Anda di halaman 1dari 123

HARGA SATUAN UPAH DAN BAHAN

KOTA MATARAM TH. 2018

NO. JENIS UPAH/BAHAN HARGA SATUAN SATUAN


1 2 3 4
A HARGA SATUAN UPAH
2 Pekerja 65,500.00 Hari
3 Buruh terampil 65,500.00 Hari
4 Mandor 102,180.00 Hari
5 Tukang batu 89,080.00 Hari
6 Kepala tukang batu 94,975.00 Hari
7 Tukang kayu 89,080.00 Hari
8 Kepala tukang kayu 94,975.00 Hari
9 Tukang besi 89,080.00 Hari
10 Kepala tukang besi 94,975.00 Hari
11 Tukang cat 89,080.00 Hari
12 Kepala tukang cat 94,975.00 Hari
13 Tukang las 85,250.00 Hari
14 Kepala tukang las 90,750.00 Hari
15 Tukang gypsum 85,250.00 Hari
16 Kepala tukang gypsum 90,750.00 Hari
17 Tukang alumunium 89,080.00 Hari
18 Kepala tukang alumunium 94,975.00 Hari
19 Tukang pipa 89,080.00 Hari
20 Kepala tukang pipa 94,975.00 Hari
21 Tukang listrik 89,080.00 Hari

B. HARGA SATUAN BAHAN. DAN ALAT


B.1 Bahan Pasangan
1 Batu kali belah 125,000.00 m³
2 Tanah urug 62,500.00 m³
3 Pasir urug 100,000.00 m³
4 Pasir pasang 125,000.00 m³
5 Pasir cor beton - 1 m³/1400 kg 150,000.00 m³
6 Pasir cor 107.14 kg
7 Sirtu Royalti 113,300.00 m³
8 Semen (Portland semen) = 50 kg 61,000.00 zak
9 Semen/Pc 1,220.00 kg
10 Semen warna mutu baik 16,800.00 kg
11 Semen putih 8,000.00 kg
12 Bata merah klas I 575.00 bh
13 Krikil pecah 2-3cm - 1 m³ /1350 kg 220,000.00 m³
14 Krikil pecah 2-3cm 162.96 kg
15 Buis beton 1/2 Ø 20cm - 1m 40,000.00 m¹
16 Buis beton 1/2 Ø 30cm - 1m 60,000.00 m¹
17 Roster pejaten (20x20)cm 6,500.00 Bh
18 Paving blok press hidrolis t.8cm K.300 110,000.00 m²
19 Beton kerb/canten (Uk. 20x20x40)cm 30,000.00 bh
20 Ijuk 20,000.00 kg

B.2 Bahan Lantai


### Keramik 20x20cm kw 1 (mutu menengah) 56,500.00 m²
### Keramik 20x25cm kw 1 (mutu menengah) 60,000.00 m²
### Keramik 30x30cm kw 1 (mutu menengah) 60,000.00 m²
### Keramik 40x40cm kw 1 (mutu menengah) 60,000.00 m²
### Keramik 10x40cm kw 1 (mutu menengah) 6,029.17 bh
### Keramik 18x30cm kw 1 (mutu menengah) 5,454.55 bh
### Keramik kembang 10x20cm kw 1 8,500.00 bh
### Granite tile 60x60cm 325,000.00 m²
### Granite tile 30x60cm 275,000.00 m²
### Granite tile 30x30cm 265,000.00 m²
### Granite tile 15x60cm 27,083.33 m²
### Batu palimanan motip sisir 150,000.00 m²
### Batu tempel andesit 150,000.00 m²
NO. JENIS UPAH/BAHAN HARGA SATUAN SATUAN
1 2 3 4

B.3 Bahan Kayu


1 Balok kayu kelas I 11,500,000.00 m³
2 Papan kayu kelas I 12,000,000.00 m³
3 Balok kayu kelas II 5,675,000.00 m³
4 Papan kayu kelas II 5,450,000.00 m³
5 Papan kayu kelas III 2,750,000.00 m³
6 Balok kayu kelas III 2,750,000.00 m³
7 Bambu perancah ø 10cm - 4 m 9,000.00 btg

B.4 Bahan Langit-langit


1 Triplek 120x240x9mm 145,000.00 lbr
2 Triplek 120x240x6mm 96,000.00 lbr
3 Triplek 120x240x4mm 87,500.00 lbr
4 Teakwood 120x240x4mm 106,250.00 lbr
5 Teakblok 120x240x1,8mm 265,000.00 lbr
6 Triplek aluminium 130,000.00 lbr
7 Kalsiboard 120x240x3,5mm 77,500.00 lbr
8 Kalsiboard 120x240x6mm 113,750.00 lbr
9 Kalsiclad 120x240x10mm 200,000.00 lbr
10 Gypsumboard 120x240x9mm 118,750.00 lbr
11 Lapisan HPL (Uk.120x240)cm 218,750.00 lbr
12 Plester kalsiboard 2,080.00 m¹
13 Plasting claster 2,080.00 m¹
14 Tepung gypsum 2,080.00 kg
15 List plafond gypsum C 15,500.00 m¹
16 List plafond gypsum C7 11,500.00 m¹
17 List plafond kayu 1x4cm 6,500.00 m¹
18 List pintu kayu profil 2x3cm 11,500.00 m¹

B.5 Bahan Atap


1 Atap genteng beton flat press minimalis warna 123,117.50 m²
2 Atap genteng pejaten press 1,550.00 bh
2 Bubungan genteng pejaten press 3,600.00 bh
3 Bubungan genteng beton flat press 12,100.00 bh
4 Atap zinkcalume 0,35mm - L.70cm 65,000.00 m¹
5 Bubungan genteng metalzing warna 0,35mm 50,000.00 m¹
6 Seng plat zinkcalume 0,35mm 69,500.00 lbr
7 Kalsiplank 8mm - 20cm 27,500.00 m¹
8 Kalsiplank 8mm - 30cm 45,000.00 m¹

B.6 Bahan Kaca


1 Kaca bening 3mm 103,500.00 m²
2 Kaca bening 5mm 129,500.00 m²
3 Kaca ryben 5mm 135,975.00 m²
4 Kaca es 3 mm/kaca buram 140,000.00 m²
5 Kaca es 5 mm/kaca buram 135,000.00 m²
6 Kaca tempred 12mm (Diamond) 1,750,000.00 m²

B.7 Bahan Alumunium


1 Aluminium 4'' silver 120,000.00 m¹
2 Frame jendela aluminium 3x8 silver 80,000.00 m¹
3 Profil kaca 15,000.00 m¹
4 Aluminium strip/rel pintu 18,500.00 m¹
5 List holow aluminium 1 x 3 8,400.00 m¹
6 Aluminium strip 25,200.00 m¹
7 Metal furing 0.4x4 m ASTM - C 645 12,500.00 m¹
8 C Channel 0.8x4 m ASTM - C 645 8,500.00 m¹
9 Wall angle 20x20.3m 4,750.00 m¹
10 Theaded rod 4 mm x 1000 mm 4,500.00 bh
11 Hanger (Root, U Klem + Dinabold) 13,750.00 bh
12 Soffit clear 2,500.00 bh
13 Saddle clip 2,000.00 bh
14 Material bantu (Join tape) dll. 20,000.00 set
15 Paku peluru 2,000.00 bh
16 Angle section 3m 5,500.00 bh
17 Sekrup 90.00 bh
18 Kornice compound 5,500.00 kg
19 Sand paper 2,750.00 bh
20 Rolling door aluminium 550,000.00 m²
NO. JENIS UPAH/BAHAN HARGA SATUAN SATUAN
1 2 3 4

B.8 Bahan Besi & Pengunci


1 Besi beton ulir 8,000.00 kg
2 Besi beton polos 7,600.00 kg
3 Baja siku profil 14,000.00 kg
4 Baja WF 15,000.00 kg
5 Baja plat 13,500.00 kg
6 Baja canal profil (gording) 14,000.00 kg
7 Kawat beton 16,000.00 kg
8 Paku usuk/reng 15,000.00 kg
9 Paku triplek 15,000.00 kg
10 Paku seng 20,000.00 kg
11 Paku kalsi 30,000.00 kg
12 Paku piles 400.00 bh
13 Paku sekrup anti karat 750.00 bh
14 Paku kait anti karat 2,250.00 bh
15 Begel plat strip 30,900.00 kg
16 Angker kuda - kuda ø 22 mm p = 40cm 29,750.00 bh
17 Bautmur ø 25 mm p = 5cm 10,000.00 bh
18 Bautmur ø 16 mm p = 5cm 8,500.00 bh
19 Bautmur ø 12 mm p = 5cm 4,250.00 bh
20 Angker kusen pintu dan jendela 1,500.00 bh
21 Grendel besar klas menengah 19,300.00 bh
22 Grendel tanam expanyolet 45,000.00 bh
23 Grendel pintu klas tinggi 20,000.00 bh
24 Grendel jendela klas tinggi 12,500.00 bh
25 Kait angin klas tinggi 15,000.00 bh
26 Engsel Jendela klas biasa 13,800.00 Bh
27 Engsel jendela klas tinggi 22,500.00 bh
28 Engsel pintu klas biasa 16,550.00 bh
29 Engsel pintu klas tinggi 30,000.00 bh
30 Engsel pintu kipas 50,000.00 bh
31 Kunci pintu 2 slaag klas menengah 63,000.00 bh
32 Kunci pintu 2 slaag klas tinggi 80,000.00 bh
33 Handle pintu double 225,000.00 bh
34 Rel pintu dorong J3 - lebar pintu 80cm 400,000.00 set
35 Rel pintu dorong S6 - lebar pintu 130cm 625,000.00 set
36 Metal stut baja ringan C 75 12,500.00 m¹
37 Hollow baja ringan 20.40 5,500.00 m¹
38 Hollow baja ringan 40.40 7,500.00 m¹
39 Kap kd-kd dan rengan baja ringan bent.6m' 150,000.00 m²
40 Floorhinges sekulitas Dekson 1,350,000.00 set
41 Fitting kaca sekualitas Dekson 975,000.00 set
42 Handle pintu stainless steel T.60cm 750,000.00 bh
43 Kunci pintu aluminium 375,000.00 bh

B.9 Bahan - bahan Listrik


### Lampu pijar 6,000.00 bh
### Lampu down light 15 watt 225,000.00 bh
### Lampu SL 10 watt + vitingan 55,000.00 bh
### Lampu SL 18 watt + vitingan 75,000.00 bh
### Lampu baret 25 watt 375,000.00 bh
### Saklar Tunggal (mutu tinggi) 25,000.00 bh
### Saklar Ganda (mutu tinggi) 25,000.00 bh
### Stop kontak (mutu tinggi) 35,000.00 bh
### Stop kontak Ac 65,000.00 bh
### Fitting lampu 18,000.00 bh
### Kabel NYA 2x2,5mm2 7,560.00 m¹
### Kabel NYM 3x2,5mm2 9,650.00 m¹
### Kabel NYMHY 2x2x0,6mm2 3,500.00 m¹
### Kabel NYMHY 2x1,5mm2 9,000.00 m¹
### Kabel NYM 2x1,5mm2 5,300.00 m¹
### Pipa conduit (Ex. Ega) 2,500.00 m¹
### Socket pipa 500.00 bh
### Tee Doos 2,000.00 bh
### Klem pipa 250.00 bh
### Fhiser 100.00 bh
### Las doop 200.00 bh
### Isolasi ban 1,500.00 bh
NO. JENIS UPAH/BAHAN HARGA SATUAN SATUAN
1 2 3 4
B.10 Bahan Sanitair
1 Pipa PVC ø 1/2" - Aw 5,500.00 m¹
2 Pipa PVC ø 3/4" - Aw 7,500.00 m¹
3 Pipa PVC ø 1 " - Aw 12,500.00 m¹
4 Pipa PVC ø 1 1/2" 17,500.00 m¹
5 Pipa PVC ø 2" - Aw 15,750.00 m¹
6 Pipa PVC ø 3" - Aw 29,000.00 m¹
7 Pipa PVC ø 4" - Aw 43,000.00 m¹
8 Pipa GI ø 1/2" - Medium B 28,000.00 m¹
9 Pipa GI ø 3/4" - Medium B 31,000.00 m¹
10 Pipa GI ø 1" - Medium B 37,500.00 m¹
11 Pipa stainles steel Ø 2" 150,000.00 m¹
12 Pipa stainles steel Ø 2,5" 185,000.00 m¹
13 Gate valve GI Ø 1'' 175,000.00 bh
14 Floor drain (Avour) - stainless steel 50,000.00 bh
15 Kran air GI ø 1/2" 20,000.00 bh
16 Kran washtafle ø 1/2" 175,000.00 bh
17 Kran bebekan ø 1/2" 250,000.00 bh
18 Kran jetcloset ø 1/2" 225,000.00 bh
19 Kran handsower ø 1/2" 275,000.00 bh
20 Seal tape 3,000.00 bh
21 Closed jongkok porselint klas menengah 185,000.00 unit
22 Closed duduk monoblok (Sekualitas Toto) 2,350,000.00 unit
23 Closed duduk klas biasa 675,000.00 unit
24 Urinoir klas menengah 600,000.00 unit
25 Washtafel komplit kran 550,000.00 unit
26 Bak stainless steel 1 lobang 350,000.00 unit
27 Bak stainless steel 2 lobang 750,000.00 unit

B.11 Bahan Finishing


### Cat tembok klas menengah 31,500.00 kg
### Cat tembok klas tinggi 89,000.00 kg
### Cat kayu klas menengah 55,000.00 kg
### Cat kayu klas tinggi 64,000.00 kg
### Cat besi klas menengah 55,000.00 kg
### Cat anti lumut 75,000.00 kg
### Meny kayu 15,500.00 kg
### Meny besi 12,500.00 kg
### Minyak cat klas menengah 11,000.00 ltr
### Minyak cat klas tinggi 23,000.00 ltr
### Amplas 3,750.00 lbr
### Kuas cat 6,800.00 bh
### Roll cat 10,800.00 bh
### Plamir tembok 9,000.00 kg
### Plamir Kayu 25,000.00 kg
### Teer 5,400.00 ltr
### Politur 57,000.00 ltr
### Alkali (anti jamur) 46,200.00 kg
### Tinner serbaguna 26,500.00 ltr
### Wood filer 25,200.00 ltr
### Seanding sealer 37,800.00 ltr
### Wood steam 39,800.00 ltr
### Clear glos 42,000.00 ltr
### Lem kayu 40,000.00 kg
### Lem silent 65,000.00 tbg
### Seaflex 35,000.00 Kg

B.12 Bahan Lain - lain


1 Kawat las 30,000.00 kg
2 Listrik 750.00 kw
3 Air kerja 5.00 ltr
4 Solar 7,000.00 ltr
5 Minyak begesting 5,000.00 ltr
6 Minyak pelumas 30,000.00 ltr
7 Mesin las (sewa) 12,500.00 jam
8 Mesin bor (sewa) 12,500.00 jam
9 Pompa air (sewa) 11,000.00 jam
10 Alat bantu 65,000.00 jam
11 Mesin potong plat ( sewa ) 12,500.00 jam
12 Mesin Gergaji (sewa) 12,500.00 jam
13 Mesin bor pistol 950,000.00 unit
14 Mata Gergaji 52,500.00 bh
15 Mata Bor 9,000.00 bh
16 Acytilyin 150,000.00 btl
17 Oksigen 75,000.00 btl
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PERMEN PU NO 11/PRT/M/2013 BIDANG CIPTA KARYA

A.2.2.1 ANALISA PEKERJAAN PERSIAPAN


A.2.2.1.1 1 M2 PEK. MEMBERSIHKAN LAPANGAN DENGAN PERALATAN
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
B JUMLAH 6,550.00

A.2.2.1.3 1 M2 PEK. BONGKARAN DINDING BATA


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
1 Pekerja L.01 OH 0.3334 65,500.00 21,834.43
B JUMLAH 21,834.43

A.2.2.1.3a 1 M3 PEK. BONGKARAN BETON


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
1 Pekerja L.01 OH 6.6670 65,500.00 436,688.50
B JUMLAH 436,688.50

A.2.2.1.3b 1 M2 PEK. BONGKARAN ATAP, USUK DAN KAP


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
1 Pekerja L.01 OH 0.1500 65,500.00 9,825.00
B JUMLAH 9,825.00

A.2.2.1.4 1 M PEK. BOUPLANK


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas III m³ 0.0070 2,750,000.00 19,250.00
2 Paku usuk/reng kg 0.0200 15,000.00 300.00
3 Balok kayu kelas II m³ 0.0120 5,675,000.00 68,100.00
JUMLAH HARGA BAHAN 87,650.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C JUMLAH ( A + B ) 94,200.00

A.2.3.1 ANALISA PEKERJAAN TANAH DAN PASIR


A.2.3.1.1 1 M3 PEK.GALIAN TANAH BIASA SEDALAM 1M
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
1 Pekerja L.01 OH 0.7500 65,500.00 49,125.00
B JUMLAH ( A ) 49,125.00

A.2.3.1.2 1 M3 PEK.GALIAN TANAH BIASA SEDALAM 2M


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
1 Pekerja L.01 OH 0.9000 65,500.00 58,950.00
B JUMLAH ( A ) 58,950.00

A.2.3.1.9 1 M3 URUGAN KEMBALI TANAH


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
1 Pekerja L.01 OH 0.2500 65,500.00 16,375.00
B JUMLAH ( A ) 16,375.00
A.2.3.1.10 1 M3 MEMADATKAN TANAH (PER 20 CM)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
1 Pekerja L.01 OH 0.5000 65,500.00 32,750.00
B JUMLAH ( A ) 32,750.00

A.2.3.1.11 1 M3 PEK.URUGAN PASIR


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pasir urug m³ 1.2000 100,000.00 120,000.00
JUMLAH HARGA BAHAN 120,000.00
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 139,650.00

A.2.3.1.11a 1 M3 PEK.URUGAN TANAH


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Tanah urug m³ 1.2000 62,500.00 75,000.00
JUMLAH HARGA BAHAN 75,000.00
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 94,650.00

A.2.3.1.11b 1 M3 PEK.URUGAN KERIKIL UNTUK RESAPAN


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Krikil pecah 2-3cm - 1 m³ /1350 kg m³ 1.2000 220,000.00 264,000.00
JUMLAH HARGA BAHAN 264,000.00
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 283,650.00

A.2.3.1.11c 1 M2 PEK.LAPISAN IJUK 10 CM UNTUK PERESAPAN


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Ijuk kg 6.0000 20,000.00 120,000.00
JUMLAH HARGA BAHAN 120,000.00
B TENAGA
1 Pekerja L.01 OH 0.1500 65,500.00 9,825.00
JUMLAH HARGA TENAGA 9,825.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 129,825.00
A.3.2.1 ANALISA PEKERJAAN PONDASI
A.3.2.1.1 1 M3 PEK. PONDASI BATU BELAH, CAMPURAN 1PC : 3PS
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Batu kali belah m³ 1.2000 125,000.00 150,000.00
2 Semen/Pc kg 202.0000 1,220.00 246,440.00
3 Pasir pasang m³ 0.4850 125,000.00 60,625.00
JUMLAH HARGA BAHAN 457,065.00
B TENAGA
1 Pekerja L.01 OH 1.5000 65,500.00 98,250.00
JUMLAH HARGA TENAGA 98,250.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 555,315.00

A.3.2.1.2 1 M3 PEK. PONDASI BATU BELAH, CAMPURAN 1PC : 4PS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Batu kali belah m³ 1.2000 125,000.00 150,000.00
2 Semen/Pc kg 163.0000 1,220.00 198,860.00
3 Pasir pasang m³ 0.5200 125,000.00 65,000.00
JUMLAH HARGA BAHAN 413,860.00
B TENAGA
1 Pekerja L.01 OH 1.5000 65,500.00 98,250.00
JUMLAH HARGA TENAGA 98,250.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 512,110.00

A.3.2.1.3 1 M3 PEK. PONDASI BATU BELAH, CAMPURAN 1PC : 5PS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Batu kali belah m³ 1.2000 125,000.00 150,000.00
2 Semen/Pc kg 136.0000 1,220.00 165,920.00
3 Pasir pasang m³ 0.5440 125,000.00 68,000.00
JUMLAH HARGA BAHAN 383,920.00
B TENAGA
1 Pekerja L.01 OH 1.5000 65,500.00 98,250.00
JUMLAH HARGA TENAGA 98,250.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 482,170.00
A.3.2.1.9 1 M3 PEK.PEMASANGAN BATU KOSONG ( AANSTAMPING )
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Batu kali belah m³ 1.2000 125,000.00 150,000.00
2 Pasir urug m³ 0.4320 100,000.00 43,200.00
JUMLAH HARGA BAHAN 193,200.00
B TENAGA
1 Pekerja L.01 OH 0.7800 65,500.00 51,090.00
JUMLAH HARGA TENAGA 51,090.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 244,290.00

A.4.1.1 ANALISA PEKERJAAN BETON


A.4.1.1.1 1 M3 BETON MUTU f 'c = 7,4 MPa ( K 100 ), slump ( 12 ± 2 ) cm, w/c = 0,87
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Semen/Pc kg 247.0000 1,220.00 301,340.00
2 Pasir cor kg 869.0000 107.14 93,107.14
3 Krikil pecah 2-3cm kg 999.0000 162.96 162,800.00
4 Air kerja ltr 215.0000 5.00 1,075.00
JUMLAH HARGA BAHAN 558,322.14
B TENAGA
1 Pekerja L.01 OH 1.6500 65,500.00 108,075.00
JUMLAH HARGA TENAGA 108,075.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 666,397.14

A.4.1.1.2 1 M3 LANTAI KERJA BETON MUTU f 'c = 9,8 MPa ( K 125 ), slump ( 12-2 ) cm, w/c = 0,78
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Semen/Pc kg 276.0000 1,220.00 336,720.00
2 Pasir cor kg 826.0000 107.14 88,500.00
3 Krikil pecah 2-3cm kg 1,012.0000 162.96 164,918.52
4 Air kerja ltr 215.0000 5.00 1,075.00
JUMLAH HARGA BAHAN 591,213.52
B TENAGA
1 Pekerja L.01 OH 1.6500 65,500.00 108,075.00
JUMLAH HARGA TENAGA 108,075.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 699,288.52
A.4.1.1.5 1 M3 BETON MUTU f 'c = 14,5 MPa ( K 175 ), slump ( 12 ± 2 ) cm, w/c = 0,66
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Semen/Pc kg 326.0000 1,220.00 397,720.00
2 Pasir cor kg 760.0000 107.14 81,428.57
3 Krikil pecah 2-3cm kg 1,029.0000 162.96 167,688.89
4 Air kerja ltr 215.0000 5.00 1,075.00
JUMLAH HARGA BAHAN 647,912.46
B TENAGA
1 Pekerja L.01 OH 1.6500 65,500.00 108,075.00
JUMLAH HARGA TENAGA 108,075.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 755,987.46

A.4.1.1.7 1 M3 BETON MUTU f 'c = 19,3 Mpa ( K 225 ), slump ( 12 ± 2 ) cm, w/c = 0,58
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Semen/Pc kg 371.0000 1,220.00 452,620.00
2 Pasir cor kg 698.0000 107.14 74,785.71
3 Krikil pecah 2-3cm kg 1,047.0000 162.96 170,622.22
4 Air kerja ltr 215.0000 5.00 1,075.00
JUMLAH HARGA BAHAN 699,102.93
B TENAGA
1 Pekerja L.01 OH 1.6500 65,500.00 108,075.00
JUMLAH HARGA TENAGA 108,075.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 807,177.93

A.4.1.1.17 1 Kg PEK. PEMBESIAN DENGAN BESI POLOS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Besi beton polos kg 1.0500 7,600.00 7,980.00
2 Kawat beton kg 0.0150 16,000.00 240.00
JUMLAH HARGA BAHAN 8,220.00
B TENAGA
1 Pekerja L.01 OH 0.0070 65,500.00 458.50
JUMLAH HARGA TENAGA 458.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 8,678.50
A.4.1.1.17a 1 Kg PEK. PEMBESIAN DENGAN BESI ULIR
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Besi beton ulir kg 1.0500 8,000.00 8,400.00
2 Kawat beton kg 0.0150 16,000.00 240.00
JUMLAH HARGA BAHAN 8,640.00
B TENAGA
1 Pekerja L.01 OH 0.0070 65,500.00 458.50
JUMLAH HARGA TENAGA 458.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 9,098.50

A.4.1.1.20 1 M2 PEK. BEKISTING UNTUK PONDASI


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas III m³ 0.0400 2,750,000.00 110,000.00
2 Paku usuk/reng kg 0.3000 15,000.00 4,500.00
3 Minyak begesting ltr 0.1000 5,000.00 500.00
JUMLAH HARGA BAHAN 115,000.00
B TENAGA
1 Pekerja L.01 OH 0.5200 65,500.00 34,060.00
JUMLAH HARGA TENAGA 34,060.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 149,060.00

A.4.1.1.21 1 M2 PEK. BEKISTING UNTUK SLOOF


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas III m³ 0.0450 2,750,000.00 123,750.00
2 Paku usuk/reng kg 0.3000 15,000.00 4,500.00
3 Minyak begesting ltr 0.1000 5,000.00 500.00
JUMLAH HARGA BAHAN 128,750.00
B TENAGA
1 Pekerja L.01 OH 0.5200 65,500.00 34,060.00
JUMLAH HARGA TENAGA 34,060.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 162,810.00
A.4.1.1.22 1 M2 PEK. BEKISTING UNTUK KOLOM
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas III m³ 0.0400 2,750,000.00 110,000.00
2 Paku usuk/reng kg 0.4000 15,000.00 6,000.00
3 Minyak begesting ltr 0.2000 5,000.00 1,000.00
4 Balok kayu kelas III m³ 0.0150 2,750,000.00 41,250.00
5 Triplek 120x240x9mm lbr 0.3500 145,000.00 50,750.00
6 Bambu perancah ø 10cm - 4 m btg 2.0000 9,000.00 18,000.00
JUMLAH HARGA BAHAN 227,000.00
B TENAGA
1 Pekerja L.01 OH 0.6600 65,500.00 43,230.00
JUMLAH HARGA TENAGA 43,230.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 270,230.00

A.4.1.1.23 1 M2 PEK. BEKISTING UNTUK BALOK


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas III m³ 0.0400 2,750,000.00 110,000.00
2 Paku usuk/reng kg 0.4000 15,000.00 6,000.00
3 Minyak begesting ltr 0.2000 5,000.00 1,000.00
4 Balok kayu kelas III m³ 0.0180 2,750,000.00 49,500.00
5 Triplek 120x240x9mm lbr 0.3500 145,000.00 50,750.00
6 Bambu perancah ø 10cm - 4 m btg 2.0000 9,000.00 18,000.00
JUMLAH HARGA BAHAN 235,250.00
B TENAGA
1 Pekerja L.01 OH 0.6600 65,500.00 43,230.00
JUMLAH HARGA TENAGA 43,230.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 278,480.00

A.4.1.1.24 1 M2 PEK. BEKISTING UNTUK PLAT LANTAI


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas III m³ 0.0400 2,750,000.00 110,000.00
2 Paku usuk/reng kg 0.4000 15,000.00 6,000.00
3 Minyak begesting ltr 0.2000 5,000.00 1,000.00
4 Balok kayu kelas III m³ 0.0150 2,750,000.00 41,250.00
5 Triplek 120x240x9mm lbr 0.3500 145,000.00 50,750.00
6 Bambu perancah ø 10cm - 4 m btg 6.0000 9,000.00 54,000.00
JUMLAH HARGA BAHAN 263,000.00
B TENAGA
1 Pekerja L.01 OH 0.6600 65,500.00 43,230.00
JUMLAH HARGA TENAGA 43,230.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 306,230.00
A.4.1.1.26 1 M2 PEK. BEKISTING UNTUK TANGGA
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas III m³ 0.0300 2,750,000.00 82,500.00
2 Paku usuk/reng kg 0.4000 15,000.00 6,000.00
3 Minyak begesting ltr 0.1500 5,000.00 750.00
4 Balok kayu kelas III m³ 0.0150 2,750,000.00 41,250.00
5 Triplek 120x240x9mm lbr 0.3500 145,000.00 50,750.00
6 Bambu perancah ø 10cm - 4 m btg 2.0000 9,000.00 18,000.00
JUMLAH HARGA BAHAN 199,250.00
B TENAGA
1 Pekerja L.01 OH 0.6600 65,500.00 43,230.00
JUMLAH HARGA TENAGA 43,230.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 242,480.00

A.4.1.1.28 1 M³ PONDASI BETON BERTULANG (UK.125X125) CM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
TENAGA/BAHAN
1 Beton mutu f'c = 19,3 Mpa K 225 (A.4.1.1.7) m³ 1.0000 807,177.93 807,177.93
2 Cetakan beton pondasi (A.4.1.1.20) m² 2.9091 149,060.00 433,629.09
3 Besi beton polos ( A.4.1.1.17) Kg 55.9558 8,678.50 485,612.25
4 Besi beton ulir ( A.4.1.1.17a) Kg 60.6188 9,098.50 551,539.82
HARGA SATUAN PEKERJAAN 2,277,959.09

A.4.1.1.28.1 1 M³ PONDASI BETON BERTULANG (UK.175X175) CM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
TENAGA/BAHAN
1 Beton mutu f'c = 19,3 Mpa K 225 (A.4.1.1.7) m³ 1.0000 807,177.93 807,177.93
2 Cetakan beton pondasi (A.4.1.1.20) m² 1.9048 149,060.00 283,923.81
3 Besi beton polos ( A.4.1.1.17) Kg 46.0320 8,678.50 399,488.71
4 Besi beton ulir ( A.4.1.1.17a) Kg 84.1728 9,098.50 765,846.22
HARGA SATUAN PEKERJAAN 2,256,436.67

A.4.1.1.30 1 M³ SLOOF BETON BERTULANG 15/20


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
TENAGA/BAHAN
1 Beton mutu f'c = 14,5 Mpa K 175 (A.4.1.1.5) m³ 1.0000 755,987.46 755,987.46
2 Cetakan beton sloof (A.4.1.1.21) m² 6.6667 162,810.00 1,085,400.00
3 Besi beton polos ( A.4.1.1.17) Kg 170.5000 8,678.50 1,479,684.25
HARGA SATUAN PEKERJAAN 3,321,071.71

A.4.1.1.30.1 1 M³ SLOOF BETON BERTULANG 20/30 - TYPE A


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
TENAGA/BAHAN
1 Beton mutu f'c = 19,3 Mpa K 225 (A.4.1.1.7) m³ 1.0000 807,177.93 807,177.93
2 Cetakan beton sloof (A.4.1.1.21) m² 5.0000 162,810.00 814,050.00
3 Besi beton polos ( A.4.1.1.17) Kg 61.6500 8,678.50 535,029.53
4 Besi beton ulir ( A.4.1.1.17a) Kg 151.6750 9,098.50 1,380,015.11
HARGA SATUAN PEKERJAAN 3,536,272.57

A.4.1.1.30.2 1 M³ SLOOF BETON BERTULANG 25/40 - TYPE B


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
TENAGA/BAHAN
1 Beton mutu f'c = 19,3 Mpa K 225 (A.4.1.1.7) m³ 1.0000 755,987.46 755,987.46
2 Cetakan beton sloof (A.4.1.1.21) m² 4.0000 162,810.00 651,240.00
3 Besi beton polos ( A.4.1.1.17) Kg 49.3200 8,678.50 428,023.62
4 Besi beton ulir ( A.4.1.1.17a) Kg 133.9113 9,098.50 1,218,391.71
HARGA SATUAN PEKERJAAN 3,053,642.79
A.4.1.1.35 1 M1 PEK. BETON KOLOM PRAKTIS BERTULANG 11X11CM (Besi 4Ø10 ; Bg. Ø6-15) - Type A
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas III m³ 0.0020 2,750,000.00 5,500.00
2 Paku usuk/reng kg 0.0100 15,000.00 150.00
3 Minyak begesting ltr - - -
4 Besi beton polos kg 3.0000 7,600.00 22,800.00
5 Kawat beton kg 0.0450 16,000.00 720.00
6 Semen/Pc kg 4.0000 1,220.00 4,880.00
7 Pasir cor beton - 1 m³/1400 kg m³ 0.0060 150,000.00 900.00
8 Krikil pecah 2-3cm - 1 m³ /1350 kg m³ 0.0090 220,000.00 1,980.00
JUMLAH HARGA BAHAN 36,930.00
B TENAGA
1 Pekerja L.01 OH 0.1800 65,500.00 11,790.00
2 Tukang batu L.02 OH 0.0200 89,080.00 1,781.60
3 Tukang kayu L.02 OH 0.0200 89,080.00 1,781.60
4 Tukang besi L.02 OH 0.0200 89,080.00 1,781.60
5 Kepala tukang kayu L.03 OH - 94,975.00 -
6 Mandor L.04 OH - 102,180.00 -
JUMLAH HARGA TENAGA 17,134.80
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 54,064.80

A.4.1.1.35a 1 M1 PEK. BETON KOLOM PRAKTIS BERTULANG 11X11CM (Besi 4Ø12 ; Bg. Ø6-15) - Type B
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas III m³ 0.0020 2,750,000.00 5,500.00
2 Paku usuk/reng kg 0.0100 15,000.00 150.00
3 Minyak begesting ltr - - -
4 Besi beton polos kg 4.1400 7,600.00 31,464.00
5 Kawat beton kg 0.0450 16,000.00 720.00
6 Semen/Pc kg 4.0000 1,220.00 4,880.00
7 Pasir cor beton - 1 m³/1400 kg m³ 0.0060 150,000.00 900.00
8 Krikil pecah 2-3cm - 1 m³ /1350 kg m³ 0.0090 220,000.00 1,980.00
JUMLAH HARGA BAHAN 45,594.00
B TENAGA
1 Pekerja L.01 OH 0.1800 65,500.00 11,790.00
2 Tukang batu L.02 OH 0.0200 89,080.00 1,781.60
3 Tukang kayu L.02 OH 0.0200 89,080.00 1,781.60
4 Tukang besi L.02 OH 0.0200 89,080.00 1,781.60
5 Kepala tukang kayu L.03 OH - 94,975.00 -
6 Mandor L.04 OH - 102,180.00 -
JUMLAH HARGA TENAGA 17,134.80
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 62,728.80

A.4.1.1.36 1 M1 PEK. BETON BALOK BERTULANG 10X15CM (Besi 4Ø10 ; Bg. Ø6-15)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas III m³ 0.0020 2,750,000.00 5,500.00
2 Paku usuk/reng kg 0.0100 15,000.00 150.00
3 Minyak begesting ltr - - -
4 Besi beton polos kg 3.6000 7,600.00 27,360.00
5 Kawat beton kg 0.0500 16,000.00 800.00
6 Semen/Pc kg 5.5000 1,220.00 6,710.00
7 Pasir cor beton - 1 m³/1400 kg m³ 0.0090 150,000.00 1,350.00
8 Krikil pecah 2-3cm - 1 m³ /1350 kg m³ 0.0150 220,000.00 3,300.00
JUMLAH HARGA BAHAN 45,170.00
B TENAGA
1 Pekerja L.01 OH 0.2970 65,500.00 19,453.50
2 Tukang batu L.02 OH 0.0330 89,080.00 2,939.64
3 Tukang kayu L.02 OH 0.0330 89,080.00 2,939.64
4 Tukang besi L.02 OH 0.0330 89,080.00 2,939.64
5 Kepala tukang kayu L.03 OH - 94,975.00 -
6 Mandor L.04 OH - 102,180.00 -
JUMLAH HARGA TENAGA 28,272.42
C PERALATAN

JUMLAH HARGA PERALATAN -


D JUMLAH ( A + B + C ) 73,442.42
A.4.1.1.39 1 M³ RINGBALK/BALOK SUNSCREN BETON BERTULANG 10/20
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
TENAGA/BAHAN
1 Beton mutu f'c = 14,5 Mpa K 175 (A.4.1.1.5) m³ 1.0000 755,987.46 755,987.46
2 Cetakan beton balok (A.4.1.1.23) m² 10.0000 278,480.00 2,784,800.00
3 Besi beton polos ( A.4.1.1.17) Kg 221.9400 8,678.50 1,926,106.29
HARGA SATUAN PEKERJAAN 5,466,893.75

A.4.1.1.39a 1 M³ BALOK BETON BERTULANG 15/20


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
TENAGA/BAHAN
1 Beton mutu f'c = 14,5 Mpa K 175 (A.4.1.1.5) m³ 1.0000 755,987.46 755,987.46
2 Cetakan beton balok (A.4.1.1.23) m² 13.3333 278,480.00 3,713,057.38
3 Besi beton polos ( A.4.1.1.17) Kg 170.9760 8,678.50 1,483,815.22
HARGA SATUAN PEKERJAAN 5,952,860.06

A.4.1.1.42 1 M³ PLAT SUNSCREN BETON BERTULANG TEBAL 8CM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
TENAGA/BAHAN
1 Beton mutu f'c = 14,5 Mpa K 175 (A.4.1.1.5) m³ 1.0000 755,987.46 755,987.46
2 Cetakan beton lantai (A.4.1.1.24) m² 10.0000 306,230.00 3,062,300.00
3 Besi beton ulir ( A.4.1.1.17a) m³ 50.0000 8,678.50 433,925.00
HARGA SATUAN PEKERJAAN 4,252,212.46

A.4.2.1 ANALISA PEKERJAAN BESI /ALUMUNIUM


A.4.2.1.1 1 Kg PEK. BESI PROFIL
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Baja siku profil kg 1.1500 14,000.00 16,100.00
JUMLAH HARGA BAHAN 16,100.00
B TENAGA
1 Pekerja L.01 OH 0.0600 65,500.00 3,930.00
JUMLAH HARGA TENAGA 3,930.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 20,030.00
A.4.2.1.2 1 Kg PEK. RANGKA KUDA - KUDA BAJA IWF
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Baja WF kg 1.1500 15,000.00 17,250.00
JUMLAH HARGA BAHAN 17,250.00
B TENAGA
1 Pekerja L.01 OH 0.0600 65,500.00 3,930.00
JUMLAH HARGA TENAGA 3,930.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 21,180.00

A.4.2.1.2a 1 Kg PEK. GORDING CANAL C


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Baja canal profil (gording) kg 1.1500 14,000.00 16,100.00
JUMLAH HARGA BAHAN 16,100.00
B TENAGA
1 Pekerja L.01 OH 0.0600 65,500.00 3,930.00
JUMLAH HARGA TENAGA 3,930.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 20,030.00

A.4.2.1.2b 1 Kg PEK. BESI BAJA PLAT


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Baja plat kg 1.1500 13,500.00 15,525.00
JUMLAH HARGA BAHAN 15,525.00
B TENAGA
1 Pekerja L.01 OH 0.0600 65,500.00 3,930.00
JUMLAH HARGA TENAGA 3,930.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 19,455.00

A.4.2.1.3 100 Kg PEK. PERAKITAN


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Solar ltr 1.0000 7,000.00 7,000.00
2 Minyak pelumas ltr 0.1000 30,000.00 3,000.00
JUMLAH HARGA BAHAN 10,000.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN
1 Sewa Alat (Krent ) Jam 0.8000 62,500.00 50,000.00
JUMLAH HARGA PERALATAN 50,000.00

D JUMLAH ( A + B + C ) 66,550.00
E Untuk 1 kg 665.50
A.4.2.1.5 1 CM PEK. PENGELASAN DENGAN LAS LISTRIK
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kawat las kg 0.0400 30,000.00 1,200.00
2 Solar ltr 0.0300 7,000.00 210.00
3 Minyak pelumas ltr 0.0040 30,000.00 120.00
JUMLAH HARGA BAHAN 1,530.00
B TENAGA
1 Pekerja L.01 OH 0.0040 65,500.00 262.00
JUMLAH HARGA TENAGA 262.00
C PERALATAN
1 Mesin las (sewa) Jam 0.0170 12,500.00 212.50
JUMLAH HARGA PERALATAN 212.50

D JUMLAH ( A + B + C ) 2,004.50

A.4.2.1.7 1 M² PEK.PINTU ROLLING DOOR ALLUMINIUM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Rolling door aluminium m² 1.0000 550,000.00 550,000.00
2 Perlengkapan (15 % x Harga kusen) Hb 0.1500 550,000.00 82,500.00
JUMLAH HARGA BAHAN 632,500.00
B TENAGA
1 Pekerja L.01 OH 1.0000 65,500.00 65,500.00
JUMLAH HARGA TENAGA 65,500.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 698,000.00

