JADWAL PELAKSANAAN PEKERJAAN

KEGIATAN : PEMBANGUNAN GEDUNG


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019 um(

WAKTU PELAKSANAAN PEKERJAAN 180 (SERATUS DELAPAN PULUH) HARI KALENDER


BOBOT
NO URAIAN PEKERJAAN BULAN Ke I BULAN Ke II BULAN Ke III BULAN Ke IV KET
%

1 2 3 4 5 6 7 Chart
8 Title
9 10 11 12 13 14 15 16
A PEKERJAAN STRUKTUR

I PEKERJAAN PERSIAPAN Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 100
II PEKERJAAN STRUKTUR BAWAH
A PEKERJAAN TANAH DAN PASIR Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
B PEKERJAAN BETON BERTULANG Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
III PEKERJAAN STRUKTUR ATAS
Pekerjaan Pemasangan 1m2 lantai keramik ukuran 25cm x 25cm Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
IV Err:509
1 PEKERJAAN PASANG ATAP BAJA RINGAN Err:509 Err:509 Err:509 Err:509 Err:509
2 PEKERJAAN PASANG DINDING BATA Err:509 Err:509 Err:509 Err:509 Err:509
3 Err:509 #REF! #REF! #REF! #REF! #REF!
4 PEKERJAAN PASANG KU p Err:509 Err:509 Err:509 Err:509 Err:509
5 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 50
B PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN Err:509 Err:509 Err:509 Err:509 Err:509
B PEKERJAAN PENUTUP LANTAI DAN DINDING Err:509 Err:509 Err:509 Err:509 Err:509
C PEKERJAAN PINTU Err:509 Err:509 Err:509
C PEKERJAAN MEKANIKAL ELEKTRIKAL
A PEKERJAAN SANITASI Err:509 Err:509 Err:509 Err:509 Err:509
B PEKERJAAN PLUMBING Err:509 Err:509 Err:509 Err:509 Err:509
C PEKERJAAN ELEKTRIKAL Err:509 Err:509 Err:509
D PENYAMBUNGAN INSTALASI AIR
A PENYAMBUNGAN INSTALASI AIR DARI GEDUNG ASRAMA KE TOWER GSG Err:509 Err:509 Err:509
0
JUMLAH Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
RENCANA - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
REALISASI 0.312 1.720 3.128 5.527 7.000 8.000 12.000 15.000 18.000 22.000 22.000 22.000 22.000 22.000 22.000 100.000
DEVIASI Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Bandar Lampung, 2 Maret 2019


CV. DAUN DIANDRA
WAKTU PELAKSANAAN PEKERJAAN 180 (SERATUS DELAPAN PULUH) HARI KALENDER
BOBOT
NO URAIAN PEKERJAAN BULAN Ke I BULAN Ke II BULAN Ke III BULAN Ke IV KET
%
Chart Title
ENDANG KUSNADI
Direktur
REKAPITULASI RAB

KEGIATAN : PEMBANGUNAN GEDUNG


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019

NO URAIAN PEKERJAAN

1 PEKERJAAN PERSIAPAN
2 PEKERJAAN STRUKTUR BAWAH
3 PEKERJAAN STRUKTUR ATAS

JUMLAH
PPN 10%
TOTAL
DIBULATKAN

Terbilang : Sembilan Puluh Tiga Juta Sembilan Belas Ribu Rupiah

Bandar Lampung, 2019

REKAP Page 3
REKAPITULASI RAB

NILAI PEKERJAAN

Rp 1,275,000.00
Rp 56,030,678.94
Rp 27,257,102.82

Rp 84,562,781.76
Rp 8,456,278.18
Rp 93,019,059.94
Rp 93,019,000.00

Bandar Lampung, 2019

REKAP Page 4
BILL OF QUANTITY (BQ)
KEGIATAN : PEMBANGUNAN GEDUNG
PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019

PEKERJAAN STRUKTUR
KODE
NO. URAIAN PEKERJAAN ANALISA VOLUME

I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bowplank A.2.2.1.4 100.00
2 Pelaporan dan Dokumentasi Ls 1.00
3 Pembentukan direksi keet A.2.2.1.5a -
4 Pek. Listrik dan Air Kerja Ls 1.00
5 Pengadaan Alat Scafolding Ls 0.00
TOTAL I
II PEKERJAAN STRUKTUR BAWAH
A PEKERJAAN TANAH DAN PASIR
1 Pembentukan muka tanah (grading) A.2.2.1.9 36.00
2 Pek. Galian tanah pondasi foot plat P1 A.2.3.1.1 50.00
3 Pek. Urugan Tanah Kembali sisi foot plat P1 A.2.3.1.9 15.00
4 Pek. Urugan Pasir Bawah Pondasi Foot Plat P1 t.5cm A.2.3.1.11 4.00
5 Pek. Urugan Tanah Peninggian Lantai A.2.3.1.10 10.80
5 Pek. Urugan Pasir Bawah Lantai A.2.3.1.11 1.08
6 Pek. Lantai Kerja Foot Plat P1 t.10cm + ANGKUR BAUT A.4.1.1.1 3.20
SUB TOTAL A
B PEKERJAAN BETON BERTULANG
1 Pek. Panel P1 150X12X10 cm
a. Panel A.4.1.1.8 0.30
b. Baut A.4.1.1.17 126.00
c. BCetakan 1.00
d Pek. Tulangan Besi 6 20.00
2 Pek. Panel P1 150X12X10 cm
a. Panel A.4.1.1.8 11.09
b. Baut A.4.1.1.17 3,456.00
c. BCetakan 1.00
d Pek. Tulangan Besi 6 60.00
SUB TOTAL B
TOTAL PEKERJAAN STRUKTUR BAWAH
III PEKERJAAN STRUKTUR ATAS
1 Pekerjaan Pemasangan 1m2 lantai keramik ukuran 25cm x 25cm
1 Pek. Sloof S1 20/40
a. Lantai Keramik 25 x 25 cm A.4.4.3.36. 36.00
b. Dilatasi Ls 1.00
TOTAL PEKERJAAN STRUKTUR LANTAI I
KODE
NO. URAIAN PEKERJAAN ANALISA VOLUME

2 PEKERJAAN PASANG ATAP BAJA RINGAN


Pek.pasang Atap Baja Ringan Ls 51.00
TOTAL PEKERJAAN PASANG ATAP BAJA RINGAN
KODE
NO. URAIAN PEKERJAAN ANALISA VOLUME

3 PEKERJAAN PASANG DINDING BATA


Pek Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu .A.4.4.1.9 46.08
TOTAL PEKERJAAN PASANG ATAP & DINDING
4 PEKERJAAN PASANG KUSEN
a Pek.pasang Pemasangan 1 m kusen pintu alluminium 4" hitam A.4.2.1.11b 4.00
b Pek Pemasangan 1 m2 pintu teakwood rangkap, rangka alumunium A.4.2.1.13b 4.00
c Pemasangan 1 m2 Jendela Kaca rangka alluminium A.4.2.1.13a 5.00
d Pek.Boven Ls 15.00
TOTAL PEKERJAAN PASANG KUSEN
TOTAL PEKERJAAN STRUKTUR ATAS
OF QUANTITY (BQ)

HARGA JUMLAH
SATUAN SATUAN HARGA
(Rp) (Rp)

M1 10,000.00 1,000,000.00
Ls 100,000.00 100,000.00
M2 865,365.00 -
Bln 175,000.00 175,000.00
Ls 7,350,000.00 -
1,275,000.00

M3 13,500.00 486,000.00
M3 64,500.00 3,225,000.00
M2 46,500.00 697,500.00
M2 217,800.00 871,200.00
M2 48,825.00 527,310.00
M3 217,800.00 235,224.00
M3 796,416.00 2,548,531.20
8,590,765.20

M3 945,461.34 283,638.40
Buah 1,500.00 189,000.00
M2 1,800,000.00 1,800,000.00
Ls 350,000.00 7,000,000.00

M3 945,461.34 10,483,275.34
Buah 1,500.00 5,184,000.00
M2 1,500,000.00 1,500,000.00
Ls 350,000.00 21,000,000.00
47,439,913.74
56,030,678.94

M3 216,350.00 7,788,600.00
Ls 2,500,000.00 2,500,000.00
10,288,600.00
HARGA JUMLAH
SATUAN SATUAN HARGA
(Rp) (Rp)

m2 145,000.00 7,395,000.00
7,395,000.00
HARGA JUMLAH
SATUAN SATUAN HARGA
(Rp) (Rp)

M2 90,235.00 4,158,028.80
4,158,028.80

Bh 102,199.10 408,796.40
Bh 830,093.78 3,320,375.12
Plong 322,260.50 1,611,302.50
bh 5,000.00 75,000.00
5,415,474.02
27,257,102.82
BILL OF QUANTITY (BQ)
KEGIATAN : PEMBANGUNAN GEDUNG
PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019

