1 Mandor Oh 160,000.00
2 Kepala Tukang Oh 150,000.00
3 Tukang Batu Oh 140,000.00
4 Tukang Listrik Oh 140,000.00
5 Tukang Kayu Oh 140,000.00
6 Tukang Besi Oh 140,000.00
7 Tukang Cat Oh 140,000.00
8 Tukang Pipa Oh 140,000.00
9 Tukang Las Oh 140,000.00
10 Pekerja Oh 120,000.00
Kerikil M3
Pasir Cor/Beton ( Lokal) M3 180,000.00
Pasir Plesteran M3
Pasir Urug M3
Pasir Pasang M3
Batu Bata Merah Buah
Batu Tela Buah
Batu Pecah 2/3 M3
Batu Belah M3
Timbunan Biasa M3
Semen Portland 50 Kg Zak
Semen Portland Kg
Semen Warna Kg
Paving Block Bata Bh 5,500.00
Paving Block Bata 50 Buah/m2 275,000.00
Paving Block 3 Berlian Bh 8,500.00
Paving Block 3 Berlian 33 Buah/m2 280,500.00
Amplas M' -
Dempul/Plamir Kayu Kg -
Plamir Tembok Kg -
Plamir Kayu Kg -
Politur Kg
Politur Jadi Kg
Cat Dasar Kayu Kg -
Cat Meni Kayu Kg -
Cat Penutup Kayu Kg -
Cat Kayu Kilap Kg -
Cat Dasar Tembok 5 Kg Kg 24,150.00
Cat Dasar Tembok Kg 4,830.00
Cat Penutup Tembok Kg 4,830.00
Kuas 2" Bh 115,000.00
Kuas 3" Bh 110,000.00
Minyak Cat/ Thinner Kg 17.00
Cat Genteng Kg
Rol Cat Bh 125,000.00
Lem Kayu Kg 135,000.00
Minyak Bekisting Liter 17.00
Sealant Kg 10,000.00
Soda Api Kg 37,000.00
C Bahan Kayu Berikut Bahan Jadinya
F Bahan Perpipaan
I Bahan Kaca
J Bahan Sanitair
K Bahan Mekanikal
Lampu SL 23 Watt Bh -
Lampu SL 18 Watt Bh -
Saklar Tunggal Bh -
Saklar Ganda Bh -
Inbow dus Bh 10,000.00
Kabel NYM 2 x 2,5 mm M' -
Stop Kontak Bh -
Sekering Box Bh -
Fitting Bh 10,000.00
Tee Dos Bh 25,000.00
KETERANGAN
quary
quary 180
quary
quary
quary
quary
site
site
site
site
site
site
site
site
site
quary
quary
quary
quary
quary
quary
quary
RJA
KETERANGAN
TERIAL
KETERANGAN
PEKERJAAN PERSIAPAN
1 M' PEMASANGAN BOWPLANK
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 140,000 14,000
Tukang Kayu L.02 OH 0.100 140,000 14,000
Kepala Tukang L.03 OH 0.010 150,000 1,500
Mandor L.04 OH 0.005 160,000 800
JUMLAH TENAGA KERJA 30,300
B BAHAN
Kayu Balok 5/7 m3 0.012 2,100,000 25,200
paku 2"-3" Kg 0.020 18,000 360
Kayu Papan Lbr 0.007 2,100,000 14,700
JUMLAH BAHAN 40,260
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 70,560
E Overhead & profit 8,820
F Harga Satuan Pekerjaan (D+E) 79,380
JUMLAH PERALATAN
D Jumlah (A+B+C) 20,000
E Overhead & profit 2,500
F Harga Satuan Pekerjaan (D+E) 22,500
PEKERJAAN TANAH
1 M3 PEKERJAAN GALIAN TANAH BIASA SEDALAM 1 METER
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.750 120,000 90,000
Mandor L.04 OH 0.025 160,000 4,000
JUMLAH TENAGA KERJA 94,000
B BAHAN
JUMLAH BAHAN
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 94,000
E Overhead & profit 11,750
F Harga Satuan Pekerjaan (D+E) 105,750
JUMLAH BAHAN
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 68,000
E Overhead & profit 8,500
F Harga Satuan Pekerjaan (D+E) 76,500
1 M3 PENGURUGAN PASIR
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 120,000 36,000
Mandor L.04 OH 0.010 160,000 1,600
JUMLAH TENAGA KERJA 37,600
B BAHAN
Pasir Urug 1.200 50,000 60,000
JUMLAH BAHAN 60,000
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 97,600
E Overhead & profit 12,200
