,000.00
2 TOTAL PEKERJAAN PANEL TEGANGAN RENDAH 7,341,375,000.00
3 TOTAL PEKERJAAN KABEL KABEL FEEDER DAN ACCESORIES 4,410,233,613.00
4 TOTAL PEKERJAAN INSTALASI PENERANGAN, SAKLAR DAN STOP KONTAK 3,181,952,001.00
5 TOTAL PEKERJAAN INSTALASI KABEL LADDER 389,871,232.00
6 TOTAL PEKERJAAN INSTALASI GROUNDING DAN PENAGKAL PETIR 154,500,000.00
PEKERJAAN ELEKTRONIK
7 TOTAL PEKERJAAN FIRE ALARM 922,513,922.00
8 TOTAL PEKERJAAN SOUND SYSTEM 443,919,800.00
9 TOTAL PEKERJAAN TELEPHON 527,592,747.00
10 TOTAL PEKERJAAN MATV 254,536,584.00
11 TOTAL PEKERJAAN CCTV IP CAMERA 430,876,636.00
12 TOTAL PEKERJAAN DATA 510,955,474.00
PEKERJAAN PLUMBING
16 TOTALPEKERJAAN AIR BERSIH 1,698,712,340.00
17 TOTAL PEKERJAAN DEEP WELL 517,670,754.00
18 TOTAL PEKERJAAN AIR KOTOR, AIR BEKAS, AIR HUJAN DAN VENT 2,788,456,785.00
38,804,379,748.20
40,450,626,161.76
STRUKTUR ORGANISASI
PROJECT
MANAGER
SITE
ENGINEERING
SPV. MEP
LABOUR
PENGAJUAN SALARY STAFF
Asumsi Total Perhitungan ( 12 Bulan + 1 Bulan ) : 48,5 juta x 13 bulan = 630,5 juta
Suprapto Engineering
Tengku Rommy Sonatha Hidayat
Logistik
Mukhamad Nurcahyo
SPV
Eduardus Nugroho B. Utomo
Drafter
Suprapto
REKAPITULASI PEKERJAAN ME
RUMAH SAKIT GONDANG WARAS KLATEN
NILAI SETELAH NILAI PEKERJAAN
NO DESKRIPSI PEKERJAAN NILAI PENAWARAN
KEPUTUSAN LAPANGAN
PEKERJAAN ELEKTRIKAL
1 TOTAL PEKERJAAN PANEL TM DAN TRANSFORMATOR 626,250,000.00 538,575,000.00 516,656,250.00
2 TOTAL PEKERJAAN PANEL TEGANGAN RENDAH 7,341,375,000.00 6,313,582,500.00 6,056,634,375.00
3 TOTAL PEKERJAAN KABEL KABEL FEEDER DAN ACCESORIES 4,410,233,613.00 3,792,800,907.18 3,638,442,730.73
4 TOTAL PEKERJAAN INSTALASI PENERANGAN, SAKLAR DAN STOP KONTAK 3,181,952,001.00 2,736,478,720.86 2,625,110,400.83
5 TOTAL PEKERJAAN INSTALASI KABEL LADDER 389,871,232.00 335,289,259.52 321,643,766.40
6 TOTAL PEKERJAAN INSTALASI GROUNDING DAN PENAGKAL PETIR 154,500,000.00 132,870,000.00 127,462,500.00
PEKERJAAN ELEKTRONIK
7 TOTAL PEKERJAAN FIRE ALARM 922,513,922.00 793,361,972.92 761,073,985.65
8 TOTAL PEKERJAAN SOUND SYSTEM 443,919,800.00 381,771,028.00 366,233,835.00
9 TOTAL PEKERJAAN TELEPHON 527,592,747.00 453,729,762.42 435,264,016.28
10 TOTAL PEKERJAAN MATV 254,536,584.00 218,901,462.24 209,992,681.80
11 TOTAL PEKERJAAN CCTV IP CAMERA 430,876,636.00 370,553,906.96 355,473,224.70
12 TOTAL PEKERJAAN DATA 510,955,474.00 439,421,707.64 421,538,266.05
PEKERJAAN PLUMBING
16 TOTALPEKERJAAN AIR BERSIH 1,698,712,340.00 1,460,892,612.40 1,401,437,680.50
17 TOTAL PEKERJAAN DEEP WELL 517,670,754.00 445,196,848.44 427,078,372.05
18 TOTAL PEKERJAAN AIR KOTOR, AIR BEKAS, AIR HUJAN DAN VENT 2,788,456,785.00 2,398,072,835.10 2,300,476,847.63
PEKERJAAN ELEKTRIKAL
1 TOTAL PEKERJAAN PANEL TM DAN TRANSFORMATOR 538,575,000.00 516,656,250.00 361,659,375.00 307,410,468.75 154,996,875.00 131,747,343.75
2 TOTAL PEKERJAAN PANEL TEGANGAN RENDAH 6,313,582,500.00 6,056,634,375.00 4,239,644,062.50 3,603,697,453.12 1,816,990,312.50 1,544,441,765.63
3 TOTAL PEKERJAAN KABEL KABEL FEEDER DAN ACCESORIES 3,792,800,907.18 3,638,442,730.73 2,546,909,911.51 2,164,873,424.78 1,091,532,819.22 927,802,896.33
4 TOTAL PEKERJAAN INSTALASI PENERANGAN, SAKLAR DAN STOP KONTAK 2,736,478,720.86 2,625,110,400.83 1,837,577,280.58 1,561,940,688.49 787,533,120.25 669,403,152.21
5 TOTAL PEKERJAAN INSTALASI KABEL LADDER 335,289,259.52 321,643,766.40 225,150,636.48 191,378,041.01 96,493,129.92 82,019,160.43
6 TOTAL PEKERJAAN INSTALASI GROUNDING DAN PENAGKAL PETIR 132,870,000.00 127,462,500.00 89,223,750.00 75,840,187.50 38,238,750.00 32,502,937.50
PEKERJAAN ELEKTRONIK
7 TOTAL PEKERJAAN FIRE ALARM 793,361,972.92 761,073,985.65 532,751,789.95 452,839,021.46 228,322,195.70 194,073,866.34
8 TOTAL PEKERJAAN SOUND SYSTEM 381,771,028.00 366,233,835.00 256,363,684.50 217,909,131.82 109,870,150.50 93,389,627.93
9 TOTAL PEKERJAAN TELEPHON 453,729,762.42 435,264,016.28 304,684,811.39 258,982,089.68 130,579,204.88 110,992,324.15
10 TOTAL PEKERJAAN MATV 218,901,462.24 209,992,681.80 146,994,877.26 124,945,645.67 62,997,804.54 53,548,133.86
11 TOTAL PEKERJAAN CCTV IP CAMERA 370,553,906.96 355,473,224.70 248,831,257.29 211,506,568.70 106,641,967.41 90,645,672.30
12 TOTAL PEKERJAAN DATA 439,421,707.64 421,538,266.05 295,076,786.23 250,815,268.30 126,461,479.81 107,492,257.84
PEKERJAAN PLUMBING
16 TOTALPEKERJAAN AIR BERSIH 1,460,892,612.40 1,401,437,680.50 981,006,376.35 833,855,419.90 420,431,304.15 357,366,608.53
17 TOTAL PEKERJAAN DEEP WELL 445,196,848.44 427,078,372.05 298,954,860.43 254,111,631.37 128,123,511.61 108,904,984.87
