Misalkan:
Panjang Hollow (L) = 6000 mm
Lebar Hollow (W) = 40 mm
Tinggi hollow (H) = 40 mm
Ketebalan (B) = 2 mm
Berat jenis besi = 7850 (Kg/M3)
Berat Jenis besi (BJ) = 7.85 Kg/ 1.000.000 mm3
56 A.4.2.1 45 1 unit
8 A.4.5.1 11 1 m²
9 A.4.5.1 12 1 m²
10 A.4.5.1 13 1 m²
11 A.4.5.1 11 1 m²
12 A.4.5.1 12 1 m²
13 A.4.5.1 13 1 m²
14 A.4.5.1 14 1 m²
Rekap / HAL 15 DARI 616
REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN
18 A.4.5.1 18 1 m²
19 A.4.5.1 19 1 m²
20 A.4.5.1 20 1 m²
21 A.4.5.1 21 1 m1
24 A.4.7.1 19 1 m2
25 A.4.7.1 20 1 m2
26 A.4.7.1 21 1 m2
27 A.4.7.1 22 10 m2
28 A.4.7.1 23 10 m2
29 A.4.7.1 24 1 m2
30 A.4.7.1 25 1 m2
31 A.4.7.1 25.a 1M1
32 A.4.7.1 25.b 1M1
33 A.4.7.1 25.c 1M1
34 A.4.7.1 26 1 m2
8 A.7.1.1 8 1 pohon
9 A.7.1.1 9 1 pohon
10 A.7.1.1 10 1 pohon
11 A.7.1.1 11 1 pohon
12 A.7.1.1 12 1 pohon
13 A.7.1.1 13 1 pohon
14 A.7.1.1 14 1 Pohon
15 A.7.1.1 15 1 Pohon
16 A.7.1.1 16 1 Pohon
17 A.7.1.1 17 1 Pohon
18 A.7.1.1 18 1 Pohon
19 A.7.1.1 19 1 Pohon
20 A.7.1.1 20 1 Pohon
21 A.7.1.1 21 1 Pohon
22 A.7.1.1 22 1 Pohon
23 A.7.1.1 23 1 Pohon
24 A.7.1.1 24 1 m'.
25 A.7.1.1 25 1 m'.
26 A.7.1.1 26 1 pohon
27 A.7.1.1 27 1 Pohon
28 A.7.1.1 28 1 pohon
29 A.7.1.1 29 1 pohon
30 A.7.1.1 30 1 pohon
31 A.7.1.1 31 1 pohon
32 A.7.1.1 32 1 pohon
33 A.7.1.1 33 1 pohon
34 A.7.1.1 34 1 pohon
35 A.7.1.1 35 1 pohon
36 A.7.1.1 36 1 pohon
37 A.7.1.1 37 1 rumpun
38 A.7.1.1 38 1 M'
39 A.7.1.1 39 1 pohon
40 A.7.1.1 40 1 pohon
41 A.7.1.1 41 1 pohon
42 A.7.1.1 42 1 rumpun
43 A.7.1.1 43 1 rumpun
44 A.7.1.1 44 1 rumpun
45 A.7.1.1 45 1 pohon
46 A.7.1.1 46 1 pohon
47 A.7.1.1 47 1 pohon
48 A.7.1.1 48 1 pohon
49 A.7.1.1 49 1 Rumpun
50 A.7.1.1 50 1 Rumpun
51 A.7.1.1 51 1 Rumpun
22 A.4.5.1 22 1 m2
50 A.4.4.3 54g 1 m²
51 A.4.4.3 54h 1 m²
22 A.4.5.1 23 1 m2
23 A.4.5.1 24 1 m2
12 A.2.2.2.12 1 bulan
15 F.4.a 1 m³
16 A.4.6.2 30 1 m2
17 A.4.2.1 30a 1 m²
53 A.4.4.3 55c 1 m'
54 A.4.4.3 55c 1 m'
55 A.4.2.1 49 1 m²
56 1 m1
57 1 m²
58 A.4.2.1 P.10 1 m3
59 A.4.2.1 P.11 1 m2
60 A.4.2.1 P.12 1 m2
PEKERJAAN PERSIAPAN
PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter -
Pembuatan Pagar sementara dari seng gelombang tinggi 2 meter 422,500.00
Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter -
Pengukuran dan Pemasangan Bouwplank 83,700.00
Pembuatan 1 m2 kantor sementara lantai plesteran 1,415,900.00
Pembuatan 1 m2 rumah jaga (konstruksi kayu ) 1,414,300.00
Pembuatan 1 m2 gudang semen dan peralatan 1,095,400.00
Pembuatan 1 m2 bedeng pekerja 1,147,300.00
Pembersihan lapangan dan perataan 18,500.00
Pembuatan steger/perancah dari bambu 457,900.00
Pembuatan 1 buah kotak adukan ukuran 40 cm x 50 cm x 25 cm 170,800.00
Pembuatan Jalan sementara 184,700.00
Pekerjaan Bongkaran Beton Bertulang 1,425,700.00
Pekerjaan Bongkaran Dinding Tembok Plesteran 712,800.00
Pekerjaan Bongkaran Lantai Ubin / Keramik 5,300.00
Pekerjaan Bongkaran Atap Genteng / Sirap 3,700.00
Pekerjaan Bongkaran Atap Seng 6,600.00
Pekerjaan Bongkaran Rangka Atap Kayu 106,900.00
Pekerjaan Bongkaran Rangka Badan Kayu 959,300.00
Pemasangan pagar kawat jaring galvanis panjang 240 cm 22,600.00
Pemasangan panel beton pracetak 5x50x240 cm untuk pagar 417,900.00
Pekerjaan Pagar BRC T= 1.2 m Pondasi (Batukali + Sloof) Dihitung setiap 2.4 m 2,249,200.00
Pasang papan nama proyek ukuran 120 x 240cm 807,800.00
Jaring pengaman proyek 23,100.00
PEKERJAAN PERSIAPAN
( NON STANDAR )
Penyediaan listrik kerja sementara 30,883,600.00
Penyediaan air kerja sementara ( Selama proyek berjalan ) 4,556,750.00
Penyediaan lift barang sementara 21,885,600.00
Sewa alat tower Crane (Type ST60/15 dengan radius 60 m termasuk Genset, dengan
192,062,836.00
standard mesin 150 KVA)
Mob demob alat pemancangan ( Sub Cont ) 106,721,900.00
Mobilisasi dan Demobilisasi Alat material (Asumsi mobil Colt Diesel) 419,300.00
Mobilisasi tenaga kerja jarak tempuh 200km kebawah 202,100.00
Dokumentasi / Poto Progres 4,253,900.00
Asbuilt dwg.(1 asli + 2 copy) 17,473,500.00
Pondasi untuk tower crane ukuran 5x5x1,5m 125,306,000.00
Sewa Tower Crane Per bulan termasuk Operator, BBM, Genset & Mob Demob 188,296,900.00
Mob demob alat Tower crane, Mobil crane dan Alat berat pengeboran 45,060,800.00
PEKERJAAN TANAH
PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
Galian Tanah Dalam s/d 1 m manual 78,030.00
Galian Tanah Dalam s/d 2 m manual 96,200.00
Galian Tanah Dalam s/d 3 m manual 114,800.00
Galian Tanah keras Dalam 1 m manual 103,800.00
Galian Tanah Cadas Dalam 1 m manual 157,800.00
Galian Tanah Lumpur Dalam 1 m manual 125,700.00
Pekerjaan Stripping Tebing 1 m 5,800.00
Buang Tanah Sejauh 30 m 34,200.00
Mengurug Kembali Galian 57,800.00
Memadatkan Tanah Per 20 cm 57,800.00
Pengurugan dengan pasir urug 191,500.00
PEKERJAAN DINDING
PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1P 437,100.00
Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1P 379,100.00
Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campuran Spesi 278,300.00
Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campuran Spesi 147,100.00
Pasangan Dinding Batako. Campuran Spesi 1PC : 4PP 61,900.00
Pasangan Dinding HB/CB 20.Campuran Spesi 1PC : 3PP -
Pasangan Dinding HB/CB 20.Campuran Spesi 1PC :4PP -
Pasangan Dinding HB/CB 15.Campuran Spesi 1PC :3PP -
Pasangan Dinding HB/CB 15.Campuran Spesi 1PC :4PP -
Pasangan Dinding HB/CB 10.Campuran Spesi 1PC :3PP -
Pasangan Dinding HB 10.Campuran Spesi 1PC 4PP -
Pasangan Dinding Terawang (Roster beton) Uk.(12x11x24)cm.Campuran Spesi 1PC : 3PP -
Pasangan Dinding Terawang (Roster beton) Uk.(12x11x24)cm.Campuran Spesi 1PC : 4PP 171,700.00
Pasangan Dinding Bata ringan tebal 7.5cm dengan mortar siap pakai 232,610.00
Pasangan Dinding Bata ringan tebal 10cm dengan mortar siap pakai 312,720.00
Pasangan Dinding Bata ringan tebal 15cm dengan mortar siap pakai 432,100.00
Panel Dinding fasade ex. Hebel 429,800.00
PEKERJAAN KAYU
PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
Membuat & memasang Kusen Pintu dan Kusen Jendela.Kayu Kelas I 4,333,800.00
Membuat & memasang Kusen Pintu dan Kusen Jendela. Kayu Kelas II & III 8,119,500.00
Membuat & memasang Pintu Klamp Standart. Kayu Kelas II 362,100.00
Membuat & memasang Pintu Klamp sederhana. Kayu Kelas III gudang sementara 332,900.00
Membuat & memasang Daun Pintu Panel.Kayu Kamper Samarinda Kelas II 769,400.00
Membuat & memasang Pintu dan Jendela Kaca. Kayu Kelas I 1,486,200.00
Membuat & memasang Pintu dan Jendela Kaca.Kayu Kamper Samarinda Kelas II 584,100.00
Membuat & memasang Pintu dan Jendela Jalusi. Kayu Kamper Samarinda 857,300.00
Membuat & memasang Daun Pintu Kayu Lapis (Plywood) Rangkap.Rangka Tertutup
688,500.00
Kayu Kamper (lebar Sampai 90 cm)
Membuat & memasang Pintu Plywood Rangkap.Rangka Expose Kayu Kamper Samarinda 752,000.00
Pasang Jalusi Kusen. Kayu Kamper Samarinda 684,000.00
Cope lampu kayu Kamper Samarinda finish cat Duco 274,700.00
Plin kayu kamper Samarinda ukuran 10 x 100mm finish melamik 113,600.00
Pasang dan pembuatan meja Counter Nurse station 4,674,900.00
PEKERJAAN PENGECATAN
PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
Mengikis/mengerok permukaan cat tembok lama 16,400.00
Mencuci bidang permukaan tembok yang pernah dicat 15,500.00
Mengerok karat cat lama permukaan baja dengan cara manual 16,500.00
Pengecatan bidang kayu baru ( 1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup 50,300.00
Pelaburan bidang kayu dengan teak oil -
Pelaburan bidang kayu dengan politur 53,200.00
Pelaburan 1 m2 bidang kayu dengan cat residu dan ter -
Pelaburan bidang kayu dengan vernis 53,000.00
Cat tembok Interior ICI Dulux (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 28,000.00
Cat tembok exterior Weathershield ICI Dulux ( 1 lapis cat dasar, 2 lapis cat penutup ) 37,100.00
Pengecatan 1 m2 tembok baru interior ICI Dulux (1 lapis plamuur, 1 lapis cat dasar, 2 lapis 40,500.00
Pengecatan 1 m2 tembok baru interior Anti bakteri (1 lapis plamuur, 1 lapis cat dasar, 2
51,900.00
lapis cat penutup)
Pengecatan plafon/dak beton baru ( lapis cat dasar, 2 lapis cat penutup) 26,200.00
Pengecatan plafon/dak beton baru Weathershield (1 lapis cat dasar, 2 lapis cat penutup) 33,000.00
Pengecatan plafon/dak beton baru jenis cat anti bakteri (1 lapis cat dasar, 2 lapis cat penut 50,200.00
Pengecatan plafon/dak beton baru jenis cat AGE (1 lapis cat dasar, 2 lapis cat penutup) 38,800.00
Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup) 20,800.00
Melabur tembok dengan kalkarium 10,900.00
Melabur tembok dengan kapur sirih 17,200.00
Melabur tembok lama dengan kapur sirih (pemeliharaan) 7,000.00
Pengecatan permukaan baja dengan meni besi 41,700.00
Pengecatan permukaan baja dengan meni besi dan perancah 72,800.00
Pengecatan permukaan baja lapis seng (galpanis) secara manual sistem 4 lapis cat
25,900.00
konvensional dengan tebal 200 um
Pengecatan permukaan baja lapis seng (galpanis) secara manual sistem 4 lapis cat
31,400.00
mutakhir dengan tebal 200 um
Pengecatan permukaan baja lapis seng (galvanis) secara manual sistem 3 lapis cat
286,500.00
konvensional dengan tebal 200 um
Pengecatan permukaan baja lapis seng (galvani) secara semprot (airless spray) dengan
239,300.00
sistem 1 lapis cat mutakhir dengan tebal 200 um
Pengecatan melamik 267,550.00
Pengecatan Duco bidang kayu baru/besi ( 1 lapis plamir), 1 lapis cat dasar, 3 lapis cat pen 258,160.00
Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) 20,700.00
Pengecatan marka jalan/garis parkir t=2-3mm 935,800.00
Dibulatkan per m1 l=5cm : 46,790.00
Dibulatkan per m1 l=10cm : 93,580.00
Dibulatkan per m1 l=15cm : 140,370.00
Pasang lapisan HPL 186,700.00
PEKERJAAN TANAMAN
Pek. Galian lubang tanam pada tanah biasa maks kedalaman 1 M' 78,000.00
Urugan Tanah Humus / Timbunan 194,900.00
Pek. Pemadatan dan pengolahan Tanah urugan 57,800.00
Buangan sisa Pekerjaan keluar Lokasi Max 30 M 34,100.00
Lubang Tanam dan pengolahan untuk Pohon 27,000.00
Penyiraman Tanaman 3,400.00
Pemupukan dan Pendangiran 11,100.00
a. Penanaman pohon peneduh
Penanaman pohon bintaro t=3m 371,500.00
Pohon Saputangan putih 140,400.00
Dadap Merah t=2 - 4 m 248,000.00
Pohon trembesi t = 3,00 m 149,600.00
Angsana Tinggi 100 cm 19,700.00
Pohon Cabefuya Caraiba `t=3m Jenis pohon peneduh 251,900.00
Pohon Janda merana t=300cm 182,800.00
Pohon bungur t=1,5 -3 m 76,900.00
Pohon kiara payung t=300cm 346,300.00
Pohon Kupu-kupu t=300cm 267,600.00
Pohon Mahoni t= 2,5 - 3 m 377,800.00
Pohon Kaliandra T=300cm 231,200.00
Pohon Ketapang laut t= 2 - 4 m 325,000.00
Pohon Ketapang kencana t= 2 - 4 m 346,300.00
Pohon Tanjung t= 2,5 - 3 m 386,500.00
Pohon Damar T= 1 - 2 m 51,700.00
b. Penanaman pohon pagar
Bambu Jepang (2 s/d 3m) 228,000.00
Bambu Kuning (2 s/d 3m) 172,000.00
c. Penanaman pohon berbuah
Pohon Nangka tinggi 100cm 35,400.00
Pohon Sukun t=1,5 - 2 m 67,100.00
d. Penanaman tanaman hias
Kembang Kancing t = 30 - 50 cm 22,400.00
Hanjuang merah t = 50 - 60 cm 24,200.00
Kemuning t = 30 - 35 cm 18,000.00
Anturium GC t = 40 - 50 cm 91,000.00
Pohon kaca piring tinggi 40cm 51,000.00
Palem botol t=100cm 94,900.00
Palem Kurma t=100cm 6,066,200.00
Pohon Liri muscari 54,600.00
Pohon pisang - pisangan 28,300.00
Pohon Lee Kwan Yew 116,300.00
Teh-Tehan ( Duranta) 65,300.00
Pohon Biola cantik t=1 - 2 m 104,000.00
Pohon Jabon t= 70 cm - 80 cm 20,400.00
Pohon Kasia kuning t=1 m 84,000.00
Miona ( 1 Rumpun=1m2 ---25 pohon ) 176,800.00
Lantana polybeg 20 ( 1 Rumpun=1m2 ---25 pohon ) 147,400.00
Tegetes polybeg 20 ( 1 Rumpun=1m2 ---25 pohon ) 147,400.00
Pohon hias bougenville tunggal t = 50 cm 56,600.00
Pohon hias bougenville campur 3 warna t = 100 cm 126,400.00
Pohon hias bougenville sambung t = 50 cm 72,900.00
Perdu Oleander 40,800.00
Azalea Ungu Polybag 30 55,200.00
Azalea Hibrit Polybag 30 90,500.00
Bayam Merah Polybag 30 114,200.00
NO URAIAN
I. PEKERJA
1 Pekerja
2 Penjaga malam
3 Tukang Aspal
4 Tukang Batu
5 Tukang Besi
6 Tukang Cat
7 Tukang Gypsum
8 Tukang Kayu
9 Tukang Las
10 Tukang Listrik
11 Tukang Taman
12 Tukang Cat Melamik
13 Tukang Pipa
14 Tukang Aluminium
15 Mekanik
16 Kepala Tukang
17 Operator
18 Pembantu Operator
19 Mandor
NO URAIAN
II. BAHAN
A BAHAN DASAR
1 Air
2 Abu Batu / Pasir saring
3 Arbocell
4 Bahan Aditif (Calbon, Strorox dll)
5 Bahan Agr. Base Kelas A
6 Bahan Agr. Base Kelas B
7 Bahan Agr. Base Kelas C
8 Bahan Pilihan
9 Bata Merah Kelas 1
10 Bata Merah Bakar Biasa
11 Bata Merah Kelas 2
12 Batako kecil 8x10x20
13 Batu Belah
14 Batu Pecah 5/10
15 Batu Pecah 5/7
16 Batu Pecah 3/4
17 Batu Pecah 2/3
18 Batu Pecah 1/2
19 Batu Split 0-5 mm Agg Halus
20 Batu Split 10-20 mm Agg Sedang
21 Batu Split 20-30 mm Agg Kasar
22 Batu Bronjong
23 Beton ringan ( Celcon block ), Leibel uk. 9 x 19 x 39 cm
24 Chiping
25 Chiping (kg)
26 Curing Compond
27 Elastomer
28 Filler
29 Glass block Lokal 20 x 20 cm lokal
30 Kerikil / Agregat beton
31 Pasir Beton
32 Pasir Pasang
33 Pasir Urug
34 Pasir Halus
35 Plastik Filter
36 Polytene 125 mikron
37 Plastik cor Hitam
38 Sirtu (Pasir Batu)
39 Tanah Urug merah
40 Tanah Subur
41 Tanah Liat
42 Semen PC type I @ 50 kg Product Tiga Roda
43 Semen PC (kg)
44 Semen Merah
45 Semen Putih
46 Semen Warna untuk nat kemasan plastik
H-Sat.upah & bahan / HAL 48 DARI 616
DAFTAR HARGA SATUAN BAHAN DAN UPAH
NO URAIAN
B BETON
B.1 BETON READY MIX
1 Beton K - 125
2 Beton K - 150
3 Beton K - 175
4 Beton K - 200
5 Beton K - 225
6 Beton K - 250
7 Beton K - 275
8 Beton K - 300
9 Beton K - 325
10 Beton K - 350
11 Beton K - 375
12 Beton K - 400
13 Beton K - 425
14 Beton K - 500
15 Sewa pompa beton
16 Sewa vibrator
C BAHAN BESI
1 Besi beton polos rata-rata
2 Besi beton ulir rata - rata
3 Baja tulangan (ulir) D39
4 Baja tulangan (ulir) D48
5 Baja tulangan (polos) U24
6 Baja tulangan (polos) U32
7 Baja pelat Tebal 2 mm
8 Baja pelat Tebal 3 mm
9 Baja pelat Tebal 5 mm
10 Pelat Rambu (eng Grade)
11 Pelat Rambu (High I, Grade)
12 Rel Pengaman
13 Besi Strip
14 Pipa Baja
15 Pipa Porus
16 Pipa Galvanis 3"
17 Pipa Galvanis 1,5"
18 Kawat beton
19 Kawat brojong
20 Kawat Jaring Galvanis
21 Kawat las listrik kg
22 Kawat las listrik doos
23 Kawat seng 3 mm
24 Kawat Duri
25 Paku rata - rata H-Sat.upah & bahan / HAL 49 DARI 616
UPAH HARGA DASAR
SAT
Rp. Rp.
