Jam Kerja - Lasan Top Angle

No Kapasitas Diameter Tinggi LF Lasan Berat Top Type Struktur Jumlah Jam Jumlah Hari
(m^3) (m) (m) Top Angle Angle (kg) Kerja Kerja

1 500 9.70 7.32 100.00 542.72 L 100 100 12 4.34 1


2 1000 11.64 10.97 120.00 651.12 L 100 100 12 5.21 1
3 1500 13.58 10.97 140.00 759.53 L 100 100 12 6.08 1
4 2000 15.52 10.97 160.00 867.93 L 100 100 12 6.94 1
5 2000 17.46 9.14 180.00 1969.47 L 150 150 15 15.76 2
6 2500 17.46 10.97 180.00 1969.47 L 150 150 15 15.76 2
7 2500 19.40 9.14 200.00 2188.11 L 150 150 15 17.50 3
8 5000 25.23 10.97 260.00 4747.08 L 200 200 20 37.98 5
9 5000 27.17 9.14 280.00 5112.47 L 200 200 20 40.90 6
10 7500 31.05 10.97 320.00 5842.05 L 200 200 20 46.74 6
11 10000 34.93 10.97 360.00 6573.43 L 200 200 20 52.59 7
12 10000 32.99 12.80 340.00 6206.84 L 200 200 20 49.65 7
13 15000 42.69 10.97 440.00 8033.19 L 200 200 20 64.27 9
14 15000 38.81 12.80 400.00 7303.61 L 200 200 20 58.43 8
15 20000 44.63 12.80 460.00 8397.98 L 200 200 20 67.18 9
16 20000 48.51 10.97 500.00 9129.96 L 200 200 20 73.04 10

Catatan
1m= 3.28084 feet
Waktu yang diperlukan dalam pemasangan top angle dan pengelasanya 8 jam per ton material