PEKERJAAN TAMBAH BANGUNAN

TLOGOMAS REGENCY KAV. A-04

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN

A PEKERJAAN TAMBAH BANGUNAN


1 Luas bangunan 18.00 m2 1,800,000.00
2 Galian tanah pondasi 8.00 m3 33,804.38
3 Rabatan lantai kerja 0.32 m3 652,129.59
4 Footplat 90x90x20 (8 titik)
- Beton K225 1.30 m3 810,384.78
- Pembesian 136.08 kg 11,225.79
5 Kolom struktur 15/20 (8 titik)
- Beton K225 1.01 m3 810,384.78
- Bekisting 13.44 m2 202,552.65
- Pembesian 105.84 kg 11,225.79
6 Balok struktur 15/20
- Beton K225 0.84 m3 810,384.78
- Bekisting 15.40 m2 202,552.65
- Pembesian 88.20 kg 11,225.79
7 Plat cor
- Beton K225 2.18 m3 810,384.78
- Bekisting 18.13 m2 202,552.65
- Pembesian 228.38 kg 11,225.79
8 Dinding Bata diatas plat (t = 1 m)
- Pek. Bata merah 21.25 m2 78,892.88
- Pek. Kolom praktis 6.00 m' 57,314.22
- Pek. Plesteran 42.50 m2 33,057.00
- Pek. Cat 42.50 m2 20,721.20
9 Keramik Tangga 6.40 m2 127,411.50
10 Railing tangga 4.00 m2 546,067.65

Jumlah
PPn (10%)
Total
TOTAL HARGA
TAMBAH BANGUNAN
REGENCY KAV. A-04

TOTAL HARGA

32,400,000.00
270,435.00
211,289.99

1,050,258.67
1,527,605.50

816,867.85
2,722,307.62
1,188,137.61

680,723.21
3,119,310.81
990,114.68

1,762,586.89
3,671,266.78
2,563,689.79

1,676,473.59
343,885.29
1,404,922.50
880,650.79
815,433.60
2,184,270.59

60,280,230.76
6,028,023.08
66,308,253.84
66,308,000.00
PEKERJAAN TAMBAH BANGUNAN
TLOGOMAS REGENCY KAV. A-04

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN

A PEKERJAAN TAMBAH BANGUNAN


1 Luas bangunan 18.00 m2 1,800,000.00
2 Galian tanah pondasi 6.00 m3 33,804.38
3 Rabatan lantai kerja 0.24 m3 652,129.59
4 Footplat 90x90x20 (6 titik)
- Beton K225 0.97 m3 810,384.78
- Pembesian 102.06 kg 11,225.79
5 Sloof Struktur
- Beton K225 0.48 m3 810,384.78
- Bekisting 6.36 m2 202,552.65
- Pembesian 50.09 kg 11,225.79
6 Kolom struktur 15/20 (6 titik)
- Beton K225 0.76 m3 810,384.78
- Bekisting 13.44 m2 202,552.65
- Pembesian 79.38 kg 11,225.79
7 Balok struktur 15/20
- Beton K225 0.48 m3 810,384.78
- Bekisting 8.75 m2 202,552.65
- Pembesian 50.09 kg 11,225.79
8 Plat cor
- Beton K225 1.35 m3 810,384.78
- Bekisting 11.25 m2 202,552.65
- Pembesian 141.75 kg 11,225.79
9 Dinding Bata diatas plat (t = 1 m)
- Pek. Bata merah 13.10 m2 78,892.88
- Pek. Kolom praktis 7.00 m' 57,314.22
- Pek. Plesteran 26.20 m2 33,057.00
- Pek. Cat 26.20 m2 20,721.20
9 Pekerjaan talang datar 5.00 m' 195,312.93
10 Pekerjaan tangga putar 1.00 unit 5,100,000.00

TOTAL PEKERJAAN TAMBAH BANGUNAN


B PEKERJAAN PENGEMBALIAN
1 Pekerjaan Atap
- Rangka atap galvalum 11.25 m2 160,000.00
- Genteng beton 11.25 m2 90,635.40
2 Pekerjaan Struktur praktis
- Sloof Praktis 11.05 m' 77,446.98
- Kolom Praktis 16.00 m' 57,314.22
- Balok Praktis 11.05 m' 78,390.78

TOTAL PEKERJAAN KURANG BANGUNAN


Jumlah
PPn (10%)
Total
TOTAL HARGA
TAMBAH BANGUNAN
REGENCY KAV. A-04

TOTAL HARGA

32,400,000.00
202,826.25
158,467.49

787,694.00
1,145,704.13

386,553.54
1,288,234.85
562,243.69

612,650.89
2,722,307.62
891,103.21

386,553.54
1,771,322.92
562,243.69

1,094,019.45
2,278,717.31
1,591,255.73

1,033,496.66
401,199.51
866,093.40
542,895.31
976,564.65
5,100,000.00

57,762,147.85

1,800,000.00
1,019,648.25

855,789.13
917,027.45
866,218.12

5,458,682.95
52,303,464.90
5,230,346.49
57,533,811.39
57,533,000.00
PEKERJAAN TAMBAH BANGUNAN
TLOGOMAS REGENCY KAV. A-04

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN

A PEKERJAAN TAMBAH BANGUNAN


1 Luas bangunan 18.00 m2 1,800,000.00
2 Galian tanah pondasi 6.00 m3 33,804.38
3 Rabatan lantai kerja 0.24 m3 652,129.59
4 Footplat 90x90x20 (6 titik)
- Beton K225 0.97 m3 810,384.78
- Pembesian 102.06 kg 11,225.79
5 Sloof Struktur
- Beton K225 0.43 m3 810,384.78
- Bekisting 5.76 m2 202,552.65
- Pembesian 45.36 kg 11,225.79
5 Kolom struktur 15/20 (6 titik)
- Beton K225 0.76 m3 810,384.78
- Bekisting 13.44 m2 202,552.65
- Pembesian 79.38 kg 11,225.79
6 Balok struktur 15/20
- Beton K225 0.43 m3 810,384.78
- Bekisting 7.92 m2 202,552.65
- Pembesian 45.36 kg 11,225.79
7 Plat cor
- Beton K225 1.01 m3 810,384.78
- Bekisting 8.40 m2 202,552.65
- Pembesian 105.84 kg 11,225.79
8 Dinding Bata diatas plat (t = 1 m)
- Pek. Bata merah 11.65 m2 78,892.88
- Pek. Kolom praktis 4.00 m' 57,314.22
- Pek. Plesteran 23.30 m2 33,057.00
- Pek. Cat 23.30 m2 20,721.20
9 Pekerjaan talang datar 5.00 m' 195,312.93

TOTAL PEKERJAAN TAMBAH BANGUNAN


B PEKERJAAN PENGEMBALIAN
1 Pekerjaan Atap
- Rangka atap galvalum 8.40 m2 160,000.00
- Genteng beton 8.40 m2 90,635.40
2 Pekerjaan Struktur praktis
- Kolom Praktis 18.00 m' 57,314.22
- Balok Praktis 14.40 m' 78,390.78
TOTAL PEKERJAAN KURANG BANGUNAN
Jumlah
PPn (10%)
Total
TOTAL HARGA
TAMBAH BANGUNAN
REGENCY KAV. A-04

TOTAL HARGA

32,400,000.00
202,826.25
158,467.49

787,694.00
1,145,704.13

350,086.22
1,166,703.26
509,201.83

612,650.89
2,722,307.62
891,103.21

350,086.22
1,604,216.99
509,201.83

816,867.85
1,701,442.26
1,188,137.61

919,101.99
229,256.86
770,228.10
482,803.84
976,564.65

50,494,653.13

1,344,000.00
761,337.36

1,031,655.88
1,128,827.23
4,265,820.47
46,228,832.66
4,622,883.27
50,851,715.92
50,851,000.00
PEKERJAAN TAMBAH BANGUNAN
TLOGOMAS REGENCY KAV. D-10

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN

A PEKERJAAN TAMBAH BANGUNAN


1 Luas bangunan 2.00 m2 1,800,000.00
2 Dinding Pagar 3 m
- Pek. Bata merah 12.00 m2 78,892.88
- Pek. Kolom praktis 6.00 m' 57,314.22
- Pek. balok praktis 4.00 m' 78,390.78
- Pek. Plesteran 24.00 m2 33,057.00
- Pek. Cat 24.00 m2 20,721.20
2 Dinding Pagar 1.75 m
- Pek. Bata merah 16.10 m2 84,268.85
- Pek. Kolom praktis 7.00 m' 57,314.22
- Pek. balok praktis 9.20 m' 78,390.78
- Pek. Plesteran 32.20 m2 33,057.00
- Pek. Cat 32.20 m2 20,721.20

TOTAL PEKERJAAN TAMBAH


Jumlah
PPn (10%)
Total
TOTAL HARGA
TAMBAH BANGUNAN
REGENCY KAV. D-10

TOTAL HARGA

3,600,000.00

946,714.50
343,885.29
313,563.12
793,368.00
497,308.68

1,356,728.40
401,199.51
721,195.18
1,064,435.40
667,222.48

10,705,620.56
10,705,620.56
1,070,562.06
11,776,182.62
11,776,000.00
PEKERJAAN TAMBAH BANGUNAN
TLOGOMAS REGENCY KAV. B-08

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN

A PEKERJAAN TAMBAH BANGUNAN


1 Luas bangunan 3.00 m2 1,800,000.00
2 Penambahan atap bangunan
1. Pasangan bata gewel 9.07 m2 78,892.88
2. Kuda-kuda Galvalum 1.00 unit 700,000.00
3. Rangka usuk reng galvalum 12.03 m2 165,000.00
4. Genteng beton 12.03 m2 90,635.40
5. Bubungan beton 0.90 m' 72,957.85
3 Pembuatan pagar 3 m
1. Galian pondasi 4.04 m3 33,804.38
2. Pas. Pondasi batu kali 3.23 m3 499,215.00
3. Sloof praktis 11.55 m' 77,446.98
4. Pas. Bata 34.65 m2 78,892.88
5. Kolom Praktis 15.00 m' 57,314.22
6. Balok Praktis 13.05 m' 78,390.78
7. Plesteran 69.30 m2 33,057.00
9. Pengecatan 69.30 m2 20,721.20
4 Pas. Keramik Kamar mandi
1. Keramik lantai 20x20 2.25 m2 123,617.26
2. Keramik dinding 20x25 9.28 m2 159,403.50

TOTAL PEKERJAAN TAMBAH


Jumlah
PPn (10%)
Total
TOTAL HARGA
TAMBAH BANGUNAN
REGENCY KAV. B-08

TOTAL HARGA

5,400,000.00

715,716.16
700,000.00
1,984,950.00
1,090,343.86
65,662.07

136,654.19
1,614,461.31
894,512.62
2,733,638.12
859,713.23
1,022,999.68
2,290,850.10
1,435,978.81

278,138.84
1,478,467.46

22,702,086.45
22,702,086.45
2,270,208.64
24,972,295.09
24,972,000.00
PEKERJAAN TAMBAH BANGUNAN
TLOGOMAS REGENCY KAV. B-08

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN

A PEKERJAAN TAMBAH BANGUNAN


1 Penambahan atap bangunan
1. Pasangan bata gewel 3.37 m2 78,892.88
2. Kuda-kuda Galvalum 1.00 unit 700,000.00
3. Rangka usuk reng galvalum 12.03 m2 165,000.00
4. Genteng beton 12.03 m2 90,635.40
5. Bubungan beton 0.90 m' 72,957.85
2 Pembuatan pagar 3 m
1. Galian pondasi 3.50 m3 33,804.38
2. Pas. Pondasi batu kali 2.80 m3 499,215.00
3. Sloof praktis 10.00 m' 77,446.98
4. Pas. Bata 30.00 m2 78,892.88
5. Kolom Praktis 15.00 m' 57,314.22
6. Balok Praktis 13.05 m' 78,390.78
7. Plesteran 60.00 m2 33,057.00
9. Pengecatan 30.00 m2 20,721.20
10. Plesteran samping 26.20 m2 33,057.00
3 Pas. Keramik Kamar mandi
1. Keramik lantai 20x20 2.25 m2 123,617.26
2. Keramik dinding 20x25 9.28 m2 159,403.50

TOTAL PEKERJAAN TAMBAH


TAMBAH BANGUNAN
REGENCY KAV. B-08

TOTAL HARGA

266,026.77
700,000.00
1,984,950.00
1,090,343.86
65,662.07

118,315.31
1,397,802.00
774,469.80
2,366,786.25
859,713.23
1,022,999.68
1,983,420.00
621,635.85
866,093.40

278,138.84
1,478,467.46

15,874,824.52
PEKERJAAN TAMBAH BANGUNAN
TLOGOMAS REGENCY KAV. B-08

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN

A PEKERJAAN TAMBAH BANGUNAN


1 Tambah luas bangunan 19.50 m2 1,800,000.00
2 Bongkar tembok lama 1.00 ls 2,000,000.00
3 Talang datar 7.50 m' 195,312.93

TOTAL PEKERJAAN TAMBAH


TAMBAH BANGUNAN
REGENCY KAV. B-08

TOTAL HARGA

35,100,000.00
2,000,000.00
1,464,846.98

38,564,846.98
DAFTAR HARGA BAHAN BANGUNAN

KODE BAHAN BANGUNAN SATUAN HARGA

M001 Pasir Urug 1 m 77,395.50


M002 Pasir Pasang 1 m 90,000.00
M003 Pasir Hitam 1 m 124,641.00
M004 Pasir Cor 1 m 130,000.00
M005 Pasir Silika 1 Kg 9,733.50
M006 Tanah Urug 1 m 67,518.00
M007 Sirtu 1 m 109,053.00
M008 Tanah Urug Taman/Katel 1 m 69,003.00
M009 Tanah Liat 1 m 51,876.00
M010 Batu Belah Gunung 1 m 109,890.00
M011 Batu Belah Kali 1 m 127,809.00
M012 Batu Kali 1 m 100,000.00
M013 Stenslah/batu pecah tangan 1/2 1 m 205,722.00
M014 Stenslah/batu pecah tangan 2/3 1 m 215,000.00
M015 Stenslah/batu pecah tangan 3/5 1 m 159,984.00
M016 Stenslah/batu pecah tangan 4/6 - 5/7 1 m 142,956.00
M017 Batu pecah mesin 1/1 1 m 229,680.00
M018 Batu pecah mesin 1/2 1 m 189,387.00
M019 Batu pecah mesin 2/3 1 m 189,387.00
M020 Batu pecah mesin 3/5 1 m 180,279.00
M021 Batu pecah mesin 4/6 - 5/7 1 m 166,221.00
M022 Bata Merah 1 bh 570.00
M022.a Batu Bata Tahan Api 1 bh 12,969.00
M023 Bata Berongga 1 bh 990.00
M024 Batako 1 bh 5,148.00
M025 Rooster 1 bh 9,603.00
M026 Batu Granito 1 kg 3,366.00
M027 Batu Teraso 1 kg 2,574.00
M028 Batu Palimanan 1 m 79,096.50
M029 Batu Tempel Hitam 1 m 74,646.00
M030 Hollow Blok (HB.20) 1 bh 4,950.00
M031 Hollow Blok (HB.15) 1 bh 4,356.00
M032 Hollow Blok (HB.10) 1 bh 3,663.00
M033 Paving Block Segi Empat Biasa 1 bh 945.00
M034 Paving Block Segi Empat Warna 1 bh 1,125.00
M035 Paving Block Segi Enam Biasa 1 bh 1,845.00
M036.a Paving Block Segi Enam Warna 1 bh 1,935.00
M036.b Paving Block Tiga Berlian Biasa 1 bh 1,305.00
M036.c Paving Block Tiga Berlian Warna 1 bh 1,485.00
M037 Portland Cement (PC) 1 kg 1,350.00
M037.a Portland Cement (PC) Tahan Api 1 kg 4,257.00
M038 Portland Cement (PC) Putih 1 kg 2,673.00
M039 Portland Cement (PC) Warna 1 kg 8,118.00
M040 Portland Cement (PC) Grouting 1 kg 8,811.00
M041 Kapur 1 m 1,402,434.00
M042 Gamping 1 kg 990.00
M043 Semen Merah 1 m 186,921.00
M044 Buis Beton 0.20 m 1 m 36,949.50
M045 Buis Beton 0.30 m 1 m 47,322.00
M046 Buis Beton 0.40 m 1 m 62,653.50
M047 Buis Beton 0.50 m 1 m 78,151.50
M048 Buis Beton 0.60 m 1 m 104,643.00
M049 Buis Beton 0.80 m 1 m 190,323.00
M050 Buis Beton 0.90 m 1 m 207,427.50
M051 Buis Beton 1.00 m 1 m 265,450.50
M052 Buis Beton U 0.20 m 1 m 32,980.50
M053 Buis Beton U 0.30 m 1 m 41,481.00
M054 Reng : 2/3, 3/5 1 m 8,698,441.50
M055 Usuk : 5/7 1 m 8,625,865.50
M056 Balok 1 m 8,625,865.50
M057 Papan (2x20) cm 1 m 10,542,609.00
M058 Papan (3x20) cm 1 m 11,021,818.50
M059 Papan (3x30) cm 1 m 11,021,818.50
M060 Reng 2/3, 3/5 1 m 4,958,415.00
M061 Usuk 5/7 1 m 4,958,415.00
M062 Balok 1 m 5,559,435.00
M063 Papan (2x20) cm 1 m 6,611,220.00
M064 Papan (3x20) cm 1 m 6,661,305.00
M065 Papan (3x30) cm 1 m 6,939,900.00
M066 Reng 2/3, 3/5 1 m 5,960,115.00
M067 Usuk 5/7 1 m 5,960,115.00
M068 Balok 1 m 6,260,625.00
M069 Papan (2x20) cm 1 m 6,761,475.00
M070 Papan (3x20) cm 1 m 6,761,475.00
M071 Papan (3x30) cm 1 m 6,761,475.00
M078 Reng 2/3, 3/5 1 m 9,015,300.00
M079 Usuk 5/7 1 m 9,265,725.00
M080 Balok 1 m 9,516,150.00
M081 Papan (2x20) cm 1 m 11,018,700.00
M082 Papan (3x20) cm 1 m 11,269,125.00
M083 Papan (3x30) cm 1 m 11,519,550.00
M084 Balok Kayu Kelas III 1 m 3,305,610.00
M085 Papan Kayu kelas III 1 m 3,712,500.00
M088 Bambu 10 cm 1 btg 23,661.00
M089 Dolken Kayu 8 cm 1 btg 27,594.00
M090 List Kayu Profil 1 m 7,821.00
M091 List Kayu 2/4 1 m 3,636,171.00
M092 Gedeg (2.00 x 3.00) m 1 Ibr 39,402.00
M093 Bilik Bambu 1 m 78,804.00
M094 Reng : 2/3, 3/5 1 m 13,226,314.50
M095 Usuk : 5/7 1 m 13,226,314.50
M096 Balok 1 m 12,757,500.00
M097 Papan (2x20) cm 1 m 14,175,000.00
M098 Papan (3x20) cm 1 m 14,175,000.00
M099 Papan (3x30) cm 1 m 15,120,000.00
M100 Reng 2/3, 3/5 1 m 16,202,439.00
M101 Usuk 5/7 1 m 16,202,439.00
M102 Balok 1 m 16,202,439.00
M103 Papan (2x20) cm 1 m 15,622,267.50
M104 Papan (3x20) cm 1 m 15,622,267.50
M105 Papan (3x30) cm 1 m 15,622,267.50
M106 Reng : 2/3, 3/5 1 m 19,487,884.50
M107 Usuk : 5/7 1 m 19,487,884.50
M108 Balok 1 m 19,487,884.50
M109 Papan (2x20) cm 1 m 19,487,884.50
M110 Papan (3x20) cm 1 m 19,487,884.50
M111 Papan (3x30) cm 1 m 19,487,884.50
M112 Besi Beton Polos 1 kg 9,750.00
M113 Besi Beton Ulir 1 kg 14,157.00
M114 Besi Strip / Plat Plendes 1 kg 9,702.00
M115 Besi Beugel/Kawel 1 kg 9,702.00
M116 Baja Profil 1 kg 15,345.00
M116.a Plat Baja 1 kg 15,345.00
M116.b Roda Railling bh 15,300.00
M117 Angker Bar / Dynabolt 1 kg 17,127.00
M118 Kabel prestressed 1 kg 29,700.00
M119 Pintu Besi Baja 1 m 737,946.00
M120 Pintu Gulung Besi 1 m 2,029,203.00
M121 Pintu Lipat 1 m 1,600,924.50
M122 Rolling Door 1 m 1,185,880.50
M123 Pagar Besi 1 m 614,988.00
M124 Pintu Pagar besi 1 m 707,157.00
M124.a Pagar Model BRC tinggi 1 m 1 m 322,839.00
M124.b Pintu Pagar Model BRC tinggi 1 m 1 m 413,127.00
M125 Profil Aluminium Putih 1 m 81,000.00
M126 Profil Aluminium Coklat 1 m 107,019.00
M127 Sunscream Aluminium 1 m 307,395.00
M128 Pintu Fiber KM 1 Unit 330,561.00
M129 Atap Aluminium 1 m 100,683.00
M130 Bubung Atap Aluminium 1 m 98,941.50
M131 Aluminium Foil/Sesalation 1 m 30,901.50
M132 Baja Ringan 1 Kg 40,095.00
M133 Kawat Galvanis 2 mm 1 Kg 42,808.50
M134 Kawat Galvanis 3 mm 1 Kg 62,748.00
M135 Kawat Beton/Bendrat RRT 1 Kg 17,293.50
M136 Kawat Harmonika Gas 1 m 23,364.00
M137 Kawat Duri 1 Kg 21,285.00
M138 Kawat Nyamuk 1 m 18,513.00
M139 Kawat Nyamuk/Kasa Plastik 1 m 19,998.00
M140 Paku Kayu Segala Ukuran 1 Kg 21,780.00
M141 Paku Seng Segala Ukuran 1 Kg 25,443.00
M142 Paku Asbes Segala Ukuran 1 bh 594.00
M143 Paku Sumbat Segala Ukuran 1 bh 891.00
M144 Paku Kait Segala Ukuran 1 bh 693.00
M145 Sekrup segala ukuran 1 bh 396.00
M146 Baut Segala Ukuran 1 kg 19,206.00
M147 Paku Keling 1 bh 3,168.00
M148 Paku Beton 1 kg 37,138.50
M148.a Wire Mesh 1 kg 16,537.50
M148.b Sealant 1 tube 28,444.50
M148.c Aluminium Strip 1 m 17,127.00
M148.d Profil Kaca 1 m 11,088.00
M148.e Venetion blinds dan vertical blinds (tirai) 1 m 532,507.50
M148.f Atap Seng Galvalum 1 m 106,123.50
M148.g Bubung Atap Seng Galvalum 1 m 103,194.00
M149 Genteng Biasa ex. Malang 1 bh 1,440.00
M150 Genteng Press ex. Trenggalek 1 bh 1,575.00
M151 Genteng Karang Pilang ex. Malang 1 bh 2,250.00
M152 Genteng Karang Pilang ex. Trenggalek 1 bh 2,475.00
M153 Genteng Karang Pilang ex. Surabaya 1 bh 2,079.00
M154 Genteng Beton biasa 1 bh 3,000.00
M155 Genteng Kaca 1 bh 13,761.00
M156 Bubung Genteng Biasa ex. Malang 1 bh 1,890.00
M157 Bubung Genteng Press ex. Trenggalek 1 bh 2,475.00
M158 Bubung Genteng Karang Pilang ex. Malang 1 bh 4,554.00
M159 Bubung Genteng Karang Pilang ex. Trenggalek 1 bh 4,950.00
M160 Bubung Genteng Karang Pilang ex. Surabaya 1 bh 5,544.00
M161 Bubung Genteng Beton biasa 1 bh 5,000.00
M162 Genteng Palentong Kecil 1 bh 2,268.00
M163 Genteng Kodok Glazuur 1 bh 2,277.00
M164 Genteng Palentong Super/Besar 1 bh 4,356.00
M165 Bubung Genteng Palentong Kecil 1 bh 3,960.00
M166 Bubung Genteng Kodok Glazuur 1 bh 7,128.00
M167 Bubung Genteng Palentong Super/Besar 1 bh 7,623.00
M168 Genteng Aspal 1 Ibr 6,534.00
M169 Genteng Metal 1 lbr 98,604.00
M170 Atap Sirap 1 bh 1,485.00
M171 Bubung Genteng Aspal 1 bh 44,154.00
M172 Bubung Genteng Metal 1 bh 98,604.00
M173 Bubung Atap Sirap 1 bh 119,394.00
M173.a Plastik Aerator 1 bh 6,732.00
M174 Seng plat BJLS 30 L = 0.45 M 1 m 32,220.00
M175 Seng plat BJLS 30 L = 0.60 M 1 m 36,720.00
M176 Seng plat BJLS 30 L = 0.90 M 1 m 46,080.00
M177 Seng plat BJLS 28 (90 x 180) cm 1 lbr 62,640.00
M178 Atap Seng Gelombang 1 Ibr 81,553.50
M179 Bubung Seng Gelombang 1 lbr 81,553.50
M180 Roof Light Fibreglass 1 m 76,626.00
M181 Atap Polycarbonat 1 m 111,870.00
M182 Asbes Gelombang (3.00 x 1.05) m x 4 mm 1 lbr 101,776.50
M183 Asbes Gelombang (2.70 x 1.05) m x 4 mm 1 lbr 94,027.50
M184 Asbes Gelombang (2.40 x 1.05) m x 4 mm 1 lbr 81,364.50
M185 Asbes Gelombang (2.10 x 1.05) m x 4 mm 1 lbr 72,103.50
M186 Asbes Gelombang (1.50 x 1.05) m x 4 mm 1 lbr 56,727.00
M187 Asbes Gelombang (2.50 x 0.92) m x 5 mm 1 lbr 103,383.00
M188 Asbes Gelombang (2.25 x 0.92) m x 5 mm 1 lbr 89,491.50
M189 Asbes Gelombang (2.00 x 0.92) m x 5 mm 1 lbr 79,285.50
M190 Asbes Gelombang (1.80 x 0.92) m x 5 mm 1 lbr 62,469.00
M191 Asbes Gelombang (3.00 x 1.08) m x 6 mm 1 lbr 127,480.50
M192 Asbes Gelombang (2.70 x 1.08) m x 6 mm 1 lbr 122,188.50
M193 Asbes Gelombang (2.10 x 1.08) m x 6 mm 1 lbr 90,342.00
M194 Asbes Gelombang (1.80 x 1.08) m x 6 mm 1 lbr 85,050.00
M195 Bubung Stel Gelombang 0.92 m 1 Ibr 46,966.50
M196 Bubung Stel Gelombang 1.05 m 1 lbr 49,698.00
M197 Bubung Stel Gelombang 1.08 m 1 lbr 50,368.50
M198 Bubung Paten 0.92 m 1 lbr 41,958.00
M199 Bubung Paten 1.05 m 1 lbr 41,580.00
M200 Bubung Paten 1.08 m 1 lbr 44,793.00
M201 Bubung Stel Rata 0.92 m 1 Ibr 50,368.50
M202 Bubung Stel Rata 1.05 m 1 lbr 39,699.00
M203 Asbes (1,00 x 1,00) m x 6 mm 1 lbr 18,315.00
M204 Asbes (1,00 x 1,00) m x 5 mm 1 Ibr 17,226.00
M205 Asbes (1,00 x 1,00) m x 4 mm 1 lbr 16,632.00
M206 Asbes (1,00 x 1,00) m x 3,5 mm 1 Ibr 16,038.00
M207 Akustik (30 x 30) cm 1 Ibr 25,110.00
M208 Akustik (30 x 60) cm 1 Ibr 27,630.00
M209 Akustik (60 x 120) cm 1 lbr 33,390.00
M210 Harplek 4 mm 1 m 52,965.00
M211 List Gypsum 1 m' 19,899.00
M212 Soft Board 1 Ibr 70,587.00
M213 Gypsum Board 9 mm 1 Ibr 75,339.00
M214 Triplek 3 mm 1 lbr 51,124.50
M215 Triplek 4 mm 1 lbr 70,380.00
M216 Multiplek 6 mm 1 lbr 81,742.50
M217 Multiplek 9 mm 1 lbr 124,929.00
M218 Multiplek 10 mm 1 lbr 142,033.50
M219 Multiplek 12 mm 1 lbr 176,053.50
M220 Multiplek 18 mm 1 lbr 244,188.00
M221 Plywood Lapis Aluminium 1 lbr 82,687.50
M222 Plywood (30 x 60) cm x 4 mm 1 lbr 7,128.00
M223 Plywood (30 x 60) cm x 6 mm 1 Ibr 9,900.00
M224 Plywood (60 x 120) cm x 4 mm 1 Ibr 23,265.00
M225 Plywood (60 x 120) cm x 6 mm 1 lbr 27,621.00
M226 Plywood (120 x 240) cm x 4 mm 1 Ibr 93,951.00
M227 Teakwood (30 x 60) cm x 4 mm 1 lbr 7,623.00
M228 Teakwood (60 x 120) cm x 4 mm 1 lbr 27,126.00
M229 Teakwood (120 x 240) cm x 4 mm 1 Ibr 91,377.00
M230 Kloset Jongkok Porselin Kw. A 1 Unit 151,011.00
M231 Kloset Duduk Porselin Kw. A 1 Unit 1,508,598.00
M232 Kloset Jongkok Lux 1 Unit 313,038.00
M233 Kloset Duduk Lux 1 Unit 1,603,948.50
M234 Kloset Jongkok Teraso 1 bh 62,667.00
M235 Kran Air 1/2 " 1 bh 39,303.00
M236 Kran Air 3/4 " 1 bh 43,956.00
M237 Bak Mandi Teraso 1 bh 141,750.00
M238 Bak Mandi Fibre 1 bh 331,978.50
M239 Bak Mandi Plastik 1 bh 209,034.00
M240 Bak Mandi Porselin 1 bh 2,112,169.50
M241 Kran Bathub Panas dan dingin 1 bh 427,896.00
M242 Bak Cuci Firing Teraso 1 bh 219,186.00
M243 Bak Cuci Firing Stainless 1 bh 301,077.00
M244 Badkip Porselen 1 bh 938,916.00
M245 Urinoir Porselin 1 bh 1,056,132.00
M246 Urinoir Keramik 1 bh 1,086,277.50
M247 Wastafel Komplit (Kran + Sipon) Lux 1 Unit 1,327,630.50
M248 Wastafel Komplit (Kran + Sipon) Kw. A 1 Unit 438,669.00
M249 Tempat Sabun Keramik 1 bh 31,383.00
M250 Afor Stainless 1 bh 53,262.00
M251 Afor Plastic 1 bh 15,741.00
M252 Kaca Wastafel 1 bh 62,667.00
M253 Kunci Tanam Antik 1 bh 93,366.00
M254 Kunci Tanam 1 bh 110,943.00
M255 Kunci Pintu Kamar Mandi 1 bh 91,080.00
M256 Kunci Silinder 1 bh 146,286.00
M257 Engsel Pintu 1 set 31,482.00
M258 Engsel Jendela 1 set 24,192.00
M259 Hak Angin 1 set 19,404.00
M260 Spring Knip 1 bh 12,573.00
M261 Kait Angin 1 bh 9,450.00
M262 Grendel Pintu 1 bh 21,546.00
M263 Grendel Jendela 1 bh 12,177.00
M264 Door Closer 1 bh 170,761.50
M265 Slot/Kunci Pintu 1 bh 134,190.00
M266 Door Holder 1 bh 126,621.00
M267 Door Stop 1 bh 36,193.50
M268 Rel Pintu Dorong 1 bh 131,638.50
M269 Kunci Lemari 1 bh 11,812.50
M270 Kaca Polos tebal 3 mm 1 m 79,191.00
M271 Kaca Polos tebal 5 mm 1 m 120,204.00
M272 Kaca Polos tebal 8 mm 1 m 232,470.00
M273 Kaca Polos tebal 12 mm 1 m 334,521.00
M274 Kaca Buram tebal 3 mm 1 m 117,274.50
M275 Kaca Buram tebal 5 mm 1 m 175,864.50
M276 Kaca Buram tebal 8 mm 1 m 198,450.00
M277 Kaca Buram tebal 12 mm 1 m 320,544.00
M278 Kaca Cermin tebal 5 mm 1 m 136,719.00
M279 Kaca Cermin tebal 6 mm 1 m 250,668.00
M280 Kaca Cermin tebal 8 mm 1 m 341,649.00
M281 Kaca Rayben tebal 3 mm 1 m 118,314.00
M282 Kaca Rayben tebal 5 mm 1 m 173,502.00
M283 Kaca Rayben tebal 8 mm 1 m 355,225.50
M284 Kaca Rayben tebal 12 mm 1 m 567,283.50
M285 Jendela Nako + accessories 1 m 231,808.50
M286 Glass Block 1 bh 22,585.50
M287 Painting Glass 1 m 527,971.50
M288 Kaca "Wireglass" 5 mm 1 m 592,515.00
M289 Kaca Patri 5 mm 1 m 1,292,193.00
M290 Ubin pc abu-abu 40 x 40 cm 1 bh 2,277.00
M291 Ubin pc abu-abu 30 x 30 cm 1 bh 1,782.00
M292 Ubin pc abu-abu 20 x 20 cm 1 bh 1,089.00
M293 Ubin pc warna 40 x 40 cm 1 bh 2,871.00
M294 Ubin pc warna 30 x 30 cm 1 bh 1,881.00
M295 Ubin pc warna 20 x 20 cm 1 bh 1,287.00
M296 Ubin Terasso 40 x 40 cm 1 bh 4,059.00
M297 Ubin Terasso 30 x 30 cm 1 bh 2,871.00
M298 Ubin Granito 40 x 40 cm 1 bh 36,234.00
M299 Ubin Granito 30 x 30 cm 1 bh 19,404.00
M299a Ubin Teralux Kerang 40 x 40 cm 1 bh 40,446.00
M299b Ubin Teralux Kerang 30 x 30 cm 1 bh 34,587.00
M299c Ubin Teralux Kerang 60 x 60 cm 1 bh 69,363.00
M299d Ubin Teralux Marmer 40 x 40 cm 1 bh 51,975.00
M300 Plint ubin pc abu-abu 15 x 20 cm 1 bh 2,871.00
M301 Plint ubin pc abu-abu 10 x 30 cm 1 bh 3,069.00
M302 Plint ubin pc abu-abu 10 x 40 cm 1 bh 3,366.00
M303 Plint ubin pc warna 10 x 20 cm 1 bh 1,782.00
M304 Plint ubin pc warna 10 x 30 cm 1 bh 2,268.00
M305 Plint ubin pc warna 10 x 40 cm 1 bh 3,366.00
M306 Plint Ubin Terasso 10 x 30 cm 1 bh 4,059.00
M307 Plint Ubin Terasso 10 x 40 cm 1 bh 5,742.00
M308 Plint Ubin Granito 10 x 40 cm 1 bh 12,474.00
M309 Plint Ubin Granito 10 x 30 cm 1 bh 8,514.00
M310 Lantai keramik artistik 10 x 20 1 bh 8,514.00
M311 Lantai keramik artistik 10 x 10 1 bh 8,514.00
M312 Lantai keramik artistik 5 x 20 1 bh 8,514.00
M313 Plint keramik artistik 10 x 20 1 bh 15,480.00
M314 Plint keramik artistik 10 x 10 1 bh 15,480.00
M315 Plint keramik artistik 5 x 20 1 bh 15,480.00
M316 Internal cove 5 x 5 x 20 cm 1 bh 21,924.00
M316.a Bahan Teraso Cor 1 m 178,398.00
M317 Keramik Lantai 40 x 40 cm putih 1 bh 11,340.00
M318 Keramik Lantai 40 x 40 cm warna/motif 1 bh 13,590.00
M319 Keramik Lantai 30 x 30 cm putih 1 bh 4,100.00
M320 Keramik Lantai 30 x 30 cm warna/motif 1 bh 4,500.00
M321 Keramik Lantai 20 x 20 cm putih 1 bh 1,840.00
M322 Keramik Lantai 20 x 20 cm warna/motif 1 bh 1,840.00
M323 Keramik Lantai KM 20 x 20 cm 1 bh 1,980.00
M324 Plint Keramik Lantai 10 x 20 cm 1 bh 4,554.00
M325 Plint Keramik Lantai 10 x 30 cm 1 bh 8,514.00
M326 Plint Keramik Lantai 10 x 40 cm 1 bh 15,939.00
M327 Keramik Dinding 20 x 25 cm 1 bh 3,690.00
M328 Keramik Dinding 20 x 20 cm 1 bh 2,610.00
M329 Porselin 15 x 15 cm putih 1 bh 891.00
M330 Porselin 15 x 15 cm warna 1 bh 945.00
M331 Porselin 10 x 20 cm warna 1 bh 945.00
M332 Porselin 20 x 20 cm warna 1 bh 1,984.50
M333 Gymflour 1 m 226,413.00
M333.a Parquet 1 m 213,097.50
M333.b Karpet 1 m 55,242.00
M333.c Lantai marmer 100x100 cm 1 m 386,595.00
M333.d Porselin 11 x 11 cm putih 1 m 792.00
M333.e Porselin 11 x 11 cm warna 1 m 990.00
M333.f Wall Paper 1 m 53,460.00
M333.g Batu Ampyangan Granit 1 kg 6,331.50
M334 Pipa PVC tipe AW 1/2" 1 m 7,560.00
M335 Pipa PVC tipe AW 3/4" 1 m 11,245.50
M336 Pipa PVC tipe AW 1" 1 m 14,742.00
M337 Pipa PVC tipe AW 1.5" 1 m 19,845.00
M338 Pipa PVC tipe AW 2" 1 m 25,231.50
M339 Pipa PVC tipe AW 2.5" 1 m 32,413.50
M340 Pipa PVC tipe AW 3 " 1 m 45,738.00
M341 Pipa PVC tipe AW 4 " 1 m 71,536.50
M342 Pipa PVC tipe AW 6 " 1 m 124,551.00
M343 Pipa PVC tipe AW 8 " 1 m 190,417.50
M344 Pipa PVC tipe D 1/2 " 1 m 3,780.00
M345 Pipa PVC tipe D 3/4 " 1 m 5,670.00
M346 Pipa PVC tipe D 1" 1 m 7,371.00
M347 Pipa PVC tipe D 1.5 " 1 m 9,922.50
M348 Pipa PVC tipe D 2 " 1 m 12,096.00
M349 Pipa PVC tipe D 2.5 " 1 m 17,671.50
M350 Pipa PVC tipe D 3 " 1 m 25,704.00
M351 Pipa PVC tipe D 4 " 1 m 36,099.00
M352 Pipa PVC tipe C 1/2 " 1 m 2,835.00
M353 Pipa PVC tipe C 3/4 " 1 m 4,252.50
M354 Pipa PVC tipe C 1" 1 m 5,575.50
M355 Pipa PVC tipe C 1.5 " 1 m 7,465.50
M356 Pipa PVC tipe C 2 " 1 m 10,017.00
M357 Pipa PVC tipe C 2.5 " 1 m 12,757.50
M358 Pipa PVC tipe C 3 " 1 m 15,120.00
M359 Pipa PVC tipe C 4 " 1 m 19,183.50
M360 Shock PVC 1/2 " 1 bh 1,485.00
M361 Shock PVC 3/4 " 1 bh 2,277.00
M362 Shock PVC 1 " 1 bh 2,673.00
M363 Shock PVC 1.5 " 1 bh 5,742.00
M364 Shock PVC 2 " 1 bh 7,654.50
M365 Shock PVC 2.5 " 1 bh 10,962.00
M366 Shock PVC 3 " 1 bh 12,379.50
M367 Shock PVC 4 " 1 bh 15,025.50
M368 Knee PVC 1/2 " 1 bh 2,079.00
M369 Knee PVC 3/4 " 1 bh 2,574.00
M370 Knee PVC 1 " 1 bh 3,762.00
M371 Knee PVC 1.5 " 1 bh 7,425.00
M372 Knee PVC 2 " 1 bh 10,773.00
M373 Knee PVC 2.5 " 1 bh 12,379.50
M374 Knee PVC 3 " 1 bh 13,797.00
M375 Knee PVC 4 " 1 bh 17,293.50
M376 Pipa Galvanis 1/2" tebal 1.8 mm 1 m 33,547.50
M377 Pipa Galvanis 3/4" tebal 1.8 mm 1 m 43,470.00
M378 Pipa Galvanis 1 ", tebal 2 mm 1 m 59,251.50
M379 Pipa Galvanis 1.5 ", tebal 2 mm 1 m 86,940.00
M380 Pipa Galvanis 2 ", tebal 2.3 mm 1 m 124,551.00
M381 Pipa Galvanis 2.5 ", tebal 2.5 mm 1 m 173,974.50
M382 Pipa Galvanis 3" tebal 2.5 mm 1 m 195,822.00
M383 Pipa Galvanis 4" tebal 2.8 mm 1 m 290,587.50
M384 Shock Galvanis 1/2 " 1 bh 3,960.00
M385 Shock Galvanis 3/4 " 1 bh 5,148.00
M386 Shock Galvanis 1 " 1 bh 7,524.00
M387 Shock Galvanis 1.5 " 1 bh 13,266.00
M388 Shock Galvanis 2 " 1 bh 21,087.00
M389 Shock Galvanis 2.5 " 1 bh 36,099.00
M390 Shock Galvanis 3 " 1 bh 54,148.50
M391 Shock Galvanis 4 " 1 bh 74,844.00
M392 Knee Galvanis 1/2 " 1 bh 4,554.00
M393 Knee Galvanis 3/4 " 1 bh 6,237.00
M394 Knee Galvanis 1 " 1 bh 8,811.00
M395 Knee Galvanis 1.5 " 1 bh 17,523.00
M396 Knee Galvanis 2 " 1 bh 27,423.00
M397 Knee Galvanis 2.5 " 1 bh 50,557.50
M398 Knee Galvanis 3 " 1 bh 78,151.50
M399 Knee Galvanis 4 " 1 bh 99,693.00
M400 Pipa Screen PVC tipe AW 6 " 1 m 144,990.00
M400.a Pipa PVC tipe AW 5 " 1 m 93,600.00
M400.b Pipa Screen PVC tipe AW 5 " 1 m 119,520.00
M400.c Pipa PVC moof 6 m S - 12,5 2" 1 m 27,180.00
M400.d Pipa PVC moof 6 m S - 12,5 2,5" 1 m 37,890.00
M400.e Pipa PVC moof 6 m S - 12,5 3" 1 m 56,520.00
M400.f Pipa PVC moof 6 m S - 12,5 4" 1 m 82,980.00
M400.g Pipa PVC moof 6 m S - 12,5 6" 1 m 179,280.00
M400.h Pipa PVC moof 6 m S - 12,5 8" 1 m 290,430.00
M401 Kertas Gosok 1 Lbr 4,455.00
M402 Plamir Kayu 1 kg 20,592.00
M403 Plamir Tembok 1 kg 12,771.00
M404 Plamir Besi 1 Kg 35,739.00
M405 Dempul Jadi 1 kg 31,284.00
M406 Minyak Cat 1 Ltr 19,008.00
M407 Spiritus 1 Ltr 14,175.00
M408 Sirlak 1 kg 157,212.00
M409 Cat meni kayu 1 kg 34,114.50
M410 Cat meni besi 1 kg 35,343.00
M411 Cat Dasar Kayu 1 kg 33,858.00
M412 Cat Dasar Tembok 1 kg 25,740.00
M413 Cat Dasar Besi 1 kg 39,897.00
M414 Cat Kayu 1 kg 70,290.00
M415 Cat Tembok 1 kg 47,025.00
M415.a Cat Tembok Interior 1 kg 84,645.00
M415.b Cat Tembok Eksterior 1 kg 97,119.00
M416 Cat Besi 1 kg 71,631.00
M417 Cat Genting 1 kg 125,212.50
M418 Waterproofing 1 kg 146,097.00
M419 Vernis 1 Ltr 33,858.00
M420 Politur Jadi 1 Ltr 73,237.50
M421 Kuas 1 bh 12,969.00
M422 Lem Kayu 1 kg 29,502.00
M423 Lem Pipa PVC 1 kg 33,858.00
M424 Lem vinyl 1 kg 56,983.50
M425 Residu atau Teer 1 Ltr 26,829.00
M426 Teak oli 1 Ltr 2,277.00
M427 Kalkarium 1 kg 8,514.00
M428 Kapur Sirih 1 kg 4,653.00
M429 Soda api 1 kg 22,585.50
M430 Sabun 1 kg 39,879.00
M430.a Vinyl (30x30)cm 1 bh 21,420.00
M430.b Batu Apung 1 kg 38,016.00
M430.c Alang-Alang 1 ikat 4,158.00
M431 Tandon Air PVC V = 0.5 m3 1 bh 688,905.00
M432 Tandon Air PVC V = 1.0 m3 1 bh 1,218,955.50
M433 Tandon Air Stainless V = 0.5 m3 1 bh 1,905,214.50
M434 Tandon Air Stainless V = 1.0 m3 1 bh 3,190,414.50
M435 Sumur Pompa Tangan Lengkap 1 Unit 187,299.00
M436 Pompa Air 1 Unit 751,275.00
M437 Kabel NYA 2.5 mm 1 m 4,356.00
M438 Kabel NYA 4.0 mm 1 m 7,425.00
M438a Kabel NYYHY 3x4 mm 1 m 12,969.00
M438b Kabel NYYHY 3x1.5 mm 1 m 7,821.00
M439 Stop Kontak 1 bh 26,271.00
M440 Saklar Broco Tunggal 1 bh 32,035.50
M440.a Saklar Broco Ganda 1 bh 36,666.00
M441 Las doof 1 bh 594.00
M442 Isolator 1 m 792.00
M443 T dos PVC 1 bh 990.00
M444 Pipa PVC 5/8" 1 Ljr 7,087.50
M445 Fiting Flafond 1 bh 10,296.00
M446 Zekering Kast Lokal 1 Group 1 Unit 63,976.50
M447 Zekering Kast Lokal 2 Group 1 Unit 92,988.00
M448 Zekering Kast Lokal 3 Group 1 Unit 127,764.00
M449 Lampu TL Komplit 20 Watt 1 bh 61,141.50
M450 Lampu TL Komplit 40 Watt 1 bh 93,753.00
M451 Lampu XL (Lilin) 5 Watt 1 bh 27,027.00
M452 Lampu XL (Lilin) 8 Watt 1 bh 30,051.00
M453 Lampu XL (Lilin) 14 Watt 1 bh 33,925.50
M454 Lampu XL (Lilin) 18 Watt 1 bh 36,477.00
M455 Lampu XL (Lilin) 23 Watt 1 bh 42,525.00
M456 Lampu Pijar 5 - 40 Watt 1 bh 17,577.00
M457 Lampu Pijar 50 -100 Watt 1 bh 29,200.50
M458 Tambah Daya 2200 Watt 1 Ls 3,505,950.00
M459 Pasang Baru PLN 1 Ls 5,008,500.00
M460 Pipa Arde 1 m 108,306.00
M460.a Splits Dia 1 1 bh 72,859.50
M460.b Timah 1 kg 412,209.00
M460.c Kawat BC 1 m 42,808.50
M460.d Klemp 1 bh 2,079.00
M461 Rumput Lamur 1 m 20,880.00
M462 Rumput Manila 1 m 17,820.00
M463 Semak Hias 1 m 12,001.50
M464 Pohon Pelindung 1 btg 182,668.50
M464.a Gebalan rumput 1 m 14,940.00
M465 Tali ijuk 1 kg 17,820.00
M466 ljuk 1 m 144,630.00
M467 Waterstop Lebar 150 mm 1 m 40,446.00
M468 Waterstop Lebar 200 mm 1 m 72,859.50
M469 Waterstop Lebar 230 mm 1 m 84,861.00
M470 Rumput Common Bermuda Grass 1 m 13,167.00
M471 Pupuk 1 kg 2,430.00
M471a Obat Tanaman 1 ltr 85,286.70
M472 Tali Plastik 0.8 cm 1 m 2,250.00
M473 Elektroda 1 kg 35,046.00
M474 Minyak bekisting 1 ltr 2,574.00
M475 Formika (90 x 120) cm 1 lbr 156,321.00
M476 Strorox 100 1 kg 102,762.00
M477 Formtie 1 bh 8,712.00
M478 Batacote 1 kg 7,821.00
M479 Rapidrant 1 Gln 39,402.00
M480 Puzzdith - 100 XR 1 Ltr 79,002.00
M481 Seal Tape / TBA 1 bh 2,079.00
M482 Bensin Industri 1 ltr 4,950.00
M482.a Bensin Umum 1 Itr 4,819.50
M483 Solar Industri 1 Itr 5,400.00
M483.a Solar Umum 1 Itr 4,356.00
M484 Minyak Pelumas 1 Itr 45,738.00
M485 Grease 1 kg 26,037.00
M486 Air Bersih 1 Itr 27.00
M487 Kuas 4" 1 bh 12,969.00
M488 Lampu Mercury 1 bh 214,560.00
M489 Jaring PEDT Mesh 2,5 cm 1 bh 28,440.00
M490 Rumput Sintetis (30x30)cm 1 bh 14,220.00
M491 Kalsiboard 4.5 mm 1 lbr 108,000.00
M492 Kalsiboard 9 mm 1 lbr 143,923.50
M493 Eternit 100x100 tbl 3,5 mm 1 lbr 16,537.50
M494 Metal furing 1 m' 13,050.00
M495 Kawat seng polos 1 Kg 21,375.00
M496 Ramset / Dynabolt 1 Bh 4,500.00
M497 Lapis aluminum jeruk 1 m2 27,000.00
M498 Pipa stainless steel 2" 1 m' 112,500.00
M499 Stud Track 7,6 1 m' 22,500.00
M500 Gypsum Board 12 mm 1 lbr 76,500.00
M501 Usuk Canal C 75. 0.75 1 m1 13,500.00
M502 Reng Purlin R 36.055 1 m1 9,000.00
M503 Baut 1 bh 90.00
M504 Batu sisir 1 m 71,910.00
M505 Coating batu alam 1 kg 40,500.00
M505 Engsel casement 15 " bh 29,250.00
M506 Tempered kaca m2 450,000.00

