Pasal 2

RUANG LINGKUP PEKERJAAN

HARGA
NO URAIAN PEKERJAAN JUMLAH SATUAN JUMLAH HARGA KET.
SATUAN

A Pekerjaan Persiapan
K3 dan Perlindungan Lingkungan
1 Sarung Tangan 12 Psg 8.500 102.000 Barang
2 Masker Hidung dan Mulut 2 Pak 29.600 59.200 Barang

B Pemasangan Panel ATS 25 kVa


1 Panel Enclosure 700 x 500 x 200 mm 1 Unit 3.473.600 3.473.600 Barang
2 COS Motorized 63A - 4 Pole 1 Unit 4.048.700 4.048.700 Barang
3 MCCB Outgoing 80A - 3 Pole 1 Unit 2.289.100 2.289.100 Barang
4 MCB Control 10A - 1 Pole 2 Unit 166.800 333.600 Barang
5 Fuse Base and Link 10A - 1 Pole 3 Set 10.800 32.400 Barang
6 Battery Charger 12V/5A 1 Unit 2.202.600 2.202.600 Barang
7 Pilot Lamp 22 mm - 220 Vac 5 Unit 103.000 515.000 Barang
8 Paku Beton 3 cm 1,25 Pak 62.500 78.125 Barang
9 Dynabolt M8x65 mm 8 Pcs 88.000 704.000 Barang

C Instalasi Kabel Genset


1 Kabel Power Al. NFA2X-T 4x16 mm 100 Meter 141.654 14.165.364 Barang
2 Kabel Control Al. NYY 4x1.5 mm 100 Meter 130.520 13.052.000 Barang
3 Kabel Penerangan NYM 2 x 1.5 mm 50 Meter 45.000 2.250.000 Barang
4 Cable Duct PVC 1700 x 100 x 50 mm 10 Set 80.000 800.000 Barang
5 Cable Conduit 3/4" x 3000 mm 10 Btg 38.295 382.950 Barang
6 Saklar dan Fitting Lampu 1 Titik 174.826 174.826 Barang
7 Cable Ties 20 cm x 3 mm 1,25 Pak 25.000 31.250 Barang
8 Cable Lugs SC16-8 30 Pcs 75.000 2.250.000 Barang
9 Cable Vynil V18 30 Pcs 51.000 1.530.000 Barang
10 Klem Pipa Conduit 3/4" 30 Pcs 6.000 180.000 Barang

D Exhaust Stack (Kenalpot Genset)


1 Exhaust Stack (Pipa Kenalpot) 2" 1 Set 850.000 850.000 Barang
Pipa Medium 2" - 6 Meter
Elbow 90O - 2"
2 Batu Gerinda Potong 4" (Inch) 2 Pcs 12.900 25.800 Barang
3 Kawat Las 2.6 mm 5 Pcs 1.550 7.750 Barang

E Pemasangan Grounding
(Pentanahan) Generator Set
1 Pengadaan Grounding Rod Cu. 5/8" x 1 Btg 780.000 780.000 Barang
1000 mm
2 Pengadaan Kabel BC 16 mm 3 Meter 135.000 405.000 Barang

F Pekerjaan Jasa Instalasi


1 Mobilisasi Material, Peralatan dan 1 LS 2.000.000 2.000.000 Jasa
Personnel
2 Instalasi Panel ATS 25 kVA 1 Ls 5.000.000 5.000.000 Jasa
3 Instalasi Kabel Genset 1 Ls 9.100.000 9.100.000 Jasa
4 Instalasi Exhaust Stack 1 Ls 1.225.000 1.225.000 Jasa
5 Instalasi Grounding Set 1 Titik 250.000 250.000 Jasa
6 Pembersihan Lokasi 1 Titik 1.000.000 1.000.000 Jasa

Jumlah 69.298.265,00
Pembulatan 69.298.000,00
PPN 11% 7.622.780,00
Jumlah Total 76.920.780,00
*** Tujuh Puluh Enam Juta Sembilan Ratus Dua Puluh Ribu Tujuh Ratus Delapan Puluh
Terbilang :
Rupiah***

Barang 50.723.265,00
Jasa 18.575.000,00