A.4.2.1.11 1 M PEK.KUSEN PINTU /JENDELA ALLUMINIUM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Aluminium 4'' silver m¹ 1.1000 120,000.00 132,000.00
2 Perlengkapan (15 % x Harga kusen) Hb 0.1500 132,000.00 19,800.00
JUMLAH HARGA BAHAN 151,800.00
B TENAGA
1 Pekerja L.01 OH 0.0150 65,500.00 982.50
JUMLAH HARGA TENAGA 982.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 152,782.50

A.4.2.1.12 1 M2 PEK. DAUN PINTU/JENDELA KACA 5MM,RANGKA ALLUMINIUM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Frame jendela aluminium 3x8 silver m¹ 4.4000 80,000.00 352,000.00
2 Perlengkapan (Harga kusen) Hb 15% 352,000.00 52,800.00
3 Profil kaca m¹ 4.5000 15,000.00 67,500.00
4 Kaca bening 5mm m² 0.8500 129,500.00 110,075.00
JUMLAH HARGA BAHAN 582,375.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 588,925.00
A.4.2.1.12a 1 M2 PEK. DAUN PINTU DILAPIS MULTIPLEK/ KACA 5MM,RANGKA ALLUMINIUM (UK.140X200)CM = 2,80M2
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Frame jendela aluminium 3x8 silver m¹ 12.7600 80,000.00 1,020,800.00
2 Perlengkapan (Harga kusen) Hb 15% 1,020,800.00 153,120.00
3 Profil kaca m¹ 12.3200 15,000.00 184,800.00
4 Kaca bening 5mm m² 0.1984 129,500.00 25,692.80
5 Triplek 120x240x9mm lbr 0.7128 145,000.00 103,356.00
JUMLAH HARGA BAHAN 1,487,768.80
B TENAGA
1 Pekerja L.01 OH 0.5000 65,500.00 32,750.00
JUMLAH HARGA TENAGA 32,750.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) = 2,8 M2 1,520,518.80


BIAYA 1 M2 = D/2,8 543,042.43

A.4.2.1 (LS.15) 1 UNIT PEK. DAUN PINTU KACA TEMPRED 12 MM UK. (160X220) CM
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kaca tempred 12mm (Diamond) #N/A 3.8720 1,750,000.00 6,776,000.00
2 Fitting kaca sekualitas Dekson #N/A 4.0000 975,000.00 3,900,000.00
3 Floorhinges sekulitas Dekson #N/A 2.0000 1,350,000.00 2,700,000.00
4 Handle pintu stainless steel T.60cm #N/A 4.0000 750,000.00 3,000,000.00
5 Kunci pintu aluminium #N/A 2.0000 375,000.00 750,000.00
JUMLAH HARGA BAHAN 17,126,000.00
B TENAGA
1 Biaya Pemasangan 20 % x Hb Ls 0.2000 17,126,000.00 3,425,200.00
JUMLAH HARGA TENAGA 3,425,200.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 20,551,200.00

LS.BA.13 1 M' RAILLING PIPA STANLES STEEL Ø 2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pipa stainles steel Ø 2" m¹ 1.0500 150,000.00 157,500.00
2 Kelengkapan bahan ( 10 % x Harga pipa) Hb 0.1000 157,500.00 15,750.00
JUMLAH HARGA BAHAN 173,250.00
B TENAGA
1 Upah pemasangan 20% Oh 1.0000 31,500.00 31,500.00
JUMLAH HARGA TENAGA 31,500.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 204,750.00

LS.BA.20 1 M2 KAP KUDA-KUDA DAN RENG BAJA RINGAN BENT. 7 M'


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kap kd-kd dan rengan baja ringan bent.6m' m² 1.0500 150,000.00 157,500.00
2 Kelengkapan bahan ( 10 % x HB) Hb 0.1000 157,500.00 15,750.00
JUMLAH HARGA BAHAN 173,250.00
B TENAGA
1 Upah pemasangan 10% Oh 0.2000 173,250.00 34,650.00
JUMLAH HARGA TENAGA 34,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 207,900.00
A.4.4.1 ANALISA PEKERJAAN DINDING
A.4.4.1.2 1 M2 PEK. DINDING UKURAN ( 5 X 11 X 22 ) CM TEBAL 1 BATA, CAMPURAN 1C : 3PS
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bata merah klas I bh 140.0000 575.00 80,500.00
2 Semen/Pc kg 32.9500 1,220.00 40,199.00
3 Pasir pasang m³ 0.0910 125,000.00 11,375.00
JUMLAH HARGA BAHAN 132,074.00
B TENAGA
1 Pekerja L.01 OH 0.6000 65,500.00 39,300.00
JUMLAH HARGA TENAGA 39,300.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 171,374.00

A.4.4.1.3 1 M2 PEK. DINDING UKURAN ( 5 X 11 X 22 ) CM TEBAL 1 BATA, CAMPURAN 1C : 4PS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bata merah klas I bh 140.0000 575.00 80,500.00
2 Semen/Pc kg 26.5500 1,220.00 32,391.00
3 Pasir pasang m³ 0.0930 125,000.00 11,625.00
JUMLAH HARGA BAHAN 124,516.00
B TENAGA
1 Pekerja L.01 OH 0.6000 65,500.00 39,300.00
JUMLAH HARGA TENAGA 39,300.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 163,816.00

A.4.4.1.4 1 M2 PEK. DINDING UKURAN ( 5 X 11 X 22 ) CM TEBAL 1 BATA, CAMPURAN 1C : 5PS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bata merah klas I bh 140.0000 575.00 80,500.00
2 Semen/Pc kg 22.2000 1,220.00 27,084.00
3 Pasir pasang m³ 0.1020 125,000.00 12,750.00
JUMLAH HARGA BAHAN 120,334.00
B TENAGA
1 Pekerja L.01 OH 0.6000 65,500.00 39,300.00
JUMLAH HARGA TENAGA 39,300.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 159,634.00

A.4.4.1.4a 1 M2 PEK. DINDING UKURAN ( 5 X 11 X 22 ) CM TEBAL 1/2 BATA - BATA KOSONG


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bata merah klas I bh 70.0000 575.00 40,250.00
JUMLAH HARGA BAHAN 40,250.00
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 59,900.00
A.4.4.1.8 1 M2 PEK. DINDING UKURAN ( 5 X 11 X 22 ) CM TEBAL 1/2 BATA, CAMPURAN 1C : 3PS
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bata merah klas I bh 70.0000 575.00 40,250.00
2 Semen/Pc kg 14.3700 1,220.00 17,531.40
3 Pasir pasang m³ 0.0400 125,000.00 5,000.00
JUMLAH HARGA BAHAN 62,781.40
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 82,431.40

A.4.4.1.9 1 M2 PEK. DINDING UKURAN ( 5 X 11 X 22 ) CM TEBAL 1/2 BATA, CAMPURAN 1C : 4PS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bata merah klas I bh 70.0000 575.00 40,250.00
2 Semen/Pc kg 11.5000 1,220.00 14,030.00
3 Pasir pasang m³ 0.0430 125,000.00 5,375.00
JUMLAH HARGA BAHAN 59,655.00
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 79,305.00

A.4.4.1.10 1 M2 PEK. DINDING UKURAN ( 5 X 11 X 22 ) CM TEBAL 1/2 BATA, CAMPURAN 1C : 5PS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bata merah klas I bh 70.0000 575.00 40,250.00
2 Semen/Pc kg 9.6800 1,220.00 11,809.60
3 Pasir pasang m³ 0.0450 125,000.00 5,625.00
JUMLAH HARGA BAHAN 57,684.60
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 77,334.60

A.4.4.1.23 1 M2 PEK. DINDING TERAWANG (ROSTER), CAMPURAN 1C : 3PS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Roster pejaten (20x20)cm Bh 25.0000 6,500.00 162,500.00
2 Semen/Pc kg 11.0000 1,220.00 13,420.00
3 Pasir pasang m³ 0.0350 125,000.00 4,375.00
JUMLAH HARGA BAHAN 180,295.00
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 199,945.00
A.4.4.2 ANALISA PEKERJAAN PLESTERAN
A.4.4.2.2 1 M2 PLESTERAN 1PC : 2PS TEBAL 15 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Semen/Pc kg 10.2240 1,220.00 12,473.28
2 Pasir pasang m³ 0.0200 125,000.00 2,500.00
JUMLAH HARGA BAHAN 14,973.28
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 34,623.28

A.4.4.2.3 1 M2 PLESTERAN 1PC : 3PS TEBAL 15 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Semen/Pc kg 7.7760 1,220.00 9,486.72
2 Pasir pasang m³ 0.0230 125,000.00 2,875.00
JUMLAH HARGA BAHAN 12,361.72
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 32,011.72

A.4.4.2.4 1 M2 PLESTERAN 1PC : 4PS TEBAL 15 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Semen/Pc kg 6.2400 1,220.00 7,612.80
2 Pasir pasang m³ 0.0240 125,000.00 3,000.00
JUMLAH HARGA BAHAN 10,612.80
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 30,262.80

A.4.4.2.5 1 M2 PLESTERAN 1PC : 5PS TEBAL 15 mm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Semen/Pc kg 5.1840 1,220.00 6,324.48
2 Pasir pasang m³ 0.0260 125,000.00 3,250.00
JUMLAH HARGA BAHAN 9,574.48
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 29,224.48
A.4.4.2.26 1 M2 SIARAN PONDASI 1PC : 2PS
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Semen/Pc kg 6.3400 1,220.00 7,734.80
2 Pasir pasang m³ 0.0120 125,000.00 1,500.00
JUMLAH HARGA BAHAN 9,234.80
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 28,884.80

A.4.4.2.27 1 M2 ACIAN PC
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Semen/Pc kg 3.2500 1,220.00 3,965.00
JUMLAH HARGA BAHAN 3,965.00
B TENAGA
1 Pekerja L.01 OH 0.2000 65,500.00 13,100.00
JUMLAH HARGA TENAGA 13,100.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 17,065.00

A.4.4.2.28 1 M¹ PLESTERAN BENANGAN


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
B BAHAN
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D JUMLAH ( B + C ) 6,550.00

A.4.4.3 ANALISA PEKERJAAN PENUTUP LANTAI DAN DINDING


A.4.4.3.35 1 M2 LANTAI KERAMIK ( 30 X 30 ) CM - MUTU MENENGAH
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Keramik 30x30cm kw 1 (mutu menengah) m² 1.0700 60,000.00 64,200.00
2 Semen/Pc kg 10.0000 1,220.00 12,200.00
3 Pasir pasang m³ 0.0450 125,000.00 5,625.00
4 Semen warna mutu baik kg 1.5000 16,800.00 25,200.00
JUMLAH HARGA BAHAN 107,225.00
B TENAGA
1 Pekerja L.01 OH 0.7000 65,500.00 45,850.00
JUMLAH HARGA TENAGA 45,850.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 153,075.00
A.4.4.3.35.1 1 M2 LANTAI GRANITE TILE ( 30 X 30 ) CM
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Granite tile 30x30cm m² 1.0700 265,000.00 283,550.00
2 Semen/Pc kg 10.0000 1,220.00 12,200.00
3 Pasir pasang m³ 0.0450 125,000.00 5,625.00
4 Semen warna mutu baik kg 1.5000 16,800.00 25,200.00
JUMLAH HARGA BAHAN 326,575.00
B TENAGA
1 Pekerja L.01 OH 0.7000 65,500.00 45,850.00
JUMLAH HARGA TENAGA 45,850.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 372,425.00

A.4.4.3.35.2 1 M2 LANTAI KERAMIK ( 40 X 40 ) CM - MUTU MENENGAH


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Keramik 40x40cm kw 1 (mutu menengah) m² 1.0600 60,000.00 63,600.00
2 Semen/Pc kg 9.8000 1,220.00 11,956.00
3 Pasir pasang m³ 0.0450 125,000.00 5,625.00
4 Semen warna mutu baik kg 1.0000 16,800.00 16,800.00
JUMLAH HARGA BAHAN 97,981.00
B TENAGA
1 Pekerja L.01 OH 0.7000 65,500.00 45,850.00
JUMLAH HARGA TENAGA 45,850.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 143,831.00

A.4.4.3.35.3 1 M2 LANTAI GRANITE TILE ( 60 X 60 ) CM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Granite tile 60x60cm m² 1.0600 325,000.00 344,500.00
2 Semen/Pc kg 9.8000 1,220.00 11,956.00
3 Pasir pasang m³ 0.0450 125,000.00 5,625.00
4 Semen warna mutu baik kg 1.0000 16,800.00 16,800.00
JUMLAH HARGA BAHAN 378,881.00
B TENAGA
1 Pekerja L.01 OH 0.7000 65,500.00 45,850.00
JUMLAH HARGA TENAGA 45,850.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 424,731.00
A.4.4.3.35.4 1 M2 LANTAI GRANITE TILE ( 30 X 60 ) CM
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Granite tile 30x60cm m² 1.0600 275,000.00 291,500.00
2 Semen/Pc kg 9.8000 1,220.00 11,956.00
3 Pasir pasang m³ 0.0450 125,000.00 5,625.00
4 Semen warna mutu baik kg 1.0000 16,800.00 16,800.00
JUMLAH HARGA BAHAN 325,881.00
B TENAGA
1 Pekerja L.01 OH 0.7000 65,500.00 45,850.00
JUMLAH HARGA TENAGA 45,850.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 371,731.00

A.4.4.3.38 1 M2 LANTAI KERAMIK ( 20 X 20 ) CM ANTI SLIP - MUTU MENENGAH


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Keramik 20x20cm kw 1 (mutu menengah) m² 1.0600 56,500.00 59,890.00
2 Semen/Pc kg 10.4000 1,220.00 12,688.00
3 Pasir pasang m³ 0.0450 125,000.00 5,625.00
4 Semen warna mutu baik kg 1.6200 16,800.00 27,216.00
JUMLAH HARGA BAHAN 105,419.00
B TENAGA
1 Pekerja L.01 OH 0.7000 65,500.00 45,850.00
JUMLAH HARGA TENAGA 45,850.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 151,269.00

A.4.4.3.39 1 M2 DINDING KERAMIK ( 20 X 25 ) CM - MUTU MENENGAH


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Keramik 20x25cm kw 1 (mutu menengah) m² 1.0600 60,000.00 63,600.00
2 Semen/Pc kg 9.3000 1,220.00 11,346.00
3 Pasir pasang m³ 0.0180 125,000.00 2,250.00
4 Semen warna mutu baik kg 1.9400 16,800.00 32,592.00
JUMLAH HARGA BAHAN 109,788.00
B TENAGA
1 Pekerja L.01 OH 0.7000 65,500.00 45,850.00
JUMLAH HARGA TENAGA 45,850.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 155,638.00
A.4.4.3.39.1 1 M2 DINDING KERAMIK ( 30 X 30 ) CM
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Keramik 30x30cm kw 1 (mutu menengah) m² 1.0600 60,000.00 63,600.00
2 Semen/Pc kg 9.3000 1,220.00 11,346.00
3 Pasir pasang m³ 0.0180 125,000.00 2,250.00
4 Semen warna mutu baik kg 1.9400 16,800.00 32,592.00
JUMLAH HARGA BAHAN 109,788.00
B TENAGA
1 Pekerja L.01 OH 0.7000 65,500.00 45,850.00
JUMLAH HARGA TENAGA 45,850.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 155,638.00

A.4.4.3.39.2 1 M2 DINDING KERAMIK ( 40 X 40 ) CM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Keramik 40x40cm kw 1 (mutu menengah) m² 1.0600 60,000.00 63,600.00
2 Semen/Pc kg 9.3000 1,220.00 11,346.00
3 Pasir pasang m³ 0.0180 125,000.00 2,250.00
4 Semen warna mutu baik kg 1.9400 16,800.00 32,592.00
JUMLAH HARGA BAHAN 109,788.00
B TENAGA
1 Pekerja L.01 OH 0.7000 65,500.00 45,850.00
JUMLAH HARGA TENAGA 45,850.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 155,638.00

A.4.4.3.39.3 1 M2 DINDING GRANITE TILE ( 30 X 60 ) CM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Granite tile 30x60cm m² 1.0600 275,000.00 291,500.00
2 Semen/Pc kg 9.3000 1,220.00 11,346.00
3 Pasir pasang m³ 0.0180 125,000.00 2,250.00
4 Semen warna mutu baik kg 1.9400 16,800.00 32,592.00
JUMLAH HARGA BAHAN 337,688.00
B TENAGA
1 Pekerja L.01 OH 0.7000 65,500.00 45,850.00
JUMLAH HARGA TENAGA 45,850.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 383,538.00
A.4.4.3.40 1 M1 PLINT KERAMIK LIST ( 10 X 20 ) CM KERAMIK KEMBANG - MUTU MENENGAH
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Keramik kembang 10x20cm kw 1 bh 5.5000 8,500.00 46,750.00
2 Semen/Pc kg 1.6500 1,220.00 2,013.00
3 Pasir pasang m³ 0.0032 125,000.00 400.00
4 Semen warna mutu baik kg 0.1000 16,800.00 1,680.00
JUMLAH HARGA BAHAN 50,843.00
B TENAGA
1 Pekerja L.01 OH 0.0900 65,500.00 5,895.00
JUMLAH HARGA TENAGA 5,895.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 56,738.00

A.4.4.3.41 1 M1 PLINT KERAMIK ( 10 X 40 ) CM - MUTU MENENGAH


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Keramik 10x40cm kw 1 (mutu menengah) bh 2.5000 6,029.17 15,072.92
2 Semen/Pc kg 1.2400 1,220.00 1,512.80
3 Pasir pasang m³ 0.0030 125,000.00 375.00
4 Semen warna mutu baik kg 0.1000 16,800.00 1,680.00
JUMLAH HARGA BAHAN 18,640.72
B TENAGA
1 Pekerja L.01 OH 0.0900 65,500.00 5,895.00
JUMLAH HARGA TENAGA 5,895.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 24,535.72

A.4.4.3.41.2 1 M1 PLINT KERAMIK ( 18 X 30 ) CM - MUTU MENENGAH


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Keramik 18x30cm kw 1 (mutu menengah) bh 3.6667 5,454.55 20,000.18
2 Semen/Pc kg 1.6500 1,220.00 2,013.00
3 Pasir pasang m³ 0.0032 125,000.00 400.00
4 Semen warna mutu baik kg 0.1000 16,800.00 1,680.00
JUMLAH HARGA BAHAN 24,093.18
B TENAGA
1 Pekerja L.01 OH 0.0900 65,500.00 5,895.00
JUMLAH HARGA TENAGA 5,895.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 29,988.18
A.4.4.3.41.3 1 M1 PLINT GRANITE TILE ( 15 X 60 ) CM
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Granite tile 15x60cm m² 1.6667 27,083.33 45,138.89
2 Semen/Pc kg 1.6500 1,220.00 2,013.00
3 Pasir pasang m³ 0.0032 125,000.00 400.00
4 Semen warna mutu baik kg 0.1000 16,800.00 1,680.00
JUMLAH HARGA BAHAN 49,231.89
B TENAGA
1 Pekerja L.01 OH 0.0900 65,500.00 5,895.00
JUMLAH HARGA TENAGA 5,895.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 55,126.89

A.4.4.3.57 1 M2 DINDING BATU PALIMANAN MOTIP SISIR


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Batu palimanan motip sisir m² 1.1000 150,000.00 165,000.00
2 Semen/Pc kg 11.7500 1,220.00 14,335.00
3 Pasir pasang m³ 0.0350 125,000.00 4,375.00
JUMLAH HARGA BAHAN 183,710.00
B TENAGA
1 Pekerja L.01 OH 0.6200 65,500.00 40,610.00
JUMLAH HARGA TENAGA 40,610.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 224,320.00

A.4.4.3.58 1 M2 DINDING BATU TEMPEL ANDESIT


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Batu tempel andesit m² 1.1000 150,000.00 165,000.00
2 Semen/Pc kg 11.7500 1,220.00 14,335.00
3 Pasir pasang m³ 0.0350 125,000.00 4,375.00
JUMLAH HARGA BAHAN 183,710.00
B TENAGA
1 Pekerja L.01 OH 0.6200 65,500.00 40,610.00
JUMLAH HARGA TENAGA 40,610.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 224,320.00
A.4.5.1 ANALISA PEKERJAAN PLAFOND
A.4.5.1.5a 1 M2 PLAFOND KALSIBOARD, RANGKA LANGIT-LANGI KAYU KLAS II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Balok kayu kelas II m³ 0.0163 5,675,000.00 92,502.50
2 Paku usuk/reng kg 0.2500 15,000.00 3,750.00
3 Paku kalsi kg 0.0500 30,000.00 1,500.00
4 Kalsiboard 120x240x3,5mm lbr 0.3600 77,500.00 27,900.00
JUMLAH HARGA BAHAN 125,652.50
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 145,302.50

A.4.5.1.5b 1 M2 PLAFOND GYPSUMBOARD T. 9MM, RANGKA LANGIT-LANGI KAYU KLAS II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Balok kayu kelas II m³ 0.0163 5,675,000.00 92,502.50
2 Paku usuk/reng kg 0.2500 15,000.00 3,750.00
3 Paku kalsi kg 0.0500 30,000.00 1,500.00
4 Gypsumboard 120x240x9mm lbr 0.3600 118,750.00 42,750.00
JUMLAH HARGA BAHAN 140,502.50
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 160,152.50

A.4.5.1.5c 1 M2 PLAFOND KALSIBOARD T. 3,5MM, RANGKA HOLLOW BAJA RINGAN


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Hollow baja ringan 20.40 #N/A 4.4000 5,500.00 24,200.00
2 Hollow baja ringan 40.40 #N/A 2.0000 7,500.00 15,000.00
3 Sekrup #N/A 20.0000 90.00 1,800.00
4 Perlengkapan material (10%xHb), 1,2 & 3 Ls 0.1000 41,000.00 4,100.00
5 Paku kalsi #N/A 0.0500 30,000.00 1,500.00
6 Kalsiboard 120x240x3,5mm #N/A 0.3600 77,500.00 27,900.00
JUMLAH HARGA BAHAN 74,500.00
B TENAGA
1 Pekerja L.01 OH 0.3000 65,500.00 19,650.00
JUMLAH HARGA TENAGA 19,650.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 94,150.00
A.4.5.1.8 1 M¹ LIST PLAFOND GYPSUM C7
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 List plafond gypsum C7 m¹ 1.0500 11,500.00 12,075.00
2 Paku piles bh 2.0000 400.00 800.00
JUMLAH HARGA BAHAN 12,875.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 19,425.00

A.4.5.1.9 1 M¹ LIST PLAFOND KAYU


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 List plafond kayu 1x4cm m¹ 1.0500 6,500.00 6,825.00
2 Paku usuk/reng kg 0.0100 15,000.00 150.00
JUMLAH HARGA BAHAN 6,975.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 13,525.00

A.4.5.2 ANALISA PEKERJAAN PENUTUP ATAP

A.4.5.2.1 1 M2 PEKERJAAN ATAP GENTENG PEJATEN PRESS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Atap genteng pejaten press bh 25.0000 1,550.00 38,750.00
2 Paku sekrup anti karat bh - 750.00 -
JUMLAH HARGA BAHAN 38,750.00
B TENAGA
1 Pekerja L.01 OH 0.2000 65,500.00 13,100.00
JUMLAH HARGA TENAGA 13,100.00
C PERALATAN
1 Mesin bor (sewa) Jam - - -
2 Listrik kwh - - -
JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 51,850.00

A.4.5.2.2 1 M2 PEKERJAAN ATAP GENTENG BETON FLAT PRESS MINIMALIS - WARNA


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Atap genteng beton flat press minimalis warna m² 1.0000 123,117.50 123,117.50
2 Paku sekrup anti karat bh 11.0000 750.00 8,250.00
JUMLAH HARGA BAHAN 131,367.50
B TENAGA
1 Pekerja L.01 OH 0.2000 65,500.00 13,100.00
JUMLAH HARGA TENAGA 13,100.00
C PERALATAN
1 Mesin bor (sewa) Jam - - -
2 Listrik kwh - - -
JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 144,467.50
A.4.5.2.2a 1 M2 PEKERJAAN PASANGAN ULANG ATAP GENTENG BETON FLAT LAMA
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Atap genteng beton flat press minimalis warna m² - - -
2 Paku sekrup anti karat bh 11.0000 750.00 8,250.00
JUMLAH HARGA BAHAN 8,250.00
B TENAGA
1 Pekerja L.01 OH 0.2000 65,500.00 13,100.00
JUMLAH HARGA TENAGA 13,100.00
C PERALATAN
1 Mesin bor (sewa) Jam - - -
2 Listrik kwh - - -
JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 21,350.00

A.4.5.2.5 1 M1 PEKERJAAN BUBUNGAN GENTENG PEJATEN PRESS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bubungan genteng pejaten press bh 5.0000 3,600.00 18,000.00
2 Paku sekrup anti karat bh - - -
3 Semen/Pc kg 8.0000 1,220.00 9,760.00
4 Pasir pasang m³ 0.0320 125,000.00 4,000.00
JUMLAH HARGA BAHAN 31,760.00
B TENAGA
1 Pekerja L.01 OH 0.4000 65,500.00 26,200.00
JUMLAH HARGA TENAGA 26,200.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 57,960.00
A.4.5.2.5.1 1 M1 PEKERJAAN BUBUNGAN GENTENG BETON FLAT PRESS
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bubungan genteng beton flat press bh 3.5000 12,100.00 42,350.00
2 Paku sekrup - - - -
3 Semen/Pc #N/A 8.0000 1,220.00 9,760.00
4 Pasir pasang #N/A 0.0320 125,000.00 4,000.00
JUMLAH HARGA BAHAN 56,110.00
B TENAGA
1 Pekerja L.01 OH 0.4000 65,500.00 26,200.00
JUMLAH HARGA TENAGA 26,200.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 82,310.00

A.4.5.2.6 1 M1 PEKERJAAN BUBUNGAN METALZING MINIMALIS WARNA 0,35MM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bubungan genteng metalzing warna 0,35mm m¹ 1.1000 50,000.00 55,000.00
2 Paku kait anti karat bh 6.0000 2,250.00 13,500.00
JUMLAH HARGA BAHAN 68,500.00
B TENAGA
1 Pekerja L.01 OH 0.2000 65,500.00 13,100.00
JUMLAH HARGA TENAGA 13,100.00
C PERALATAN
1 Mesin bor (sewa) Jam 0.0200 12,500.00 250.00
2 Listrik kwh 1.5000 750.00 1,125.00
JUMLAH HARGA PERALATAN 1,375.00

D JUMLAH ( A + B + C ) 82,975.00

A.4.5.2.30 1 M2 PEKERJAAN ATAP ZINKCALUME 0,35MM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Atap zinkcalume 0,35mm - L.70cm m¹ 1.3500 65,000.00 87,750.00
2 Paku kait anti karat bh 6.0000 2,250.00 13,500.00
JUMLAH HARGA BAHAN 101,250.00
B TENAGA
1 Pekerja L.01 OH 0.2000 65,500.00 13,100.00
JUMLAH HARGA TENAGA 13,100.00
C PERALATAN
1 Mesin bor (sewa) Jam 0.0200 12,500.00 250.00
2 Listrik kwh - 750.00 -
JUMLAH HARGA PERALATAN 250.00

D JUMLAH ( A + B + C ) 114,600.00
A.4.5.2.42 1 M1 PEKERJAAN TALANG PATAHAN ZINKCALUME 0,35MM
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Seng plat zinkcalume 0,35mm lbr 0.5000 69,500.00 34,750.00
2 Papan kayu kelas II m³ 0.0096 5,450,000.00 52,320.00
3 Paku seng kg 0.0150 20,000.00 300.00
4 Meny besi kg 0.2500 12,500.00 3,125.00
JUMLAH HARGA BAHAN 90,495.00
B TENAGA
1 Pekerja L.01 OH 0.1500 65,500.00 9,825.00
JUMLAH HARGA TENAGA 9,825.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 100,320.00

A.4.6.1 ANALISA PEKERJAAN KAYU


A.4.6.1.1 1 M3 MEMBUAT DAN MEMASANG KUSEN PINTU/JENDELA KAYU KLAS II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Balok kayu kelas II m³ 1.1000 5,675,000.00 6,242,500.00
2 Paku usuk/reng kg 1.2500 15,000.00 18,750.00
3 Lem kayu kg 0.5000 40,000.00 20,000.00
JUMLAH HARGA BAHAN 6,281,250.00
B TENAGA
1 Pekerja L.01 OH 6.0000 65,500.00 393,000.00
JUMLAH HARGA TENAGA 393,000.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 6,674,250.00

A.4.6.1.2 1 M3 MEMBUAT DAN MEMASANG KUSEN PINTU/JENDELA KAYU KLAS II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Balok kayu kelas II m³ 1.1000 5,675,000.00 6,242,500.00
2 Paku usuk/reng kg 1.2500 15,000.00 18,750.00
3 Lem kayu kg 0.5000 40,000.00 20,000.00
JUMLAH HARGA BAHAN 6,281,250.00
B TENAGA
1 Pekerja L.01 OH 6.0000 65,500.00 393,000.00
JUMLAH HARGA TENAGA 393,000.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 6,674,250.00
A.4.6.1.5 1 M² MEMBUAT DAN MEMASANG DAUN PINTU PANEL KAYU KLAS II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas II m³ 0.0400 5,450,000.00 218,000.00
2 Lem kayu kg 0.5000 40,000.00 20,000.00
JUMLAH HARGA BAHAN 238,000.00
B TENAGA
1 Pekerja L.01 OH 1.0000 65,500.00 65,500.00
JUMLAH HARGA TENAGA 65,500.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 303,500.00

A.4.6.1.5a 1 M² MEMBUAT DAN MEMASANG DAUN PINTU PANEL KAYU KLAS II, DALAM DILAPISI TRIPLEK ALUMINIUM - PINTU TOILET
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas II m³ 0.0400 5,450,000.00 218,000.00
2 Lem kayu kg 0.5000 40,000.00 20,000.00
3 Triplek aluminium lbr 0.4000 130,000.00 52,000.00
JUMLAH HARGA BAHAN 290,000.00
B TENAGA
1 Pekerja L.01 OH 1.0000 65,500.00 65,500.00
JUMLAH HARGA TENAGA 65,500.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 355,500.00

A.4.6.1.5b 1 M² MEMBUAT DAN MEMASANG DAUN PINTU DOUBLE TEAKWOOD RANGKA KAYU KLAS II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas II #N/A 0.0250 5,450,000.00 136,250.00
2 Lem kayu #N/A 0.5000 40,000.00 20,000.00
3 Teakwood 120x240x4mm #N/A 0.7200 106,250.00 76,500.00
JUMLAH HARGA BAHAN 232,750.00
B TENAGA
1 Pekerja L.01 OH 0.6000 65,500.00 39,300.00
JUMLAH HARGA TENAGA 39,300.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 272,050.00
A.4.6.1.5c 1 M² MEMBUAT DAN MEMASANG DAUN PINTU LUAR TEAKWOOD,DALAM LAPIS TRIPLEK ALUMINIUM RANGKA KAYU KLAS II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas II #N/A 0.0250 5,450,000.00 136,250.00
2 Lem kayu #N/A 0.5000 40,000.00 20,000.00
3 Teakwood 120x240x4mm #N/A 0.3600 106,250.00 38,250.00
4 Triplek aluminium #N/A 0.3600 130,000.00 46,800.00
JUMLAH HARGA BAHAN 241,300.00
B TENAGA
1 Pekerja L.01 OH 0.6000 65,500.00 39,300.00
JUMLAH HARGA TENAGA 39,300.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 280,600.00

A.4.6.1.6 1 M² MEMBUAT DAN MEMASANG DAUN JENDELA KACA KAYU KLAS I


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas I m³ 0.0240 12,000,000.00 288,000.00
2 Lem kayu kg 0.3000 40,000.00 12,000.00
3 Kaca ryben 5mm m² 0.8900 135,975.00 121,017.75
JUMLAH HARGA BAHAN 421,017.75
B TENAGA
1 Pekerja L.01 OH 0.8000 65,500.00 52,400.00
JUMLAH HARGA TENAGA 52,400.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 473,417.75

A.4.6.1.6a 1 M² MEMBUAT DAN MEMASANG DAUN PINTU KACA KAYU KLAS I


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas I m³ 0.0264 12,000,000.00 316,800.00
2 Lem kayu kg 0.3000 40,000.00 12,000.00
3 Kaca ryben 5mm m² 0.8900 135,975.00 121,017.75
JUMLAH HARGA BAHAN 449,817.75
B TENAGA
1 Pekerja L.01 OH 0.8000 65,500.00 52,400.00
JUMLAH HARGA TENAGA 52,400.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 502,217.75
A.4.6.1.13 1 M3 PASANGAN KONSTRUKSI KUDA-KUDA KAYU KLAS II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Balok kayu kelas II m³ 1.1000 5,675,000.00 6,242,500.00
2 Paku usuk/reng kg 5.6000 15,000.00 84,000.00
3 Begel plat strip kg 15.0000 30,900.00 463,500.00
JUMLAH HARGA BAHAN 6,790,000.00
B TENAGA
1 Pekerja L.01 OH 4.0000 65,500.00 262,000.00
JUMLAH HARGA TENAGA 262,000.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 7,052,000.00

A.4.6.1.15 1 M3 PASANGAN KONSTRUKSI GORDING KAYU KLAS II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Balok kayu kelas II m³ 1.1000 5,675,000.00 6,242,500.00
2 Paku usuk/reng kg 5.6000 15,000.00 84,000.00
3 Begel plat strip kg 15.0000 30,900.00 463,500.00
JUMLAH HARGA BAHAN 6,790,000.00
B TENAGA
1 Pekerja L.01 OH 2.4000 65,500.00 157,200.00
JUMLAH HARGA TENAGA 157,200.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 6,947,200.00

A.4.6.1.16 1 M3 PASANGAN USUK 5/7 DAN RENG 2/3 KAYU


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Balok kayu kelas II usuk 5/7 m³ 0.0140 5,675,000.00 79,450.00
2 Balok kayu kelas II reng 2/3 m³ 0.0036 5,675,000.00 20,430.00
3 Paku usuk/reng kg 0.2500 15,000.00 3,750.00
JUMLAH HARGA BAHAN 103,630.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 110,180.00
A.4.6.1.21 1 M1 PASANGAN LISPLANK 3/20 KAYU KLAS I
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas I m³ 0.0108 12,000,000.00 129,600.00
2 Paku usuk/reng kg 0.1000 15,000.00 1,500.00
JUMLAH HARGA BAHAN 131,100.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 137,650.00

A.4.6.1.21a 1 M1 PASANGAN LISPLANK 3/25 KAYU KLAS I


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas I m³ 0.0110 12,000,000.00 132,000.00
2 Paku usuk/reng kg 0.1000 15,000.00 1,500.00
JUMLAH HARGA BAHAN 133,500.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 140,050.00

A.4.6.1.21b 1 M1 PASANGAN LISPLANK KALSIPLANK 8MM-30CM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kalsiplank 8mm - 30cm m¹ 1.1000 45,000.00 49,500.00
2 Paku usuk/reng kg 0.1000 15,000.00 1,500.00
JUMLAH HARGA BAHAN 51,000.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 57,550.00

A.4.6.1.21c 1 M1 PASANGAN LISPLANK KALSIPLANK 8MM-30CM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kalsiplank 8mm - 20cm m¹ 1.1000 27,500.00 30,250.00
2 Paku usuk/reng kg 0.1000 15,000.00 1,500.00
JUMLAH HARGA BAHAN 31,750.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 38,300.00
A.4.6.1.24b 1 M2 PASANGAN DINDING TEAKBLOK T.1,8MM DILAPIS HPL
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Balok kayu kelas II #N/A 0.0018 5,675,000.00 10,215.00
2 Paku usuk/reng #N/A 0.1500 15,000.00 2,250.00
3 Teakblok 120x240x1,8mm #N/A 1.1821 265,000.00 313,261.28
4 Lapisan HPL (Uk.120x240)cm #N/A 1.0943 218,750.00 239,371.74
5 Lem kayu #N/A 0.5000 40,000.00 20,000.00
JUMLAH HARGA BAHAN 585,098.02
B TENAGA
1 Pekerja L.01 OH 0.5000 65,500.00 32,750.00
JUMLAH HARGA TENAGA 32,750.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 617,848.02

A.4.6.1.34 1 M1 PASANGAN KREPYAK VENTILASI 2/13 KAYU KLAS I


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Papan kayu kelas I #N/A 0.0031 12,000,000.00 37,440.00
2 Paku usuk/reng #N/A 0.1000 15,000.00 1,500.00
JUMLAH HARGA BAHAN 38,940.00
B TENAGA
1 Pekerja L.01 OH 0.1000 65,500.00 6,550.00
JUMLAH HARGA TENAGA 6,550.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 45,490.00

A.4.6.2 ANALISA PEKERJAAN PENGUNCI DAN KACA


A.4.6.2.1 MEMASANG 1 BUAH KUNCI TANAM
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kunci pintu 2 slaag klas tinggi bh 1.0000 80,000.00 80,000.00
JUMLAH HARGA BAHAN 80,000.00
B TENAGA
1 Pekerja L.01 OH 0.0100 65,500.00 655.00
JUMLAH HARGA TENAGA 655.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 80,655.00

A.4.6.2.3 MEMASANG 1 BUAH KUNCI KM/WC


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kunci pintu 2 slaag klas menengah bh 1.0000 63,000.00 63,000.00
JUMLAH HARGA BAHAN 63,000.00
B TENAGA
1 Pekerja L.01 OH 0.0050 65,500.00 327.50
JUMLAH HARGA TENAGA 327.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 63,327.50
A.4.6.2.5 MEMASANG 1 BUAH ENGSEL PINTU
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Engsel pintu klas biasa bh 1.0000 16,550.00 16,550.00
JUMLAH HARGA BAHAN 16,550.00
B TENAGA
1 Pekerja L.01 OH 0.0150 65,500.00 982.50
JUMLAH HARGA TENAGA 982.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 17,532.50

A.4.6.2.5a MEMASANG 1 BUAH ENGSEL PINTU KIPAS


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Engsel pintu kipas bh 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 50,000.00
B TENAGA
1 Pekerja L.01 OH 0.0150 65,500.00 982.50
JUMLAH HARGA TENAGA 982.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 50,982.50

A.4.6.2.6 MEMASANG 1 BUAH ENGSEL JENDELA KUPU-KUPU


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Engsel jendela klas tinggi bh 1.0000 22,500.00 22,500.00
JUMLAH HARGA BAHAN 22,500.00
B TENAGA
1 Pekerja L.01 OH 0.0100 65,500.00 655.00
JUMLAH HARGA TENAGA 655.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 23,155.00

A.4.6.2.7 MEMASANG 1 BUAH HAK ANGIN


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kait angin klas tinggi bh 1.0000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 15,000.00
B TENAGA
1 Pekerja L.01 OH 0.0150 65,500.00 982.50
JUMLAH HARGA TENAGA 982.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 15,982.50
A.4.6.2.9 MEMASANG 1 BUAH GRENDEL JENDELA
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Grendel jendela klas tinggi bh 1.0000 12,500.00 12,500.00
JUMLAH HARGA BAHAN 12,500.00
B TENAGA
1 Pekerja L.01 OH 0.0200 65,500.00 1,310.00
JUMLAH HARGA TENAGA 1,310.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D JUMLAH ( A + B + C ) 13,810.00

A.4.6.2.9a MEMASANG 1 BUAH GRENDEL PINTU


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Grendel pintu klas tinggi bh 1.0000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 20,000.00
B TENAGA
1 Pekerja L.01 OH 0.0200 65,500.00 1,310.00
JUMLAH HARGA TENAGA 1,310.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D JUMLAH ( A + B + C ) 21,310.00

A.4.6.2.11a MEMASANG 1 BUAH EXPANYOLET


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Grendel tanam expanyolet bh 1.0000 45,000.00 45,000.00
JUMLAH HARGA BAHAN 45,000.00
B TENAGA
1 Pekerja L.01 OH 0.0200 65,500.00 1,310.00
JUMLAH HARGA TENAGA 1,310.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 46,310.00