18 TOTAL PEKERJAAN AIR KOTOR, AIR BEKAS, AIR HUJAN DAN VENT 2,398,072,835.10 2,300,476,847.63 1,610,333,793.34 1,368,783,724.34 690,143,054.29 586,621,596.14
23 TOTAL PEKERJAAN GAS MEDIS 3,683,963,522.90 3,534,034,774.88 2,473,824,342.41 2,102,750,691.05 1,060,210,432.46 901,178,867.59
24 TOTAL PEKERJAAN NURSE CALL 810,951,222.68 777,947,393.85 544,563,175.69 462,878,699.34 233,384,218.15 198,376,585.43
REKAP TOTAL MEP 40,450,626,161.76 38,804,379,748.20 27,163,065,823.74 23,088,605,950.18 11,641,313,924.46 9,895,116,835.79
PERSENTASE SELISIH NILAI KONTRAK & PERSENTASE SELISIH RAP 1,646,246,413.56 4,074,459,873.56 1,746,197,088.67
MASTER SCHEDULE PEKERJAAN
PEKERJAAN ELEKTRONIK
7 TOTAL PEKERJAAN FIRE ALARM 1.96% 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008 0.0008
8 TOTAL PEKERJAAN SOUND SYSTEM 0.94% 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004
9 TOTAL PEKERJAAN TELEPHON 1.12% 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005
10 TOTAL PEKERJAAN MATV 0.54% 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002
11 TOTAL PEKERJAAN CCTV IP CAMERA 0.92% 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 60%
12 TOTAL PEKERJAAN DATA 1.09% 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 0.0005 57%
55% 55% 55%
52%
13 TOTAL PEKERJAAN GENSET 8.45% 49%
46%
14 TOTAL PEKERJAAN LIFT 3.60%
44%
15 TOTAL PEKERJAAN PEMADAM KEBAKARAN 6.00% 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020
41%
38%
PEKERJAAN PLUMBING 35%
16 TOTALPEKERJAAN AIR BERSIH 3.61% 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011
33% 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011
17 TOTAL PEKERJAAN DEEP WELL 1.10% 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003
30% 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003
28%
18 TOTAL PEKERJAAN AIR KOTOR, AIR BEKAS, AIR HUJAN DAN VENT 5.93% 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019
26%
23%
21%
19%
PEKERJAAN TATA UDARA 18%
16%
19 TOTAL PEKERJAAN AIR CONDITIONING 12.92% 0.0043 0.0043 0.0043 0.0043 0.004314% 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043
22 TOTAL PEKERJAAN HVAC SYSTEM 6.47% 0.0022 0.0022 0.0022 0.002212% 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022
10%
8%
6%
4%
23 TOTAL PEKERJAAN GAS MEDIS 9.11% 3% 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033
2% 2%
0% 1%
24 TOTAL PEKERJAAN NURSE CALL 2.00% 0% 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
0.0000% 0.4228% 0.4228% 0.7553% 0.7553% 1.0371% 1.0764% 1.7694% 1.7919% 1.8301% 2.2722% 2.0088% 2.0088% 1.6367% 1.5974% 1.9675% 1.9843% 2.6391% 2.2196% 2.1887% 2.6308% 2.2983% 2.2983% 3.1285% 3.0892% 2.5962% 2.5737% 3.1817% 2.7396% 0.0000%
TOTAL BOBOT MEP 100.00%
0.0000% 0.4228% 0.8456% 1.6010% 2.3563% 3.3934% 4.4698% 6.2391% 8.0311% 9.8612% 12.1334% 14.1422% 16.1510% 17.7877% 19.3851% 21.3527% 23.3370% 25.9761% 28.1957% 30.3844% 33.0151% 35.3134% 37.6117% 40.7401% 43.8293% 46.4255% 48.9991% 52.1809% 54.9205% 54.9205%
Jan-24 Feb-24 Mar-24 Apr-24 May-24
31/12 - 06/01 07/01 - 13/01 14/01 - 20/01 21/01 - 27/01 28/01 - 03/02 04/02 - 10/02 11/02 - 17/02 18/02 - 24/02 25/02 - 02/03 03/03 - 09/03 10/03 - 16/03 17/03 - 23/03 24/03 - 30/03 31/03 - 06/04 07/04 - 13/04 14/04 - 20/04 21/04 - 27/04 28/04 - 04/05 05/05 - 11/05 12/05 - 18/05 19/05 - 25/05 26/05 - 01/06
0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011 0.0011
0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003
0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019 0.0019
0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043 0.0043
0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022
0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033
0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007
29 30 31 32 33
34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
0.0000% 2.2010% 2.5979% 2.8797% 2.9190% 2.2350% 2.2575% 1.8814% 1.8874% 0.5028% 0.0834% 0.0453% 0.0000% 0.0000% 6.3973% 6.3973% 6.3973% 6.3973%
54.9205% 57.1215% 59.7194% 62.5991% 65.5181% 67.7530% 70.0105% 71.8920% 73.7793% 74.2822% 74.3656% 74.4109% 74.4109% 74.4109% 80.8082% 87.2054% 93.6027% ###
RENCANA ANGGARAN BIAYA
PEKERJAAN : PROYEK RUMAH SAKIT GONDANG WARAS
LOKASI : KABUPATEN KLATEN
Unit Rate Amount
No. Description Quantity
(Rp) (Rp)
PEKERJAAN ELEKTRIKAL
A PEKERJAAN PANEL TM DAN TRANSFORMATOR
Pengadaan dan Pemasangan Panel, termasuk brakers, box panel, busbar, grounding,
penyambungan, semuanya terpasanga dengan baik sesuai dengan spesifikasi dan
gambar
D. INSTALASI
PENERANGAN,
Pengadaan dan pemasangan accessories lampu, saklar dan stop kontak ,