F Harga Satuan Pekerjaan (D+E) 109,800
JUMLAH PERALATAN
D Jumlah (A+B+C) 97,600
E Overhead & profit 12,200
F Harga Satuan Pekerjaan (D+E) 109,800
1 METER PASANGAN PONDASI CAMPURAN 1 PC : 4 PS
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 120,000 180,000
Tukang Kayu L.02 OH 0.750 140,000 105,000
Kepala Tukang L.03 OH 0.075 150,000 11,250
Mandor L.04 OH 0.075 160,000 12,000
JUMLAH TENAGA KERJA 308,250
B BAHAN
Batu Belah m3 1.200 320,000 384,000
Semen Portland Kg 163.000 1,800 293,400
Pasir Pasang m3 0.520 160,000 83,200
JUMLAH BAHAN 760,600
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 1,068,850
E Overhead & profit 133,606
F Harga Satuan Pekerjaan (D+E) 1,202,456
JUMLAH PERALATAN
D Jumlah (A+B+C) 1,068,850
E Overhead & profit 133,606
F Harga Satuan Pekerjaan (D+E) 1,202,456
1 M3 PASANGAN BATU KOSONG
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.780 120,000 93,600
Tukang L.02 OH 0.390 140,000 54,600
Kepala Tukang L.03 OH 0.039 150,000 5,850
Mandor L.04 OH 0.039 160,000 6,240
JUMLAH TENAGA KERJA 160,290
B BAHAN
Batu Belah m3 1.200 320,000 384,000
Pasir Urug m3 0.432 50,000 21,600
JUMLAH BAHAN 405,600
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 565,890
E Overhead & profit 70,736
F Harga Satuan Pekerjaan (D+E) 636,626
JUMLAH PERALATAN
Pembesian
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 120,000 6,000
Tukang L.02 OH 0.050 140,000 7,000
Kepala Tukang L.03 OH 0.005 150,000 750
Mandor L.04 OH 0.003 160,000 480
JUMLAH TENAGA KERJA 14,230
B BAHAN
Besi Beton Kg 1.05 12,000 12,600
Kawat Beton Kg 0.100 27,500 2,750
JUMLAH BAHAN 15,350
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 15,765
E Overhead & profit 1,577
F Harga Satuan Pekerjaan (D+E) 17,342
1 m2 bekisting Kolom
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.660 120,000 79,200
Tukang L.02 OH 0.330 140,000 46,200
Kepala Tukang L.03 OH 0.033 150,000 4,950
Mandor L.04 OH 0.033 160,000 5,280
JUMLAH TENAGA KERJA 135,630
B BAHAN
Kayu Kelas II m3 0.04 2,400,000 96,000
Paku 5-12 cm Kg 0.400 18,000 7,200
Minyak Bekisting Liter 0.200 3,300 660
Balok Kayu Kelas III m3 0.015 2,100,000 31,500
Kayu Kelas II Lebar 0.035 170,000 5,950
Dolken Kayu 8-10cm panjang 4m Batang 2.000 35,000 70,000
JUMLAH BAHAN 211,310
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 346,940
E Overhead & profit 43,368
F Harga Satuan Pekerjaan (D+E) 390,308
1 m2 bekisting pondasi
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.520 120,000 62,400
Tukang L.02 OH 0.260 140,000 36,400
Kepala Tukang L.03 OH 0.026 150,000 3,900
Mandor L.04 OH 0.026 160,000 4,160
JUMLAH TENAGA KERJA 106,860
B BAHAN
Kayu Kelas II m3 0.04 2,400,000 96,000
Paku 5-12 cm Kg 0.300 18,000 5,400
Minyak Bekisting Liter 0.100 3,300 330
JUMLAH BAHAN 101,730
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 208,590
E Overhead & profit 26,074
F Harga Satuan Pekerjaan (D+E) 234,664
JUMLAH PERALATAN
JUMLAH PERALATAN
JUMLAH PERALATAN
cor beton 1:2:3 K.175 (m3) (SNI 7394-2008-05) f'c=14.5 Mpa slump (12±2) cm w/c=0.66
