LAPORAN AKHIR

DAFTAR ISI

DAFTAR ISI ..................................................................................................................................................I

DAFTAR GAMBAR ...................................................................................................................................... V

DAFTAR TABEL ........................................................................................................................................ VII

BAB 1 PENDAHULUAN .........................................................................................................................1-1

1.1 LATAR BELAKANG ............................................................................................................................ 1-1


1.1.1 Kondisi Lahan Rencana Areal Daerah Irigasi .......................................................................... 1-1
1.1.2 Potensi Sumber Air dan Prasarana Sumber Daya Air ............................................................. 1-1
1.1.3 Permasalahan ........................................................................................................................ 1-2
1.1.4 Rencana Penanganan ............................................................................................................ 1-2
1.2 REFERENSI DAN SUMBER HUKUM ................................................................................................... 1-2
1.3 MAKSUD DAN TUJUAN..................................................................................................................... 1-3
1.4 LOKASI PEKERJAAN .......................................................................................................................... 1-3
1.5 INFORMASI KEGIATAN ..................................................................................................................... 1-4
1.6 LINGKUP PEKERJAAN ....................................................................................................................... 1-4
1.7 SISTEMATIKA PELAPORAN ............................................................................................................... 1-7

BAB 2 GAMBARAN UMUM LOKASI STUDI ............................................................................................2-1

2.1 GAMBARAN UMUM LOKASI............................................................................................................. 2-1


2.1.1 Administrasi ........................................................................................................................... 2-1
2.1.2 Geografi ................................................................................................................................. 2-2
2.1.3 Iklim ........................................................................................................................................ 2-2
2.1.4 Hidrologi ................................................................................................................................. 2-3
2.1.5 Geologi ................................................................................................................................... 2-4
2.1.6 Hidrogeologi ........................................................................................................................... 2-8
2.1.7 Faktor Kegempaan ................................................................................................................. 2-9
2.1.8 Pertanian .............................................................................................................................. 2-10
2.1.9 Daerah Irigasi ....................................................................................................................... 2-12
2.2 KONDISI SOSIAL EKONOMI DAN KEPENDUDUKAN ........................................................................ 2-15
2.2.1 Kondisi Demografi ................................................................................................................ 2-15
2.2.2 Kondisi Sosial Budaya ........................................................................................................... 2-15
2.2.3 Kondisi Ekonomi ................................................................................................................... 2-17
2.3 PERTEMUAN KONSULTASI MASYARAKAT ...................................................................................... 2-18

BAB 3 KETERSEDIAAN DATA.................................................................................................................3-1

3.1 DEM LOKASI STUDI........................................................................................................................... 3-1


3.2 TATA GUNA LAHAN .......................................................................................................................... 3-1
3.3 KONDISI HIDROKLIMATOLOGI ......................................................................................................... 3-2
3.3.1 Curah Hujan ........................................................................................................................... 3-2
3.3.2 Klimatologi ............................................................................................................................. 3-4
3.3.3 Pengukuran Debit Sesaat ....................................................................................................... 3-5
3.4 SURVEY LAPANGAN AWAL ............................................................................................................... 3-6

BAB 4 PEMETAAN TOPOGRAFI .............................................................................................................4-1

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN i


LAPORAN AKHIR

4.1 UMUM ............................................................................................................................................. 4-1


4.2 KONDISI TOPOGRAFI ........................................................................................................................ 4-1
4.2.1 Kemiringan dan Ketinggian Lahan ......................................................................................... 4-1
4.2.2 Luas dan Batas-batas Areal ................................................................................................... 4-1
4.2.3 Vegetasi dan Penggunaan Lahan ........................................................................................... 4-1
4.3 REFERENSI PENGUKURAN ................................................................................................................ 4-2
4.4 PATOK PENGUKURAN ...................................................................................................................... 4-2
4.5 PETA DAN GAMBAR PENGUKURAN ................................................................................................. 4-2

BAB 5 HASIL ANALISIS ..........................................................................................................................5-1

5.1 DAERAH ALIRAN SUNGAI (DAS) DI GUDANG .................................................................................... 5-1


5.2 ANALISIS KETERSEDIAAN ................................................................................................................. 5-3
5.2.1 Hujan Efektif ........................................................................................................................... 5-3
5.2.2 Evapotranspirasi .................................................................................................................... 5-3
5.2.3 Debit Andal DAS Gudang........................................................................................................ 5-4
5.3 ANALISIS KEBUTUHAN AIR ............................................................................................................... 5-7
5.3.1 Kebutuhan Air ........................................................................................................................ 5-7
5.3.2 Areal Potensial ..................................................................................................................... 5-39
5.4 NERACA AIR ................................................................................................................................... 5-45
5.5 ANALISIS DEBIT BANJIR .................................................................................................................. 5-48
5.5.1 Analisis Frekuensi ................................................................................................................. 5-48
5.5.2 Hujan Efektif DAS Gudang .................................................................................................... 5-49
5.5.3 Distribusi Hujan Jam-jaman DAS Gudang ............................................................................ 5-49
5.5.4 Hidrograf Snyder DAS Gudang ............................................................................................. 5-50
5.5.5 Hidrograf Nakayasu DAS Gudang ........................................................................................ 5-50
5.5.6 Hidrograf ITB I dan II DAS Gudang ....................................................................................... 5-51
5.5.7 Rekap Debit Banjir Rancangan DAS Gudang ........................................................................ 5-53

BAB 6 HASIL PERENCANAAN ................................................................................................................6-1

6.1 PERENCANAAN JARINGAN IRIGASI .................................................................................................. 6-1


6.1.1 DAS DI Gudang ....................................................................................................................... 6-1
6.1.2 Areal Sawah pada Citra Satelit .............................................................................................. 6-1
6.1.3 Petak Tersier........................................................................................................................... 6-3
6.1.4 Penentuan Trase Saluran ....................................................................................................... 6-5
6.2 OPTIMASI SKENARIO PENGAIRAN AREAL SAWAH ........................................................................... 6-7
6.2.1 Skenario 1 ............................................................................................................................... 6-8
6.2.2 Skenario 2 ............................................................................................................................... 6-9
6.3 PERENCANAAN BANGUNAN UTAMA ............................................................................................. 6-10
6.3.1 Bendung ............................................................................................................................... 6-10
6.3.2 Bangunan Pengambilan (Intake).......................................................................................... 6-17
6.3.3 Kantong Lumpur ................................................................................................................... 6-19
6.3.4 Saluran Pembawa Primer ..................................................................................................... 6-22
6.3.5 Saluran Pembawa Kuarter ................................................................................................... 6-31
6.3.6 Bangunan Bagi Sadap .......................................................................................................... 6-32
6.3.7 Kehilangan Energi (Headloss)............................................................................................... 6-35
6.3.8 Saluran Pembuang ............................................................................................................... 6-36
6.3.9 Bangunan Ukur Ambang Lebar ............................................................................................ 6-41
6.4 REKAP DATA TEKNIS DI GUDANG ................................................................................................... 6-45

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN ii


LAPORAN AKHIR

BAB 7 ESTIMASI VOLUME DAN RENCANA ANGGARAN BIAYA (RAB) PELAKSANAAN ...........................7-1

7.1 ESTIMASI VOLUME DAN BIAYA PELAKSANAAN ................................................................................ 7-1


7.1.1 Harga Satuan pekerjaan ........................................................................................................ 7-1
7.1.2 Analisis Harga Satuan (AHS) pekerjaan ................................................................................. 7-1
7.1.3 Rencana Volume dan Biaya Pekerjaan ................................................................................... 7-1
7.2 REKAPITULASI BIAYA PEKERJAAN..................................................................................................... 7-1

BAB 8 OPERASI DAN PEMELIHARAAN ..................................................................................................8-1

8.1 UMUM ............................................................................................................................................. 8-1


8.2 POKOK KEGIATAN OPERASI JARINGAN IRIGASI ................................................................................ 8-2
8.3 OPERASI BANGUNAN PADA JARINGAN IRIGASI ............................................................................... 8-4
8.3.1 Bangunan Utama ................................................................................................................... 8-4
8.3.2 Jaringan Irigasi ....................................................................................................................... 8-6
8.4 ALAT PENGUKUR DEBIT ................................................................................................................... 8-9
8.4.1 Ambang Lebar ........................................................................................................................ 8-9
8.4.2 Alat Ukur Parshall Flume ........................................................................................................ 8-9
8.4.3 Pengukuran debit saluran tidak menggunakan bangunan ukur .......................................... 8-10
8.5 PEMELIHARAAN JARINGAN IRIGASI ............................................................................................... 8-10
8.5.1 Persiapan Pemeliharaan Jaringan lrigasi ............................................................................. 8-10
8.5.2 Pemeliharaan ....................................................................................................................... 8-12
8.6 EVALUASI OPERASI JARINGAN LRIGASI .......................................................................................... 8-14

BAB 9 ORGANISASI PELAKSANA DAN RENCANA KERJA .......................................................................9-1

9.1 UMUM ............................................................................................................................................. 9-1


9.2 STRUKTUR ORGANISASI ................................................................................................................... 9-1
9.3 JADWAL PELAKSANAAN ................................................................................................................... 9-3

BAB 10 SIMPULAN DAN SARAN ....................................................................................................... 10-1

10.1 SIMPULAN ................................................................................................................................. 10-1


10.2 SARAN ....................................................................................................................................... 10-2

LAMPIRAN .................................................................................................................................................. 1

LAMPIRAN A. METODOLOGI PEKERJAAN .............................................................................................. 1

A. KEGIATAN I : PERSIAPAN DAN SURVEY PENDAHULUAN ........................................................................ 1


A.I. Mobilisasi Personil..................................................................................................................... 1
A.II. Perijinan, Klarifikasi dan Survey Pendahuluan .......................................................................... 1
A.III. Pengumpulan Data Sosial, Ekonomi dan Lingkungan ............................................................... 2
A.IV. Inventarisasi Data Awal dan Identifikasi Masalah .................................................................... 2
A.V. Penyusunan Rencana Kerja Detail............................................................................................. 3
B. KEGIATAN II: SURVEY LAPANGAN .......................................................................................................... 3
B.I. Inventarisasi Infrastruktur Pengguna Air .................................................................................. 3
B.II. Inventarisasi Data Sekunder ..................................................................................................... 3
B.III. Survey Hidrometri (Current Meter) ........................................................................................... 5
B.IV. Survey Sosial Ekonomi ............................................................................................................... 7
C. KEGIATAN III: ANALISIS HIDROLOGI DAN PERENCANAAN ...................................................................... 9
C.I. Analisis Ketersediaan Air ................................................................................................................ 9
C.II. Kebutuhan Air untuk Pemeliharaan Sungai ............................................................................ 14
C.III. Analisis Kebutuhan Air ............................................................................................................ 15

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN iii


LAPORAN AKHIR

C.IV. Perluasan Sawah ..................................................................................................................... 20


C.V. Debit Banjir ............................................................................................................................. 21
C.VI. Kriteria Perencanaan Bangunan Hidraulik .............................................................................. 26
C.VII. Analisis Ekonomi ..................................................................................................................... 35
D. KEGIATAN IV : PENYUSUNAN LAPORAN DAN DISKUSI ...................................................................... 36
E. OGANISASI, KEWENANGAN DAN TANGGUNGJAWAB ...................................................................... 37
E.I. Pusat ............................................................................................................................................ 37
E.II. Provinsi .................................................................................................................................... 37
E.III. Kabupaten ............................................................................................................................... 38

LAMPIRAN B. TABULASI HASIL ANALISIS HIDROLOGI (DEBIT ANDAL DAN DEBIT BANJIR) ................... 40

LAMPIRAN C. BILL OF QUANTITY (BOQ), RENCANA ANGGARAN BIAYA (RAB), HARGA MATERIAL ALAT,
DAN ANALISIS HARGA SATUAN (AHS) ...................................................................................................... 41

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN iv


LAPORAN AKHIR

DAFTAR GAMBAR

GAMBAR 2.1 PETA ADMINISTRASI KABUPATEN BANGKA SELATAN ............................................................................... 2-1


GAMBAR 2.2 LOKASI STASIUN HUJAN BMKG PANGKALPINANG .................................................................................. 2-3
GAMBAR 2.3 PETA HUJAN SUMATERA DAN BANGKA BELITUNG................................................................................... 2-3
GAMBAR 2.4 PETA GEOLOGI KECAMATAN SIMPANG RIMBA ....................................................................................... 2-7
GAMBAR 2.5 PETA HIDROGEOLOGI KECAMATAN SIMPANG RIMBA .............................................................................. 2-8
GAMBAR 2.6 RESPONS SPEKTRUM....................................................................................................................... 2-10
GAMBAR 2.7 PETA KALENDER TANAM PADI SAWAH ............................................................................................... 2-12
GAMBAR 2.8 PETA STATUS KETERSEDIAAN NUTRISI TERCERNA ................................................................................. 2-13
GAMBAR 2.9 KEGIATAN PKM............................................................................................................................. 2-19
GAMBAR 2.10 KEGIATAN PKM........................................................................................................................... 2-19
GAMBAR 2.11 KEGIATAN PKM........................................................................................................................... 2-19
GAMBAR 3.1 PETA DEM WILAYAH DI GUDANG ...................................................................................................... 3-1
GAMBAR 3.2 TATA GUNA LAHAN BANGKA BELITUNG TAHUN 2012 ............................................................................ 3-2
GAMBAR 3.3 HUJAN BULANAN STASIUN BMKG PANGKAL PINANG ............................................................................. 3-4
GAMBAR 3.4 LAYOUT DAERAH IRIGASI GUDANG ...................................................................................................... 3-6
GAMBAR 4.1 PETA TOPOGRAFI DAERAH IRIGASI GUDANG.......................................................................................... 4-5
GAMBAR 5.1 WILAYAH SUNGAI (WS) BANGKA........................................................................................................ 5-2
GAMBAR 5.2 DAS GUDANG PADA PETA RUPA BUMI ................................................................................................ 5-2
GAMBAR 5.3 TATA GUNA LAHAN DAS GUDANG ...................................................................................................... 5-3
GAMBAR 5.4 EVAPOTRANSPIRASI BULANAN HASIL SOFTWARE CROPWAT...................................................................... 5-4
GAMBAR 5.5 GRAFIK DEBIT SINTETIS GUDANG ........................................................................................................ 5-5
GAMBAR 5.6 GRAFIK KURVA DURASI (FLOW DURATION CURVE) GUDANG .................................................................... 5-6
GAMBAR 5.7 NERACA AIR D.I. GUDANG 3 POLA TANAM......................................................................................... 5-46
GAMBAR 5.8 NERACA AIR D.I. GUDANG 2 POLA TANAM......................................................................................... 5-47
GAMBAR 5.9 GRAFIK DISTRIBUSI HUJAN JAM-JAMAN.............................................................................................. 5-49
GAMBAR 5.10 HIDROGRAF DAS GUDANG PERIODE ULANG 2 TAHUN ........................................................................ 5-53
GAMBAR 5.11 HIDROGRAF DAS GUDANG PERIODE ULANG 5 TAHUN ........................................................................ 5-54
GAMBAR 5.12 HIDROGRAF DAS GUDANG PERIODE ULANG 10 TAHUN ...................................................................... 5-54
GAMBAR 5.13 HIDROGRAF DAS GUDANG PERIODE ULANG 25 TAHUN ...................................................................... 5-54
GAMBAR 5.14 HIDROGRAF DAS GUDANG PERIODE ULANG 50 TAHUN ...................................................................... 5-55
GAMBAR 5.15 HIDROGRAF DAS GUDANG PERIODE ULANG 100 TAHUN .................................................................... 5-55
GAMBAR 6.1 TITIK OUTLET DAS GUDANG .............................................................................................................. 6-1
GAMBAR 6.2 HASIL DAS ..................................................................................................................................... 6-2
GAMBAR 6.3 GAMBAR ZOOM IN NOMOR 1 (KEBUN) ................................................................................................ 6-2
GAMBAR 6.4 GAMBAR ZOOM IN NOMOR 2 (LAHAN KOSONG) ................................................................................... 6-3
GAMBAR 6.5 GAMBAR ZOOM IN NOMOR 3 (SAWAH) ............................................................................................... 6-3
GAMBAR 6.6 RENCANA PEMBAGIAN PETAK SAWAH DI GUDANG ................................................................................ 6-5
GAMBAR 6.7 TRASE SALURAN............................................................................................................................... 6-7
GAMBAR 6.8 SKEMATISASI PETAK SAWAH SKENARIO 1.............................................................................................. 6-8
GAMBAR 6.9 SKEMATISASI PETAK SAWAH SKENARIO 2.............................................................................................. 6-9
GAMBAR 6.10 POSISI BENDUNG BARU TERHADAP BENDUNG EKSISTING ..................................................................... 6-11
GAMBAR 6.11 RATING CURVE PADA BENDUNG...................................................................................................... 6-12
GAMBAR 6.12 GRAFIK MDO – 1A PENENTUAN BAHAY KAVITASI DI HILIR MERCU BANGUNAN TERJUN ........................... 6-15
GAMBAR 6.13 MDO – 1 PENGALIRAN MELALUI MERCU BANGUNAN TERJUN ............................................................. 6-15
GAMBAR 6.14 GRAFIK MDO – 2 PENENTUAN KEDALAMAN LANTAI PEREDAM ENERGI ................................................. 6-16

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN v


LAPORAN AKHIR

GAMBAR 6.15 GAMBAR MDO – 3 PENENTUAN PANJANG LANTAI PEREDAM ENERGI ................................................... 6-16
GAMBAR 6.16 BANGUNAN UTAMA ..................................................................................................................... 6-18
GAMBAR 6.17 ILUSTRASI PENAMPANG MELINTANG INTAKE ..................................................................................... 6-19
GAMBAR 6.18 SKEMA KANTONG LUMPUR ............................................................................................................. 6-19
GAMBAR 6.19 TIPE-TIPE POTONGAN MELINTANG SALURAN IRIGASI .......................................................................... 6-30
GAMBAR 6.20 GAMBAR TIPIKAL SALURAN DAN JALAN INSPEKSI ................................................................................ 6-31
GAMBAR 6.21 SALURAN EKSISTING DINAS PERTANIAN ............................................................................................ 6-31
GAMBAR 6.22 TATA LETAK BANGUNAN BAGI SADAP .............................................................................................. 6-34
GAMBAR 6.23 TRASE SALURAN PEMBUANG .......................................................................................................... 6-38
GAMBAR 6.24 SALURAN PEMBUANG ................................................................................................................... 6-40
GAMBAR 6.25 SKEMATISASI JARINGAN IRIGASI ...................................................................................................... 6-47
GAMBAR 6.26 SKEMATISASI BANGUNAN IRIGASI .................................................................................................... 6-48
GAMBAR 9.1 STRUKTUR ORGANISASI PELAKSANAAN ................................................................................................. 9-1
GAMBAR A.1 BEBERAPA METODE PENGUKURAN DEBIT SECARA LANGSUNG ....................................................................... 5
GAMBAR A.2 METODE MERAWAS ............................................................................................................................ 7
GAMBAR A.3 DIAGRAM ALIR KALIBRASI MODEL.......................................................................................................... 9
GAMBAR A.4 DIAGRAM MODEL SACRAMENTO (SYAHRIL, 2006) ................................................................................. 13
GAMBAR A.5 HIDROGRAF SATUAN SINTETIK SNYDER (A) TP = 5.5 TR , (B) TPR ≠ 5.5 TR .................................................... 22
GAMBAR A.6 HIDROGRAF SATUAN SINTETIK NAKAYASU ............................................................................................. 24
GAMBAR A.7. BENTUK ELIPS PUNCAK BENDUNG (EM-1110-2-160 PLATE 3-23, USACE MANUAL) ................................. 28
GAMBAR A.8 JARI-JARI MINIMUM BAK (KP-02 1986) .............................................................................................. 29
GAMBAR A.9 BATAS MINIMUM TINGGI AIR DI HILIR (KP-02 1986) ............................................................................. 30
GAMBAR A.10 SKETSA PENAMPANG PEREDAM ENERGI TIPE BAK (KP-02, 1986) ........................................................... 30
GAMBAR A.11 CONTOH BANGUNAN BAGI-SADAP ...................................................................................................... 32
GAMBAR A.12 CONTOH BANGUNAN TERJUN ............................................................................................................ 34

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN vi


LAPORAN AKHIR

DAFTAR TABEL

TABEL 2.1 LUAS DESA DI KECAMATAN SIMPANG RIMBA (HA) ..................................................................................... 2-2
TABEL 2.2 JENIS PENGGUNAAN LAHAN DI KECAMATAN SIMPANG RIMBA ...................................................................... 2-2
TABEL 2.3 POS HUJAN DI KABUPATEN BANGKA SELATAN ........................................................................................... 2-3
TABEL 2.4 NAMA-NAMA SUNGAI YANG ADA MENURUT KECAMATAN DI KABUPATEN BANGKA SELATAN .............................. 2-4
TABEL 2.5 PARAMETER RESPON SPEKTRA DESAIN ...................................................................................................... 2-9
TABEL 2.6 KATEGORI DESAIN SEISMIC BERDASARKAN PARAMETER RESPONS PERCEPATAN PADA PERIODA PENDEK ................ 2-10
TABEL 2.7 KATEGORI DESAIN SEISMIK BERDASARKAN PARAMETER RESPONS PERCEPATAN PADA PERIODA 1 DETIK................. 2-10
TABEL 2.8 LUAS PANEN (HA), PRODUKSI SAWAH DAN PADI LADANG (TON) MENURUT DESA DI KECAMATAN SIMPANG RIMBA,
2016 (SUMBER : BPS KAB. BAGKA SELATAN, 2017) .................................................................................... 2-11
TABEL 2.9 LUAS PANEN (HA), PRODUKSI PRODUKSI PALAWIJA (TON) MENURUT DESA DI KECAMATAN SIMPANG RIMBA, 2016
(SUMBER : BPS KAB. BAGKA SELATAN, 2017) ............................................................................................. 2-11
TABEL 2.10 KALENDER TANAM TERPADU KECAMATAN SIMPANG RIMBA .................................................................... 2-13
TABEL 2.11 JENIS BENCANA DAN TINGKAT KERUSAKAN – PADI ................................................................................. 2-14
TABEL 2.12 JENIS BENCANA DAN TINGKAT KERUSAKAN – JAGUNG ............................................................................. 2-14
TABEL 2.13 JENIS BENCANA DAN TINGKAT KERUSAKAN – KEDELAI ............................................................................. 2-14
TABEL 2.14 KEPENDUDUKAN KECAMATAN SIMPANG RIMBA..................................................................................... 2-15
TABEL 2.15 KONDISI TEMPAT TINGGAL WARGA KECAMATAN SIMPANG RIMBA............................................................ 2-15
TABEL 2.16 JUMLAH SEKOLAH NEGERI DAN SWASTA DI KECAMATAN SIMPANG RIMBA .................................................. 2-16
TABEL 2.17 JUMLAH PUSKESMAS DAN POSYANDU DI KECAMATAN SIMPANG RIMBA ..................................................... 2-16
TABEL 2.18 JUMLA RUMAH TANGGA YANG MENGGUNAKAN SUMBER AIR UNTUK MCK DAN AIR MINUM DI KECAMATAN
SIMPANG RIMBA ..................................................................................................................................... 2-16
TABEL 2.19 JUMLAH KOPERASI DI KECAMATAN SIMPANG RIMBA .............................................................................. 2-17
TABEL 2.20JUMLAH LEMBAGA KEUANGAN DI KECAMATAN SIMPANG RIMBA ............................................................... 2-17
TABEL 3.1 KETERSEDIAAN DATA HUJAN .................................................................................................................. 3-2
TABEL 3.2 CURAH HUJAN MAKSIMUM TAHUNAN (R24) (MM) ................................................................................... 3-3
TABEL 3.3 DATA HUJAN 2-MINGGUAN (MM)........................................................................................................... 3-3
TABEL 3.4 PARAMETER KLIMATOLOGI..................................................................................................................... 3-4
TABEL 3.5 KONDISI EKSISTING DI GUDANG.............................................................................................................. 3-7
TABEL 4.1 KOORDINAT BM DAN CP....................................................................................................................... 4-2
TABEL 4.2 DOKUMENTASI SURVEY TOPOGRAFI DI GUDANG ....................................................................................... 4-3
TABEL 5.1 PRESENTASI TUTUPAN LAHAN DAS GUDANG ............................................................................................ 5-2
TABEL 5.2 ANALISIS HUJAN EFEKTIF BULANAN ......................................................................................................... 5-3
TABEL 5.3 PARAMETER DAS................................................................................................................................. 5-4
TABEL 5.4 PROBABILITAS KURVA DURASI (FLOW DURATION CURVE) GUDANG ............................................................... 5-6
TABEL 5.5 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 1, MULAI OKT-2 .................................. 5-9
TABEL 5.6 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 2, MULAI OKT-2 ................................ 5-10
TABEL 5.7 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 3, MULAI OKT-2 ................................ 5-11
TABEL 5.8 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 1, MULAI NOV-1 ................................ 5-12
TABEL 5.9 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 2, MULAI NOV-1 ................................ 5-13
TABEL 5.10 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 3, MULAI NOV-1 .............................. 5-14
TABEL 5.11 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 1, MULAI NOV-2 .............................. 5-15
TABEL 5.12 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 2, MULAI NOV-2 .............................. 5-16
TABEL 5.13 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 3, MULAI NOV-2 .............................. 5-17
TABEL 5.14 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 1, MULAI DEC-1 .............................. 5-18
TABEL 5.15 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 2, MULAI DEC-1 .............................. 5-19

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN vii


LAPORAN AKHIR

TABEL 5.16 PERHITUNGAN KEBUTUHAN AIR IRIGASI 3 POLA TANAM ALTERNATIF – 3, MULAI DEC-1 .............................. 5-20
TABEL 5.17 KEBUTUHAN AIR IRIGASI 3 POLA TANAM - LAMA PENGOLAHAN LAHAN : 30 HARI GUDANG (LITER/S.HA)
(ALTERNATIF-1) ...................................................................................................................................... 5-21
TABEL 5.18 REKAP KEBUTUHAN AIR IRIGASI 3 POLA TANAM - LAMA PENGOLAHAN LAHAN : 45 HARI GUDANG (LITER/S.HA)
(ALTERNATIF-2) ...................................................................................................................................... 5-22
TABEL 5.19 KEBUTUHAN AIR IRIGASI 3 POLA TANAM - LAMA PENGOLAHAN LAHAN : 30 HARI, VARIETAS BIASA GUDANG
(LITER/S.HA) (ALTERNATIF-3) .................................................................................................................... 5-23
TABEL 5.20 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 1, MULAI OKT-2 .............................. 5-24
TABEL 5.21 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 2, MULAI OKT-2 .............................. 5-25
TABEL 5.22 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 3, MULAI OKT-2 .............................. 5-26
TABEL 5.23 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 1, MULAI NOV-1 .............................. 5-27
TABEL 5.24 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 2, MULAI NOV-1 .............................. 5-28
TABEL 5.25 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 3, MULAI NOV-1 .............................. 5-29
TABEL 5.26 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 1, MULAI NOV-2 .............................. 5-30
TABEL 5.27 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 2, MULAI NOV-2 .............................. 5-31
TABEL 5.28 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 3, MULAI NOV-2 .............................. 5-32
TABEL 5.29 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 1, MULAI DEC-1 .............................. 5-33
TABEL 5.30 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 2, MULAI DEC-1 .............................. 5-34
TABEL 5.31 PERHITUNGAN KEBUTUHAN AIR IRIGASI 2 POLA TANAM ALTERNATIF – 3, MULAI DEC-1 .............................. 5-35
TABEL 5.32 KEBUTUHAN AIR IRIGASI 2 POLA TANAM - LAMA PENGOLAHAN LAHAN : 30 HARI GUDANG (LITER/S.HA)
(ALTERNATIF-1) ...................................................................................................................................... 5-36
TABEL 5.33 REKAP KEBUTUHAN AIR IRIGASI 2 POLA TANAM - LAMA PENGOLAHAN LAHAN : 45 HARI GUDANG (LITER/S.HA)
(ALTERNATIF-2) ...................................................................................................................................... 5-37
TABEL 5.34 KEBUTUHAN AIR IRIGASI 3 POLA TANAM - LAMA PENGOLAHAN LAHAN : 30 HARI, VARIETAS BIASA GUDANG
(LITER/S.HA) (ALTERNATIF-3).................................................................................................................... 5-38
TABEL 5.35 LUAS DAERAH IRIGASI 3 POLA TANAM – 30 HARI GUDANG (HA) (ALTERNATIF-1) ....................................... 5-39
TABEL 5.36 LUAS DAERAH IRIGASI 3 POLA TANAM – 45 HARI GUDANG (HA) (ALTERNATIF-2) ....................................... 5-40
TABEL 5.37 LUAS DAERAH IRIGASI 3 POLA TANAM – 30 HARI, VARIETAS BIASA GUDANG (HA) (ALTERNATIF-3)................ 5-41
TABEL 5.38 LUAS MAKSIMUM DAERAH IRIGASI GUDANG 3 POLA TANAM ................................................................... 5-41
TABEL 5.39 LUAS DAERAH IRIGASI 2 POLA TANAM – 30 HARI GUDANG (HA) (ALTERNATIF-1) ....................................... 5-42
TABEL 5.40 LUAS DAERAH IRIGASI 2 POLA TANAM – 45 HARI GUDANG (HA) (ALTERNATIF-2) ....................................... 5-43
TABEL 5.41 LUAS DAERAH IRIGASI 2 POLA TANAM – 30 HARI, VARIETAS BIASA GUDANG (HA) (ALTERNATIF-3)................ 5-44
TABEL 5.42 LUAS MAKSIMUM DAERAH IRIGASI GUDANG 2 POLA TANAM ................................................................... 5-44
TABEL 5.43 ANALISIS FREKUENSI STASIUN PANGKALPINANG ..................................................................................... 5-48
TABEL 5.44 KOEFISIEN PENGALIRAN DAN CURAH HUJAN RENCANA GUDANG............................................................... 5-49
TABEL 5.45 PARAMETER SNYDER GUDANG ........................................................................................................... 5-50
TABEL 5.46 PARAMETER NAKAYASHU GUDANG ..................................................................................................... 5-50
TABEL 5.47 UNIT HIDROGRAF DAS GUDANG HSS ITB 1 ......................................................................................... 5-51
TABEL 5.48 UNIT HIDROGRAF DAS GUDANG HSS ITB 2 ......................................................................................... 5-52
TABEL 5.49 REKAP DEBIT BANJIR GUDANG ........................................................................................................... 5-53
TABEL 6.1 TINGGI MUKA AIR DI ATAS BENDUNG .................................................................................................... 6-12
TABEL 6.2 RESUME DIMENSI BENDUNG ................................................................................................................ 6-13
TABEL 6.3 HASIL PERENCANAAN KOLAM OLAK....................................................................................................... 6-14
TABEL 6.4 HASIL PERHITUNGAN DIMENSI INTAKE ................................................................................................... 6-18
TABEL 6.5 ELEVASI MUKA AIR SALURAN ............................................................................................................... 6-22
TABEL 6.6 TINGGI JAGAAN UNTUK SALURAN PASANGAN .......................................................................................... 6-24
TABEL 6.7 HASIL PERHITUNGAN DEBIT DAN DIMENSI SALURAN PRIMER 3 POLA TANAM ................................................ 6-27
TABEL 6.8 HASIL PERHITUNGAN DEBIT DAN DIMENSI SALURAN PRIMER 2 POLA TANAM ................................................ 6-28

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN viii


LAPORAN AKHIR

TABEL 6.9 LEBAR MINIMUM TANGGUL ................................................................................................................. 6-30


TABEL 6.10 REKAPITULASI DIMENSI BANGUNAN BAGI DAN BOKS KUARTER ................................................................. 6-34
TABEL 6.11 RESUME KEHILANGAN TINGGI ENERGI.................................................................................................. 6-35
TABEL 6.12 HASIL ANALISIS FREKUENSI ................................................................................................................ 6-38
TABEL 6.13 DEBIT DAN MUKA AIR UNTUK ALAT UKUR AMBANG LEBAR SEGI EMPAT .................................................... 6-43
TABEL 9.1 DAFTAR PERSONIL TENAGA AHLI PELAKSANAAN PEKERJAAN......................................................................... 9-2
TABEL 9.2 DAFTAR PERSONIL TENAGA PENDUKUNG PELAKSANAAN PEKERJAAN.............................................................. 9-2
TABEL 9.3 JADWAL RENCANA PELAKSANAAN PEKERJAAN ........................................................................................... 9-3
TABEL 9.4 KURVA S PEKERJAAN DI GUDANG ........................................................................................................... 9-3
TABEL 9.5 JADWAL PENUGASAN TENAGA AHLI ......................................................................................................... 9-3
TABEL A.1 DATA DAN INFORMASI YANG PERLU DIKUMPULKAN........................................................................................ 3
TABEL A.2 PENTAHAPAN PADA MODEL NRECA........................................................................................................ 11
TABEL A.3 PARAMETER MODEL SACRAMENTO (VRUGT, ET AL., 2006) ..................................................................... 14
TABEL A.4 NILAI KOEFISIEN TANAMAN PADI ............................................................................................................. 16
TABEL A.5 NILAI KOEFISIEN TANAMAN PALAWIJA (DIGUNAKAN UNTUK ETO FAO) ......................................................... 17
TABEL A.6 NILAI PERKOLASI UNTUK BERBAGAI TEKSTUR TANAH................................................................................... 17
TABEL A.7 KOEFISIEN PENGALIRAN ......................................................................................................................... 25
TABEL A.8 HARGA-HARGA KOEFISIEN KONTRAKSI ....................................................................................................... 27
TABEL A.9 PARAMETER K DAN N (CHOW, 1986)....................................................................................................... 28
TABEL A.10 KECEPATAN PENGENDAPAN .................................................................................................................. 30

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN ix


LAPORAN AKHIR

BAB 1 PENDAHULUAN

1.1 LATAR BELAKANG


1.1.1 Kondisi Lahan Rencana Areal Daerah Irigasi
Rencana areal Daerah Irigasi Gudang termasuk daerah datar dan merupakan daerah rawa tetapi
tidak dipengaruhi pasang-surut muka air laut. Pada lokasi areal Daerah Irigasi Gudang ini telah
dilakukan pekerjaan Pencetakan Sawah oleh Dinas Pertanian dan Peternakan Kabupaten Bangka
Selatan pada tahun anggaran 2013, dan telah dilakukan budidaya penanaman padi sawah pada
tahun 2014 dengan 2 kali musim tanam.
Dengan adanya Pencetakan Sawah tersebut di atas, maka lahan sudah terbuka, tidak terdapat
pohon-pohon besar, namun karena budidaya penanaman padi sawah hanya dilakukan pada tahun
2014 dan selanjutnya sampai saat ini tidak dilakukan penanaman maka hampir 50% lahan pada saat
ini tertutup kembali oleh vegetasi semak belukar.
Pada areal Daerah Irigasi, telah dibangun tata air/sistem pengendalian air, yang terdiri dari :
 Saluran dan tanggul keliling pada batas areal;
 Ruas-ruas saluran di tengah areal;
 Saluran pembuang (external drain), mengalirkan kelebihan air dari lahan ke Sungai Babuar.
Tujuan dari dibangunnya saluran-saluran, tanggul keliling dan saluran pembuang utama ini untuk
mengatasi masalah genangan, namun karena sistem tidak dilengkapi dengan bangunan Pintu
Pengatur maka terjadi masalah genangan dan kekurangan air di lahan, yaitu :
• Karena beban limpahan curah hujan di lahan cukup besar, sementara di Sungai Babuar terjadi
banjir dan dalam kondisi pasang, maka air sungai masuk ke lahan melalui saluran pembuang
utama, sehingga terjadi genangan di lahan;
• Pada saat tidak terjadi hujan/musim kemarau, debit Sungai Babuar dalam keadaan normal
sampai relatif mengecil, maka air yang ada di lahan keluar tidak terkendali melalui saluran
pembuang utama, sehingga muka air di lahan turun dan lahan tidak dapat ditanami;
Bulan Juni 2016 terjadi banjir Sungai Babuar cukup besar dan besarnya beban limpahan curah hujan
di lahan, mengakibatkan air sungai melimpah masuk ke lahan sehingga terjadi genangan yang cukup
tinggi. Berdasarkan informasi dari ketua Gapoktan Desa Gudang Bapak Muslimin, genangan
mencapai ketinggian rata-rata di atas tanggul ± 0,70 m.

1.1.2 Potensi Sumber Air dan Prasarana Sumber Daya Air


Sumber air untuk rencana Daerah Irigasi Gudang adalah Sungai Babuar yang terletak di bagian hulu
areal. Disamping sumber air permukaan tersebut di atas, potensi curah hujan di sekitar lokasi
rencana Daerah Irigasi yang cukup tinggi, juga dapat digunakan sebagai sumber air untuk memenuhi
kebutuhan air tanaman terutama pada Musim Tanam di musim hujan.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 1-1


LAPORAN AKHIR

Selain sistem tata air tersebut di atas, di sekitar lokasi rencana Daerah Irigasi Desa Gudang terdapat
prasarana sumber daya air berupa bangunan Pintu Air pada Sungai Babuar, yang bertujuan untuk
mengalirkan air Sungai Babuar ke lahan guna memenuhi kebutuhan air untuk tanaman.
Dari hasil peninjauan di lapangan dan berdasarkan informasi dari ketua dan sekertaris Gapoktan
Desa Gudang, bangunan Pintu Air eksisting tersebut tidak berfungsi.

1.1.3 Permasalahan
Berdasarkan uraian mengenai kondisi lahan tersebut di atas, maka permasalahan pokok yang
terdapat pada lokasi rencana Daerah Irigasi Gudang, adalah tidak dapat dilakukan budidaya
penanaman padi/sawah, karena :
• Pada musim hujan lahan tergenang.
• Pada musim kemarau, muka air di lahan turun, sehingga tidak dapat memenuhi kebutuhan
air untuk tanaman padi/sawah, atau terjadi kekurangan air.
Permasalahan yang ada tersebut di atas yaitu lahan tergenang, kekurangan air ke lahan, pada
dasarnya adalah karena sistem tata air yang ada tidak dilengkapi dengan bangunan Pintu Pengatur
Air.

1.1.4 Rencana Penanganan


Upaya penanganan yang perlu dilakukan dalam Perencanaan Jaringan Irigasi D.I. Gudang adalah
merencanakan sistem tata air dengan komponen sistem yang lengkap sesuai kebutuhan, yaitu terdiri
dari :
• Saluran-saluran yang berfungsi untuk mengalirkan beban limpahan curah hujan sehingga
tidak terjadi genangan pada lahan.
• Pada musim kemarau saluran dapat berfungsi sebagai long storage sehingga dapat
memenuhi kebutuhan air untuk tanaman, atau minimal dapat mepertahankan tinggi muka
air tanah agar masih berada pada zona perakaran tanaman padi.
• Bangunan Pintu Pengatur pada saluran pembuang utama yang berfungsi untuk mencegah
masuknya aliran banjir sungai ke lahan dan dapat mengalirkan kelebihan air dari lahan.
• Pintu direncanakan berupa Pintu Klep otomatis yang dilengkapi Pintu Sorong di bagian
hulunya agar dapat menahan air sehingga tidak terjadi kekeringan.
• Bangunan Pengambilan (Intake) pada sungai/sumber air dan mengalirkan air masuk lahan
untuk memenuhi kebutuhan air terutama dimusim kemarau.

1.2 REFERENSI DAN SUMBER HUKUM


Sumber referensi hukum mengikuti peraturan – peraturan yang berlaku di Indonesia antara lain :
A. Undang - Undang
a. Undang – Undang No. 11 tahun 1974 tentang Pengairan;
b. Undang – Undang No. 7 tahun 2004 tentang Sumber Daya Air;
B. Peraturan Pemerintah

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 1-2


LAPORAN AKHIR

a. Peraturan Pemerintah No. 20 tahun 2006 tentang Irigasi;


b. Peraturan Pemerintah No. 42 tahun 2008 tentang Pengelolaan Sumber Daya Air;
c. Peraturan Pemerintah No. 38 tahun 2011 tentang Sungai.
C. Peraturan Presiden / Keputusan Presiden
a. Inpres No. 3 tahun 1999 tentang Pembaharuan Kebijaksanaan Pengelolaan Irigasi
Presiden Republik Indonesia.
D. Peraturan Menteri
a. Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Nomor
12/PRT/M/2015 tentang Eksploitasi dan Pemeliharaan Jaringan Irigasi.
E. Standar Perencanaan Irigasi (Kementrian PU Direktorat jenderal Sumber Daya Air)
a. SDA – KP 01 – Spesifikasi Teknis Kriteria Perencanaan – Jaringan Irigasi;
b. SDA – KP 02 – Spesifikasi Teknis Kriteria Perencanaan – Bangunan Utama;
c. SDA – KP 03 – Spesifikasi Teknis Kriteria Perencanaan – Saluran;
d. SDA – KP 04 – Spesifikasi Teknis Kriteria Perencanaan – Bagian Bangunan;
e. SDA – KP 05 – Spesifikasi Teknis Kriteria Perencanaan – Petak Tersier;
f. SDA – KP 06 – Spesifikasi Teknis Kriteria Perencanaan – Parameter Bangunan;
g. SDA – KP 07 – Spesifikasi Teknis Kriteria Perencanaan – Standar Penggambaran;
h. SDA – KP 08 – Spesifikasi Teknis Kriteria Perencanaan – Standar Pintu Pengatur Air
Irigasi – Perencanaan, Pemasangan, Operasi, dan Pemeliharaan;
i. SDA – KP 09 – Spesifikasi Teknis Kriteria Perencanaan – Standar Pintu Pengatur Air
Irigasi – Spesifikasi Teknis.

1.3 MAKSUD DAN TUJUAN


Maksud dari pekerjaan ini adalah mengadakan penyusunan perencanaan sistem irigasi yang efektif
dan efisien untuk Jaringan Daerah Irigasi Gudang di Desa Gudang Kecamatan Simpang Rimba
Kabupaten Bangka Selatan.
Tujuan dari proyek Daerah Irigasi Gudang ini adalah untuk menyediakan jaringan irigasi bagi Daerah
Irigasi Gudang Kabupaten Bangka Selatan.

1.4 LOKASI PEKERJAAN


Lokasi pekerjaan Daerah Irigasi Gudang di Desa Gudang terletak di Kecamatan Simpang Rimba
Kabupaten Bangka Selatan Provinsi Kepulauan Bangka Belitung, secara geografis terletak antara 2°
35 '07.11" Lintang Selatan dan 106° 00' 09.5" Bujur Timur. Untuk mencapai lokasi pekerjaan ini dapat
ditempuh dengan jalur berikut:

 Jakarta - Pangkal Pinang dengan pesawat waktu tempuh ±45 menit atau Jakarta -
Pangkalpinang dengan kapal waktu tempuh ±23 jam;

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 1-3


LAPORAN AKHIR

 Pangkal Pinang - Simpang Rimba (kecamatan di Bangka Selatan) dengan kendaraan roda 4
selama ±1,5 jam
 Simpang Rimba - Desa Gudang melalui jalan Raya Sawahan dengan jarak ±22 km dan waktu
tempuh selama ±30 menit;

Lokasi proyek DED Irigasi


Gudang, Bangka Selatan

Gambar 1.1 Lokasi Pekerjaan

1.5 INFORMASI KEGIATAN


Informasi Kegiatan yang akan dilaksanakan adalah sebagai berikut :
Nama Pekerjaan : Daerah Irigasi Gudang di Desa Gudang Kecamatan Simpang Rimba
Lokasi Pekerjaan : Kabupaten Bangka Selatan, Propinsi Kepulauan Bangka Belitung
Jangka Waktu : 120 (Seratus Duapuluh) Hari Kalender
Nama Pengguna Jasa : Dinas Pekerjaan Umum dan Penataan Ruang Kabupaten Bangka
Selatan

1.6 LINGKUP PEKERJAAN


Lingkup kegiatan meliputi :
I. Umum
Melaksanakan sistem irigasi di daerah studi. Disamping itu Konsultan harus menyusun
rencana sistem irigasi.
i. Pengukuran dan perencanaan jaringan utama dan bangunan pengambilan.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 1-4


LAPORAN AKHIR

ii. Desain Jaringan Irigasi, meliputi desain saluran pembawa, saluran pembuang, dan
bangunan airnya.
iii. Penyelidikan tanah jika diperlukan.
II. Kegiatan persiapan
A. Pengumpulan data sekunder dan program kerja meliputi
i. Pengkajian tata letak jaringan irigasi
ii. Pengkajian desain jaringan utama/tersier
iii. Pengkajian peta kesesuaian lahan
iv. Pengkajian peta tata guna lahan
v. Pengkajian data hidrologi, ketersediaan air dan genangan banjir
vi. Penyiapan program kerja
B. Pengumpulan data sekunder dan program kerja meliputi
i. Program kerja survey (jadwal kerja dan personil)
ii. Pembuatan peta kerja
iii. Pemeriksaan alat survey.
C. Pembuatan Laporan Pendahuluan
III. Kegiatan Survey Lapangan
A. Investigasi Data Primer
i. Inventarisasi penggunaan lahan
ii. Kondisi vegetasi dan kemiringan lahan
iii. Inventarisasi kondisi jaringan irigasi
B. Pengukuran, pemasangan BM dan Pemetaan
Pengukuran dalam perencanaan merupakan pekerjaan wajib yang harus
dilaksanakan. Pengukuran merupakan pengambilan data primer terhadap kondisi
lapangan. Pada kegiatan ini pengukuran daerah layanan irigasi dengan bantuan alat
theodolite dan GPS, dan pengukuran debit air sebagai data pembanding dengan
analisa hidrologi. Juga perlu dilakukan uji tanah dengan pengambilan sampel sesuai
standar SNI dan sondir. Hasil pengukuran dibukukan dalam buka hasil pengukuran.
BM harus disesuaikan dengan BM pengukuran nasional.
i. Pembuatan Bench Mark baru
ii. Pengukuran dan pemetaan situasi
iii. Pengukuran trase jaringan utama
iv. Pengukuran situasi bangunan
C. Perencanaan Sawah Tertinggi

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 1-5


LAPORAN AKHIR

Perencanaan sawah tertinggi sangat penting untuk mengetahui level mercu yang
akan direncanakan. Perencanaan ini akan menjadi acuan bagi percetakan sawah
baru sehingga akan menyesuaikan dengan level ini sebagai limit tertinggi.
D. Pembuatan Sistem Planning dan Peta Petak
Menyusun peta petak dan system planning untuk keseluruhan areal yang akan
diairiyang akan mengintegrasikan rencana perluasan jaringan irigasi.
E. Perencanaan Detail
Perencanaan detail jaringan utama (Bangunan Pengambilan, saluran pembawa, dan
pembuang beserta bangunan-bangunannya). Perencanaan bangunan utama
disesuaikan dengan kemampuan daerah tangkapan dan kemampuan secara
hidrologi pada kawasan tersebut. Pada Perencanaan ini, bangunan utama berupa
bendung yang direncanakan dengan safety factor minimal 3, detail bestek, detail
spesifikasi bahan dengan diutamakan bahan yang berasal dari bahan lokal, detail
tata cara pelaksanaan dan pengujian, serta detail pengoperasian dan pemeliharaan.
Umur bangunan direncanakan minimal 25 tahun.
F. Sumber Air
Konsultan harus melakukan penelitian terhadap semua sumber-sumber yang
terdapat di sekitar daerah studi dan mengevaluasi sumber air yang diusulkan dalam
rancangan rinci pekerjaan ini meliputi antara lain :
i. Pengumpulan dan evaluasi dari data yang ada tentang kondisi hidrologi,
geohidrologi, hidrolika aliran dan sedimentasi.
ii. Melakukan survey di lapangan yang meliputi pengenalan, pengukuran debit
dan fluktuasi sumber-sumber air, sampling air dan memeriksakan ke
laboratorium berdasarkan pemeriksaan standar.
G. Perencanaan SOP Bangunan dan Kawasan.
Perencanaan Standar Operasi dan Pemeliharaan bangunan merupakan buku
manual dalam OP Irigasi pada masa mendatang. Perencanaan SOP Kawasan yang
dimaksud adalah perencanaan yang dilakukan untuk mempertahankan kawasan
tersebut tetap utuh baik sebagai daerah pertanian maupun sebagai daerah
tangkapan. Di dalam SOP kawasan tersebut terdapat larangan maupun kewajiban
terhadap kegiatan di kawasan tersebut, misalnya pada daerah pertanian dilarang
menanam tanaman keras seperti sawit atau karet , pada daerah tangkapan misalnya
dilarang melakukan aktifitas yang dapat merusak hujan dengan jarak berapa meter
dari sumber air atau diwajibkan menanam pohon yang dapat menangkap dan
membantu perkolasi atau penyaringan air tanah di kawasan yang ditentukan dalam
buku SOP kawasan tersebut.
H. Non Teknis
Dalam pekerjaan-pekerjaan yang bersifat non teknis, didalam pekerjaan ini
menyangkut pekerjaan survey/laporan sosial ekonomi, besarnya investasi, biaya

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 1-6


LAPORAN AKHIR

operasi dan pemeliharaan serta sumber dana untuk investasi, tarif air dan struktur
yang diusulkan juga jadwal pembiayaan proyek.