PEKERJAAN ARSITEKTUR
KODE
NO. URAIAN PEKERJAAN ANALISA VOLUME SATUAN

PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN
1 Pas.Dinding batu bata 1/2 1: 4 A.4.4.1.9 550.00 M2
2 Plesteran Dinding Batu Bata A.4.4.2.4 1,100.00 M2
TOTAL PEKERJAAN PASANGAN
B PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Keramik dinding 25x40 A.4.4.3.54b 66.00 M2
2 Keramik lantai 25 x25 A.4.4.3.36 14.00 M2
TOTAL PEKERJAAN PENUTUP LANTAI DAN DINDING
C PEKERJAAN PINTU
1 Pek.pas pintu doubel swing 3,6 lebar 1,8m pintu utama Ls 6.00 Unit
- Multiplek 4mm fin Wood Stain
- Engsel : Fino, Kend, Cisa
- Lockcase Sliding setara Fino , Kend, Cisa
2 Pas.pintu kamar mandi alumunium Ls 8.00 Unit
TOTAL PEKERJAAN PINTU
TOTAL PEKERJAAN ARSITEKTUR
PEKERJAAN MEKANIKAL ELEKTRIKAL
A PEKERJAAN SANITASI
1 Kloset jongkok porselen A.5.1.1.2 8.00 Bh
2 Kran air 1/2 " A.5.1.1.19 8.00 Bh
3 Pemasangan Floor Drain A.5.1.1.14 8.00 Bh
4 Tower air kap.1 m3 Ls 1.00 Bh
5 Pembuatan Septik Tank Ls 1.00 Bh
TOTAL PEKERJAAN SANITASI
B PEKERJAAN PLUMBING
1 Instalasi air bersih
Pipa PVC kelas AW dia. 1" A.5.1.1.27 25.00 M1
Pipa PVC kelas AW dia. 3/4" A.5.1.1.26 150.00 M1
Pipa PVC kelas AW dia. 1/2" A.5.1.1.25 9.60 M1
Assesories Pemipaan Ls 1.00 Ls
2 Instalasi air kotor
Pipa PVC kelas AW dia. 4" A.5.1.1.32 30.00 M1
KODE
NO. URAIAN PEKERJAAN ANALISA VOLUME SATUAN

Pipa PVC kelas AW dia. 3" A.5.1.1.31 50.00 M1


Assesories Pemipaan Ls 1.00 Bh
TOTAL PEKERJAAN PLUMBING
C PEKERJAAN ELEKTRIKAL
I PEKERJAAN LISTRIK DAN PENGKABELAN
1 Penyambungan Kabel titik api dari Gedung E ke Panel GSG NY Ls 240.00 M1
2 Pembuatan Panel Listrik Ls 1.00 Unit
3 Lampu TL SPL. A.8.4.6.6 16.00 Bh
4 Saklat double SPL. A.8.4.6.9 4.00 Bh
5 Instalasi titik penerangan, kabel NYY 3x2,5 mm dalam conduit SPL. A.8.4.6.1 16.00 Titik
TOTAL PEKERJAAN LISTRIK
PENYAMBUNGAN INSTALASI AIR DARI GEDUNG ASRAMA KE TOWER GSG
1 Penyambungan Instalasi Air dari Gedung Asrama ke GSG Ls 1.00 Ls
Penyambungan Pipa AW 1"
Pembuatan Panel Pompa
Pengadaan Pompa Pendorong
Pembuatan Water Toren
TOTAL PEKERJAAN INSTALASI AIR DARI GEDUNG ASRAMA KE TOWER GSG
OF QUANTITY (BQ)

HARGA JUMLAH
SATUAN HARGA
(Rp) (Rp)

90,235.00 49,629,250.00
52,914.00 58,205,400.00
107,834,650.00

238,065.00 15,712,290.00
216,350.00 3,028,900.00
18,741,190.00

3,250,000.00 19,500,000.00

1,250,000.00 10,000,000.00
29,500,000.00
156,075,840.00

526,750.00 4,214,000.00
74,517.50 596,140.00
306,620.00 2,452,960.00
4,850,000.00 4,850,000.00
5,000,000.00 5,000,000.00
17,113,100.00

23,024.50 575,612.50
19,149.50 2,872,425.00
16,824.50 161,515.20
150,000.00 150,000.00

115,904.50 3,477,135.00
HARGA JUMLAH
SATUAN HARGA
(Rp) (Rp)
75,217.00 3,760,850.00
150,000.00 150,000.00
11,147,537.70

85,000.00 20,400,000.00
5,000,000.00 5,000,000.00
165,436.00 2,646,976.00
38,936.00 155,744.00
183,736.00 2,939,776.00
31,142,496.00

22,500,000.00 22,500,000.00

22,500,000.00
ANALISA HARGA SATUAN PEKERJAAN
SESUAI DENGAN PERMEN PU NO.11 / PRT / M / 2013
TAHUN 2018

KEGIATAN : PEMBANGUNAN GEDUNG


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019

A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.1000
Tukang Kayu L.02 OH 0.1000
Kepala Tukang L.03 OH 0.0100
Mandor L.04 OH 0.0050
JUMLAH TENAGA KERJA
B BAHAN
Kayu kasau kelas III m3 0.1200
Paku 5 – 10 cm Kg 0.0200
Kayu papan kelas III m3 0.0070
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A. 2.2.1.5a. Pembuatan 1 M2 kantor Direksi keet


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 2.0000
Tukang Kayu L.02 OH 2.0000
Kepala Tukang L.03 OH 0.3000
Mandor L.04 OH 0.0500
JUMLAH TENAGA KERJA
B BAHAN
Dolken kayu gelam φ(8-10) cm Btg 1.2500
Kayu kasau kelas IV M3 0.1800
Paku 5 – 10 cm Kg 0.0800
Besi strip Kg 1.1000
Semen Portland Kg 10.5000
Pasir Beton M3 0.0300
Koral beton M3 0.1500
Seng Gelombang Lbr 0.2500
Jendela Nako Bh 0.2000
Kaca Bening 5mm M2 0.0800
Kunci tanam biasa Bh 0.1500
Plywood 9 mm Lbr 0.0600
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A. 2.2.1.9. Pembersihan 1 M2 lapangan dan perataan


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.1000
Mandor L.04 OH 0.0500
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 5% x D
F Harga Satuan Pekerjaan (D+E)

A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m


No Uraian Kode Koefisien Satuan
A TENAGA
Pekerja L.01 0.7500 OH
Mandor L.04 0.0250 OH
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.2.3.1.2. Penggalian 1 m3 tanah biasa sedalam 2 m


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.9000
Mandor L.04 OH 0.0450
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
No Uraian Kode Koefisien Satuan
A TENAGA
Pekerja L.01 0.5000 OH
Mandor L.04 0.0500 OH
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.2.3.1.10. Pemadatan tanah 1 m3 tanah ( per 20 cm)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.5000
Mandor L.04 OH 0.0500
JUMLAH TENAGA KERJA
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit 5% x D
F Harga Satuan Pekerjaan (D+E)

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.3000
Mandor L.04 OH 0.0100
JUMLAH TENAGA KERJA
B BAHAN
Pasir urug 1.2000
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)

A.2.3.1.16. Pengurugan 1 m3 Tanah timbunan pilihan


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.2500
Mandor L.04 OH 0.0250
JUMLAH TENAGA KERJA
B BAHAN
Tanah Urug pilihan m3 1.2000
NALISA HARGA SATUAN PEKERJAAN
UAI DENGAN PERMEN PU NO.11 / PRT / M / 2013
TAHUN 2018

Harga Satuan (Rp) Jumlah Harga (Rp)

82,500.00 8,250.00
93,000.00 9,300.00
97,000.00 970.00
105,000.00 525.00
JUMLAH TENAGA KERJA 19,045.00

2,300,000.00 276,000.00
14,000.00 280.00
2,600,000.00 18,200.00
JUMLAH HARGA BAHAN 294,480.00

JUMLAH HARGA ALAT


313,525.00

313,525.00

Harga Satuan (Rp) Jumlah Harga (Rp)

80,000.00 160,000.00
95,000.00 190,000.00
100,000.00 30,000.00
110,000.00 5,500.00
JUMLAH TENAGA KERJA 385,500.00

22,500.00 28,125.00
1,700,000.00 306,000.00
15,000.00 1,200.00
15,000.00 16,500.00
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
75,000.00 15,000.00
95,000.00 7,600.00
130,000.00 19,500.00
125,000.00 7,500.00
JUMLAH HARGA BAHAN 479,865.00

JUMLAH HARGA ALAT


865,365.00

865,365.00

Harga Satuan (Rp) Jumlah Harga (Rp)

80,000.00 8,000.00
110,000.00 5,500.00
JUMLAH TENAGA KERJA 13,500.00

JUMLAH HARGA BAHAN

JUMLAH HARGA ALAT


13,500.00

13,500.00

Harga Satuan (Rp) Jumlah Harga (Rp)

