PT. ADIYA
WIDYAJASA (Jo.)
WIJAYA KARYA – PANDJI, KSO
INFORMASI UMUM
Paket Penggantian Jembatan Sei Alalak bertujuan untuk meningkatkan Aksesibilitas dari Kota Banjarmasin ke
Kabupaten Barito Kuala (Jalur Utama Trans Kalimantan)
2
WIJAYA KARYA – PANDJI, KSO
TIMELINE KONTRAK
Surat Perintah Mulai Kerja
Jaminan Pelaksanaan
(SPMK)
Pengumuman Pemenang November 21, 2018
November 30, 2018 Rapat Pra
November 16, 2018
TandaTangan Konstruksi (PCM)
Jaminan Uang Muka Pencairan Uang Muka
Rapat Pra Kontrak Kontrak Serah Terima Lahan December 07, 2018
November 30, 2018 December 17, 2018
November 19, 2018 November 23, 2018 November 26, 2018
16 20 24 28 02 06 10 14
Today
Spirit of Innovation
STRUKTUR ORGANISASI
Spirit of Innovation
STRUKTUR ORGANISASI
Spirit of Innovation
KONDISI EKSISTING AWAL
Spirit of Innovation
STRIP MAP
MAIN BRIDGE
PENDEKAT OPRIT PILESLAB 0+339 BOX CULVERT PILESLA PENDEKAT
0+480
COUNTERWEIGH
0+329 ABUTMENT
0+469 BOX TRAFFIC OPRIT
0+000 0+175 0+240 0+326 0+850
0+450 0+554 0+631
0+025 0+075 0+125 0+175 0+225 0+275 0+325 0+375 0+425 0+475 0+525 0+575 0+625 0+675 0+725 0+775 0+825
Spirit of Innovation
DETAIL PEKERJAAN
Struktur Atas
PYLON
- Tiang Pylon Beton fc’45 Mpa
Tinggi 42.4 m Stage 11 Segmen
Struktur Atas
- Stayed Cable ɸ 15.2 mm dibungkus HDPE
Counter weight & Box
- Wall Beton fc’45 Mpa
Struktur Atas
- Edge Beam & Cross Beam
Abutmen A1
Insitu Beton fc’ 45 Mpa
- Wall, Pier Head Beton fc’30
- Slab Insitu Beton fc’ 45 Mpa
Mpa
- Wing Wall Beton fc’3o Mpa
- Box Trafic fc’30 Mpa
Struktur Bawah
Struktur Bawah Struktur Bawah Counter Weight A2,A3
Abutmen A1 Pylon - Tiang Bor Beton fc’ 35 Mpa Dim.
- Tiang Bor Beton fc’ 35 Mpa Dim. - Tiang Bor Beton fc’ 35 Mpa 1.8m L=70m, 12 Titik
1.8m L=70m, 8 Titik Dim. 1.8m L=70m, 32 Titik - Pile Cap Beton fc’ 45 Mpa
- Pile Cap Beton fc’ 30 Mpa - Pile Cap Beton fc’ 45 Mpa 20 m x 20m x 2m
9m x 20 x 2m 19.8 m x 19.8m x 3.0m - Tiang Pancang 500mm L = 70 m
Spirit of Innovation
DETAIL PEKERJAAN
Spirit of Innovation
PROGRESS SD 25 Juni 2019
PROGRES FISIK PEKERJAAN S.D. 25 Juni 2019
REALISASI PEKERJAAN 19.53%
RENCANA PEKERJAAN 20,50 %
DEVIASI - 0.97%
Spirit of Innovation
DOKUMENTASI
Pemancangan Pemancangan
Sisi Banjarmasin Sisi Batola
Spirit of Innovation
DOKUMENTASI
Spirit of Innovation
DOKUMENTASI
Spirit of Innovation
DOKUMENTASI
Pengecoran Lc Pembesian
Pile Head Batola Pile Head Batola
Spirit of Innovation
DOKUMENTASI
Spirit of Innovation
DOKUMENTASI
Spirit of Innovation
DOKUMENTASI
Spirit of Innovation
DOKUMENTASI
Pembesian Pengecoran
Precast Half Slab Precast Half Slab
Spirit of Innovation
DOKUMENTASI
Curring Stok
Precast Half Slab Precast Half Slab
Spirit of Innovation
HOUSEKEEPING
Spirit of Innovation
SURVEY BATHIMETRI
Spirit of Innovation
TRIAL BETON
Spirit of Innovation
HOUSEKEEPING
KANTOR PROYEK
GERBANG PROYEK
HOUSEKEEPING
ABT 1 = 8 titik
Total titik = 52 titik
Denah Pondasi Bored Pile 1800 mm Leff = 70 m
TOTAL = 52 titik
Spirit of Innovation
General Layout Pekerjaan Borepile
Titik Pengeboran
Alat Bore
Silo Bentonite
Spirit of Innovation
General Layout Pekerjaan Borepile
Titik Bor
Sheetpile
Stock Baja Tulangan
Platform Timbun
Crane Service
Excavator
Dump Truck
Truck Mixer
Spirit of Innovation
Metode Kerja Bored Pile
Batching Plan
Lokasi
Pengeboran
Spirit of Innovation
KESIAPAN PEKERJAAN BOREPILE
a. Peralatan Bored Pile
Spirit of Innovation
KESIAPAN PEKERJAAN BOREPILE
b. Besi Beton
Spirit of Innovation
KESIAPAN PEKERJAAN BOREPILE
Spirit of Innovation
KESIAPAN PEKERJAAN BOREPILE
Perkuatan Sisi Sungai
Penimbunan dan Perataan Platform
Spirit of Innovation
SISTEM MANAJEMEN MUTU
Spirit of Innovation
SISTEM MANAJEMEN MUTU
Spirit of Innovation
THANK YOU!
• Penggantian Jembatan Sei Alalak
• Banjarmasin