Anda di halaman 1dari 5

REKAPITULASI

SAT-KER : DINAS KELAUTAN & PERIKANAN KABUPATEN KOLAKA


PEKERJAAN : PEMBANGUNAN GEDUNG TEMPAT PELELANGAN IKAN (TPI) ANAIWOI
LOKASI : KECAMATAN TANGGETADA
SUMBER DANA : DAU-APBD
TAHUN ANGG. : 2020

JUMLAH HARGA
BAG. URAIAN PEKERJAAN
(Rp.)

I PEKERJAAN PERSIAPAN 1.000.000,00


II PEKERJAAN TANAH 11.069.937,33
III PEKERJAAN PONDASI 35.993.729,27
IV PEKERJAAN BETON 24.378.254,11
V PEKERJAAN BESI & ALUMINIUM 10.445.764,82
VI PEKERJAAN DINDING 10.723.925,40
VII PEKERJAAN PLESTERAN 8.827.539,74
VIII PEKERJAAN ATAP 12.045.080,76
IX PEKERJAAN KAYU 3.172.625,83
X PEKERJAAN KUNCI & KACA 1.414.292,63
XI PEKERJAAN PENGECATAN 3.125.898,44
XII PEKERJAAN SANITASI 4.746.941,10
XIII PEKERJAAN LAIN-LAIN 500.000,00

A REAL COST (I s/d XVI) 127.443.989,42


B PPn (10% x A) 12.744.398,94
C TOTAL COST (A+B) 140.188.388,36
D DIBULATKAN 140.188.000,00

TERBILANG : SERATUS EMPAT PULUH JUTA SERATUS DELAPAN PULUH DELAPAN RIBU RUPIAH

Kolaka, 2019
Plt. Kepala Dinas Kelautan & Perikanan Konsultan Perencana
Kabupaten Kolaka CV. PANCAR SEMESTA ALAM
Selaku Pengguna Anggaran (PA) Pusat Kolaka

……………………….. JUSTIAN TAPUHE, A.Md


NIP. ………………. Direktur
RENCANA ANGGARAN BIAYA (RAB)
SAT-KER : : DINAS KELAUTAN & PERIKANAN KABUPATEN KOLAKA
PEKERJAAN : : PEMBANGUNAN GEDUNG TEMPAT PELELANGAN IKAN (TPI) ANAIWOI
LOKASI : : KECAMATAN TANGGETADA
SUMBER DANA : : DAU-APBD
TAHUN ANGG. : : 2020

HARGA JUMLAH HARGA


NO. URAIAN PEKERJAAN SAT. KUANT.
SATUAN (Rp.) (Rp.)

I PEKERJAAN PERSIAPAN
1 Pengukuran & Pemasangan Bouwplank Ls 1,00 1.000.000,00 1.000.000,00
JUMLAH TOTAL I 1.000.000,00

II PEKERJAAN TANAH
3
1 Galian Tanah Biasa Sedalam 0-1 Meter (Talud) m 20,70 83.761,25 1.733.857,88
2 Galian Tanah Biasa Sedalam 0-1 Meter (Pondasi) m3 34,44 83.761,25 2.884.318,64
3 Urugan Tanah Kembali Bekas Galian m3 16,13 34.154,25 550.771,44
4 Urugan Pasir m3 5,81 169.104,50 981.989,83
5 Timbunan Biasa (Lahan) m3 49,16 91.106,25 4.479.093,01
3
6 Urugan Biasa (Bawah Lantai) m 4,83 91.106,25 439.906,53
JUMLAH TOTAL II 11.069.937,33

III PEKERJAAN PONDASI


1 Pasangan Batu Kosong (Talud) m3 6,11 568.418,25 3.473.035,51
2 Pasangan Batu Kosong (Pondasi) m3 5,46 568.418,25 3.103.563,65
3 Pasangan Batu Belah 1PC : 4PP (Talud) m3 20,73 1.031.695,65 21.387.050,82
4 Pasangan Batu Belah 1PC : 4PP (Pondasi) m3 7,78 1.031.695,65 8.030.079,29
JUMLAH TOTAL III 35.993.729,27

