Anda di halaman 1dari 3

PROYEK PEMBANGUNAN KIRMIR HOTEL WIRTON BATUKARAS

Absensi Harian Mandor, Kepala Tukang, Tukang, dan Kernet Nomor: HWB/Kirmir/Abh/........../...../2011
Hari : Keterangan No. A. 1 B. 1 2 3 4 5 6 Umar Aksom Dede Bantarsari Dudu Ujang Mulyadi Unang
5 6 3 4 1 2

Uraian

C&R No. Uraian Hadir ( ) Tidak Hadir ( X ) Kepala Tukang / Karang Taruna Batukaras 2 Tukang 7 8 9 10 11 12 Total Tukang : Bihin Didi Suhro

Tanggal : Nopember 2011 Keterangan C&R Hadir ( ) Tidak Hadir ( X )

10

11

12

C. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Apip Asep Dede Patrol Dudu Pasuketan Halil Herlan Kuwir Misar Nana Bantarsari Nana Sanoy Nasrudin Rosidin Sodik Soleh Tete Usman Hendar Nanang
17 18 15 16 13 14 11 12 9 10 7 8 5 6 3 4 1 2

Kernet 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Total Kernet : Catatan :


35 36 33 34 31 32 29 30 27 28

Edi Engkos Kusmana Nana Nasrudin Pidin Sobirin

19

20

21

22

23

24

25

26

Diterima oleh,

Batukaras, ........ Nopember 2011 Dilaporkan oleh,

ERIK KRIDA SETIA Project Manager

________________________ Site Manager

PROYEK PEMBANGUNAN KIRMIR HOTEL WIRTON BATUKARAS


Rekapitulasi Absensi Mingguan Mandor, Kepala Tukang, Tukang, dan Kernet Nomor: HWB/Kirmir/Ram/........../...../2011
Minggu Ke : 1 (Satu) No. A. 1 2 Sub Total Ka. Tukang HOK B. 1 2 3 4 5 6 Umar Aksom Dede Bantarsari Dudu Ujang Mulyadi Unang HOK Kernet Apip Asep Dede Patrol Dudu Pasuketan Halil Herlan Kuwir Misar Nana Bantarsari Nana Sanoy Nasrudin Rosidin Sodik Soleh Tete Usman Hendar Nanang HOK HOK Catatan :
17 18 15 16 13 14 11 12 9 10 7 8 5 6 3 4 1 2 5 6 3 4 1 2 1

Tanggal : 1 s.d. 3 Nopember 2011 Total HOK Jumlah Upah Kerja (Rupiah) No. Uraian Total HOK Jumlah Upah Kerja (Rupiah)

Uraian

Kepala Tukang / Karang Taruna Batukaras


2

3 4 Upah Kerja Tukang 7 8 9 10 11 12 Upah Kerja Rp. Bihin Didi Suhro Rp.

10

11

12

Sub Total Tukang C. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

Edi Engkos Kusmana Nana Nasrudin Pidin Sobirin

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

Sub Total Kernet TOTAL

Upah Kerja Upah Kerja

Rp. Rp.

Diterima oleh,

Batukaras, ........ Nopember 2011 Dilaporkan oleh,

ERIK KRIDA SETIA Project Manager

________________________ Site Manager