6 1.3.2 Pekerjaan Direksi Keet& Gudang 40 days Mon 01/03/21 Fri 09/04/21
7 1.3.3 Air Kerja& Listrik Kerja 40 days Mon 08/03/21 Fri 16/04/21
8 1.3.4 Mobilisasi& demobilisasi Peralatan dan60 days Mon 01/03/21 Thu 29/04/21
10 1.3.6 Keselamatan kerja K3& Rambu-rambu 40 days Mon 01/03/21 Fri 09/04/21
14 1.3.10 Mengurug dengan tanah urug (t=0,5 m)60 days Thu 18/03/21 Sun 16/05/21
15 1.3.11 Memadatkan tanah (per 20 cm) 40 days Sat 17/04/21 Wed 26/05/21
21 1.5.1 JALAN BETON, DPT & SALURAN 90 days Fri 30/04/21 Wed 28/07/21
24 1.5.1.3 Pekerjaan Dinding Penahan tanah 56 days Thu 03/06/21 Wed 28/07/21
29 1.6 BANGUNAN UTAMA & PENDUKUN G173 days Fri 30/04/21 Tue 19/10/21
30 1.6.1 GEDUNG PUSAT PENJUALAN 130 days Fri 30/04/21 Mon 06/09/21
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
48 1.6.4.4 Pekerjaan Instalasi Listrik, Plumbin 30 days Wed 18/08/21 Thu 16/09/21
53 1.6.5.4 Pekerjaan Instalasi Listrik, Plumbin 30 days Wed 18/08/21 Thu 16/09/21
58 1.6.6.4 Pekerjaan Instalasi Listrik, Plumbin 30 days Mon 23/08/21 Tue 21/09/21
63 1.6.7.4 Pekerjaan Instalasi Listrik, Plumbin 30 days Tue 07/09/21 Wed 06/10/21
68 1.6.8.4 Pekerjaan Instalasi Listrik, Plumbin 28 days Fri 17/09/21 Thu 14/10/21
72 1.6.9.3 Pekerjaan Instalasi Listrik, Plumbin 30 days Wed 15/09/21 Thu 14/10/21
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
77 1.6.10.4 Pekerjaan Instalasi Listrik, Plumbin 30 days Mon 20/09/21 Tue 19/10/21
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress