CONTOH PERHITUNGAN KEWAJARAN HARGA SATUAN PEKERJAAN GALIAN SELOKAN (JENIS TANAH BIASA)

GALIAN SELOKAN/ DRAINASE

ALAT YANG DIGUNAKAN


BIAYA SEWA SEHARI VOLUME
EXCAVATOR MINI 2,500,000.00 1
DUMP TRUK 600,000.00 5
ALAT BANTU (10% DARI BIAYA TENAGA KERJA) 140,000.00 1

JUMLAH PEKERJA 125,000.00 10


MANDOR 150,000.00 1
TOTAL
VOLUME GALIAN YANG DIHASILKAN SEHARI (200 X 1,2 X 1,0) 240
BIAYA GALIAN/ METER KUBIK TOTAL BIAYA SEHARI / VOLUME HASIL PEKERJAAN

30
6
IS TANAH BIASA)

TOTAL BIAYA
2,500,000.00
3,000,000.00 1,800,000.00 3 1,800,000.00
140,000.00 140,000.00 140,000.00
-
1,250,000.00 1,400,000.00 45 5,625,000.00
150,000.00 1 150,000.00
7,040,000.00 3,340,000.00 7,565,000.00
135 16.875
29,333.33 56,037.04