RENCANA ANGGARAN BIAYA PEKERJAAN KANTIN KANTOR INDOMARET

NO NAMA PEKERJAAN SATUAN VOLUME HRG SATUAN HRG TOTAL


1 PEKERJAAN SIPIL Ls 1 5,594,800 5,594,800
2 MATERIAL LISTRIK Ls 1 2,400,300 2,400,300
3 AREA DEPAN TOILET Ls 1 503,354 503,354
SUB TOTAL 8,498,454

PEKERJAAN SIPIL
NO NAMA PEKERJAAN SATUAN VOLUME HRG SATUAN HRG TOTAL
1 Kanopi Zyncalum m² 6.175 300,000 1,852,500
2 Grill penutup got m² 1.38 125,000 172,500
3 Polycarbonate m² 3.92 125,000 490,000
4 Zink Wastafel + Kran air unit 3 600,000 1,800,000
5 Pipa PVC ½" (saluran air bersih) ujg 4 25,000 100,000
6 Pipa PVC 2" (saluran air kotor) ujg 2 110,000 220,000
7 Knee ½" Pcs 4 3,200 12,800
8 Tee ½" Pcs 2 4,000 8,000
9 Knee 2" Pcs 6 21,500 129,000
Besi siku 4 x 4 (perkuatan rangka grill ujg 6 135,000 810,000
10 penutup got)
SUB TOTAL 5,594,800

MATERIAL LISTRIK
NO NAMA PEKERJAAN SATUAN VOLUME HRG SATUAN HRG TOTAL
1 Stopkontak 3 lubang Pcs 3 24,300 72,900
2 Pipa Kabel Listrik ujg 8 15,000 120,000
3 Knee Pipa Listrik Pcs 10 1,000 10,000
4 Klem Pipa Listrik Pcs 25 500 12,500
5 Sock Pipa Listrik Pcs 1 1,000 1,000
6 Paku beton 1" dus 1 25,000 25,000
7 Saklar single + Outbow dus saklar Pcs 3 28,300 84,900
8 Lampu Phillips LED 20 W + Fitting unit 3 100,200 300,600
9 Kabel Supreme NYM 3 x 2,5 mm (100 m) Roll 1 1,741,000 1,741,000
10 Isolasi Listrik Pcs 2 11,000 22,000
11 Tedos Pcs 4 2,600 10,400
SUB TOTAL 2,400,300

AREA DEPAN TOILET


NO NAMA PEKERJAAN SATUAN VOLUME HRG SATUAN HRG TOTAL
1 Urugan Tanah m³ 1.80 200,000 360,225
2 Urugan Pasir m³ 0.72 200,000 143,129
SUB TOTAL 503,354
Disetujui Diperiksa

BM DBM HRM PM
Dibuat

BMT