1.7 SISTEMATIKA PELAPORAN


BAB 1 : PENDAHULUAN
Pada bab ini diuraikan mengenai latar belakang, referensi dan sumber hukum, maksud dan tujuan,
lokasi pekerjaan, informasi kegiatan, dan lingkup pekerjaan.
BAB 2 : GAMBARAN UMUM LOKASI STUDI
Bab ini menjelaskan mengenai kondisi eksisting wilayah pekerjaan, dilihat dari sudut pandang
administrasi, geografi, iklim, hidrologi, geologi, faktor kegempaan, pertanian, daerah irigasi,
demografi, sosial-budaya, dan ekonomi.
BAB 3 : KETERSEDIAAN DATA
Pada bab ini akan diuraikan data-data yang dibutuhkan untuk analisis perencanaan daerah irigasi.
BAB 4 : PEMETAAN TOPOGRAFI
Pada bab ini akan diuraikan kondisi topografi, referensi pengukuran, patok pengukuran, serta peta
dan gambar pengukuran untuk pekerjaan topografi di area DI Gudang.
BAB 5 : HASIL ANALISIS
Pada bab ini diuraikan mengenai hasil perhitungan analisis perencanaan daerah irigasi, mencakup
debit andal dan debit banjir area proyek.
BAB 6 : HASIL PERENCANAAN
Pada bab ini diuraikan hasil perencanaan tata letak petak sawah serta jaringan irigasi mencakup
bangunan-bangunan dan saluran irigasi di area DI Gudang.
BAB 7: ESTIMASI VOLUME DAN RENCANA ANGGARAN BIAYA (RAB) PELAKSANAAN
Pada bab ini diuraikan estimasi volume dan biaya pelaksanaan, serta rekapitulasi biaya pekerjaan
irigasi Gudang.
BAB 8: OPERASI DAN PEMELIHARAAN
Bab ini menjelaskan mengenai pokok kegiatan operasi jaringan irigasi, operasi bangunan pada
jaringan irigasi, alat pengukur debit, pemeliharaan jaringan irigasi, dan evaluasi operasi jaringan
irigasi.
BAB 9: ORGANISASI PELAKSANA DAN RENCANA KERJA
Pada bab ini dijelaskan struktur organisasi dan jadwal pelaksanaan pekerjaan jaringan irigasi Gudang.
BAB 10: SIMPULAN DAN SARAN
LAMPIRAN:
A. METODOLOGI PEKERJAAN
B. TABULASI HASIL ANALISIS HIDROLOGI (DEBIT ANDAL DAN DEBIT BANJIR)
C. BOQ DAN RAB

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 1-7


LAPORAN AKHIR

BAB 2 GAMBARAN UMUM LOKASI STUDI

2.1 GAMBARAN UMUM LOKASI


2.1.1 Administrasi
Lokasi pekerjaan Daerah Irigasi Gudang di Desa Gudang terletak di Kecamatan Simpang Rimba,
Kabupaten Bangka Selatan, Provinsi Kepulauan Bangka Belitung. Menurut data Statistik, Kecamatan
Simpang Rimba merupakan salah satu wilayah bagian dari Kabupaten Bangka Selatan yang secara
geografis mempunyai luas sekitar 36.232 Ha (sudah termasuk hutan negara). Wilayah ini berbatasan
dengan :

 Sebelah Utara : Kabupaten Bangka Tengah


 Sebelah Barat : Selat Bangka
 Sebelah Timur : Kecamatan Payung dan Kecamatan Pulau Besar
 Sebelah Selatan : Selat Bangka

Gambar 2.1 Peta Administrasi Kabupaten Bangka Selatan

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-1


LAPORAN AKHIR

2.1.2 Geografi
Secara geografis terletak antara 2° 35' 07.11" LS dan 106° 00' 09.5" BT. Kecamatan Simpang Rimba
berada pada ketinggian antara 7 - 28 m di atas permukaan laut. Sebagian besar wilayah desa yang
ada di Kecamatan Simpang Rimba terletak di daerah dataran rendah. Luas Kecamatan Simpang
Rimba adalah 36.232 Ha, yang terbagi kedalam 7 Desa. Desa dengan wilayah terluas yaitu Desa
Gudang yaitu 11.606,2 Ha, sementara desa yang terkecil luasnya adalah Desa Rajik dengan luas
2.225 Ha. Untuk lebih rincinya dapat dilihat pada tabel di bawah ini.
Tabel 2.1 Luas Desa di Kecamatan Simpang Rimba (Ha)

No Desa Luas Desa Persentase

1. Jelutung II 5 012,2 13,83


2. Gudang 11 606,2 32,03
3. Sebagin 6 243,1 17,23
4. Rajik 2 225,0 6,14
5. Simpang Rimba 3 096,0 8,55
6. Bangka Kota 5 631,4 15,54
7. Permis 2 418,1 6,68
Jumlah/Total 36 232,0 100,00
Sumber : Kecamatan Simpang Rimba Dalam Angka 2017

Sedangkan untuk penggunaan Lahan di Kecamatan Simpang Rimba dapat dilihat dari tabel dibawah
ini.
Tabel 2.2 Jenis Penggunaan Lahan di Kecamatan Simpang Rimba

Bangunan/
No Desa Lahan Kering Lahan Sawah
Pekarangan
1. Jelutung II 51,98 4 110,22 850
2. Gudang 20,40 11 425,80 160
3. Sebagin 19,90 5 723,20 500
4. Rajik 21,89 2 203,11 -
5. Simpang Rimba 21,63 3 074,37 -
6. Bangka Kota 84,97 5 546,43 -
7. Permis 22,46 2 395,64 -
Jumlah/Total 243,23 34 478,77 1 510
Sumber : Kecamatan Simpang Rimba Dalam Angka 2017

2.1.3 Iklim
Kabupaten Bangka Selatan beriklim Tropis Tipe A dengan variasi curah hujan antara 4,0 hingga 466,2
mm tiap bulan untuk tahun 2012 dengan curah hujan terendah pada bulan Agustus. Suhu rata-rata
daerah Kabupaten Bangka Selatan berdasarkan data dari Badan Meteorologi dan Geofisika Stasiun
Klimatologi Pangkalpinang menunjukkan variasi antara 26,10 Celcius hingga 28,00 Celcius.
Sedangkan kelembaban udara bervariasi antara 74 hingga 88 persen pada tahun 2012. Sementara,
intensitas penyinaran matahari pada tahun 2012 rata-rata bervarias antara 27,6 hingga 82,3 persen
dan tekanan udara antara 1009,3 hingga 1011,5 mb.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-2


LAPORAN AKHIR

Tabel 2.3 Pos Hujan di Kabupaten Bangka Selatan

Kota Nama Stasiun Alamat


Stasiun Meteorologi Klas III Bandara Dipati Amir, Bangka,
Pangkal Pinang
Pangkalpinang Pangkalpinang 33171
Sumber : Stasiun BMKG Indonesia

Gambar 2.2 Lokasi Stasiun Hujan BMKG Pangkalpinang

Lokasi Pekerjaan

Gambar 2.3 Peta Hujan Sumatera dan Bangka Belitung

2.1.4 Hidrologi
Pada umumnya sungai di daerah Kabupaten Bangka Selatan berhulu di daerah perbukitan dan
pegunungan dan bermuara di pantai laut. Sungai yang terdapat di daerah Kabupaten Bangka Selatan
dapat dikelompokkan menjadi 3 (tiga) yaitu sungai utama, sungai sekunder dan sungai tersier.
Sungai utama antara lain Sungai Bantel, Sungai Kepuh, Sungai Kurau, dan Sungai Bangka Kota.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-3


LAPORAN AKHIR

Sungai-sungai tersebut berfungsi sebagai sarana transportasi dan belum bermanfaat untuk
pertanian dan perikanan karena para nelayan lebih cenderung mencari ikan ke laut.
Tabel 2.4 Nama-nama Sungai yang Ada menurut Kecamatan di Kabupaten Bangka Selatan

Pada dasarnya di Daerah Kabupaten Bangka Selatan tidak ada danau alam, hanya ada bekas
penambangan bijih timah yang luas dan hingga menjadikannya seperti danau buatan yang disebut
kolong.

2.1.5 Geologi
Keadaan tanah di daerah Kabupaten Bangka Selatan mempunyai pH rata-rata di bawah 5,
didalamnya mengandung mineral biji timah dan bahan galian lainnya seperti: Pasir Kwarsa, Kaolin,
Batu Gunung dan lain-lain. Bentuk dan keadaan tanahnya adalah sebagai berikut:
 4% berbukit seperti Bukit Paku, Permis dan lain-lain. Jenis tanah perbukitan tersebut adalah
Komplek Podsolik Coklat Kekuning-kuningan dan Litosol berasal dari Batu Plutonik Masam.
 51% berombak dan bergelombang, tanahnya berjenis Asosiasi Podsolik Coklat Kekuning-
kuningan dengan bahan induk Komplek Batu pasir Kwarsit dan Batuan Plutonik Masam.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-4


LAPORAN AKHIR

 20% lembah/datar sampai berombak, jenis tanahnya asosiasi Podsolik berasal dari Komplek
Batu Pasir dan Kwarsit.
 25% rawa dan bencah/datar dengan jenis tanahnya Asosiasi Alluvial Hedromotif dan Glei
Humus serta Regosol Kelabu Muda berasal dari endapan pasir dan tanah liat.
2.1.5.1 Fisiografi Kepulauan Bangka
Secara fisiografi, Pulau Bangka termasuk ke dalam Sunda Land dan merupakan bagian terangkat dari
peneplain Sunda. Bila ditinjau dari sudut geologi, penyebaran bijih timah di Indonesia masih
merupazkan kelanjutan dari ”Granite Belt” yang berumur Yura – Kapur yang membentang mulai dari
Birma, Muangthai, Malasyia, Kepulauan Riau (Pulau Singkep, Pulau Karimun dan Pulau Kundur),
pulau Bangka dan Pulau Belitung hingga Pulau Karimata. ”Granite Belt” sendiri merupakan deretan
formasi batuan granite kaya akan mineral cassiterite yang kemudian dikenal dengan sebutan ”The
Tin Belt”.
Pulau-pulau dari ”The Tin Belt” diinterpretasikan merupakan sisa bagian resisten dari gunung yang
muncul pada masa terbentuknya Sunda Shelf. Pupili (1973) menyatakan bahwa Malaysia, Kepulauan
Riau, dan Bangka berada dalam kelompok elemen tektonik yang sama. Evolusi tektonik di wilayah
ini telah dimulai sejak Paleozoikum Bawah dimana berdasarakan Teori Tektonik Lempeng bahwa
daerah penunjaman (subduction zone) berada di bagian timur Malysia dan pada Mesozoikum
Bawah – tengah menghasilkan busur gunung api (magmatic arc) dalam bentuk deretan Pulau
Kundur, Pulau Singkep, Pulau Bangka, Pulau Belitung dan sebagian dari Kalimantan Barat.
Bangka merupakan daerah dengan stadia erosi tingkat lanjut, hal ini dicirikan dengan keadaan yang
umumnya relatif datar dan adanya bukit-bukit sisa erosi (“monadrock”). Bukit-bukit sisa erosi
tersebut tersusun atas batuan beku granit yang umumnya menempati bagian tepi P.Bangka.

 Di bagian utara: Granit Klabat, yang berrrientasi barat-timur melewati teluk Klabat, granit yang
ada di sekitarnya terdiri atas granit Pelangas, granit Menumbing, granit Mangkol.
 Di bagian selatan: Tersusun atas pluton yang lebih kecil yaitu Pluton Koba, Pluton Bebuluh,
Pluton Permis, dan granit Toboali, serta pluton yang lain yang terletak di antaranya.
Daerah pedataran menempati ± 80% luas seluruh daerah. Daerah inilah merupakan tempat endapan
alluvial yang mengandung konsentrasi bijih Timah. Umumnya sungai-sungai yang ada mengalir di
atas endapan-endapan muda (Plistosen/Pliosen), kecuali pada hulu-hulu sungai /dekat pada daerah
perbukitan.
2.1.5.2 Tatanan Stratigrafi Regional
Stratigrafi regional daerah studi mengacu pada Peta Geologi skala 1:50.000 Lembar Bangka Selatan
yang diterbitkan oleh Pusat Penelitian dan Pengembangan Geologi. Berdasarkan peta geologi di
bawah, struktur geologi yang teramati di lembar Bangka Selatan adalah kelurusan, lipatan dan sesar.
Kelurusan terutama pada granit dengan arah beragam. Lipatan terdapat pada satuan batupasir dan
batulempung formasi Tanjung Genting dan formasi Ranggam dengan kemiringan antara 18-75
derajat. Sumbu lipatan diduga berarah TL-BD. Dua jenis sesar yang berkembang adalah sesar
mendatar dan sesar normal. Sesar mendatar berarah TL-BD, sedangkan sesar normal berarah BL-
TG.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-5


LAPORAN AKHIR

Kegiatan tektonik ditafsirkan berlangsung sejak Perm yang ditandai dengan terbentuknya Kompleks
Malihan Pemali. Pada Trias Awal terjadi penurunan dan pengendapan formasi Tanjung Genting
dalam lingkungan laut dangkal. Kemudian pada Trias Akhir-Jura Akhir terjadi pengangkatan dan
diikuti penerobosan Granit Klabat. Mulai Miosen Tengah-Pliosen Awal pengendapan berlangsung
dengan terbentuknya formasi Ranggam di lingkungan fluvial. Selanjutnya pengangkatan dan
pengendapan aluvial di sungai, rawa dan pantai berlangsung pada Holosen.
Sumberdaya mineral utama di daerah Bangka Selatan adalah timah putih, dengan mineral
tambahannya berupa monazite, zircon, xenotim, ilmenit, magnetit dan pirit. Endapan timah
terdapat sebagai endapan timah primer dan sekunder. Endapan timah primer ditemukan dalam
tubuh gneissic granit di gunung Sepat dekat Lubuk Besar, sedangkan endapan timah sekunder
terdapat di sepanjang alur-alur sungai purba.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-6


LAPORAN AKHIR

Lokasi Pekerjaan

Gambar 2.4 Peta Geologi Kecamatan Simpang Rimba

Dapat dilihat pada Gambar 2.4, bahwa lokasi studi ada di formasi Rt (pada peta berwarna hijau).
Formasi ini dinamakan formasi Tanjung Genting, terdiri atas perselingan batupasir dan
batulempung. Batupasir berwarna kelabu kecoklatan, berbutir halus-sedang, sortasi baik, keras dan
tebal lapisan 2-60 cm. Struktur sedimen berupa cross bedding dan ripple mark. Setempat ditemukan
lensa batugamping setebal 1,5 meter. Batulempung berwarna kelabu kecoklatan, berlapis baik
dengan tebal 15 meter, setempat dijumpai lensa batupasir halus. Dalam lensa batugamping
Osberger menemukan fosil Montlivaultia molukkana (J. Wanner), Peronidella (G. Wilkens),
Entrochus sp. dan Encrinus sp. yang menunjukkan umur Trias. Berdasarkan kandungan fosil-fosil
tersebut formasi ini diduga berumur Trias Awal dan terendapkan di lingkungan laut dangkal. Kontak
dengan granit ditemukan di utara Lembar Bangka Selatan. Formasi Tanjung Genting terendapkan
tidak selaras di atas batuan malihan.
Batuan-batuan yang dijumpai terdiri atas batuan Pra-Tersier di antaranya, batu pasir, batu lempung,
lapisan-lapisan pasir, lempung mengandung sisa tanaan, campuran antara lempung-pasir-lanau,dan
sebagainya.
Menurut Katili (1967) di P. Bangka terdapat 2 generasi granit. Granit yang tua tidak mengandung
kasiterit dan umunya terdapat di daerah rendah, yakni granit Klabat & A. Kapo. Granit generasi muda
sebagai pembawa Timah umumnya telah tererosi lanjut (“monadnock”). Menurut Suyitno, S (1981),
generasi granit tersebut adalah :
1. Granit Klabat-Jebus, terletak di utara.
2. Granit Belinyu-Sungailiat, menybar di bagian timur granit Jebus.
3. Granit Menumbing
4. Granit Tempilang
5. Granit Mangkol
6. Granit Pading-Koba
7. Granit Toboali
Granit yang terpenting adalah granit Klabat, Menumbing, Plangas, Tempilang, Mangkol, dan Pading.
Umumnya tubuh granit tersebut tersusun atas granit biotit, granit hornblende, granit muskovit;

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-7


LAPORAN AKHIR

mineral yang umum terdiri atas kwarsa, ortoklas, oligoklas, biotit, serta sebagai asesori zircon,apatit,
dan ortit.
Ada empat kelompok endapan yang dianggap mewakili sedimentasi Quarter di Pulau Bangka, antara
lain :

 Lapisan Alluvium Muda, umumnya mengandung bijih timah, terdapat di lembah, di atas
batuan Pra Tersier dan dialasi lapisan lempung liat.
 Lapisan Marine Muda, menutupi lapisan alluvium muda, berupa pasir hingga lempung.
 Lapisan Alluvium Tua, mewakili keadaan daratan yang meluas pada saat regeresi muka ait
laut karena glacial.
 Lapisan Marine Tua, merupakan bidang erosi dan dapat dikorelasikan dengan lapisan
lempung liat

2.1.6 Hidrogeologi
Air tanah bawah permukaan adalah air tanah yang menempati rongga dalam lapisan batuan atau
formasi geologi seperti sungai bawah tanah, air sumur, dan lain-lain. Air tanah bawah permukaan
dapat ditemukan pada lapisan jenuh air atau akuifer. Kondisi air tanah pada daerah di sekitar
Kecamatan Simpang Rimba menunjukkan akuifer produktivitas kecil hingga sedang. Komposisi
litologinya berupa endapan aluvium pantai dan rawa serta batupasir dengan tingkat kelulusan
sedang hingga tinggi. Untuk menentukan kedalaman muka air tanah secara detail, maka investigasi
tanah (soil investigastion) perlu dilakukan.

Lokasi Pekerjaan

Gambar 2.5 Peta Hidrogeologi Kecamatan Simpang Rimba

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-8


LAPORAN AKHIR

2.1.7 Faktor Kegempaan


Respons spektrum untuk Bangka Selatan dengan berbagai kategori tanah dapat dilihat pada Gambar
2.6. Sementara parameter pada Tabel 2.5 Parameter respon spektra desain mengambil asumsi
kondisi terburuk katergori tanah lunak. Berikut penentuan kategori resiko bangunan berdasarkan
Desain Spektra Indonesia.
 Asumsi kategori tanah on-site yang adalah tanah lunak (SE).

 Parameter respons spektra percepatan gempa MCER terpetakan untuk periode pendek, Ss
= 0,063 g.
 Parameter repons spectra percepatan gempa MCER terpetakan untuk periode 1,0 detik, S1
= 0,078 g.
 Koefisien situs periode pendek, Fa = 2,5.

 Kofefisien situs periode 1,0 detik, Fv = 3,5.

 Parameter percepatan desain spektral periode pendek, SDS = 0,106g.


 Parameter percepatan desain spektral periode pendek, SD1 = 0,182g.
 Kategori risiko : Tipe IV
Tabel 2.5 Parameter respon spektra desain

Parameter Spektrum Respons


Kelas Situs SE Tanah Lunak
Dari Peta
Ss 0,063 g
S1 0,078 g
Koefisien Situs
Fa 2,5
Fv 3,5
Parameter
SMS 0,159 g
SM1 0,273 g
Parameter Percepatan Desain
SDS 0,106 g
SD1 0,182 g
Spektrum Respons Desain
To 0,106 detik
Ts 0,106 detik

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-9


LAPORAN AKHIR

Gambar 2.6 Respons Spektrum

Penentuan kategori desain seismik (KDS) dari bangunan didesain berdasarkan SNI 1726:2012 Pasal
6.5. Yang ditentukan berdasakan SDS dan SD1 dalam Tabel 1.2 dan Tabel 1.3.
Tabel 2.6 Kategori desain seismic berdasarkan parameter respons percepatan pada perioda pendek

Tabel 2.7 Kategori desain seismik berdasarkan parameter respons percepatan pada perioda 1 detik

Dari tabel diatas dapat disimpulkan bahwa dengan nilai SDS = 0,106g dan SD1 = 0,182g maka kategori
resiko IV dan masuk dalam KDS C.

2.1.8 Pertanian
Data produksi tanaman pertanian (padi dan palawija) disajikan dalam kualitas : gabah kering giling
(padi), pipilan kering (jagung), biji kering (kedelai dan kacang tanah), dan umbi basah (ubi kayu dan
ubi jalar). Berdasarkan data Badan Pusat Statistik Kabupaten Bangka Selatan tahun 2017, bahwa
produksi palawija yang berpengaruh terhadap pola pemodelan irigasi di kecamatan Simpang Rimba

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-10


LAPORAN AKHIR

terdiri dari jagung, ketela, dan ubi jalar. Jumlah produksi per desa dapat diihat pada Tabel 2.8 dan
Tabel 2.9.
Tabel 2.8 Luas Panen (Ha), Produksi Sawah dan Padi Ladang (Ton) Menurut Desa di Kecamatan Simpang Rimba, 2016
(Sumber : BPS Kab. Bagka Selatan, 2017)

Tabel 2.9 Luas Panen (Ha), Produksi Produksi Palawija (Ton) Menurut Desa di Kecamatan Simpang Rimba, 2016
(Sumber : BPS Kab. Bagka Selatan, 2017)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-11


LAPORAN AKHIR

2.1.9 Daerah Irigasi


Kabupaten Bangka Selatan yang terdiri dari 9 kecamatan memiliki potensi luas baku sawah sebesar
2.081 Ha, yang ditunjukkan pada gambar berikut.

Gambar 2.7 Peta Kalender Tanam Padi Sawah

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-12


LAPORAN AKHIR

Gambar 2.8 Peta Status Ketersediaan Nutrisi Tercerna

Luas total daerah irigasi di Kecamatan Simpang Rimba ada 1.510 Ha, dengan komposisi masa tanam
secara jelas ditampilkan pada tabel berikut. Kalender Tanam Terpadu merupakan pedoman atau alat
bantu yang bisa memberikan informasi spasial dan turbular tentang prediksi musim, awal tanam,
pola tanam, luas tanam potensial, wilayah rawan banjir dan kekeringan.
Tabel 2.10 Kalender Tanam Terpadu Kecamatan Simpang Rimba

Musim Hujan
Tanam Pertama : MT1 Tanam Kedua : MT2
Komoditas
Awal Waktu Tanam Luas Tanam Awal Waktu Tanam Luas Tanam
(dasarian) (ha) (dasarian) (ha)
Padi Sawah NOV I-II 350 MAR I-II 350
Jagung/ Kedelai 0 0
SESUAI PADI SESUAI PADI
Kedelai 0 0

Musim Kemarau
Tanam Pertama : MT3 Tanam Kedua : -
Komoditas
Awal Waktu Tanam Luas Tanam Awal Waktu Tanam Luas Tanam
(dasarian) (ha) (dasarian) (ha)
MASIH ADA
Padi Sawah JUL I-II 350 0
TANAMAN
Jagung/ Kedelai 0 MASIH ADA 0
SESUAI PADI
Kedelai 0 TANAMAN 0
Sumber : Badan Penelitian dan Pengembangan Pertanian – Kementrian Pertanian

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-13


LAPORAN AKHIR

Iklim merupakan sumberdaya yang memainkan peranan penting dalam pembangunan pertaninan.
Ketidak menentuan pola curah hujan dan musim serta anomali iklim merupakan dampak dari
perubahan iklim yang sudah dan akan terjadi. Adapun permasalahan yang mungkin terjadi disaat
masa tanam yang bisa berasal dari bencana maupun hama yang dijelaskan pada tabel berikut.
Tabel 2.11 Jenis Bencana dan Tingkat Kerusakan – Padi

PERKIRAAN LUAS
TINGKAT KERUSAKAAN
NO JENIS BENCANA KERUSAKAAN
TANAMAN
TANAMAN (%)
1 BANJIR AMAN 0,0
2 KEKERINGAN AMAN 0,0
3 WERENG BATANG COKLAT TINGGI 0,2
4 TIKUS SAWAH TINGGI 0,2
5 PENGGEREK BATANG PADI SEDANG 0,1
6 TUNGRO TINGGI 0,1
7 BLAST SANGAT TINGGI 0,4
Sumber : Badan Penelitian dan Pengembangan Pertanian – Kementrian Pertanian
Tabel 2.12 Jenis Bencana dan Tingkat Kerusakan – Jagung

PERKIRAAN LUAS
TINGKAT KERUSAKAAN
NO JENIS BENCANA KERUSAKAAN
TANAMAN
TANAMAN (%)
1 BANJIR AMAN 0,0
2 KEKERINGAN RENDAH 0,0
3 BULAI JAGUNG AMAN 0,0
4 LALAT BIBIT JAGUNG AMAN 0,0
PENGGEREK BATANG
5 AMAN 0,0
JAGUNG
6 PENGGEREK TONGKOL AMAN 0,0
7 TIKUS JAGUNG AMAN 0,0
8 ULAT GRAYAK JAGUNG AMAN 0,0
Sumber : Badan Penelitian dan Pengembangan Pertanian – Kementrian Pertanian
Tabel 2.13 Jenis Bencana dan Tingkat Kerusakan – Kedelai

TINGKAT PERKIRAAN LUAS


NO JENIS BENCANA KERUSAKAAN KERUSAKAAN
TANAMAN TANAMAN (%)
1 BANJIR AMAN 0,0
2 KEKERINGAN AMAN 0,0
3 LALAT KACANG KEDELAI AMAN 0,0
4 PENGGULUNG DAUN KEDELAI AMAN 0,0
PENGGEREK POLONG
5 AMAN 0,0
KEDELAI
6 TIKUS KEDELAI AMAN 0,0
7 ULAT GRAYAK KEDELAI AMAN 0,0
8 ULAT JENGKAL KEDELAI AMAN 0,0
Sumber : Badan Penelitian dan Pengembangan Pertanian – Kementrian Pertanian

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-14


LAPORAN AKHIR

2.2 KONDISI SOSIAL EKONOMI DAN KEPENDUDUKAN


2.2.1 Kondisi Demografi
Sumber utama data kependudukan adalah sensus penduduk yang dilaksanakan setiap sepuluh
tahun sekali. Sensus penduduk telah dilaksanakan sebanyak enam kali sejak Indonesia merdeka,
yaitu tahun 1961, 1971, 1980, 1990, 2000, dan 2010.
Di dalam sensus penduduk, pencacahan dilakukan terhadap seluruh penduduk yang berdomisili di
wilayah teritorial Indonesia termasuk warga negara asing kecuali anggota korps diplomatik negara
sahabat beserta keluarganya.
Metode pengumpulan data dalam sensus dilakukan dengan wawancara antara petugas sensus
dengan responden dan juga melalui e-census. Pencatatan penduduk menggunakan konsep usual
residence, yaitu konsep di mana penduduk biasa bertempat tinggal. Bagi penduduk yang bertempat
tinggal tetap dicacah di mana mereka biasa tinggal, sedangkan untuk penduduk yang tidak
bertempat tinggal tetap dicacah di tempat di mana mereka ditemukan petugas sensus pada malam
‘Hari Sensus’. Termasuk penduduk yang tidak bertempat tinggal tetap adalah tuna wisma, awak
kapal berbendera Indonesia, penghuni perahu/rumah apung, masyarakat terpencil/terasing, dan
pengungsi.
Tabel 2.14 Kependudukan Kecamatan Simpang Rimba

Desa Laki-laki Perempuan Jumlah


Village Male Female Total
1. Jelutung II 2 581 2 476 5 057
2. Gudang 921 927 1 848
3. Sebagin 1 878 1 980 3 858
4. Rajik 2 217 2 011 4 228
5. Simpang Rimba 936 852 1 788
6. Bangka Kota 1 614 1 720 3 334
7. Permis 1 905 1 989 3 894
Jumlah/Total 12 052 11 955 24 007
Sumber : Kecamatan Simpang Rimba Dalam Angka 2017

2.2.2 Kondisi Sosial Budaya


Kondisi dan kualitas rumah/tempat tinggal penduduk dan lingkungannya menunjukkan keadaan
sosial ekonomi rumah tangga. Di Kecamatan Simpang Rimba masih banyak warga masyarakat yang
tinggal di rumah tidak permanen. Selain kondisi rumah, jumlah fasilitas pendidikan dan kesehatan
pun bisa menunjukkan kondisi sosial dan budaya Kecamatan Simpang Rimba.
Tabel 2.15 Kondisi Tempat Tinggal Warga Kecamatan Simpang Rimba

Desa Permanen Semi permanen Lainnya Jumlah


Village Male Female Total Total
(1) (2) (3) (4) (5)
1. Jelutung II 571 430 121 1 122
2. Gudang 217 183 43 443
3. Sebagin 253 191 40 484
4. Rajik 429 382 28 839

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-15


LAPORAN AKHIR

Desa Permanen Semi permanen Lainnya Jumlah


Village Male Female Total Total
(1) (2) (3) (4) (5)
5. Simpang Rimba 116 277 70 463
6. Bangka Kota 308 354 96 758
7. Permis 385 358 27 770
Jumlah/Total 2 279 2 175 425 4 879
Sumber : Kecamatan Simpang Rimba Dalam Angka 2017
Tabel 2.16 Jumlah Sekolah Negeri dan Swasta di Kecamatan Simpang Rimba

Desa SDN SDS SMPN SMPS SMAN SMAS


Village
(1) (2) (3) (4)
1. Jelutung II 2 - 1 - - -
2. Gudang 1 - - - - -
3. Sebagin 1 - - - - -
4. Rajik 1 - 1 - - -
5. Simpang Rimba 1 - 1 - 1 -
6. Bangka Kota 3 - - - - -
7. Permis 2 - - - - -
Jumlah/Total 11 - 3 - 1 -
Sumber : Kecamatan Simpang Rimba Dalam Angka 2017
Tabel 2.17 Jumlah Puskesmas dan Posyandu di Kecamatan Simpang Rimba

Desa Puskesmas Posyandu Posyandu


Aktif Tak Aktif

(1) (2) (3) (4)


1. Jelutung II - 3 -
2. Gudang - 1 -
3. Sebagin - 2 -
4. Rajik - 3 -
5. Simpang Rimba 1 3 -
6. Bangka Kota - 2 -
7. Permis - 3 -
Jumlah/Total 1 17 -
Sumber : Kecamatan Simpang Rimba Dalam Angka 2017

Untuk penggunaan air bersih, sebanyak 4.526 rumah tangga memanfaatkan air sumur pompa, 5.058
rumah tangga menggunakan sumur, 1.321 rumah tangga menggunakan sungai atau danau dan yang
memanfaatkan air dari mata air sebanyak 5.993 rumah tangga
Tabel 2.18 Jumla Rumah Tangga yang Menggunakan Sumber Air untuk MCK dan Air Minum di Kecamatan Simpang
Rimba

Desa Sumur Mata Air Sungai Air


PAM
/Danau Hujan
(1) (2) (3) (4)
1. Jelutung II 631 291 168 - -

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-16


LAPORAN AKHIR

Desa Sumur Mata Air Sungai Air


PAM
/Danau Hujan
(1) (2) (3) (4)
2. Gudang 228 355 51 - -
3. Sebagin 251 282 132 - -
4. Rajik 441 662 34 - -
5. Simpang Rimba 448 542 42 - -
6. Bangka Kota 363 244 25 - -
7. Permis 552 298 84 - -
Jumlah/Total 2 914 2 674 536 - -
Sumber : Kecamatan Simpang Rimba Dalam Angka 2017

2.2.3 Kondisi Ekonomi


Tingkat perekonomian suatu masyarakat merupakan salah satu faktor yang menggambarkan tingkat
perkembangan suatu wilayah. Perdagangan menjadi salah satu penunjang perekonomian di
masyarakat. Salah satu pusat perekonomian bagi suatu daerah adalah koperasi. Koperasi
merupakan suatu lembaga keuangan yang berbasis kerakyatan. Untuk itu keberadaannya sangat
besar manfaatnya dalam menunjang perekonomian masyarakat khususnya kelas menengah
kebawah, demikian halnya dengan keberadaan lembaga keuangan lainnya baik yang dikelola oleh
pemerintah maupun oleh pihak swasta, namun sampai dengan tahun 2017 sarana koperasi hanya
ada 3 buah Koperasi Non KUD.
Tabel 2.19 Jumlah Koperasi di Kecamatan Simpang Rimba

Desa Koperasi KUD Jumlah


(1) (2) (3) (4)
1. Jelutung II - - -
2. Gudang - - -
3. Sebagin - - -
4. Rajik - - -
5. Simpang Rimba 1 - 1
6. Bangka Kota 1 - 1
7. Permis 1 - 1
Jumlah/Total 3 - 3
Sumber : Kecamatan Simpang Rimba Dalam Angka 2017
Tabel 2.20Jumlah Lembaga Keuangan di Kecamatan Simpang Rimba

Desa Koperasi KUD Jumlah


(1) (2) (3) (4)
1. Jelutung II - - -
2. Gudang - - -
3. Sebagin - - -
4. Rajik - - -
5. Simpang Rimba 1 - -
6. Bangka Kota - - -
7. Permis - - -
Jumlah/Total 1 - -
Sumber : Kecamatan Simpang Rimba Dalam Angka 2017

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-17


LAPORAN AKHIR

2.3 PERTEMUAN KONSULTASI MASYARAKAT


Pada tanggal 15 November 2018, bertempat di rumah GAPOKTAN telah berlangsung Pertemuan
Konsultasi Masyarakat (PKM) untuk pekerjaan DED Daerah Irigasi (DI) Gudang di Kecamatan
Simpang Rimba Kabupaten Bangka Selatan.
Peserta yang hadir dalam PKM ini berasal dari Dinas Pekerjaan Umum dan Penataan Ruang,
Perhubungan Kab. Bangka Selatan, konsultan PT. Dinar Rianda, Kepala Desa, Masyarakat, dan
Kelompok Tani setempat. Dalam kegiatan ini Konsultan PT. Dinar Rianda Konsultan sebagai
Pelaksana Kegiatan DED Daerah Irigasi (DI) Gudang, menyampaikan hasil analisa desain terkait
dengan pengembangan areal lahan sawah.
Hasil PKM telah diperoleh berbagai masukan baik yang berupa saran, informasi koreksi dan
tanggapan mengenai konsep matrik desain dasar program dan kegiatan serta usulan yang perlu
ditindaklanjuti dalam pekerjaan DED Daerah Irigasi (DI) Gudang di Kecamatan Simpang Rimba
Kabupaten Bangka Selatan.
Adapun butir-butir penting yang dihasilkan dalam PKM adalah sebagai berikut :
1 GAPOKTAN – Pak Muslimin
a. Berdasarkan pengamatan sumber air di desa Gudang cukup namun pengaturannya
yang belum tepat.
b. Sumber air yang digunakan tidak berasal dari satu tempat.
c. Bangian tengah sawah mengalami kenaikan elevasi cukup tinggi.
d. Setelah kenaikan elevasi (pada poin c) terdapat lahan dengan luas kurang lebih 25
Ha mengalami penurunan elevasi dan juga temasuk dalam elevasi paling rendah).
e. Terdapat 16 GAPOKTAN di desa Gudang dengan anggota minimal 25 orang.
2 Kepala Desa Gudang
a. Desain irigasi diprioritaskan seluas 120 Ha.
b. Penanaman dilakukan satu tahun sekali.
c. Jenis padi yang ditanam Ciliwung.
Berikut foto - foto dari kegiatan PKM yang berlangsung di rumah GAPOKTAN:

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-18


LAPORAN AKHIR

Gambar 2.9 Kegiatan PKM

Gambar 2.10 Kegiatan PKM

Gambar 2.11 Kegiatan PKM

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2-19


LAPORAN AKHIR

BAB 3 KETERSEDIAAN DATA

3.1 DEM LOKASI STUDI


Digital Elevation Model (DEM) adalah data digital yang menggambarkan geometri dari bentuk
permukaan bumi atau bagiannya yang terdiri dari himpunan titik-titik koordinat hasil sampling dari
permukaan dengan algoritma yang mendefinisikan permukaan tersebut menggunakan himpunan
koordinat (Tempfli, 1991). DEM merupakan suatu sistem, model, metode, dan alat dalam
mengumpulkan, prosessing, dan penyajian informasi medan. Susunan nilai-nilai digital yang
mewakili distribusi spasial dari karakteristik medan, distribusi spasial di wakili oleh nilai sistem
koordinat horisontal X Y dan karakteristik medan diwakili oleh ketinggian medan dalam sistem
koordinat Z (Frederic J. Doyle, 1991). DEM khususnya digunakan untuk menggambarkan relief
medan. Gambaran model relief rupabumi tiga dimensi (3 dimensi yang menyerupai keadaan
sebenarnya di dunia nyata (real world) divisualisaikan dengan bantuan teknologi komputer grafis
dan teknologi virtual reality (Mogal, 1993).
Untuk mendapatkan data DEM pada lokasi yang ditinjau didapat dari website
http://earthexplorer.usgs.gov/ yang di produksi oleh United State Geological Survey bekerja sama
dengan NASA. Pada USGS sendiri banyak terdapat data mengenai daerah yang akan ditinjau, seperti
tata guna lahan dan lain sebagainya. Namun permasalahannya tidak semua data tersebut
dipublikasikan. Untuk kebutuhan pembuatan daerah tangkapan hujan hanya diperlukan data DEM
dari SRTM atau Shuttle Radar Topography Mission. Gambar DEM dapat dilihat pada Gambar
dibawah ini.

Gambar 3.1 Peta DEM Wilayah DI Gudang

3.2 TATA GUNA LAHAN


Karakteristik tata guna lahan pada perencanaan ini didapat dari Direktorat Jenderal Planologi
Kehutanan Kementerian Kehutanan Republik Indonesia untuk Provinsi Kepulauan Bangka Belitung
tahun 2011 seperti pada gambar di berikut.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-1


LAPORAN AKHIR

Gambar 3.2 Tata Guna Lahan Bangka Belitung Tahun 2012

Sumber : Direktorat Jenderal Planologi Kehutanan - Kementerian Kehutanan Republik Indonesia

3.3 KONDISI HIDROKLIMATOLOGI


Data klimatologi sangat penting dalam analisis hidrologi, karena jumlah hujan yang terjadi pada
suatu daerah dipengaruhi oleh kondisi fisik dan klimatologi. Kondisi iklim daerah studi didasarkan
pada data hasil pencatatan di stasiun pengamatan klimatologi yaitu data dari stasiun Klimatologi
Pangkalpinang, begitupun unutk stasiun pencatatan hujan juga dari stasiun BMKG Pangkalpinang.
Kondisi iklim yang akan dibahas lebih lanjut dalam studi ini didasarkan pada data hasil pencatatan di
stasiun pengamatan yang terdekat di wilayah Kabupaten Bangka Selatan yang mewakili kondisi
hidrologi daerah pengaliran sungai (DAS) Gudang.
Data pengamatan curah hujan Stasiun BMKG Pangkalpinang berupa data hujan bulanan dan harian
maksimum. Periode pencatatan dimulai dari tahun 2004 sampai 2017. Selanjutnya, uraian tentang
keadaan dan karakteristik iklim dalam daerah studi ini secara rinci dapat dijelaskan pada bahasan
berikut.

3.3.1 Curah Hujan


Data curah hujan diambil dari stasiun penakar hujan terdekat di wilayah Kabupaten Bangka Selatan
yang mewakili kondisi hidrologi daerah pengaliran sungai (DAS) Gudang. Data hujan yang digunakan
adalah stasiun curah hujan BMKG Pangkalpinang. Berikut adalah lokasi dan ketersediaan data di
stasiun hujan tersebut.
Tabel 3.1 Ketersediaan Data Hujan

No Stasiun Pengukuran Hujan Lokasi Tahun


1 Pangkal Pinang S02 9' 46'' E106 8' 13'' 2004-2017
Sumber: BMKG Bangka

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-2


LAPORAN AKHIR

Berikut adalah rekapitulasi data hujan maksimum tahunan (R24) dan hujan bulanan untuk stasiun
hujan tersebut.
Tabel 3.2 Curah Hujan Maksimum Tahunan (R24) (mm)

R24 Max
No Tahun
(mm)
1 2004 54.7
2 2005 121.5
3 2006 75.7
4 2007 148.6
5 2008 107.1
6 2009 92.0
7 2010 124.7
8 2011 87.0
9 2012 108.4
10 2013 141.4
11 2014 94.6
12 2015 100.0
13 2016 184.0
14 2017 92.0

Tabel 3.3 Data Hujan 2-mingguan (mm)


R (mm) Rata-rata
Bulan Setengah
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Bulanan
Bulanan
Jan-1 137 228 137 122 245 148 155 72 131 56 253.5 113 69.7 152.9 144.3
131
Jan-2 49 0 26 354 127 102 126 181 55 147 0.6 16.5 196.4 258.5 117.1
Feb-1 68 43 77 13 52 19 79 156 268 271 0 45.8 397 149.2 117.0
115
Feb-2 129 30 143 156 79 30 209 154 198 34 59.4 55 210.9 89.9 112.7
Mar-1 108 23 87 56 162 137 191 98 92 177 7 356 178 101.2 126.7
130
Mar-2 129 189 109 135 45 234 280 130 167 84 73.6 47.7 140.3 106 133.5
Aprl-1 80 155 168 111 121 70 255 205 67 133 164.3 84 80.1 162.3 132.6
123
Apr-2 77 68 227 116 155 25 58 151 60 57 128.9 138.3 188.5 130 112.8
Mei-1 54 99 175 197 32 82 84 231 33 201 97 111 52.5 206.2 118.2
105
Mei-1 121 121 58 83 71 159 53 113 111 57 79.2 0.6 172.1 73.1 90.9
Jun-1 23 52 50 83 103 42 91 110 79 48 45 87.9 54 3.4 62.2
71
Jun-2 44 104 64 129 16 88 93 162 86 72 41.8 4 140 63.4 79.1
Jul-1 99 36 3 26 59 57 67 20 178 116 87.8 13.8 14.5 115.5 63.8
67
Jul-2 55 82 53 231 23 98 74 71 14 133 54.6 9 31.1 48.2 69.8
Ags-1 0 80 2 8 4 0 224 29 2 73 116.8 3 69 93 50.3
52
Ags-2 2 76 17 51 116 78 206 15 3 11 14.4 0 107 45.1 53.0
Sep-1 2 146 33 55 110 1 99 29 9 197 0.8 0 113 33.1 59.1
48
Sep-2 2 32 4 30 11 11 104 50 5 38 0 0 185.1 54.8 37.6
Okt-1 0 69 0 107 53 59 94 37 20 96 0 0 158.5 152.3 60.4
76
Okt-2 129 122 21 102 42 36 193 265 26 103 38.6 32 115.5 66.7 92.3
Nov-2 2 202 4 166 137 88 235 146 69 164 45.9 25.4 63.4 72 101.4
114
Nov-2 149 196 31 76 119 97 130 206 147 172 89.9 64.8 103.8 188.6 126.4
Des-1 168 166 117 166 95 62 215 86 110 148 162.4 50 65.5 143 125.3
151
Des-2 292 244 241 163 149 144 127 182 90 259 107.4 188 72.6 218 176.9
Total 1919 2563 1847 2736 2126 1867 3442 2899 2020 2847 1669 1446 2979 2726

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-3


LAPORAN AKHIR

R (mm)
Bulan
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Jan 186 228 163 476 372 250 281 253 186 203 254 130 266 411
Feb 197 73 220 169 131 49 288 310 466 305 59 101 608 239
Mar 237 212 196 191 207 371 471 228 259 261 81 404 318 207
Apr 157 223 395 227 276 95 313 356 127 190 293 222 269 292
May 175 220 233 280 103 241 137 344 144 258 176 112 225 279
Jun 67 156 114 212 119 130 184 272 165 120 87 92 194 67
Jul 154 118 56 257 82 155 141 91 192 249 142 23 46 164
Aug 2 156 19 59 120 78 430 44 5 84 131 3 176 138
Sep 4 178 37 85 121 12 203 79 14 235 1 0 298 88
Oct 129 191 21 209 95 95 287 302 46 199 39 32 274 219
Nov 151 398 35 242 256 185 365 352 216 336 136 90 167 261
Dec 460 410 358 329 244 206 342 268 200 407 270 238 138 361
Max 460 410 395 476 372 371 471 356 466 407 293 404 608 411
Jumlah 1 9 1 9 2563 1847 2736 2126 1867 3442 2899 2020 2847 1669 1446 2979 2726

700
Hujan Bulanan
600
TINGGI HUJAN (MM)

500

400

300

200

100

0
2007
2004

2005

2006

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017
TAHUN

Gambar 3.3 Hujan Bulanan Stasiun BMKG Pangkal Pinang

3.3.2 Klimatologi
Untuk data Klimatologi DAS Gudang diambil dari Stasiun Klimatologi Pangkalpinang untuk tahun
pengamatan tahun 2017.
Tabel 3.4 Parameter Klimatologi

Total
Temperatur Kelembaban Kecepatan
Penyinaran
Udara Udara Angin
Bulan Matahari
T Rh U S=n/N
oC % m/dt jam
Jan 26.1 89.5 1.8 57.0
Feb 26.3 87.0 2.3 73.0
Mar 26.8 86.0 2.0 135.0
Apr 27.0 86.0 1.6 105.0
May 27.8 83.0 2.6 149.0
Jun 27.5 82.0 2.6 150.0

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-4


LAPORAN AKHIR

Total
Temperatur Kelembaban Kecepatan
Penyinaran
Udara Udara Angin
Bulan Matahari
T Rh U S=n/N
oC % m/dt jam
Jul 27.0 84.0 2.9 190.0
Aug 27.6 79.0 3.7 175.0
Sep 27.7 79.0 3.0 162.0
Oct 27.5 83.0 1.7 144.0
Nov 26.7 86.0 1.9 111.0
Dec 26.1 88.0 1.8 74.0

3.3.3 Pengukuran Debit Sesaat


Pengukuran debit dapat dilakukan secara langsung dan secara tidak langsung. Pengukuran debit
secara langsung adalah pengukuran yang dilakukan dengan menggunakan peralatan berupa alat
pengukur arus (current meter). Debit hasil pengukuran dapat dihitung segera setelah pengukuran
selesai dilakukan. Pengukuran debit sesaat dilakukan untuk mendapatkan gambaran umum
mengenai debit rata-rata yang mengalir di daerah DAS. Berikut adalah hasil pengukuran debit sesaat
pada salah satu penampang sungai lokasi rencana bendung.
KETERANGAN
NO FOTO
LOKASI DEBIT WAKTU

v = 0.1 m/s 15/08/2018


Sungai A = 0.3 m2
1
kiri Pukul 11.30
Q = 30 li/s WIB

15/08/2018
v = 0.1 m/s
2 Bendung A = 1.5 m2
Pukul 11.58
WIB
Q = 150 li/s

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-5


LAPORAN AKHIR

KETERANGAN
NO FOTO
LOKASI DEBIT WAKTU

v = 0.3 m/s 15/08/2018


Saluran A = 0.09 m2
3
Primer Pukul 11.20
Q = 27 li/s WIB

3.4 SURVEY LAPANGAN AWAL


Survey lapangan awal merupakan kegiatan awal terhadap permasalahan yang terjadi di Daerah
Irigasi (DI) Gudang. Selain secara visual kondisi DI Gudang, survey juga dengan melakukan
wawancara dengan penduduk di sekitar DI Gudang serta pengamatan kondisi DI itu sendiri. Kondisi
eksisting tapak dapat dilihat pada gambar berikut.

10
00

8
3
7
2
6
9

4 dan 5
1
dan

Gambar 3.4 Layout Daerah Irigasi Gudang

Berikut foto-foto kondisi eksisting DI Gudang

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-6


LAPORAN AKHIR

Tabel 3.5 Kondisi Eksisting DI Gudang

NO
FOTO KETERANGAN
GAMBAR

1 Bendung
Waktu : 15/11/2018
Gambar
menunjukkan
bendung sungai
utama (Sungai
Babuar).

Gambar
menunjukkan
kegiatan pengukuran
debit sesaat di
bendung.

2 Boks Bagi
Waktu : 15/11/2018

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-7


LAPORAN AKHIR

NO
FOTO KETERANGAN
GAMBAR

3 Gorong – Gorong /
Rencana Bendung
Waktu : 15/11/2018
Gambar disamping
menunjukkan
sumber air sungai
dari kiri gorong -
gorong.

Gambar
menunjukkan air
yang mengalir ke
bagian kanan gorong
– gorong.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-8


LAPORAN AKHIR

NO
FOTO KETERANGAN
GAMBAR

4 Saluran Primer
Waktu : 15/11/2018
Gambar
menunjukkan
kegiatan
pengukuran debit
sesaat pada saluran
primer.

5 Saluran Primer dan


Bangunan Sadap
Waktu : 15/11/2018

Pembangunan
saluran primer
terhenti pada lokasi
ini.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-9


LAPORAN AKHIR

NO
FOTO KETERANGAN
GAMBAR

6 Bangunan Sadap
Waktu : 15/11/2018

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-10


LAPORAN AKHIR

NO
FOTO KETERANGAN
GAMBAR

7 Jembatan Suplesi
Waktu : 15/11/2018

8 Jembatan / Gorong -
Gorong
Waktu : 15/11/2018

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-11


LAPORAN AKHIR

NO
FOTO KETERANGAN
GAMBAR

9 Bangunan Sadap
Waktu : 15/11/2018

10 Batas Sawah / Areal


Semak Belukar
Waktu : 15/11/2018

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3-12


LAPORAN AKHIR

BAB 4 PEMETAAN TOPOGRAFI

4.1 UMUM
Pemetaan Topografi sebagai bagian kegiatan dari pelaksanaan Pekerjaan “Penyusunan DED Daerah
Irigasi Gudang”, dilakukan untuk memperoleh data dasar yang sangat diperlukan dalam
Perencanaan Jaringan Irigasi. Pekerjaan topografi secara umum terdiri dari kegiatan lapangan,
perhitungan dan penggambaran, dilaksanakan sesuai dengan Spesifikasi Teknis yang diberikan
dalam Kerangka Acuan Kerja (KAK/TOR), dan mengikuti ketentuan yang tercantum dalam Buku
“Standar Perencanaan Irigasi” bagian Persyaratan Teknis Pengukuran Topografi (PT-02), yang
dikeluarkan oleh Direktorat Jenderal Pengairan Departemen Pekerjaan Umum, tahun 1986.
Survey pendahuluan pada survey topografi meliputi pekerjaan survey lokasi untuk mengamati lahan
sebelum melaksanakannya survey pengukuran. Pekerjaan ini perlu dilaksanakan untuk menyiapkan
perencanaan dan system kerja yang akan dipergunakan supaya pekerjaan dapat dilaksanakan
dengan efektif dan tepat.
Hasil pekerjaan pengukuran berupa data, peta dan besaran lain yang diperlukan, sebagaimana
diuraikan berikut ini.

4.2 KONDISI TOPOGRAFI


4.2.1 Kemiringan dan Ketinggian Lahan
Keadaan topografi rencana D.I. Gudang termasuk daerah datar, dengan kemiringan lahan antara 0 -
3 % dari arah barat ke timur.
Ketinggian lahan berdasarkan hasil pengukuran dengan referensi elevasi (Z) yang digunakan, berada
diantara + 17 meter sampai dengan + 33 meter (di atas permukaan laut).

4.2.2 Luas dan Batas-batas Areal


D.I. Gudang memiliki luas ±198 Ha yang tersebar ke dalam beberapa lokasi hamparan sawah.
Hamparan terluas adalah 115 Ha dan 60 Ha, sisanya tersebar dalam petak-petak sawah kecil.
Kegiatan pengukuran dilakukan pada kedua lokasi dengan hamparan terluas. Adapun batas wilayah
DI Gudang berada di sebelah kanan aliran Sungai Babuar melingkari areal di sebelah utara dan
sebelah timur, batas-batas areal, yaitu :
• Sebelah Utara : Lahan Sawit
• Sebelah Selatan : Saluran dan tanggul keliling
• Sebelah Timur : Sungai Babuar
• Sebelah Barat : Sungai Babuar

4.2.3 Vegetasi dan Penggunaan Lahan


Dengan adanya Pencetakan Sawah oleh Dinas Pertanian dan Peternakan Kabupaten Bangka Selatan
pada tahun anggaran 2013, maka lahan sudah terbuka, tidak terdapat pohon-pohon besar, namun

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 4-1


LAPORAN AKHIR

karena budidaya penanaman padi sawah hanya dilakukan pada tahun 2014 dan selanjutnya sampai
saat ini tidak dilakukan penanaman maka hampir seluruh lahan pada saat ini tertutup kembali oleh
vegetasi semak belukar.