A.4.6.2.11b MEMASANG 1 SET REL PINTU DORONG LEBAR PINTU 80CM - J3


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Rel pintu dorong J3 - lebar pintu 80cm set 1.0000 400,000.00 400,000.00
2 Aluminium strip/rel pintu m¹ 1.7600 18,500.00 32,560.00
JUMLAH HARGA BAHAN 432,560.00
B TENAGA
1 Pekerja L.01 OH 0.0100 65,500.00 655.00
JUMLAH HARGA TENAGA 655.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 433,215.00
A.4.6.2.11c MEMASANG 1 SET REL PINTU DORONG LEBAR PINTU 130CM - S6
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Rel pintu dorong S6 - lebar pintu 130cm set 1.0000 625,000.00 625,000.00
2 Aluminium strip/rel pintu m¹ 2.5300 18,500.00 46,805.00
JUMLAH HARGA BAHAN 671,805.00
B TENAGA
1 Pekerja L.01 OH 0.0100 65,500.00 655.00
JUMLAH HARGA TENAGA 655.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 672,460.00

A.4.6.2.13 MEMASANG 1 HANDLE PINTU DOUBLE


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Handle pintu double bh 1.0000 225,000.00 225,000.00
JUMLAH HARGA BAHAN 225,000.00
B TENAGA
1 Pekerja L.01 OH 0.0200 65,500.00 1,310.00
JUMLAH HARGA TENAGA 1,310.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 226,310.00

A.4.6.2.16 MEMASANG 1 M2 KACA POLOS TEBAL 3MM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kaca bening 3mm m² 1.1000 103,500.00 113,850.00
JUMLAH HARGA BAHAN 113,850.00
B TENAGA
1 Pekerja L.01 OH 0.0150 65,500.00 982.50
JUMLAH HARGA TENAGA 982.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 114,832.50

A.4.6.2.17 MEMASANG 1 M2 KACA POLOS TEBAL 5MM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kaca bening 5mm m² 1.1000 129,500.00 142,450.00
JUMLAH HARGA BAHAN 142,450.00
B TENAGA
1 Pekerja L.01 OH 0.0150 65,500.00 982.50
JUMLAH HARGA TENAGA 982.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 143,432.50
A.4.6.2.17a MEMASANG 1 M2 KACA RYBEN TEBAL 5MM
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kaca ryben 5mm m² 1.1000 135,975.00 149,572.50
JUMLAH HARGA BAHAN 149,572.50
B TENAGA
1 Pekerja L.01 OH 0.0150 65,500.00 982.50
JUMLAH HARGA TENAGA 982.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 150,555.00

A.4.7.1 ANALISA PEKERJAAN PENGECATAN


A.4.7.1.4 1 M2 PENGECATAN KAYU BARU (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Meny kayu kg 0.2000 15,500.00 3,100.00
2 Plamir Kayu kg 0.1500 25,000.00 3,750.00
3 Minyak cat klas menengah ltr 0.0300 11,000.00 330.00
4 Amplas lbr 0.2000 3,750.00 750.00
5 Kuas cat bh 0.0100 6,800.00 68.00
Cat dasar Cat kayu klas menengah kg 0.1700 55,000.00 9,350.00
Cat penutup Cat kayu klas menengah kg 0.2600 55,000.00 14,300.00
JUMLAH HARGA BAHAN 31,648.00
B TENAGA
1 Pekerja L.01 OH 0.2000 65,500.00 13,100.00
JUMLAH HARGA TENAGA 13,100.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 44,748.00

A.4.7.1.4a 1 M2 PENGECATAN KAYU BARU (1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Plamir Kayu kg 0.1500 25,000.00 3,750.00
2 Minyak cat klas menengah ltr 0.0300 11,000.00 330.00
3 Amplas lbr 0.2000 3,750.00 750.00
4 Kuas cat bh 0.0100 6,800.00 68.00
Cat dasar Cat kayu klas menengah kg 0.1700 55,000.00 9,350.00
Cat penutup Cat kayu klas menengah kg 0.2600 55,000.00 14,300.00
JUMLAH HARGA BAHAN 28,548.00
B TENAGA
1 Pekerja L.01 OH 0.2000 65,500.00 13,100.00
JUMLAH HARGA TENAGA 13,100.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 41,648.00
A.4.7.1.7 1 M2 POLITURAN DAUN PINTU (2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Wood filer ltr 0.1000 25,200.00 2,520.00
2 Politur ltr 0.3720 57,000.00 21,204.00
3 Amplas lbr 2.0000 3,750.00 7,500.00
JUMLAH HARGA BAHAN 31,224.00
B TENAGA
1 Pekerja L.01 OH 0.2000 65,500.00 13,100.00
JUMLAH HARGA TENAGA 13,100.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 44,324.00

A.4.7.1.10 1 M2 PENGECATAN TEMBOK BARU - INTERIOR (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
Plamir tembok
1 kg 0.1000 9,000.00 900.00
Cat dasar Cat tembok klas menengah kg 0.1000 31,500.00 3,150.00
Cat penutup Cat tembok klas menengah kg 0.2600 31,500.00 8,190.00
JUMLAH HARGA BAHAN 12,240.00
B TENAGA
1 Pekerja L.01 OH 0.0200 65,500.00 1,310.00
JUMLAH HARGA TENAGA 1,310.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 13,550.00

A.4.7.1.10a 1 M2 PENGECATAN TEMBOK BARU - EXSTERIOR (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
Alkali (anti jamur)
1 kg 0.1000 46,200.00 4,620.00
Cat dasar Cat tembok klas tinggi kg 0.1000 89,000.00 8,900.00
Cat penutup Cat tembok klas tinggi kg 0.2600 89,000.00 23,140.00
JUMLAH HARGA BAHAN 36,660.00
B TENAGA
1 Pekerja L.01 OH 0.0200 65,500.00 1,310.00
JUMLAH HARGA TENAGA 1,310.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 37,970.00
A.4.7.1.10b 1 M2 PENGECATAN TEMBOK LAMA - INTERIOR (1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
Plamir tembok
1 kg - - -
Cat dasar Cat tembok klas menengah kg 0.1000 31,500.00 3,150.00
Cat penutup Cat tembok klas menengah kg 0.2600 31,500.00 8,190.00
JUMLAH HARGA BAHAN 11,340.00
B TENAGA
1 Pekerja L.01 OH 0.0200 65,500.00 1,310.00
JUMLAH HARGA TENAGA 1,310.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 12,650.00

A.4.7.1.17 1 M2 PENGECATAN BESI


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Cat besi klas menengah kg 0.2600 55,000.00 14,300.00
2 Kuas cat bh 0.0100 6,800.00 68.00
JUMLAH HARGA BAHAN 14,368.00
B TENAGA
1 Pekerja L.01 OH 0.0200 65,500.00 1,310.00
JUMLAH HARGA TENAGA 1,310.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 15,678.00

A.4.7.1.17a 1 M2 PENGECATAN BESI DGN CAT MENY


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Meny besi kg 0.2600 12,500.00 3,250.00
2 Kuas cat bh 0.0100 6,800.00 68.00
JUMLAH HARGA BAHAN 3,318.00
B TENAGA
1 Pekerja L.01 OH 0.0200 65,500.00 1,310.00
JUMLAH HARGA TENAGA 1,310.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 4,628.00

A.4.7.1.18 1 M2 PENGECATAN BATU PALIMANAN ANTI LUMUT


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Cat anti lumut kg 0.2600 75,000.00 19,500.00
2 Kuas cat bh 0.0100 6,800.00 68.00
JUMLAH HARGA BAHAN 19,568.00
B TENAGA
1 Pekerja L.01 OH 0.0200 65,500.00 1,310.00
JUMLAH HARGA TENAGA 1,310.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 20,878.00
A.5.1.1 ANALISA PEKERJAAN SANITASI
A.5.1.1.1 MEMASANG 1 BUAH KLOSED DUDUK
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
Closed duduk monoblok (Sekualitas Toto) unit 1.0000 2,350,000.00 2,350,000.00
Perlengkapan (6% dari harga klosed) HK 0.0600 2,350,000.00 141,000.00
JUMLAH HARGA BAHAN 2,491,000.00
B TENAGA
1 Pekerja L.01 OH 3.3000 65,500.00 216,150.00
JUMLAH HARGA TENAGA 216,150.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 2,707,150.00

A.5.1.1.2 MEMASANG 1 BUAH KLOSED JONGKOK PORSELIN


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
Closed jongkok porselint klas menengah unit 1.0000 185,000.00 185,000.00
Semen/Pc kg 6.0000 1,220.00 7,320.00
Pasir pasang m³ 0.0100 125,000.00 1,250.00
JUMLAH HARGA BAHAN 193,570.00
B TENAGA
1 Pekerja L.01 OH 1.0000 65,500.00 65,500.00
JUMLAH HARGA TENAGA 65,500.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 259,070.00

A.5.1.1.4 MEMASANG 1 BUAH URINOIR


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Urinoir klas menengah unit 1.0000 575,000.00 575,000.00
2 Perlengkapan (15% dari harga urinoir) HK 0.1500 575,000.00 86,250.00
JUMLAH HARGA BAHAN 661,250.00
B TENAGA
1 Pekerja L.01 OH 3.3000 65,500.00 216,150.00
JUMLAH HARGA TENAGA 216,150.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 877,400.00
A.5.1.1.5 MEMASANG 1 BUAH WASTAFLE
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Washtafel komplit kran unit 1.0000 550,000.00 550,000.00
2 Perlengkapan (12%) hk 0.1200 550,000.00 66,000.00
3 Semen/Pc kg 6.0000 1,220.00 7,320.00
4 Pasir pasang m³ 0.0100 125,000.00 1,250.00
JUMLAH HARGA BAHAN 624,570.00
B TENAGA
1 Pekerja L.01 OH 1.2000 65,500.00 78,600.00
JUMLAH HARGA TENAGA 78,600.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 703,170.00

A.5.1.1.15 MEMASANG 1 M PIPA BETON BUIS 1/2 Ø 20CM


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Buis beton 1/2 Ø 30cm - 1m m¹ 1.1000 60,000.00 66,000.00
2 Bata merah klas I bh 1.0000 575.00 575.00
3 Semen/Pc kg 1.0300 1,220.00 1,256.60
4 Pasir pasang m³ 0.0610 125,000.00 7,625.00
JUMLAH HARGA BAHAN 75,456.60
B TENAGA
1 Pekerja L.01 OH 0.1900 65,500.00 12,445.00
JUMLAH HARGA TENAGA 12,445.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 87,901.60

A.5.1.1.19 MEMASANG 1 M PIPA GIP MEDIUM B - Ø 1/2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pipa GI ø 1/2" - Medium B m¹ 1.2000 28,000.00 33,600.00
2 Perlengkapan (Support) 35% harga pipa Ls 0.3500 33,600.00 11,760.00
JUMLAH HARGA BAHAN 45,360.00
B TENAGA
1 Pekerja L.01 OH 0.0540 65,500.00 3,537.00
JUMLAH HARGA TENAGA 3,537.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 48,897.00
A.5.1.1.20 MEMASANG 1 M PIPA GIP MEDIUM B - Ø 3/4"
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pipa GI ø 3/4" - Medium B m¹ 1.2000 31,000.00 37,200.00
2 Perlengkapan (Support) 35% harga pipa Ls 0.3500 37,200.00 13,020.00
JUMLAH HARGA BAHAN 50,220.00
B TENAGA
1 Pekerja L.01 OH 0.0540 65,500.00 3,537.00
JUMLAH HARGA TENAGA 3,537.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 53,757.00

A.5.1.1.21 MEMASANG 1 M PIPA GIP MEDIUM B - Ø 1"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pipa GI ø 1" - Medium B m¹ 1.2000 37,500.00 45,000.00
2 Perlengkapan (Support) 35% harga pipa Ls 0.3500 45,000.00 15,750.00
JUMLAH HARGA BAHAN 60,750.00
B TENAGA
1 Pekerja L.01 OH 0.0540 65,500.00 3,537.00
JUMLAH HARGA TENAGA 3,537.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 64,287.00

A.5.1.1.25 MEMASANG 1 M PIPA PVC TIPE AW DIAMETER 1/2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pipa PVC ø 1/2" - Aw m¹ 1.2000 5,500.00 6,600.00
2 Perlengkapan (Support) 15% harga pipa Ls 0.1500 6,600.00 990.00
JUMLAH HARGA BAHAN 7,590.00
B TENAGA
1 Pekerja L.01 OH 0.0360 65,500.00 2,358.00
JUMLAH HARGA TENAGA 2,358.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 9,948.00

A.5.1.1.26 MEMASANG 1 M PIPA PVC TIPE AW DIAMETER 3/4"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pipa PVC ø 3/4" - Aw m¹ 1.2000 7,500.00 9,000.00
2 Perlengkapan (Support) 15% harga pipa Ls 0.1500 9,000.00 1,350.00
JUMLAH HARGA BAHAN 10,350.00
B TENAGA
1 Pekerja L.01 OH 0.0360 65,500.00 2,358.00
JUMLAH HARGA TENAGA 2,358.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 12,708.00
A.5.1.1.27 MEMASANG 1 M PIPA PVC TIPE AW DIAMETER 1"
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pipa PVC ø 1 " - Aw m¹ 1.2000 12,500.00 15,000.00
2 Perlengkapan (Support) 15% harga pipa Ls 0.1500 15,000.00 2,250.00
JUMLAH HARGA BAHAN 17,250.00
B TENAGA
1 Pekerja L.01 OH 0.0360 65,500.00 2,358.00
JUMLAH HARGA TENAGA 2,358.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 19,608.00

A.5.1.1.29 MEMASANG 1 M PIPA PVC TIPE AW DIAMETER 2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pipa PVC ø 2" - Aw m¹ 1.2000 15,750.00 18,900.00
2 Perlengkapan (Support) 15% harga pipa Ls 0.1500 18,900.00 2,835.00
JUMLAH HARGA BAHAN 21,735.00
B TENAGA
1 Pekerja L.01 OH 0.0540 65,500.00 3,537.00
JUMLAH HARGA TENAGA 3,537.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 25,272.00

A.5.1.1.31 MEMASANG 1 M PIPA PVC TIPE AW DIAMETER 3"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pipa PVC ø 3" - Aw m¹ 1.2000 29,000.00 34,800.00
2 Perlengkapan (Support) 15% harga pipa Ls 0.1500 34,800.00 5,220.00
JUMLAH HARGA BAHAN 40,020.00
B TENAGA
1 Pekerja L.01 OH 0.0810 65,500.00 5,305.50
JUMLAH HARGA TENAGA 5,305.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 45,325.50

A.5.1.1.32 MEMASANG 1 M PIPA PVC TIPE AW DIAMETER 4"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Pipa PVC ø 4" - Aw m¹ 1.2000 43,000.00 51,600.00
2 Perlengkapan (Support) 15% harga pipa Ls 0.1500 51,600.00 7,740.00
JUMLAH HARGA BAHAN 59,340.00
B TENAGA
1 Pekerja L.01 OH 0.0810 65,500.00 5,305.50
JUMLAH HARGA TENAGA 5,305.50
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 64,645.50
A.5.1.1.33 MEMASANG 1 BAK CUCI PIRING STAILESS STEEL
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Bak stainless steel 1 lobang unit 1.0000 350,000.00 350,000.00
2 Water Drain + accessoris unit 1.0000 - -
JUMLAH HARGA BAHAN 350,000.00
B TENAGA
1 Pekerja L.01 OH 0.0300 65,500.00 1,965.00
JUMLAH HARGA TENAGA 1,965.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 351,965.00

A.5.1.1.35 MEMASANG 1 BUAH KRAN 1/2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kran air GI ø 1/2" bh 1.0000 20,000.00 20,000.00
2 Seal tape bh 0.0250 3,000.00 75.00
JUMLAH HARGA BAHAN 20,075.00
B TENAGA
1 Pekerja L.01 OH 0.0100 65,500.00 655.00
JUMLAH HARGA TENAGA 655.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 20,730.00

A.5.1.1.35a MEMASANG 1 BUAH GATE VALVE Ø 1"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Gate valve GI Ø 1'' bh 1.0000 175,000.00 175,000.00
2 Seal tape bh 0.0250 3,000.00 75.00
JUMLAH HARGA BAHAN 175,075.00
B TENAGA
1 Pekerja L.01 OH 0.0100 65,500.00 655.00
JUMLAH HARGA TENAGA 655.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 175,730.00

A.5.1.1.35b MEMASANG 1 BUAH KRAN HANDSOWER Ø 1/2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kran handsower ø 1/2" bh 1.0000 275,000.00 275,000.00
2 Seal tape bh 0.0250 3,000.00 75.00
JUMLAH HARGA BAHAN 275,075.00
B TENAGA
1 Pekerja L.01 OH 0.0100 65,500.00 655.00
JUMLAH HARGA TENAGA 655.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 275,730.00
A.5.1.1.35c MEMASANG 1 BUAH KRAN WASHTAFLE Ø 1/2"
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kran washtafle ø 1/2" bh 1.0000 175,000.00 175,000.00
2 Seal tape bh 0.0250 3,000.00 75.00
JUMLAH HARGA BAHAN 175,075.00
B TENAGA
1 Pekerja L.01 OH 0.0100 65,500.00 655.00
JUMLAH HARGA TENAGA 655.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D JUMLAH ( A + B + C ) 175,730.00

A.5.1.1.35d MEMASANG 1 BUAH JETCLOSET Ø 1/2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kran jetcloset ø 1/2" bh 1.0000 225,000.00 225,000.00
2 Seal tape bh 0.0250 3,000.00 75.00
JUMLAH HARGA BAHAN 225,075.00
B TENAGA
1 Pekerja L.01 OH 0.0100 65,500.00 655.00
JUMLAH HARGA TENAGA 655.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D JUMLAH ( A + B + C ) 225,730.00

A.5.1.1.36 MEMASANG 1 BUAH FLOOR DRAIN


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Floor drain (Avour) - stainless steel bh 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 50,000.00
B TENAGA
1 Pekerja L.01 OH 0.0100 65,500.00 655.00
JUMLAH HARGA TENAGA 655.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D JUMLAH ( A + B + C ) 50,655.00

ANALISA PEKERJAAN LISTRIK


Ls.Inst.1 1 TITIK PEKERJAAN MEMASANG INSTALASI TITIK LAMPU
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kabel NYA 2x2,5mm2 m¹ 4.0000 7,560.00 30,240.00
2 Pipa conduit (Ex. Ega) m¹ 4.0000 2,500.00 10,000.00
3 Socket pipa bh 1.0000 500.00 500.00
4 Tee Doos bh 2.0000 2,000.00 4,000.00
5 Klem pipa bh 3.0000 250.00 750.00
6 Fhiser bh 6.0000 100.00 600.00
7 Las doop bh 2.0000 200.00 400.00
8 Isolasi ban bh 0.2500 1,500.00 375.00
JUMLAH HARGA BAHAN 46,865.00
B TENAGA
1 Tukang listrik L.02 OH 0.5000 89,080.00 44,540.00
JUMLAH HARGA TENAGA 44,540.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 91,405.00

Ls.Inst.2 1 TITIK PEKERJAAN MEMASANG INSTALASI TITIK STOP KONTAK


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Kabel NYM 3x2,5mm2 m¹ 4.0000 9,650.00 38,600.00
2 Pipa conduit (Ex. Ega) m¹ 4.0000 2,500.00 10,000.00
3 Socket pipa bh 1.0000 500.00 500.00
4 Tee Doos bh 2.0000 2,000.00 4,000.00
5 Klem pipa bh 3.0000 250.00 750.00
6 Fhiser bh 6.0000 100.00 600.00
7 Las doop bh 2.0000 200.00 400.00
8 Isolasi ban bh 0.2500 1,500.00 375.00
JUMLAH HARGA BAHAN 55,225.00
B TENAGA
1 Tukang listrik L.02 OH 0.7500 89,080.00 66,810.00
JUMLAH HARGA TENAGA 66,810.00
C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH ( A + B + C ) 122,035.00
BACK UP VOLUME
PEKERJAAN #REF!
LOKASI #REF!
TAHUN #REF!

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME


1 2 3 4
SALURAN AIR / DRAINASE

1 SALURAN VOLUME = P x JMH 113.05 M1


Depan = 14.00 x 1.00 = 14.00 M1
= 6.45 x 1.00 = 6.45 M1
= 11.70 x 1.00 = 11.70 M1
= 4.40 x 2.00 = 8.80 M1
Samping brt = 25.25 x 1.00 = 25.25 M1
Samping timur = 18.70 x 1.00 = 18.70 M1
Belakang = 28.15 x 1.00 = 28.15 M1
113.05 M1

1 Galian tanah VOLUME = P x L x T x JMH 31.65 M3


= 113.05 x 0.70 x 0.40 x 1.00 = 31.65 M3
31.65 M3

2 Pasir urugan VOLUME = P x L x T x JMH 3.96 M3


= 113.05 x 0.70 x 0.05 x 1.00 = 3.96 M3
3.96 M3

I PEK. PASANGAN/PLESTERAN
1 PAS. TRASRAM 1/2 BT. VOLUME = P x T x SISI 107.00 M2
Depan = 6.45 x 0.63 x 1.00 = 4.06 M2
= 6.45 x 0.45 x 1.00 = 2.90 M2
= 4.40 x 0.45 x 4.00 = 7.92 M2
= 14.00 x 0.45 x 2.00 = 12.60 M2
= 6.90 x 0.63 x 1.00 = 4.35 M2
= 6.90 x 0.45 x 1.00 = 3.11 M2
= 4.80 x 0.45 x 2.00 = 4.32 M2
Samping barat = 25.25 x 0.45 x 2.00 = 22.73 M2
Samping timur = 9.90 x 0.63 x 1.00 = 6.24 M2
= 9.90 x 0.45 x 1.00 = 4.46 M2
= 8.70 x 0.63 x 1.00 = 5.48 M2
= 8.70 x 0.45 x 1.00 = 3.92 M2
Belakang = 27.70 x 0.45 x 2.00 = 24.93 M2
107.00 M2

2 PLEST. TRASRAM VOLUME = P x T x SISI 160.10 M2


Depan = 6.45 x 0.60 x 1.00 = 3.87 M2
= 6.45 x 0.73 x 1.00 = 4.71 M2
= 4.40 x 0.73 x 4.00 = 12.85 M2
= 14.00 x 0.73 x 2.00 = 20.44 M2
= 6.90 x 0.60 x 1.00 = 4.14 M2
= 6.90 x 0.73 x 1.00 = 5.04 M2
= 4.80 x 0.73 x 2.00 = 7.01 M2
Samping barat = 25.25 x 0.73 x 2.00 = 36.87 M2
Samping timur = 9.90 x 0.60 x 1.00 = 5.94 M2
= 9.90 x 0.73 x 1.00 = 7.23 M2
= 8.70 x 0.60 x 1.00 = 5.22 M2
= 8.70 x 0.73 x 1.00 = 6.35 M2
Belakang = 27.70 x 0.73 x 2.00 = 40.44 M2
160.10 M2

II PEKERJAAN BUIS BETON


1 Buis beton 1/2 Ø 30cm VOLUME = P x JMH 113.05 M1
= 113.05 x 1.00 = 113.05 M1
113.05 M1

2 Gril Besi penutup saluran VOLUME = P x JMH 36.00 M1


= 14.00 x 1.00 = 14.00 M1
= 4.40 x 2.00 = 8.80 M1
= 6.40 x 1.00 = 6.40 M1
= 6.80 x 1.00 = 6.80 M1
36.00 M1
RABAT KELILING

1 Pasir urugan bawah rabat VOLUME = P x L x T x JMH 27.30 M3


depan = 23.50 x 1.00 x 0.30 x 1.00 = 7.05 M3
samping = 20.50 x 1.00 x 0.30 x 2.00 = 12.30 M3
belakang = 26.50 x 1.00 x 0.30 x 1.00 = 7.95 M3
27.30 M3

2 Cor rabat beton VOLUME = P x L x T x JMH 7.20 M3


depan = 23.50 x 1.13 x 0.07 x 1.00 = 1.86 M3
samping = 20.50 x 1.13 x 0.07 x 2.00 = 3.24 M3
belakang = 26.50 x 1.13 x 0.07 x 1.00 = 2.10 M3
7.20 M3

3 Plest. Rabat beton VOLUME = P x L x JMH 102.83 M2


depan = 23.50 x 1.13 x 1.00 = 26.56 M2
samping = 20.50 x 1.13 x 2.00 = 46.33 M2
belakang = 26.50 x 1.13 x 1.00 = 29.95 M2
102.83 M2
BACK UP VOLUME
PEKERJAAN #REF!
LOKASI #REF!
TAHUN #REF!

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME


1 2 3 4
GROUNDTANK & RUMAH POMPA
1 Galian tanah VOLUME = P x L x T x JMH 13.24 M3
= 3.40 x 1.90 x 2.05 x 1.00 = 13.24 M3
13.24 M3

2 Pasir urugan VOLUME = P x L x T x JMH 0.65 M3


= 3.40 x 1.90 x 0.10 x 1.00 = 0.65 M3
0.65 M3

I PEK. PASANGAN/PLESTERAN
1 PAS. TRASRAM 1 BT. VOLUME = P x T x SISI 6.00 M2
= 1.50 x 1.00 x 2.00 = 3.00 M2
= 1.50 x 1.00 x 2.00 = 3.00 M2
6.00 M2

2 PLEST. TRASRAM VOLUME = P x T x SISI 12.78 M2


= 1.50 x 2.13 x 4.00 = 12.78 M2
12.78 M2

II PEKERJAAN BETON
1 Lantai kerja VOLUME = P x L x T 0.27 M3
= 3.20 x 1.70 x 0.05 = 0.27 M3
0.27 M3

2 Lantai Plat bertulang VOLUME = P x L x T 0.54 M3


= 3.20 x 1.70 x 0.10 = 0.54 M3
0.54 M3

3 Penutup Plat bertulang VOLUME = P x L x T - lbg 0.52 M3


= 3.20 x 1.70 x 0.10 - 0.03 = 0.52 M3
0.52 M3

4 Dinding beton bertulang VOLUME = P x L x T x JMH 1.69 M3


= 3.20 x 1.80 x 0.10 x 2.00 = 1.15 M3
= 1.50 x 1.80 x 0.10 x 2.00 = 0.54 M3
1.69 M3

III PEKERJAAN KERAMIK


1 Lantai keramik VOLUME = P x T x SISI 4.50 M2
= 3.00 x 1.50 x 1.00 = 4.50 M2
4.50 M2

2 Dinding keramik VOLUME = P x T x SISI 16.20 M2


= 3.00 x 1.80 x 2.00 = 10.80 M2
= 1.50 x 1.80 x 2.00 = 5.40 M2
16.20 M2
BACK UP VOLUME
LANTAI 2

PEKERJAAN #REF!
LOKASI #REF!
TAHUN #REF!

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME


1 2 3 4

I PEKERJAAN BETON LT. II


1 KOLOM BETON 25/25 - Lantai II VOLUME = T x DIMENSI x JMH 4.00 M3
( Besi 16D22 ; Bg. Ø10-10 )
Lantai 2 = 4.00 x 0.25 x 0.25 x 16.00 = 4.00 M3
4.00 M3

BEGISTING = 0.25 + 0.25 x 2.00 x 53.33 = 53.33 M2 13.33 M2/M3


53.33 M2
berat bs x isi x P
PEMBESIAN Bs D 16 = 1.578 x 8.00 x 53.33 = 673.38 Kg 168.35 KG
673.38 Kg
Bs polos berat bs x kllg x jmh bgl
Bs ø 8 = 0.395 x 0.900 x 355.56 = 126.26 Kg 31.56 KG
126.26 Kg

2 KOLOM PRAKTIS 10/10 - LT. 2 VOLUME = T x JMH 48.00 M1


( Besi 4 Ø 10 ; bg. Ø 6 - 15 ) = 4.00 x 12.00 = 48.00 M1
48.00 M1

3 BALOK LATEI 10/15 - LT. 2 VOLUME = P x JMH 26.40 M1


( Besi 4 Ø 10 ; bg. Ø 6 - 15 ) = 3.00 x 8.00 = 24.00 M1
= 2.40 x 1.00 = 2.40 M1
26.40 M1

II PEK.BETON RINGBALK
1 RINGBALK 10/20 VOL. = P x DIMENSI x JMH 1.65 M3
Bagian Luar 17.00 = 17.00 x 0.10 x 0.20 x 2.00 = 0.68 M3
10.50 = 10.50 x 0.10 x 0.20 x 2.00 = 0.42 M3
Bagian Dalam -
9.00 = 9.00 x 0.10 x 0.20 x 1.00 = - M3
6.00 = 6.00 x 0.10 x 0.20 x 1.00 = 0.12 M3
3.00 = 3.00 x 0.10 x 0.20 x 1.00 = 0.06 M3
melintang 10.50 = 10.50 x 0.10 x 0.20 x 1.00 = 0.21 M3
4.10 = 4.10 x 0.10 x 0.20 x 2.00 = 0.16 M3
1.65 M3
III PEKERJAAN PLESTERAN
1 PLESTERAN BETON P/T x L x JMH 82.72 M2
a. Kolom 25/30 = 4.00 x 1.10 x 17.00 = 74.80 M2
b. Balok Beton Luar 3.00 = 3.00 x 0.30 x 8.00 = 7.20 M2
memanjang 2.40 = 2.40 x 0.30 x 1.00 = 0.72 M2
82.72 M2

IV. PEK. PASANGAN/PLESTERAN


1 PAS. TRASRAM BATA VOL. = PJG x T x JMH 16.44 M2
Memanjang 17.00 = 16.75 x 0.20 x 2.00 = 6.70 M2
9.00 = 9.00 x 0.20 x 2.00 = - M2
6.00 = 6.00 x 0.20 x 1.00 = 1.20 M2
3.00 = 3.00 x 0.20 x 1.00 = 0.60 M2
Melintang 10.50 = 10.50 x 0.20 x 3.00 = 6.30 M2
4.10 = 4.10 x 0.20 x 2.00 = 1.64 M2
16.44 M2

2 PAS. DINDING BATA VOL. = PJG x T x JMH 297.72 M2


Memanjang 17.00 = 17.00 x 3.60 x 2.00 = 122.40 M2
9.00 = 9.00 x 3.60 x 1.00 = - M2
6.00 = 6.00 x 3.60 x 1.00 = 21.60 M2
3.00 = 3.00 x 3.60 x 1.00 = 10.80 M2
Melintang 10.50 = 10.50 x 3.60 x 3.00 = 113.40 M2
4.10 = 4.10 x 3.60 x 2.00 = 29.52 M2
LA 297.72 M2

Lbg kusen = L x T x JMH


1 P1 = 0.90 x 2.60 x 6.00 = 14.04 M2
2 P2/ Pd = 1.40 x 2.60 x 1.00 = 3.64 M2
3 J2 = 1.35 x 1.60 x 6.00 = 12.96 M2
4 V1 = 0.80 x 0.50 x 9.00 = 3.60 M2
LB 34.24 M2
VOL.AKHIR = LA - LB
= 297.72 - 34.24 = 263.48 M2

3 PAS.TRASRAM BATA 1pc : 3psr LA = LUAS x SISI JMH 32.88 M2


= 16.44 x 2.00 x 1.00 = 32.88 M2
32.88 M2

4 PLEST. DINDING BATA Vol = Luas Dinding x Sisi 526.96 M²


= 263.48 x 2.00 = 526.96 M2
Luas Plesteran - L.DIND KRMK
*** VOL. AKHIR = 526.96 - - = 526.96 M2
5 PLEST.BENANGAN/SUDUT VOLUME = P/T x SISI x JMH 256.00 M1
Kolom struktur kolom 25/30 = 4.00 x 4.00 x 16.00 = 256.00 M1
256.00 M1

V PEKERJAAN KERAMIK
1 LANTAI KERAMIK 40 X 40 KW.1 VOL. = P x L x JMH 166.50 M2
= 17.00 x 10.50 x 1.00 - 12.00 = 166.50 M2
166.50 M2

5 Plint Keramik 10 X 40 KW.1 ( Motif ) VOLUME = P x JMH 111.30 M1


Kasi kesra/PMD = 15.20 x 1.00 = 15.20 M1
Darma wanita = 13.30 x 1.00 = 13.30 M1
Persiapan + sound = 18.40 x 1.00 = 18.40 M1
Lorong tangga = 28.70 x 1.00 = 28.70 M1
Rapat = 35.70 x 1.00 = 35.70 M1
111.30 M1

VI PEKERJAAN PLAFOND
1 PLAFOND KALSIBOARD VOL. = P x L x JMH 178.50 M2
Bangunan = 17.00 x 10.50 x 1.00 = 178.50 M2
178.50 M1

2 List. plafond Gipsum - Dalam VOL. = P x JMH 128.40 M1


Kasi kesra/PMD = 26.00 x 1.00 = 26.00 M1
Darma wanita = 14.20 x 1.00 = 14.20 M1
Persiapan + sound = 20.20 x 1.00 = 20.20 M1
Lorong tangga = 31.00 x 1.00 = 31.00 M1
Rapat = 37.00 x 1.00 = 37.00 M1
128.40 M1

3 PLAFOND KALSIBOARD - Luar VOL. = P x L x JMH 75.00 M2


Bangunan = 19.50 x 1.25 x 2.00 = 48.75 M2
= 10.50 x 1.25 x 2.00 = 26.25 M2
75.00 M2

4 List. plafond Gipsum - Luar VOL. = P x JMH 123.00 M1


Pinggir tembok = 18.00 x 2.00 = 36.00 M1
= 11.00 x 2.00 = 22.00 M1
Pinggir lisplank = 19.50 x 2.00 = 39.00 M1
= 13.00 x 2.00 = 26.00 M1
123.00 M1
VII PEK. KUZEN/JENDELA & KACA
1 KUSEN PINTU dan JENDELA VOL. = P x DIMENSI x JMH 0.63 M3
1 KUZEN KAYU 5/13 ( LT. 2 )
P1 = 6.10 x 0.05 x 0.13 x 2.00 = 0.08 M3
P2 = 8.00 x 0.05 x 0.13 x 1.00 = 0.05 M3
PJ2 = 11.00 x 0.05 x 0.13 x 2.00 = 0.14 M3
J2 = 9.05 x 0.05 x 0.13 x 6.00 = 0.35 M3
0.63 M3

2 DAUN JENDELA KACA VOL. = L x T x SISI x JMH 13.41 M2


J2 jendela = 0.62 x 1.22 x 2.00 x 6.00 = 9.08 M2
ventilasi = 0.62 x 0.42 x 2.00 x 6.00 = 3.12 M2
KP2 ventilasi = 0.62 x 0.42 x 2.00 x 1.00 = 0.52 M2
KP1 ventilasi = 0.82 x 0.42 x 1.00 x 2.00 = 0.69 M2
13.41 M2

3 DAUN PINTU PANIL VOL. = L x T x JMH 13.10 M2


P1 = 0.82 x 2.10 x 6.00 = 10.33 M2
P2 = 1.32 x 2.10 x 1.00 = 2.77 M2
13.10 M2

4 KACA BENING 5MM VOL. L T JMH 1.90 M2


P1 = 0.82 x 0.42 x 4.00 = - M2
PJ2 = 0.82 x 0.42 x 2.00 = 0.69 M2
= 1.44 x 0.42 x 2.00 = 1.21 M2
1.90 M2

VII PEKERJAAN PENGUNCI


1 KINCI TANAM VOL. = Masing² x JMH 7.00 Bh
P1 = 1.00 x 6.00 = 6.00 Bh
P2 = 1.00 x 1.00 = 1.00 Bh
7.00 Bh
2 ENGSEL PINTU VOL. = Masing² x JMH 24.00 Bh
P1 = 3.00 x 6.00 = 18.00 Bh
P2 = 6.00 x 1.00 = 6.00 Bh
24.00 Bh

3 ENGSEL JENDELA VOL. = Masing² x JMH 56.00 Bh


J2 jendela = 4.00 x 6.00 = 24.00 Bh
ventilasi = 4.00 x 6.00 = 24.00 Bh
KP2 ventilasi = 4.00 x 1.00 = 4.00 Bh
KP1 ventilasi = 2.00 x 2.00 = 4.00 Bh
56.00 Bh

4 KAIT ANGIN VOL. = Masing² x JMH 56.00 Bh

5 GRENDEL JENDELA VOL. = Masing² x JMH 56.00 Bh

6 Grendel pintu besar Volume = Masing² x JMH 6.00 BH


P1 = 1.00 x 5.00 = 5.00 Bh
Pw = 1.00 x 1.00 = 1.00 Bh
= 6.00 Bh

7 Pas. Angker Kusen Ø 10mm Volume = Masing² x JMH 76.00 BH


P1 = 8.00 x 4.00 = 32.00 Bh
P2 = 8.00 x 1.00 = 8.00 Bh
J2 = 6.00 x 6.00 = 36.00 Bh
= 76.00 BH

IX PEKERJAAN PARTISI
1 PARTISI RANGKA KAYU VOL. = P x T x JMH 25.31 M2
PR 5 = 4.00 x 2.10 x 1.00 = 8.40 M2
PR 6 = 3.54 x 2.10 x 2.00 = 14.87 M2
= 0.31 x 3.30 x 2.00 = 2.05 M2
25.31 M2

2 KUSEN KAYU PARTISI VOL. = P x DIMENSI x JMH 0.30 M3


PR5 = 12.80 x 0.05 x 0.12 x 1.00 = 0.08 M3
PR6 = 18.46 x 0.05 x 0.12 x 2.00 = 0.22 M3
0.30 M3

3 KACA BENING 5MM VOL. = P x T x JMH 13.13 M2


PR5 = 3.80 x 1.12 x 1.00 = 4.26 M2
PR6 = 3.96 x 1.12 x 2.00 = 8.87 M2
13.13 M2

4 PLINT PAPAN 2,5/15 VOL. = P x SISI x JMH 22.16 M1


PR5 = 4.00 x 2.00 x 1.00 = 8.00 M1
PR6 = 3.54 x 2.00 x 2.00 = 14.16 M1
22.16 M1
VIII PEKERJAAN INST. LISTRIK
II LANTAI II ( Dua )
1 Instalasi Titik lampu & Instalasi = 165.00 x 1.00 = 165.00 Ttk
2 Lampu Downlight 15 wat = 124.00 x 1.00 = 124.00 Bh
3 Lampu SL 15 wat = 14.00 x 1.00 = 14.00 Bh
4 Lampu Baret = 4.00 x 1.00 = 4.00 Bh
5 Continues Light = 74.50 = 74.50 M1
6 Saklar tunggal = 23.00 x 1.00 = 23.00 Bh
7 Saklar Ganda = 24.00 x 1.00 = 24.00 Bh
8 Stop kontak = 23.00 x 1.00 = 23.00 Ttk
9 Zekering Box = 1.00 x 1.00 = 1.00 Unit

IX PEKERJAAN SANITASI
SANITAIR Volume = JMH JMH
1 Closed Duduk Monoblok = 1.00 x 1.00 = 1.00 Bh
2 Floor drain /saringan air = 1.00 x 1.00 = 1.00 Bh 1.00 Bh
3 Kran air Ø 1/2" = 1.00 x 1.00 = 1.00 Bh 1.00 Bh
4 Kran Closet Ø 1/2" = 1.00 x 1.00 = 1.00 Bh
5 Kran bebekan Ø 1/2" = 1.00 x 1.00 = 1.00 Bh
6 Bak stainless = 1.00 x 1.00 = 1.00 Bh

PLUMBING/PIPA
1 Masang Pipa PVC Ø 1/2 " PJG x JMH 210.00 M1
closet = 1.50 x 20.00 = 30.00 M1
washtafle = 1.50 x 20.00 = 30.00 M1
handsower = 1.50 x 20.00 = 30.00 M1
samb. = 4.00 x 20.00 = 80.00 M1
= 2.00 x 20.00 = 40.00 M1
210.00 M1

2 Masang Pipa PVC Ø 3/4 " PJG x JMH 74.00 M1


Dari lantai 2 ke lt. 1 Shaf = 5.00 x 10.00 = 50.00 M1
samb. = 12.00 x 2.00 = 24.00 M1
74.00 M1

3 Masang Pipa PVC Ø 2 " PJG x JMH 150.00 M1


washtafle = 4.00 x 20.00 = 80.00 M1
samb. = 1.00 x 20.00 = 20.00 M1
Dari lantai 2 ke lt. 1 = 5.00 x 10.00 = 50.00 M1
150.00 M1

4 Masang Pipa PVC Ø 3 " PJG x JMH 109.00 M1


= 4.00 x 6.00 = 24.00 M1
= 10.00 x 2.00 = 20.00 M1
= 1.00 x 10.00 = 10.00 M1
Dari Lt. 2 Ke Lt. 1 = 5.50 x 10.00 = 55.00 M1
109.00 M1

5 Masang Pipa PVC Ø 4 " - Dari closet PJG x JMH 103.80 M1


= 5.80 x 2.00 = 11.60 M1
= 2.20 x 1.00 = 2.20 M1
= 20.00 x 1.00 = 20.00 M1
= 15.00 x 1.00 = 15.00 M1
Dari Lt. 2 Ke Lt. 1 = 5.50 x 10.00 = 55.00 M1
103.80 M1
3 Masang Pipa GI Ø 3/4 " - LT.II P/T x JMH 194.00 M1
Pipa kloset 1 = 1.50 x 20.00 = 30.00 M1
Pipa wastafle 2 = 1.50 x 20.00 = 30.00 M1
Handsower 3 = 1.50 x 20.00 = 30.00 M1
Samb.dari shaf 4 = 4.00 x 6.00 = 24.00 M1
5 = 10.00 x 2.00 = 20.00 M1
6 = 2.00 x 20.00 = 40.00 M1
7 = 1.00 x 20.00 = 20.00 M1
194.00 M1

Dari lantai I - Ke Lt.II 8 = 4.50 x 10.00 = 45.00 M1


45.00 M1

14 Masang Pipa PVC Ø 2 " - LT.II P/T x JMH 90.00 M1


Dari washtafle ke shaf 1 = 2.50 x 20.00 = 50.00 M1
Dari lantai I - Ke Lt.II 2 = 4.00 x 10.00 = 40.00 M1
90.00 M1

15 Pemasangan Pipa PVC Ø 4 " P x SISI x JMH 156.00 M1


( PEMBUANGAN AIR HUJAN ) belakang = 6.00 x 8.00 x 1.00 = 48.00 M1
depan = 6.00 x 8.00 x 1.00 = 48.00 M1
Jalur shaf = 6.00 x 10.00 x 1.00 = 60.00 M1
156.00 M1

16 Saringan air PVC Ø 4 " P x SISI x JMH 42.00 Bh


( PEMBUANGAN AIR HUJAN ) Jalur pinggir = 1.00 x 11.00 x 2.00 = 22.00 Bh
= 1.00 x 5.00 x 2.00 = 10.00 Bh
Jalur shaf = 1.00 x 10.00 x 1.00 = 10.00 Bh
42.00 Bh

X PEKERJAAN PENGECATAN
1 Pengecatan Kayu 60.29 M2
A KUSEN PINTU/JENDELA Volume = P x kllg x JMH
A Kusen pintu jendela
KP1 kusen = 5.80 x 0.23 x 4.00 = 5.34 M2
= 0.80 x 0.36 x 4.00 = 1.15 M2
KP2 kusen = 6.30 x 0.23 x 1.00 = 1.45 M2
= 1.70 x 0.36 x 1.00 = 0.61 M2
ventilasi = 3.96 x 0.22 x 1.00 = 0.87 M2
KPJ2 kusen = 8.85 x 0.23 x 2.00 = 4.07 M2
= 1.20 x 0.36 x 2.00 = 0.86 M2
KJ2 kusen = 5.70 x 0.23 x 6.00 = 7.87 M2
= 2.65 x 0.36 x 6.00 = 5.72 M2
jendela = 4.30 x 0.22 x 12.00 = 11.35 M2
ventilasi = 2.60 x 0.22 x 12.00 = 6.86 M2
B Kusen Partisi -
PR5 kusen = 10.20 x 0.23 x 1.00 = 2.35 M2
= 4.40 x 0.34 x 1.00 = 1.50 M2
PR6 kusen = 9.66 x 0.23 x 2.00 = 4.44 M2
= 8.60 x 0.34 x 2.00 = 5.85 M2
60.29 M2

3 CAT DINDING ( Dalam ) VOL. = P.Kllg x T x JMH


R.Kasi = 26.00 x 3.30 x 1.00 = 85.80 M2 391.74 M2
Darma wanita = 14.20 x 3.30 x 1.00 = 46.86 M2
Persiapan + Sound = 20.20 x 3.30 x 1.00 = 66.66 M2
Lorong tangga = 31.00 x 3.30 x 1.00 = 102.30 M2
Rapat = 37.00 x 3.30 x 1.00 = 122.10 M2
423.72 M2

Lbng kusen = L x T x JMH


1 P1 = 0.90 x 2.60 x 4.00 = 9.36 M2
2 P2a = 0.90 x 2.60 x 2.00 = 4.68 M2
= 1.60 x 0.50 x 2.00 = 1.60 M2
3 Pd = 1.30 x 2.60 x 1.00 = 3.38 M2
4 J2 = 1.35 x 1.60 x 6.00 = 12.96 M2
31.98 M2
VOL.AKHIR = LA - LB
= 423.72 - 31.98 = 391.74 M2
4 CAT DINDING (Luar) Volume = P.Kllg x T x SISI 197.04 M2
17.25 = 17.25 x 3.75 x 2.00 = 129.38 M2
10.75 = 10.75 x 3.75 x 2.00 = 80.63 M2
210.00 M2

Lobang kusen = L x T x JMH


1 J2 = 1.35 x 1.60 x 6.00 = 12.96 M2
12.96 M2
VOL.AKHIR = LA - LB
= 210.00 - 12.96 = 197.04 M2
BACK UP VOLUME
LANTAI 1
PEKERJAAN #REF!
LOKASI #REF!
TAHUN #REF!

