JADWAL PELAKSANAAN

PEMBANGUNAN GUDANG MODERN - DC


TANJUNG GUSTA, KOTA MEDAN - SUMATERA UTARA
ID WBS Task Name Duration Start Finish Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21 Sep '21 Oct '21 Nov '21
1 1 PEKERJAAN PELAKSANAAN 234 days Mon 01/03/21 Wed 20/10/21
PEMBANGUNAN GUDANG MODERN -
DC

2 1.1 SPMK 0 days Mon 01/03/21 Mon 01/03/21 01/03


3 1.2 Pengurusan IMB 90 days Mon 01/03/21 Sat 29/05/21

4 1.3 PEKERJAAN PERSIAPAN 87 days Mon 01/03/21 Wed 26/05/21

5 1.3.1 Pekerjaan Pengukuran 40 days Mon 01/03/21 Fri 09/04/21

6 1.3.2 Pekerjaan Direksi Keet& Gudang 40 days Mon 01/03/21 Fri 09/04/21

7 1.3.3 Air Kerja& Listrik Kerja 40 days Mon 08/03/21 Fri 16/04/21

8 1.3.4 Mobilisasi& demobilisasi Peralatan dan60 days Mon 01/03/21 Thu 29/04/21

9 1.3.5 Astek 40 days Mon 08/03/21 Fri 16/04/21

10 1.3.6 Keselamatan kerja K3& Rambu-rambu 40 days Mon 01/03/21 Fri 09/04/21

11 1.3.7 Papan Nama Proyek 14 days Mon 01/03/21 Sun 14/03/21

12 1.3.8 Bongkar Pagar depan 14 days Mon 01/03/21 Sun 14/03/21

13 1.3.9 Pembersihan Lahan 30 days Mon 08/03/21 Tue 06/04/21

14 1.3.10 Mengurug dengan tanah urug (t=0,5 m)60 days Thu 18/03/21 Sun 16/05/21

15 1.3.11 Memadatkan tanah (per 20 cm) 40 days Sat 17/04/21 Wed 26/05/21

16 1.4 PEKERJAAN ENGINEERING, 210 days Mon 01/03/21 Sun 26/09/21


PENGADAAN & FABRIKASI

17 1.4.1 Engineering 60 days Mon 01/03/21 Thu 29/04/21

18 1.4.2 Pengadaan 180 days Wed 31/03/21 Sun 26/09/21

19 1.4.3 Fabrikasi 45 days Fri 30/04/21 Sun 13/06/21

20 1.5 PEKERJAAN INFRASTRUKTUR 90 days Fri 30/04/21 Wed 28/07/21

21 1.5.1 JALAN BETON, DPT & SALURAN 90 days Fri 30/04/21 Wed 28/07/21

22 1.5.1.1 Pekerjaan Jalan Beton 90 days Fri 30/04/21 Wed 28/07/21

23 1.5.1.2 Pekerjaan Saluran 90 days Fri 30/04/21 Wed 28/07/21

24 1.5.1.3 Pekerjaan Dinding Penahan tanah 56 days Thu 03/06/21 Wed 28/07/21

25 1.5.2 PAGAR DAN GERBANG 40 days Fri 30/04/21 Tue 08/06/21

26 1.5.2.1 Pekerjaan Pondasi 40 days Fri 30/04/21 Tue 08/06/21

27 1.5.2.2 Pekerjaan Pagar 40 days Fri 30/04/21 Tue 08/06/21

28 1.5.2.3 Pekerjaan Gerbang 28 days Wed 12/05/21 Tue 08/06/21

29 1.6 BANGUNAN UTAMA & PENDUKUN G173 days Fri 30/04/21 Tue 19/10/21

30 1.6.1 GEDUNG PUSAT PENJUALAN 130 days Fri 30/04/21 Mon 06/09/21

31 1.6.1.1 Pekerjaan Struktur 60 days Fri 30/04/21 Mon 28/06/21

32 1.6.1.2 Pekerjaan Struktur Baja 60 days Sun 30/05/21 Wed 28/07/21

33 1.6.1.3 Pekerjaan Arsitektur 60 days Tue 29/06/21 Fri 27/08/21

34 1.6.1.4 Pekerjaan Mekanikal, Elektrikal, Pl 30 days Sun 08/08/21 Mon 06/09/21

35 1.6.2 GUDANG DC 54X30 130 days Wed 09/06/21 Sat 16/10/21

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Schedule Pelaksanaan r
Milestone Inactive Summary Start-only Critical
Date: Wed 24/02/21
Summary Manual Task Finish-only Critical
Split

Project Summary Duration-only External Tasks Pro gress


Page 1
JADWAL PELAKSANAAN
PEMBANGUNAN GUDANG MODERN - DC
TANJUNG GUSTA, KOTA MEDAN - SUMATERA UTARA
ID WBS Task Name Duration Start Finish Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21 Sep '21 Oct '21 Nov '21
36 1.6.2.1 Pekerjaan Struktur 60 days Wed 09/06/21 Sat 07/08/21