SAKLAR DAN STOP
KONTAK
terpasang dengan baik sesuai spesifikasi dan gambar
1 LANTAI BASEMENT
- TKI 2 x 36 Watt Cover 30 bh 1,022,727 30,681,810
Acrilic
- TKI 2 x 36 Watt 9 bh 681,818 6,136,362
- Down Light PL 18 29 bh 392,045 11,369,305
Watt
- Exhaust Fan type 62 bh 1,022,727 63,409,074
Ceiling
- Saklar Tunggal 15 bh 54,545 818,175
- Saklar Ganda 32 bh 61,364 1,963,648
- Stop Kontak 1 Phase 19 bh 61,364 1,165,916
- Instalasi Penerangan 120 ttk 289,773 34,772,760
- Instalasi Saklar 47 ttk 64,914 3,050,958
- Instalasi Stop Kontak 19 ttk 540,948 10,278,012
- Instalasi Exhaust Fan 62 ttk 757,327 46,954,274
- Material Bantu 1 lot 28,745,905 28,745,905
SUB TOTAL LANTAI BASEMENT 239,346,199
2 LANTAI I
- TKI 2 x 36 Watt Cover 40 bh 1,661,719 66,468,760
Acrilic
- TKO 2 x 36 Watt c/w 4 bh 2,811,346 11,245,384
Battery
- Down Light PL 18 460 bh 470,293 216,334,780
Watt
- Exit Lamp 10 Watt c/w 6 bh 2,246,982 13,481,892
Battery
- Exhaust Fan type 40 bh 2,574,911 102,996,440
Ceiling
- Saklar Tunggal 95 bh 57,545 5,466,775
- Saklar Ganda 130 bh 87,546 11,380,980
- Stop Kontak 1 Phase 120 bh 80,871 9,704,520
- Instalasi Penerangan 510 ttk 476,034 242,777,340
- Instalasi Saklar 225 ttk 64,914 14,605,650
- Instalasi Stop Kontak 120 ttk 540,948 64,913,760
- Instalasi Exhaust Fan 40 ttk 757,327 30,293,080
- Material Bantu 1 lot 66,479,372 66,479,372
SUB TOTAL LANTAI I 856,148,733
3 UTILITY
- TKO 2 x 36 Watt 21 bh 803,360 16,870,560
- Saklar Tunggal 4 bh 57,545 230,180
- Saklar Ganda 2 bh 87,546 175,092
- Stop Kontak 1 Phase 8 bh 80,871 646,968
- Instalasi Penerangan 21 ttk 476,034 9,996,714
- Instalasi Saklar 6 ttk 64,914 389,484
- Instalasi Stop Kontak 8 ttk 540,948 4,327,584
- Material Bantu 1 lot 2,751,601 2,751,601
SUB TOTAL UTILITY 35,388,183
4 LANTAI II
- TKI 2 x 36 Watt Cover 30 bh 1,661,719 49,851,570
Acrilic
- Down Light PL 18 464 bh 470,293 218,215,952
Watt
- Exit Lamp 10 Watt c/w 5 bh 2,246,982 11,234,910
Battery
- Exhaust Fan type 50 bh 2,574,911 128,745,550
Ceiling
- Saklar Tunggal 90 bh 57,545 5,179,050
- Saklar Ganda 124 bh 87,546 10,855,704
- Stop Kontak 1 Phase 260 bh 80,871 21,026,460
- Instalasi Penerangan 499 ttk 476,034 237,540,966
- Instalasi Saklar 214 ttk 64,914 13,891,596
- Instalasi Stop Kontak 260 ttk 540,948 140,646,480
- Instalasi Exhaust Fan 50 ttk 757,327 37,866,350
- Material Bantu 1 lot 74,788,585 74,788,585
SUB TOTAL LANTAI II 949,843,173
5 LANTAI III
- TKI 2 x 36 Watt Cover 12 bh 1,661,719 19,940,628
Acrilic
- TKI 2 x 36 Watt Cover 4 bh 3,647,434 14,589,736
Acrilic c/w Battery
- Down Light PL 18 360 bh 470,293 169,305,480
Watt
- Exit Lamp 10 Watt c/w 3 bh 2,246,982 6,740,946
Battery
- Exhaust Fan type 15 bh 2,574,911 38,623,665
Ceiling
- Saklar Tunggal 110 bh 57,545 6,329,950
- Saklar Ganda 84 bh 87,546 7,353,864
- Stop Kontak 1 Phase 106 bh 80,871 8,572,326
- Instalasi Penerangan 379 ttk 476,034 180,416,886
- Instalasi Saklar 194 ttk 64,914 12,593,316
- Instalasi Stop Kontak 106 ttk 540,948 57,340,488
- Instalasi Exhaust Fan 15 ttk 757,327 11,359,905
- Material Bantu 1 lot 45,561,179 45,561,179
SUB TOTAL LANTAI III 578,728,369
6 LANTAI ATAP
- Lampu Sorot 100 Watt 2 bh 5,978,030 11,956,060
LED
- Saklar Tunggal 1 bh 57,545 57,545
- Saklar Ganda 2 bh 87,546 175,092
- Stop Kontak 1 Phase 2 bh 80,871 161,742
- Instalasi Lampu Sorot 2 ttk 757,327 1,514,654
- Instalasi Saklar 3 ttk 64,914 194,742
- Instalasi Stop Kontak 2 ttk 540,948 1,081,896
- Material Bantu 1 lot 1,161,305 1,161,305
SUB TOTAL LANTAI ATAP 16,303,036
7 PENERANGAN
LUAR
- Lampu Jalan, Halogen 25 bh 12,750,349 318,758,725
250 Watt c/w tiang PJU
- Pondasi Tiang 25 bh 1,211,723 30,293,075
bulat 9 mtr
- Instalasi Lampu Jalan 25 ttk 1,947,412 48,685,300
- Galian Kabel 380 mtr 202,848 77,082,240
- Material Bantu 1 lot 31,374,968 31,374,968
SUB TOTAL PENERANGAN LUAR 506,194,308
TOTAL PEKERJAAN INSTALASI PENERANGAN, SAKLAR DAN STOP KONTAK 3,181,952,001
RENCANA ANGGARAN BIAYA
PEKERJAAN : PROYEK RUMAH SAKIT GONDANG WARAS
LOKASI : KABUPATEN KLATEN
Unit Rate Amount
No. Description Quantity
(Rp) (Rp)
1 LANTAI BASEMENT
- Kabel Rack / Ladder, 300 x 100 x 3000 112 mtr 337,331 37,781,072
- Accessories 1 lot 10,794,996 10,794,996
- Material Bantu 1 lot 4,048,112 4,048,112
2 LANTAI I
- Kabel Rack / Ladder, 1000 x 100 x 3000 36 mtr 573,616 20,650,176
- Kabel Rack / Ladder, 600 x 100 x 3000 75 mtr 417,856 31,339,200
- Kabel Rack / Ladder, 300 x 100 x 3000 124 mtr 337,331 41,829,044
- Kabel Rack / Ladder, 200 x 100 x 3000 90 mtr 307,165 27,644,850
- Accessories 1 lot 34,704,690 34,704,690