4.3 REFERENSI PENGUKURAN


Referensi koordinat planimetris adalah sistem koordinat yang digunakan sebagai dasar dalam
penetapan posisi sumbu koordinat (x,y,z) . Dikarenakan sebaran referensi koordinat dilokasi tidak
ada maka sebagai acuan koordinat dilakukan pengamatan/pengukuran GPS sebagai titik referesi
koordinatnya. Dalam pelaksanaanya dilakukan pemasangan BM sebanyak 3 buah dan CP sebanyak
3 buah.
Tabel 4.1 Koordinat BM dan CP

POINT X Y Z (m)
BM 01 611422.79 9714009.16 35.42
BM 02 613422.705 9714999.984 25.174
BM 03 613702.373 9717554.794 18.314
CP 01 611410.874 9713996.195 35.1
CP 02 613410.539 9714989.44 24.842
CP 03 613703.375 9717544.317 18.135

4.4 PATOK PENGUKURAN


Pada pengukuran topografi D.I. Gudang ini, dilakukan kegiatan pemasangan dan pengukuran
patok/titik tetap pengukuran, berupa patok Bench Mark (BM) dan Control Point (CP) yang diperlukan
sebagai referensi untuk pelaksanaan pengukuran pada studi selanjutnya, dan untuk pelaksanaan
fisik di lapangan nantinya.
Penentuan koordinat bidang datar sumbu (X, Y) pada pengukuran titik tetap ini dikontrol dengan
menggunakan alat bantu Global Positioning System (GPS) dan penentuan levelling (Z) digunakan
data elevasi lokal, sebagai referensi ketinggian/elevasi (Z).

4.5 PETA DAN GAMBAR PENGUKURAN


Peta dan gambar-gambar hasil pengukuran/pemetaan topografi yang telah dibuat
diperlukan/digunakan sebagai data dasar untuk Pembuatan Sistem Planning dan Perencanaan Detail
(Detail Design) Jaringan Irigasi, terdiri dari :
1. Peta Situasi Daerah Irigasi, skala 1 : 2.000.
2. Peta Ikhtisar Situasi Daerah Rawa, skala 1 : 10.000.
3. Peta Situasi Trase skala 1 : 2.000, Potongan Memanjang skala (V) 1 : 2.000 (H) 1 : 100 dan
Potongan Melintang skala 1 : 100, saluran dan tanggul eksisting
4. Peta Situasi Trase skala 1 : 2.000, Potongan Memanjang skala (V) 1 : 2.000 (H) 1 : 100 dan
Potongan Melintang skala 1 : 100 rencana saluran.
Metode Penggambaran Peta situasi :

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 4-2


LAPORAN AKHIR

Setelah mendapatkan data dari Total Station dengan cara di download dari alat tersebut kemuadian
diolah untuk mendapatkan hasil hitungan. Setelah itu baru diplotkan titik situasi dan poligon
kedalam software Autocad Land Development 2009 dengan ketentuan sesuai dengan petunjuk
direksi dimana skala peta menyesuaikan.
Tabel 4.2 Dokumentasi Survey Topografi DI Gudang

No. Foto Keterangan

1. Pekerjaan
pengukuran
dengan
theodolite
digital

2 Pekerjaan
pengukuran
dengan
theodolite
digital

3 Pekerjaan
pengukuran
dengan
theodolite
digital

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 4-3


LAPORAN AKHIR

No. Foto Keterangan

4 Pekerjaan
pengukuran
dengan
theodolite
digital

5 BM

6 CP

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 4-4


LAPORAN AKHIR

Gambar 4.1 Peta Topografi Daerah Irigasi Gudang

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 4-5


LAPORAN AKHIR

BAB 5 HASIL ANALISIS

5.1 DAERAH ALIRAN SUNGAI (DAS) DI GUDANG


Daerah Aliran Sungai (DAS) merupakan wilayah yang dikelilingi dan dibatasi oleh topografi alami
berupa punggung bukit atau pegunungan, dimana presipitasi yang jatuh di atasnya mengalir melalui
titik keluar tertentu (outlet) yang akhirnya bermuara ke danau atau laut. Batas-batas alami DAS
dapat dijadikan sebagai batas ekosistem alam, yang dimungkinkan bertumpang tindih dengan
ekosistem buatan, seperti wilayah administratif dan wilayah ekonomi. Namun sering kali batas DAS
melintasi batas kabupaten, propinsi, bahkan lintas negara. Suatu DAS kemudian dibagi-bagi lagi
menjadi sub-sub DAS.
Secara umum sub-DAS Gudang berada pada satu DAS Bangka Kota yang mengalir Sungai Babuar
didalamnya dan termasuk ke dalam WS Bangka. DAS Gudang memiliki luas 6.16 km2 dengan panjang
sungai ±2.84. Tutupan lahan pada DAS Gudang mempunyai karakteristik mayoritas berupa semak
belukar. Berikut tata guna lahan pada DAS Gudang.

DAS D.I. GUDANG

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-1


LAPORAN AKHIR

DAS D.I. GUDANG

Gambar 5.1 Wilayah Sungai (WS) Bangka

Gambar 5.2 DAS Gudang pada Peta Rupa Bumi


Tabel 5.1 Presentasi Tutupan Lahan DAS Gudang

Tata Guna Lahan Area (Km2) % C


Semak/Belukar 4.33 70.3% 0.5
Hutan Lahan Kering Sekunder 1.40 22.7% 0.25
Pemukiman 0.43 7.0% 0.8
6.16 100% 0.46

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-2


LAPORAN AKHIR

Keterangan:
Semak/Belukar
Hutan Lahan Kering Sekunder
Pemukiman
Gambar 5.3 Tata Guna Lahan DAS Gudang

5.2 ANALISIS KETERSEDIAAN


Analisis debit andal diperoleh dari data hujan harian selama periode pengamatan tertentu yang
diolah agar menjadi debit sintetis. Berikut adalah ketersediaan air berdasarkan DAS Gudang yang
telah dianalisis.

5.2.1 Hujan Efektif


Tabel 5.2 Analisis Hujan Efektif Bulanan

Rank Prob Jan Peb Mar Apr Mei Jun Jul Aug Sep Okt Nov Des
1 7.14 476 608 471 395 344 272 257 430 298 302 398 460
2 14.29 411 466 403.7 356 280 212 249 176 235 287 365 410
3 21.43 372 310 371 313 279 194 192 156 203 274 352 407
4 28.57 281 305 318.3 293 258 184 164 138 178 219 336 361
5 35.71 266 288 261 292 241 165 155 131 121 209 261 358
6 42.86 254 239 259 276 233 156 154 120 88 199 256 342
7 50.00 253 220 237 269 225 130 142 84 85 191 242 329
8 57.14 250 197 228 227 220 120 141 78 79 129 216 270
9 64.29 228 169 212 223 176 119 118 59 37 95 185 268
10 71.43 203 131 207.2 222 175 114 91 44 14 95 167 244
11 78.57 186 101 207 190 144 92 82 19 12 46 151 238
12 85.71 186 73 196 157 137 87 56 5 4 39 136 206
13 92.86 163 59 191 127 112 67 46 3 1 32 90 200
14 100.00 130 49 80.6 95 103 67 23 2 0 21 35 138
R 80 % 186.00 95.24 204.80 183.40 142.60 90.88 76.80 16.20 10.40 44.52 147.96 231.60
Re 4.20 2.38 4.62 4.28 3.22 2.12 1.73 0.37 0.24 1.01 3.45 5.23

5.2.2 Evapotranspirasi
Nilai evaporasi dihitung menggunakan data iklim dari Stasiun Klimatologi Pangkalpinang tahun 2017
dengan Metode Modifikasi Penman menggunakan software CROPWAT. Berikut nilai evaporasi
dengan Metode Penman.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-3


LAPORAN AKHIR

Gambar 5.4 Evapotranspirasi Bulanan Hasil Software Cropwat

5.2.3 Debit Andal DAS Gudang


Ada dua metode perhitungan debit andalan untuk DAS Gudang, yaitu menggunakan Model NRECA
dan model Sacramento series 15-harian. Pemodelan debit 15-harian DAS Gudang dilakukan dengan
ketentuan sebagai berikut:
1. Data curah hujan yang dipakai adalah data curah hujan bulanan STA BMKG Pangkalpinang
untuk 14 tahun periode 2004-2017. Karena hanya menggunakan data dari satu stasiun
hujan saja, maka tidak diperlukan pembobotan curah hujan rata-rata untuk DAS Gudang.
2. Parameter DAS yang digunakan adalah parameter NRECA dan Sacramento 15-harian yang
ditunjukkan pada Tabel 5.3, yaitu untuk daerah dengan curah hujan sedang sampai tinggi.
Tabel 5.3 Parameter DAS

NRECA Sacramento
Luas Daerah Aliran 6.73 UZTWM 116.29
Hujan Rata-rata Tahunan 2363 UZFWM 150
Koefisien C 0.20 LZTWM 100.596
Nominal 572.65 LZFSM 233.617
PSUB 0.90 LZFPM 80.606
GWF 0.20 UZK 0.336
Storage 1260.00 LZSK 0.0811
IGWS 760.00 LZPK 0.024
Faktor Hujan 1.00 ZPERC 1.366
REXP 1
PFREE 0.075
RSERV 0.3
PCTIM 0.1
SIDE 0
SARVA 0.003872893
SSOUT 0
Debit andal 15-harian yang dihasilkan dari analisis sintetis untuk DAS Gudang seperti pada gambar
berikut.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-4


LAPORAN AKHIR

Gambar 5.5 Grafik Debit Sintetis Gudang

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-5


LAPORAN AKHIR

Dari data debit rata-rata 15-harian menghasilkan kurva FDC dengan menggunakan metode NRECA
dan Sacramento yang ditunjukan pada gambar berikut.

Gambar 5.6 Grafik Kurva Durasi (Flow Duration Curve) Gudang


Tabel 5.4 Probabilitas Kurva Durasi (Flow Duration Curve) Gudang

Debit Andalan (m3/s) NRECA


Q
NRECA Sacramento Koreksi 80%
5% 0.521 0.861 0.417
10% 0.471 0.551 0.377
20% 0.392 0.368 0.314
30% 0.320 0.313 0.256
40% 0.285 0.268 0.228
50% 0.238 0.230 0.190
60% 0.201 0.196 0.161
70% 0.166 0.155 0.133
80% 0.129 0.124 0.103
90% 0.083 0.084 0.066
100% 0.020 0.033 0.016

Karena data hujan yang digunakan merupakan data hujan dari alat ukur otomatik dengan durasi
yang cukup panjang (> 10 tahun) lebih valid daripada alat ukur manual. Maka data dari BMKG
Pangkal Pinang dipilih walaupun jaraknya cukup jauh dari kecamatan Simpang Rimba (> 120 km).
Oleh karena itu nilai debit perlu dikoreksi sebesar 80%. Pengoreksian dilakukan untuk
mengantisipasi terjadinya penurunan debit andalan dari waktu ke waktu yang menyebabkan kinerja
irigasi berkurang.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-6


LAPORAN AKHIR

Dengan melihat hasil iterasi untuk parameter setiap metode, dapat disimpulkan bahwa hasil dari
kedua metode ternyata memiliki nilai debit sintestik yang mirip satu dengan yang lain. Karena
merupakan metode yang lebih umum digunakan, maka dipilihlah metode NRECA sebagai dasar
pengambilan nilai debit sintetis. Berdasarkan debit kebutuhan air untuk irigasi diambil nilai debit
80% pada kurva FDC NRECA, yakni sebesar 0.129 m3/s. Dengan nilai debit yang sudah dikoreksi 80%,
yakni sebesar 0.103 m3/s.

5.3 ANALISIS KEBUTUHAN AIR


5.3.1 Kebutuhan Air
Kebutuhan air merupakan besarnya debit yang dibutuhkan oleh suatu lahan untuk mengairi jenis
tanaman yang sedang ditanam dalam satuan waktu tertentu. Besarnya nilai kebutuhan air
tergantung dari nilai evaporasi dan kualitas tanaman baik padi maupun palawija. Terdapat tiga
alternatif perhitungan yang terdiri dari alternatif 1, alternatif 2, dan alternatif 3, di mana perbedaan
antara ketiga alternatif tersebut ada pada lamanya pengolahan tanam dan/atau jenis padi.

Tiga Alternatif Perhitungan :


Alt 1 : Padi Unggul-Padi Unggul-Palawija, Pengolahan Lahan 30 Hari
Alt 2 : Padi Unggul-Padi Unggul-Palawija, Pengolahan Lahan 45 Hari
Alt 3 : Padi Biasa-Padi Unggul-Palawija, Pengolahan Lahan 30 Hari
Total Genangan Rendeng 300 mm
Total Genangan Gadu 250 mm
Perkolasi 2 mm/hari
Penggantian Lapisan Air 50 mm/15 hari
Efisiensi Total Saluran 65 %
Tanaman Palawija Kedelai (Kedelai, Jagung, Bawang, Buncis)
Koefisien Tanaman FAO (Prosida/FAO)

5.3.1.1 Pergantian lapisan air (WLR)


Penggantian air dilakukan dua kali, masing 50 mm (3,3 mm/hari selama 1/2 bulan) selama sebulan
dan dua bulan setelah transplantasi. Dengan model perhitungan penggantian lapis air ditunjukkan
pada tabel di bawah ini.

Penggantian Lapisan Air Untuk Pengolahan lahan 30 Hari

Nop Des Jan Feb Mrt Apr Mei Jun Jul Agt Sep Ok
1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2
WLR 1 3.3 3.3 3.3 3.3
WLR 2 3.3 3.3 3.3 3.3
WLR 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7

Penggantian Lapisan Air Untuk Pengolahan lahan 45 Hari

Nop Des Jan Feb Mrt Apr Mei Jun Jul Agt Sep Ok
1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2
WLR 1 3.3 3.3 3.3 3.3
WLR 2 3.3 3.3 3.3 3.3
WLR 3 3.3 3.3 3.3 3.3
WLR 1.1 1.1 2.2 1.1 1.1 1.1 1.1 2.2 1.1 1.1

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-7


LAPORAN AKHIR

5.3.1.2 Koefisien tanaman (Kc)

Untuk nilai koefisien tanaman (Kc) mengacu pada metodologi yang ada di Lampiran A.
5.3.1.3 Perhitungan Kebutuhan Air Irigasi Berbagai Alternatif
Berikut pemodelan kebutuhan air irigasi yang digunakan :
A. Skenario 1 : 3 pola tanam (padi-padi-palawija)

 Alternatif 1 : Padi Unggul-Padi Unggul-Palawija, Pengolahan Lahan 30 Hari


 Alternatif 2 : Padi Unggul-Padi Unggul-Palawija, Pengolahan Lahan 45 Hari

 Alternatif 3 : Padi Biasa-Padi Unggul-Palawija, Pengolahan Lahan 30 Hari


B. Skenario 2 : 2 pola tanam (padi-padi)

 Alternatif 1 : Padi Unggul-Padi Unggul-Palawija, Pengolahan Lahan 30 Hari

 Alternatif 2 : Padi Unggul-Padi Unggul-Palawija, Pengolahan Lahan 45 Hari


 Alternatif 3 : Padi Biasa-Padi Unggul-Palawija, Pengolahan Lahan 30 Hari
Tabel berikut menunjukan resume hasil analisis kebutuhan air secara lengkap.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-8


LAPORAN AKHIR

A. Skenario 1 (3 Pola Tanam)


Tabel 5.5 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 1, Mulai Okt-2
Kelompok 1, Mulai Tanam Pertengahan Oktober, Pengolahan Lahan 30 hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 13.1 1.10 LP LP 13.1 9.6 1.71
Nop 2 3.3 2.0 3.5 3.5 5.61 1.10 1.10 1.10 3.61 2.2 0.38
Des 1 2.8 2.0 5.2 5.2 5.08 1.7 1.05 1.10 1.08 3.0 1.4 0.26
Des 2 2.8 2.0 5.2 5.2 5.08 1.7 1.05 1.05 1.05 2.9 1.4 0.25
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 0.95 1.05 1.00 2.6 2.1 0.37
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 0.00 0.95 0.48 1.2 0.7 0.13
Feb 1 3.0 2.0 2.4 2.4 5.31 0.00 0.00 0.0 0.0 0.00
Feb 2 3.0 2.0 2.4 2.4 5.31 0.0 0.0 0.00
Mar 1 3.5 2.0 4.6 4.6 5.86 11.6 LP LP LP 11.6 7.0 1.24
Mar 2 3.5 2.0 4.6 4.6 5.86 11.6 1.10 LP LP 11.6 7.0 1.24
Apr 1 3.1 2.0 4.3 4.3 5.45 1.10 1.10 1.10 3.45 1.2 0.21
Apr 2 3.1 2.0 4.3 4.3 5.45 1.7 1.05 1.10 1.08 3.4 2.8 0.49
Mei 1 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.05 1.05 3.7 4.2 0.75
Mei 2 3.6 2.0 3.2 3.2 5.92 1.7 0.95 1.05 1.00 3.6 4.0 0.71
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 0.00 0.95 0.48 1.7 3.2 0.57
Jun 2 3.5 2.0 2.1 2.1 5.87 0.50 0.00 0.25 0.4 1.1 0.3 0.0 0.06
Jul 1 3.7 2.0 1.7 1.7 6.02 0.75 0.50 0.63 2.3 0.5 0.10
Jul 2 3.7 2.0 1.7 1.7 6.02 1.00 0.75 0.88 3.2 1.5 0.26
Agt 1 4.2 2.0 0.4 0.4 6.62 1.00 1.00 1.00 4.2 3.8 0.68
Agt 2 4.2 2.0 0.4 0.4 6.62 0.82 1.00 0.91 3.8 3.5 0.62
Sep 1 4.2 2.0 0.2 0.2 6.65 0.45 0.82 0.64 2.7 2.4 0.44
Sep 2 4.2 2.0 0.2 0.2 6.65 0.45 0.23 1.0 0.7 0.13
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.01 6.08 13.3 LP LP LP 13.3 12.3 2.20

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-9


LAPORAN AKHIR

Tabel 5.6 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 2, Mulai Okt-2
Kelompok 1, Mulai Tanam Pertengahan Oktober, Pengolahan Lahan 45 Hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C3 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11 12 a 12 b 13 a 13 b 14
Nop 1 3.3 2.0 3.5 3.5 5.61 9.9 1.10 LP LP LP 9.9 6.4 1.14
Nop 2 3.3 2.0 3.5 3.5 5.61 9.9 1.10 1.10 LP LP 9.9 6.4 1.14
Des 1 2.8 2.0 5.2 5.2 5.08 1.1 1.05 1.10 1.10 1.08 3.0 0.9 0.16
Des 2 2.8 2.0 5.2 5.2 5.08 1.1 1.05 1.05 1.10 1.07 3.0 0.9 0.15
Jan 1 2.6 2.0 4.2 4.2 4.87 2.2 0.95 1.05 1.05 1.02 2.7 2.7 0.48
Jan 2 2.6 2.0 4.2 4.2 4.87 1.1 0.00 0.95 1.05 0.67 1.7 0.7 0.12
Feb 1 3.0 2.0 2.4 2.4 5.31 1.1 0.00 0.95 0.32 1.0 1.7 0.30
Feb 2 3.0 2.0 2.4 2.4 5.31 0.00 0.00 0.0 0.0 0.00
Mar 1 3.5 2.0 4.6 4.6 5.86 9.0 LP LP LP LP 9.0 4.4 0.78
Mar 2 3.5 2.0 4.6 4.6 5.86 9.0 1.10 LP LP LP 9.0 4.4 0.78
Apr 1 3.1 2.0 4.3 4.3 5.45 8.7 1.10 1.10 LP LP 8.7 4.4 0.79
Apr 2 3.1 2.0 4.3 4.3 5.45 1.1 1.05 1.10 1.10 1.08 3.4 2.2 0.40
Mei 1 3.6 2.0 3.2 3.2 5.92 1.1 1.05 1.05 1.10 1.07 3.8 3.7 0.66
Mei 2 3.6 2.0 3.2 3.2 5.92 2.2 0.95 1.05 1.05 1.02 3.6 4.6 0.82
Jun 1 3.5 2.0 2.1 2.1 5.87 1.1 0.00 0.95 1.05 0.67 2.3 3.3 0.59
Jun 2 3.5 2.0 2.1 2.1 5.87 1.1 0.50 0.00 0.95 0.48 1.1 0.5 2.1 0.0 0.38
Jul 1 3.7 2.0 1.7 1.7 6.02 0.75 0.50 0.00 0.42 1.5 0.0 0.00
Jul 2 3.7 2.0 1.7 1.7 6.02 1.00 0.75 0.50 0.75 2.7 1.0 0.18
Agt 1 4.2 2.0 0.4 0.4 6.62 1.00 1.00 0.75 0.92 3.9 3.5 0.62
Agt 2 4.2 2.0 0.4 0.4 6.62 0.82 1.00 1.00 0.94 3.9 3.6 0.64
Sep 1 4.2 2.0 0.2 0.2 6.65 0.45 0.82 1.00 0.76 3.2 3.0 0.53
Sep 2 4.2 2.0 0.2 0.2 6.65 0.45 0.82 0.42 1.8 1.5 0.28
Okt 1 3.7 2.0 1.0 1.0 6.08 0.45 0.15 0.6 0.0 0.00
Okt 2 3.7 2.0 1.0 1.01 6.08 12.0 LP LP LP LP 12.0 10.9 1.95

Catatan : - Pengolahan lahan (Land preparation) : 45 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-10


LAPORAN AKHIR

Tabel 5.7 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 3, Mulai Okt-2
Kelompok 1, Mulai Tanam Pertengahan Oktober, Pengolahan Lahan 30 hari, Varietas Biasa, Varietas Unggul, Palawija
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 13.1 1.10 LP LP 13.1 9.6 1.71
Nop 2 3.3 2.0 3.5 3.5 5.61 1.10 1.10 1.10 3.61 2.2 0.38
Des 1 2.8 2.0 5.2 5.2 5.08 1.7 1.10 1.10 1.10 3.1 1.5 0.27
Des 2 2.8 2.0 5.2 5.2 5.08 1.7 1.10 1.10 1.10 3.1 1.5 0.27
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.05 1.10 1.08 2.8 2.3 0.40
Feb 1 3.0 2.0 2.4 2.4 5.31 0.95 1.05 1.00 3.0 2.6 0.47
Feb 2 3.0 2.0 2.4 2.4 5.31 0.00 0.95 0.48 1.4 1.0 0.19
Mar 1 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 11.6 LP LP LP 11.6 7.0 1.24
Apr 1 3.1 2.0 4.3 4.3 5.45 11.4 1.10 LP LP 11.4 7.1 1.26
Apr 2 3.1 2.0 4.3 4.3 5.45 1.10 1.10 1.10 3.5 1.2 0.21
Mei 1 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.10 1.08 3.8 4.3 0.76
Mei 2 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.05 1.05 3.7 4.2 0.75
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 0.95 1.05 1.00 3.5 5.1 0.90
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 0.00 0.95 0.48 1.7 3.2 0.57
Jul 1 3.7 2.0 1.7 1.7 6.02 0.50 0.00 0.25 0.5 0.5 0.7 0.0 0.13
Jul 2 3.7 2.0 1.7 1.7 6.02 0.75 0.50 0.63 2.3 0.5 0.10
Agt 1 4.2 2.0 0.4 0.4 6.62 1.00 0.75 0.88 3.7 3.3 0.59
Agt 2 4.2 2.0 0.4 0.4 6.62 1.00 1.00 1.00 4.2 3.8 0.68
Sep 1 4.2 2.0 0.2 0.2 6.65 0.82 1.00 0.91 3.8 3.6 0.64
Sep 2 4.2 2.0 0.2 0.2 6.65 0.45 0.82 0.64 2.7 2.4 0.44
Okt 1 3.7 2.0 1.0 1.0 6.08 0.45 0.23 0.8 0.0 0.00
Okt 2 3.7 2.0 1.0 1.01 6.08 13.3 LP LP LP 13.3 12.3 2.20

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-11


LAPORAN AKHIR

Tabel 5.8 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 1, Mulai Nov-1
Kelompok 2, Mulai Tanam Awal Nopember, Pengolahan Lahan 30 Hari, Variets Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 13.1 LP LP LP 13.1 9.6 1.71
Nop 2 3.3 2.0 3.5 3.5 5.61 13.1 1.10 LP LP 13.1 9.6 1.71
Des 1 2.8 2.0 5.2 5.2 5.08 1.10 1.10 1.10 3.08 0.0 0.00
Des 2 2.8 2.0 5.2 5.2 5.08 1.7 1.05 1.10 1.08 3.0 1.4 0.26
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 1.05 1.05 1.05 2.7 2.2 0.39
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 0.95 1.05 1.00 2.6 2.1 0.37
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 0.00 0.95 0.48 1.4 2.7 0.48
Feb 2 3.0 2.0 2.4 2.4 5.31 0.00 0.00 0.0 0.0 0.00
Mar 1 3.5 2.0 4.6 4.6 5.86 0.0 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 11.6 LP LP LP 11.6 7.0 1.24
Apr 1 3.1 2.0 4.3 4.3 5.45 11.4 1.10 LP LP 11.4 7.1 1.26
Apr 2 3.1 2.0 4.3 4.3 5.45 1.10 1.10 1.10 3.45 1.2 0.21
Mei 1 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.10 1.08 3.8 4.3 0.76
Mei 2 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.05 1.05 3.7 4.2 0.75
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 0.95 1.05 1.00 3.5 5.1 0.90
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 0.00 0.95 0.48 1.7 3.2 0.57
Jul 1 3.7 2.0 1.7 1.7 6.02 0.50 0.00 0.25 0.5 0.5 0.7 0.0 0.13
Jul 2 3.7 2.0 1.7 1.7 6.02 0.75 0.50 0.63 2.3 0.5 0.10
Agt 1 4.2 2.0 0.4 0.4 6.62 1.00 0.75 0.88 3.7 3.3 0.59
Agt 2 4.2 2.0 0.4 0.4 6.62 1.00 1.00 1.00 4.2 3.8 0.68
Sep 1 4.2 2.0 0.2 0.2 6.65 0.82 1.00 0.91 3.8 3.6 0.64
Sep 2 4.2 2.0 0.2 0.2 6.65 0.45 0.82 0.64 2.7 2.4 0.44
Okt 1 3.7 2.0 1.0 1.0 6.08 0.45 0.23 0.8 0.0 0.00
Okt 2 3.7 2.0 1.0 1.01 6.08 0.00 0.0 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-12


LAPORAN AKHIR

Tabel 5.9 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 2, Mulai Nov-1
Kelompok 2, Mulai Tanam Awal Nopember, Pengolahan Lahan 45 Hari, Variets Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C3 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11 12 a 12 b 13 a 13 b 14
Nop 1 3.3 2.0 3.5 3.5 5.61 9.9 LP LP LP LP 9.9 6.4 1.14
Nop 2 3.3 2.0 3.5 3.5 5.61 9.9 1.10 LP LP LP 9.9 6.4 1.14
Des 1 2.8 2.0 5.2 5.2 5.08 9.5 1.10 1.10 LP LP 9.5 4.3 0.77
Des 2 2.8 2.0 5.2 5.2 5.08 1.1 1.05 1.10 1.10 1.08 3.0 0.9 0.16
Jan 1 2.6 2.0 4.2 4.2 4.87 1.1 1.05 1.05 1.10 1.07 2.8 1.7 0.30
Jan 2 2.6 2.0 4.2 4.2 4.87 2.2 0.95 1.05 1.05 1.02 2.7 2.7 0.48
Feb 1 3.0 2.0 2.4 2.4 5.31 1.1 0.00 0.95 1.05 0.67 2.0 2.7 0.49
Feb 2 3.0 2.0 2.4 2.4 5.31 1.1 0.00 0.95 0.32 1.0 1.7 0.30
Mar 1 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 9.0 LP LP LP LP 9.0 4.4 0.78
Apr 1 3.1 2.0 4.3 4.3 5.45 8.7 1.10 LP LP LP 8.7 4.4 0.79
Apr 2 3.1 2.0 4.3 4.3 5.45 8.7 1.10 1.10 LP LP 8.7 4.4 0.79
Mei 1 3.6 2.0 3.2 3.2 5.92 1.1 1.05 1.10 1.10 1.08 3.9 3.7 0.67
Mei 2 3.6 2.0 3.2 3.2 5.92 1.1 1.05 1.05 1.10 1.07 3.8 3.7 0.66
Jun 1 3.5 2.0 2.1 2.1 5.87 2.2 0.95 1.05 1.05 1.02 3.6 5.7 1.01
Jun 2 3.5 2.0 2.1 2.1 5.87 1.1 0.00 0.95 1.05 0.67 2.3 3.3 0.59
Jul 1 3.7 2.0 1.7 1.7 6.02 1.1 0.50 0.00 0.95 0.48 1.2 0.6 2.6 0.0 0.45
Jul 2 3.7 2.0 1.7 1.7 6.02 0.75 0.50 0.00 0.42 1.5 0.0 0.00
Agt 1 4.2 2.0 0.4 0.4 6.62 1.00 0.75 0.50 0.75 3.2 2.8 0.50
Agt 2 4.2 2.0 0.4 0.4 6.62 1.00 1.00 0.75 0.92 3.9 3.5 0.62
Sep 1 4.2 2.0 0.2 0.2 6.65 0.82 1.00 1.00 0.94 4.0 3.7 0.66
Sep 2 4.2 2.0 0.2 0.2 6.65 0.45 0.82 1.00 0.76 3.2 3.0 0.53
Okt 1 3.7 2.0 1.0 1.0 6.08 0.45 0.82 0.42 1.6 0.6 0.10
Okt 2 3.7 2.0 1.0 1.01 6.08 0.45 0.15 0.6 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 45 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-13


LAPORAN AKHIR

Tabel 5.10 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 3, Mulai Nov-1
Kelompok 2, Mulai Tanam Awal Nopember, Pengolahan Lahan 30 Hari, Variets Biasa, Varietas Unggul, Palawija
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 13.1 LP LP LP 13.1 9.6 1.71
Nop 2 3.3 2.0 3.5 3.5 5.61 13.1 1.10 LP LP 13.1 9.6 1.71
Des 1 2.8 2.0 5.2 5.2 5.08 1.10 1.10 1.10 3.08 0.0 0.00
Des 2 2.8 2.0 5.2 5.2 5.08 1.7 1.10 1.10 1.10 3.1 1.5 0.27
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 1.05 1.10 1.08 3.2 4.5 0.81
Feb 2 3.0 2.0 2.4 2.4 5.31 0.95 1.05 1.00 3.0 2.6 0.47
Mar 1 3.5 2.0 4.6 4.6 5.86 0.00 0.95 0.48 1.7 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 11.4 LP LP LP 11.4 7.1 1.26
Apr 2 3.1 2.0 4.3 4.3 5.45 11.4 1.10 LP LP 11.4 7.1 1.26
Mei 1 3.6 2.0 3.2 3.2 5.92 1.10 1.10 1.10 3.9 2.7 0.48
Mei 2 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.10 1.08 3.8 4.3 0.76
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.05 1.05 3.7 5.2 0.93
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 0.95 1.05 1.00 3.5 5.1 0.90
Jul 1 3.7 2.0 1.7 1.7 6.02 1.7 0.00 0.95 0.48 1.7 3.7 0.65
Jul 2 3.7 2.0 1.7 1.7 6.02 0.50 0.00 0.25 0.5 0.5 0.7 0.0 0.13
Agt 1 4.2 2.0 0.4 0.4 6.62 0.75 0.50 0.63 2.6 2.3 0.40
Agt 2 4.2 2.0 0.4 0.4 6.62 1.00 0.75 0.88 3.7 3.3 0.59
Sep 1 4.2 2.0 0.2 0.2 6.65 1.00 1.00 1.00 4.2 4.0 0.71
Sep 2 4.2 2.0 0.2 0.2 6.65 0.82 1.00 0.91 3.8 3.6 0.64
Okt 1 3.7 2.0 1.0 1.0 6.08 0.45 0.82 0.64 2.4 1.4 0.24
Okt 2 3.7 2.0 1.0 1.01 6.08 0.45 0.23 0.8 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-14


LAPORAN AKHIR

Tabel 5.11 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 1, Mulai Nov-2
Kelompok 3, Mulai Tanam Pertengahan Nopember, Pengolahan Lahan 30 Hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 0.00 0.0 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 13.1 LP LP LP 13.1 9.6 1.71
Des 1 2.8 2.0 5.2 5.2 5.08 12.8 1.10 LP LP 12.8 7.5 1.34
Des 2 2.8 2.0 5.2 5.2 5.08 1.10 1.10 1.10 3.1 0.0 0.00
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 1.05 1.10 1.08 2.8 2.3 0.40
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.05 1.05 1.05 2.7 2.2 0.39
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 0.95 1.05 1.00 3.0 4.3 0.76
Feb 2 3.0 2.0 2.4 2.4 5.31 1.7 0.00 0.95 0.48 1.4 2.7 0.48
Mar 1 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 0.00 0.0 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 11.4 LP LP LP 11.4 7.1 1.26
Apr 2 3.1 2.0 4.3 4.3 5.45 11.4 1.10 LP LP 11.4 7.1 1.26
Mei 1 3.6 2.0 3.2 3.2 5.92 1.10 1.10 1.10 3.9 2.7 0.48
Mei 2 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.10 1.08 3.8 4.3 0.76
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.05 1.05 3.7 5.2 0.93
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 0.95 1.05 1.00 3.5 5.1 0.90
Jul 1 3.7 2.0 1.7 1.7 6.02 1.7 0.00 0.95 0.48 1.7 3.7 0.65
Jul 2 3.7 2.0 1.7 1.7 6.02 0.50 0.00 0.25 0.5 0.5 0.7 0.0 0.13
Agt 1 4.2 2.0 0.4 0.4 6.62 0.75 0.50 0.63 2.6 2.3 0.40
Agt 2 4.2 2.0 0.4 0.4 6.62 1.00 0.75 0.88 3.7 3.3 0.59
Sep 1 4.2 2.0 0.2 0.2 6.65 1.00 1.00 1.00 4.2 4.0 0.71
Sep 2 4.2 2.0 0.2 0.2 6.65 0.82 1.00 0.91 3.8 3.6 0.64
Okt 1 3.7 2.0 1.0 1.0 6.08 0.45 0.82 0.64 2.4 1.4 0.24
Okt 2 3.7 2.0 1.0 1.0 6.08 0.45 0.23 0.8 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-15


LAPORAN AKHIR

Tabel 5.12 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 2, Mulai Nov-2
Kelompok 3, Mulai Tanam Pertengahan Nopember, Pengolahan Lahan 45 Hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C3 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11 12 a 12 b 13 a 13 b 14
Nop 1 3.3 2.0 3.5 3.5 5.61 0.45 0.15 0.5 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 9.9 LP LP LP LP 9.9 6.4 1.14
Des 1 2.8 2.0 5.2 5.2 5.08 9.5 1.10 LP LP LP 9.5 4.3 0.77
Des 2 2.8 2.0 5.2 5.2 5.08 9.5 1.10 1.10 LP LP 9.5 4.3 0.77
Jan 1 2.6 2.0 4.2 4.2 4.87 1.1 1.05 1.10 1.10 1.08 2.8 1.7 0.31
Jan 2 2.6 2.0 4.2 4.2 4.87 1.1 1.05 1.05 1.10 1.07 2.8 1.7 0.30
Feb 1 3.0 2.0 2.4 2.4 5.31 2.2 0.95 1.05 1.05 1.02 3.1 4.9 0.87
Feb 2 3.0 2.0 2.4 2.4 5.31 1.1 0.00 0.95 1.05 0.67 2.0 2.7 0.49
Mar 1 3.5 2.0 4.6 4.6 5.86 1.1 0.00 0.95 0.32 1.1 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 8.7 LP LP LP LP 8.7 4.4 0.79
Apr 2 3.1 2.0 4.3 4.3 5.45 8.7 1.10 LP LP LP 8.7 4.4 0.79
Mei 1 3.6 2.0 3.2 3.2 5.92 9.0 1.10 1.10 LP LP 9.0 5.8 1.03
Mei 2 3.6 2.0 3.2 3.2 5.92 1.1 1.05 1.10 1.10 1.08 3.9 3.7 0.67
Jun 1 3.5 2.0 2.1 2.1 5.87 1.1 1.05 1.05 1.10 1.07 3.8 4.7 0.84
Jun 2 3.5 2.0 2.1 2.1 5.87 2.2 0.95 1.05 1.05 1.02 3.6 5.7 1.01
Jul 1 3.7 2.0 1.7 1.7 6.02 1.1 0.00 0.95 1.05 0.67 2.4 3.8 0.68
Jul 2 3.7 2.0 1.7 1.7 6.02 1.1 0.50 0.00 0.95 0.48 1.2 0.6 2.6 0.0 0.45
Agt 1 4.2 2.0 0.4 0.4 6.62 0.75 0.50 0.00 0.42 1.8 1.4 0.25
Agt 2 4.2 2.0 0.4 0.4 6.62 1.00 0.75 0.50 0.75 3.2 2.8 0.50
Sep 1 4.2 2.0 0.2 0.2 6.65 1.00 1.00 0.75 0.92 3.9 3.6 0.65
Sep 2 4.2 2.0 0.2 0.2 6.65 0.82 1.00 1.00 0.94 4.0 3.7 0.66
Okt 1 3.7 2.0 1.0 1.0 6.08 0.45 0.82 1.00 0.76 2.8 1.8 0.32
Okt 2 3.7 2.0 1.0 1.0 6.08 0.45 0.82 0.42 1.6 0.6 0.10

Catatan : - Pengolahan lahan (Land preparation) : 45 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-16


LAPORAN AKHIR

Tabel 5.13 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 3, Mulai Nov-2
Kelompok 3, Mulai Tanam Pertengahan Nopember, Pengolahan Lahan 30 Hari, Varietas Biasa, Varietas Unggul, Palawija
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 0.45 0.23 0.7 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 13.1 LP LP LP 13.1 9.6 1.71
Des 1 2.8 2.0 5.2 5.2 5.08 12.8 1.10 LP LP 12.8 7.5 1.34
Des 2 2.8 2.0 5.2 5.2 5.08 1.10 1.10 1.10 3.1 0.0 0.00
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 1.10 1.10 1.10 3.3 4.6 0.82
Feb 2 3.0 2.0 2.4 2.4 5.31 1.7 1.05 1.10 1.08 3.2 4.5 0.81
Mar 1 3.5 2.0 4.6 4.6 5.86 0.95 1.05 1.00 3.5 0.9 0.16
Mar 2 3.5 2.0 4.6 4.6 5.86 0.00 0.95 0.48 1.7 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 0.00 0.00 0.0 0.0 0.00
Apr 2 3.1 2.0 4.3 4.3 5.45 11.4 LP LP LP 11.4 7.1 1.26
Mei 1 3.6 2.0 3.2 3.2 5.92 11.6 1.10 LP LP 11.6 8.4 1.50
Mei 2 3.6 2.0 3.2 3.2 5.92 1.10 1.10 1.10 3.9 2.7 0.48
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.10 1.08 3.8 5.3 0.95
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.05 1.05 3.7 5.2 0.93
Jul 1 3.7 2.0 1.7 1.7 6.02 1.7 0.95 1.05 1.00 3.7 5.6 0.99
Jul 2 3.7 2.0 1.7 1.7 6.02 1.7 0.00 0.95 0.48 1.7 3.7 0.65
Agt 1 4.2 2.0 0.4 0.4 6.62 0.50 0.00 0.25 0.5 0.5 2.2 0.2 0.41
Agt 2 4.2 2.0 0.4 0.4 6.62 0.75 0.50 0.63 2.6 2.3 0.40
Sep 1 4.2 2.0 0.2 0.2 6.65 1.00 0.75 0.88 3.7 3.5 0.62
Sep 2 4.2 2.0 0.2 0.2 6.65 1.00 1.00 1.00 4.2 4.0 0.71
Okt 1 3.7 2.0 1.0 1.0 6.08 0.82 1.00 0.91 3.4 2.4 0.42
Okt 2 3.7 2.0 1.0 1.0 6.08 0.45 0.82 0.64 2.4 1.4 0.24

Catatan : - Pengolahan lahan (Land preparation) :30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-17


LAPORAN AKHIR

Tabel 5.14 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 1, Mulai Dec-1
Kelompok 4, Mulai Tanam Awal Desember, Pengolahan Lahan 30 Hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR padi
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 0.45 0.23 0.7 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 0.00 0.0 0.0 0.00
Des 1 2.8 2.0 5.2 5.2 5.08 12.8 LP LP LP 12.8 7.5 1.34
Des 2 2.8 2.0 5.2 5.2 5.08 12.8 1.10 LP LP 12.8 7.5 1.34
Jan 1 2.6 2.0 4.2 4.2 4.87 1.10 1.10 1.10 2.9 0.7 0.12
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.05 1.10 1.08 2.8 2.3 0.40
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 1.05 1.05 1.05 3.2 4.4 0.79
Feb 2 3.0 2.0 2.4 2.4 5.31 1.7 0.95 1.05 1.00 3.0 4.3 0.76
Mar 1 3.5 2.0 4.6 4.6 5.86 1.7 0.00 0.95 0.48 1.7 0.7 0.13
Mar 2 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 0.00 0.0 0.0 0.00
Apr 2 3.1 2.0 4.3 4.3 5.45 11.4 LP LP LP 11.4 7.1 1.26
Mei 1 3.6 2.0 3.2 3.2 5.92 11.6 1.10 LP LP 11.6 8.4 1.50
Mei 2 3.6 2.0 3.2 3.2 5.92 1.10 1.10 1.10 3.9 2.7 0.48
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.10 1.08 3.8 5.3 0.95
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.05 1.05 3.7 5.2 0.93
Jul 1 3.7 2.0 1.7 1.7 6.02 1.7 0.95 1.05 1.00 3.7 5.6 0.99
Jul 2 3.7 2.0 1.7 1.7 6.02 1.7 0.00 0.95 0.48 1.7 3.7 0.65
Agt 1 4.2 2.0 0.4 0.4 6.62 0.50 0.00 0.25 0.5 0.5 2.2 0.2 0.41
Agt 2 4.2 2.0 0.4 0.4 6.62 0.75 0.50 0.63 2.6 2.3 0.40
Sep 1 4.2 2.0 0.2 0.2 6.65 1.00 0.75 0.88 3.7 3.5 0.62
Sep 2 4.2 2.0 0.2 0.2 6.65 1.00 1.00 1.00 4.2 4.0 0.71
Okt 1 3.7 2.0 1.0 1.0 6.08 0.82 1.00 0.91 3.4 2.4 0.42
Okt 2 3.7 2.0 1.0 1.0 6.08 0.45 0.82 0.64 2.36 1.4 0.24

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-18


LAPORAN AKHIR

Tabel 5.15 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 2, Mulai Dec-1
Kelompok 4, Mulai Tanam Awal Desember, Pengolahan Lahan 45 Hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR padi
Periode C1 C2 C3 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11 12 a 12 b 13 a 13 b 14
Nop 1 3.3 2.0 3.5 3.5 5.61 0.45 0.82 0.42 1.4 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 0.45 0.15 0.5 0.0 0.00
Des 1 2.8 2.0 5.2 5.2 5.08 9.5 LP LP LP LP 9.5 4.3 0.77
Des 2 2.8 2.0 5.2 5.2 5.08 9.5 1.10 LP LP LP 9.5 4.3 0.77
Jan 1 2.6 2.0 4.2 4.2 4.87 9.4 1.10 1.10 LP LP 9.4 5.2 0.93
Jan 2 2.6 2.0 4.2 4.2 4.87 1.1 1.05 1.10 1.10 1.08 2.8 1.7 0.31
Feb 1 3.0 2.0 2.4 2.4 5.31 1.1 1.05 1.05 1.10 1.07 3.2 3.9 0.70
Feb 2 3.0 2.0 2.4 2.4 5.31 2.2 0.95 1.05 1.05 1.02 3.1 4.9 0.87
Mar 1 3.5 2.0 4.6 4.6 5.86 1.1 0.00 0.95 1.05 0.67 2.3 0.8 0.15
Mar 2 3.5 2.0 4.6 4.6 5.86 1.1 0.00 0.95 0.32 1.1 ` 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 0.00 0.00 0.0 0.0 0.00
Apr 2 3.1 2.0 4.3 4.3 5.45 8.7 LP LP LP LP 8.7 4.4 0.79
Mei 1 3.6 2.0 3.2 3.2 5.92 9.0 1.10 LP LP LP 9.0 5.8 1.03
Mei 2 3.6 2.0 3.2 3.2 5.92 9.0 1.10 1.10 LP LP 9.0 5.8 1.03
Jun 1 3.5 2.0 2.1 2.1 5.87 1.1 1.05 1.10 1.10 1.08 3.8 4.8 0.86
Jun 2 3.5 2.0 2.1 2.1 5.87 1.1 1.05 1.05 1.10 1.07 3.8 4.7 0.84
Jul 1 3.7 2.0 1.7 1.7 6.02 2.2 0.95 1.05 1.05 1.02 3.7 6.2 1.10
Jul 2 3.7 2.0 1.7 1.7 6.02 1.1 0.00 0.95 1.05 0.67 2.4 3.8 0.68
Agt 1 4.2 2.0 0.4 0.4 6.62 1.1 0.50 0.00 0.95 0.48 1.4 0.7 4.1 0.3 0.79
Agt 2 4.2 2.0 0.4 0.4 6.62 0.75 0.50 0.00 0.42 1.8 1.4 0.25
Sep 1 4.2 2.0 0.2 0.2 6.65 1.00 0.75 0.50 0.75 3.2 2.9 0.52
Sep 2 4.2 2.0 0.2 0.2 6.65 1.00 1.00 0.75 0.92 3.9 3.6 0.65
Okt 1 3.7 2.0 1.0 1.0 6.08 0.82 1.00 1.00 0.94 3.5 2.5 0.44
Okt 2 3.7 2.0 1.0 1.0 6.08 0.45 0.82 1.00 0.76 2.81 1.8 0.32

Catatan : - Pengolahan lahan (Land preparation) : 45 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-19


LAPORAN AKHIR

Tabel 5.16 Perhitungan Kebutuhan Air Irigasi 3 Pola Tanam Alternatif – 3, Mulai Dec-1
Kelompok 4, Mulai Tanam Awal Desember, Pengolahan Lahan 30 Hari, Varietas Biasa, Varietas Unggul, Palawija
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR padi
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 0.45 0.82 0.64 2.1 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 0.45 0.23 0.7 0.0 0.00
Des 1 2.8 2.0 5.2 5.2 5.08 12.8 LP LP LP 12.8 7.5 1.34
Des 2 2.8 2.0 5.2 5.2 5.08 12.8 1.10 LP LP 12.8 7.5 1.34
Jan 1 2.6 2.0 4.2 4.2 4.87 1.10 1.10 1.10 2.9 0.7 0.12
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 1.10 1.10 1.10 3.3 4.6 0.82
Feb 2 3.0 2.0 2.4 2.4 5.31 1.7 1.10 1.10 1.10 3.3 4.6 0.82
Mar 1 3.5 2.0 4.6 4.6 5.86 1.7 1.05 1.10 1.08 3.8 2.8 0.50
Mar 2 3.5 2.0 4.6 4.6 5.86 0.95 1.05 1.00 3.5 0.9 0.16
Apr 1 3.1 2.0 4.3 4.3 5.45 0.00 0.95 0.48 1.5 0.0 0.00
Apr 2 3.1 2.0 4.3 4.3 5.45 0.00 0.00 0.0 0.0 0.00
Mei 1 3.6 2.0 3.2 3.2 5.92 11.6 LP LP LP 11.6 8.4 1.50
Mei 2 3.6 2.0 3.2 3.2 5.92 11.6 1.10 LP LP 11.6 8.4 1.50
Jun 1 3.5 2.0 2.1 2.1 5.87 1.10 1.10 1.10 3.9 3.8 0.67
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.10 1.08 3.8 5.3 0.95
Jul 1 3.7 2.0 1.7 1.7 6.02 1.7 1.05 1.05 1.05 3.8 5.8 1.03
Jul 2 3.7 2.0 1.7 1.7 6.02 1.7 0.95 1.05 1.00 3.7 5.6 0.99
Agt 1 4.2 2.0 0.4 0.4 6.62 1.7 0.00 0.95 0.48 2.0 5.3 0.94
Agt 2 4.2 2.0 0.4 0.4 6.62 0.50 0.00 0.25 0.5 0.5 2.2 0.2 0.41
Sep 1 4.2 2.0 0.2 0.2 6.65 0.75 0.50 0.63 2.6 2.4 0.43
Sep 2 4.2 2.0 0.2 0.2 6.65 1.00 0.75 0.88 3.7 3.5 0.62
Okt 1 3.7 2.0 1.0 1.0 6.08 1.00 1.00 1.00 3.7 2.7 0.48
Okt 2 3.7 2.0 1.0 1.0 6.08 0.82 1.00 0.91 3.38 2.4 0.42

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-20


LAPORAN AKHIR

Hasil rekap perhitungan kebutuhan air irigasi dengan skenario 1 pada tabel sebelumnya, dapat
dilihat pada tabel berikut.
Tabel 5.17 Kebutuhan Air Irigasi 3 Pola Tanam - Lama pengolahan lahan : 30 hari Gudang (liter/s.Ha) (Alternatif-1)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-21


LAPORAN AKHIR

Tabel 5.18 Rekap Kebutuhan Air Irigasi 3 Pola Tanam - Lama pengolahan lahan : 45 hari Gudang (liter/s.Ha)
(Alternatif-2)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-22


LAPORAN AKHIR

Tabel 5.19 Kebutuhan Air Irigasi 3 Pola Tanam - Lama pengolahan lahan : 30 hari, Varietas Biasa Gudang (liter/s.Ha)
(alternatif-3)

Hasil analisis menunjukkan bahwa untuk 3 pola tanam golongan yang terpilih yaitu golongan 2 (dua
rotasi golongan). Lama pengolahan lahan 45 hari dengan padi unggul, padi unggul, palawija
(alternatif-2), dengan nilai NFR sebesar 1.03 l/dt/ha.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-23


