A PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 3,00 Lot
2 Barak Kerja 1,00 Lot
3 Listrik Kerja 1,00 Lot
4 Pengukuran & Bouplank 344,00 m2
Sub Total A
B PEKERJAAN TANAH
1 Galian Tanah Foot Plate @ 1000mm x 1000mm x 1000mm (85 titik) + urug 85 m3
2 Galian Tanah Foot Plate @ 800mm x 800mm x 1000mm (95 titik) + urug 60,8 m3
3 Galian Sloof @ 200mm x 300mm x (261 meter) + Urug 15,66 m3
4 Galian Drainase @ 60cm x 50cm (275 meter) + Urug 96,25 m3
Sub Total B
C PEKERJAAN BETON
1 Pondasi Setapak 800mm x 800mm x 1000mm (85 titik) K-175 20,4 m3
2 Pondasi Setapak 600mm x 600mm x 1000mm (95 titik) K-175 15,2 m3
3 Sloof Gantung @ 15cm x 25cm (561,6 meter) K-175 210,563 m3
4 Plate Lantai Bawah @ T 10cm K-225 (1566.4 m2) 156,64 m3
a. Plastik Cor
b. Wiremess M8 1 Layer
c. Trowel
d. Begisting
Sub Total C
D PEKERJAAN PASANGAN DINDING HEBEL
Pekerjaan Dinding Hebel + Plesteran + Acian 263 m2
a. Bata Hebel 100mm x 200mm x 600mm
b. MU - 380 @ 40kg Perekat T.3mm
c. MU - 301 @ 40kg Perekat T.15mm
d. MU - 200 @ 40kg Acian T.2mm
Sub Total D
E PEKERJAAN DRAINASE
Pekerjaan Pasangan Bata Merah + Plesteran + Acian 268 m1
Sub Total E
F PEKERJAAN KONTRUKSI BAJA
a. Baja IWF 200 x 100 x 5.5 x 8 15.528
b. Baja IWF 150 x 75 x 5 x7 12.146
c Plat Simpul 2.992
d. Ikatan Angin Rb @ 12mm 895
e. Clem Bakel @ 5/8 x 8inc 84
f. Stud Gordeng Rb @ 10mm 520
g. Angkur Baut @ 5/8 x 20cm 176
h. Baut Hitam @ 12mm x 2,5inc 1.800
i. Baut Hitam @ 10mm x 2,5inc 700
j. Baut Hitam @ 10mm x 2inc 400
k CNP 125, 50, 20,2 2.772
l Angku Baut @ 5/8 x 600mm 720