Malang, 28 Januari 2013


Kepala Dinas Pendidikan
Kota Malang

Dra. Sri Wahyuningtyas, M.Si.


Pembina Utama Muda
NIP. 19581218 198503 2 007
AN

KETERANGAN
HSPK 2013
Tanah dan Pasir
85,000.00
###
125,000.00
###
###
###
###
###
Batu,Bata & Beton Block
###
95,000.00
###
205,000.00
###
###
###
###
###
###
###
560.00
###
###
###
###
###
###
###
###
###
###
###
Per Meter isi 45
Per Meter isi 45
Per Meter isi 28
Per Meter isi 28
Per Meter isi 33
Per Meter isi 33
Semen 1325
###
###
###
###
###
###
###
Buis Beton
###
###
###
###
###
###
###
###
###
Kayu Borneo
###
###
###
###
###
Kayu Meranti
###
###
###
###
###
Kayu Kruing
###
###
###
###
###
Kayu Kamper
###
###
###
###
###
Kayu Lain-lain
###
###
###
###
###
###
###
Kayu Jati Ex Malang
###
###
###
###
###
Kayu Jati Ex Madiun/Ngawi
###
###
###
###
###
Kayu Jati Ex Bojonegoro
###
###
###
###
###
Besi dan Aluminium
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Atap Genteng
###
###
###
###
1 m2 -- 25 bh
###
###
###
###
###
###
1 m' -- 3,5 bh
###
###
###
###
###
###
###
###
###
###
###
###
###
Atap Seng / Asbes
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Kayu Olahan
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Perlengkapan Kamar Mandi
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Alat-Alat Penggantung
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Kaca
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Perlengkapan Lantai
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
45500/dus
###
46000/dus
###
###
###
###
###
48500/dus
###
###
###
###
###
###
###
###
###
###
###
###
###
Perpipaan
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Plitur & Cat
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Peralatan Air Bersih
###
###
###
###
###
Instalasi Listrik
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Lain - Lain
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

Wahyuningtyas, M.Si.

81218 198503 2 007


DAFTAR UPAH
TAHUN ANGGARAN 2013

KODE URAIAN SATUAN UPAH KETERANGAN

L01 Mandor Org/hr 65,175.00


L02 Kepala Tukang Batu Org/hr 55,275.00
L03 Kepala Tukang Kayu Org/hr 55,275.00
L04 Kepala Tukang Besi Org/hr 55,275.00
L05 Kepala Tukang Cat Org/hr 55,275.00
L06 Kepala Tukang Listrik Org/hr 55,275.00
L07 Tukang Batu Org/hr 51,975.00
L08 Tukang Kayu Org/hr 51,975.00
L09 Tukang Besi/Baja Org/hr 51,975.00
L10 Tukang Cat Org/hr 51,975.00
L11 Tukang Listrik Org/hr 51,975.00
L12 Tukang Pipa Org/hr 51,975.00
L13 Tukang Plitur Org/hr 51,975.00
L14 Tukang Taman Org/hr 51,975.00
L15 Tukang Aspal Org/hr 51,975.00
L16 Pembantu Tukang Org/hr 42,900.00
L17 Pekerja Biasa Org/hr 42,900.00
L18 Penjaga Malam Org/hr 40,700.00
L19 Sopir Org/hr 50,875.00
L20 Operator Org/hr 53,900.00
L21 Mekanik Org/hr 53,900.00
L22 Pembantu Sopir Org/hr 46,200.00
L23 Pembantu Operator Org/hr 49,500.00
L24 Pembantu Mekanik Org/hr 49,500.00
L25 Juru Ukur Org/hr 155,100.00
L26 Engineer dan Crew Ls 526,240.00
L27 Tenaga Ahli Geolistrik Org/hr 654,500.00
L28 Tenaga Ahli Geofisika Or / hr 561,000.00

Malang, 28 Januari 2013


Kepala Dinas Pendidikan
Kota Malang

Dra. Sri Wahyuningtyas, M.Si.


Pembina Utama Muda
NIP. 19581218 198503 2 007
DAFTAR PERALATAN
TAHUN ANGGARAN 2013

KODE URAIAN SATUAN HARGA

E01 Sewa Mesin Bor hari 1,485,000.00


E02 Sewa Kompresor (15-20 bar) hari 2,640,000.00
E03 Sewa Genset (15 KVA) hari 1,100,000.00
E04 Sewa Pompa Tes hari 4,400,000.00
E05 Sewa Mesin Las (150A) hari 400,000.00
E06 Sewa Alat Geolistrik hari 1,925,000.00
E07 Sewa Alat Geofisikal, Elektrikal, Logging hari 1,925,000.00
E08 Sewa Mud Pump Jam 63,000.00
E09 Sewa Alat Sandblasting hari 1,210,000.00
E10 Sewa Excavator (Excavator 80-140 HP) hari 3,574,606.49
E11 Sewa Whell Loader (Wheel Loader 1.0-1.6 M3) hari 2,520,000.00
E12 Sewa Motor Grader (Motor Grader >100 HP) hari 3,366,117.80
E13 Sewa Vibro Roller (Vibratory Roller 5-8 T.) hari 2,551,208.67
E14 Sewa Water Tanker (Water Tanker 3000-4500 L.) hari 1,853,206.12
E15 Pesawat Ukur Unit/hr 110,000.00
E16 Meteran bh 100,000.00
E17 Palu bh 25,000.00
E18 Keranjang bh 10,000.00
E19 Ganco bh 75,000.00
E20 Alat pelancip/pisau besar bh 25,000.00
E21 Palu Besar/bodem bh 100,000.00
E22 Timbris Unit 30,000.00
E23 Kereta Dorong Unit 100,000.00
E24 Jack Hammer bh 122,769.00
E25 Molen (Condrete Mixer.350) Unit/hr 529,827.21
E26 Ember bh 5,000.00
E27 Kotak Adukan bh 25,000.00
E28 Cetok bh 10,000.00
E29 Kuas bh 10,000.00
E30 Kasut Kayu bh 10,000.00
E31 Tang Pemotong Kawat bh 50,000.00
E32 Vibrator (Concrete Vibrator) Unit/hr 233,144.80
E33 Gergaji bh 50,000.00
E34 Gunting pemotong besi bh 50,000.00
E35 Kunci Pembengkok tulangan bh 25,000.00
E36 Bor Besi bh 100,000.00
E37 Stamper Unit/hr 271,954.55
E38 Sewa Dump Truk (Dump Truck 3.5 Ton) hr 2,025,215.00
E39 Sewa Mobil Picup hr 250,000.00
AFTAR PERALATAN
HUN ANGGARAN 2013

KETERANGAN
ANALISA HARGA SATUAN

KODE ANALISA : A.001


JENIS PEKERJAAN : Pagar sementara dari kayu tinggi 2 m
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.4000 42,900.00 17,160.00


2 Tukang Kayu L08 Org/hr 0.2000 51,975.00 10,395.00
3 Kepala Tukang Kayu L03 Org/hr 0.0200 55,275.00 1,105.50
4 Mandor L01 Org/hr 0.0200 65,175.00 1,303.50

JUMLAH HARGATENAGA 29,964.00

B BAHAN

1 Dolken Kayu 8 cm M089 btg 1.2500 27,594.00 34,492.50


2 Portland Cement (PC) M037 kg 2.5000 1,350.00 3,375.00
3 Pasir Cor M004 m 0.0050 130,000.00 650.00
4 Stenslah/batu pecah tangan 2/3 M014 m 0.0090 215,000.00 1,935.00
5 Usuk 5/7 M061 m 0.0720 4,958,415.00 357,005.88
6 Paku Kayu Segala Ukuran M140 kg 0.0600 21,780.00 1,306.80
7 Residu atau Teer M425 Ltr 0.4000 26,829.00 10,731.60

JUMLAH HARGA BAHAN 409,496.78

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 439,460.78

ANALISA HARGA SATUAN

KODE ANALISA : A.002


JENIS PEKERJAAN : Pagar sementara dari seng gelombang tinggi 2 m
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.4000 42,900.00 17,160.00


2 Tukang Kayu L08 Org/hr 0.2000 51,975.00 10,395.00
3 Kepala Tukang Kayu L03 Org/hr 0.0200 55,275.00 1,105.50
4 Mandor L01 Org/hr 0.0200 65,175.00 1,303.50

JUMLAH HARGATENAGA 29,964.00

B BAHAN

1 Dolken Kayu 8 cm M089 btg 1.2500 27,594.00 34,492.50


2 Portland Cement (PC) M037 kg 2.5000 1,350.00 3,375.00
3 Atap Seng Gelombang M178 Ibr 1.2000 81,553.50 97,864.20
4 Pasir Cor M004 m 0.0050 130,000.00 650.00
5 Stenslah/batu pecah tangan 2/3 M014 m 0.0090 215,000.00 1,935.00
6 Usuk 5/7 M061 m 0.0720 4,958,415.00 357,005.88
7 Paku Kayu Segala Ukuran M140 kg 0.0600 21,780.00 1,306.80
8 Cat meni besi M410 kg 0.4500 35,343.00 15,904.35

JUMLAH HARGA BAHAN 512,533.73

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 542,497.73

ANALISA HARGA SATUAN

KODE ANALISA : A.003


JENIS PEKERJAAN : Pagar sementara dari kawat duri tinggi 1.8 m
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3000 42,900.00 12,870.00


2 Tukang Kayu L08 Org/hr 0.2000 51,975.00 10,395.00
3 Kepala Tukang Kayu L03 Org/hr 0.0200 55,275.00 1,105.50
4 Mandor L01 Org/hr 0.0200 65,175.00 1,303.50

JUMLAH HARGATENAGA 25,674.00

B BAHAN

1 Dolken Kayu 8 cm M089 btg 1.0000 27,594.00 27,594.00


2 Portland Cement (PC) M037 kg 2.0000 1,350.00 2,700.00
3 Kawat Duri M137 kg 25.0000 21,285.00 532,125.00
4 Pasir Cor M004 m 0.0050 130,000.00 650.00
5 Stenslah/batu pecah tangan 2/3 M014 m 0.0090 215,000.00 1,935.00
6 Paku Kayu Segala Ukuran M140 kg 0.0600 21,780.00 1,306.80

JUMLAH HARGA BAHAN 566,310.80

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 591,984.80

ANALISA HARGA SATUAN

KODE ANALISA : A.004


JENIS PEKERJAAN : Pagar kawat jaring galvanis, tinggi 1,0 m
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0420 42,900.00 1,801.80


2 Tukang Kayu L08 Org/hr 0.0420 51,975.00 2,182.95
3 Kepala Tukang Kayu L03 Org/hr 0.0040 55,275.00 221.10
4 Mandor L01 Org/hr 0.0020 65,175.00 130.35

JUMLAH HARGATENAGA 4,336.20

B BAHAN

1 Kawat Harmonika Gas M136 m 1.1000 23,364.00 25,700.40

JUMLAH HARGA BAHAN 25,700.40

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 30,036.60

ANALISA HARGA SATUAN

KODE ANALISA : A.005


JENIS PEKERJAAN : Pengukuran dan pemasangan bouwplank
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1000 42,900.00 4,290.00


2 Tukang Kayu L08 Org/hr 0.1000 51,975.00 5,197.50
3 Kepala Tukang Kayu L03 Org/hr 0.0100 55,275.00 552.75
4 Mandor L01 Org/hr 0.0050 65,175.00 325.88

JUMLAH HARGATENAGA 10,366.13

B BAHAN

1 Balok Kayu Kelas III M084 m 0.0120 3,305,610.00 39,667.32


2 Paku Kayu Segala Ukuran M140 kg 0.0200 21,780.00 435.60
3 Papan Kayu kelas III M085 m 0.0070 3,712,500.00 25,987.50

JUMLAH HARGA BAHAN 66,090.42

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 76,456.55

ANALISA HARGA SATUAN

KODE ANALISA : A.006


JENIS PEKERJAAN : Pembuatan kantor sementara, dengan lantai plesteran
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 2.0000 42,900.00 85,800.00


2 Tukang Kayu L08 Org/hr 1.0000 51,975.00 51,975.00
3 Tukang Batu L07 Org/hr 1.0000 51,975.00 51,975.00
4 Kepala Tukang Kayu L03 Org/hr 0.3000 55,275.00 16,582.50
5 Mandor L01 Org/hr 0.0500 65,175.00 3,258.75

JUMLAH HARGATENAGA 209,591.25

B BAHAN

1 Balok M062 m 0.1800 5,559,435.00 1,000,698.30


2 Paku Kayu Segala Ukuran M140 kg 0.3000 21,780.00 6,534.00
2 Portland Cement (PC) M037 kg 35.0000 1,350.00 47,250.00
3 Pasir Pasang M002 m 0.1500 90,000.00 13,500.00
4 Pasir Cor M004 m 0.1000 130,000.00 13,000.00
5 Stenslah/batu pecah tangan 2/3 M014 m 0.1500 215,000.00 32,250.00
6 Bata Merah M022 bh 30.0000 570.00 17,100.00
7 Atap Seng Gelombang M178 Ibr 0.5000 81,553.50 40,776.75
8 Jendela Nako + accessories M285 m 0.0750 231,808.50 17,385.64
9 Kaca Polos tebal 3 mm M270 m 0.1500 79,191.00 11,878.65
11 Multiplek 6 mm M216 lbr 1.5000 81,742.50 122,613.75
12 Grendel Pintu M262 bh 2.0000 21,546.00 43,092.00
13 Engsel Pintu M257 bh 2.0000 31,482.00 62,964.00

JUMLAH HARGA BAHAN 1,429,043.09

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1,638,634.34

ANALISA HARGA SATUAN

KODE ANALISA : A.007


JENIS PEKERJAAN : Pembuatan gudang semen dan alat-alat
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 2.0000 42,900.00 85,800.00


2 Tukang Kayu L08 Org/hr 1.0000 51,975.00 51,975.00
3 Tukang Batu L07 Org/hr 1.0000 51,975.00 51,975.00
4 Kepala Tukang Kayu L03 Org/hr 0.3000 55,275.00 16,582.50
5 Mandor L01 Org/hr 0.0500 65,175.00 3,258.75

JUMLAH HARGATENAGA 209,591.25

B BAHAN

1 Balok M062 m 0.2100 5,559,435.00 1,167,481.35


2 Paku Kayu Segala Ukuran M140 kg 0.3000 21,780.00 6,534.00
3 Portland Cement (PC) M037 kg 10.5000 1,350.00 14,175.00
4 Pasir Cor M004 m 0.0300 130,000.00 3,900.00
5 Stenslah/batu pecah tangan 2/3 M014 m 0.0500 215,000.00 10,750.00
6 Atap Seng Gelombang M178 Ibr 0.5000 81,553.50 40,776.75
7 Multiplek 6 mm M216 lbr 1.1500 81,742.50 94,003.88
8 Grendel Pintu M262 bh 2.0000 21,546.00 43,092.00
9 Engsel Pintu M257 bh 2.0000 31,482.00 62,964.00

JUMLAH HARGA BAHAN 1,443,676.98

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1,653,268.23

ANALISA HARGA SATUAN

KODE ANALISA : A.008


JENIS PEKERJAAN : Pembuatan rumah jaga/konstruksi kayu
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 2.0000 42,900.00 85,800.00


2 Tukang Kayu L08 Org/hr 1.0000 51,975.00 51,975.00
3 Kepala Tukang Kayu L03 Org/hr 0.3000 55,275.00 16,582.50
4 Mandor L01 Org/hr 0.0500 65,175.00 3,258.75

JUMLAH HARGATENAGA 157,616.25

B BAHAN

1 Balok M062 m 0.1800 5,559,435.00 1,000,698.30


2 Paku Kayu Segala Ukuran M140 kg 0.3000 21,780.00 6,534.00
2 Portland Cement (PC) M037 kg 35.0000 1,350.00 47,250.00
3 Pasir Pasang M002 m 0.1500 90,000.00 13,500.00
4 Pasir Cor M004 m 0.1000 130,000.00 13,000.00
5 Stenslah/batu pecah tangan 2/3 M014 m 0.1500 215,000.00 32,250.00
6 Bata Merah M022 bh 30.0000 570.00 17,100.00
7 Atap Seng Gelombang M178 Ibr 0.5000 81,553.50 40,776.75
8 Jendela Nako + accessories M285 m 0.1500 231,808.50 34,771.28
9 Kaca Polos tebal 3 mm M270 m 0.3000 79,191.00 23,757.30
11 Multiplek 6 mm M216 lbr 1.5000 81,742.50 122,613.75

JUMLAH HARGA BAHAN 1,352,251.38

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1,509,867.63

ANALISA HARGA SATUAN

KODE ANALISA : A.009


JENIS PEKERJAAN : Membersihkan lapangan dan perataan
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1000 42,900.00 4,290.00


2 Tukang Kayu L08 Org/hr - 51,975.00 -
3 Kepala Tukang Kayu L03 Org/hr - 55,275.00 -
4 Mandor L01 Org/hr 0.0500 65,175.00 3,258.75

JUMLAH HARGATENAGA 7,548.75

B BAHAN
JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 7,548.75

ANALISA HARGA SATUAN

KODE ANALISA : A.010


JENIS PEKERJAAN : Pembuatan bedeng buruh
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 2.0000 42,900.00 85,800.00


2 Tukang Kayu L08 Org/hr 1.0000 51,975.00 51,975.00
3 Tukang Batu L07 Org/hr 1.0000 51,975.00 51,975.00
4 Kepala Tukang Kayu L03 Org/hr 0.3000 55,275.00 16,582.50
5 Mandor L01 Org/hr 0.0500 65,175.00 3,258.75

JUMLAH HARGATENAGA 209,591.25

B BAHAN

1 Balok M062 m 0.2100 5,559,435.00 1,167,481.35


2 Paku Kayu Segala Ukuran M140 kg 0.3000 21,780.00 6,534.00
3 Portland Cement (PC) M037 kg 10.5000 1,350.00 14,175.00
4 Pasir Cor M004 m 0.0300 130,000.00 3,900.00
5 Stenslah/batu pecah tangan 2/3 M014 m 0.0500 215,000.00 10,750.00
6 Atap Seng Gelombang M178 Ibr 0.5000 81,553.50 40,776.75
7 Jendela Nako + accessories M285 m 0.0750 231,808.50 17,385.64
8 Multiplek 6 mm M216 lbr 1.1500 81,742.50 94,003.88
9 Grendel Pintu M262 bh 2.0000 21,546.00 43,092.00
10 Engsel Pintu M257 bh 2.0000 31,482.00 62,964.00

JUMLAH HARGA BAHAN 1,461,062.61

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1,670,653.86

ANALISA HARGA SATUAN

KODE ANALISA : A.011


JENIS PEKERJAAN : Pembuatan bak adukan ukuran (40 x 50 x 20) cm
SATUAN PEMBAYARAN : bh

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr - 42,900.00 -


2 Tukang Kayu L08 Org/hr 0.3000 51,975.00 15,592.50
3 Kepala Tukang Kayu L03 Org/hr - 55,275.00 -
4 Mandor L01 Org/hr 0.0015 65,175.00 97.76

JUMLAH HARGATENAGA 15,690.26

B BAHAN

1 Papan (2x20) cm M063 m 0.0360 6,611,220.00 238,003.92


2 Paku Kayu Segala Ukuran M140 kg 0.0800 21,780.00 1,742.40
3 Usuk 5/7 M061 m 0.0150 4,958,415.00 74,376.23

JUMLAH HARGA BAHAN 314,122.55

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 329,812.81

ANALISA HARGA SATUAN

KODE ANALISA : A.012


JENIS PEKERJAAN : Pembuatan jalan sementara
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.0000 42,900.00 42,900.00


2 Tukang Kayu L08 Org/hr - 51,975.00 -
3 Kepala Tukang Kayu L03 Org/hr - 55,275.00 -
4 Mandor L01 Org/hr 0.0500 65,175.00 3,258.75

JUMLAH HARGATENAGA 46,158.75

B BAHAN

1 Batu Belah Kali M011 m 0.1500 127,809.00 19,171.35


2 Stenslah/batu pecah tangan 4/6 - 5/7 M016 m 0.0900 142,956.00 12,866.04
3 Pasir Pasang M002 m 0.0100 90,000.00 900.00

JUMLAH HARGA BAHAN 32,937.39

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 79,096.14

ANALISA HARGA SATUAN

KODE ANALISA : A.013


JENIS PEKERJAAN : Bongkar pasang kayu kuda-kuda / kusen / loteng
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 4.0000 42,900.00 171,600.00


2 Tukang Kayu L08 Org/hr 6.0000 51,975.00 311,850.00
3 Kepala Tukang Kayu L03 Org/hr 0.6000 55,275.00 33,165.00
4 Mandor L01 Org/hr 0.0600 65,175.00 3,910.50

JUMLAH HARGATENAGA 520,525.50

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 520,525.50

ANALISA HARGA SATUAN

KODE ANALISA : A.014


JENIS PEKERJAAN : Bongkaran beton bertulang
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 6.6670 42,900.00 286,014.30


2 Tukang Kayu L08 Org/hr - 51,975.00 -
3 Kepala Tukang Kayu L03 Org/hr - 55,275.00 -
4 Mandor L01 Org/hr 0.3330 65,175.00 21,703.28

JUMLAH HARGATENAGA 307,717.58

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 307,717.58

ANALISA HARGA SATUAN

KODE ANALISA : A.015


JENIS PEKERJAAN : Bongkaran tembok bata merah
SATUAN PEMBAYARAN : m3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 6.6670 42,900.00 286,014.30


2 Tukang Kayu L08 Org/hr - 51,975.00 -
3 Kepala Tukang Kayu L03 Org/hr - 55,275.00 -
4 Mandor L01 Org/hr 0.0330 65,175.00 2,150.78

JUMLAH HARGATENAGA 288,165.08

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 288,165.08

ANALISA HARGA SATUAN

KODE ANALISA : A.016


JENIS PEKERJAAN : Bongkaran atap
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.1000 42,900.00 47,190.00


2 Tukang Kayu L08 Org/hr - 51,975.00 -
3 Kepala Tukang Kayu L03 Org/hr - 55,275.00 -
4 Mandor L01 Org/hr 0.0500 65,175.00 3,258.75

JUMLAH HARGATENAGA 50,448.75

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 50,448.75

ANALISA HARGA SATUAN

KODE ANALISA : A.017


JENIS PEKERJAAN : Bongkaran lantai
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2000 42,900.00 8,580.00


2 Tukang Kayu L08 Org/hr - 51,975.00 -
3 Kepala Tukang Kayu L03 Org/hr - 55,275.00 -
4 Mandor L01 Org/hr 0.0100 65,175.00 651.75

JUMLAH HARGATENAGA 9,231.75

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 9,231.75

ANALISA HARGA SATUAN

KODE ANALISA : A.018


JENIS PEKERJAAN : Bongkaran plafon
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2000 42,900.00 8,580.00


2 Tukang Kayu L08 Org/hr 0.0600 51,975.00 3,118.50
3 Kepala Tukang Kayu L03 Org/hr 0.0060 55,275.00 331.65
4 Mandor L01 Org/hr 0.0100 65,175.00 651.75

JUMLAH HARGATENAGA 12,681.90

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 12,681.90

ANALISA HARGA SATUAN

KODE ANALISA : A.019


JENIS PEKERJAAN : Bongkaran penutup atap lama (Genteng)
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2000 42,900.00 8,580.00


2 Tukang Kayu L08 Org/hr - 51,975.00 -
3 Kepala Tukang Kayu L03 Org/hr - 55,275.00 -
4 Mandor L01 Org/hr 0.1000 65,175.00 6,517.50

JUMLAH HARGATENAGA 15,097.50

B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA PERALATAN -


10 m2 15,097.50
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1 m2 1,509.75

ANALISA HARGA SATUAN

KODE ANALISA : A.020


JENIS PEKERJAAN : Bongkaran rangka penutup atap lama (Usuk+Reng)
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.0000 42,900.00 42,900.00


2 Tukang Kayu L08 Org/hr 0.2500 51,975.00 12,993.75
3 Kepala Tukang Kayu L03 Org/hr 0.0250 55,275.00 1,381.88
4 Mandor L01 Org/hr 0.0500 65,175.00 3,258.75

JUMLAH HARGATENAGA 60,534.38

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -


10 m2 60,534.38
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1 m2 6,053.44

ANALISA HARGA SATUAN

KODE ANALISA : A.021


JENIS PEKERJAAN : Bongkaran konstruksi atap lama
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 4.0000 42,900.00 171,600.00


2 Tukang Kayu L08 Org/hr 6.0000 51,975.00 311,850.00
3 Kepala Tukang Kayu L03 Org/hr 0.6000 55,275.00 33,165.00
4 Mandor L01 Org/hr 0.2000 65,175.00 13,035.00

JUMLAH HARGATENAGA 529,650.00

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -


10 m2 529,650.00
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1 m2 52,965.00

ANALISA HARGA SATUAN

KODE ANALISA : A.022


JENIS PEKERJAAN : Bongkaran plafon
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr - 42,900.00 -


2 Tukang Kayu L08 Org/hr 0.5000 51,975.00 25,987.50
3 Kepala Tukang Kayu L03 Org/hr - 55,275.00 -
4 Mandor L01 Org/hr 0.1000 65,175.00 6,517.50

JUMLAH HARGATENAGA 32,505.00

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -


10 m2 32,505.00
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1 m2 3,250.50

ANALISA HARGA SATUAN

KODE ANALISA : A.023


JENIS PEKERJAAN : Mengupas plesteran Lama
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5000 42,900.00 21,450.00


2 Tukang Kayu L08 Org/hr - 51,975.00 -
3 Kepala Tukang Kayu L03 Org/hr - 55,275.00 -
4 Mandor L01 Org/hr 0.0250 65,175.00 1,629.38

JUMLAH HARGATENAGA 23,079.38

B BAHAN

JUMLAH HARGA BAHAN -

C PERALATAN

JUMLAH HARGA PERALATAN -


10 m2 23,079.38
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1 m2 2,307.94
ANALISA HARGA SATUAN

KODE ANALISA : B.001


JENIS PEKERJAAN : Galian tanah biasa sedalam 1 m
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.7500


2 Tukang Batu L07 Org/hr -
3 Kepala Tukang Batu L02 Org/hr -
4 Mandor L01 Org/hr 0.0250

JUMLAH HARGA TENAGA

B BAHAN

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 32,175.00
51,975.00 -
55,275.00 -
65,175.00 1,629.38

33,804.38

33,804.38
ANALISA HARGA SATUAN

KODE ANALISA : B.008


JENIS PEKERJAAN : Pembuangan tanah sejauh 30 m
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3300


2 Tukang Batu L07 Org/hr -
3 Kepala Tukang Batu L02 Org/hr -
4 Mandor L01 Org/hr 0.0100

JUMLAH HARGA TENAGA

B BAHAN

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 14,157.00
51,975.00 -
55,275.00 -
65,175.00 651.75

14,808.75

14,808.75
ANALISA HARGA SATUAN

KODE ANALISA : B.009


JENIS PEKERJAAN : Urugan kembali
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3000


2 Tukang Batu L07 Org/hr -
3 Kepala Tukang Batu L02 Org/hr -
4 Mandor L01 Org/hr 0.0150

JUMLAH HARGA TENAGA

B BAHAN

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 12,870.00
51,975.00 -
55,275.00 -
65,175.00 977.63

13,847.63

13,847.63
ANALISA HARGA SATUAN

KODE ANALISA : B.011


JENIS PEKERJAAN : Urugan pasir
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3000


2 Tukang Batu L07 Org/hr -
3 Kepala Tukang Batu L02 Org/hr -
4 Mandor L01 Org/hr 0.0100

JUMLAH HARGA TENAGA

B BAHAN

1 Pasir Urug M001 m 1.2000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 12,870.00
51,975.00 -
55,275.00 -
65,175.00 651.75

13,521.75

77,395.50 92,874.60

92,874.60

106,396.35
ANALISA HARGA SATUAN

KODE ANALISA : B.015


JENIS PEKERJAAN : Urugan sirtu padat untuk peninggian lantai bangunan
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2500


2 Tukang Batu L07 Org/hr -
3 Kepala Tukang Batu L02 Org/hr -
4 Mandor L01 Org/hr 0.0250

JUMLAH HARGA TENAGA

B BAHAN

1 Sirtu M007 m 1.2000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Urugan sirtu padat untuk peninggian lantai bangunan

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 10,725.00
51,975.00 -
55,275.00 -
65,175.00 1,629.38

12,354.38

109,053.00 130,863.60

130,863.60

143,217.98
ANALISA HARGA SATUAN

KODE ANALISA : B.020


JENIS PEKERJAAN : Pembuangan tanah sejauh > 1 km
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3300


2 Tukang Batu L07 Org/hr -
3 Kepala Tukang Batu L02 Org/hr -
4 Mandor L01 Org/hr 0.0100

JUMLAH HARGA TENAGA

B BAHAN

JUMLAH HARGA BAHAN

C PERALATAN
1 Sewa Dump Truk (Dump Truck 3.5 Ton) E38 hari 0.0095238095

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 14,157.00
51,975.00 -
55,275.00 -
65,175.00 651.75

14,808.75

2,025,215.00 19,287.76

19,287.76

34,096.51
ANALISA HARGA SATUAN

KODE ANALISA : C.002


JENIS PEKERJAAN : Pasang pondasi batu kali, 1 Pc : 4 Ps
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.5000


2 Tukang Batu L07 Org/hr 0.7500
3 Kepala Tukang Batu L02 Org/hr 0.0750
4 Mandor L01 Org/hr 0.0750

JUMLAH HARGA TENAGA

B BAHAN

1 Batu Kali M012 m 1.2000


2 Portland Cement (PC) M037 kg 163.0000
3 Pasir Pasang M002 m 0.5200

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 64,350.00
51,975.00 38,981.25
55,275.00 4,145.63
65,175.00 4,888.13

112,365.00

100,000.00 120,000.00
1,350.00 220,050.00
90,000.00 46,800.00

386,850.00

499,215.00
ANALISA HARGA SATUAN

KODE ANALISA : C.004


JENIS PEKERJAAN : Pasang pondasi batu kali, 1 Pc : 6 Ps
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.5000


2 Tukang Batu L07 Org/hr 0.7500
3 Kepala Tukang Batu L02 Org/hr 0.0750
4 Mandor L01 Org/hr 0.0750

JUMLAH HARGA TENAGA

B BAHAN

1 Batu Kali M012 m 1.2000


2 Portland Cement (PC) M037 kg 117.0000
3 Pasir Pasang M002 m 0.5610

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 64,350.00
51,975.00 38,981.25
55,275.00 4,145.63
65,175.00 4,888.13

112,365.00

100,000.00 120,000.00
1,350.00 157,950.00
90,000.00 50,490.00

328,440.00

440,805.00
ANALISA HARGA SATUAN

KODE ANALISA : C.009


JENIS PEKERJAAN : Pasang pondasi batu kosong
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.7800


2 Tukang Batu L07 Org/hr 0.3900
3 Kepala Tukang Batu L02 Org/hr 0.0390
4 Mandor L01 Org/hr 0.0390

JUMLAH HARGA TENAGA

B BAHAN

1 Batu Kali M012 m 1.2000


2 Pasir Urug M001 m 0.4320

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 33,462.00
51,975.00 20,270.25
55,275.00 2,155.73
65,175.00 2,541.83

58,429.80

100,000.00 120,000.00
77,395.50 33,434.86

153,434.86

211,864.66
ANALISA HARGA SATUAN

KODE ANALISA : D.003


JENIS PEKERJAAN : Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6000


2 Tukang Batu L07 Org/hr 0.2000
3 Kepala Tukang Batu L02 Org/hr 0.0200
4 Mandor L01 Org/hr 0.0300

JUMLAH HARGA TENAGA

B BAHAN

1 Bata Merah M022 bh 140.0000


2 Portland Cement (PC) M037 kg 26.5500
3 Pasir Pasang M002 m 0.0930

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 25,740.00
51,975.00 10,395.00
55,275.00 1,105.50
65,175.00 1,955.25

39,195.75

570.00 79,800.00
1,350.00 35,842.50
90,000.00 8,370.00

124,012.50

163,208.25
ANALISA HARGA SATUAN

KODE ANALISA : D.005


JENIS PEKERJAAN : Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6000


2 Tukang Batu L07 Org/hr 0.2000
3 Kepala Tukang Batu L02 Org/hr 0.0200
4 Mandor L01 Org/hr 0.0300

JUMLAH HARGA TENAGA

B BAHAN

1 Bata Merah M022 bh 140.0000


2 Portland Cement (PC) M037 kg 18.5000
3 Pasir Pasang M002 m 0.1220

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 25,740.00
51,975.00 10,395.00
55,275.00 1,105.50
65,175.00 1,955.25

39,195.75

570.00 79,800.00
1,350.00 24,975.00
90,000.00 10,980.00

115,755.00

154,950.75
ANALISA HARGA SATUAN

KODE ANALISA : D.009


JENIS PEKERJAAN : Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3000


2 Tukang Batu L07 Org/hr 0.1000
3 Kepala Tukang Batu L02 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0150

JUMLAH HARGA TENAGA

B BAHAN

1 Bata Merah M022 bh 70.0000


2 Portland Cement (PC) M037 kg 11.5000
3 Pasir Pasang M002 m 0.0430

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 12,870.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 977.63

19,597.88

570.00 39,900.00
1,350.00 15,525.00
90,000.00 3,870.00

59,295.00

78,892.88
ANALISA HARGA SATUAN

KODE ANALISA : D.011


JENIS PEKERJAAN : Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3000


2 Tukang Batu L07 Org/hr 0.1000
3 Kepala Tukang Batu L02 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0150

JUMLAH HARGA TENAGA

B BAHAN

1 Bata Merah M022 bh 70.0000


2 Portland Cement (PC) M037 kg 8.3200
3 Pasir Pasang M002 m 0.0490

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 12,870.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 977.63

19,597.88

570.00 39,900.00
1,350.00 11,232.00
90,000.00 4,410.00

55,542.00

75,139.88
ANALISA HARGA SATUAN

KODE ANALISA : E.004


JENIS PEKERJAAN : Plesteran 1 Pc : 4 Ps, tebal 15 mm
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3000


2 Tukang Batu L07 Org/hr 0.1500
3 Kepala Tukang Batu L02 Org/hr 0.0150
4 Mandor L01 Org/hr 0.0150

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg 6.2400


2 Pasir Pasang M002 m 0.0240

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 12,870.00
51,975.00 7,796.25
55,275.00 829.13
65,175.00 977.63

22,473.00

1,350.00 8,424.00
90,000.00 2,160.00

10,584.00

33,057.00
ANALISA HARGA SATUAN

KODE ANALISA : E.006


JENIS PEKERJAAN : Plesteran 1 Pc : 6 Ps, tebal 15 mm
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3000


2 Tukang Batu L07 Org/hr 0.1500
3 Kepala Tukang Batu L02 Org/hr 0.0150
4 Mandor L01 Org/hr 0.0150

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg 4.4160


2 Pasir Pasang M002 m 0.0270

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 12,870.00
51,975.00 7,796.25
55,275.00 829.13
65,175.00 977.63

22,473.00

1,350.00 5,961.60
90,000.00 2,430.00

8,391.60

30,864.60
ANALISA HARGA SATUAN

KODE ANALISA : E.015


JENIS PEKERJAAN : Plesteran 1 Pc : 4 Ps, tebal 20 mm
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.4000


2 Tukang Batu L07 Org/hr 0.2000
3 Kepala Tukang Batu L02 Org/hr 0.0200
4 Mandor L01 Org/hr 0.0220

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg 8.3200


2 Pasir Pasang M002 m 0.0320

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 17,160.00
51,975.00 10,395.00
55,275.00 1,105.50
65,175.00 1,433.85

30,094.35

1,350.00 11,232.00
90,000.00 2,880.00

14,112.00

44,206.35
ANALISA HARGA SATUAN

KODE ANALISA : E.014


JENIS PEKERJAAN : Plesteran 1 Pc : 3 Ps, tebal 20 mm
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2600


2 Tukang Batu L07 Org/hr 0.2000
3 Kepala Tukang Batu L02 Org/hr 0.0200
4 Mandor L01 Org/hr 0.0130

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg 10.3680


2 Pasir Pasang M002 m 0.0310

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 11,154.00
51,975.00 10,395.00
55,275.00 1,105.50
65,175.00 847.28

23,501.78

1,350.00 13,996.80
90,000.00 2,790.00

16,786.80

40,288.58
ANALISA HARGA SATUAN

KODE ANALISA : E.023


JENIS PEKERJAAN : Plesteran Ciprat 1 Pc : 2 Ps,
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3000


2 Tukang Batu L07 Org/hr 0.1000
3 Kepala Tukang Batu L02 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0150

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg 4.3200


2 Pasir Pasang M002 m 0.0060

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 12,870.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 977.63

19,597.88

1,350.00 5,832.00
90,000.00 540.00

6,372.00

25,969.88
ANALISA HARGA SATUAN

KODE ANALISA : E.024


JENIS PEKERJAAN : Plesteran siar pasangan batu kali adukan 1 Pc : 2 Ps
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3000


2 Tukang Batu L07 Org/hr 0.1500
3 Kepala Tukang Batu L02 Org/hr 0.0150
4 Mandor L01 Org/hr 0.0150

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg 6.3400


2 Pasir Pasang M002 m 0.0120

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Plesteran siar pasangan batu kali adukan 1 Pc : 2 Ps

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 12,870.00
51,975.00 7,796.25
55,275.00 829.13
65,175.00 977.63

22,473.00

1,350.00 8,559.00
90,000.00 1,080.00

9,639.00

32,112.00
ANALISA HARGA SATUAN

KODE ANALISA : E.025


JENIS PEKERJAAN : Benangan
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr -


2 Tukang Batu L07 Org/hr 0.1200
3 Kepala Tukang Batu L02 Org/hr -
4 Mandor L01 Org/hr -

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg 6.5000


2 Pasir Pasang M002 m 0.0210

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 -
51,975.00 6,237.00
55,275.00 -
65,175.00 -

6,237.00

1,350.00 8,775.00
90,000.00 1,890.00

10,665.00

16,902.00
ANALISA HARGA SATUAN

KODE ANALISA : E.026


JENIS PEKERJAAN : Acian
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2000


2 Tukang Batu L07 Org/hr 0.1000
3 Kepala Tukang Batu L02 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0100

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg 3.2500

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 8,580.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 651.75

14,982.00

1,350.00 4,387.50

4,387.50

19,369.50
ANALISA HARGA SATUAN

KODE ANALISA : E.027


JENIS PEKERJAAN : Finishing beton expose
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1500


2 Tukang Batu L07 Org/hr 0.0700
3 Kepala Tukang Batu L02 Org/hr 0.0070
4 Mandor L01 Org/hr 0.0080

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg 4.3200


2 Pasir Pasang M002 m 0.0160

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 6,435.00
51,975.00 3,638.25
55,275.00 386.93
65,175.00 521.40

10,981.58

1,350.00 5,832.00
90,000.00 1,440.00

7,272.00

18,253.58
ANALISA HARGA SATUAN

KODE ANALISA : E.028


JENIS PEKERJAAN : Benangan Sudut
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr -


2 Tukang Batu L07 Org/hr 0.1200
3 Kepala Tukang Batu L02 Org/hr -
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg 1.6250

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 -
51,975.00 6,237.00
55,275.00 -
65,175.00 -

6,237.00

1,350.00 2,193.75

2,193.75

8,430.75
ANALISA HARGA SATUAN

KODE ANALISA : F.012a


JENIS PEKERJAAN : Pasang pintu panel kayu meranti
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.0000


2 Tukang Kayu L08 Org/hr 3.0000
3 Kepala Tukang Kayu L03 Org/hr 0.3000
4 Mandor L01 Org/hr 0.0500

JUMLAH HARGA TENAGA

B BAHAN

1 Papan (3x30) cm M065 m 0.0400


2 Lem Kayu M422 kg 0.5000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 42,900.00
51,975.00 155,925.00
55,275.00 16,582.50
65,175.00 3,258.75

218,666.25

6,939,900.00 277,596.00
29,502.00 14,751.00

292,347.00

-
1 m2 511,013.25
Bh (Uk 80x210 cm) 858,502.26
ANALISA HARGA SATUAN

KODE ANALISA : F.012b


JENIS PEKERJAAN : Pasang pintu panel kayu meranti. Lapis alumi jeruk
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.0000


2 Tukang Kayu L08 Org/hr 3.0000
3 Kepala Tukang Kayu L03 Org/hr 0.3000
4 Mandor L01 Org/hr 0.0500

JUMLAH HARGA TENAGA

B BAHAN

1 Papan (3x30) cm M065 m 0.0400


2 Lem Kayu M422 kg 0.5000
3 Lapis aluminum jeruk M497 m2 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasang pintu panel kayu meranti. Lapis alumi jeruk

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 42,900.00
51,975.00 155,925.00
55,275.00 16,582.50
65,175.00 3,258.75

218,666.25

6,939,900.00 277,596.00
29,502.00 14,751.00
27,000.00 27,000.00

319,347.00

-
1 m2 538,013.25
Bh (Uk 70x210 cm) 790,879.48
ANALISA HARGA SATUAN

KODE ANALISA : F.091


JENIS PEKERJAAN : Pasang lisplang ukuran (3 x 30) cm, kayu meranti
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1000


2 Tukang Kayu L08 Org/hr 0.2000
3 Kepala Tukang Kayu L03 Org/hr 0.0200
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Papan (3x30) cm M065 m 0.0110


2 Paku Kayu Segala Ukuran M140 kg 0.0500

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasang lisplang ukuran (3 x 30) cm, kayu meranti

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 4,290.00
51,975.00 10,395.00
55,275.00 1,105.50
65,175.00 325.88

16,116.38

6,939,900.00 76,338.90
21,780.00 1,089.00

77,427.90

93,544.28
ANALISA HARGA SATUAN

KODE ANALISA : F.016


JENIS PEKERJAAN : Pasang pintu dan jendela kaca freme kayu meranti
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.8000


2 Tukang Kayu L08 Org/hr 2.4000
3 Kepala Tukang Kayu L03 Org/hr 0.2400
4 Mandor L01 Org/hr 0.0400

JUMLAH HARGA TENAGA

B BAHAN

1 Papan (3x30) cm M065 m 0.0240


2 Kaca Polos tebal 5 mm M271 m 0.8464
3 Lem Kayu M422 kg 0.3000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Daun Jendela (Luas
Daun Jendela
Pasang pintu dan jendela kaca freme kayu meranti

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 34,320.00
51,975.00 124,740.00
55,275.00 13,266.00
65,175.00 2,607.00

174,933.00

6,939,900.00 166,557.60
120,204.00 101,740.67
29,502.00 8,850.60

277,148.87

-
1 m2 452,081.87
Daun Pintu 80 x 210 cm 759,497.53
Daun Jendela (Luas Rata2 0,65 m2) 293,853.21
Daun Jendela BV 60 x 50 cm 135,624.56
ANALISA HARGA SATUAN

KODE ANALISA : F.020


JENIS PEKERJAAN : Pasang pintu dan jendela jalusi kayu meranti
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.0000


2 Tukang Kayu L08 Org/hr 3.0000
3 Kepala Tukang Kayu L03 Org/hr 0.3000
4 Mandor L01 Org/hr 0.0500

JUMLAH HARGA TENAGA

B BAHAN

1 Papan (3x30) cm M065 m 0.0640


2 Lem Kayu M422 kg 0.5000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 42,900.00
51,975.00 155,925.00
55,275.00 16,582.50
65,175.00 3,258.75

218,666.25

6,939,900.00 444,153.60
29,502.00 14,751.00

458,904.60

-
1 m2 677,570.85
Uk. 50 x 110 cm 372,663.97
ANALISA HARGA SATUAN

KODE ANALISA : F.045


JENIS PEKERJAAN : Pasang konstruksi kuda-kuda kayu meranti
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 4.0000


2 Tukang Kayu L08 Org/hr 12.0000
3 Kepala Tukang Kayu L03 Org/hr 1.2000
4 Mandor L01 Org/hr 0.2000

JUMLAH HARGA TENAGA

B BAHAN

1 Balok M062 m 1.1000


2 Besi Strip / Plat Plendes M114 kg 15.0000
3 Paku Kayu Segala Ukuran M140 kg 5.6000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 171,600.00
51,975.00 623,700.00
55,275.00 66,330.00
65,175.00 13,035.00

874,665.00

5,559,435.00 6,115,378.50
9,702.00 145,530.00
21,780.00 121,968.00

6,382,876.50

7,257,541.50
ANALISA HARGA SATUAN

KODE ANALISA : F.049


JENIS PEKERJAAN : Pasang konstruksi gording kayu meranti
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 2.4000


2 Tukang Kayu L08 Org/hr 7.2000
3 Kepala Tukang Kayu L03 Org/hr 0.7200
4 Mandor L01 Org/hr 0.1200

JUMLAH HARGA TENAGA

B BAHAN

1 Balok M062 m 1.1000


2 Besi Strip / Plat Plendes M114 kg 15.0000
3 Paku Kayu Segala Ukuran M140 kg 3.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 102,960.00
51,975.00 374,220.00
55,275.00 39,798.00
65,175.00 7,821.00

524,799.00

5,559,435.00 6,115,378.50
9,702.00 145,530.00
21,780.00 65,340.00

6,326,248.50

6,851,047.50
ANALISA HARGA SATUAN

KODE ANALISA : F.067


JENIS PEKERJAAN : Pasang kaso + reng genteng beton kayu meranti
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1000


2 Tukang Kayu L08 Org/hr 0.1000
3 Kepala Tukang Kayu L03 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Usuk 5/7 M061 m 0.0140


2 Paku Kayu Segala Ukuran M140 kg 0.2500
3 Reng 2/3, 3/5 M060 m 0.0090

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasang kaso + reng genteng beton kayu meranti

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 4,290.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 325.88

10,366.13

4,958,415.00 69,417.81
21,780.00 5,445.00
4,958,415.00 44,625.74

119,488.55

129,854.67
ANALISA HARGA SATUAN

KODE ANALISA : F.079


JENIS PEKERJAAN : Pasang Kembali rangka langit-langit (1.0 x 1.0) m, kayu m
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1500


2 Tukang Kayu L08 Org/hr 0.3000
3 Kepala Tukang Kayu L03 Org/hr 0.0300
4 Mandor L01 Org/hr 0.0750

JUMLAH HARGA TENAGA

B BAHAN

1 Paku Kayu Segala Ukuran M140 kg 0.2000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasang Kembali rangka langit-langit (1.0 x 1.0) m, kayu meranti

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 6,435.00
51,975.00 15,592.50
55,275.00 1,658.25
65,175.00 4,888.13

28,573.88

21,780.00 4,356.00

4,356.00

32,929.88
ANALISA HARGA SATUAN

KODE ANALISA : G.001


JENIS PEKERJAAN : Beton mutu fc'=7,4 Mpa (K100) slump (12
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.002


JENIS PEKERJAAN : Beton mutu fc'=9,8 Mpa (K125) slump (12
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN


A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.003


JENIS PEKERJAAN : Beton mutu fc'=12,2 Mpa (K150) slump (1
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.004


JENIS PEKERJAAN : Lantai kerja beton mutu fc'=7,4 Mpa (K10
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.005


JENIS PEKERJAAN : Beton mutu fc'=14,5 Mpa (K175) slump (1
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.006


JENIS PEKERJAAN : Beton mutu fc'=16,9 Mpa (K200) slump (1
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.007


JENIS PEKERJAAN : Beton mutu fc'=19,3 Mpa (K225) slump (1
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN
JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.008


JENIS PEKERJAAN : Beton mutu fc'=24,0 Mpa (K275) slump (1
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.009


JENIS PEKERJAAN : Beton mutu fc'=21,7 Mpa (K250) slump (1
SATUAN PEMBAYARAN : m3
NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.010


JENIS PEKERJAAN : Beton mutu fc'=26,4 Mpa (K300) slump (1
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN
1 Portland Cement (PC) M037 kg
2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.011


JENIS PEKERJAAN : Beton mutu fc'=28,8 Mpa (K325) slump (1
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : G.012


JENIS PEKERJAAN : Beton mutu fc'=31,2 Mpa (K350) slump (1
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.013


JENIS PEKERJAAN : Beton kedap air dengan strorox - 100
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA
1 Pekerja Biasa L17 Org/hr
2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Portland Cement (PC) M037 kg


2 Pasir Cor M004 m
3 Batu pecah mesin 2/3 M019 m
4 Strorox 100 M476 kg
5 Air Bersih M486 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.014


JENIS PEKERJAAN : Pasang PVC Waterstop lebar 150 mm
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Waterstop Lebar 150 mm M467 m


JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.015


JENIS PEKERJAAN : Pasang PVC Waterstop lebar 200 mm
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Waterstop Lebar 200 mm M468 m

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.016


JENIS PEKERJAAN : Pasang PVC Waterstop lebar 230 mm - 32
SATUAN PEMBAYARAN : m
NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Waterstop Lebar 230 mm M469 m

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.017


JENIS PEKERJAAN : Pembesian dengan besi polos
SATUAN PEMBAYARAN : kg

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Besi/Baja L09 Org/hr
3 Kepala Tukang Besi L04 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN
1 Besi Beton Polos M112 kg
2 Kawat Beton/Bendrat RRT M135 kg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.018


JENIS PEKERJAAN : Pembesian dengan besi ulir
SATUAN PEMBAYARAN : kg

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Besi/Baja L09 Org/hr
3 Kepala Tukang Besi L04 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Besi Beton Ulir M113 kg


2 Kawat Beton/Bendrat RRT M135 kg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.019


JENIS PEKERJAAN : Kabel prestressed polos/strands
SATUAN PEMBAYARAN : kg

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Besi/Baja L09 Org/hr
3 Kepala Tukang Besi L04 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Kabel prestressed M118 kg


2 Kawat Beton/Bendrat RRT M135 kg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.020


JENIS PEKERJAAN : Memasang 1 kg jaring kawat baja / wire m
SATUAN PEMBAYARAN : kg

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Besi/Baja L09 Org/hr
3 Kepala Tukang Besi L04 Org/hr
4 Mandor L01 Org/hr
JUMLAH HARGA TENAGA

B BAHAN

1 Wire Mesh M148.a kg


2 Kawat Beton/Bendrat RRT M135 kg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.021


JENIS PEKERJAAN : Pasang bekisting untuk pondasi
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : G.022


JENIS PEKERJAAN : Pasang bekisting untuk pondasi ( 2x pak
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.023


JENIS PEKERJAAN : Pasang bekisting untuk sloof
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA
1 Pekerja Biasa L17 Org/hr
2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.024


JENIS PEKERJAAN : Pasang bekisting untuk sloof ( 2x pakai )
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.025


JENIS PEKERJAAN : Pasang bekisting untuk kolom
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Balok Kayu Kelas III M084 m
5 Multiplek 9 mm M217 lbr
6 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.026


JENIS PEKERJAAN : Pasang bekisting untuk kolom ( 2x pakai
SATUAN PEMBAYARAN : m
NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Balok Kayu Kelas III M084 m
5 Multiplek 9 mm M217 lbr
6 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.027


JENIS PEKERJAAN : Pasang bekisting untuk balok
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Balok Kayu Kelas III M084 m
5 Multiplek 9 mm M217 lbr
6 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.028


JENIS PEKERJAAN : Pasang bekisting untuk balok ( 2x pakai )
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Balok Kayu Kelas III M084 m
5 Multiplek 9 mm M217 lbr
6 Dolken Kayu 8 cm M089 btg
JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.029


JENIS PEKERJAAN : Pasang bekisting untuk plat lantai
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Balok Kayu Kelas III M084 m
5 Multiplek 9 mm M217 lbr
6 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN


KODE ANALISA : G.030
JENIS PEKERJAAN : Pasang bekisting untuk plat lantai ( 2x pa
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Balok Kayu Kelas III M084 m
5 Multiplek 9 mm M217 lbr
6 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.031


JENIS PEKERJAAN : Pasang bekisting untuk dinding
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA
1 Pekerja Biasa L17 Org/hr
2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Balok Kayu Kelas III M084 m
5 Multiplek 9 mm M217 lbr
6 Dolken Kayu 8 cm M089 btg
7 Formtie M477 bh

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.032


JENIS PEKERJAAN : Pasang bekisting untuk dinding ( 2x paka
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Balok Kayu Kelas III M084 m
5 Multiplek 9 mm M217 lbr
6 Dolken Kayu 8 cm M089 btg
7 Formtie M477 bh

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.033


JENIS PEKERJAAN : Pasang bekisting untuk tangga
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Balok Kayu Kelas III M084 m
5 Multiplek 9 mm M217 lbr
6 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN
JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.034


JENIS PEKERJAAN : Pasang bekisting untuk tangga ( 2x paka
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Kayu L08 Org/hr
3 Kepala Tukang Kayu L03 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Balok Kayu Kelas III M084 m
5 Multiplek 9 mm M217 lbr
6 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.035


JENIS PEKERJAAN : Pasang bekisting jembatan untuk pengec
SATUAN PEMBAYARAN : m
NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Kepala Tukang Batu L02 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Balok Kayu Kelas III M084 m


2 Paku Kayu Segala Ukuran M140 kg
3 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.036


JENIS PEKERJAAN : Pondasi beton bertulang (150 kg besi + b
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Tukang Kayu L08 Org/hr
4 Tukang Besi/Baja L09 Org/hr
5 Kepala Tukang Batu L02 Org/hr
6 Mandor L01 Org/hr

JUMLAH HARGA TENAGA


B BAHAN

1 Balok Kayu Kelas III M084 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Besi Beton Polos M112 kg
5 Kawat Beton/Bendrat RRT M135 kg
6 Portland Cement (PC) M037 kg
7 Pasir Cor M004 m
8 Batu pecah mesin 2/3 M019 m

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.037


JENIS PEKERJAAN : Sloof beton bertulang (200 kg besi + beki
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Tukang Kayu L08 Org/hr
4 Tukang Besi/Baja L09 Org/hr
5 Kepala Tukang Batu L02 Org/hr
6 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Besi Beton Polos M112 kg
5 Kawat Beton/Bendrat RRT M135 kg
6 Portland Cement (PC) M037 kg
7 Pasir Cor M004 m
8 Batu pecah mesin 2/3 M019 m

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.038


JENIS PEKERJAAN : Kolom beton bertulang (150 kg besi + be
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Tukang Kayu L08 Org/hr
4 Tukang Besi/Baja L09 Org/hr
5 Kepala Tukang Batu L02 Org/hr
6 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Besi Beton Polos M112 kg
5 Kawat Beton/Bendrat RRT M135 kg
6 Portland Cement (PC) M037 kg
7 Pasir Cor M004 m
8 Batu pecah mesin 2/3 M019 m
9 Balok Kayu Kelas III M084 m
10 Multiplek 9 mm M217 lbr
11 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.039


JENIS PEKERJAAN : Kolom beton bertulang (300 kg besi + be
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Tukang Kayu L08 Org/hr
4 Tukang Besi/Baja L09 Org/hr
5 Kepala Tukang Batu L02 Org/hr
6 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Besi Beton Polos M112 kg
5 Kawat Beton/Bendrat RRT M135 kg
6 Portland Cement (PC) M037 kg
7 Pasir Cor M004 m
8 Batu pecah mesin 2/3 M019 m
9 Balok Kayu Kelas III M084 m
10 Multiplek 9 mm M217 lbr
11 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN


D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.040


JENIS PEKERJAAN : Balok beton bertulang (200 kg besi + bek
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Tukang Kayu L08 Org/hr
4 Tukang Besi/Baja L09 Org/hr
5 Kepala Tukang Batu L02 Org/hr
6 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Besi Beton Polos M112 kg
5 Kawat Beton/Bendrat RRT M135 kg
6 Portland Cement (PC) M037 kg
7 Pasir Cor M004 m
8 Batu pecah mesin 2/3 M019 m
9 Balok Kayu Kelas III M084 m
10 Multiplek 9 mm M217 lbr
11 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN


KODE ANALISA : G.041
JENIS PEKERJAAN : Dinding beton bertulang (150 kg besi + b
SATUAN PEMBAYARAN : m3

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Tukang Kayu L08 Org/hr
4 Tukang Besi/Baja L09 Org/hr
5 Kepala Tukang Batu L02 Org/hr
6 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Besi Beton Polos M112 kg
5 Kawat Beton/Bendrat RRT M135 kg
6 Portland Cement (PC) M037 kg
7 Pasir Cor M004 m
8 Batu pecah mesin 2/3 M019 m
9 Balok Kayu Kelas III M084 m
10 Multiplek 9 mm M217 lbr
11 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.042


JENIS PEKERJAAN : Dinding beton bertulang (200 kg besi + b
SATUAN PEMBAYARAN : m3
NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Tukang Kayu L08 Org/hr
4 Tukang Besi/Baja L09 Org/hr
5 Kepala Tukang Batu L02 Org/hr
6 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Minyak bekisting M474 Itr
4 Besi Beton Polos M112 kg
5 Kawat Beton/Bendrat RRT M135 kg
6 Portland Cement (PC) M037 kg
7 Pasir Cor M004 m
8 Batu pecah mesin 2/3 M019 m
9 Balok Kayu Kelas III M084 m
10 Multiplek 9 mm M217 lbr
11 Dolken Kayu 8 cm M089 btg

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.043


JENIS PEKERJAAN : Kolom penguat beton bertulang (11 x 11)
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN


A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Tukang Kayu L08 Org/hr
4 Tukang Besi/Baja L09 Org/hr
5 Kepala Tukang Batu L02 Org/hr
6 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Besi Beton Polos M112 kg
4 Kawat Beton/Bendrat RRT M135 kg
5 Portland Cement (PC) M037 kg
6 Pasir Cor M004 m
7 Batu pecah mesin 2/3 M019 m

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.044


JENIS PEKERJAAN : Ring balok beton bertulang (10 x 15) cm
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Tukang Kayu L08 Org/hr
4 Tukang Besi/Baja L09 Org/hr
5 Kepala Tukang Batu L02 Org/hr
6 Mandor L01 Org/hr
JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Besi Beton Polos M112 kg
4 Kawat Beton/Bendrat RRT M135 kg
5 Portland Cement (PC) M037 kg
6 Pasir Cor M004 m
7 Batu pecah mesin 2/3 M019 m

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.045


JENIS PEKERJAAN : Sloof beton bertulang (10 x 15) cm
SATUAN PEMBAYARAN : m

NO. KOMPONEN SATUAN

A. TENAGA

1 Pekerja Biasa L17 Org/hr


2 Tukang Batu L07 Org/hr
3 Tukang Kayu L08 Org/hr
4 Tukang Besi/Baja L09 Org/hr
5 Kepala Tukang Batu L02 Org/hr
6 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m


2 Paku Kayu Segala Ukuran M140 kg
3 Besi Beton Polos M112 kg
4 Kawat Beton/Bendrat RRT M135 kg
5 Portland Cement (PC) M037 kg
6 Pasir Cor M004 m
7 Batu pecah mesin 2/3 M019 m

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

Beton mutu fc'=7,4 Mpa (K100) slump (12 2) cm, w/c = 0,87

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1.6500 42,900.00 70,785.00


0.2750 51,975.00 14,293.13
0.0280 55,275.00 1,547.70
0.0830 65,175.00 5,409.53

92,035.35

247.0000 1,350.00 333,450.00


0.6207 130,000.00 80,692.86
0.7400 189,387.00 140,146.38
215.000 27.00 5,805.00

560,094.24

652,129.59

ANALISA HARGA SATUAN

Beton mutu fc'=9,8 Mpa (K125) slump (12 2) cm, w/c = 0,78

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
1.6500 42,900.00 70,785.00
0.2750 51,975.00 14,293.13
0.0280 55,275.00 1,547.70
0.0830 65,175.00 5,409.53

92,035.35

276.0000 1,350.00 372,600.00


0.5914 130,000.00 76,885.71
0.7496 189,387.00 141,970.11
215.000 27.00 5,805.00

597,260.82

689,296.17

ANALISA HARGA SATUAN

Beton mutu fc'=12,2 Mpa (K150) slump (12 2) cm, w/c = 0,72

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1.6500 42,900.00 70,785.00


0.2750 51,975.00 14,293.13
0.0280 55,275.00 1,547.70
0.0830 65,175.00 5,409.53

92,035.35

299.0000 1,350.00 403,650.00


0.5707 130,000.00 74,192.86
0.7533 189,387.00 142,671.54
215.000 27.00 5,805.00

626,319.40

718,354.75

ANALISA HARGA SATUAN

Lantai kerja beton mutu fc'=7,4 Mpa (K100) slump (3 - 6) cm, w/c = 0,87

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1.2000 42,900.00 51,480.00


0.2000 51,975.00 10,395.00
0.0200 55,275.00 1,105.50
0.0600 65,175.00 3,910.50

66,891.00

230.0000 1,350.00 310,500.00


0.6379 130,000.00 82,921.43
0.7607 189,387.00 144,074.41
215.000 27.00 5,805.00

543,300.84

610,191.84

ANALISA HARGA SATUAN


Beton mutu fc'=14,5 Mpa (K175) slump (12 2) cm, w/c = 0,66

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1.6500 42,900.00 70,785.00


0.2750 51,975.00 14,293.13
0.0280 55,275.00 1,547.70
0.0830 65,175.00 5,409.53

92,035.35

326.0000 1,350.00 440,100.00


0.5429 130,000.00 70,571.43
0.7622 189,387.00 144,354.98
215.000 27.00 5,805.00

660,831.41

752,866.76

ANALISA HARGA SATUAN

Beton mutu fc'=16,9 Mpa (K200) slump (12 2) cm, w/c = 0,61

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1.6500 42,900.00 70,785.00


0.2750 51,975.00 14,293.13
0.0280 55,275.00 1,547.70
0.0830 65,175.00 5,409.53

92,035.35

352.0000 1,350.00 475,200.00


0.5221 130,000.00 67,878.57
0.7637 189,387.00 144,635.55
215.000 27.00 5,805.00

693,519.12

785,554.47

ANALISA HARGA SATUAN

Beton mutu fc'=19,3 Mpa (K225) slump (12 2) cm, w/c = 0,58

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1.6500 42,900.00 70,785.00


0.2750 51,975.00 14,293.13
0.0280 55,275.00 1,547.70
0.0830 65,175.00 5,409.53

92,035.35

371.0000 1,350.00 500,850.00


0.4986 130,000.00 64,814.29
0.7756 189,387.00 146,880.14
215.000 27.00 5,805.00

718,349.43
-

810,384.78

ANALISA HARGA SATUAN

Beton mutu fc'=24,0 Mpa (K275) slump (12 2) cm, w/c = 0,53

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1.6500 42,900.00 70,785.00


0.2750 51,975.00 14,293.13
0.0280 55,275.00 1,547.70
0.0830 65,175.00 5,409.53

92,035.35

406.0000 1,350.00 548,100.00


0.4886 130,000.00 63,514.29
0.7600 189,387.00 143,934.12
215.000 27.00 5,805.00

761,353.41

853,388.76

ANALISA HARGA SATUAN

Beton mutu fc'=21,7 Mpa (K250) slump (12 2) cm, w/c = 0,56

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1.6500 42,900.00 70,785.00


0.2750 51,975.00 14,293.13
0.0280 55,275.00 1,547.70
0.0830 65,175.00 5,409.53

92,035.35

384.0000 1,350.00 518,400.00


0.4943 130,000.00 64,257.14
0.7696 189,387.00 145,757.85
215.000 27.00 5,805.00

734,219.99

826,255.34

ANALISA HARGA SATUAN

Beton mutu fc'=26,4 Mpa (K300) slump (12 2) cm, w/c = 0,52

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1.6500 42,900.00 70,785.00


0.2750 51,975.00 14,293.13
0.0280 55,275.00 1,547.70
0.0830 65,175.00 5,409.53

92,035.35
413.0000 1,350.00 557,550.00
0.4864 130,000.00 63,235.71
0.7563 189,387.00 143,232.69
215.000 27.00 5,805.00

769,823.40

861,858.75

ANALISA HARGA SATUAN

Beton mutu fc'=28,8 Mpa (K325) slump (12 2) cm, w/c = 0,49

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

2.1000 42,900.00 90,090.00


0.3500 51,975.00 18,191.25
0.0350 55,275.00 1,934.63
0.1050 65,175.00 6,843.38

117,059.25

439.0000 1,350.00 592,650.00


0.4786 130,000.00 62,214.29
0.7452 189,387.00 141,128.39
215.000 27.00 5,805.00

801,797.67

918,856.92
ANALISA HARGA SATUAN

Beton mutu fc'=31,2 Mpa (K350) slump (12 2) cm, w/c = 0,48

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

2.1000 42,900.00 90,090.00


0.3500 51,975.00 18,191.25
0.0350 55,275.00 1,934.63
0.1050 65,175.00 6,843.38

117,059.25

448.0000 1,350.00 604,800.00


0.4764 130,000.00 61,935.71
0.7407 189,387.00 140,286.67
215.000 27.00 5,805.00

812,827.38

929,886.63

ANALISA HARGA SATUAN

Beton kedap air dengan strorox - 100

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
2.1000 42,900.00 90,090.00
0.3500 51,975.00 18,191.25
0.0350 55,275.00 1,934.63
0.1050 65,175.00 6,843.38

117,059.25

400.0000 1,350.00 540,000.00


0.4800 130,000.00 62,400.00
0.8000 189,387.00 151,509.60
1.2000 102,762.00 123,314.40
210.0000 27.00 5,670.00

