Anda di halaman 1dari 2

DIHITUNG

HARGA SATUAN
NO KOMPONEN KUANTITAS SATUAN
Rp

A TENAGA

1 Pekerja 3.9200 jam 11,553.57

2 Tukang 1.9600 jam 17,267.86

3 Mandor 0.9800 jam 18,696.43

JUMLAH TENAGA

B BAHAN

1 Batu Belah 1.0140 m3 267,200.00

2 Pasir Urug 0.1340 m3 115,850.00

3 Sirtu 0.2680 m3 125,500.00

JUMLAH BAHAN

C ALAT

1 3-Wheel Roller 0.0120 jam 227,470.36

2 Water Tanker 0.0382 jam 216,323.46

JUMLAH ALAT

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E OVERHEAD & PROFIT 12.5 %xD
F HARGA SATUAN PEKERJAAN ( D + E )
JUMLAH HARGA

Rp

45,290.00

33,845.00

18,322.50

97,457.50

270,940.80

15,523.90

33,634.00

320,098.70

2,740.61

8,253.30

2,740.61

420,296.81
52,537.10
472,833.91