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME


1 2 3 4

I LUAS BANGUNAN
1 LUAS BANGUNAN VOL. = P x L x JMH 13.50 M2
SELASAR plat = 3.00 x 3.00 x 0.50 = 4.50 M2
= 2.00 x 6.00 x 0.50 = 6.00 M2
= 3.00 x 2.00 x 0.50 = 3.00 M2
13.50 M2

II PEKERJAAN TANAH
1 GALIAN PONDASI VOL. = P x L x T x JMH 20.70 M3
memanjang 3.00 = 3.00 x 0.90 x 1.00 x 1.00 = 2.70 M3
melintang 2.00 = 2.00 x 0.90 x 1.00 x 1.00 = 1.80 M3
selasar = 3.00 x 0.90 x 1.00 x 6.00 = 16.20 M3
20.70 M3

2 PASIR URUG PONDASI VOL. = P x L x T x JMH 2.07 M3


memanjang 3.00 = 3.00 x 0.90 x 0.10 x 1.00 = 0.27 M3
melintang 2.00 = 2.00 x 0.90 x 0.10 x 1.00 = 0.18 M3
selasar = 3.00 x 0.90 x 0.10 x 6.00 = 1.62 M3
2.07 M3

3 PASIR URUG BWH LANTAI VOL. = P x L x T x JMH 2.70 M3


= 3.00 x 2.00 x 0.10 x 1.00 = 0.60 M3
= 3.00 x 3.00 x 0.10 x 1.00 = 0.90 M3
= 2.00 x 6.00 x 0.10 x 1.00 = 1.20 M3
2.70 M3

4 TANAH URUG BWH LANTAI VOL. = P x L x T x JMH 5.67 M3


= 3.00 x 2.00 x 0.21 x 1.00 = 1.26 M3
= 3.00 x 3.00 x 0.21 x 1.00 = 1.89 M3
= 2.00 x 6.00 x 0.21 x 1.00 = 2.52 M3
5.67 M3

II PEKERJAAN PONDASI
1 BATU KOSONG VOL. = P x L x T x JMH 0.90 M3
memanjang 3.00 = 3.00 x 0.90 x 0.20 x 1.00 = 0.54 M3
melintang 2.00 = 2.00 x 0.90 x 0.20 x 1.00 = 0.36 M3
selasar = 3.00 x 0.90 x 0.20 x 6.00 = 3.24 M3
0.90 M3

2 PONDASI BATU KALI VOL. = P x L x T x JMH 7.65 M3


memanjang 3.00 = 3.00 x 0.48 x 0.70 x 1.00 = 1.00 M3
melintang 2.00 = 2.00 x 0.48 x 0.70 x 1.00 = 0.67 M3
selasar = 3.00 x 0.48 x 0.70 x 6.00 = 5.99 M3
7.65 M3
II PEKERJAAN BETON
1 BETON RABAT BWH LANTAI VOL. = P x L x T x JMH 1.35 M3
= 3.00 x 2.00 x 0.05 x 1.00 = 0.30 M3
= 3.00 x 3.00 x 0.05 x 1.00 = 0.45 M3
= 2.00 x 6.00 x 0.05 x 1.00 = 0.60 M3
1.35 M3

2 SLOOF 15/20 VOL. = P x L x T x JMH 0.99 M3


memanjang 3.00 = 3.00 x 0.15 x 0.20 x 3.00 = 0.27 M3
2.00 = 2.00 x 0.15 x 0.20 x 2.00 = 0.12 M3
melintang 2.00 = 2.00 x 0.15 x 0.20 x 1.00 = 0.06 M3
3.00 = 3.00 x 0.15 x 0.20 x 6.00 = 0.54 M3
0.99 M3

3 KOLOM PLAT DAK 20/20 - type B VOL. = T x L x T x JMH 1.24 M3


dibawah lantai = 0.70 x 0.20 x 0.20 x 9.00 = 0.25 M3
diatas lantai = 2.75 x 0.20 x 0.20 x 9.00 = 0.99 M3
1.24 M3

Begisting = 0.20 + 0.20 x 2.00 x 31.05 = 24.84 M2 20.00 M2/M3

Pembesian 6Ø12mm = 0.89 x 6.00 x 31.05 = 165.39 Kg 179.20 Kg/M3


bgØ8-15 = 0.39 x 0.70 x 207.00 = 57.17 Kg
222.56 Kg

II BETON DAK
1 BALOK 15/20 VOL. = P x L x T x JMH 0.24 M3
memanjang = 2.00 x 0.15 x 0.20 x 2.00 = 0.12 M3
melintang = 2.00 x 0.15 x 0.20 x 2.00 = 0.12 M3
0.24 M3

2 BALOK 15/25 VOL. = P x L x T x JMH 0.45 M3


memanjang = 3.00 x 0.15 x 0.25 x 4.00 = 0.45 M3
melintang = 3.00 x 0.15 x 0.25 x 6.00 = 0.68 M3
0.45 M3

Begisting = 0.15 + 0.20 x 1.00 x 12.00 = 4.20 M2 9.33 M2/M3

Pembesian 6Ø12mm = 0.89 x 6.00 x 12.00 = 63.92 Kg 191.14 Kg/M3


bgØ8-15 = 0.39 x 0.70 x 80.00 = 22.10 Kg
86.01 Kg

3 PLAT DAK T. 10CM VOL. = P x L x T x JMH 4.28 M3


= 3.50 x 3.00 x 0.10 x 1.00 = 1.05 M3
= 3.00 x 3.50 x 0.10 x 1.00 = 1.05 M3
= 3.00 x 3.00 x 0.10 x 1.00 = 0.90 M3
= 4.00 x 3.00 x 0.10 x 1.00 = 1.20 M3
= 0.50 x 1.50 x 0.10 x 1.00 = 0.08 M3
4.28 M3

4 LISPLANK t.30CM VOL. = P x L x T x JMH 0.63 M3


memanjang = 11.00 x 0.30 x 0.06 x 1.00 = 0.20 M3
melintang = 24.00 x 0.30 x 0.06 x 1.00 = 0.43 M3
0.63 M3
I PEKERJAAN PASANGAN/PLEST.
1 Trasram Bata 1/2 bt VOL. = P x T x SISI 7.90 M2
memanjang 3.00 = 3.00 x 0.30 x 2.00 = 1.80 M2
1.00 = 1.00 x 0.30 x 1.00 = 0.30 M2
2.00 = 2.00 x 0.20 x 1.00 = 0.40 M2
melintang 3.00 = 3.00 x 0.30 x 6.00 = 5.40 M2
7.90 M2

2 Plest.Trasram Bata VOL. = LUAS x SISI 15.80 M2


= 7.90 X 2.00 = 15.80 M2
15.80 M2

5 Plesteran Beton VOL. = P x kllg x SISI 45.75 M2


kolom 20/20 = 2.65 x 0.80 x 9.00 = 19.08 M2
Balok dak blk 15/20 = 1.80 x 0.33 x 3.00 = 1.78 M2
blk 15/25 = 2.80 x 0.33 x 8.00 = 7.39 M2
lisplank 1 = 11.00 x 0.50 x 1.00 = 5.50 M2
lisplank 2 = 24.00 x 0.50 x 1.00 = 12.00 M2
45.75 M2

6 Plesteran Benangan VOL. = T x SISI x JMH 256.00 M1


kolom 20/20 = 2.65 x 4.00 x 9.00 = 95.40 M1
Balok dak blk 15/20 = 1.80 x 2.00 x 3.00 = 10.80 M1
blk 15/25 = 2.80 x 2.00 x 8.00 = 44.80 M1
lisplank 1 = 11.00 x 3.00 x 1.00 = 33.00 M1
lisplank 2 = 24.00 x 3.00 x 1.00 = 72.00 M1
256.00 M1
IV PEKERJAAN KERAMIK
1 LANTAI KERAMIK 40X40CM VOL. = P x L x JMH 27.00 M2
Dalam Ruang RAM = 3.00 x 2.00 x 1.00 = 6.00 M2
= 3.00 x 3.00 x 1.00 = 9.00 M2
= 2.00 x 6.00 x 1.00 = 12.00 M2
27.00 M2
IV PEKERJAAN PLAFOND
1 PLAFOND KALSIBOARD - DALAM VOL. = P x L x JMH 168.00 M2
Dalam Ruang = 42.00 x 4.00 x 1.00 = 168.00 M2
168.00 M2

2 PLAFOND KALSIBOARD - LUAR VOL. = P x L x JMH 184.00 M2


Selasar = 42.00 x 2.00 x 1.00 = 84.00 M2
Overstek belakang = 42.00 x 1.00 x 1.00 = 42.00 M2
depan = 42.00 x 1.00 x 1.00 = 42.00 M2
samping = 8.00 x 1.00 x 2.00 = 16.00 M2
184.00 M2

3 LISTPLAFOND GYPSUM - DALAM VOL. = P x JMH 193.00 M1


Irna = 29.00 x 3.00 = 87.00 M1
Linen alat = 10.00 x 1.00 = 10.00 M1
R.Jaga = 17.00 x 1.00 = 17.00 M1
km/wc = 7.00 x 6.00 = 42.00 M1
Lorong wc = 11.00 x 1.00 = 11.00 M1
Lorong linen = 10.00 x 1.00 = 10.00 M1
Lorong Irna = 8.00 x 2.00 = 16.00 M1
193.00 M1

4 LISTPLAFOND GYPSUM - LUAR VOL. = P x JMH 185.00 M1


PINGGIR TEMBOK Selasar = 88.00 x 1.00 = 88.00 M1
belakang = 42.00 x 1.00 = 42.00 M1
depan = 42.00 x 1.00 = 42.00 M1
samping = 6.50 x 2.00 = 13.00 M1
185.00 M1

5 LISTPLAFOND GYPSUM - LUAR VOL. = P x JMH 103.00 M1


PINGGIR LISPLANK depan/blkng = 44.00 x 2.00 = 88.00 M1
samping = 7.50 x 2.00 = 15.00 M1
103.00 M1
III PEKERJAAN KUSEN KAYU
1 KUSEN ALUMINIUM VOL. = P x JMH 346.80 M1
P1 = 6.72 x 2.00 = 13.44 M1
Pw = 4.86 x 6.00 = 29.16 M1
PJ1 = 14.68 x 3.00 = 44.04 M1
J3 = 11.96 x 18.00 = 215.28 M1
V1 = 4.08 x 11.00 = 44.88 M1
346.80 M1

2 KACA MATI 5MM VOL. = L x T x JMH 6.82 M2


J3 = 0.62 x 1.02 x 18.00 = 11.38 M2
V1 = 1.24 x 0.50 x 11.00 = 6.82 M2
6.82 M2

3 DAUN JENDELA KACA/VENT. VOL. = L x T x JMH 40.31 M2


J3 ventilasi = 0.60 x 0.40 x 54.00 = 12.96 M2
jendela = 0.60 x 1.00 x 36.00 = 21.60 M2
P1 ventilasi = 0.80 x 0.40 x 2.00 = 0.64 M2
PJ1 jendela = 0.60 x 1.00 x 6.00 = 3.60 M2
ventilasi = 1.26 x 0.40 x 3.00 = 1.51 M2
40.31 M2

5 DAUN PINTU KACA RANGKA ALUM. VOL. = L x T x JMH 11.00 M2


PDj = 1.30 x 2.00 x 3.00 = 7.80 M2
P1 = 0.80 x 2.00 x 2.00 = 3.20 M2
11.00 M2

6 DAUN PINTU WC VOL. = L x T x JMH 8.61 M2


PW = 0.70 x 2.05 x 6.00 = 8.61 M2
8.61 M2

IV PEKERJAAN BESI
1 ENGSEL PINTU VOL. = MASING 2 x JMH 42.00 BH
PDJ = 6.00 x 3.00 = 18.00 BH
P1 = 3.00 x 2.00 = 6.00 BH
Pw = 3.00 x 6.00 = 18.00 BH
42.00 BH

2 ENGSEL JENDELA VOL. = MASING 2 x JMH 220.00 BH


J3 ventilasi = 6.00 x 18.00 = 108.00 BH
jendela = 4.00 x 18.00 = 72.00 BH
p1 ventilasi = 2.00 x 2.00 = 4.00 BH
PJ1 jendela = 4.00 x 3.00 = 12.00 BH
ventilasi = 8.00 x 3.00 = 24.00 BH
220.00 BH

3 KUNCI TANAM VOL. = MASING 2 x JMH 5.00 BH


PDJ = 1.00 x 3.00 = 3.00 BH
p1 = 1.00 x 2.00 = 2.00 BH
5.00 BH

4 KUNCI TANAM wc VOL. = MASING 2 x JMH 6.00 BH


PD = 1.00 x 6.00 = 6.00 BH
6.00 BH
V PEKERJAAN PENGECATAN
1 CAT DINDING (Dalam) - BARU Luas = P x T x JMH 430.19 M2
A IRNA = 29.00 x 3.50 x 3.00 = 304.50 M2
LINEN = 10.00 x 3.50 x 1.00 = 35.00 M2
K.JAGA = 17.00 x 3.50 x 1.00 = 59.50 M2
= 4.00 x 3.50 x 1.00 = 14.00 M2
km/wc = 7.00 x 1.90 x 6.00 = 79.80 M2
LORONG = 8.00 x 3.50 x 1.00 = 28.00 M2
A 520.80 M2

B
Lbg kusen = L x T x JMH
J3 = 1.96 x 1.52 x 18.00 = 53.63 M2
V = 1.32 x 0.48 x 11.00 = 6.97 M2
p1 = 0.88 x 2.48 x 2.00 = 4.36 M2
Pw = 0.78 x 2.04 x 6.00 = 9.55 M2
PJ1 = 1.38 x 2.48 x 3.00 = 10.27 M2
= 1.28 x 1.52 x 3.00 = 5.84 M2
B 90.61 M2

VOL.AKHIR = A - B
= 520.80 - 90.61 = 430.19 M2

3 CAT DINDING (Luar) - BARU Luas = P x T x JMH 430.07 M2


A belakng = 42.00 x 3.80 x 1.00 = 159.60 M2
samping = 4.00 x 3.80 x 2.00 = 30.40 M2
= 2.00 x 1.00 x 2.00 = 4.00 M2
Gv = 6.00 x 2.10 x 1.00 = 12.60 M2
depan = 46.00 x 3.80 x 1.00 = 174.80 M2
Diatas balok gantung 2.00 = 2.00 x 1.00 x 2.00 = 4.00 M2
42.00 = 42.00 x 1.63 x 1.00 = 68.46 M2
Kolom = 2.65 x 0.92 x 15.00 = 36.57 M2
= 2.50 x 0.92 x 9.00 = 20.70 M2
A 511.13 M2

B
Lbg kusen = L x T x JMH
J3 = 1.96 x 1.52 x 18.00 = 53.63 M2
V = 1.32 x 0.48 x 11.00 = 6.97 M2
p1 = 0.88 x 2.48 x 2.00 = 4.36 M2
PJ1 = 1.38 x 2.48 x 3.00 = 10.27 M2
= 1.28 x 1.52 x 3.00 = 5.84 M2
B 81.06 M2
VOL.AKHIR = A - B
= 511.13 - 81.06 = 430.07 M2
I PEKERJAAN ATAP
1 ATAP GENTENG VOL. = P x L x SISI 467.25 M2
TRAVESIUM (36+44,5)/2 = 40.25 x 5.25 x 2.00 = 422.63 M2
SEGITIGA 1 = 8.50 x 5.25 x 1.00 = 44.63 M2
467.25 M2

2 BUBUNGAN VOL. = P x JMH 63.00 M1


NOK = 36.00 x 1.00 = 36.00 M1
JURAI = 6.75 x 4.00 = 27.00 M1
63.00 M1

3 LISPLANK KALSIPLANK VOL. = P x JMH 108.00 M1


= 45.00 x 2.00 = 90.00 M1
= 9.00 x 2.00 = 18.00 M1
108.00 M1

3 GORDING 8/12 VOL. = P x DIMENSI x JMH 0.35 M3


murplat = 11.00 x 0.08 x 0.12 x 1.00 = 0.11 M3
gording = 11.00 x 0.08 x 0.12 x 2.00 = 0.21 M3
kayu talang = 1.20 x 0.06 x 0.12 x 4.00 = 0.03 M3
0.35 M3

4 KAP KD-KD 8/12 VOL. = P x DIMENSI x JMH 0.24 M3


blk tarik = 4.83 x 0.08 x 0.12 x 2.00 = 0.09 M3
kaki kd-kd = 5.00 x 0.08 x 0.12 x 2.00 = 0.10 M3
skur = 2.50 x 0.08 x 0.12 x 2.00 = 0.05 M3
0.24 M3

C DINDING TEAKBLOK
KEB. TEAKBLOK VOL. = P x L x JMH 3.10 M2
Meja Meja = 1.00 x 0.43 x 1.00 = 0.43 M2 1.07 Lbr
bok bawah = 0.90 x 0.20 x 2.00 = 0.36 M2
= 0.25 x 0.20 x 2.00 = 0.10 M2
Tiang = 1.00 x 0.20 x 2.00 = 0.40 M2
Bok atas ambang = 1.00 x 0.43 x 1.00 = 0.43 M2
bok = 0.90 x 0.50 x 2.00 = 0.90 M2
= 0.90 x 0.25 x 1.00 = 0.23 M2
= 0.25 x 0.50 x 2.00 = 0.25 M2
3.10 M2

KEB. TEAKBLOK VOL. = P x L x JMH 2.87 M2


Meja Meja = 1.00 x 0.43 x 1.00 = 0.43 M2 0.99 Lbr
bok bawah = 0.90 x 0.20 x 1.00 = 0.18 M2
= 0.25 x 0.20 x 2.00 = 0.10 M2
Tiang = 1.00 x 0.20 x 4.00 = 0.80 M2
Bok atas ambang = 1.00 x 0.43 x 1.00 = 0.43 M2
bok = 0.90 x 0.50 x 1.00 = 0.45 M2
= 0.90 x 0.25 x 1.00 = 0.23 M2
= 0.25 x 0.50 x 2.00 = 0.25 M2
2.87 M2
10 Pembuatan bak kontrol Volume = JMH 27.00 unit
27.00 = 27.00 unit
BACK UP VOLUME
LANTAI 1
PEKERJAAN #REF!
LOKASI #REF!
TAHUN #REF!

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME


1 2 3 4

I LUAS BANGUNAN
1 LUAS BANGUNAN VOL. = P x L x JMH 113.16 M2
DALAM = 16.40 x 6.90 x 1.00 = 113.16 M2 113.16
113.16 M2 113.16

II PEKERJAAN TANAH
1 PASIR URUG PERATAAN LANTAI VOL. = LUAS x T 6.79 M3
= 113.16 x 0.06 = 6.79 M3
6.79 M3

IV PEKERJAAN BETON
1 KOLOM 10/10 VOL. = T x JMH 129.80 M1
1 = 5.00 x 18.00 = 90.00 M1
2 = 1.50 x 2.00 = 3.00 M1
3 = 3.50 x 4.00 = 14.00 M1
4 = 4.56 x 5.00 = 22.80 M1
129.80 M1

2 BALOK LATEI 10/15 - diatas kusen VOL. = P x JMH 76.50 M1


Balok diatas kusen
Jendela J2a = 2.00 x 2.00 = 4.00 M1
J2b = 2.00 x 1.00 = 2.00 M1
J2c = 2.00 x 2.00 = 4.00 M1
J3 = 3.00 x 1.00 = 3.00 M1
= 2.50 x 1.00 = 2.50 M1
V1 = 1.00 x 3.00 = 3.00 M1
J = 1.50 x 2.00 = 3.00 M1
Pintu P1 = 1.00 x 1.00 = 1.00 M1
PD = 2.00 x 2.00 = 4.00 M1
B.ksng = 1.00 x 1.00 = 1.00 M1
Pw = 1.00 x 2.00 = 2.00 M1
Balok latei manjang = 4.00 x 1.00 = 4.00 M1
= 8.50 x 1.00 = 8.50 M1
= 7.50 x 1.00 = 7.50 M1
= 3.00 x 1.00 = 3.00 M1
lintang = 1.00 x 1.00 = 1.00 M1
= 3.00 x 1.00 = 3.00 M1
= 4.00 x 1.00 = 4.00 M1
= 6.00 x 1.00 = 6.00 M1
= 5.00 x 2.00 = 10.00 M1
76.50 M1

3 KOLOM BETON 25/25 - K2 VOL. = T x L x T x JMH 0.38 M3


diatas lantai 3.00 = 3.00 x 0.25 x 0.25 x 2.00 = 0.38 M3
0.38 M3

4 KOLOM BETON 25/25 - K3 VOL. = T x L x T x JMH 3.75 M3


diatas lantai 5.00 = 5.00 x 0.25 x 0.25 x 12.00 = 3.75 M3
3.75 M3

Begisting = 0.25 + 0.25 x 2.00 x 60.00 = 60.00 M2 16.00 M2/M3

Pembesian 8 D 16mm = 1.58 x 4.00 x 60.00 = 378.78 Kg 101.01 Kg/M3

bg. Ø8-15 = 0.39 x 0.90 x 400.00 = 142.04 Kg 37.88 Kg/M3


142.04 Kg
5 PENEBALAN KOLOM SIRIF 10/28 VOL. = T x L x T x JMH 0.28 M3
diatas lantai 2.25 = 2.25 x 0.10 x 0.18 x 7.00 = 0.28 M3
0.28 M3

Begisting = 0.10 + 0.28 x 2.00 x 10.13 = 7.70 M2 27.14 M2/M3

Pembesian 6 Ø 10mm = 0.62 x 6.00 x 10.13 = 37.45 Kg 174.38 Kg/M3


bg. Ø6-15 = 0.22 x 0.80 x 67.50 = 11.98 Kg
49.44 Kg

6 PLAT SUNSCREN T. 8CM VOL. = P x L x T x JMH 0.29 M3


DIATAS KUSEN
J2a = 2.00 x 0.40 x 0.08 x 2.00 = 0.13 M3
J2b = 2.00 x 0.40 x 0.08 x 1.00 = 0.06 M3
V1 = 1.00 x 0.40 x 0.08 x 3.00 = 0.10 M3
0.29 M3

7 PLAT SUNSCREN T. 8CM VOL. = P x L x T x JMH 0.39 M3


KUSEN depan
J = 6.08 x 0.40 x 0.08 x 2.00 = 0.39 M3
0.39 M3

BETON DAK - DEPAN


1 BALOK BETON 10/20 VOL. = P x L x T x JMH 0.51 M3
melintang 10.50 = 10.25 x 0.10 x 0.25 x 2.00 = 0.51 M3
1 0.51 M3

Begisting = 0.20 + 0.20 x 1.00 x 25.63 = 10.25 M2 20.00 M2/M3

Pembesian = Brat Bs x P.Bs x Jmh Bs x JMH


4 Ø 12mm = 0.89 x 10.50 x 4.00 x 2.00 = 74.57 Kg 224.42 Kg/M3
bg. Ø8-15 = 0.39 x 0.60 x 170.83 = 40.44 Kg
115.01 Kg

1A BALOK BETON 10/20 VOL. = P x L x T x JMH 0.06 M3


melintang 0.74 = 0.74 x 0.10 x 0.20 x 4.00 = 0.06 M3
1A 0.06 M3

2 PLAT DAK T. 10CM VOL. = P x L x T x JMH 1.05 M3


Dalam 1050X100 = 10.50 x 1.00 x 0.10 x 1.00 = 1.05 M3 10.50
1.05 M3 10.50

Pembesian = Luas Plat x Brat Bs x Jmh Bs/M2 x SISI


= 10.50 x 0.39 x 10.00 x 2.00 = 82.86 Kg 78.91 KG/M3
BETON SHAF
1 BALOK BETON 10/20 VOL. = P x L x T x JMH 0.07 M3
memanjang 3.70 = 3.70 x 0.10 x 0.20 x 1.00 = 0.07 M3
0.07 M3

2 PLAT TANGGA T. 10CM VOL. = P x L x T x JMH 0.09 M3


= 0.70 x 1.30 x 0.10 x 1.00 = 0.09 M3 0.91
0.09 M3 0.91

BETON DAK - TANGGA + 7.00


1 BALOK BETON 20/30 VOL. = P x L x T x JMH 0.72 M3
memanjang 3.00 = 2.75 x 0.20 x 0.30 x 2.00 = 0.33 M3
melintang 3.50 = 3.25 x 0.20 x 0.30 x 2.00 = 0.39 M3
0.72 M3

2 BALOK BETON 20/30 - Ks VOL. = P x L x T x JMH 0.30 M3


memanjang 0.50 = 0.50 x 0.20 x 0.30 x 4.00 = 0.12 M3
melintang 1.50 = 1.50 x 0.20 x 0.30 x 2.00 = 0.18 M3
0.30 M3

3 PLAT DAK T. 12CM VOL. = P x L x T x JMH 1.86 M3


Dalam 300X350 = 2.80 x 2.80 x 0.12 x 1.00 = 0.94 M3 10.50
Overstek 300X150 = 2.80 x 1.40 x 0.12 x 1.00 = 0.47 M3 4.50
50X150 = 0.40 x 1.40 x 0.12 x 2.00 = 0.13 M3 1.50
50X350 = 0.40 x 3.30 x 0.12 x 2.00 = 0.32 M3 3.50
1.86 M3 20.00

Pembesian = Luas Plat x Brat Bs x Jmh Bs/M2 x SISI


Bawah = 20.00 x 0.62 x 6.67 x 2.00 = 164.40 Kg 144.77 KG/M3
atas = 20.00 x 0.39 x 6.67 x 2.00 = 105.22 Kg
269.62 KG

IV BETON RINGBALK +
1 BALOK BETON 10/20 VOL. = P x L x T x JMH 1.82 M3
memanjang 16.50 = 16.50 x 0.10 x 0.20 x 2.00 = 0.66 M3 33.00
11.50 = 11.50 x 0.10 x 0.20 x 1.00 = 0.23 M3 11.50
3.00 = 3.00 x 0.10 x 0.20 x 2.00 = 0.12 M3 6.00
melintang 7.00 = 7.00 x 0.10 x 0.20 x 3.00 = 0.42 M3 21.00
3.00 = 3.00 x 0.10 x 0.20 x 2.00 = 0.12 M3 6.00
4.00 = 4.00 x 0.10 x 0.20 x 1.00 = 0.08 M3 4.00
ditangga 4.85 = 4.85 x 0.10 x 0.20 x 2.00 = 0.19 M3 9.70
1.82 M3 91.20

Begisting = 0.20 + 0.20 x 1.00 x 91.20 = 36.48 M2 20.00 M2/M3

Pembesian = Brat Bs x P.Bs x Jmh Bs x JMH


4 Ø 12mm = 0.89 x 91.20 x 4.00 x 1.00 = 323.85 Kg
bg. Ø6-15 = 0.22 x 0.60 x 608.00 = 80.96 Kg 221.94 Kg/M3
404.82 Kg

V PEKERJAAN PASANGAN/PLEST.
1 Trasram Bata 1/2 bt VOL. = P x T x SISI 15.84 M2
memanjang 3.00 = 2.75 x 0.20 x 4.00 = 2.20 M2
3.00 = 3.00 x 0.20 x 1.00 = 0.60 M2
4.00 = 3.75 x 0.20 x 4.00 = 3.00 M2
2.50 = 2.25 x 0.20 x 1.00 = 0.45 M2
11.50 = 10.50 x 0.20 x 1.00 = 2.10 M2
Diatas plat dak 10.50 = 10.50 x 0.20 x 1.00 = 2.10 M2
melintang 7.00 = 6.75 x 0.20 x 3.00 = 4.05 M2
3.00 = 3.00 x 0.20 x 1.00 = 0.60 M2
3.00 = 2.00 x 0.20 x 1.00 = 0.40 M2
0.85 = 0.85 x 0.20 x 2.00 = 0.34 M2
15.84 M2
2 Dinding Bata 1/2 bt - T.500 M VOL. = P x T x JMH 351.27 M2
memanjang 3.00 = 2.75 x 4.70 x 4.00 = 51.70 M2
3.00 = 3.00 x 4.70 x 1.00 = 14.10 M2
4.00 = 3.75 x 4.70 x 4.00 = 70.50 M2
2.50 = 2.25 x 4.70 x 2.00 = 21.15 M2
11.50 = 11.25 x 4.70 x 1.00 = 52.88 M2
ralling 1.50 = 1.50 x 1.00 x 1.00 = 1.50 M2
depan - diatas dak beton 10.50 = 10.50 x 4.16 x 1.00 = 43.68 M2
melintang 7.00 = 6.75 x 4.70 x 2.00 = 63.45 M2
7.00 = 7.00 x 4.70 x 1.00 = 32.90 M2
3.00 = 3.00 x 4.70 x 2.00 = 28.20 M2
4.00 = 4.00 x 4.70 x 1.00 = 18.80 M2
depan - diatas dak beton 0.74 = 0.74 x 4.16 x 2.00 = 6.16 M2
di Shaf 2.45 = 2.45 x 2.00 x 1.00 = 4.90 M2
A 409.91 M2
B
lobang kusen = L x T x JMH
J2A 142X142 = 1.42 x 1.42 x 2.00 = 4.03 M2
J2B 142X162 = 1.42 x 1.62 x 1.00 = 2.30 M2
J2C 152X152 = 1.52 x 1.52 x 2.00 = 4.62 M2
J3 226X152 = 2.26 x 1.52 x 2.00 = 6.87 M2
J 112X239 = 1.12 x 2.39 x 2.00 = 5.35 M2
V1 68X48 = 0.68 x 0.48 x 3.00 = 0.98 M2
V2 142X48 = 1.42 x 0.48 x 1.00 = 0.68 M2
P1 88x253 = 0.88 x 2.53 x 1.00 = 2.23 M2
Pd1 138x253 = 1.38 x 2.53 x 1.00 = 3.49 M2
Pd2 148x253 = 1.48 x 2.53 x 1.00 = 3.74 M2
Pw 78x209 = 0.78 x 2.09 x 2.00 = 3.26 M2
B.ksng 80x209 = 0.80 x 2.09 x 2.00 = 3.34 M2
225x209 = 2.25 x 2.09 x 1.00 = 4.70 M2
B.ksng- depan dak 275x180 = 2.62 x 1.80 x 2.00 = 9.43 M2
63x180 = 0.50 x 1.80 x 4.00 = 3.60 M2
B 58.64 M2
VOL.AKHIR = A - B
= 409.91 - 58.64 = 351.27 M2

3 Plest.Dinding Bata VOL. = LUAS x SISI keramik wc 647.67 M2


= 351.27 X 2.00 - 54.87 = 647.67 M2
647.67 M2

4 Plest.Trasram Bata VOL. = LUAS x SISI 31.68 M2


= 15.84 X 2.00 = 31.68 M2
31.68 M2

5 Plesteran Beton VOL. = P x kllg x SISI 119.47 M2


kolom 25/25 = 5.00 x 1.00 x 12.00 = 60.00 M2
kolom 10/28 = 2.25 x 0.76 x 5.00 = 8.55 M2
kolom 10/10 = 2.25 x 0.30 x 2.00 = 1.35 M2
Beton shaf blk 10/20 = 2.45 x 0.20 x 1.00 = 0.49 M2
beton sunscren - dak depan blk 10/25 = 10.50 x 0.40 x 1.00 = 4.20 M2
beton plat - dak depan blk 10/25 = 10.50 x 0.40 x 2.00 = 8.40 M2
Ringbalk 10/20 91.20 = 91.20 x 0.20 x 2.00 = 36.48 M2
119.47 M2

6 Plesteran Benangan VOL. = T/P x SISI x JMH 357.00 M1


kolom 25/25 = 5.00 x 4.00 x 12.00 = 240.00 M1
kolom 10/28 = 2.25 x 4.00 x 5.00 = 45.00 M1
kolom 10/10 = 2.25 x 2.00 x 2.00 = 9.00 M1
beton sunscren - dak depan blk 10/25 = 10.50 x 2.00 x 1.00 = 21.00 M1
beton plat - dak depan blk 10/25 = 10.50 x 2.00 x 2.00 = 42.00 M1
357.00 M1
VI PEKERJAAN KERAMIK
1 LANTAI KERAMIK 40X40CM VOL. = P x L x JMH 106.59 M2
Dalam Ruang Aula = 4.90 x 6.90 x 1.00 = 33.81 M2
R.Program = 7.40 x 3.90 x 1.00 = 28.86 M2
Kapus = 3.90 x 3.90 x 1.00 = 15.21 M2
Loby = 8.40 x 2.90 x 1.00 = 24.36 M2
washtafle = 1.50 x 2.90 x 1.00 = 4.35 M2
106.59 M2

2 LANTAI KERAMIK - KM/WC VOL. = P x L x JMH 3.92 M2


= 1.40 x 1.40 x 2.00 = 3.92 M2
3.92 M2

3 DINDING KERAMIK - KM/WC VOL. = P x T x JMH 17.35 M2


= 4.82 x 1.80 x 2.00 = 17.35 M2
17.35 M2

4 PLINT KERAMIK VOL. = P x JMH 89.48 M1


Aula = 22.52 x 1.00 = 22.52 M1
R.Program = 21.62 x 1.00 = 21.62 M1
Kapus = 15.92 x 1.00 = 15.92 M1
Loby = 17.46 x 1.00 = 17.46 M1
washtafle = 5.98 x 2.00 = 11.96 M1
89.48 M1

VIa PEKERJAAN GRANITE TILE - LUAR


1 DINDING GRANITE TILE VOL. = P/L x T x JMH 26.89 M2
Luar samp. = 1.06 x 2.87 x 2.00 = 6.08 M2
Tengah = 10.63 x 1.15 x 1.00 = 12.22 M2
= 1.38 x 3.11 x 2.00 = 8.58 M2
26.89 M2

2 DINDING BATU ANDESIT VOL. = P/L x T x JMH 10.62 M2


Tengah/Nama = 7.87 x 1.35 x 1.00 = 10.62 M2
10.62 M2

VII PEKERJAAN PLAFOND


1 PLAFOND KALSIBOARD - DALAM VOL. = P x L x JMH 118.10 M2
Dalam Ruang R.Aula = 4.87 x 6.87 x 1.00 = 33.46 M2
R.Program = 7.37 x 3.87 x 1.00 = 28.52 M2
R. kapus = 3.87 x 3.87 x 1.00 = 14.98 M2
Loby = 8.37 x 2.87 x 1.00 = 24.02 M2
km/wc = 1.37 x 1.37 x 2.00 = 3.75 M2
= 1.37 x 1.37 x 1.00 = 1.88 M2
tanggga = 2.37 x 4.85 x 1.00 = 11.49 M2
118.10 M2

2 PLAFOND KALSIBOARD - Overstek VOL. = P x L x JMH 66.06 M2


Induk = 18.70 x 1.10 x 2.00 = 41.14 M2
= 7.00 x 1.10 x 2.00 = 15.40 M2
Tangga = 2.50 x 0.70 x 1.00 = 1.75 M2
= 5.55 x 0.70 x 2.00 = 7.77 M2
66.06 M2