TH. 2017
89,320 /Org/Hr 81,200.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
137,445 /Org/Hr 124,950.00
184,800 /Org/Hr 168,000.00
157,850 /Org/Hr 143,500.00
184,800 /Org/Hr 168,000.00
89,320 /Org/Hr 81,200.00
157,850 /Org/Hr 143,500.00
-
-
-
-
-
19,800 m3 18,000.00
298,320 m3 271,200.00
103,070 kg 93,700.00
55,440 ltr 50,400.00
467,500 m3 425,000.00
456,500 m3 415,000.00
330,000 m3 300,000.00
151,580 m3 137,800.00
990 bh 900
770 bh 700
880 bh 800
2,420 bh 2,200.00
178,640 m3 162,400.00
261,140 m3 237,400.00
243,320 m3 221,200.00
269,170 m3 244,700.00
281,380 m3 255,800.00
291,500 m3 265,000.00
287,210 m3 261,100.00
259,490 m3 235,900.00
231,880 m3 210,800.00
187,440 m3 170,400.00
1,929,825 m3 0.01
284,900 m3 259,000.00
149,930 kg 136,300.00
50,820 ltr 46,200.00
706,750 bh 642,500.00
1,650 kg 1,500.00
27,500 bh 25,000.00
159,500 m3 145,000.00
175,450 m3 159,500.00
175,450 m3 159,500.00
121,440 m3 110,400.00
159,610 m3 145,100.00
59,180 m2 53,800.00
25,410 kg 23,100.00
7,700 m2 7,000.00
151,800 m3 138,000.00
137,500 m3 125,000.00
137,203 m3 124,730.00
121,550 m3 110,500.00
66,110 Zak 60,100.00
1,760 kg 1,600.00
4,620 kg 4,200.00
9,680 kg 8,800.00
11,660 kg 10,600.00
H-Sat.upah & bahan / HAL 51 DARI 616
UPAH HARGA DASAR
SAT
Rp. Rp.
3,740 kg 3,400.00
2,186 kg 1,987.50
3,339 kg 3,035.00
11,827,200 m2 10,752,000.00
946,000 m3 860,000.00
-
-
-
921,250 m3 837,500.00
956,120 m3 869,200.00
998,360 m3 907,600.00
1,016,510 m3 924,100.00
1,033,010 m3 939,100.00
1,060,180 m3 963,800.00
1,112,540 m3 1,011,400.00
1,153,020 m3 1,048,200.00
1,175,020 m3 1,068,200.00
1,218,580 m3 1,107,800.00
1,023,000 m3 930,000.00
1,292,060 m3 1,174,600.00
1,363,340 m3 1,239,400.00
1,404,260 m3 1,276,600.00
71,500 m3 65,000.00
5,775 m3 5,250.00
-
-
11,110 kg 10,100.00
11,550 kg 10,500.00
18,480 kg 16,800.00
19,360 kg 17,600.00
13,200 kg 12,000.00
16,060 kg 14,600.00
517,000 m2 470,000.00
797,500 m2 725,000.00
1,210,000 m2 1,100,000.00
749,100 bh 681,000.00
909,040 bh 826,400.00
892,760 m' 811,600.00
13,310 kg 12,100.00
13,750 kg 12,500.00
103,180 m' 93,800.00
209,660 m' 190,600.00
42,900 m' 39,000.00
18,590 kg 16,900.00
28,820 kg 26,200.00
28,820 kg 26,200.00
30,360 kg 27,600.00
157,630 doos 143,300.00
28,380 kg 25,800.00
69,300 m' 63,000.00
18,370 kg 16,700.00 H-Sat.upah & bahan / HAL 52 DARI 616
SEWA ALAT BERAT & MESIN MESIN
No. Jenis Barang / Jasa Satuan Harga (Rp) 1.00
1 Asphalt Finisher 10 T /Jam 776,461.11 776,461.11
2 Asphalt Mixing Plant 30 T /Jam 364,000.00 364,000.00
3 Asphalt Mixing Plant 60 T /Jam 6,209,870.05 6,209,870.05
3 Asphalt Sprayer, Selfprop /jam 71,274.88 71,274.88
4 Asphalt Sprayer, Towed /Jam 26,190.00 26,190.00
5 Asphalt Distributor 4000 litter /Jam 364,598.75 364,598.75
6 Asphalt tanker /Jam 616,485.99 616,485.99
7 Blower /Jam 8,362.20 8,362.20
8 Bulldozer 100-160 HP /jam 651,433.52 651,433.52
9 Cement Tanker 4000 litter /jam 498,656.66 498,656.66
10 Compressor 210 m3 /Jam 173,435.48 173,435.48
11 Compressor Air /Jam 98,844.90 98,844.90
12 Concrete Mixer 0,3-0,6 m3 /Jam 128,831.27 128,831.27
13 Concrete Mixer 350 L /Jam 79,307.84 79,307.84
14 Concrete pump 100 HP /Jam 315,373.05 315,373.05
15 Concrete Vibrator /Jam 50,922.12 50,922.12
16 Concrete Pan Mixer 600 litter /Jam 642,320.57 642,320.57
17 Concrete Saw 14 mm /Jam 53,841.22 53,841.22
18 Cordrill DLL /Jam 213,418.01 213,418.01
19 Cold Recycle 2,2 M /Jam 6,159,697.89 6,159,697.89
20 Crane 10-15 Ton /Jam 457,014.59 457,014.59
21 Alat pancang /Jam 346,661.91 346,661.91
22 Crane on track 35 ton/200HP /Jam 449,962.32 449,962.32
23 Crane on track 75 - 100 Ton /Jam 615,562.98 615,562.98
24 Crusher 30 T/H /Jam 704,469.29 704,469.29
25 Dump Truck /Jam 207,398.88 207,398.88
26 Dump Truck /Jam 437,745.00 437,745.00
27 Dump truk 3 ton /Jam 290,783.82 290,783.82
28 Dump truk 10 ton /Jam 475,167.11 475,167.11
29 Excavator long 1,5 m3 /Jam 321,200.00 321,200.00
30 Excavator long 2 m3 /Jam 624,977.30 624,977.30
31 Fulvimixer 345 HP /Jam 898,763.10 898,763.10
32 Hydraulik Exacavator 1,3 M3 /Jam 316,129.28 316,129.28
33 Hot Recycle 3,0 M /Jam 7,421,296.84 7,421,296.84
34 Jack Hammer /Jam 43,318.56 43,318.56
35 Wheel Loader 2,5 m3 /Jam 231,000.00 231,000.00
36 Low Loader Tractor /Jam 287,247.45 287,247.45
37 Mesin Gilas 3 roda /Jam 219,754.18 219,754.18
38 Mesin Penyemprot Aspal 200 L /Jam 65,288.31 65,288.31
39 Motor Grader 135 HP /Jam 258,500.00 258,500.00
40 Motor Grader 150 HP /Jam 582,421.73 582,421.73
41 Pedestrian roller /Jam 85,313.95 85,313.95
42 Pengaduk Beton 125 L/6 HP /Jam 85,490.21 85,490.21
43 Pengaduk Beton 500 L/20 HP /Jam 85,490.21 85,490.21
44 Peralatan Tractor /Jam 205,422.53 205,422.53
45 Pick Up Truck /Jam 100,866.15 100,866.15
46 Pile driver +hammer 25 HP /Jam 280,389.01 280,389.01
47 Flat Bed Truck /Jam 290,783.82 290,783.82
48 Pneumatic Roller /Jam 274,959.30 274,959.30
49 Screening Plant /Jam 236,463.15 236,463.15
50 Self Vibrator Roller /Jam 206,837.40 206,837.40
51 Sprayer Slee Propeellered /Jam 331,023.00 331,023.00
SEWA ALAT BERAT & MESIN MESIN
No. Jenis Barang / Jasa Satuan Harga (Rp) 1.00
52 Stone crusher /Jam 1,094,144.83 1,094,144.83
53 Spill from paver 2,5 M /Jam 339,691.46 339,691.46
54 Rock Drill breaker /Jam 312,312.51 312,312.51
55 Tamper 4 HP /Jam 50,775.25 50,775.25
56 Tamper 4,7 HP /Jam 57,500.01 57,500.01
57 Tandem Roller 8-18 Ton /Jam 404,666.92 404,666.92
58 Three whell roller 6-8 T /Jam 353,825.92 353,825.92
59 Tire roller 8-10T /Jam 439,502.42 439,502.42
60 Towed Vibrator Rooler /Jam 82,490.10 82,490.10
61 Track loader 2,8m3 /Jam 284,852.12 284,852.12
62 Tractor Wheeled /Jam 116,320.05 116,320.05
63 Trailer 20 ton/175 HP /Jam 418,466.76 418,466.76
64 Vibrator Roller /Jam 404,666.92 404,666.92
65 Vibro Compactor /Jam 220,000.00 220,000.00
66 Water Pump (0 - 5 cm) /Jam 16,273.95 16,273.95
67 Water Pump (70 - 100 mm) /Jam 49,275.66 49,275.66
68 Water Tank Truck /Jam 223,411.65 223,411.65
69 Water tanker 300-4500L /Jam 257,793.83 257,793.83
70 Wheel loader 1-1,6 m3 /Jam 467,182.34 467,182.34
SEWA ALAT BERAT & MESIN MESIN
No. Jenis Barang / Jasa Satuan Harga (Rp) 1.00
SEWA ALAT BERAT & MESIN MESIN
No.
Jenis Barang / Jasa Satuan Harga (Rp) Harga (Rp)
1 Asphalt liquid mixer 40 HP /Jam 82,396.78 82,396.78
2 Asphalt liquid mixer 5 HP /Jam 55,968.41 55,968.41
3 Asphalt liquid mixer 20,000 litter /Jam 118,396.36 118,396.36
4 Aggregat (chip) Speared 3,5 M /Jam 531,202.37 531,202.37
5 Blending equipment 50 HP /Jam 229,756.95 229,756.95
6 Cold milling 248 HP /Jam 55,968.41 55,968.41
7 Cold milling 1000 m /Jam 1,643,150.59 1,643,150.59
8 Concrete breaker 290 HP 20 m3/jam /Jam 830,828.87 830,828.87
9 Condrete mixer (350)/20 HP /Jam 97,667.96 97,667.96
10 Pontoon /Jam 668,422.76 668,422.76
11 Tronton 150 HP /Jam 528,591.26 528,591.26
12 Truk mixer (agitator) 220 HP 5 m3 /Jam 619,328.15 619,328.15
13 Vibrating rammer 4,2 HP 80 kg /Jam 55,770.47 55,770.47
14 Welding set 40 HP /Jam 117,133.87 117,133.87
15 SEWA ALAT PANCANG pemakaian tiang min 400m
b. Biaya pemborongan penyambungan tiang pancang /Jam 98,175.00 98,175.00
=
Maka harga sewa peralatan adalah : =
=
B.2 Biaya Pelumas
g= DK x f + c liter/jam
195.50 t
Dimana:
g = banyaknya minyak pelumas yang digunakan
DK = Kekuatan minyak = 150 KVA
F = faktor = ( 0,8 x 0,83 )
c = isi dari carter mesin = 200 liter
t = selang waktu pergantian = 42 jam
maka :
g = 150x(0.8x0.83) + 200
195.50 42
= 5,27 liter/jam
Biaya pemakaian minyak pelumas :
C. Biaya Operator
Biaya operator =
Rp 75,075,000.00 /bulan
Rp 26,000,000.00 /bulan
Rp 4,620,000.00 /bulan
Rp 30,000.00 /liter
Rp 8,500.00 /liter
Rp 40,425,000.00 PP
Rp 40,000,000.00 /Unit
Rp 75,075,000.00 /bulan
200 jam
Rp 375,375.00 /jam
Rp 26,000,000.00 /bulan
200 jam
Rp 130,000.00 /jam
Rp 375,375.00 /jam
Rp 130,000.00 /jam +
Rp 505,375.00 /jam
5.27 liter/jam
Rp 30,000.00 /liter x
Rp 158,100.00 /jam
Rp 169,320.00 /jam
Rp 158,100.00 /jam +
Rp 327,420.00 /jam
Rp 4,620,000.00 /bulan
Rp 200.00 /jam /
Rp 23,100.00 /jam
Rp 505,375.00 /jam
Rp 327,420.00 /jam
Rp 23,100.00 /jam
Rp 855,895.00 /jam
Rp 855,895.00 /jam
200 jam x
Rp 171,179,000.00 /bulan
Rp 17,117,900.00
Rp 188,296,900.00 /bulan
=
B.2 Biaya Pelumas
g= DK x f + c liter/jam
195.50 t
Dimana:
g = banyaknya minyak pelumas yang digunakan
DK = Kekuatan minyak = 150 KVA
F = faktor = ( 0,8 x 0,83 )
c = isi dari carter mesin = 200 liter
t = selang waktu pergantian = 42 jam
maka :
g = 150x(0.8x0.83) + 200
195.50 42
= 5,27 liter/jam
Biaya pemakaian minyak pelumas :
C. Biaya Operator
Biaya operator =
Rp 56,306,250.00 /bulan
Rp 4,620,000.00 /bulan
Rp 30,000.00 /liter
Rp 8,500.00 /liter
Rp 40,425,000.00 PP
Rp 56,306,250.00 /bulan
200 jam
Rp 281,531.25 /jam
Rp 281,531.25 /jam
Rp - /jam +
Rp 281,531.25 /jam
19.92 liter/jam
Rp 8,500.00 /liter x
Rp 169,320.00 /jam
5.27 liter/jam
Rp 30,000.00 /liter x
Rp 158,100.00 /jam
Rp 169,320.00 /jam
Rp 158,100.00 /jam +
Rp 327,420.00 /jam
Rp 4,620,000.00 /bulan
Rp 200.00 /jam /
Rp 23,100.00 /jam
Rp 281,531.25 /jam
Rp 327,420.00 /jam
Rp 23,100.00 /jam
Rp 632,051.25 /jam
Rp 632,051.25 /jam
Analisa mobile crane / HAL 64 DARI 616
alatan yang disebut harga sewa peralatan persatuan waktu, biaya operasional
200 jam x
Rp 126,410,250.00 /bulan
Rp 12,641,025.00
Rp 139,051,200.00 /bulan
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
2 A.2.2.1.2 1m1 Pembuatan Pagar sementara dari seng gelombang tinggi 2 meter
Bahan
Kayu dolken Ø8-10 / p=400 cm 1.250 batang
Semen PC ( 50 kg / zak ) 0.050 zak
Seng gelombang BJLS 28 1.200 lbr
Pasir beton 0.005 m3
Batu split 2x3 0.009 m3
Kayu 5/7 setara lokal (sembarang) 0.072 m3
Paku 0.060 kg
Residu 0.400 liter
Tenaga Kerja
Pekerja 0.200 org/hr
Tukang kayu/batu 0.400 org/hr
Kepala Tukang 0.020 org/hr
mandor 0.020 org/hr
A.2.2.1.2 1m1 Pembuatan Pagar sementara dari seng gelombang tinggi 2 meter
3 A.2.2.1.3 1m1 Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter
c
A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
Kaca polos tebal 5mm 0.080 m2
Kunci tanam loakal 0.150 Bh
Plywood 4mm 0.060 Lbr
Tenaga Kerja
Pekerja 2.000 org/hr
Tukang kayu 2.000 org/hr
Tukang tembok 1.000 org/hr
Kepala Tukang 0.300 org/hr
Mandor 0.050 org/hr
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
Tenaga Kerja
Pekerja 1.000 org/hr
Tukang kayu 2.000 org/hr
Kepala Tukang 0.200 org/hr
Mandor 0.050 org/hr
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
12 A.2.2.1.12 1 m2 Pembuatan Jalan sementara
Bahan :
Batu belah/batu krop 0.150 m3
Batu pecah 5x7cm 0.090 m3
Pasir pasang 0.010 m3
Tenaga Kerja
Pekerja 1.000 0rg/hr
Mandor 0.005 0rg/hr
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
22 A.2.2.1.17 1m1 Pekerjaan Pagar BRC T= 1.2 m Pondasi (Batukali + Sloof) Dihitung setiap 2.4 m
Terpasang :
Galian tanah 1.188 m³
Urugan pasir bawah pondasi 0.132 m³
Aanstamping 0.198 m³
Pondasi batu kali 1PC : 5Ps 0.343 m³
Sloof beton 15/20 0.030 m³
- Beton 0.03
- Besi 6.00
- Bekistin 0.40
Urugan tanah 0.515 m³
Pagar BRC 1.000 bh
Tiang pipa BRC 1.500 bh
Plesteran 1PC : 5Ps 0.960 m²
Pengecatan dinding 0.960 m²
A.2.2.1.17 1m1 Pekerjaan Pagar BRC T= 1.2 m Pondasi (Batukali + Sloof) Dihitung setiap
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
Cat kayu 1.000 kg
Minyak cat 0.500 kg
Paku 0.025 kg
Kwas 2.000 bh
2 Tenaga
Tukang 0.500 oh
Pekerja 0.500 oh
Kepala Tukang 0.050 oh
Mandor 0.005 oh
2 Tenaga
Pekerja 0.042 oh
Mandor 0.004 oh
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
A.1 A.2.2.2 PEKERJAAN PERSIAPAN
( NON STANDAR )
Sarana dan prasarana fasilitas kerja sementara
1 A.2.2.2.1 1 Bulan Penyediaan listrik kerja sementara
Sewa Generator 100KVA 1.000 BL
Bahan bakar solar industri 182.000 ltr
Operator (harian perusahaan) 25.000 Hari
4 A.2.2.2.4 1 Bulan Sewa alat tower Crane (Type ST60/15 dengan radius 60 m termasuk Genset, deng
A.2.2.2.4 1 Bulan Sewa alat tower Crane (Type ST60/15 dengan radius 60 m termasuk
Genset, dengan standard mesin 150 KVA)
6 A.2.2.2.6 1 Hari Mobilisasi dan Demobilisasi Alat material (Asumsi mobil Colt Diesel)
Transfortasi material asumsi mobil Colt Diesel 1.000 unit
A.2.2.1 Pek. Persiapan / HAL 74 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
Upah muat dan bongkar barang (pekerja) 0.350 hari
A.2.2.2.6 1 Hari Mobilisasi dan Demobilisasi Alat material (Asumsi mobil Colt Diesel)
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
12 A.2.2.2.10 1 Unit Mob demob alat Tower crane, Mobil crane dan Alat berat pengeboran
Tower crane 1.000 pp
Asuransi Alat dan Ekspedisi 1.000 ls
A.2.2.2.10 1 Unit Mob demob alat Tower crane, Mobil crane dan Alat berat pengeboran
KODE
NO. KOEF/SATUAN/URAIAN Koef. SATUAN
ANALISA
1 2 3 4
- Galian Tanah Dewa tering (DW) 4.000 m3
- Pengeboran Tanah pipa Recharge well 90.000 m1
- Plesteran 1pc : 3ps Recharge well 295.000 m2
- Recharge (RW) Panjang Pipa 15 m ∅ 4" 90.000 m1
- Sewa Pompa Dewatering(DW), Inklino Meter (INK) &
Piezometer (PZ) termasuk Genset dan operator 4.000 unit
5 6 7
304,961.69
37,510.00 46,887.50
66,110.00 3,305.50
69,300.00 83,160.00
175,450.00 877.25
231,880.00 2,086.92
2,158,310.00 155,398.32
18,370.00 1,102.20
30,360.00 12,144.00
79,156.00
89,320.00 17,864.00
137,445.00 54,978.00
157,850.00 3,157.00
157,850.00 3,157.00
Jumlah : 384,117.69
Overhead & keuntungan 10% : 38,411.77
Jumlah : 422,529.46
Jumlah & pembulatan : 422,500.00
89,320.00 8,932.00
137,445.00 13,744.50 25,044.25
157,850.00 1,578.50
157,850.00 789.25
Jumlah : 76,127.59
Overhead & keuntungan 10% : 7,612.76
Jumlah : 83,740.35
Jumlah & pembulatan : 83,700.00
641,029.40
37,510.00 46,887.50
2,158,310.00 388,495.80
18,370.00 1,469.60
66,110.00 46,277.00
175,450.00 26,317.50
175,450.00 17,545.00
231,880.00 34,782.00
990.00 29,700.00
45,000.00 11,250.00
14,400.00 2,880.00
A.2.2.1 Pek. Persiapan / HAL 78 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
5 6 7
108,680.00 8,694.40
150,000.00 22,500.00
70,510.00 4,230.60
646,222.50
89,320.00 178,640.00
137,445.00 274,890.00
137,445.00 137,445.00
157,850.00 47,355.00
157,850.00 7,892.50
Jumlah : 1,287,251.90
Overhead & keuntungan 10% : 128,725.19
Jumlah : 1,415,977.09
Jumlah & pembulatan : 1,415,900.00
788,582.56
37,510.00 112,530.00
2,158,310.00 595,693.56
18,370.00 12,859.00
45,000.00 67,500.00
497,227.50
259,490.00 259,490.00
137,445.00 206,167.50
157,850.00 23,677.50
157,850.00 7,892.50
Jumlah : 1,285,810.06
Overhead & keuntungan 10% : 128,581.01
Jumlah : 1,414,391.07
Jumlah & pembulatan : 1,414,300.00
5 6 7
632,013.70
37,510.00 63,767.00
2,158,310.00 453,245.10
18,370.00 5,511.00
66,110.00 13,883.10
175,450.00 5,263.50
231,880.00 11,594.00
45,000.00 67,500.00
45,000.00 11,250.00
363,893.75
2,186.25 2,186.25
137,445.00 274,890.00
157,850.00 78,925.00
157,850.00 7,892.50
Jumlah : 995,907.45
Overhead & keuntungan 10% : 99,590.75
Jumlah : 1,095,498.20
Jumlah & pembulatan : 1,095,400.00
657,189.76
37,510.00 46,887.50
2,158,310.00 401,445.66
18,370.00 5,511.00
66,110.00 23,799.60
175,450.00 5,263.50
231,880.00 11,594.00
45,000.00 67,500.00
70,510.00 95,188.50
385,852.50
71,500.00 71,500.00
137,445.00 274,890.00
157,850.00 31,570.00
157,850.00 7,892.50
Jumlah : 1,043,042.26
Overhead & keuntungan 10% : 104,304.23
Jumlah : 1,147,346.49
Jumlah & pembulatan : 1,147,300.00
89,320.00 8,932.00
157,850.00 7,892.50
Jumlah : 16,824.50
Overhead & keuntungan 10% : 1,682.45
Jumlah : 18,506.95
Jumlah & pembulatan : 18,500.00
83,411.00
40,000.00 50,000.00
150,000.00 27,900.00
18,370.00 5,511.00
A.2.2.1 Pek. Persiapan / HAL 80 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
5 6 7
332,942.50
18,590.00 18,590.00
137,445.00 274,890.00
157,850.00 31,570.00
157,850.00 7,892.50
Jumlah : 416,353.50
Overhead & keuntungan 10% : 41,635.35
Jumlah : 457,988.85
Jumlah & pembulatan : 457,900.00
109,385.10
2,158,310.00 77,699.16
2,158,310.00 30,216.34
18,370.00 1,469.60
45,969.00
137,445.00 41,233.50
157,850.00 4,735.50
Jumlah : 155,354.10
Overhead & keuntungan 10% : 15,535.41
Jumlah : 170,889.51
Jumlah & pembulatan : 170,800.00
5 6 7
77,845.54
292,327.17 43,849.08
358,244.08 32,241.97
175,450.00 1,754.50
90,109.25
89,320.00 89,320.00
157,850.00 789.25
Jumlah : 167,954.79
Overhead & keuntungan 10% : 16,795.48
Jumlah : 184,750.27
Jumlah & pembulatan : 184,700.00
1,296,120.98
89,320.00 1,190,992.88
157,850.00 105,128.10
Jumlah 1,296,120.98
Overhead & keuntungan 10% : 129,612.10
Jumlah : 1,425,733.08
Jumlah & pembulatan : 1,425,700.00
648,060.49
89,320.00 595,496.44
157,850.00 52,564.05
Jumlah 648,060.49
Overhead & keuntungan 10% : 64,806.05
Jumlah : 712,866.54
Jumlah & pembulatan : 712,800.00
4,860.63
89,320.00 4,466.00
157,850.00 394.63
Jumlah 4,860.63
Overhead & keuntungan 10% : 486.06
Jumlah : 5,346.69
Jumlah & pembulatan : 5,300.00
3,364.90
89,320.00 1,786.40
157,850.00 1,578.50
Jumlah 3,364.90
Overhead & keuntungan 10% : 336.49
Jumlah : 3,701.39
Jumlah & pembulatan : 3,700.00
6,044.50
89,320.00 4,466.00
157,850.00 1,578.50
Jumlah 6,044.50
Overhead & keuntungan 10% : 604.45
A.2.2.1 Pek. Persiapan / HAL 82 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
5 6 7
Jumlah : 6,648.95
Jumlah & pembulatan : 6,600.00
97,212.50
89,320.00 89,320.00
157,850.00 7,892.50
Jumlah 97,212.50
Overhead & keuntungan 10% : 9,721.25
Jumlah : 106,933.75
Jumlah & pembulatan : 106,900.00
872,153.33
137,445.00 549,780.00
89,320.00 238,186.67
157,850.00 63,140.00
157,850.00 21,046.67
Jumlah 872,153.33
Overhead & keuntungan 10% : 87,215.33
Jumlah : 959,368.67
Jumlah & pembulatan : 959,300.00
5 6 7
9,321.00
65,000.00 9,321.00
11,246.62
89,320.00 3,751.44
137,445.00 549.78
157,850.00 315.70
157,850.00 6,629.70
Jumlah 20,567.62
Overhead & keuntungan 10% : 2,056.76
Jumlah : 22,624.38
Jumlah & pembulatan : 22,600.00
324,369.55
88,773.30 87,530.47
248,575.80 130,502.30
1,322.20 59,499.00
175,450.00 12,983.30
231,880.00 33,854.48
55,568.98
89,320.00 33,495.00
137,445.00 17,180.63
157,850.00 1,894.20
157,850.00 2,999.15
Jumlah 379,938.52
Overhead & keuntungan 10% : 37,993.85
Jumlah : 417,932.38
Jumlah & pembulatan : 417,900.00
70,936.25 84,272.27
174,102.50 22,981.53
501,415.53 99,280.27
849,373.25 291,335.02
1,173,363.49 35,200.90
963,240.24
15,580.00
194,543.25
24,827.69 12,786.26
360,000.00 360,000.00
698,544.00 1,047,816.00
61,128.23 58,683.11
33,801.52 32,449.45
Jumlah : 2,044,804.82
Overhead & keuntungan 10% : 204,480.48
Jumlah : 2,249,285.30
si (Batukali + Sloof) Dihitung setiap 2.4 m Jumlah & pembulatan : 2,249,200.00
612,312.07
3,332,010.00 341,197.82
146,850.00 161,535.00
5 6 7
57,640.00 57,640.00
19,800.00 9,900.00
18,370.00 459.25
20,790.00 41,580.00
122,064.25
137,445.00 68,722.50
89,320.00 44,660.00
157,850.00 7,892.50
157,850.00 789.25
Jumlah : 734,376.32
Overhead & keuntungan 10% : 73,437.63
Jumlah : 807,813.96
Jumlah & pembulatan : 807,800.00
16,675.01
15,159.10 16,675.01
4,414.41
89,320.00 3,751.44
157,850.00 662.97
Jumlah : 21,089.42
Overhead & keuntungan 10% : 2,108.94
Jumlah : 23,198.36
Jumlah & pembulatan : 23,100.00
5 6 7
22,000,000.00 22,000,000.00
8,000.00 1,456,000.00
184,800.00 4,620,000.00
Jumlah : 28,076,000.00
Overhead & keuntungan 10% : 2,807,600.00
Jumlah : 30,883,600.00
Jumlah & pembulatan : 30,883,600.00
7,500,000.00 7,500,000.00
75,000.00 3,375,000.00
3,400,000.00 6,800,000.00
15,000,000.00 15,000,000.00
8,750,000.00 8,750,000.00
Jumlah : 41,425,000.00
Overhead & keuntungan 10% : 4,142,500.00
Jumlah & pembulatan : 45,567,500.00
Jumlah & pembulatan per bulan : 4,556,750.00
550,000.00 13,750,000.00
184,800.00 4,620,000.00
8,000.00 1,456,000.00
35,000.00 70,000.00
Jumlah : 19,896,000.00
Overhead & keuntungan 10% : 1,989,600.00
Jumlah : 21,885,600.00
Jumlah & pembulatan per bulan : 21,885,600.00
Jumlah : 174,602,580.00
Overhead & keuntungan 10% : 17,460,258.00
76,594,735.80 76,594,735.80
20,425,262.00 20,425,262.00
- -
Jumlah : 97,019,997.80
Overhead & keuntungan 10% : 9,701,999.78
Jumlah : 106,721,997.58
Jumlah & pembulatan : 106,721,900.00
350,000.00 350,000.00
A.2.2.1 Pek. Persiapan / HAL 86 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
5 6 7
89,320.00 31,262.00
Jumlah : 381,262.00
Overhead & keuntungan 10% : 38,126.20
Jumlah : 419,388.20
Jumlah & pembulatan : 419,300.00
875.00 175,000.00
8,750.00 8,750.00
Jumlah : 183,750.00
Overhead & keuntungan 10% : 18,375.00
Jumlah : 202,125.00
Jumlah & pembulatan : 202,100.00
3,500,000.00 3,500,000.00
850.00 367,200.00
Jumlah : 3,867,200.00
Overhead & keuntungan 10% : 386,720.00
Jumlah : 4,253,920.00
Jumlah & pembulatan : 4,253,900.00
150,000.00 15,000,000.00
2,500.00 750,000.00
45,000.00 135,000.00
Jumlah : 15,885,000.00
Overhead & keuntungan 10% : 1,588,500.00
Jumlah : 17,473,500.00
Jumlah & pembulatan : 17,473,500.00
5 6 7
920,720.91
89,320.00 59,522.85
137,445.00 45,741.70
157,850.00 5,051.20
157,850.00 10,481.24
791,839.97 63,347.20
Jumlah per m' : 184,144.18
15,846,354.64
1,325,075.40 4,992,884.11
14,167.34 10,853,470.53
90,891,770.14
1,325,075.40 49,690,327.50
14,167.34 30,176,340.64
183,751.70 11,025,102.00
Jumlah : 113,914,573.23
Overhead & keuntungan 10% : 11,391,457.32
Jumlah : 125,306,030.55
Jumlah & pembulatan : 125,306,000.00
59,325.22
59,325.22 59,325.22
11,246.62
89,320.00 3,751.44
137,445.00 549.78
157,850.00 315.70
157,850.00 6,629.70
Jumlah 70,571.84
Overhead & keuntungan 10% : 7,057.18
Jumlah : 77,629.03
Jumlah & pembulatan : 77,600.00
40,425,000.00 40,425,000.00
539,442.20 539,442.20
Jumlah : 40,964,442.20
Overhead & keuntungan 10% : 4,096,444.22
Jumlah : 45,060,886.42
Jumlah & pembulatan : 45,060,800.00
70,936.25 4,185,238.75
A.2.2.1 Pek. Persiapan / HAL 88 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
5 6 7
70,936.25 283,745.00
419,830.98 37,784,788.40
85,746.22 25,295,134.78
411,220.93 37,009,883.54
38,250,000.00 153,000,000.00
Jumlah : 257,558,790.48
Overhead & keuntungan 10% : 25,755,879.05
Jumlah : 283,314,669.52
Jumlah & pembulatan : 283,314,600.00
Tenaga Kerja
Pekerja 0.750 org/hr
Mandor 0.025 org/hr
Tenaga Kerja
Pekerja 0.900 org/hr
Mandor 0.045 org/hr
Tenaga Kerja
Pekerja 1.050 org/hr
Mandor 0.067 org/hr
Tenaga Kerja
Pekerja 1.000 org/hr
Mandor 0.032 org/hr
Tenaga Kerja
Pekerja 1.500 org/hr
Mandor 0.060 org/hr
Tenaga Kerja
Pekerja 1.200 org/hr
Mandor 0.045 org/hr
Tenaga Kerja
Pekerja 0.050 org/hr
Mandor 0.005 org/hr
Tenaga Kerja
Pekerja 0.330 org/hr
Mandor 0.010 org/hr
Tenaga Kerja
Pekerja 0.500 org/hr
Mandor 0.050 org/hr
Bahan
Pasir urug 1.200 m³
Tenaga Kerja
Pekerja 0.300 org/hr
Mandor 0.010 org/hr
Bahan
A.2.3.1 Als-Pek.Tanah / HAL 92 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KODE
NO. URAIAN PEKERJAAN KOEF SATUAN
ANALISA
1 2 3 4
Bahan
Kapur Padam 0.248 m³
Pasir pasang 0.400 m³
Tanah liat 1.240 m³
Tenaga Kerja
Pekerja 0.800 org/hr
Tukang Gali 0.400 org/hr
Kepala Tukang 0.040 org/hr
Mandor 0.080 org/hr
Bahan
Ijuk 6.000 kg
Tenaga Kerja
Pekerja 0.150 org/hr
Mandor 0.015 org/hr
Bahan
Sirtu 1.20 m³
Bahan
Cerucuk Ø 8-10 Cm Panjang 4m' 1.000 Bh
Papan Kepala Tiang kayu Kamper Medan 0.002 m³
Paku 0.100 Kg
Alat
Excavator 0.010 Jam
Tenaga Kerja
Pekerja 0.050 org/hr
Mandor 0.010 org/hr
Bahan
Anti rayap 1.000 m2
Tenaga Kerja
Pekerja 0.107 hari
Mandor 0.018 hari
Bahan
Styrofoam t = 2.6 cm 0.030 m3
Tenaga Kerja
Tukang 0.026 hari
Pekerja 0.052 hari
Mandor 0.005 hari
5 A.2.3.1a.5 1 m2 Pemasangan 1 m² Lapisan Geotekstil non waven tebal 5 mm untuk bidang resa
Bahan
Lapisan Geotextile 1.1000 M²
Alat Bantu 1.0000 Ls
Tenaga Kerja
Pekerja 0.0400 org/hr
Mandor 0.0050 org/hr
A.2.3.1a.5 1 m2 Pemasangan 1 m² Lapisan Geotekstil non waven tebal 5 mm untuk bidang resa
5 6 7
Rp 89,320.00 Rp 66,990.00
Rp 157,850.00 Rp 3,946.25
Jumlah : Rp 70,936.25
Overhead & keuntungan 10% : Rp 7,093.63
Jumlah : Rp 78,029.88
Dibulatkan : Rp 78,030.00
Rp 89,320.00 Rp 80,388.00
Rp 157,850.00 Rp 7,103.25
Jumlah : Rp 87,491.25
Overhead & keuntungan 10% : Rp 8,749.13
Jumlah : Rp 96,240.38
Dibulatkan : Rp 96,200.00
Rp 89,320.00 Rp 93,786.00
Rp 157,850.00 Rp 10,575.95
Jumlah : Rp 104,361.95
Overhead & keuntungan 10% : Rp 10,436.20
Jumlah : Rp 114,798.15
Dibulatkan : Rp 114,800.00
Rp 89,320.00 Rp 89,320.00
Rp 157,850.00 Rp 5,051.20
Jumlah : Rp 94,371.20
Overhead & keuntungan 10% : Rp 9,437.12
Jumlah : Rp 103,808.32
Dibulatkan : Rp 103,800.00
Rp 89,320.00 Rp 133,980.00
Rp 157,850.00 Rp 9,471.00
Jumlah : Rp 143,451.00
Overhead & keuntungan 10% : Rp 14,345.10
Jumlah : Rp 157,796.10
Dibulatkan : Rp 157,800.00
5 6 7
Rp 89,320.00 Rp 107,184.00
Rp 157,850.00 Rp 7,103.25
Jumlah : Rp 114,287.25
Overhead & keuntungan 10% : Rp 11,428.73
Jumlah : Rp 125,715.98
Dibulatkan : Rp 125,700.00
5 6 7
Rp 89,320.00 Rp 4,466.00
Rp 157,850.00 Rp 789.25
Jumlah : Rp 5,255.25
Overhead & keuntungan 10% : Rp 525.53
Jumlah : Rp 5,780.78
Dibulatkan : Rp 5,800.00
Rp 89,320.00 Rp 29,475.60
Rp 157,850.00 Rp 1,578.50
Jumlah : Rp 31,054.10
Overhead & keuntungan 10% : Rp 3,105.41
Jumlah : Rp 34,159.51
Dibulatkan : Rp 34,200.00
Rp 89,320.00 Rp 44,660.00
Rp 157,850.00 Rp 7,892.50
Jumlah : Rp 52,552.50
Overhead & keuntungan 10% : Rp 5,255.25
Jumlah : Rp 57,807.75
Dibulatkan : Rp 57,800.00
Rp 89,320.00 Rp 44,660.00
Rp 157,850.00 Rp 7,892.50
Jumlah : Rp 52,552.50
Overhead & keuntungan 10% : Rp 5,255.25
Jumlah : Rp 57,807.75
Dibulatkan : Rp 57,800.00
Rp 145,728.00
Rp 121,440.00 Rp 145,728.00
Rp 28,374.50
Rp 89,320.00 Rp 26,796.00
Rp 157,850.00 Rp 1,578.50
Jumlah : Rp 174,102.50
Overhead & keuntungan 10% : Rp 17,410.25
Jumlah : Rp 191,512.75
Dibulatkan : Rp 191,500.00
Rp 160,040.00
A.2.3.1 Als-Pek.Tanah / HAL 100 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
5 6 7
Rp 70,000.00 Rp 9,450.00
Rp 175,450.00 Rp 70,180.00
Rp 85,000.00 Rp 80,410.00
Rp 145,376.00
Rp 89,320.00 Rp 71,456.00
Rp 137,445.00 Rp 54,978.00
Rp 157,850.00 Rp 6,314.00
Rp 157,850.00 Rp 12,628.00
Jumlah : Rp 305,416.00
Overhead & keuntungan 10% : Rp 30,541.60
Jumlah : Rp 335,957.60
Dibulatkan : Rp 336,000.00
5 6 7
Rp 161,940.00
Rp 70,000.00 Rp 17,360.00
Rp 175,450.00 Rp 70,180.00
Rp 60,000.00 Rp 74,400.00
Rp 145,376.00
Rp 89,320.00 Rp 71,456.00
Rp 137,445.00 Rp 54,978.00
Rp 157,850.00 Rp 6,314.00
Rp 157,850.00 Rp 12,628.00
Jumlah : Rp 307,316.00
Overhead & keuntungan 10% : Rp 30,731.60
Jumlah : Rp 338,047.60
Dibulatkan : Rp 338,000.00
Rp 154,761.42
Rp 25,793.57 Rp 154,761.42
Rp 15,765.75
Rp 89,320.00 Rp 13,398.00
Rp 157,850.00 Rp 2,367.75
Jumlah : Rp 170,527.17
Overhead & keuntungan 10% : Rp 17,052.72
Jumlah : Rp 187,579.89
Dibulatkan : Rp 187,600.00
Rp 182,160.00
Rp 151,800.00 Rp 182,160.00
Rp 26,276.25
Rp 89,320.00 Rp 22,330.00
Rp 157,850.00 Rp 3,946.25
Jumlah : Rp 208,436.25
Overhead & keuntungan 10% : Rp 20,843.63
Jumlah : Rp 229,279.88