- Material Bantu 1 lot 13,014,253 13,014,253
3 LANTAI II
- Kabel Rack / Ladder, 300 x 100 x 3000 233 mtr 337,331 78,598,123
- Kabel Rack / Ladder, 200 x 100 x 3000 70 mtr 307,165 21,501,550
- Accessories 1 lot 28,600,871 28,600,871
- Material Bantu 1 lot 10,725,321 10,725,321
4 LANTAI III
- Kabel Rack / Ladder, 200 x 50 x 3000 92 mtr 224,471 20,651,332
- Accessories 1 lot 5,775,000 5,775,000
- Material Bantu 1 lot 2,212,642 2,212,642
TOTAL PEKERJAAN INSTALASI KABEL LADDER 389,871,232
F. INSTALASI GROUNDING DAN PENANGKAL PETIR
Pengadaan dan pemasangan grounding system dan penangkal petir lengkap dengan
hanger, material bantu dan accessories yang dibutuhkan sesuai dengan gambar dan spesifikasi.
3 Grounding Pit, lengkap dengan bak kontrol, cooper rod 25 mm 2 bh 8,250,000 16,500,000
diameter dengan kedalam minimum 12 meter atau tahanan
pentanahan maksimum 2 OHM (penangkal petir)
4 Grounding Pit, lengkap dengan bak kontrol, terminal grounding 1 lot 8,250,000 8,250,000
box, cooper rod 25 mm2 dengan kedalam minimum 12 meter
atau tahanan pentanahan maksimum 1 OHM, termasuk semua
asesoris ( Untuk peralatan Electronic )
5 Grounding Pit, lengkap dengan bak kontrol, cooper plate, 1 lot 8,250,000 8,250,000
cooper rod 25 mm2 dengan kedalam minimum 12 meter
atau tahanan pentanahan maksimum 2 OHM (TM)
6 Grounding Pit, lengkap dengan bak kontrol, cooper plate, 1 lot 8,250,000 8,250,000
cooper rod 25 mm2 dengan kedalam minimum 12 meter
atau tahanan pentanahan maksimum 2 OHM (Transformer)
7 Grounding Pit, lengkap dengan bak kontrol, cooper plate, 1 lot 8,250,000 8,250,000
cooper rod 25 mm2 dengan kedalam minimum 12 meter
atau tahanan pentanahan maksimum 2 OHM ( LVMDP)
8 Grounding Pit, lengkap dengan bak kontrol, cooper plate, 1 lot 8,250,000 8,250,000
cooper rod 25 mm2 dengan kedalam minimum 12 meter
atau tahanan pentanahan maksimum 2 OHM (Genset)
TOTAL PEKERJAAN INSTALASI GROUNDING DAN PENANGKAL PETIR 154,500,000
GRAND TOTAL PEKERJAAN ELEKTRIKAL 16,104,181,846
RENCANA ANGGARAN BIAYA
PEKERJAAN : PROYEK RUMAH SAKIT GONDANG WARAS
LOKASI : KABUPATEN KLATEN
Unit Rate Amount
No. Description Quantity
(Rp) (Rp)
PEKERJAAN ELEKTRONIK
1 PERALATAN UTAMA
- Master Control Fire Alarm (MCFA) 1 Loop, Semi Addresable 1 set 49,194,519 49,194,519
- MTB - MCFA 1 bh 5,856,490 5,856,490
- Announciator 1 Loop 1 set 18,740,764 18,740,764
- Kabel control dari MCFA ke Panel Announciator, in conduit PVC Hi 25 mm 1 lot 12,495,893 12,495,893
- Material bantu 1 lot 2,499,179 2,499,179
- Testing Commisioning 1 lot 7,497,536 7,497,536
SUB TOTAL PERALATAN UTAMA 96,284,381
2 LANTAI 1 DAN BASEMENT
- Manual Call Point 9 bh 410,264 3,692,376
- Alarm Bell 9 bh 468,602 4,217,418
- Indicator lamp 9 bh 135,285 1,217,565
- Handset/Intercom 9 bh 213,428 1,920,852
- Smoke detector 126 bh 538,820 67,891,320
- Rate of heat detector 4 bh 170,974 683,896
- Juction Box Fire Alarm ( JB-FA1), termasuk module 3 bh 4,216,697 12,650,091
- Instalasi Manual Call Point 9 ttk 374,977 3,374,793
- Instalasi Alarm Bell 9 ttk 374,977 3,374,793
- Instalasi Indicator Lamp 9 ttk 374,977 3,374,793
- Instalasi Detector 130 ttk 316,563 41,153,190
- Material bantu 1 lot 17,577,730 17,577,730
SUB TOTAL LANTAI I 161,128,817
3 LANTAI II
- Manual Call Point 6 bh 410,264 2,461,584
- Alarm Bell 6 bh 468,602 2,811,612
- Indicator lamp 6 bh 135,285 811,710
- Handset/Intercom 6 bh 213,428 1,280,568
- Smoke detector 112 bh 538,820 60,347,840
- Rate of heat detector 10 bh 170,974 1,709,740
- Juction Box Fire Alarm ( JB-FA1), termasuk module 2 bh 4,216,697 8,433,394
- Instalasi Manual Call Point 6 ttk 374,977 2,249,862
- Instalasi Alarm Bell 6 ttk 374,977 2,249,862
- Instalasi Indicator Lamp 6 ttk 374,977 2,249,862
- Instalasi Detector 122 ttk 316,563 38,620,686
- Material bantu 1 lot 15,147,075 15,147,075
SUB TOTAL LANTAI II 138,373,795
4 LANTAI III
- Manual Call Point 6 bh 410,264 2,461,584
- Alarm Bell 6 bh 468,602 2,811,612
- Indicator lamp 6 bh 135,285 811,710
- Handset/Intercom 6 bh 213,428 1,280,568
- Smoke detector 105 bh 538,820 56,576,100
- Rate of heat detector 5 bh 170,974 854,870
- Juction Box Fire Alarm ( JB-FA1), termasuk module 1 bh 4,216,697 4,216,697
- Instalasi Manual Call Point 6 ttk 374,977 2,249,862
- Instalasi Alarm Bell 6 ttk 374,977 2,249,862
- Instalasi Indicator Lamp 6 ttk 374,977 2,249,862
- Instalasi Detector 110 ttk 316,563 34,821,930
- Material bantu 1 lot 13,629,758 13,629,758
SUB TOTAL LANTAI III 124,214,415
5 PENGKABELAN FIRE ALARM
Pengadaan dan pemasangan kabe fire alarm c/w pipa conduit Hi 20mm
termasuk support dan accesories.