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.65 120,000 198,000
Tukang L.02 OH 0.275 140,000 38,500
Kepala Tukang L.03 OH 0.111 150,000 16,650
Mandor L.04 OH 0.083 160,000 13,280
JUMLAH TENAGA KERJA 266,430
B BAHAN
Semen Portland Kg 326 1,800 586,800
Pasir Beton m3 0.5429 180,000 97,722
Agregat 2/3 m3 0.5717 425,000 242,973
JUMLAH BAHAN 927,495
C PERALATAN
JUMLAH PERALATAN
JUMLAH PERALATAN
JUMLAH PERALATAN
D 186,480
E Overhead & profit 23,310
F Harga Satuan Pekerjaan (D+E) 209,790
JUMLAH PERALATAN
D Jumlah (A+B+C) 85,586
E Overhead & profit 10,698
F Harga Satuan Pekerjaan (D+E) 96,284
Acian (m2)
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 120,000 24,000
Tukang L.02 OH 0.100 140,000 14,000
Kepala Tukang L.03 OH 0.010 150,000 1,500
Mandor L.04 OH 0.010 160,000 1,600
JUMLAH TENAGA KERJA 41,100
B BAHAN
Semen Portland Kg 3.250 1,800 5,850
JUMLAH PERALATAN
D Jumlah (A+B+C) 46,950
E Overhead & profit 5,869
F Harga Satuan Pekerjaan (D+E) 52,819
JUMLAH PERALATAN
D Jumlah (A+B+C) 47,335
E Overhead & profit 5,917
F Harga Satuan Pekerjaan (D+E) 53,252
Membuat 1 m3 beton mutu f’c = 24,0 Mpa
Harga Jumlah
No Uraian Kode Satuan Koefisien satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.65 120,000 198,000
Tukang L.02 OH 0.275 140,000 38,500
Kepala Tukang L.03 OH 0.028 150,000 4,200
Mandor L.04 OH 0.083 160,000 13,280
JUMLAH TENAGA KERJA 253,980
B BAHAN
Semen Portland kg 406 1,800 730,800
Pasir Beton kg 684 128.571.4 87,943
Kerikil kg 1026 236.111.1 242,250
Air Liter 215 50.000.0 10,750
JUMLAH BAHAN 1,071,743
C PERALATAN
JUMLAH PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 207,090
E Overhead & profit 25,886
F Harga Satuan Pekerjaan (D+E) 232,976
NO. URAIAN PEKERJAAN VOLUME SAT. HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6
I. PEKERJAAN PENDAHULUAN
1 Pek. Pengukuran dan Pemasangan Bouplank 66.00 1 Rp 79,380.00 Rp 5,239,080.00
2 Pelaporan dan Dokumentasi 1.00 Ls Rp 1,000,000.00 Rp 1,000,000.00
3 Listrik dan Air Kerja 1.00 Ls Rp 2,000,000.00 Rp 2,000,000.00
4 Pek. Papan nama Proyek 1.00 bh Rp 500,000.00 Rp 500,000.00
Jumlah I. Rp 8,739,080.00
II. PEKERJAAN TANAH
1 Pek. Galian tanah pondasi menerus 66.00 m3 Rp 105,750.00 Rp 6,979,500.00
2 Pek. Urugan Tanah Kembali 24.00 m3 Rp 76,500.00 Rp 1,836,000.00
3 Pek. Urugan Pasir Bawah Pondasi 3.30 m3 Rp 109,800.00 Rp 362,340.00
Jumlah II. Rp 9,177,840.00
III. PEKERJAAN PONDASI
1 Pek. Pondasi Batu Camp 1:4 66.00 m3 Rp 1,202,456.25 Rp 79,362,112.50
2 Pek. Pas Dinding Talud 85.80 m3 Rp 1,202,456.25 Rp 103,170,746.25
3 Pek. Plesteran, camp 1 : 4 228.75 m2 Rp 96,284.25 Rp 22,025,022.19
Jumlah III. Rp 182,532,858.75
IV. PEKERJAAN STRUKTUR BETON DAN PEMBESIAN
1 Pek. Sloof Beton Bertulang 25x25 cm
a. Beton Mutu f’c = 24,0 Mpa 4.13 m3 Rp 5,227,845.75 Rp 21,564,863.72
b. Bekisting 4.95 m2 Rp 232,976.25 Rp 1,153,232.44
Jumlah IV. Rp 22,718,096.16
2 Pek. Kolom Beton Bertulang 25x25 cm
a. Beton Mutu f’c = 24,0 Mpa 4.13 m3 Rp 6,010,096.50 Rp 24,791,648.06
b. Bekisting 43.50 m2 Rp 390,307.50 Rp 16,978,376.25
Jumlah IV. Rp 41,770,024.31