PT.

DUNIA DAGING FOOD INDUSTRIES


PROYEK PEMBANGUNAN PABRIK PENGOLAHAN DAGING
PURWAKARTA - JAWA BARAT

EXTERNAL WORKS

PEKERJAAN RUANG CHILLER

HARGA
JUMLAH HARGA
No. URAIAN PEKERJAAN Qty Unit SATUAN Remarks
(Rp)
(Rp)

RUANG CHILLER

A Pekerjaan Galian Tanah


1 Galian Tanah Sloof & Pondasi Tapak 9.48 m3 78,000 739,440
2 Galian Tanah Pondasi Strauss Pile, kedalaman 2m, dia 15cm 20.00 titik 50,000 1,000,000
3 Urugan Tanah Kembali 5.59 m3 31,500 176,085

B Pondasi Struspile Dia.15 cm - 2 meter


1 Beton K-300 0.71 m3
2 Tul. Utama D19 mm (3 btg - 2 meter) 267.07 kg 12,500 3,338,348
3 Cincin/Sengkang D8-150 mm 52.03 kg 12,500 650,432

C. Pondasi Tapak 1500x800x350


1 Beton K-300 1.68 m3
2 Tul. Utama D16-150 mm Pile Cap 299.55 kg 12,500 3,744,374

D Kolom Pedestal
1 Beton K-300 2.20 m3 1,000,000 2,200,000
2 Tul. Utama D13 Pedestal 288.39 kg 12,500 3,604,922
3 Cincin Sengkang D8-150 mm Pedestal 51.01 kg 12,500 637,609

E Pek.Sloof
1 Beton K-300 1.66 m3 1,000,000 1,662,750
2 Tul. Utama D19 175.02 kg 12,500 2,187,730
3 Tul. Utama D10 9.56 kg 12,500 119,447
4 Tul. Extra D10 14.80 kg 12,500 184,950
5 Cincin Sengkang D10-150 mm 28.44 kg 12,500 355,451

F Angkur
1 Angkur D16 16.00 Bh 150,000 2,400,000

F PEKERJAAN BAJA Ruang Chiller LT 1 & 2


1 KOLOM BAJA
- BAJA IWF 300 x 300 8,047.68 Kg 16,500 132,786,720
2 H BEAM BALOK LANTAI
- HC 450 x 150 6,550.80 Kg 17,100 112,018,680
- HC 675 x 200 5,326.08 kg 17,100 91,075,968
- Baut 3/4 x 3" x 7.5 cm 100.00 Bh 7,000 700,000
- Baut 3/4 x 2.5" x 7.5 cm 380.00 Bh 7,000 2,660,000
3 PELAT SAMBUNGAN
- Plat Tb 10 mm 3.97 m2 190,000 753,607
- Plat Bracket Tb 10 mm & 8 mm 4.31 m2 190,000 819,774
4 PENUTUP BAJA HC
- Plat Tb 6 mm 7.92 m2 190,000 1,504,800
- Plat Tb 10 mm 1.13 m2 190,000 214,130
5 PLAT BONDEK
- Pelat Bondek 0.75mm 314.00 m2 230,000 72,220,000
- Shear Connector D16 mm ,Jarak 150mm, Pj 10 cm 330.38 Kg 12,500 4,129,728

G Beton Lantai, mutu K-300 Tbl 15 cm 47.10 m3 1,000,000 47,100,000

H Wiremesh M8 (2 Lapis) 3,421.88 Kg 13,500 46,195,381

I PEKERJAAN TANGGA
- Galian Tanah Pondasi m3
- Urugan Tanah Kembali m3
- Pembesian Pondasi Tangga
- Besi kg
- Besi kg
- kg
-
- Coran K-300 m3

Sub Bill No. 21 Pekerjaan R.Chiller Ke Summary Bill No. 1 535,180,326


Jasa 2,70% 14,449,869
Total 549,630,194
PPN 10 % 54,963,019
Total 604,593,214
Rounded 604,600,000