82,500.00 61,875.00
105,000.00 2,625.00
JUMLAH TENAGA KERJA 64,500.00

JUMLAH HARGA BAHAN

JUMLAH HARGA ALAT


64,500.00

64,500.00

Harga Satuan (Rp) Jumlah Harga (Rp)

82,500.00 74,250.00
105,000.00 4,725.00
JUMLAH TENAGA KERJA 78,975.00

JUMLAH HARGA BAHAN

JUMLAH HARGA ALAT


78,975.00
78,975.00
Harga Satuan (Rp) Jumlah Harga (Rp)

82,500.00 41,250.00
105,000.00 5,250.00
JUMLAH TENAGA KERJA 46,500.00

JUMLAH HARGA BAHAN

JUMLAH HARGA ALAT


46,500.00

46,500.00

Harga Satuan (Rp) Jumlah Harga (Rp)

82,500.00 41,250.00
105,000.00 5,250.00
JUMLAH TENAGA KERJA 46,500.00

JUMLAH HARGA BAHAN

JUMLAH HARGA ALAT


46,500.00
2,325.00
48,825.00

Harga Satuan (Rp) Jumlah Harga (Rp)

82,500.00 24,750.00
105,000.00 1,050.00
JUMLAH TENAGA KERJA 25,800.00

160,000.00 192,000.00
JUMLAH HARGA BAHAN

JUMLAH HARGA ALAT


217,800.00

217,800.00

Harga Satuan (Rp) Jumlah Harga (Rp)

82,500.00 20,625.00
105,000.00 2,625.00
JUMLAH TENAGA KERJA 23,250.00

35,000.00 42,000.00
HARGA SATUAN UPAH DAN BAHAN
KEGIATAN : PEMBANGUNAN GEDUNG
PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019

No Uraian Satuan Harga (Rp)


1 2 3 4

A HARGA UPAH PEKERJA :


1 Kepala Tukang Hari 97,000.00
2 Mandor Hari 105,000.00
3 Tukang Hari 93,000.00
4 Tukang Batu Hari 93,000.00
5 Tukang Besi Hari 93,000.00
6 Tukang Cat Hari 93,000.00
7 Tukang Kayu Hari 93,000.00
8 Tukang Pipa Hari 95,000.00
9 Tukang Las Konstruksi Hari 95,000.00
10 Pekerja Hari 82,500.00
11 Instalatur Listrik Hari 95,000.00
12 Asisten Instalatur Listrik Hari 82,500.00

B HARGA BAHAN BANGUNAN:


1 Air Liter 120.00
2 Amplas Lembar 14,000.00
3 Batu bata Buah 475.00
4 Batu Belah Hitam Utk Pondasi M3 225,000.00
5 Batu Belah Putih Utk Pondasi M3 175,000.00
6 Batu Split M3 285,000.00
7 Baut HTB M16 bh 1,500.00
8 Baut HTB M20 bh 2,000.00
9 Besi Beton (Polos/Ulir) Kg 10,000.00
10 Besi Profil Kg 11,500.00
11 Beton K250 (Truk vol 3-4 m3) m3 1,200,000.00
12 Bondek Metal L=1m, T=0,75mm m2 120,000.00
13 Bubungan Genteng Zincalume pasir M 63,000.00
14 Cat Alkali Liter 45,000.00
15 Cat Dasar Kg 17,000.00
16 Cat Penutup Kg 19,000.00
17 Cat Penutup Eksterior Kg 95,000.00

Page 23 of 128
No Uraian Satuan Harga (Rp)
1 2 3 4
18 Cat Kayu/Besi Kg 65,000.00
19 Cat Meni kayu/besi Kg 20,000.00
20 Cat Tembok Kg 45,000.00
21 Engsel Angin Casement Buah 50,000.00
22 Engsel Jendela Buah 28,000.00
23 Engsel Pintu Buah 22,000.00
24 Engsel Pintu Sliding lengkap unit 125,000.00
25 Fitting Lampu Buah 25,000.00
26 Fitting Lampu Down Light 5" Buah 75,000.00
27 Floor Drain Stainless bh 295,000.00
28 Genteng Metal Zincalume pasir M2 95,000.00
29 Gypsum board Lbr 80,000.00
30 GRC Lbr 89,000.00
31 Hollow galvanis 4/4 Btg 82,000.00
32 Hollow galvanis 2/4 Btg 42,000.00
33 HPL Motif Serat Kayu t=0,7mm Lembar 210,000.00
34 Ijuk kg 7,500.00
35 Isolasi bh 5,000.00
36 Kabel M' 8,000.00
37 Kabel Listrik NYA 1 x 1,5 mm M' 3,000.00
38 Kabel Listrik NYA 1 x 2,5 mm M' 5,000.00
39 Kabel Listrik NYM 2 x 1,5 mm M' 6,000.00
40 Kabel Listrik NYM 2 x 2,5 mm M' 8,500.00
41 Kabel Listrik NYM 3 x 2,5 mm M' 9,500.00

Page 24 of 128
No Uraian Satuan Harga (Rp)
1 2 3 4
42 Kawat Beton Kg 19,500.00
43 Kawat Anyam m2 20,500.00
44 Kawat Las Kg 25,000.00
45 Kawat Nyamuk Kg 22,500.00
46 Kayu Balok kelas II M3 3,250,000.00
47 Kayu Balok kelas III M3 2,500,000.00
48 Kayu Balok kelas IV M3 1,900,000.00
49 Kayu kasau kelas II M3 3,200,000.00
50 Kayu kasau kelas III M3 2,300,000.00
51 Kayu kasau kelas IV M3 1,800,000.00
52 Kayu papan kelas II M3 3,500,000.00
53 Kayu papan kelas III M3 2,600,000.00
54 Kayu papan kelas IV M3 2,200,000.00
55 Kayu perancah/begisting M3 1,900,000.00
56 Keramik artistik 5/20 Motif bh 7,500.00
57 Keramik 25/25 Warna bh 5,000.00
58 Keramik 20/25 Warna bh 4,750.00
59 Keramik 20/40 Warna bh 5,450.00
60 Keramik 30/30 bh 5,600.00
61 Keramik 30/30 Kasar bh 5,800.00
62 Keramik 40/40 Polos bh 6,000.00
63 Keramik 40/40 Warna bh 6,200.00
64 Keramik 50/50 Polos bh 20,000.00
65 Keramik 50/50 Warna bh 24,000.00
66 Keramik 60/60 Warna bh 47,000.00
67 Keramik dinding uk. 25 x 40 cm bh 7,250.00
68 Keramik Plin 10 x 30 cm Buah 1,900.00
69 Keramik Plin 10 x 40 cm Buah 1,600.00
70 Kloset Duduk Keramik (Natural) Buah 2,900,000.00
71 Kloset Jongkok Keramik Buah 265,000.00
72 Koral beton m3 285,000.00
73 Koral beton (kg) Kg 212.06
74 Kran air stainless Ø 1/2" Buah 32,000.00
75 Kunci pintu kamar mandi Buah 58,000.00
81 Kusen Almunium 4"(coklat/hitam) m' 83,000.00
82 Kuas cat Buah 25,000.00
83 Klem Buah 1,800.00
84 Lampu LED 13 Watt Buah 107,500.00
85 Lampu LED 5 Watt Buah 80,000.00
86 Lampu 30 x 30 cm led Outbow Buah 215,000.00
87 Lampu RM 300 TL 2 x 18 W Divider Buah 245,000.00
88 Lampu SL 18 Watt Buah 45,000.00
Page 25 of 128
No Uraian Satuan Harga (Rp)
1 2 3 4
89 Lampu Down Light +SL Buah 72,500.00
90 Lem Plastik / Kayu Kg 15,000.00