a. Dari Announciator ke MCFA
- STP AWG 18 + NYM 3 x 2,5 mm2 200 mtr 89,803 17,960,600
b. Dari MCFA ke MTB-MCFA
- STP AWG 18 + FRC 2 x 1,5 mm2 20 mtr 116,582 2,331,640
c. Dari MTB-MCFA ke JB-FA Basement
- STP AWG 18 + FRC 2 x 1,5 mm2 40 mtr 116,582 4,663,280
d. Dari MTB-MCFA ke JB-FA 1
- STP AWG 18 + FRC 2 x 1,5 mm2 36 mtr 116,582 4,196,952
e. Dari MTB-MCFA ke JB-FA 2
- STP AWG 18 + FRC 2 x 1,5 mm2 10 mtr 116,582 1,165,820
f Dari MTB-MCFA ke JB-FA 3
- STP AWG 18 + FRC 2 x 1,5 mm2 12 mtr 116,582 1,398,984
g. Dari MCFA ke Intercom
- ITC 2 x 2 x 0,6 mm2 150 mtr 22,149 3,322,350
h. Dari MCFA ke Terminal Box Grounding
- NYA 10 mm2 100 mtr 54,196 5,419,600
i. Material Bantu 1 lot 5,780,400 5,780,400
SUB TOTAL PEKERJAAN PENGKABELAN FA 46,239,626
6 PEKERJAAN KABEL TRAY
Pengadaan dan pemasangan kabel tray lengkap dengan peyanggah, hager, material bantu
dan accessories yang dibutuhkan sesuai dengan spesifikasi dan gambar
1 PERALATAN UTAMA
a. Central System 1 ls 142,745,604 142,745,604
Mixer Pre-Amfiefier : 1 bh
MDF-SS : 1 bh
Speaker Selector, 10 : 1 bh
Power Amflifier, 240 W : 4 bh
Mixer call car sysyem : 1 bh
Tunner FM/AM : 1 bh
Tape Deck, compac disc : 1 bh
Emergency Mic : 1 bh
Paging + Chime : 2 bh
UPS, 4 jam : 1 bh
Arester : 1 bh
b. Terminal Box, TB 1 sampai TB 7 6 unit 816,398 4,898,388
c. Ceiling Speaker 3 W 309 bh 291,571 90,095,439
d. Columb Speaker 6 W 11 bh 1,154,611 12,700,721
e. Volume Control 68 bh 274,074 18,637,032
2 INSTALASI SOUNDS SYSTEM
Pengadaan dan pemasangan kabel tata suara didalam konduit 20 mm diameter,
terpasang dengan baik lengkap dengan support dan assesoris, sesuai gambar dan spesifikasi
a. NYMHY 3 x 1,5 mm, ke 309 ttk 499,836 154,449,324
b. NYMHY 3 x 1,5 mm, ke 11 ttk 499,836 5,498,196
c. NYMHY 3 x 1,5 mm, ke 68 ttk 85,686 5,826,648
d. Grounding System 1 lot 4,070,091 4,070,091
e. Koneksi kabel di area 1 lot 4,998,357 4,998,357
TOTAL PEKERJAAN SOUND SYSTEM 443,919,800
RENCANA ANGGARAN BIAYA
PEKERJAAN : PROYEK RUMAH SAKIT GONDANG WARAS
LOKASI : KABUPATEN KLATEN
Unit Rate Amount
No. Description Quantity
(Rp) (Rp)
C. PEKERJAAN TELEPHONE
Pengadaan dan pemasangan peralatan telepon, lengkap dengan material bantu,
assesoris pelengkap, terpasang dengan baik sesuai dengan spesifikasi dan gambar
1 PERALATAN UTAMA
a. PABX , 12/200 lengkap dengan battery 1 unit 332,672,641 332,672,641
b. MDF, 200 pairs, termasuk kabel grounding ke terminal box 1 unit 6,997,700 6,997,700
c. Terminal Box, 20 pair 1 bh 699,770 699,770
d. Terminal Box, 30 pair 4 bh 699,770 2,799,080
e. Telepon Outlet, Basement 5 bh 109,962 549,810
f. Telepon Outlet, lantai 1 dan Pos Jaga 45 bh 109,962 4,948,290
g. Telepon Outlet, lantai 2 16 bh 109,962 1,759,392
h. Telepon Outlet, lantai 3 32 bh 109,962 3,518,784
i. Pesawat Telepon Digital 5 bh 3,898,718 19,493,590
j. Pesawat Telepon Analog 110 bh 309,896 34,088,560
2 INSTALASI TELEPON
Pengadaan dan pemasangan kabel telepon didalam konduit termasuk terminasi lengkap dengan
support dan asesoris sesuai dengan gambar dan spesifikasi
a. ITC 6 x (50 x 2 x 0,6 mm2) + konduit, dari PABX ke MDF 10 mtr 733,324 7,333,240
b. ITC 30 x 2 x 0,6 mm2 + konduit, dari MDF ke TB I/1 dan TB I/2 275 mtr 103,130 28,360,750
c. ITC 30 x 2 x 0,6 mm2 + konduit, dari MDF ke TB II/1 dan TB II/2 350 mtr 103,130 36,095,500
d. ITC 30 x 2 x 0,6 mm2 + konduit, dari MDF ke TB III 80 mtr 103,130 8,250,400
e. Instalasi Telephon ( ITC 2 x 2 x 0,6 in conduit PVC Hi 20 mm ) 98 ttk 314,182 30,789,836
f. Material BAntu 1 lot 9,235,404 9,235,404
TOTAL PEKERJAAN TELEPHON 527,592,747
D. PEKERJAAN MATV
Pengadaan dan pemasangan peralatan MATV, lengkap dengan material bantu,
assesoris pelengkap, terpasang dengan baik sesuai dengan spesifikasi dan gambar