3 LISTPLAFOND GYPSUM - DALAM VOL. = P x JMH 110.00 M1


Aula = 24.00 x 1.00 = 24.00 M1
R.Program = 23.00 x 1.00 = 23.00 M1
Kapus = 16.00 x 1.00 = 16.00 M1
Loby = 23.00 x 1.00 = 23.00 M1
washtafle = 6.00 x 2.00 = 12.00 M1
km/wc = 6.00 x 2.00 = 12.00 M1
110.00 M1

4 LISTPLAFOND GYPSUM - LUAR VOL. = P x JMH 104.00 M1


Pinggir tembok = 16.75 x 2.00 = 33.50 M1
= 7.25 x 2.00 = 14.50 M1
Pinggir lIsplank = 18.75 x 2.00 = 37.50 M1
= 9.25 x 2.00 = 18.50 M1
104.00 M1
VIII PEKERJAAN KUSEN KAYU
1 KUSEN ALUMINIUM VOL. = P x JMH 111.70 M1
P1 88x253 = 6.82 x 1.00 = 6.82 M1
Pd1 138x253 = 8.22 x 1.00 = 8.22 M1
Pd2 148x253 = 8.42 x 1.00 = 8.42 M1
Pw 78x209 = 4.96 x 2.00 = 9.92 M1
J2a 142x142 = 8.52 x 2.00 = 17.04 M1
J2b 142x162 = 9.12 x 1.00 = 9.12 M1
J2c 152x152 = 9.12 x 2.00 = 18.24 M1
J3 226x152 = 11.34 x 2.00 = 22.68 M1
V1 68x48 = 2.32 x 3.00 = 6.96 M1
V2 142x48 = 4.28 x 1.00 = 4.28 M1
111.70 M1

2 KACA MATI 5MM VOL. = L x T x JMH 10.11 M2


J2C = 1.44 x 0.72 x 2.00 = 2.07 M2
J3 = 2.16 x 0.72 x 2.00 = 3.11 M2
J = 1.04 x 2.04 x 2.00 = 4.24 M2
V1 = 0.67 x 0.34 x 3.00 = 0.68 M2
10.11 M2

3 DAUN JENDELA KACA/VENT. VOL. = L x T x JMH 14.08 M2


J2A ventilasi = 0.65 x 0.40 x 4.00 = 1.04 M2
jendela = 0.65 x 0.90 x 4.00 = 2.34 M2
J2B ventilasi = 0.65 x 0.40 x 2.00 = 0.52 M2
jendela = 0.65 x 1.10 x 2.00 = 1.43 M2
J2C ventilasi = 0.70 x 0.70 x 4.00 = 1.96 M2
J3 ventilasi = 0.70 x 0.70 x 6.00 = 2.94 M2
J ventilasi = 0.50 x 0.98 x 4.00 = 1.96 M2
P1 ventilasi = 0.80 x 0.40 x 1.00 = 0.32 M2
PD1 ventilasi = 1.26 x 0.40 x 1.00 = 0.50 M2
PD2 ventilasi = 1.36 x 0.40 x 1.00 = 0.54 M2
V2 ventilasi = 0.65 x 0.40 x 2.00 = 0.52 M2
14.08 M2

4 DAUN PINTU KM/WC VOL. = L x T x JMH 2.87 M2


WC = 0.70 x 2.05 x 2.00 = 2.87 M2
2.87 M2

5 DAUN PINTU DOUBLE TEAKWOOD VOL. = L x T x JMH 7.18 M2


P1 = 0.80 x 2.05 x 1.00 = 1.64 M2
PD1 = 1.30 x 2.05 x 1.00 = 2.67 M2
PD2 = 1.40 x 2.05 x 1.00 = 2.87 M2
7.18 M2

IX PEKERJAAN BESI
1 ENGSEL PINTU VOL. = MASING 2 x JMH 12.00 BH
P1 = 3.00 x 1.00 = 3.00 BH
PJ = 3.00 x 1.00 = 3.00 BH
PU = 6.00 x 1.00 = 6.00 BH
12.00 BH

2 ENGSEL JENDELA VOL. = MASING 2 x JMH 54.00 BH


J2A ventilasi = 4.00 x 2.00 = 8.00 BH
jendela = 4.00 x 2.00 = 8.00 BH
J2B jendela = 4.00 x 1.00 = 4.00 BH
J2C jendela = 4.00 x 2.00 = 8.00 BH
J3 jendela = 6.00 x 2.00 = 12.00 BH
P1 ventilasi = 2.00 x 1.00 = 2.00 BH
PD1 ventilasi = 4.00 x 1.00 = 4.00 BH
PD2 ventilasi = 4.00 x 1.00 = 4.00 BH
V2 ventilasi = 4.00 x 1.00 = 4.00 BH
54.00 BH

3 KUNCI TANAM VOL. = MASING 2 x JMH 3.00 BH


P1 = 1.00 x 1.00 = 1.00 BH
PD1 = 1.00 x 1.00 = 1.00 BH
PD2 = 1.00 x 1.00 = 1.00 BH
3.00 BH

4 GRENDEL TANAM EXPAGNYOLET VOL. = MASING 2 x JMH 4.00 BH


PD1 = 2.00 x 1.00 = 2.00 BH
PD2 = 2.00 x 1.00 = 2.00 BH
4.00 BH

5 GRENDEL PINTU VOL. = MASING 2 x JMH 3.00 BH


P1 = 1.00 x 1.00 = 1.00 BH
PW = 1.00 x 2.00 = 2.00 BH
3.00 BH
X PEKERJAAN PENGECATAN
1 POLITURAN DAUN PINTU VOL. = LUAS x SISI 17.22 M2
teakwood = 7.18 x 2.00 = 14.35 M2
wc = 2.87 x 1.00 = 2.87 M2
17.22 M2

1 CAT DINDING (Dalam) - BARU Luas = P x T x JMH 264.25 M2


A AULA = 23.48 x 3.20 x 1.00 = 75.14 M2
P.PROGRAM = 22.48 x 3.20 x 1.00 = 71.94 M2
KAPUS = 15.48 x 3.20 x 1.00 = 49.54 M2
LOBY = 22.48 x 3.20 x 1.00 = 71.94 M2
WASHTAFLE = 5.48 x 3.20 x 2.00 = 35.07 M2
WC = 5.48 x 1.50 x 2.00 = 16.44 M2
RALLING = 1.25 x 2.13 x 1.00 = 2.66 M2
A 322.72 M2

B
Lbg kusen = L x T x JMH
PD1 = 1.38 x 2.53 x 2.00 = 6.98 M2
PD2 = 1.48 x 2.53 x 2.00 = 7.49 M2
P1 = 0.88 x 2.53 x 2.00 = 4.45 M2
PW = 0.78 x 2.09 x 2.00 = 3.26 M2
J2A = 1.42 x 1.42 x 2.00 = 4.03 M2
J2B = 1.42 x 1.62 x 1.00 = 2.30 M2
J2C = 1.52 x 1.52 x 2.00 = 4.62 M2
J3 = 2.26 x 1.52 x 2.00 = 6.87 M2
J = 1.12 x 2.39 x 2.00 = 5.35 M2
V1 = 0.68 x 0.48 x 3.00 = 0.98 M2
V2 = 1.42 x 0.48 x 1.00 = 0.68 M2
Blk kosong - 1 = 0.80 x 2.10 x 4.00 = 6.72 M2
Blk kosong - 2 = 2.25 x 2.10 x 1.00 = 4.73 M2
B 58.47 M2

VOL.AKHIR = A - B
= 322.72 - 58.47 = 264.25 M2
3 CAT DINDING (Luar) - BARU VOL. = P x T x JMH 314.67 M2
A samping = 7.25 x 4.50 x 1.00 = 32.63 M2
= 8.45 x 4.50 x 1.00 = 38.03 M2
belakang = 16.75 x 4.50 x 1.00 = 75.38 M2
depan = 16.75 x 4.50 x 1.00 = 75.38 M2
= 23.96 x 4.16 x 1.00 = 99.67 M2
keramik dinding = 37.52 = 37.52 M2
A 358.59 M2

B
Lbg kusen = L x T x JMH
J2a = 1.42 x 1.42 x 2.00 = 4.03 M2
J2b = 1.42 x 1.62 x 1.00 = 2.30 M2
J2c = 1.52 x 1.52 x 2.00 = 4.62 M2
J3 = 2.26 x 1.52 x 2.00 = 6.87 M2
J = 1.12 x 2.39 x 2.00 = 5.35 M2
V1 = 0.68 x 0.48 x 3.00 = 0.98 M2
V2 = 1.42 x 0.48 x 1.00 = 0.68 M2
blk kosong = 2.65 x 1.80 x 4.00 = 19.08 M2
B 43.92 M2
VOL.AKHIR = A - B
= 358.59 - 43.92 = 314.67 M2

XI PEKERJAAN ATAP
1 ATAP GENTENG - INDUK VOL. = P x L x SISI 218.50 M2
TRAVES. 1 = 14.25 x 5.75 x 2.00 = 163.88 M2
segitiga 2 = 9.50 x 5.75 x 2.00 x 0.50 = 54.63 M2
218.50 M2

2 BUBUNGAN VOL. = P x JMH 41.50 M1


NOK = 9.50 x 1.00 = 9.50 M1
JURAI = 8.00 x 4.00 = 32.00 M1
41.50 M1

3 LISPLANK KALSIPLANK VOL. = P x JMH 56.20 M1


belakang = 18.80 x 1.00 = 18.80 M1
samping = 9.30 x 2.00 = 18.60 M1
depan = 18.80 x 1.00 = 18.80 M1
56.20 M1
ATAP TANGGA
1 ATAP GENTENG - TANGGA VOL. = P x L x SISI 24.00 M2
1 = 4.00 x 6.00 x 1.00 = 24.00 M2
24.00 M2

2 LISPLANK KALSIPLANK VOL. = P x JMH 16.00 M1


samping = 6.00 x 2.00 = 12.00 M1
belakang = 4.00 x 1.00 = 4.00 M1
16.00 M1

3 GORDING 6/12 VOL. = P x DIMENSI x JMH 0.20 M3


gording = 4.00 x 0.06 x 0.12 x 7.00 = 0.20 M3
0.20 M3

10 Pembuatan bak kontrol Volume = JMH 27.00 unit


27.00 = 27.00 unit
BACK UP VOLUME
LANTAI 1
PEKERJAAN #REF!
LOKASI #REF!
TAHUN #REF!

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME


1 2 3 4

I LUAS BANGUNAN
1 LUAS BANGUNAN VOL. = P x L x JMH 76.00 M2
DALAM = 8.00 x 4.00 x 1.00 = 32.00 M2 32.00
= 4.00 x 8.00 x 1.00 = 32.00 M2 32.00
SELASAR = 8.00 x 2.00 x 0.50 = 8.00 M2 16.00
= 4.00 x 2.00 x 0.50 = 4.00 M2 8.00
76.00 M2 88.00

2 BONGKAR BANGUNAN LAMA VOL. = P x L x JMH 154.50 M2


DALAM = 17.50 x 7.00 x 1.00 = 122.50 M2
= 8.00 x 2.00 x 2.00 = 32.00 M2
154.50 M2

II PEKERJAAN TANAH
1 GALIAN PONDASI VOL. = P x L x T x JMH 94.93 M3
Pondasi stempat 125x125 cm = 1.45 x 1.45 x 1.50 x 6.00 = 18.92 M3
Pondasi stempat 175x175 cm = 1.95 x 1.95 x 1.50 x 12.00 = 68.45 M3
Galian sloof 25/40 = 7.00 x 0.40 x 0.50 x 4.00 = 5.60 M3
Galian pondasi bt.kali shaf = 2.45 x 0.80 x 1.00 x 1.00 = 1.96 M3
94.93 M3

2 PASIR URUG PONDASI VOL. = P x L x T x JMH 6.02 M3


Pondasi stempat 125x125 cm - = 1.45 x 1.45 x 0.10 x 6.00 = 1.26 M3
Pondasi stempat 175x175 cm - = 1.95 x 1.95 x 0.10 x 12.00 = 4.56 M3
Galian pondasi bt.kali shaf = 2.45 x 0.80 x 0.10 x 1.00 = 0.20 M3
6.02 M3

3 PASIR URUG BWH LANTAI VOL. = P x L x T x JMH 3.15 M3


= 10.50 x 3.00 x 0.10 x 1.00 = 3.15 M3
3.15 M3

4 TANAH URUG BWH LANTAI VOL. = P x L x T x JMH 6.62 M3


= 10.50 x 3.00 x 0.21 x 1.00 = 6.62 M3
6.62 M3

5 BATU KOSONG VOL. = P x L x T x JMH 0.44 M3


shaf = 2.45 x 0.90 x 0.20 x 1.00 = 0.44 M3

6 PONDASI BATU KALI VOL. = P x L x T x JMH 0.86 M3


shaf = 2.45 x 0.50 x 0.70 x 1.00 = 0.86 M3

IV PEKERJAAN BETON
1 BETON RABAT BWH LANTAI VOL. = P x L x T x JMH 1.51 M3
= 10.50 x 3.00 x 0.05 x 1.00 = 1.51 M3
1.51 M3

2 BETON LANTAI KERJA PONDASI VOL. = P x L x T x JMH 4.08 M3


Pondasi stempat 125x125 cm = 1.45 x 1.45 x 0.07 x 6.00 = 0.88 M3
Pondasi stempat 175x175 cm = 1.95 x 1.95 x 0.07 x 12.00 = 3.19 M3
4.08 M3

3 FOOTPLAT 125X125 CM VOL. = P x L x T x JMH 2.58 M3


= 1.25 x 1.25 x 0.28 x 6.00 = 2.58 M3
2.58 M3

Begisting = 1.25 + 1.25 x 2.00 x 6.00 x 0.25 = 7.50 M2 2.91 M2/M3

Pembesian = Brat besi x P. Bs x Jmh Bs x JMH x SISI


D13mm - 12,5 = 1.042 x 1.25 x 10.00 x 6.00 x 2.00 = 156.28 Kg 60.62 KG/M3

Ø10mm - 12,5 = 0.617 x 1.95 x 10.00 x 6.00 x 2.00 = 144.26 Kg 55.96 KG/M3
4 FOOTPLAT 175X175 CM VOL. = P x L x T x JMH 11.03 M3
= 1.75 x 1.75 x 0.30 x 12.00 = 11.03 M3
11.03 M3

Begisting = 1.75 + 1.75 x 2.00 x 12.00 x 0.25 = 21.00 M2 1.90 M2/M3

Pembesian = Brat besi x P. Bs x Jmh Bs x JMH x SISI


D16mm - 12,5 = 1.578 x 1.75 x 14.00 x 12.00 x 2.00 = 928.01 Kg 84.17 KG/M3

Ø10mm - 12,5 = 0.617 x 2.45 x 14.00 x 12.00 x 2.00 = 507.50 Kg 46.03 KG/M3

5 SLOOF 15/20 VOL. = P x L x T x JMH 0.07 M3


memanjang 2.45 = 2.45 x 0.15 x 0.20 x 1.00 = 0.07 M3 2.45

6 SLOOF 20/30 VOL. = P x L x T x JMH 3.47 M3


memanjang 3.00 = 2.75 x 0.20 x 0.30 x 4.00 = 0.66 M3 12.00
3.50 = 3.25 x 0.20 x 0.30 x 9.00 = 1.76 M3 31.50
melintang 3.00 = 2.75 x 0.20 x 0.30 x 4.00 = 0.66 M3 12.00
3.50 = 3.25 x 0.20 x 0.30 x 2.00 = 0.39 M3 7.00
3.47 M3 Panjang 55.50

Begisting = 0.30 + 0.30 x 1.00 x 57.75 = 34.65 M2 10.00 M2/M3

Pembesian = Brat besi x Jmh Bs x P


6D16mm = 1.578 x 6.00 x 55.50 = 525.55 Kg 151.68 KG/M3
= Brat besi x P.sengkang x Jmh Bg
Bg. Ø10-15cm = 0.617 x 0.90 x 385.00 = 213.62 Kg 61.65 KG/M3

7 SLOOF 25/40 VOL. = P x L x T x JMH 3.96 M3


melintang 7.00 = 6.60 x 0.25 x 0.40 x 6.00 = 3.96 M3 42.00
3.96 M3 Panjang 42.00

Begisting = 0.40 + 0.40 x 1.00 x 39.60 = 31.68 M2 8.00 M2/M3

Pembesian = Brat besi x Jmh Bs x P


8D16mm = 1.578 x 8.00 x 42.00 = 530.29 Kg 133.91 KG/M3
= Brat besi x P.sengkang x Jmh Bg
Bg. Ø10-15cm = 0.617 x 1.20 x 264.00 = 195.31 Kg 49.32 KG/M3

8 KOLOM 10/10 VOL. = T x JMH 88.75 M1


dibawah lantai = 0.50 x 17.00 = 8.50 M1
diatas lantai = 3.75 x 17.00 = 63.75 M1
loket rolling = 2.00 x 4.00 = 8.00 M1
Ralling tangga = 1.00 x 4.00 = 4.00 M1
= 2.25 x 2.00 = 4.50 M1
88.75 M1

9 BALOK LATEI 10/15 - diatas kusen VOL. = P x JMH 20.25 M1


Jendela J2 = 2.00 x 1.00 = 2.00 M1
J1 - entrance = 1.50 x 2.00 = 3.00 M1
Pintu P1 = 1.00 x 4.00 = 4.00 M1
PD = 2.25 x 1.00 = 2.25 M1
P.rolling = 1.00 x 2.00 = 2.00 M1
PJ = 3.00 x 2.00 = 6.00 M1
Ps = 1.00 x 1.00 = 1.00 M1
20.25 M1

10 KOLOM BETON 25/25 - K1 VOL. = T x L x T x JMH 1.89 M3


dibawah lantai 1.90 = 1.38 x 0.25 x 0.25 x 6.00 = 0.52 M3
diatas lantai = 3.50 x 0.25 x 0.25 x 4.00 = 0.88 M3
= 4.00 x 0.25 x 0.25 x 2.00 = 0.50 M3
1.89 M3

Begisting = 0.25 + 0.25 x 2.00 x 30.28 = 30.28 M2 16.00 M2/M3

Pembesian 8 D 16mm = 1.58 x 8.00 x 30.28 = 382.31 Kg 202.01 Kg/M3

bg. Ø8-15 = 0.39 x 0.90 x 201.87 = 71.68 Kg 37.88 Kg/M3


71.68 Kg
11 KOLOM BETON 25/40 VOL. = T x L x T x JMH 6.46 M3
dibawah lantai 1.90 = 1.38 x 0.25 x 0.40 x 12.00 = 1.66 M3
diatas lantai = 4.00 x 0.25 x 0.40 x 12.00 = 4.80 M3
6.46 M3

Begisting = 0.25 + 0.40 x 2.00 x 64.56 = 83.93 M2 13.00 M2/M3

Pembesian 10 D 16mm = 1.58 x 10.00 x 64.56 = 1,018.91 Kg 157.82 Kg/M3

bg. Ø10-15 = 0.62 x 1.20 x 430.40 = 318.41 Kg 49.32 Kg/M3


318.41 Kg

12 PLAT SUNSCREN T. 8CM VOL. = P x L x T x JMH 0.63 M3


J.konseling + Mtbs 7.30 = 7.30 x 0.40 x 0.08 x 2.00 = 0.47 M3
J. Teras 1.50 = 1.50 x 0.40 x 0.08 x 2.00 = 0.10 M3
J2 - BPU 2.00 = 2.00 x 0.40 x 0.08 x 1.00 = 0.06 M3
0.63 M3

BETON DAK - TERAS


1 BALOK BETON 25/30 VOL. = P x L x T x JMH 0.83 M3
melintang 3.00 = 2.75 x 0.25 x 0.30 x 4.00 = 0.83 M3
1 0.83 M3

Begisting = 0.25 + 0.96 x 1.00 x 8.25 = 9.98 M2 12.10 M2/M3

Pembesian = Brat Bs x P.Bs x Jmh Bs x JMH


4 D 16mm = 1.58 x 3.00 x 4.00 x 4.00 = 75.76 Kg 235.30 Kg/M3
Extra Tump. = 1.58 x 0.75 x 10.00 x 4.00 = 47.35 Kg
Extra Lap. = 1.58 x 2.25 x 5.00 x 4.00 = 71.02 Kg
194.12 Kg

bg. Ø10-15 = 0.62 x 1.00 x 66.00 = 40.69 Kg 49.32 Kg/M3


40.69 Kg

2 BALOK BETON 25/30 - Ks VOL. = P x L x T x JMH 0.26 M3


melintang 1.00 = 0.88 x 0.25 x 0.30 x 4.00 = 0.26 M3
0.26 M3

3 BALOK BETON 20/30 VOL. = P x L x T x JMH 1.17 M3


memanjang 3.50 = 3.25 x 0.20 x 0.30 x 6.00 = 1.17 M3
1.17 M3

4 BALOK BETON 20/30 - KS VOL. = P x L x T x JMH 0.21 M3


memanjang 1.00 = 0.88 x 0.20 x 0.30 x 4.00 = 0.21 M3
0.21 M3

5 PLAT DAK T. 12CM VOL. = P x L x T x JMH 5.13 M3


Dalam 350X300 = 3.25 x 2.80 x 0.12 x 3.00 = 3.28 M3 31.50
Overstek 350X100 = 3.25 x 0.90 x 0.12 x 3.00 = 1.05 M3 10.50
100X300 = 0.90 x 2.80 x 0.12 x 2.00 = 0.60 M3 6.00
100X100 = 0.90 x 0.90 x 0.12 x 2.00 = 0.19 M3 2.00
5.13 M3 50.00

Pembesian = Luas Plat x Brat Bs x Jmh Bs/M2 x SISI


= 50.00 x 0.39 x 10.00 x 2.00 = 394.56 Kg 76.94 KG/M3
7 LISPLANK T. 7CM VOL. = P x L x T x JMH 0.86 M3
12.50 = 12.50 x 0.60 x 0.07 x 1.00 = 0.53 M3 7.50
4.00 = 4.00 x 0.60 x 0.07 x 2.00 = 0.34 M3 4.80
0.86 M3 12.30

Pembesian = Luas Plat x Brat Bs x Jmh Bs/M2 x SISI


= 12.30 x 0.39 x 6.67 x 2.00 = 64.71 Kg 75.15 KG/M3

IV BETON LANTAI 2
1 BALOK BETON 25/60 VOL. = P x L x T x JMH 5.94 M3
melintang 7.00 = 6.60 x 0.25 x 0.60 x 6.00 = 5.94 M3
5.94 M3

Begisting = 0.25 + 0.96 x 1.00 x 39.60 = 47.92 M2 8.07 M2/M3

Pembesian = Brat Bs x P.Bs x Jmh Bs x JMH


4 D 19mm = 2.23 x 7.00 x 4.00 x 6.00 = 373.89 Kg 183.62 Kg/M3
2 D 16mm = 1.58 x 7.00 x 2.00 x 6.00 = 132.57 Kg
Extra Tump. = 2.23 x 1.75 x 10.00 x 6.00 = 233.68 Kg
Extra Lap. = 2.23 x 5.25 x 5.00 x 6.00 = 350.53 Kg
1,090.68 Kg

bg. Ø10-15 = 0.62 x 1.60 x 316.80 = 312.49 Kg 52.61 Kg/M3


312.49 Kg

2 BALOK BETON 20/30 VOL. = P x L x T x JMH 0.66 M3


memanjang 3.00 = 2.75 x 0.20 x 0.30 x 4.00 = 0.66 M3
2 0.66 M3

Begisting = 0.20 + 0.36 x 1.00 x 11.00 = 6.16 M2 9.33 M2/M3

Pembesian = Brat Bs x P.Bs x Jmh Bs x JMH


4 D 16mm = 1.58 x 3.00 x 4.00 x 4.00 = 75.76 Kg 222.39 Kg/M3
Extra Tump. = 1.58 x 0.75 x 6.00 x 4.00 = 28.41 Kg
Extra Lap. = 1.58 x 2.25 x 3.00 x 4.00 = 42.61 Kg
146.78 Kg

bg. Ø10-15 = 0.62 x 1.00 x 88.00 = 54.25 Kg 82.20 Kg/M3


54.25 Kg

2A BALOK BETON 20/30 VOL. = P x L x T x JMH 1.17 M3


memanjang 3.50 = 3.25 x 0.20 x 0.30 x 6.00 = 1.17 M3
2A 1.17 M3

VOL.AKHIR = 2 + 2A
= 0.66 + 1.17 = 1.83 M3

3 BALOK BETON 20/30 - BA VOL. = P x L x T x JMH 1.71 M3


memanjang 3.00 = 2.75 x 0.20 x 0.30 x 2.00 = 0.33 M3 6.00
2.50 = 2.25 x 0.20 x 0.30 x 1.00 = 0.14 M3 2.50
4.00 = 3.75 x 0.20 x 0.30 x 2.00 = 0.45 M3 8.00
melintang 3.00 = 2.75 x 0.20 x 0.30 x 1.00 = 0.17 M3 3.00
4.00 = 3.75 x 0.20 x 0.30 x 1.00 = 0.23 M3 4.00
7.00 = 6.80 x 0.20 x 0.30 x 1.00 = 0.41 M3 7.00
1.71 M3 30.50

Begisting = 0.20 + 0.36 x 1.00 x 28.55 = 15.99 M2 9.33 M2/M3

Pembesian = Brat Bs x P.Bs x Jmh Bs x JMH


4 D 16mm = 1.58 x 30.50 x 4.00 x 1.00 = 192.55 Kg 112.40 Kg/M3
192.55 Kg

bg. Ø10-15 = 0.62 x 1.00 x 228.40 = 140.81 Kg 82.20 Kg/M3


140.81 Kg

5 PLAT DAK T. 12CM VOL. = P x L x T x JMH 12.44 M3


Dalam 300X700 = 2.75 x 6.80 x 0.12 x 2.00 = 4.49 M3 24.00
350X700 = 3.25 x 6.80 x 0.12 x 3.00 = 7.96 M3 22.50
12.44 M3 46.50

6 BALOK BETON 10/20 - SHAF VOL. = P x L x T x JMH 0.04 M3


2.45 = 2.20 x 0.10 x 0.20 x 1.00 = 0.04 M3
0.04 M3
BETON TANGGA
1 BALOK BORDES BETON 20/30 VOL. = P x L x T x JMH 0.27 M3
memanjang 2.50 = 2.25 x 0.20 x 0.30 x 2.00 = 0.27 M3
0.27 M3

2 BALOK BETON 20/35 - KS VOL. = P x L x T x JMH 0.19 M3


1.50 = 1.38 x 0.20 x 0.35 x 2.00 = 0.19 M3
0.19 M3

3 BALOK BETON 25/30 VOL. = P x L x T x JMH 0.37 M3


Pengaku 3.35 = 3.10 x 0.20 x 0.30 x 2.00 = 0.37 M3
0.37 M3

4 BALOK BETON 10/20 VOL. = P x L x T x JMH 0.12 M3


6.00 = 5.75 x 0.10 x 0.20 x 1.00 = 0.12 M3
0.12 M3

5 PLAT TANGGA T. 15CM VOL. = P x L x T x JMH 2.14 M3


Bordes = 2.50 x 1.50 x 0.15 x 1.00 = 0.56 M3 3.75
Miring = 4.00 x 1.40 x 0.15 x 1.00 = 0.84 M3 5.60
= 3.50 x 1.40 x 0.15 x 1.00 = 0.74 M3 4.90
2.14 M3 14.25

Pembesian = Luas Plat x Brat Bs x Jmh Bs/M2 x SISI


Ø12 - 12,5cm = 14.25 x 0.89 x 8.00 x 2.00 = 202.41 Kg 94.69 KG/M3
Ø10 - 12,5cm = 14.25 x 0.62 x 8.00 x 2.00 = 140.56 Kg 65.76 KG/M3
160.45 KG/M3

6 FOOTPLAT 100X125 CM VOL. = P x L x T x JMH 0.34 M3


= 1.00 x 1.25 x 0.28 x 1.00 = 0.34 M3
0.34 M3

Begisting = 1.00 + 1.25 x 2.00 x 1.00 x 0.25 = 1.13 M2 3.27 M2/M3

Pembesian = Brat besi x P. Bs x Jmh Bs x JMH x SISI


bawah D13mm - 12,5 = 1.042 x 1.00 x 11.00 x 1.00 x 1.00 = 11.46 Kg 63.65 KG/M3
D13mm - 12,5 = 1.042 x 1.25 x 8.00 x 1.00 x 1.00 = 10.42 Kg
21.88 Kg

Ø10mm - 12,5 = 0.617 x 1.70 x 11.00 x 1.00 x 1.00 = 11.53 Kg 61.52 KG/M3
= 0.617 x 1.95 x 8.00 x 1.00 x 1.00 = 9.62 Kg
21.15 Kg

7 KOLOM TANGGA 20X125 CM VOL. = P x L x T x JMH 0.30 M3


= 1.50 x 0.20 x 1.00 x 1.00 = 0.30 M3
0.30 M3

V PEKERJAAN PASANGAN/PLEST.
2 Trasram Bata 1/2 bt VOL. = P x T x SISI 46.71 M2
memanjang 3.00 = 2.75 x 0.40 x 4.00 = 4.40 M2
3.50 = 3.25 x 0.40 x 7.00 = 9.10 M2
1.00 = 1.00 x 0.40 x 1.00 = 0.40 M2
Trap tangga 10.50 = 10.50 x 0.50 x 2.00 = 10.50 M2
Shaf 2.45 = 2.45 x 0.50 x 1.00 = 1.23 M2
melintang 4.00 = 4.00 x 0.40 x 2.00 = 3.20 M2
3.00 = 3.00 x 0.40 x 5.00 = 6.00 M2
7.00 = 6.60 x 0.40 x 1.00 = 2.64 M2
anak tangga = 0.04 x 22.00 x 10.00 = 9.24 M2
46.71 M2
2 Dinding Bata 1/2 bt - T.400 M VOL. = P x T x JMH 307.28 M2
2.1 memanjang 3.00 = 2.75 x 3.70 x 4.00 = 40.70 M2
3.50 = 3.25 x 3.70 x 3.00 = 36.08 M2
1.00 = 1.00 x 4.00 x 1.00 = 4.00 M2
7.00 = 7.00 x 3.88 x 2.00 = 54.32 M2
Shaf 2.45 = 2.45 x 3.80 x 1.00 = 9.31 M2
Bordes tangga 3.50 = 3.50 x 3.00 x 1.00 = 10.50 M2
melintang 7.00 = 6.60 x 3.50 x 1.00 = 23.10 M2
4.00 = 4.00 x 3.50 x 2.00 = 28.00 M2
3.00 = 3.00 x 3.88 x 2.00 = 23.28 M2
3.00 = 3.00 x 3.50 x 2.00 = 21.00 M2
3.00 = 3.00 x 3.20 x 2.00 = 19.20 M2
di tangga 4.85 = 4.85 x 3.65 x 2.00 = 35.41 M2
= 3.35 x 2.00 x 0.50 x 2.00 = 6.70 M2
Ralling tangga 8.00 = 8.00 x 0.80 x 1.00 = 6.40 M2
2.2 DINDING BANG. LAMA Kesmas = 3.35 x 3.30 x 2.00 = 22.11 M2
R.kosong = 2.00 x 3.30 x 1.00 = 6.60 M2
A 346.70 M2
B
lobang kusen = L x T x JMH
J2 R.BPU = 1.32 x 1.62 x 1.00 = 2.14 M2
J1 R.Mtba = 1.12 x 2.95 x 2.00 = 6.61 M2
J1-rolling Loket = 1.00 x 0.85 x 2.00 = 1.70 M2
J1-Teras Teras = 1.27 x 2.20 x 2.00 = 5.59 M2
P1 = 0.88 x 2.53 x 4.00 = 8.91 M2
PJ = 0.88 x 2.53 x 2.00 = 4.45 M2
= 1.68 x 1.62 x 2.00 = 5.44 M2
Ps = 0.68 x 1.58 x 1.00 = 1.07 M2
PU = 1.68 x 2.09 x 1.00 = 3.51 M2
B 39.42 M2
VOL.AKHIR = A - B
= 346.70 - 39.42 = 307.28 M2

3 Plest.Dinding Bata VOL. = LUAS x SISI keramik wc 448.84 M2


= 307.28 X 2.00 - 165.72 = 448.84 M2
448.84 M2

4 Plest.Trasram Bata VOL. = LUAS x SISI 93.41 M2


= 46.71 X 2.00 = 93.41 M2
93.41 M2

5 Plesteran Beton VOL. = P x kllg x SISI 128.01 M2


kolom 25/25 = 4.00 x 1.00 x 6.00 = 24.00 M2
kolom 25/40 = 4.00 x 1.17 x 12.00 = 56.16 M2
memanjang blk 20/30 = 3.00 x 0.50 x 2.00 = 3.00 M2
= 2.50 x 0.50 x 3.00 = 3.75 M2
blk 20/35 = 4.00 x 0.55 x 2.00 = 4.40 M2
blk 25/60 = 7.00 x 0.85 x 2.00 = 11.90 M2
blk Ks 20/35 = 1.50 x 0.75 x 2.00 = 2.25 M2
Lisplank 12.50 = 12.50 x 1.10 x 1.00 = 13.75 M2
4.00 = 4.00 x 1.10 x 2.00 = 8.80 M2
128.01 M2

6 Plesteran Benangan VOL. = T/P x SISI x JMH 467.50 M1


kolom 25/25 = 4.00 x 4.00 x 6.00 = 96.00 M1
kolom 25/40 = 4.00 x 4.00 x 12.00 = 192.00 M1
memanjang blk 20/30 = 3.00 x 2.00 x 2.00 = 12.00 M1
= 2.50 x 2.00 x 3.00 = 15.00 M1
blk 20/35 = 4.00 x 2.00 x 2.00 = 16.00 M1
blk 25/60 = 7.00 x 2.00 x 2.00 = 28.00 M1
blk Ks 20/35 = 1.50 x 2.00 x 2.00 = 6.00 M1
Lisplank 12.50 = 12.50 x 5.00 x 1.00 = 62.50 M1
4.00 = 4.00 x 5.00 x 2.00 = 40.00 M1
467.50 M1
VI PEKERJAAN KERAMIK
1 LANTAI KERAMIK 40X40CM VOL. = P x L x JMH 182.15 M2
Dalam Ruang Teras = 10.40 x 3.00 x 1.00 = 31.20 M2
R.BPU = 2.87 x 3.87 x 1.00 = 11.11 M2
Mtbs = 3.87 x 2.87 x 1.00 = 11.11 M2
Loket = 2.87 x 2.87 x 1.00 = 8.24 M2
apotik = 2.87 x 2.87 x 1.00 = 8.24 M2
Konseling = 3.87 x 2.87 x 1.00 = 11.11 M2
Hall = 2.37 x 3.00 x 1.00 = 7.11 M2
= 10.37 x 6.00 x 1.00 = 62.22 M2
R.Kesmas = 2.87 x 2.00 x 1.00 = 5.74 M2
R.Kosong = 3.87 x 2.00 x 1.00 = 7.74 M2
R.Gizi = 4.00 x 3.87 x 1.00 = 15.48 M2
= 1.00 x 2.87 x 1.00 = 2.87 M2
182.15 M2

2 LANTAI KERAMIK - TANGGA VOL. = P x L x JMH 15.80 M2


Bordes = 3.27 x 1.50 x 1.00 = 4.91 M2
anak tangga = 1.65 x 0.30 x 22.00 = 10.89 M2
15.80 M2

3 TRAP TANGGA TERAS VOL. = P x L x JMH 8.60 M2


= 10.75 x 0.40 x 2.00 = 8.60 M2
8.60 M2

4 PLINT KERAMIK VOL. = P x JMH 134.12 M1


Teras = 15.02 x 1.00 = 15.02 M1
R.Konseling = 13.12 x 1.00 = 13.12 M1
Apotik = 11.12 x 1.00 = 11.12 M1
Loket = 11.12 x 1.00 = 11.12 M1
Mtbs = 13.12 x 1.00 = 13.12 M1
BPU = 13.12 x 1.00 = 13.12 M1
R.Gizi = 13.24 x 1.00 = 13.24 M1
R.Kesmas = 10.00 x 1.00 = 10.00 M1
Hall/Loby = 20.86 x 1.00 = 20.86 M1
= 13.40 x 1.00 = 13.40 M1
134.12 M1

5 DINDING GRANITE - RUANG VOL. = P/L x T x JMH 157.12 M2


R. Konseling 400x300 = 12.72 x 1.80 x 1.00 - 1.00 = 21.90 M2
R. Apotik 300x300 = 10.72 x 1.80 x 1.00 - 0.76 = 18.54 M2
R. Loket 300x300 = 10.72 x 1.80 x 1.00 - 0.76 = 18.54 M2
R. Mtbs 400x300 = 12.72 x 1.80 x 1.00 - 1.00 = 21.90 M2
R. BPU 300x400 = 12.72 x 1.80 x 1.00 - 2.80 = 20.09 M2
R. GIZI 14.00 = 13.12 x 1.80 x 1.00 - 1.54 = 22.08 M2
R. Hall/R.Tunggu 13.00 = 9.48 x 1.80 x 1.00 - 1.54 = 15.52 M2
14.50 = 11.86 x 1.80 x 1.00 - 2.80 = 18.54 M2
157.12 M2

VIa PEKERJAAN GRANITE TILE - LUAR


1 DINDING GRANITE TILE VOL. = P/L x T x JMH 13.48 M2
Luar samp. = 1.06 x 4.40 x 2.00 = 9.33 M2
pintu masuk = 0.60 x 2.20 x 2.00 = 2.64 M2
= 0.50 x 0.50 x 2.00 = 0.50 M2
= 0.60 x 1.68 x 1.00 = 1.01 M2
13.48 M2

2 DINDING BATU ANDESIT VOL. = P/L x T x JMH 9.23 M2


Luar samp. = 1.94 x 3.95 x 2.00 - 6.10 = 9.23 M2
9.23 M2

VII PEKERJAAN PLAFOND


1 PLAFOND KALSIBOARD - DALAM VOL. = P x L x JMH 198.25 M2
Dalam Ruang R.Kesmas = 2.87 x 3.37 x 1.00 = 9.67 M2
R.BPU = 2.87 x 3.87 x 1.00 = 11.11 M2
R. Mtbs = 3.87 x 2.87 x 1.00 = 11.11 M2
R. Loket = 2.87 x 2.87 x 1.00 = 8.24 M2
Apotik = 2.87 x 2.87 x 1.00 = 8.24 M2
Konseling = 3.87 x 2.87 x 1.00 = 11.11 M2
Hall/Loby = 10.37 x 3.87 x 1.00 = 40.13 M2
= 2.37 x 2.87 x 1.00 = 6.80 M2
= 4.00 x 2.00 x 2.00 = 16.00 M2
R.Gizi = 4.00 x 4.00 x 1.00 = 16.00 M2
= 1.00 x 3.00 x 1.00 = 3.00 M2
R.Kosong = 3.87 x 1.87 x 1.00 = 7.24 M2
Teras - dalam = 10.37 x 3.00 x 1.00 = 31.11 M2
luar = 10.50 x 1.00 x 1.00 = 10.50 M2
= 4.00 x 1.00 x 2.00 = 8.00 M2
198.25 M2

3 LISTPLAFOND GYPSUM - DALAM VOL. = P x JMH 175.20 M1


Teras dalam = 16.50 x 1.00 = 16.50 M1
luar = 26.50 x 1.00 = 26.50 M1
R.Konseling = 14.00 x 1.00 = 14.00 M1
Apotik = 12.00 x 1.00 = 12.00 M1
Loket = 12.00 x 1.00 = 12.00 M1
Mtbs = 14.00 x 1.00 = 14.00 M1
BPU = 14.00 x 1.00 = 14.00 M1
R.Gizi = 15.00 x 1.00 = 15.00 M1
R.Kesmas = 13.00 x 1.00 = 13.00 M1
Hall/Loby = 28.50 x 1.00 = 28.50 M1
= 9.70 x 1.00 = 9.70 M1
175.20 M1
VIII PEKERJAAN KUSEN KAYU
1 KUSEN ALUMINIUM VOL. = P x JMH 96.24 M1
P1 = 6.82 x 4.00 = 27.28 M1
PJ = 15.45 x 2.00 = 30.90 M1
PU = 5.86 x 1.00 = - M1
Ps = 4.52 x 1.00 = 4.52 M1
J2 R.BPU = 9.12 x 1.00 = 9.12 M1
J2a R.Mtbs/Konseling = 12.21 x 2.00 = 24.42 M1
96.24 M1