Page 26 of 128
No Uraian Satuan Harga (Rp)
1 2 3 4
91 Lem PVC Buah 8,250.00
92 Lis Gypsum M' 15,000.00
93 List kayu profil M' 8,750.00
94 List Plafond PVC btg 110,000.00
95 Listplank GRC 20 cm M' 45,000.00
96 Listplank Zincalume 24 cm M' 40,000.00
97 L Bow Buah 10,000.00
98 Las Dop Buah 10,000.00
99 Mangkok Buah 15,000.00
100 MCB 4 A bh 35,000.00
101 MCB 10 A bh 75,000.00
102 MESIN LAS LISTRIK Jam 24,500.00
103 Pacul Aduk bh 45,000.00
104 Paku 1 - 5 cm Kg 12,000.00
105 Paku 5 – 10 cm Kg 14,000.00
106 Paku GRC Kg 25,000.00
107 Paku Sekrup (50 Bh / Kg) Kg 16,000.00
108 Paku Triplek Kg 23,500.00
109 Paku Skrup Kg 16,000.00
110 Papan GRC Lbr 68,000.00
111 Pasir beton M3 185,000.00
112 Pasir beton (kg) Kg 150.00
113 Pasir Pasang M3 180,000.00
114 Pasir Urug M3 160,000.00
115 Paving Block T = 6 Cm Buah 2,150.00
116 Pengencer/thinner Kg 20,000.00
117 Penangkal Petir unit 3,100,000.00
118 Penjaga Jarak Begisting / Spacer buah 17,500.00
119 Pintu UPVC KM/WC Buah 1,210,000.00
120 Pipa PVC Ø 1/2" M' 4,750.00
121 Pipa PVC Ø 3/4" M' 6,250.00
122 Pipa PVC Ø 1" M' 8,750.00
123 Pipa PVC Ø 1,25" M' 11,625.00
124 Pipa PVC Ø 1,5" M' 14,375.00
125 Pipa PVC Ø 2" M' 18,750.00
126 Pipa PVC Ø 2 1/2" M' 24,700.00
127 Pipa PVC Ø 3" M' 35,000.00
128 Pipa PVC Ø 4" M' 61,250.00
129 Pipa Listrik 5/8" btg 15,000.00
130 Plamir kayu / besi Kg 50,000.00
131 Plamir Tembok Kg 52,000.00
132 Plat Perletakan bh 65,000.00
Page 27 of 128
No Uraian Satuan Harga (Rp)
1 2 3 4
133 Plat Sudut bh 25,000.00
134 Plat Steinliss 3 mm m2 100,000.00

Page 28 of 128
No Uraian Satuan Harga (Rp)
1 2 3 4
135 Plint ubin granit 10 x 60 cm (Ivory/Krem) Buah 15,000.00
136 Plywood 9 mm Lembar 120,000.00
137 Pompa Beton jam 97,500.00
138 Rel Pintu Dorong buah 185,000.00
139 Reservoir Tower Air Fiber 0,50 M3 unit 780,000.00
140 Reservoir Tower Air Fiber 1,00 M3 unit 1,400,000.00
141 Roster Beton 20/20 Buah 45,000.00
142 Skrup fixer buah 500.00
143 Saklar ganda Buah 35,000.00
144 Saklar Single kualitas baik Buah 32,500.00
145 Saklar Triple kualitas baik Buah 37,500.00
146 Sealant Tube 25,000.00
147 Seal tape Buah 3,500.00
149 Semen PC (50 Kg) Zak 55,000.00
150 Semen portland Kg 1,100.00
151 Semen Putih (25 Kg) Zak 85,000.00
152 Semen warna Kg 12,000.00
153 Seng gelombang Lbr 32,000.00
156 Spandek Metal Zincalume T=0,35mm M1 55,000.00
157 Stop kontak Buah 32,500.00
158 Stop Kran 1" Buah 175,000.00
159 Talang jurai dalam Lapis Zinc Alumunium M' 78,750.00
160 Tanah Urug Pilihan m3 35,000.00
161 Triplek 5mm Lembar 70,000.00
162 Ubin granit 60 x 60 cm (Ivory/Krem) bh 75,000.00
163 Washtafel keramik lengkap unit 1,900,000.00

Page 29 of 128
SATUAN UPAH DAN BAHAN

Keterangan
5

495,000.00
1,980,000.00

Page 30 of 128
Keterangan
5

155,000.00 /roll
260,000.00 /roll
325,000.00 /roll
432,500.00 /roll
568,250.00 /roll

Page 31 of 128
Keterangan
5

Rp 65,000.00 /m2
Rp 57,000.00 /m2
Rp 94,500.00 /m2
Rp 58,000.00 /m2
Rp 58,000.00 /m2
Rp 60,000.00 /m2
Rp 65,000.00 /m2
Rp 78,000.00 /m2
Rp 81,000.00 /m2
Rp 142,500.00 /m2

Page 32 of 128
Keterangan
5

Page 33 of 128
Keterangan
5

19,000.00
25,250.00
35,000.00
46,500.00
55,000.00
77,770.00
98,800.00
150,000.00
245,000.00

6,000.00

Page 34 of 128
Keterangan
5

Page 35 of 128
Keterangan
5

45,000.00

145,000.00 /rit

Page 36 of 128
NETWORK PLANNING
PEKERJAAN FISIK : PEMBANGUNAN GEDUNG LK FMIPA UNIVERSITAS LAMPUNG TAHAP 1
LOKASI : FMIPA UNIVERSITAS LAMPUNG
TAHUN ANGGARAN : 2018

2 2 8
2
8

0 12
1 4
2 16

6 6 4
3
12

10

1 PEKERJAAN PERSIAPAN DAN SITE DEVELOPMENT : 2 minggu


2 PEKERJAAN STRUKTUR : 6 minggu
3 PEKERJAAN ARSITEKTUR : 6 minggu
4 PEKERJAAN MEKANIKAL ELEKTRIKAL DAN PLUMBING : 4 minggu

Bandar Lampung, Mei 2018


cv…………
JADWAL PENGADAAN MATERIAL
KEGIATAN : PEMBANGUNAN GEDUNG
PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019

JANGKA WAKTU PELAKSANAAN PEKERJAAN


NO JENIS BAHAN/ MATERIAL VOLUME SAT BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5 BULAN 6 KETERANGAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

1 Air 1,800.00 Liter


2 Amplas 150.00 Lembar
3 Angkur dia 19 panjang 50 80.00 Buah
5 Batu Split 55.00 M3
6 Besi Beton (Polos/Ulir) 9,500.00 Kg
4 Batu bata 42,600.00 Buah
7 CNP 125.50.20.2,3mm 4,336.00 Kg
8 Dinding spandek 0,45mm 740.00 M2
9 Gelagar iwf 150.75.5.7mm 1,176.00 Kg
10 Gording CNP 150.50.20.2,3mm 4,797.80 Kg
13 Kayu kasau kelas III 4.00 M3
14 Kayu kasau kelas IV 6.00 M3
15 Kayu papan kelas IV 3.00 M3
16 Kayu perancah/begisting 7.00 M3
11 Kawat Beton 250.00 Kg
12 Kolom iwf 250.125.6.8 mm 3,681.00 Kg
17 Keramik 25/25 18.00 dus
18 Keramik dinding uk. 25 x 40 cm 44.00 dus
19 Kloset Jongkok 4.00 Buah
20 Mor baut spand HTB dia =3/4mm 288.00 Bh
21 Mor baut HTB over stek dia 5/8mm 96.00 Bh
24 Pasir beton 45.00 M3
25 Pasir Pasang 25.00 M3
26 Pasir Urug 15.00 M3
22 Paku 5 – 10 cm 150.00 Kg
23 Paku Skrup 250.00 Kg
27 Pintu UPVC KM/WC 4.00 Buah
28 Pipa PVC Ø 3" 24.00 Btg
29 Pipa Listrik 5/8" 40.00 btg
30 Saklar ganda 4.00 Buah
31 Semen PC (50 Kg) 750.00 Zak
32 Semen warna 50.00 Kg
33 Spand iwf 250.125.6.8mm 4,440.00 Kg
34 Spandek 0,35mm 968.00 M2
35 Talang zincalume 88.00 M1

Bandar Lampung, 2019


0

ENDANG KUSNADI
Direktur
DAFTAR MATA PEKERJAAN UMUM
KEGIATAN : PEMBANGUNAN GEDUNG
PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019

HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp)
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bowplank M1 124.00 313,525.00
2 Pelaporan dan Dokumentasi Ls 1.00 750,000.00
3 Pembentukan direksi keet M2 18.00 865,365.00
4 Pek. Listrik dan Air Kerja Bln 6.00 175,000.00
5 Pengadaan Alat Scafolding Ls 1.00 7,350,000.00
TOTAL I
DAFTAR MATA PEKERJAAN UTAMA
KEGIATAN : PEMBANGUNAN GEDUNG
PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019

