RENCANA ANGGARAN BIAYA PEKERJAAN KANTIN KANTOR INDOMARET

NO NAMA PEKERJAAN SATUAN VOLUME HRG SATUAN HRG TOTAL


1 PEKERJAAN SIPIL Ls 1 5.594.800 5.594.800
2 MATERIAL LISTRIK Ls 1 2.400.300 2.400.300
3 AREA DEPAN TOILET Ls 1 503.354 503.354
SUB TOTAL 8.498.454

PEKERJAAN SIPIL
NO NAMA PEKERJAAN SATUAN VOLUME HRG SATUAN HRG TOTAL
1 Kanopi Zyncalum m² 6,175 300.000 1.852.500
2 Grill penutup got m² 1,38 125.000 172.500
3 Polycarbonate m² 3,92 125.000 490.000
4 Zink Wastafel + Kran air unit 3 600.000 1.800.000
5 Pipa PVC ½" (saluran air bersih) ujg 4 25.000 100.000
6 Pipa PVC 2" (saluran air kotor) ujg 2 110.000 220.000
7 Knee ½" Pcs 4 3.200 12.800
8 Tee ½" Pcs 2 4.000 8.000
9 Knee 2" Pcs 6 21.500 129.000
Besi siku 4 x 4 (perkuatan rangka grill
ujg 6 135.000 810.000
10 penutup got)
SUB TOTAL 5.594.800

MATERIAL LISTRIK
NO NAMA PEKERJAAN SATUAN VOLUME HRG SATUAN HRG TOTAL
1 Stopkontak 3 lubang Pcs 3 24.300 72.900
2 Pipa Kabel Listrik ujg 8 15.000 120.000
3 Knee Pipa Listrik Pcs 10 1.000 10.000
4 Klem Pipa Listrik Pcs 25 500 12.500
5 Sock Pipa Listrik Pcs 1 1.000 1.000
6 Paku beton 1" dus 1 25.000 25.000
7 Saklar single + Outbow dus saklar Pcs 3 28.300 84.900
8 Lampu Phillips LED 20 W + Fitting unit 3 100.200 300.600
9 Kabel Supreme NYM 3 x 2,5 mm (100 m) Roll 1 1.741.000 1.741.000
10 Isolasi Listrik Pcs 2 11.000 22.000
11 Tedos Pcs 4 2.600 10.400
SUB TOTAL 2.400.300

AREA DEPAN TOILET


NO NAMA PEKERJAAN SATUAN VOLUME HRG SATUAN HRG TOTAL
1 Urugan Tanah m³ 1,80 200.000 360.225
2 Urugan Pasir m³ 0,72 200.000 143.129
SUB TOTAL 503.354