Dibulatkan : Rp 229,300.00
Rp 89,320.00 Rp 53,592.00
Rp 157,850.00 Rp 4,735.50
Jumlah : Rp 58,327.50
Overhead & keuntungan 10% : Rp 5,832.75
Jumlah : Rp 64,160.25
Dibulatkan : Rp 64,200.00
Rp 89,320.00 Rp 98,252.00
Rp 157,850.00 Rp 10,418.10
Jumlah : Rp 108,670.10
A.2.3.1 Als-Pek.Tanah / HAL 102 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
5 6 7
5 6 7
Rp 39,347.00
Rp 37,510.00 Rp 37,510.00
Rp - Rp -
Rp 18,370.00 Rp 1,837.00
Rp 6,249.77
Rp 624,977.30 Rp 6,249.77
Rp 6,044.50
Rp 89,320.00 Rp 4,466.00
Rp 157,850.00 Rp 1,578.50
Jumlah : Rp 51,641.27
Overhead & keuntungan 10% : Rp 5,164.13
Jumlah : Rp 56,805.40
Dibulatkan : Rp 56,800.00
Rp 17,500.00
Rp 17,500.00 Rp 17,500.00
Rp 12,333.69
Rp 89,320.00 Rp 9,527.47
Rp 157,850.00 Rp 2,806.22
Jumlah : Rp 29,833.69
Overhead & keuntungan 10% : Rp 2,983.37
Jumlah : Rp 32,817.06
Dibulatkan : Rp 32,800.00
Rp 11,875.80
Rp 393,760.00 Rp 11,875.80
Rp 9,039.03
137,445.00 Rp 3,573.57
Rp 89,320.00 Rp 4,644.64
Rp 157,850.00 Rp 820.82
Jumlah : Rp 20,914.83
Overhead & keuntungan 10% : Rp 2,091.48
Jumlah : Rp 23,006.31
Dibulatkan : Rp 23,000.00
Rp 287,387.00
Rp 125,000.00 Rp 175,000.00
Rp 66,110.00 Rp 112,387.00
Rp 69,747.94
Rp 404,666.92 Rp 32,373.35
Rp 467,182.34 Rp 37,374.59
Rp 4,258.10
Rp 89,320.00 Rp 2,679.60
Rp 157,850.00 Rp 1,578.50
Jumlah : Rp 361,393.04
Overhead & keuntungan 10% : Rp 36,139.30
A.2.3.1 Als-Pek.Tanah / HAL 104 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
5 6 7
Jumlah : Rp 397,532.34
Dibulatkan : Rp 397,500.00
6 TM.04.C 1 m³ Pemadatan tanah di lokasi pekerjaan (tanah menggunakan hasil galian setempat)
Alat berat ( Termasuk Operator )
Bulldozer 0.0200 jam
Vibrator roller 6-8 ton 0.0178 jam
Water Tanker 0.0078 jam
Tenaga Kerja
Pekerja 0.1422 jam
Mandor 0.0142 jam
TM.04.C 1 m³ Pemadatan tanah di lokasi pekerjaan (tanah menggunakan hasil galian setempat)
7 F.5a 1 m³ Timbunan tanah berikut Pemadatan tanah tiap 20 cm (Tanah dari luar)
F.5a 1 m³ Timbunan tanah berikut Pemadatan tanah tiap 20 cm (Tanah dari luar)
6 7 8
Rp 19,606.91
Rp 321,200.00 Rp 8,222.72
Rp 290,783.82 Rp 11,384.19
Rp 3,602.23
Rp 17,864.00 Rp 1,913.23
Rp 31,570.00 Rp 1,689.00
Jumlah : Rp 23,209.14
Overhead & keuntungan 10% : Rp 2,320.91
Jumlah : Rp 25,530.05
Dibulatkan : Rp 25,530.00
Rp 93,622.80
Rp 173,435.48 Rp 12,799.54
Rp 16,000.00 Rp 1,180.80
Rp 467,182.34 Rp 34,478.06
Rp 321,200.00 Rp 23,704.56
Rp 290,783.82 Rp 21,459.85
Rp 12,873.20
Rp 17,864.00 Rp 10,543.33
Rp 31,570.00 Rp 2,329.87
Jumlah : Rp 106,496.00
Overhead & keuntungan 10% : Rp 10,649.60
Jumlah : Rp 117,145.60
Dibulatkan : Rp 117,100.00
Rp 31,505.01
Rp 321,200.00 Rp 8,736.64
Rp 290,783.82 Rp 22,768.37
Rp 3,431.78
Rp 17,864.00 Rp 2,917.19
Rp 31,570.00 Rp 514.59
Jumlah : Rp 34,936.80
Overhead & keuntungan 10% : Rp 3,493.68
Jumlah : Rp 38,430.47
Dibulatkan : Rp 38,400.00
Rp 31,858.33
Rp 321,200.00 Rp 9,089.96
Rp 290,783.82 Rp 22,768.37
Rp 3,431.78
Rp 17,864.00 Rp 2,917.19
Rp 31,570.00 Rp 514.59
Jumlah : Rp 35,290.12
Overhead & keuntungan 10% : Rp 3,529.01
Jumlah : Rp 38,819.13
Dibulatkan : Rp 38,800.00
Rp 35,391.53
Rp 321,200.00 Rp 12,623.16
F Pek.Tanah (dg alat berat) / HAL 112 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
6 7 8
Rp 290,783.82 Rp 22,768.37
Rp 3,431.78
Rp 17,864.00 Rp 2,917.19
Rp 31,570.00 Rp 514.59
Jumlah : Rp 38,823.32
Overhead & keuntungan 10% : Rp 3,882.33
Jumlah : Rp 42,705.65
Dibulatkan : Rp 42,700.00
Rp 326,288.17
Rp 116,800.20 Rp 140,160.24
Rp 321,200.00 Rp 3,244.12
Rp 290,783.82 Rp 177,465.37
Rp 582,421.73 Rp 2,154.96
Rp 404,666.92 Rp 1,699.60
Rp 223,411.65 Rp 1,563.88
Rp 4,068.65
Rp 17,864.00 Rp 3,506.70
Rp 31,570.00 Rp 561.95
Jumlah : Rp 330,356.82
Overhead & keuntungan 10% : Rp 33,035.68
Jumlah : Rp 363,392.50
Dibulatkan : Rp 363,400.00
6 7 8
Rp 369,762.35
Rp 151,800.00 Rp 182,160.00
Rp 467,182.34 Rp 4,718.54
Rp 290,783.82 Rp 177,465.37
Rp 582,421.73 Rp 2,154.96
Rp 404,666.92 Rp 1,699.60
Rp 223,411.65 Rp 1,563.88
Rp 4,068.65
Rp 17,864.00 Rp 3,506.70
Rp 31,570.00 Rp 561.95
Jumlah : Rp 373,831.00
Overhead & keuntungan 10% : Rp 37,383.10
Jumlah : Rp 411,214.10
Dibulatkan : Rp 411,214.00
Rp 45,535.62
Rp 321,200.00 Rp 17,184.20
Rp 290,783.82 Rp 28,351.42
Rp 3,602.23
Rp 17,864.00 Rp 1,913.23
Rp 31,570.00 Rp 1,689.00
Jumlah : Rp 49,137.85
Overhead & keuntungan 10% : Rp 4,913.79
Jumlah : Rp 54,051.64
Dibulatkan : Rp 54,100.00
Rp 5,418.44
Rp 582,421.73 Rp 2,154.96
Rp 404,666.92 Rp 1,699.60
Rp 223,411.65 Rp 1,563.88
Rp 9,703.89
Rp 17,864.00 Rp 3,506.70
Rp 31,570.00 Rp 6,197.19
Jumlah : Rp 15,122.34
Overhead & keuntungan 10% : Rp 1,512.23
Jumlah : Rp 16,634.57
Dibulatkan : Rp 16,630.00
Rp 405,422.06
Rp 791,839.97 Rp 405,422.06
Rp 14,408.92
Rp 17,864.00 Rp 7,652.94
Rp 31,570.00 Rp 6,755.98
Jumlah : Rp 419,830.98
Overhead & keuntungan 10% : Rp 41,983.10
Jumlah : Rp 461,814.08
Dibulatkan : Rp 461,800.00
Rp 405,422.06
Rp 791,839.97 Rp 405,422.06
Rp 18,011.15
Rp 17,864.00 Rp 9,566.17
6 7 8
Rp 31,570.00 Rp 8,444.98
Jumlah : Rp 423,433.21
Overhead & keuntungan 10% : Rp 42,343.32
Jumlah : Rp 465,776.53
Dibulatkan : Rp 465,800.00
Rp 405,422.06
Rp 791,839.97 Rp 405,422.06
Rp 18,911.70
Rp 17,864.00 Rp 10,044.48
Rp 31,570.00 Rp 8,867.22
Jumlah : Rp 424,333.77
Overhead & keuntungan 10% : Rp 42,433.38
Jumlah : Rp 466,767.15
Dibulatkan : Rp 466,800.00
Rp 405,422.06
Rp 791,839.97 Rp 405,422.06
Rp 19,857.29
Rp 17,864.00 Rp 10,546.70
Rp 31,570.00 Rp 9,310.58
Jumlah : Rp 425,279.35
Overhead & keuntungan 10% : Rp 42,527.94
Jumlah : Rp 467,807.29
Dibulatkan : Rp 467,800.00
6 7 8
Rp 480,620.02
Rp 791,839.97 Rp 405,620.02
Rp 75,000.00 Rp 75,000.00
Rp 20,850.15
Rp 17,864.00 Rp 11,074.04
Rp 31,570.00 Rp 9,776.11
Rp 12,015.50 Rp 12,015.50 Rp 12,015.50
Jumlah : Rp 513,485.68
Overhead & keuntungan 10% : Rp 51,348.57
Jumlah : Rp 564,834.25
Dibulatkan : Rp 564,800.00
Rp 561,744.03
Rp 791,839.97 Rp 486,744.03
Rp 75,000.00 Rp 75,000.00
Rp 21,892.66
Rp 17,864.00 Rp 11,627.74
Rp 31,570.00 Rp 10,264.92
Rp 14,043.60 Rp 14,043.60 Rp 14,043.60
Jumlah : Rp 597,680.29
Overhead & keuntungan 10% : Rp 59,768.03
Jumlah : Rp 657,448.32
Dibulatkan : Rp 657,400.00
Rp 582,025.03
Rp 791,839.97 Rp 507,025.03
Rp 75,000.00 Rp 75,000.00
Rp 22,987.29
Rp 17,864.00 Rp 12,209.13
Rp 31,570.00 Rp 10,778.17
Rp 14,550.63 Rp 14,550.63 Rp 14,550.63
Jumlah : Rp 619,562.95
Overhead & keuntungan 10% : Rp 61,956.30
Jumlah : Rp 681,519.25
Dibulatkan : Rp 681,500.00
Rp 405,422.06
Rp 791,839.97 Rp 405,422.06
Rp 16,322.15
Rp 17,864.00 Rp 9,566.17
Rp 31,570.00 Rp 6,755.98
Jumlah : Rp 421,744.22
Overhead & keuntungan 10% : Rp 42,174.42
Jumlah : Rp 463,918.64
Dibulatkan : Rp 463,900.00
Rp 278,256.00
6 7 8
Rp 231,880.00 Rp 278,256.00
Rp 4,068.65
Rp 17,864.00 Rp 3,506.70
Rp 31,570.00 Rp 561.95
Jumlah : Rp 282,324.65
Overhead & keuntungan 10% : Rp 28,232.46
Jumlah : Rp 310,557.11
Dibulatkan : Rp 310,557.00
1 2 2 3
A.3.2.1 PEKERJAAN PONDASI
PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
1 1 m³ Pasang Pondasi Batu Belah 1 : 3
Bahan
Batu Belah 15 cm / 20 cm 1.2000 m³
PC/Semen 202.0000 Kg
Pasir pasang 0.4850 m³
Tenaga Kerja
Pekerja 1.5000 org/hr
Tukang Batu 0.7500 org/hr
Kepala Tukang 0.0750 org/hr
Mandor 0.0750 org/hr
1 2 2 3
5 1 m³ Pasang Pondasi Batu Belah 1 : 8
Bahan
Batu Belah 15 cm / 20 cm 1.2000 m³
PC/Semen 91.0000 Kg
Pasir pasang 0.5840 m³
Tenaga Kerja
Pekerja 1.5000 org/hr
Tukang Batu 0.7500 org/hr
Kepala Tukang 0.0750 org/hr
Mandor 0.0750 org/hr
1 2 2 3
6 6 1 m³ Pasang Pondasi Batu Belah 1 KP : 1PC : 2 PP
7 7 1 m³ Pasang Pondasi Batu Belah 1 PC : 3KP : 10 PP
8 8 1 m³ Pasang Pondasi Batu Belah 1/4 PC : 1KP : 4 PP
1 2 2 3
Mandor 0.1190 org/hr
665,545.65
261,140.00 313,368.00
1,322.20 267,084.40
175,450.00 85,093.25
620,120.60
261,140.00 313,368.00
1,322.20 215,518.60
175,450.00 91,234.00
588,632.00
261,140.00 313,368.00
1,322.20 179,819.20
175,450.00 95,444.80
566,492.85
261,140.00 313,368.00
1,322.20 154,697.40
175,450.00 98,427.45
536,151.00
261,140.00 313,368.00
1,322.20 120,320.20
175,450.00 102,462.80
365,830.08
261,140.00 313,368.00
121,440.00 52,462.08
135,585.45
89,320.00 69,669.60
137,445.00 53,603.55
157,850.00 6,156.15
157,850.00 6,156.15
Jumlah : 501,415.53
Overhead & keuntungan 10% : 50,141.55
Jumlah : 551,557.08
Dibulatkan : 551,600.00
610,368.00
261,140.00 313,368.00
27,000.00 297,000.00
135,585.45
89,320.00 69,669.60
137,445.00 53,603.55
157,850.00 6,156.15
157,850.00 6,156.15
Jumlah : 745,953.45
Overhead & keuntungan 10% : 74,595.35
Jumlah : 820,548.80
Dibulatkan : 820,500.00
1,978,436.24
261,140.00 125,347.20
1,322.20 256,506.80
175,450.00 54,740.40
231,880.00 108,519.84
11,110.00 1,399,860.00
18,590.00 33,462.00
460,768.00
89,320.00 303,688.00
137,445.00 116,828.25
157,850.00 13,417.25
157,850.00 26,834.50
Jumlah : 2,439,204.24
Overhead & keuntungan 10% : 243,920.42
Jumlah : 2,683,124.66
Dibulatkan : 2,683,100.00
537,280.04
261,140.00 117,513.00
1,322.20 256,506.80
175,450.00 54,740.40
231,880.00 108,519.84
355,736.15
89,320.00 214,368.00
137,445.00 109,956.00
157,850.00 12,628.00
A.3.2.1.Pek.Pondasi / HAL 124 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
4 5 6
157,850.00 18,784.15
Jumlah : 893,016.19
Overhead & keuntungan 10% : 89,301.62
Jumlah : 982,317.81
Dibulatkan : 982,300.00
670,168.40
990.00 470,250.00
1,322.20 126,931.20
175,450.00 72,987.20
630,514.50
89,320.00 133,980.00
137,445.00 20,616.75
157,850.00 473,550.00
157,850.00 2,367.75
Jumlah : 1,300,682.90
Overhead & keuntungan 10% : 130,068.29
Jumlah : 1,430,751.19
Dibulatkan : 1,430,800.00
6 7 8
61,446.00
Rp 89,320.00 42,873.60
Rp 137,445.00 10,995.60
Rp 157,850.00 7,576.80
233,718.64
226,911.30 233,718.64
88,837.87
Rp 457,014.59 36,561.17
Rp 346,661.91 27,732.95
Rp 98,175.00 24,543.75
Jumlah : 384,002.51
Overhead & keuntungan 10% : 38,400.25
Jumlah : 422,402.76
Dibulatkan : 422,402.00
Rp 69,126.75
Rp 89,320.00 Rp 48,232.80
Rp 137,445.00 Rp 12,370.05
Rp 157,850.00 Rp 8,523.90
Rp 290,587.31
Rp 282,123.60 Rp 290,587.31
Rp 72,330.89
Rp 457,014.59 Rp 41,131.31
Rp 346,661.91 Rp 31,199.57
Jumlah : 432,044.94
Overhead & keuntungan 10% : 43,204.49
Jumlah : 475,249.44
Dibulatkan : 475,249.00
84,488.25
Rp 89,320.00 58,951.20
Rp 137,445.00 15,118.95
Rp 157,850.00 10,418.10
510,171.77
495,312.40 510,171.77
88,404.42
Rp 457,014.59 50,271.60
Rp 346,661.91 38,132.81
Jumlah : 683,064.44
Overhead & keuntungan 10% : 68,306.44
Jumlah : 751,370.88
Dibulatkan : 751,370.00
6 7 8
7,406.40
Rp 89,320.00 3,081.54
Rp 137,445.00 948.37
Rp 137,445.00 948.37
Rp 157,850.00 536.69
Rp 184,800.00 1,275.12
Rp 89,320.00 616.31
499,187.50
475,416.67 499,187.50
43,559.43
Rp 457,014.59 22,073.80
Rp 346,661.91 16,743.77
Rp 98,175.00 4,741.85
Jumlah : 550,153.33
Overhead & keuntungan 10% : 55,015.33
Jumlah : 605,168.66
Dibulatkan : 605,168.00
6 7 8
245,000.00 245,000.00
Jumlah : 245,000.00
Overhead & keuntungan 10% : 24,500.00
Jumlah : 269,500.00
Dibulatkan : 269,500.00
60,000.00 60,000.00
Jumlah : 60,000.00
Overhead & keuntungan 10% : 6,000.00
Jumlah : 66,000.00
Dibulatkan : 66,000.00
1 A. A.4.1..1.4 1 m³ Membuat beton mutu fc=7,4 Mpa (K 100), slum (12 ± 2) cm, w/c = 0.87
-
Bahan
Portland Cement 230.000 kg
Pasir Beton 893.000 kg
Kerikil (maksimum 30 mm) 1,027.000 kg
Air 200.000 Liter
Tenaga Kerja
Pekerja 1.200 org/hr
Tukang Batu 0.200 org/hr
Kepala Tukang 0.020 org/hr
Mandor 0.060 org/hr
A. A.4.1..1.4 1 m³ Membuat beton mutu fc=7,4 Mpa (K 100), slum (12 ± 2) cm, w/c = 0.87
4 A. A.4.1.1.8 1 m³ Membuat beton mutu fc=21.7 Mpa (K 250), slum (12 ± 2) cm, w/c = 0.56
Bahan
Portland Cement 384.000 kg
Pasir Beton 692.000 kg
A.A.4.1.1 Pek.Beton / HAL 132 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KODE
NO. URAIAN KOEF SATUAN
ANALISA
1 2 3 4 5
Kerikil (maksimum 30 mm) 1,039.000 kg
Air 215.000 Liter
Tenaga Kerja
Pekerja 1.650 org/hr
Tukang Batu 0.275 org/hr
Kepala Tukang 0.028 org/hr
Mandor 0.083 org/hr
A. A.4.1.1.8 1 m³ Membuat beton mutu fc=21.7 Mpa (K 250), slum (12 ± 2) cm, w/c = 0.56
A. A.4.1.1.9 1 m³ Membuat beton mutu fc=24.0 Mpa (K 275), slum (12 ± 2) cm, w/c = 0.53
6 A. A.4.1.1.10 1 m³ Membuat beton mutu fc=26.4 Mpa (K 300), slum (12 ± 2) cm, w/c = 0.52
-
Bahan
Portland Cement 413.000 kg
Pasir Beton 681.000 kg
Kerikil (maksimum 30 mm) 1,021.000 kg
Air 215.000 Liter
Tenaga Kerja
Pekerja 1.650 org/hr
Tukang Batu 0.275 org/hr
Kepala Tukang 0.028 org/hr
Mandor 0.083 org/hr
A. A.4.1.1.10 1 m³ Membuat beton mutu fc=26.4 Mpa (K 300), slum (12 ± 2) cm, w/c = 0.52
Pembesian tiap 10 kg
A. A.4.1.1.17 1 kg Pembesian tiap 1 kg
Bahan:
Pembesian tiap 10 kg
A. A.4.1.1.17 1 kg Pembesian tiap 1 kg
6 7 8
578,318.46
1,322.20 304,106.00
125.32 111,912.04
128.82 132,300.42
150.00 30,000.00
147,301.00
89,320.00 107,184.00
137,445.00 27,489.00
157,850.00 3,157.00
157,850.00 9,471.00
Jumlah : 725,619.46
Overhead & keuntungan 10% : 72,561.95
Jumlah : 798,181.00
640,434.74
1,322.20 375,002.36
125.32 102,608.17
128.82 130,574.20
150.00 32,250.00
202,696.73
89,320.00 147,378.00
137,445.00 37,797.38
157,850.00 4,419.80
157,850.00 13,101.55
Jumlah : 843,131.47
Overhead & keuntungan 10% : 84,313.15
Jumlah : 927,444.00
691,477.77
1,322.20 431,466.92
125.32 95,198.92
128.82 132,561.93
150.00 32,250.00
202,696.73
89,320.00 147,378.00
137,445.00 37,797.38
157,850.00 4,419.80
157,850.00 13,101.55
Jumlah : 894,174.49
Overhead & keuntungan 10% : 89,417.45