1 PERALATAN UTAMA
a. Power Divider 5 Way 1 bh 1,713,722 1,713,722
b. Power Divider 4 Way 1 bh 1,570,912 1,570,912
c. Reciver Digital 14 bh 3,998,686 55,981,604
d. VSB Modulator 14 bh 5,569,598 77,974,372
e. Active Combiner 1 bh 8,282,992 8,282,992
f. Surge Arester 1 bh 1,499,507 1,499,507
g. Terminal Box Utama c/w Spliter 8 port 1 bh 1,299,573 1,299,573
h. Material Bantu 1 lot 2,999,014 2,999,014
i. Pengkabelan dari parabola ke peralatan utama 1 lot 9,996,714 9,996,714
j. Testing and Commisioning 1 lot 5,998,028 5,998,028
2 INSTALASI MATV
Pengadaan dan pemasangan kabel matv didalam konduit termasuk terminasi lengkap dengan
support dan asesoris sesuai dengan gambar dan spesifikasi
a. Lantai Basement
- Terminal Box TV c/w Spliter 6 port 1 unit 1,099,639 1,099,639
- Outlet TV 1 bh 114,954 114,954
- Instalasi MATV ( Coaxial RG 6 in conduit PVC Hi 20 mm2 ) 1 ttk 828,299 828,299
- Material Bantu 1 lot 357,026 357,026
b. Lantai I
- Terminal Box TV c/w Spliter 6 port 6 unit 1,099,639 6,597,834
- Outlet TV 27 bh 114,954 3,103,758
- Instalasi MATV ( Coaxial RG 6 in conduit PVC Hi 20 mm2 ) 27 ttk 828,299 22,364,073
- Material Bantu 1 lot 2,142,253 2,142,253
c. Lantai II
- Terminal Box TV c/w Spliter 6 port 7 unit 1,099,639 7,697,473
- Outlet TV 37 bh 114,954 4,253,298
- Instalasi MATV ( Coaxial RG 6 in conduit PVC Hi 20 mm2 ) 37 ttk 828,299 30,647,063
- Material Bantu 1 lot 2,499,179 2,499,179
d. Lantai III
- Terminal Box TV c/w Spliter 6 port 1 unit 1,099,639 1,099,639
- Outlet TV 4 bh 114,954 459,816
- Instalasi MATV ( Coaxial RG 6 in conduit PVC Hi 20 mm2 ) 4 ttk 828,299 3,313,196
- Material Bantu 1 lot 642,646 642,646
TOTAL PEKERJAAN MATV 254,536,584
F. PEKERJAAN DATA
Pengadaan dan pemasangan peralatan data, lengkap dengan material bantu,
assesoris pelengkap, terpasang dengan baik sesuai dengan spesifikasi dan gambar
1 PERALATAN UTAMA
a. Switch Hub Giga Byte, 24 port 5 bh 3,098,981 15,494,905
b. Server/Gateway 1 set 31,500,000 31,500,000
c. Router/Broadband 25 bh 2,999,014 74,975,350
d. Access Point (Wifi) 25 bh 2,949,031 73,725,775
e. Outlet Data 70 bh 174,942 12,245,940
f. Rak 1 unit 8,997,043 8,997,043
2 INSTALASI DATA
Pengadaan dan pemasangan kabel data didalam konduit 20 mm diameter, terpasang dengan
baik lengkap dengan terminasi support dan assesoris lainnya, sesuai dengan spesifikasi gambar
a. Instalasi Data ( Kabel UTP Cat 6 In Conduit PVC Hi Ø 20 mm ) 95 ttk 2,784,799 264,555,905
b. Instalasi Data ( Kabel UTP Cat 6 In Conduit PVC Hi Ø 20 mm ), dari swicth Hub ke peralatan 5 ttk 3,641,660 18,208,300
utama ( Server )
c. NYA 10 mm2 dari MDF-SS ke Terminal Grounding Electronik 150 mtr 46,453 6,967,950
d. Koneksi kabel di area peralatan utama 1 lot 4,284,306 4,284,306
A PERALATAN UTAMA
Pengadaan dan pemasangan peralatan utama lengkap dengan support dan aksesoris pelengkap
dengan spesifikasi dan gambar.
2 PEMIPAAAN
Pengadaan dan pemasangan Hydrant dar bahan baja hitam sch 40, lengkap dengan
fiting-fiting, penyanggah, terpasang dengan baik sesuai spesifikasi dan gambar.
a. Pipa Hydrant Diameter :
- 100 mm 9 mtr 562,500 5,062,500
- 80 mm 83 mtr 337,500 28,012,500
- 65 mm 12 mtr 262,500 3,150,000
- 40 mm 3 mtr 112,500 337,500
b. Fitting - fitting 1 lot 7,500,000 7,500,000
c. Material Bantu 1 lot 6,000,000 6,000,000
d. Suporting Material 1 lot 2,250,000 2,250,000
3 Pengadaan dan pemasangan valve 16 Kg dan perlengkapannya.
a. Gate Valve, diameter :
- 100 mm 1 bh 10,729,793 10,729,793
SUB TOTAL LANTAI BASEMENT 95,863,378
C. LANTAI SATU DAN RUANG POMPA
1. PEMIPAAN
Pengadaan dan pemasangan pipa Hydrant / bahan baja hitam sch 40, lengkap dengan
fiting-fiting, penyanggah, terpasang dengan baik sesuai dengan spesifikasi dan gambar.