LAPORAN AKHIR

B. Skenario 2 (2 Pola Tanam)


Tabel 5.20 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 1, Mulai Okt-2
Kelompok 1, Mulai Tanam Pertengahan Oktober, Pengolahan Lahan 30 hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 13.1 1.10 LP LP 13.1 9.6 1.71
Nop 2 3.3 2.0 3.5 3.5 5.61 1.10 1.10 1.10 3.61 2.2 0.38
Des 1 2.8 2.0 5.2 5.2 5.08 1.7 1.05 1.10 1.08 3.0 1.4 0.26
Des 2 2.8 2.0 5.2 5.2 5.08 1.7 1.05 1.05 1.05 2.9 1.4 0.25
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 0.95 1.05 1.00 2.6 2.1 0.37
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 0.00 0.95 0.48 1.2 0.7 0.13
Feb 1 3.0 2.0 2.4 2.4 5.31 0.00 0.00 0.0 0.0 0.00
Feb 2 3.0 2.0 2.4 2.4 5.31 0.0 0.0 0.00
Mar 1 3.5 2.0 4.6 4.6 5.86 11.6 LP LP LP 11.6 7.0 1.24
Mar 2 3.5 2.0 4.6 4.6 5.86 11.6 1.10 LP LP 11.6 7.0 1.24
Apr 1 3.1 2.0 4.3 4.3 5.45 1.10 1.10 1.10 3.45 1.2 0.21
Apr 2 3.1 2.0 4.3 4.3 5.45 1.7 1.05 1.10 1.08 3.4 2.8 0.49
Mei 1 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.05 1.05 3.7 4.2 0.75
Mei 2 3.6 2.0 3.2 3.2 5.92 1.7 0.95 1.05 1.00 3.6 4.0 0.71
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 0.00 0.95 0.48 1.7 3.2 0.57
Jun 2 3.5 2.0 2.1 2.1 5.87 0.00 0.00 0.00 0.0 0.0 0.0 0.0 0.00
Jul 1 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.0 0.0 0.00
Jul 2 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.0 0.0 0.00
Agt 1 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.01 6.08 13.3 LP LP LP 13.3 12.3 2.20

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-24


LAPORAN AKHIR

Tabel 5.21 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 2, Mulai Okt-2
Kelompok 1, Mulai Tanam Pertengahan Oktober, Pengolahan Lahan 45 Hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C3 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11 12 a 12 b 13 a 13 b 14
Nop 1 3.3 2.0 3.5 3.5 5.61 9.9 1.10 LP LP LP 9.9 6.4 1.14
Nop 2 3.3 2.0 3.5 3.5 5.61 9.9 1.10 1.10 LP LP 9.9 6.4 1.14
Des 1 2.8 2.0 5.2 5.2 5.08 1.1 1.05 1.10 1.10 1.08 3.0 0.9 0.16
Des 2 2.8 2.0 5.2 5.2 5.08 1.1 1.05 1.05 1.10 1.07 3.0 0.9 0.15
Jan 1 2.6 2.0 4.2 4.2 4.87 2.2 0.95 1.05 1.05 1.02 2.7 2.7 0.48
Jan 2 2.6 2.0 4.2 4.2 4.87 1.1 0.00 0.95 1.05 0.67 1.7 0.7 0.12
Feb 1 3.0 2.0 2.4 2.4 5.31 1.1 0.00 0.95 0.32 1.0 1.7 0.30
Feb 2 3.0 2.0 2.4 2.4 5.31 0.00 0.00 0.0 0.0 0.00
Mar 1 3.5 2.0 4.6 4.6 5.86 9.0 LP LP LP LP 9.0 4.4 0.78
Mar 2 3.5 2.0 4.6 4.6 5.86 9.0 1.10 LP LP LP 9.0 4.4 0.78
Apr 1 3.1 2.0 4.3 4.3 5.45 8.7 1.10 1.10 LP LP 8.7 4.4 0.79
Apr 2 3.1 2.0 4.3 4.3 5.45 1.1 1.05 1.10 1.10 1.08 3.4 2.2 0.40
Mei 1 3.6 2.0 3.2 3.2 5.92 1.1 1.05 1.05 1.10 1.07 3.8 3.7 0.66
Mei 2 3.6 2.0 3.2 3.2 5.92 2.2 0.95 1.05 1.05 1.02 3.6 4.6 0.82
Jun 1 3.5 2.0 2.1 2.1 5.87 1.1 0.00 0.95 1.05 0.67 2.3 3.3 0.59
Jun 2 3.5 2.0 2.1 2.1 5.87 1.1 0.00 0.00 0.95 0.32 0.7 0.0 1.7 0.0 0.31
Jul 1 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Jul 2 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Agt 1 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.01 6.08 12.0 LP LP LP LP 12.0 10.9 1.95

Catatan : - Pengolahan lahan (Land preparation) : 45 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-25


LAPORAN AKHIR

Tabel 5.22 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 3, Mulai Okt-2
Kelompok 1, Mulai Tanam Pertengahan Oktober, Pengolahan Lahan 30 hari, Varietas Biasa, Varietas Unggul, Palawija
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 13.1 1.10 LP LP 13.1 9.6 1.71
Nop 2 3.3 2.0 3.5 3.5 5.61 1.10 1.10 1.10 3.61 2.2 0.38
Des 1 2.8 2.0 5.2 5.2 5.08 1.7 1.10 1.10 1.10 3.1 1.5 0.27
Des 2 2.8 2.0 5.2 5.2 5.08 1.7 1.10 1.10 1.10 3.1 1.5 0.27
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.05 1.10 1.08 2.8 2.3 0.40
Feb 1 3.0 2.0 2.4 2.4 5.31 0.95 1.05 1.00 3.0 2.6 0.47
Feb 2 3.0 2.0 2.4 2.4 5.31 0.00 0.95 0.48 1.4 1.0 0.19
Mar 1 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 11.6 LP LP LP 11.6 7.0 1.24
Apr 1 3.1 2.0 4.3 4.3 5.45 11.4 1.10 LP LP 11.4 7.1 1.26
Apr 2 3.1 2.0 4.3 4.3 5.45 1.10 1.10 1.10 3.5 1.2 0.21
Mei 1 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.10 1.08 3.8 4.3 0.76
Mei 2 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.05 1.05 3.7 4.2 0.75
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 0.95 1.05 1.00 3.5 5.1 0.90
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 0.00 0.95 0.48 1.7 3.2 0.57
Jul 1 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.0 0.0 0.3 0.0 0.05
Jul 2 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.0 0.0 0.00
Agt 1 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.01 6.08 13.3 LP LP LP 13.3 12.3 2.20

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-26


LAPORAN AKHIR

Tabel 5.23 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 1, Mulai Nov-1
Kelompok 2, Mulai Tanam Awal Nopember, Pengolahan Lahan 30 Hari, Variets Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 13.1 LP LP LP 13.1 9.6 1.71
Nop 2 3.3 2.0 3.5 3.5 5.61 13.1 1.10 LP LP 13.1 9.6 1.71
Des 1 2.8 2.0 5.2 5.2 5.08 1.10 1.10 1.10 3.08 0.0 0.00
Des 2 2.8 2.0 5.2 5.2 5.08 1.7 1.05 1.10 1.08 3.0 1.4 0.26
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 1.05 1.05 1.05 2.7 2.2 0.39
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 0.95 1.05 1.00 2.6 2.1 0.37
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 0.00 0.95 0.48 1.4 2.7 0.48
Feb 2 3.0 2.0 2.4 2.4 5.31 0.00 0.00 0.0 0.0 0.00
Mar 1 3.5 2.0 4.6 4.6 5.86 0.0 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 11.6 LP LP LP 11.6 7.0 1.24
Apr 1 3.1 2.0 4.3 4.3 5.45 11.4 1.10 LP LP 11.4 7.1 1.26
Apr 2 3.1 2.0 4.3 4.3 5.45 1.10 1.10 1.10 3.45 1.2 0.21
Mei 1 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.10 1.08 3.8 4.3 0.76
Mei 2 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.05 1.05 3.7 4.2 0.75
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 0.95 1.05 1.00 3.5 5.1 0.90
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 0.00 0.95 0.48 1.7 3.2 0.57
Jul 1 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.0 0.0 0.3 0.0 0.05
Jul 2 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.0 0.0 0.00
Agt 1 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.01 6.08 0.00 0.0 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-27


LAPORAN AKHIR

Tabel 5.24 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 2, Mulai Nov-1
Kelompok 2, Mulai Tanam Awal Nopember, Pengolahan Lahan 45 Hari, Variets Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C3 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11 12 a 12 b 13 a 13 b 14
Nop 1 3.3 2.0 3.5 3.5 5.61 9.9 LP LP LP LP 9.9 6.4 1.14
Nop 2 3.3 2.0 3.5 3.5 5.61 9.9 1.10 LP LP LP 9.9 6.4 1.14
Des 1 2.8 2.0 5.2 5.2 5.08 9.5 1.10 1.10 LP LP 9.5 4.3 0.77
Des 2 2.8 2.0 5.2 5.2 5.08 1.1 1.05 1.10 1.10 1.08 3.0 0.9 0.16
Jan 1 2.6 2.0 4.2 4.2 4.87 1.1 1.05 1.05 1.10 1.07 2.8 1.7 0.30
Jan 2 2.6 2.0 4.2 4.2 4.87 2.2 0.95 1.05 1.05 1.02 2.7 2.7 0.48
Feb 1 3.0 2.0 2.4 2.4 5.31 1.1 0.00 0.95 1.05 0.67 2.0 2.7 0.49
Feb 2 3.0 2.0 2.4 2.4 5.31 1.1 0.00 0.95 0.32 1.0 1.7 0.30
Mar 1 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 9.0 LP LP LP LP 9.0 4.4 0.78
Apr 1 3.1 2.0 4.3 4.3 5.45 8.7 1.10 LP LP LP 8.7 4.4 0.79
Apr 2 3.1 2.0 4.3 4.3 5.45 8.7 1.10 1.10 LP LP 8.7 4.4 0.79
Mei 1 3.6 2.0 3.2 3.2 5.92 1.1 1.05 1.10 1.10 1.08 3.9 3.7 0.67
Mei 2 3.6 2.0 3.2 3.2 5.92 1.1 1.05 1.05 1.10 1.07 3.8 3.7 0.66
Jun 1 3.5 2.0 2.1 2.1 5.87 2.2 0.95 1.05 1.05 1.02 3.6 5.7 1.01
Jun 2 3.5 2.0 2.1 2.1 5.87 1.1 0.00 0.95 1.05 0.67 2.3 3.3 0.59
Jul 1 3.7 2.0 1.7 1.7 6.02 1.1 0.00 0.00 0.95 0.32 0.8 0.4 2.1 0.0 0.38
Jul 2 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Agt 1 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.01 6.08 0.00 0.00 0.0 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 45 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-28


LAPORAN AKHIR

Tabel 5.25 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 3, Mulai Nov-1
Kelompok 2, Mulai Tanam Awal Nopember, Pengolahan Lahan 30 Hari, Variets Biasa, Varietas Unggul, Palawija
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 13.1 LP LP LP 13.1 9.6 1.71
Nop 2 3.3 2.0 3.5 3.5 5.61 13.1 1.10 LP LP 13.1 9.6 1.71
Des 1 2.8 2.0 5.2 5.2 5.08 1.10 1.10 1.10 3.08 0.0 0.00
Des 2 2.8 2.0 5.2 5.2 5.08 1.7 1.10 1.10 1.10 3.1 1.5 0.27
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 1.05 1.10 1.08 3.2 4.5 0.81
Feb 2 3.0 2.0 2.4 2.4 5.31 0.95 1.05 1.00 3.0 2.6 0.47
Mar 1 3.5 2.0 4.6 4.6 5.86 0.00 0.95 0.48 1.7 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 11.4 LP LP LP 11.4 7.1 1.26
Apr 2 3.1 2.0 4.3 4.3 5.45 11.4 1.10 LP LP 11.4 7.1 1.26
Mei 1 3.6 2.0 3.2 3.2 5.92 1.10 1.10 1.10 3.9 2.7 0.48
Mei 2 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.10 1.08 3.8 4.3 0.76
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.05 1.05 3.7 5.2 0.93
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 0.95 1.05 1.00 3.5 5.1 0.90
Jul 1 3.7 2.0 1.7 1.7 6.02 1.7 0.00 0.95 0.48 1.7 3.7 0.65
Jul 2 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.0 0.0 0.3 0.0 0.05
Agt 1 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.01 6.08 0.00 0.00 0.0 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-29


LAPORAN AKHIR

Tabel 5.26 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 1, Mulai Nov-2
Kelompok 3, Mulai Tanam Pertengahan Nopember, Pengolahan Lahan 30 Hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 0.00 0.0 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 13.1 LP LP LP 13.1 9.6 1.71
Des 1 2.8 2.0 5.2 5.2 5.08 12.8 1.10 LP LP 12.8 7.5 1.34
Des 2 2.8 2.0 5.2 5.2 5.08 1.10 1.10 1.10 3.1 0.0 0.00
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 1.05 1.10 1.08 2.8 2.3 0.40
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.05 1.05 1.05 2.7 2.2 0.39
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 0.95 1.05 1.00 3.0 4.3 0.76
Feb 2 3.0 2.0 2.4 2.4 5.31 1.7 0.00 0.95 0.48 1.4 2.7 0.48
Mar 1 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 0.00 0.0 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 11.4 LP LP LP 11.4 7.1 1.26
Apr 2 3.1 2.0 4.3 4.3 5.45 11.4 1.10 LP LP 11.4 7.1 1.26
Mei 1 3.6 2.0 3.2 3.2 5.92 1.10 1.10 1.10 3.9 2.7 0.48
Mei 2 3.6 2.0 3.2 3.2 5.92 1.7 1.05 1.10 1.08 3.8 4.3 0.76
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.05 1.05 3.7 5.2 0.93
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 0.95 1.05 1.00 3.5 5.1 0.90
Jul 1 3.7 2.0 1.7 1.7 6.02 1.7 0.00 0.95 0.48 1.7 3.7 0.65
Jul 2 3.7 2.0 1.7 1.7 6.02 0.00 0.00 0.00 0.0 0.0 0.3 0.0 0.05
Agt 1 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.0 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-30


LAPORAN AKHIR

Tabel 5.27 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 2, Mulai Nov-2
Kelompok 3, Mulai Tanam Pertengahan Nopember, Pengolahan Lahan 45 Hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C3 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11 12 a 12 b 13 a 13 b 14
Nop 1 3.3 2.0 3.5 3.5 5.61 0.00 0.00 0.0 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 9.9 LP LP LP LP 9.9 6.4 1.14
Des 1 2.8 2.0 5.2 5.2 5.08 9.5 1.10 LP LP LP 9.5 4.3 0.77
Des 2 2.8 2.0 5.2 5.2 5.08 9.5 1.10 1.10 LP LP 9.5 4.3 0.77
Jan 1 2.6 2.0 4.2 4.2 4.87 1.1 1.05 1.10 1.10 1.08 2.8 1.7 0.31
Jan 2 2.6 2.0 4.2 4.2 4.87 1.1 1.05 1.05 1.10 1.07 2.8 1.7 0.30
Feb 1 3.0 2.0 2.4 2.4 5.31 2.2 0.95 1.05 1.05 1.02 3.1 4.9 0.87
Feb 2 3.0 2.0 2.4 2.4 5.31 1.1 0.00 0.95 1.05 0.67 2.0 2.7 0.49
Mar 1 3.5 2.0 4.6 4.6 5.86 1.1 0.00 0.95 0.32 1.1 0.0 0.00
Mar 2 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 8.7 LP LP LP LP 8.7 4.4 0.79
Apr 2 3.1 2.0 4.3 4.3 5.45 8.7 1.10 LP LP LP 8.7 4.4 0.79
Mei 1 3.6 2.0 3.2 3.2 5.92 9.0 1.10 1.10 LP LP 9.0 5.8 1.03
Mei 2 3.6 2.0 3.2 3.2 5.92 1.1 1.05 1.10 1.10 1.08 3.9 3.7 0.67
Jun 1 3.5 2.0 2.1 2.1 5.87 1.1 1.05 1.05 1.10 1.07 3.8 4.7 0.84
Jun 2 3.5 2.0 2.1 2.1 5.87 2.2 0.95 1.05 1.05 1.02 3.6 5.7 1.01
Jul 1 3.7 2.0 1.7 1.7 6.02 1.1 0.00 0.95 1.05 0.67 2.4 3.8 0.68
Jul 2 3.7 2.0 1.7 1.7 6.02 1.1 0.00 0.00 0.95 0.32 0.8 0.4 2.1 0.0 0.38
Agt 1 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.0 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 45 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-31


LAPORAN AKHIR

Tabel 5.28 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 3, Mulai Nov-2
Kelompok 3, Mulai Tanam Pertengahan Nopember, Pengolahan Lahan 30 Hari, Varietas Biasa, Varietas Unggul, Palawija
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 0.00 0.00 0.0 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 13.1 LP LP LP 13.1 9.6 1.71
Des 1 2.8 2.0 5.2 5.2 5.08 12.8 1.10 LP LP 12.8 7.5 1.34
Des 2 2.8 2.0 5.2 5.2 5.08 1.10 1.10 1.10 3.1 0.0 0.00
Jan 1 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 1.10 1.10 1.10 3.3 4.6 0.82
Feb 2 3.0 2.0 2.4 2.4 5.31 1.7 1.05 1.10 1.08 3.2 4.5 0.81
Mar 1 3.5 2.0 4.6 4.6 5.86 0.95 1.05 1.00 3.5 0.9 0.16
Mar 2 3.5 2.0 4.6 4.6 5.86 0.00 0.95 0.48 1.7 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 0.00 0.00 0.0 0.0 0.00
Apr 2 3.1 2.0 4.3 4.3 5.45 11.4 LP LP LP 11.4 7.1 1.26
Mei 1 3.6 2.0 3.2 3.2 5.92 11.6 1.10 LP LP 11.6 8.4 1.50
Mei 2 3.6 2.0 3.2 3.2 5.92 1.10 1.10 1.10 3.9 2.7 0.48
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.10 1.08 3.8 5.3 0.95
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.05 1.05 3.7 5.2 0.93
Jul 1 3.7 2.0 1.7 1.7 6.02 1.7 0.95 1.05 1.00 3.7 5.6 0.99
Jul 2 3.7 2.0 1.7 1.7 6.02 1.7 0.00 0.95 0.48 1.7 3.7 0.65
Agt 1 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 1.6 0.0 0.29
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.0 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) :30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-32


LAPORAN AKHIR

Tabel 5.29 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 1, Mulai Dec-1
Kelompok 4, Mulai Tanam Awal Desember, Pengolahan Lahan 30 Hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR padi
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 0.00 0.00 0.0 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 0.00 0.0 0.0 0.00
Des 1 2.8 2.0 5.2 5.2 5.08 12.8 LP LP LP 12.8 7.5 1.34
Des 2 2.8 2.0 5.2 5.2 5.08 12.8 1.10 LP LP 12.8 7.5 1.34
Jan 1 2.6 2.0 4.2 4.2 4.87 1.10 1.10 1.10 2.9 0.7 0.12
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.05 1.10 1.08 2.8 2.3 0.40
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 1.05 1.05 1.05 3.2 4.4 0.79
Feb 2 3.0 2.0 2.4 2.4 5.31 1.7 0.95 1.05 1.00 3.0 4.3 0.76
Mar 1 3.5 2.0 4.6 4.6 5.86 1.7 0.00 0.95 0.48 1.7 0.7 0.13
Mar 2 3.5 2.0 4.6 4.6 5.86 0.00 0.00 0.0 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 0.00 0.0 0.0 0.00
Apr 2 3.1 2.0 4.3 4.3 5.45 11.4 LP LP LP 11.4 7.1 1.26
Mei 1 3.6 2.0 3.2 3.2 5.92 11.6 1.10 LP LP 11.6 8.4 1.50
Mei 2 3.6 2.0 3.2 3.2 5.92 1.10 1.10 1.10 3.9 2.7 0.48
Jun 1 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.10 1.08 3.8 5.3 0.95
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.05 1.05 3.7 5.2 0.93
Jul 1 3.7 2.0 1.7 1.7 6.02 1.7 0.95 1.05 1.00 3.7 5.6 0.99
Jul 2 3.7 2.0 1.7 1.7 6.02 1.7 0.00 0.95 0.48 1.7 3.7 0.65
Agt 1 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 1.6 0.0 0.29
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.00 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-33


LAPORAN AKHIR

Tabel 5.30 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 2, Mulai Dec-1
Kelompok 4, Mulai Tanam Awal Desember, Pengolahan Lahan 45 Hari, Varietas Unggul
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR padi
Periode C1 C2 C3 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11 12 a 12 b 13 a 13 b 14
Nop 1 3.3 2.0 3.5 3.5 5.61 0.00 0.00 0.00 0.0 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 0.00 0.00 0.0 0.0 0.00
Des 1 2.8 2.0 5.2 5.2 5.08 9.5 LP LP LP LP 9.5 4.3 0.77
Des 2 2.8 2.0 5.2 5.2 5.08 9.5 1.10 LP LP LP 9.5 4.3 0.77
Jan 1 2.6 2.0 4.2 4.2 4.87 9.4 1.10 1.10 LP LP 9.4 5.2 0.93
Jan 2 2.6 2.0 4.2 4.2 4.87 1.1 1.05 1.10 1.10 1.08 2.8 1.7 0.31
Feb 1 3.0 2.0 2.4 2.4 5.31 1.1 1.05 1.05 1.10 1.07 3.2 3.9 0.70
Feb 2 3.0 2.0 2.4 2.4 5.31 2.2 0.95 1.05 1.05 1.02 3.1 4.9 0.87
Mar 1 3.5 2.0 4.6 4.6 5.86 1.1 0.00 0.95 1.05 0.67 2.3 0.8 0.15
Mar 2 3.5 2.0 4.6 4.6 5.86 1.1 0.00 0.95 0.32 1.1 ` 0.0 0.00
Apr 1 3.1 2.0 4.3 4.3 5.45 0.00 0.00 0.0 0.0 0.00
Apr 2 3.1 2.0 4.3 4.3 5.45 8.7 LP LP LP LP 8.7 4.4 0.79
Mei 1 3.6 2.0 3.2 3.2 5.92 9.0 1.10 LP LP LP 9.0 5.8 1.03
Mei 2 3.6 2.0 3.2 3.2 5.92 9.0 1.10 1.10 LP LP 9.0 5.8 1.03
Jun 1 3.5 2.0 2.1 2.1 5.87 1.1 1.05 1.10 1.10 1.08 3.8 4.8 0.86
Jun 2 3.5 2.0 2.1 2.1 5.87 1.1 1.05 1.05 1.10 1.07 3.8 4.7 0.84
Jul 1 3.7 2.0 1.7 1.7 6.02 2.2 0.95 1.05 1.05 1.02 3.7 6.2 1.10
Jul 2 3.7 2.0 1.7 1.7 6.02 1.1 0.00 0.95 1.05 0.67 2.4 3.8 0.68
Agt 1 4.2 2.0 0.4 0.4 6.62 1.1 0.00 0.00 0.95 0.32 0.9 0.4 3.6 0.1 0.66
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.00 0.00 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 45 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-34


LAPORAN AKHIR

Tabel 5.31 Perhitungan Kebutuhan Air Irigasi 2 Pola Tanam Alternatif – 3, Mulai Dec-1
Kelompok 4, Mulai Tanam Awal Desember, Pengolahan Lahan 30 Hari, Varietas Biasa, Varietas Unggul, Palawija
ETo P Re padi Re plwj Eo + P PL WLR ETc padi ETc plwj NFR padi NFR plwj DR padi
Periode C1 C2 C
[mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [mm/hari] [l/det/ha]
1 2 3 4a 4b 5 6 7 8 9 10 11a 11 b 12 a 12 b 13
Nop 1 3.3 2.0 3.5 3.5 5.61 0.00 0.00 0.00 0.0 0.0 0.00
Nop 2 3.3 2.0 3.5 3.5 5.61 0.00 0.00 0.0 0.0 0.00
Des 1 2.8 2.0 5.2 5.2 5.08 12.8 LP LP LP 12.8 7.5 1.34
Des 2 2.8 2.0 5.2 5.2 5.08 12.8 1.10 LP LP 12.8 7.5 1.34
Jan 1 2.6 2.0 4.2 4.2 4.87 1.10 1.10 1.10 2.9 0.7 0.12
Jan 2 2.6 2.0 4.2 4.2 4.87 1.7 1.10 1.10 1.10 2.9 2.3 0.42
Feb 1 3.0 2.0 2.4 2.4 5.31 1.7 1.10 1.10 1.10 3.3 4.6 0.82
Feb 2 3.0 2.0 2.4 2.4 5.31 1.7 1.10 1.10 1.10 3.3 4.6 0.82
Mar 1 3.5 2.0 4.6 4.6 5.86 1.7 1.05 1.10 1.08 3.8 2.8 0.50
Mar 2 3.5 2.0 4.6 4.6 5.86 0.95 1.05 1.00 3.5 0.9 0.16
Apr 1 3.1 2.0 4.3 4.3 5.45 0.00 0.95 0.48 1.5 0.0 0.00
Apr 2 3.1 2.0 4.3 4.3 5.45 0.00 0.00 0.0 0.0 0.00
Mei 1 3.6 2.0 3.2 3.2 5.92 11.6 LP LP LP 11.6 8.4 1.50
Mei 2 3.6 2.0 3.2 3.2 5.92 11.6 1.10 LP LP 11.6 8.4 1.50
Jun 1 3.5 2.0 2.1 2.1 5.87 1.10 1.10 1.10 3.9 3.8 0.67
Jun 2 3.5 2.0 2.1 2.1 5.87 1.7 1.05 1.10 1.08 3.8 5.3 0.95
Jul 1 3.7 2.0 1.7 1.7 6.02 1.7 1.05 1.05 1.05 3.8 5.8 1.03
Jul 2 3.7 2.0 1.7 1.7 6.02 1.7 0.95 1.05 1.00 3.7 5.6 0.99
Agt 1 4.2 2.0 0.4 0.4 6.62 1.7 0.00 0.95 0.48 2.0 5.3 0.94
Agt 2 4.2 2.0 0.4 0.4 6.62 0.00 0.00 0.00 0.0 0.0 1.6 0.0 0.29
Sep 1 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Sep 2 4.2 2.0 0.2 0.2 6.65 0.00 0.00 0.00 0.0 0.0 0.00
Okt 1 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.0 0.0 0.00
Okt 2 3.7 2.0 1.0 1.0 6.08 0.00 0.00 0.00 0.00 0.0 0.00

Catatan : - Pengolahan lahan (Land preparation) : 30 hari

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-35


LAPORAN AKHIR

Hasil rekap perhitungan kebutuhan air irigasi dengan skenario 2 pada tabel sebelumnya, dapat
dilihat pada tabel berikut.
Tabel 5.32 Kebutuhan Air Irigasi 2 Pola Tanam - Lama pengolahan lahan : 30 hari Gudang (liter/s.Ha) (Alternatif-1)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-36


LAPORAN AKHIR

Tabel 5.33 Rekap Kebutuhan Air Irigasi 2 Pola Tanam - Lama pengolahan lahan : 45 hari Gudang (liter/s.Ha)
(Alternatif-2)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-37


LAPORAN AKHIR

Tabel 5.34 Kebutuhan Air Irigasi 3 Pola Tanam - Lama pengolahan lahan : 30 hari, Varietas Biasa Gudang (liter/s.Ha)
(Alternatif-3)

Hasil analisis menunjukkan bahwa untuk 2 pola tanam golongan yang terpilih yaitu golongan 2 (dua
rotasi golongan). Lama pengolahan lahan 45 hari dengan padi unggul, padi unggul, palawija
(alternatif-2), dengan nilai NFR sebesar 1.03 l/dt/ha.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-38


LAPORAN AKHIR

5.3.2 Areal Potensial


Luas areal irigasi atau luas areal yang dapat diairi dihitung berdasarkan keseimbangan air antara
ketersediaan dan kebutuhan air, dengan dua skenario pola tanam. Pertama untuk pola tanam Padi
- Padi - Palawija, dengan beberapa alternatif jadwal mulai tanam. Kedua untuk pola tanam Padi –
Padi, dengan beberapa alternatif jadwal mulai tanam.
Ringkasan hasil perhitungan luas areal irigasi yang dapat dipenuhi sebagai berikut:

 Skenario 1 : 3 pola tanam (Padi – Padi – Palawija) sebesar 90.4 Ha.

 Skenario 2 : dua pola tanam (Padi – Padi) sebesar 115 Ha.


Lahan Daerah Irigasi Gudang memiliki luas sebesar 100 Ha berdasarkan hasil pengukuran topografi.
Berikut adalah hasil analisis areal potensial dengan berbagai alternatif.
A. Skenario 1 (3 Pola Tanam)
Tabel 5.35 Luas Daerah Irigasi 3 Pola Tanam – 30 Hari Gudang (Ha) (Alternatif-1)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-39


LAPORAN AKHIR

Tabel 5.36 Luas Daerah Irigasi 3 Pola Tanam – 45 Hari Gudang (Ha) (Alternatif-2)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-40


LAPORAN AKHIR

Tabel 5.37 Luas Daerah Irigasi 3 Pola Tanam – 30 Hari, Varietas Biasa Gudang (Ha) (Alternatif-3)

Hasil analisis menunjukkan bahwa untuk 3 pola tanam golongan yang terpilih yaitu golongan 2 (dua
rotasi golongan). Lama pengolahan lahan 45 hari dengan padi unggul, padi unggul, palawija
(Alternatif-2). Dan nilai NFR sebesar 1.03 l/dt/ha. Dengan luas areal yang dapat ditanami sebesar
90.4 Ha. Hasil analisis juga dapat dilihat pada Tabel 5.38.
Tabel 5.38 Luas Maksimum Daerah Irigasi Gudang 3 Pola Tanam

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-41


LAPORAN AKHIR

B. Skenario 2 (2 Pola Tanam)


Tabel 5.39 Luas Daerah Irigasi 2 Pola Tanam – 30 Hari Gudang (Ha) (Alternatif-1)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-42


LAPORAN AKHIR

Tabel 5.40 Luas Daerah Irigasi 2 Pola Tanam – 45 Hari Gudang (Ha) (Alternatif-2)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-43


LAPORAN AKHIR

Tabel 5.41 Luas Daerah Irigasi 2 Pola Tanam – 30 Hari, Varietas Biasa Gudang (Ha) (Alternatif-3)

Hasil analisis untuk 2 pola tanam golongan yang terpilih yaitu golongan 2 (2 rotasi golongan). Lama
pengolahan lahan 45 hari dengan padi unggul, padi unggul, palawija (Alternatif-2). Nilai NFR sebesar
1.03 l/dt/ha dan luas areal yang dapat ditanami sebesar 115 Ha. Hasil analisis juga dapat dilihat pada
Tabel 5.42.
Tabel 5.42 Luas Maksimum Daerah Irigasi Gudang 2 Pola Tanam

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-44


LAPORAN AKHIR

5.4 NERACA AIR


Simulasi neraca air merupakan grafik perbandingan antara kebutuhan air dan ketersediaan air dari
hasil sintesis debit NRECA. Neraca air untuk Daerah Irigasi Gudang dapat dilihat pada Gambar 5.7.
Neraca air ini hanya untuk alternatif dan golongan terpilih saja.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-45


LAPORAN AKHIR

Gambar 5.7 Neraca Air D.I. Gudang 3 Pola Tanam

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-46


LAPORAN AKHIR

Gambar 5.8 Neraca Air D.I. Gudang 2 Pola Tanam

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-47


LAPORAN AKHIR

5.5 ANALISIS DEBIT BANJIR


Perhitungan banjir rancangan digunakan model hujan limpasan, salah satu metode empiris yang
digunakan adalah model hidrograf satuan sintetis. Metode ini digunakan untuk mengatasi
permasalahan keterbatasan data banjir yang tercatat dalam periode tertentu. Hidrograf satuan
sintetis dikembangkan dengan mempertimbangkan karakteristik fisik DAS (panjang sungai, luas DAS,
kemiringan rata-rata sungai, koefisien pengaliran) dan hujan daerah rencana.
Untuk menentukan debit banjir rancangan pada DAS dilakukan analisis debit puncak banjir dengan
beberapa metode, antara lain:
 Hidrograf Satuan Sintetik (HSS) Nakayasu,
 Hidrograf Satuan Sintetik (HSS) Snyder,
 Hidrograf Satuan Sintetik (HSS) ITB 1, dan

 Hidrograf Satuan Sintetik (HSS) ITB 2.


Berikut hasil analisis debit banjir untuk DAS Gudang.

5.5.1 Analisis Frekuensi


Analisis frekuensi digunakan untuk mencari periode ulang curah hujan maksimum berdasarkan
curah hujan maksimum yang terjadi dalam satu tahunnya. Hasil dari curah hujan rencana ini akan
digunakan sebagai data untuk menghasilkan debit banjir rancangan. Periode ulang yang akan
dihitung pada masing-masing metode adalah 2, 5, 10, 25, 50, dan 100 tahun. Dalam penentuan
curah hujan rencana dilakukan analisis distribusi frekuensi dengan beberapa metode, yaitu Distribusi
Normal, Log Normal 2 Parameter, Log Normal 3 Parameter, Pearson Tipe III, dan Log Pearson Tipe
III. Berikut adalah hasil analisis frekuensi.
Tabel 5.43 Analisis Frekuensi Stasiun Pangkalpinang

Tabel : Hasil Analisis Frekuensi Curah Hujan Harian Maksimum Tahunan [mm]
Stasiun : Pangkalpinang

Proyek : Irigasi Gudang

Kala Ulang T Distribusi Probabilitas Diprogram Oleh : BaR

(Tahun) t Lognormal Lognormal Log


Normal Gumbel I Pearson III
2 Paramet. 3 Paramet. Pearson III
2 0.0000 109.4 104.8 105.7 104.7 105.5 106.1
5 0.8416 137.1 134.2 135.0 141.7 135.2 135.8
10 1.2816 151.5 152.7 152.8 166.1 153.2 153.4
20 1.6449 163.5 170.0 168.9 189.5 169.3 169.2
25 1.7507 167.0 175.3 173.9 197.0 174.2 174.0
50 2.0537 176.9 191.7 188.8 219.9 188.9 188.3
100 2.3263 185.9 207.7 203.1 242.6 202.9 201.9
500 2.8782 204.0 244.3 235.1 295.2 233.4 231.2
1000 3.0902 211.0 260.0 248.5 317.8 246.0 243.2
Penyimpangan Maksimum 11.22 6.36 6.61 10.28 6.50 7.20
Delta Kritis (Sig. Level 5 %) 34.9 34.9 34.9 34.9 34.9 34.9

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-48


LAPORAN AKHIR

Dari tabel di atas terlihat bahwa perhitungan curah hujan rancangan dengan menggunakan
beberapa metode di atas, memperlihatkan hasil yang tidak jauh berbeda (hampir sama) antara
metode distribusi satu dengan distribusi yang lainnya. Berdasarkan hasil uji Smirnov-Kolmogorov
untuk analisis debit banjir akan menggunakan curah hujan rancangan berdasarkan Log Normal 2
Parameter karena memiliki nilai penyimpangan maksimum paling kecil.

5.5.2 Hujan Efektif DAS Gudang


Hujan efektif dianalisis menggunakan metode koefisien limpasan. Berikut nilai koefisien limpasan
pada DAS Gudang.
Tabel 5.44 Koefisien Pengaliran dan Curah Hujan Rencana Gudang

Koefisien Limpasan C= 0.46


Periode Ulang 2 5 10 25 50 100
Curah Hujan 104.80 134.20 152.70 175.30 191.70 207.70
Hujan Efektif 48.66 62.31 70.90 81.39 89.01 96.44

5.5.3 Distribusi Hujan Jam-jaman DAS Gudang


Dalam melakukan estimasi limpasan permukaan perlu memasukkan nilai dari distribusi hujan pada
periode ulang yang dipilih. Dalam studi ini, distribusi hujan jam-jaman menggunakan metode
Mononobe dan dengan perkiraan durasi hujan selama 6 jam. Distribusi curah hujan jam-jaman dari
hujan rancangan pada DAS Gudang dapat dilihat pada gambar berikut.

Gambar 5.9 Grafik Distribusi Hujan Jam-jaman

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-49


LAPORAN AKHIR

5.5.4 Hidrograf Snyder DAS Gudang


Berikut parameter DAS dan hidrograf satuan metode Snyder dari DAS Gudang.
Tabel 5.45 Parameter Snyder Gudang

Luas DAS (A) = 6.16 km2


Pjg. Sungai (L) = 2.84 km
Lc = 1.41 km
n = 0.3 (0.1-0.38)
Ct = 1.00 (0.75-3.0)
Cp = 0.56 (0.9-1.4)
tp = 1.14 jam
Te = 0.21 jam
Tp = 1.64 jam
qp = 94.02 m3/s
Qp = 0.58 m3/s
W = 6.16
λ = 0.55
a = 0.53
5.5.5 Hidrograf Nakayasu DAS Gudang
Berikut parameter DAS dan hidrograf satuan metode Nakayasu dari DAS Gudang.
Tabel 5.46 Parameter Nakayashu Gudang

INPUT FISIK DAS


2
Luas DAS (A) = 6.16 km
Panjang (L) = 2.84 km

INPUT FISIK NON DAS


Curah Hujan Satuan (R)
Koef. Pengaliran = 0.46

TIME LAG
tg = 0.21 * L07 (L < 15 km)
tg = 0.4 + 0.058 L (L > 15 km)
tg = 0.44 jam

WAKTU PUNCAK
tr = 0.5 x tg sampai dengan tg
tr = 0.22 jam
Tp = tg + 0.8 x tr
Tp = 0.61 jam
T03 = α x tg
T03 = 0.87 jam (α antara 1.5 sampai dengan 3.5)

DEBIT PUNCAK
Qp = C * A * Ro / 3.6 / (0.3 Tp + T0.3 )
Qp = 0.75 m3 /det

2.4
Qa = Qp (t / Tp)
Qd > 0.3 Qp : Qd1 = Qp * 0.3((t-Tp) / T0.3))
0.3 Qp > Qd > 0.09 Qp : Qd2 = Qp * 0.3((t - Tp + 0.5T0.3) / (1.5T0.3))
0.09 Qp > Qd : Qd3 = Qp * 0.3((t - Tp + 1.5 T0.3) / (2 T0.3))

0.3 Qp = 0.22603
0.09 Qp = 0.06781

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-50


LAPORAN AKHIR

5.5.6 Hidrograf ITB I dan II DAS Gudang


Berikut parameter DAS dan hidrograf satuan metode HSS ITB 1 dan ITB 2 dari DAS Gudang.
Tabel 5.47 Unit Hidrograf DAS Gudang HSS ITB 1
Parameter Pembentuk HSS - ITB - 1

I. Karakteristik DAS dan Hujan IV. Tabel Perhitungan HSS - ITB - 1


1 Luas DAS (A) = 6.16 km2
2 Panjang Sungai Utama (L) = 2.84 km HSS Tak Berdimensi HSS Berdimensi
T (jam)
3 Panjang ke titik berat (Lc=0.5L) = 1.41 km t = T/Tp q = Q/Qp A Q = q*Qp V (m3)
4 Tinggi Hujan ( R ) = 1 mm 0 0 0 0 0 0
5 Durasi Hujan (Tr) = 1 jam 1 0.495 0.276 0.068 0.193 347.67
2.02 1.000 1.000 0.322 0.700 1639.82
II. Perhitungan Waktu Puncak (Tp) dan Waktu Dasar (Tb) 2 0.990 1.000 0.010 0.700 50.39
1 Koefisien Waktu (Ct) = 1 3 1.485 0.673 0.414 0.471 2107.5
2 Time Lag (TL) 4 1.980 0.297 0.240 0.208 1222.42
TL = Ct 0.81225 L^0.6 = 1.52 jam 5 2.475 0.111 0.101 0.078 514.48
3 Waktu Puncak (Tp) 6 2.970 0.038 0.037 0.027 187.89
Tp = 2.02 jam 7 3.465 0.012 0.013 0.009 63.72
4 Waktu Dasar (TB) 8 3.960 0.004 0.004 0.003 20.69
TB/TP = 10 Ratio TB/TP 9 4.455 0.001 0.001 0.001 6.54
TB = 20.2 jam 10 4.950 0.000 0.000 0.000 2.03
11 5.446 0.000 0.000 0.000 0.62
III. Debit Puncak (Qp) 12 5.941 0.000 0.000 0.000 0.19
1 Koefisien Puncak (Cp) = 1 13 6.436 0.000 0.000 0.000 0.06
2 Alpha (α) = 2.5 14 6.931 0.000 0.000 0.000 0.02
3 Luas HSS (Numerik) = 1.211 15 7.426 0.000 0.000 0.000 0.01
4 Qp = 0.7 m3/s 16 7.921 0.000 0.000 0.000 0
3
5 Volume Hujan pada DAS (V DAS ) = 6162.246 m 17 8.416 0.000 0.000 0.000 0
6 Volume Unit Hidrograf = 6164.05 m3 18 8.911 0.000 0.000 0.000 0
7 Tinggi Limpasan = 1.000 mm 19 9.406 0.000 0.000 0.000 0
20 9.901 0.000 0.000 0.000 0
21 10.396 0.000 0.000 0.000 0
22 10.891 0.000 0.000 0.000 0
23 11.386 0.000 0.000 0.000 0
24 11.881 0.000 0.000 0.000 0
25 12.376 0.000 0.000 0.000 0
26 12.871 0.000 0.000 0.000 0
27 13.366 0.000 0.000 0.000 0
28 13.861 0.000 0.000 0.000 0
29 14.356 0.000 0.000 0.000 0
30 14.851 0.000 0.000 0.000 0
31 15.347 0.000 0.000 0.000 0
32 15.842 0.000 0.000 0.000 0
33 16.337 0.000 0.000 0.000 0
34 16.832 0.000 0.000 0.000 0
35 17.327 0.000 0.000 0.000 0
36 17.822 0.000 0.000 0.000 0
37 18.317 0.000 0.000 0.000 0
38 18.812 0.000 0.000 0.000 0
39 19.307 0.000 0.000 0.000 0
40 19.802 0.000 0.000 0.000 0
41 20.297 0.000 0.000 0.000 0
42 20.792 0.000 0.000 0.000 0
43 21.287 0.000 0.000 0.000 0
44 21.782 0.000 0.000 0.000 0
45 22.277 0.000 0.000 0.000 0
46 22.772 0.000 0.000 0.000 0
47 23.267 0.000 0.000 0.000 0
48 23.762 0.000 0.000 0.000 0
Luas HSS 1.210914 Vol. H.S. 6164.05
Tinggi Limpasan 1.0000

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-51


LAPORAN AKHIR

Tabel 5.48 Unit Hidrograf DAS Gudang HSS ITB 2


Parameter Pembentuk HSS - ITB - 2

I. Karakteristik DAS dan Hujan IV. Tabel Perhitungan HSS - ITB - 1


1 Luas DAS (A) = 6.16 km2
2 Panjang Sungai Utama (L) = 2.84 km HSS Tak Berdimensi HSS Berdimensi
T (jam)
3 Tinggi Hujan ( R ) = 1 mm t = T/Tp q = Q/Qp A Q = q*Qp V (m3)
4 Durasi Hujan (Tr) = 1 jam 0 0 0 0 0 0
0.70 1.000 1.000 0.500 0.720 907.2
II. Perhitungan Waktu Puncak (Tp) dan Waktu Dasar (Tb) 1.00 1.429 0.796 0.385 0.573 698.31
1 Koefisien Waktu (Ct) = 1 2 2.857 0.436 0.880 0.314 1596.43
2 Time Lag (TL) 3 4.286 0.269 0.504 0.194 913.61
TL = Ct 0.21L0.7 4 5.714 0.177 0.319 0.128 578.86
TL = 0.527 + 0.058L = 0.44 jam 6 8.571 0.087 0.377 0.062 684.31
3 Waktu Puncak (Tp) 6 8.571 0.087 0.000 0.062 0
Tp = 1.6TL = 0.70 jam 7 10.000 0.063 0.107 0.045 193.63
4 Waktu Dasar (TB) 8 11.429 0.047 0.078 0.033 141.72
TB/TP = 10 Ratio TB/TP 9 12.857 0.035 0.058 0.025 105.57
TB = 7 jam 10 14.286 0.027 0.044 0.019 79.79
11 15.714 0.021 0.034 0.015 61.07
III. Debit Puncak (Qp) 12 17.143 0.016 0.026 0.011 47.24
1 Koefisien Puncak (Cp) = 0.8 13 18.571 0.013 0.020 0.009 36.89
2 Alpha (α) = 2.5 14 20.000 0.010 0.016 0.007 29.04
3 Betha (β) = 0.72 15 21.429 0.008 0.013 0.006 23.04
4 Luas HSS (Numerik) = 3.416317 16 22.857 0.006 0.010 0.005 18.4
5 Qp = 0.72 m3/s 17 24.286 0.005 0.008 0.004 14.79
3
6 Volume Hujan pada DAS (V DAS ) = 6198.57 m 18 25.714 0.004 0.007 0.003 11.95
3
7 Volume Unit Hidrograf = 6162.246 m 19 27.143 0.003 0.005 0.002 9.7
8 Tinggi Limpasan = 1.010 mm 20 28.571 0.003 0.004 0.002 7.92
21 30.000 0.002 0.004 0.002 6.49
22 31.429 0.002 0.003 0.001 5.34
23 32.857 0.002 0.002 0.001 4.41
24 34.286 0.001 0.002 0.001 3.66
25 35.714 0.001 0.002 0.001 3.04
26 37.143 0.001 0.001 0.001 2.54
27 38.571 0.001 0.001 0.001 2.13
28 40.000 0.001 0.001 0.000 1.79
29 41.429 0.001 0.001 0.000 1.5
30 42.857 0.000 0.001 0.000 1.27
31 44.286 0.000 0.001 0.000 1.07
32 45.714 0.000 0.001 0.000 0.91
33 47.143 0.000 0.000 0.000 0.77
34 48.571 0.000 0.000 0.000 0.66
35 50.000 0.000 0.000 0.000 0.56
36 51.429 0.000 0.000 0.000 0.48
37 52.857 0.000 0.000 0.000 0.41
38 54.286 0.000 0.000 0.000 0.35
39 55.714 0.000 0.000 0.000 0.3
40 57.143 0.000 0.000 0.000 0.26
41 58.571 0.000 0.000 0.000 0.23
42 60.000 0.000 0.000 0.000 0.19
43 61.429 0.000 0.000 0.000 0.17
44 62.857 0.000 0.000 0.000 0.15
45 64.286 0.000 0.000 0.000 0.13
46 65.714 0.000 0.000 0.000 0.11
47 67.143 0.000 0.000 0.000 0.1
48 68.571 0.000 0.000 0.000 0.08
Luas HSS 3.416317 Vol. H.S. 6198.57
Tinggi Limpasan 1.0000

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-52


LAPORAN AKHIR

5.5.7 Rekap Debit Banjir Rancangan DAS Gudang


Berdasarkan hasil perhitungan hidrograf sintetik pada sub-bab sebelumnya, maka rekap debit banjir
rancangan adalah sebagai berikut.
Tabel 5.49 Rekap Debit Banjir Gudang

Periode Ulang HSS - ITB


HSS - SNYDER HSS - NAKAYASU
tahun 1 2
2 24.2 25.4 24.6 20.4
5 31.0 32.5 31.4 26.1
10 35.3 37.0 35.8 29.7
25 40.5 42.4 41.1 34.1
50 44.3 46.4 44.9 37.2
100 48.0 50.3 48.7 40.4

Metode yang akan dipilih adalah metode Nakayashu karena memiliki nilai Tp yang paling cepat (1
jam), disamping itu metode ini juga telah dikembangkan untuk kondisi geografis di Indonesia dan
telah dilakukan pengujian untuk beberapa wilayah di Indonesia.

Gambar 5.10 Hidrograf DAS Gudang Periode Ulang 2 Tahun

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-53


LAPORAN AKHIR

Gambar 5.11 Hidrograf DAS Gudang Periode Ulang 5 Tahun

Gambar 5.12 Hidrograf DAS Gudang Periode Ulang 10 Tahun

Gambar 5.13 Hidrograf DAS Gudang Periode Ulang 25 Tahun

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-54


LAPORAN AKHIR

Gambar 5.14 Hidrograf DAS Gudang Periode Ulang 50 Tahun

Gambar 5.15 Hidrograf DAS Gudang Periode Ulang 100 Tahun

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5-55


LAPORAN AKHIR

BAB 6 HASIL PERENCANAAN

6.1 PERENCANAAN JARINGAN IRIGASI


6.1.1 DAS DI Gudang
Di dalam menentukan DAS terlebih dahulu harus diketahui titik outlet dari DAS tersebut. Data yang
digunakan pada awal analisis ini adalah peta Rupa Bumi Indonesia (RBI) dan data DEM. Pada analisis
ini titik outlet ditentukan pada kontur +34 mdpl dimana areal sawah yang akan diairi rata-rata elevasi
maksimalnya berada pada elevasi tersebut. Kontur ini kemudian di plot pada peta RBI untuk
mendapatkan wilayah dengan batas kontur tersebut.
Titik outlet tersebut kemudian diinputkan sebagai sebuah titik untuk dijadikan patokan di dalam
pembentukan DAS. Dengan melalui tahapan analisis spasial maka akan didapatkan bentuk DAS yang
akan digunakan baik untuk menghitung debit andal maupun debit banjir.

Titik Outlet DAS Gudang

Gambar 6.1 Titik Outlet DAS Gudang

6.1.2 Areal Sawah pada Citra Satelit


Kenampakan wilayah DI Gudang pada citra satelit menunjukkan sebagian besar wilayah terdiri dari
sawah. Dengan sebagian kecil wilayah terdapat kebun, lahan kosong, dan semak belukar.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-1


LAPORAN AKHIR

Gambar 6.2 Hasil DAS

Gambar 6.3 Gambar Zoom In Nomor 1 (Kebun)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-2


LAPORAN AKHIR

Gambar 6.4 Gambar Zoom In Nomor 2 (Lahan Kosong)

Gambar 6.5 Gambar Zoom In Nomor 3 (Sawah)

6.1.3 Petak Tersier


Ukuran petak bergantung pada besarnya biaya pelaksanaan jaringan irigasi dan pembuang (primer,
sekunder, tersier, dan kuarter) serta biaya operasi dan pemeliharaan jaringan. Di petak yang
berukuran kecil, efisiensi irigasi akan menjadi lebih tinggi karena:

 Diperlukan lebih sedikit titik-titik pembagian air.


