RENCANA ANGGARAN BIAYA

ANALISA HARGA SATUAN RAB


1 Instalasi listrik/titik
no material volume satuan harga jumlah
1 kabel nya 1,5 mm2 24 m 2,500 60,000
2 pipa pvc 20 mm 7m 2,000 14,000
3 klem 20 mm 6 bh 800 4,800
4 sok 20 mm 1 bh 3,000 3,000
5 elbow 20 mm 1 bh 3,500 3,500
6 teedus 20 mm 1 bh 600 600
7 Fiser + paku skrup 12 bh 150 1,800
8 alat bantu 1 ls 2,000 2,000
9 upah 1 ttk 30,000 30,000
total 119,700
over heat 5% 5,985

keuntungan 5% 5,985
pph 2.50% 2,993
total 134,663

2 Instalasi stop kontak/titik


no material volume satuan harga jumlah
1 kabel nya 1,5 mm2 36 m 2,500 90,000
2 pipa pvc 20 mm 11 m 2,000 22,000
3 klem 20 mm 10 bh 800 8,000
4 sok 20 mm 3 bh 3,000 9,000
5 elbow 20 mm 2 bh 3,500 7,000
6 teedus 20 mm 1 bh 600 600
7 Fiser + paku skrup 20 bh 150 3,000
8 alat bantu 1 ls 2,000 2,000
9 upah 1 ttk 35,000 35,000
total 176,600
over heat 5% 8,830

keuntungan 5% 8,830
pph 2.50% 4,415
total 198,675