2 KACA MATI 5MM VOL. = L x T x JMH 2.28 M2


PJ = 1.02 x 1.12 x 2.00 = 2.28 M2
2.28 M2

3 DAUN JENDELA KACA/VENT. VOL. = L x T x JMH 6.61 M2


J2 ventilasi = 0.65 x 0.40 x 1.00 = 0.26 M2
jendela = 0.65 x 1.00 x 2.00 = 1.30 M2
J2A jendela = 0.50 x 0.90 x 2.00 = 0.90 M2
P1 ventilasi = 0.80 x 0.40 x 4.00 = 1.28 M2
PJ ventilasi = 0.80 x 0.40 x 2.00 = 0.64 M2
ventilasi = 1.00 x 0.40 x 2.00 = 0.80 M2
jendela = 0.65 x 1.10 x 2.00 = 1.43 M2
6.61 M2

4 DAUN PINTU KACA RANGKA ALUM. VOL. = L x T x JMH 3.28 M2


PU = 1.60 x 2.05 x 1.00 = 3.28 M2
3.28 M2

5 DAUN PINTU DOUBLE TEAKWOOD VOL. = L x T x JMH 9.84 M2


P1 = 0.80 x 2.05 x 4.00 = 6.56 M2
PJ = 0.80 x 2.05 x 2.00 = 3.28 M2
9.84 M2

IX PEKERJAAN BESI
1 ENGSEL PINTU VOL. = MASING 2 x JMH 24.00 BH
P1 = 3.00 x 4.00 = 12.00 BH
PJ = 3.00 x 2.00 = 6.00 BH
PU = 6.00 x 1.00 = 6.00 BH
24.00 BH

2 ENGSEL JENDELA VOL. = MASING 2 x JMH 40.00 BH


J2 ventilasi = 4.00 x 1.00 = 4.00 BH
jendela = 4.00 x 1.00 = 4.00 BH
J2A jendela = 4.00 x 2.00 = 8.00 BH
P1 ventilasi = 2.00 x 4.00 = 8.00 BH
PJ ventilasi = 6.00 x 2.00 = 12.00 BH
jendela = 2.00 x 2.00 = 4.00 BH
40.00 BH

3 KUNCI TANAM VOL. = MASING 2 x JMH 4.00 BH


PDJ = 1.00 x 4.00 = 4.00 BH
4.00 BH

4 GRENDEL TANAM EXPAGNYOLET VOL. = MASING 2 x JMH 2.00 BH


PU = 2.00 x 1.00 = 2.00 BH
2.00 BH

5 GRENDEL PINTU VOL. = MASING 2 x JMH 6.00 BH


P1 = 1.00 x 4.00 = 4.00 BH
PJ = 1.00 x 2.00 = 2.00 BH
6.00 BH

6 RALLING GANTUNG HOLLOW VOL. = P x JMH 9.75 M2


= 3.25 x 3.00 = 9.75 M1
9.75 M1
X PEKERJAAN PENGECATAN
1 POLITURAN DAUN PINTU VOL. = LUAS x SISI 19.68 M2
= 9.84 x 2.00 = 19.68 M2

1 CAT DINDING (Dalam) - BARU Luas = P x T x JMH 302.66 M2


A KONSELING = 13.48 x 3.10 x 1.00 = 41.79 M2
APOTIK = 11.48 x 3.10 x 1.00 = 35.59 M2
LOKET = 11.48 x 3.10 x 2.00 = 71.18 M2
MTBS = 13.48 x 3.10 x 1.00 = 41.79 M2
BPU = 13.48 x 3.10 x 1.00 = 41.79 M2
KESMAS = 12.48 x 3.10 x 1.00 = 38.69 M2
R.GIZI = 14.74 x 3.10 x 1.00 = 45.69 M2
HALL/LOBY = 24.37 x 3.10 x 1.00 = 75.55 M2
tangga = 6.70 x 3.10 x 1.00 = 20.77 M2
= 6.00 x 3.10 x 1.00 = 18.60 M2
R.KOSONG = 11.48 x 3.10 x 1.00 = 35.59 M2
TERAS = 16.50 x 3.10 x 1.00 = 51.15 M2
A 518.17 M2

B
Lbg kusen = L x T x JMH
PU = 1.68 x 2.09 x 1.00 = 3.51 M2
P1 = 0.88 x 2.53 x 6.00 = 13.36 M2
pd = 1.68 x 2.09 x 1.00 = 3.51 M2
PJ = 0.88 x 2.53 x 4.00 = 8.91 M2
= 1.73 x 1.62 x 4.00 = 11.21 M2
J2 = 1.42 x 1.62 x 1.00 = 2.30 M2
J2A = 1.12 x 2.95 x 2.00 = 6.61 M2
J.ROLLING = 1.00 x 0.85 x 4.00 = 3.40 M2
J.TERAS = 1.27 x 2.20 x 2.00 = 5.59 M2
keramik dinding = 157.12 = 157.12 M2
B 215.51 M2

VOL.AKHIR = A - B
= 518.17 - 215.51 = 302.66 M2
3 CAT DINDING (Luar) - BARU VOL. = P x T x JMH 93.01 M2
A samping = 11.30 x 4.40 x 1.00 = 49.72 M2
= 3.00 x 4.40 x 1.00 = 13.20 M2
depan = 3.00 x 4.40 x 2.00 = 26.40 M2
= 10.50 x 0.40 x 1.00 = 4.20 M2
kolom = 1.00 x 3.20 x 2.00 = 6.40 M2
Lisplank = 20.50 x 1.00 x 1.00 = 20.50 M2
sunscren = 7.20 x 0.68 x 2.00 = 9.79 M2
A 130.21 M2

B
Lbg kusen = L x T x JMH
J2 = 1.42 x 1.62 x 1.00 = 2.30 M2
J2A = 1.12 x 2.95 x 2.00 = 6.61 M2
J - Teras = 1.27 x 2.20 x 2.00 = 5.59 M2
keramik dinding = 22.70 = 22.70 M2
B 37.20 M2
VOL.AKHIR = A - B
= 130.21 - 37.20 = 93.01 M2

C DINDING TEAKBLOK
KEB. TEAKBLOK VOL. = P x L x JMH 3.10 M2
Meja Meja = 1.00 x 0.43 x 1.00 = 0.43 M2 1.07 Lbr
bok bawah = 0.90 x 0.20 x 2.00 = 0.36 M2
= 0.25 x 0.20 x 2.00 = 0.10 M2
Tiang = 1.00 x 0.20 x 2.00 = 0.40 M2
Bok atas ambang = 1.00 x 0.43 x 1.00 = 0.43 M2
bok = 0.90 x 0.50 x 2.00 = 0.90 M2
= 0.90 x 0.25 x 1.00 = 0.23 M2
= 0.25 x 0.50 x 2.00 = 0.25 M2
3.10 M2

KEB. TEAKBLOK VOL. = P x L x JMH 2.87 M2


Meja Meja = 1.00 x 0.43 x 1.00 = 0.43 M2 0.99 Lbr
bok bawah = 0.90 x 0.20 x 1.00 = 0.18 M2
= 0.25 x 0.20 x 2.00 = 0.10 M2
Tiang = 1.00 x 0.20 x 4.00 = 0.80 M2
Bok atas ambang = 1.00 x 0.43 x 1.00 = 0.43 M2
bok = 0.90 x 0.50 x 1.00 = 0.45 M2
= 0.90 x 0.25 x 1.00 = 0.23 M2
= 0.25 x 0.50 x 2.00 = 0.25 M2
2.87 M2

KOEFESIEN BESI PLAT LANTAI VOL. dihitung bersih


1 PLAT BETON T. 12CM VOL. = P X L X T 2.24 M3
300 X 700 300 - 25 = 2.75 x 6.80 x 0.12 = 2.24 M3

VOL. = P x JMH besi x Berat BS x SISI 97.38 Kg/M3


KOLAMAN Ø10-12,5 3.00 = 3.10 x 28.00 x 0.62 x 1.00 = 53.51 Kg
7.00 = 7.10 x 13.00 x 0.62 x 1.00 = 56.90 Kg
TUL.SUSUT Ø 8MM-15 3.00 = 3.00 x 20.00 x 0.39 x 2.00 = 47.35 Kg
7.00 = 7.00 x 11.00 x 0.39 x 2.00 = 60.76 Kg
218.52 kg

VII PEKERJAAN INSTALASI PIPA


1 PIPA PVC Ø 3/4'' - ALIRAN VOL. = P/L x JMH 47.50 M1
Dr instalasi lama = 15.00 x 1.00 = 15.00 M1
sambungan = 16.50 x 1.00 = 16.50 M1
= 6.00 x 2.00 = 12.00 M1
= 4.00 x 1.00 = 4.00 M1
47.50 M1

2 PIPA PVC Ø 1/2'' - washtafle VOL. = P/L x JMH 8.00 M1


Ke washtafle = 2.00 x 4.00 = 8.00 M1
8.00 M1

3 PIPA PVC Ø 2'' - washtafle VOL. = P/L x JMH 28.00 M1


Ke washtafle = 1.50 x 4.00 = 6.00 M1
= 4.00 x 2.00 = 8.00 M1
= 3.00 x 2.00 = 6.00 M1
= 4.00 x 2.00 = 8.00 M1
28.00 M1

4 PIPA PVC Ø 3'' VOL. = P/L x JMH 17.00 M1


Dari lt 2 ke lt.1 = 5.00 x 1.00 = 5.00 M1
Ke peresapan = 12.00 x 1.00 = 12.00 M1
17.00 M1
BACK UP VOLUME
LANTAI 1
PEKERJAAN #REF!
LOKASI #REF!
TAHUN #REF!

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME


1 2 3 4

I PEKERJAAN BONGKAR
1 BONGKAR ATAP GENTENG VOL. = P x L x SISI 370.01 M2
Depan Traves. 1 = 14.30 x 4.33 x 1.00 = 61.92 M2
Traves. 2 = 8.05 x 4.33 x 1.00 = 34.86 M2
Samping kiri Traves. 3 = 18.65 x 2.94 x 1.00 = 54.83 M2
Traves. 4 = 13.05 x 4.33 x 1.00 = 56.51 M2
Samping kanan Traves. 5 = 8.55 x 2.94 x 1.00 = 25.14 M2
ketupat = 6.00 x 4.33 x 1.00 = 25.98 M2
Segitiga = 5.10 x 2.94 x 0.50 = 7.50 M2
Belakang Traves. 6 = 15.20 x 2.94 x 1.00 = 44.69 M2
ketupat = 11.80 x 4.33 x 1.00 = 51.09 M2
Segitiga = 5.10 x 2.94 x 0.50 = 7.50 M2
370.01 M2
Batas sampai Lorong
2 BONGKAR KUSEN/DINDING VOL. = P x L x SISI 60.31 M2
Kusen P1 = 0.90 x 2.50 x 8.00 = 18.00 M2
JF1 = 0.80 x 1.65 x 3.00 = 3.96 M2
JF2 = 1.55 x 1.65 x 7.00 = 17.90 M2
Dinding kedudukan Kusen baru P1 = 0.90 x 1.00 x 8.00 = 7.20 M2
JF1 = 0.80 x 1.00 x 3.00 = 2.40 M2
JF2 = 1.55 x 1.00 x 7.00 = 10.85 M2
60.31 M2

3 BONGKAR KOLOM LAMA VOL. = P x DIMENSI x JMH 0.29 M3


Penyambungan kolom K.selasar = 0.40 x 0.15 x 0.20 x 8.00 = 0.10 M3
K.praktis = 0.40 x 0.13 x 0.13 x 22.00 = 0.15 M3
K.depan = 0.40 x 0.13 x 0.13 x 6.00 = 0.04 M3
0.29 M3

I PEKERJAAN PASANGAN/PLEST.
1 Trasram Bata 1/2 bt VOL. = P x L x SISI 7.86 M2
Peninggian dinding bata 20cm
1.50 = 1.50 x 0.30 x 2.00 = 0.90 M2
6.00 = 6.00 x 0.30 x 1.00 = 1.80 M2
14.20 = 14.20 x 0.30 x 1.00 = 4.26 M2
1.50 = 1.50 x 0.30 x 2.00 = 0.90 M2
7.86 M2

2 Dinding Bata 1/2 bt VOL. = P x L x SISI 116.71 M2


Peninggian dinding bata
Kusen yg dibongkar P1 = 0.90 x 1.00 x 8.00 = 7.20 M2
JF1 = 0.80 x 1.00 x 3.00 = 2.40 M2
JF2 = 1.55 x 1.00 x 7.00 = 10.85 M2
Peninggian dinding bata memanjang = 3.00 x 0.80 x 4.00 = 9.60 M2
= 6.10 x 0.80 x 4.00 = 19.52 M2
melintang = 3.10 x 0.80 x 4.00 = 9.92 M2
= 6.70 x 0.80 x 1.00 = 5.36 M2
= 9.80 x 0.80 x 1.00 = 7.84 M2
= 6.00 x 0.80 x 1.00 = 4.80 M2
= 9.10 x 0.80 x 1.00 = 7.28 M2
gevel - lorong = 4.50 x 1.58 x 0.50 = 3.54 M2
Peninggian dinding bata depan = 14.20 x 2.00 x 1.00 = 28.40 M2
116.71 M2

3 Plest.Dinding Bata VOL. = LUAS x SISI 233.43 M2


= 116.71 X 2.00 = 233.43 M2

4 Plest.Trasram Bata VOL. = LUAS x SISI 15.72 M2


= 7.86 X 2.00 = 15.72 M2
II PEKERJAAN BETON
1 KOLOM PRAKTIS 10/10 VOL. = T x JMH 55.00 M1
Sambungan kolom 10/10 = 1.50 x 22.00 = 33.00 M1
= 2.50 x 6.00 = 15.00 M1
kolom 10/10 baru = 3.50 x 2.00 = 7.00 M1
55.00 M1

2 KOLOM BETON 15/20 VOL. = P x DIMENSI x JMH 0.36 M3


Penyambungan kolom K.selasar = 1.50 x 0.15 x 0.20 x 8.00 = 0.36 M3
0.36 M3

3 BALOK GANTUNG BETON 10/20 VOL. = P x DIMENSI x JMH 0.28 M3


DEPAN ENTRANCE = 4.10 x 0.10 x 0.20 x 2.00 = 0.16 M3
= 2.00 x 0.10 x 0.20 x 3.00 = 0.12 M3
0.28 M3

4 BALOK 10/15 - Diatas kusen VOL. = P x JMH 27.60 M1


P1 = 1.20 x 8.00 = 9.60 M1
J1 = 1.00 x 4.00 = 4.00 M1
J2 = 2.00 x 7.00 = 14.00 M1
27.60 M1

5 BALOK 10/15 - TOP RING depan VOL. = P x JMH 26.20 M1


= 14.20 x 1.00 = 14.20 M1
= 1.50 x 2.00 = 3.00 M1
Gevel = 3.50 x 1.00 = 3.50 M1
= 5.50 x 1.00 = 5.50 M1
26.20 M1

6 RINGBALK BETON 10/20 VOL. = P x DIMENSI x JMH 2.52 M3


memanjang 4.50 = 4.50 x 0.10 x 0.20 x 2.00 = 0.18 M3
3.00 = 3.00 x 0.10 x 0.20 x 2.00 = 0.12 M3
14.20 = 14.20 x 0.10 x 0.20 x 3.00 = 0.85 M3
6.00 = 6.00 x 0.10 x 0.20 x 1.00 = 0.12 M3
melintang 11.30 = 11.30 x 0.10 x 0.20 x 1.00 = 0.23 M3
6.70 = 6.70 x 0.10 x 0.20 x 2.00 = 0.27 M3
4.50 = 4.50 x 0.10 x 0.20 x 2.00 = 0.18 M3
3.00 = 3.00 x 0.10 x 0.20 x 2.00 = 0.12 M3
6.00 = 6.00 x 0.10 x 0.20 x 2.00 = 0.24 M3
10.60 = 10.60 x 0.10 x 0.20 x 1.00 = 0.21 M3
2.52 M3

7 Plest. Beton VOL. = T x Kllg x SISI 19.75 M2


Kolom peninggian selasar 15/20 = 1.50 x 0.70 x 8.00 = 8.40 M2
K.10/10 = 3.00 x 0.39 x 2.00 = 2.34 M2
Blk gantung = 1.50 x 0.53 x 2.00 = 1.59 M2
= 2.00 x 0.53 x 3.00 = 3.18 M2
= 4.00 x 0.53 x 2.00 = 4.24 M2
19.75 M2

III PEKERJAAN KERAMIK


1 LANTAI KERAMIK VOL. = P x L x JMH 129.77 M2
DALAM RUANG R.Gizi = 3.00 x 3.30 x 1.00 = 9.90 M2
R.Promkes = 3.00 x 3.40 x 1.00 = 10.20 M2
R.Obat = 4.10 x 3.10 x 1.00 = 12.71 M2
R.Apotik = 2.00 x 3.10 x 1.00 = 6.20 M2
R.Loket = 2.00 x 3.10 x 1.00 = 6.20 M2
Poli umum = 4.10 x 3.10 x 1.00 = 12.71 M2
Laboratorium = 3.00 x 3.90 x 1.00 = 11.70 M2
R.Sample = 3.00 x 2.10 x 1.00 = 6.30 M2
SELASAR 1 = 1.50 x 6.70 x 1.00 = 10.05 M2
2 = 5.00 x 1.50 x 1.00 = 7.50 M2
3 = 1.50 x 6.00 x 1.00 = 9.00 M2
4 = 2.00 x 3.00 x 1.00 = 6.00 M2
ENTRANCE 5 = 14.20 x 1.50 x 1.00 = 21.30 M2
129.77 M2

IV PEKERJAAN PLAFOND
1 PLAFOND KALSIBOARD - DALAM VOL. = P x L x JMH 75.92 M2
DALAM RUANG R.Gizi = 3.00 x 3.30 x 1.00 = 9.90 M2
R.Promkes = 3.00 x 3.40 x 1.00 = 10.20 M2
R.Obat = 4.10 x 3.10 x 1.00 = 12.71 M2
R.Apotik = 2.00 x 3.10 x 1.00 = 6.20 M2
R.Loket = 2.00 x 3.10 x 1.00 = 6.20 M2
Poli umum = 4.10 x 3.10 x 1.00 = 12.71 M2
Laboratorium = 3.00 x 3.90 x 1.00 = 11.70 M2
R.Sample = 3.00 x 2.10 x 1.00 = 6.30 M2
75.92 M2

2 PLAFOND KALSIBOARD - LUAR VOL. = P x L x JMH 90.16 M2


SELASAR 1 = 8.00 x 2.20 x 1.00 = 17.60 M2
2 = 4.50 x 2.20 x 1.00 = 9.90 M2
3 = 3.80 x 2.20 x 1.00 = 8.36 M2
lorong = 2.00 x 3.00 x 1.00 = 6.00 M2
ENTRANCE = 14.20 x 1.50 x 1.00 = 21.30 M2
Overstek samp.kiri = 10.80 x 1.00 x 1.00 = 10.80 M2
Overstek samp.kanan = 11.10 x 1.00 x 1.00 = 11.10 M2
= 5.10 x 1.00 x 1.00 = 5.10 M2
90.16 M2

3 LISTPLAFOND GYPSUM - DALAM VOL. = P x JMH 98.00 M1


DALAM RUANG R.Gizi = 12.60 x 1.00 = 12.60 M1
R.Promkes = 12.80 x 1.00 = 12.80 M1
R.Obat = 14.20 x 1.00 = 14.20 M1
R.Apotik = 10.00 x 1.00 = 10.00 M1
R.Loket = 10.00 x 1.00 = 10.00 M1
Poli umum = 14.20 x 1.00 = 14.20 M1
Laboratorium = 14.00 x 1.00 = 14.00 M1
R.Sample = 10.20 x 1.00 = 10.20 M1
98.00 M1

4 LISTPLAFOND GYPSUM - LUAR VOL. = P x JMH 83.80 M1


PINGGIR TEMBOK Selasar = 8.70 x 1.00 = 8.70 M1
= 6.00 x 1.00 = 6.00 M1
= 6.00 x 1.00 = 6.00 M1
lorong = 6.00 x 1.00 = 6.00 M1
Entrance = 31.40 x 1.00 = 31.40 M1
Overstek S.Kr = 10.80 x 1.00 = 10.80 M1
Overstek S.Kn = 14.90 x 1.00 = 14.90 M1
83.80 M1

5 LISTPLAFOND GYPSUM - LUAR VOL. = P x JMH 42.40 M1


PINGGIR LISPLANK Selasar = 6.50 x 1.00 = 6.50 M1
= 5.00 x 1.00 = 5.00 M1
= 3.80 x 1.00 = 3.80 M1
Overstek S.Kr = 10.80 x 1.00 = 10.80 M1
Overstek S.Kn = 16.30 x 1.00 = 16.30 M1
42.40 M1

III PEKERJAAN KUSEN ALUM.


1 KUSEN ALUMINIUM VOL. = P x JMH 149.44 M1
P1 = 6.72 x 8.00 = 53.76 M1
J1 = 5.08 x 4.00 = 20.32 M1
J2 = 8.52 x 7.00 = 59.64 M1
J.Loket = 7.86 x 2.00 = 15.72 M1
149.44 M1

2 DAUN JENDELA/VENTILASI VOL. = L x T x JMH 22.72 M2


P1 ventilasi = 0.80 x 0.40 x 8.00 = 2.56 M2
J1 venti;asi = 0.60 x 0.40 x 4.00 = 0.96 M2
jendela = 0.60 x 1.00 x 4.00 = 2.40 M2
J2 venti;asi = 0.60 x 1.00 x 14.00 = 8.40 M2
jendela = 0.60 x 1.00 x 14.00 = 8.40 M2
22.72 M2
3 KACA BENING VOL. = L x T x SISI x JMH 2.36 M2
J.LOKET = 0.72 x 0.82 x 2.00 x 2.00 = 2.36 M2
2.36 M2

4 DAUN PINTU PANEL VOL. = L x T x JMH 12.80 M2


P1 = 0.80 x 2.00 x 8.00 = 12.80 M2
12.80 M2

IV PEKERJAAN BESI
1 ENGSEL PINTU VOL. = MASING 2 x JMH 24.00 BH
P1 = 3.00 x 8.00 = 24.00 BH
24.00 BH

2 ENGSEL JENDELA VOL. = MASING 2 x JMH 88.00 BH


J1 ventilasi = 2.00 x 4.00 = 8.00 BH
jendela = 2.00 x 4.00 = 8.00 BH
J2 ventilasi = 4.00 x 7.00 = 28.00 BH
jendela = 4.00 x 7.00 = 28.00 BH
P1 ventilasi = 2.00 x 8.00 = 16.00 BH
88.00 BH

3 HAAG ANGIN VOL. = MASING 2 x JMH 88.00 BH

4 GRENDEL JENDELA VOL. = MASING 2 x JMH 88.00 BH

5 KUNCI TANAM VOL. = MASING 2 x JMH 8.00 BH


P1 = 1.00 x 8.00 = 8.00 BH
8.00 BH

V PEKERJAAN PENGECATAN
1 POLITURAN DAUN PINTU VOL. = L x T x SISI x JMH 25.60 M2
KP1 pintu = 0.80 x 2.00 x 2.00 x 8.00 = 25.60 M2

2 CAT DINDING (Dalam) Luas = P x T x JMH 158.27 M2


R.Gizi = 12.60 x 1.75 x 1.00 = 22.05 M2
R.Promkes = 12.80 x 1.75 x 1.00 = 22.40 M2
R. Obat = 14.20 x 1.75 x 1.00 = 24.85 M2
R.Apotik = 10.00 x 1.75 x 1.00 = 17.50 M2
Loket = 10.00 x 1.75 x 1.00 = 17.50 M2
Poli Umum = 14.20 x 1.75 x 1.00 = 24.85 M2
Laboratorium = 13.80 x 1.75 x 1.00 = 24.15 M2
R.Sample = 10.20 x 1.75 x 1.00 = 17.85 M2
A 171.15 M2

B
Lbg kusen = L x T x JMH
P1 = 0.88 x 0.98 x 8.00 = 6.90 M2
J1 = 0.68 x 0.50 x 4.00 = 1.36 M2
J2 = 1.32 x 0.50 x 7.00 = 4.62 M2
B 12.88 M2

VOL.AKHIR = A - B
= 171.15 - 12.88 = 158.27 M2
I PEKERJAAN TANAH
1 GALIAN PONDASI SETEMPAT VOL. = P x L x T x JMH 162.84 M3
1.1 Pondasi 250x250 = 2.70 x 2.70 x 2.20 x 4.00 = 64.15 M3
1.2 Pondasi 200x200 = 2.20 x 2.20 x 2.20 x 2.00 = 21.30 M3
1.3 Pondasi 175x175 = 1.95 x 1.95 x 2.20 x 4.00 = 33.46 M3
1.4 Pondasi 150x150 = 1.70 x 1.70 x 2.20 x 4.00 = 25.43 M3
1.5 Pondasi 125x125 = 1.45 x 1.45 x 2.20 x 4.00 = 18.50 M3
162.84 M3

2 GALIAN BATU KALI VOL. = P x L x T x JMH 85.50 M3


memanjang 4.75 = 4.75 x 0.90 x 0.80 x 4.00 = 13.68 M3
3.00 = 3.00 x 0.90 x 0.80 x 6.00 = 12.96 M3
1.75 = 1.75 x 0.90 x 0.80 x 3.00 = 3.78 M3
11.00 = 11.00 x 0.90 x 0.80 x 1.00 = 7.92 M3
4.50 = 4.50 x 0.90 x 0.80 x 2.00 = 6.48 M3
melintang 6.40 = 6.40 x 0.90 x 0.80 x 2.00 = 9.22 M3
4.00 = 4.00 x 0.90 x 0.80 x 2.00 = 5.76 M3
4.10 = 4.10 x 0.90 x 0.80 x 2.00 = 5.90 M3
3.00 = 3.00 x 0.90 x 0.80 x 2.00 = 4.32 M3
1.50 = 1.50 x 0.90 x 0.80 x 2.00 = 2.16 M3
4.50 = 4.50 x 0.90 x 0.80 x 1.00 = 3.24 M3
7.00 = 7.00 x 0.90 x 0.80 x 2.00 = 10.08 M3
85.50 M3

3 PASIR URUG POND.SETEMPAT VOL. = P x L x T x JMH 7.40 M3


1.1 Pondasi 250x250 = 2.70 x 2.70 x 0.10 x 4.00 = 2.92 M3
1.2 Pondasi 200x200 = 2.20 x 2.20 x 0.10 x 2.00 = 0.97 M3
1.3 Pondasi 175x175 = 1.95 x 1.95 x 0.10 x 4.00 = 1.52 M3
1.4 Pondasi 150x150 = 1.70 x 1.70 x 0.10 x 4.00 = 1.16 M3
1.5 Pondasi 125x125 = 1.45 x 1.45 x 0.10 x 4.00 = 0.84 M3
7.40 M3

4 PASIR URUG BATU KALI VOL. = P x L x T x JMH 10.69 M3


memanjang 4.75 = 4.75 x 0.90 x 0.10 x 4.00 = 1.71 M3
3.00 = 3.00 x 0.90 x 0.10 x 6.00 = 1.62 M3
1.75 = 1.75 x 0.90 x 0.10 x 3.00 = 0.47 M3
11.00 = 11.00 x 0.90 x 0.10 x 1.00 = 0.99 M3
4.50 = 4.50 x 0.90 x 0.10 x 2.00 = 0.81 M3
melintang 6.40 = 6.40 x 0.90 x 0.10 x 2.00 = 1.15 M3
4.00 = 4.00 x 0.90 x 0.10 x 2.00 = 0.72 M3
4.10 = 4.10 x 0.90 x 0.10 x 2.00 = 0.74 M3
3.00 = 3.00 x 0.90 x 0.10 x 2.00 = 0.54 M3
1.50 = 1.50 x 0.90 x 0.10 x 2.00 = 0.27 M3
4.50 = 4.50 x 0.90 x 0.10 x 1.00 = 0.41 M3
7.00 = 7.00 x 0.90 x 0.10 x 2.00 = 1.26 M3
10.69 M3

5 PASIR URUG DIBAWAH LANTAI VOL. = P x L x T x JMH 37.09 M3


= 11.00 x 7.00 x 0.10 x 1.00 = 7.70 M3
= 23.00 x 10.50 x 0.10 x 1.00 = 24.15 M3
= 1.75 x 6.40 x 0.10 x 2.00 = 2.24 M3
= 5.00 x 6.00 x 0.10 x 1.00 = 3.00 M3
37.09 M3

6 TANAH URUG DIBAWAH LANTAI VOL. = P x L x T x JMH 378.32 M3


= 11.00 x 7.00 x 1.02 x 1.00 = 78.54 M3
= 23.00 x 10.50 x 1.02 x 1.00 = 246.33 M3
= 1.75 x 6.40 x 1.02 x 2.00 = 22.85 M3
= 5.00 x 6.00 x 1.02 x 1.00 = 30.60 M3
378.32 M3
7 BATU KOSONG VOL. = P x L x T x JMH 25.34 M3
memanjang 4.75 = 4.75 x 0.90 x 0.20 x 4.00 = 3.42 M3
3.00 = 3.00 x 0.90 x 0.20 x 6.00 = 3.24 M3
1.75 = 1.75 x 0.90 x 0.20 x 3.00 = 0.95 M3
11.00 = 11.00 x 0.90 x 0.20 x 1.00 = 1.98 M3
4.50 = 4.50 x 0.90 x 0.20 x 2.00 = 1.62 M3
5.00 = 5.00 x 0.90 x 0.20 x 2.00 = 1.80 M3
melintang 6.40 = 6.40 x 0.90 x 0.20 x 2.00 = 2.30 M3
4.00 = 4.00 x 0.90 x 0.20 x 2.00 = 1.44 M3
4.10 = 4.10 x 0.90 x 0.20 x 2.00 = 1.48 M3
3.00 = 3.00 x 0.90 x 0.20 x 2.00 = 1.08 M3
1.50 = 1.50 x 0.90 x 0.20 x 2.00 = 0.54 M3
4.50 = 4.50 x 0.90 x 0.20 x 1.00 = 0.81 M3
7.00 = 7.00 x 0.90 x 0.20 x 2.00 = 2.52 M3
6.00 = 6.00 x 0.90 x 0.20 x 2.00 = 2.16 M3
25.34 M3

8 PONDASI BATU KALI VOL. = P x L x T x JMH 66.86 M3


memanjang 4.75 = 4.75 x 0.48 x 1.00 x 4.00 = 9.03 M3
3.00 = 3.00 x 0.48 x 1.00 x 6.00 = 8.55 M3
1.75 = 1.75 x 0.48 x 1.00 x 3.00 = 2.49 M3
11.00 = 11.00 x 0.48 x 1.00 x 1.00 = 5.23 M3
4.50 = 4.50 x 0.48 x 1.00 x 2.00 = 4.28 M3
5.00 = 5.00 x 0.48 x 1.00 x 2.00 = 4.75 M3
melintang 6.40 = 6.40 x 0.48 x 1.00 x 2.00 = 6.08 M3
4.00 = 4.00 x 0.48 x 1.00 x 2.00 = 3.80 M3
4.10 = 4.10 x 0.48 x 1.00 x 2.00 = 3.90 M3
3.00 = 3.00 x 0.48 x 1.00 x 2.00 = 2.85 M3
1.50 = 1.50 x 0.48 x 1.00 x 2.00 = 1.43 M3
4.50 = 4.50 x 0.48 x 1.00 x 1.00 = 2.14 M3
7.00 = 7.00 x 0.48 x 1.00 x 2.00 = 6.65 M3
6.00 = 6.00 x 0.48 x 1.00 x 2.00 = 5.70 M3
66.86 M3

II PEK. BETON TAK BERTULANG


1 RABAT BETON BWAH LANTAI VOL. = P x L x T x JMH 16.69 M3
= 11.00 x 7.00 x 0.05 x 1.00 = 3.47 M3
= 23.00 x 10.50 x 0.05 x 1.00 = 10.87 M3
= 1.75 x 6.40 x 0.05 x 2.00 = 1.01 M3
= 5.00 x 6.00 x 0.05 x 1.00 = 1.35 M3
16.69 M3

2 LANTAI KERJA PONDASI VOL. = P x L x T x JMH 5.29 M3


1.1 Pondasi 250x250 = 2.70 x 2.70 x 0.07 x 4.00 = 2.04 M3
1.2 Pondasi 200x200 = 2.20 x 2.20 x 0.07 x 2.00 = 0.68 M3
1.3 Pondasi 175x175 = 1.95 x 1.95 x 0.07 x 4.00 = 1.06 M3
1.4 Pondasi 150x150 = 1.70 x 1.70 x 0.07 x 4.00 = 0.81 M3
1.5 Pondasi 125x125 = 1.45 x 1.45 x 0.07 x 4.00 = 0.59 M3
1.6 Pondasi tangga = 1.50 x 1.00 x 0.07 x 1.00 = 0.11 M3
5.29 M3

3 LANTAI KERJA SLOOF VOL. = P x L x T x JMH 1.35 M3


Memanjang 3.00 = 2.75 x 0.30 x 0.05 x 6.00 = 0.25 M3
5.00 = 4.75 x 0.30 x 0.05 x 3.00 = 0.21 M3
Melintang 4.00 = 3.75 x 0.30 x 0.05 x 6.00 = 0.34 M3
6.50 = 6.10 x 0.30 x 0.05 x 6.00 = 0.55 M3
1.35 M3

III PEK. BETON BERTULANG


1 SLOOF 20/30 VOL. = P x L x T x JMH 6.38 M3
Memanjang 3.00 = 2.75 x 0.20 x 0.30 x 12.00 = 1.98 M3
5.00 = 4.75 x 0.20 x 0.30 x 3.00 = 0.86 M3
Melintang 4.00 = 3.75 x 0.20 x 0.30 x 6.00 = 1.35 M3
6.50 = 6.10 x 0.20 x 0.30 x 6.00 = 2.20 M3
6.38 M3

Begisting = 0.30 + 0.30 x 1.00 x 106.35 = 63.81 M2 10.00 M2/M3

Pembesian 6 D 16mm = 1.58 x 6.00 x 106.35 = 1,007.07 KG 157.82 KG/M3

Ø 8 -15 = 0.39 x 0.90 x 709.00 = 251.77 KG 39.46 KG/M3


2 SLOOF 15/20 VOL. = P x L x T x JMH 5.71 M3
Memanjang 4.75 = 4.75 x 0.15 x 0.20 x 4.00 = 0.57 M3
3.00 = 3.00 x 0.15 x 0.20 x 7.00 = 0.63 M3
1.75 = 1.75 x 0.15 x 0.20 x 4.00 = 0.21 M3
11.00 = 11.00 x 0.15 x 0.20 x 4.00 = 1.32 M3
4.50 = 4.50 x 0.15 x 0.20 x 2.00 = 0.27 M3
6.94 = 6.94 x 0.15 x 0.20 x 1.00 = 0.21 M3
5.00 = 5.00 x 0.15 x 0.20 x 2.00 = 0.30 M3
Melintang 7.90 = 7.90 x 0.15 x 0.20 x 2.00 = 0.47 M3
10.50 = 10.50 x 0.15 x 0.20 x 2.00 = 0.63 M3
4.50 = 4.50 x 0.15 x 0.20 x 1.00 = 0.14 M3
1.50 = 1.50 x 0.15 x 0.20 x 2.00 = 0.09 M3
1.60 = 1.60 x 0.15 x 0.20 x 2.00 = 0.10 M3
7.00 = 7.00 x 0.15 x 0.20 x 2.00 = 0.42 M3
6.00 = 6.00 x 0.15 x 0.20 x 2.00 = 0.36 M3
5.71 M3

Begisting = 0.20 + 0.20 x 1.00 x 190.44 = 76.18 M2 13.33 M2/M3

Pembesian 4 D 12mm = 0.89 x 4.00 x 190.44 = 676.26 KG 170.98 KG/M3


Ø 8 -15 = 0.39 x 0.60 x 1,269.60 = 300.56 KG
976.82 KG

3 PONDASI FOOTPLAT 250x250 VOL. = P x L x T x JMH 7.50 M3


= 2.50 x 2.50 x 0.30 x 4.00 = 7.50 M3
7.50 M3

Begisting = 2.50 + 2.50 x 2.00 x 4.00 x 0.25 = 10.00 M2 1.33 M2/M3

Pembesian D16 - 125 = 1.58 x 2.50 x 21.00 x 4.00 x 2.00 = 662.86 KG 88.38 KG/M3

Ø 10 -125 = 0.62 x 3.30 x 21.00 x 4.00 x 2.00 = 341.79 KG 45.57 KG/M3

4 PONDASI FOOTPLAT 200x200 VOL. = P x L x T x JMH 2.40 M3


= 2.00 x 2.00 x 0.30 x 2.00 = 2.40 M3
2.40 M3

Begisting = 2.00 + 2.00 x 2.00 x 2.00 x 0.25 = 4.00 M2 1.67 M2/M3

Pembesian D16 - 125 = 1.58 x 2.00 x 17.00 x 2.00 x 2.00 = 214.64 KG 89.43 KG/M3

Ø 10 -15 = 0.62 x 2.80 x 17.00 x 2.00 x 2.00 = 117.38 KG 48.91 KG/M3

5 PONDASI FOOTPLAT 175x175 VOL. = P x L x T x JMH 3.68 M3


= 1.75 x 1.75 x 0.30 x 4.00 = 3.68 M3
3.68 M3

Begisting = 1.75 + 1.75 x 2.00 x 4.00 x 0.25 = 7.00 M2 1.90 M2/M3

Pembesian D13 - 15 = 1.04 x 1.75 x 15.00 x 4.00 x 2.00 = 218.80 KG 59.54 KG/M3

Ø 10 -15 = 0.62 x 2.55 x 15.00 x 4.00 x 2.00 = 188.65 KG 51.33 KG/M3

6 PONDASI FOOTPLAT 150x150 VOL. = P x L x T x JMH 2.70 M3


= 1.50 x 1.50 x 0.30 x 4.00 = 2.70 M3
2.70 M3

Begisting = 1.50 + 1.50 x 2.00 x 4.00 x 0.25 = 6.00 M2 2.22 M2/M3

Pembesian D13 - 15 = 1.04 x 1.50 x 13.00 x 4.00 x 2.00 = 162.53 KG 60.20 KG/M3

Ø 10 -15 = 0.62 x 2.30 x 13.00 x 4.00 x 2.00 = 147.47 KG 54.62 KG/M3

7 PONDASI FOOTPLAT 125x125 VOL. = P x L x T x JMH 1.88 M3


= 1.25 x 1.25 x 0.30 x 4.00 = 1.88 M3
1.88 M3

Begisting = 1.25 + 1.25 x 2.00 x 4.00 x 0.25 = 5.00 M2 2.67 M2/M3

Pembesian D13 - 15 = 1.04 x 1.25 x 11.00 x 4.00 x 2.00 = 114.61 KG 61.12 KG/M3

Ø 10 -15 = 0.62 x 2.05 x 11.00 x 4.00 x 2.00 = 111.22 KG 59.32 KG/M3

8 PONDASI FOOTPLAT TANGGA VOL. = P x L x T x JMH 0.41 M3


= 1.50 x 1.00 x 0.28 x 1.00 = 0.41 M3
0.41 M3

9 KOLOM BETON 40/40 VOL. = P x DIMENSI x JMH 1.81 M3


Bawah Lantai = 2.83 x 0.40 x 0.40 x 4.00 = 1.81 M3
1.81 M3

10 KOLOM BETON 25/40 VOL. = P x DIMENSI x JMH 2.26 M3


Bawah Lantai = 2.83 x 0.25 x 0.40 x 8.00 = 2.26 M3
2.26 M3

11 KOLOM BETON 30/30 - type 1 VOL. = P x DIMENSI x JMH 0.50 M3


Bawah Lantai entrance = 1.40 x 0.30 x 0.30 x 4.00 = 0.50 M3
0.50 M3

12 KOLOM BETON 30/30 - type 2 VOL. = P x DIMENSI x JMH 0.51 M3


Bawah Lantai induk = 2.83 x 0.30 x 0.30 x 2.00 = 0.51 M3
0.51 M3

13 KOLOM BETON 25/30 VOL. = P x DIMENSI x JMH 0.85 M3


Bawah Lantai = 2.83 x 0.25 x 0.30 x 4.00 = 0.85 M3
0.85 M3

14 KOLOM BETON 25/25 VOL. = P x DIMENSI x JMH 1.93 M3


Bawah Lantai samping = 1.40 x 0.25 x 0.25 x 14.00 = 1.23 M3
belkang = 1.40 x 0.25 x 0.25 x 8.00 = 0.70 M3
1.93 M3