 Saluran-saluran yang lebih pendek menyebabkan kehilangan air yang lebih sedikit.
 Lebih sedikit petani yang terlibat, jadi kerja sama lebih baik.
 Pengaturan (air) yang lebih baik sesuai dengan kondisi tanaman.
 Perencanaan lebih fleksibel sehubungan dengan batas-batas desa.
Bentuk optimal suatu petak tersier bergantung pada biaya minimum pembuatan saluran, jalan dan
boks bagi. Apabila semua saluran kuarter diberi air dari satu saluran primer, maka panjang total jalan

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-3


LAPORAN AKHIR

dan saluran menjadi minimum. Dengan dua saluran primer untuk areal yang sama, maka panjang
total jalan dan saluran akan bertambah.
Berikut adalah kriteria umum untuk pengembangan :
 Ukuran petak tersier : 50 - 100 ha
 Ukuran petak kuarter : 8 - 15 ha
 Panjang saluran tersier : < 1500 m
 Panjang saluran kuarter : < 500 m
 Jarak antara saluran kuarter & pembuang: < 300 m
Beberapa faktor pertimbangan untuk langkah penetapan petak sawah berdasarkan kondisi lapangan
di daerah irigasi Gudang sebagai berikut.
1. Penentuan petak-petak sawah ditentukan berdasarkan gambar peta administrasi irigasi
Kabupaten Bangka Selatan yang telah di overlay dengan areal sawah hasil pengukuran
topografi.
2. Petak sawah irigasi ada di sebelah kiri Sungai Babuar.
3. DI Gudang dibagi menjadi 5 petak tersier (G1ka (39.47Ha), G2Ka (15.53Ha), G2Ki (2.54Ha),
G3Ka (31.5Ha) dan G3Ki (10.9Ha)), didasarkan pada pengembangan tahap 1 seluas 100 Ha.
4. Pada area dengan kemiringan lahan 0.25 – 1 %, tidak ada petak sawah karena kemiringan
lahan yang curam.
5. Terdapat beberapa areal sawah yang tidak dapat terairi karena wilayahnya cukup tinggi,
terutama pada areal petak sawah kiri (G2Ki dan G3Ki).
Hasil pembagian lahan untuk petak-petak sawah pada wilayah Gudang dapat dilihat pada gambar di
bawah ini.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-4


LAPORAN AKHIR

Gambar 6.6 Rencana Pembagian Petak Sawah DI Gudang

6.1.4 Penentuan Trase Saluran


Setelah menentukan areal sawah pada wilayah studi maka selanjutnya ada menentukan trase
saluran untuk mengairi sawah tersebut mulai dari titik bendung rencana. Adapun data topografi
yang diperlukan atau harus dibuat adalah :
a) Peta topografi dengan garis-garis ketinggian dan tata letak jaringan irigasi dengan skala 1 :
25.000 dan 1 : 5.000;
b) Peta situasi trase saluran berskala 1 : 2000 dengan garis-garis ketinggian pada interval 0,5 m
untuk daerah datar dan 1,0 m untuk daerah berbukit-bukit;
c) Profil memanjang pada skala horisontal 1 : 2000 dan skala vertikal 1 : 200 (atau skala 1 : 100
untuk saluran berkapasitas kecil bilamana diperlukan);

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-5


LAPORAN AKHIR

d) Potongan melintang pada skala horisontal dan vertikal 1 : 200 (atau 1 : 100 untuk saluran-
saluran berkapasitas kecil) dengan interval 50 m untuk bagian lurus dan interval 25 m pada
bagian tikungan;
e) Peta lokasi titik tetap/benchmark, termasuk deskripsi benchmark.
Penggunaan peta-peta foto udara dan foto (ortofoto dan peta garis) yang dilengkapi dengan garis
ketinggian akan sangat besar artinya untuk perencanaan tata letak dari trase saluran. Peta-peta
teristris masih diperlukan sebagai peta baku/peta dasar. Kelebihan foto citra satelit dapat diperoleh
secara luas dan beberapa jenis foto landsat mempunyai karakteristik khusus yang berbeda, sehingga
banyak informasi lain yang dapat diperoleh antara lain dengan program/software yang dapat
memproses garis kontur secara digital. Foto-foto satelit ini bisa dipakai untuk studi awal, studi
identifikasi dan studi pengenalan. Kelemahan foto citra satelit tidak stereometris sehingga aspek
beda tinggi kurang dapat diperoleh informasi detailnya tidak seperti pengukuran teristris, sedangkan
dalam perencanaan irigasi presisi dalam pengukuran beda tinggi sangat penting. Meskipun demikian
banyak informasi lain yang dapat dipakai sebagai pelengkap perencanaan jaringan irigasi antara lain
sebagai cross check untuk perencanaan jaringan irigasi. Data pengukuran topografi dan saluran yang
disebutkan di atas merupakan data akhir untuk perencanaan detail saluran.
Beberapa poin penting yang harus diperhatikan dalam merencanakan jalur trase saluran ialah
sebagai berikut.
1. Trase saluran pembawa primer direncanakan mengikuti jalur eksisting agar memudahkan
dalam pelaksanaan. Trase saluran pembawa primer akan bersebelahan dengan trase
saluran eksisting milik Dinas Pertanian.
2. Saluran pembawa primer direncanakan di sisi kiri Sungai Babuar. Hal ini diputuskan setelah
melihat kontur di sisi kanan sungai yang lebih rendah, sehingga saluran primer di sepanjang
sungai Babuar yang berada di posisi lebih tinggi nantinya bisa mengalirkan air dengan
gravitasi ke saluran kuarter.
3. Jalan inspeksi saluran irigasi akan berada di antara saluran eksisting Dinas Pertanian dan
saluran irigasi.
4. Saluran kuarter akan memanfaatkan saluran eksisting Dinas Pertanian, yang akan langsung
mengairi petak kuarter. Saluran kuarter akan ada di setiap batas antar petak kuarter, dan
masing-masing akan berada di elevasi tertinggi dalam petak kuarter tersebut supaya bisa
mengaliri petak kuarter dengan gravitasi.
5. Saluran pembuang berada di sisi kanan petak sawah, yang akan memanfaatkan Sungai
Babuar sebagai Saluran Pembuang. Sisa air berlebih dari petak sawah akan mengalir
mengikuti gravitasi ke saluran pembuang di sisi kanan, kemudian air akan mengalir di
sepanjang saluran pembuang ke elevasi yang lebih rendah hingga dibuang kembali ke
sungai.
Trase saluran ditunjukan dengan garis berwarna merah, sementara warna biru muda adalah trase
saluran pembuang. Warna hitam adalah jalan eksisting. Penentuan saluran kuarter mengikuti
pembagian petak sawah. Berikut adalah arah trase saluran irigasinya.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-6


LAPORAN AKHIR

Gambar 6.7 Trase Saluran

6.2 OPTIMASI SKENARIO PENGAIRAN AREAL SAWAH


Perencanaan areal lahan sawah DI Gudang memiliki 2 skenario pengairan, yaitu 3 pola tanam padi-
padi-palawija dan 2 pola tanam padi-padi. Skenario terpilih diharapkan mampu memberikan pilihan
mengenai skenario yang paling optimum dari segi luasan areal sawah yang dapat terairi.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-7


LAPORAN AKHIR

6.2.1 Skenario 1
Pengembangan areal sawah untuk skenario 1 terdapat di sebelah kiri aliran Sungai Babuar. Sumber
air memanfaatkan rencana bendung DI Gudang, dengan total rencana lahan yang akan diairi seluas
90.4 Ha. Penentuan petak-petak sawah didasarkan pada ketentuan yang telah dijelaskan pada
Subbab 6.1.3 Petak . Pada skenario 1, panjang saluran tersier adalah 4.3 Km dengan jumlah
bangunan bagi sadap sebanyak 2 unit dan boks kuarter sebanyak 1 unit.
Kondisi lahan pada skenario 1 cenderung pipih memanjang dan mengairi areal irigasi sisi kiri.
Kelebihan skenario 1 adalah 3 pola tanam padi-padi-palawija, sehingga dari segi kelayakan ekonomi
lebih menguntungkan petani. Sedangkan kelemahan skenario 1 adalah luasan areal lahan yang kecil
sebesar 90.4 Ha, dimana masih di bawah target pengembangan 100 Ha. Sehingga tidak semua area
dapat terairi, terutama area petak sawah di sisi kiri. Disamping itu, adanya 2 x rotasi golongan pada
scenario ini menyebabkan perlunya pengaturan air di boks tersier. Berikut adalah skema trase serta
petak sawah untuk skenario 1.

Gambar 6.8 Skematisasi Petak Sawah Skenario 1

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-8


LAPORAN AKHIR

6.2.2 Skenario 2
Pengembangan areal sawah untuk skenario 2 terdapat di sebelah kiri aliran Sungai Babuar. Sumber
air memanfaatkan rencana bendung DI Gudang dengan 2 pola tanam padi-padi, dengan total
rencana lahan yang akan diairi seluas 115 Ha. Penentuan petak-petak sawah didasarkan pada
ketentuan yang telah dijelaskan pada Subbab 6.1.3 Petak . Pada skenario 2, panjang saluran tersier
adalah 4.3 Km dengan jumlah bangunan bagi sadap sebanyak 2 unit dan boks kuarter sebanyak 1
unit.
Berdasarkan kondisi topografi lahan pada skenario 2 dapat mencapai target pengembangan wilayah
irigasi seluas 97.5 Ha, dengan mengairi areal irigasi sisi kanan dan kiri. Kelemahan pada skenario 2
adalah 2 pola tanam padi-padi, sehingga dari segi kelayakan ekonomi kurang menguntungkan
petani. Berikut adalah skema trase serta petak sawah untuk skenario 2.

Gambar 6.9 Skematisasi Petak Sawah Skenario 2

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-9


LAPORAN AKHIR

6.3 PERENCANAAN BANGUNAN UTAMA


Perencanaan bangunan utama meliputi bendung; intake; kantong lumpur; saluran irigasi yang terdiri
dari saluran primer dan kuarter; dan bangunan pelengkap. Berikut yang perlu dipertimbangkan
dalam tata letak bangunan irigasi :

6.3.1 Bendung
Pada studi ini bendung eksisting tidak dapat digunakan, karena elevasi mercu terlalu rendah
sehingga tidak dapat mengairi sawah pada area hulu (sekitar 200 m dari lokasi bendung, pada elevasi
lahan +33.00m). Oleh sebab itu, lokasi rencana bendung akan digeser ke arah hulu sekitar 20 m
dari bendung eksisting. Perencanaan bendung baru didasarkan pada pertimbangkan sebagai
berikut.
1) Secara topografi lokasi bendung berada pada ruas yang sempit dan tidak terlalu dalam.
2) Lokasi rencana bendung berada pada belokan di bagian tikungan luar dan terdapat bagian
sungai yang lurus di hulu bendungnya. Disamping itu, morfologi sungai di lokasi rencana
bendung kemiringan dasarnya relatif tetap sepanjang ruas tertentu. Sehingga sudah
memenuhi syarat kriteria perencanaan bendung.
3) Tinggi mercu bendung ditentukan agar dapat mengairi seluruh petak sawah.
4) Tinggi mercu bendung ditentukan agar dapat mengairi petak sawah sampai ke elevasi sawah
di hilir.
5) Bendung dilengkapi dengan trash log di bagian hulu pintu pembilas, yang berfungsi untuk
menghindari sampah (floating debris) masuk ke jaringan irigasi.
6) Luas DAS di lokasi bendung sudah mempertimbangkan luas layanan DI Gudang sebesar
198 Ha, yang terkait dengan ketersediaan debit andalan dan debit banjir yang mungkin
terjadi menghantam bendung.
7) Geoteknik dipilih dasar sungai yang mempunyai daya dukung kuat, stratigrafi lapisan batuan
miring ke arah hulu, tidak ada sesar aktif, tidak ada erosi buluh, dan dasar sungai hilir
bendung tahan terhadap gerusan air. Disamping itu diusahakan keadaan batuan tebing
kanan dan kiri bendung cukup kuat dan stabil seta relatif tidak terdapat bocoran samping.
Berikut rencana posisi bendung DI Gudang.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-10


LAPORAN AKHIR

Gambar 6.10 Posisi Bendung Baru terhadap Bendung Eksisting

6.3.1.1 Penentuan Elevasi Mercu Bendung


Rencana bendung akan berada di Sungai Babuar dan direncakan pada elevasi mercu +34.0 mdpl
untuk mengairi areal sawah D.I. Gudang. Pengembangan skema pada studi potensi irigasi dimulai
dari penentuan lokasi bangunan-bangunan tersebut di atas sehingga bisa mengairi areal lahan
sawah paling hilir pada elevasi +17.0 mdpl. Dengan melihat panjang rencana saluran ±4.3km dengan
kemiringan variasi 0.02% - 0.39% maka kehilangan energi didapat ±12.46 m. Agar air yang bermula
dari titik bendung dapat mengairi areal sawah yang paling ujung maka didapatkan perkiraan elevasi
mercu bendung ada pada elevasi + 34.0 mdpl.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-11


LAPORAN AKHIR

6.3.1.2 Dimensi Bendung


Lebar bendung (B) adalah jarak antara tembok pangkal di sebelah kiri dan kanan. Lebar efektif
bendung (Be) adalah lebar bendung akibat adanya pengaruh pilar. Lebar pembilas yang sebenarnya
(dengan bagian depan terbuka) sebaiknya diambil 80% dari lebar rencana bendung. Tinggi tembok
pada bendung dirancang memiliki tinggi jagaan sebesar 1 meter untuk memastikan keamanan
struktur dari debit banjir 25 tahunan.
Bentuk mercu bendung pada bagian hulu adalah dinding tegak, sementara pada hilir bendung
dihitung menurut bentuk bulat dengan radius 1 m. Hasil perhitungan dari tinggi muka air di atas
bendung dapat dilihat pada tabel berikut.
Tabel 6.1 Tinggi Muka Air di Atas Bendung
H1 P+H1 Ha Hd Be Q WS El
No H1/Hd P/Hd P/H1 H1/r C0 C1 C2 Cd
(m) (m) (m) (m) (m) (m3/s) (m)
1 0.80 2.80 0.01 0.79 1.01 2.53 2.50 0.80 1.05 0.99 1.000 1.04 6.82 8.65 34.8
2 0.90 2.90 0.01 0.89 1.02 2.26 2.22 0.90 1.05 0.99 1.000 1.04 6.80 10.29 34.9
3 1.00 3.00 0.02 0.98 1.02 2.05 2.00 1.00 1.17 0.99 1.000 1.16 6.78 13.38 35.0
4 1.20 3.20 0.03 1.17 1.03 1.71 1.67 1.20 1.17 0.99 1.000 1.16 6.74 17.48 35.2
5 1.40 3.40 0.05 1.35 1.03 1.48 1.43 1.40 1.17 0.97 1.002 1.14 6.69 21.48 35.4
6 1.60 3.60 0.06 1.54 1.04 1.30 1.25 1.60 1.17 0.97 1.002 1.14 6.65 26.07 35.6
7 1.80 3.80 0.08 1.72 1.04 1.16 1.11 1.80 1.17 0.97 1.002 1.14 6.60 30.90 35.8
8 2.08 4.08 0.13 1.95 1.07 1.03 0.96 2.08 1.33 0.95 1.004 1.27 6.54 42.40 36.1
9 2.40 4.40 0.17 2.23 1.08 0.90 0.83 2.40 1.33 0.95 1.004 1.27 6.47 52.02 36.4
10 2.60 4.60 0.20 2.40 1.08 0.83 0.77 2.60 1.33 0.95 1.004 1.27 6.43 58.25 36.6
Keterangan:
Hd = tinggi muka air banjir di atas bendung
C = koefisien debit
Be = lebar efektif bendung
Q = debit rencana, Q100th
El MA = elevasi muka air banjir di atas bendung

Gambar 6.11 Rating Curve pada Bendung

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-12


LAPORAN AKHIR

Dimensi bendung direncanakan dengan debit banjir kala ulang 25 tahun sebesar 42.4 m3/s. Bendung
didesain dengan tinggi 2 m, maka elevasi puncak bendung pada ketinggian +34.0 mdpl. Dari Tabel
6.1, tinggi muka air banjir di atas bendung sebesar 2.08 m pada elevasi +36.10 mdpl. Weir wing wall
akan berada pada elevasi +37.1 mdpl untuk mengakomodasi freeboard sebesar 1 m dari muka air
banjir. Berdasarkan hasil perhitungan bendung di atas maka dimensi bendung DI Gudang adalah
sebagai berikut:
Tabel 6.2 Resume Dimensi Bendung

Parameter Metric Unit


Design Flood Flow (Q25) = 42.40 m3/s
Lebar mercu = 7 m
Lebar pembilas = 1.00 m
Tinggi mercu = 2.00 m
Elevasi dasar mercu = +32.00 m
Elevasi mercu = +34.00 m
Elevasi atas retwall = +37.10 m
Hretwall = 5.10 m

6.3.1.3 Peredam Energi


Peredam energi bertujuan untuk menghancurkan energi yang melimpah melewati mercu bendung.
Aliran superkritis akibat adanya bendung diubah menjadi aliran subkritis di hilir bendung
menggunakan peredam energi. Peredam energi direncanakan menggunakan tipe MDO, karena tipe
ini cocok untuk morfologi saluran hilir dengan material bawaan sungai berupa pasir dan batu-batu
kecil. Kolam olak tipe MDO terdiri dari lantai datar, di ujung hilir lantai dilengkapi dengan endsill
dengan rip rap. Sebelum mendesain tipe ini perlu ditentukan terlebih dahulu nilai parameter.
a) Tipe mercu bangunan terjun harus bentuk bulat dengan satu atau dua jari-jari.
b) Permukaan tubuh bangunan terjun bagian hilir dibuat miring dengan perbandingan
kemiringan 1 m atau lebih tegak dari kemiringan 1:1.
c) Tubuh bangunan terjun dan peredam energi harus dilapisi dengan lapisan tahan aus.
d) Elevasi dasar sungai atau saluran di hilir tubuh bangunan terjun yang ditentukan, dengan
memperhitungkan kemungkinan terjadinya degradasi dasar sungai.
e) Elevasi muka air hilir bangunan terjun yang dihitung, berdasarkan elevasi dasar sungai
dengan kemungkinan perubahan geometri badan sungai.
Selain parameter di atas kriteria desain yang disyaratkan yaitu:
a) tinggi air udik bangunan terjun dibatasi maksimum 4 meter,
b) tinggi pembangunan terjunan (dihitung dari elevasi mercu bangunan terjun sampai dengan
elevasi dasar sungai di hilir) maksimum 10 meter, dalam hal tinggi air udik bangunan terjun
lebih dari 4 meter dan atau tinggi pembangunan terjunan lebih dari 10 meter tata cara
peredam energi tipe MDO ini masih dapat digunakan asalkan dimensinya perlu diuji dengan
model test.
Penggunaan tipe MDO dapat juga dimodifikasi dan dilakukan pengembangan pemakaiannya:

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-13


LAPORAN AKHIR

a) dimensi hidraulik peredam energi tipe MDO dapat diterapkan di hilir tubuh bangunan terjun
di bidang miring lebih tegak dari perbandingan 1:1;
b) tubuh bangunan terjun dengan peredam energi tipe MDO dapat dilengkapi dengan
pembilas sedimen tipe undersluice tanpa mengubah dimensi hidraulik peredam ebergi tipe
MDO.
Data awal yang harus ditentukan terlebih dahulu adalah:
a) debit desain banjir dengan memperhitungkan tingkat keamanan bangunan air terhadap
bahaya banjir,
b) debit desain penggerusan, dapat diambil sama dengan debit alur penuh,
c) lengkung debit sungai di hilir rencana bangunan terjun berdasarkan data geometri-
hidrometri-hidraulik morfologi sungai.
Grafik – grafik yang dipakai dalam desain hidraulik bangunan terjun dengan kelengkapannya
mengacu dari lampiran A (RSNI T-04-2002).
Berikut hasil desain kolam olak dengan tipe MDO.
Tabel 6.3 Hasil Perencanaan Kolam Olak

Tinggi terjun Z 1.01 m


Kedalaman lantai peredam energi Ds 3.00 m
Panjang lantai dasar peredam energi Ls 3.00 m
Tinggi ambang hilir a 0.50 m
Lebar ambang hilir b 1.00 m
Elevasi Dekzerk
Tembok pangkal udik EiDzu 37.00 m
Tembok pangkal hilir EiDzi 35.99 m
Panjang tembok sayap hilir Lsi 4.00 m
Panjang tembok pangkal bangunan terjun di udik Lpu 2.50 m
Panjang tembok sayap udik Lsu 3.00 m

Berikut langkah perhitungan dan penentuan dimensi hidraulik tubuh bangunan terjun dan peredam
energinya.
1) Menghitung debit desain persatuan lebar pelimpah, nilai Q menggunakan debit untuk
bahaya banjir).
q = Q/Bp = 42.4 / 7 = 6.071 m3/s
2) Menentukan dimensi radius mercu bangunan terjun = r : 1.00 m ≤ r ≤ 3.00m. Pada desain
menggunakan radius mercu sebesar 1 m.
3) Untuk nilai radius mercu bangunan terjun tersebut; periksa kavitasi di bidang hilir tubuh
bangunan terjun dengan bantuan grafik MDO-1a. Jika tekanan berada di daerah positif
pemilihan radius mercu bangunan terjun; diijinkan. Untuk muka air udik diperoleh dari grafik

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-14


LAPORAN AKHIR

MDO-1. Maka dengan radius 1 m dan muka air udik sebesar 2 m diperoleh desain radius
diijinkan.

Gambar 6.12 Grafik MDO – 1a Penentuan Bahay Kavitasi di Hilir Mercu Bangunan Terjun

4) Menentukan tinggi dan elevasi muka air di udik bangunan. Dimana Hudp dan Hudf dihitung
dengan grafik MDO-1.
El = M + Hudf = 34.0 + 2 = +36.0 m

Gambar 6.13 MDO – 1 Pengaliran Melalui Mercu Bangunan Terjun

5) Menghitung tinggi terjun. Hidf didapat dari grafik lengkung debit saluran.
Z = Hudf - Hidf = 2 – 0.991 = 1.009 m
Berikut perhitungan Hidf dengan rumus manning.

6) Menghitung parameter energi (E).

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-15


LAPORAN AKHIR

Edp = qdp / (g × Zdp3)1/2 = 6.071 / (9.8 × 1.0093)1/2 = 1.908 m


7) Menghitung kedalaman peredam energi (Ds). D1/D2 dicari dengan grafik MDO-2.
Ds = (Ds) (D1/D2) = 1.5 x 1.55 = 2.33 m ≈ 3.0 m

Gambar 6.14 Grafik MDO – 2 Penentuan Kedalaman Lantai Peredam Energi

8) Menghitung panjang lantai dasar peredam energi. Nilai Ls/Ds dicari dengan grafik MDO-3.
Ls = (Ds) (Ls/Ds) = (1.5) (1.95) = 2.93 m ≈ 3.0 m

Gambar 6.15 Gambar MDO – 3 Penentuan Panjang Lantai Peredam Energi

9) Menghitung tinggi ambang hilir.


a = (0.2 – 0.3) Ds = 0.2 × 2.33 = 0.47 m ≈ 0.5 m
10) Menghitung lebar ambang hilir.
b = 2 × a = 2 × 0.5 = 1.0 m
11) Menghitung Elevasi Dekzerk tembok pangkal bangunan terjun.
Fb diambil : 1.00 meter ≤ Fb ≤ 1.5 meter
EiDzu = M + Hudf + Fb = 34.0 + 2 + 1 = +37.0 m

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-16


LAPORAN AKHIR

EiDzi = M + Hidf + Fb = 34.0 + 0.991 + 1 = +35.99 m ≈ +36.0 m


12) Menghitung panjang tembok sayap hilir (Lsi) dihitung dari ujung hilir lantai peredam energi
diambil:
Ls ≤ Lsi ≤ 1.5Ls = (Lsi = 4.0 m)
13) Menghitung panjang tembok pangkal bangunan terjun di bagian udik (Lpu) bagian yang
tegak.
0.5Ls ≤ Lpu ≤ Ls = (Lpu = 2.5 m)
14) Menghitung panjang tembok sayap udik dengan tebing saluran yang tidak jauh dari sisi
tembok pangkal bangunan terjun, ujung tembok sayap udik dilengkungkan masuk ke tebing
dengan panjang total tembok pangkal bangunan terjun ditambah sayap udik.
0.5Ls ≤ Lsu ≤ 1.5Ls = (Lsu = 3 m)
6.3.1.4 Saluran Pembilas
Perhitungan saluran pembilas di bendung mengacu ke Kriteria Perencanaan Irigasi – 02, lebar
saluran pembilas termasuk pilar nilainya diantara 1/6 – 1/10 dari lebar bersih bendung. Berikut
rumus yang digunakan dalam menentukan lebar saluran pembilas.

𝐵𝑝𝑒𝑚𝑏𝑖𝑙𝑎𝑠 = (1⁄6) 𝑥 𝐵𝑏𝑒𝑛𝑑𝑢𝑛𝑔 = (1⁄6) 𝑥 7 = 1.2 𝑚

𝐵𝑝𝑒𝑚𝑏𝑖𝑙𝑎𝑠 = (60 %) 𝑥 𝐵𝑖𝑛𝑡𝑎𝑘𝑒 = 60% 𝑥 0.4 = 0.24 𝑚

Berdasarkan perhitungan di atas, lebar saluran pembilas (pintu pembilas dan pilar) nilainya diantara
0.24 - 1.2 m. Pada studi ini, digunakan 1 unit pintu pembilas dengan lebar saluran pembilas diambil
1 m dan lebar pilar adalah 0.5 m.

6.3.2 Bangunan Pengambilan (Intake)


Bangunan pengambilan sebaiknya dibuat sedekat mungkin dengan pembilas dan as bendung. Lebih
disukai jika pengambilan ditempatkan di ujung tikungan luar sungai atau pada ruas luar guna
memperkecil masuknya sedimen. Pada studi ini, posisi intake tegak lurus (90o) terhadap bendung
mengikuti topografi lahan dan trase saluran primer. Berikut rencana posisi intake DI Gudang.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-17


LAPORAN AKHIR

Gambar 6.16 Bangunan Utama

Pada studi ini, pintu yang direncanakan adalah pintu sorong dari baja. Debit rencana pada intake
adalah 0.159 m3/s (Qintake = A x DRPrimer). Berikut rincian nilai untuk mencari debit rencana.
Qintake = 0.159 m3/s.
A = 100 Ha
NFR = 1.03 lt/s/ha
DRPrimer = NFR/(80% x 90% x 90%)/1000 = 0.00159 m3/s/ha

Berikut dimensi pintu intake:


bpintu = 0.7 m
apintu = 0.17 m
npintu = 1 unit
Elevasi ambang intake = +33.09 mdpl
Bangunan intake direncanakan berdasarkan pedoman pada KP-02.

𝑄 = 𝜇. 𝑏. 𝑎√2𝑔𝑧
Dimana:
μ = koefisien debit (0.8)
a = tinggi bukaan pintu (m)
b = lebar bukaan pintu (m)
z = perbedaan antara muka air hulu dan hilir (m)
Tabel 6.4 Hasil Perhitungan Dimensi Intake

Berdasarkan hasil perhitungan pada tabel di atas, maka dimensi pintu yang akan digunakan adalah
B = 0.7 m dan H = 0.7 m.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-18


LAPORAN AKHIR

Gambar 6.17 Ilustrasi Penampang Melintang Intake

6.3.3 Kantong Lumpur


Dimensi-dimensi L (panjang) dan B (lebar) kantong lumpur dapat diturunkan dari LAMPIRAN A. C.VI.4
Kolam Pengendap Lumpur. Partikel yang masuk ke kolam pada A, dengan kecepatan endap partikel
w dan kecepatan air v harus mencapai dasar pada C. Ini berakibat bahwa, partikel, selama waktu
(H/w) yang diperlukan untuk mencapai dasar, akan berjalan (berpindah) secara horisontal sepanjang
jarak L dalam waktu L/v.
A v
v
w H H
w C

L B

Gambar 6.18 Skema kantong lumpur

H L Q
Jadi: = , dengan v =
w v HB
di mana:
H = kedalaman aliran saluran, m
w = kecepatan endap partikel sedimen, m/dt
L = panjang kantong lumpur, m

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-19


LAPORAN AKHIR

v = kecepatan aliran air, m/dt


Q = debit saluran, m3/dt
B = lebar kantong lumpur, m

Q
ini menghasilkan: LB =
W
Karena sangat sederhana, rumus ini dapat dipakai untuk membuat perkiraan awal dimensi-dimensi
tersebut. Untuk perencanaan yang lebih detail, harus dipakai faktor koreksi guna menyelaraskan
faktor-faktor yang mengganggu, seperti:
 Turbulensi air.

 Pengendapan yang terhalang.

 Bahan layang sangat banyak.

Velikanov menganjurkan faktor-faktor koreksi dalam rumus berikut:

Q 2 v ( H 0.5  0.2) 2
LB =   
w 7.51 w H
Di mana:
L = panjang kantong lumpur, m
B = lebar kantong lumpur, m
Q = debit saluran, m3/dt
w = kecepatan endap partikel sedimen, m/dt

 = koefisiensi pembagian/distribusi Gauss


 adalah fungsi D/T, di mana D = jumlah sedimen yang diendapkan dan T = jumlah sedimen yang
diangkut
 = 0 untuk D/T = 0,5 ;  = 1,2 untuk D/T = 0,95 dan

 = 1,55 untuk D/T = 0,98


v = kecepatan rata-rata aliran, m/dt
H = kedalaman aliran air di saluran, m
Dimensi kantong sebaiknya juga sesuai dengan kaidah bahwa L/B > 8, untuk mencegah agar aliran
tidak “meander” di dalam kantong.
Data :

 Q= 0.159 m³/s
 Kedalam tampungan sedimen, H = 1 m

 HNWL = 0.32 m (tinggi muka air di atas area pengendapan)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-20


LAPORAN AKHIR

 Kedalaman Kantong Lumpur, H = 1.5 m (termasuk tampungan sedimen)

 Kecepatan aliran Kantong Lumpur, v = 0.3 m/s


 Diameter butiran sedimen, d50 = 0.3 mm (asumsi)
 Kecepatan jatuh sedimen, w = 0.045 m/s (lihat Tabel berikut)
Particle Diameter (mm) 0.3 0.4 0.5 0.7 1
Theoretical Settling Velocity (mm/s) 45 60 70 95 120
Theoretical Settling Velocity (m/s) 0.045 0.06 0.07 0.095 0.12

Hasil Perhitungan:
Berikut perhitungan dimensi kantong lumpur dengan metode koresi velikanov :

f(1) = 1.2
koreksi velikanov = 0.534191
L/B = 13.793 ≈ 8.5 (OK)
B = Q*koreksi / (L x w)
B= 0.370 m ≈ 0.7 m
L= 5.102 m ≈ 6.0 m
6.3.3.1 Pelimpah Samping
Pelimpah samping terletak di hilir Kantong Lumpur sebagai bangunan kontrol yang melimpahkan
kelebihan air pada saat banjir. Perhitungan pelimpah samping pada Kantong Lumpur dapat dilihat
pada tabel berikut.
Hitungan Bangunan Pelimpah

Highest Water Qin Qout selisih


μ g c m b Δx 3 3
el. Above crest m /s m /s
1.35 9.81 1.97 0 0.70 0.50 0.07 0.54 0.54 0.000

No Δx Qo Ho vo ho ho-c qx Qo+qx Ax vx hx Σx Σq
1 0.5 0.00 2.04 0.00 2.042 0.07 0.06 0.06 1.43 0.00 2.042 0.5 0.06
2 0.5 0.06 2.04 0.04 2.042 0.07 0.06 0.11 1.43 0.04 2.042 1 0.11
3 0.5 0.11 2.04 0.08 2.042 0.07 0.06 0.17 1.43 0.08 2.041 1.5 0.17
4 0.5 0.17 2.04 0.12 2.041 0.07 0.06 0.23 1.43 0.12 2.041 2 0.23
5 0.5 0.23 2.04 0.16 2.041 0.07 0.06 0.28 1.43 0.16 2.040 2.5 0.28
6 0.5 0.28 2.04 0.20 2.040 0.07 0.05 0.33 1.43 0.20 2.039 3 0.33
7 0.5 0.33 2.04 0.23 2.039 0.07 0.05 0.39 1.43 0.23 2.038 3.5 0.39
8 0.5 0.39 2.04 0.27 2.038 0.07 0.05 0.44 1.43 0.27 2.037 4 0.44
9 0.5 0.44 2.04 0.31 2.037 0.07 0.05 0.49 1.43 0.31 2.036 4.5 0.49
10 0.5 0.49 2.04 0.34 2.036 0.07 0.05 0.54 1.43 0.34 2.035 5 0.54
5.0 0.000

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-21


LAPORAN AKHIR

6.3.3.2 Pintu Pembilas


Pintu pembilas pada kantong lumpur berfungsi saat dilakukan kegiatan rutin pemeliharaan. Pintu
pembilas direncanakan dengan dimensi sebagai berikut:
 Lebar pintu = 1.0 m
 Tinggi pintu = 1.0 m
 Jumlah pintu = 1 unit

6.3.4 Saluran Pembawa Primer


Pada studi ini, saluran pembawa didesain dengan pertimbangan sebagai berikut.
 Saluran pembawa primer direncanakan dibangun di sebelah kiri saluran kuarter eksisting
Dinas Pertanian. Saluran pembawa primer tidak menggunakan saluran eksisting Dinas
Pertanian karena elevasi saluran pada beberapa tempat terlalu rendah.
 Kecepatan rencana saluran pada perencanaan ini lebih besar dari 0.3 m/s, yang bertujuan
untuk menghindari adanya pengendapan di saluran.

 Saluran pembawa primer menggunakan material beton, yang bertujuan untuk memperkecil
kehilangan energy (headlosses).

 Kemiringan dasar saluran pada trase saluran pembawa primer direncanakan mengikuti
topografi lahan dengan Kecepatan aliran minimal 0.3 m/s.

 Saluran kuarter akan memanfaatkan saluran eksisting Dinas Pertanian.

 Jalan inspeksi irigasi akan memanfaatkan jalan eksisting.


6.3.4.1 Penentuan Elevasi Muka Air dan Debit pada Saluran Primer
Muka air pada saluran primer harus lebih tinggi daripada elevasi sawah yang akan diairi. Pada
perhitungan ini, elevasi ditentukan mulai dari elevasi mercu +34.0 mdpl yang akan dikurangin
dengan nilai kehilangan energi mayor dan minor. Berikut hasil rekap elevasi muka air saluran.
Tabel 6.5 Elevasi Muka Air Saluran

Ruas Saluran MA Hulu MA Hilir Keterangan


RG.1 +33.813 m +33.483 m Bendung (BG.0) –
Bangunan Bagi Sadap 1
(BG.1)
RG.2 +33.483 m +24.048 m Bangunan Bagi Sadap 1
(BG.1) – Bagi Bagi
Sadap 2 (BG.2)
RG.3 +24.048 m +21.354 m Bangunan Bagi Sadap 2
(BG.2) – Boks Kuarter
(K1)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-22


LAPORAN AKHIR

6.3.4.2 Dimensi
Kapasitas saluran setiap saluran dihitung dengan menggunakan persamaan pada aliran seragam,
yaitu persamaan Manning. Saluran pembawa dibuat dari material beton bertulang. Debit rencana
pada saluran pembawa primer (DR primer) adalah 0.00159 m3/s/ha. Nilai ini kemudian dikalikan
dengan total luas areal petak sawah tersier. Berikut salah satu contoh perhitungan dimensi saluran
terbuka menggunakan rumus manning (Ruas Saluran RG 1, dengan dua pola tanam).
1. Menghitung nilai Q saluran
Q saluran = QDI = DR primer × luas petak kuarter
= 0.00159 m3/det/ha × 97.53 Ha
= 0.155 m3/s
2. Mencari panjang saluran (L)
L = STA Akhir – STA - Awal
= 95 – 0 = 95 m
3. Menentukan nilai lebar saluran (B). Pada ruas RG 1 diambil lebar sebesar 0.7 m.
4. Input perkiraan kedalaman saluran (h).
h = 0.27 m (hasil yang sudah di solver)
5. Menentukan kemiringan saluran (m). Dengan nilai m yang digunakan sebesar 0.5.
6. Memasukkan koefisien manning (n) sesuai bahan saluran yang digunakan. Bahan saluran
menggunakan beton bertulang sehingga memiliki nilai n sebesar 0.016.
7. Menghitung luas penampang basah saluran (A).
A = bh + mh2
= (0.7× 0.27) + (0.5×0.272) = 0.22 m2
8. Menghitung keliling penampang basah (P).
P = b + 2h√(1+m2) = 1.30 m
9. Menghitung kecepatan saluran (v).
v = [(A/P)2/3 × s1/2] / n = 0.7 m/s
10. Hitung debit (Q).
Q = [A × (A/P)2/3 × s1/2] / n = 0.155 = 0.16 m3/s
11. Nilai debit (Q) pada langkah ke-8 harus sama dengan Q saluran pada langkah ke-1. Agar
menghasilkan nilai yang sama, nilai (h) dapat diubah hingga mendapatkan nilai Q sama
dengan Q saluran.
12. Mendesain tinggi saluran dengan meninjau kedalaman saluran. Pada ruas RG 1 tinggi
saluran yang diambil adalah 0.5 m.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-23


LAPORAN AKHIR

6.3.4.3 Tinggi Jagaan Saluran


Tinggi jagaan berguna untuk menaikkan muka air di atas tinggi muka air maksimum dan mencegah
kerusakan tanggul saluran. Harga minimum untuk tinggi jagaan adalah seperti yang disajikan pada
Tabel 6.6. Harga-harga tersebut diambil dari USBR. Tabel ini juga menunjukkan tinggi jagaan tanggul
tanah dan saluran pasangan.
Tabel 6.6 Tinggi Jagaan untuk Saluran Pasangan

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-24


LAPORAN AKHIR

Tabel 6.7 Hasil Perhitungan Debit dan Dimensi Saluran Primer 3 Pola Tanam

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-27


LAPORAN AKHIR

Tabel 6.8 Hasil Perhitungan Debit dan Dimensi Saluran Primer 2 Pola Tanam

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-28


LAPORAN AKHIR

Berikut adalah rekapitulasi dimensi saluran primer pada rencana DI Gudang.


1. Dimensi Saluran
Tipe
Ruas B H Talud Hnwl-US Hnwl-DS So L
Saluran
3 POLA TANAM
Bendung –
Bangunan Bagi 0.7 0.70 33.813 33.483 0.13% 95
Sadap 1
Bangunan Bagi
0.02% -
Sadap 1 -
0.5 0.50 Trapesium 1 : 0.5 33.483 24.048 0.39% 3445
Bangunan Bagi
Varies
Sadap 2
Bangunan Bagi
Sadap 2 – Boks 0.5 0.50 24.048 21.354 0.30% 830
Kuarter
2 POLA TANAM
Bendung –
Bangunan Bagi 0.7 0.50 33.813 33.483 0.13% 95
Sadap 1
Bangunan Bagi
0.02% -
Sadap 1 -
0.5 0.60 Trapesium 1 : 0.5 33.483 24.048 0.39% 3445
Bangunan Bagi
Varies
Sadap 2
Bangunan Bagi
Sadap 2 – Boks 0.5 0.50 24.048 21.558 0.30% 830
Kuarter

2. Gambar Penampang Saluran

Ruas Gambar

Bendung – Bangunan Bagi


Sadap 1

Bangunan Bagi Sadap 1 -


Bangunan Bagi Sadap 2

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-29


LAPORAN AKHIR

Ruas Gambar

Bangunan Bagi Sadap 2 –


Boks Kuarter

6.3.4.4 Lebar Tanggul dan Jalan Inspeksi


Untuk tujuan-tujuan eksploitasi, pemeliharaan, dan inspeksi akan diperlukan tanggul di sepanjang
saluran dengan lebar minimum seperti yang disajikan pada Tabel 6.9. Contoh–contoh potongan
melintangnya diberikan pada Gambar 6.19.

Gambar 6.19 Tipe-Tipe Potongan Melintang Saluran Irigasi


Tabel 6.9 Lebar Minimum Tanggul

Berikut gambar salah satu tipe saluran yang digunakan.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-30


LAPORAN AKHIR

Gambar 6.20 Gambar Tipikal Saluran dan Jalan Inspeksi

Jalan inspeksi terletak di tepi saluran di sisi yang diairi agar bangunan sadap dapat dicapai secara
langsung dan usaha penyadapan liar makin sulit dilakukan. Lebar jalan inspeksi dengan perkerasaan
yang dianjurkan adalah 5,0 m atau lebih, dengan lebar perkerasan sekurang-kurangnya 3,0 meter,
untuk pertimbangan stabilitas tanggul, lebar tanggul yang diberikan pada Tabel 6.9 dan/atau talut
luar dapat ditambah. Pada studi ini, jalan inspeksi menggunakan jalan eksisting yang lebarnya
sebesar 5 meter. Sedangkan jalan di samping saluran (dapat dilihat pada Gambar 6.20) dengan lebar
1 meter merupakan tanggul pemisah antara saluran rencana dan saluran dinas pertanian.

6.3.5 Saluran Pembawa Kuarter


Pada studi ini, saluran pembawa kuarter akan memanfaatkan saluran eksisting milik Dinas Pertanian.
Berikut foto dari saluran eksisting dengan perkiraan dimensinya.

Gambar 6.21 Saluran Eksisting Dinas Pertanian

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-31


LAPORAN AKHIR

Dimensi (m) Ket


Lebar Dasar (b) 0.9 m
Lebar Puncak (B) 1.2 m
Tinggi Saluran (H) 1.0 m
Kedalaman Air (h) 0.1 m Saat pengukuran debit sessat

6.3.6 Bangunan Bagi Sadap


Pada studi ini, bangunan bagi sadap didesain dengan pertimbangan sebagai berikut.
 Jumlah bangunan bagi sadap didasarkan pada pertimbangan batas luas petak tersier yang
akan dilayani, sebesar 50-100 Ha. Sehingga pada DI Gudang jumlah bangunan bagi sadap
sebanyak 2 unit, yaitu BG.1 dan BG.2 dan boks kuarter sebanyak 1 unit, yaitu K.1.
 Tata letak dari bangunan bagi sadap dibuat bentuk menyamping, dimana posisi
bangunan/pintu sadap tersier berada disamping kiri atau kanan saluran dengan arah aliran
ke petak tersier mempunyai sudut tegak lurus.
 Pada bangunan bagi sadap, air irigasi dibagi dari saluran primer ke saluran kuarter (Dinas
Pertanian). Bangunan bagi terdiri dari pintu-pintu yang dengan teliti mengukur dan
mengatur air yang mengalir ke berbagai saluran. Bangunan sadap akan memberi air ke
saluran kuarter dan melayani lebih dari satu petak tersier.

 Secara umum, bangunan sadap primer yang akan memberi air kepada petak-petak tersier
dengan kapasitas debit berkisar antara 50 - 250 l/dt.
Tata letak bangunan bagi sadap ditunjukkan Gambar 6.22.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-32


LAPORAN AKHIR

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-33


LAPORAN AKHIR

Gambar 6.22 Tata Letak Bangunan Bagi Sadap

Perhitungan pintu bangunan sadap tergantung dari dimensi saluran primer yang lebar dan tingginya
dipengaruhi oleh luasan petak tersiernya. Penamaan bangunan bagi dan sadap mengikuti skema
pada Gambar 6.8 dan Gambar 6.9. Bangunan bagi membagi aliran air kepada dua atau lebih saluran
primer atau petak tersier.
Berikut adalah rekap dimensi banguna bagi sadap pada rencana DI Gudang.
Tabel 6.10 Rekapitulasi Dimensi Bangunan Bagi dan Boks Kuarter

Boks Bagi Sadap 1 (BG.1)


Bentuk Pintu
B H
saluran Sorong
Hulu 0.70 0.70 Trapesium Tidak
Hilir 0.50 0.50 Trapesium Ada
Kuarter Kanan 0.50 0.50 Persegi Ada
Boks Bagi Sadap 2 (BG.2)
Bentuk
B H Pintu
saluran
Hulu 0.50 0.50 Trapesium Tidak
Hilir 0.50 0.50 Trapesium Ada
Kuarter Kiri 0.40 0.40 Persegi Ada
Kuarter Kanan 0.40 0.40 Persegi Ada
Boks Kuarter
Bentuk
B H Pintu
saluran
Hulu 0.50 0.50 Trapesium Tidak
Kuarter Kiri 0.40 0.40 Persegi Ada
Kuarter Kanan 0.40 0.40 Persegi Ada

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-34


LAPORAN AKHIR

6.3.7 Kehilangan Energi (Headloss)


Kehilangan tinggi muka air dihitung sepanjang bangunan pembawa air mulai dari bangunan
pengambilan sampai ke boks kuarter.
Tabel 6.11 Resume Kehilangan Tinggi Energi

H [m] MAN
INTAKE
MAN di hulu intake + 34.00 m
Kehilangan energi akibat bagian masuk 0.0026 m
Kehilangan energi akibat pintu 0.1500 m
Kehilangan energi akibat gesekan 0.0051 m
Total Head Loss 0.1577 m
MAN di hilir intake + 33.84 m
KOLAM PASIR (SAND TRAP)
MAN di hulu kolam pasir + 33.84 m
Kehilangan energi akibat bagian ekspansi 3.62321E-06 m
Kehilangan energi akibat gesekan 0.0250 m
Kehilangan energi akibat kontraksi 0.001539858 m
Kehilangan energi akibat bagian masuk menuju 0.00256643 m
saluran pembawa
Total Head Loss 0.0291 m
MAN di hilir kolam pasir + 33.81 m
SALURAN PEMBAWA (BENDUNG – BG.1)
MAN di hulu saluran RG.1 + 33.813 m
a : Lapisan air di sawah 0.10000 m
d : Kehilangan energi akibat gesekan 0.12400 m
e : Kehilangan tinggi energi di boks bagi tersier 0.10000 m
f : Kehilangan tinggi energi di gorong-gorong 0.00000 m
g : Kehilangan tinggi energi di bangunan sadap tersier
Kontraksi 0.00240 m
Ekspansi 0.00030 m
Entrance 0.00390 m
Total Head Loss 0.33060 m
MAN di hilir saluran RG.1 + 33.690 m
SALURAN PEMBAWA (BG.1 – BG.2)
MAN di hulu saluran RG.2 + 33.690 m
a : Lapisan air di sawah 0.10000 m
d : Kehilangan energi akibat gesekan 9.08000 m
e : Kehilangan tinggi energi di boks bagi tersier 0.10000 m
f : Kehilangan tinggi energi di gorong-gorong 0.15000 m
g : Kehilangan tinggi energi di bangunan sadap tersier
Kontraksi 0.00190 m
Ekspansi 0.00020 m
Entrance 0.00320 m

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-35


LAPORAN AKHIR

H [m] MAN
Total Head Loss 9.43530 m
MAN di hilir saluran RG.2 + 24.403 m
SALURAN PEMBAWA (BG.2 – BOKS KUARTER)
MAN di hulu saluran RG.3 + 24.403 m
a : Lapisan air di sawah 0.10000 m
d : Kehilangan energi akibat gesekan 2.49000 m
e : Kehilangan tinggi energi di boks bagi tersier 0.10000 m
f : Kehilangan tinggi energi di gorong-gorong 0.00000 m
g : Kehilangan tinggi energi di bangunan sadap tersier
Kontraksi 0.00160 m
Ekspansi 0.00020 m
Entrance 0.00260 m
Total Head Loss 2.69440 m
BOKS KUARTER
MAN di Boks Kuarter +21.558 m
Total headloss 12.6471 m

Berdasarkan tabel di atas, total kehilangan energy (headlosses) dari bendung (BG.0) sampai ke boks
kuarter (K.1) sebesar 12.647 m, dengan muka air di hilir +21.558m. Muka air tersebut masih dapat
mengairi air sampai ke elevasi sawah terendah +17.00m.

6.3.8 Saluran Pembuang


Pada studi ini, saluran pembuang didesain dengan pertimbangan sebagai berikut.
 Saluran pembuang direncanakan memanfaat saluran eksisting (di samping Sungai Babuar),
karena elevasi saluran tersebut terendah.

 Bila saluran air alamiah digunakan sebagai saluran pembuang, maka umumnya akan lebih
baik untuk tidak mengubah trasenya karena saluran alamiah ini sudah menyesuaikan
potongan melintang dan kemiringannya dengan alirannya sendiri.
 Perencanaan saluran pembuang harus mempertimbangkan biaya pelaksanaan dan
pemeliharaan yang terendah. Ruas-ruas harus stabil terhadap erosi dan sedimentasi
minimal pada setiap potongan melintang dan seimbang.
 Dengan adanya saluran pembuang, air dari sawah menjadi lebih bersih dari sedimen. Erosi
di saluran pembuang akan merupakan kriteria yang menentukan. Kecepatan rencana
hendaknya tidak melebihi kecepatan maksimum yang diizinkan. Kecepatan maksimum yang
diizinkan bergantung kepada tanah serta kondisinya.

 Apabila kemiringan dasar terlalu curam dan kecepatan maksimum yang diizinkan akan
terlampaui, maka harus dibuat bangunan pengatur (terjun).

 Kecepatan rencana sebaiknya diambil sama atau mendekati kecepatan maksimum yang
diizinkan, karena debit rencana atau debit puncak tidak sering terjadi, debit dan kecepatan
aliran pembuang akan lebih rendah, aliran akan cenderung berkelok – kelok (meander) bila

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-36


LAPORAN AKHIR

dasar saluran dibuat lebar. Oleh karena itu, biasanya saluran pembuang direncana relatif
sempit dan dalam. Variasi tinggi air dengan debit yang berubah-ubah biasanya tidak
mempunyai arti penting. Potongan-potongan yang dalam akan memberikan pemecahan
yang lebih ekonomis.

 Kemiringan dasar saluran pembuang biasanya mengecil di sebelah hilir sedangkan debit
rencana bertambah besar. Parameter angkutan sedimen relatif I√R dalam prakteknya akan
menurun di sebelah hilir akibat akar R kuadrat. Sejauh berkenaan dengan air buangan yang
relatif bersih dari sawah, hal ini tidak akan merupakan masalah yang berarti. Keadaan ini
harus dihindari apabila air buangan yang bersedimen harus dialirkan.
 Dasar dan talutnya mempunyai daya tahan yang lebih tinggi terhadap kikisan jika
dibandingkan dengan saluran pembuang yang baru dibangun dengan kemiringan talut yang
sama.