a. Pemipaan ruang pompa dan pipa header, 250 mm diameter termasuk end cap, 1 lot 28,407,329 28,407,329
b. Pipa Hydrant diameter :
- 150 mm 38 m 851,670 32,363,460
- 100 mm 504 m 486,864 245,379,456
- 80 mm 157 m 342,007 53,695,099
- 65 mm 15 m 262,611 3,939,165
- 50 mm 20 m 164,964 3,299,280
- 40 mm 7 m 130,099 910,693
- 25 mm ( dari kontrol ke flow switch area pompa ) 10 m 76,170 761,700
c. Fitting - fitting 1 lot 72,932,306 72,932,306
d. Material Bantu 1 lot 32,998,601 32,998,601
e. Suporting Material 1 lot 24,310,765 24,310,765
f. Galian dan Pengurugan 390 mtr 168,689 65,788,710
2 PEMIPAAN
Pengadaan dan pemasangan pipa Hydrant / Sprinklers dari bahan baja hitam sch 40, lengkap
dengan fiting-fiting, penyanggah, terpasang dengan baik sesuai spesifikasi dan gambar.
a. Pipa Hydrant, diameter:
- 100 mm 88 mtr 486,864 42,844,032
- 80 mm 130 mtr 342,007 44,460,910
- 65 mm 15 mtr 262,611 3,939,165
- 40 mm 6 mtr 130,099 780,594
b. Fitting - fitting 1 lot 19,719,748 19,719,748
c. Material Bantu 1 lot 9,859,874 9,859,874
d. Suporting Material 1 lot 6,573,246 6,573,246
2 PEMIPAAAN
Pengadaan dan pemasangan Hydrant dar bahan baja hitam sch 40, lengkap dengan fiting-fiting,
penyanggah, terpasang dengan baik sesuai spesifikasi dan gambar.
a. Pipa Hydrant, diameter :
- 100 mm 99 mtr 486,864 48,199,536
- 80 mm 95 mtr 488,581 46,415,195
- 65 mm 15 mtr 375,159 5,627,385
- 40 mm 6 mtr 185,856 1,115,136
b. Fitting - fitting 1 lot 26,146,101 26,146,101
c. Material Bantu 1 lot 13,073,051 13,073,051
d. Suporting Material 1 lot 8,715,367 8,715,367
PEKERJAAN PLUMBING
A. PEKERJAAN AIR BERSIH
Pengadaan dan Pemasangan peralatan utama lengkap dengan suport, assesoris sesuai
dengan spesifikasi dan gambar
f Tanki Air Bersih (Bahan Fiber lengkap dengan Pondasi) 2 set 131,250,000 262,500,000
- Kapasitas 15 m3
- Type Panel
g. Pemipaan dan Header Air Bersih Ruang Pompa 1 lot 45,363,240 45,363,240
h. Pemipaan dan Header Air Bersih untuk Tanki Atas dan Booster Pump 1 lot 35,912,565 35,912,565
i. Material Bantu 1 lot 15,401,100 15,401,100
j. Suporting Material 1 lot 15,401,100 15,401,100
c. Pemipaan
Pipa Suplay dari Ruang Utility ke Roof Tank Lantai Atas ( PPR PN-10 )
- Dia 80 mm 192 mtr 457,316 87,804,672
- Fitting - Fitting 1 lot 18,815,460 18,815,460
- Material Bantu 1 lot 6,271,820 6,271,820
- Suporting Material 1 lot 6,860,490 6,860,490
SUB TOTAL PEKERJAAN PERALATAN UTAMA 1,375,448,861
2 LANTAI BASEMENT
a. Pemipaan
- Pipa PPR PN 10, diameter :
- 32 mm 114 mtr 92,479 10,542,606
- 20 mm 20 mtr 36,213 724,260
- 15 mm 42 mtr 27,710 1,163,820
- Fitting - fitting 1 lot 3,107,791 3,107,791
- Material Bantu 1 lot 887,933 887,933
- Suporting Material 1 lot 917,335 917,335
2 PEKERJAAN KONTRUKSI
a. Pengadaan, Pompa Submersible 5 HP 380V 3 Phase (Franklin) 1 bh 169,062,075 169,062,075
Termasuk Control Panel, WLC, Suport dan asesories
b. Pipa PVC AW, diameter:
- 6" 80 mtr 399,208 31,936,640
- 4" 120 mtr 171,676 20,601,120
- 2,5" 72 mtr 100,846 7,260,912
c. Screen L/C dia. 3" 12 mtr 580,384 6,964,608
d. Grevel Pack 11 m3 1,029,074 11,319,814
e. Groting Sement 6 sak 1,989,542 11,937,252
f. Pembuatan Tutup Sumur Bor 1 bh 4,802,343 4,802,343
TOTAL PEKERJAAN DEEP WELL 517,670,754
C. PEKERJAAN AIR KOTOR, AIR BEKAS, AIR HUJAN DAN VENT
Pengadaan dan Pemasangan peralatan utama lengkap dengan suport, assesoris sesuai
dengan spesifikasi dan gambar
1 PERALATAN UTAMA
a. Pompa Submersible 2 unit 12,958,382 25,916,764
- Kapasitas : 100 Lpm
- Tekanan : 30 meter, lengkap dengan Water Level Control
e. Sumur Resapan
Ukuran : 1200 mm x 4000 mm
b. Instalasi Pipa Refrigerant c/w isolasi , lengkap dengan support dan terpasang dengan baik.
- Pipa Refrigerant, 3/8 dan 5/8 58 mtr 506,934 29,402,172
- Pipa Refrigerant, 3/8 dan 5/8 35 mtr 506,934 17,742,690
- Pipa Refrigerant, 3/8 dan 3/4 71 mtr 572,426 40,642,246
- Fitting Pipa 1 lot 15,676,452 15,676,452
b. Ac Cassette
- Kap : 18,000 Btu/h ( 2 Pk ) 6 unit 36,517,408 219,104,448
- Kap : 22,500 Btu/h ( 2,5 Pk ) 3 unit 42,603,643 127,810,929
- Kap : 26,000 Btu/h ( 3 Pk ) 3 unit 44,985,213 134,955,639
c. Instalasi Pipa Refrigerant c/w isolasi , lengkap dengan support dan terpasang dengan baik.