Jumlah : 983,591.00
760,543.52
1,322.20 507,724.80
125.32 86,722.43
A.A.4.1.1 Pek.Beton / HAL 149 DARI 616
HARGA STUAN SUB. Jumlah : JUMLAH
6 7 8
128.82 133,846.29
150.00 32,250.00
202,696.73
89,320.00 147,378.00
137,445.00 37,797.38
157,850.00 4,419.80
157,850.00 13,101.55
Jumlah : 963,240.24
Overhead & keuntungan 10% : 96,324.02
Jumlah : 1,059,564.27
Dibulatkan : Rp 1,059,500.00
6 7 8
786,954.66
1,322.20 536,813.20
125.32 85,719.86
128.82 132,171.60
150.00 32,250.00
202,696.73
89,320.00 147,378.00
137,445.00 37,797.38
157,850.00 4,419.80
157,850.00 13,101.55
Jumlah : 989,651.38
Overhead & keuntungan 10% : 98,965.14
Jumlah : 1,088,616.52
Dibulatkan : Rp 1,088,600.00
795,189.98
1,322.20 546,068.60
125.32 85,343.89
128.82 131,527.49
150.00 32,250.00
202,696.73
89,320.00 147,378.00
137,445.00 37,797.38
157,850.00 4,419.80
157,850.00 13,101.55
Jumlah : 997,886.71
Overhead & keuntungan 10% : 99,788.67
Jumlah : 1,097,675.38
Dibulatkan : Rp 1,097,600.00
6 7 8
1,286,791.00
1,153,020.00 1,210,671.00
71,500.00 71,500.00
5,775.00 4,620.00
38,284.40
89,320.00 22,330.00
137,445.00 13,744.50
157,850.00 1,578.50
157,850.00 631.40
Jumlah : 1,325,075.40
Overhead & keuntungan 10% : 132,507.54
Jumlah : 1,457,582.94
Dibulatkan : Rp 1,457,500.00
1,356,784.00
1,218,580.00 1,279,509.00
71,500.00 71,500.00
5,775.00 5,775.00
38,284.40
89,320.00 22,330.00
137,445.00 13,744.50
157,850.00 1,578.50
157,850.00 631.40
Jumlah : 1,395,068.40
Overhead & keuntungan 10% : 139,506.84
Jumlah : 1,534,575.24
Dibulatkan : Rp 1,534,500.00
1,151,425.00
1,023,000.00 1,074,150.00
71,500.00 71,500.00
5,775.00 5,775.00
38,284.40
89,320.00 22,330.00
137,445.00 13,744.50
157,850.00 1,578.50
157,850.00 631.40
Jumlah : 1,189,709.40
Overhead & keuntungan 10% : 118,970.94
Jumlah : 1,308,680.34
Dibulatkan : Rp 1,308,600.00
1,433,938.00
1,292,060.00 1,356,663.00
71,500.00 71,500.00
5,775.00 5,775.00
38,284.40
89,320.00 22,330.00
137,445.00 13,744.50
157,850.00 1,578.50
157,850.00 631.40
Jumlah : 1,472,222.40
Overhead & keuntungan 10% : 147,222.24
Jumlah : 1,619,444.64
A.A.4.1.1 Pek.Beton / HAL 152 DARI 616
HARGA STUAN SUB. Jumlah : JUMLAH
6 7 8
Dibulatkan : Rp 1,619,400.00
1,508,782.00
1,363,340.00 1,431,507.00
71,500.00 71,500.00
5,775.00 5,775.00
38,284.40
89,320.00 22,330.00
137,445.00 13,744.50
157,850.00 1,578.50
157,850.00 631.40
Jumlah : 1,547,066.40
Overhead & keuntungan 10% : 154,706.64
Jumlah : 1,701,773.04
Dibulatkan : Rp 1,701,700.00
1,551,748.00
1,404,260.00 1,474,473.00
71,500.00 71,500.00
5,775.00 5,775.00
38,284.40
89,320.00 22,330.00
137,445.00 13,744.50
157,850.00 1,578.50
157,850.00 631.40
Jumlah : 1,590,032.40
Overhead & keuntungan 10% : 159,003.24
Jumlah : 1,749,035.64
Dibulatkan : Rp 1,749,000.00
6 7 8
111,226.50
105,930.00 111,226.50
10,429.65
89,320.00 5,359.20
137,445.00 4,123.35
157,850.00 473.55
157,850.00 473.55
Jumlah : 121,656.15
Overhead & keuntungan 10% : 12,165.62
Jumlah : 133,821.77
Dibulatkan : Rp 133,800.00
145,414.50
138,490.00 145,414.50
12,325.78
89,320.00 6,252.40
137,445.00 4,810.58
157,850.00 631.40
157,850.00 631.40
Jumlah : 157,740.28
Overhead & keuntungan 10% : 15,774.03
Jumlah : 173,514.30
Dibulatkan : Rp 173,500.00
15,592.50
14,850.00 15,592.50
13,906.20
89,320.00 7,145.60
137,445.00 5,497.80
157,850.00 631.40
157,850.00 631.40
Jumlah : 29,498.70
Overhead & keuntungan 10% : 2,949.87
Jumlah : 32,448.57
Dibulatkan : Rp 32,400.00
124,063.50
11,550.00 121,275.00
18,590.00 2,788.50
17,609.90
89,320.00 6,252.40
137,445.00 9,621.15
157,850.00 1,104.95
157,850.00 631.40
Jumlah : 141,673.40
Overhead & keuntungan 10% : 14,167.34
Jumlah : 155,840.74
Dibulatkan : 155,800.00
Jumlah : Rp 15,580.00
46,107.12
A.A.4.1.1 Pek.Beton / HAL 154 DARI 616
HARGA STUAN SUB. Jumlah : JUMLAH
6 7 8
42,644.67 43,071.12
30,360.00 3,036.00
21,016.19
89,320.00 8,932.00
137,445.00 10,308.38
157,850.00 1,183.88
157,850.00 591.94
Jumlah : 67,123.30
Overhead & keuntungan 10% : 6,712.33
Jumlah : 73,835.63
Dibulatkan : Rp 73,800.00
61,660.58
58,044.13 58,624.58
30,360.00 3,036.00
21,016.19
89,320.00 8,932.00
137,445.00 10,308.38
157,850.00 1,183.88
157,850.00 591.94
Jumlah : 82,676.76
Overhead & keuntungan 10% : 8,267.68
Jumlah : 90,944.44
Dibulatkan : Rp 90,900.00
6 7 8
79,606.87
75,812.75 76,570.87
30,360.00 3,036.00
21,016.19
89,320.00 8,932.00
137,445.00 10,308.38
157,850.00 1,183.88
157,850.00 591.94
Jumlah : 100,623.06
Overhead & keuntungan 10% : 10,062.31
Jumlah : 110,685.37
Dibulatkan : Rp 110,600.00
122,677.99
118,457.42 119,641.99
30,360.00 3,036.00
21,016.19
89,320.00 8,932.00
137,445.00 10,308.38
157,850.00 1,183.88
157,850.00 591.94
Jumlah : 143,694.18
Overhead & keuntungan 10% : 14,369.42
Jumlah : 158,063.60
Dibulatkan : Rp 158,000.00
93,361.40
2,158,310.00 86,332.40
18,370.00 5,511.00
15,180.00 1,518.00
90,390.30
89,320.00 46,446.40
137,445.00 35,735.70
157,850.00 4,104.10
157,850.00 4,104.10
Jumlah : 183,751.70
Overhead & keuntungan 10% : 18,375.17
Jumlah : 202,126.87
Dibulatkan : Rp 202,100.00
104,152.95
2,158,310.00 97,123.95
18,370.00 5,511.00
15,180.00 1,518.00
90,390.30
89,320.00 46,446.40
137,445.00 35,735.70
157,850.00 4,104.10
157,850.00 4,104.10
Jumlah : 194,543.25
Overhead & keuntungan 10% : 19,454.33
Jumlah : 213,997.58
A.A.4.1.1 Pek.Beton / HAL 156 DARI 616
HARGA STUAN SUB. Jumlah : JUMLAH
6 7 8
Dibulatkan : Rp 213,900.00
254,238.05
2,158,310.00 86,332.40
18,370.00 7,348.00
15,180.00 3,036.00
2,158,310.00 32,374.65
143,220.00 50,127.00
37,510.00 75,020.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 368,964.20
Overhead & keuntungan 10% : 36,896.42
Jumlah : 405,860.62
Dibulatkan : Rp 405,800.00
6 7 8
132,311.03
2,158,310.00 43,166.20
18,370.00 7,348.00
15,180.00 3,036.00
2,158,310.00 16,187.33
143,220.00 25,063.50
37,510.00 37,510.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 247,037.18
Overhead & keuntungan 10% : 24,703.72
Jumlah : 271,740.89
Dibulatkan : Rp 271,700.00
145,150.78
2,158,310.00 43,166.20
18,370.00 7,348.00
15,180.00 3,036.00
2,158,310.00 16,187.33
216,590.00 37,903.25
37,510.00 37,510.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 259,876.93
Overhead & keuntungan 10% : 25,987.69
Jumlah : 285,864.62
Dibulatkan : Rp 285,800.00
260,712.98
2,158,310.00 86,332.40
18,370.00 7,348.00
15,180.00 3,036.00
2,158,310.00 38,849.58
143,220.00 50,127.00
37,510.00 75,020.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 375,439.13
Overhead & keuntungan 10% : 37,543.91
Jumlah : 412,983.04
Dibulatkan : Rp 412,900.00
135,548.49
6 7 8
2,158,310.00 43,166.20
18,370.00 7,348.00
15,180.00 3,036.00
2,158,310.00 19,424.79
143,220.00 25,063.50
37,510.00 37,510.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 250,274.64
Overhead & keuntungan 10% : 25,027.46
Jumlah : 275,302.10
Dibulatkan : Rp 275,300.00
148,388.24
2,158,310.00 43,166.20
18,370.00 7,348.00
15,180.00 3,036.00
2,158,310.00 19,424.79
216,590.00 37,903.25
37,510.00 37,510.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 263,114.39
Overhead & keuntungan 10% : 26,311.44
Jumlah : 289,425.83
Dibulatkan : Rp 289,400.00
6 7 8
323,674.45
143,220.00 5,728.80
18,370.00 7,348.00
15,180.00 3,036.00
2,158,310.00 32,374.65
143,220.00 50,127.00
37,510.00 225,060.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 438,400.60
Overhead & keuntungan 10% : 43,840.06
Jumlah : 482,240.66
Dibulatkan : Rp 482,200.00
181,336.38
216,590.00 4,331.80
18,370.00 7,348.00
15,180.00 3,036.00
2,158,310.00 16,187.33
216,590.00 37,903.25
37,510.00 112,530.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 296,062.53
Overhead & keuntungan 10% : 29,606.25
Jumlah : 325,668.78
Dibulatkan : Rp 325,600.00
255,440.30
143,220.00 4,296.60
18,370.00 7,348.00
15,180.00 3,036.00
2,158,310.00 43,166.20
143,220.00 25,063.50
37,510.00 112,530.00
15,000.00 60,000.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 370,166.45
Overhead & keuntungan 10% : 37,016.65
Jumlah : 407,183.10
Dibulatkan : Rp 407,100.00
6 7 8
175,443.90
143,220.00 2,148.30
18,370.00 7,348.00
15,180.00 3,036.00
2,158,310.00 21,583.10
143,220.00 25,063.50
37,510.00 56,265.00
15,000.00 60,000.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 290,170.05
Overhead & keuntungan 10% : 29,017.01
Jumlah : 319,187.06
Dibulatkan : Rp 319,100.00
171,443.25
143,220.00 4,296.60
18,370.00 7,348.00
15,180.00 2,277.00
2,158,310.00 32,374.65
143,220.00 50,127.00
37,510.00 75,020.00
114,726.15
89,320.00 58,951.20
137,445.00 45,356.85
157,850.00 5,209.05
157,850.00 5,209.05
Jumlah : 286,169.40
Overhead & keuntungan 10% : 28,616.94
Jumlah : 314,786.34
Dibulatkan : Rp 314,700.00
6 7 8
55,058.63
2,158,310.00 4,316.62
18,370.00 183.70
11,110.00 33,330.00
18,590.00 8,551.40
1,322.20 5,288.80
175,450.00 1,052.70
259,490.00 2,335.41
26,692.05
89,320.00 16,077.60
137,445.00 2,748.90
137,445.00 2,748.90
137,445.00 2,748.90
157,850.00 947.10
157,850.00 1,420.65
Jumlah : 81,750.68
Overhead & keuntungan 10% : 8,175.07
Jumlah : 89,925.75
Dibulatkan : Rp 89,900.00
60,511.33
2,158,310.00 6,474.93
18,370.00 367.40
11,110.00 39,996.00
18,590.00 929.50
1,322.20 7,272.10
175,450.00 1,579.05
259,490.00 3,892.35
44,081.35
89,320.00 26,528.04
137,445.00 4,535.69
137,445.00 4,535.69
137,445.00 4,535.69
157,850.00 1,578.50
157,850.00 2,367.75
Jumlah : 104,592.68
Overhead & keuntungan 10% : 10,459.27
Jumlah : 115,051.94
Dibulatkan : Rp 115,000.00
9,788.64
3,500.00 3,675.00
30,318.20 6,063.64
2,500.00 50.00
20,035.40
89,320.00 7,145.60
137,445.00 10,995.60
157,850.00 1,262.80
157,850.00 631.40
Jumlah : 29,824.04
Overhead & keuntungan 10% : 2,982.40
6 7 8
Jumlah : 32,806.44
Dibulatkan : Rp 32,800.00
6 7 8
119,443.50
11,110.00 116,655.00
18,590.00 2,788.50
A.A.4.1.1 Pek.Beton / HAL 164 DARI 616
HARGA STUAN SUB. Jumlah : JUMLAH
6 7 8
17,609.90
89,320.00 6,252.40
137,445.00 9,621.15
157,850.00 1,104.95
157,850.00 631.40
Jumlah : 137,053.40
Overhead & keuntungan 10% : 13,705.34
Jumlah : 150,758.74
Dibulatkan : 150,800.00
Jumlah : Rp 15,080.00
1 2 3 4
A.4.2.1 PEKERJAAN BESI DAN ALUMUNIUM
PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
1 1 kg Memasang besi profil
Bahan
Besi Profil 1.1500 kg
Tenaga Kerja
Pekerja 0.0600 org/hr
Tukang Las 0.0600 org/hr
Kepala Tukang 0.0060 org/hr
Mandor 0.0030 org/hr
1 2 3 4
4 1 m² Membuat Pintu Besi Plat Baja Tebal 2 mm Rangkap. Rangka Baja Siku
Bahan
Besi Siku L 30.30.3 15.0000 kg
Besi Plat Baja 32.8000 kg
Kawat Las 0.0500 kg
Tenaga Kerja
Pekerja 1.0500 org/hr
Tukang las 1.0500 org/hr
Kepala Tukang 0.1050 org/hr
Mandor 0.0520 org/hr
4 1 m² Membuat Pintu Besi Plat Baja Tebal 2 mm Rangkap. Rangka Baja Siku
1 2 3 4
5b 1 kg Memasang rangka kuda-kuda Baja C, UNP dan L ( Termasuk pengelasan dan pera
Harga terpasang :
Analisa no.4 Besi Baja C, UNP dan L 1.0000 kg
Analisa no.3 Perakitan 1.0000 kg
Analisa no.5 Pengelasan 1.0000 cm
5b 1 kg Memasang rangka kuda-kuda Baja C, UNP dan L ( Termasuk pengelasan dan pera
1 2 3 4
1 2 3 4
Mur baut M12mm 1.1000 bh
Tenaga Kerja
Pekerja 0.0100 org/hr
Tukang Las 0.0100 org/hr
Kepala Tukang 0.0010 org/hr
Mandor 0.0005 org/hr
1 2 3 4
5k 1 bh Mur baut M19/20mm
Bahan
Mur baut M19/20mm 1.1000 bh
Tenaga Kerja
Pekerja 0.0100 org/hr
Tukang Las 0.0100 org/hr
Kepala Tukang 0.0010 org/hr
Mandor 0.0005 org/hr
5n 1 bh Walter moor
1 2 3 4
6 1 m² Membuat Rangka Jendela Besi Scuare Tube (25 x 5) cm
1 2 3 4
1 2 3 4
Skrup Fixer 2.0000 buah
Sealant 0.0600 tube
Tenaga Kerja
Pekerja 0.0430 org/hr
Tukang khusus alumunium 0.0430 org/hr
Kepala Tukang 0.0043 org/hr
Mandor 0.0021 org/hr
1 2 3 4
1 2 3 4
1 2 3 4
20 1 m² Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, untuk par
Bahan
Hollow 4 x 4 cm t=2mm
Assesoris 3.50 m'
(perkuatan, las dll) 100% x rangka 1.00 LS
Tenaga Kerja
Tukang 0.25 org/hr
Pekerja 0.25 org/hr
Kepala Tukang 0.03 org/hr
Mandor 0.01 org/hr
1 2 3 4
20 1 m² Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, untuk pa
1 2 3 4
21b 1 m² Pasang rangka metal furing BMSys ( Untuk ceilling panel 600 x 1200 )
Bahan
Bracket PN-220 / PN-221 1.04 pc(s)
Suspension Rod 2400mm PN-409 0.26 pc(s)
Suspension Clip Adjuster PN-410 1.04 pc(s)
Wall Angel 3000mm PN-408 0.13 pc(s)
Main Tee 3600mm PN-400 0.22 pc(s)
Cross Tee 600mm PN-401 - pc(s)
Cross Tee 1200mm PN-401 1.44 pc(s)
Tenaga Kerja
Tukang 0.25 org/hr
A.4.2.1.Pek.Besi&Allm / HAL 179 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KOEF SATUAN
NO. URAIAN
1 2 3 4
Pekerja 0.25 org/hr
Kepala Tukang 0.03 org/hr
Mandor 0.01 org/hr
21b 1 m² Pasang rangka metal furing BMSys ( Untuk ceilling panel 600 x 1200 )
1 2 3 4
24 1 m1 Railling tangga dari pipa Stainles
1. Bahan : Hand railing pipa Stainlees steel Ø 2 1/2" 1.100 m1
Tiang railing pipa Stainlees steel Ø 2" 0.975 m1
Kisi-kisi railing pipa Stainlees steel Ø 1" 4.000 m1
Mur Ring 2.000 bh
Dop tutup dudukan tangga 2.000 bh
Dinabolt Ø 12 m 4.000 bh
Kawat las stainlees 0.750 kg
2. Upah : Upah pembuatan & pemasangan
Kepala Tukang 0.120 hari
Tukang Las 1.200 hari
Pekerja 1.200 hari
Mandor 0.060 hari
1 2 3 4
26 1 m1 Hand Railling tangga dari pipa stainless steel
27 1 Unit Partisi cubical toilet lengkap daun pintu berikut Accessories ( terpasang ) :
Partisi cubical lengkap : 1 unit
- Partisi Phenolic resin Board ex. D'CUBICS
tebal 12mm, (100% kedap air )
- Pintu Phenolic resin Board ex. D'CUBICS uk.