 Pemantapan saluran air dan sungai alamiah untuk menambah kapasitas pembuang sering
terbatas pada konstruksi tanggul banjir dan sodetan dari lengkung meander. Air dari saluran
pembuang mempunyai pengaruh negatif pada muka air tanah atau pada air yang masuk
dari laut dan sebagainya. Oleh sebab itu perencana harus mempertimbangkan faktor
tersebut dengan hati-hati guna memperkecil dampak yang timbul.
Trase saluran pembuang ditunjukkan Gambar 6.23.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-37


LAPORAN AKHIR

Gambar 6.23 Trase Saluran Pembuang

Berikut contoh perhitungan debit rencana saluran pembuang (contoh perhitungan : ruas RG. 1).
A. Perhitungan Debit Rencana
Berikut hasil analisis frekuensi curah hujan harian maksimum tahunan (mm). Berdasarkan tabel di
bawah dapat dilihat nilai curah hujan rencana [R(n)T] yaitu 200.50.
Tabel 6.12 Hasil Analisis Frekuensi

B. Pembuang Intern
1. Menghitung D(n) pembuang permukaan untuk satuan luas. Untuk perhitungan modulus
pembuang, komponen – komponennya dapat diambil sebagai berikut:
 R(n)T didapat dari curah hujan selama 3 hari berturut – turut dengan periode ulang
5 tahun dengan menggunakan distribusi probabilitas Log Pearson III. (Tabel 6.12)
 Pemberian air irigasi IR sama dengan nol jika pemberian dihentikan.

 Tampungan di sawah dengan lapisan air maksimum 150 mm; tampungan tambahan
∆s di akhir n hari berturut – turut maksimum 50 mm

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-38


LAPORAN AKHIR

 Perkolasi P sama dengan nol.


D(n) = R(n)T + n(IR – ET – P) - ∆s
= 200.50 + 3(0 – 3.44 – 0) – 50
= 140.18 mm
2. Menghitung Dm modulus pembuang rencana. Dm merupakan curah hujan 3 hari dengan
periode ulang 5 tahun.
Dm = D(n) / n × 8.64
= 140.18 / 3 × 8.64
= 5.41 l/dt.ha
3. Menghitung debit rencana Qd
Qdintern= 1.62 Dm A0.92
= 1.62 × 5.41 × 37.690.92
= 247 l/dt = 0.25 m3/s
C. Pembuang Ekstern
1. Menghitung debit rencana Qd. Untuk perhitungan modulus pembuang ekstern, komponen
– komponennya dapat diambil sebagai berikut:

 R(1)5 didapat dari curah hujan sehari dengan periode ulang 5 tahun.
 𝞪 merupakan koefisien limpasan air hujan.
Qdekstern= 0.116 𝞪 R(1)5 A0.92
= 0.116 x 0.8 x 134.2 x 37.690.92
= 0.35 m3/s
Berikut hasil perhitungan saluran pembuang.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-39


LAPORAN AKHIR

Gambar 6.24 Saluran Pembuang

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-40


LAPORAN AKHIR

6.3.9 Bangunan Ukur Ambang Lebar


Alat ukur ambang lebar adalah bangunan aliran atas (overflow), untuk ini tinggi energi hulu lebih
kecil dari panjang mercu. Bangunan ukur ambang lebar dianjurkan karena:

 Bangunan kokoh;

 Mudah dibuat;
 Murah/ekonomis;

 Dapat menyesuaikan dengan tipe saluran apa saja;


 Pembacaan debit langsung dari papan duga, tanpa memerlukan tabel debit;

 Benda hanyut dapat dilewatkan.


6.3.9.1 POSISI BANGUNAN UKUR
Bangunan ukur ditempatkan di awal saluran primer, pada titik cabang saluran besar, dan tepat di
hilir pintu sorong pada titik masuk petak tersier.

No Lokasi Tipe Keterangan


1 Hulu Saluran Primer
2 BG.1 (saluran primer) Hilir pintu bagi BG.1
3 Hilir pintu sadap BG.1,
BG.1 (saluran kuarter)
menuju petak BG1.Ka
4 BG.2 (saluran primer) Ambang Lebar Segi Empat Hilir pintu bagi BG.2
5 Hilir pintu sadap BG.2,
BG.2 (saluran kuarter)
menuju petak BG2.Ka
6 Hilir pintu sadap K.1,
K.1
menuju petak BG3.Ka
Keterangan: pintu sadap ke petak BG2.Ki dan BG3.Ki tidak dipasang bangunan ukur karena
muka air <10cm. Untuk mengukur debit dapat dilakukan menggunakan current meter oleh
petugas operasi irigasi.
6.3.9.2 PERSAMAAN DEBIT PADA AMBANG LEBAR
𝑄 = 1.71 × 𝑏 × ℎ1.5
Contoh perhitungan:
Diketahui:
 Posisi alat ukur di hulu saluran primer
 Debit, Q = 155.02 lt/s
 Dimensi saluran, B = 0.7 m
Penyelesaian:
 𝑄100% = 155.02 𝑙𝑡⁄𝑠
155.02
 𝑄50% = 2
= 77.5 𝑙𝑡⁄𝑠

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-41


LAPORAN AKHIR

0.155 2⁄3
 ℎ100% = (1.71×0.7) = 0.25 𝑚

0.155 2⁄3
 ℎ50% = (1.71×0.7) = 0.16 m

 𝐿 = 1.75 × ℎ100% = 0.5 𝑚


 𝑃1 = 0.3 𝑚
 𝑃2 = 0.4 𝑚
Sketsa dimensi hidraulik alat ukur ambang lebar segi empat:

Berikut tabel Q vs H pada alat ukur ambang lebar segi empat.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-42


LAPORAN AKHIR

Tabel 6.13 Debit dan Muka Air untuk Alat Ukur Ambang Lebar Segi Empat
BANGUNAN UK UR P ADA SALURAN P RIMER
HULU BG.1 HILIR BG.1 HILIR BG.2
B= 0.7 m B= 0.5 m B= 0.5 m
Q= 155.02 lt/s 0.00 Q= 95.12 lt/s 0.00 Q= 67.51 lt/s 0.00
Qmin = 77.51 lt/s 0.00 Qmin = 47.56 lt/s 0.00 Qmin = 33.75 lt/s 0.00
H1 = 0.26 m H1 = 0.23 m H1 = 0.18 m
L= 0.50 m L= 0.50 m L= 0.40 m

No H Q H Q No H Q H Q No H Q H Q
(m) (m 3 /s) (c m) (lt/s) (m) (m 3 /s) (c m) (lt/s) (m) (m 3 /s) (c m) (lt/s)
1 0.02 0.003 2 3.39 1 0.02 0.002 2 2.42 1 0.02 0.002 2 2.42
2 0.04 0.010 4 9.58 2 0.04 0.007 4 6.84 2 0.04 0.007 4 6.84
3 0.06 0.018 6 17.59 3 0.06 0.013 6 12.57 3 0.06 0.013 6 12.57
4 0.08 0.027 8 27.09 4 0.08 0.019 8 19.35 4 0.08 0.019 8 19.35
5 0.1 0.038 10 37.85 5 0.1 0.027 10 27.04 5 0.1 0.027 10 27.04
6 0.12 0.050 12 49.76 6 0.12 0.036 12 35.54 6 0.11594 0.034 11.59399 33.75
7 0.14 0.063 14 62.70 7 0.14 0.045 14 44.79 7 0.14 0.045 14 44.79
8 0.16 0.077 16 76.61 8 0.145715 0.048 14.57153 47.56 8 0.16 0.055 16 54.72
9 0.161257 0.078 16.12566 77.51 9 0.18 0.065 18 65.29 9 0.18 0.065 18 65.29
10 0.2 0.107 20 107.06 10 0.2 0.076 20 76.47 10 0.184043 0.068 18.40428 67.51
11 0.22 0.124 22 123.52 11 0.22 0.088 22 88.23 11 0.22 0.088 22 88.23
12 0.24 0.141 24 140.74 12 0.231309 0.095 23.1309 95.12 12 0.24 0.101 24 100.53
13 0.255979 0.155 25.59789 155.02 13 0.26 0.113 26 113.35 13 0.26 0.113 26 113.35
14 0.28 0.177 28 177.35 14 0.28 0.127 28 126.68 14 0.28 0.127 28 126.68
15 0.3 0.197 30 196.69 15 0.3 0.140 30 140.49 15 0.3 0.140 30 140.49
16 0.32 0.217 32 216.68 16 0.32 0.155 32 154.77 16 0.32 0.155 32 154.77
17 0.34 0.237 34 237.31 17 0.34 0.170 34 169.51 17 0.34 0.170 34 169.51
18 0.36 0.259 36 258.55 18 0.36 0.185 36 184.68 18 0.36 0.185 36 184.68
19 0.38 0.280 38 280.39 19 0.38 0.200 38 200.28 19 0.38 0.200 38 200.28
20 0.4 0.303 40 302.82 20 0.4 0.216 40 216.30 20 0.4 0.216 40 216.30
21 0.42 0.326 42 325.81 21 0.42 0.233 42 232.72 21 0.42 0.233 42 232.72
22 0.44 0.349 44 349.36 22 0.44 0.250 44 249.54 22 0.44 0.250 44 249.54
23 0.46 0.373 46 373.45 23 0.46 0.267 46 266.75 23 0.46 0.267 46 266.75
24 0.48 0.398 48 398.07 24 0.48 0.284 48 284.33 24 0.48 0.284 48 284.33
25 0.5 0.423 50 423.20 25 0.5 0.302 50 302.29 25 0.5 0.302 50 302.29

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-43


LAPORAN AKHIR

BANGUNAN UK UR P ADA SALURAN K UARTER


SADAP BG1 .K a SADAP BG3 .K a
B= 0.4 m B= 0.4 m
Q= 59.91 lt/s 0.00 Q= 40.59 lt/s 0.00
Qmin = 29.95 lt/s 0.00 Qmin = 20.30 lt/s 0.00
H1 = 0.17 m H1 = 0.13 m
L= 0.30 m L= 0.30 m

No H Q H Q No H Q H Q
(m) (m 3 /s) (c m) (lt/s) (m) (m 3 /s) (c m) (lt/s)
1 0.01 0.001 1 0.86 1 0.01 0.001 1 0.86
2 0.02 0.002 2 2.42 2 0.02 0.002 2 2.42
3 0.03 0.004 3 4.44 3 0.03 0.004 3 4.44
4 0.04 0.007 4 6.84 4 0.04 0.007 4 6.84
5 0.05 0.010 5 9.56 5 0.05 0.010 5 9.56
6 0.06 0.013 6 12.57 6 0.06 0.013 6 12.57
7 0.07 0.016 7 15.83 7 0.07 0.016 7 15.83
8 0.08 0.019 8 19.35 8 0.08 0.019 8 19.35
9 0.09 0.023 9 23.09 9 0.082603 0.020 8.260323 20.30
10 0.1 0.027 10 27.04 10 0.1 0.027 10 27.04
11 0.107068 0.030 10.70685 29.95 11 0.11 0.031 11 31.19
12 0.12 0.036 12 35.54 12 0.12 0.036 12 35.54
13 0.13 0.040 13 40.08 13 0.13 0.040 13 40.08
14 0.14 0.045 14 44.79 14 0.131122 0.041 13.1122 40.60
15 0.15 0.050 15 49.67 15 0.15 0.050 15 49.67
16 0.16 0.055 16 54.72 16 0.16 0.055 16 54.72
17 0.16996 0.060 16.99605 59.91 17 0.17 0.060 17 59.93
18 0.18 0.065 18 65.29 18 0.18 0.065 18 65.29
19 0.19 0.071 19 70.81 19 0.19 0.071 19 70.81
20 0.2 0.076 20 76.47 20 0.2 0.076 20 76.47
21 0.21 0.082 21 82.28 21 0.21 0.082 21 82.28
22 0.22 0.088 22 88.23 22 0.22 0.088 22 88.23
23 0.23 0.094 23 94.31 23 0.23 0.094 23 94.31
24 0.24 0.101 24 100.53 24 0.24 0.101 24 100.53
25 0.25 0.107 25 106.88 25 0.25 0.107 25 106.88

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-44


LAPORAN AKHIR

6.4 REKAP DATA TEKNIS DI GUDANG


Berikut informasi teknis rencana Daerah Irigasi Gudang :
1) Bendung
 Debit Desain Banjir : 42.4 m3/s
 Lebar Mercu : 7m
 Lebar pelimpah : 1m
 Tinggi Mercu : 2m
 Elevasi Dasar Mercu : EL. +32.0 m
 Elevasi Mercu : EL. +34.0 m
 Hretwall : 5.1 m
 Tipe Peredam Energi : MDO
 Kedalaman Lantai Peredam Energi :3m
 Panjang Lantai Dasar Peredam Energi :3m
 Tinggi Ambang Hilir (endsill) : 0.5 m
 Lebar Ambang Hilir (endsill) :1m
 Panjang Tembok Sayap Hilir :3m
2) Intake
 DR primer : 0.00159 m3/s/ha
 Debit : 0.159 m3/s
 Lebar Pintu : 0.7 m
 Tinggi Pintu : 0.7 m
 Tinggi Bukaan Pintu : 0.19 m
3) Kantong Lumpur
 Lebar Kantong Lumpur : 0.7 m
 Panjang Kantong Lumpur : 6m
4) Bangunan Bagi Sadap
Boks Bagi Sadap 1 (BG.1)
B H Bentuk Pintu
saluran Sorong
Hulu 0.70 0.70 Trapesium Tidak
Hilir 0.50 0.50 Trapesium Ada
Kuarter Kanan 0.50 0.50 Persegi Ada
Boks Bagi Sadap 2 (BG.2)
B H Bentuk Pintu
saluran

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-45


LAPORAN AKHIR

Hulu 0.50 0.50 Trapesium Tidak


Hilir 0.50 0.50 Trapesium Ada
Kuarter Kiri 0.40 0.40 Persegi Ada
Kuarter Kanan 0.40 0.40 Persegi Ada
Boks Kuarter
B H Bentuk Pintu
saluran
Hulu 0.50 0.50 Trapesium Tidak
Kuarter Kiri 0.40 0.40 Persegi Ada
Kuarter Kanan 0.40 0.40 Persegi Ada

5) Bangunan Ukur

No Lokasi Tipe Keterangan


1 Hulu Saluran Primer
2 BG.1 (saluran primer) Hilir pintu bagi BG.1
3 Hilir pintu sadap BG.1,
BG.1 (saluran kuarter)
menuju petak BG1.Ka
4 BG.2 (saluran primer) Ambang Lebar Segi Empat Hilir pintu bagi BG.2
5 Hilir pintu sadap BG.2,
BG.2 (saluran kuarter)
menuju petak BG2.Ka
6 Hilir pintu sadap K.1,
K.1
menuju petak BG3.Ka

6) Saluran Pembawa
 Ruas saluran pembawa RG.1 : Bendung – bangunan bagi sadap 1
 Dimensi Saluran Primer RG.1 : 0.7x0.7 (BxH), Talud 1:0.5 (1:H), Trapesium
 Ruas saluran pembawa RG.2 : Bangunan bagi sadap 1 – bangunan bagi sadap 2
 Dimensi Saluran Primer RG.2 : 0.5x0.5 (BxH), Talud 1:0.5 (1:H), Trapesium
 Ruas saluran pembawa RG.3 : Bangunan bagi sadap 2 – boks kuarter 1
 Dimensi Saluran Primer RG.3 : 0.5x0.5 (BxH), Talud 1:0.5 (1:H), Trapesium
 Panjang Saluran Pembawa Primer : ± 4.3 Km
 Panjang Saluran Pembuang Primer : ± 6.5 m
 Saluran Kuarter : Saluran eksisting Dinas Pertanian
7) Skema Jaringan dan Bangunan Irigasi
 Luas Layanan (Asawah) : 97.5 Ha

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-46


LAPORAN AKHIR

Gambar 6.25 Skematisasi Jaringan Irigasi

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-47


LAPORAN AKHIR

Gambar 6.26 Skematisasi Bangunan Irigasi

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6-48


LAPORAN AKHIR

BAB 7 ESTIMASI VOLUME DAN RENCANA


ANGGARAN BIAYA (RAB) PELAKSANAAN

7.1 ESTIMASI VOLUME DAN BIAYA PELAKSANAAN


Rencana anggaran biaya yang disusun mengikuti bentuk perhitungan volume pekerjaan. Selanjutnya
volume dari setiap jenis pekerjaan dikalikan dengan harga satuan, hingga akhirnya diperoleh
estimasi total biaya pelaksanaan pekerjaan.

7.1.1 Harga Satuan pekerjaan


Harga satuan pekerjaan didasarkan pada harga satuan Kabupaten Bangka Selatan tahun 2017.
Mengingat dalam Daftar harga satuan sangat banyak ragam dan jenisnya, maka harga satuan yang
dipakai sebagai acuan adalah jenis pekerjaan yang sesuai/berkaitan dengan jenis pekerjaan yang
akan dilaksanakan.

7.1.2 Analisis Harga Satuan (AHS) pekerjaan


Analisis harga satuan mengacu pada Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat
nomor 28/PRT/M/2016 tentang analisis harga satuan pekerjaan bidang pekerjaan umum. AHS
dimasukkan di Lampiran.

7.1.3 Rencana Volume dan Biaya Pekerjaan


Rincian estimasi volume dan biaya pelaksanaan pekerjaan DED DI Gudang di Kecamatan Simpang
Rimba, Bangka Selatan, dapat dilihat pada Lampiran.

7.2 REKAPITULASI BIAYA PEKERJAAN


Rekapitulasi biaya pelaksanaan pekerjaan DED DI Gudang di Kecamatan Simpang Rimba, Bangka
Selatan, dapat dilihat pada tabel berikut.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 7-1


LAPORAN AKHIR

REKAPITULASI

Proyek : DED Daerah Irigasi Gudang


Lokasi : Desa Gudang, Kec. Simpang Rimba, Kab. Bangka Selatan

No. Uraian Pekerjaan Total Harga Setiap Pekerjaan (Rp.)

1 Pekerjaan Umum 234,383,000.00

4 Pekerjaan Bendung 1,733,121,004.06

5 Pekerjaan Intake 40,564,866.93

6 Pekerjaan Kantong Lumpur 278,746,446.13

7 Pekerjaan Saluran Primer 21,988,817,628.94

8 Pekerjaan Bangunan Pelengkap (Pengatur dan Pengukur) 155,069,919.65

Total 24,430,702,865.71

PPn 10% 2,443,070,286.57

Total+PPn 10% 26,873,773,152.28

Dibulatkan 26,873,800,000.00

Total biaya konstruksi DI Gudang untuk areal 100 Ha sebesar Rp. 26,873,800,000.00,- (dua puluh
enam milyar delapan ratus tujuh puluh tiga juta delapan ratus ribu rupiah). Adapun item pekerjaan
yang dilaksanakan diantaranya pekerjaan persiapan, bangunan utama (bendung, intake, dan
kantong lumpur), saluran pembawa primer, bangunan pelengkap/pengatur (bangunan bagi sadap
dan boks kuarter), dan bangunan pengukur ambang lebar.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 7-2


LAPORAN AKHIR

BAB 8 OPERASI DAN PEMELIHARAAN

8.1 UMUM
Sebagaimana yang telah diatur dalam PP Nomor 20/2006 tentang irigasi dimana dijelasakan bahwa:
Operasi jaringan irigasi adalah upaya pengaturan air irigasi dan pembuangannya, termasuk kegiatan
membuka-menutup pintu bangunan irigasi, menyusun rencana tata tanam, menyusun sistem
golongan, menyusun rencana pembagian air, melaksanakan kalibrasi pintu/bangunan,
mengumpulkan data, memantau, dan mengevaluasi.
Pemeliharaan jaringan irigasi adalah upaya menjaga dan mengamankan jaringan irigasi agar selalu
dapat berfungsi denga baik guna memperlancar pelaksanaan operasi dan mempertahankan
kelestariannya.
Oleh karena itu Operasi dan Pemerliharaan merupakan upaya pengelolaan jaringan irigasi yang
memerlukan partisipasi dan koordinasi dari semua pihak yaitu masyarakat dan pemerintah.
Koordinasi pada pengelolaan jaringan irigasi mempunyai tujuan :
 Untuk mempersiapkan kebijaksanaan dalam pemanfaatan air dalam satuan wilayah sungai
secara optimal, dengan memperhatikan semua kepentingan pemanfaatan air, yaitu untuk
kebutuhan domestik, irigasi, tenaga, listrik, dll.
 Untuk pendekatan terkoordinir dari semua pihak, yaitu pemerintah provinsi/ kabupaten
dengan petani yang meliputi penyediaan, pembagian dan pemberian serta pengamanan air
sampai ke petak tersier, yang didasari ketentuan peraturan.
Kegiatan pokok pengelolaan jaringan irigasi adalah operasi dan pemeliharaan. Untuk melakukan
O&P jaringan irigasi dengan baik diperlukan informasi dan pemahaman terhadap jenis dan tata cara
O&P dari bangunan-bangunan pada jaringan irigasi bagi para pertugas.
Informasi tersebut diantaranya adalah :

 Mekanisme dan pokok-pokok kegiatan.


 Inventarisasi jaringan irigasi.

 Peta, skema daerah irigasi.


 Luas daerah irigasi, dan batas-batas wilayah administrasi.
 Tata cara pengoperasian bangunan-bangunan.

 Peraturan tentang sumber daya air (SDA).


 SK jadwal dan pola tanam.
 Blangko-blangko laporan, dll.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-1


LAPORAN AKHIR

8.2 POKOK KEGIATAN OPERASI JARINGAN IRIGASI


Kegiatan operasi jaringan irigasi akan dilaksanakan atas dasar Surat Keputusan panitia pengairan.
Pada SK tersebut berisikan jadwal pengaliran air kapan dimulai, dan luas areal daerah irigasi yang
akan mendapat pelayanan air. Surat keputusan jadwal dan pola tanam tersebut proses dan
prosedurnya dijelaskan pada pokok-pokok kegiatan operasi jaringan sebagai berikut.
Tabel 8.1 Pokok Kegiatan Operasi Jaringan lrigasi

Penanggung
No. Uraian Kegiatan
Jawab

Mengusulkan rencana tata tanam pada tiap tersier dan luas areal kepada
1 P3A
Dinas yang membidangi irigasi.
Mengumpulkan usulan rencana Tata tanam dari P3A dan kemudian
2 P3A
melaporkannya ke Ranting Dinas .

 Menerima dan mengelola data usulan rencana tanam dari para mantri
pengairan.
3 P3A
 Menyusun dan mengelompokan usulan rencana tata tanam.
 Mengirim atau melaporkan usulan rencana tata tanam.

 Menerima data usulan rencana tata tanam dari Ranting Dinas.


 Menyusun rencana jadwal tanam dan pemberian air termasuk pemberian
air dengan golongan atau giliran .
 Menghitung kebutuhan air ( 1/2 bulanan).
4 Menghitung ketersediaan air (1/2 bulanan). UPTD

 Menyusun Rencana Tata Tanam Global.


 Menyusun neraca air

 Melaporkan rencana tata tanam global dan neraca air kepada Dinas
Pengairan Kabupaten/ Propinsi.

 Menerima laporan rencana tata tanam global jadwal pemberian air dan
neraca air.
Sub BidSDA
 Mengevaluasi laporan rencana tata tanam global jadwal pemberian air dan
5 Kabupaten/
neraca air.
Propinsi
 Mengajukan rencana tata tanam global dan jadwal pemberian air kepada
panitia tata pengaturan air/Panitia lrigasi Kabupaten/ Propinsi.

 Mendiskusikan dengan semua anggota Panitia lrigasi dan selanjutnya Panitia Tata
menetapkan dan mengesahkan Rencana Tata Tanam Global dan jadwal
6 Pengaliran Air
pemberian air tiap daerah irigasi dengan surat keputusan Bupati/
Gubernur. (Panitia Irigasi

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-2


LAPORAN AKHIR

Penanggung
No. Uraian Kegiatan
Jawab

 Mendistribusikan SK Bupati I Gubernur tentan Rencana Tata Tanam Global Kabupaten/


dan jadwal pemberian air kepada Dinas/ Instansi terkait dan P3A Propinsi)
(Gabungan).

Mendistribusikan Rencana Tata Tanam Global dan jadwal pemberian air


Dinas/ Instansi/
7 yang telah ditetapkan/ disyahkan ke tingkat pelaksana (UPTD, Ranting
P3A Gabungan
Dinas/Mantri).

Menginformasikan RTTG, jadwal pemberian air yang di syahkan ke petugas


8 UPTD
I pelaksana lapangan (Ranting dinas dan Mentri, P3A).

Menginformasikan dan menyampaikan RTIG, jadwal pemberian air yang


telah disyahkan pada rapat koordinasi Kecamatan I Panitia Irigasi dan P3A
(petugas instansi terkait mengadakan persiapan).
 Menentukan atau menginformasikan tentang kapan pengaliran air,
9 UPTD
sehingga P3A/ Petani mempersiapkan: (pembersihan saluram, olah tanah,
bibit, pupuk, dan tanaman yang masih ada).
 Menghitung dan melaporkan kebutuhan air : untuk tanaman yang masih
ada, olah tanah, bibit dan sebagainya kepada ranting Dinas..

Mengusulkan I menginformasikan :
10 P3A
 Debit yang dibutuhkan (masing-masing Daerah Irigasi/ blok).

Menentukan :
 Faktor K.
 Pengaliran air, pembagian/ pengaturn air yang disesuaikan dengan waktu
11 UPTD
dan kebutuhan debit.
 Instruksi kepada petugas lapangan (mantri juru di bendung, sampai
dengan bagi sadap)

Menentukan :
 Pengaliran dan pengaturan pembagian air pada jaringan utama sesuai
12 UPTD
dengan jadwal dan lokasi.

 Pengaturan pintu sadap sesuai dengan kebutuhan airnya.

13 Memonitor pelaksanaan penyediaan, pembagian dan pemberian air. Juru

 Pengolahan tanah di petak terseir, persiapan bibit dll.


14
 Adanya informasi balik P3A kepada mantri/ juru pengairan apakah air P3A
tepat waktu dantepat jumlah.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-3


LAPORAN AKHIR

Penanggung
No. Uraian Kegiatan
Jawab

 Memonitor dengan pengecekam debit atau pengaturan pintu bagi dan


sadap tersier secara rutine/ periodik pada wilayahnya kerjanya.
15 Juru
 Pengecekan /lnformasi debit di bendung.
 Cukup atau kurang dikaitkan dengan faktor K.

 Membuat laporan luas tanaman, luas pengolahan tanah, debit serta curah
16 Juru
hujan.

8.3 OPERASI BANGUNAN PADA JARINGAN IRIGASI


8.3.1 Bangunan Utama
Bangunan utama adalah bangunan yang dibangun di sungai untuk mengarahkan atau membelokkan
air sungai ke jaringan irigasi sedemikian rupa agar jumlah pengaliran air-nya dapat diatur, dan
endapan serta kotoran yang masuk ke saluran dapat se-sedikit mungkin.
Bagian dari bangunan utama diantaranya :
8.3.1.1 Bendung
 Pintu pengambilan/Intake
 Bangunan pembilas/penguras
 Lantai pengaman Hulu dan Hilir

 Tanggul
8.3.1.2 Bangunan Pengambilan I Intake
Dalam pengoperasian bangunan utama tersebut, selain pintu pengambilan perlu juga diperhatikan
fungsi bangunan yang lain yaitu penguras dan kantong lumpur. Pengaturan debit di pintu
pengambilan diatur sedemikian rupa, sehingga sedimen yang terlanjur masuk ke saluran bisa sedikit
mungkin, sedang sedimen/endapan yang terlanjur masuk pintu pengambilan diusahakan supaya
dapat mengendap di kantong lumpur.
Berikut ini adalah beberapa pertimbangan dalam pengoperasian pintu pengambilan antara lain :'
 Debit yang masuk pintu pengambilan, diatur dengan menarik/menurunkan pintu secara
manual maupun dengan mesin.
 Pada saat debit sungai kecil, kecepatan lebih kecil dari pada kecepatan maksimum saluran,
seluruhnya akan disadap untuk Irigasi.
 Sebaliknya saat debit air sungai bertambah besar/banjir, biasanya pada kondisi seperti ini
air sungai membawa sedimen/lumpur sehingg perlu dipertimbangkan apakah pintu
pengambilan perlu diturunkan atau tidak, agar sedimen yang masuk bisa se-sedikit mungkin.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-4


LAPORAN AKHIR

 Pada saat banjir besar, pintu pengambilan di tutup semua dan pintu penguras diangkat yang
disesuaikan dengan karakter sungai (bahan yang hanyut).
Bangunan ini dilengkapi dengan pintu satu atau lebih sesuai kebutuhan, yang fungsinya :
 Mengatur air Irigasi yang masuk saluran.

 Mencegah air banjir masuk ke saluran.


 Menjaga agar endapan dan kotoran-kotoran/sampah di sungai tidak masuk ke saluran.
Pengaturan bangunan pengambilan selama operasi berlangsung kalau pintu pengambilan yang
mempunyai lebih dari satu pintu tinggi bukaan pintu harus sama kecuali ada perbaikan atau
kerusakkan yang di tutup sehingga pengaliran air dihentikan agar endapan atau sampah tidak masuk
saluran. Pada saat banjir, pintu pengambilan ditutup dan setelah banjir berhenti dan air akan di
alirkan ke saluran lagi dan sebelum pintu pengambilan dibuka kembali, sampah yang ada didepan
pintu dibersihkan terlebih dahulu.
Disamping itu hal yang perlu diperhatikan petugas adalah :

 Mencatat tinggi muka air.


 Waktu terjadi banjir, mengecek bukaan pintu pagi dan sore.

 Pengaliran debit untuk kalibrasi lengkung debit.


8.3.1.3 Bangunan Pembilas atau Penguras
Merupakan bagunan yang mempunyai satu kesatuan dengan bendung yang berada di depan
bangunan pengambilan, dan membentuk kantong yang dasarnya lebih rendah dari pada ambang
pintu pengambilan dan biasanya dasar kantong pembilas sama dengan dasar sungai yang dilengkapi
dengan pintu.
 Fungsi bangunan pembilas :
 Mengarahkan alur aliran sungai, sehingga dekat dengan pintu pengambilan.
 Membilas atau menguras endapan yang ada dikantong pembilas .
 Melepaskan banjir tahunan yang lebih besar.
Pengoperasian bangunan pembilas pertama menutup pintu pengambilan, dan kemudian pintu
pembilas dibuka, sehingga endapan terangkut aliran. Setelah kantong endapan bersih, kemudian
pintu pembilas ditutup, dan pintu pengambilan dibuka kembali sesuai dengan kebutuhan.
Cara pengoperasian pintu pembilas dibedakan :

 Sistem operasi kolam tenang, yaitu dengan menutup pintu penguras, dan air yang masuk ke
saluran sama dengan yang diperlukan saja, sehingga kecepatan air dikantong pembilas
rendah dan endapan dibiarkan mengendap. Setelah tebal/ketinggian endapan cukup (0,5
m), pintu pembilas dibuka untuk membilas endapan, dan setelah endapan bersih, pintu air
ditutup kembali .

 Sistem operasi kolam semi tenang yaitu pintu pembilas dan pengambilan sama dibuka,
dengan debit yang dialirkan ke pintu pembilas lebih besar dari pada debit yang dialirkan

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-5


LAPORAN AKHIR

kesaluran. Pada cara ini endapan mengendap tetapi melayang dan karena kecepatan ke
pembilas lebih besar maka endapan akan ikut aliran ke pembilas.
8.3.1.4 Kantong Lumpur
Kantong lumpur berfungsi untuk mengurangi banyaknya sedimen/endapan yang terangkut ke
saluran, dengan memberi kesempatan untuk sedimen tersebut mengendap dikantong lumpur pada
pangkal atau awal saluran, karena kecepatan airnya lebih kecil dari pada kecepatan air di sungai,
sehingga sedimen yang ikut terus pada aliran air di saluran adalah sedimen yang lebih halus. Oleh
karena itu, pengoperasiannya harus benar, sehingga sedimen yang masuk ke saluran dapat ditekan
se sedikit mungkin, dan pelayanan air lebih lancar.
Pada waktu kantong lumpur endapan bertambah (tebal), hal ini berarti kecepatan air akan
bertambah dan sedimen tidak mengendap lagi tetapi ikut aliran air disaluran bagian hilirnya dan
akhirnya ke sawah.
Pada kondisi seperti di atas, kantong lumpur harus dikuras yaitu dengan menutup pintu di saluran,
sehingga muka air akan naik dan selanjutnya pintu pengambilan diatur (ditambah) bukaannya
sehingga air yang masuk saluran sama dengan debit air untuk menguras dan kemudian pintu
penguras bisa dibuka penuh, dengan demikian lumpur akan terangkut semuanya.
Dengan pelayanan air irigasi demikian, air dikantong lumpur turun dan akhirnya menguras lumpur
yang ada sehingga air irigasi tidak menggangu.
Setelah pengurasan selesai, pintu penguras ditutup, dan muka air dikantong lumpur akan naik
sehingga pintu pengambilan bisa diatur sesuai dengan kebutuhan dengan membuka pintu saluran.

8.3.2 Jaringan Irigasi


Jaringan Irigasi terdiri dari saluran induk kuarter dan tersier serta bangunan-bangunan bagi/sadap
dan bangunan pengatur serta bangunan-bangunan pelengkap lainnya.
Pengoperasian jaringan irigasi dimaksudkan untuk melayani kebutuhan air irigasi ke seluruh
arealIsawah terjamin, dengan tepat jumlah dan tepat waktu, tanpa mengabaikan keamanan jaringan
irigasi itu sendiri, khususnya tanggul saluran, untuk itu diperlukan kemampuan, ketrampilan,
pengetahuan dan juga jumlah petugas serta sarana penunjang yang memadai.
8.3.2.1 Saluran
Pengoerasian Jaringan Irigasi pada umumnya berdasarkan jadwal dan tata tanam yang telah
ditetapkan oleh panitia pengairan.
Berdasarkan ketentuan peraturan tersebut yang berupa SK jadwal dan pola tanam, petugas (mantri
/ juru pengairan) seharusnya mengetahui hal – hal sebagai berikut, diantaranya :
 Waktu I jadwal pengaliran I pemberian air.

 Tata tanam.
 Kapasitas saluran.
 Debit yang dibutuhkan pada masing-masing petak tersier.
 Sistim pemberian air (golongan/giliran).

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-6


LAPORAN AKHIR

SK dan jadwal pola tanam tersebut akan dipergunakan untuk koordinasi dan informasi beberapa
saat sebelum pelaksanaan dimulai, diantaranya :
 Menginformasikan kepada petani/P3A kapan pemberian air dipetak tersier, bagaimana cara
pemberiannya, dengan demikian petani/P3A akan mengadakan persiapan-persiapan,
misalnya pembersihan saluran tersier, tenaga kerja; dan sarana lainnya.

 Sedang dalam pelaksanaannya, mantri/juru pengairan harus mengatur kapasitas debit


saluran dan debit yang dialirkan supaya tidak melebihi. Mengatur debit pada masing-masing
saluran melalui pintu pengatur sehingga tinggi muka air sesuai dengan debit yang
dibutuhkan dan aman (tidak melimpas).

 Dalam pengaturan debit, petugas perlu kesabaran dan hati-hati dalam menilai serta
memantau pintu air, karena debit yang diterima pun belum tentu stabil atau sesuai dengan
yang direncanakan. Dalam pengaturan air tersebut, kalau pada bangunan pengatur belum
ada pintu maka dapat dipergunakan scot balk .

 Kemungkinan yang terjadi :


 Debit kecil maka petugas juru/mantri pengairan mengevaluasi tinggi muka air di hulu
saluran, dan kemudian mengupayakan dengan mengatur tinggi muka air normal melalui
pintu pengatur.
 Selanjutnya menginformasikan serta memonitor keadaan air di bangunan-bangunan bagi
dan pintu sadap, yang ada dalam wilayah kerjanya apakah sudah sesuai dengan rencana.
Kalau hal ini masih berlanjut dan debit tidak cukup, maka dapat mengambil langkah
pemberian air dengan giliran.
 Debit besar, petugas harus segera memberi laporan ke atasannya (Ranting Dinas/UPTD)
sehingga kelebihan debit dapat dipindah/dengan mengalokasikan ke areal/wilayah lainnya,
selanjutnya mengadakan lnspeksi kemungkinan terjadi over toping pada tanggul saluran.
 Hujan lebat
Bila terjadi hujan di daerah Irigasi, maka langkah yang perlu diambil adalah :
 Inspeksi lapangan sehingga mengetahui kondisi lapangan.
 Kalau kondisi air di persawahan ada tanda lebih,sebaiknya pintu-pintu sadap tersier,
sampai pintu pengambilan dikurangi atau di turunkan.
 Untuk air lebih di persawahan dapat disalurkan atau dibuang ke saluran pembuang.
 Berkaitan dengan hal tersebut, untuk keamanan saluran pada tempat tertentu
diberikan tanda tinggi muka air maksimum dengan harapan kalau tinggi muka air di
saluran melebihi maksimum, masyarakat akan dapat membantu memberi tahu kepada
petugas.
 Pada saat terjadi kerusakkan (misalnya tanggul jebol) maka harus diambil tindakan
cepat oleh petugas yaitu memindahkan aliran air kesaluran yang lain dengan kondisi
yang lebih aman atau kesaluran yang masih mampu menerima tambahan debit,

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-7


LAPORAN AKHIR

selanjutnya menutup pintu pemberi atau pengatur kemudian melaporkan ke Ranting


Dinas/UPTD agar segera dapat dilakukan Iangkah-langkah perbaikan.
8.3.2.2 Bangunan Pengatur
Bangunan pengatur mempunyai fungsi untuk mengatur tinggi muka air pada saluran induk kuarter
dibagian hulunya, sehingga pembagian dan pemberian air sesuai dengan kebutuhan/ rencana debit
pada masing-masing pintu. Karena bangunan pengatur bukan alat pengukur debit maka untuk
mengetahui debit di bagian hilirnya, dipergunakan dengan kurva dan tabel debit pada aliran pintu
yang sudah dikalibrasi sehingga mudah dalam melaksanakannya.
Operasi dan pengaturannya :
 Petugas harus memonitor dengan mengamati debit air di saluran pada papan duga apakah
tinggi muka air sudah sesuai rencana atau belum, selain itu ada kemungkinan ada kebocoran
atau rusak pada tanggul saluran dan lain-lain .
 Pada saat debit berkurang atau muka air turun maka pintu pengatur diturunkan atau
dengan menambah sekat balok (kalau belum ada pintu pengatur), sehingga muka air saluran
(di hulunya) naik kembali pada muka air sebelumnya, dengan demikian debit-debit pada
bangunan sadap sudah sesuai dengan rencana.
 Pada waktu musim tanam/pemberian air, bila ada bagian saluran yang rusak perlu segera
diperbaikki, maka pintu pengatur ditutup beberapa saat untuk melakukan perbaikan. Bila
akan diadakan pengukuran debit disaluran, pintu pengatur dibuka penuh dan kalau itu
berupa sekot balok supaya diangkat, sehingga tidak terjadi Back Water.
Pengoperasian hanya dapat dilakukan oleh petugas, dan selalu terkunci.
8.3.2.3 Pintu Pengambilan atau Sadap
Pada umumnya pintu-pintu disaluran induk atau kuarter di lengkapi dengan tabel dan kurva debit
yang telah di kalibrasi, dan telah memperhitungkan kehilangan air di saluran. Pada pengoperasian
atau pengaturan pintu air, untuk mendapatkan tinggi muka air yang diinginkan hal yang perlu
diperhatikan adalah :

 Pengaturan pintu perlu hati-hati dan cermat, sehingga memerlukan waktu yang lama.
 Pintu air akan di atur hanya oleh petugas pada saat terjadi perubahan tinggi muka air dan
atau jadwal yang sudah ditentukan dengan menyesuaikan kebutuhan air dan kemudian
dikunci supaya tidak dirubah posisinya/ pencurian air .
 Petugas mencatat debit yang dialirkan setiap hari.
8.3.2.4 Pintu Sadap Tersier
Pengoperasian pintu sadap tersier hanya dilakukan oleh petugas juru pengairan dengan mengatur
pintu sesuai dengan debit yang dibutuhkan.
Dalam pengoperasian pintu tersier, petugas pengairan berkoordinasi dengan P3AIpetani agar
jadwalItata tanam yang telah direncanakan dapat dilaksanakan dengan tepat, yaitu tentang :

 Luas persiapan olah tanah dan pembibitan, dalam kaitannya dengan waktu pengaliran dan
debit air.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-8


LAPORAN AKHIR

 Luas olah tanah, luas tanaman padi, palawija dan lain-lain guna mengatur debit sesuai
dengan kebutuhan air. Dan selanjutnya pemberian air akan disesuaikan dengan luas dan
tahap/ masa pertumbuhan tanaman.
 Pengaturan pada saat hujan besar, pintu tersier akan di tutup atau dikurangi debitnya
supaya sawah tidak terendam.
 Setiap saat setelah pintu tersier selesai diatur harus dikunci supaya tidak berubah posisinya
I terjadinya pencurian air.

8.4 ALAT PENGUKUR DEBIT


Pada pengelolaan jaringan irigasi yang bangunan-bangunannya (pintu-pintu dan saluran) dilengkapi
dengan alat pengukur debit dengan harapan pengelolaan air akan lebih efektif karena semua aliran
dapat diketahui besamya, sehingga tidak terbuang dan sesuai dengan kebutuhan.
Berikut ini adalah beberapa alat yang digunakan dalam pengukuran debit yaitu :

 Ambang Lebar
 Alat ukur Parshall Flume
 Pengukuran debit saluran tidak menggunakan bangunan ukur.

8.4.1 Ambang Lebar


Ambang lebar merupakan alat ukur debit pada saluran yang tersedia/mempunyai beda tinggi muka
air bagian hulu dan hilir, dengan ambang tajam yang bentuknya segi empat, dan lebar ambang
sekurang-kurangnya 2 (dua) kali tinggi energi diatas ambang.
Debit diukur dengan membaca tinggi muka air pada duga yang dipasang dibagian hulu.
Kebaikannya :
 Bangunan sederhana dan murah

 Debit mudah dilaksanakan dengan mengamati tinggi muka air.


 Kotoran (sedimen) yang halus mudah terangkut aliran .
Kelemahannya :

 Memerlukan tinggi energi yang cukup


 Tidak dapat mengatur debit
 Bila digunakan pintu sorong untuk mengatur, perubahan pintu sorong tidak sebanding
dengan besarnya debit.

8.4.2 Alat Ukur Parshall Flume


Merupakan alat ukur debit pada saluran terbuka dan hanya memerlukan tinggi energi kecil.
Debit air yang melalui alat ukur ini dapat berupa aliran bebas, yaitu bila tidak ada/terjadi olakan air
yang merupakan Back Water yang cukup sehingga mengurangi besarnya debit. Dan aliran ini
terendam, bila di bagian hilir leher muka airnya cukup tinggi dibanding ambang Flume, sehingga

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-9


LAPORAN AKHIR

dapat mengurangi besarnya debit, dan untuk aliran merendam biasanya dihindari karena ada
kesulitan perhitungan.
Kelebihan:
 Pengukuran debit mudah dilakukan

 Kehilangan tinggi energi kecil


 Mampu mengukur debit pada aliran bebas yang beubah-ubah
 Tidak ada kotoran yang tinggal (karena alirannya cepat)
 Aliran tetap/ tidak dapat berubah-ubah
Kelemahan:

 Penggunaanya sulit dan mahal


 Tidak dapat mengatur debit
 Tidak dapat dikombinasikan dengan bangunan pengatur lainnya.

8.4.3 Pengukuran debit saluran tidak menggunakan bangunan ukur


Pada saluran yang beda tinggi muka airnya kecil sekali dan tidak dapat dilengkapi/dibangun
bangunan pengukur debit, maka dalam pengoperasian jaringan irigasi perlu dilakukan pengukuran,
yaitu dengan menggunakan pelampung dan stop watch, dan atau dengan Current meter.
Pengukuran debit dengan menggunakan pelampung dan stop watch dengan cara :
 Menentukan ruas saluran yang lurus dengan panjang 50 – 100 m (pada jembatan atau
lainnya) guna melepas pelampung.
 Menghitung lama atau kecepatan pelampung pada saluran sepanjang 50 – 100 m tersebut
beberapa kali.

8.5 PEMELIHARAAN JARINGAN IRIGASI


Pemeliharaan Jaringan Irigasi adalah upaya menjaga dan mempertahankan kondisi dan fungsi
jaringan, sehingga penyediaan, pembagian dan pemberian air dari sumbemya sampai ke petak-
petak sawah sesuai dengan rencana. Selain itu kegiatan tersebut juga dimaksudkan agar Jaringan
Irigasi mempunyai umur pelayanan yang panjang. Pada kegiatan pemeliharaan jaringan Irigasi dapat
dibagi :

8.5.1 Persiapan Pemeliharaan Jaringan lrigasi


Kegiatan persiapan ini dengan melakukan pemeriksaan Jaringan Irigasi, yang menyangkut ;
 Pemeriksaan kondisi struktur bangunan yang terkait dengan fungsinya dalam pengaliran air.

 Pemeriksaan kondisi stabilitas bangunan


Maksud kegiatan pemeriksaan tersebut adalah untuk mengetahui gangguan/hambatan
pengaliran air yang diakibatkan kondisi bangunan, misalnya kebocoran, bangunan yang
besar; dan lain-lain serta mendata kerusakkan-kerusakan tersebut. Sehingga dengan

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-10


LAPORAN AKHIR

pemeriksaan tersebut dapat diketahui secara dini kerusakan atau hambatan yang terjadi,
dengan demikian dapat mengantisipasi lebih awal dan dapat dihindari kerusakan yang fatal.
Bangunan-Bangunan Jaringan lrigasi yang diperiksa meliputi :
a. Bangunan Utama
b. Saluran
c. Pintu air
8.5.1.1 Bangunan Utama
Yang perlu diperhatikan adalah :

 Bendung
Yaitu pada bagian-bagian lantai bangunan di Hulu dan Hilir. Pada bagian hilir biasanya lebih
memungkinkan terjadinya penggerusan, dan juga sering terjadi rongga dibawah lantai, serta
kemungkinan lain terjadinya keretakan bangunan.
 Bangunan pengambilan (Intake)
Di depan pintu biasanya terjadi penumpukan sampah atau kotoran, dan yang jadi masalah
adalah bagaimana memberisihkannya.
Dalam pengoperasian manual/ mesin dan kesulitannya, apakah pintu-pintu tersebut dapat
diopersikan semua atau tidak .

 Bangunan Penguras/pembilas
Yang perlu diperikasa seperti halnya pintu pengambilan yaitu mengenai sampah yang ada
didepan pintu, sedang endapan dapat dibersihkan dengan gelontoran melalui pintu
penguras .
 Tanggul
Yang perlu diamati terjadinya kerusakan dan penurunan permukaan tanggul atau terkikis
/erosi
8.5.1.2 Saluran
Pada saluran, yang menjadi masalah diantaranya endapan, sampah, atau kotoran, bocor, rembesan,
erosi atau longsoran, serta tanaman yang tumbuh.I - Orasi & Pemeliharaan
Untuk itu pemeriksaan mengarah pada hal-hal tesebut, dan menghindari terjadinya masuknya air
buangan dari kampung ke saluran pada saat hujan.
Pada saluran tanah dengan timbunan pemeriksaan pada kemungkinan terjadinya penyusutan,
penurunan permukaan dan keretakan.
Endapan pada saluran bisa disebabkan karena :

 Banyaknya endapan yang masuk melalui pintu pengambilan karena operasi yang kurang
tepat
 Masuknya air buangan ke saluran Irigasi

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-11


LAPORAN AKHIR

 Saat banjir pintu pengambilan tidak ditutup

 Pintu yang rusak atau bocor,dan lainnya


Saluran Drainase
Saluran drainase akan mengalirkan air saat terjadi air lebih. Hal itu terjadi pada saat hujan dan banjir,
sedang pada saat tidak hujan jarang terjadi aliran sehingga saluran menjadi kering. Oleh karena itu
banyak ditumbuhi rumput atau tanaman serta sampah. Hal ini akan berdampak pada saat terjadi
banjir besar.
8.5.1.3 Pintu Air
Permasalahan pada pintu air biasanya pada pintu yang sudah lama, berkarat, sehingga sulit dibuka
atau ditutup serta kemungkinan terjadi kebocoran. Pemeriksaan pintu air akan lebih baik saat
pengeringan saluran. Disamping hal tersebut yang sering terjadi yaitu sampah/kotoran yang
terkumpul didepan pintu, sehingga akan menggangu aliran dan membendung.

8.5.2 Pemeliharaan
Kegiatan pemeliharaanya dibagi :
a. Tahap perencanaan
b. Tahap pelaksanaan
8.5.2.1 Tahap Perencanaan Pemeliharaan
Pada tahap ini kegiatannya mencakup inventarisasi kondisi dan fungsi jaringan irigasi dengan
maksud untuk menentukan prioritas pemeliharaanya.
Untuk menentukan bangunan mana yang mendapatkan prioritas pemeliharaan, diperlukan
beberapa kategori kondisi dan kategori fungsi jariangan irigasi. Kategori kondisi adalah kondisi
bangunan menurut desain semula, yang dapat dibedakan :
 Kategori baik atau rusak ringan yaitu kerusakan bangunan ringan dan dapat diatasi melalui
pemeliharaan rutin.
 Kategori rusak sedang yaitu kerusakan tidak terlalu berat dan perbaikannya tidak
memerlukan keahlian khusus.
 Kategori rusak berat yaitu kerusakkan yang perlu ditangani dengan ketrampilan dan biaya
yang cukup.
Kategori fungsi didasarkan pada tingkat pelayanannya, yang dibedakan menjadi:

 Berfungsi baik, kalau fungsinya dalam pelayanan lebih besar dari 80% (kriteria desain).
 Berfungsi kurang, kalau fungsi pelayanannya lebih kecil dari 80% (kriteria desain).