- Pipa Refrigerant, 1/4dan 3/8 640 mtr 311,479 199,346,560
- Pipa Refrigerant, 1/4 dan 1/2 124 mtr 377,846 46,852,904
- Pipa Refrigerant, 1/4 dan 5/8 112 mtr 451,419 50,558,928
- Fitting Pipa 1 lot 52,992,753 52,992,753
b. Ac Cassette
- Kap : 18,000 Btu/h ( 2 Pk ) 4 unit 36,517,408 146,069,632
- Kap : 22,500 Btu/h ( 2 1/2 Pk ) 6 unit 42,603,643 255,621,858
- Kap : 28,000 Btu/h ( 3 Pk ) 4 unit 44,985,213 179,940,852
- Kap : 36,000 Btu/h ( 4 Pk ) 1 unit 58,216,158 58,216,158
c. Instalasi Pipa Refrigerant c/w isolasi , lengkap dengan support dan terpasang dengan baik.
- Pipa Refrigerant, 1/4dan 3/8 767 mtr 311,479 238,904,393
- Pipa Refrigerant, 1/4 dan 1/2 60 mtr 377,846 22,670,760
- Pipa Refrigerant, 1/4 dan 5/8 180 mtr 451,419 81,255,420
- Pipa Refrigerant, 3/8 dan 5/8 22 mtr 506,934 11,152,548
- Fitting Pipa 1 lot 63,211,471 63,211,471
b. Ac Cassette
- Kap : 18,000 Btu/h ( 2 Pk ) 10 unit 37,869,905 378,699,050
- Kap : 36,000 Btu/h ( 4 Pk ) 1 unit 60,372,312 60,372,312
- Kap : 45,000 Btu/h ( 5 Pk ) 4 unit 66,272,333 265,089,332
c. Instalasi Pipa Refrigerant c/w isolasi , lengkap dengan support dan terpasang dengan baik.
- Pipa Refrigerant, 1/4dan 3/8 715 mtr 311,479 222,707,485
- Pipa Refrigerant, 1/4 dan 1/2 330 mtr 377,846 124,689,180
- Pipa Refrigerant, 3/8 dan 3/4 75 mtr 572,426 42,931,950
- Fitting Pipa 1 lot 69,701,978 69,701,978
1 LANTAI BASMENT
a. Central Oksigen Manual sistem Kap. 2 x 10 Cylinder 1 unit 90,000,000 90,000,000
b. Cylinder Oxygen tbg 10 tbg 6,048,432 60,484,320
c. Nitrous Oxide manual system kap. 2 x 2 Cylinder 1 unit 41,129,322 41,129,322
d. Cylinder Nitrous Oxide Include Isi 4 tbg 16,028,337 64,113,348
e. Compressor Air Duplex kap. 2 x 5kw Merk. Atlas copco 1 unit 562,500,000 562,500,000
Kap : 480 ltr/menit
Kap.Tanki : 500 ltr
Panel Mounted with bracked
Air Dryer with filter
d. Vacuum kap. 2 x 2,4kw Duplex merk.Becker 1 unit 562,500,000 562,500,000
Model : U4.70 SAK
Kap. : 63 M3/jam
Kap.Tanki : 300 ltr
Panel Mounted with bracked
b. Nitrous Oxide
Cooper tube Type L Ø 3/4" 60 mtr 388,877 23,332,620
Cooper tube Type L Ø 5/8" 52 mtr 307,336 15,981,472
Cooper tube Type LØ 1/2" 42 mtr 232,066 9,746,772
Cooper tube Type LØ 3/8" 18 mtr 153,660 2,765,880
Fiting 1 lot 14,808,347 14,808,347
Material Bantu 1 lot 3,702,083 3,702,083
Wall Outlet Nitrous Oxide Quic Conect 4 unit 5,419,393 21,677,572
c. Compressor Air
Cooper tube Type L Ø 7/8" 54 mtr 479,840 25,911,360
Cooper tube Type L Ø 3/4" 46 mtr 388,877 17,888,342
Cooper tube Type L Ø 5/8" 48 mtr 307,336 14,752,128
Cooper tube Type L Ø 1/2" 42 mtr 232,066 9,746,772
Cooper tube Type L Ø 3/8" 30 mtr 153,660 4,609,800
Fiting 1 lot 21,226,858 21,226,858
Material Bantu 1 lot 5,306,714 5,306,714
Wall Outlet Compressor Air Quic Conect 12 unit 5,419,393 65,032,716
d. Vacuum
Cooper tube Type L Ø 1.1/8" 54 mtr 688,397 37,173,438
Cooper tube Type L Ø 7/8" 22 mtr 479,840 10,556,480
Cooper tube Type L Ø 3/4" 26 mtr 388,877 10,110,802
Cooper tube Type L Ø 5/8" 52 mtr 307,336 15,981,472
Cooper tube Type L Ø 1/2" 32 mtr 232,066 7,426,112
Cooper tube Type L Ø 3/8" 36 mtr 153,660 5,531,760
Fiting 1 lot 24,794,983 24,794,983
Material Bantu 1 lot 6,198,738 6,198,738
Wall Outlet Oxygen Quic Conect 12 unit 5,419,393 65,032,716
LANTAI I & II
a. Announciator 20 Way Master 3 unit 23,484,037 70,452,111
b. Nurse Presence 54 unit 865,597 46,742,238
c. Emergency Toilet 54 pcs 884,411 47,758,194
d. Lampu Indicator / Lampu Coridor ( Hijau & Merah ) 54 pcs 1,025,544 55,379,376
e. Pasien Call / Bead Call 85 pcs 865,597 73,575,745
f. Pende / Tombol Tempat Tidur 85 pcs 784,056 66,644,760
g. Flaher/ Pengerak lampu emergency 3 pcs 1,619,857 4,859,571
h. Cheme / Audio Suara 3 pcs 8,630,887 25,892,661
i. Ceiling Grill 3 unit 1,505,384 4,516,152
j. Power Suplay 24 Volt DC 10 A 3 pcs 11,039,496 33,118,488
k. Instalasi c/w pipa conduit Hi 20 mm2 320 ttk 1,254,490 401,436,800
l. Programing Jaringan 1 lot 20,385,456 20,385,456
m. Material Bantu 1 lot 41,129,338 41,129,338
n. Mobilisasi alat dan material 1 lot 33,602,400 33,602,400
o. Transportasi & Akomodasi 1 lot 17,473,248 17,473,248
TOTAL PEKERJAAN NURSE CALL 942,966,538