800x1800x12 mm,(100% kedap air )
- Door hardware stainless steel accessories
- Rangka frame alumunium N/A
- Kaki pedestal dan Screw conection stainless
steel
27 1 Unit Partisi cubical toilet lengkap daun pintu berikut Accessories ( terpasang ) :
1 2 3 4
1 2 3 4
Skrup 2.0000 buah
Tenaga Kerja
Pekerja 0.0323 org/hr
Tukang khusus alumunium 0.0323 org/hr
Kepala Tukang 0.0032 org/hr
Mandor 0.0016 org/hr
1 2 3 4
1 2 3 4
1 2 3 4
39 1 unit Type P.1 Kusen berikut daun pintu baja & accessories setara Bostinco
Terpasang Pintu baja single fire door finish cat anti karat,
Hardware setara Griff, Ukuran 2200 x 1000 setara
Bostinco ( Harga Terpasang ) 1.000 unit
39 1 unit Type P.1 Kusen berikut daun pintu baja & accessories setara Bostinco
40 1 unit Type P.2 Kusen berikut daun pintu baja & accessories setara Bostinco
Terpasang Pintu baja double fire door finish cat anti karat,
Hardware setara Griff, Ukuran 2200 x 1900 setara
Bostinco ( Harga Terpasang ) 1.000 unit
40 1 unit Type P.2 Kusen berikut daun pintu baja & accessories setara Bostinco
41 1 unit Tipe P.3 Pintu baja double fire door finish cat anti karat, Hardware setara Griff
Terpasang Pintu baja double steel door finish cat anti karat,
Hardware setara Griff, Ukuran 2100 x 1800 setara
Bostinco ( Harga Terpasang ) 1.000 unit
41 1 unit Tipe P.3 Pintu baja double fire door finish cat anti karat, Hardware setara Griff
42 1 unit Tipe P.4 Pintu baja double fire door finish cat anti karat, Hardware setara Griff
Terpasang Pintu baja double steel door finish cat anti karat,
Hardware setara Griff, Ukuran 2200 x 1300 setara
Bostinco ( Harga Terpasang ) 1.000 unit
42 1 unit Tipe P.4 Pintu baja double fire door finish cat anti karat, Hardware setara Griff
43 1 unit TipeP.5 Pintu baja single door finish cat anti karat, Hardware setara Griff, setara Bo
Terpasang Pintu single steel door finish cat anti karat,
Hardware setara Griff, Ukuran 900 x 2000 setara
Bostinco ( Harga Terpasang ) 1.000 unit
43 1 unit TipeP.5 Pintu baja single door finish cat anti karat, Hardware setara Griff, setara Bo
44 1 unit Tipe P.6 Kusen berikut Pintu baja double shaft steel door finish cat anti karat, Hard
Terpasang Pintu baja double shaft steel door finish cat anti
karat, Hardware setara Griff, Ukuran 1200 x 1200
setara Bostinco ( Harga Terpasang ) 1.000 unit
1 2 3 4
44 1 unit Tipe P.6 Kusen berikut Pintu baja double shaft steel door finish cat anti karat, Hard
45 1 unit Tipe P.7 Kusen berikut Pintu baja single shaft steel door finish cat anti karat, Hardw
Terpasang Pintu baja single shaft steel door finish cat anti
karat, Hardware setara Griff, Ukuran 120 x 800
setara Bostinco ( Harga Terpasang ) 1.000 unit
45 1 unit Tipe P.7 Kusen berikut Pintu baja single shaft steel door finish cat anti karat, Hardw
46 1 unit Tangga servis tipe 1 tipe dari pipa BSP finish cat duco
1. Bahan : Tiang pipa BSP Ø 2 1/2" 21.516 m1
Injakan pipa BSP Ø 1 1/5" 13.200 m1
Dop tutup dudukan 14.000 bh
Dinabolt Ø 12 m 28.000 bh
Kawat las 3.750 kg
2. Upah : Upah pembuatan & pemasangan
Pekerja 3.500 hari
Tukang Las 3.500 hari
Kepala Tukang 0.350 hari
Mandor 0.175 hari
1 2 3 4
47 1 unit Tangga servis tipe 3 tipe dari pipa BSP finish cat duco
1. Bahan : Tiang pipa BSP Ø 2 1/2" 16.060 m1
Injakan pipa BSP Ø 1 1/5" 11.200 m1
Dop tutup dudukan 12.000 bh
Dinabolt Ø 12 m 24.000 bh
Kawat las 3.750 kg
2. Upah : Upah pembuatan & pemasangan
Pekerja 2.000 hari
Tukang Las 2.000 hari
Kepala Tukang 0.200 hari
Mandor 0.100 hari
48 1 bh Manhole Pelat baja + rangka baja finish cat duco, ukuran 600x600
Bahan
Rangka siku 50x50x5mm 19.0159 kg
Plat baja t=3mm 8.4240 kg
Kawat las 0.750 kg
Dinabolt Ø 12 m 10.000 bh
Tenaga Kerja
Pekerja 1.5000 org/hr
Tukang las 1.5000 org/hr
Kepala Tukang 0.1500 org/hr
Mandor 0.0750 org/hr
49 1 m² Pemasangan 1 m2 pagar besi hollow 20x80x3,8 dan 20x80x2,2mm finish cat duco
Harga terpasang
A.4.2.1 2.a Hollow 80x100x2,5mm 39.56 kg
A.4.2.1 2.a Baja U 75x40x5x7 4.80 kg
A.4.2.1 2.a Hollow 20x80x2,2mm 290.14 kg
A.4.2.1 2.a Hollow 20x80x3.8mm 28.64 kg
A.4.2.1 5 Pengelasan 181.57 cm
A.4.7.1 Finishing cat duco 21.17 m2
A.4.2.1.Pek.Besi&Allm / HAL 189 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KOEF SATUAN
NO. URAIAN
1 2 3 4
6.72 m2
1.00 m2
49 1 m² Pemasangan 1 m2 pagar besi hollow 20x80x3,8 dan 20x80x2,2mm finish cat duco
50 1 unit Tipe P.21 Kusen berikut Pintu baja single shaft steel door finish cat anti karat, Hard
Terpasang Pintu baja single shaft steel door finish cat anti
karat, Hardware setara Griff, Ukuran 60 x 800
setara Bostinco ( Harga Terpasang ) 1.000 unit
50 1 unit Tipe P.21 Kusen berikut Pintu baja single shaft steel door finish cat anti karat, Hard
51 1 m² Pemasangan 1 m2 rangka besi hollow 50.50.2mm, modul 60 x 120 cm, untuk atap
Bahan
Hollow 5 x 5las
(perkuatan, cmdll)
t=2mm
30% x rangka 4.00 m'
1.00 LS
Tenaga Kerja
Tukang 0.25 org/hr
Pekerja 0.25 org/hr
Kepala Tukang 0.03 org/hr
Mandor 0.01 org/hr
1 2 3 4
52 1 m1 Railling pengaman curtain wall dari pipa Stainles
1. Bahan : Hand railing pipa Stainlees steel Ø 2 1/2" 1.100 m1
Tiang railing pipa Stainlees steel Ø 2 1/2" 0.600 m1
Mur Ring 2.000 bh
Dop tutup dudukan tangga 2.000 bh
Dinabolt Ø 12 m 4.000 bh
Kawat las stainlees 0.750 kg
2. Upah : Upah pembuatan & pemasangan
Kepala Tukang 0.120 hari
Tukang Las 1.200 hari
Pekerja 1.200 hari
Mandor 0.060 hari
15,306.50
13,310.00 15,306.50
15,026.55
89,320.00 5,359.20
137,445.00 8,246.70
157,850.00 947.10
157,850.00 473.55
Jumlah 30,333.05
Overhead & keuntungan 10% : 3,033.31
Jumlah : 33,366.36
Dibulatkan : 33,300.00
15,306.50
13,310.00 15,306.50
15,026.55
89,320.00 5,359.20
137,445.00 8,246.70
157,850.00 947.10
157,850.00 473.55
Jumlah 30,333.05
Overhead & keuntungan 10% : 3,033.31
Jumlah : 33,366.36
Dibulatkan : 33,300.00
15,306.50
13,310.00 15,306.50
15,026.55
89,320.00 5,359.20
137,445.00 8,246.70
157,850.00 947.10
157,850.00 473.55
Jumlah 30,333.05
Overhead & keuntungan 10% : 3,033.31
Jumlah : 33,366.36
Dibulatkan : 33,300.00
15,306.50
13,310.00 15,306.50
15,026.55
89,320.00 5,359.20
137,445.00 8,246.70
157,850.00 947.10
157,850.00 473.55
Jumlah 30,333.05
Overhead & keuntungan 10% : 3,033.31
Jumlah : 33,366.36
Dibulatkan : 33,300.00
10,000.00
6,500.00 6,500.00
35,000.00 3,500.00
23,623.60
89,320.00 8,932.00
137,445.00 13,744.50
157,850.00 157.85
157,850.00 789.25
76,000.00
95,000.00 76,000.00
Jumlah 109,623.60
Overhead & keuntungan 10% : 10,962.36
Jumlah : 120,585.96
Dibulatkan : 120,500.00
Dibulatkan per 1 kg : 1,205.00
670,736.00
15,510.00 232,650.00
13,310.00 436,568.00
30,360.00 1,518.00
262,885.70
89,320.00 93,786.00
137,445.00 144,317.25
157,850.00 16,574.25
157,850.00 8,208.20
Jumlah 933,621.70
Overhead & keuntungan 10% : 93,362.17
Jumlah : 1,026,983.87
Dibulatkan : 1,026,900.00
16,544.00
30,360.00 12,144.00
8,000.00 2,400.00
50,000.00 2,000.00
6,953.10
89,320.00 3,572.80
137,445.00 2,748.90
157,850.00 315.70
157,850.00 315.70
33,300.00 33,300.00
1,205.00 1,205.00
3,980.00 3,980.00
Jumlah 38,485.00
F (Termasuk pengelasan dan perakitan) Dibulatkan : 38,400.00
A.4.2.1.Pek.Besi&Allm / HAL 193 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
33,300.00 33,300.00
1,205.00 1,205.00
3,840.00 3,840.00
Jumlah 38,345.00
UNP dan L ( Termasuk pengelasan dan perakitan ) Dibulatkan : 38,300.00
33,300.00 33,300.00
1,205.00 1,205.00
3,830.00 3,830.00
Jumlah 38,335.00
Dibulatkan : 38,300.00
49,500.00
45,000.00 49,500.00
2,504.43
89,320.00 893.20
137,445.00 1,374.45
157,850.00 157.85
157,850.00 78.93
Jumlah 52,004.43
Overhead & keuntungan 10% : 5,200.44
Jumlah : 57,200.00
66,000.00
60,000.00 66,000.00
2,504.43
89,320.00 893.20
137,445.00 1,374.45
157,850.00 157.85
157,850.00 78.93
Jumlah 68,504.43
Overhead & keuntungan 10% : 6,850.44
Jumlah : 75,400.00
78,375.00
71,250.00 78,375.00
2,504.43
89,320.00 893.20
137,445.00 1,374.45
157,850.00 157.85
157,850.00 78.93
Jumlah 80,879.43
Overhead & keuntungan 10% : 8,087.94
Jumlah : 89,000.00
9,020.00
71,250.00 9,020.00
2,504.43
89,320.00 893.20
137,445.00 1,374.45
157,850.00 157.85
157,850.00 78.93
Jumlah 11,524.43
Overhead & keuntungan 10% : 1,152.44
Jumlah : 12,700.00
33,330.00
135,000.00 33,330.00
2,504.43
89,320.00 893.20
137,445.00 1,374.45
157,850.00 157.85
157,850.00 78.93
Jumlah 35,834.43
Overhead & keuntungan 10% : 3,583.44
Jumlah : 39,400.00
8,488.70
A.4.2.1.Pek.Besi&Allm / HAL 195 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
8,488.70
2,504.43
89,320.00 893.20
137,445.00 1,374.45
157,850.00 157.85
157,850.00 78.93
Jumlah 10,993.13
Overhead & keuntungan 10% : 1,099.31
Jumlah : 12,100.00
20,010.10
20,010.10
2,504.43
89,320.00 893.20
137,445.00 1,374.45
157,850.00 157.85
157,850.00 78.93
Jumlah 22,514.53
Overhead & keuntungan 10% : 2,251.45
Jumlah : 24,800.00
25,011.80
25,011.80
2,504.43
89,320.00 893.20
137,445.00 1,374.45
157,850.00 157.85
157,850.00 78.93
Jumlah 27,516.23
Overhead & keuntungan 10% : 2,751.62
Jumlah : 30,300.00
13,750.00
13,750.00
2,504.43
89,320.00 893.20
137,445.00 1,374.45
157,850.00 157.85
157,850.00 78.93
Jumlah 16,254.43
Overhead & keuntungan 10% : 1,625.44
Jumlah : 17,900.00
33,765.60
33,765.60
2,504.43
89,320.00 893.20
137,445.00 1,374.45
157,850.00 157.85
157,850.00 78.93
Jumlah 36,270.03
Overhead & keuntungan 10% : 3,627.00
Jumlah : 39,900.00
87,924.10
87,924.10
4,115.65
89,320.00 893.20
137,445.00 2,748.90
157,850.00 315.70
157,850.00 157.85
Jumlah 92,039.75
Overhead & keuntungan 10% : 9,203.98
Jumlah : 101,200.00
355,119.20
47,500.00 226,100.00
12,500.00 56,525.00
3,624.71 72,494.20
162,708.70
89,320.00 58,058.00
137,445.00 89,339.25
157,850.00 10,260.25
157,850.00 5,051.20
Jumlah 517,827.90
Overhead & keuntungan 10% : 51,782.79
Jumlah : 569,610.69
A.4.2.1.Pek.Besi&Allm / HAL 197 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
Dibulatkan : 569,600.00
325,000.00
325,000.00 325,000.00
110,194.70
89,320.00 39,300.80
137,445.00 60,475.80
157,850.00 6,945.40
157,850.00 3,472.70
Jumlah 435,194.70
Overhead & keuntungan 10% : 43,519.47
Jumlah : 478,714.17
Dibulatkan : 478,700.00
667,012.50
667,012.50 667,012.50
110,194.70
89,320.00 39,300.80
137,445.00 60,475.80
157,850.00 6,945.40
157,850.00 3,472.70
Jumlah 777,207.20
Overhead & keuntungan 10% : 77,720.72
Jumlah : 854,927.92
Dibulatkan : 854,900.00
264,110.00
264,110.00 264,110.00
130,361.00
89,320.00 7,145.60
137,445.00 109,956.00
157,850.00 12,628.00
157,850.00 631.40
Jumlah 394,471.00
Overhead & keuntungan 10% : 39,447.10
Jumlah : 433,918.10
Dibulatkan : 433,900.00
1,334,025.00
1,334,025.00 1,334,025.00
Jumlah 1,334,025.00
Overhead & keuntungan 10% : 133,402.50
Jumlah : 1,467,427.50
Dibulatkan : 1,467,400.00
246,819.09
220,000.00 242,000.00
1,500.00 3,000.00
30,318.20 1,819.09
10,761.14
89,320.00 3,840.76
137,445.00 5,910.14
157,850.00 678.76
157,850.00 331.49
Jumlah 257,580.23
Overhead & keuntungan 10% : 25,758.02
Jumlah : 283,338.25
Dibulatkan : 283,300.00
210,519.09
187,000.00 205,700.00
1,150,500.00
220,000.00 968,000.00
12,500.00 182,500.00
21,279.72
89,320.00 7,592.20
137,445.00 11,682.83
157,850.00 1,341.73
157,850.00 662.97
Jumlah 1,171,779.72
Overhead & keuntungan 10% : 117,177.97
Jumlah : 1,288,957.69
Dibulatkan : 1,288,900.00
1,032,435.91
220,000.00 968,000.00
12,500.00 56,250.00
30,318.20 8,185.91
21,484.93
89,320.00 7,592.20
137,445.00 11,682.83
157,850.00 1,420.65
157,850.00 789.25
Jumlah 1,053,920.84
Overhead & keuntungan 10% : 105,392.08
Jumlah : 1,159,312.92
Dibulatkan : 1,159,300.00
394,435.91
75,000.00 330,000.00
12,500.00 56,250.00
30,318.20 8,185.91
21,484.93
89,320.00 7,592.20
137,445.00 11,682.83
157,850.00 1,420.65
157,850.00 789.25
Jumlah 415,920.84
Overhead & keuntungan 10% : 41,592.08
Jumlah : 457,512.92
Dibulatkan : 457,500.00
75,000.00
75,000.00 75,000.00
87,733.80
89,320.00 31,262.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 2,841.30
Jumlah 162,733.80
Overhead & keuntungan 10% : 16,273.38
Jumlah : 179,007.18
Dibulatkan : 179,000.00
180,373.02
13,310.00 82,215.87
3,624.71 98,157.15
418,160.05
89,320.00 149,164.40
137,445.00 229,533.15
157,850.00 26,360.95
157,850.00 13,101.55
Jumlah 598,533.07
Overhead & keuntungan 10% : 59,853.31
Jumlah : 658,386.37
Dibulatkan : 658,300.00
76,860.49
12,500.00 13,750.00
3,624.71 40,270.53
13,310.00 22,839.96
25,044.25
89,320.00 8,932.00
137,445.00 13,744.50
157,850.00 1,578.50
157,850.00 789.25
Jumlah 101,904.74
Overhead & keuntungan 10% : 10,190.47
Jumlah : 112,095.21
Dibulatkan : 112,000.00
292,006.00
175,000.00 192,500.00
633.60 6,336.00
13,310.00 93,170.00
48,667.85
89,320.00 17,864.00
137,445.00 27,489.00
157,850.00 3,157.00
157,850.00 157.85
Jumlah 340,673.85
Overhead & keuntungan 10% : 34,067.39
Jumlah : 374,741.24
Dibulatkan : 374,700.00
2,274,735.76
2,117,500.00 2,223,375.00
42,988.00 644.82
2,669,260.00 50,715.94
48,667.85
89,320.00 17,864.00
137,445.00 27,489.00
157,850.00 3,157.00
157,850.00 157.85
Jumlah 2,323,403.61
Overhead & keuntungan 10% : 232,340.36
Jumlah : 2,555,743.97
Dibulatkan : 2,555,700.00
2,236,342.90
2,117,500.00 2,223,375.00
42,988.00 429.88
13,310.00 12,538.02
60,629.80
89,320.00 13,398.00
137,445.00 41,233.50
157,850.00 4,735.50
157,850.00 1,262.80
Jumlah 2,296,972.70
Overhead & keuntungan 10% : 229,697.27
Jumlah : 2,526,669.97
Dibulatkan : 2,526,600.00
55,203.98
60,573.33 34,526.80
60,573.33 13,459.39
111,026.67 4,219.01
30,213.33 966.83
83.60 2,031.95
62,216.00
137,445.00 34,361.25
89,320.00 22,330.00
157,850.00 3,946.25
157,850.00 1,578.50
Jumlah 117,419.98
Overhead & keuntungan 10% : 11,742.00
Jumlah : 129,161.98
Dibulatkan : 129,100.00
48,524.67
9,331.67 37,326.67
11,198.00 11,198.00
62,216.00
137,445.00 34,361.25
89,320.00 22,330.00