 Tidak berfungsi, kalau bangunan tidak dapat berfungsi dalam pelayanan air.
Prioritas pemeliharaan ditentukan dengan dasar keutamaan fungsi. Meskipun kerusakan kecilpada
suatu bangunan, kalau akibat kerusakan tersebut menyebabkan terganggunya pelayanan air dalam
cakupan area yang lebih luas maka bangunan tersebut akan diprioritaskan pemeliharaanya
dibanding suatu perusahaan yang besar pada suatu bangunan tetapi luas daerah pelayanannya lebih

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-12


LAPORAN AKHIR

kecil. Sebagai contoh pada suatu daerah irigasi kerusakan bendung yang kecil akan mendapatkan
prioritas pemeliharaan daripada kerusakan saluran kuarter.
Disamping itu karena fungsinya fasilitas penunjang juga bisa mendapatkan prioritas pemeliharaan
karena fasilitas tersebut dapat mempengaruhi fungsi pelayanan. Sebagai contoh kerusakkan jalan
inspeksi akan berpengaruh pada transportasi alat pengolah tanah maupun hasil produksi.
Kegiaran selanjutnya adalah menghitung rencana biaya pemeliharaan dari masing-masing kerusakan
bangunan, dan kemudian dilanjutkan dengan membuat jadwal pelaksanaan.
Pada pelaksanaan pemeliharaan tersebut penanganannya dapat melalui pemeliharaan rutin dan
berkala dengan swakelola, dan diborongkan.
Dalam proses persiapan pemeliharaan sampai dengan usulan rencana biaya perlu diingat waktunya
sehingga bahan-bahan tersebut telah siap sebelum usulan anggaran disusun.
8.5.2.2 Tahap Pelaksanaan
Pada pelaksanaan pemeliharaan akan dipengaruhi besarnya dana yang tersedia, kalau dananya lebih
besar pelaksanaanya akan mudah, namun kalau dananya yang tersedia lebih kecil maka akan ada
sebagian pekerjaan pemeliharaan yang tidak dapat dilaksanakan. Dalam hal ini dengan tersedianya
urutan prioritas maka akan mudah menentukan pekerjaan mana yang tidak dilaksanakan.
Pekerjaan perneliharaan cara pelaksanaannya dibedakan:
 Dengan swakelola yaitu pekerjaan yang dikerjakan sendiri oleh petugas, sehingga
pelaksanaannya akan lebih cepat dimulai namun hasil pekerjaannya kurang baik .
Dengan diborongkan yaitu pekerjaan yang dikerjakan oleh pemborong dan pada umumnya pada
pekerjaan yang tidak mendesak atau waktu pelaksanaanya dapat direncanakan.
Disamping itu pekerjaan pemeliharaan dapat dikelompokan menjadi :
 Pemeliharaan rutin yaitu pemeliharaan yang dilakukan terus menerus sepanjang tahun
selama sistem jaringan irigasi tersebut beroperasi. Kegiatan ini tidak nmemerlukan
ketrampilan khusus dan biasanya dipekerjakan oleh petugas atau pekerja pengairan.
Termasuk pekerjaan ini diantaranya pemeliharaan pembersihan tanggul saluran,
pembersihan/pengangkatan lumpur, pelumasan dan pengecatan pintu air, perbaikan ringan
bangunan dan lain-lain.

 Pemeliharaan berkala yaitu pekerjaan perneliharaan yang dilakukan secara berkala


terutama pada waktu pengeringan saluran. Pekerjaan ini memerlukan perencanaan yang
lebih rinci serta dana yang lebih besar dan perlunya pengawasan. Cara pelaksanaannya
dapat diborongkan atau dengan swakelola. Termasuk pekerjaan ini diantaranya : perbaikan
bendung, perbaikan/ penggantian pintu air, penggantian papan duga air, pengangkatan
lumpur di saluran dan lain-lain .
 Pemeliharaan darurat yaitu pekerjaan pemeliharaan atau perbaikan yang tidak dapat
diperkirakan sebelumnya dan biasanya akibat dari bencana banjir, gempa bumi, dan lain-
lain.
Dalam mengatasi pemeliharaan darurat biasanya dilaksanakan dengan pekerjaan perbaikan yang
sifatnya darurat/sementara, yang pada waktu kemudian akan diperbaiki secara permanen.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-13


LAPORAN AKHIR

8.6 EVALUASI OPERASI JARINGAN LRIGASI


Evaluasi jaringaan irigasi mempunyai maksud dan tujuan untuk mengamati dan memonitor perilaku
kegiatan O&P dan efisiensi pelayanan pemanfaatan dari air yang tersedia terhadap kebutuhan air
pada lahan sawah. Melalui kegiatan tersebut akan diketahui kinerja O&P jaringan irigasi. Dan
selanjutnya dari hasil tersebut dapat dipergunakan untuk menyikapi kegiatan O&P berikutnya, yaitu
dengan menindak lanjuti masalah-masalah yang ada.
Permasalahan dalam evaluai jaringaan irigasi di bedakan menjadi aspek teknis dan aspek non teknis.
 Aspek teknis, yang termasuk aspek teknis diantaranya :
 Debit sungai yang stabilitas debitnya akan sangat dipengaruhi oleh kondisi chatman
area, sedang kualitas air sungai dipengaruhi oleh limbah yang masuk..
 Jaringan Irigasi.
Kondisi dan fungsinya akan berpengaruh terhadap kelancaran, besar debit serta keamanan
pengaliran air irigasi .

 Aspek Non Teknis, meliputi :


 Sumber daya manusia (SDM)
Keberasilan kegiatan O&P jaringan irigasi akan ditentukan oleh kemampuan,
ketrampilan, jumlah petugas serta sarana penunjang yang memadai.
 Petani, akan berpengaruh pada jumlah tenaga kerja yang tersedia khususnya pada masa
pengolahan tanah dan panen, dengan jumlah petani yang memada maka jadwal
pemberian air dan pola tanam serta pengolahan tanah akan dapat dilaksanakan sesuai
rencana. Selain itu juga kemampuan petani juga berpengaruh terhadapa kegiatan
pertanian lainnya.
 Pertanian, yang terkait diantaranya pola tanam, hal ini akan berpengaruh terhadap
kebutuhan air penyediaan sarana produksi dan harga pasca panen.
 Kelembagaan, banyak dinas/instansi yang terkait dalam O&P jaringan irigasi, untuk itu
biasanya dibentuk wadah yang disebut panitia irigasi/Panitia tata pengaturan air.
Kelembagaan ini merupakan wadah koordinasi dinas instansi tentang sumber daya air
(SDA) secara menyeluruh. Dengan demikian permasalahan yang terjadi yang berkaitan
dengan air dapat di bahas pada lembaga ini. Diantaranya : stabilitas debit sungai yang
diakibatkan oleh akan dipengaruhi oleh kondisi catchment area, kualitas air sungai yang
diakibatkan oleh limbah yang masuk, dll.
 Kelembagaan petani (P3A) selain sebagai pemilik Iahan tetapi juga pelaku O&P ditingkat
tersier, sehingga keberadaanya yang akan menunjang aktifitas kegiatan-kegiatan di
petak tersier baik dalam O&P jaringan tersier maupun dalam pengadaan tenaga dan
sarana-sarana produksi pertanian.

 Sedangkan aspek alami terutama yang menyangkut masalah iklim seringkali tidak sesuai
dengan yang diperhitungkan, untuk itu maka saat terjadi penyimpangan kiranya perlu
dipersiapkan langkah-langkah altematif yang perlu ditempuh.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-14


LAPORAN AKHIR

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8-15


LAPORAN AKHIR

BAB 9 ORGANISASI PELAKSANA


DAN RENCANA KERJA

9.1 UMUM
Organisasi pelaksanaan pekerjaan disusun dengan tujuan sebagai berikut :
a. Terciptanya sistem koordinasi yang baik antara konsultan dan pemberi tugas
b. Terciptanya koordinasi yang baik antara unit-unit kerja yang terlibat dalam penanganan
pekerjaan.
c. Terjaminnya kelancaran jalannya pekerjaan secara keseluruhan.

9.2 STRUKTUR ORGANISASI


Seluruh pekerjaan akan dilaksanakan dibawah tanggung jawab langsung para tenaga ahli yang sesuai
dengan latar belakang pendidikan, latihan/kursus, pengalaman, wawasannya yang berpengetahuan
luas dan ahli dalam melakukan perencanaan sejenis, serta para tenaga ahli tersebut akan
bertanggung jawab atas hasil pekerjaannya.
Penyelesaikan pekerjaan DED DI Gudang akan dilaksanakan oleh beberapa tenaga ahli dari berbagai
disiplin keahlian bidang pekerjaan, antara lain Ahli Sumber Daya Air dan Ahli Landscape/Geodesi.
Susunan personil tenaga ahli yang terlibat dalam pelaksanaan pekerjaan ini sebagaimana tercantum
dalam daftar berikut:

Team Leader

Ahli Sumber
Ahli Geodesi
Daya Air

Drafter Administrasi Surveyor

Asisten
Surveyor

Gambar 9.1 Struktur Organisasi Pelaksanaan

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 9-1


LAPORAN AKHIR

Tabel 9.1 Daftar Personil Tenaga Ahli Pelaksanaan Pekerjaan

Jumla
Posisi
Lingkup Keahlian Uraian Pekerjaan h
Diusulkan
Orang
Ahli Sumber Team a. Mengkoordinasikan semua personil yang terlibat dalam 1
Daya Air Leader pekerjaan ini sehingga bisa menghasilkan suatu
perencanaan yang baik.
b. Mempersiapkan petunjuk teknis dari setiap kegiatan
pekerjaan baik pengambilan data, pengolahan maupun
penyajian akhir seluruh hasil pekerjaan.
c. Berkoordinasi dengan pejabat pembuat komitmen dala
hal pelaksanaan pekerjaan.
d. Meneliti dan menyarankan material yang dapat
dimanfaatkan.
Ahli Sumber Daya Tenaga a. Menerapkan Ketentuan UUJK, K3, Lingkungan dan Kode 1
Air Ahli Etik Profesi.
b. Menyusun pekerjaan persiapan.
c. Melakukan survey awal.
d. Menyusun rencana kerja pekerjaan hidrologi dan
hidraulika.
e. Melaksanakan pekerjaan analisis hidrologi dan
hidraulika.
f. Menyusun laporan hasil pekerjaan hidrologi dan
hidraulika.
g. Melaksanakan komunikasi dengan pihak lain.
Ahli Tenaga a. Menerapkan Ketentuan UUJK, K3, Lingkungan dan Kode 1
Geodesi/Landsca Ahli Etik Profesi.
pe. b. Menyusun pekerjaan persiapan.
c. Melakukan survey awal.
d. Menyusun rencana kerja pekerjaan geodesi.
e. Melaksanakan pekerjaan geodesi berupa pemetaan
topografi.
f. Menyusun laporan hasil pekerjaan geodesi.
g. Melaksanakan komunikasi dengan pihak lain.

Tabel 9.2 Daftar Personil Tenaga Pendukung Pelaksanaan Pekerjaan

Jumlah
Posisi
Lingkup Keahlian Uraian Pekerjaan Orang
Diusulkan
Bulan
Surveyor Tenaga a. Mempersiapkan rencana pelaksanaan pengukuran di 1
Pendukung lapangan
b. Mempersiapkan baik perhitungan maupun gambaran
hasul pengukuran beserta laporannya.
c. Berkoordinasi dengan draffman untuk kegiatan
perencannan dan gambar.
Pembantu Tenaga Membantu surveyor untuk mengumpulkan semua data yang 1
Surveyor Pendukung dibutuhkan dari lapangan dan bertanggung jawab atas
ketelitian hasil yang didapat.
Pembantu Tenaga Membantu surveyor untuk mengumpulkan semua data yang 1
Surveyor Pendukung dibutuhkan dari lapangan dan bertanggung jawab atas
ketelitian hasil yang didapat.
Draftman Tenaga Membantu tenaga ahli dalam membuat dan menyiapkan 1
Pendukung gambar teknis.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 9-2


LAPORAN AKHIR

Jumlah
Posisi
Lingkup Keahlian Uraian Pekerjaan Orang
Diusulkan
Bulan
Administrasi Tenaga a. Membantu tenaga ahli dalam membuat dan 1
Pendukung mempersiapkan administrasi pendukung proyek, seperti
surat menyurat.
b. Menyusun dan merapikan pengarsipan dokumen
proyek.
c. Mengatur administrasi proyek.

9.3 JADWAL PELAKSANAAN


Untuk menunjang kelancaran pelaksanaan kegiatan DED DI Gudang Kabupaten Bangka Selatan,
perlu disusun program kegiatan yang mencakup jadwal rencana pelaksanaan kegiatan, serta jadwal
pengerahan/mobilisasi personil maupun peralatan/perlengkapan kerja untuk setiap tahapan
kegiatan. Rumusan jadwal rencana pelaksanaan kegiatan harus dikoordinasikan terlebih dahulu dan
mendapat persetujuan pihak Direksi/Pengawas Pekerjaan dengan mempertimbangkan tingkat
kesulitan, kebutuhan waktu pelaksanaan, asistensi / diskusi pembahasan dan pelaporan.
Jadwal pelaksanaan pekerjaan disusun team Konsultan sebagai alat kendali dan panduan kegiatan :
mencakup pertimbangan kebutuhan waktu pelaksanaan survai, proses kajian/analisa, pelaporan
serta diskusi. Rumusan jadwal pelaksanaan pekerjaan merupakan masukan penting dalam analisis
dan rumusan Rencana Anggaran Biaya (RAB) pelaksanaan kegiatan ini. Jadwal pelaksanaan kegiatan
disajikan pada Tabel 9.3.
Tabel 9.3 Jadwal Rencana Pelaksanaan Pekerjaan

Tabel 9.4 Kurva S Pekerjaan DI Gudang

Jadwal penugasan personil disusun team Konsultan sebagai alat kendali dan panduan kegiatan
mencakup pertimbangan kebutuhan waktu penugasan personil, proses kajian / analisa, pelaporan
serta monitoring evaluasi. Jadwal penugasan personil disajikan pada tabel berikut.
Tabel 9.5 Jadwal Penugasan Tenaga Ahli

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 9-3


LAPORAN AKHIR

BAB 10 SIMPULAN DAN SARAN

10.1 SIMPULAN
Berdasarkan hasil analisis tahap akhir pada pekerjaan DED DI Gudang dapat ditarik sebagai berikut:
 Berdasarkan hasil analisis terkait dengan kondisi dan potensi di Areal Daerah Irigasi (DI)
Gudang bahwa kondisi lapangan mengharuskan pengembangan jaringan irigasi tersier
teknis untuk dilakukan.

 Setelah melakukan analisis ketersediaan air dengan metode NRECA dan Sacramento serta
mencari kebutuhan air dengan analisis kebutuhan air irigasi, maka diperoleh grafik neraca
air untuk DAS Gudang. Hasil debit sintetis NRECA menunjukan nilai 0.103 m3/s untuk
probabilitas 80%.

 Ketersediaan air di Bendung DI Gudang (ADAS = 6.16 km2) direncanakan mengairi sampai
dengan 97.5 Ha untuk 2 pola tanam (padi-padi) dengan nilai NFR sebesar 1.03 l/dt/ha.
Luasan areal tersebut merupakan pengembangan tahap-1 (100 Ha) untuk DI Gudang.

 Rencana bendung akan berada di Sungai Babuar dan direncakan pada elevasi mercu +34.0
mdpl. Elevasi mercu didasarkan pada elevasi sawah paling hilir, yaitu pada elevasi +17.0
mdpl. Dengan pertimbangan hidraulis, yaitu panjang rencana saluran ±4.3km dengan
kemiringan variasi anatara 0.02-0.39% maka kehilangan energi didapat ±12.6 m. Bendung
akan dilengkapi dengan intake dan kantong lumpur.
 Untuk pengembangan jaringan irigasi DI Gudang terletak pada areal kiri aliran sungai. DI
Gudang termasuk dalam kategori jaringan irigasi tersier, yang memiliki 2 bangunan bagi
sadap dan 1 boks kuarter. Panjang saluran primer dari bendung ke boks kuarter (K1)
sepanjang 4.3Km.
 Debit pengambilan digunakan untuk analisis dimensi saluran primer trapezium (talud 1:0.5)
dengan ukuran variasi 0.7 x 0.7 (BxH) m dan 0.5 x 0.5 m. Sedangkan, saluran kuarter akan
memanfaatkan saluran kuarter eksisting milik Dinas Pertanian.
 Di dalam perhitungan debit banjir untuk mendesain bendung digunakan metode Nakayashu
karena memiliki nilai Tp yang paling cepat, disamping itu metode ini juga telah
dikembangkan untuk kondisi geografis di Indonesia dan telah dilakukan pengujian untuk
beberapa wilayah di Indonesia. Adapun periode ulang yang digunakan dalam desain
bendung adalalah Tr 25 tahun yang nilainya 42.4 m3/s.

 Total biaya konstruksi DI Gudang untuk areal 100 Ha sebesar Rp. 26,873,800,000.00,- (dua
puluh enam milyar delapan ratus tujuh puluh tiga juta delapan ratus ribu rupiah). Adapun
item pekerjaan yang dilaksanakan diantaranya pekerjaan persiapan, bangunan utama
(bendung, intake, dan kantong lumpur), saluran pembawa primer, bangunan
pelengkap/pengatur (bangunan bagi sadap dan boks kuarter), dan bangunan pengukur
ambang lebar.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 10-1


LAPORAN AKHIR

10.2 SARAN
Saran yang mungkin dapat kami sampaikan pada tahap draft akhir ini adalah perlu dilakukan
penyelidikan tanah yang terdiri dari uji sondir dan bor tangan. Penyelidikan dilakukan karena adanya
beberapa ruas saluran primer yang letaknya pada timbunan sehingga diperlukan proteksi khusus
sesuai dengan hasil parameter tanahnya. Disamping itu data parameter tanah menjadi faktor
penting dalam menghitung stabilitas bendung.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 10-2


LAPORAN AKHIR

LAMPIRAN

LAMPIRAN A. METODOLOGI PEKERJAAN

Dari hasil pemahaman Konsultan terhadap lingkup pekerjaan yang tertuang dalam Kerangka Acuan
Kerja, didukung oleh pengalaman perusahaan, maka disusun metodologi secara menyeluruh dalam
menyelesaikan pekerjaan mulai dari pekerjaan persiapan sampai penyerahan produk akhir berupa
gambar desain dan laporan.

A. Kegiatan I : PERSIAPAN DAN SURVEY PENDAHULUAN


Untuk menunjang kelancaran kegiatan pekerjaan diperlukan dukungan administrasi yang baik
antara pemberi kerja dengan konsultan. Sehingga dalam tahapan, satelah proses penandatangan
kontrak dan Konsultan menerima surat perintah mulai kerja (SPMK) akan segera dilaksanakan
pekerjaan persiapan, diantaranya:

A.I. Mobilisasi Personil


Konsultan akan berusaha semaksimal mungkin untuk menugaskan tenaga ahli yang cukup
berpengalaman sesuai dengan bidang disiplin ilmu masing-masing untuk mengawasi, mengkoordinir
dan menganalisis semua aktivitas pekerjaan agar diperoleh standar kualitas yang cukup tinggi.
Seluruh Tenaga Ahli yang dibutuhkan untuk pelaksanaan pekerjaan akan dimobilisir sesuai dengan
jadwal penugasan yang telah disusun. Dengan telah dimobilisasinya Tenaga Ahli tersebut, maka
kegiatan penanganan proyek dengan skala penuh telah berjalan.
Untuk memperoleh hasil yang optimal, Konsultan akan menyiapkan fasilitas kerja sesuai dengan
spesifikasi yang telah ditetapkan dalam Kerangka Acuan Kerja. Dalam hal untuk meningkatkan
kualitas hasil dan efisiensi kerja apabila dimungkinkan Konsultan akan menambah atau
meningkatkan kualitas/spesifikasi peralatan yang digunakan.
Mengingat komponen perangkat keras dan lunak dalam pekerjaan ini memegang peranan penting
dalam perwujudan hasil studi yang optimal, khususnya perangkat lunak untuk perhitungan dan
Analisis hidrologi, hidrolika dan struktur bangunan, maka pemilihan peralatan yang akan digunakan
perlu dilakukan dengan seksama agar hasil yang direncanakan betul-betul dapat dipertanggung
jawabkan baik dalam kualitas perencanaan maupun biaya pelaksanaannya. Untuk mendukung
terciptanya kerja yang menghasilkan produktifitas yang tinggi, serta untuk mengaplikasikan dari
suatu rencana pekerjaan yang telah disusun perlu ditunjang adanya peralatan dan sarana yang
memadai, baik perangkat keras maupun perangkat lunak.

A.II. Perijinan, Klarifikasi dan Survey Pendahuluan


Persiapan administrasi merupakan kegiatan paling awal dari Konsultan setelah menerima Surat
Perintah Mulai Kerja (SPK)/Kontrak dari Pemberi Kerja/Pengguna Jasa. Persiapan administrasi
tersebut mencakup pembuatan dokumen kontrak, pengurusan surat ijin ke instansi terkait,
pembuatan surat tugas kepada personil yang akan terlibat dalam penanganan proyek, surat

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 1


LAPORAN AKHIR

permohonan data dan sebagainya. Persiapan administrasi tersebut diusahakan dapat diselesaikan
sesegera mungkin sehingga tidak menghambat pelaksanaan pekerjaan berikutnya.
Pekerjaan persiapan ini akan dilaksanakan oleh seorang administrasi teknik yang telah cukup
berpengalaman dalam menangani pekerjaan yang sejenis, sehingga diharapkan dapat dilaksanakan
sesuai dengan waktu yang disediakan untuk itu. Segala sesuatu yang terkait dengan masalah
administrasi tersebut akan selalu di bawah pengawasan Team Leader yang bertanggung jawab atas
penyelesaian seluruh pekerjaan.
Orientasi lapangan bertujuan untuk mengenal area yang akan disurvey juga untuk memberikan
gambaran mengenai data awal untuk penentuan alternatif lokasi bendungan yang akan dipilih
sehingga sehingga kegiatan survey selanjutnya dapat melanjutkan hasil dari orientasi lapangan.
Peninjauan Lapangan Pendahuluan akan dilakukan bersama direksi pekerjaan dan unsur daerah
yaitu Dinas, Cabang Dinas atau aparat terkait, dengan maksud agar memperoleh gambaran
mengenai:
a) Letak dari usulan lokasi-lokasi untuk calon bendungan beserta situasi/gambaran umum
lokasi dan batasan yang kemungkinan kan dipetakan
b) Mengadakan pengamatan singkat dimulai dari usulan calon lokasi bendungan termasuk
menelusuri hingga akhir lokasi sungai sedemikian rupa sehingga dapat memberikan
gambaran mengenai system sungai termasuk melihat kondisi topografi, morfologi dan
geologi calon bendungan termasuk sungai sungai yang ada.
c) Pada awal survey pendahuluan ini, dilakukan pemberitahuan tentang memulai pekerjaan
lapangan kepada pihak-pihak yang berwenang diantaranya:
 Dinas PU pengairan
 Aparat lainnya
d) Menginventarisir lahan-lahan potensi untuk penyelidikan geolistrik, sumur uji dan lainnya
untuk bahan kajian kelayakan.
A.III.Pengumpulan Data Sosial, Ekonomi dan Lingkungan
Kegiatan pengumpulan data sosial, ekonomi dan lingkungan dilakukan berdasarkan data dari Badan
Pusat Statistik untuk daerah Kabupaten Bangka Selatan terutama Kecamatan Simpang Rimba. Dari
pengumpulan data ini akan didapatkan gambaran umum yang terjadi seperti jumlah penduduk dan
keadaan ekonomi serta mata pencaharian masyarakat di lokasi studi.

A.IV. Inventarisasi Data Awal dan Identifikasi Masalah


Kegiatan pengumpulan data awal adalah kegatan awal sebelum dilakukan diskusi pendahuluan guna
mencari, menetukan dan mengidentifiksi masalah di lapangan. Data yang di inventarisasi antara lain
laporan perencanaan, hasil studi, kebijakan, yang terkait dengan permasalahan di sekitar lokasi
pekerjaan serta peta yang tersedia dari berbagai instansi Pemerintah atau swasta terkait. Data
lainnya juga bisaa dicari untuk melengkapi kegiatan inventarisasi data sekunder pada kegiatan II,
yang terdiri atas data-data yang bersifat data dasar diantaranya peta topografi yang akan dipakai
sebagai dasar perhitungan besaran-besaran yang menyangkut luasan, arah dan posisi.
Pengamatan langsung terhadap kondisi fisik lapangan idealnya meliputi:
a. Topografi/hidrotopografi

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 2


LAPORAN AKHIR

b. Pengukuran ketinggian/elevasi lahan dan tinggi luapan maksimum perlu untuk menentkan
tipe luasan air pasang.
c. Keadaan tanah meliputi jenis tanah, tekstur, pH tanah dan air, ketebalan gambut.
Kedalaman lapis parit, kedalaman air tanah, dan pengelolaan tanah.
d. Keadaan jalan dan jembatan (perhubungan dan transportasi)
e. Keadaan jalan usaha tani, meliputi dimensi dan kondisinya
f. Kondisi jaringan tata air makro (meliputi ketersediaan pintu air dan fasilitas lain)
g. Jenis vegetasi yang tumbuh di lapangan

A.V. Penyusunan Rencana Kerja Detail


Agar tujuan pekerjaan dapat dicapai baik mutu maupun waktu sesuai sasaran yang di harapkan maka
perlu di susun rencana kerja detail yang meliputi jadwal pelaksanaan pekerjaan, jadwal penugasan
personil, jadwal pemakaian peralatan yang enar-benar lebih didetailkan kembali.

B. Kegiatan II: SURVEY LAPANGAN


B.I. Inventarisasi Infrastruktur Pengguna Air
Kegiatan pencatatan infrastruktur bangunan air yang sudah ada serta melihat kondisi terkini
infrastruktur agar bisa dilakukan suatu pengembangan apabila dimungkinkan.

B.II. Inventarisasi Data Sekunder


Kegiatan pengumpulan data sekunder akan dilakukan dengan melanjutkan mengumpulkan data
awal pada kegiatan I antara lain: laporan perencanaan, hasil studi, kebijakan, yang terkait dengan
permasalahan di sekitar lokasi pekerjaan serta peta yang tersedia dari berbagai instansi Pemerintah
atau swasta terkait. Pengumpulan data terdiri atas data-data yang bersifat data dasar diantaranya
peta topografi yang akan dipakai sebagai dasar perhitungan besaran-besaran yang menyangkut
luasan, arah dan posisi.
Tabel A.1 Data dan informasi yang perlu dikumpulkan

No Data dan informasi yang diperlukan Kegunaan

I Data yang terkait dengan Penyusunan Sistem Alokasi Air

1 Peta topografi DAS/WS serta batas administrasi Bahan dokumen


2 Data lokasi jaringan hidrologi (termasuk lokasi bendung Untuk membangun skematik sistem
teknis), lokasi pemanfaat SDA (legal maupun ilegal) yang
berada dalam sistem tata air yang akan dibangun.
3 Ploting seluruh lokasi tersebut diatas dalam peta topografi Untuk menunjang peramalan debit/
dan batas DAS/SubDAS ketersediaan air
4 Luas catchment area dari masing-masing sub DAS (pada Untuk menunjang perhitungan rainfall-
titik-titik pos duga air maupun lokasi bangunan pemanfaat runoff (jika diperlukan)
SDA)

II Data yang terkait dengan ketersediaan air

1 Data debit sungai dengan periode pengamatan panjang Untuk menetapkan debit andalan
(>10 thn) pada bangunan ukur maupun pos duga air (dependable flow) atau debit
kemungkinan (probabilitas) lainnya

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 3


LAPORAN AKHIR

No Data dan informasi yang diperlukan Kegunaan


2 Data hujan periode pengamatan panjang (>10 thn) serta Untuk analisa hujan-limpasan (rainfall-
data klimatologi runoff) jika data debit tidak tersedia atau
data debit kurang panjang
pengamatannya (<10 thn)
III Data yang terkait dengan kebutuhan air
1 Informasi mengenai rencana tanam yang ditetapkan Mengetahui luas Daerah Irigasi (DI) dan
(RTTG) kebutuhan air untuk irigasi pada setiap
DI
2 Daftar pengambilan air ilegal dan estimasi besarnya Mengetahui faktor kehilangan air pada
kapasitas terpasang suatu jaringan sumber air akibat
pengambilan air ilegal, atau untuk
dialokasikan kebutuhan airnya karena
secara de facto mereka menggunakan
air
3 Informasi penggunaan air non-konsumtif (misalnya PLTA Mengetahui saat terjadi beban puncak
dan pelayaran di sungai). water outflow dan besar aliran yang
diperlukan.
4 Pola Pengelolaan SDA pada DAS terkait Mengetahui saat dan volume air yang
harus dipasok dari suatu bangunan
pengambilan.
5 Nilai satuan kebutuhan irigasi (sesuai dengan Memperhitungkan besarnya kebutuhan
pertumbuhan tanaman), perikanan, dll air
III Data terkait dengan penyiapan model/data pendukung
1 Kondisi, tipe dan akurasi dari bangunan ukur Air yang dialirkan dapat terukur dengan
akurat
2 Data/peta geologi dan land use Menunjang perhitungan peramalan/
pembangkitan data ketersediaan air
3 Ketetapan pemerintah daerah atau konsensus tentang : Salah satu dasar “rule” penetapkan
- Prioritas penggunaan air saat kekurangan air prioritas pemberian air dalam model
- Penetapan Rencana Tata tanam saat terjadi kekurangan air.
-Rencana Tata ruang
4 Peta Isohyet Mengetahui tinggi curah hujan rata-rata
di DAS
IV Data sekunder lainnya
1 Data kependudukan
2 Data potensi desa dan kecamatan
3 Daftar harga satuan dan bahan upah setempat Menyusun rencana anggaran biaya
(RAB)
4 Data laporan kegiatan terdahulu (bila ada)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 4


LAPORAN AKHIR

No Data dan informasi yang diperlukan Kegunaan


5 Informasi kegiatan fisik yang dilakukan Dinas Pekerjaan
Ummum (P2DR) termasuk keadaan jaringan tata air

B.III. Survey Hidrometri (Current Meter)


Pengukuran debit dengan menggunakan current meter (alat ukur arus) dilakukan dengan cara
merawas, dari jembatan, dengan menggunakan perahu, dengan menggunakan winch cable way dan
dengan menggunakan cable car.
Apabila pengukuran dilakukan dengan kabel penggantung dan posisi kabel penduga tidak tegak lurus
terhadap muka air, maka kedalaman air harus dikoreksi dengan besarnya sudut penyimpangan.

Gambar A.1 Beberapa metode pengukuran debit secara langsung

Pengukuran dengan merawas dilakukan apabila kedalaman air tidak lebih dari 1,2 m dan kecepatan
air lebih kecil dari 1 m/detik, apabila kedalaman dan kecepatan arus air lebih dari kriteria tersebut
maka pengukuran dapat dilakukan dengan menggunakan alat bantu pengukuran yang lain.
Tahapan pengukuran dengan menggunakan current meter adalah sebagai berikut:
1) Siapkan peralatan yang akan digunakan untuk pengukuran yaitu:

 1 (satu) set alat ukur arus atau current meter lengkap


 2 buah alat penduga kedalaman (stang/stick) panjang masing-2masing 1 m
 Kartu Pengukuran
 Alat Tulis
 Alat pengambilan sample air
 Botol tempat sample air
 Peralatan penunjang lainnya seperti topi, sepatu lapangan dll.

2) Bentangkan kabel pada lokasi yang memenuhi persyaratan dan posisi tegak lurus dengan
arah arus air dan tidak melendut
3) Tentukan titik pengukuran dengan jarak antar vertikal ± 1/20 dari lebar sungai dan jarak
minimum = 0.50 m
4) Berikan tanda pada masing-masing titik
5) Baca ketinggian muka air pada pelskal

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 5


LAPORAN AKHIR

6) Tulis semua informasi/keterangan yang ada pada kartu pengukuran seperti nama sungai
dan tempat, tanggal pengukuran, nama petugas dll.
7) Catat jumlah putaran baling – baling selama interval waktu yang telah ditentukan (40 – 70
detik), apabila arus air lambat waktu yang digunakan lebih lama (misal 70 detik), apabila
arus air cepat waktu yang digunakan lebih pendek (misal 40 detik)
8) Hitung kecepatan arus dari jumlah putaran yang didapat dengan menggunakan rumus
baling – balingtergantung dari alat bantu yang digunakan (tongkat penduga dan berat
bandul)
9) Hitung kecepatan (v) rata-rata pada setiap vertikal dengan rumus :

 Apabilapengukuran dilakukan pada 1 titik (0.5 atau 0.6 d) contoh (vertikal 2) maka v
rata – rata = v pada titik tersebut
 Apabilapengukuran dilakukan pada 2 titik (0.2 dan 0.8 d) contoh (vertikal 3) maka v
rata – rata = (v0.2 + v0.8) / 2
 Apabilapengukuran dilakukan pada 3 titik (0.2 – 0.8 d dan 0.6 d) contoh (vertikal 4)
maka v rata – rata = [{(v0.2 + v0.8) / 2} + (v0.5 atau v0.6 )] / 2

10) Hitung luas sub/bagian penampang melintang


11) Hitung debit pada setiap sub/bagian penampang melintang
12) Ulangi kegiatan pada butir 10 sampai dengan butir 12 untuk seluruh sub bagian
penampang
13) Hitung debit total (Q total)
Debit total dihitung dengan cara menjumlahkan debit dari seluruh debit pada sub/ bagian
penampang
Q (total) = q1 + q2 + q3 + … + qn
14) 14). Hitung luas seluruh penampang melintang (A)
Luas seluruh penampang melintang dihitung dengan cara menjumlahkan seluruh luas
pada sub/bagian penampang dengan : A = a1 + a2 + a3 + … + an
15) Hitung kecepatan rata-rata seluruh penampang melintang (V)
Kecepatan rata-rata seluruh penampang melintang = debit total / luas seluruh penampang
melintang atau V = Q total / A
16) Catat waktu dan tinggi muka air pada pelskal segera setelah pengukuran selesai pada
kartu pengukuran.
17) Catat hasil perhitungan butir 14 sampai dengan 16 pada kartu pengukuran
Pengukuran debit dengan menggunakan current meter dapat dilakukan dengan beberapa metode.
Di antaranya yang paling umum dilakukan adalah dengan cara merawas.
Pengukuran debit dengan cara merawas adalah petugas pengukur langsung masuk ke dalam badan
air. Petugas pengukur minimal terdiri dari 2 orang, 1 orang petugasmengoperasikan peralatan dan

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 6


LAPORAN AKHIR

1 orang petugas mencatat data pengukuran. Dalam pelaksanaannya perlu memperhatikan hal-hal
sebagai berikut:

1. dilakukan pada lokasi sebatas pengukur mampu merawas


2. posisi berdiri pengukur harus berada di hilir alat ukur arus dan tidak boleh menyebabkan
berubahnya garis aliran pada jalur vertikal yang diukur
3. letakkan tongkat penduga tegak lurus pada jarak antara 2,5 – 7,5 cm di hilir kabel baja
yang telah dibentangkan
4. hindari berdiri dalam air apabila akan mengakibatkan penyempitan penampang
melintang
5. apabila posisi current meter (arah aliran) tidak tegak lurus terhadap penampang
melintang sungai, maka besarnya sudut penyimpangan perlu dicatat untuk menghitung
koreksi kecepatan di vertikalnya.

Gambar A.2 Metode Merawas

B.IV. Survey Sosial Ekonomi


Alat survei sosial-ekonomi dirancang untuk mengumpulkan informasi sebagai sarana meningkatkan
pemahaman tentang sistem pengelolaan sumberdaya lokal, penggunaan sumberdaya dan
kepentingan relatif masing-masing untuk rumah tangga dan desa. Survei juga memberikan informasi
tentang interaksi antara sistem pengambilan keputusan oleh pemerintah dan tren persepsi
masyarakat dan isu-isu prioritas. Pengetahuan tentang lembaga berbasis masyarakat, yang juga
diperoleh melalui survei, dan peran mereka dalam pemanfaatan berkelanjutan dan konservasi
sumberdaya alam, membantu untuk melancarkan atau memperkuat konsensus tentang
kepemilikan lahan dan hak-hak di daerah, sekarang dan di masa depan.
Langkah pertama dalam proses ini adalah melibatkan masyarakat lokal. Hal ini dapat dicapai melalui
penggunaan survei rumah tangga dan desa, dan diskusi kelompok terfokus. Langkah ini merupakan
cara penting positif yang melibatkan para pemangku kepentingan lokal dalam proses perencanaan
dan untuk memastikan bahwa suara-suara lokal didengar.
Survei dan diskusi kelompok terfokus juga menyediakan cara untuk mendapatkan pemahaman
menyeluruh tentang hubungan masyarakat lokal dengan sumberdaya yang relevan – ekonomi dan
sosial – dan hak hukum mereka serta akses untuk menggunakan sumberdaya. Informasi ini sangat

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 7


LAPORAN AKHIR

penting untuk perencanaan penggunaan lahan yang efektif, yaitu perencanaan yang akan dapat
diterapkan secara praktis dan yang memenuhi kebutuhan lokal, sehingga berpotensi menghindari
konflik atas sumberdaya di antara pihak-pihak yang berkepentingan.
Ada beberapa tahap yang dilakukan didalam melakukan survey sosial ekonomi yaitu :
Tahap 1 – Desain survei, pengambilan sampel dan data yang dibutuhkan : Ketika melakukan survei,
langkah pertama adalah menentukan maksud dan tujuan survei. Langkah ini menjelaskan kerangka
kerja survei, termasuk muatan dan cakupan pekerjaan survei dan juga digunakan untuk membantu
mengidentifikasi jenis pemangku kepentingan dan masyarakat yang harus disurvei.

 Tahap pertama dijelaskan dengan melakukan poin – poin berikut :


 Data yang dibutuhkan dan desain survei
 Objek yang akan disurvei
 Pengambilan sampel acak dan ukuran sampe
 Jenis pertanyaan
Tahap 2 – Perencanaan dan pelatihan tim : Sebuah tim yang terlatih dan berpengalaman sangat
penting bagi keberhasilan setiap survei sosial-ekonomi. Pengalaman praktis sebelumnya adalah aset
besar untuk tim, misalnya dengan pengetahuan teknis yang relevan di bidang sosialekonomi,
kehutanan dan sumberdaya alam.
Semua anggota tim membutuhkan pelatihan secara lengkap dan rinci untuk semua jenis survei
(rumah tangga, desa, diskusi kelompok terfokus, wawancara informan kunci) yang akan dilakukan.
Semua anggota tim harus memiliki pemahaman yang menyeluruh tentang tujuan kegiatan dan
makna setiap pertanyaan yang akan ditanyakan. Kombinasi pelatihan di kelas dan di lapangan akan
memberikan pemahaman terbaik tentang prosedur dan metode survei. Selain itu, pelatihan
lapangan sangat berguna untuk memeriksa pertanyaan survei dan maksud pengumpulan data,
sehingga memberikan kesempatan untuk melakukan revisi yang diperlukan untuk survei,
pertanyaan wawancara dan prosedur surveinya.
Pembagian tugas antara anggota tim juga perlu dipertimbangkan – fasilitator, manajer sumberdaya,
pengamat/perekam, dan pemimpin tim.
Tahap 3 – Pelaksanaan : Pendekatan survei bervariasi. Pendekatan yang berbeda digunakan untuk
tujuan yang berbeda. Untuk perencanaan penggunaan lahan kolaboratif, digunakan tiga metode
survei, yaitu:
 Wawancara informan kunci
 Survei rumah tangga
 Diskusi kelompok terfokus
Beberapa cara yang dilakukan di lapangan adalah :
 Pertemuan dengan masyarakat
 Wawancara informan kunci
 Survei desa dan rumah tangga
 Diskusi kelompok terfokus

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 8


LAPORAN AKHIR

C. Kegiatan III: ANALISIS HIDROLOGI DAN PERENCANAAN


C.I. Analisis Ketersediaan Air
Perhitungan dan atau peramalan ketersediaan air di sungai (tanpa waduk) umumnya dibutuhkan
untuk memenuhi kebutuhan air irigasi (sebagai kebutuhan mayoritas) maka perhitungan
ketersediaan air tersebut dihitung berdasarkan kondisi tahun kering atau adalah debit dengan
probabilitas 80%, yaitu debit dengan kemungkinan tidak terpenuhinya sebesar 20%, atau dalam
jangka 10 tahun akan terjadi 2 kali kegagalan (tidak terpenuhi), debit dengan probabilitas tersebut
disebut dengan Debit Andalan (dependable flow).
C.I.1. Pembangkitan Data Debit (Rainfall-Runoff)
Umumnya data curah hujan tersedia dengan periode ≥ 10 tahun dan sebagaimana diketahui
besarnya debit terpengaruh oleh curah hujan, kondisi topografi dan tata guna lahan serta geologi
pada DAS yang ditinjau. Dengan demikian bila pada suatu DAS tidak tersedia data debit dengan
periode ≥10 tahun, perlu membangkitkan data debit dengan model debit – curah hujan (Rainfall –
runoff).
Data yang digunakan dalam studi ini yaitu data sekunder berupa data hujan, data klimatologi, dan
data debit observasi. Prosedur pekerjaan ini secara garis besar dapat disajikan dalam diagram
berikut.

Gambar A.3 Diagram Alir Kalibrasi Model

Untuk keperluan kalibrasi model, diperlukan kedua data tersebut (data dari pos duga air dan data
dari pos curah hujan) tercatat pada waktu yang bersamaan. Tersedia banyak metode/model Rainfall
– runoff, dan diantaranya adalah :
A. NRECA Water Balance
Salah satu model yang dipakai dalam menghitung ketersediaan air adalah model NRECA.
Model kesetimbangan air dari NRECA ini didasarkan pada proses kesetimbangan air yang
telah umum yaitu hujan yang jatuh di atas permukaan tanah dan tumbuhan penutup lahan
sebagian akan menguap, sebagian akan menjadi aliran permukaan dan sebagian lagi akan

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 9


LAPORAN AKHIR

meresap masuk ke dalam tanah. Infiltrasi air akan menjenuhkan tanah permukaan dan
kemudian air merambat menjadi perkolasi dan keluar menuju sungai sebagai aliran dasar.
Model ini dapat mensimulasi kesetimbangan air bulanan pada suatu daerah tangkapan air
dengan tujuan untuk menghitung total run-off dari curah hujan bulanan, evapotranspirasi,
kelembaban tanah dan ketersediaan air tanah. Perbedaan model NRECA dengan model
kesetimbangan air yang lain hanyalah pada jumlah parameter yang diambil. Data masukan
yang diperlukan untuk model NRECA ini antara lain :
a) Hujan bulanan
Hujan bulanan yang dipakai dalam perhitungan NRECA adalah hujan bulanan hasil
pengukuran. Berdasarkan curah hujan yang turun, bulan hujan dapat dibagi dalam 3
kelompok, yaitu
 Kelompok bulan kering : jumlah curah hujan kurang dari 60 mm setiap bulannya.
 Kelompok bulan lembab : Jumlah Curah hujan antara 60-100 mm setiap bulannya.
 Kelompok bulan basah : Jumlah curah hujan lebih dari 100 mm setiap bulannya
b) Evapotranspirasi
c) Temperatur rata-rata bulanan
d) Intensitas sinar matahari
e) Kelembaban relatif
f) Kecepatan angin
g) Kondisi awal kadar kelembapan tanah
h) Tampungan awal air tanah
i) Index soil moisture storage capacity pada daerah tangkapan
j) Persentase run off yang mengalir pada jalur subsurface
k) Persentase air yang masuk menjadi aliran air tanah
Metoda perhitungan yang dilakukan dalam model limpasan NRECA ini menggunakan data
hujan bulanan dan evapotranspirasi untuk menghitung debit bulanan yang terjadi.
Persamaan dasar keseimbangan air yang digunakan: :

RO = P – AE + S
Dimana :
P = Presipitasi (mm)
AE = Penguapan aktual (mm)
ΔS = Perubahan tampungan (mm)
RO = Aliran permukaan (mm)
Beberapa parameter karakteristik daerah tangkapan yang digunakan dalam model limpasan
ini diuraikan sebagai berikut :

 NOMINAL (Index soil moisture storage capacity pada daerah tangkapan)


100 + C*(hujan tahunan rata-rata), dimana :

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 10


LAPORAN AKHIR

C = 0.2 , untuk daerah dengan hujan sepanjang tahun


C < 0.2 , untuk daerah dengan hujan musiman
Hujan NOMINAL dapat dikurangi hingga 25 % untuk daerah dengan tetumbuhan
terbatas dan penutup tanah yang tipis.

 PSUB (Persentase runoff yang mengalir pada jalur subsurface)


PSUB = 0.5, untuk daerah tangkapan hujan yang normal/biasa
0.5 < PSUB < 0.9 , untuk daerah dengan akuifer permeabel yang besar
0.3<PSUB<0.5 , untuk daerah dengan akuifer terbatas dan lapisan tanah yang tipis

 GWF (Persentase air yang masuk menjadi aliran air tanah)


GWF = 0.5, untuk daerah tangkapan hujan yang normal/biasa
0.5<GWF≤0.8, untuk daerah yang memiliki aliran menerus yang kecil
0.2≤GWF<0.5, untuk daerah yang memiliki aliran menerus yang dapat diandalkan
Pemilihan parameter karakteristik NOMINAL, PSUB dan GWF dilakukan dengan coba-coba
sehingga koefisien korelasi antara debit aktual dan model mendekati satu. Langkah
Perhitungan mencakup 18 tahap yang dinyatakan dengan contoh pada tabel berikut.
Perhitungan dapat dilakukan kolom per kolom dari kolom (1) hingga (18) berikut ini :
Tabel A.2 Pentahapan Pada Model NRECA

KOLOM KETERANGAN
1 Nama bulan Januari sampai Desember
2 Presipitasi (hujan) bulanan rata-rata (mm)
3 Evapotranspirasi potensial (PET) (mm)
4 Penyimpanan kadar kelembaban tanah (moisture storage) (mm). Harga kelembaban
tanaha ditetapkan dengan coba-coba dan sebagai kondisi awal dan digunakan untuk
perhitungan selanjutnya.Moisture Storage (i) = Moisture Storage (i-1)+Delta Storage (i-
1)
5 Rasio penyimpanan (Storage Ratio)
6 Rasio Presipitasi(Rb)/Evapotranspirasi potensial = kolom (2)/kolom (3)
7 Rasio AET/PET
AET = Evopotranspirasi aktual. Rasio ini didapat dengan bantuan grafik 1, tergantung
dari nilai Rb/PET
8 Harga ini didapatkan dari perkalian kolom (3) dan (7)
9 Neraca air (water balance) = Rb – AET (kolom (2) – kolom (8)
10 Rasio kelebihan kelembaban tanah (excess moisture ratio) : 1. Bila neraca air pada
kolom (9) positif, maka harga kelebihan kelembaban tanah didapatkan dengan bantuan
graafik 2. Jika harga kesetimbangan air negatif, maka harga rasio ini sama dengan nol

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 11


LAPORAN AKHIR

KOLOM KETERANGAN
11 Kelebihan kelembaban tanah (excess moiture) didapatkan dengan mengalikan harga
kolom (10) dengan (9).
Excess Moiisture(i) = Excess Moisture Ratio (i) x Water Balance (i)
12 Perubahan tampungan = kolom (9) – kolom (11)
Delta Storage (i) = Water Balance (i) – Excess Moisture(i)
13 Pengisian air tanah (recharge to groundwater). Harga pengisian air tanah didapaatkan
dengan mengalikan PSUB dengan kolom 11.
Recharge to Ground Water(i) = PSUB x Excess moisture (i)
14 Tampungan awal air tanah (begin storage GW). Harga tampungan awal air tanah
ditetapkan sebagai kondisi awal dan digunakan pada perhitungan selanjutnya.
15 Tampungan akhir air tanah (end storage Ground Water). Harga tampungan akhir air
tanah didapatkan dari penjumlahan antara kolom (13) dan kolom (14).
End Storage GW (i) = Recharge to GW (i) + Begin Storage GW(i)
16 Aliran air tanah (GW flow). Harga ini didapatkan dari perkalian antara GWF dengan
kolom (15)
17 Direct Flow. Harga direct flow didapatkan dari pengurangan antara kolom (11) dengan
kolom (13)
18 Debit Total. = kolom (16) + kolom (17)
19 Debit pengamatan (observed discharge). Harga debit pengamatan digunakan untuk
proses kalibrasi model.