PEKERJAAN STRUKTUR
HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp)
I PEKERJAAN STRUKTUR BAWAH
A PEKERJAAN TANAH DAN PASIR
1 Pembentukan muka tanah (grading) M3 1,210.80 13,500.00
2 Pek. Galian tanah pondasi foot plat P1 M3 120.00 64,500.00
3 Pek. Urugan Tanah Kembali sisi foot plat P1 M2 40.00 46,500.00
4 Pek. Urugan Pasir Bawah Pondasi Foot Plat P1 t.5cm M2 4.00 217,800.00
5 Pek. Urugan Tanah Peninggian Lantai M2 517.50 48,825.00
5 Pek. Urugan Pasir Bawah Lantai M2 51.75 217,800.00
6 Pek. Lantai Kerja Foot Plat P1 t.10cm M3 8.00 796,416.00
SUB TOTAL A
B PEKERJAAN BETON BERTULANG
1 Pek. Foot Plat P1 150X150X30 cm
a. Beton K 250 M3 13.50 945,461.34
b. Besi Penulangan Kg 2,074.51 12,130.90
c. Begisting M2 36.00 165,049.50
2 Pek. Pedestal Kolom K1 40x40
a. Beton K 250 M3 4.80 945,461.34
b. Besi Penulangan Kg 551.87 12,130.90
c. Begisting M2 48.00 165,049.50
SUB TOTAL B
TOTAL PEKERJAAN STRUKTUR BAWAH
II PEKERJAAN STRUKTUR LANTAI I
A PEKERJAAN BETON BERTULANG
1 Pek. Sloof S1 20/40
a. Beton K 250 M3 13.17 945,461.34
b. Besi Penulangan Kg 2,082.50 12,130.90
c. Begisting M2 164.58 194,049.50
2 Pek. Kolom K1 40x40
a. Beton K 250 M3 9.60 945,461.34
b. Besi Penulangan Kg 1,093.53 12,130.90
c. Begisting M2 96.00 363,126.00
3 Pek. Plat Lantai t.12 cm Elv. ± 0,00
a. Beton K 250 M3 116.16 945,461.34
b. Besi Penulangan Kg 602.62 12,130.90
c. Dilatasi Ls 1.00 2,500,000.00
TOTAL PEKERJAAN STRUKTUR LANTAI I
III PEKERJAAN STRUKTUR BAJA
1 PEKERJAAN PASANG KOLOM BAJA
a Pek.pasang angkur dia 19 panjang 50 Bh 120.00 50,000.00
b Pek kolom base plate uk.25 x 30 cm T =13mm Kg 176.39 19,156.00
c Pek. Pasang kolom iwf 250.125.6.8 mm Kg 3,552.00 19,156.00
d Pek.pasang stifner plate base plate T =12mm Kg 50.16 19,156.00
e Pek.pasang plate sambung kolom T=8mm Kg 22.44 19,156.00
f Pek.pasang plate tutup kolom atas T = 8mm Kg 34.78 19,156.00
TOTAL PEKERJAAN PASANG KOLOM BAJA
2 PEKERJAAN PASANG KUDA-KUDA BAJA
a Pek.pasang spand iwf 250.125.6.8mm Kg 5,209.60 19,156.00
b Pek.pasang plat penyambung span T=8mm Kg 205.00 19,156.00
c Pek.pasang stifner plate torsi spand T =8mm Kg 187.00 19,156.00
d Pek.pasang spand stout iwf 250.125.6.8mm Kg 444.00 19,156.00
e Pek.pasang plate spand atas T =12mm Kg 100.00 19,156.00
f Pek.plate spand bawah T = 12mm Kg 100.00 19,156.00
g Pek.pasang plate penyambung spand T=8mm Kg 205.00 19,156.00
h Pek.pasang mor baut spand HTB dia =3/4mm Bh 288.00 10,000.00
i Pek.pasang overstek iwf 150.75.5.7mm Kg 224.00 19,156.00
j Pek.pasang plate overstek T=10mm Kg 41.99 19,156.00
k Pek.pasang stifner plat overstek T=8mm Kg 28.05 19,156.00
l Pek.pasang mor baut HTB over stek dia 5/8mm Bh 96.00 7,500.00
TOTAL PEKERJAAN PASANG KUDA-KUDA BAJA
3 PEKERJAAN PASANG RANGKA DAN ATAP PENUTUP
a Pek.pasang gording CNP 150.50.20.2,3mm Kg 5,244.80 19,156.00
b Pek.pasang dudukan gording uk.150.120 T 6mm Kg 144.20 19,156.00
c Pek.pasang strekstang gording Dia 12mm Kg 331.70 19,156.00
d Pek.pasang mor baut strekstang dia 12mm Bh 304.00 7,500.00
e Pek.pasang mor baut gording dia 1/2'' Bh 560.00 5,000.00
f Pek.pasang ikatan angin dia 12mm Kg 171.20 19,156.00
g Pek.pasang spandscrew ikatan angin m20 Bh 16.00 75,000.00
h Pek.pasang atap spandek 0,35mm M2 968.00 77,650.00
i Pek.pasang roofing (paku seng) Bh 1,800.00 2,500.00
j Pek.pasang bubungan atap M1 44.00 65,000.00
TOTAL PEKERJAAN PASANG RANGKA DAN ATAP PENU
4 PEKERJAAN PASANG GELAGAR
a Pek.pasang gelagar iwf 150.75.5.7mm Kg 1,232.00 19,156.00
b Pek.stifner gelagar plate gelagar T = 8mm Kg 52.36 19,156.00
c Pek.pasang dudukan gelagar L 80.80.8mm Kg 57.96 19,156.00
d Pek.pasang mor baut dia 1/2'' Bh 84.00 5,000.00
TOTAL PEKERJAAN PASANG GELAGAR
5 PEKERJAAN PAS.RANGKA DAN CLADING
a Pek.pasang rangka CNP 125.50.20.2,3mm Kg 3,864.96 19,156.00
b Pek.pasang dudukan rangka T = 6mm Kg 84.00 19,156.00
c Pek.pasang strekstang gording Dia 12mm Kg 224.70 19,156.00
d Pek.pasang mor baut strekstang dia 12mm Bh 100.00 7,500.00
e Pek.pasang mor baut gording dia 12mm Bh 100.00 7,500.00
f Pek.pasang dinding spandek 0,45mm M2 784.00 85,000.00
g Pek.pasang roofing screw spandek Bh 750.00 5,000.00
TOTAL PEKERJAAN PAS.RANGKA DAN CLADING
TOTAL PEKERJAAN STRUKTUR BAJA
TOTAL PEKERJAAN STRUKTUR
PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN
1 Pas.Dinding batu bata 1/2 1: 4 M2 550.00 90,235.00
2 Plesteran Dinding Batu Bata M2 1,100.00 52,914.00
TOTAL PEKERJAAN PASANGAN
B PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Keramik dinding 25x40 M2 66.00 238,065.00
2 Keramik lantai 25 x25 M2 14.00 216,350.00
TOTAL PEKERJAAN PENUTUP LANTAI DAN DINDING
C PEKERJAAN PINTU
1 Pek.pas pintu doubel swing 3,6 lebar 1,8m pintu utama Unit 6.00 3,250,000.00
- Multiplek 4mm fin Wood Stain
- Engsel : Fino, Kend, Cisa
- Lockcase Sliding setara Fino , Kend, Cisa
2 Pas.pintu kamar mandi alumunium Unit 8.00 1,250,000.00
TOTAL PEKERJAAN PINTU
TOTAL PEKERJAAN ARSITEKTUR

PEKERJAAN MEKANIKAL ELEKTRIKAL


A PEKERJAAN SANITASI
1 Kloset jongkok porselen Bh 8.00 526,750.00
2 Kran air 1/2 " Bh 8.00 74,517.50
3 Pemasangan Floor Drain Bh 8.00 306,620.00
4 Tower air kap.1 m3 Bh 1.00 4,850,000.00
5 Pembuatan Septik Tank Bh 1.00 5,000,000.00
TOTAL PEKERJAAN SANITASI
B PEKERJAAN PLUMBING
1 Instalasi air bersih
Pipa PVC kelas AW dia. 1" M1 25.00 23,024.50
Pipa PVC kelas AW dia. 3/4" M1 150.00 19,149.50
Pipa PVC kelas AW dia. 1/2" M1 9.60 16,824.50
Assesories Pemipaan Ls 1.00 150,000.00
2 Instalasi air kotor
Pipa PVC kelas AW dia. 4" M1 30.00 115,904.50
Pipa PVC kelas AW dia. 3" M1 50.00 75,217.00
Assesories Pemipaan Bh 1.00 150,000.00
TOTAL PEKERJAAN PLUMBING
C PEKERJAAN ELEKTRIKAL
I PEKERJAAN LISTRIK DAN PENGKABELAN
1 Penyambungan Kabel titik api dari Gedung E ke Pane M1 240.00 85,000.00
2 Pembuatan Panel Listrik Unit 1.00 5,000,000.00
3 Lampu TL Bh 16.00 165,436.00
4 Saklat double Bh 4.00 38,936.00
5 Instalasi titik penerangan, kabel NYY 3x2,5 mm dalam c Titik 16.00 183,736.00
TOTAL PEKERJAAN LISTRIK
DAFTAR MATA PEKERJAAN LAIN-LAIN
KEGIATAN : PEMBANGUNAN GEDUNG
PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019

PEKERJAAN LAIN-LAIN
PENYAMBUNGAN INSTALASI AIR DARI GEDUNG ASRAMA KE TOWER GSG
1 Penyambungan Instalasi Air dari Gedung Asrama ke GS Ls 1.00 22,500,000.00
Penyambungan Pipa AW 1"
Pembuatan Panel Pompa
Pengadaan Pompa Pendorong
Pembuatan Water Toren
TOTAL PEKERJAAN INSTALASI AIR DARI GEDUNG AS
JUMLAH
HARGA
(Rp)

