I PEKERJAAN PERSIAPAN
1 Mobilisasi 1 Ls 13.165.098
JUMLAH I 13.165.098
II PENGADAAN PERALATAN
1 Cone Fan Butterfly Punos 50’’ (3 Phase) Siemens 8 Roll 53.360.000
2 Kabel Eterna Uk.3 X 2,5 Mm @50 Mtr 8 Pcs 7.135.336
3 Collingpad Punos Uk.150 X 60 X 15 Cm 60 Btg 24.495.000
4 Gutter Atas 12 Btg 6.555.000
5 Gutter Bawah 12 Btg 6.555.000
6 Gutter Samping 8 Unit 2.530.000
7 Regulator Nipple 4 Set 1.610.000
8 Super Feeder Punos 600 Btg 17.043.000
9 Paket Pipa Pvc Wavin Uk.3/4’’ + Nipple Punos : 16 Pcs 150 Unit 20.700.000