B. Sacramento Water Balance


Model Sacramento adalah model simulasi perkolasi dan limpasan, yang dapat digambarkan
sebagai berikut:

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 12


LAPORAN AKHIR

Gambar A.4 Diagram Model Sacramento (Syahril, 2006)

Air berada di dua zona, yaitu Upper zone dan Lower Zone. Upper Tension Zone adalah
volume air yang dapat disimpan oleh upper zone berkisar antara kapasitas lapang sampai
dengan titik layu. Air di dalam Upper zone dapat berkurang karena evaporasi dan
evapotranspirasi. Penyimpanan ini akan terisi sebelum air melakukan transformasi ke
lapisan bawahnya atau mengalir secara lateral.
Pada bagian Lower Zone Tension, air dari sumber penyimpanan hanya akan berkurang
karena evapotranspirasi. Sedang pada Upper Zone Free akan menyimpan air sebagai
sumber interflow dan sebagai gaya penggerak (driving force) untuk pergerakan air ke lapisan
di bawahnya.
Untuk limpasan menghasilkan direct runoff dan surface runoff. Pada zona tanpa tekanan di
Upper zone air akan turun kearah lower zone dan menghasilkan baseflow maupun
subsurface outflow.
Besarnya aliran dinyatakan dalam persamaan-persamaan sebagai berikut:
Interflow = UZK*UZFWC
dimana:
UZK = Upper Zone Free Water storage depletion coefficient
UZFWC = Volume of free water presently stored in the upper zone
Batas pengaliran dari saturated lower zone storages disebut PBASE, yang dapat dinyatakan
dengan persamaan :
PBASE = LZFSM*LZSK + LZFPM*LZPK
dimana:
LZFSM = Lower Zone Free Water
LZSK = Lower Zone supplementary storage depletion coefficient

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 13


LAPORAN AKHIR

LZDPM = Lower Zone Free Water maximum primary storage


LZPK = Lower Zone primary storage depletion coefficient
Kapasitas Maksimum Perkolasi = PBASE*(1+ZPERC)
Keterangan mengenai parameter-parameter pemodelan dapat diringkaskan dalam tabel
berikut:
Tabel A.3 Parameter Model SACRAMENTO (Vrugt, et al., 2006)

C.II. Kebutuhan Air untuk Pemeliharaan Sungai


Dalam rangka untuk menjaga kelestarian aneka ragam hayati dalam sumber air, maka sangat
diperlukan terjaganya ketersediaan debit sungai/debit minimum yang harus tersedia di sungai dari
hulu sampai muara sungai.
Kebutuhan ini dikategorikan sebagai kebutuhan non konsumtif, dan besarnya debit sungai
minimum/pemeliharaan sungai ditetapkan berdasarkan kesepakatan/konsensus dalam agenda
rapat TKPSDA.
Perhitungan debit minimum sungai dapat dilakukan dengan berbagai metode diantaranya:
• Berdasarkan debit minimum sungai dengan kondisi sebelum terjadi pengambilan/
pemanfaatan SDA.
• Berdasarkan Q90 untuk debit minimum dari Qharian rata-rata selama 7 hari berturut-
turut.
• Berdasarkan Q95 debit minimum dari Qsetengah bulanan rata-rata

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 14


LAPORAN AKHIR

C.III. Analisis Kebutuhan Air


A. Kebutuhan Air Irigasi
Kebutuhan air di sawah untuk padi ditentukan oleh faktor-faktor berikut :
1. Penyiapan lahan
2. Penggunaan konsumtif
3. Perkolasi dan rembesan
4. Penggantian lapisan air
5. Curah hujan efektif
Kebutuhan total air di sawah (GFR) mencakup 1 sampai 4, sedangkan kebutuhan bersih air
di sawah (NFR) juga memperhitungkan besarnya curah hujan efektif. Kebutuhan air di sawah
dinyatakan dalam mm/hari atau liter/dt.ha.
B. Penyiapan Lahan
Kebutuhan air untuk penyiapan lahan umumnya merupakan kebutuhan terbesar yang
menentukan kebutuhan maksimum air irigasi. Kebutuhan air untuk penyiapan lahan
ditentukan oleh faktor-faktor berikut :
 Jangka waktu penyiapan lahan
 Kebutuhan air untuk penyiapan lahan
a. Jangka Waktu Penyiapan Lahan
Jangka waktu penyiapan lahan dipengaruhi oleh faktor tersedianya tenaga kerja dan ternak
untuk penghela atau traktor untuk menggarap tanah. Jangka waktu penyiapan lahan
sedapat mungkin diperpendek agar tersedia cukup waktu untuk menanam padi sawah atau
padi gadu kedua. Sebagai pedoman jangka waktu penyiapan lahan sebagai berikut :

 1,5 bulan untuk menyelesaikan penyiapan lahan di seluruh petak tersier bila
dikerjakan dengan tenaga manusia dan atau hewan,
 1 bulan bila digunakan peralatan mesin secara luas.

b. Kebutuhan Air Untuk Penyiapan Lahan


Jumlah air yang dibutuhkan untuk penyiapan lahan dapat ditentukan berdasarkan
kedalaman serta porositas tanah di sawah. Kebutuhan air untuk penyiapan lahan ini dapat
diambil sebagai berikut :
 200 mm ditambah 50 mm lapisan air awal setelah transplantasi selesai untuk
tanah bertekstur berat, tanpa retak-retak.
 Bila lahan telah dibiarkan bera selama jangka waktu yang lama (2,5 bulan atau
lebih), maka lapisan air yang diperlukan untuk penyiapan lahan dan penggengan
setelah transplantasi sebesar 300 mm
Untuk menghitung kebutuhan air irigasi selama penyiapan lahan, digunakan metode yang
dikembangkan oleh van de Goor dan Zijlstra (1968). Metode ini didasarkan atas laju air
konstan dalam mm/hari selama periode penyiapan lahan menghasilkan rumus berikut :

M ek
IR 
ek 1
dimana :

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 15


LAPORAN AKHIR

IR : Kebutuhan air irigasi untuk penyiapan lahan di sawah [mm/hari]


M : Kebutuhan air untuk mengganti/mengkompensasi kehilangan air akibat
evaporasi dan perkolasi di sawah yang sudah dijenuhkan, dimana :

M  Eo  P [mm/hari]

Eo : Evaporasi dari air terbuka, yang diambil 1,1 ETo selama penyiapan lahan
[mm/hari]
P : Perkolasi [mm/hari]

MT
k
S
T : Jangka waktu penyiapan lahan [hari]
S : Kebutuhan air untuk penjenuhan ditambah dengan lapisan air 50 mm ( total
sebesar 250 mm atau 300 mm ) seperti telah diuraikan di atas.
C. Penggunaan Konsumtif
Penggunaan konsumtif dihitung dengan rumus berikut :

ETc  k c  ETo
dimana :
ETc : Evapotranspirasi tanaman [mm/hari]
ETo : Evapotranspirasi tanaman acuan [mm/hari]
kc : Koefisien tanaman
Evapotranspirasi tanaman acuan adalah evapotranspirasi tanaman yang dijadikan acuan,
yaitu rerumputan pendek. Evapotranspirasi acuan dapat dihitung dengan rumus-rumus
teoritis-empiris. Di Indonesia dianjurkan untuk menggunakan rumus Penman yang sudah
dimodifikasi. Terdapat dua metode yang dapat digunakan, yaitu:

 Metode Nedeco/Prosida, dan


 Metode FAO, lebih umum dipakai
Nilai ETo dari rumus Penman menunjuk pada tanaman acuan apabila digunakan albedo 0,25
(rerumputan pendek). Koefisien-koefisien tanaman yang dipakai untuk perhitungan ETc
harus mengacu pada ETo ini dengan albedo 0,25.
Nilai koefisien tanaman untuk padi dapat dilihat pada table berikut.
Tabel A.4 Nilai Koefisien Tanaman Padi

Nedeco/Prosida FAO
Bulan
Varietas Biasa Varietas Unggul Varietas Biasa Varietas Unggul
0,5 1,20 1,20 1,10 1,10
1,0 1,20 1,27 1,10 1,10
1,5 1,32 1,33 1,10 1,05
2,0 1,40 1,30 1,10 1,05
2,5 1,35 1,30 1,10 0,95
3,0 1,24 0,00 1,05 0,00
3,5 1,12 0,95

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 16


LAPORAN AKHIR

Nedeco/Prosida FAO
Bulan
Varietas Biasa Varietas Unggul Varietas Biasa Varietas Unggul
4,0 0,00 0,00
Sumber : Dirjen Pengairan, Bina Program PSA 001, 1985

Nilai koefisien untuk tanaman Palawija dapat dilihat pada Tabel 4.6
Tabel A.5 Nilai Koefisien Tanaman Palawija (Digunakan Untuk ETo FAO)

Catatan : - Sumber FAO Guideline for Crop Water Requirements (1977)


- Bila digunakan dengan ETo Prosida, Koefisein Tanaman di atas dikalikan dengan koefisien 1,15
D. Perkolasi dan Rembesan
Laju perkolasi sangat bergantung pada sifat-sifat tanah. Pada tanah lempung berat dengan
karakteristik pengolahan (puddling) yang baik, laju perkolasi dapat mencapai 1-3 mm/hari.
Pada tanah-tanah yang lebih ringan, laju perkolasi bisa lebih tinggi. Nilai perkolasi untuk
berbagai tekstur tanah dapat dilihat pada Tabel 4.7.
Tabel A.6 Nilai Perkolasi Untuk Berbagai Tekstur Tanah

Tekstur Tanah Kedalaman Perkolasi


[mm/hari]
1) Clay 1,0 – 1,5
2) Silty Clay 1,5 – 2,0
3) Clay Loam, Silty Clay Loam 2,0 – 2,5
4) Mudy Clay Loam 2,5 – 3,0
5) Sandy Loam 3,0 – 5,0
Sumber : Dirjen Pengairan, Pedoman Umum OP Jaringan Irigasi

E. Penggantian Lapisan Air


Pengantian lapisan air dilakukan sebagai berikut :

 Setelah pemupukan, usahakanlah untuk menjadwalkan dan mengganti lapisan air


menurut kebutuhan,
 Jika tidak ada penjadwalan semacam itu, lakukan penggantian sebanyak dua kali,
masing-masing 50 mm selama ½ bulan (atau 3,3 mm/hari) pada waktu sebulan dan dua
bulan setelah transplantasi.
F. Curah Hujan Efektif
Curah hujan efektif adalah bagian dari curah hujan yang efektif untuk kebutuhan irigasi.
Pada lahan irigasi dengan cakupan areal tanaman padi yang luas, menghitung koefisien
curah hujan efektif dilakukan dengan melakukan analisis nilai curah hujan dari berbagai
stasiun hujan yang tersebar di daerah irigasi untuk tahun-tahun yang berbeda.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 17


LAPORAN AKHIR

Besarnya curah hujan efektif untuk padi adalah 70 % dari curah hujan tengah bulanan yang
terlampaui 80 % (periode ulang 5 tahun). Curah hujan efektif rata-rata hariannya dapat
dirumuskan sebagai berikut :

0,70  R(Setengah bulan)5


Re 
15
dimana :
Re : Curah hujan efektif harian [mm/hari]
R5 : Curah hujan setengah bulanan dengan periode ulang 5 tahun [mm/setengah
bulan]
G. Kebutuhan Bersih Air Di Sawah
Kebutuhan bersih air di tingkat usaha tani (di sawah) untuk pertumbuhan tanaman padi,
dihitung dengan rumus :

NFR  ETc  P  Re  WLR


dimana :
NFR : Kebutuhan air bersih di sawah [mm/hari]
Etc : Penggunaan konsumtif untuk tanaman dengan koefisien tanaman untuk padi
pada tahap pertumbuhan [mm/hari]
P :Kehilangan air akibat perkolasi [mm/hari]
Re : Curah hujan efektif [mm/hari]
WLR : Pengantian lapisan air [mm/hari]
H. Efisiensi Irigasi
Efsiensi irigasi merupakan tolok ukur suksesnya operasi dalam semua jaringan irigasi. Tolok
ukur efisiensi irigasi adalah besarnya kehilangan air dibandingkan dengan jumlah air yang
dipasok dari bangunan utama.
Kehilangan air secara umum dibagi dalam dua kategori, yaitu :

 Kehilangan akibat fisik, disebabkan rembesan air di saluran dan perkolasi di tingkat
lahan usaha tani (sawah),
 Kehilangan akibat opersional, disebabkan pelimpasan dan kelebihan air pembuangan
dan pada waktu pengoperasian saluran dan pemborosan penggunaan air.
Kehilangan air akibat fisik, relatif lebih mudah untuk diperkirakan dan dikontrol secara teliti,
sedangkan kehilangan akibat operasional lebih sulit diperkirakan dan dikontrol karena
tergantung pada faktor yang sulit diketahui sejak awal seperti datangnya hujan, sikap
tanggap petugas operasi dan tingkat keterlibatannya.
Pengoperasian pengaliran air melalui suatu jaringan irigasi dibagi atas 3 (tiga) macam
operasi, yaitu:

 di jaringan utama,
 di jaringan tersier,
 di tingkat usaha tani
Sesuai buku Kriteria Perencanaan Irigasi Bagian Penunjang efisiensi irigasi secara
keseluruhan sebesar 0,65 (65 %) dengan rincian sebagai berikut :

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 18


LAPORAN AKHIR

 Efisiensi saluran primer : 90 %


 Efisiensi saluran sekunder : 90 %
 Efisiensi salluran tersier : 80 %
Efisiensi Total : 65 %
I. Kebutuhan Pengambilan
Kebutuhan pengambilan adalah kebutuhan bersih air di sawah dibagi dengan efisiensi irigasi
seperi rumus di berikut :

NFR
DR  [liter/detik/Ha]
Efisiensi  8,64
dimana :
DR : Kebutuhan pengambilan [liter/detik/Ha]
NFR : Kebutuhan air bersih di sawah [mm/hari]
Efisiensi : Efisiensi irigasi
8,64 : Konversi dari [mm/hari] ke [liter/detik/Ha]
J. Pola Tanam
Pola tanam adalah susunan rencana penanaman berbagai jenis tanaman selama satu tahun
yang umumnya di Indonesia dikelompokkan dalam 3 (tiga) jenis tanaman, yaitu Padi, Padi
dan Palawija, atau Padi, Tebu dan Palawija.
Umumnya pola tanam mengikuti debit andalan yang tersedia untuk mendapatkan luas
tanam yang seluas-luasnya. Perencanaan dan persiapan pola tanam serta jadwal tanam
suatu jaringan irigasi bervariasi sesuai dengan kebiasaan petani terhadap jenis tanaman
yang akan dibudidayakan dan jadwal tanamnya. Dalam penerapan pola tanam dan jadwal
tanam, kadang-kadang petani mempertimbangkan banyak faktor lain seperti keterbatasan
modal, buruh, cuaca, hama, ketersediaan benih dan pangsa pasar.
Guna mendapatkan areal tanam yang seluas-luasnya dari debit yang tersedia, dapat di atasi
dengan cara golongan, yaitu pembagian luas areal tanam pada suatu daerah irigasi dengan
mulai awal tanam yang tidak bersamaan.
Golongan dapat dilaksanakan secara alam dan teknis. Golongan secara alam dilaksanakan
oleh para petani sendiri pada tingkat usaha tani dengan pemilihan tanaman secara bebas
atau saat penentuan pengolahan tanah yang tergantung pada ketersediaan tenaga kerja,
sedangkan golongan teknis dilaksanakan oleh Panitia Irigasi sesuai aturan tertentu.
Cara golongan teknis adalah dengan membagi suatu daerah irigasi dalam beberapa
golongan yang mulai pengolahan tanahnya dengan selang waktu 10 atau 15 hari. Dengan
pengunduran waktu memulai pengolahan tanah pada setiap golongan maka kebutuhan air
dapat terpenuhi sesuai dengan debit yang tersedia.
Alternatif jumlah golongan yang digabungkan dengan alternatif selang waktu mulai tanam
dapat dilakukan dengan berulang-ulang jika ingin mendapatkan jumlah golongan yang
memberikan luas tanam optimal. Pencarian alternatif ini dapat dipercepat dan dipermudah
bila digunakan komputer untuk mensimulasikan berbagai alternatif tersebut di atas.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 19


LAPORAN AKHIR

Beberapa hal yang perlu diperhatikan dalam pembuatan golongan untuk mendapatkan hasil
yang optimal :
 Pengaruh golongan pertama terhadap golongan terakhir, contoh hama yang sempat
timbul saat golongan pertama, tidak sempat berakibat fatal bagi tanaman golongan
pertama akan tetapi bisa berakibat fatal pada golongan terakhir. Untuk mengatasi ini
perlu diperhatikan banyak golongan sekecil mungkin dan selang waktu sependek
mungkin,
 Petugas O&P yang tersedia, semakin banyak golongan maka semakin rumit
opersionalnya sehingga semakin banyak dibutuhkan petugas untuk mengoperasikan
dan mengawasi secara ketat pemberian air yang diperlukan pada setiap golongan,
 Jumlah golongan yang terlalu banyak akan memerlukan waktu yang lama untuk
pengolahan lahan, mengganggu mulai musim tanam berikutnya dan penyakit dapat
berpengaruh pada padi muda di golongan terakhir. Atas dasar hal tersebut, maka
jumlah golongan disarankan antara 3 sampai 6,
 Banyak golongan tergantung pada perkiraan air yang tersedia setiap tahun, terutama
pada musim kemarau.

C.IV. Perluasan Sawah


C.IV.1. Sawah Lahan Irigasi
1. Norma
Perluasan sawah pada lahan irigasi merupakan upaya untuk menambah baku lahan sawah
yang dilakukan di daerah irigasi yang sudah mempunyai jaringan irigasi sampai pada tingkat
tersier atau akan dibangun yang selesainya bersamaan dengan selesainya sawah dicetak.
Pembukaan lahan baru ini dilakukan dalam satu hamparan yang mengelompok sehingga
dapat terairi sepenuhnya.
2. Standar Teknis
Standar teknis lokasi perluasan sawah pada lahan irigasi adalah:
a. Memunyai kemiringan hamparan < 5%
b. Luas satu hamparan > 10 Ha
c. Dekat dari pemukiman
3. Kriteria
Kriteria perluasan sawah pada lahan irigasi adalah:
a. Tersedia air irigasi dalam jumlah yang cukup
b. Lahan relatif subur
c. Sudah ada petani dalam suatu wadah kelompok
d. Petaninya pemilik penggarap atau penggarap
e. Luas lahan pemilik penggarap atau penggarap maksimum 2 Ha / KK
f. Petugas lapangan sudah ada
g. Lokasi mudah diakses atau dekat jalan desa
4. Prosedur
Prosedur perluasan sawah pada lahan irigasi adalah:
a. Identifikasi calon petani dan calok lokasi (CPCL) serta penetapan lokasi
b. Survey / investigasi dan desain

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 20


LAPORAN AKHIR

c. Konstruksi (land clearing dan land leveling)


d. Bantuan saprotan untuk pemanfaatan lahan sawah baru
C.IV.2. Sawah Lahan Tadah Hujan
1. Norma
Perluasan sawah pada lahan tadah hujan merupakan upaya untuk menambah baku lahan
sawah yang dilakukan di daerah tadah hujan yang belum dimanfaatkan.
2. Standar Teknis
Standar teknis lokasi perluasan sawah pada lahan irigasi adalah:
a. Memunyai kemiringan hamparan < 5%
b. Luas satu hamparan 10 Ha
c. Dekat dari pemukiman
3. Kriteria
Kriteria perluasan sawah pada lahan irigasi adalah:
a. Mempunyai bulan basah > 3 bulan, terutama yang tersedia air untuk 2 kali tanam
setahun
b. Lahan relatif subur
c. Sudah ada petani dalam suatu wadah kelompok
d. Petaninya pemilik penggarap atau penggarap
e. Luas lahan pemilik penggarap atau penggarap maksimum 2 Ha / KK
f. Petugas lapangan sudah ada
g. Lokasi mudah diakses atau dekat jalan desa
4. Prosedur
Prosedur perluasan sawah pada lahan irigasi adalah:
a. Identifikasi calon petani dan calok lokasi (CPCL) serta penetapan lokasi
b. Survey / investigasi dan desain
c. Konstruksi (land clearing dan land leveling)
d. Bantuan saprotan untuk pemanfaatan lahan sawah baru

C.V. Debit Banjir


Pada umumnya debit banjir rencana (design flood) di Indonesia ditentukan berdasarkan data curah
hujan yang tercatat, karena data debit banjir jarang sekali dapat diterapkan karena keterbatasan
masa pengamatan.
Langkah-langkah yang ditempuh dalam penentuan banjir dari data hujan untuk daerah aliran sungai
adalah sebagai berikut :
 Membuat analisis hubungan antara curah hujan dan debit banjir yang tercatat.
 Membuat analisis frekuensi curah hujan harian maksimum tahunan.
Dari kedua analisis di atas ditentukan besarnya banjir untuk beberapa kala ulang tertentu.
Ada beberapa metode dan rumus yang biasa digunakan untuk mentukan debit banjir rencana
(design flood).

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 21


LAPORAN AKHIR

Metode yang dipakai dalam merencanakan debit banjir rencana adalah sebagai berikut :
 Metode rasional
 metode karakteristik cekungan (basin characteristic)
 metode hidrograf satuan (unit hydrograph)
 metode simulasi matematika.
Dari ke empat metode di atas, guna keperluan perhitungan bendung yang paling banyak dipakai
adalah metode hidrograf satuan (unit hydrograph).
Metode penentuan debit banjir rencana akan dilakukan dengan metode hidrograf satuan sintetik
metode Nakayasu dan metode Snyder.
C.V.1. Hidrograf Satuan Sintetik Snyder
Pada tahun 1938, Snyder mempublikasikan parameter unit hidrograf yang ia kembangkan
untuk analisis pada “ungagged wataershed”, DAS yang tidak terdapat pos pengukuran
elevasi muka air atau debit sungai. Pada model ini, Snyder memilih lag time, debit puncak,
dan total waktu dasar/hidrograf sebagai karakteristik dari unit hidrograf. Metode ini dapat
digunakan untuk luas DAS antara 30 - 30000 km2.

Gambar A.5 Hidrograf Satuan Sintetik Snyder (a) tp = 5.5 tr , (b) tpR ≠ 5.5 tR

Berikut rumus yang digunakan dalam membuat hidrograf sintetik Snyder.

t p  Ct ( LLc ) 0.3
AC p
Qp 
tp

tp
tb  3 
8

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 22


LAPORAN AKHIR

tp
td 
5,5
Apabila durasi hujan efektif tr tidak sama dengan durasi standar tD, maka:

t pR  t p  0,25(t r  t d )
tp
Q pR  Q p
t pR

Dengan :
td = durasi standar dari hujan efektif (jam)
tr = durasi hujan efektif (jam)
tp = waktu dari titk berat durasi hujan efektif td ke puncak hidrograf satuan
(jam)
tpR = waktu dari titik berat durasi hujan tr ke puncak hidrograf satuan (jam)
tb = waktu dasar hidrograf satuan (hari)
Qp = debit puncak untuk durasi td
QpR = debit puncak untuk durasi tr
L = panjang sungai utama terhadap titik control yang ditinjau (km)
Lc = jarak antara titik control ke titik yang terdekat dengan titik berat DAS (km)
A = luas DAS (km2)
Ct = koefisien yang tegantung kemiringan DAS, yang bervariasi dari 1.4 – 1.7
Cp = koefisien yang tegantung pada karakteristik DAS, yang bervariasi antara
0.15 – 0.19
0.23𝐴1.08
𝑊50 = 1.08
𝑄𝑝𝑅

0.13𝐴1.08
𝑊75 = 1.08
𝑄𝑝𝑅

Dimana W50 dan W75 adalah lebar unit hidrograf pada debit 50% dan 75% dari debit puncak,
yang dinyatakan dalam jam.
C.V.2. Hidrograf Satuan Sintetik Nakayasu
Nakayasu dari Jepang, telah membuat rumus hidrograf satuan sintetik dari hasil
penyelidikannya. Rumus tersebut adalah sebagai berikut:
𝐶 × 𝐴 × 𝑅𝑜
𝑄𝑝 =
3.6(0.3𝑇𝑝 + 𝑇0.3 )
Keterangan :
Qp = debit puncak banjir (m3/det)
R0 = hujan satuan (mm)
Tp = tenggang waktu (time lag) dari permulaan hujan sampai puncak banjir (jam)
Tp = tg + 0,8 tr

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 23


LAPORAN AKHIR

Tg = waktu konsentrasi (jam), tenggang waktu dari titik berat hujan sampai titik berat
hidrograf (time lag), dalam hal ini, jika:
L<15 km tg = 0,21 . L0,7
L>15 km tg = 0,4 + 0,058 . L
tr = tenggang waktu hidrograf (time base of hidrograf)
= 0,5 sampai 1 tg
T0,3 = .tg
0.47(𝐴𝐿)0.25
𝛼=
𝑡𝑔
untuk :

Daerah pengaliran biasa  = 2


Bagian naik hidrograf yang lambat dan bagian menurun yang cepat  = 1,5
Bagian naik hidrograf yang cepat dan bagian menurun yang lambat = 1
Bagian lengkung naik (rising limb) hidrograf satuan memiliki rumus :
2.4
𝑡
𝑄𝑎 = 𝑄𝑝 ( )
𝑇𝑝
Keterangan,
Qa = limpasan sebelum mencapai debit puncak (m3/det)
t = waktu (jam)
Bagian lengkung turun (decreasing limb) hidrograf satuan
𝑡−𝑇𝑝
𝑄𝑑1 = 𝑄𝑝 × 0.3 𝑇0.3
𝑡−𝑇𝑝 +0.5𝑇0.3
𝑄𝑑2 = 𝑄𝑝 × 0.3 1.5𝑇0.3

𝑡−𝑇𝑝 +1.5𝑇0.3
𝑄𝑑3 = 𝑄𝑝 × 0.3 2𝑇0.3

Gambar A.6 Hidrograf Satuan Sintetik Nakayasu

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 24


LAPORAN AKHIR

Data yang digunakan dalam analisis debit puncak banjir adalah data hujan, kondisi fisik sungai,
kondisi lahan DAS serta jenis tanah dominan. Koefisien pengaliran adalah suatu variabel yang
didasarkan pada kondisi daerah pengaliran dan karakteristik hujan yang jatuh di daerah tersebut.
Adapun kondisi dan karakteristik yang dimaksud adalah :
1. Keadaan hujan,
2. Luas dan bentuk daerah aliran,
3. Kemiringan daerah aliran dan kemiringan dasar sungai,
4. Daya infiltrasi dan perkolasi tanah,
5. Kebasahan tanah,
6. Suhu udara dan angin serta evaporasi dan
7. Tata guna tanah.
Koefisien pengaliran seperti yang disajikan pada tabel berikut.
Tabel A.7 Koefisien Pengaliran

C.V.3. Hidrograf Satuan Regresi Gama


Metode regresi yang digunakan untuk perhitungan adalah Metode GAMA I. Parameter-parameter
yang digunakan adalah :
a. Faktor sumber (SF) adalah perbandingan antara jumlah panjang sungai sungai tingkat 1
dengan jumlah panjang sungai semua tingkat.
b. Frekwensi sumber (SN) adalah perbandingan antara jumlah sungai sungai tingkat satu
dengan jumlah sungai semua tingkat.
c. Faktor lebar (WF) adalah perbandingan antara lebar DAS yang diukur dititik sungai yang
bertjarak 0,75 L dengan lebar DAS yang diukur dititik sungai yang berjarak 0,25 L dari tempat
pengukuran.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 25


LAPORAN AKHIR

d. Luas DAS sebelah hulu (RUA) adalah perbandingan antara luas DAS yang diukur dihulu garis
yang ditarik tegak lurus garis hubung antara lokasi pengukuran dengan titik yang dekat
dengan titik berat DAS, melewati titik tersebut.
e. Faktor simetri (SIM) adalah (WF) x (RUA)
f. Jumlah pertemuan sungai (JN) adalah jumlah semua pertemuan sungai didalam DAS.
g. Kerapatan jaringan sungai (D), Luas daerah aliran sungai (A)
Persamaan-persamaan yang digunakan untuk perhitungan adalah :
Qp = 0,1836 x A0,5886 x JN0,2381 x TR-0,4008

TR = 0,43 x ( L /(100SF))3 + 1,0665 SIM + 1,2775

TB = 27,4132 x TR0,1457 x S-0,0956 x SN-0,7344 x RUA0,2574

K = 0,5617 x A0,1798 x S-0,1446 x SF-1,0897 x D0,0452

 = 10,4903 - 3,859 x 10-6 x A2 + 1,6985 x 10-13 (A/SN)4

B = 1,5518 x A-0,1491 x N-0,2725 x SIM-0,0259 x S-0,0733

dimana :
Qp = Debit puncak ( m3/dt )
TR = Waktu naik ( jam )
TB = Waktu dasar ( jam )
K = Koefisin tampungan
 = Hujan efektif ( mm/jam )

C.VI. Kriteria Perencanaan Bangunan Hidraulik


C.VI.1. Bendung
Lokasi bendung dipilih berdasarkan alasan topografis, geologi, teknis dan ekonomis. Secara
ekonomis, artinya ditinjau dari volume pekerjaan merupakan alternatif yang paling murah. Alasan
topografis, menyangkut aspek elevasi, kondisi palung, dan lain-lain. Sedangkan alasan geologis,
menyangkut aspek stabilitas konstruksi.
Lebar efektif bendung (Be), ditentukan sebagai berikut:
Be(mercu) = B(mercu) -2 (nKp + Ka) H1
Be(pembilas) = 0,80 x B(pembilas)
Be(total) = Be(mercu) + Be(pembilas)
dimana :
Kp = Koefisien kontraksi pilar
Ka = Koefisien kontraksi pangkal bendung

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 26


LAPORAN AKHIR

H1= Tinggi energi, m


Harga-harga koefisien Ka dan Kp diberikan pada Tabel A.8.
Dalam memperhitungkan lebar efektif, lebar pembilas yang sebenarnya (dengan bagian depan
terbuka) sebaiknya diambil 80% dari lebar rencana untuk mengkompensasi perbedaan koefisien
debit dibandingkan dengan mercu bendung itu sendiri.
Tabel A.8 Harga-harga koefisien kontraksi

Keterangan Kp
Untuk pilar berujung segi empat dengan sudut-sudut yang dibulatkan 0,02
pada jari-jari yang hampir sama dengan 0,1 dari tebal pilar.
Untuk pilar berujung bulat. 0,01
Untuk pilar berujung runcing.
0
Ka
Untuk pangkal tembok segi empat dengan tembok hulu pada 90o ke arah 0,20
aliran.
Untuk pangkal tembok bulat dengan tembok hulu pada 90o ke arah aliran 0,10
dengan 0,5 H1 > r > 0,15 H1.
Untuk pangkal tembok bulat dimana r > 0,5 H 1 dan tembok hulu tidak
0
lebih dari 45o ke arah aliran

Debit yang dapat dialirkan oleh bendung untuk suatu lebar efektif dan kaitannya dengan tinggi
badan air yang berada di atas mercu di atur oleh persamaan berikut ini:
Q = C L He1.5
Dimana:
Q = Debit limpasan diatas mercu (ft3/s)
C = Koefisien debit
L = Panjang mercu pelimpah efektif (ft)
He = Tinggi tekan total, termasuk Ha (ft)
Ha = Tinggi kecepatan(ft)
Hd = Tinggi tekan rencana (ft)
Satuan dalam feet ini adalah karena koefisien dan persamaan dibuat atas dasar pengamatan dengan
memakai satuan British. Untuk selanjutnya hasil debit dan muka air harus dikonversikan lagi ke
satuan internasional.
Tinggi jagaan yang dipakai dalam merencanakan bendung adalah bahwa dalam segala kondisi harus
terdapat spasi satu meter antara muka air dengan sayap bendung.
Bentuk mercu bendung pada bagian hulu adalah dinding vertikal, sementara pada hilir bendung
dihitung menurut bentuk ogee/WES (Waterways Experiment Station) yang dikembangkan oleh
USACE (United States Army Corps of Engineer). Berikut sketsa dari mercu bentuk ogee.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 27


LAPORAN AKHIR

Gambar A.7. Bentuk Elips Puncak Bendung (EM-1110-2-160 plate 3-23, USACE manual)

Bentuk mercu bendung dihitung berdasarkan ogee:

𝑋 𝑛 = 𝐾𝐻𝑑𝑛−1 𝑌
Dimana:
X dan Y = koordinat profil mercu dengan koordinat awal terletak pada puncak mercu
Hd = kedalaman aliran tanpa tinggi kecepatan (m)
K dan n = parameter (tergantung dari kemiringan mercu sebelum puncak)
Tabel A.9 Parameter K dan n (Chow, 1986)

Kemiringan mercu sebelum


K n
puncak
Vertikal 2.000 1.850

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 28


LAPORAN AKHIR

3:1 1.936 1.836


3:2 1.939 1.810
3:3 1.873 1.776

C.VI.2. Kolam Peredam Energi


Peredam energi menggunakan tipe bak (bucket type), dimana diasumsikan bendung berada di
sungai yang mengangkut bongkah atau batu-batu besar dengan dasar yang relatif tahan gerusan.
Peredam energi memakai standar yang diakui yakni EM 1110-2-1603 dari USACE, “Hydraulic designs
of spillway”, dan juga USBR Engineering monograph No. 25, “Hydraulic designs of stilling basins and
dissipator”.
Peredam energi tipe bak menggunakan jari-jari minimum bak yang diizinkan (Rmin) dan batas
minimum tinggi air hilir (Tmin) dalam menentukan dimensinya. Perhitungan peredam energi tipe bak
menggunakan grafik untuk mendapatkan dimensi-dimensinya yang ditunjukkan pada gambar
berikut.

q2
hc  3
g
Dimana:

hc = kedalaman aliran kritis (m)


q = debit per lebar satuan (m3/s.m)
g = percepatan gravitasi (9,81 m/s2)

Gambar A.8 Jari-Jari Minimum Bak (KP-02 1986)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 29


LAPORAN AKHIR

Gambar A.9 Batas Minimum Tinggi Air di Hilir (KP-02 1986)

Gambar A.10 Sketsa Penampang Peredam Energi Tipe Bak (KP-02, 1986)

C.VI.3. Pintu Pengambilan Bendung


Pintu pengambilan direncanakan sebagai pintu tenggelam, dimana besarnya debit yang mengalir

Q = μ a b 2gz
Dimana:
μ = Koefisien debit
a = Tinggi bukaan , m
b = Lebar bukaan, m
h = Kehilangan tinggi energi pada bukaan, m
C.VI.4. Kolam Pengendap Lumpur
Kantong lumpur merupakan pembesaran potongan melintang saluran sampai panjang tertentu
untuk mengurangi kecepatan aliran dan memberi kesempatan kepada sedimen untuk mengendap.
Untuk menampung endapan sedimen ini, dasar bagian saluran tersebut diperdalam atau diperlebar.
Tampungan ini dibersihkan tiap jangka waktu tertentu dengan cara membilas sedimennya kembali
ke sungai dengan aliran terkonsentrasi yang berkecepatan tinggi. (KP-02, 1986)
Tujuan kantong lumpur adalah untuk menghilangkan partikel sedimen yang berbahaya bagi turbin.
Dimana kecepatan pengendapan partikel didefinisikan dengan kecepatan:
Tabel A.10 Kecepatan Pengendapan

Particle Diameter (mm) 0.3 0.4 0.5 0.7 1.0

Kecepatan jatuh sedimen (mm/s) 45 60 70 95 120

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 30


LAPORAN AKHIR

Dalam menentukan dimensi kantong lumpur dapat digunakan rumus sebagai berikut:
Lebar kantong lumpur:
𝑄
𝐵=
ℎ𝑣
Dimana:
B = lebar kantong lumpur (m)
h = tinggi kantong lumpur (m)
Q = 1.1 x debit pembangkitan (m3/s)
v = kecepatan aliran dalam kantong lumpur (m/s)
Waktu pengendapan:

𝑡=
𝑤
Dimana:
t = waktu pengendapan (s)
h = tinggi kantong lumpur (m)
w = kecepatan jatuh sedimen (m/s)
Panjang kantong lumpur saat kondisi diam:
L =v*t
Dimana:
L = panjang kantong lumpur (m)
t = waktu pengendapan (s)
v = kecepatan aliran dalam kantong lumpur (m/s)
kecepatan pengendapan:
0.132𝑣
𝑤1 =
ℎ0.5
Dimana:
w1 = kecepatan pengendapan (m/s)
h = tinggi kantong lumpur (m)
v = kecepatan aliran dalam kantong lumpur (m/s)
kecepatan pengendapan efektif:
w2 = w - w1
Dimana:
W2 = kecepatan pengendapan efektif (m/s)
w1 = kecepatan pengendapan (m/s)
w = kecepatan jatuh sedimen (m/s)
Waktu pengendapan: (kondisi aliran turbulen)

𝑡𝑡 =
𝑤2
Dimana:
tt = waktu pengendapan (s)
h = tinggi kantong lumpur (m)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 31


LAPORAN AKHIR

W2 = kecepatan pengendapan efektif (m/s)


Panjang kantong lumpur: (kondisi aliran turbulen)
Lt = v * tt
Dimana:
Lt = Panjang kantong lumpur (m)
tt = waktu pengendapan (s)
v = kecepatan aliran dalam kantong lumpur (m/s)

C.VI.5. Bangunan Bagi Sadap


Bangunan bagi-sadap adalah sebuah bangunan yang berfungsi membagikan air dan menyabang dari
:
 Saluran primer ke saluran primer yang lain dan atau dari saluran primer ke saluran tersier.
 Saluran primer ke saluran sekunder dan atau saluran sekunder ke saluran tersier.
 Saluran sekunder yang satu ke saluran sekunder yang lain dan atau saluran sekunder ke
saluran tersier.
Bangunan bagi-sadap terletak di saluran primer dan/atau saluran sekunder. Bangunan bagi dan
bangunan sadap dapat digabung menjadi satu rangkaian.
Untuk mengontrol taraf muka air di bagian hilir bangunan, umumnya diperlukan bangunan
pengatur. Untuk mengatur debit air di atas 900 liter/detik dapat digunakan alat pengukur debit tipe
Crump de Gruyter atau Cipoletti. Untuk pengukuran debit lebih kecil dari 900 l/det dapat digunakan
alat ukur tipe Romijin.

Gambar A.11 Contoh bangunan bagi-sadap

C.VI.6. Bangunan Terjun


Dalam suatu sistem drainase, saluran drainase sangat erat hubungannya dengan bangunan
pelengkapnya, seperti bangunan terjunan, bangunan silang seperti gorong-gorong dan box culvert,
pintu air, pompa dan rumah pompa, sumur resapan, bangunan penyaring sampah, kolam
penampungan sementara atau kolam tandon, dan lain-lain. Masing-masing bagian mempunyai

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 32


LAPORAN AKHIR

peranan tersendiri. Pada kesempatan kali ini kumpulengineer akan membahas sedikit tentang
bangunan terjunan.
Bangunan terjunan adalah suatu bangunan pelengkap sistem drainase yang dibangun untuk
mengurangi kemiringan saluran yang terlalu curam dan untuk menurunkan kecepatan aliran air agar
tidak merusak saluran atau bangunan lainnya.
D. Lebar bukaan efektif (B)
𝑄
𝐵=
1,71 𝑚 𝐻 3/2

𝑣1
𝐻 = ℎ1 +
2𝑔

Dengan
B = lebar bukaan efektif (m)
Q = debit (m3 /dt)
m = koefisien aliran = 1
H = tinggi gari energi di udik (m)
h1 = tinggi muka air di udik (m)
v1 = kecepatan aliran saluran di hulu (m/dt)
E. Tinggi ambang di hilir (a)
1
𝑎 = 𝑑𝑐
2
𝑄2
𝑑𝑐 =
(𝑔. 𝐵2 )1/3
Dimana:
A = tinggi ambang hilir (m)
Dc = kedalaman air kritis (m)
Q = koefisien aliran = 1
B = lebar bukaan efektif (m)
F. Panjang olakan (L)
𝐿 = 𝐶1 𝑍 𝑑𝑐 + 0,25

𝑑𝑐 𝑑𝑐 3
𝐶1 = 2,5 + 1,1 ( ) + 0,7 ( )
𝑍 𝑍
Dimana:
L = panjang kolam olakan (m)
Z = tinggi terjun (m)
Dilihat dari bentuknya, secara umum bangunan terjun terbagi dua, yaitu:
1. Bangunan terjunan tegak
Bangunan terjunan tegak biasanya terdapat pada saluran induk dan saluran sekunder.
Tinggi terjun pada Bangunan terjunan tegak dibatasi maksimum 1,50 meter untuk debit

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 33


LAPORAN AKHIR

aliran kurang dari 2,50 m3/detik. Sedangkan untuk debit lebih dari 2,50 m3/detik tinggi
terjun maksimum adalah 0,75 meter.
2. Bangunan terjunan miring
Pada Bangunan terjunan miring kedalaman air tidak boleh kurang dari 0,4 kali kedalaman
kritis. Apabila kecepatan aliran di dalam bangunan terjunan miring lebih dari 9
meter/detik maka dinding saluran terjunan harus ditinggikan.

Gambar A.12 Contoh bangunan terjun

C.VI.7. Saluran Terbuka


Kapasitas saluran setiap saluran dihitung dengan menggunakan persamaan pada aliran steady
uniform yaitu persamaan manning
1 3
v  1 So 2  R 2
n
Dimana:
v = Kecepatan aliran (m/det)
So = Kemiringan energi (m/m)
R = Jari-jari hidrolik (m) = A/P
A = Luas Basah (m2)
P = Keliling Basah (m)
Sedangkan,
Q  Av
Dimana:
Q = Debit rencana (m3/det)
A = Luas Basah (m2)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 34


LAPORAN AKHIR

C.VII. Analisis Ekonomi


Analisis ekonomi teknik (engineering economic analysis) adalah bagian dari ilmu ekonomi yang
diaplikasikan pada proyek-proyek teknik. Digunakan oleh para insinyur untuk mencari solusi terbaik
dengan mengukur nilai ekonomi dari setiap alternatif solusi yang potensial.
Masalah yang dapat diselesaikan menggunakan alnalisis ekonomi teknik adalah masalah yang
memiliki tiga karakteristik berikut:
1. Masalah itu cukup penting, dan memerlukan pemikiran dan usaha serius dalam
pemecahannya.
2. Masalah tersebut tidak dapat diselesaikan dalam pemikiran tapi memerlukan analisis yang
teliti yang mengorganisasikan setiap elemen masalah dan semua konsekuensi yang mungkin
terjadi, dan tidak dapat diselesaikan sekaligus.
3. Masalah itu memiliki aspek ekononis yang cukup penting sebagai komponen yang
mengarahkan analisis pada keputusan.
Ada beberapa hal yang perlu dilakukan untuk melakukan suatu analisis kelayakan ekonomi untuk
mengambil sebuah keputusan yakni, mengenali suatu masalah, menetapkan tujuan dan sasaran,
menyuusun data yang relevan mengidentifikasi alternatif yang layak, menetapkan kriteria penilaian
alternatif dimana untuk menilai suatu alternatif dapat dilakukan dengan cara yang berbeda, seperti:

 Menghasilkan paling sedikit kerusakan ekologi


 Memperbaiki distribusi kekayaan penduduk
 Menggunakan uang secara efisiensi ekonomis
 Minimasi pengeluaran uang
 Memastikan bahwa yang mendapatkan benefit dari keputusan lebih banyak daripada yang
merugi akibat keputusan itu
 Minimasi waktu pencapaian tujuan
Kemudian hal selanjutnya yang dilakukan adalah memprediksi keluaran alternatif serta memilih
sebuah pilihan yang paling banyak memenuhi kriteria dan kebutuhan.
Analisis ekonomi dilaksanakan dengan metode IRR (Internal Rate of Return) yang akan dilengkapi
cash flow disamping itu akan dilakukan perhitungan untuk mendapatkan besaran-besaran sebagai
berikut.
1. Benefit cost ratio (B/C Ratio)
Untuk mengkaji kelayakan proyek sering digunakan pula evaluasi yang disebut benefit – cost
ratio, B/C Ratio, Rumus yang digunakan sebagai berikut:

Adapun kriteria B/C Ratio akan memberikan petunjuk sebagai berikut:


• BCR > 1, usulan proyek diterima.
• BCR < 1, usulan proyek ditolak.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 35


LAPORAN AKHIR

• BCR = 1, netral
2. NPV (Nett Present Value)
Evaluasi nilai sekarang netto (net present value / NPV) didasarkan pada konsep mendiskontokan
seluruh aliran kas ke nilai sekarang. Ditulis dengan rumus :

Dimana:
NPV = nilai sekarang netto (dollar atau rupiah)
(B)t = benefit pada tahun ke t (dollar atau rupiah)
(C)t = biaya pada tahun ke t (dollar atau rupiah)
n = umur ekonomis proyek (tahun)
i = arus pengembalian
t = waktu (tahun)
Mengkaji usulan proyek dengan NPV memberikan petunjuk (indikasi) sebagai berikut:
• NPV = Positif, usulan proyek dapat diterima, makin tinggi angka NPV makin baik.
• NPV =Negatif, usulan proyek ditolak.
• NPV = 0, netral.
3. Payback period
Periode pengembalian atau payback period adalah jangka waktu yang diperlukan untuk
mengembalikan modal suatu investasi, yang dihitung dari aliran kas bersih (net). Untuk
mendapatkan periode pengembalian (rate of return) tertentu di gunakan model formula
berikut.

D. KEGIATAN IV : PENYUSUNAN LAPORAN DAN DISKUSI


Laporan dan diskusi yang ada dalam KAK adalah sebagai berikut:
A. Laporan
a) Laporan Pendahuluan
b) Laporan Antara
c) Draft Laporan Akhir
d) Laporan Akhir
i. Latar belakang
ii. Ruang lingkup
iii. Maksud dan tujuan
iv. Lokasi Pekerjaan dan volume
v. Hasil akhir/kesimpulan/resume/analisis pekerjaan
vi. Peralatan dan data yang telah digunakan atau dikumpulkan

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 36


LAPORAN AKHIR

vii. Struktur organisasi dan pelaksana pekerjaan


viii. Buku-buku perencanaan sesuai output pekerjaan
ix. Berita acara alih pengetahuan sesuia output pekerjaan
B. Diskusi
1) Alih Pengetahuan
E. OGANISASI, KEWENANGAN DAN TANGGUNGJAWAB
E.I. Pusat
Pusat dalam hal ini adalah Direktorat Jenderal Prasarana dan Sarana Pertanian, mempunyai tugas
sebagai berikut:
a. Menetapkan sasaran dan kebijakan operasional perluasan sawah;
b. Menetapkan program dan penganggaran perluasan sawah;
c. Menerbitkan pedoman teknis perluasan sawah;
d. Melaksanakan pemantauan, evaluasi dan bimbingan teknis perluasan sawah.

E.II. Provinsi
E.III.1. Tim Pengendali dan Pembina Provinsi
Tim pengendali dan pembina diangkat dan ditetapkan oleh Gubernur atau pejabat yang ditunjuk,
dengan susunan sebagai berikut :
Ketua : Gubernur atau pejabat yang ditunjuk
Sekretaris : Kepala Dinas Pertanian Provinsi
Anggota : Unsur Muspida yang terkait atau pejabat yang ditunjuk
Tim Pengendali dan Pembina mempunyai tugas sebagai berikut :
a. Melakukan pengendalian dan pembinaan kegiatan perluasan sawah sejak perencanaan,
pelaksanaan, evaluasi;
b. Memberikan rekomendasi untuk pemecahan masalah yang belum dapat diselesaikan di
tingkat Provinsi dan Kabupaten.
E.III.2. Tim Teknis
Tim teknis diangkat dan ditetapkan oleh Kepala Dinas Pertanian Provinsi, selaku KPA dengan
susunan sebagai berikut :
Ketua : Berasal dari Dinas Pertanian Povinsi
Sekretaris : Berasal dari Dinas Pertanian Povinsi
Anggota : Berasal dari Dinas Pertanian Provinsi dan Instansi Teknis terkait di Tingkat Provinsi
Tugas tim teknis provinsi adalah :
a. Melakukan pembinaan dan bimbingan teknis pelaksanaan perluasan sawah dan
pemanfaatan sawah
b. Menyajikan bahan-bahan monitoring dan evaluasi serta penyusunan alternatif pemecahan
masalah yang timbul antar instansi terkait

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 37


LAPORAN AKHIR

c. Menyiapkan bahan/data yang diperlukan untuk rapat-rapat Tim Pengendali dan Pembina
Provinsi
d. Menyampaikan laporan kegiatan perluasan sawah kepada Tim Pengendali dan Pembina
Provinsi

E.III. Kabupaten
E.III.1. Tim Pengendali dan Pembina Kabupaten
Tim pengendali dan pembina diangkat dan ditetapkan oleh Bupati, dengan susunan sebagai berikut:
Ketua : Bupati atau Pejabat yang ditunjuk
Sekretaris : Kepala Dinas Pertanian Kabupaten
Anggota : Unsur Muspida yang terkait
Tim pengendali dan pembina kabupaten mempunyai tugas yaitu:
1. Melakukan pengendalian dan pembinaan dalam pelaksanaan kegiatan perluasan sawah
mulai dari persiapan, perencanaan, pelaksanaan, pengawasan hingga evaluasi dan
pelaporan;
2. Mengusahakan pemecahan masalah yang belum dapat diselesaikan di tingkat lapangan dan
mengkoordinasikannya dengan instansi yang terkait;
E.III.2. Tim Perencana Kegiatan Perluasan Sawah
Tim perencana diangkat dan ditetapkan oleh Kepala Dinas Pertanian Kabupaten selaku PPK, dengan
susunan sebagai berikut:
Ketua : Petugas Dinas Pertanian Kabupaten
Sekretaris : Petugas Dinas Pertanian Kabupaten
Anggota : Petugas Dinas Pertanian Kabupaten dan Petugas dari Instansi Pelaksana
Konstruksi Perluasan Sawah. Untuk anggota dari instansi pelaksana konstruksi,
petugas yang masuk kedalam tim berdasarkan surat penetapan dari Instansi
tersebut.
Apabila diperlukan dapat melibatkan petugas dari instansi pemerintah lainya dalam kapasitas
sebagai narasumber
Tim perencana perluasan sawah mempunyai tugas yaitu:
1. Menyiapkan dokumen perencanaan perluasan sawah yang berasal dari review terhadap
dokumen hasil survei CPCL dan Pemetaan Desain;
2. Sosialisasi kegiatan perluasan sawah kepada seluruh stakeholder;
3. Menyiapkan Kerangka Acuan Kerja (KAK), RAB dan Jadual pelaksanaan kegiatan perluasan
sawah;
E.III.3. Tim Pengawas Perluasan Sawah
Tim pengawas di tingkat Kabupaten ditetapkan oleh PPK yang beranggotakan dari unsur Dinas
Pertanian Kabupaten selaku Penanggungjawab Anggaran dan dari Instansi Pelaksana Swakelola
Perluasan Sawah.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 38


LAPORAN AKHIR

Bila dipandang perlu Tim Pengawas ini dapat melibatkan:


1. Tenaga ahli perorangan antara lain dibidang sipil konstruksi, pemetaan, pengukuran tanah
dan administrasi keuangan dan managemen informasi sesuai dengan Perpres 54 Tahun
2010.
2. Tenaga ahli dari instansi pemerintah terkait sebagai narasumber
Tim pengawas bertugas membantu Kepala Dinas Pertanian Kabupaten selaku PPK dalam
menjalankan tugas dan fungsi pengawasan yaitu:
1. Melakukan pengawasan aspek administrasi dan keuangan maupun teknis pelaksanaan
perluasan sawah;
2. Melakukan pemantauan dan pelaporan secara periodik pelaksanaan perluasan sawah;
3. Melakukan evaluasi berkala terhadap kemajuan pelaksanaan pekerjaan perluasan sawah;
4. Melakukan identifikasi permasalahan yang dihadapi dalam pelaksanaan perluasan sawah
dan disampaikan kepada PPK untuk memperoleh pemecahan masalah.
E.III.4. Pejabat/Panitia Penerima Hasil Pekerjaan (PPHP)
PPHP diangkat dan ditetapkan oleh KPA, dengan susunan Ketua, Sekretaris dan Anggota berasal dari
PNS lingkup Dinas Pertanian Kabupaten dan instansi lain yang memiliki kemampuan dibidang
pengukuran dan pemetaan.
PPHP mempunyai tugas dan fungsi dalam hal :
1. Melakukan pemeriksaan hasil pekerjaan berdasarkan pengukuran progres/hasil tiap
tahapan pekerjaan yang dilakukan oleh Pelaksana swakelola kegiatan perluasan sawah;
2. Membuat berita acara hasil pemeriksaan pekerjaan fisik kegiatan perluasan sawah;
3. Menyiapkan Berita Acara Serah Terima hasil pekerjaan perluasan sawah dari PPK kepada
KPA.

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 39


LAPORAN AKHIR

LAMPIRAN B. TABULASI HASIL ANALISIS


HIDROLOGI (DEBIT ANDAL DAN DEBIT BANJIR)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 40


LAPORAN AKHIR

LAMPIRAN C. BILL OF QUANTITY (BOQ), RENCANA


ANGGARAN BIAYA (RAB), HARGA MATERIAL
ALAT, DAN ANALISIS HARGA SATUAN (AHS)

DED DAERAH IRIGASI GUDANG KAB. BANGKA SELATAN 41