882,894.00

999,953.25

ANALISA HARGA SATUAN

Pasang PVC Waterstop lebar 150 mm

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.0600 42,900.00 2,574.00


0.0300 51,975.00 1,559.25
0.0030 55,275.00 165.83
0.0030 65,175.00 195.53

4,494.60

1.0500 40,446.00 42,468.30


42,468.30

46,962.90

ANALISA HARGA SATUAN

Pasang PVC Waterstop lebar 200 mm

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.0700 42,900.00 3,003.00


0.0350 51,975.00 1,819.13
0.0040 55,275.00 221.10
0.0040 65,175.00 260.70

5,303.93

1.0500 72,859.50 76,502.48

76,502.48

81,806.40

ANALISA HARGA SATUAN

Pasang PVC Waterstop lebar 230 mm - 320 mm


PERKIRAAN HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.0800 42,900.00 3,432.00


0.0400 51,975.00 2,079.00
0.0040 55,275.00 221.10
0.0040 65,175.00 260.70

5,992.80

1.0500 84,861.00 89,104.05

89,104.05

95,096.85

ANALISA HARGA SATUAN

Pembesian dengan besi polos

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.0070 42,900.00 300.30


0.0070 51,975.00 363.83
0.0007 55,275.00 38.69
0.0004 65,175.00 26.07

728.89
1.0500 9,750.00 10,237.50
0.0150 17,293.50 259.40

10,496.90

11,225.79

ANALISA HARGA SATUAN

Pembesian dengan besi ulir

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.0070 42,900.00 300.30


0.0070 51,975.00 363.83
0.0007 55,275.00 38.69
0.0004 65,175.00 26.07

728.89

1.0500 14,157.00 14,864.85


0.0150 17,293.50 259.40

15,124.25

15,853.14

ANALISA HARGA SATUAN


Kabel prestressed polos/strands

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.0050 42,900.00 214.50


0.0050 51,975.00 259.88
0.0005 55,275.00 27.64
0.0003 65,175.00 19.55

521.57

1.0500 29,700.00 31,185.00


0.0100 17,293.50 172.94

31,357.94

31,879.50

ANALISA HARGA SATUAN

Memasang 1 kg jaring kawat baja / wire mesh

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.0250 42,900.00 1,072.50


0.0250 51,975.00 1,299.38
0.0020 55,275.00 110.55
0.0010 65,175.00 65.18
2,547.60

1.0200 16,537.50 16,868.25


0.0500 17,293.50 864.68

17,732.93

20,280.53

ANALISA HARGA SATUAN

Pasang bekisting untuk pondasi

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.5200 42,900.00 22,308.00


0.2600 51,975.00 13,513.50
0.0260 55,275.00 1,437.15
0.0260 65,175.00 1,694.55

38,953.20

0.0400 3,712,500.00 148,500.00


0.3000 21,780.00 6,534.00
0.1000 2,574.00 257.40

155,291.40

194,244.60
ANALISA HARGA SATUAN

Pasang bekisting untuk pondasi ( 2x pakai )

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.5200 42,900.00 22,308.00


0.2600 51,975.00 13,513.50
0.0260 55,275.00 1,437.15
0.0260 65,175.00 1,694.55

38,953.20

0.0200 3,712,500.00 74,250.00


0.1500 21,780.00 3,267.00
0.0500 2,574.00 128.70

77,645.70

116,598.90

ANALISA HARGA SATUAN

Pasang bekisting untuk sloof

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.5200 42,900.00 22,308.00
0.2600 51,975.00 13,513.50
0.0260 55,275.00 1,437.15
0.0260 65,175.00 1,694.55

38,953.20

0.0450 3,712,500.00 167,062.50 kayu klas III


0.3000 21,780.00 6,534.00
0.1000 2,574.00 257.40

173,853.90

212,807.10

ANALISA HARGA SATUAN

Pasang bekisting untuk sloof ( 2x pakai )

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.5200 42,900.00 22,308.00


0.2600 51,975.00 13,513.50
0.0260 55,275.00 1,437.15
0.0260 65,175.00 1,694.55

38,953.20

0.0225 3,712,500.00 83,531.25 kayu klas III


0.1500 21,780.00 3,267.00
0.0500 2,574.00 128.70

86,926.95
-

125,880.15

ANALISA HARGA SATUAN

Pasang bekisting untuk kolom

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.6600 42,900.00 28,314.00


0.3300 51,975.00 17,151.75
0.0330 55,275.00 1,824.08
0.0330 65,175.00 2,150.78

49,440.60

0.0400 3,712,500.00 148,500.00


0.4000 21,780.00 8,712.00
0.2000 2,574.00 514.80
0.0150 3,305,610.00 49,584.15
0.3500 124,929.00 43,725.15 1.008
2.0000 27,594.00 55,188.00

306,224.10

355,664.70

ANALISA HARGA SATUAN

Pasang bekisting untuk kolom ( 2x pakai )


PERKIRAAN HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.6600 42,900.00 28,314.00


0.3300 51,975.00 17,151.75
0.0330 55,275.00 1,824.08
0.0330 65,175.00 2,150.78

49,440.60

0.0200 3,712,500.00 74,250.00


0.2000 21,780.00 4,356.00
0.1000 2,574.00 257.40
0.0075 3,305,610.00 24,792.08
0.1750 124,929.00 21,862.58 1.008
1.0000 27,594.00 27,594.00

153,112.05

202,552.65

ANALISA HARGA SATUAN

Pasang bekisting untuk balok

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.6600 42,900.00 28,314.00


0.3300 51,975.00 17,151.75
0.0330 55,275.00 1,824.08
0.0330 65,175.00 2,150.78

49,440.60

0.0400 3,712,500.00 148,500.00


0.4000 21,780.00 8,712.00
0.2000 2,574.00 514.80
0.0180 3,305,610.00 59,500.98
0.3500 124,929.00 43,725.15
2.0000 27,594.00 55,188.00

316,140.93

365,581.53

ANALISA HARGA SATUAN

Pasang bekisting untuk balok ( 2x pakai )

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.6600 42,900.00 28,314.00


0.3300 51,975.00 17,151.75
0.0330 55,275.00 1,824.08
0.0330 65,175.00 2,150.78

49,440.60

0.0200 3,712,500.00 74,250.00


0.2000 21,780.00 4,356.00
0.1000 2,574.00 257.40
0.0090 3,305,610.00 29,750.49
0.1750 124,929.00 21,862.58
1.0000 27,594.00 27,594.00
158,070.47

207,511.07

ANALISA HARGA SATUAN

Pasang bekisting untuk plat lantai

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.6600 42,900.00 28,314.00


0.3300 51,975.00 17,151.75
0.0330 55,275.00 1,824.08
0.0330 65,175.00 2,150.78

49,440.60

0.0400 3,712,500.00 148,500.00


0.4000 21,780.00 8,712.00
0.2000 2,574.00 514.80
0.0150 3,305,610.00 49,584.15
0.3500 124,929.00 43,725.15
6.0000 27,594.00 165,564.00

416,600.10

466,040.70

ANALISA HARGA SATUAN


Pasang bekisting untuk plat lantai ( 2x pakai )

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.6600 42,900.00 28,314.00


0.3300 51,975.00 17,151.75
0.0330 55,275.00 1,824.08
0.0330 65,175.00 2,150.78

49,440.60

0.0200 3,712,500.00 74,250.00


0.2000 21,780.00 4,356.00
0.1000 2,574.00 257.40
0.0075 3,305,610.00 24,792.08
0.1750 124,929.00 21,862.58
3.0000 27,594.00 82,782.00

208,300.05

257,740.65

ANALISA HARGA SATUAN

Pasang bekisting untuk dinding

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.6600 42,900.00 28,314.00
0.3300 51,975.00 17,151.75
0.0330 55,275.00 1,824.08
0.0330 65,175.00 2,150.78

49,440.60

0.0300 3,712,500.00 111,375.00


0.4000 21,780.00 8,712.00
0.2000 2,574.00 514.80
0.0200 3,305,610.00 66,112.20
0.3500 124,929.00 43,725.15
3.0000 27,594.00 82,782.00
4.0000 8,712.00 34,848.00

348,069.15

397,509.75

ANALISA HARGA SATUAN

Pasang bekisting untuk dinding ( 2x pakai )

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.6600 42,900.00 28,314.00


0.3300 51,975.00 17,151.75
0.0330 55,275.00 1,824.08
0.0330 65,175.00 2,150.78

49,440.60

0.0150 3,712,500.00 55,687.50


0.2000 21,780.00 4,356.00
0.1000 2,574.00 257.40
0.0100 3,305,610.00 33,056.10
0.1750 124,929.00 21,862.58
1.5000 27,594.00 41,391.00
2.0000 8,712.00 17,424.00

174,034.58

223,475.18

ANALISA HARGA SATUAN

Pasang bekisting untuk tangga

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.6600 42,900.00 28,314.00


0.3300 51,975.00 17,151.75
0.0330 55,275.00 1,824.08
0.0330 65,175.00 2,150.78

49,440.60

0.0300 3,712,500.00 111,375.00


0.4000 21,780.00 8,712.00
0.1500 2,574.00 386.10
0.0150 3,305,610.00 49,584.15
0.3500 124,929.00 43,725.15
2.0000 27,594.00 55,188.00

268,970.40
-

318,411.00

ANALISA HARGA SATUAN

Pasang bekisting untuk tangga ( 2x pakai )

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.6600 42,900.00 28,314.00


0.3300 51,975.00 17,151.75
0.0330 55,275.00 1,824.08
0.0330 65,175.00 2,150.78

49,440.60

0.0150 3,712,500.00 55,687.50


0.2000 21,780.00 4,356.00
0.0750 2,574.00 193.05
0.0075 3,305,610.00 24,792.08
0.1750 124,929.00 21,862.58
1.0000 27,594.00 27,594.00

134,485.20

183,925.80

ANALISA HARGA SATUAN

Pasang bekisting jembatan untuk pengecoran


PERKIRAAN HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.1500 42,900.00 6,435.00


0.0500 51,975.00 2,598.75
0.0050 55,275.00 276.38
0.0080 65,175.00 521.40

9,831.53

0.0264 3,305,610.00 87,268.10


0.6000 21,780.00 13,068.00
0.5000 27,594.00 13,797.00

114,133.10

123,964.63

ANALISA HARGA SATUAN

Pondasi beton bertulang (150 kg besi + bekisting)

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

5.3000 42,900.00 227,370.00


0.2750 51,975.00 14,293.13
1.3000 51,975.00 67,567.50
1.0500 51,975.00 54,573.75
0.2620 55,275.00 14,482.05
0.2650 65,175.00 17,271.38

395,557.80
0.2000 3,305,610.00 661,122.00
1.5000 21,780.00 32,670.00
0.4000 2,574.00 1,029.60
157.5000 9,750.00 1,535,625.00
2.2500 17,293.50 38,910.38
336.0000 1,350.00 453,600.00
0.5400 130,000.00 70,200.00
0.8100 189,387.00 153,403.47

2,946,560.45

3,342,118.25

ANALISA HARGA SATUAN

Sloof beton bertulang (200 kg besi + bekisting)

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

5.6500 42,900.00 242,385.00


0.2750 51,975.00 14,293.13
1.5600 51,975.00 81,081.00
1.4000 51,975.00 72,765.00
0.3230 55,275.00 17,853.83
0.2830 65,175.00 18,444.53

446,822.48

0.2700 3,712,500.00 1,002,375.00


2.0000 21,780.00 43,560.00
0.6000 2,574.00 1,544.40
210.0000 9,750.00 2,047,500.00
3.0000 17,293.50 51,880.50
336.0000 1,350.00 453,600.00
0.5400 130,000.00 70,200.00
0.8100 189,387.00 153,403.47

3,824,063.37

4,270,885.85

ANALISA HARGA SATUAN

Kolom beton bertulang (150 kg besi + bekisting)

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

5.3000 42,900.00 227,370.00


0.2750 51,975.00 14,293.13
1.3000 51,975.00 67,567.50
1.0500 51,975.00 54,573.75
0.2650 55,275.00 14,647.88
0.2650 65,175.00 17,271.38

395,723.63

0.3200 3,712,500.00 1,188,000.00


3.2000 21,780.00 69,696.00
1.6000 2,574.00 4,118.40
157.5000 9,750.00 1,535,625.00
2.2500 17,293.50 38,910.38
336.0000 1,350.00 453,600.00
0.5400 130,000.00 70,200.00
0.8100 189,387.00 153,403.47
0.1200 3,305,610.00 396,673.20
2.8000 124,929.00 349,801.20
32.0000 27,594.00 883,008.00

5,143,035.65
-

5,538,759.27

ANALISA HARGA SATUAN

Kolom beton bertulang (300 kg besi + bekisting)

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

7.0500 42,900.00 302,445.00


0.2750 51,975.00 14,293.13
1.6500 51,975.00 85,758.75
2.1000 51,975.00 109,147.50
0.4030 55,275.00 22,275.83
0.3530 65,175.00 23,006.78

556,926.98

0.4000 3,712,500.00 1,485,000.00


4.0000 21,780.00 87,120.00
2.0000 2,574.00 5,148.00
315.0000 9,750.00 3,071,250.00
4.5000 17,293.50 77,820.75
336.0000 1,350.00 453,600.00
0.5400 130,000.00 70,200.00
0.8100 189,387.00 153,403.47
0.1500 3,305,610.00 495,841.50
3.5000 124,929.00 437,251.50
20.0000 27,594.00 551,880.00

6,888,515.22

-
7,445,442.20

ANALISA HARGA SATUAN

Balok beton bertulang (200 kg besi + bekisting)

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

6.3500 42,900.00 272,415.00


0.2750 51,975.00 14,293.13
1.6500 51,975.00 85,758.75
1.4000 51,975.00 72,765.00
0.3330 55,275.00 18,406.58
0.3180 65,175.00 20,725.65

484,364.10

0.3200 3,712,500.00 1,188,000.00


3.2000 21,780.00 69,696.00
1.6000 2,574.00 4,118.40
210.0000 9,750.00 2,047,500.00
3.0000 17,293.50 51,880.50
336.0000 1,350.00 453,600.00
0.5400 130,000.00 70,200.00
0.8100 189,387.00 153,403.47
0.1400 3,305,610.00 462,785.40
2.8000 124,929.00 349,801.20
16.0000 27,594.00 441,504.00

5,292,488.97

5,776,853.07

ANALISA HARGA SATUAN


Dinding beton bertulang (150 kg besi + bekisting)

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

5.3000 42,900.00 227,370.00


0.2750 51,975.00 14,293.13
1.3000 51,975.00 67,567.50
1.0500 51,975.00 54,573.75
0.2620 55,275.00 14,482.05
0.2650 65,175.00 17,271.38

395,557.80

0.2400 3,712,500.00 891,000.00


3.2000 21,780.00 69,696.00
1.6000 2,574.00 4,118.40
157.5000 9,750.00 1,535,625.00
2.2500 17,293.50 38,910.38
336.0000 1,350.00 453,600.00
0.5400 130,000.00 70,200.00
0.8100 189,387.00 153,403.47
0.1600 3,305,610.00 528,897.60
2.8000 124,929.00 349,801.20
24.0000 27,594.00 662,256.00

4,757,508.05

5,153,065.85

ANALISA HARGA SATUAN

Dinding beton bertulang (200 kg besi + bekisting)


PERKIRAAN HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

5.6500 42,900.00 242,385.00


0.2750 51,975.00 14,293.13
1.5600 51,975.00 81,081.00
1.4000 51,975.00 72,765.00
0.3230 55,275.00 17,853.83
0.2830 65,175.00 18,444.53

446,822.48

0.2500 3,712,500.00 928,125.00


3.0000 21,780.00 65,340.00
1.2000 2,574.00 3,088.80
210.0000 9,750.00 2,047,500.00
3.0000 17,293.50 51,880.50
336.0000 1,350.00 453,600.00
0.5400 130,000.00 70,200.00
0.8100 189,387.00 153,403.47
0.1050 3,305,610.00 347,089.05
2.5000 124,929.00 312,322.50
14.0000 27,594.00 386,316.00

4,818,865.32

5,265,687.80

ANALISA HARGA SATUAN

Kolom penguat beton bertulang (11 x 11) cm

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.1800 42,900.00 7,722.00
0.0200 51,975.00 1,039.50
0.0200 51,975.00 1,039.50
0.0200 51,975.00 1,039.50
0.0060 55,275.00 331.65
0.0090 65,175.00 586.58

11,758.73

0.0020 3,712,500.00 7,425.00


0.0100 21,780.00 217.80
3.0000 9,750.00 29,250.00
0.0450 17,293.50 778.21
4.0000 1,350.00 5,400.00
0.0060 130,000.00 780.00
0.0090 189,387.00 1,704.48

45,555.49

57,314.22

ANALISA HARGA SATUAN

Ring balok beton bertulang (10 x 15) cm

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.297 42,900.00 12,741.30


0.033 51,975.00 1,715.18
0.033 51,975.00 1,715.18
0.033 51,975.00 1,715.18
0.010 55,275.00 552.75
0.015 65,175.00 977.63
19,417.20

0.0030 3,712,500.00 11,137.50


0.0200 21,780.00 435.60
3.6000 9,750.00 35,100.00
0.0500 17,293.50 864.68
5.5000 1,350.00 7,425.00
0.0090 130,000.00 1,170.00
0.0150 189,387.00 2,840.81

58,973.58

78,390.78

ANALISA HARGA SATUAN

Sloof beton bertulang (10 x 15) cm

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

0.275 42,900.00 11,797.50


0.033 51,975.00 1,715.18
0.033 51,975.00 1,715.18
0.033 51,975.00 1,715.18
0.010 55,275.00 552.75
0.015 65,175.00 977.63

18,473.40

0.0030 3,712,500.00 11,137.50


0.0200 21,780.00 435.60
3.6000 9,750.00 35,100.00
0.0500 17,293.50 864.68
5.5000 1,350.00 7,425.00
0.0090 130,000.00 1,170.00
0.0150 189,387.00 2,840.81

58,973.58

77,446.98
0.9056603774
0.024
0.024
2.88
0.3541666667
10
10
7.5

7.4074074074
4,379,788.43
ANALISA HARGA SATUAN

KODE ANALISA : Btn.001


JENIS PEKERJAAN : Strouss 30 cm
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 2.6790


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Besi/Baja L09 Org/hr 1.0290
4 Kepala Tukang Batu L02 Org/hr 0.1309
5 Mandor L01 Org/hr 0.1418

JUMLAH HARGA TENAGA

B BAHAN
a. Besi Tulangan
1 Besi Beton Polos M112 kg 147.0000
2 Kawat Beton/Bendrat RRT M135 kg 2.1000

b. Bahan Beton
3 Portland Cement (PC) M037 kg 336.0000
4 Pasir Cor M004 m 0.5400
5 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 002


JENIS PEKERJAAN : Pondasi Footplat beton bertulang (150 kg besi polos + b
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 5.3000


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 1.3000
4 Tukang Besi/Baja L09 Org/hr 1.0500
5 Kepala Tukang Batu L02 Org/hr 0.2620
6 Mandor L01 Org/hr 0.2650

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Balok Kayu Kelas III M084 m 0.1000
2 Paku Kayu Segala Ukuran M140 kg 0.7500
3 Minyak bekisting M474 Itr 0.4000

b. Besi Tulangan
4 Besi Beton Polos M112 kg 157.5000
5 Kawat Beton/Bendrat RRT M135 kg 2.2500

c. Bahan Beton
6 Portland Cement (PC) M037 kg 336.0000
7 Pasir Cor M004 m 0.5400
8 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 003


JENIS PEKERJAAN : Pondasi Footplat beton bertulang (150 kg besi ulir + bek
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 5.3000


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 1.3000
4 Tukang Besi/Baja L09 Org/hr 1.0500
5 Kepala Tukang Batu L02 Org/hr 0.2620
6 Mandor L01 Org/hr 0.2650

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Balok Kayu Kelas III M084 m 0.1000
2 Paku Kayu Segala Ukuran M140 kg 0.7500
3 Minyak bekisting M474 Itr 0.4000

b. Besi Tulangan
4 Besi Beton Ulir M113 kg 157.5000
5 Kawat Beton/Bendrat RRT M135 kg 2.2500

c. Bahan Beton
6 Portland Cement (PC) M037 kg 336.0000
7 Pasir Cor M004 m 0.5400
8 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 004


JENIS PEKERJAAN : Sloof beton bertulang 20/30 + bekisting
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 7.8300


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 2.6000
4 Tukang Besi/Baja L09 Org/hr 0.9800
5 Kepala Tukang Batu L02 Org/hr 0.3860
6 Mandor L01 Org/hr 0.3990

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Papan Kayu kelas III M085 m 0.2250
2 Paku Kayu Segala Ukuran M140 kg 1.5000
3 Minyak bekisting M474 Itr 1.0000

b. Besi Tulangan
4 Besi Beton Polos M112 kg 147.0000
5 Kawat Beton/Bendrat RRT M135 kg 2.1000

c. Bahan Beton
6 Portland Cement (PC) M037 kg 336.0000
7 Pasir Cor M004 m 0.5400
8 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 005


JENIS PEKERJAAN : Sloof beton bertulang 15/25 + bekisting
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 9.2833


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 3.4667
4 Tukang Besi/Baja L09 Org/hr 0.7000
5 Kepala Tukang Batu L02 Org/hr 0.4447
6 Mandor L01 Org/hr 0.4697

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Papan Kayu kelas III M085 m 0.3000
2 Paku Kayu Segala Ukuran M140 kg 2.0000
3 Minyak bekisting M474 Itr 1.3333

b. Besi Tulangan
4 Besi Beton Polos M112 kg 105.0000
5 Kawat Beton/Bendrat RRT M135 kg 1.5000

c. Bahan Beton
6 Portland Cement (PC) M037 kg 336.0000
7 Pasir Cor M004 m 0.5400
8 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 006


JENIS PEKERJAAN : Kolom beton bertulang 20x20 + bekisting
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 15.8300


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 6.6000
4 Tukang Besi/Baja L09 Org/hr 0.9800
5 Kepala Tukang Batu L02 Org/hr 0.7860
6 Mandor L01 Org/hr 0.7990

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Paku Kayu Segala Ukuran M140 kg 4.0000
2 Minyak bekisting M474 Itr 4.0000
3 Balok Kayu Kelas III M084 m 0.1500
4 Multiplek 9 mm M217 lbr 3.5000
5 Dolken Kayu 8 cm M089 btg 20.0000

b. Besi Tulangan
6 Besi Beton Polos M112 kg 147.0000
7 Kawat Beton/Bendrat RRT M135 kg 2.1000

c. Bahan Beton
8 Portland Cement (PC) M037 kg 336.0000
9 Pasir Cor M004 m 0.5400
10 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 007


JENIS PEKERJAAN : Kolom beton bertulang 30x30 + bekisting
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 11.2550


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 4.4000
4 Tukang Besi/Baja L09 Org/hr 0.8050
5 Kepala Tukang Batu L02 Org/hr 0.5485
6 Mandor L01 Org/hr 0.5690

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Paku Kayu Segala Ukuran M140 kg 2.6667
2 Minyak bekisting M474 Itr 2.6667
3 Balok Kayu Kelas III M084 m 0.1000
4 Multiplek 9 mm M217 lbr 2.3333
5 Dolken Kayu 8 cm M089 btg 13.3333

b. Besi Tulangan
6 Besi Beton Polos M112 kg 120.7500
7 Kawat Beton/Bendrat RRT M135 kg 1.7250

c. Bahan Beton
8 Portland Cement (PC) M037 kg 336.0000
9 Pasir Cor M004 m 0.5400
10 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 008


JENIS PEKERJAAN : Balok beton bertulang 15/25 + bekisting
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 17.5818


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 6.9385
4 Tukang Besi/Baja L09 Org/hr 2.0549
5 Kepala Tukang Batu L02 Org/hr 0.9273
6 Mandor L01 Org/hr 0.8943

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Paku Kayu Segala Ukuran M140 kg 4.2051
2 Minyak bekisting M474 Itr 4.2051
3 Balok Kayu Kelas III M084 m 0.1892
4 Multiplek 9 mm M217 lbr 3.6795
5 Dolken Kayu 8 cm M089 btg 21.0256

b. Besi Tulangan
6 Besi Beton Ulir M113 kg 199.3385
7 Besi Beton Polos M112 kg 108.8985
8 Kawat Beton/Bendrat RRT M135 kg 4.4034

c. Bahan Beton
9 Portland Cement (PC) M037 kg 336.0000
10 Pasir Cor M004 m 0.5400
11 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 009


JENIS PEKERJAAN : Balok beton bertulang 30/60 + bekisting
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 17.5818


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 6.9385
4 Tukang Besi/Baja L09 Org/hr 2.0549
5 Kepala Tukang Batu L02 Org/hr 0.9273
6 Mandor L01 Org/hr 0.8943

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Paku Kayu Segala Ukuran M140 kg 1.7500
2 Minyak bekisting M474 Itr 1.7500
3 Balok Kayu Kelas III M084 m 0.0788
4 Multiplek 9 mm M217 lbr 1.5313
5 Dolken Kayu 8 cm M089 btg 8.7500

b. Besi Tulangan
6 Besi Beton Ulir M113 kg 115.5000
7 Besi Beton Polos M112 kg 52.5000
8 Kawat Beton/Bendrat RRT M135 kg 2.4000

c. Bahan Beton
9 Portland Cement (PC) M037 kg 336.0000
10 Pasir Cor M004 m 0.5400
11 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 010


JENIS PEKERJAAN : Plat Lantai Beton Bertulang + Bekisting
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 17.5818


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 6.9385
4 Tukang Besi/Baja L09 Org/hr 2.0549
5 Kepala Tukang Batu L02 Org/hr 0.9273
6 Mandor L01 Org/hr 0.8943

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Paku Kayu Segala Ukuran M140 kg 1.6667
2 Minyak bekisting M474 Itr 1.6667
3 Balok Kayu Kelas III M084 m 0.0625
4 Multiplek 9 mm M217 lbr 1.4583
5 Dolken Kayu 8 cm M089 btg 25.0000

b. Besi Tulangan
6 Besi Beton Polos M112 kg 63.0000
7 Kawat Beton/Bendrat RRT M135 kg 0.9000

c. Bahan Beton
8 Portland Cement (PC) M037 kg 336.0000
9 Pasir Cor M004 m 0.5400
10 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 011


JENIS PEKERJAAN : Plat Atap Beton Bertulang + Bekisting
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 10.3900


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 4.1250
4 Tukang Besi/Baja L09 Org/hr 0.4900
5 Kepala Tukang Batu L02 Org/hr 0.4895
6 Mandor L01 Org/hr 0.5235

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Paku Kayu Segala Ukuran M140 kg 2.5000
2 Minyak bekisting M474 Itr 1.2500
3 Balok Kayu Kelas III M084 m 0.1875
4 Multiplek 9 mm M217 lbr 2.1875
5 Dolken Kayu 8 cm M089 btg 37.5000

b. Besi Tulangan
6 Besi Beton Polos M112 kg 73.5000
7 Kawat Beton/Bendrat RRT M135 kg 1.0500

c. Bahan Beton
8 Portland Cement (PC) M037 kg 336.0000
9 Pasir Cor M004 m 0.5400
10 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 012


JENIS PEKERJAAN : Plat Tangga Beton Bertulang + Bekisting
SATUAN PEMBAYARAN : m3

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 6.6800


2 Tukang Batu L07 Org/hr 0.2750
3 Tukang Kayu L08 Org/hr 2.2000
4 Tukang Besi/Baja L09 Org/hr 0.6300
5 Kepala Tukang Batu L02 Org/hr 0.3110
6 Mandor L01 Org/hr 0.3390

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Paku Kayu Segala Ukuran M140 kg 1.3333
2 Minyak bekisting M474 Itr 1.0000
3 Balok Kayu Kelas III M084 m 0.0500
4 Multiplek 9 mm M217 lbr 1.1667
5 Dolken Kayu 8 cm M089 btg 6.6667

b. Besi Tulangan
6 Besi Beton Polos M112 kg 94.5000
7 Kawat Beton/Bendrat RRT M135 kg 1.3500

c. Bahan Beton
8 Portland Cement (PC) M037 kg 336.0000
9 Pasir Cor M004 m 0.5400
10 Batu pecah mesin 2/3 M019 m 0.8100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 013


JENIS PEKERJAAN : Sloof Praktis Beton bertulang 11/20 + bekisting
SATUAN PEMBAYARAN : m'

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2679


2 Tukang Batu L07 Org/hr 0.0061
3 Tukang Kayu L08 Org/hr 0.1040
4 Tukang Besi/Baja L09 Org/hr 0.0236
5 Kepala Tukang Batu L02 Org/hr 0.0134
6 Mandor L01 Org/hr 0.0136

JUMLAH HARGA TENAGA

B BAHAN
a. Bekisting dipakai 2 x
1 Papan Kayu kelas III M085 m 0.0090
2 Paku Kayu Segala Ukuran M140 kg 0.0600
3 Minyak bekisting M474 Itr 0.0200

b. Besi Tulangan
4 Besi Beton Polos M112 kg 3.5453
5 Kawat Beton/Bendrat RRT M135 kg 0.0506

c. Bahan Beton
6 Portland Cement (PC) M037 kg 6.4548
7 Pasir Cor M004 m 0.0119
8 Batu pecah mesin 2/3 M019 m 0.0168

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

KODE ANALISA : Btn. 014


JENIS PEKERJAAN : Sloof Praktis Beton bertulang 11/25
SATUAN PEMBAYARAN : m'

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0613


2 Tukang Batu L07 Org/hr 0.0061
3 Tukang Besi/Baja L09 Org/hr 0.0250
4 Kepala Tukang Batu L02 Org/hr 0.0031
5 Mandor L01 Org/hr 0.0033

JUMLAH HARGA TENAGA

B BAHAN
a. Besi Tulangan
1 Besi Beton Polos M112 kg 3.7527
2 Kawat Beton/Bendrat RRT M135 kg 0.0536

b. Bahan Beton
3 Portland Cement (PC) M037 kg 8.0685
4 Pasir Cor M004 m 0.0149
5 Batu pecah mesin 2/3 M019 m 0.0210

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 114,929.10
51,975.00 14,293.13
51,975.00 53,482.28
55,275.00 7,235.50
65,175.00 9,241.82

199,181.81

9,750.00 1,433,250.00
17,293.50 36,316.35
1,469,566.35

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
2,146,769.82

2,345,951.63
Pondasi Footplat beton bertulang (150 kg besi polos + bekisting)

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 227,370.00
51,975.00 14,293.13
51,975.00 67,567.50
51,975.00 54,573.75
55,275.00 14,482.05
65,175.00 17,271.38

395,557.80

3,305,610.00 330,561.00
21,780.00 16,335.00
2,574.00 1,029.60
347,925.60

9,750.00 1,535,625.00
17,293.50 38,910.38
1,574,535.38

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
2,599,664.45

2,995,222.25
Pondasi Footplat beton bertulang (150 kg besi ulir + bekisting)

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 227,370.00
51,975.00 14,293.13
51,975.00 67,567.50
51,975.00 54,573.75
55,275.00 14,482.05
65,175.00 17,271.38

395,557.80

3,305,610.00 330,561.00
21,780.00 16,335.00
2,574.00 1,029.60
347,925.60

14,157.00 2,229,727.50
17,293.50 38,910.38
2,268,637.88

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
3,293,766.95

3,689,324.75
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 335,907.00
51,975.00 14,293.13
51,975.00 135,135.00
51,975.00 50,935.50
55,275.00 21,336.15
65,175.00 26,004.83

583,611.60

3,712,500.00 835,312.50
21,780.00 32,670.00
2,574.00 2,574.00
870,556.50

9,750.00 1,433,250.00
17,293.50 36,316.35
1,469,566.35

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
3,017,326.32

3,600,937.92
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 398,255.00
51,975.00 14,293.13
51,975.00 180,180.00
51,975.00 36,382.50
55,275.00 24,578.95
65,175.00 30,610.53

684,300.10

3,712,500.00 1,113,750.00
21,780.00 43,560.00
2,574.00 3,432.00
1,160,742.00

9,750.00 1,023,750.00
17,293.50 25,940.25
1,049,690.25

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
2,887,635.72

3,571,935.82
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 679,107.00
51,975.00 14,293.13
51,975.00 343,035.00
51,975.00 50,935.50
55,275.00 43,446.15
65,175.00 52,074.83

1,182,891.60

21,780.00 87,120.00
2,574.00 10,296.00
3,305,610.00 495,841.50
124,929.00 437,251.50
27,594.00 551,880.00
1,582,389.00

9,750.00 1,433,250.00
17,293.50 36,316.35
1,469,566.35

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
3,729,158.82

4,912,050.42
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 482,839.50
51,975.00 14,293.13
51,975.00 228,690.00
51,975.00 41,839.88
55,275.00 30,318.34
65,175.00 37,084.58

835,065.41

21,780.00 58,080.00
2,574.00 6,864.00
3,305,610.00 330,561.00
124,929.00 291,501.00
27,594.00 367,920.00
1,054,926.00

9,750.00 1,177,312.50
17,293.50 29,831.29
1,207,143.79

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
2,939,273.26

3,774,338.67
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 754,260.76
51,975.00 14,293.13
51,975.00 360,626.54
51,975.00 106,804.09
55,275.00 51,258.58
65,175.00 58,284.03

1,345,527.12

21,780.00 91,587.69
2,574.00 10,824.00
3,305,610.00 625,523.12
124,929.00 459,674.65
27,594.00 580,181.54
1,767,791.01

14,157.00 2,822,034.60
9,750.00 1,061,760.00
17,293.50 76,149.93
3,959,944.53

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
6,404,939.01

7,750,466.13
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 754,260.76
51,975.00 14,293.13
51,975.00 360,626.54
51,975.00 106,804.09
55,275.00 51,258.58
65,175.00 58,284.03

1,345,527.12

21,780.00 38,115.00
2,574.00 4,504.50
3,305,610.00 260,316.79
124,929.00 191,297.53
27,594.00 241,447.50
735,681.32

14,157.00 1,635,133.50
9,750.00 511,875.00
17,293.50 41,504.40
2,188,512.90

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
3,601,397.69

4,946,924.81
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 754,260.76
51,975.00 14,293.13
51,975.00 360,626.54
51,975.00 106,804.09
55,275.00 51,258.58
65,175.00 58,284.03

1,345,527.12

21,780.00 36,300.00
2,574.00 4,290.00
3,305,610.00 206,600.63
124,929.00 182,188.13
27,594.00 689,850.00
1,119,228.75

9,750.00 614,250.00
17,293.50 15,564.15
629,814.15

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
2,426,246.37

3,771,773.49
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 445,731.00
51,975.00 14,293.13
51,975.00 214,396.88
51,975.00 25,467.75
55,275.00 27,057.11
65,175.00 34,119.11

761,064.98

21,780.00 54,450.00
2,574.00 3,217.50
3,305,610.00 619,801.88
124,929.00 273,282.19
27,594.00 1,034,775.00
1,985,526.56

9,750.00 716,625.00
17,293.50 18,158.18
734,783.18

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
3,397,513.21

4,158,578.18
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 286,572.00
51,975.00 14,293.13
51,975.00 114,345.00
51,975.00 32,744.25
55,275.00 17,190.53
65,175.00 22,094.33

487,239.23

21,780.00 29,040.00
2,574.00 2,574.00
3,305,610.00 165,280.50
124,929.00 145,750.50
27,594.00 183,960.00
526,605.00

9,750.00 921,375.00
17,293.50 23,346.23
944,721.23

1,350.00 453,600.00
130,000.00 70,200.00
189,387.00 153,403.47
677,203.47
2,148,529.70

2,635,768.92
Sloof Praktis Beton bertulang 11/20 + bekisting

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 11,494.43
51,975.00 314.45
51,975.00 5,405.40
51,975.00 1,228.46
55,275.00 739.55
65,175.00 884.85

20,067.15

3,712,500.00 33,412.50
21,780.00 1,306.80
2,574.00 51.48
34,770.78

9,750.00 34,566.92
17,293.50 875.87
35,442.79

1,350.00 8,713.98
130,000.00 1,552.57
189,387.00 3,175.81
13,442.36
83,655.93

103,723.08
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 2,630.54
51,975.00 314.45
51,975.00 1,300.31
55,275.00 172.34
65,175.00 212.18

4,629.82

9,750.00 36,588.83
17,293.50 927.10
37,515.93

1,350.00 10,892.48
130,000.00 1,940.71
189,387.00 3,969.76
16,802.95
54,318.88

58,948.70
ANALISA HARGA SATUAN

KODE ANALISA : G.021


JENIS PEKERJAAN : Pasang bekisting untuk pondasi
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5200


2 Tukang Kayu L08 Org/hr 0.2600
3 Kepala Tukang Kayu L03 Org/hr 0.0260
4 Mandor L01 Org/hr 0.0260

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m 0.0400


2 Paku Kayu Segala Ukuran M140 kg 0.3000
3 Minyak bekisting M474 Itr 0.1000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.022


JENIS PEKERJAAN : Pasang bekisting untuk pondasi ( 2x pakai )
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS
A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5200


2 Tukang Kayu L08 Org/hr 0.2600
3 Kepala Tukang Kayu L03 Org/hr 0.0260
4 Mandor L01 Org/hr 0.0260

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m 0.0200


2 Paku Kayu Segala Ukuran M140 kg 0.3000
3 Minyak bekisting M474 Itr 0.1000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.023


JENIS PEKERJAAN : Pasang bekisting untuk sloof
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5200


2 Tukang Kayu L08 Org/hr 0.2600
3 Kepala Tukang Kayu L03 Org/hr 0.0260
4 Mandor L01 Org/hr 0.0260

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m 0.0450


2 Paku Kayu Segala Ukuran M140 kg 0.3000
3 Minyak bekisting M474 Itr 0.1000
JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.024


JENIS PEKERJAAN : Pasang bekisting untuk sloof ( 2x pakai )
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5200


2 Tukang Kayu L08 Org/hr 0.2600
3 Kepala Tukang Kayu L03 Org/hr 0.0260
4 Mandor L01 Org/hr 0.0260

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m 0.0225


2 Paku Kayu Segala Ukuran M140 kg 0.1500
3 Minyak bekisting M474 Itr 0.0500

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.025


JENIS PEKERJAAN : Pasang bekisting untuk kolom
SATUAN PEMBAYARAN : m
PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6600


2 Tukang Kayu L08 Org/hr 0.3300
3 Kepala Tukang Kayu L03 Org/hr 0.0330
4 Mandor L01 Org/hr 0.0330

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m -


2 Paku Kayu Segala Ukuran M140 kg 0.4000
3 Minyak bekisting M474 Itr 0.2000
4 Balok Kayu Kelas III M084 m 0.0150
5 Multiplek 9 mm M217 lbr 0.3500
6 Dolken Kayu 8 cm M089 btg 2.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.026