38,877,100.00
750,000.00
15,576,570.00
1,050,000.00
7,350,000.00
63,603,670.00
JUMLAH
HARGA
(Rp)

16,345,800.00
7,740,000.00
1,860,000.00
871,200.00
25,266,937.50
11,271,150.00
6,371,328.00
69,726,415.50

12,763,728.09
25,165,673.36
5,941,782.00

4,538,214.43
6,694,679.78
7,922,376.00
63,026,453.66
132,752,869.16

12,451,725.85
25,262,599.25
31,936,666.71

9,076,428.86
13,265,503.08
34,860,096.00

109,824,789.25
7,310,322.96
2,500,000.00
246,488,131.96

6,000,000.00
3,378,926.84
68,042,112.00
960,864.96
429,860.64
666,245.68
79,478,010.12

99,795,097.60
3,926,980.00
3,582,172.00
8,505,264.00
1,915,600.00
1,915,600.00
3,926,980.00
2,880,000.00
4,290,944.00
804,360.44
537,325.80
720,000.00
132,800,323.84

100,469,388.80
2,762,295.20
6,354,045.20
2,280,000.00
2,800,000.00
3,279,507.20
1,200,000.00
75,165,200.00
4,500,000.00
2,860,000.00
201,670,436.40

23,600,192.00
1,003,008.16
1,110,281.76
420,000.00
26,133,481.92

74,037,173.76
1,609,104.00
4,304,353.20
750,000.00
750,000.00
66,640,000.00
3,750,000.00
151,840,630.96
591,922,883.24
1,034,767,554.37
49,629,250.00
58,205,400.00
107,834,650.00

15,712,290.00
3,028,900.00
18,741,190.00

19,500,000.00

10,000,000.00
29,500,000.00
156,075,840.00

4,214,000.00
596,140.00
2,452,960.00
4,850,000.00
5,000,000.00
17,113,100.00

575,612.50
2,872,425.00
161,515.20
150,000.00

3,477,135.00
3,760,850.00
150,000.00
11,147,537.70

20,400,000.00
5,000,000.00
2,646,976.00
155,744.00
2,939,776.00
31,142,496.00
22,500,000.00

22,500,000.00
LAPORAN MINGGUAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN GEDUNG MINGGU KE : 1 (Satu)
PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA PERIODE : 10 April - 16 April 2019
NO KONTRAK : 0368/IT9.PPK/KS/SP/2019 BOBOT KEMAJUAN 55.24 %
TGL. KONTRAK : 10 April 2019
NAMA PELAKSANA : CV. DAUN DIANDRA
NILAI KONTRAK : Rp. 1.400.020.000,00
LOKASI : KAMPUS ITERA - LAMPUNG SELATAN
TAHUN ANGGARAN : 2019

PEKERJAAN STRUKTUR
REALISASI PEKERJAAN
KONTRAK
NO. URAIAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU IN
VOLUME SATUAN BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bowplank 124.00 M1 45.974 124.00 45.974 124.00
2 Pelaporan dan Dokumentasi 1.00 Ls 0.887 0.06 0.055 0.06
3 Pembentukan direksi keet 18.00 M2 18.420 9.00 9.210 9.00
4 Pek. Listrik dan Air Kerja 6.00 Bln 1.242
5 Pengadaan Alat Scafolding 1.00 Ls 8.692
TOTAL I 75.215 55.240
II PEKERJAAN STRUKTUR BAWAH
A PEKERJAAN TANAH DAN PASIR
1 Pembentukan muka tanah (grading) 1,210.80 M3 19.330
2 Pek. Galian tanah pondasi foot plat P1 120.00 M3 9.153
3 Pek. Urugan Tanah Kembali sisi foot plat P1 40.00 M2 2.200
4 Pek. Urugan Pasir Bawah Pondasi Foot Plat P1 t.5cm 4.00 M2 1.030
5 Pek. Urugan Tanah Peninggian Lantai 517.50 M2 29.880
5 Pek. Urugan Pasir Bawah Lantai 51.75 M2 13.329
6 Pek. Lantai Kerja Foot Plat P1 t.10cm 8.00 M3 7.534
SUB TOTAL A 82.455
B PEKERJAAN BETON BERTULANG
1 Pek. Foot Plat P1 150X150X30 cm
a. Beton K 250 13.50 M3 15.094
b. Besi Penulangan 2,074.51 Kg 29.760
c. Begisting 36.00 M2 7.026
2 Pek. Pedestal Kolom K1 40x40
a. Beton K 250 4.80 M3 5.367
b. Besi Penulangan 551.87 Kg 7.917
c. Begisting 48.00 M2 9.369
SUB TOTAL B 74.532
TOTAL PEKERJAAN STRUKTUR BAWAH
III PEKERJAAN STRUKTUR LANTAI I
A PEKERJAAN BETON BERTULANG
1 Pek. Sloof S1 20/40
a. Beton K 250 13.17 M3 14.725
b. Besi Penulangan 2,082.50 Kg 29.874
c. Begisting 164.58 M2 37.767
2 Pek. Kolom K1 40x40
a. Beton K 250 9.60 M3 10.733
b. Besi Penulangan 1,093.53 Kg 15.687
c. Begisting 96.00 M2 41.224
3 Pek. Plat Lantai t.12 cm Elv. ± 0,00
a. Beton K 250 116.16 M3 129.874
b. Besi Penulangan 602.62 Kg 8.645
c. Dilatasi 1.00 Ls 2.956
TOTAL PEKERJAAN STRUKTUR LANTAI I 291.485
IV PEKERJAAN STRUKTUR BAJA
1 PEKERJAAN PASANG KOLOM BAJA
a Pek.pasang angkur dia 19 panjang 50 120.00 Bh 7.095
b Pek kolom base plate uk.25 x 30 cm T =13mm 176.39 Kg 3.996
c Pek. Pasang kolom iwf 250.125.6.8 mm 3,552.00 Kg 80.463
d Pek.pasang stifner plate base plate T =12mm 50.16 Kg 1.136
e Pek.pasang plate sambung kolom T=8mm 22.44 Kg 0.508
f Pek.pasang plate tutup kolom atas T = 8mm 34.78 Kg 0.788
TOTAL PEKERJAAN PASANG KOLOM BAJA 93.987
2 PEKERJAAN PASANG KUDA-KUDA BAJA
a Pek.pasang spand iwf 250.125.6.8mm 5,209.60 Kg 118.013
b Pek.pasang plat penyambung span T=8mm 205.00 Kg 4.644
c Pek.pasang stifner plate torsi spand T =8mm 187.00 Kg 4.236
d Pek.pasang spand stout iwf 250.125.6.8mm 444.00 Kg 10.058
e Pek.pasang plate spand atas T =12mm 100.00 Kg 2.265
f Pek.plate spand bawah T = 12mm 100.00 Kg 2.265
g Pek.pasang plate penyambung spand T=8mm 205.00 Kg 4.644
h Pek.pasang mor baut spand HTB dia =3/4mm 288.00 Bh 3.406
i Pek.pasang overstek iwf 150.75.5.7mm 224.00 Kg 5.074
j Pek.pasang plate overstek T=10mm 41.99 Kg 0.951
k Pek.pasang stifner plat overstek T=8mm 28.05 Kg 0.635
l Pek.pasang mor baut HTB over stek dia 5/8mm 96.00 Bh 0.851
TOTAL PEKERJAAN PASANG KUDA-KUDA BAJA 157.043
3 PEKERJAAN PASANG RANGKA DAN ATAP PENUTUP
a Pek.pasang gording CNP 150.50.20.2,3mm 5,244.80 Kg 118.810
b Pek.pasang dudukan gording uk.150.120 T 6mm 144.20 Kg 3.267
c Pek.pasang strekstang gording Dia 12mm 331.70 Kg 7.514
d Pek.pasang mor baut strekstang dia 12mm 304.00 Bh 2.696
e Pek.pasang mor baut gording dia 1/2'' 560.00 Bh 3.311
f Pek.pasang ikatan angin dia 12mm 171.20 Kg 3.878
g Pek.pasang spandscrew ikatan angin m20 16.00 Bh 1.419
h Pek.pasang atap spandek 0,35mm 968.00 M2 88.887
i Pek.pasang roofing (paku seng) 1,800.00 Bh 5.321
j Pek.pasang bubungan atap 44.00 M1 3.382
TOTAL PEKERJAAN PASANG RANGKA DAN ATAP PENUTUP 238.486
4 PEKERJAAN PASANG GELAGAR
a Pek.pasang gelagar iwf 150.75.5.7mm 1,232.00 Kg 27.908
b Pek.stifner gelagar plate gelagar T = 8mm 52.36 Kg 1.186
c Pek.pasang dudukan gelagar L 80.80.8mm 57.96 Kg 1.313
d Pek.pasang mor baut dia 1/2'' 84.00 Bh 0.497
TOTAL PEKERJAAN PASANG GELAGAR 30.904
5 PEKERJAAN PAS.RANGKA DAN CLADING
a Pek.pasang rangka CNP 125.50.20.2,3mm 3,864.96 Kg 87.553
b Pek.pasang dudukan rangka T = 6mm 84.00 Kg 1.903
c Pek.pasang strekstang gording Dia 12mm 224.70 Kg 5.090
d Pek.pasang mor baut strekstang dia 12mm 100.00 Bh 0.887
e Pek.pasang mor baut gording dia 12mm 100.00 Bh 0.887
f Pek.pasang dinding spandek 0,45mm 784.00 M2 78.805
g Pek.pasang roofing screw spandek 750.00 Bh 4.435
TOTAL PEKERJAAN PAS.RANGKA DAN CLADING 179.560
TOTAL PEKERJAAN STRUKTUR BAJA
TOTAL PEKERJAAN STRUKTUR
PEKERJAAN ARSITEKTUR
REALISASI PEKERJAAN
KONTRAK
NO. URAIAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU IN
VOLUME SATUAN BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME
PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN
1 Pas.Dinding batu bata 1/2 1: 4 550.00 M2 58.689
2 Plesteran Dinding Batu Bata 1,100.00 M2 68.831
TOTAL PEKERJAAN PASANGAN 127.520
B PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Keramik dinding 25x40 66.00 M2 18.581
2 Keramik lantai 25 x25 14.00 M2 3.582
TOTAL PEKERJAAN PENUTUP LANTAI DAN DINDING 22.162
C PEKERJAAN PINTU
1 Pek.pas pintu doubel swing 3,6 lebar 1,8m pintu utama 6.00 Unit 23.060
- Multiplek 4mm fin Wood Stain
- Engsel : Fino, Kend, Cisa
- Lockcase Sliding setara Fino , Kend, Cisa
2 Pas.pintu kamar mandi alumunium 8.00 Unit 11.826
TOTAL PEKERJAAN PINTU 34.885
TOTAL PEKERJAAN ARSITEKTUR
PEKERJAAN MEKANIKAL ELEKTRIKAL
A PEKERJAAN SANITASI
1 Kloset jongkok porselen 8.00 Bh 4.983
2 Kran air 1/2 " 8.00 Bh 0.705
3 Pemasangan Floor Drain 8.00 Bh 2.901
4 Tower air kap.1 m3 1.00 Bh 5.735
5 Pembuatan Septik Tank 1.00 Bh 5.913
TOTAL PEKERJAAN SANITASI 20.237
B PEKERJAAN PLUMBING
1 Instalasi air bersih
Pipa PVC kelas AW dia. 1" 25.00 M1 0.681
Pipa PVC kelas AW dia. 3/4" 150.00 M1 3.397
Pipa PVC kelas AW dia. 1/2" 9.60 M1 0.191
Assesories Pemipaan 1.00 Ls 0.177
2 Instalasi air kotor
Pipa PVC kelas AW dia. 4" 30.00 M1 4.112
Pipa PVC kelas AW dia. 3" 50.00 M1 4.447
Assesories Pemipaan 1.00 Bh 0.177
TOTAL PEKERJAAN PLUMBING 13.183
C PEKERJAAN ELEKTRIKAL
I PEKERJAAN LISTRIK DAN PENGKABELAN
1 Penyambungan Kabel titik api dari Gedung E ke Panel G 240.00 M1 24.124
2 Pembuatan Panel Listrik 1.00 Unit 5.913
3 Lampu TL 16.00 Bh 3.130
4 Saklat double 4.00 Bh 0.184
5 Instalasi titik penerangan, kabel NYY 3x2,5 mm dalam con 16.00 Titik 3.476
TOTAL PEKERJAAN LISTRIK 36.828
PENYAMBUNGAN INSTALASI AIR DARI GEDUNG ASRAMA KE TOWER GSG
1 Penyambungan Instalasi Air dari Gedung Asrama ke GSG 1.00 Ls 26.607
Penyambungan Pipa AW 1"
Pembuatan Panel Pompa
Pengadaan Pompa Pendorong
Pembuatan Water Toren
TOTAL PEKERJAAN INSTALASI AIR DARI GEDUNG ASRAMA KE TOWER 26.607