157,850.00 3,946.25
157,850.00 1,578.50
Jumlah 110,740.67
Overhead & keuntungan 10% : 11,074.07
Jumlah : 121,814.73
Dibulatkan : 121,800.00
43,030.87
1,320.00 1,372.80
5,573.33 1,463.00
4,253.33 4,423.47
28,013.33 3,734.18
49,133.33 10,917.43
7,480.00 -
14,666.67 21,120.00
62,216.00
137,445.00 34,361.25
A.4.2.1.Pek.Besi&Allm / HAL 205 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
89,320.00 22,330.00
157,850.00 3,946.25
157,850.00 1,578.50
Jumlah 105,246.87
Overhead & keuntungan 10% : 10,524.69
Jumlah : 115,771.56
Dibulatkan : 115,700.00
1,690,930.34
3,332,010.00 19,992.06
243,231.34 87,563.28
594,000.00 1,113,750.00
7,500.00 15,000.00
15,000.00 30,000.00
6,500.00 26,000.00
85,000.00 340,000.00
117,250.00 58,625.00
450,796.50
157,850.00 28,413.00
137,445.00 247,401.00
89,320.00 160,776.00
157,850.00 14,206.50
Jumlah 2,141,726.84
Overhead & keuntungan 10% : 214,172.68
Dibulatkan : 2,355,899.53
Dibulatkan : 2,355,800.00
Jumlah 1,094,549.45
Overhead & keuntungan 10% : 109,454.95
Jumlah : 1,204,004.40
Dibulatkan : 1,204,000.00
Jumlah 522,797.46
Overhead & keuntungan 10% : 52,279.75
Jumlah : 575,077.20
258,160.00 216,030.87
Dibulatkan : 791,100.00
Jumlah 514,696.08
Overhead & keuntungan 10% : 51,469.61
Jumlah : 566,165.68
Jumlah 5,969,920.00
Overhead & keuntungan 10% : 596,992.00
Jumlah : 6,566,912.00
u berikut Accessories ( terpasang ) : Dibulatkan : 6,566,900.00
300,288.34
280,750.80 294,788.34
27,500.00 5,500.00
47,786.20
89,320.00 893.20
137,445.00 13,744.50
157,850.00 31,570.00
157,850.00 1,578.50
72,799.32
30,333.05 72,799.32
Jumlah 420,873.86
Overhead & keuntungan 10% : 42,087.39
Jumlah : 462,961.25
Dibulatkan : 462,900.00
297,000.00 311,850.00
1,006,830.00 1,057,171.50
100,000.00 100,000.00
45,000.00 45,000.00
Jumlah 1,514,021.50
Overhead & keuntungan 10% : 151,402.15
Jumlah : 1,665,423.65
Dibulatkan : 1,665,400.00
Jumlah 1,373,689.00
Overhead & keuntungan 10% : 137,368.90
Jumlah : 1,511,057.90
Dibulatkan : 1,511,000.00
21,150.00
16,500.00 18,150.00
A.4.2.1.Pek.Besi&Allm / HAL 209 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
1,500.00 3,000.00
8,076.77
89,320.00 2,880.57
137,445.00 4,432.60
157,850.00 509.07
157,850.00 254.53
Jumlah 29,226.77
Overhead & keuntungan 10% : 2,922.68
Jumlah : 32,149.45
Dibulatkan : 32,100.00
Jumlah 950,263.03
Overhead & keuntungan 10% : 95,026.30
Jumlah : 1,045,289.34
Dibulatkan : 1,045,200.00
Jumlah 1,512,901.25
Overhead & keuntungan 10% : 151,290.13
Jumlah : 1,664,191.38
Dibulatkan : 1,664,100.00
Jumlah Rp 371,765.63
Overhead & keuntungan 10% : 37,176.56
Jumlah : Rp 408,942.19
Dibulatkan : Rp 408,900.00
Jumlah Rp 97,945.38
Overhead & keuntungan 10% : 9,794.54
Jumlah : Rp 107,739.91
Dibulatkan : Rp 107,700.00
Jumlah Rp 3,404,656.55
Overhead & keuntungan 10% : 340,465.65
Jumlah : Rp 3,745,122.20
Dibulatkan : Rp 3,745,100.00
A.4.2.1.Pek.Besi&Allm / HAL 211 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
Jumlah Rp 32,632,472.03
Overhead & keuntungan 10% : 3,263,247.20
Jumlah : Rp 35,895,719.24
Dibulatkan : Rp 35,895,700.00
Jumlah Rp 13,824,800.00
Overhead & keuntungan 10% : 1,382,480.00
Jumlah : Rp 15,207,280.00
Dibulatkan : Rp 15,207,200.00
Jumlah Rp 17,131,400.00
Overhead & keuntungan 10% : 1,713,140.00
Jumlah : Rp 18,844,540.00
Dibulatkan : Rp 18,844,500.00
- - Rp -
Jumlah Rp -
Overhead & keuntungan 10% : -
Jumlah : Rp -
sh cat anti karat, Hardware setara Griff Dibulatkan : Rp -
Jumlah Rp 17,952,200.00
Overhead & keuntungan 10% : 1,795,220.00
Jumlah : Rp 19,747,420.00
sh cat anti karat, Hardware setara Griff Dibulatkan : Rp 19,747,400.00
Jumlah Rp 17,952,200.00
Overhead & keuntungan 10% : 1,795,220.00
Jumlah : Rp 19,747,420.00
at anti karat, Hardware setara Griff, setara Bostinco Dibulatkan : Rp 19,747,400.00
le shaft steel door finish cat anti karat, Hardware setara Griff, setara Bostinco
Jumlah Rp 6,560,400.00
A.4.2.1.Pek.Besi&Allm / HAL 213 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
Overhead & keuntungan 10% : 656,040.00
Jumlah : Rp 7,216,440.00
le shaft steel door finish cat anti karat, Hardware setara Dibulatkan : Rp 7,216,400.00
e shaft steel door finish cat anti karat, Hardware setara Griff, setara Bostinco
Jumlah Rp 4,246,000.00
Overhead & keuntungan 10% : 424,600.00
Jumlah : Rp 4,670,600.00
e shaft steel door finish cat anti karat, Hardware setara G Dibulatkan : Rp 4,670,600.00
Jumlah 3,823,332.90
Overhead & keuntungan 10% : 382,333.29
Jumlah : 4,205,666.19
258,160.00 1,716,314.60
Dibulatkan : 5,921,900.00
Jumlah 2,838,322.31
Overhead & keuntungan 10% : 283,832.23
Jumlah : 3,122,154.54
258,160.00 1,313,856.79
Dibulatkan : 4,436,000.00
494,830.36
15,510.00 294,936.92
13,310.00 112,123.44
30,360.00 22,770.00
6,500.00 65,000.00
375,663.75
89,320.00 133,980.00
137,445.00 206,167.50
157,850.00 23,677.50
157,850.00 11,838.75
Jumlah 870,494.11
Overhead & keuntungan 10% : 87,049.41
Jumlah : 957,543.52
258,160.00 185,875.20
Dibulatkan : 1,143,400.00
192,000.00
24,000.00 96,000.00
96,000.00 96,000.00
62,216.00
137,445.00 34,361.25
89,320.00 22,330.00
157,850.00 3,946.25
157,850.00 1,578.50
Jumlah 254,216.00
Overhead & keuntungan 10% : 25,421.60
Jumlah : 279,637.60
1x50x50.2mm, modul 100 x 100 cm Dibulatkan : 279,600.00
gle shaft steel door finish cat anti karat, Hardware setara Griff, setara Bostinco
Jumlah Rp 2,547,600.00
Overhead & keuntungan 10% : 254,760.00
Jumlah : Rp 2,802,360.00
gle shaft steel door finish cat anti karat, Hardware setara Dibulatkan : Rp 2,802,300.00
Jumlah 799,277.55
Overhead & keuntungan 10% : 79,927.76
Jumlah : 879,205.31
Dibulatkan : 879,200.00
48,524.67
9,331.67 37,326.67
11,198.00 11,198.00
62,216.00
137,445.00 34,361.25
89,320.00 22,330.00
157,850.00 3,946.25
157,850.00 1,578.50
Jumlah 110,740.67
Overhead & keuntungan 10% : 11,074.07
Jumlah : 121,814.73
Dibulatkan : 121,800.00
Dibulatkan : 54,810.00
1 2 2 3
A.4.4.1 PEKERJAAN DINDING
PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
Bahan
Bata Merah kelas 1 140.000 Buah
PC 22.200 kg
PP 0.102 m³
Tenaga Kerja
Pekerja 0.600 org/hr
Tukang Batu 0.200 org/hr
Kepala Tukang 0.020 org/hr
Mandor 0.030 org/hr
8 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campura
Bahan
Bata Merah kelas 1 70.000 Buah
PC 14.370 kg
PP 0.040 m³
Tenaga Kerja
Pekerja 0.300 org/hr
Tukang Batu 0.100 org/hr
Kepala Tukang 0.010 org/hr
Mandor 0.015 org/hr
8 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campura
10 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campura
Bahan
Bata Merah kelas 1 70.000 Buah
PC 9.680 kg
PP 0.045 m³
Tenaga Kerja
Pekerja 0.300 org/hr
Tukang Batu 0.100 org/hr
1 2 2 3
Kepala Tukang 0.010 org/hr
Mandor 0.015 org/hr
10 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campura
1 2 2 3
25 1 m2 Pasangan Dinding Bata ringan tebal 7.5cm dengan mortar siap pakai
Bahan
Bata ringan 0.084 m3
Sement / mortal 4.612 kg
Tenaga Kerja
Pekerja 0.210 org/hr
Tukang Batu 0.090 org/hr
Kepala Tukang 0.009 org/hr
Mandor 0.009 org/hr
25 1 m2 Pasangan Dinding Bata ringan tebal 7.5cm dengan mortar siap pakai
26 1 m2 Pasangan Dinding Bata ringan tebal 10cm dengan mortar siap pakai
. Bahan
Bata ringan setara Hebel 0.110 m3
Sement / mortal 4.612 kg
Tenaga Kerja
Pekerja 0.350 org/hr
Tukang Batu 0.150 org/hr
Kepala Tukang 0.015 org/hr
Mandor 0.015 org/hr
26 1 m2 Pasangan Dinding Bata ringan tebal 10cm dengan mortar siap pakai
27 1 m3 Pasangan Dinding Bata ringan tebal 15cm dengan mortar siap pakai
Bahan
Bata ringan 0.165 m2
Sement / mortal 5.333 kg
Tenaga Kerja
Pekerja 0.350 org/hr
Tukang Batu 0.150 org/hr
Kepala Tukang 0.015 org/hr
Mandor 0.015 org/hr
27 1 m3 Pasangan Dinding Bata ringan tebal 15cm dengan mortar siap pakai
1 2 2 3
28 1 m² Panel Dinding fasade ex. Hebel
Bahan
Super panel dinding fasade t= 100mm ex. Hebel 1.100 m2
Sement / mortal 4.000 kg
alat bantu 1.000 lot
Tenaga Kerja
Pekerja 0.350 org/hr
Tukang Batu 0.150 org/hr
Kepala Tukang 0.015 org/hr
Mandor 0.015 org/hr
255,710.88
990.00 138,600.00
4,971.52 110,367.66
66,110.00 6,743.22
88,973.50
89,320.00 53,592.00
137,445.00 27,489.00
157,850.00 3,157.00
157,850.00 4,735.50
Jumlah : 344,684.38
Overhead & keuntungan 10% : 34,468.44
Jumlah : 379,152.81
kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1 Dibulatkan : 379,100.00
34,424.82
2,500.00 27,500.00
1,760.00 6,072.00
66,110.00 852.82
21,848.75
89,320.00 13,398.00
137,445.00 6,872.25
157,850.00 789.25
157,850.00 789.25
Jumlah : 56,273.57
Overhead & keuntungan 10% : 5,627.36
Jumlah : 61,900.93
Dibulatkan : 61,900.00
227,677.86
1,929,824.56 212,280.70
3,338.50 15,397.16
56,614.25
89,320.00 31,262.00
137,445.00 20,616.75
157,850.00 2,367.75
157,850.00 2,367.75
Jumlah : 284,292.11
Overhead & keuntungan 10% : 28,429.21
Jumlah : 312,721.33
Dibulatkan : 312,720.00
336,226.39
1,929,824.56 318,421.05
3,338.50 17,805.33
56,614.25
89,320.00 31,262.00
137,445.00 20,616.75
157,850.00 2,367.75
157,850.00 2,367.75
Jumlah : 392,840.64
Overhead & keuntungan 10% : 39,284.06
Jumlah : 432,124.70
Dibulatkan : 432,100.00
334,129.40
264,000.00 290,400.00
3,338.50 13,354.00
30,375.40 30,375.40
56,614.25
89,320.00 31,262.00
137,445.00 20,616.75
157,850.00 2,367.75
157,850.00 2,367.75
Jumlah : 390,743.65
Overhead & keuntungan 10% : 39,074.37
Jumlah : 429,818.02
Dibulatkan : 429,800.00
1 1 m² Plesteran 1 : 1 Tebal 15 mm
2 1 m² Plesteran 1 : 2 Tebal 15 mm
Bahan
Portland Cement 10.224 Kg
Pasir Pasang 0.020 m³
Tenaga Kerja
Pekerja 0.300 org/hr
Tukang Batu 0.150 org/hr
Kepala Tukang 0.015 org/hr
Mandor 0.015 org/hr
2 1 m² Plesteran 1 : 2 Tebal 15 mm
3 1 m² Plesteran 1 : 3 Tebal 15 mm
Bahan
Portland Cement 7.776 Kg
Pasir Pasang 0.023 m³
Tenaga Kerja
Pekerja 0.300 org/hr
Tukang Batu 0.150 org/hr
Kepala Tukang 0.015 org/hr
Mandor 0.015 org/hr
3 1 m² Plesteran 1 : 3 Tebal 15 mm
4 1 m² Plesteran 1 : 4 Tebal 15 mm
Bahan
Portland Cement 6.240 Kg
Pasir Pasang 0.024 m³
Tenaga Kerja
Pekerja 0.300 org/hr
Tukang Batu 0.150 org/hr
Kepala Tukang 0.015 org/hr
Mandor 0.015 org/hr
4 1 m² Plesteran 1 : 4 Tebal 15 mm
A.4.4.2.Pek.Plesteran / HAL 226 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
NO. URAIAN KOEF SATUAN
1 2 2 3
5 1 m² Plesteran 1 : 5 Tebal 15 mm
Bahan
Portland Cement 5.184 Kg
Pasir Pasang 0.026 m³
Tenaga Kerja
Pekerja 0.300 org/hr
Tukang Batu 0.150 org/hr
Kepala Tukang 0.015 org/hr
Mandor 0.015 org/hr
5 1 m² Plesteran 1 : 5 Tebal 15 mm
13 1 m² Plesteran 1 : 2 Tebal 20 mm
Bahan
Portland Cement 13.632 Kg
Pasir Pasang 0.027 m³
Tenaga Kerja
Pekerja 0.400 org/hr
Tukang Batu 0.200 org/hr
Kepala Tukang 0.020 org/hr
Mandor 0.022 org/hr
13 1 m² Plesteran 1 : 2 Tebal 20 mm
14 1 m² Plesteran 1 : 3 Tebal 20 mm
15 1 m² Plesteran 1 : 4 Tebal 20 mm
Bahan
Portland Cement 8.320 Kg
Pasir Pasang 0.032 m³
Tenaga Kerja
Pekerja 0.400 org/hr
Tukang Batu 0.200 org/hr
Kepala Tukang 0.020 org/hr
Mandor 0.022 org/hr
15 1 m² Plesteran 1 : 4 Tebal 20 mm
16 1 m² Plesteran 1 : 5 Tebal 20 mm
Bahan
Portland Cement 6.912 Kg
Pasir Pasang 0.035 m³
Tenaga Kerja
Pekerja 0.400 org/hr
Tukang Batu 0.200 org/hr
Kepala Tukang 0.020 org/hr
Mandor 0.022 org/hr
16 1 m² Plesteran 1 : 5 Tebal 20 mm
27 1 m² Finishing Acian
Bahan
Portland Cement 3.250 Kg
Tenaga Kerja
Pekerja 0.200 org/hr
Tukang Batu 0.100 org/hr
Kepala Tukang 0.010 org/hr
Mandor 0.010 org/hr
27 1 m² Finishing Acian
29 1 m² Finish Trowel
Bahan
Tenaga Kerja
A.4.4.2.Pek.Plesteran / HAL 230 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
NO. URAIAN KOEF SATUAN
1 2 2 3
Pekerja 0.050 org/hr
Tukang Batu 0.025 org/hr
Kepala Tukang 0.003 org/hr
Mandor 0.003 org/hr
29 1 m² Finish Trowel
23,306.59
1,322.20 20,499.39
175,450.00 2,807.20
49,712.25
81,200.00 24,360.00
137,445.00 20,616.75
157,850.00 2,367.75
157,850.00 2,367.75
Jumlah 73,018.84
Overhead & keuntungan 10% : 7,301.88
Jumlah : 80,320.72
Dibulatkan : 80,300.00
17,027.17
1,322.20 13,518.17
175,450.00 3,509.00
49,712.25
81,200.00 24,360.00
137,445.00 20,616.75
157,850.00 2,367.75
157,850.00 2,367.75
Jumlah 66,739.42
Overhead & keuntungan 10% : 6,673.94
Jumlah : 73,413.37
Dibulatkan : 73,400.00
14,316.78
1,322.20 10,281.43
175,450.00 4,035.35
49,712.25
81,200.00 24,360.00
137,445.00 20,616.75
157,850.00 2,367.75
157,850.00 2,367.75
Jumlah 64,029.03
Overhead & keuntungan 10% : 6,402.90
Jumlah : 70,431.93
Dibulatkan : 70,400.00
12,461.33
1,322.20 8,250.53
175,450.00 4,210.80
49,712.25
81,200.00 24,360.00
137,445.00 20,616.75
157,850.00 2,367.75
157,850.00 2,367.75
Jumlah 62,173.58
Overhead & keuntungan 10% : 6,217.36
Jumlah : 68,390.94
Dibulatkan : 68,300.00
A.4.4.2.Pek.Plesteran / HAL 232 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
4.00 5.00 6.00
11,415.98
1,322.20 6,854.28
175,450.00 4,561.70
49,712.25
81,200.00 24,360.00
137,445.00 20,616.75
157,850.00 2,367.75
157,850.00 2,367.75
Jumlah 61,128.23
Overhead & keuntungan 10% : 6,112.82
Jumlah : 67,241.06
Dibulatkan : 67,200.00
22,761.38
1,322.20 18,024.23
175,450.00 4,737.15
66,598.70
81,200.00 32,480.00
137,445.00 27,489.00
157,850.00 3,157.00
157,850.00 3,472.70
Jumlah 89,360.08
Overhead & keuntungan 10% : 8,936.01
Jumlah : 98,296.09
Dibulatkan : 98,200.00
19,147.52
1,322.20 13,708.57
175,450.00 5,438.95
66,598.70
81,200.00 32,480.00
137,445.00 27,489.00
157,850.00 3,157.00
157,850.00 3,472.70
Jumlah 85,746.22
Overhead & keuntungan 10% : 8,574.62
Jumlah : 94,320.84
Dibulatkan : 94,300.00
16,615.10
1,322.20 11,000.70
175,450.00 5,614.40
66,598.70
81,200.00 32,480.00
137,445.00 27,489.00
157,850.00 3,157.00
157,850.00 3,472.70
Jumlah 83,213.80
Overhead & keuntungan 10% : 8,321.38
Jumlah : 91,535.18
Dibulatkan : 91,500.00
15,279.80
1,322.20 9,139.05
175,450.00 6,140.75
66,598.70
81,200.00 32,480.00
137,445.00 27,489.00
