BILL OF QUANTITY

PROYEK : PERUMAHAN MUTIARA LAND BOUW


PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL TYPE 36 LB/ 98 LT
PAKET PEKERJAAN : STRUKTUR, ARSITEKTUR DAN ELEKTRIKAL
LOKASI : PERDAGANGAN

KONSULTAN BoQ
TANGGAL : 19-Agu-19 CV. HARYANTO ARSTEKTUR (HAS), Medan-Indonesia
REVISI KE : - 0811 6484 545

NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN TOTAL


(Rp.) (Rp.)

A PEKERJAAN JALAN LINGKUNGAN

1 Pekerjaan Jalan Lingkungan, Beton K175, Wiremesh M6 M² 10.932,66 163.700 1.789.676.442

2 Pekerjaan Bahu Jalan M² 2.199,87 34.000 74.795.580

3 Pekerjaan Parit Lingkungan M' 4.311,17 24.850 107.132.575

PEKERJAAN PERSIAPAN TOTAL HARGA Rp. 1.971.604.597


ANALISA HARGA SATUAN
PERUMAHAN MUTIARA LAND BOUW
PERDAGANGAN

NO URAIAN KOEF. SAT. HARGA SAT TOTAL HARGA


( Rp ) ( Rp )

36 1m² JALAN LINGKUNGAN, BETON K175. T = 10 mm


Beton K=175 0,105 m3 774.044,44 81.274,67
Wiremesh M6 1,050 m² 30.864,20 32.407,41
Base 0,158 m3 126.562,50 19.933,59
Upah kerja 1,000 unit 25.000,00 25.000,00
Alat bantu 1,000 unit 5.000,00 5.000,00
163.616
Profit & Overhead 0% 0
Dibulatkan 163.700,00

37 1m² BAHU JALAN


Base 0,158 m3 126.562,50 19.933,59
Upah kerja 1,000 unit 11.000,00 11.000,00
Alat bantu 1,000 unit 3.000,00 3.000,00
33.934
Profit & Overhead 0% 0
Dibulatkan 34.000,00