JENIS PEKERJAAN : Pasang bekisting untuk kolom ( 2x pakai )
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6600


2 Tukang Kayu L08 Org/hr 0.3300
3 Kepala Tukang Kayu L03 Org/hr 0.0330
4 Mandor L01 Org/hr 0.0330
JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m -


2 Paku Kayu Segala Ukuran M140 kg 0.2000
3 Minyak bekisting M474 Itr 0.1000
4 Balok Kayu Kelas III M084 m 0.0075
5 Multiplek 9 mm M217 lbr 0.1750
6 Dolken Kayu 8 cm M089 btg 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.027


JENIS PEKERJAAN : Pasang bekisting untuk balok
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6600


2 Tukang Kayu L08 Org/hr 0.3300
3 Kepala Tukang Kayu L03 Org/hr 0.0330
4 Mandor L01 Org/hr 0.0330

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m -


2 Paku Kayu Segala Ukuran M140 kg 0.4000
3 Minyak bekisting M474 Itr 0.2000
4 Balok Kayu Kelas III M084 m 0.0180
5 Multiplek 9 mm M217 lbr 0.3500
6 Dolken Kayu 8 cm M089 btg 2.0000
JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.028


JENIS PEKERJAAN : Pasang bekisting untuk balok ( 2x pakai )
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6600


2 Tukang Kayu L08 Org/hr 0.3300
3 Kepala Tukang Kayu L03 Org/hr 0.0330
4 Mandor L01 Org/hr 0.0330

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m -


2 Paku Kayu Segala Ukuran M140 kg 0.2000
3 Minyak bekisting M474 Itr 0.1000
4 Balok Kayu Kelas III M084 m 0.0090
5 Multiplek 9 mm M217 lbr 0.1750
6 Dolken Kayu 8 cm M089 btg 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.029


JENIS PEKERJAAN : Pasang bekisting untuk plat lantai
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6600


2 Tukang Kayu L08 Org/hr 0.3300
3 Kepala Tukang Kayu L03 Org/hr 0.0330
4 Mandor L01 Org/hr 0.0330

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m -


2 Paku Kayu Segala Ukuran M140 kg 0.4000
3 Minyak bekisting M474 Itr 0.2000
4 Balok Kayu Kelas III M084 m 0.0150
5 Multiplek 9 mm M217 lbr 0.3500
6 Dolken Kayu 8 cm M089 btg 6.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.030


JENIS PEKERJAAN : Pasang bekisting untuk plat lantai ( 2x pakai )
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6600


2 Tukang Kayu L08 Org/hr 0.3300
3 Kepala Tukang Kayu L03 Org/hr 0.0330
4 Mandor L01 Org/hr 0.0330

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m -


2 Paku Kayu Segala Ukuran M140 kg 0.2000
3 Minyak bekisting M474 Itr 0.1000
4 Balok Kayu Kelas III M084 m 0.0075
5 Multiplek 9 mm M217 lbr 0.1750
6 Dolken Kayu 8 cm M089 btg 3.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.031


JENIS PEKERJAAN : Pasang bekisting untuk dinding
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6600


2 Tukang Kayu L08 Org/hr 0.3300
3 Kepala Tukang Kayu L03 Org/hr 0.0330
4 Mandor L01 Org/hr 0.0330

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m -


2 Paku Kayu Segala Ukuran M140 kg 0.4000
3 Minyak bekisting M474 Itr 0.2000
4 Balok Kayu Kelas III M084 m 0.0200
5 Multiplek 9 mm M217 lbr 0.3500
6 Dolken Kayu 8 cm M089 btg 3.0000
7 Formtie M477 bh 4.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.032


JENIS PEKERJAAN : Pasang bekisting untuk dinding ( 2x pakai )
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6600


2 Tukang Kayu L08 Org/hr 0.3300
3 Kepala Tukang Kayu L03 Org/hr 0.0330
4 Mandor L01 Org/hr 0.0330

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m -


2 Paku Kayu Segala Ukuran M140 kg 0.2000
3 Minyak bekisting M474 Itr 0.1000
4 Balok Kayu Kelas III M084 m 0.0100
5 Multiplek 9 mm M217 lbr 0.1750
6 Dolken Kayu 8 cm M089 btg 1.5000
7 Formtie M477 bh 2.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN


D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.033


JENIS PEKERJAAN : Pasang bekisting untuk tangga
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6600


2 Tukang Kayu L08 Org/hr 0.3300
3 Kepala Tukang Kayu L03 Org/hr 0.0330
4 Mandor L01 Org/hr 0.0330

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m -


2 Paku Kayu Segala Ukuran M140 kg 0.4000
3 Minyak bekisting M474 Itr 0.1500
4 Balok Kayu Kelas III M084 m 0.0150
5 Multiplek 9 mm M217 lbr 0.3500
6 Dolken Kayu 8 cm M089 btg 2.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.034


JENIS PEKERJAAN : Pasang bekisting untuk tangga ( 2x pakai )
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS
A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.6600


2 Tukang Kayu L08 Org/hr 0.3300
3 Kepala Tukang Kayu L03 Org/hr 0.0330
4 Mandor L01 Org/hr 0.0330

JUMLAH HARGA TENAGA

B BAHAN

1 Papan Kayu kelas III M085 m -


2 Paku Kayu Segala Ukuran M140 kg 0.2000
3 Minyak bekisting M474 Itr 0.0750
4 Balok Kayu Kelas III M084 m 0.0075
5 Multiplek 9 mm M217 lbr 0.1750
6 Dolken Kayu 8 cm M089 btg 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

ANALISA HARGA SATUAN

KODE ANALISA : G.035


JENIS PEKERJAAN : Pasang bekisting jembatan untuk pengecoran
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1500


2 Tukang Batu L07 Org/hr 0.0500
3 Kepala Tukang Batu L02 Org/hr 0.0050
4 Mandor L01 Org/hr 0.0080

JUMLAH HARGA TENAGA


B BAHAN

1 Balok Kayu Kelas III M084 m 0.0264


2 Paku Kayu Segala Ukuran M140 kg 0.6000
3 Dolken Kayu 8 cm M089 btg 0.5000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 22,308.00
51,975.00 13,513.50
55,275.00 1,437.15
65,175.00 1,694.55

38,953.20

3,712,500.00 148,500.00
21,780.00 6,534.00
2,574.00 257.40

155,291.40

194,244.60

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)
42,900.00 22,308.00
51,975.00 13,513.50
55,275.00 1,437.15
65,175.00 1,694.55

38,953.20

3,712,500.00 74,250.00
21,780.00 6,534.00
2,574.00 257.40

81,041.40

119,994.60

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 22,308.00
51,975.00 13,513.50
55,275.00 1,437.15
65,175.00 1,694.55

38,953.20

3,712,500.00 167,062.50
21,780.00 6,534.00
2,574.00 257.40
173,853.90

212,807.10

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 22,308.00
51,975.00 13,513.50
55,275.00 1,437.15
65,175.00 1,694.55

38,953.20

3,712,500.00 83,531.25
21,780.00 3,267.00
2,574.00 128.70

86,926.95

125,880.15
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 28,314.00
51,975.00 17,151.75
55,275.00 1,824.08
65,175.00 2,150.78

49,440.60

3,712,500.00 -
21,780.00 8,712.00
2,574.00 514.80
3,305,610.00 49,584.15
124,929.00 43,725.15
27,594.00 55,188.00

157,724.10

207,164.70

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 28,314.00
51,975.00 17,151.75
55,275.00 1,824.08
65,175.00 2,150.78
49,440.60

3,712,500.00 -
21,780.00 4,356.00
2,574.00 257.40
3,305,610.00 24,792.08
124,929.00 21,862.58
27,594.00 27,594.00

78,862.05

128,302.65

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 28,314.00
51,975.00 17,151.75
55,275.00 1,824.08
65,175.00 2,150.78

49,440.60

3,712,500.00 -
21,780.00 8,712.00
2,574.00 514.80
3,305,610.00 59,500.98
124,929.00 43,725.15
27,594.00 55,188.00
167,640.93

217,081.53

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 28,314.00
51,975.00 17,151.75
55,275.00 1,824.08
65,175.00 2,150.78

49,440.60

3,712,500.00 -
21,780.00 4,356.00
2,574.00 257.40
3,305,610.00 29,750.49
124,929.00 21,862.58
27,594.00 27,594.00

83,820.47

133,261.07
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 28,314.00
51,975.00 17,151.75
55,275.00 1,824.08
65,175.00 2,150.78

49,440.60

3,712,500.00 -
21,780.00 8,712.00
2,574.00 514.80
3,305,610.00 49,584.15
124,929.00 43,725.15
27,594.00 165,564.00

268,100.10

317,540.70

Pasang bekisting untuk plat lantai ( 2x pakai )

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 28,314.00
51,975.00 17,151.75
55,275.00 1,824.08
65,175.00 2,150.78

49,440.60

3,712,500.00 -
21,780.00 4,356.00
2,574.00 257.40
3,305,610.00 24,792.08
124,929.00 21,862.58
27,594.00 82,782.00

134,050.05

183,490.65

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 28,314.00
51,975.00 17,151.75
55,275.00 1,824.08
65,175.00 2,150.78

49,440.60

3,712,500.00 -
21,780.00 8,712.00
2,574.00 514.80
3,305,610.00 66,112.20
124,929.00 43,725.15
27,594.00 82,782.00
8,712.00 34,848.00

236,694.15

286,134.75

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 28,314.00
51,975.00 17,151.75
55,275.00 1,824.08
65,175.00 2,150.78

49,440.60

3,712,500.00 -
21,780.00 4,356.00
2,574.00 257.40
3,305,610.00 33,056.10
124,929.00 21,862.58
27,594.00 41,391.00
8,712.00 17,424.00

118,347.08

-
167,787.68

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 28,314.00
51,975.00 17,151.75
55,275.00 1,824.08
65,175.00 2,150.78

49,440.60

3,712,500.00 -
21,780.00 8,712.00
2,574.00 386.10
3,305,610.00 49,584.15
124,929.00 43,725.15
27,594.00 55,188.00

157,595.40

207,036.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 28,314.00
51,975.00 17,151.75
55,275.00 1,824.08
65,175.00 2,150.78

49,440.60

3,712,500.00 -
21,780.00 4,356.00
2,574.00 193.05
3,305,610.00 24,792.08
124,929.00 21,862.58
27,594.00 27,594.00

78,797.70

128,238.30

Pasang bekisting jembatan untuk pengecoran

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 6,435.00
51,975.00 2,598.75
55,275.00 276.38
65,175.00 521.40

9,831.53
3,305,610.00 87,268.10
21,780.00 13,068.00
27,594.00 13,797.00

114,133.10

123,964.63
ANALISA BETON DALAM 1 M3

KODE P E K E R JAAN
G.005 Beton mutu fc'=14,5 Mpa (K175) slump (12 2) cm, w/c = 0,66
G.007 Beton mutu fc'=19,3 Mpa (K225) slump (12 2) cm, w/c = 0,58
G.017 Pembesian dengan besi polos
G.018 Pembesian dengan besi ulir
G.022 Pasang bekisting untuk pondasi ( 2x pakai )
G.024 Pasang bekisting untuk sloof ( 2x pakai )
G.026 Pasang bekisting untuk kolom ( 2x pakai )
G.028 Pasang bekisting untuk balok ( 2x pakai )
G.030 Pasang bekisting untuk plat lantai ( 2x pakai )
G.032 Pasang bekisting untuk dinding ( 2x pakai )
G.034 Pasang bekisting untuk tangga ( 2x pakai )
G.035 Pasang bekisting jembatan untuk pengecoran
Alat bantu pengecoran

1 1 m3 Beton STROUS 20 cm, mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

2 1 m3 Beton PONDASI FOOT PLAT (Type K1), mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

3 1 m3 Beton PONDASI FOOT PLAT (Type K2), mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

4 1 m3 Beton PONDASI FOOT PLAT (Type K3), mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

5 1 m3 Beton PONDASI TANGGA, mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

6 1 m3 Beton SLOOF Struktur 15/25 cm, mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

7 1 m3 Beton SLOOF Praktis 15/20 cm, mutu K.175


1.000 m3
- kg
- kg
- m2
1.000 ls

8 1 m3 Beton KOLOM 30/50 cm (K1), mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

9 1 m3 Beton KOLOM 30/30 cm (K2), mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

10 1 m3 Beton KOLOM 30/30 cm (K3), mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

11 1 m3 Beton KOLOM 25/25 cm (K4), mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

12 1 m3 Beton Kolom PRAKTIS 15/15 cm, mutu K.175


1.000 m3
- kg
- kg
- m2
1.000 ls

13 1 m3 Beton Balok INDUK 30/60 cm, mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

14 1 m3 Beton Balok ANAK 20/30 cm, mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

15 1 m3 Beton Balok KONSOL 30/40 - 30/30 cm, mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

16 1 m3 Beton Balok TEPI / LISPLANK 20/30 cm, mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

17 1 m3 Beton Balok BORDES 15/30 cm, mutu K.225


1.000 m3
- kg
- kg
- m2
1.000 ls

18 1 m3 Beton RING BALK + GEWEL 15/20 cm, mutu K.175


1.000 m3
- kg
- kg
- m2
1.000 ls

19 1 m3 Beton RING 15/15 cm, mutu K.175_Kantin


1.000 m3
- kg
- kg
- m2
1.000 ls

20 1 m3 Beton Balok RING LEUNENG 10/15 cm, mutu K.175


1.000 m3
- kg
- kg
- m2
1.000 ls

21 1 m3 Beton BALOK LEUFEL 15/40 cm, mutu K.175


1.000 m3
- kg
- kg
- m2
1.000 ls

22 1 m3 Beton BALOK LATEI 15/20 cm, mutu K.175


1.000 m3
- kg
- kg
- m2
1.000 ls

23 1 m3 Beton PLAT LANTAI Tbl 12 cm, mutu K.225


Tebal plat 1.000 m3
0.12 - kg
- kg
- m2
1.000 ls

24 1 m3 Beton PLAT ATAP Tbl 10 cm, mutu K.225


Tebal plat 1.000 m3
0.10 - kg
- kg
- m2
1.000 ls

25 1 m3 Beton PLAT LISPLANK Tbl 10 cm, mutu K.225


Tebal plat 1.000 m3
0.10 - kg
- kg
- m2
1.000 ls

26 1 m3 Beton CANOPI Tbl 10 cm, mutu K.175_Induk


Tebal plat 1.000 m3
0.10 - kg
- kg
- m2
1.000 ls

27 1 m3 PLAT MEJA Beton Tbl 10 cm, mutu K.175


Tebal plat 1.000 m3
0.10 - kg
- kg
- m2
1.000 ls

28 1 m3 PLAT TANGGA Tbl 15 cm, mutu K.225


Tebal plat 1.000 m3
0.15 - kg
- kg
- m2
1.000 ls
ANALISA BETON DALAM 1 M3

E K E R JAAN PER HARGA SATUAN


m3 Rp 752,866.76
m3 Rp 810,384.78
kg Rp 11,225.79
kg Rp 15,853.14
m Rp 116,598.90
m Rp 125,880.15
m Rp 202,552.65
m Rp 207,511.07
m Rp 257,740.65
m Rp 223,475.18
m Rp 183,925.80
m Rp 123,964.63
m3 Rp -

Kode Harga Satuan


Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting G.022 Rp 116,598.90
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting G.022 Rp 116,598.90
Alat bantu Rp -
Jumlah
Pembulatan

Kode Harga Satuan


Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting G.022 Rp 116,598.90
Alat bantu Rp -
Jumlah
Pembulatan

Kode Harga Satuan


Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting G.022 Rp 116,598.90
Alat bantu Rp -
Jumlah
Pembulatan

Kode Harga Satuan


Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting G.022 Rp 116,598.90
Alat bantu Rp -
Jumlah
Pembulatan

Kode Harga Satuan


Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting G.024 Rp 125,880.15
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.005 Rp 752,866.76
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting G.024 Rp 125,880.15
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Begisting 9 mm G.026 Rp 202,552.65
Alat bantu Rp -
Jumlah
Pembulatan

Kode Harga Satuan


Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Begisting 9 mm G.026 Rp 202,552.65
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Begisting 9 mm G.026 Rp 202,552.65
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Begisting 9 mm G.026 Rp 202,552.65
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.005 Rp 752,866.76
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting G.026 Rp 202,552.65
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting (9 mm) G.028 Rp 207,511.07
Alat bantu Rp -
Jumlah
Pembulatan

Kode Harga Satuan


Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting (9 mm) G.028 Rp 207,511.07
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting (9 mm) G.028 Rp 207,511.07
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting (9 mm) G.028 Rp 207,511.07
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting (9 mm) G.028 Rp 207,511.07
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.005 Rp 752,866.76
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting (9 mm) G.028 Rp 207,511.07
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.005 Rp 752,866.76
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting (9 mm) G.028 Rp 207,511.07
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.005 Rp 752,866.76
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting (9 mm) G.028 Rp 207,511.07
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.005 Rp 752,866.76
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting (9 mm) G.028 Rp 207,511.07
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.005 Rp 752,866.76
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos G.017 Rp 11,225.79
Bekisting (9 mm) G.028 Rp 207,511.07
Alat bantu Rp -
Jumlah
Pembulatan
Kode Harga Satuan
Mengecor G.007 Rp 810,384.78
Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos (Konvensional) G.017 Rp 11,225.79
Bekisting (12 mm) G.030 Rp 257,740.65
Alat bantu Rp -
Jumlah
Pembulatan

Mengecor G.007 Rp 810,384.78


Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos (Konvensional) G.017 Rp 11,225.79
Bekisting G.030 Rp 257,740.65
Alat bantu Rp -
Jumlah
Pembulatan

Mengecor G.007 Rp 810,384.78


Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos (Konvensional) G.017 Rp 11,225.79
Bekisting G.030 Rp 257,740.65
Alat bantu Rp -
Jumlah
Pembulatan

Mengecor G.005 Rp 752,866.76


Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos (Konvensional) G.017 Rp 11,225.79
Bekisting G.030 Rp 257,740.65
Alat bantu Rp -
Jumlah
Pembulatan

Mengecor G.005 Rp 752,866.76


Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos (Konvensional) G.017 Rp 11,225.79
Bekisting G.030 Rp 257,740.65
Alat bantu Rp -
Jumlah
Pembulatan

Mengecor G.007 Rp 810,384.78


Pembesian Ulir G.018 Rp 15,853.14
Pembesian Polos (Konvensional) G.017 Rp 11,225.79
Bekisting G.034 Rp 183,925.80
Alat bantu Rp -
Jumlah
Pembulatan
Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00
Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00

Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00

Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00

Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00

Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00
Jumlah
Rp 752,866.76
Rp -
Rp -
Rp -
Rp -
Rp 752,866.76
Rp 752,800.00
Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00

Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00
Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00
Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00
Jumlah
Rp 752,866.76
Rp -
Rp -
Rp -
Rp -
Rp 752,866.76
Rp 752,800.00
Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00

Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00
Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00
Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00
Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00
Jumlah
Rp 752,866.76
Rp -
Rp -
Rp -
Rp -
Rp 752,866.76
Rp 752,800.00
Jumlah
Rp 752,866.76
Rp -
Rp -
Rp -
Rp -
Rp 752,866.76
Rp 752,800.00
Jumlah
Rp 752,866.76
Rp -
Rp -
Rp -
Rp -
Rp 752,866.76
Rp 752,800.00
Jumlah
Rp 752,866.76
Rp -
Rp -
Rp -
Rp -
Rp 752,866.76
Rp 752,800.00
Jumlah
Rp 752,866.76
Rp -
Rp -
Rp -
Rp -
Rp 752,866.76
Rp 752,800.00
Jumlah
Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00

Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00

Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00

Rp 752,866.76
Rp -
Rp -
Rp -
Rp -
Rp 752,866.76
Rp 752,800.00

Rp 752,866.76
Rp -
Rp -
Rp -
Rp -
Rp 752,866.76
Rp 752,800.00

Rp 810,384.78
Rp -
Rp -
Rp -
Rp -
Rp 810,384.78
Rp 810,300.00
ANALISA HARGA SATUAN

KODE ANALISA : H.003


JENIS PEKERJAAN : Pasang atap genteng karangpilang ex. Malang
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1500


2 Tukang Kayu L08 Org/hr 0.0750
3 Kepala Tukang Kayu L03 Org/hr 0.0080
4 Mandor L01 Org/hr 0.0080

JUMLAH HARGA TENAGA

B BAHAN

1 Genteng Karang Pilang ex. Malang M151 bh 25.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasang atap genteng karangpilang ex. Malang

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 6,435.00
51,975.00 3,898.13
55,275.00 442.20
65,175.00 521.40

11,296.73

2,250.00 56,250.00

56,250.00

67,546.73
ANALISA HARGA SATUAN

KODE ANALISA : H.014


JENIS PEKERJAAN : Pasang atap genteng beton biasa
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2000


2 Tukang Kayu L08 Org/hr 0.1000
3 Kepala Tukang Kayu L03 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0100

JUMLAH HARGA TENAGA

B BAHAN

1 Genteng Beton biasa M154 bh 25.0000


2 Paku Kayu Segala Ukuran M140 kg 0.0300

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 8,580.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 651.75

14,982.00

3,000.00 75,000.00
21,780.00 653.40

75,653.40

90,635.40
ANALISA HARGA SATUAN

KODE ANALISA : H.021


JENIS PEKERJAAN : Pasang bubung genteng beton Monier
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.4000


2 Tukang Kayu L08 Org/hr 0.2000
3 Kepala Tukang Kayu L03 Org/hr 0.0200
4 Mandor L01 Org/hr 0.0020

JUMLAH HARGA TENAGA

B BAHAN

1 Bubung Genteng Beton biasa M161 bh 3.5000


2 Paku Kayu Segala Ukuran M140 kg 0.0500
3 Portland Cement (PC) M037 kg 10.8000
4 Pasir Pasang M002 m 0.0320
5 Portland Cement (PC) Warna M039 kg 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 17,160.00
51,975.00 10,395.00
55,275.00 1,105.50
65,175.00 130.35

28,790.85

5,000.00 17,500.00
21,780.00 1,089.00
1,350.00 14,580.00
90,000.00 2,880.00
8,118.00 8,118.00

44,167.00

72,957.85
ANALISA HARGA SATUAN

KODE ANALISA : H.050


JENIS PEKERJAAN : Pasang lapisan aluminium foil / sesalation
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1500


2 Tukang Kayu L08 Org/hr 0.0500
3 Kepala Tukang Kayu L03 Org/hr 0.0050
4 Mandor L01 Org/hr 0.0080

JUMLAH HARGA TENAGA

B BAHAN

1 Aluminium Foil/Sesalation M131 m 1.0500

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 6,435.00
51,975.00 2,598.75
55,275.00 276.38
65,175.00 521.40

9,831.53

30,901.50 32,446.58

32,446.58

42,278.10
ANALISA HARGA SATUAN

KODE ANALISA : I.046


JENIS PEKERJAAN : Langit-langit tripleks (120x240) cm, tebal 4 mm
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1000


2 Tukang Kayu L08 Org/hr 0.1000
3 Kepala Tukang Kayu L03 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Triplek 4 mm M215 lbr 0.3750


2 Paku Tripleks M140 kg 0.0300

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Langit-langit tripleks (120x240) cm, tebal 4 mm

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 4,290.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 325.88

10,366.13

70,380.00 26,392.50
21,780.00 653.40

27,045.90

37,412.03
ANALISA HARGA SATUAN

KODE ANALISA : I.049


JENIS PEKERJAAN : List langit-langit kayu profil
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0500


2 Tukang Kayu L08 Org/hr 0.0500
3 Kepala Tukang Kayu L03 Org/hr 0.0050
4 Mandor L01 Org/hr 0.0030

JUMLAH HARGA TENAGA

B BAHAN

1 List Kayu Profil M090 m 1.0500


2 Paku Kayu Segala Ukuran M140 kg 0.0100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 2,145.00
51,975.00 2,598.75
55,275.00 276.38
65,175.00 195.53

5,215.65

7,821.00 8,212.05
21,780.00 217.80

8,429.85

13,645.50
ANALISA HARGA SATUAN

KODE ANALISA : I.050


JENIS PEKERJAAN : List langit-langit gypsum
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0500


2 Tukang Kayu L08 Org/hr 0.0500
3 Kepala Tukang Kayu L03 Org/hr 0.0050
4 Mandor L01 Org/hr 0.0030

JUMLAH HARGA TENAGA

B BAHAN

1 List Gypsum M211 m' 1.1000


2 Lem Kayu M422 kg 0.0500

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 2,145.00
51,975.00 2,598.75
55,275.00 276.38
65,175.00 195.53

5,215.65

19,899.00 21,888.90
29,502.00 1,475.10

23,364.00

28,579.65
ANALISA HARGA SATUAN

KODE ANALISA : I.054


JENIS PEKERJAAN : Langit-langit Kalsiboard 9mm + Rangka galvalum
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1500


2 Tukang Kayu L08 Org/hr 0.2000
3 Kepala Tukang Kayu L03 Org/hr 0.0450
4 Mandor L01 Org/hr 0.0750

JUMLAH HARGA TENAGA

B BAHAN

1 Metal furing M494 m' 3.6000


2 Kawat seng polos M495 kg 0.1500
3 Ramset / Dynabolt M496 bh 1.0000
4 Kalsiboard 9 mm M492 lbr 0.3500

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Langit-langit Kalsiboard 9mm + Rangka galvalum

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 6,435.00
51,975.00 10,395.00
55,275.00 2,487.38
65,175.00 4,888.13

24,205.50

13,050.00 46,980.00
21,375.00 3,206.25
4,500.00 4,500.00
143,923.50 50,373.23

105,059.48

129,264.98
ANALISA HARGA SATUAN

KODE ANALISA : I.055


JENIS PEKERJAAN : Dinding partisi gypsum 2 x 12 mm, rangka galvalum
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1500


2 Tukang Kayu L08 Org/hr 0.2000
3 Kepala Tukang Kayu L03 Org/hr 0.0450
4 Mandor L01 Org/hr 0.0750

JUMLAH HARGA TENAGA

B BAHAN

1 Stud Track 7,6 M499 m' 3.6000


2 Ramset / Dynabolt M496 Bh 1.0000
3 Gypsum Board 12 mm M500 lbr 0.7000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Dinding partisi gypsum 2 x 12 mm, rangka galvalum

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 6,435.00
51,975.00 10,395.00
55,275.00 2,487.38
65,175.00 4,888.13

24,205.50

22,500.00 81,000.00
4,500.00 4,500.00
76,500.00 53,550.00

139,050.00

163,255.50
ANALISA HARGA SATUAN

KODE ANALISA : I.056


JENIS PEKERJAAN : Plafond Papan Grill 3/30 cm (Uk.25x25 cm) + Politur
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0700


2 Tukang Kayu L08 Org/hr 0.1000
3 Kepala Tukang Kayu L03 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0035

JUMLAH HARGA TENAGA

B BAHAN

1 Papan (3x30) cm M083 m3 0.0400


2 Paku Kayu Segala Ukuran M140 kg 0.0200
3 Politur Jadi M420 ltr 0.6720
4 Kertas Gosok M401 lbr 2.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Plafond Papan Grill 3/30 cm (Uk.25x25 cm) + Politur

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 3,003.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 228.11

8,981.36

11,519,550.00 460,782.00
21,780.00 435.60
73,237.50 49,215.60
4,455.00 8,910.00

519,343.20

528,324.56
ANALISA HARGA SATUAN

KODE ANALISA : I.025


JENIS PEKERJAAN : Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka ka
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1800


2 Tukang Kayu L08 Org/hr 0.3200
3 Kepala Tukang Kayu L03 Org/hr 0.0320
4 Mandor L01 Org/hr 0.0090

JUMLAH HARGA TENAGA

B BAHAN

1 Usuk 5/7 M061 m 0.0120


2 Paku Kayu Segala Ukuran M140 kg 0.0600
3 Asbes (1,00 x 1,00) m x 3,5 mm M206 lbr 1.1000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka kayu meranti

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 7,722.00
51,975.00 16,632.00
55,275.00 1,768.80
65,175.00 586.58

26,709.38

4,958,415.00 59,500.98
21,780.00 1,306.80
16,038.00 17,641.80

78,449.58

105,158.96
ANALISA HARGA SATUAN

KODE ANALISA : I.057


JENIS PEKERJAAN : Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka ka
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1800


2 Tukang Kayu L08 Org/hr 0.3200
3 Kepala Tukang Kayu L03 Org/hr 0.0320
4 Mandor L01 Org/hr 0.0090

JUMLAH HARGA TENAGA

B BAHAN

1 Paku Kayu Segala Ukuran M140 kg 0.0600


2 Asbes (1,00 x 1,00) m x 3,5 mm M206 lbr 1.1000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka kayu lama

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 7,722.00
51,975.00 16,632.00
55,275.00 1,768.80
65,175.00 586.58

26,709.38

21,780.00 1,306.80
16,038.00 17,641.80

18,948.60

45,657.98
ANALISA HARGA SATUAN

KODE ANALISA : J.003


JENIS PEKERJAAN : Pasang kloset jongkok lux
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.0000


2 Tukang Batu L07 Org/hr 1.5000
3 Kepala Tukang Batu L02 Org/hr 1.5000
4 Mandor L01 Org/hr 0.1600

JUMLAH HARGA TENAGA

B BAHAN

1 Kloset Jongkok Lux M232 Unit 1.0000


2 Portland Cement (PC) M037 kg 6.0000
3 Pasir Pasang M002 m 0.0100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 42,900.00
51,975.00 77,962.50
55,275.00 82,912.50
65,175.00 10,428.00

214,203.00

313,038.00 313,038.00
1,350.00 8,100.00
90,000.00 900.00

322,038.00

536,241.00
ANALISA HARGA SATUAN

KODE ANALISA : J.008


JENIS PEKERJAAN : Pasang wastafel lux
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.2000


2 Tukang Batu L07 Org/hr 1.4500
3 Kepala Tukang Batu L02 Org/hr 0.1500
4 Mandor L01 Org/hr 0.1000

JUMLAH HARGA TENAGA

B BAHAN

1 Wastafel Komplit (Kran + Sipon) Lux M247 Unit 1.0000


2 Perlengkapan 12.00%
3 Portland Cement (PC) M037 kg 6.0000
4 Pasir Pasang M002 m 0.0100

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 51,480.00
51,975.00 75,363.75
55,275.00 8,291.25
65,175.00 6,517.50

141,652.50

1,327,630.50 1,327,630.50
1,327,630.50 159,315.66
1,350.00 8,100.00
90,000.00 900.00

1,495,946.16

1,637,598.66
ANALISA HARGA SATUAN

KODE ANALISA : J.009


JENIS PEKERJAAN : Pasang tempat sabun keramik
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100


2 Tukang Batu L07 Org/hr 0.1000
3 Kepala Tukang Batu L02 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Tempat Sabun Keramik M249 bh 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 429.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 325.88

6,505.13

31,383.00 31,383.00

31,383.00

37,888.13
ANALISA HARGA SATUAN

KODE ANALISA : J.028


JENIS PEKERJAAN : Pasang bak kontrol pasangan batu bata
ukuran (45 x 45) tinggi 50 cm
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 1.4200


2 Tukang Batu L07 Org/hr 0.4730
3 Kepala Tukang Batu L02 Org/hr 0.0470
4 Mandor L01 Org/hr 0.0710

JUMLAH HARGA TENAGA

B BAHAN

1 Bata Merah M022 bh 112.5000


2 Portland Cement (PC) M037 kg 77.0000
3 Pasir Pasang M002 m 0.1300
4 Stenslah/batu pecah tangan 2/3 M014 m 0.0200
5 Besi Beton Polos M112 kg 2.6000
6 Pasir Cor M004 m 0.0900

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 60,918.00
51,975.00 24,584.18
55,275.00 2,597.93
65,175.00 4,627.43

92,727.53

570.00 64,125.00
1,350.00 103,950.00
90,000.00 11,700.00
215,000.00 4,300.00
9,750.00 25,350.00
130,000.00 11,700.00

221,125.00

313,852.53
ANALISA HARGA SATUAN

KODE ANALISA : J.030


JENIS PEKERJAAN : Pasang pipa galvanis, diameter 1/2"
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0540


2 Tukang Batu L07 Org/hr 0.0900
3 Kepala Tukang Batu L02 Org/hr 0.0090
4 Mandor L01 Org/hr 0.0270

JUMLAH HARGA TENAGA

B BAHAN

1 Pipa Galvanis 1/2" tebal 1.8 mm M376 m 1.2000


2 Perlengkapan 35.00%

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 2,316.60
51,975.00 4,677.75
55,275.00 497.48
65,175.00 1,759.73

9,251.55

33,547.50 40,257.00
33,547.50 11,741.63

51,998.63

61,250.18
ANALISA HARGA SATUAN

KODE ANALISA : J.031


JENIS PEKERJAAN : Pasang pipa galvanis, diameter 3/4"
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0540


2 Tukang Batu L07 Org/hr 0.0900
3 Kepala Tukang Batu L02 Org/hr 0.0090
4 Mandor L01 Org/hr 0.0270

JUMLAH HARGA TENAGA

B BAHAN

1 Pipa Galvanis 3/4" tebal 1.8 mm M377 m 1.200


2 Perlengkapan 35.00%

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 2,316.60
51,975.00 4,677.75
55,275.00 497.48
65,175.00 1,759.73

9,251.55

43,470.00 52,164.00
43,470.00 15,214.50

67,378.50

76,630.05
ANALISA HARGA SATUAN

KODE ANALISA : J.042


JENIS PEKERJAAN : Pasang pipa PVC tipe AW, diameter 2"
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0540


2 Tukang Batu L07 Org/hr 0.0900
3 Kepala Tukang Batu L02 Org/hr 0.0090
4 Mandor L01 Org/hr 0.0027

JUMLAH HARGA TENAGA

B BAHAN

1 Pipa PVC tipe AW 2" M338 m 1.2000


2 Perlengkapan 35.00%

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 2,316.60
51,975.00 4,677.75
55,275.00 497.48
65,175.00 175.97

7,667.80

25,231.50 30,277.80
25,231.50 8,831.03

39,108.83

46,776.62
ANALISA HARGA SATUAN

KODE ANALISA : J.045


JENIS PEKERJAAN : Pasang pipa PVC tipe AW, diameter 4"
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0810


2 Tukang Batu L07 Org/hr 0.1350
3 Kepala Tukang Batu L02 Org/hr 0.0135
4 Mandor L01 Org/hr 0.0041

JUMLAH HARGA TENAGA

B BAHAN

1 Pipa PVC tipe AW 4 " M341 m 1.2000


2 Perlengkapan 35.00%

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 3,474.90
51,975.00 7,016.63
55,275.00 746.21
65,175.00 267.22

11,504.96

71,536.50 85,843.80
71,536.50 25,037.78

110,881.58

122,386.53
ANALISA HARGA SATUAN

KODE ANALISA : J.046


JENIS PEKERJAAN : Pasang pipa PVC tipe AW, diameter 6"
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1215


2 Tukang Batu L07 Org/hr 0.2025
3 Kepala Tukang Batu L02 Org/hr 0.0203
4 Mandor L01 Org/hr 0.0062

JUMLAH HARGA TENAGA

B BAHAN

1 Pipa PVC tipe AW 6 " M342 m 1.2000


2 Perlengkapan 35.00%

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 5,212.35
51,975.00 10,524.94
55,275.00 1,122.08
65,175.00 400.83

17,260.20

124,551.00 149,461.20
124,551.00 43,592.85

193,054.05

210,314.25
ANALISA HARGA SATUAN

KODE ANALISA : J.066


JENIS PEKERJAAN : Pasang kran diameter 1/2"
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100


2 Tukang Batu L07 Org/hr 0.1000
3 Kepala Tukang Batu L02 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Kran Air 1/2 " M235 bh 1.0000


2 Seal Tape / TBA M481 bh 0.0250

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 429.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 325.88

6,505.13

39,303.00 39,303.00
2,079.00 51.98

39,354.98

45,860.10
ANALISA HARGA SATUAN

KODE ANALISA : J.068


JENIS PEKERJAAN : Pasang Afor Stainless Steel
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100


2 Tukang Batu L07 Org/hr 0.1000
3 Kepala Tukang Batu L02 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Afor Stainless M250 bh 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 429.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 325.88

6,505.13

53,262.00 53,262.00

53,262.00

59,767.13
ANALISA HARGA SATUAN

KODE ANALISA : J.073


JENIS PEKERJAAN : Pasang pipa Staenless steel, diameter 2"
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1080


2 Tukang Batu L07 Org/hr 0.1800
3 Kepala Tukang Batu L02 Org/hr 0.0180
4 Mandor L01 Org/hr 0.0054

JUMLAH HARGA TENAGA

B BAHAN

1 Pipa stainless steel 2" M498 - 1.2000


2 Perlengkapan 35.00%

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 4,633.20
51,975.00 9,355.50
55,275.00 994.95
65,175.00 351.95

15,335.60

112,500.00 135,000.00
112,500.00 39,375.00

174,375.00

189,710.60
ANALISA HARGA SATUAN

KODE ANALISA : J.005


JENIS PEKERJAAN : Pasang kloset duduk lux
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 3.3000


2 Tukang Batu L07 Org/hr 1.1000
3 Kepala Tukang Batu L02 Org/hr 0.0010
4 Mandor L01 Org/hr 0.1600

JUMLAH HARGA TENAGA

B BAHAN

1 Kloset Duduk Lux M233 Unit 1.0000


2 Perlengkapan 6.00%

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 141,570.00
51,975.00 57,172.50
55,275.00 55.28
65,175.00 10,428.00

209,225.78

1,603,948.50 1,603,948.50
1,603,948.50 96,236.91

1,700,185.41

1,909,411.19
ANALISA HARGA SATUAN

KODE ANALISA : K.001


JENIS PEKERJAAN : Pasang besi profil
SATUAN PEMBAYARAN : kg

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0610


2 Tukang Besi/Baja L09 Org/hr 0.0061
3 Kepala Tukang Besi L04 Org/hr 0.0061
4 Mandor L01 Org/hr 0.0003

JUMLAH HARGA TENAGA

B BAHAN

1 Baja Profil M116 kg 1.1500


2 Solar Industri M483 Itr 0.0100
3 Minyak Pelumas M484 Itr 0.0010
4 Elektroda M473 kg 0.0200

JUMLAH HARGA BAHAN

C PERALATAN

1 Sewa Mesin Las (150A) E05 hari 0.0160

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 2,616.90
51,975.00 317.05
55,275.00 337.18
65,175.00 19.55