IV PEKERJAAN BETON
1 Rabat Beton Mutu K.100 (Dilicin) T=5 cm m3 1,73 959.231,82 1.661.389,51
2 Sloof Beton Mutu K.175 m3 1,04 1.190.779,88 1.241.388,02
3 Kolom Beton Mutu K.175 m3 1,03 1.190.779,88 1.229.492,13
4 Balok Latei Beton Mutu K.175 m3 0,12 1.190.779,88 137.535,08
5 Ringbalk Beton Mutu K.175 m3 1,08 1.190.779,88 1.286.042,27
3
6 Plat Dak Beton Mutu K.175 m 0,81 1.190.779,88 958.577,80
7 Pembesian Sloof (Polos) Kg 152,35 20.054,39 3.055.236,18
8 Pembesian Kolom (Polos) Kg 204,49 20.054,39 4.100.855,36
9 Pembesian Balok Latei (Polos) Kg 27,03 20.054,39 542.084,60
10 Pembesian Ringbalk (Polos) Kg 109,80 20.054,39 2.201.921,89
11 Pembesian Plat Dak (Polos) Kg 134,99 20.054,39 2.707.108,68
HARGA JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. KUANT.
SATUAN (Rp.) (Rp.)
12 Bekisting Sloof m2 7,20 117.717,75 847.567,80
13 Bekisting Kolom Utama m2 5,63 184.853,88 1.039.803,05
14 Bekisting Kolom Praktis m2 1,72 92.426,94 158.604,62
15 Bekisting Balok Latei m2 1,05 126.173,92 132.482,61
2
16 Bekisting Ringbalk m 7,20 189.260,88 1.362.678,30
17 Bekisting Plat Dak m2 8,05 213.103,88 1.715.486,19
JUMLAH TOTAL IV 24.378.254,11
V PEKERJAAN BESI & ALUMINIUM
1 Rangka Atap Baja Ringan m2 87,40 119.516,76 10.445.764,82
JUMLAH TOTAL V 10.445.764,82
VI PEKERJAAN DINDING
1 Pas. Dinding Bata T=1/2 Batu, 1PC : 2PP m2 33,05 186.311,01 6.157.578,88
2 Pas. Dinding Bata T=1/2 Batu, 1PC : 5PP m2 27,01 169.061,33 4.566.346,52
JUMLAH TOTAL VI 10.723.925,40
VII PEKERJAAN PLESTERAN
1 Plesteran Dinding 1PC : 2PP Tebal 15 mm m2 66,10 77.539,74 5.125.376,81
2 Plesteran Dinding 1PC : 5PP Tebal 15 mm m2 54,02 68.533,19 3.702.162,92
JUMLAH TOTAL VII 8.827.539,74
VIII PEKERJAAN ATAP
1 Pasangan Atap Spandeck m2 87,40 116.491,70 10.181.374,58
1
2 Pasangan Nok Galvalium Plat m 25,67 72.602,50 1.863.706,18
JUMLAH TOTAL VIII 12.045.080,76
IX PEKERJAAN KAYU
1 Kusen Kayu Kelas-II m3 0,18 7.852.370,00 1.446.995,48
2 Pintu Panil Kayu Kelas-II m2 2,54 678.847,50 1.725.630,35
JUMLAH TOTAL IX 3.172.625,83
X PEKERJAAN KUNCI & KACA
1 Kaca Bening 5 mm m2 1,20 370.263,71 444.316,45
2 Kunci Tanam Biasa Bh 2,00 270.663,25 541.326,50
3 Grendel Pintu Biasa Bh 2,00 65.446,21 130.892,42
4 Engsel Pintu Biasa Bh 6,00 49.626,21 297.757,26
JUMLAH TOTAL X 1.414.292,63
XI PEKERJAAN PENGECATAN
1 Cat Kayu Baru (1Pla, 1Cat Dsr, 3Cat Pen) m2 6,42 63.814,05 409.399,04
2 Pelaburan Kayu Dengan Vernis m2 5,08 65.450,73 332.751,51
3 Cat Tembok Baru (1Pla, 1Cat Dsr, 2Cat Pen) m2 108,11 22.049,69 2.383.747,89
JUMLAH TOTAL XI 3.125.898,44
XII PEKERJAAN SANITASI
1 Kloset Jongkok Bh 1,00 716.939,80 716.939,80
2 Floor Draine Bh 1,00 71.331,25 71.331,25
3 Kran Air Ø1/2" Bh 1,00 132.520,75 132.520,75
1
4 Pipa PVC Type AW Ø1/2" (Air Bersih) m 10,00 27.314,93 273.149,30
5 Septictank Ls 1,00 3.553.000,00 3.553.000,00
JUMLAH TOTAL XII 4.746.941,10
XIII PEKERJAAN LAIN-LAIN
1 Pembersihan Akhir Ls 1,00 500.000,00 500.000,00
JUMLAH TOTAL XIII 500.000,00
140 970 30

150 200 300 200 120

125
R. RETRIBUSI PODIUM KM/WC

150

150
±0.00 ±0.00 -0.05

625

500
240
RUANG LELANG

350
±0.00
55

100

100
MAIN ENTRANCE
125

125
-0.10

200 300 200

125 700 125

DENAH
SKALA 1 : 100

CATATAN / REVISI PARAF MENGETAHUI / MENYETUJUI DIPERIKSA / DISETUJUI OLEH NAMA GAMBAR SKALA NO. PAKET KODE GAMBAR KONSULTAN PERENCANA ADD. NOTES :
PEMERINTAH KABUPATEN KOLAKA
DINAS KELAUTAN & PERIKANAN DENAH 1 : 100 Jbt
Jl. Pemuda No. Telp.(0405) .......... Kolaka
- 01
PRA-DESIGN NO. GAMBAR JLH. LEMBAR DIREKTUR
Team Leader

PEMBANGUNAN Architect
GEDUNG TEMPAT PELELANGAN IKAN (TPI) ANAIWOI
KECAMATAN TANGGETADA
TAHUN ANGGARAN 2019 01 02 JUSTIAN T., A.Md Surveyor

CAD Draftman
TPI ANAIWOI

120

220
TAMPAK DEPAN
SKALA 1 : 100

TAMPAK BELAKANG
SKALA 1 : 100
220

TAMPAK SAMPING
SKALA 1 : 100

CATATAN / REVISI PARAF MENGETAHUI / MENYETUJUI DIPERIKSA / DISETUJUI OLEH NAMA GAMBAR SKALA NO. PAKET KODE GAMBAR KONSULTAN PERENCANA ADD. NOTES :
PEMERINTAH KABUPATEN KOLAKA
DINAS KELAUTAN & PERIKANAN TAMPAK 1 : 100 Jbt
Jl. Pemuda No. Telp.(0405) .......... Kolaka
- 01
PRA-DESIGN NO. GAMBAR JLH. LEMBAR DIREKTUR
Team Leader

PEMBANGUNAN Architect
GEDUNG TEMPAT PELELANGAN IKAN (TPI) ANAIWOI
KECAMATAN TANGGETADA
TAHUN ANGGARAN 2019 02 02 JUSTIAN T., A.Md Surveyor

CAD Draftman