TOTAL BOBOT KEMAJUAN PEKERJAAN 1,505.09 55.240

Dibuat oleh:
Kontraktor Pelaksana
CV. DAUN DIANDRA

ENDANG KUSNADI
Direktur
pril 2019

/D MINGGU INI %
BOBOT

45.974 100
0.055 6.25
9.210 50

55.240
/D MINGGU INI %
BOBOT
55.240

at oleh:
or Pelaksana
N DIANDRA

G KUSNADI
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
A PEKERJAAN PERSIAPAN

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI

1 Pengukuran dan Pemasangan Bowplank Ls 124.00 124.00


2 Pelaporan dan Dokumentasi Ls 1.00 0.25
3 Pembentukan direksi keet Ls 18.00 18.00
4 Pek. Listrik dan Air Kerja Ls 6.00 2.00
5 Pengadaan Alat Scafolding Ls 1.00 0.00

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
II PEKERJAAN STRUKTUR BAWAH

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
A PEKERJAAN TANAH DAN PASIR
1 Pembentukan muka tanah (grading) M3 1210.80 242.16
2 Pek. Galian tanah pondasi foot plat P1 M3 120.00 120.00
3 Pek. Urugan Tanah Kembali sisi foot plat P1 M2 40.00 0.00
4 Pek. Urugan Pasir Bawah Pondasi Foot Plat P1 t.5cm M2 4.00 0.00
5 Pek. Urugan Tanah Peninggian Lantai M2 517.50 0.00
6 Pek. Urugan Pasir Bawah Lantai M2 51.75 0.00
7 Pek. Lantai Kerja Foot Plat P1 t.10cm M3 8.00 4.00

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
II PEKERJAAN STRUKTUR BAWAH

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
B PEKERJAAN BETON BERTULANG
1 Pek. Foot Plat P1 150X150X30 cm
a. Beton K 250 M3 13.50 15.094
b. Besi Penulangan Kg 2074.51 29.760
c. Begisting M2 36.00 7.026
2 Pek. Pedestal Kolom K1 40x40
a. Beton K 250 M3 4.80 5.367
b. Besi Penulangan Kg 551.87 7.917
c. Begisting M2 48.00 9.369

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH
PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
III PEKERJAAN STRUKTUR ATAS

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
A PEKERJAAN BETON BERTULANG
1 Pek. Sloof S1 20/40
a. Beton K 250 M3 13.17 0.000
b. Besi Penulangan Kg 2082.50 0.000
c. Begisting M2 164.58 0.000
2 Pek. Kolom K1 40x40
a. Beton K 250 M3 9.60 0.000
b. Besi Penulangan Kg 1093.53 0.000
c. Begisting M2 96.00 0.000
3 Pek. Plat Lantai t.12 cm Elv. ± 0,00
a. Beton K 250 M3 116.16 0.000
b. Besi Penulangan Kg 602.62 0.000
c. Dilatasi Ls 1.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
IV Err:509

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
1 PEKERJAAN PASANG ATAP BAJA RINGAN
a Pek.pasang angkur dia 19 panjang 50 Bh 120.00 0.000
b Pek kolom base plate uk.25 x 30 cm T =13mm Kg 176.39 0.000
c Pek. Pasang kolom iwf 250.125.6.8 mm Kg 3552.00 0.000
d Pek.pasang stifner plate base plate T =12mm Kg 50.16 0.000
e Pek.pasang plate sambung kolom T=8mm Kg 22.44 0.000
f Pek.pasang plate tutup kolom atas T = 8mm Kg 34.78 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
IV Err:509

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
2 PEKERJAAN PASANG DINDING BATA
a Pek.pasang spand iwf 250.125.6.8mm Kg 5209.60 0.000
b Pek.pasang plat penyambung span T=8mm Kg 205.00 0.000
c Pek.pasang stifner plate torsi spand T =8mm Kg 187.00 0.000
d Pek.pasang spand stout iwf 250.125.6.8mm Kg 444.00 0.000
e Pek.pasang plate spand atas T =12mm Kg 100.00 0.000
f Pek.plate spand bawah T = 12mm Kg 100.00 0.000
g Pek.pasang plate penyambung spand T=8mm Kg 205.00 0.000
h Pek.pasang mor baut spand HTB dia =3/4mm Bh 288.00 0.000
i Pek.pasang overstek iwf 150.75.5.7mm Kg 224.00 0.000
j Pek.pasang plate overstek T=10mm Kg 41.99 0.000
k Pek.pasang stifner plat overstek T=8mm Kg 28.05 0.000
l Pek.pasang mor baut HTB over stek dia 5/8mm Bh 96.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
IV Err:509