3,290.68

15,345.00 17,646.75
5,400.00 54.00
45,738.00 45.74
35,046.00 700.92

18,447.41

400,000.00 6,400.00

6,400.00

28,138.09
ANALISA HARGA SATUAN

KODE ANALISA : K.002


JENIS PEKERJAAN : Pasang rangka kuda-kuda baja WF
SATUAN PEMBAYARAN : kg

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0610


2 Tukang Besi/Baja L09 Org/hr 0.0061
3 Kepala Tukang Besi L04 Org/hr 0.0061
4 Mandor L01 Org/hr 0.0003

JUMLAH HARGA TENAGA

B BAHAN

1 Baja Profil M116 kg 1.1500


2 Solar Industri M483 Itr 0.0100
3 Minyak Pelumas M484 Itr 0.0010
4 Elektroda M473 kg 0.0200

JUMLAH HARGA BAHAN

C PERALATAN

1 Sewa Mesin Las (150A) E05 hari 0.0160

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 2,616.90
51,975.00 317.05
55,275.00 337.18
65,175.00 19.55

3,290.68

15,345.00 17,646.75
5,400.00 54.00
45,738.00 45.74
35,046.00 700.92

18,447.41

400,000.00 6,400.00

6,400.00

28,138.09
ANALISA HARGA SATUAN

KODE ANALISA : K.003


JENIS PEKERJAAN : Pemasangan baut anker baja
SATUAN PEMBAYARAN : kg

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200


2 Tukang Besi/Baja L09 Org/hr 0.0300
3 Kepala Tukang Besi L04 Org/hr
4 Mandor L01 Org/hr

JUMLAH HARGA TENAGA

B BAHAN

1 Angker Bar / Dynabolt M117 kg 1.0500

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 858.00
51,975.00 1,559.25
55,275.00 -
65,175.00 -

2,417.25

17,127.00 17,983.35

17,983.35

20,400.60
ANALISA HARGA SATUAN

KODE ANALISA : K.004


JENIS PEKERJAAN : Ikatan angin/Trekstang
SATUAN PEMBAYARAN : kg

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0610


2 Tukang Besi/Baja L09 Org/hr 0.0061
3 Kepala Tukang Besi L04 Org/hr 0.0061
4 Mandor L01 Org/hr 0.0003

JUMLAH HARGA TENAGA

B BAHAN

1 Besi Beton Polos M112 kg 1.0500


2 Solar Industri M483 Itr 0.0100
3 Minyak Pelumas M484 Itr 0.0010
4 Elektroda M473 kg 0.0200

JUMLAH HARGA BAHAN

C PERALATAN

1 Sewa Mesin Las (150A) E05 hari 0.0160

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 2,616.90
51,975.00 317.05
55,275.00 337.18
65,175.00 19.55

3,290.68

9,750.00 10,237.50
5,400.00 54.00
45,738.00 45.74
35,046.00 700.92

11,038.16

400,000.00 6,400.00

6,400.00

20,728.84
ANALISA HARGA SATUAN

KODE ANALISA : K.005


JENIS PEKERJAAN : Plendes
SATUAN PEMBAYARAN : kg

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0610


2 Tukang Besi/Baja L09 Org/hr 0.0061
3 Kepala Tukang Besi L04 Org/hr 0.0061
4 Mandor L01 Org/hr 0.0003

JUMLAH HARGA TENAGA

B BAHAN

1 Baja Profil M116 kg 1.1500


2 Solar Industri M483 Itr 0.0100
3 Minyak Pelumas M484 Itr 0.0010
4 Elektroda M473 kg 0.0200

JUMLAH HARGA BAHAN

C PERALATAN

1 Sewa Mesin Las (150A) E05 hari 0.0160

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 2,616.90
51,975.00 317.05
55,275.00 337.18
65,175.00 19.55

3,290.68

15,345.00 17,646.75
5,400.00 54.00
45,738.00 45.74
35,046.00 700.92

18,447.41

400,000.00 6,400.00

6,400.00

28,138.09
ANALISA HARGA SATUAN

KODE ANALISA : K.012


JENIS PEKERJAAN : Pasang Kusen Alluminium Coklat
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0430


2 Tukang Besi/Baja L09 Org/hr 0.0430
3 Kepala Tukang Besi L04 Org/hr 0.0043
4 Mandor L01 Org/hr 0.0021

JUMLAH HARGA TENAGA

B BAHAN

1 Profil Aluminium Coklat M126 m 1.1000


2 Sekrup segala ukuran M145 bh 2.0000
3 Sealant M148.b tube 0.0600

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 1,844.70
51,975.00 2,234.93
55,275.00 237.68
65,175.00 136.87

4,454.18

107,019.00 117,720.90
396.00 792.00
28,444.50 1,706.67

120,219.57

124,673.75
ANALISA HARGA SATUAN

KODE ANALISA : K.014


JENIS PEKERJAAN : Pasang Pintu Kaca Rangka Aluminium Coklat
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0850


2 Tukang Besi/Baja L09 Org/hr 0.0850
3 Kepala Tukang Besi L04 Org/hr 0.0090
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Profil Aluminium Coklat M126 m 4.4000


2 Profil Kaca M148.d m 4.5000
3 Sealant M148.b tube 0.2700

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) Daun Pintu 80


Daun Jendela (
Daun Jendela BV 60
Pasang Pintu Kaca Rangka Aluminium Coklat

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 3,646.50
51,975.00 4,417.88
55,275.00 497.48
65,175.00 325.88

8,887.73

107,019.00 470,883.60
11,088.00 49,896.00
28,444.50 7,680.02

528,459.62

-
1 m2 537,347.34
Daun Pintu 80 x 210 cm 902,743.53
Daun Jendela (0,65 m2) 349,275.77
Daun Jendela BV 60 x 50 cm 161,204.20
ANALISA HARGA SATUAN

KODE ANALISA : K.032


JENIS PEKERJAAN : Pasang Atap Baja Ringan untuk Penutup Atap Genteng
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.7500


2 Tukang Besi/Baja L09 Org/hr 0.5000
3 Kepala Tukang Besi L04 Org/hr 0.0500
4 Mandor L01 Org/hr 0.0500

JUMLAH HARGA TENAGA

B BAHAN

1 Baja Ringan M132 kg 5.4912


2 Besi Strip / Plat Plendes M114 kg 0.4212
3 Baut Segala Ukuran M146 kg 0.2521
4 Angker Bar / Dynabolt M117 kg 0.1411

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasang Atap Baja Ringan untuk Penutup Atap Genteng

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 32,175.00
51,975.00 25,987.50
55,275.00 2,763.75
65,175.00 3,258.75

64,185.00

40,095.00 220,169.66
9,702.00 4,086.48
19,206.00 4,840.91
17,127.00 2,416.17

231,513.23

295,698.23
ANALISA HARGA SATUAN

KODE ANALISA : K.033


JENIS PEKERJAAN : Pasang Atap Baja Ringan untuk Penutup Atap Asbes Ge
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.7500


2 Tukang Besi/Baja L09 Org/hr 0.5000
3 Kepala Tukang Besi L04 Org/hr 0.0500
4 Mandor L01 Org/hr 0.0500

JUMLAH HARGA TENAGA

B BAHAN

1 Baja Ringan M132 kg 4.7303


2 Besi Strip / Plat Plendes M114 kg 0.4212
3 Baut Segala Ukuran M146 kg 0.2521
4 Angker Bar / Dynabolt M117 kg 0.1411

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasang Atap Baja Ringan untuk Penutup Atap Asbes Gelombang

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 32,175.00
51,975.00 25,987.50
55,275.00 2,763.75
65,175.00 3,258.75

64,185.00

40,095.00 189,662.82
9,702.00 4,086.48
19,206.00 4,840.91
17,127.00 2,416.17

201,006.39

265,191.39
ANALISA HARGA SATUAN

KODE ANALISA : K.034


JENIS PEKERJAAN : Pasang rangka Plafon Metal Furing
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0800


2 Tukang Besi/Baja L09 Org/hr 0.8000
3 Kepala Tukang Besi L04 Org/hr 0.0800
4 Mandor L01 Org/hr 0.0040

JUMLAH HARGA TENAGA

B BAHAN

1 Baja Ringan M132 kg 11.5374


2 Baja Profil M116 kg 1.1092
3 Baja Clips & Adjustable M116 kg 1.2000

4 Gypsum Board 9 mm M213 lbr 0.3500

JUMLAH HARGA BAHAN

C TOTAL

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 3,432.00
51,975.00 41,580.00
55,275.00 4,422.00
65,175.00 260.70

49,694.70

40,095.00 462,593.02
15,345.00 17,020.74
15,345.00 18,414.00
498,027.76
9.50 52,423.97
75,339.00 26,368.65

78,792.62

128,487.32
ANALISA HARGA SATUAN

KODE ANALISA : K.038


JENIS PEKERJAAN : 1 m2 Pasang Rangka atap (Usuk+reng Zincalume)
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.1000


2 Tukang Besi/Baja L09 Org/hr 0.1000
3 Kepala Tukang Besi L04 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Usuk Canal C 75. 0.75 M501 m 3.0000


2 Reng Purlin R 36.055 M502 m 5.0000
3 Baut M503 m 30.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


1 m2 Pasang Rangka atap (Usuk+reng Zincalume)

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 4,290.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 325.88

10,366.13

13,500.00 40,500.00
9,000.00 45,000.00
90.00 2,700.00

88,200.00

98,566.13
ANALISA HARGA SATUAN

KODE ANALISA : L.002


JENIS PEKERJAAN : Pasang kunci tanam biasa
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100


2 Tukang Kayu L08 Org/hr 0.5000
3 Kepala Tukang Kayu L03 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Kunci Tanam M254 bh 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 429.00
51,975.00 25,987.50
55,275.00 552.75
65,175.00 325.88

27,295.13

110,943.00 110,943.00

110,943.00

138,238.13
ANALISA HARGA SATUAN

KODE ANALISA : L.003


JENIS PEKERJAAN : Pasang kunci tanam kamar mandi
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0050


2 Tukang Kayu L08 Org/hr 0.5000
3 Kepala Tukang Kayu L03 Org/hr 0.0050
4 Mandor L01 Org/hr 0.0025

JUMLAH HARGA TENAGA

B BAHAN

1 Kunci Pintu Kamar Mandi M255 bh 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 214.50
51,975.00 25,987.50
55,275.00 276.38
65,175.00 162.94

26,641.31

91,080.00 91,080.00

91,080.00

117,721.31
ANALISA HARGA SATUAN

KODE ANALISA : L.007


JENIS PEKERJAAN : Pasang engsel pintu
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0150


2 Tukang Kayu L08 Org/hr 0.1500
3 Kepala Tukang Kayu L03 Org/hr 0.0150
4 Mandor L01 Org/hr 0.0008

JUMLAH HARGA TENAGA

B BAHAN

1 Engsel Pintu M257 bh 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 643.50
51,975.00 7,796.25
55,275.00 829.13
65,175.00 48.88

9,317.76

31,482.00 31,482.00

31,482.00

-
1 Pasang 40,799.76
1 Buah 20,399.88
ANALISA HARGA SATUAN

KODE ANALISA : L.010


JENIS PEKERJAAN : Pasang grendel jendela
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0100


2 Tukang Kayu L08 Org/hr 0.1000
3 Kepala Tukang Kayu L03 Org/hr 0.0100
4 Mandor L01 Org/hr 0.0005

JUMLAH HARGA TENAGA

B BAHAN

1 Grendel Jendela M263 bh 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 429.00
51,975.00 5,197.50
55,275.00 552.75
65,175.00 32.59

6,211.84

12,177.00 12,177.00

12,177.00

18,388.84
ANALISA HARGA SATUAN

KODE ANALISA : L.019


JENIS PEKERJAAN : Pasang kaca polos, tebal 5 mm
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0150


2 Tukang Kayu L08 Org/hr 0.1500
3 Kepala Tukang Kayu L03 Org/hr 0.0150
4 Mandor L01 Org/hr 0.0008

JUMLAH HARGA TENAGA

B BAHAN

1 Kaca Polos tebal 5 mm M271 m 1.1000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 643.50
51,975.00 7,796.25
55,275.00 829.13
65,175.00 48.88

9,317.76

120,204.00 132,224.40

132,224.40

141,542.16
ANALISA HARGA SATUAN

KODE ANALISA : L.027


JENIS PEKERJAAN : Pasang kaca cermin, tebal 6 mm
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0150


2 Tukang Kayu L08 Org/hr 0.1500
3 Kepala Tukang Kayu L03 Org/hr 0.0150
4 Mandor L01 Org/hr 0.0008

JUMLAH HARGA TENAGA

B BAHAN

1 Kaca Cermin tebal 6 mm M279 m 1.1000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 643.50
51,975.00 7,796.25
55,275.00 829.13
65,175.00 48.88

9,317.76

250,668.00 275,734.80

275,734.80

285,052.56
ANALISA HARGA SATUAN

KODE ANALISA : L.037


JENIS PEKERJAAN : Pasang casement
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200


2 Tukang Kayu L08 Org/hr 0.2000
3 Kepala Tukang Kayu L03 Org/hr 0.0200
4 Mandor L01 Org/hr 0.0100

JUMLAH HARGA TENAGA

B BAHAN

1 Engsel casement 15 " M505 1.00 1.1000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 858.00
51,975.00 10,395.00
55,275.00 1,105.50
65,175.00 651.75

13,010.25

29,250.00 32,175.00

32,175.00

45,185.25
ANALISA HARGA SATUAN

KODE ANALISA : L.038


JENIS PEKERJAAN : Pasang kaca polos, tebal 12 mm termpered
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0150


2 Tukang Kayu L08 Org/hr 0.1500
3 Kepala Tukang Kayu L03 Org/hr 0.0150
4 Mandor L01 Org/hr 0.0008

JUMLAH HARGA TENAGA

B BAHAN

1 Kaca Polos tebal 12 mm M273 m 1.1000


2 Tempered kaca M506 m2 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 643.50
51,975.00 7,796.25
55,275.00 829.13
65,175.00 48.88

9,317.76

334,521.00 367,973.10
450,000.00 450,000.00

817,973.10

827,290.86
ANALISA HARGA SATUAN

KODE ANALISA : M.032


JENIS PEKERJAAN : Pasang plint keramik artistik 10 x 20 cm
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0900


2 Tukang Batu L07 Org/hr 0.0900
3 Kepala Tukang Batu L02 Org/hr 0.0090
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Plint keramik artistik 10 x 20 M313 bh 5.3000


2 Portland Cement (PC) M037 kg 1.1400
3 Pasir Pasang M002 m 0.0030
4 Portland Cement (PC) Putih M038 kg 0.0250

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 3,861.00
51,975.00 4,677.75
55,275.00 497.48
65,175.00 325.88

9,362.10

15,480.00 82,044.00
1,350.00 1,539.00
90,000.00 270.00
2,673.00 66.83

83,919.83

93,281.93
ANALISA HARGA SATUAN

KODE ANALISA : M.040


JENIS PEKERJAAN : Pasang lantai keramik ukuran 20 x 20 cm warna/motif
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.7000


2 Tukang Batu L07 Org/hr 0.3500
3 Kepala Tukang Batu L02 Org/hr 0.0350
4 Mandor L01 Org/hr 0.0350

JUMLAH HARGA TENAGA

B BAHAN

1 Keramik Lantai 20 x 20 cm warna/motif M322 bh 26.5000


2 Portland Cement (PC) M037 kg 10.4000
3 Pasir Pasang M002 m 0.0450
4 Portland Cement (PC) Putih M038 kg 1.6200

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasang lantai keramik ukuran 20 x 20 cm warna/motif

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 30,030.00
51,975.00 18,191.25
55,275.00 1,934.63
65,175.00 2,281.13

52,437.00

1,840.00 48,760.00
1,350.00 14,040.00
90,000.00 4,050.00
2,673.00 4,330.26

71,180.26

123,617.26
ANALISA HARGA SATUAN

KODE ANALISA : M.045


JENIS PEKERJAAN : Pasang lantai keramik ukuran 40 x 40 cm warna/motif
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.7000


2 Tukang Batu L07 Org/hr 0.3500
3 Kepala Tukang Batu L02 Org/hr 0.0350
4 Mandor L01 Org/hr 0.0350

JUMLAH HARGA TENAGA

B BAHAN

1 Keramik Lantai 40 x 40 cm warna/motif M318 bh 6.9300


2 Portland Cement (PC) M037 kg 9.8000
3 Pasir Pasang M002 m 0.0215
4 Portland Cement (PC) Putih M038 kg 1.3000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasang lantai keramik ukuran 40 x 40 cm warna/motif

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 30,030.00
51,975.00 18,191.25
55,275.00 1,934.63
65,175.00 2,281.13

52,437.00

13,590.00 94,178.70
1,350.00 13,230.00
90,000.00 1,935.00
2,673.00 3,474.90

112,818.60

165,255.60
ANALISA HARGA SATUAN

KODE ANALISA : M.049


JENIS PEKERJAAN : Pasang plint keramik lantai ukuran 10 x 40 cm
SATUAN PEMBAYARAN : m1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.9000


2 Tukang Batu L07 Org/hr 0.0900
3 Kepala Tukang Batu L02 Org/hr 0.0090
4 Mandor L01 Org/hr 0.0050

JUMLAH HARGA TENAGA

B BAHAN

1 Plint Keramik Lantai 10 x 40 cm M326 bh 2.6500


2 Portland Cement (PC) M037 kg 1.2400
3 Pasir Pasang M002 m 0.0030
4 Portland Cement (PC) Putih M038 kg 0.1000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pasang plint keramik lantai ukuran 10 x 40 cm

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 38,610.00
51,975.00 4,677.75
55,275.00 497.48
65,175.00 325.88

44,111.10

15,939.00 42,238.35
1,350.00 1,674.00
90,000.00 270.00
2,673.00 267.30

44,449.65

88,560.75
ANALISA HARGA SATUAN

KODE ANALISA : M.057


JENIS PEKERJAAN : Pasang dinding keramik ukuran 20 x 25 cm
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.9000


2 Tukang Batu L07 Org/hr 0.4500
3 Kepala Tukang Batu L02 Org/hr 0.0450
4 Mandor L01 Org/hr 0.0450

JUMLAH HARGA TENAGA

B BAHAN

1 Keramik Dinding 20 x 25 cm M327 bh 20.0000


2 Portland Cement (PC) M037 kg 9.3000
3 Pasir Pasang M002 m 0.0180
4 Portland Cement (PC) Putih M038 kg 1.5000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 38,610.00
51,975.00 23,388.75
55,275.00 2,487.38
65,175.00 2,932.88

67,419.00

3,690.00 73,800.00
1,350.00 12,555.00
90,000.00 1,620.00
2,673.00 4,009.50

91,984.50

159,403.50
ANALISA HARGA SATUAN

KODE ANALISA : M.073


JENIS PEKERJAAN : Pasang dinding batu sisir
SATUAN PEMBAYARAN : m2

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.7000


2 Tukang Batu L07 Org/hr 0.3500
3 Kepala Tukang Batu L02 Org/hr 0.0350
4 Mandor L01 Org/hr 0.0350

JUMLAH HARGA TENAGA

B BAHAN

1 Batu sisir M504 m2 1.0500


2 Portland Cement (PC) M037 kg 11.7500
3 Pasir Pasang M002 m 0.0350

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 30,030.00
51,975.00 18,191.25
55,275.00 1,934.63
65,175.00 2,281.13

52,437.00

71,910.00 75,505.50
1,350.00 15,862.50
90,000.00 3,150.00

94,518.00

146,955.00
ANALISA HARGA SATUAN

KODE ANALISA : N.008


JENIS PEKERJAAN : Pengecatan kayu baru (1 lapis plamir, 1 lapis cat dasar,
2 lapis cat penutup)
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0700


2 Tukang Cat L10 Org/hr 0.0090
3 Kepala Tukang Cat L05 Org/hr 0.0060
4 Mandor L01 Org/hr 0.0025

JUMLAH HARGA TENAGA

B BAHAN

1 Cat meni kayu M409 kg 0.2000


2 Plamir Kayu M402 kg 0.1500
3 Cat Dasar Kayu M411 kg 0.1700
4 Cat Kayu M414 kg 0.2600

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pengecatan kayu baru (1 lapis plamir, 1 lapis cat dasar,

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 3,003.00
51,975.00 467.78
55,275.00 331.65
65,175.00 162.94

3,965.36

34,114.50 6,822.90
20,592.00 3,088.80
33,858.00 5,755.86
70,290.00 18,275.40

33,942.96

37,908.32
ANALISA HARGA SATUAN

KODE ANALISA : N.011


JENIS PEKERJAAN : Pelaburan kayu dengan politur
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr -


2 Tukang Cat L10 Org/hr 0.0600
3 Kepala Tukang Cat L05 Org/hr 0.0160
4 Mandor L01 Org/hr 0.0025

JUMLAH HARGA TENAGA

B BAHAN

1 Politur Jadi M420 Ltr 0.5500


2 Kertas Gosok M401 Lbr 2.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 -
51,975.00 3,118.50
55,275.00 884.40
65,175.00 162.94

4,165.84

73,237.50 40,280.63
4,455.00 8,910.00

49,190.63

53,356.46
ANALISA HARGA SATUAN

KODE ANALISA : N.014


JENIS PEKERJAAN : Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasa
2 lapis cat penutup)
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200


2 Tukang Cat L10 Org/hr 0.0630
3 Kepala Tukang Cat L05 Org/hr 0.0063
4 Mandor L01 Org/hr 0.0025

JUMLAH HARGA TENAGA

B BAHAN

1 Plamir Tembok M403 kg 0.1000


2 Cat Dasar Tembok M412 kg 0.1000
3 Cat Tembok M415 kg 0.2600

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar,

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 858.00
51,975.00 3,274.43
55,275.00 348.23
65,175.00 162.94

4,643.60

12,771.00 1,277.10
25,740.00 2,574.00
47,025.00 12,226.50

16,077.60

20,721.20
ANALISA HARGA SATUAN

KODE ANALISA : N.016


JENIS PEKERJAAN : Pengecatan tembok baru eksterior
(1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200


2 Tukang Cat L10 Org/hr 0.0630
3 Kepala Tukang Cat L05 Org/hr 0.0063
4 Mandor L01 Org/hr 0.0025

JUMLAH HARGA TENAGA

B BAHAN

1 Plamir Tembok M403 kg 0.1000


2 Cat Dasar Tembok M412 kg 0.1000
3 Cat Tembok Eksterior M415.b kg 0.2600

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


(1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 858.00
51,975.00 3,274.43
55,275.00 348.23
65,175.00 162.94

4,643.60

12,771.00 1,277.10
25,740.00 2,574.00
97,119.00 25,250.94

29,102.04

33,745.64
ANALISA HARGA SATUAN

KODE ANALISA : N.021


JENIS PEKERJAAN : Pengecatan plafon (1 lapis plamir, 1 lapis cat dasar,
2 lapis cat penutup)
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200


2 Tukang Cat L10 Org/hr 0.0630
3 Kepala Tukang Cat L05 Org/hr 0.0063
4 Mandor L01 Org/hr 0.0025

JUMLAH HARGA TENAGA

B BAHAN

1 Plamir Tembok M403 kg 0.1000


2 Cat Dasar Tembok M412 kg 0.1000
3 Cat Tembok M415 kg 0.2600

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pengecatan plafon (1 lapis plamir, 1 lapis cat dasar,

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 858.00
51,975.00 3,274.43
55,275.00 348.23
65,175.00 162.94

4,643.60

12,771.00 1,277.10
25,740.00 2,574.00
47,025.00 12,226.50

16,077.60

20,721.20
ANALISA HARGA SATUAN

KODE ANALISA : N.029


JENIS PEKERJAAN : Pekerjaan waterproofing
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0200


2 Tukang Cat L10 Org/hr 0.0630
3 Kepala Tukang Cat L05 Org/hr 0.0063
4 Mandor L01 Org/hr 0.0025

JUMLAH HARGA TENAGA

B BAHAN

1 Waterproofing M418 kg 0.3600

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 858.00
51,975.00 3,274.43
55,275.00 348.23
65,175.00 162.94

4,643.60

146,097.00 52,594.92

52,594.92

57,238.52
ANALISA HARGA SATUAN

KODE ANALISA : N.030


JENIS PEKERJAAN : Pengecatan tembok LAMA eksterior (1 lapis cat dasar, 2
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0280


2 Tukang Cat L10 Org/hr 0.0420
3 Kepala Tukang Cat L05 Org/hr 0.0042
4 Mandor L01 Org/hr 0.0025

JUMLAH HARGA TENAGA

B BAHAN

1 Cat Dasar Tembok M412 kg 0.1200


2 Cat Tembok Eksterior M415.b kg 0.1800

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pengecatan tembok LAMA eksterior (1 lapis cat dasar, 2 lapis cat penutup)

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 1,201.20
51,975.00 2,182.95
55,275.00 232.16
65,175.00 162.94

3,779.24

25,740.00 3,088.80
97,119.00 17,481.42

20,570.22

24,349.46
ANALISA HARGA SATUAN

KODE ANALISA : N.033


JENIS PEKERJAAN : Coating batu alam / Batu hias
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.0700


2 Tukang Cat L10 Org/hr 0.0090
3 Kepala Tukang Cat L05 Org/hr 0.0060
4 Mandor L01 Org/hr 0.0025

JUMLAH HARGA TENAGA

B BAHAN

1 Engsel casement 15 " M505 kg 0.1700


2 Engsel casement 15 " M505 kg 0.2600

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 3,003.00
51,975.00 467.78
55,275.00 331.65
65,175.00 162.94

3,965.36

29,250.00 4,972.50
29,250.00 7,605.00

12,577.50

16,542.86
ANALISA HARGA SATUAN

KODE ANALISA : P.001


JENIS PEKERJAAN : Pemasangan stop kontak
SATUAN PEMBAYARAN : Titik

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5000


2 Tukang Listrik L11 Org/hr 0.5000
3 Kepala Tukang Listrik L06 Org/hr 0.0500
4 Mandor L01 Org/hr 0.0500

JUMLAH HARGA TENAGA

B BAHAN

1 Kabel NYA 2.5 mm M437 m 10.0000


2 Stop Kontak M439 bh 1.0000
3 T dos PVC M443 bh 1.0000
4 Pipa PVC 5/8" M444 Ljr 0.6500
5 Las doof M441 bh 3.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 21,450.00
51,975.00 25,987.50
55,275.00 2,763.75
65,175.00 3,258.75

53,460.00

4,356.00 43,560.00
26,271.00 26,271.00
990.00 990.00
7,087.50 4,606.88
594.00 1,782.00

77,209.88

130,669.88
ANALISA HARGA SATUAN

KODE ANALISA : P.002


JENIS PEKERJAAN : Pemasangan saklar tunggal
SATUAN PEMBAYARAN : Titik

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5000


2 Tukang Listrik L11 Org/hr 0.5000
3 Kepala Tukang Listrik L06 Org/hr 0.0500
4 Mandor L01 Org/hr 0.0500

JUMLAH HARGA TENAGA

B BAHAN

1 Kabel NYA 2.5 mm M437 m 6.0000


2 Saklar Broco Tunggal M440 bh 1.0000
3 T dos PVC M443 bh 1.0000
4 Pipa PVC 5/8" M444 Ljr 0.6500
5 Las doof M441 bh 2.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 21,450.00
51,975.00 25,987.50
55,275.00 2,763.75
65,175.00 3,258.75

53,460.00

4,356.00 26,136.00
32,035.50 32,035.50
990.00 990.00
7,087.50 4,606.88
594.00 1,188.00

64,956.38

118,416.38
ANALISA HARGA SATUAN

KODE ANALISA : P.003


JENIS PEKERJAAN : Pemasangan saklar ganda
SATUAN PEMBAYARAN : Titik

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.5000


2 Tukang Listrik L11 Org/hr 0.5000
3 Kepala Tukang Listrik L06 Org/hr 0.0500
4 Mandor L01 Org/hr 0.0500

JUMLAH HARGA TENAGA

B BAHAN

1 Kabel NYA 2.5 mm M437 m 10.0000


2 Saklar Broco Ganda M440.a bh 1.0000
3 T dos PVC M443 bh 1.0000
4 Pipa PVC 5/8" M444 Ljr 0.6500
5 Las doof M441 bh 3.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 21,450.00
51,975.00 25,987.50
55,275.00 2,763.75
65,175.00 3,258.75

53,460.00

4,356.00 43,560.00
36,666.00 36,666.00
990.00 990.00
7,087.50 4,606.88
594.00 1,782.00

87,604.88

141,064.88
ANALISA HARGA SATUAN

KODE ANALISA : P.007


JENIS PEKERJAAN : Pemasangan titik lampu TL 40 Watt (komplit)
SATUAN PEMBAYARAN : Titik

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2500


2 Tukang Listrik L11 Org/hr 0.2500
3 Kepala Tukang Listrik L06 Org/hr 0.0250
4 Mandor L01 Org/hr 0.0250

JUMLAH HARGA TENAGA

B BAHAN

1 Lampu TL Komplit 40 Watt M450 bh 1.0000


2 Kabel NYA 2.5 mm M437 m 10.0000
3 Isolator M442 m 4.0000
4 Las doof M441 bh 2.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Pemasangan titik lampu TL 40 Watt (komplit)

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 10,725.00
51,975.00 12,993.75
55,275.00 1,381.88
65,175.00 1,629.38

26,730.00

93,753.00 93,753.00
4,356.00 43,560.00
792.00 3,168.00
594.00 1,188.00

141,669.00

168,399.00
ANALISA HARGA SATUAN

KODE ANALISA : P.011


JENIS PEKERJAAN : Pemasangan titik lampu XL 18 Watt
SATUAN PEMBAYARAN : Titik

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.2500


2 Tukang Listrik L11 Org/hr 0.2500
3 Kepala Tukang Listrik L06 Org/hr 0.0250
4 Mandor L01 Org/hr 0.0250

JUMLAH HARGA TENAGA

B BAHAN

1 Lampu XL (Lilin) 18 Watt M454 bh 1.0000


2 Kabel NYA 2.5 mm M437 m 10.0000
3 Isolator M442 m 4.0000
4 Fiting Flafond M445 bh 1.0000
5 Las doof M441 bh 2.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 10,725.00
51,975.00 12,993.75
55,275.00 1,381.88
65,175.00 1,629.38

26,730.00

36,477.00 36,477.00
4,356.00 43,560.00
792.00 3,168.00
10,296.00 10,296.00
594.00 1,188.00

94,689.00

121,419.00
ANALISA HARGA SATUAN

KODE ANALISA : Q.001


JENIS PEKERJAAN : Penyetelan mesin bor dan buat bak sirkulasi
SATUAN PEMBAYARAN : Unit

A. Biaya Pemasangan Balok Landasan

NO. KOMPONEN SATUAN

A. TENAGA

JUMLAH HARGA TENAGA

B BAHAN

1 Kayu untuk landasan Ls


2 Kayu untuk dinding spul bak sirkulasi Ls

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


ANALISA HARGA SATUAN

Penyetelan mesin bor dan buat bak sirkulasi

PERKIRAAN HARGA JUMLAH


KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1.0000 1,210,000.00 1,210,000.00


1.0000 385,000.00 385,000.00

1,595,000.00

1,595,000.00
ANALISA HARGA SATUAN

KODE ANALISA : R.001


JENIS PEKERJAAN : Pengukuran bendung untuk MC
SATUAN PEMBAYARAN : bh

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Juru Ukur L25 Org/hr 1.5000


2 Pekerja Biasa L17 Org/hr 4.5000

JUMLAH HARGA TENAGA

B BAHAN

1 Cat meni kayu M409 kg 0.1200


2 Paku Kayu Segala Ukuran M140 kg 0.0500
3 Usuk 5/7 M061 m 0.0120

JUMLAH HARGA BAHAN

C PERALATAN

1 Pesawat Ukur E15 Unit/hr 1.0000


2 Meteran E16 bh 0.0450
3 Palu E17 bh 0.0900

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

155,100.00 232,650.00
42,900.00 193,050.00

425,700.00

34,114.50 4,093.74
21,780.00 1,089.00
4,958,415.00 59,500.98

64,683.72

110,000.00 110,000.00
100,000.00 4,500.00
25,000.00 2,250.00

116,750.00

607,133.72
ANALISA HARGA SATUAN

KODE ANALISA : S.001


JENIS PEKERJAAN : Menanam rumput lamur
SATUAN PEMBAYARAN : m

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1 Pekerja Biasa L17 Org/hr -


2 Tukang Taman L14 Org/hr 0.1500
3 Mandor L01 Org/hr 0.0100

JUMLAH HARGA TENAGA

B BAHAN

1 Rumput Lamur M461 m 1.0000

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

42,900.00 -
51,975.00 7,796.25
65,175.00 651.75

8,448.00

20,880.00 20,880.00

20,880.00

29,328.00
DAFTAR HARGA SATUAN PEKERJAAN KONSTRUKSI (HSPK)
DINAS PENDIDIKAN KOTA MALANG
TAHUN ANGGARAN 2013
KODE
JENIS PEKERJAAN
ANALISA
1 2

I. PEKERJAAN PERSIAPAN
A.001 Pagar sementara dari kayu tinggi 2 m
A.002 Pagar sementara dari seng gelombang tinggi 2 m
A.003 Pagar sementara dari kawat duri tinggi 1.8 m
A.004 Pagar kawat jaring galvanis, tinggi 1,0 m
A.005 Pengukuran dan pemasangan bouwplank
A.006 Pembuatan kantor sementara, dengan lantai plesteran
A.007 Pembuatan gudang semen dan alat-alat
A.008 Pembuatan rumah jaga/konstruksi kayu
A.009 Membersihkan lapangan dan perataan
A.010 Pembuatan bedeng buruh
A.011 Pembuatan bak adukan ukuran (40 x 50 x 20) cm
A.012 Pembuatan jalan sementara
A.013 Bongkar pasang kayu kuda-kuda / kusen / loteng
A.014 Bongkaran beton bertulang
A.015 Bongkaran tembok bata merah
A.016 Bongkaran atap
A.017 Bongkaran lantai
A.018 Bongkaran plafon
A.019 Bongkaran penutup atap lama (Genteng)
A.020 Bongkaran rangka penutup atap lama (Usuk+Reng)
A.021 Bongkaran konstruksi atap lama
A.022 Bongkaran plafon
A.023 Mengupas plesteran Lama

II. PEKERJAAN TANAH


B.001 Galian tanah biasa sedalam 1 m
B.002 Galian tanah biasa sedalam 2 m
B.003 Galian tanah biasa sedalam 3 m
B.004 Galian tanah keras sedalam 1 m
B.005 Galian tanah cadas sedalam 1 m
B.006 Galian tanah lumpur sedalam 1 m
B.007 Pekerjaan stripping setinggi 1 m
B.008 Pembuangan tanah sejauh 30 m
B.009 Urugan kembali
B.010 Pemadatan tanah (per 20 cm)
B.011 Urugan pasir
B.012 Lapisan Pudel Campuran 1 Kp : 3 Ps : 7 TL
B.013 Lapisan Pudel Campuran 1 Kp : 5 TL
B.014 Pemasangan lapisan ijuk (tebal 10 cm)
B.015 Urugan sirtu padat untuk peninggian lantai bangunan
B.016 Urugan Tanah
B.017 Cut and fill
B.018 Galian tanah keras sedalam > 5 m
B.019 Galian tanah keras sedalam > 10 m
B.020 Pembuangan tanah sejauh > 1 km
B.021 Perataan Lahan (Dengan alat)
III. PEKERJAAN PONDASI
C.001 Pasang pondasi batu kali, 1 Pc : 3 Ps
C.002 Pasang pondasi batu kali, 1 Pc : 4 Ps
C.003 Pasang pondasi batu kali, 1 Pc : 5 Ps
C.004 Pasang pondasi batu kali, 1 Pc : 6 Ps
C.005 Pasang pondasi batu kali, 1 Pc : 8 Ps
C.006 Pasang pondasi batu kali, 1 Kp : 1 Sm : 2 Ps
C.007 Pasang pondasi batu kali, 1 Pc : 3 Kp : 10 Ps
C.008 Pasang pondasi batu kali, 1/4 Pc : 1 Kp : 4 Ps
C.009 Pasang pondasi batu kosong
C.010 Pasang pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu kali
C.011 Pasang pondasi sumuran diameter 100 cm

IV. PEKERJAAN DINDING


D.001 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps
D.002 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps
D.003 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps
D.004 Pasangan bata merah tebal 1 bata, 1 Pc : 5 Ps
D.005 Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps
D.006 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps
D.007 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps
D.008 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps
D.009 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps
D.010 Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps
D.011 Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps
D.012 Pasangan bata merah tebal 1/2 bata, 1 Pc : 8 Ps
D.013 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps
D.014 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1 Ps
D.015 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2 Ps
D.016 Pasangan dinding hollowblock (HB. 20), Spesi 1 PC : 3 Ps
D.017 Pasangan dinding hollowblock (HB. 20), Spesi 1 PC : 4 Ps
D.018 Pasangan dinding hollowblock (HB. 15), spesi 1 PC : 3 Ps
D.019 Pasangan dinding hollowblock (HB. 15), spesi 1 PC : 4 Ps
D.020 Pasangan dinding hollowblock (HB. 10), Spesi 1 PC : 3 Ps
D.021 Pasangan dinding hollowblock (HB. 10), Spesi 1 PC : 4 Ps
D.022 Pasangan dinding roster/terawang (12 x 11 x 24) cm, Spesi 1 PC : 3 Ps
D.023 Pasangan dinding roster/terawang (12 x 11 x 24) cm, Spesi 1 PC : 4 Ps
D.024 Pasang bata berongga (5 x 11 x 24) cm, Spesi 1PC:3Ps
D.025 Pasang Batu Bata Tahan Api

V. PEKERJAAN PLESTERAN
E.001 Plesteran 1 Pc : 1 Ps, tebal 15 mm
E.002 Plesteran 1 Pc : 2 Ps, tebal 15 mm
E.003 Plesteran 1 Pc : 3 Ps, tebal 15 mm
E.004 Plesteran 1 Pc : 4 Ps, tebal 15 mm
E.005 Plesteran 1 Pc : 5 Ps, tebal 15 mm
E.006 Plesteran 1 Pc : 6 Ps, tebal 15 mm
E.007 Plesteran 1 Pc : 7 Ps, tebal 15 mm
E.008 Plesteran 1 Pc : 8 Ps, tebal 15 mm
E.009 Plesteran 1 Pc : 0.5 Kp : 3 Ps, tebal 15 mm
E.010 Plesteran 1 Pc : 2 Kp : 8 Ps, tebal 15 mm
E.011 Plesteran 1 Kp : 1 Sm : 1 Ps, tebal 15 mm
E.012 Plesteran 1 Kp : 1 Sm : 2 Ps, tebal 15 mm
E.013 Plesteran 1 Pc : 2 Ps, tebal 20 mm
E.014 Plesteran 1 Pc : 3 Ps, tebal 20 mm
E.015 Plesteran 1 Pc : 4 Ps, tebal 20 mm
E.016 Plesteran 1 Pc : 5 Ps, tebal 20 mm
E.017 Plesteran 1 Pc : 6 Ps, tebal 20 mm
E.018 Plesteran 1 Kp : 1 Sm : 2 Ps, tebal 20 mm
E.019 Berapen 1 Pc : 5 Ps, tebal 15 mm
E.020 Plesteran skoning 1 Pc : 2 Ps, Lebar 10 mm
E.021 Plesteran granito 1 Pc warna : 2 granito, tebal 10 mm
E.022 Plesteran Teraso, 1 Pc Warna : 2 Batu Teraso, tebal 10 mm
E.023 Plesteran Ciprat 1 Pc : 2 Ps,
E.024 Plesteran siar pasangan batu kali adukan 1 Pc : 2 Ps
E.025 Benangan
E.026 Acian
E.027 Finishing beton expose
E.028 Benangan Sudut