14 KOLOM BETON 10/10 VOL. = P x JMH 9.60 M1


Bawah Lantai Induk = 0.40 x 24.00 = 9.60 M1
9.60 M1

15 STEK BESI KOLOM KPONDASI VOL. = P x BJ x Berat x JMH 310.54 KG


K.40/40 = 0.75 x 12.00 x 2.23 x 4.00 = 80.12 KG
K.25/40 = 0.75 x 10.00 x 1.58 x 8.00 = 94.69 KG
K.25/30 = 0.75 x 8.00 x 1.58 x 4.00 = 37.88 KG
K.30/30 = 0.75 x 12.00 x 1.58 x 2.00 = 28.41 KG
samping K.25/25 = 0.25 x 8.00 x 1.58 x 14.00 = 44.19 KG
belakang K.25/25 = 0.25 x 8.00 x 1.58 x 8.00 = 25.25 KG
310.54 KG
III PEK. BETON BERTULANG
Diatas Lantai
1 KOLOM BETON 15/25 VOL. = P x DIMENSI x JMH 0.23 M3
= 3.00 x 0.15 x 0.25 x 2.00 = 0.23 M3
0.23 M3

Begisting = 0.15 + 0.25 x 2.00 x 6.00 = 4.80 M2 21.33 M2/M3

Pembesian 6 D 12mm = 0.888 x 6.00 x 6.00 = 31.96 KG


Ø 6 -15 = 0.222 x 0.70 x 40.00 = 6.21 KG 169.66 KG/M3
38.17 Kg

1 KOLOM BETON 40/40 VOL. = P x DIMENSI x JMH 2.56 M3


= 4.00 x 0.40 x 0.40 x 4.00 = 2.56 M3
2.56 M3

Begisting = 0.40 + 0.40 x 2.00 x 16.00 = 25.60 M2 10.00 M2/M3

Pembesian 12 D 16mm = 1.578 x 12.00 x 16.00 = 303.02 KG 118.37 KG/M3

Ø 10 -15 = 0.617 x 1.50 x 106.67 = 98.64 KG 38.53 KG/M3

2 KOLOM BETON 25/40 VOL. = P x DIMENSI x JMH 3.20 M3


= 4.00 x 0.25 x 0.40 x 8.00 = 3.20 M3
3.20 M3

Begisting = 0.25 + 0.40 x 2.00 x 32.00 = 41.60 M2 13.00 M2/M3

Pembesian 12 D 16mm = 1.578 x 10.00 x 32.00 = 505.04 KG 157.82 KG/M3

Ø 10 -15 = 0.617 x 1.20 x 213.33 = 157.82 KG 49.32 KG/M3

3 KOLOM BETON 25/30 VOL. = P x DIMENSI x JMH 1.20 M3


= 4.00 x 0.25 x 0.30 x 4.00 = 1.20 M3
1.20 M3

Begisting = 0.25 + 0.30 x 2.00 x 16.00 = 17.60 M2 14.67 M2/M3

Pembesian 10 D 16mm = 1.578 x 10.00 x 16.00 = 252.52 KG 210.43 KG/M3

Ø 10 -15 = 0.617 x 1.00 x 106.67 = 65.76 KG 54.80 KG/M3

4 KOLOM BETON 30/30 - Type a VOL. = P x DIMENSI x JMH 1.44 M3


= 4.00 x 0.30 x 0.30 x 4.00 = 1.44 M3
1.44 M3

Begisting = 0.30 + 0.30 x 2.00 x 16.00 = 19.20 M2 13.33 M2/M3

Pembesian 4 D 16mm = 1.578 x 4.00 x 16.00 = 101.01 KG 70.14 KG/M3

Ø 8 -15 = 0.395 x 1.10 x 106.67 = 46.30 KG 32.15 KG/M3

5 KOLOM BETON 30/30 - Type b VOL. = P x DIMENSI x JMH 0.72 M3


= 4.00 x 0.30 x 0.30 x 2.00 = 0.72 M3
0.72 M3

Begisting = 0.30 + 0.30 x 2.00 x 8.00 = 9.60 M2 13.33 M2/M3

Pembesian 12 D 16mm = 1.578 x 12.00 x 8.00 = 151.51 KG 210.43 KG/M3

Ø 10 -15 = 0.617 x 1.10 x 53.33 = 36.17 KG 50.23 KG/M3

6 KOLOM BETON 25/25 VOL. = P x DIMENSI x JMH 5.50 M3


samping = 4.00 x 0.25 x 0.25 x 14.00 = 3.50 M3
belakang = 4.00 x 0.25 x 0.25 x 8.00 = 2.00 M3
5.50 M3

Begisting = 0.25 + 0.25 x 2.00 x 88.00 = 88.00 M2 16.00 M2/M3

Pembesian 8 D 13mm = 1.042 x 8.00 x 88.00 = 733.49 KG 133.36 KG/M3

Ø 8 -15 = 0.395 x 0.90 x 586.67 = 208.33 KG 37.88 KG/M3

7 KOLOM BETON 10/10 VOL. = P x JMH 102.40 M1


Bawah Lantai Induk = 4.00 x 24.00 = 96.00 M1
ralling tangg = 0.80 x 4.00 = 3.20 M1
ralling blkg = 0.80 x 4.00 = 3.20 M1
102.40 M1

8 BALOKRING RALLING 10/15 VOL. = P x JMH 8.00 M1


Tangga = 8.00 x 1.00 = 8.00 M1
8.00 M1
IIIa PEK. BETON PLAT DAK
1 BALOK BETON 20/30 VOL. = P x DIMENSI x JMH 2.17 M3
memanjang 1.75 = 1.75 x 0.20 x 0.30 x 6.00 = 0.63 M3
melintang 4.00 = 4.00 x 0.20 x 0.30 x 4.00 = 0.96 M3
2.40 = 2.40 x 0.20 x 0.30 x 4.00 = 0.58 M3
2.17 M3

2 PLAT DAK BETON T.12CM VOL. = P x DIMENSI x JMH 5.85 M3


Dalam 175X400 = 1.60 x 3.85 x 0.12 x 2.00 = 1.48 M3
175X240 = 1.60 x 2.25 x 0.12 x 2.00 = 0.86 M3
Overstek 175X80 = 1.75 x 0.80 x 0.12 x 4.00 = 0.67 M3
80X(6,4+1,6) = 0.80 x 8.00 x 0.12 x 2.00 = 1.54 M3
Belakang 600X180 = 6.00 x 1.80 x 0.12 x 1.00 = 1.30 M3
5.85 M3

4 LISPLANK T.7CM - sunscren VOL. = P x L x T x JMH 2.84 M3


depan 11.75 = 11.75 x 0.50 x 0.06 x 2.00 = 0.71 M3
samping 19.50 = 19.50 x 0.50 x 0.06 x 2.00 = 1.17 M3
belakang 28.50 = 28.50 x 0.50 x 0.06 x 1.00 = 0.86 M3
1.80 = 1.80 x 0.50 x 0.06 x 2.00 = 0.11 M3
2.84 M3

5 BALOK KS SUNSCREN 20/30 VOL. = P x L x T x JMH 2.14 M3


Pemegang Lisplank - depan 1.00 = 1.00 x 0.20 x 0.25 x 6.00 = 0.30 M3
samping 1.00 = 1.00 x 0.20 x 0.25 x 18.00 = 0.90 M3
Pemegang Lisplank - blkng 1.00 = 1.00 x 0.20 x 0.25 x 8.00 = 0.40 M3
1.80 = 1.80 x 0.20 x 0.25 x 2.00 = 0.18 M3
6.00 = 6.00 x 0.20 x 0.30 x 1.00 = 0.36 M3
2.14 M3

IIIb PEK. BETON RINGBALK


1 RINGBALOK BETON 10/20 VOL. = P x DIMENSI x JMH 2.20 M3
Entrance 5.00 = 5.00 x 0.10 x 0.20 x 2.00 = 0.20 M3
6.00 = 6.00 x 0.10 x 0.20 x 2.00 = 0.24 M3
Bang.belakang 4.50 = 4.50 x 0.10 x 0.20 x 1.00 = 0.09 M3
4.50 = 4.50 x 0.10 x 0.20 x 1.00 = 0.09 M3
Bang.samping 3.00 = 3.00 x 0.10 x 0.20 x 10.00 = 0.60 M3
10.50 = 10.50 x 0.10 x 0.20 x 2.00 = 0.42 M3
1.50 = 1.50 x 0.10 x 0.20 x 2.00 = 0.06 M3
11.00 = 11.00 x 0.10 x 0.20 x 1.00 = 0.22 M3
7.00 = 7.00 x 0.10 x 0.20 x 2.00 = 0.28 M3
2.20 M3

2 RINGBALOK BETON 20/30 VOL. = P x DIMENSI x JMH 1.50 M3


memanjang 11.00 = 11.00 x 0.20 x 0.30 x 1.00 = 0.66 M3
melintang 7.00 = 7.00 x 0.20 x 0.30 x 2.00 = 0.84 M3
1.50 M3

Begisting = 0.30 + 0.30 x 1.00 x 25.00 = 15.00 M2 10.00 M2/M3

Berat x P x Jmh bs x JMH


Pembesian 6 D 16mm = 1.58 x 25.00 x 6.00 x 1.00 = 236.74 KG 157.82 KG/M3
236.74 kG

Ø 8 -125 = 0.39 x 0.90 x 166.67 = 59.18 KG 39.46 KG/M3

3 BALOK GANTUNG 20/50 VOL. = P x DIMENSI x JMH 2.68 M3


memanjang 5.00 = 4.70 x 0.20 x 0.50 x 2.00 = 0.94 M3
Ks = 1.00 x 0.20 x 0.50 x 4.00 = 0.40 M3
melintang 6.00 = 5.70 x 0.20 x 0.50 x 2.00 = 1.14 M3
Ks = 1.00 x 0.20 x 0.50 x 2.00 = 0.20 M3
2.68 M3

Begisting = 0.20 + 1.00 x 1.00 x 26.80 = 32.16 M2 12.00 M2/M3

Berat x P x Jmh bs x JMH


Pembesian 6 D 16mm = 1.58 x 26.80 x 6.00 x 2.00 = 507.56 KG 231.06 KG/M3
2 D 16mm = 1.04 x 26.80 x 2.00 x 2.00 = 111.69 KG
619.25 kG

Ø 8 -125 = 0.39 x 1.30 x 178.67 = 91.64 KG 34.20 KG/M3

4 BALOK LATEI (BL) 10/15 VOL. = P x JMH 50.50 M1


BL 1 5.00 = 5.00 x 1.00 = 5.00 M1
3.00 = 3.00 x 2.00 = 6.00 M1
BL.2 3.00 = 3.00 x 6.00 = 18.00 M1
1.75 = 1.75 x 2.00 = 3.50 M1
4.00 = 4.00 x 1.00 = 4.00 M1
2.50 = 2.50 x 4.00 = 10.00 M1
2.00 = 2.00 x 2.00 = 4.00 M1
50.50 M1
IIIc PEK. BETON PLAT LANTAI
1 BALOK BETON 20/30 - B6 VOL. = P x DIMENSI x JMH 1.98 M3
Memanjang 3.00 = 2.75 x 0.20 x 0.30 x 12.00 = 1.98 M3
1.98 M3

Begisting = 0.20 + 0.36 x 1.00 x 33.00 = 18.48 M2 9.33 M2/M3

Berat x P x Jmh bs x JMH


Pembesian 6 D 16mm = 1.58 x 3.00 x 6.00 x 12.00 = 340.90 KG 172.17 KG/M3
340.90 kG

Ø 10 -125 = 0.62 x 0.90 x 264.00 = 146.48 KG 73.98 KG/M3

2 BALOK BETON 20/30 - Ba VOL. = P x DIMENSI x JMH 1.10 M3


Memanjang 3.00 = 2.75 x 0.20 x 0.30 x 3.00 = 0.50 M3
Melintang 4.00 = 3.75 x 0.20 x 0.30 x 1.00 = 0.23 M3
6.50 = 6.25 x 0.20 x 0.30 x 1.00 = 0.38 M3
1.10 M3

Begisting = 0.20 + 0.36 x 1.00 x 18.25 = 10.22 M2 9.33 M2/M3

Berat x P x Jmh bs x JMH


Pembesian 6 D 16mm = 1.58 x 3.00 x 4.00 x 3.00 = 56.82 KG 112.42 KG/M3
= 1.58 x 4.00 x 4.00 x 1.00 = 25.25 KG
= 1.58 x 6.50 x 4.00 x 1.00 = 41.03 KG
123.10 kG

Ø 8 -125 = 0.39 x 0.90 x 146.00 = 51.85 KG 47.35 KG/M3

2 BALOK BETON 20/50 - B5 VOL. = P x DIMENSI x JMH 1.90 M3


Memanjang 5.00 = 4.75 x 0.20 x 0.50 x 4.00 = 1.90 M3
1.90 M3

Begisting = 0.20 + 0.76 x 1.00 x 19.00 = 18.24 M2 9.60 M2/M3

Berat x P x Jmh bs x JMH


Pembesian 6 D 16mm = 1.58 x 5.00 x 6.00 x 4.00 = 189.39 KG 195.37 KG/M3
2 D 16mm = 1.58 x 2.00 x 6.00 x 4.00 = 75.76 KG
Extra Tump. = 1.58 x 1.50 x 6.00 x 4.00 = 56.82 KG
Extra Lap. = 1.58 x 2.60 x 3.00 x 4.00 = 49.24 KG
371.20 kG

Ø 10 -125 = 0.62 x 1.10 x 152.00 = 103.08 KG 54.25 KG/M3


3 BALOK BETON 25/40 - B4 VOL. = P x DIMENSI x JMH 2.25 M3
Melintang 4.00 = 3.75 x 0.25 x 0.40 x 6.00 = 2.25 M3
2.25 M3

Begisting = 0.25 + 0.56 x 1.00 x 22.50 = 18.23 M2 8.10 M2/M3

Berat x P x Jmh bs x JMH


Pembesian 4 D 16mm = 1.58 x 4.00 x 4.00 x 6.00 = 151.51 KG 164.14 KG/M3
2 D 16mm = 1.58 x 4.00 x 2.00 x 6.00 = 75.76 KG
Extra Tump. = 1.58 x 1.25 x 4.00 x 6.00 = 47.35 KG
Extra Lap. = 1.58 x 2.50 x 4.00 x 6.00 = 94.69 KG
369.31 kG

Ø 10 -125 = 0.62 x 1.20 x 180.00 = 133.16 KG 59.18 KG/M3

4 BALOK BETON 25/60 - B3 VOL. = P x DIMENSI x JMH 5.63 M3


Melintang 6.50 = 6.25 x 0.25 x 0.60 x 6.00 = 5.63 M3
5.63 M3

Begisting = 0.25 + 0.96 x 1.00 x 37.50 = 45.38 M2 8.07 M2/M3

Berat x P x Jmh bs x JMH


Pembesian 6 D 16mm = 1.58 x 6.50 x 5.00 x 6.00 = 307.76 KG 143.66 KG/M3
2 D 16mm = 1.58 x 6.50 x 2.00 x 6.00 = 123.10 KG
Extra Tump. = 2.23 x 2.15 x 5.00 x 6.00 = 143.55 KG
Extra Lap. = 2.23 x 3.50 x 5.00 x 6.00 = 233.68 KG
808.09 kG

Ø 10 -125 = 0.62 x 1.60 x 300.00 = 295.92 KG 52.61 KG/M3

5 BALOK BETON 25/60 - B1 VOL. = P x DIMENSI x JMH 6.75 M3


Melintang 6.50 = 6.25 x 0.30 x 0.60 x 6.00 = 6.75 M3
6.75 M3

Begisting = 0.25 + 0.96 x 1.00 x 45.00 = 54.45 M2 8.07 M2/M3

Berat x P x Jmh bs x JMH


Pembesian 6 D 16mm = 2.23 x 6.50 x 6.00 x 6.00 = 520.78 KG 187.97 KG/M3
6 D 16mm = 1.58 x 6.50 x 2.00 x 6.00 = 123.10 KG
Extra Tump. = 2.23 x 2.15 x 12.00 x 6.00 = 344.52 KG
Extra Lap. = 2.23 x 3.50 x 6.00 x 6.00 = 280.42 KG
1,268.82 kG

Ø 10 -125 = 0.62 x 1.70 x 360.00 = 377.30 KG 55.90 KG/M3

6 PLAT BETON LANTAI T.12CM VOL. = P x L x T x JMH 19.09 M3


300x400 = 2.75 x 3.80 x 0.12 x 4.00 = 5.02 M3
500x400 = 4.75 x 3.80 x 0.12 x 1.00 = 2.17 M3
300x650 = 2.75 x 6.30 x 0.12 x 4.00 = 8.32 M3
500x650 = 4.75 x 6.30 x 0.12 x 1.00 = 3.59 M3
19.09 M3

8 PLAT TANGGA BETON T.15CM VOL. = P x L x T x JMH 2.36 M3


bordes = 3.00 x 1.50 x 0.15 x 1.00 = 0.68 M3
miring = 7.50 x 1.50 x 0.15 x 1.00 = 1.69 M3
2.36 M3

IV PEK. PASANGAN/PLESTERAN
1 PAS. TRASRAM BATA 1/2 BT. VOL. = P x L x JMH 125.48 M2
Memanjang 3.00 = 2.75 x 0.50 x 12.00 = 16.50 M2
3.00 = 3.00 x 0.50 x 5.00 = 7.50 M2
1.75 = 1.50 x 0.50 x 6.00 = 4.50 M2
1.75 = 1.75 x 0.50 x 1.00 = 0.88 M2
trap tangga 1.75 = 1.75 x 0.80 x 10.00 = 14.00 M2
4.50 = 4.50 x 0.50 x 2.00 = 4.50 M2
5.00 = 4.70 x 0.50 x 3.00 = 7.05 M2
11.00 = 11.00 x 0.50 x 1.00 = 5.50 M2
blkng = 6.00 x 0.50 x 1.00 = 3.00 M2
Melintang 6.40 = 6.40 x 0.50 x 2.00 = 6.40 M2
4.00 = 4.00 x 0.50 x 4.00 = 8.00 M2
4.50 = 4.50 x 0.50 x 1.00 = 2.25 M2
4.10 = 4.10 x 0.50 x 3.00 = 6.15 M2
3.00 = 3.00 x 0.50 x 2.00 = 3.00 M2
1.50 = 1.50 x 0.50 x 2.00 = 1.50 M2
1.10 = 1.10 x 0.50 x 1.00 = 0.55 M2
6.00 = 6.00 x 0.50 x 2.00 = 6.00 M2
Tangga samp. 1.50 = 1.50 x 0.50 x 2.00 = 1.50 M2
Teras Blkng Trap = 1.20 x 0.50 x 10.00 = 6.00 M2
anak tangga = 1.50 x 0.03 x 20.00 x 10.00 = 9.00 M2
Ram teras = 3.00 x 1.20 x 2.00 = 7.20 M2
= 4.50 x 0.50 x 2.00 = 4.50 M2
125.48 M3
2 PAS. DINDING BATA 1/2 BT. VOL. = P x L x JMH 499.75 M2
Memanjang
Antar kolom 3.00 = 2.75 x 3.70 x 12.00 = 122.10 M2
3.00 = 3.00 x 3.88 x 5.00 = 58.20 M2
1.75 = 1.50 x 3.70 x 6.00 = 33.30 M2
1.75 = 1.75 x 3.88 x 1.00 = 6.79 M2
4.50 = 4.50 x 3.80 x 1.00 = 17.10 M2
4.50 = 4.50 x 3.88 x 1.00 = 17.46 M2
5.00 = 4.70 x 3.70 x 1.00 = 17.39 M2
5.00 = 4.70 x 0.60 x 2.00 = 5.64 M2
11.00 = 10.75 x 3.70 x 1.00 = 39.78 M2
Melintang 6.40 = 6.15 x 3.70 x 2.00 = 45.51 M2
4.00 = 3.75 x 3.70 x 4.00 = 55.50 M2
4.50 = 4.50 x 3.80 x 1.00 = 17.10 M2
4.10 = 3.85 x 3.70 x 3.00 = 42.74 M2
3.00 = 3.00 x 3.70 x 2.00 = 22.20 M2
1.50 = 1.50 x 3.88 x 2.00 = 11.64 M2
1.10 = 1.10 x 3.70 x 1.00 = 4.07 M2
7.00 = 7.00 x 3.70 x 2.00 = 51.80 M2
blk gtg = 6.00 x 0.60 x 2.00 = 7.20 M2
ralling tangga 8.00 = 8.00 x 0.80 x 1.00 = 6.40 M2
selimut pilar teras bawah = 0.37 x 4.00 = 1.48 M2
pilar bata = 4.00 x 0.90 x 4.00 = 14.40 M2
A 597.79 M2

B
Lbg kusen = L x T x JMH
Pu = 4.60 x 2.75 x 1.00 = 12.65 M2
P1 / PD = 1.50 x 2.60 x 3.00 = 11.70 M2
P2 = 0.90 x 2.60 x 4.00 = 9.36 M2
Pw = 0.80 x 2.05 x 5.00 = 8.20 M2
blk gntng = 1.00 x 2.20 x 3.00 = 6.60 M2
J1 = 0.70 x 1.60 x 2.00 = 2.24 M2
J2 = 1.35 x 1.60 x 12.00 = 25.92 M2
J3 = 2.68 x 3.10 x 2.00 = 16.62 M2
V1 = 0.80 x 0.50 x 8.00 = 3.20 M2
V2 = 1.55 x 0.50 x 2.00 = 1.55 M2
B 98.04 M2

VOL.AKHIR = A - B
= 597.79 - 98.04 = 499.75 M2

3 PLEST. TRASRAM BATA VOL. = LUAS x SISI 250.95 M2


= 125.48 x 2.00 = 250.95 M2

4 PLEST. DINDING BATA VOL. = LUAS x SISI 999.51 M2


= 499.75 x 2.00 = 999.51 M2

5 PLEST. BETON VOL. = P x L x JMH 370.21 M2


Kolom K.25/25 = 4.00 x 1.00 x 22.00 = 88.00 M2
K.25/30 = 4.00 x 1.20 x 6.00 = 28.80 M2
K.25/40 = 4.00 x 1.30 x 8.00 = 41.60 M2
K.30/30 = 4.00 x 1.20 x 8.00 = 38.40 M2
K.40/40 = 4.00 x 1.60 x 4.00 = 25.60 M2
Balok luar - Memanjang B.20/30 = 2.75 x 0.50 x 6.00 = 8.25 M2
B.15/20 = 1.75 x 0.40 x 4.00 = 2.80 M2
B.15/30 = 4.40 x 0.75 x 2.00 = 6.60 M2
Balok luar - Melintang B.15/20 = 2.40 x 0.40 x 2.00 = 1.92 M2
B.15/30 = 4.00 x 0.40 x 2.00 = 3.20 M2
= 5.40 x 0.75 x 2.00 = 8.10 M2
Lisplank sunscren 15.10 = 15.10 x 1.10 x 2.00 = 33.22 M2
28.60 = 28.60 x 1.10 x 2.00 = 62.92 M2
Balok sunscren 1.00 = 1.00 x 0.80 x 26.00 = 20.80 M2
370.21 M2

6 PLEST. BENANGAN VOL. = P x SISI x JMH 1,121.50 M1


Kolom K.25/25 = 4.00 x 4.00 x 22.00 = 352.00 M1
K.25/30 = 4.00 x 4.00 x 6.00 = 96.00 M1
K.25/40 = 4.00 x 4.00 x 8.00 = 128.00 M1
K.30/30 = 4.00 x 4.00 x 8.00 = 128.00 M1
K.40/40 = 4.00 x 4.00 x 4.00 = 64.00 M1
Balok luar - Memanjang B.20/30 = 2.75 x 2.00 x 6.00 = 33.00 M1
B.15/20 = 1.75 x 2.00 x 2.00 = 7.00 M1
Balok luar - Melintang B.25/30 = 3.25 x 2.00 x 3.00 = 19.50 M1
= 3.75 x 2.00 x 2.00 = 15.00 M1
= 4.25 x 2.00 x 2.00 = 17.00 M1
Lisplank 18.75 = 18.75 x 4.00 x 2.00 = 150.00 M1
14.00 = 14.00 x 4.00 x 2.00 = 112.00 M1
1,121.50 M1

7 PLEST. PLAT DAK VOL. = P x L x JMH 46.20 M2


= 2.75 x 8.40 x 2.00 = 46.20 M2
46.20 M2
V PEKERJAAN KERAMIK
1 LANTAI KERAMIK 40X40CM VOL. = P x L x JMH 340.25 M2
= 11.00 x 7.00 x 1.00 = 77.00 M2
= 23.00 x 10.50 x 1.00 = 241.50 M2
= 1.75 x 6.40 x 2.00 = 22.40 M2
Teras depan = 1.50 x 5.00 x 1.00 = 7.50 M2
Teras belakang = 3.75 x 1.00 x 1.00 = 3.75 M2
anak tangga samping = 1.75 x 0.30 x 8.00 = 4.20 M2
depan = 5.00 x 0.30 x 2.00 = 3.00 M2
belakang = 1.00 x 0.30 x 8.00 = 2.40 M2
A 361.75 M2
B
KM/WC = P x L x JMH
= 1.75 x 2.00 x 1.00 = 3.50 M2
= 3.00 x 3.00 x 2.00 = 18.00 M2
B 21.50 M2

VOL.AKHIR = A - B
= 361.75 - 21.50 = 340.25 M2
2 LANTAI KERAMIK KM/WC VOL. = P x L x JMH 21.50 M2
= 1.75 x 2.00 x 1.00 = 3.50 M2
= 3.00 x 3.00 x 2.00 = 18.00 M2
21.50 M2

3 DINDING KERAMIK KM/WC VOL. = P x L x JMH 49.50 M2


WC = 6.70 x 1.80 x 1.00 = 12.06 M2
= 5.20 x 1.80 x 4.00 = 37.44 M2
49.50 M2

4 LANTAI KERAMIK TANGGA VOL. = P x L x JMH 14.40 M2


Bordes = 3.00 x 1.50 x 1.00 = 4.50 M2
A.Tangga = 1.50 x 0.30 x 22.00 = 9.90 M2
14.40 M2

5 PLINT KERAMIK TANGGA VOL. = P x JMH 33.00 M1


= 1.50 x 22.00 = 33.00 M1
33.00 M1

6 PLINT KERAMIK RUANG VOL. = P x JMH 183.60 M1


Sekcam = 19.10 x 1.00 = 19.10 M1
Gudang = 10.60 x 1.00 = 10.60 M1
keuangan = 17.10 x 1.00 = 17.10 M1
R.Camat = 18.30 x 1.00 = 18.30 M1
R.tunggu kiri = 19.60 x 1.00 = 19.60 M1
R.tunggu kanan = 27.30 x 1.00 = 27.30 M1
Lorong/R.Belakang = 41.50 x 1.00 = 41.50 M1
Loby R.Tunggu = 30.10 x 1.00 = 30.10 M1
183.60 M1

7 DINDING PINTU MASUK VOL. = P x L x JMH 8.04 M2


pilar = 2.25 x 1.20 x 2.00 = 5.40 M2
= 0.30 x 0.30 x 2.00 = 0.18 M2
= 0.30 x 0.90 x 2.00 = 0.54 M2
ambang = 1.60 x 1.20 x 1.00 = 1.92 M2
8.04 M2

VI PEKERJAAN PLAFOND
1 PLAFOND KALSIBOARD VOL. = P x L x JMH 328.90 M2
(Dalam) = 11.00 x 7.00 x 1.00 = 77.00 M2
= 23.00 x 10.50 x 1.00 - 12.00 = 229.50 M2
= 1.75 x 6.40 x 2.00 = 22.40 M2
328.90 M2

2 LISPLAFOND GYP - Dalam VOL. = P x JMH 265.90 M1


Sekcam = 20.00 x 1.00 = 20.00 M1
Gudang = 11.50 x 1.00 = 11.50 M1
keuangan = 18.00 x 1.00 = 18.00 M1
R.Camat = 20.00 x 1.00 = 20.00 M1
R.tunggu kiri = 20.10 x 1.00 = 20.10 M1
R.tunggu kanan = 26.10 x 1.00 = 26.10 M1
Lorong/R.Belakang = 42.00 x 1.00 = 42.00 M1
Loby R.Tunggu = 51.20 x 1.00 = 51.20 M1
wc 1 = 7.50 x 1.00 = 7.50 M1
Pantry = 7.50 x 1.00 = 7.50 M1
wc 2 = 6.00 x 4.00 = 24.00 M1
R.ganti = 9.00 x 2.00 = 18.00 M1
265.90 M1

3 PLAFOND KALSIBOARD VOL. = P x L x JMH 155.30 M2


(Luar) depan = 25.50 x 1.15 x 1.00 = 29.33 M2
= 7.50 x 6.00 x 1.00 = 45.00 M2
samp. = 17.50 x 1.15 x 2.00 = 40.25 M2
belakang = 25.50 x 1.15 x 1.00 = 29.33 M2
= 6.00 x 0.70 x 1.00 = 4.20 M2
Gevel = 6.00 x 0.60 x 2.00 = 7.20 M2
155.30 M2

4 LISPLAFOND GYP - luar VOL. = P x JMH 121.00 M1


Pinggir tembok depan = 23.00 x 1.00 = 23.00 M1
= 22.00 x 1.00 = 22.00 M1
= 17.00 x 1.00 = 17.00 M1
samp. = 18.00 x 2.00 = 36.00 M1
belakang = 23.00 x 1.00 = 23.00 M1
121.00 M1

5 LISPLAFOND GYP - luar VOL. = P x JMH 103.00 M1


Pinggir lisplank depan = 25.50 x 1.00 = 25.50 M1
= 12.00 x 1.00 = 12.00 M1
samp. = 20.00 x 2.00 = 40.00 M1
belakang = 25.50 x 1.00 = 25.50 M1
103.00 M1
VII PEKERJAAN KUSEN/JENDELA
1 KUSEN PINTU / JENDELA VOL. = P x DIMENSI x JMH 1.41 M3
Pw = 5.10 x 0.05 x 0.13 x 5.00 = 0.17 M3
KP1 = 7.20 x 0.05 x 0.13 x 6.00 = 0.28 M3
KP2 = 8.90 x 0.05 x 0.13 x 3.00 = 0.17 M3
KJ1 = 5.50 x 0.05 x 0.13 x 3.00 = 0.11 M3
KJ2 = 9.05 x 0.05 x 0.13 x 8.00 = 0.47 M3
V1 = 2.80 x 0.05 x 0.13 x 8.00 = 0.15 M3
V2 = 4.80 x 0.05 x 0.13 x 2.00 = 0.06 M3
1.41 M3

2 DAUN JENDELA/VENTILASI VOL. = P x L x SISI x JMH 20.58 M2


J1 jendela = 0.62 x 1.07 x 1.00 x 3.00 = 1.99 M2
ventilasi = 0.62 x 0.42 x 1.00 x 3.00 = 0.78 M2
J2 jendela = 0.62 x 1.07 x 2.00 x 8.00 = 10.61 M2
ventilasi = 0.62 x 0.42 x 2.00 x 8.00 = 4.17 M2
V2 ventilasi = 0.72 x 0.42 x 2.00 x 2.00 = 1.21 M2
KP2 ventilasi = 0.72 x 0.42 x 2.00 x 3.00 = 1.81 M2
20.58 M2
3 KACA BENING 5mm VOL. = P x L x SISI x JMH 3.00 M2
V1 Kaca slip = 0.72 x 0.52 x 1.00 x 8.00 = 3.00 M2

4 KACA RYBEN 5mm VOL. = P x L x SISI x JMH 25.47 M2


KP1 = 0.82 x 0.42 x 1.00 x 6.00 = 2.07 M2
Pu = 1.14 x 3.02 x 2.00 x 1.00 = 6.89 M2
= 2.22 x 0.42 x 1.00 x 1.00 = 0.93 M2
KJ3 = 0.86 x 3.02 x 3.00 x 2.00 = 15.58 M2
25.47 M2

5 DAUN PINTU KM/WC VOL. = P x L x SISI x JMH 7.24 M2


PW = 0.72 x 2.01 x 1.00 x 5.00 = 7.24 M2
7.24 M2

6 DAUN PINTU panil VOL. = P x L x SISI x JMH 18.94 M2


Kusen KP1 = 0.82 x 2.10 x 1.00 x 4.00 = 6.89 M2
KP- wc = 0.82 x 2.10 x 1.00 x 2.00 = 3.44 M2
Partisi PR1 = 0.82 x 2.10 x 1.00 x 3.00 = 5.17 M2
PR4 = 0.82 x 2.10 x 1.00 x 1.00 = 1.72 M2
PR5 = 0.82 x 2.10 x 1.00 x 1.00 = 1.72 M2
18.94 M2

7 DAUN PINTU kaca VOL. = P x L x SISI x JMH 8.95 M2


KP2 = 1.42 x 2.10 x 1.00 x 3.00 = 8.95 M2
VIII PEKERJAAN BESI
1 ANGKER KUSEN VOL. = BJ x JMH 198.00 BH
Pw = 8.00 x 5.00 = 40.00 BH
KP1 8.00 x 6.00 = 48.00 BH
Kp2 8.00 x 3.00 = 24.00 BH
KJ1 6.00 x 3.00 = 18.00 BH
KJ2 6.00 x 8.00 = 48.00 BH
V1 2.00 x 8.00 = 16.00 BH
V2 2.00 x 2.00 = 4.00 BH
198.00 BH

2 ENGSEL PINTU VOL. = Bj x JMH 60.00 BH


Kusen Pw = 3.00 x 5.00 = 15.00 BH
KP1 3.00 x 6.00 = 18.00 BH
KP2 6.00 x 3.00 = 18.00 BH
Partisi PR2 = 3.00 x 1.00 = 3.00 BH
PR4 = 3.00 x 2.00 = 6.00 BH
60.00 BH

3 ENGSEL JENDELA VOL. = BJ x JMH 120.00 BH


KJ1 jendela 2.00 x 3.00 = 6.00 BH
ventilasi 2.00 x 3.00 = 6.00 BH
KJ2 jendela 4.00 x 8.00 = 32.00 BH
ventilasi 4.00 x 8.00 = 32.00 BH
V2 ventilasi 4.00 x 8.00 = 32.00 BH
KP2 ventilasi 4.00 x 3.00 = 12.00 BH
120.00 BH

4 HAAG ANGIN VOL. = BJ x JMH 120.00 BH

5 GRENDEL JENDELA VOL. = BJ x JMH 120.00 BH

6 GRENDEL TANAM EXPAGNYOLET VOL. = BJ x JMH 2.00 BH


P2 2.00 x 1.00 = 2.00 BH
2.00 BH
7 GRENDEL PINTU VOL. = BJ x JMH 14.00 BH
Kusen Pw 1.00 x 5.00 = 5.00 BH
Kp1 1.00 x 6.00 = 6.00 BH
Partisi PR2 1.00 x 1.00 = 1.00 BH
PR4 1.00 x 2.00 = 2.00 BH
14.00 BH

8 KUNCI TANAM VOL. = BJ x JMH 12.00 BH


Kusen Kp1 1.00 x 6.00 = 6.00 BH
Kp2 1.00 x 3.00 = 3.00 BH
Partisi PR2 1.00 x 1.00 = 1.00 BH
PR4 1.00 x 2.00 = 2.00 BH
12.00 BH

9 KUNCI TANAM wc VOL. = BJ x JMH 5.00 BH


Pw 1.00 x 5.00 = 5.00 BH
5.00 BH

10 KUSEN ALUMINIUM VOL. = P x JMH 70.24 M1


PU = 24.00 x 1.00 = 24.00 M1
Kj3 = 23.12 x 2.00 = 46.24 M1
70.24 M1

IX PEKERJAAN PARTISI
1 PARTISI RANGKA KAYU VOL. = P x T x JMH 58.19 M2
Dilapis double teakwoood PR 1 = 2.09 x 2.11 x 3.00 = 13.23 M2
PR2 = 2.19 x 2.11 x 1.00 = 4.62 M2
PR3 = 4.67 x 2.11 x 3.00 = 29.56 M2
= 2.72 x 0.88 x 1.00 = 2.39 M2
PR5 = 1.97 x 2.11 x 1.00 = 4.16 M2
= 1.49 x 2.11 x 1.00 = 3.14 M2
PR6 = 1.23 x 0.88 x 1.00 = 1.08 M2
58.19 M2

2 KUSEN KAYU PARTISI VOL. = P x DIMENSI x JMH 0.76 M3


PR1 = 12.26 x 0.05 x 0.12 x 3.00 = 0.22 M3
PR2 = 16.18 x 0.05 x 0.12 x 1.00 = 0.10 M3
PR3 = 15.34 x 0.05 x 0.12 x 3.00 = 0.28 M3
PR5 = 17.14 x 0.05 x 0.12 x 1.00 = 0.10 M3
PR6 = 9.75 x 0.05 x 0.12 x 1.00 = 0.06 M3
0.76 M3

3 KACA BENING 5MM VOL. = P x T x JMH 33.81 M2


PR1 = 2.87 x 1.12 x 3.00 = 9.64 M2
PR2 = 2.82 x 1.12 x 1.00 = 3.16 M2
PR3 = 4.50 x 1.12 x 3.00 = 15.12 M2
PR5 = 4.14 x 1.12 x 1.00 = 4.64 M2
Pts 6 = 1.12 x 1.12 x 1.00 = 1.25 M2
33.81 M2

4 PLINT PAPAN 2,5/15 VOL. = P x SISI x JMH 51.92 M1


PR1 = 2.09 x 2.00 x 3.00 = 12.54 M1
PR2 = 2.21 x 2.00 x 1.00 = 4.42 M1
PR3 = 4.67 x 2.00 x 3.00 = 28.02 M1
PR5 = 3.47 x 2.00 x 1.00 = 6.94 M1
51.92 M1

5 PARTISI RANGKA KAYU VOL. = P x T x JMH 44.69 M2


Dilapis double triplek 4mm Pts 4 = 5.59 x 3.30 x 1.00 = 18.45 M2
Dilapisi HPL = 1.95 x 3.30 x 2.00 - 2.94 = 9.93 M2
= 1.62 x 3.30 x 2.00 = 10.69 M2
= 1.36 x 3.30 x 2.00 - 3.36 = 5.62 M2
44.69 M2

IX PEKERJAAN ATAP
1 ATAP GENTENG VOL. = P x L x SISI 412.72 M2
Lumbung depan = 7.07 x 5.75 x 2.00 = 81.25 M2
Ks 1 = 5.58 x 1.90 x 1.00 = 10.59 M2
Ks 2 = 5.00 x 1.90 x 2.00 = 19.00 M2
Samping traves. = 8.95 x 5.50 x 2.00 = 98.45 M2
segitiga = 4.25 x 5.50 x 4.00 x 0.50 = 46.75 M2
Belakang Ks = 1.75 x 1.90 x 2.00 = 6.65 M2
traves. = 5.45 x 8.50 x 2.00 = 92.65 M2
segitiga = 13.50 x 8.50 x 1.00 x 0.50 = 57.38 M2
412.72 M2

2 Bubungan VOL. = P/T x JMH 62.65 M1


Nok = 7.00 x 1.00 = 7.00 M1
Nok = 2.65 x 1.00 = 2.65 M1
Jurai dep. = 2.50 x 2.00 = 5.00 M1
Jurai samp. = 6.50 x 4.00 = 26.00 M1
Jurai blkng = 11.00 x 2.00 = 22.00 M1
62.65 M1
3 Lisplank VOL. = P/T x JMH 133.75 M1
Lumbung gv = 6.00 x 2.00 = 12.00 M1
= 7.25 x 1.00 = 7.25 M1
= 6.00 x 2.00 = 12.00 M1
= 5.00 x 2.00 = 10.00 M1
Samping = 4.50 x 4.00 = 18.00 M1
= 13.50 x 2.00 = 27.00 M1
Belakang = 1.75 x 2.00 = 3.50 M1
= 13.50 x 1.00 = 13.50 M1
= 13.50 x 1.00 = 13.50 M1
= 8.50 x 2.00 = 17.00 M1
133.75 M1