37 1.6.2.2 Pekerjaan Struktur Baja 60 days Fri 09/07/21 Mon 06/09/21

38 1.6.2.3 Pekerjaan Arsitektur 60 days Sun 08/08/21 Wed 06/10/21

39 1.6.2.4 Pekerjaan Mekanikal, Elektrikal, Pl 30 days Fri 17/09/21 Sat 16/10/21

40 1.6.3 COLD STORAGE 55 days Fri 09/07/21 Wed 01/09/21

41 1.6.3.1 Pekerjaan Struktur 30 days Fri 09/07/21 Sat 07/08/21

42 1.6.3.2 Pekerjaan Struktur Baja 30 days Sat 24/07/21 Sun 22/08/21

43 1.6.3.3 Pekerjaan Arsitektur 30 days Tue 03/08/21 Wed 01/09/21

44 1.6.4 MUSHOLA 55 days Sat 24/07/21 Thu 16/09/21

45 1.6.4.1 Pekerjaan Tanah 45 days Sat 24/07/21 Mon 06/09/21

46 1.6.4.2 Pekerjaan Struktur 45 days Sat 24/07/21 Mon 06/09/21

47 1.6.4.3 Pekerjaan Arsitektur 30 days Wed 18/08/21 Thu 16/09/21

48 1.6.4.4 Pekerjaan Instalasi Listrik, Plumbin 30 days Wed 18/08/21 Thu 16/09/21

49 1.6.5 TOILET UMUM 40 days Sun 08/08/21 Thu 16/09/21

50 1.6.5.1 Pekerjaan Tanah 30 days Sun 08/08/21 Mon 06/09/21

51 1.6.5.2 Pekerjaan Struktur 30 days Sun 08/08/21 Mon 06/09/21

52 1.6.5.3 Pekerjaan Arsitektur 30 days Wed 18/08/21 Thu 16/09/21

53 1.6.5.4 Pekerjaan Instalasi Listrik, Plumbin 30 days Wed 18/08/21 Thu 16/09/21

54 1.6.6 POWER HOUSE 45 days Sun 08/08/21 Tue 21/09/21

55 1.6.6.1 Pekerjaan Tanah 45 days Sun 08/08/21 Tue 21/09/21

56 1.6.6.2 Pekerjaan Struktur 45 days Sun 08/08/21 Tue 21/09/21

57 1.6.6.3 Pekerjaan Arsitektur 30 days Mon 23/08/21 Tue 21/09/21

58 1.6.6.4 Pekerjaan Instalasi Listrik, Plumbin 30 days Mon 23/08/21 Tue 21/09/21

59 1.6.7 GARDU PLN 45 days Mon 23/08/21 Wed 06/10/21

60 1.6.7.1 Pekerjaan Tanah 45 days Mon 23/08/21 Wed 06/10/21

61 1.6.7.2 Pekerjaan Struktur 45 days Mon 23/08/21 Wed 06/10/21

62 1.6.7.3 Pekerjaan Arsitektur 30 days Tue 07/09/21 Wed 06/10/21

63 1.6.7.4 Pekerjaan Instalasi Listrik, Plumbin 30 days Tue 07/09/21 Wed 06/10/21

64 1.6.8 POS KEAMANAN 38 days Tue 07/09/21 Thu 14/10/21

65 1.6.8.1 Pekerjaan Tanah 30 days Tue 07/09/21 Wed 06/10/21

66 1.6.8.2 Pekerjaan Struktur 30 days Tue 07/09/21 Wed 06/10/21

67 1.6.8.3 Pekerjaan Arsitektur 28 days Fri 17/09/21 Thu 14/10/21

68 1.6.8.4 Pekerjaan Instalasi Listrik, Plumbin 28 days Fri 17/09/21 Thu 14/10/21

69 1.6.9 MENARA AIR 30 days Wed 15/09/21 Thu 14/10/21

70 1.6.9.1 Pekerjaan Struktur Beton 30 days Wed 15/09/21 Thu 14/10/21

71 1.6.9.2 Pekerjaan Arsitektur 30 days Wed 15/09/21 Thu 14/10/21

72 1.6.9.3 Pekerjaan Instalasi Listrik, Plumbin 30 days Wed 15/09/21 Thu 14/10/21

73 1.6.10 GUDANG PERALATAN 35 days Wed 15/09/21 Tue 19/10/21

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Schedule Pelaksanaan r
Milestone Inactive Summary Start-only Critical
Date: Wed 24/02/21
Summary Manual Task Finish-only Critical
Split

Project Summary Duration-only External Tasks Pro gress


Page 2
JADWAL PELAKSANAAN
PEMBANGUNAN GUDANG MODERN - DC
TANJUNG GUSTA, KOTA MEDAN - SUMATERA UTARA
ID WBS Task Name Duration Start Finish Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21 Sep '21 Oct '21 Nov '21
74 1.6.10.1 Pekerjaan Tanah 30 days Wed 15/09/21 Thu 14/10/21

75 1.6.10.2 Pekerjaan Struktur 30 days Wed 15/09/21 Thu 14/10/21

76 1.6.10.3 Pekerjaan Arsitektur 30 days Mon 20/09/21 Tue 19/10/21

77 1.6.10.4 Pekerjaan Instalasi Listrik, Plumbin 30 days Mon 20/09/21 Tue 19/10/21

78 1.7 AC DAN FIRE ALARM 50 days Sat 28/08/21 Sat 16/10/21

79 1.8 WAREHOUSE EQUIPMENT 50 days Sat 28/08/21 Sat 16/10/21

80 1.9 INFRASTRUKTUR IT 50 days Sat 28/08/21 Sat 16/10/21

81 1.10 LANSEKAP 60 days Wed 18/08/21 Sat 16/10/21

82 1.11 FURNITURE 30 days Fri 17/09/21 Sat 16/10/21

83 1.12 SERAH TERIMA 1 day Wed 20/10/21 Wed 20/10/21

84 1.13 FINISH 0 days Wed 20/10/21 Wed 20/10/21 20/10

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Schedule Pelaksanaan r
Milesto ne Inactive Summary Start-o nly Critical
Date: Wed 24/02/21
Summary Manual Task Finish-only Critical
Split

Project Summary Duration-only External Tasks Progress