VI. PEKERJAAN KAYU


F.001 Pasang kusen pintu dan jendela kayu jati (kelas I)
F.002 Pasang kusen pintu dan jendela kayu kamper
F.003 Pasang kusen pintu dan jendela kayu borneo
F.004 Pasang kusen pintu dan jendela kayu meranti
F.005 Pasang pintu klamp kayu jati
F.006 Pasang pintu klamp kayu kamper
F.007 Pasang pintu klamp kayu borneo
F.008 Pasang pintu klamp kayu meranti
F.009 Pasang pintu panel kayu jati
F.010 Pasang pintu panel kayu kamper
F.011 Pasang pintu panel kayu borneo
F.012a Pasang pintu panel kayu meranti
Bh (Uk 80x210 cm)
F.012b Pasang pintu panel kayu meranti. Lapis alumi jeruk
Bh (Uk 70x210 cm)
F.013 Pasang pintu dan jendela kaca kayu jati
F.014 Pasang pintu dan jendela kaca kayu kamper
F.015 Pasang pintu dan jendela kaca kayu borneo
F.016 Pasang pintu dan jendela kaca freme kayu meranti
Daun Pintu 80 x 210 cm
Daun Jendela (Luas Rata2 0,65 m2)
Daun Jendela BV 60 x 50 cm
F.017 Pasang pintu dan jendela jalusi kayu jati
F.018 Pasang pintu dan jendela jalusi kayu kamper
F.019 Pasang pintu dan jendela jalusi kayu borneo
F.020 Pasang pintu dan jendela jalusi kayu meranti
Uk. 50 x 110 cm
F.021 Pasang pintu plywood rangkap, rangka kayu jati
F.022 Pasang pintu plywood rangkap, rangka kayu kamper
F.023 Pasang pintu plywood rangkap, rangka kayu borneo
F.024 Pasang pintu plywood rangkap, rangka kayu meranti
F.025 Pasang jalusi mati kusen kayu jati
F.026 Pasang jalusi mati kusen kayu kamper
F.027 Pasang jalusi mati kusen kayu borneo
F.028 Pasang jalusi mati kusen kayu meranti
F.029 Pasang pintu teakwood rangkap, rangka kayu jati
F.030 Pasang pintu teakwood rangkap, rangka kayu kamper
F.031 Pasang pintu teakwood rangkap, rangka kayu borneo
F.032 Pasang pintu teakwood rangkap, rangka kayu meranti
F.033 Pasang pintu plywood & formika, rangka kayu jati
F.034 Pasang pintu plywood & formika, rangka kayu kamper
F.035 Pasang pintu plywood & formika, rangka kayu borneo
F.036 Pasang pintu plywood & formika, rangka kayu meranti
F.037 Pasang pintu teakwood & formika, rangka kayu jati
F.038 Pasang pintu teakwood & formika, rangka kayu borneo (divernis)
F.039 Pasang pintu teakwood & formika, rangka kayu meranti (divernis)
F.040 Pasang konstruksi kuda-kuda kayu jati
F.041 Pasang konstruksi kuda-kuda kayu kamper
F.042 Pasang konstruksi kuda-kuda kayu borneo
F.043 Pasang konstruksi kuda-kuda kayu bengkirai
F.044 Pasang konstruksi kuda-kuda kayu kruing
F.045 Pasang konstruksi kuda-kuda kayu meranti
F.046 Pasang konstruksi kuda-kuda ekspose kayu jati
F.047 Pasang konstruksi kuda-kuda ekspose kayu kamper
F.048 Pasang konstruksi gording kayu kamper
F.049 Pasang konstruksi gording kayu meranti
F.050 Pasang kaso + reng genteng biasa kayu jati
F.051 Pasang kaso + reng genteng biasa kayu kamper
F.052 Pasang kaso + reng genteng biasa kayu borneo
F.053 Pasang kaso + reng genteng biasa kayu bengkirai
F.054 Pasang kaso + reng genteng biasa kayu kruing
F.055 Pasang kaso + reng genteng biasa kayu meranti
F.056 Pasang kaso + reng genteng karangpilang kayu jati
F.057 Pasang kaso + reng genteng karangpilang kayu kamper
F.058 Pasang kaso + reng genteng karangpilang kayu borneo
F.059 Pasang kaso + reng genteng karangpilang kayu bengkirai
F.060 Pasang kaso + reng genteng karangpilang kayu kruing
F.061 Pasang kaso + reng genteng karangpilang kayu meranti
F.062 Pasang kaso + reng genteng beton kayu jati
F.063 Pasang kaso + reng genteng beton kayu kamper
F.064 Pasang kaso + reng genteng beton kayu borneo
F.065 Pasang kaso + reng genteng beton kayu bengkirai
F.066 Pasang kaso + reng genteng beton kayu kruing
F.067 Pasang kaso + reng genteng beton kayu meranti
F.068 Pasang kaso + reng atap sirap kayu jati
F.069 Pasang kaso + reng atap sirap kayu kamper
F.070 Pasang kaso + reng atap sirap kayu borneo
F.071 Pasang kaso + reng atap sirap kayu bengkirai
F.072 Pasang kaso + reng atap sirap kayu kruing
F.073 Pasang kaso + reng atap sirap kayu meranti
F.074 Pasang rangka langit-langit (0.5 x 1.0) m, kayu jati
F.075 Pasang rangka langit-langit (0.5 x 1.0) m, kayu kamper
F.076 Pasang rangka langit-langit (0.5 x 1.0) m, kayu borneo
F.077 Pasang rangka langit-langit (0.5 x 1.0) m, kayu bengkirai
F.078 Pasang rangka langit-langit (0.5 x 1.0) m, kayu kruing
F.079 Pasang rangka langit-langit (0.5 x 1.0) m, kayu meranti
F.080 Pasang lisplang ukuran (3 x 20) cm, kayu jati
F.081 Pasang lisplang ukuran (3 x 20) cm, kayu kamper
F.082 Pasang lisplang ukuran (3 x 20) cm, kayu borneo
F.083 Pasang lisplang ukuran (3 x 20) cm, kayu bengkirai
F.084 Pasang lisplang ukuran (3 x 20) cm, kayu kruing
F.085 Pasang lisplang ukuran (3 x 20) cm, kayu meranti
F.086 Pasang lisplang ukuran (3 x 30) cm, kayu jati
F.087 Pasang lisplang ukuran (3 x 30) cm, kayu kamper
F.088 Pasang lisplang ukuran (3 x 30) cm, kayu borneo
F.089 Pasang lisplang ukuran (3 x 30) cm, kayu bengkirai
F.090 Pasang lisplang ukuran (3 x 30) cm, kayu kruing
F.091 Pasang lisplang ukuran (3 x 30) cm, kayu meranti
F.092 Pasang rangka dinding pemisah kayu jati
F.093 Pasang rangka dinding pemisah kayu kamper
F.094 Pasang rangka dinding pemisah kayu borneo
F.095 Pasang rangka dinding pemisah kayu meranti
F.096 Pasang rangka dinding pemisah teakwood rangkap, rangka kayu jati
F.097 Pasang rangka dinding pemisah teakwood rangkap, rangka kayu kamper
F.098 Pasang rangka dinding pemisah teakwood rangkap, rangka kayu borneo
F.099 Pasang rangka dinding pemisah teakwood rangkap, rangka kayu meranti
F.100 Pasang rangka dinding pemisah plywood rangkap, rangka kayu jati
F.101 Pasang rangka dinding pemisah plywood rangkap, rangka kayu kamper
F.102 Pasang rangka dinding pemisah plywood rangkap, rangka kayu borneo
F.103 Pasang rangka dinding pemisah plywood rangkap, rangka kayu meranti
F.104 Pasang dinding lambriziring dari papan jati
F.105 Pasang dinding lambriziring dari papan kamper
F.106 Pasang kembali konstruksi kuda-kuda lama
F.107 Pasang konstruksi gording lama
F.108 Pasang kaso (Kamper)+ reng (Meranti) genteng beton

VII. PEKERJAAN BETON


G.001 Beton mutu fc'=7,4 Mpa (K100) slump (12 2) cm, w/c = 0,87
G.002 Beton mutu fc'=9,8 Mpa (K125) slump (12 2) cm, w/c = 0,78
G.003 Beton mutu fc'=12,2 Mpa (K150) slump (12 2) cm, w/c = 0,72
G.004 Lantai kerja beton mutu fc'=7,4 Mpa (K100) slump (3 - 6) cm, w/c = 0,87
G.005 Beton mutu fc'=14,5 Mpa (K175) slump (12 2) cm, w/c = 0,66
G.006 Beton mutu fc'=16,9 Mpa (K200) slump (12 2) cm, w/c = 0,61
G.007 Beton mutu fc'=19,3 Mpa (K225) slump (12 2) cm, w/c = 0,58
G.008 Beton mutu fc'=24,0 Mpa (K275) slump (12 2) cm, w/c = 0,53
G.009 Beton mutu fc'=21,7 Mpa (K250) slump (12 2) cm, w/c = 0,56
G.010 Beton mutu fc'=26,4 Mpa (K300) slump (12 2) cm, w/c = 0,52
G.011 Beton mutu fc'=28,8 Mpa (K325) slump (12 2) cm, w/c = 0,49
G.012 Beton mutu fc'=31,2 Mpa (K350) slump (12 2) cm, w/c = 0,48
G.013 Beton kedap air dengan strorox - 100
G.014 Pasang PVC Waterstop lebar 150 mm
G.015 Pasang PVC Waterstop lebar 200 mm
G.016 Pasang PVC Waterstop lebar 230 mm - 320 mm
G.017 Pembesian dengan besi polos
G.018 Pembesian dengan besi ulir
G.019 Kabel prestressed polos/strands
G.020 Memasang 1 kg jaring kawat baja / wire mesh
G.021 Pasang bekisting untuk pondasi
G.022 Pasang bekisting untuk pondasi ( 2x pakai )
G.023 Pasang bekisting untuk sloof
G.024 Pasang bekisting untuk sloof ( 2x pakai )
G.025 Pasang bekisting untuk kolom
G.026 Pasang bekisting untuk kolom ( 2x pakai )
G.027 Pasang bekisting untuk balok
G.028 Pasang bekisting untuk balok ( 2x pakai )
G.029 Pasang bekisting untuk plat lantai
G.030 Pasang bekisting untuk plat lantai ( 2x pakai )
G.031 Pasang bekisting untuk dinding
G.032 Pasang bekisting untuk dinding ( 2x pakai )
G.033 Pasang bekisting untuk tangga
G.034 Pasang bekisting untuk tangga ( 2x pakai )
G.035 Pasang bekisting jembatan untuk pengecoran
G.036 Pondasi beton bertulang (150 kg besi + bekisting)
G.037 Sloof beton bertulang (200 kg besi + bekisting)
G.038 Kolom beton bertulang (150 kg besi + bekisting)
G.039 Kolom beton bertulang (300 kg besi + bekisting)
G.040 Balok beton bertulang (200 kg besi + bekisting)
G.041 Dinding beton bertulang (150 kg besi + bekisting)
G.042 Dinding beton bertulang (200 kg besi + bekisting)
G.043 Kolom penguat beton bertulang (11 x 11) cm
G.044 Ring balok beton bertulang (10 x 15) cm
G.045 Sloof beton bertulang (10 x 15) cm

ANALISA BETON DALAM 1 M3


Btn.001 Strouss 30 cm
Btn. 002 Pondasi Footplat beton bertulang (150 kg besi polos + bekisting)
Btn. 003 Pondasi Footplat beton bertulang (150 kg besi ulir + bekisting)
Btn. 004 Sloof beton bertulang 20/30 + bekisting
Btn. 005 Sloof beton bertulang 15/25 + bekisting
Btn. 006 Kolom beton bertulang 20x20 + bekisting
Btn. 007 Kolom beton bertulang 30x30 + bekisting
Btn. 008 Balok beton bertulang 15/25 + bekisting
Btn. 009 Balok beton bertulang 30/60 + bekisting
Btn. 010 Plat Lantai Beton Bertulang + Bekisting
Btn. 011 Plat Atap Beton Bertulang + Bekisting
Btn. 012 Plat Tangga Beton Bertulang + Bekisting
Btn. 013 Sloof Praktis Beton bertulang 11/20 + bekisting
Btn. 014 Sloof Praktis Beton bertulang 11/25

VIII. PEKERJAAN PENUTUP ATAP


H.001 Pasang atap genteng biasa ex. Malang
H.002 Pasang atap genteng press ex.Trenggalek
H.003 Pasang atap genteng karangpilang ex. Malang
H.004 Pasang atap genteng karangpilang ex. Trenggalek
H.005 Pasang atap genteng karangpilang ex. Surabaya
H.006 Pasang bubung genteng biasa ex. Malang
H.007 Pasang bubung genteng press ex. Trenggalek
H.008 Pasang bubung genteng karangpilang ex. Malang
H.009 Pasang bubung genteng karangpilang ex. Trenggalek
H.010 Pasang bubung genteng karangpilang ex. Surabaya
H.011 Pasang atap genteng palentong kecil
H.012 Pasang atap genteng kodok glazuur
H.013 Pasang atap genteng palentong super / besar
H.014 Pasang atap genteng beton biasa
H.015 Pasang atap genteng aspal
H.016 Pasang atap genteng metal
H.017 Pasang atap sirap
H.018 Pasang bubung genteng palentong kecil
H.019 Pasang bubung genteng kodok / glazuur
H.020 Pasang bubung genteng palentong super / besar
H.021 Pasang bubung genteng beton Monier
H.022 Pasang bubung genteng aspal
H.023 Pasang bubung genteng metal
H.024 Pasang bubung atap sirap
H.025 Pasang atap asbes gelombang (3,00 x 1,05) m x 4 mm
H.026 Pasang atap asbes gelombang (2,70 x 1,05) m x 4 mm
H.027 Pasang atap asbes gelombang (2,40 x 1,05) m x 4 mm
H.028 Pasang atap asbes gelombang (2,10 x 1,05) m x 4 mm
H.029 Pasang atap asbes gelombang (1,50 x 1,05) m x 4 mm
H.030 Pasang atap asbes gelombang (2,50 x 0,92) m x 5 mm
H.031 Pasang atap asbes gelombang (2,25 x 0,92) m x 5 mm
H.032 Pasang atap asbes gelombang (2,00 x 0,92) m x 5 mm
H.033 Pasang atap asbes gelombang (1,80 x 0,92) m x 5 mm
H.034 Pasang atap asbes gelombang (3,00 x 1,08) m x 6 mm
H.035 Pasang atap asbes gelombang (2,70 x 1,08) m x 6 mm
H.036 Pasang atap asbes gelombang (2,10 x 1,08) m x 6 mm
H.037 Pasang atap asbes gelombang (1.80 x 1,08) m x 6 mm
H.038 Pasang bubung stel gelombang 0,92 m
H.039 Pasang bubung stel gelombang 1,05 m
H.040 Pasang bubung stel gelombang 1,08 m
H.041 Pasang nok paten 0,92 m
H.042 Pasang nok paten 1,05 m
H.043 Pasang nok paten 1,08 m
H.044 Pasang nok stel rata 0,92 m
H.045 Pasang nok stel rata 1,05 m
H.046 Pasang atap seng gelombang
H.047 Pasang bubung seng gelombang
H.048 Pasang atap aluminium
H.049 Pasang bubung atap aluminium
H.050 Pasang lapisan aluminium foil / sesalation
H.051 Pasang roof light fibreglass
H.052 Pasang atap polycarbonat
H.053 Pasang atap seng galvalum
H.054 Pasang bubung atap seng galvalum
H.055 Pasang kembali atap genteng LAMA (karangpilang ex. Malang)

IX. PEKERJAAN LANGIT - LANGIT


I.001 Langit-langit asbes (1,0 x 1,0) m, tebal 6 mm
I.002 Langit-langit asbes (1,0 x 1,0) m, tebal 5 mm
I.003 Langit-langit asbes (1,0 x 1,0) m, tebal 4 mm
I.004 Langit-langit asbes (1,0 x 1,0) m, tebal 3,50 mm
I.005 Langit-langit akustik (30 x 30) cm
I.006 Langit-langit akustik (30 x 60) cm
I.007 Langit-langit akustik (60 x 120) cm
I.008 Langit-langit plywood (30 x 60) cm, tebal 4 mm
I.009 Langit-langit plywood (30 x 60) cm, tebal 6 mm
I.010 Langit-langit plywood (60 x 120) cm, tebal 4 mm
I.011 Langit-langit plywood (60 x 120) cm, tebal 6 mm
I.012 Langit-langit teakwood (30 x 60) cm, tebal 4 mm
I.013 Langit-langit teakwood (60 x 120) cm, tebal 4 mm
I.014 Langit-langit lat kayu jati
I.015 Langit-langit lat kayu ramin
I.016 Langit-langit lat kayu kamper
I.017 Langit-langit soft board
I.018 Langit-langit gypsum board ukuran (120x240x9)mm, tebal 9 mm
I.019 Langit-langit akustik (60 x 120) cm + rangka aluminium
I.020 Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka kayu jati
I.021 Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka kayu kamper
I.022 Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka kayu borneo
I.023 Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka kayu bengkirai
I.024 Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka kayu kruing
I.025 Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka kayu meranti
I.026 Langit-langit plywood 4 mm + rangka kayu jati
I.027 Langit-langit plywood 4 mm + rangka kayu kamper
I.028 Langit-langit plywood 4 mm + rangka kayu borneo
I.029 Langit-langit plywood 4 mm + rangka kayu bengkirai
I.030 Langit-langit plywood 4 mm + rangka kayu kruing
I.031 Langit-langit plywood 4 mm + rangka kayu meranti
I.032 Langit-langit akustik (30 x 60) cm + rangka kayu jati
I.033 Langit-langit akustik (30 x 60) cm + rangka kayu kamper
I.034 Langit-langit akustik (30 x 60) cm + rangka kayu borneo
I.035 Langit-langit akustik (30 x 60) cm + rangka kayu bengkirai
I.036 Langit-langit akustik (30 x 60) cm + rangka kayu kruing
I.037 Langit-langit akustik (30 x 60) cm + rangka kayu meranti
I.038 Langit-langit akustik (30 x 30) cm + rangka kayu jati
I.039 Langit-langit akustik (30 x 30) cm + rangka kayu kamper
I.040 Langit-langit akustik (30 x 30) cm + rangka kayu borneo
I.041 Langit-langit akustik (30 x 30) cm + rangka kayu bengkirai
I.042 Langit-langit akustik (30 x 30) cm + rangka kayu kruing
I.043 Langit-langit akustik (30 x 30) cm + rangka kayu meranti
I.044 Langit-langit gypsum board (120x240x9) mm, tebal 9 mm
I.045 Langit-langit tripleks (120x240) cm, tebal 3 mm
I.046 Langit-langit tripleks (120x240) cm, tebal 4 mm
I.047 Langit-langit lambriziring kayu jati, tebal 9 mm
I.048 Langit-langit lambriziring kayu kamper, tebal 9 mm
I.049 List langit-langit kayu profil
I.050 List langit-langit gypsum
I.051 Langit-langit Kalsiboard 6 mm + rangka kayu meranti
I.052 Langit-langit eternit (1,00 x 1,00) m x 3,5 mm + rangka kayu meranti
I.053 Langit-langit Gypsum board 9mm + Rangka aluminium
I.054 Langit-langit Kalsiboard 9mm + Rangka galvalum
I.055 Dinding partisi gypsum 2 x 12 mm, rangka galvalum
I.056 Plafond Papan Grill 3/30 cm (Uk.25x25 cm) + Politur
I.057 Langit-langit asbes (1,00 x 1,00) m x 3,5 mm + rangka kayu lama

X. PEKERJAAN SANITASI
J.001 Pasang kloset jongkok teraso
J.002 Pasang kloset jongkok porselin kw. A
J.003 Pasang kloset jongkok lux
J.004 Pasang kloset duduk porselin kw. A
J.005 Pasang kloset duduk lux
J.006 Pasang urinoir
J.007 Pasang wastafel kw. A
J.008 Pasang wastafel lux
J.009 Pasang tempat sabun keramik
J.010 Pasang bak mandi teraso volume 0.3 m3
J.011 Pasang bak mandi fibreglass volume 0.3 m3
J.012 Pasang bak mandi batu bata volume 0.3 m3
J.013 Pasang badkip porselen
J.014 Pasang bak beton volume 1.0 m3, head 2.5 m
J.015 Pasang pipa penyalur air limbah jenis pipa tanah, diameter 15 cm
J.016 Pasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm
J.017 Pasang pipa beton, diameter 20 cm
J.018 Pasang pipa beton, diameter 30 cm
J.019 Pasang pipa beton, diameter 40 cm
J.020 Pasang pipa beton, diameter 50 cm
J.021 Pasang pipa beton, diameter 60 cm
J.022 Pasang pipa beton, diameter 80 cm
J.023 Pasang pipa beton, diameter 90 cm
J.024 Pasang pipa beton, diameter 100 cm
J.025 Pasang pipa beton U, diameter 20
J.026 Pasang pipa beton U, diameter 30
J.027 Pasang bak kontrol pasangan batu bata ukuran (30 x 30) tinggi 35 cm
J.028 Pasang bak kontrol pasangan batu bata ukuran (45 x 45) tinggi 50 cm
J.029 Pasang bak kontrol pasangan batu bata ukuran (60 x 60) tinggi 65 cm
J.030 Pasang pipa galvanis, diameter 1/2"
J.031 Pasang pipa galvanis, diameter 3/4"
J.032 Pasang pipa galvanis, diameter 1"
J.033 Pasang pipa galvanis, diameter 1 1/2"
J.034 Pasang pipa galvanis, diameter 2"
J.035 Pasang pipa galvanis, diameter 2 1/2"
J.036 Pasang pipa galvanis, diameter 3"
J.037 Pasang pipa galvanis, diameter 4"
J.038 Pasang pipa PVC tipe AW, diameter 1/2"
J.039 Pasang pipa PVC tipe AW, diameter 3/4"
J.040 Pasang pipa PVC tipe AW, diameter 1"
J.041 Pasang pipa PVC tipe AW, diameter 1 1/2"
J.042 Pasang pipa PVC tipe AW, diameter 2"
J.043 Pasang pipa PVC tipe AW, diameter 2.5"
J.044 Pasang pipa PVC tipe AW, diameter 3"
J.045 Pasang pipa PVC tipe AW, diameter 4"
J.046 Pasang pipa PVC tipe AW, diameter 6"
J.047 Pasang pipa PVC tipe AW, diameter 8"
J.048 Pasang pipa PVC tipe D, diameter 1/2"
J.049 Pasang pipa PVC tipe D, diameter 3/4"
J.050 Pasang pipa PVC tipe D, diameter 1"
J.051 Pasang pipa PVC tipe D, diameter 1 1/2"
J.052 Pasang pipa PVC tipe D, diameter 2"
J.053 Pasang pipa PVC tipe D, diameter 2.5"
J.054 Pasang pipa PVC tipe D, diameter 3"
J.055 Pasang pipa PVC tipe D, diameter 4"
J.056 Pasang pipa PVC tipe C, diameter 1/2"
J.057 Pasang pipa PVC tipe C, diameter 3/4"
J.058 Pasang pipa PVC tipe C, diameter 1"
J.059 Pasang pipa PVC tipe C, diameter 1 1/2"
J.060 Pasang pipa PVC tipe C, diameter 2"
: J.061 Pasang pipa PVC tipe C, diameter 2.5"
J.062 Pasang pipa PVC tipe C, diameter 3"
J.063 Pasang pipa PVC tipe C, diameter 4"
J.064 Pasang bak cuci piring stainles steel
J.065 Pasang bak cuci piring teraso
J.066 Pasang kran diameter 1/2"
J.067 Pasang kran diameter 3/4"
J.068 Pasang Afor Stainless Steel
J.069 Pasang Afor Plastik
J.070 Pasang kaca wastafel
J.071 Pasang pipa screen PVC tipe AW, diameter 3"
J.072 Pasang pipa screen PVC tipe AW, diameter 4"
J.073 Pasang pipa Staenless steel, diameter 2"

XI. PEKERJAAN BESI DAN ALUMINIUM


K.001 Pasang besi profil
K.002 Pasang rangka kuda-kuda baja WF
K.003 Pemasangan baut anker baja
K.004 Ikatan angin/Trekstang
K.005 Plendes
K.006 Pasang pintu plat baja tebal 2 mm rangkap, rangka baja siku
K.007 pengelasan dengan las listrik
K.008 Pasang pintu gulung besi (rolling door)
K.009 Pasang pintu lipat (folding door)
K.010 Pasang sunscream alluminium
K.011 Pasang Rolling door Aluminium
K.012 Pasang Kusen Alluminium Coklat
K.013 Pasang pintu Alluminium coklat strip lebar 8 cm
K.014 Pasang Pintu Kaca Rangka Aluminium Coklat
Daun Pintu 80 x 210 cm
Daun Jendela (0,65 m2)
Daun Jendela BV 60 x 50 cm
K.015 Pasang venetion blinds dan vertical blinds (tirai)
K.016 Pasang teralis besi (2 x 3) mm
K.017 Pasang kawat nyamuk
K.018 Pasang jendela nako & trails
K.019 Pasang pintu fiber KM
K.020 Pasang talang datar, seng bjls 30 L = 0.60 m
K.021 Pasang talang datar, seng bjls 30 L = 0.90 m
K.022 Pasang talang miring, seng bjls 30 L = 0.60 m
K.023 Pasang talang miring, seng bjls 30 L = 0.90 m
K.024 Pasang talang tegak pipa PVC f 3"
K.025 Pasang talang tegak pipa PVC f 4"
K.026 Pasang talang 1/2 lingkaran D-15 cm bjls 30, L = 45 cm
K.027 Pasang pagar BRC tinggi 1 m
K.028 Pasang tiang pagar BRC Dia 2" tinggi 1 m
K.029 Pasang pintu pagar BRC tinggi 1 m
K.030 Pasang pagar besi
K.031 Pasang pintu pagar besi
K.032 Pasang Atap Baja Ringan untuk Penutup Atap Genteng
K.033 Pasang Atap Baja Ringan untuk Penutup Atap Asbes Gelombang
K.034 Pasang rangka Plafon Metal Furing
K.035 Pasang pagar besi hollow
K.036 Pasang pagar besi hollow
K.037 Pasang pintu pagar besi hollow
K.038 1 m2 Pasang Rangka atap (Usuk+reng Zincalume)
XII. PEKERJAAN KUNCI DAN KACA
L.001 Pasang kunci tanam antik
L.002 Pasang kunci tanam biasa
L.003 Pasang kunci tanam kamar mandi
L.004 Pasang kunci silinder
L.005 Pasang kunci selot
L.006 Pasang kunci lemari
L.007 Pasang engsel pintu
L.008 Pasang engsel jendela
L.009 Pasang grendel pintu
L.010 Pasang grendel jendela
L.011 Pasang hak angin
L.012 Pasang spring knip
L.013 Pasang kait angin
L.014 Pasang door closer
L.015 Pasang pegangan pintu/door holder
L.016 Pasang door stop
L.017 Pasang rel pintu dorong
L.018 Pasang kaca polos, tebal 3 mm
L.019 Pasang kaca polos, tebal 5 mm
L.020 Pasang kaca polos, tebal 8 mm
L.021 Pasang kaca polos, tebal 12 mm
L.022 Pasang kaca buram, tebal 3 mm
L.023 Pasang kaca buram, tebal 5 mm
L.024 Pasang kaca buram, tebal 8 mm
L.025 Pasang kaca buram, tebal 12 mm
L.026 Pasang kaca cermin, tebal 5 mm
L.027 Pasang kaca cermin, tebal 6 mm
L.028 Pasang kaca cermin, tebal 8 mm
L.029 Pasang kaca rayben, tebal 3 mm
L.030 Pasang kaca rayben, tebal 5 mm
L.031 Pasang kaca rayben, tebal 8 mm
L.032 Pasang kaca rayben, tebal 12 mm
L.033 Pasang kaca " wireglass", tebal 5 mm
L.034 Pasang kaca patri, tebal 5 mm
L.035 Pasang glass block
L.036 Pasang kaca painting glass
L.037 Pasang casement
L.038 Pasang kaca polos, tebal 12 mm termpered

XIII. PEKERJAAN LANTAI DAN DINDING


M.001 Pasang lantai ubin pc abu-abu ukuran 40 x 40 cm
M.002 Pasang lantai ubin pc abu-abu ukuran 30 x 30 cm
M.003 Pasang lantai ubin pc abu-abu ukuran 20 x 20 cm
M.004 Pasang lantai ubin pc warna ukuran 40 x 40 cm
M.005 Pasang lantai ubin pc warna ukuran 30 x 30 cm
M.006 Pasang lantai ubin pc warna ukuran 20 x 20 cm
M.007 Pasang lantai ubin teraso ukuran 40 x 40 cm
M.008 Pasang lantai ubin teraso ukuran 30 x 30 cm
M.009 Pasang lantai ubin granito ukuran 40 x 40 cm
M.010 Pasang lantai ubin granito ukuran 30 x 30 cm
M.011 Pasang lantai ubin teralux kerang ukuran 40 x 40 cm
M.012 Pasang lantai ubin teralux kerang ukuran 30 x 30 cm
M.013 Pasang lantai ubin teralux marmer ukuran 60 x 60 cm
M.014 Pasang lantai ubin teralux marmer ukuran 40 x 40 cm
M.015 Pasang lantai ubin teralux marmer ukuran 30 x 30 cm
M.016 Pasang plint ubin pc abu-abu ukuran 15 x 20 cm
M.017 Pasang plint ubin pc abu-abu ukuran 10 x 30 cm
M.018 Pasang plint ubin pc abu-abu ukuran 10 x 40 cm
M.019 Pasang plint ubin pc warna ukuran 10 x 20 cm
M.020 Pasang plint ubin pc warna ukuran 10 x 30 cm
M.021 Pasang plint ubin pc warna ukuran 10 x 40 cm
M.022 Pasang plint ubin teraso ukuran 10 x 30 cm
M.023 Pasang plint ubin teraso ukuran 10 x 40 cm
M.024 Pasang plint ubin granito ukuran 10 x 40 cm
M.025 Pasang plint ubin granito ukuran 10 x 30 cm
M.026 Pasang teraso cor di tempat, tebal 3 cm
M.027 Pasang lantai keramik artistik 10 x 20 cm
M.028 Pasang lantai keramik artistik 10 x 10 cm
M.029 Pasang lantai keramik artistik 5 x 20 cm
M.030 Pasang dinding keramik artistik 10 x 20 cm
M.031 Pasang dinding keramik artistik 5 x 20 cm
M.032 Pasang plint keramik artistik 10 x 20 cm
M.033 Pasang plint keramik artistik 10 x 10 cm
M.034 Pasang plint keramik artistik 5 x 20 cm
M.035 Pasang internal cove artistik (5 x 5 x 20) cm
M.036 Pasang gymflour
M.037 Pasang lantai parquet
M.038 Pasang lantai karpet
M.039 Pasang lantai keramik ukuran 20 x 20 cm putih
M.040 Pasang lantai keramik ukuran 20 x 20 cm warna/motif
M.041 Pasang lantai keramik KM ukuran 20 x 20 cm
M.042 Pasang lantai keramik ukuran 30 x 30 cm putih
M.043 Pasang lantai keramik ukuran 30 x 30 cm warna/motif
M.044 Pasang lantai keramik ukuran 40 x 40 cm putih
M.045 Pasang lantai keramik ukuran 40 x 40 cm warna/motif
M.046 Pasang lantai marmer ukuran 100 x 100 cm
M.047 Pasang plint keramik lantai ukuran 10 x 20 cm
M.048 Pasang plint keramik lantai ukuran 10 x 30 cm
M.049 Pasang plint keramik lantai ukuran 10 x 40 cm
M.050 Pasang dinding porselin ukuran 15 x 15 cm, putih
M.051 Pasang dinding porselin ukuran 11 x 11 cm, putih
M.052 Pasang dinding porselin ukuran 11 x 11 cm, warna
M.053 Pasang dinding porselin ukuran 15 x 15 cm, warna
M.054 Pasang dinding porselin ukuran 10 x 20 cm, warna
M.055 Pasang dinding porselin ukuran 20 x 20 cm, warna
M.056 Pasang dinding keramik ukuran 20 x 20 cm
M.057 Pasang dinding keramik ukuran 20 x 25 cm
M.058 Pasang dinding batu tempel hitam
M.059 Pasang lantai vinyl ukuran (30x30)cm KL I
M.060 Pasang wallpaper, lebar 50 cm
M.061 Pasang dinding batu palimanan
M.062 Pasang dinding granito
M.063 Pasang dinding marmer ukuran 100 x 100 cm
M.064 Pasang dinding teraso
M.065 Pasang paving stone (blok) segi empat biasa
M.066 Pasang paving stone (blok) segi empat warna
M.067 Pasang paving stone (blok) Segi Enam biasa
M.068 Pasang paving stone (blok) Segi Enam Warna
M.069 Pasang paving stone (blok) Tiga Berlian biasa
M.070 Pasang paving stone (blok) Tiga Berlian warna
M.071 Pasang Batu Ampyangan Granit
M.072 Pasang dinding keramik ukuran 10 x 20 cm, Warna / Motif
M.073 Pasang dinding batu sisir

XIV. PEKERJAAN PENGECATAN


N.001 Mengikis/mengerok permukaan cat lama
N.002 Mencuci bidang permukaan cat tembok lama
N.003 mengerok karat cat lama permukaan baja dengan cara manual
N.004 menyabun permukaan tembok lama
N.005 mengerok karat/cat lama permukaan baja dengan pancar pasir (sandblasting) dengan tingkat kebersihan Sa 2,5
N.006 Mendempul dan menggosok kayu
N.007 Pengecatan kayu lama
N.008 Pengecatan kayu baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
N.009 Pengecatan kayu baru (1 lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup)
N.010 Pelaburan kayu dengan teak oil
N.011 Pelaburan kayu dengan politur
N.012 Pelaburan kayu dengan cat residu dan ter
N.013 Pelaburan kayu dengan vernis
N.014 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
N.015 Pengecatan tembok baru interior 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
N.016 Pengecatan tembok baru eksterior lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
N.017 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
N.018 Melabur tembok dengan kalkarium
N.019 Melabur tembok dengan kapur sirih
N.020 Melabur tembok lama dengan kapur sirih (untuk pemeliharaan)
N.021 Pengecatan plafon (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
N.022 Pengecatan permukaan baja dengan meni besi
N.023 Pengecatan permukaan baja dengan cat besi
N.024 Pengecatan permukaan baja
N.025 Pengecatan permukaan baja dengan meni besi dan perancah
N.026 Pengecatan permukaan baja lapis seng (galbani) secara manual sistem 1 lapis cat mutakhir tebal 0.20 mm
N.027 Pengecatan permukaan baja lapis seng (galbani) secara manual sistem 3 lapis cat konvensional tebal 0.20 mm
N.028 Pengecatan permukaan baja lapis seng (galbani) secara semprot less spray) sistem 1 lapis cat mutakhir tebal 0.20 mm
N.029 Pekerjaan waterproofing
N.030 Pengecatan tembok LAMA eksterior (1 lapis cat dasar, 2 lapis cat penutup)
N.031 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar 2 lapis cat penutup)_CAT MINYAK
N.032 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat p dengan CAT MINYAK
N.033 Coating batu alam / Batu hias

XVI. PEKERJAAN INSTALASI LISTRIK


P.001 Pemasangan stop kontak
P.002 Pemasangan saklar tunggal
P.003 Pemasangan saklar ganda
P.004 Pemasangan titik lampu pijar 5 - 40 watt
P.005 Pemasangan titik lampu pijar 50 - 100 watt
P.006 Pemasangan titik lampu TL 20 Watt (komplit)
P.007 Pemasangan titik lampu TL 40 Watt (komplit)
P.008 Pemasangan titik lampu XL 5 Watt
P.009 Pemasangan titik lampu XL 8 Watt
P.010 Pemasangan titik lampu XL 14 Watt
P.011 Pemasangan titik lampu XL 18 Watt
P.012 Pemasangan titik lampu XL 23 Watt
P.013 Pemasangan sekering 1 group
P.014 Pemasangan sekering 2 group
P.015 Pemasangan sekering 3 group
P.016 Pemasangan penangkal petir
P.017 Pemasangan titik Instalasi