4 Talang patahan VOL. = P/T x JMH 18.00 M1


= 2.50 x 4.00 = 10.00 M1
= 4.00 x 2.00 = 8.00 M1
18.00 M1

X PEKERJAAN KAP KD-KD


1 KAP KD-KD BAJA WF VOL. = P x SISI x JMH 10.98 M1
Kap kd-kd lumbung tiang tump. = 0.35 x 2.00 x 1.00 = 0.70 M1
tengah = 0.50 x 1.00 x 1.00 = 0.50 M1
kd = 4.89 x 2.00 x 1.00 = 9.78 M1
10.98 M1

1 Berat kap kd-kd VOL. = P x Berat x JMH


WF 150.75.5.7.8 = 10.98 x 14.00 x 2.00 = 307.44 Kg 307.44 KG

Angker bautmur = 6.00 x 2.00 = 12.00 BH

bautmur samb. = 10.00 x 2.00 = 20.00 BH

Cat Meny besi = 10.98 x 0.57 x 2.00 = 12.52 M2

2 KAP KD-KD BAJA WF VOL. = P x SISI x JMH 6.45 M1


Kap kd-kd samping tiang tump. = 0.35 x 1.00 x 1.00 = 0.35 M1
skur = 0.60 x 1.00 x 1.00 = 0.60 M1
kd = 5.50 x 1.00 x 1.00 = 5.50 M1
6.45 M1

2 Berat kap kd-kd VOL. = P x Berat x JMH


= 6.45 x 14.00 x 4.00 = 361.20 Kg 361.20 KG

Angker bautmur = 6.00 x 4.00 = 24.00 BH

Cat Meny besi = 6.45 x 0.57 x 4.00 = 14.71 M2

3 JURAI KD-KD BAJA WF VOL. = P x SISI x JMH 7.55 M1


Kap kd-kd samping tiang tump. = 0.35 x 1.00 x 1.00 = 0.35 M1
skur = 0.60 x 1.00 x 1.00 = 0.60 M1
kd = 6.60 x 1.00 x 1.00 = 6.60 M1
7.55 M1

3 Berat kap kd-kd VOL. = P x Berat x JMH


WF 150.75.5.7.8 = 7.55 x 14.00 x 4.00 = 422.80 Kg 422.80 KG

Angker bautmur = 6.00 x 4.00 = 24.00 BH

bautmur samb. = 20.00 x 4.00 = 80.00 BH

Cat Meny besi = 7.55 x 0.57 x 4.00 = 17.21 M2

4 TRAVESIUM KD-KD BAJA WF VOL. = P x SISI x JMH 18.00 M1


Kap kd-kd Belakang tiang tump. = 0.35 x 2.00 x 1.00 = 0.70 M1
skur 1 = 0.60 x 2.00 x 1.00 = 1.20 M1
skur 2 = 0.60 x 2.00 x 1.00 = 1.20 M1
kd = 4.95 x 2.00 x 1.00 = 9.90 M1
ambang = 5.00 x 1.00 x 1.00 = 5.00 M1
18.00 M1

4 Berat kap kd-kd VOL. = P x Berat x JMH


WF 200.100.5,5.8.11 = 18.00 x 21.30 x 1.00 = 383.40 Kg 383.40 KG

Angker bautmur = 12.00 x 1.00 = 12.00 BH

bautmur samb. = 20.00 x 1.00 = 20.00 BH

Cat Meny besi = 18.00 x 0.78 x 1.00 = 14.04 M2

5 1/4 KD-KD BAJA WF VOL. = P x SISI x JMH 5.90 M1


Kap kd-kd Belakang tiang tump. = 0.35 x 1.00 x 1.00 = 0.35 M1
skur 1 = 0.60 x 1.00 x 1.00 = 0.60 M1
kd = 4.95 x 1.00 x 1.00 = 4.95 M1
5.90 M1

5 Berat kap kd-kd VOL. = P x Berat x JMH


WF 200.100.5,5.8.11 = 5.90 x 21.30 x 2.00 = 251.34 Kg 251.34 KG

Angker bautmur = 6.00 x 2.00 = 12.00 BH

Cat Meny besi = 5.90 x 0.78 x 2.00 = 9.20 M2


6 JURAI KD-KD BAJA WF VOL. = P x SISI x JMH 11.55 M1
Kap kd-kd Belakang tiang tump. = 0.35 x 1.00 x 1.00 = 0.35 M1
skur 1 = 0.60 x 1.00 x 1.00 = 0.60 M1
kd = 10.60 x 1.00 x 1.00 = 10.60 M1
11.55 M1

6 Berat kap kd-kd VOL. = P x Berat x JMH


WF 200.100.5,5.8.11 = 11.55 x 21.30 x 2.00 = 492.03 Kg 492.03 KG

Angker bautmur = 6.00 x 2.00 = 12.00 BH

bautmur samb. = 40.00 x 2.00 = 80.00 BH

Cat Meny besi = 11.55 x 0.78 x 2.00 = 18.02 M2

7 1/2 KD-KD BAJA WF VOL. = P x SISI x JMH 12.10 M1


Kap kd-kd Belakang tiang tump. = 0.35 x 1.00 x 1.00 = 0.35 M1
skur 1 = 0.60 x 1.00 x 1.00 = 0.60 M1
skur 2 = 0.60 x 2.00 x 1.00 = 1.20 M1
kd = 8.35 x 1.00 x 1.00 = 8.35 M1
nok = 1.60 x 1.00 x 1.00 = 1.60 M1
12.10 M1

7 Berat kap kd-kd VOL. = P x Berat x JMH


WF 200.100.5,5.8.11 = 12.10 x 21.30 x 1.00 = 257.73 Kg 257.73 KG

Angker bautmur = 6.00 x 1.00 = 6.00 BH

bautmur samb. = 40.00 x 1.00 = 40.00 BH

Cat Meny besi = 12.10 x 0.78 x 1.00 = 9.44 M2

8 KONSOL BAJA WF VOL. = P x SISI x JMH 2.95 M1


Keliling tiang tump. = 0.35 x 1.00 x 1.00 = 0.35 M1
skur = 0.75 x 1.00 x 1.00 = 0.75 M1
kd = 1.85 x 1.00 x 1.00 = 1.85 M1
2.95 M1

8 Berat kap kd-kd VOL. = P x Berat x JMH


WF 150.75.5.7.8 = 2.95 x 14.00 x 25.00 = 1,032.50 Kg 1,032.50 KG

Cat Meny besi = 2.95 x 0.57 x 25.00 = 42.04 M2

REKAPITULASI
1 KUDA-KUDA BAJ WF 3,508.44 KG
KD-KD LUMBUNG = 307.44 = 307.44 KG
KD-KD SAMPING = 361.20 = 361.20 KG
JURAI SAMPING = 422.80 = 422.80 KG
TRAVESIUM BELAKANG = 383.40 = 383.40 KG
1/4 KD-KD BELAKANG = 251.34 = 251.34 KG
JURAI BELAKANG = 492.03 = 492.03 KG
1/2 KD-KD BELAKANG = 257.73 = 257.73 KG
KONSOL KELILING = 1,032.50 = 1,032.50 KG
3,508.44 KG

2 ANGKER BAUTMUR 102.00 BH


KD-KD LUMBUNG = 12.00 = 12.00 BH
KD-KD SAMPING = 24.00 = 24.00 BH
JURAI SAMPING = 24.00 = 24.00 BH
TRAVESIUM BELAKANG = 12.00 = 12.00 BH
1/4 KD-KD BELAKANG = 12.00 = 12.00 BH
JURAI BELAKANG = 12.00 = 12.00 BH
1/2 KD-KD BELAKANG = 6.00 = 6.00 BH
KONSOL KELILING = - = - BH
102.00 BH

3 BAUTMUR 270.00 BH
KD-KD LUMBUNG = 20.00 = 20.00 BH
KD-KD SAMPING = 20.00 = 20.00 BH
JURAI SAMPING = 80.00 = 80.00 BH
TRAVESIUM BELAKANG = 20.00 = 20.00 BH
1/4 KD-KD BELAKANG = 10.00 = 10.00 BH
JURAI BELAKANG = 80.00 = 80.00 BH
1/2 KD-KD BELAKANG = 40.00 = 40.00 BH
KONSOL KELILING = - = - BH
270.00 BH
4 PLAT BAJA LUAS x berat x JMH 278.04 KG
KD-KD LUMBUNG plat tump. = 0.30 x 39.25 x 2.00 = 23.55 KG
plent gording = 0.11 x 39.25 x 2.00 = 8.83 KG
KD-KD SAMPING plat tump. = 0.30 x 39.25 x 4.00 = 47.10 KG
plent gording = 0.06 x 39.25 x 4.00 = 8.83 KG
JURAI SAMPING plat tump. = 0.30 x 39.25 x 4.00 = 47.10 KG
plent gording = 0.06 x 39.25 x 4.00 = 8.83 KG
plat samb. = 0.20 x 39.25 x 4.00 = 31.40 KG
TRAVESIUM BELAKANG plat tump. = 0.30 x 39.25 x 1.00 = 11.78 KG
plent gording = 0.11 x 39.25 x 1.00 = 4.42 KG
1/4 KD-KD BELAKANG plat tump. = 0.30 x 39.25 x 1.00 = 11.78 KG
plent gording = 0.05 x 39.25 x 1.00 = 1.77 KG
JURAI BELAKANG plat tump. = 0.30 x 39.25 x 2.00 = 23.55 KG
plent gording = 0.09 x 39.25 x 2.00 = 7.07 KG
plat samb. = 0.20 x 39.25 x 1.00 = 7.85 KG
1/2 KD-KD BELAKANG plat tump. = 0.30 x 39.25 x 1.00 = 11.78 KG
plent gording = 0.09 x 39.25 x 1.00 = 3.53 KG
plat samb. = 0.20 x 39.25 x 1.00 = 7.85 KG
KONSOL KELILING plent gording = 0.01 x 39.25 x 25.00 = 11.04 KG
278.04 KG
X PEKERJAAN PENGECATAN
1 CAT KUSEN/JENDELA VOL. = P x Kllg x JMH 116.49 M2
A Kusen pintu jendela
Pw kusen = 4.70 x 0.23 x 5.00 = 5.41 M2
KP1 kusen = 5.80 x 0.23 x 7.00 = 9.34 M2
= 0.80 x 0.36 x 7.00 = 2.02 M2
KP2 kusen = 6.30 x 0.23 x 3.00 = 4.35 M2
= 1.70 x 0.36 x 3.00 = 1.84 M2
jendela = 3.96 x 0.22 x 3.00 = 2.61 M2
KJ1 kusen = 4.40 x 0.23 x 3.00 = 3.04 M2
= 0.60 x 0.36 x 3.00 = 0.65 M2
jendela = 4.30 x 0.22 x 3.00 = 2.84 M2
ventilasi = 2.60 x 0.22 x 3.00 = 1.72 M2
KJ2 kusen = 5.70 x 0.23 x 8.00 = 10.49 M2
= 2.65 x 0.36 x 8.00 = 7.63 M2
jendela = 4.30 x 0.22 x 16.00 = 15.14 M2
ventilasi = 2.60 x 0.22 x 16.00 = 9.15 M2
V1 kusen = 2.40 x 0.23 x 8.00 = 4.42 M2
V2 kusen = 3.90 x 0.23 x 2.00 = 1.79 M2
= 0.40 x 0.36 x 2.00 = 0.29 M2
ventilasi = 2.80 x 0.22 x 4.00 = 2.46 M2
B Kusen Partisi -
PR1 kusen = 8.28 x 0.23 x 3.00 = 5.71 M2
= 3.30 x 0.34 x 3.00 = 3.37 M2
PR2 kusen = 7.43 x 0.23 x 1.00 = 1.71 M2
= 8.20 x 0.34 x 1.00 = 2.79 M2
PR3 kusen = 11.54 x 0.23 x 3.00 = 7.96 M2
= 3.30 x 0.34 x 3.00 = 3.37 M2
PR5 kusen = 7.84 x 0.23 x 1.00 = 1.80 M2
= 6.40 x 0.34 x 1.00 = 2.18 M2
PR6 kusen = 7.32 x 0.23 x 1.00 = 1.68 M2
= 2.23 x 0.34 x 1.00 = 0.76 M2
116.49 M2

2 POLITURAN DAUN PINTU VOL. = L x T x SISI x JMH 76.79 M2


2.1 Pintu Panil Pada Kusen
Pw pintu = 0.72 x 2.01 x 1.00 x 5.00 = 7.24 M2
KP1 pintu = 0.82 x 2.10 x 2.00 x 7.00 = 24.11 M2
KP2 pintu = 1.42 x 2.10 x 2.00 x 3.00 = 17.89 M2
2.2 Pintu Panil Pada Partisi -
PR1 pintu = 0.82 x 2.10 x 2.00 x 3.00 = 10.33 M2
PR4 pintu = 0.82 x 2.10 x 2.00 x 4.00 = 13.78 M2
PR5 pintu = 0.82 x 2.10 x 2.00 x 1.00 = 3.44 M2
76.79 M2

4 CAT DINDING (LUAR) Luas = P x T x SISI 558.47 M2


26.50 = 26.50 x 4.50 x 2.00 = 238.50 M2
18.00 = 18.00 x 4.50 x 2.00 = 162.00 M2
ralling teras belakng 6.00 = 6.00 x 1.25 x 1.00 = 7.50 M2
ralling teras samp. 1.50 = 1.50 x 1.25 x 2.00 = 3.75 M2
kolom 1 = 1.20 x 3.50 x 4.00 = 16.80 M2
Balok gantung entrance = 0.80 x 6.00 x 2.00 = 9.60 M2
= 0.80 x 5.00 x 2.00 = 8.00 M2
Ks keliling = 0.80 x 1.00 x 35.00 = 28.00 M2
= 0.80 x 1.75 x 2.00 = 2.80 M2
Lisplank 29.00 = 29.00 x 1.40 x 2.00 = 81.20 M2
26.50 = 26.50 x 1.40 x 2.00 = 74.20 M2
A 632.35 M2

B
Lbg kusen = L x T x JMH
PU = 4.60 x 2.75 x 1.00 = 12.65 M2
P1/Pd = 1.50 x 2.60 x 3.00 = 11.70 M2
J1 = 0.70 x 1.60 x 2.00 = 2.24 M2
J2 = 1.35 x 1.60 x 12.00 = 25.92 M2
J3 = 2.68 x 3.10 x 2.00 = 16.62 M2
V1 = 0.80 x 0.50 x 8.00 = 3.20 M2
V2 = 1.55 x 0.50 x 2.00 = 1.55 M2
B 73.88 M2

VOL.AKHIR = A - B
= 632.35 - 73.88 = 558.47 M2

2 CAT DINDING (Dalam) Luas = P x T x JMH 561.68 M2


R.Sekcam = 20.00 x 3.00 x 1.00 = 60.00 M2
Gudang = 11.50 x 3.00 x 1.00 = 34.50 M2

R. Keuangan = 18.00 x 3.00 x 1.00 = 54.00 M2


R.Camat = 20.00 x 3.00 x 1.00 = 60.00 M2
Pantry = 7.50 x 3.00 x 1.00 = 22.50 M2
R.Tunggu kiri = 20.10 x 3.00 x 1.00 = 60.30 M2
R.Tunggu kanan = 26.10 x 3.00 x 1.00 = 78.30 M2
Ralling tangga = 8.00 x 2.13 x 1.00 = 17.04 M2
R.ganti wc = 9.00 x 3.00 x 2.00 = 54.00 M2
wc = 6.00 x 1.25 x 4.00 = 30.00 M2
Loby = 25.20 x 3.00 x 1.00 = 75.60 M2
R.Kebelakang = 42.00 x 3.00 x 1.00 = 126.00 M2
A 672.24 M2

B
Lbg kusen = L x T x JMH
PU = 4.60 x 2.75 x 1.00 = 12.65 M2
P1/Pd = 1.50 x 2.60 x 3.00 = 11.70 M2
P2 = 0.90 x 2.60 x 12.00 = 28.08 M2
Pw = 0.80 x 2.15 x 5.00 = 8.60 M2
J1 = 0.70 x 1.60 x 2.00 = 2.24 M2
J2 = 1.35 x 1.60 x 12.00 = 25.92 M2
J3 = 2.68 x 3.10 x 2.00 = 16.62 M2
V1 = 0.80 x 0.50 x 8.00 = 3.20 M2
V2 = 1.55 x 0.50 x 2.00 = 1.55 M2
B 110.56 M2

VOL.AKHIR = A - B
= 672.24 - 110.56 = 561.68 M2

3 CAT PLAT tangga Luas = P x L x JMH 13.50 M2


= 3.00 x 1.00 x 1.00 = 3.00 M2
= 7.00 x 1.50 x 1.00 = 10.50 M2
13.50 M2
XI PEKERJAAN RABAT KELILING
1 Galian Tanah Volume = L x T x PJG 38.88 M3
= 0.54 x 0.45 x 160.00 = 38.88 M3
38.88 M3
2 Urugan Kembali Volume = 0.25 x Galian 9.72 M3
= 0.25 x 38.88 = 9.72 M3

3 Urugan Pasir pondasi Saluran Volume = L x T x PJG 3.20 M3


= 0.20 x 0.10 x 160.00 = 3.20 M3

4 Urugan pasir Bawah Rabat


Volume = L x T x PJG 11.60 M3
= 1.24 x 0.15 x 62.60 = 11.60 M3

5 Urugan tanah Bawah Rabat


Volume = L x T x PJG 46.39 M3
= 1.24 x 0.60 x 62.60 = 46.39 M3

6 Pas. Trasram Bata - Saluran LA = P x T x JMH 128.00 M2


= 160.00 x 0.40 x 2.00 = 128.00 M2
128.00 M2

7 Plest..Trasram Bata - Saluran Volume = PJG x L 190.40 M2


= 160.00 x 0.53 = 84.80 M2
= 160.00 x 0.66 = 105.60 M2
190.40 M2
PJG 158.00 M1
8 Pas. Buis Beton 1/2 Ø 20 Cm Volume = 160.00 - 2.00 = 158.00 M1

9 Pasangan /Cor Rabat Beton Volume = L x T x P 5.41 M3


= 1.24 x 0.07 x 62.60 = 5.41 M3

10 Pembuatan bak kontrol Volume = JMH 27.00 unit


27.00 = 27.00 unit
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : BANTUAN SANITASI SD SEKOLAH DASAR
LOKASI : SD NEGERI 2 CAKRANRGARA
TAHUN : 2017

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT. KODE ANALISA
(Rp.) (Rp.)
1 2 3 4 5 6 7

A Bangunan Sanitasi
I. PEKERJAAN PERSIAPAN
1 Papan nama proyek 1.000 Unit Ls 200,000.00 200,000.00
2 Uitzet/Pengukuran/Pas. Bouwplank 5.000 m' A.2.2.1.4 94,200.00 471,000.00
3 Pembersihan awal dan akhir proyek 1.000 unit Ls 500,000.00 500,000.00
JUMLAH ( I ) 1,171,000.00
II. PEKERJAAN TANAH
1 Galian pondasi 6.720 m³ A.2.3.1.1 49,125.00 330,120.00
2 Urugan tanah kembali 1.680 m³ A.2.3.1.9 16,375.00 27,510.00
3 Pasir urug dibawah pondasi 1.480 m³ A.2.3.1.11 139,650.00 206,682.00
4 Tanah urug dibawah lantai 3.247 m³ A.2.3.1.11a 94,650.00 307,319.09
JUMLAH ( II ) 871,631.09
III. PEKERJAAN BETON
1 Pek. beton bertulang sloof 15/20 0.740 m³ A.4.1.1.30 3,321,071.71 2,457,593.07
2 Pek. beton bertulang kolom 10/10 64.600 m' A.4.1.1.35 54,064.80 3,492,586.08
3 Pek. beton bertulang balok 10/15 - sunscreen 26.800 m' A.4.1.1.36 73,442.42 1,968,256.86
4 Pek. beton bertulang balok ring 10/15 65.890 m' A.4.1.1.36 73,442.42 4,839,121.05
4 Pek. beton bertulang plat sunscren T.8cm 0.804 m³ A.4.1.1.42 4,252,212.46 3,418,778.82
JUMLAH ( III ) 16,176,335.87
IV. PEKERJAAN ATAP
1 Pas. Kap kd-kd dan reng baja ringan (SNI) + Spandek 0,3 mm 79.900 m² Ls 265,000.00 21,173,500.00
2 Lisplank kalsiplank Jati 8mm-20cm 27.300 m¹ A.4.6.1.21c 38,300.00 1,045,590.00
JUMLAH ( III ) 22,219,090.00
V. PEKERJAAN PASANGAN / PLESTERAN
1 Pas. Pondasi batu kali camp. 1pc : 5psr 8.325 m³ A.3.2.1.3 482,170.00 4,014,065.25
2 Pas. trasram bata 1/2 bt. camp. 1pc : 3psr 21.213 m² A.4.4.1.8 82,431.40 1,748,617.29
3 Pas. dinding bata 1/2 bt. camp. 1pc : 5psr 117.530 m² A.4.4.1.10 77,334.60 9,089,135.54
4 Plesteran trasram bata camp. 1pc : 3psr 42.426 m² A.4.4.2.3 32,011.72 1,358,129.23
5 Plesteran dinding bata camp. 1pc : 5psr 155.252 m² A.4.4.2.5 29,224.48 4,537,158.97
6 Acian Pc 155.252 m² A.4.4.2.27 17,065.00 2,649,375.38
7 Pek. Pemasangan dinding roster pejaten 20x20 4.320 m² A.4.4.1.23 199,945.00 863,762.40
8 Pek. Pemasangan dinding batu andesit 14.000 m² A.4.4.3.58 224,320.00 3,140,480.00
JUMLAH ( IV ) 27,400,724.06
VI. PEKERJAAN LANTAI DAN PLAFOND
a. Pekerjaan Plafon
1 Pas. Plafond kalsiboard T. 3,5mm,rangka hollow - Dalam 24.721 m² A.4.5.1.5c 94,150.00 2,327,519.81
2 Pas. LisPlafond gypsum C7 - Dalam 48.880 m² A.4.5.1.8 19,425.00 949,494.00
b. Pekerjaan Keramik
2 Pas. Keramik lantai 30x30 km/wc 41.717 m² A.4.4.3.35 153,075.00 6,385,829.78
3 Pas. Dinding keramik 30x30cm - KM/Wc 65.808 m² A.4.4.3.35 153,075.00 10,073,559.60
JUMLAH ( V ) 19,736,403.19
VII. PEKERJAAN KUSEN,PINTU DAN KACA
1 Kusen pintu/ventilasi kayu klas II 0.135 m³ A.4.6.1.1 6,674,250.00 902,358.60
2 Daun pintu luar teakwood dlm triplek aluminium -km/wc 5.010 m² A.4.6.1.5c 280,600.00 1,405,693.76
3 Daun pintutype koboy 4.848 m² A.4.6.1.5b 272,050.00 1,318,898.40
JUMLAH ( VI ) 3,626,950.76
VIII. PEKERJAAN BESI/PENGUNCI
1 Kunci tanam - toilet 4.000 bh A.4.6.2.3 63,327.50 253,310.00
2 Engsel pintu 18.000 bh A.4.6.2.5 17,532.50 315,585.00
JUMLAH ( VII ) 568,895.00
IX. PEKERJAAN PENGECATAN/FINISHING
1 Cat dinding (Exterior) 58.216 m² A.4.7.1.10 13,550.00 788,826.80
2 Cat dinding (Interior) 113.352 m² A.4.7.1.10 13,550.00 1,535,919.60
3 Cat plafon 24.721 m² A.4.7.1.10 13,550.00 334,974.97
4 Polituran (daun pintu) 14.706 m² A.4.7.1.7 44,324.00 651,811.01
JUMLAH ( VIII ) 3,311,532.38
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT. KODE ANALISA
(Rp.) (Rp.)
1 2 3 4 5 6 7

X. PEKERJAAN INSTALASI LISTRIK


1 Instalasi titik lampu 6.000 ttk Ls.Inst.1 91,405.00 548,430.00
2 Lampu XL 5 wat + vitingan 4.000 bh Ls 39,000.00 156,000.00
3 Lampu XL 10 wat + vitingan 2.000 bh Ls 48,000.00 96,000.00
4 Saklar tunggal 2.000 bh Ls 24,000.00 48,000.00
5 Saklar double 2.000 bh Ls 24,000.00 48,000.00
JUMLAH ( IX ) 896,430.00
XI. PEKERJAAN INST. AIR & SANITAIR
1 Washtafle porselint + assesories 3.000 unit A.5.1.1.5 703,170.00 2,109,510.00
2 Closet jongkok porselin 4.000 unit A.5.1.1.2 259,070.00 1,036,280.00
3 Urinoir + assesories 2.000 unit A.5.1.1.4 877,400.00 1,754,800.00
4 Kran air 1/2 ' 10.000 unit A.5.1.1.35 20,730.00 207,300.00
5 Pipa PVC Ø 1/2'' - Aw 30.000 m' A.5.1.1.25 9,948.00 298,440.00
6 Pipa PVC Ø 3'' - Aw (pembuangan air avoor) 4.500 m' A.5.1.1.31 45,325.50 203,964.75
7 Pipa PVC Ø 4'' - Aw (pembuangan air closet) 4.000 m' A.5.1.1.32 64,645.50 258,582.00
8 Floordrain stainles 4.000 bh A.5.1.1.36 50,655.00 202,620.00
9 Pembuatan septictank 1.000 unit Ls 500,000.00 500,000.00
10 Pembuatan peresapan 1.000 unit Ls 800,000.00 850,000.00
JUMLAH ( X ) 7,421,496.75
REKAPITULASI
PEKERJAAN : BANTUAN SANITASI SD SEKOLAH DASAR
LOKASI : SD NEGERI 2 CAKRANRGARA
TAHUN ANGGARAN : 2018

NO JENIS PEKERJAAN JUMLAH

1 2 3

A Bangunan Sanitasi
I. PEKERJAAN PERSIAPAN Rp. 1,171,000.00
II. PEKERJAAN TANAH Rp. 871,631.09
III. PEKERJAAN BETON Rp. 16,176,335.87
IV. PEKERJAAN ATAP Rp. 22,219,090.00
IV. PEKERJAAN PASANGAN / PLESTERAN Rp. 27,400,724.06
V. PEKERJAAN LANTAI DAN PLAFOND Rp. 19,736,403.19
VI. PEKERJAAN KUSEN,PINTU DAN KACA Rp. 3,626,950.76
VII. PEKERJAAN BESI/PENGUNCI Rp. 568,895.00
VIII. PEKERJAAN PENGECATAN/FINISHING Rp. 3,311,532.38
IX. PEKERJAAN INSTALASI LISTRIK Rp. 896,430.00
X. PEKERJAAN INST. AIR & SANITAIR Rp. 7,421,496.75

A. JUMLAH BIAYA KONSTRUKSI ( A ) Rp. 103,400,489.10


PEMBULATAN Rp. 103,400,000.00
B BIAYA OPERASIONAL TPBSSD (2%) Rp. 2,200,000.00
C BIAYA PERENCANAAN DAN PENGAWASAN / TIM TEKNIS (4%) Rp. 4,400,000.00
D TOTAL BIAYA BANGUNAN SANITASI (D = A + B + C ) Rp. 110,000,000.00

TERBILANG : SERATUS SEPULUH JUTA RUPIAH,-

Mataram, 2018
Ketua Tim Pelaksana Dibuat Oleh :
Bantuan Sanitasi Sekolah Dasar Tim Teknis

.............................. .............................
Nip :..........................

Mengetahui :
Kepala Sekolah
........................................

....................................
Nip : ................................
BACK UP VOLUME
SANITASI
PEKERJAAN PERENCANAAN SANITASI SD 02 CAKRANEGARA
LOKASI SDN 02 CAKRANEGARA
TAHUN 2018

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME


1 2 3 4

I LUAS BANGUNAN
1 LUAS BANGUNAN VOL. = P x L x JMH 37.60 M2
DALAM = 9.40 x 4.00 x 1.00 = 37.60 M2 37.60

37.60 M2 37.60

II PEKERJAAN TANAH
1 GALIAN PONDASI VOL. = P x L x T x JMH 6.72 M3
Galian pondasi bt.kali Memanjang = 7.00 x 0.80 x 0.60 x 2.00 = 6.72 M3
= 3.00 x 0.80 x 0.60 x 1.00 = 1.44 M3
Melintang = 4.00 x 0.80 x 0.60 x 5.00 = 9.60 M3

6.72 M3

2 PASIR URUG PONDASI VOL. = P x L x T x JMH 1.48 M3


Pondasi stempat 125x125 cm Memanjang = 7.00 x 0.80 x 0.05 x 2.00 = 0.56 M3
Melintang = 3.00 x 0.80 x 0.05 x 1.00 = 0.12 M3
= 4.00 x 0.80 x 0.05 x 5.00 = 0.80 M3

1.48 M3

3 PASIR URUG BWH LANTAI VOL. = P x L x T x JMH 2.47 M3


km/wc = 1.37 x 1.87 x 0.10 x 4.00 = 1.02 M3
= 1.87 x 3.87 x 0.10 x 2.00 = 1.45 M3
2.47 M3

4 TANAH URUG BWH LANTAI VOL. = P x L x T x JMH 3.25 M3


= 1.37 x 1.37 x 0.15 x 4.00 = 1.13 M3
= 1.37 x 3.87 x 0.20 x 2.00 = 2.12 M3

3.25 M3

5 BATU KOSONG VOL. = P x L x T x JMH 5.92 M3


Memanjang = 7.00 x 0.80 x 0.20 x 2.00 = 2.24 M3
Melintang = 3.00 x 0.80 x 0.20 x 1.00 = 0.48 M3
= 4.00 x 0.80 x 0.20 x 5.00 = 3.20 M3

5.92 M3
6 PONDASI BATU KALI VOL. = P x L x T x JMH 8.33 M3
Memanjang = 7.00 x 0.45 x 0.50 x 2.00 = 3.15 M3
Melintang = 3.00 x 0.45 x 0.50 x 1.00 = 0.68 M3
= 4.00 x 0.45 x 0.50 x 5.00 = 4.50 M3

8.33 M3

IV PEKERJAAN BETON
1 BETON RABAT BWH LANTAI VOL. = P x L x T x JMH 1.24 M3
= 1.37 x 1.87 x 0.05 x 4.00 = 0.51 M3
= 1.87 x 3.87 x 0.05 x 2.00 = 0.72 M3

1.24 M3

5 SLOOF 15/20 VOL. = P x L x T x JMH 0.74 M3


memanjang Memanjang = 7.00 x 0.10 x 0.20 x 2.00 = 0.28 M3 ,
Melintang = 3.00 x 0.10 x 0.20 x 1.00 = 0.06 M3 #VALUE!
= 4.00 x 0.10 x 0.20 x 5.00 = 0.40 M3 -

0.74 M3

8 KOLOM 10/10 VOL. = T x JMH 64.60 M1


dibawah lantai = 0.40 x 17.00 = 6.80 M1
diatas lantai = 3.40 x 17.00 = 57.80 M1
64.60 M1

9 BALOK sunscreen 10/15 VOL. = P x JMH 26.80 M1


depan = 4.00 x 2.00 = 8.00 M1
belakang = 9.40 x 2.00 = 18.80 M1

26.80 M1

12 PLAT SUNSCREN T. 8CM VOL. = P x L x T x JMH 0.80 M3


depan 0.50 = 4.00 x 0.50 x 0.06 x 2.00 = 0.24 M3
samping 1.80 = 9.40 x 0.50 x 0.06 x 2.00 = 0.56 M3

0.80 M3

9 BALOK RING 10/15 VOL. = P x JMH 65.89 M1


Memanjang = 9.40 x 2.00 = 18.80 M1
= 3.00 x 1.00 = 3.00 M1
Melintang = 3.87 x 7.00 = 27.09 M1
gv = 4.25 4.00 = 17.00 M1

65.89 M1

V PEKERJAAN PASANGAN/PLEST.
2 Trasram Bata 1/2 bt VOL. = P x T x SISI 21.21 M2
memanjang 9.40 = 9.27 x 0.30 x 2.00 = 5.56 M2
7.00 = 6.87 x 0.30 x 2.00 = 4.12 M2
3.00 = 3.00 x 0.30 x 1.00 = 0.90 M2
melintang 5.20 = 4.85 x 0.30 x 2.00 = 2.91 M2
4.00 = 3.65 x 0.30 x 5.00 = 5.48 M2
km 2.00 = 1.87 x 0.30 x 4.00 = 2.24 M2

21.21 M2

2 Dinding Bata 1/2 bt - T.3 M VOL. = P x T x JMH 117.53 M2


2.1 memanjang 9.40 = 9.27 x 2.80 x - = - M2
7.00 = 6.87 x 2.80 x 2.00 = 38.47 M2
3.00 = 3.00 x 2.80 x 1.00 = 8.40 M2
melintang 5.20 = 4.85 x 2.80 x 2.00 = 27.16 M2
4.00 = 3.65 x 2.80 x 5.00 = 51.10 M2
4.00 = 3.87 x 1.50 x 2.00 = 11.61 M2

A 136.74 M2
B
lobang kusen = L x T x JMH
loster = 0.60 x 0.90 x 8.00 = 4.32 M2
P1 = 0.88 x 2.10 x 4.00 = 7.39 M2
lubang = 1.50 x 2.10 x 2.00 = 6.30 M2
= 0.50 x 0.60 x 4.00 = 1.20 M2
B 19.21 M2
VOL.AKHIR = A - B
= 136.74 - 19.21 = 117.53 M2

3 Plest.Dinding Bata VOL. = LUAS x SISI keramik wc 155.25 M2


= 117.53 X 2.00 - 79.81 = 155.25 M2
155.25 M2

4 Plest.Trasram Bata VOL. = LUAS x SISI 42.43 M2


= 21.21 X 2.00 = 42.43 M2
42.43 M2

5 Plesteran Beton VOL. = P x kllg x SISI 16.08 M2


sunscreen 4.00 = 4.00 x 0.60 x 2.00 = 4.80 M2
9.40 = 9.40 x 0.60 x 2.00 = 11.28 M2
16.08 M2

6 Plesteran Benangan VOL. = T/P x SISI x JMH 52.00 M1


sunscreen 4.00 = 4.00 x 2.00 x 2.00 = 16.00 M1
9.00 = 9.00 x 2.00 x 2.00 = 36.00 M1
52.00 M1

VI PEKERJAAN KERAMIK
1 LANTAI KERAMIK 30X30CM VOL. = P x L x JMH 41.72 M2
Dalam Ruang = 1.37 x 1.87 x 4.00 = 10.25 M2
= 1.87 x 3.87 x 2.00 = 14.47 M2
= 9.27 x 0.47 x 2.00 = 8.71 M2
= 3.87 x 1.07 x 2.00 = 8.28 M2
41.72 M2

5 DINDING KM/WC - RUANG VOL. = P/L x T x JMH 65.81 M2


150x150 = 5.60 x 1.80 x 4.00 - - = 40.32 M2
= 7.08 x 1.80 x 2.00 - - = 25.49 M2
65.81 M2

5 LOSTER PEJATEN 20X20 VOL. = P/L x T x JMH 4.32 M2


= 0.60 x 0.90 x 8.00 - - = 4.32 M2

4.32 M2

1 BATU ANDESIT VOL. = P x L x JMH 14.00 M2


SAMPING = 7.00 x 1.00 x 2.00 = 14.00 M2
14.00 M2

VII PEKERJAAN PLAFOND


1 PLAFOND KALSIBOARD - DALAM VOL. = P x L x JMH 24.72 M2
Dalam Ruang km/wc = 1.37 x 1.87 x 4.00 = 10.25 M2
ruang = 1.87 x 3.87 x 2.00 = 14.47 M2
24.72 M2

3 LISTPLAFOND GYPSUM - DALAM VOL. = P x JMH 48.88 M1


dalam = 6.48 x 4.00 = 25.92 M1
ruang = 11.48 x 2.00 = 22.96 M1

48.88 M1

1 PLAFOND KALSIBOARD - LUAR VOL. = P x L x JMH 17.00 M2


= 9.27 x 0.47 x 2.00 = 8.71 M2
= 3.87 x 1.07 x 2.00 = 8.28 M2

17.00 M2

3 LISTPLAFOND GYPSUM - LUAR VOL. = P x JMH 26.80 M1


= 26.80 x 1.00 = 26.80 M1

26.80 M1

VIII PEKERJAAN KUSEN KAYU

1 KUSEN KAYU VOL. = P x DIMENSI x JMH 0.14 M3


P1 = 5.20 x 0.05 x 0.13 x 4.00 = 0.14 M3
koboy = 5.20 x 0.05 x 0.13 x 2.00 = 0.07 M3
0.14 M3

7 DAUN PINTU WC VOL. = L x T x SISI x JMH 5.01 M2


Pw = 0.62 x 2.02 x 1.00 x 4.00 = 5.01 M2
5.01 M2

7 DAUN PINTU koboy VOL. = L x T x SISI x JMH 4.85 M2


p1 = 1.20 x 2.02 x 1.00 x 2.00 = 4.85 M2
4.85 M2

X PEKERJAAN PENGECATAN
1 POLITURAN DAUN PINTU VOL. = LUAS x SISI 14.71 M2
= 5.01 x 1.00 = 5.01 M2
= 4.85 x 2.00 = 9.70 M2
14.71 M2

1 CAT DINDING (Dalam) - BARU Luas = P x T x JMH 113.35 M2


A = 6.48 x 2.80 x 4.00 = 72.58 M2
= 11.48 x 2.80 x 2.00 = 64.29 M2
A 136.86 M2

B
Lbg kusen = L x T x JMH
PU = 0.80 x 2.09 x 8.00 = 13.38 M2
P1 = 1.20 x 2.09 x 2.00 = 5.02 M2
loster = 0.60 x 0.90 x 8.00 = 4.32 M2
v1 = 0.50 x 0.40 x 4.00 = 0.80 M2
B 23.51 M2

VOL.AKHIR = A - B
= 136.86 - 23.51 = 113.35 M2

3 CAT DINDING (Luar) - BARU VOL. = P x T x JMH 58.22 M2


A samping = 7.00 x 3.00 x 2.00 = 42.00 M2
depan = 4.00 x 3.00 x 2.00 = 24.00 M2
sunscren = 9.40 x 0.60 x 2.00 = 11.28 M2
= 4.00 x 0.60 x 2.00 = 4.80 M2
A 82.08 M2

B
Lbg kusen = L x T x JMH
p1 = 1.20 x 2.06 x 2.00 = 4.94 M2
loster = 0.60 x 0.90 x 8.00 = 4.32 M2
v1 = 0.60 x 0.50 x 2.00 = 0.60 M2
andesit = 7.00 x 1.00 x 2.00 = 14.00 M2
B 23.86 M2
VOL.AKHIR = A - B
= 82.08 - 23.86 = 58.22 M2

VII PEKERJAAN INSTALASI PIPA


1 PIPA PVC Ø 3/4'' - ALIRAN VOL. = P/L x JMH 31.50 M1
Dr instalasi lama = 15.00 x 1.00 = 15.00 M1
sambungan = 16.50 x 1.00 = 16.50 M1
31.50 M1

2 PIPA PVC Ø 1/2'' - washtafle VOL. = P/L x JMH 6.00 M1


Ke washtafle = 2.00 x 3.00 = 6.00 M1
6.00 M1
3 PIPA PVC Ø 2'' - washtafle VOL. = P/L x JMH 14.00 M1
Ke washtafle = 1.50 x 4.00 = 6.00 M1
= 4.00 x 2.00 = 8.00 M1
14.00 M1

4 PIPA PVC Ø 3'' VOL. = P/L x JMH 9.00 M1


Dari lt 2 ke lt.1 = 5.00 x 1.00 = 5.00 M1
Ke peresapan = 4.00 x 1.00 = 4.00 M1
9.00 M1

VII PEKERJAAN ATAP


1 ATAP GENTENG VOL. = P x L x JMH 79.90 M2
= 9.40 x 4.25 x 2.00 = 79.90 M2

79.90 M2

4 BUBUNGAN VOL. = P/L x JMH 9.40 M1


NOK = 9.40 x 1.00 = 9.40 M1

9.40 M1

4 KALSIPLANK VOL. = P/L x JMH 27.30 M1


= 9.40 x 2.00 = 18.80 M1
= 4.25 x 2.00 = 8.50 M1
27.30 M1

Anda mungkin juga menyukai