Anda di halaman 1dari 2

DAFTAR HARGA UPAH BORONG KERJA PERUMAHAN INSANUTAMA RESIDENCE & COURSES

LOKASI KERJA : PARE - KEDIRI PERIODE : AGUSTUS s.d DESEMBER 2019 2019

No JENIS PEKERJAAN SAT VLM HARGA/SAT HARGA TOTAL

D PEKERJAAN PASANGAN
1 Pasang aanstamping batu kali m3 - -
2 Pasang pondasi batu kali/kumbung m3 - -
3 Pasang rolag m' - -
4 Pasang pavingstone (perataan, pemadatan, pemberian abu batu) m2 - -
5 Pasang kanstin/paving S ujung lengkap cor m' - -
6 Pasang bata merah/hebel lantai I m2 75 45,000 3,375,000
7 Pasang bata merah/hebel lantai II m2 75 55,000 4,125,000
8 Pasang bata merah/hebel lantai III dan lantai IV m2 - -
9 Pasang Roaster Salib bh -
10 Pasang Glassblock bh -
11 Pasang keramik lantai (60x60) termasuk las m2 125 55,000 6,875,000
12 Pasang keramik lantai (40x40) termasuk las m2 - -
13 Pasang keramik kolom (30x30/40x40) termasuk las m2 - -
14 Pasang keramik lantai carport termasuk las m2 25 50,000 1,250,000
15 Pasang keramik dinding termasuk las m2 15 50,000 750,000
16 Pasang batu alam m2 6 50,000 300,000
17 Pasang keramik meja dapur (20x25) termasuk las ut 6 45,000 270,000
18 Pasang keramik meja dapur (20x20) termasuk las m2 6 45,000 270,000
19 Prostekan keramik m' - -
20 Pasang woodplank untuk dinding m2 - -

F PEKERJAAN PLESTERAN
1 Plesteran dinding bata + kepalaan (lantai I) m2 400 45,000 18,000,000
2 Acian dinding bata (lantai I) m2 400 30,000 12,000,000
3 Plesteran dinding bata + kepalaan (lantai II) m2 400 55,000 22,000,000
4 Acian dinding bata (lantai II) m2 400 40,000 16,000,000
5 Plesteran dinding bata + kepalaan (Gewel) m2 65,000 -
6 Acian dinding bata (Gewel) m2 55,000 -
7 Benangan m' 150 25,000 3,750,000
8 Ban2an m' 150 25,000 3,750,000
9 Sudutan m' 20,000 -

G PEKERJAAN BETON BERTULANG


1 Rabat lantai kerja 1:3:5 (t=5cm) tanpa pembesian m2 65 35,000 2,275,000
2 Cor Pondasi Plat Setempat+pembesian+bekisting (site mix) m3 - -
3 Cor sloof+pembesian+bekisting (site mix) m3 10 95,000 950,000
4 Cor kolom praktis+pembesian+bekisting (site mix) m3 10 85,000 850,000
5 Cor ring balk 10/15+pembesian+bekisting (site mix) m3 10 95,000 950,000
6 Cor ring balk 12/12+pembesian+bekisting (site mix) m3 10 105,000 1,050,000
7 Cor balok stopper teras 10/15+pembesian+bekisting (site mix) m3 -
8 Cor kolom struktur 20/20+pembesian+bekisting (site mix) m3 10 105,000 1,050,000
9 Cor kolom struktur 25/25+pembesian+bekisting (site mix) m3 10 105,000 1,050,000
10 Cor balok gantung 15/30+pembesian+bekisting (site mix) m3 10 105,000 1,050,000
11 Cor balok gantung 20/40+pembesian+bekisting (site mix) m3 10 105,000 1,050,000
12 Cor balok konsol 15/30+pembesian+bekisting (site mix) m3 10 105,000 1,050,000
13 Cor lisplank beton t=8cm+pembesian+bekisting (site mix) m3 - -
14 Cor dug beton t=8cm+pembesian+bekisting (site mix) m3 - -
15 Cor dug beton t=18cm+pembesian+bekisting (site mix) m3 8.037 850,000 6,831,450
16 Cor plat tempat sabun ut - -
17 Cor meja dapur+pembesian+bekisting (site mix) ut 1 250,000 250,000
18 Cor tutup septictank & resapan+pembesian+bekisting (site mix) set 2 250,000 500,000
19 Cor tutup bak kontrol+pembesian+bekisting (site mix) set 2 250,000 500,000
20 Cor lantai beton t=5cm+pembesian ȼ6mm-200 m3 4 250,000 1,000,000
21 Rabatan diatas waterproofing m2 -
22 Buat beton decker t=15cm+pembesian D13mm+bekisting (site mix) m3 -
23 Buat beton decker t=20cm+pembesian D16mm+bekisting (site mix) m3 -

DAFTAR HARGA UPAH BORONG KERJA PERUMAHAN INSANUTAMA RESIDENCE & COURSES
LOKASI KERJA : PARE - KEDIRI PERIODE : AGUSTUS s.d DESEMBER 2019 2019
24 Beton bertulang lain-lain (selain No. G2 s.d G23) -
a. Cor beton Sitemix m3 -
b. Cor beton Readymix m3 -
c. Bekisting m2 -
d. Pekerjaan Stager/Perancah Bekisting (bongkar + pasang) m2 -
e. Pembesian kg m2 -
f. Pembesian wiremesh bh -
g. Korset bh -
J PEKERJAAN SANITARY
1 Pasang pipa PVC 3/4" s.d 2" + bobokan + kawat ram lengkap cor m' 8 35,000 280,000
2 Pasang pipa PVC 2,5" s.d 4" + bobokan + kawat ram lengkap cor m' 8 35,000 280,000
3 Instalasi pompa air biasa ut 1 250,000 250,000
4 Buat bak mandi keramik ut - -
5 Ps. Closet jongkok/duduk ut 1 175,000 175,000
6 Buat bak kontrol pasangan bata + tutup beton 6cm ut 2 200,000 400,000
7 Pasang kicthen zinc 1 lubang ut 1 200,000 200,000
8 Pasang stop kran ut 2 25,000 50,000
9 Pasang avour ut 3 25,000 75,000
10 Pasang hand shower ut 3 50,000 150,000
11 Pasang jet shower ut -
12 Pasang kran air leher angsa ut 1 50,000 50,000
13 Buat septictank 3 buis ȼ80cm lengkap galian + tutup ut 1 750,000 750,000
14 Buat resapan dari pasangan bata kosong ȼ80cm ut 1 750,000 750,000
15 Pasang tandon air atas lengkap aksesoris sanitair ut -

K PEKERJAAN LAIN-LAIN*
1 Waterproofing dag beton dengan SIKATOP 107 m2 -
(Termasuk pembersihan dag beton sebelum di waterproofing) -
2 Pembersihan kotoran s.d bersih untuk serah terima -
a. Kategori bangunan baik N4 m2 100 35,000 3,500,000
b. Kategori bangunan kotor sedang N4 m2 -
c. Kategori bangunan sangat kotor N4 m2 -
3 Pasang scafolding m2 100 30,000 3,000,000
4 Pekerjaan yang tidak bisa diopname -
a. Tukang tkg tkng -
b. Pembantu pbt pmbt -
5 Bongkar perancah dari bambu m2 -
6 Pasang perancah dari bambu m2 -
123,031,450