XVII. PEKERJAAN AIR BERSIH


Q.001 Penyetelan mesin bor dan buat bak sirkulasi
Q.002 Geolistrik
Q.003 Pemboran pilot hole 8 3/4" kedalaman 0 - 25 m kecepatan pemboran 15 m'/hr
Q.004 Pemboran pilot hole 8 3/4" kedalaman 25 - 50 m kecepatan pemboran 12 m'/hr
Q.005 Pemboran pilot hole 8 3/4" kedalaman 50 - 75 m kecepatan pemboran 10 m'/hr
Q.006 Pemboran pilot hole 8 3/4" kedalaman 75 - 100 m kecepatan pemboran 8 m'/hr
Q.007 Pemboran pilot hole 8 3/4" kedalaman 100 - 125 m kecepatan pemboran 6 m'/hr
Q.008 Pemboran pilot hole 8 3/4" kedalaman 125 - 175 m kecepatan pemboran 4 m'/hr
Q.009 Pemboran pilot hole 8 3/4" kedalaman 175 - 225 m kecepatan pemboran 3 m'/hr
Q.010 Pemboran pilot hole 8 3/4" kedalaman 225 - 275 m kecepatan pemboran 2 m'/hr
Q.011 Geofisikal, Elektrikal, Logging
Q.012 Pumping test open hole
Q.013 Pembesaran lubang (Reaming) lubang bor 8 3/4" - 12" kedalaman 0 - 25 m kecepatan pemboran 18 m'/hr
Q.014 Pembesaran lubang (Reaming) lubang bor 8 3/4" - 12" kedalaman 25 - 50 m kecepatan pemboran 15 m'/hr
Q.015 Pembesaran lubang (Reaming) lubang bor 8 3/4" - 12" kedalaman 50 - 75 m kecepatan pemboran 12 m'/hr
Q.016 Pembesaran lubang (Reaming) lubang bor 8 3/4" - 12" kedalaman 75 - 100 m kecepatan pemboran 9 m'/hr
Q.017 Pembesaran lubang (Reaming) lubang bor 8 3/4" - 12" edalaman 100 - 125 m kecepatan pemboran 7 m'/hr
Q.018 Pembesaran lubang (Reaming) lubang bor 8 3/4" - 12" edalaman 125 - 175 m kecepatan pemboran 5 m'/hr
Q.019 Pembesaran lubang (Reaming) lubang bor 8 3/4" - 12" edalaman 175 - 225 m kecepatan pemboran 3 m'/hr
Q.020 Pengadaan dan pemasangan pipa jambang PVC-AW 150 mm
Q.021 Pengadaan dan pemasangan pipa buta PVC-AW 150 mm
Q.022 Pengadaan dan pemasangan pipa screen PVC-AW 150 mm
Q.023 Pengadaan dan pemasangan pipa jambang PVC-AW 125 mm
Q.024 Pengadaan dan pemasangan pipa buta PVC-AW 125 mm
Q.025 Pengadaan dan pemasangan pipa screen PVC-AW 125 mm
Q.026 Pengadaan dan pemasangan pipa sounding PVC-AW 2.50"
Q.027 Pengadaan dan pemasangan pipa sounding SWL PVC-AW 1"
Q.028 Pengisian gravel pack Dia 5 mm - 10 mm
Q.029 Beton Mortar 1 pc 1 ps
Q.030 Pencucian sumur bor dengan kedalaman < 200 m
Q.031 Pencucian sumur bor dengan kedalaman > 200 m
Q.032 Pumping test dan test nonstop 24 jam
Q.033 Pasang pipa PVC Moof 6 m S-12.5 2"
Q.034 Pasang pipa PVC Moof 6 m S-12.5 2.5"
Q.035 Pasang pipa PVC Moof 6 m S-12.5 3"
Q.036 Pasang pipa PVC Moof 6 m S-12.5 4"
Q.037 Pasang pipa PVC Moof 6 m S-12.5 6"
Q.038 Pasang pipa PVC Moof 6 m S-12.5 8"
Q.039 Pasang pipa Moof S-12.5 2" lintas jalan
Q.040 Pasang pipa Moof S-12.5 3" lintas jalan
Q.041 Pasang pipa PVC Moof S-12.5 4" lintas jalan
Q.042 Pasang pompa air
Q.043 Pasang tandon air PVC V = 0.50 m3
Q.044 Pasang tandon air PVC V = 1.0 m3
Q.045 Pasang tandon air stainless V = 0.5 m3
Q.046 Pasang tandon air stainless V = 1.0 m3
XVIII. PEKERJAAN PENUNJANG IRIGASI
R.001 Pengukuran bendung untuk MC
R.002 Pengukuran saluran untuk MC
R.003 Pengukuran bangunan untuk MC
R.004 Pendongkelan rumpun bambu
R.005 Pembuatan dan pembongkaran kisdam > 1 m
R.006 Galian tanah biasa diangkut > 1 m dibuang
R.007 Galian tanah biasa diangkut > 50 m dibuang
R.008 Galian tanah berbatu diangkut > 1 m dibuang
R.009 Galian tanah berbatu diangkut > 50 m dibuang
R.010 Galian tanah keras/cadas diangkut > 1 m dibuang
R.011 Galian tanah keras/cadas diangkut > 50 m dibuang
R.012 Galian tanah biasa langsung untuk timbunan / dibuang
R.013 Pemadatan tanah timbunan & dirapikan
R.014 Timbunan tanah kembali dipadatkan dan dirapikan (manual)
R.015 Timbunan tanah dari luar dipadatkan dan dirapikan (manual)
R.016 Bongkaran pasangan batu kali
R.017 Pasangan batu kali dengan spesi 1 pc ; 4 ps
R.018 Siaran dengan spesi 1 pc ; 2 ps
R.019 Plesteran tebal 1,5 cm dengan spesi 1 pc ; 3 ps
R.020 Bronjong kawat galvanis d = 4 mm (0.50 x 1.00 x 2.00)
R.021 Beton K-125
R.022 Beton K-175
R.023 Bekisting kayu termasuk pembongkaran
R.024 Besi Tulangan Ulir
R.025 Besi Tulangan Polos
R.026 Kisi-Kisi
R.027 Pintu Air Type A Plat
R.028 Pintu Air Type C - 2
R.029 Pintu Air Type C - 3
R.030 Pintu Air Type C - 3
R.031 Pintu Air Type C - 3
R.032 Pintu Air Type C - 5

XIX. PEKERJAAN LAIN - LAIN


S.001 Menanam rumput lamur
S.002 Menanam rumput manila
S.003 Menanam semak hias
S.004 Menanam pohon pelindung
S.005 Pengisian koral sumur resapan
S.006 Menanam gebalan rumput
S.007 Pasang papan kayu jembatan gantung, kayu kamper
S.008 Menanam Rumput Common Bermuda Grass
S.009 Penyiraman Rumput
S.010 Penyiangan / Pematunan Rumput
S.011 Pemotongan Rumput
S.012 Pemupukan
S.013 Pemberian Obat Tanaman
S.014 Pasang Mistar Gawang
S.015 Pasang Jala Gawang
S.016 Pembuatan Garis Lapangan
S.017 Pasang pipa besi 1.5" untuk tangga dan pagar
S.018 Pasang besi polos untuk tangga
S.019 Pasang Pipa Udara GI 2"
S.020 Pasang Pompa submersible Q = 3,5 l/det, H = 150 m
S.021 Pasang Flange Pipe 3" - 0.35 m
S.022 Pasang Flange Pipe 4" - 0.35 m
S.023 Pasang Flange Pipe 4" - 1 m
S.024 Pasang All Flange Wall Pipe 4" - 0.5 m
S.025 Pasang Bend Socket PVC 2" 90
S.026 Pasang Bend Socket PVC 2" x 45
S.027 Pasang Tee All Socket PVC 2" x 2"
S.028 Pasang Tee All Socket PVC 3" x 2"
S.029 Pasang Tee All Socket PVC 3" x 3"
S.030 Pasang Flange Gate Valve 2"
S.031 Pasang Flange Gate Valve 3"
S.032 Pasang Bend All Flange GI 3" x 90
S.033 Pasang Bend All Flange GI 3" x 45
S.034 Pasang Flange Socket 2"
S.035 Pasang Flange Socket 3"
S.036 Pasang Flange Spigot 2"
S.037 Pasang Flange Spigot 3"
S.038 Pasang Straatport 2"
S.039 Pasang Straatport 3"
S.040 Pasang Flange Check Valve 3"
S.041 Pasang Flange Air Valve 1"
S.042 Pasang Flange Air Valve 2"
S.043 Pasang Flange Water Meter 3"
S.044 Pasang Manometer 10 bar
S.045 Pasang Dop PVC 2"
S.046 Pasang Dop PVC 3"
S.047 Uji Coba Instalasi Pipa
S.048 Pasang Kabel Pompa NYYHY 3 x 4 mm
S.049 Pasang Kabel Elektrode NYYHY 3 x 1.5 mm
S.050 Pasang Panel Pompa
S.051 Pasang Junction Box
S.052 Pasang Elektrode Pompa

Catatan : Harga belum termasuk PPn 10 %


UKSI (HSPK)

HARGA
SATUAN
( Rp )
3 4

m 439,460.78
m 542,497.73
m 591,984.80
m 30,036.60
m 76,456.55
m 1,638,634.34
m 1,653,268.23
m 1,509,867.63
m 7,548.75
m 1,670,653.86
bh 329,812.81
m 79,096.14
m 520,525.50
m3 307,717.58
m3 288,165.08
m 50,448.75
m 9,231.75
m 12,681.90
m 1,509.75
m 6,053.44
m 52,965.00
m 3,250.50
m 2,307.94

m3 33,804.38
m3 41,542.88
m3 49,411.73
m3 44,985.60
m3 68,260.50
m3 54,412.88
m2 2,470.88
m3 14,808.75
m3 13,847.63
m3 24,708.75
m3 106,396.35
m3 332,000.24
m3 474,664.87
m2 114,332.63
m3 143,217.98
m3 95,157.98
m3 103,809.88
m3 86,431.52
m3 215,069.27
m3 34,096.51
m3 32,729.46
m3 548,715.00
m3 499,215.00
m3 464,925.00
m3 440,805.00
m3 407,775.00
m3 533,155.35
m3 565,152.80
m3 518,503.85
m3 211,864.66
m3 1,904,538.29
m3 591,952.94

m 184,920.75
m 171,668.25
m 163,208.25
m 158,145.75
m 154,950.75
m 179,495.69
m 88,500.38
m 82,497.38
m 78,892.88
m 76,615.88
m 75,139.88
m 72,772.88
m 91,109.39
m 89,726.27
m 84,268.85
m 195,870.53
m 191,649.53
m 159,050.10
m 155,801.10
m 121,341.38
m 119,410.88
m 329,467.88
m 325,687.88
m 113,553.00
m 980,253.38

m 44,843.40
m 38,075.40
m 35,040.60
m 33,057.00
m 31,811.40
m 30,864.60
m 30,306.60
m 29,748.60
m 36,670.75
m 36,379.62
m 38,631.65
m 35,992.94
m 50,927.55
m 40,288.58
m 44,206.35
m 42,575.55
m 41,283.15
m 48,884.60
m 20,635.13
m 28,538.70
m 165,439.73
m 153,559.73
m 25,969.88
m 32,112.00
m 16,902.00
m 19,369.50
m 18,253.58
m 8,430.75

m3 15,620,640.75
m3 12,788,104.50
m3 11,719,763.10
m3 8,040,046.50
m 682,454.78
m 538,436.78
m 518,527.52
m 355,250.78
m 838,217.25
m 694,199.25
m 674,289.99
m2 511,013.25
bh 858,502.26
m2 538,013.25
bh 790,879.48
m 546,663.60
m 460,252.80
m 448,307.24
m 452,081.87
bh 759,497.53
bh 293,853.21
bh 135,624.56
m 1,201,097.25
m 970,668.45
m 938,813.63
m 677,570.85
bh 372,663.97
m 640,421.78
m 550,410.53
m 537,967.24
m 435,919.28
m 1,076,048.63
m 860,021.63
m 830,157.74
m 585,242.63
m 653,814.00
m 563,802.75
m 551,359.46
m 449,311.50
m 760,265.40
m 670,254.15
m 657,810.86
m 555,762.90
m 757,691.40
m 672,165.86
m 570,117.90
m3 15,175,413.00
m3 11,609,928.00
m3 10,630,615.05
m3 8,579,785.50
m3 8,028,850.50
m3 7,257,541.50
m3 17,041,561.88
m3 13,151,941.88
m3 11,203,434.00
m3 6,851,047.50
m 296,208.99
m 210,441.44
m 199,202.02
m 159,154.40
m 142,165.56
m 120,929.52
m 296,208.99
m 210,441.44
m 199,202.02
m 159,154.40
m 142,165.56
m 120,929.52
m 320,016.36
m 226,668.98
m 214,859.22
m 171,325.05
m 152,893.77
m 129,854.67
m 235,029.54
m 169,679.81
m 159,122.13
m 128,359.69
m 115,137.25
m 98,609.20
m 236,615.12
m 175,622.04
m 165,768.20
m 137,056.59
m 124,715.65
m 109,289.47
m 171,384.38
m 140,000.93
m 137,330.01
m 91,318.31
m 91,318.31
m 90,236.47
m 183,525.38
m 143,920.43
m 138,445.38
m 91,581.60
m 91,581.60
m 93,544.28
m 393,309.53
m 302,551.73
m 277,623.76
m 191,763.71
m 488,414.87
m 397,657.07
m 372,729.10
m 286,869.05
m 501,529.23
m 410,771.43
m 385,843.46
m 299,983.41
m 242,098.65
m 216,895.50
m3 1,142,163.00
m3 735,669.00
m 190,157.01

m3 652,129.59
m3 689,296.17
m3 718,354.75
m3 610,191.84
m3 752,866.76
m3 785,554.47
m3 810,384.78
m3 853,388.76
m3 826,255.34
m3 861,858.75
m3 918,856.92
m3 929,886.63
m3 999,953.25
m 46,962.90
m 81,806.40
m 95,096.85
kg 11,225.79
kg 15,853.14
kg 31,879.50
kg 20,280.53
m 194,244.60
m 116,598.90
m 212,807.10
m 125,880.15
m 355,664.70
m 202,552.65
m 365,581.53
m 207,511.07
m 466,040.70
m 257,740.65
m 397,509.75
m 223,475.18
m 318,411.00
m 183,925.80
m 123,964.63
m3 3,342,118.25
m3 4,270,885.85
m3 5,538,759.27
m3 7,445,442.20
m3 5,776,853.07
m3 5,153,065.85
m3 5,265,687.80
m 57,314.22
m 78,390.78
m 77,446.98

m3 2,345,951.63
m3 2,995,222.25
m3 3,689,324.75
m3 3,600,937.92
m3 3,571,935.82
m3 4,912,050.42
m3 3,774,338.67
m3 7,750,466.13
m3 4,946,924.81
m3 3,771,773.49
m3 4,158,578.18
m3 2,635,768.92
m' 103,723.08
m' 58,948.70

m2 47,296.73
m2 50,671.73
m2 67,546.73
m2 73,171.73
m2 63,271.73
m1 51,920.85
m1 54,845.85
m1 65,240.85
m1 67,220.85
m1 70,190.85
m2 67,996.73
m2 68,221.73
m2 62,548.20
m2 90,635.40
m2 102,703.95
m2 119,327.51
m2 115,474.43
m1 62,270.85
m1 78,110.85
m1 72,962.85
m1 72,957.85
m1 139,716.70
m1 129,751.05
m1 75,340.58
m2 49,162.34
m2 53,032.11
m2 49,185.02
m2 50,157.42
m2 50,257.19
m2 65,612.39
m2 67,615.79
m2 61,111.86
m2 60,392.31
m2 102,620.99
m2 59,816.27
m2 57,652.22
m2 61,863.14
m1 126,175.35
m1 117,821.55
m1 116,711.18
m1 63,805.35
m1 63,351.75
m1 67,207.35
m1 68,861.10
m1 57,124.65
m2 66,585.51
m1 36,390.27
m2 152,475.51
m2 177,217.02
m2 42,278.10
m2 95,892.23
m2 142,298.48
m2 158,188.04
m2 182,320.02
m2 11,296.73

m2 25,937.18
m2 24,739.28
m2 24,085.88
m2 23,432.48
m2 314,848.35
m2 171,709.13
m2 61,540.13
m2 52,797.53
m2 68,875.13
m2 46,352.63
m2 52,886.63
m2 55,668.53
m2 52,144.13
m2 388,903.05
m2 137,803.05
m2 313,151.85
m2 58,809.30
m2 40,854.40
m2 248,851.65
m2 204,373.75
m2 156,846.68
m2 149,168.36
m2 126,795.68
m2 117,179.36
m2 105,158.96
m2 376,207.52
m2 285,113.96
m2 270,397.19
m2 228,925.48
m2 209,084.93
m2 186,045.83
m2 500,768.31
m2 409,674.75
m2 394,957.98
m2 352,077.00
m2 333,645.72
m2 310,606.62
m2 688,517.68
m2 581,581.76
m2 564,305.56
m2 513,967.01
m2 492,330.29
m2 564,305.56
m2 38,478.40
m 30,191.21
m 37,412.03
m 295,771.80
m 248,427.30
m1 13,645.50
m1 28,579.65
m2 125,317.16
m2 105,708.41
m2 105,260.40
m2 129,264.98
m2 163,255.50
m2 528,324.56
m2 45,657.98

bh 220,271.25
bh 374,214.00
bh 536,241.00
bh 1,808,339.66
bh 1,909,411.19
bh 1,528,080.75
bh 641,961.78
bh 1,637,598.66
bh 37,888.13
bh 290,859.75
bh 646,304.88
bh 895,296.00
bh 1,000,564.13
bh 9,261,115.34
m1 156,862.56
m1 238,207.36
m1 70,246.84
m1 130,263.09
m1 163,708.77
m1 197,337.59
m1 243,059.27
m1 370,469.33
m1 405,865.31
m1 486,271.64
m 65,880.94
m 157,000.04
bh 212,001.69
bh 313,852.53
bh 476,708.70
m1 61,250.18
m1 76,630.05
m1 101,091.38
m1 150,092.60
m1 208,389.65
m1 284,996.07
m1 318,859.70
m1 469,583.38
m1 16,829.87
m1 22,542.39
m1 27,961.97
m1 35,871.62
m1 46,776.62
m1 57,908.72
m1 82,398.86
m1 122,386.53
m1 210,314.25
m1 321,034.66
m1 10,970.87
m1 13,900.37
m1 16,536.92
m1 20,491.74
m1 26,416.60
m1 35,058.62
m1 51,346.16
m1 67,458.41
m1 9,506.12
m1 11,703.24
m1 13,753.89
m1 16,683.39
m1 23,194.15
m1 27,441.92
m1 34,940.96
m1 41,239.38
bh 319,712.51
bh 250,245.19
bh 45,860.10
bh 50,513.10
bh 59,767.13
bh 22,246.13
m2 159,708.66
m1 89,568.62
m1 129,556.30
m1 189,710.60

kg 28,138.09
kg 28,138.09
kg 20,400.60
kg 20,728.84
kg 28,138.09
m 844,055.03
cm 5,053.00
m2 2,150,077.05
m2 1,646,535.45
m2 357,089.70
m2 1,289,541.75
m1 124,673.75
m2 729,745.75
m2 902,743.53
bh 902,743.53
bh 349,275.77
bh 161,204.20
m2 568,821.53
m2 443,524.75
m2 101,632.96
m2 347,009.03
Unit 384,966.86
m1 195,312.93
m1 205,140.93
m1 195,312.93
m1 205,140.93
m1 52,347.60
m1 64,278.23
m1 63,106.95
m 337,597.26
bh 201,584.76
m 550,249.92
m 570,022.49
m 709,410.37
m 295,698.23
m 265,191.39
m 128,487.32
m 546,067.65
m 579,763.77
m 634,844.14
m 98,566.13
bh 130,637.03
bh 138,238.13
bh 117,721.31
bh 172,780.67
bh 146,613.68
bh 27,342.09
bh 20,399.88
bh 15,201.92
bh 30,863.76
bh 18,388.84
bh 32,414.25
bh 21,890.76
bh 15,661.84
bh 201,820.69
bh 157,680.19
bh 42,405.34
bh 168,909.53
m 96,427.86
m 141,542.16
m 265,034.76
m 377,290.86
m 144,531.54
m 208,980.54
m 234,761.26
m 369,064.66
m 159,708.66
m 285,052.56
m 386,061.80
m 139,463.16
m 200,169.96
m 400,995.95
m 634,259.75
m 661,084.26
m 1,430,730.06
bh 34,161.81
m 590,086.41
bh 45,185.25
m2 827,290.86

m2 51,136.60
m2 58,178.94
m2 67,234.43
m2 58,577.36
m2 63,363.57
m2 76,811.69
m2 66,453.80
m2 75,114.87
m2 279,774.05
m2 271,361.58
m2 307,699.61
m2 451,583.79
m2 254,023.20
m2 383,866.88
m2 657,979.35
m1 27,165.90
m1 22,139.67
m1 20,226.00
m1 20,883.00
m1 19,444.44
m1 20,358.30
m1 25,766.67
m1 26,654.70
m1 44,494.50
m1 41,492.82
m2 33,389.93
m2 526,136.25
m2 978,581.10
m2 978,581.10
m2 540,186.75
m2 991,829.70
m1 93,281.93
m1 175,392.75
m1 92,345.35
m2 196,052.03
m2 324,360.75
m2 310,379.48
m2 95,603.33
m2 123,617.26
m2 123,617.26
m2 127,327.26
m2 122,663.50
m2 127,411.50
m2 149,663.10
m2 165,255.60
m2 479,071.65
m1 35,374.13
m1 76,241.82
m1 88,560.75
m2 133,189.50
m2 161,206.50
m2 178,234.50
m2 135,619.50
m2 139,029.75
m2 139,368.87
m2 155,944.62
m2 159,403.50
m2 153,560.10
m2 289,781.40
m2 157,038.53
m2 154,500.83
m2 91,823.70
m2 526,217.70
m2 74,464.05
m2 83,130.00
m2 91,230.00
m2 92,265.00
m2 94,785.00
m2 83,670.00
m2 89,610.00
m2 139,784.06
m2 146,732.00
m2 146,955.00

m 7,727.21
m 8,591.89
m 8,591.89
m 8,591.89
m 680,416.50
m 7,442.08
m 28,272.59
m 37,908.32
m 49,113.47
m 9,618.35
m 53,356.46
m 14,071.20
m 23,445.43
m 20,721.20
m 30,502.40
m 33,745.64
m 15,332.54
m 4,630.64
m 16,610.22
m 13,479.18
m 20,721.20
m 16,674.24
m 20,303.04
m 20,303.04
m 45,067.60
m 25,919.55
m 109,048.20
m 89,601.60
m 57,238.52
m 24,349.46
m 27,581.90
m 20,494.40
m 16,542.86

Titik 130,669.88
Titik 118,416.38
Titik 141,064.88
Titik 102,519.00
Titik 114,142.50
Titik 135,787.50
Titik 168,399.00
Titik 111,969.00
Titik 114,993.00
Titik 118,867.50
Titik 121,419.00
Titik 127,467.00
Unit 131,307.15
Unit 213,399.90
Unit 301,196.93
Unit 3,124,561.50
Titik 219,566.25

Unit 3,630,000.00
Ls 3,875,740.00
m 324,731.13
m 405,913.92
m 487,096.70
m 608,870.88
m 811,827.83
m 1,217,741.75
m 1,623,655.67
m 2,435,483.50
m 17,960.00
Ls 7,980,716.00
m 240,053.72
m 288,064.47
m 360,080.58
m 480,107.44
m 617,281.00
m 864,193.40
m 1,440,322.33
m 305,226.00
m 305,226.00
m 325,665.00
m 255,300.00
m 255,300.00
m 281,220.00
m 46,191.00
m 28,519.50
m3 388,154.25
m3 789,599.96
Titik 9,223,343.00
Titik 14,424,206.00
Jam 340,785.44
m1 49,796.80
m1 66,397.30
m1 99,110.96
m1 140,123.96
m1 295,144.20
m1 476,054.03
m1 122,599.24
m1 168,076.24
m1 209,089.24
Unit 870,471.38
Unit 812,420.25
Unit 1,432,068.08
Unit 2,216,221.05
Unit 3,709,335.68
bh 607,133.72
km1 859,033.72
bh 112,016.92
m 65,861.18
m3 132,016.34
m3 43,536.13
m3 53,103.55
m3 81,451.65
m3 81,418.65
m3 75,019.78
m3 81,327.73
m3 32,952.20
m3 14,648.48
m3 35,129.23
m3 106,746.20
m3 103,050.08
m3 490,589.63
m 31,536.98
m 30,424.73
m3 1,066,517.85
m3 689,296.17
m3 752,866.76
m 262,340.10
kg 15,853.14
kg 11,225.79
m 535,137.91
Buah 59,585,000.00
Buah 10,279,000.00
Buah 6,825,000.00
Buah 7,272,000.00
Buah 8,838,000.00
Buah 8,838,000.00

m 29,328.00
m 26,268.00
m 29,805.00
btg 204,762.00
m3 225,121.10
m3 24,823.50
m3 13,709,124.00
m 15,637.88
m2 68.26
m2 435.52
m2 224.32
m2 110.17
m2 262.63
m1 356,253.75
m2 76,679.63
m2 12,148.95
m1 119,663.60
kg 10,966.39
m1 208,389.65
Unit 63,456,291.25
bh 293,960.45
bh 327,128.38
bh 574,127.75
bh 370,716.50
bh 81,730.83
bh 74,030.83
bh 65,123.85
bh 103,623.85
bh 120,123.85
bh 661,509.20
bh 1,030,821.11
bh 318,087.55
bh 255,387.55
bh 149,132.64
bh 193,132.64
bh 138,132.64
bh 182,132.64
bh 69,698.96
bh 91,698.96
bh 1,195,821.11
bh 392,818.25
bh 1,266,509.20
bh 1,981,509.20
bh 196,381.90
bh 10,219.48
bh 12,419.48
Unit 2,076,230.00
m1 15,216.30
m1 9,790.48
bh 5,644,375.00
bh 486,640.00
bh 75,328.00

Malang, 28 Januari 2013


Kepala Dinas Pendidikan
Kota Malang

Dra. Sri Wahyuningtyas, M.Si.


Pembina Utama Muda
NIP. 19581218 198503 2 007
NO. URAIAN PEKERJAAN PARAMETER
Panjang Lebar
A PEKERJAAN TANAH
1 Galian tanah biasa sedalam 1 m
Bangunan utama 40.00 0.60
Pagar 22.50 0.40
Footplat 0.80 0.80

2 Urugan Kembali
(+) Galian pondasi
(-) Aanstampeng
(-) Urugan pasir
(-) Pondasi batu kali

3 Urugan Pasir
Pasir bawah pondasi 40.00 0.60
22.50 0.40
Pasir bawah lantai 34.91

B PEKERJAAN PONDASI
1 Pasangan batu Kosong

2 Pondasi batu kali 1 PC : 5 PS 40.00 0.45


22.50 0.35

Rollag bata 5.00 0.30


C PEKERJAAN PASANGAN
1 Pasangan bata 1 Pc : 5 Ps
Bangunan utama 40.00
(-) Luas Jendela + Pintu
Gewel 6.00
5.00
Pagar 18.02
4.48

2 Plesteran 1 Pc : 5 Ps
Bangunan utama 141.20
Pagar 5.38
Gewel 13.63

3 Benangan
Pagar 22.50
Sudutan luar 3.70
2.40
3.15
1.50

4 Acian

5 Pasangan beton alur 2.55 0.30


2.55 0.15
1.38 0.40

5 Kamprotan 2.30 0.77


D PEKERJAAN KERAMIK
1 Keramik utama 40 x 40
R tidur Utama 2.85 2.85
R tidur 2.85 2.35
R. keluarga 2.85 2.85
R. tamu 2.85 2.35

2 Keramik teras 30 x 30 1.15 3.00


3 Keramik lantai KM 20 x 20 1.35 1.35
4 Keramik dinding KM 20 x 25 4.60 2.00

E PEKERJAAN BETON
1 Pekerjaan Rabat & Lantai Kerja
Carport 3.55 3.00
Lantai kerja 0.80 0.80

2 Pengecoran beton K-175


Kolom praktis 11/11 3.70 0.11
Kolom gewel 11/11 1.49 0.11
1.65 0.11
Kolom pagar 11/11 2.00 0.11
Kolom teras 15/30 3.50 0.15
Balok ring 11/15 40.00 0.11
18.02 0.11
Balok gewel 11/15 19.92 0.11
Footplat 80x80x15 0.80 0.80
Plat teras 1.65 3.50

3 Pembesian dengan besi polos Panjang Jumlah


Kolom praktis 410 3.90 40.00
1.49 4.00
1.65 8.00
2.00 20.00
Kolom teras 610 10.50 6.00
Sengkang 6_200 0.49 268.95
0.90 52.50
Ringbalk 410 77.94 4.00
Sengkang 6_200 0.52 389.70
Footplat 12_200 1.20 20.00
0.90 20.00
plat teras 8_200 1.65 35.00
3.50 16.50

4 Pekerjaan bekisting
Kolom praktis 47.00 0.30
Kolom praktis 15/30 0.90 10.50
Ringbalk 10/15 77.94 0.30
Plat 7.88

F PEKERJAAN ATAP
1 Pekerjaan Rangka Galvalum 3.98 4.35
3.61 2.98
3.67 2.38

2 Pekerjaan plafon + rangka


Ruang dalam
Overstek 19.96 0.60

3 Pekerjaan atap beton


4 Pekerjaan bubungan beton 10.10
5 Pekerjaan lisplank 3/20 19.70
G PEKERJAAN KUSEN & PENGGANTUNG
1 Kusen kayu
Pintu 5.10
Jendela 1 5.00
Jendela 2 8.10
Jendela 3 6.00

Vol. kusen 44.50 0.15

2 Daun pintu panil 0.80 2.04

3 Daun pintu double triplek 0.80 2.04

4 Daun jendela 1.78 0.60


1.08 0.60

5 Selot pintu
6 Engsel pintu
7 Engsel jendela
8 Grendel jendela
9 Hak angin
10 Kaca polos 1.62 0.44
0.92 0.44

G PEKERJAAN FINISHING
1 Pengecatan dinding interior
2 Pengecatan plafon
3 Pengecatan kayu
Cat lisplank 19.70
Cat daun pintu 6.53
Cat daun jendela 0.36
0.24

4 Pengecatan genteng

H PEKERJAAN LAIN-LAIN
1 Tanaman/rumput
PARAMETER SUBVOLUME VOLUME SATUAN
Tinggi Jumlah

0.70 16.80 21.30 m3


0.50 4.50
0.80 2.00 1.02
21.30

21.30 3.11 m3
0.00
-1.65
-16.54
3.11

0.05 1.20 3.40 m3


0.05 0.45
0.05 1.75
3.40

0.00 0.00

0.70 12.60 16.54


0.50 3.94
16.54
0.23 0.35 m3

3.90 156.00 196.24 m2


-14.80
1.65 2.00 9.90
1.49 1.00 3.73
2.00 36.04
1.20 5.38
196.24

2.00 282.40 306.78 m2


2.00 10.75
1.00 13.63
306.78

2.00 45.00 95.00 m'


5.00 18.50
8.00 19.20
2.00 6.30
4.00 6.00
95.00

306.78 306.78 m2

2.00 1.53 2.85 m2


2.00 0.77
1.00 0.55
2.85

2.00 3.54 3.54 m2


1.00 8.12 29.64 m2
1.00 6.70
1.00 8.12
1.00 6.70
29.64
3.45 m2
1.82 m2
9.20 m2

0.05 1.00 0.53 0.60 m3


0.05 2.00 0.06
0.60

0.11 10.00 0.45 3.22 m3


0.11 1.00 0.02
0.11 2.00 0.04
0.11 5.00 0.12
0.30 3.00 0.47
0.15 1.00 0.66
0.15 1.00 0.30
0.15 1.00 0.33
0.20 2.00 0.26
0.10 1.00 0.58
3.22

Panjang total berat besi berat total


156.00 0.62 96.21
5.96 0.62 3.68
13.20 0.62 8.14
40.00 0.62 24.67
63.00 0.62 38.85
131.79 0.22 29.26
47.25 0.22 10.49
311.76 0.62 192.26
202.64 0.22 44.99
24.00 0.62 14.80
18.00 0.62 11.10
57.75 0.62 35.61
57.75 0.62 35.61
545.67

14.10 54.81
9.45
23.38
7.88
54.81

2.00 34.63 54.12 m2


1.00 10.76
1.00 8.73
54.12

31.46 43.44
11.98
43.44
54.12 m2
10.10 10.10
19.70 19.70
0.40 m3
4.00 20.40
2.00 10.00
1.00 8.10
1.00 6.00
44.50

0.06 0.40

1.00 1.63 m2

3.00 4.90 m2

4.00 4.27 5.57 m2


2.00 1.30
5.57

4.00 4.00 bh
6.00 6.00 set
6.00 6.00 set
6.00 bh
6.00 set
4.00 2.85 3.66 m2
2.00 0.81
3.66

306.78 m2
43.44 m2
22.78 m2
0.30 5.91
2.00 13.06
2.00 4.00 2.84
2.00 2.00 0.97
22.78
54.12 m2
RENCANA ANGGARAN BIAYA
UNIT RUMAH PERUM TLOGOMAS

NO URAIAN PEKERJAAN VOLUME SATUAN KODE HARGA SATUAN TOTAL HARGA

A PEKERJAAN PERSIAPAN
1 Pembersihan 75.00 m2 A.009 7,548.75 566,156.25
2 Pasang bowplank 23.10 m' A.005 76,456.55 1,766,146.19
2,332,302.44
B PEKERJAAN TANAH
1 Galian tanah biasa sedalam 1 m 21.30 m3 B.001 33,804.38 720,033.19
2 Urugan Kembali 3.11 m3 B.009 13,847.63 43,100.73
3 Urugan Pasir (t = 5 cm) 3.40 m3 B.011 106,396.35 361,282.11
1,124,416.03
C PEKERJAAN PONDASI
1 Pondasi batu kali 1 PC : 6 PS 16.54 m3 C.004 440,805.00 7,289,812.69
2 Rollag bata 0.35 m3 D.002 171,668.25 59,225.55
7,349,038.23
D PEKERJAAN PASANGAN
1 Pasangan bata 1 Pc : 5 Ps 196.24 m2 D.004 158,145.75 31,034,996.42
2 Plesteran 1 Pc : 4 Ps 306.78 m2 E.004 33,057.00 10,141,259.52
3 Benangan 95.00 m' E.025 16,902.00 1,605,690.00
4 Acian 306.78 m2 E.026 19,369.50 5,942,194.58
5 Pasangan beton alur 2.85 m2 M.058 153,560.10 437,185.60
6 Kamprotan 3.54 m2 E.023 25,969.88 91,985.30
49,253,311.42
E PEKERJAAN KERAMIK
1 Keramik utama 40 x 40 29.64 m2 M.045 165,255.60 4,898,175.98
2 Keramik teras 30 x 30 3.45 m2 M.043 127,411.50 439,569.68
3 Keramik lantai KM 20 x 20 1.82 m2 M.040 123,617.26 225,292.46
4 Keramik dinding KM 20 x 25 9.20 m2 M.057 159,403.50 1,466,512.20
7,029,550.32
F PEKERJAAN BETON
1 Pekerjaan Rabat & Lantai Kerja 0.60 m2 G.004 610,191.84 363,979.43
2 Pengecoran beton K-175 3.22 m3 G.005 752,866.76 2,423,228.90
3 Pembesian dengan besi polos 545.67 kg G.017 11,225.79 6,125,540.49
4 Pekerjaan bekisting 54.81 m2 G.022 116,598.90 6,390,435.91
15,303,184.73
G PEKERJAAN ATAP
1 Pekerjaan Rangka Galvalum 54.12 m2 K.032 295,698.23 16,002,715.17
2 Pekerjaan plafon eternit rangka meranti 43.44 m2 I.052 105,708.41 4,591,814.55
3 Pekerjaan atap genteng beton 54.12 m2 H.014 90,635.40 4,905,042.83
4 Pekerjaan bubungan beton 10.10 m' H.021 72,957.85 736,874.29
5 Pekerjaan lisplank 3/20 kamper 19.70 m' F.081 140,000.93 2,758,018.22
28,994,465.06
H PEKERJAAN PINTU & JENDELA
1 Pasang kusen kayu kamper 0.40 m3 F.002 12,788,104.50 5,121,635.85
2 Pasang Pintu Panil kayu kamper 1.63 m2 F.010 694,199.25 1,132,933.18
3 Pasang Pintu double triplek 4.90 m2 F.022 550,410.53 2,694,809.93
4 Pasang jendela kaca kamper 5.57 m2 F.014 460,252.80 2,562,687.59
5 Kaca polos 5 mm 3.66 m2 L.019 141,542.16 518,157.53
6 Selot pintu 4.00 bh L.005 146,613.68 586,454.70
7 Engsel pintu 6.00 set L.007 20,399.88 122,399.27
8 Engsel Jendela 6.00 set L.008 15,201.92 91,211.51
9 Grendel Jendela 6.00 bh L.010 18,388.84 110,333.03
10 Hak angin 6.00 set L.011 32,414.25 194,485.50
13,135,108.08
I PEKERJAAN FINISHING
1 Pengecatan tembok baru 306.78 m2 N.014 20,721.20 6,356,868.92
2 Pengecatan plafon 43.44 m2 N.021 20,721.20 900,097.63
3 Pengecatan kayu 22.78 m2 N.009 49,113.47 1,118,824.55
4 Pengecatan genteng 54.12 m2 N.022 16,674.24 902,383.19
9,278,174.29
J PEKERJAAN LAIN-LAIN
1 Tanaman/rumput 24.35 m2 S.008 15,637.88 380,782.26
380,782.26

TOTAL HARGA 134,180,332.85


PEKERJAAN TAMBAH BANGUNAN
TLOGOMAS REGENCY

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN

1 Galian tanah pondasi 9.00 m3 33,804.38


2 Rabatan lantai kerja 0.36 m3 652,129.59
3 Footplat 90x90x20 (9 titik)
- Beton K175 1.46 m3 752,866.76
- Pembesian 124.68 kg 11,225.79
4 Kolom struktur 15/20 (9 titik)
- Beton K175 1.13 m3 752,866.76
- Bekisting 15.12 m2 202,552.65
- Pembesian 271.02 kg 11,225.79

Jumlah
PPn (10%)
Total
TOTAL HARGA
TAMBAH BANGUNAN
MAS REGENCY

TOTAL HARGA

304,239.38
237,701.23

1,097,679.73
1,399,577.61

853,750.90
3,062,596.07
3,042,452.67

9,997,997.60
999,799.76
10,997,797.36
10,997,000.00
Update tanggl 28 Februari
Item Bahan Harga Satuan
1 Pasir pasang 85,000.00 m3
2 Pasir cor 125,000.00 m3
3 Batu belah 95,000.00 m3
4 Bata merah 560.00 bh
5 Besi 6 (5,8) 24,000.00 lonjor
6 Besi 6 (5,1) 18,500.00 lonjor
7 Besi 8 (7,2) 34,000.00 lonjor
8 besi 10 (8,2) 50,500.00 lonjor
9 Keramik 30 x 30 45,500.00 dus
10 Keramik 20 x 25 48,500.00 dus
11 Keramik 20 x 20 46,000.00 dus
12 Genteng beton (25/m2) 3,000.00 bh
13 Genteng bubung (3.5/m') 5,000.00 bh
14 Semen gresik 40 kg 53,000.00 zak
15 Galvalum C-75 70,000.00 lonjor
16 Reng galvalum 30,000.00 lonjor
17 Batu alur 35,000.00 m2
19 Cat maxilite 5 kg 46,000.00 galon
20 Cat avitex 5 kg 80,000.00 galon
21 Lem rajawali 10,000.00 kg