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
3 Err:509
a Pek.pasang gording CNP 150.50.20.2,3mm Kg 5244.80 0.000
b Pek.pasang dudukan gording uk.150.120 T 6mm Kg 144.20 0.000
c Pek.pasang strekstang gording Dia 12mm Kg 331.70 0.000
d Pek.pasang mor baut strekstang dia 12mm Bh 304.00 0.000
e Pek.pasang mor baut gording dia 1/2'' Bh 560.00 0.000
f Pek.pasang ikatan angin dia 12mm Kg 171.20 0.000
g Pek.pasang spandscrew ikatan angin m20 Bh 16.00 0.000
h Pek.pasang atap spandek 0,35mm M2 968.00 0.000
i Pek.pasang roofing (paku seng) Bh 1800.00 0.000
j Pek.pasang bubungan atap M1 44.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
IV Err:509

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
4 PEKERJAAN PASANG KUSEN
a Pek.pasang gelagar iwf 150.75.5.7mm Kg 1232.00 0.000
b Pek.stifner gelagar plate gelagar T = 8mm Kg 52.36 0.000
c Pek.pasang dudukan gelagar L 80.80.8mm Kg 57.96 0.000
d Pek.pasang mor baut dia 1/2'' Bh 84.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
IV Err:509

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
5 Err:509
a Pek.pasang rangka CNP 125.50.20.2,3mm Kg 3864.96 0.000
b Pek.pasang dudukan rangka T = 6mm Kg 84.00 0.000
c Pek.pasang strekstang gording Dia 12mm Kg 224.70 0.000
d Pek.pasang mor baut strekstang dia 12mm Bh 100.00 0.000
e Pek.pasang mor baut gording dia 12mm Bh 100.00 0.000
f Pek.pasang dinding spandek 0,45mm M2 784.00 0.000
g Pek.pasang roofing screw spandek Bh 750.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
PEKERJAAN ARSITEKTUR

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
A PEKERJAAN PASANGAN
1 Pas.Dinding batu bata 1/2 1: 4 M2 550.00 0.000
2 Plesteran Dinding Batu Bata M2 1100.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
PEKERJAAN ARSITEKTUR

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
B PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Keramik dinding 25x40 M2 66.00 0.000
2 Keramik lantai 25 x25 M2 14.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
PEKERJAAN ARSITEKTUR

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
C PEKERJAAN PINTU
1 Pek.pas pintu doubel swing 3,6 lebar 1,8m pintu utama Unit 6.00 0.000
- Multiplek 4mm fin Wood Stain
- Engsel : Fino, Kend, Cisa
- Lockcase Sliding setara Fino , Kend, Cisa
2 Pas.pintu kamar mandi alumunium Unit 8.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
PEKERJAAN MEKANIKAL ELEKTRIKAL

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
A PEKERJAAN SANITASI
1 Kloset jongkok porselen Bh 8.00 0.000
2 Kran air 1/2 " Bh 8.00 0.000
3 Pemasangan Floor Drain Bh 8.00 0.000
4 Tower air kap.1 m3 Bh 1.00 0.000
5 Pembuatan Septik Tank Bh 1.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
PEKERJAAN MEKANIKAL ELEKTRIKAL

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
B PEKERJAAN PLUMBING
1 Instalasi air bersih
Pipa PVC kelas AW dia. 1" M1 25.00 0.000
Pipa PVC kelas AW dia. 3/4" M1 150.00 0.000
Pipa PVC kelas AW dia. 1/2" M1 9.60 0.000
Assesories Pemipaan Ls 1.00 0.000
2 Instalasi air kotor
Pipa PVC kelas AW dia. 4" M1 30.00 0.000
Pipa PVC kelas AW dia. 3" M1 50.00 0.000
Assesories Pemipaan Bh 1.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
PEKERJAAN MEKANIKAL ELEKTRIKAL

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI
C PEKERJAAN ELEKTRIKAL
I PEKERJAAN LISTRIK DAN PENGKABELAN
1 Penyambungan Kabel titik api dari Gedung E ke Panel GSG NYY 4x25 mm M1 240.00 0.000
2 Pembuatan Panel Listrik Unit 1.00 0.000
3 Lampu TL Bh 16.00 0.000
4 Saklat double Bh 4.00 0.000
5 Instalasi titik penerangan, kabel NYY 3x2,5 mm dalam conduit Titik 16.00 0.000

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH
JUMLAH

PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
KEMENTERIAN RISET, TEKNOLOGI, DAN PENDIDIKAN TINGGI
INSTITUT TEKNOLOGI SUMATERA
Jalan Terusan Ryacudu, Eay Hui Jati Agung, Lampung Selatan 35365
Telepon (0721) 8030188, Fax (0721) 8030189, Email: pusat@itera.ac.id
www.itera.ac.id

KEGIATAN : PEMBANGUNAN GEDUNG Sertifikat Bulanan No


PEKERJAAN : PEMBANGUNAN GEDUNG GSG ITERA Tanggal Periode
PENYAMBUNGAN INSTALASI AIR DARI GEDUNG ASRAMA KE TOWER GSG

VOLUME REALISASI VOLUME


NO URAIAN PEKERJAAN SATUAN
KONTRAK BULAN LALU BULAN INI

1 Penyambungan Instalasi Air dari Gedung Asrama ke GSG Ls 1.00 0.000


Penyambungan Pipa AW 1"
Pembuatan Panel Pompa
Pengadaan Pompa Pendorong
Pembuatan Water Toren

PEJABAT PELAKSANA KEGIATAN (PPK) KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAUN DIANDRA
JUMLAH
PROSENTASE........%
…………………………… …………………… ENDANG KUSNADI
NIP. …………………………. Site Engineer Deriktur
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

124.00 10,000.00 1,240,000.00


0.25 100,000.00 25,000.00
18.00 865,365.00 15,576,570.00
2.00 175,000.00 350,000.00
0.00 7,350,000.00 -

UMLAH 17,191,570.00

BULAN LALU BULAN INI S/D BULAN INI


64.97 64.97
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

242.16 13,500.00 3,269,160.00


120.00 64,500.00 7,740,000.00
0.00 46,500.00 -
0.00 217,800.00 -
0.00 48,825.00 -
0.00 217,800.00 -
4.00 796,416.00 3,185,664.00

UMLAH 11,009,160.00

BULAN LALU BULAN INI S/D BULAN INI


19.91 19.91
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

15.094 945,461.34 14,270,594.24


29.760 1,500.00 44,639.63
7.026 1,800,000.00 12,647,653.47

5.367 945,461.34 5,073,989.06


7.917 1,500.00 11,875.22
9.369 1,500,000.00 14,052,948.30

UMLAH 46,101,699.92
BULAN LALU BULAN INI S/D BULAN INI
74.53 74.53
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 216,350.00 -
0.000 Err:509 Err:509
0.000 Err:509 Err:509

0.000 Err:509 Err:509


0.000 Err:509 Err:509
0.000 Err:509 Err:509

0.000 Err:509 Err:509


0.000 Err:509 Err:509
0.000 2,500,000.00 -

UMLAH
UMLAH Err:509

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 145,000.00 -
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509

UMLAH Err:509

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 90,235.00 -
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509

UMLAH
UMLAH Err:509

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 Err:509 Err:509


0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509

UMLAH Err:509
UMLAH

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 102,199.10 -
0.000 830,093.78 -
0.000 322,260.50 -
0.000 5,000.00 -

UMLAH -

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 Err:509 Err:509


0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509
0.000 Err:509 Err:509

UMLAH Err:509

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 90,235.00 -
0.000 52,914.00 -

UMLAH -

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 238,065.00 -
0.000 216,350.00 -

UMLAH -

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 3,250,000.00 -

0.000 1,250,000.00 -

UMLAH -

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 526,750.00 -
0.000 74,517.50 -
0.000 306,620.00 -
0.000 4,850,000.00 -
0.000 5,000,000.00 -

UMLAH -

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 23,024.50 -
0.000 19,149.50 -
0.000 16,824.50 -
0.000 150,000.00 -

0.000 115,904.50 -
0.000 75,217.00 -
0.000 150,000.00 -

UMLAH -
UMLAH

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 85,000.00 -
0.000 5,000,000.00 -
0.000 165,436.00 -
0.000 38,936.00 -
0.000 183,736.00 -

UMLAH -
UMLAH

BULAN LALU BULAN INI S/D BULAN INI


0.00 0.00
kat Bulanan No : 1 (Satu)
: 10 April - 7 Mei 2018
NILAI KONTRAK : Rp. 1.400.020.000,00
SASI VOLUME H. SATUAN JUMLAH HARGA
S/D BULAN INI Rp Rp

0.000 22,500,000.00 -

UMLAH -
BULAN LALU BULAN INI S/D BULAN INI
0.00 0.00