157,850.00 3,157.00
157,850.00 3,472.70
Jumlah 81,878.50
Overhead & keuntungan 10% : 8,187.85
Jumlah : 90,066.35
Dibulatkan : 90,000.00
2,941.95
1,322.20 661.10
175,450.00 2,280.85
68,419.40
81,200.00 6,496.00
137,445.00 54,978.00
157,850.00 6,314.00
157,850.00 631.40
Jumlah 71,361.35
Overhead & keuntungan 10% : 7,136.14
Jumlah : 78,497.49
Dibulatkan : 78,400.00
4,109.40
1,322.20 4,109.40
25,013.98
81,200.00 12,180.00
137,445.00 10,308.38
157,850.00 1,262.80
157,850.00 1,262.80
Jumlah 29,123.37
Overhead & keuntungan 10% : 2,912.34
Jumlah : 32,035.71
Dibulatkan : 32,000.00
2,115.52
1,322.20 2,115.52
11,757.38
81,200.00 5,684.00
137,445.00 4,810.58
157,850.00 631.40
157,850.00 631.40
Jumlah 13,872.90
Overhead & keuntungan 10% : 1,387.29
Jumlah : 15,260.18
Dibulatkan : 15,200.00
10,488.15
1,322.20 8,382.75
175,450.00 2,105.40
49,712.25
81,200.00 24,360.00
137,445.00 20,616.75
157,850.00 2,367.75
157,850.00 2,367.75
Jumlah 60,200.40
Overhead & keuntungan 10% : 6,020.04
Jumlah : 66,220.44
Dibulatkan : 66,200.00
4,297.15
1,322.20 4,297.15
33,141.50
81,200.00 16,240.00
137,445.00 13,744.50
157,850.00 1,578.50
157,850.00 1,578.50
Jumlah 37,438.65
Overhead & keuntungan 10% : 3,743.87
Jumlah : 41,182.52
Dibulatkan : 41,100.00
49,122.86
2,186.25 41,642.86
3,740.00 7,480.00
40,440.31
81,200.00 20,300.00
137,445.00 17,180.63
157,850.00 1,973.13
157,850.00 986.56
Jumlah 89,563.17
Overhead & keuntungan 10% : 8,956.32
Jumlah : 98,519.49
Dibulatkan : 98,500.00
8,285.38
A.4.4.2.Pek.Plesteran / HAL 236 DARI 616
HARGA STUAN SUB. JUMLAH JUMLAH
4.00 5.00 6.00
81,200.00 4,060.00
137,445.00 3,436.13
157,850.00 394.63
157,850.00 394.63
Jumlah 8,285.38
Overhead & keuntungan 10% : 828.54
Jumlah : 9,113.91
Dibulatkan : 9,100.00
1 2 3 4
A.4.4.3 PEKERJAAN PENUTUP DINDING & LANTAI
PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
34 1 m² Pasang Lantai keramik Ukuran (33 x 33)cm polished setara Roman Gol. A
Bahan
Keramik uk. 33x33cm Polished/Glazed setara Roman 1.050 M2
PC 8.190 kg
PP 0.045 M³
Semen Warna 0.500 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
34 1 m² Pasang Lantai keramik Ukuran (33 x 33)cm polished setara Roman Gol. A
34a 1 m² Pasang Lantai keramik Ukuran (33 x 33)cm unpolished setara Roman Gol. C
Bahan
Keramik uk. 33x33cm Unpolished/Anti slip setara Roman 1.050 M2
PC 8.190 kg
PP 0.045 M³
Semen Warna 0.500 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
34a 1 m² Pasang Lantai keramik Ukuran (33 x 33)cm unpolished setara Roman Gol. C
35 1 m² Pasang Lantai Keramik Ukuran (30 x 30)cm polished setara Roman Gol. A
Bahan
Keramik uk. 30x30cm Polished/Glazed setara Roman 1.050 M2
PC 10.000 kg
PP 0.045 M³
Semen Warna 0.500 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
35 1 m² Pasang Lantai Keramik Ukuran (30 x 30)cm polished setara Roman Gol. A
35a 1 m² Pasang Lantai Keramik Ukuran (30 x 30) cm Unpolished/Anti slip setara Roman Gol. B
Bahan
Keramik uk. 30x30cm Unpolished/Anti slip 1.068 M2
PC 10.000 kg
PP 0.045 M³
Semen Warna 1.500 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
A.4.4.3.Pek.Penutup lt&Ddg / HAL 238 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KOEF SATUAN
NO. URAIAN
1 2 3 4
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
35a 1 m² Pasang Lantai Keramik Ukuran (30 x 30) cm Unpolished/Anti slip setara Roman Gol. B
36 1 m² Pasang Lantai Keramik Ukuran (20 x 20) cm setara Roman Gol. A
Bahan
Keramik uk. 20x20cm 1.050 m2
PC 10.400 kg
PP 0.045 M³
Semen Warna 0.500 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
1 2 3 4
36a 1 m² Pasang Lantai Keramik Ukuran (20 x 20) cm anti slip setara Roman Gol. B
Bahan
Keramik uk. 20x20cm anti slip 1.050 m2
PC 10.400 kg
PP 0.045 M³
Semen Warna 0.500 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
36a 1 m² Pasang Lantai Keramik Ukuran (20 x 20) cm anti slip setara Roman Gol. B
1 2 3 4
36a 1 m² Pasang Lantai Keramik Ukuran (20 x 20) cm Unpolised setara Roman Gol. B
Bahan
Keramik uk. 20x20cm Unpolised setara Roman Gol. B 1.050 m2
PC 10.400 kg
PP 0.045 M³
Semen Warna 0.500 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
36a 1 m² Pasang Lantai Keramik Ukuran (20 x 20) cm Unpolised setara Roman Gol. B
36b 1 m² Pasang Lantai keramik Ukuran (40 x 40) cm Polised Setara Roman Gol. A
Bahan
Keramik lantai 40 x 40 type Polised Gol. A 1.040 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.300 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
36b 1 m² Pasang Lantai keramik Ukuran (40 x 40) cm Polised Setara Roman Gol. A
36c 1 m² Pasang Lantai keramik Ukuran (40 x 40) cm Unpolised Setara Roman Gol. B
Bahan
Keramik lantai 40 x 40 type Unpolised Gol. B 1.040 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.300 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
36c 1 m² Pasang Lantai keramik Ukuran (40 x 40) cm Unpolised Setara Roman Gol. B
36d 1 m² Pasang Lantai keramik Ukuran (50 x 50) cm Polised Setara Roman Gol. A
Bahan
Keramik lantai 50 x 50 type Polised Gol. A 1.080 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.300 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
A.4.4.3.Pek.Penutup lt&Ddg / HAL 241 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KOEF SATUAN
NO. URAIAN
1 2 3 4
Mandor 0.035 0rg/hr
36d 1 m² Pasang Lantai keramik Ukuran (50 x 50) cm Polised Setara Roman Gol. A
36e 1 m² Pasang Lantai keramik Ukuran (60 x 60) cm Unpolised Setara Roman Gol. B
Bahan
Keramik lantai 50 x 50 type Unpolised Gol. B 1.080 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.300 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
36e 1 m² Pasang Lantai keramik Ukuran (60 x 60) cm Unpolised Setara Roman Gol. B
1 2 3 4
36f 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm setara Niro Granit Polished Bermotif
Bahan
Homogeneus 600 x 600 type Polished BERMOTIF 1.080 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.300 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
36f 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm setara Niro Granit Polished Bermotif
36g 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm setara Niro Granit Matte Bermotif
Bahan
Homogeneus 600 x 600 type Matte BERMOTIF 1.080 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.300 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
36g 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm setara Niro Granit Matte Bermotif
36h 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm setara Niro Granit Polished Polos
Bahan
Homogeneus 600 x 600 type Polished POLOS 1.080 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.300 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
36h 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm setara Niro Granit Polished Polos
36i 1 m² Pasang Lantai Homogenous Ukuran (40 x 60) cm setara Niro Granit
Bahan
Homogeneus 400 x 800 type Polished 1.020 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.200 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
A.4.4.3.Pek.Penutup lt&Ddg / HAL 243 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KOEF SATUAN
NO. URAIAN
1 2 3 4
Mandor 0.035 0rg/hr
36i 1 m² Pasang Lantai Homogenous Ukuran (40 x 60) cm setara Niro Granit
36j 1 m² Pasang Lantai Homogenous Ukuran (60 x 120) cm setara Niro Granit
Bahan
Homogeneus 600 x 1200 type Matte 1.080 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.200 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
36j 1 m² Pasang Lantai Homogenous Ukuran (60 x 120) cm setara Niro Granit
1 2 3 4
36k 1 m² Pasang Lantai Homogenous Ukuran (20 x 120) cm setara Niro Granit
Bahan
Homogeneus 200 x 1200 type Matte 1.080 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.200 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
36k 1 m² Pasang Lantai Homogenous Ukuran (20 x 120) cm setara Niro Granit
37 1 m² Pasang Lantai Keramik Ukuran (10 x 33) cm. polished setara Roman Gol. A
Bahan
Keramik uk. 10x33cm 33.000 m2
PC 9.800 kg
PP 0.045 M³
Semen Warna 4.370 kg
Tenaga Kerja
Pekerja 1.050 0rg/hr
Tukang Batu 0.525 0rg/hr
Kepala Tukang 0.053 0rg/hr
Mandor 0.053 0rg/hr
37 1 m² Pasang Lantai Keramik Ukuran (10 x 33) cm. polished setara Roman Gol. A
39 1 m' Pasang Plint Keramik Ukuran (10 x 20) cm polished setara Roman Gol. A
Bahan
Plint Keramik Artistik 5.300 buah
PC 1.140 kg
PP 0.003 M³
Semen Warna 0.025 kg
Tenaga Kerja
Pekerja 0.090 0rg/hr
Tukang Batu 0.090 0rg/hr
Kepala Tukang 0.009 0rg/hr
Mandor 0.005 0rg/hr
39 1 m' Pasang Plint Keramik Ukuran (10 x 20) cm polished setara Roman Gol. A
39a 1 m' Pasang Plint Keramik Ukuran (10 x 30) cm polished setara Roman Gol. A
Bahan
Plint Keramik 10 x 30 3.333 buah
PC 1.140 kg
PP 0.003 M³
Semen Warna 0.025 kg
Tenaga Kerja
Pekerja 0.090 0rg/hr
Tukang Batu 0.090 0rg/hr
Kepala Tukang 0.009 0rg/hr
Mandor 0.005 0rg/hr
A.4.4.3.Pek.Penutup lt&Ddg / HAL 245 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KOEF SATUAN
NO. URAIAN
1 2 3 4
39a 1 m' Pasang Plint Keramik Ukuran (10 x 30) cm polished setara Roman Gol. A
1 2 3 4
39b 1 m' Pasang Plint Keramik Ukuran (10 x 40) cm polished setara Roman Gol. A
Bahan
Plint Keramik 10 x 40 2.500 buah
PC 1.140 kg
PP 0.003 M³
Semen Warna 0.025 kg
Tenaga Kerja
Pekerja 0.090 0rg/hr
Tukang Batu 0.090 0rg/hr
Kepala Tukang 0.009 0rg/hr
Mandor 0.005 0rg/hr
39b 1 m' Pasang Plint Keramik Ukuran (10 x 40) cm polished setara Roman Gol. A
39c 1 m' Pasang Plint Keramik Ukuran (10 x 50) cm polished setara Roman Gol. A
Bahan
Plint Keramik 10 x 50 polished setara Roman Gol. A 1.667 buah
PC 1.140 kg
PP 0.003 M³
Semen Warna 0.025 kg
Tenaga Kerja
Pekerja 0.090 0rg/hr
Tukang Batu 0.090 0rg/hr
Kepala Tukang 0.009 0rg/hr
Mandor 0.005 0rg/hr
39c 1 m' Pasang Plint Keramik Ukuran (10 x 50) cm polished setara Roman Gol. A
1 2 3 4
43 1 m2 Pasang lantai Marmer slab cream Malaga Premium C1 Setara ex. Ujung Pandang
1 2 3 4
43a 1 m2 Pasang lantai Marmer Ukuran (60x60) cm Polised Setara ex. Ujung Pandang
Bahan
Marmer 60 x 60 type Polised 1.060 M2
PC 8.190 kg
PP 0.045 M³
Semen Warna 0.134 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
43a 1 m2 Pasang lantai Marmer Ukuran (60x60) cm Polised Setara ex. Ujung Pandang
43b 1 m2 Pasang lantai Granit macam-macam corakslab setara India
Bahan
Granit macam-macam corak slab Luar Negeri (Nero India) 1.060 M2
PC 8.190 kg
PP 0.045 M³
Semen Warna 0.650 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
43c 1 m² Pasang Lantai Homogenous Ukuran (100 x 100) cm polished Setara Niro granit
43d 1 m² Pasang Lantai Homogenous Ukuran (100 x 100) cm matte setara Niro Granit
Bahan
Homogeneus 1000 x 1000 type Polished matte 1.050 M2
PC 9.800 kg
PP 0.045 M³
Semen Warna 1.300 kg
Tenaga Kerja
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
A.4.4.3.Pek.Penutup lt&Ddg / HAL 249 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KOEF SATUAN
NO. URAIAN
1 2 3 4
Mandor 0.035 0rg/hr
43d 1 m² Pasang Lantai Homogenous Ukuran (100 x 100) cm matte setara Niro Granit
44 1 m² Pasang lantai karpet Heavy Duty
Bahan
Floc Carpet Heavy Duty 1.050 M²
Lem 0.350 kg
Tenaga Kerja
Pekerja 0.170 0rg/hr
Tukang 0.170 0rg/hr
Kepala Tukang 0.017 0rg/hr
Mandor 0.009 0rg/hr
1 2 3 4
1 2 3 4
PC 9.300 kg
PP 0.045 M³
Semen Warna 1.940 kg
Tenaga Kerja
Pekerja 0.900 0rg/hr
Tukang Batu 0.450 0rg/hr
Kepala Tukang 0.045 0rg/hr
Mandor 0.045 0rg/hr
54 1 m² Pasang Dinding Keramik Ukuran (20 x 20) cm polished setara Roman Gol. A
1 2 3 4
54a 1 m² Pasang Dinding Keramik Ukuran (20 x 25) cm polished setara Roman Gol. A
Bahan
Keramik Dinding 20 x 25 Gol. A 1.050 M2
PC 9.300 kg
PP 0.045 M³
Semen Warna 1.940 kg
Tenaga Kerja
Pekerja 0.900 0rg/hr
Tukang Batu 0.450 0rg/hr
Kepala Tukang 0.045 0rg/hr
Mandor 0.045 0rg/hr
54a 1 m² Pasang Dinding Keramik Ukuran (20 x 25) cm polished setara Roman Gol. A
54b 1 m² Pasang Dinding Keramik Ukuran (30 x 60) cm polished setara Roman Gol. A
Bahan
Keramik dinding 30 x 60 Gol. A 1.050 M2
PC 9.300 kg
PP 0.045 M³
Semen Warna 1.940 kg
Tenaga Kerja
Pekerja 0.900 0rg/hr
Tukang Batu 0.450 0rg/hr
Kepala Tukang 0.045 0rg/hr
Mandor 0.045 0rg/hr
54b 1 m² Pasang Dinding Keramik Ukuran (30 x 60) cm polished setara Roman Gol. A
54c 1 m² Pasang Dinding Keramik Ukuran (20 x 60 ) cm polished setara Roman Gol. B
Bahan
Keramik dinding 20 x 60 Gol. B 1.320 M2
PC 9.300 kg
PP 0.045 M³
Semen Warna 1.940 kg
Tenaga Kerja
Pekerja 0.900 0rg/hr
Tukang Batu 0.450 0rg/hr
Kepala Tukang 0.045 0rg/hr
Mandor 0.045 0rg/hr
54c 1 m² Pasang Dinding Keramik Ukuran (20 x 60 ) cm polished setara Roman Gol. B
1 2 3 4
Mandor 0.045 0rg/hr
1 2 3 4
54f 1 m² Pasang Dinding Homogenous Ukuran (60 x 120 ) cm setara Niro Granit
Bahan
Homogeneus 600 x 1200 type Matte 1.008 M2
PC 9.300 kg
PP 0.045 M³
Semen Warna 1.940 kg
Tenaga Kerja
Pekerja 0.900 0rg/hr
Tukang Batu 0.450 0rg/hr
Kepala Tukang 0.045 0rg/hr
Mandor 0.045 0rg/hr
54f 1 m² Pasang Dinding Homogenous Ukuran (60 x 120 ) cm setara Niro Granit
55 1 m' Pasang dinding Marmer Ukuran (slab ) setara Ujung Pandang
Bahan
Marmer slab Ujungpandang 1.060 M2
PC 12.440 kg
PP 0.025 M³
Semen Warna 0.650 kg
Tenaga Kerja
Pekerja 1.300 0rg/hr
Tukang Batu 0.650 0rg/hr
Kepala Tukang 0.065 0rg/hr
Mandor 0.065 0rg/hr
55a 1 m' Pasang dinding Marmer Ukuran (60x60) cm setara Ujung Pandang
55b 1 m' Pasang dinding Granit alam slab setara India
Bahan
Granit macam-macam corak slab Luar Negeri (Nero India) 1.060 M2
PC 12.440 kg
PP 0.025 M³
Semen Warna 0.650 kg
Tenaga Kerja
Pekerja 1.300 0rg/hr
Tukang Batu 0.650 0rg/hr
Kepala Tukang 0.065 0rg/hr
1 2 3 4
Mandor 0.065 0rg/hr
1 2 3 4
55c 1 m' Pasang Marmer tangga Ukuran (slab ) setara Ujung Pandang
Bahan
Marmer slab Ujungpandang 1.060 M2
PC 12.440 kg
PP 0.025 M³
Semen Warna 0.650 kg
Tenaga Kerja
Pekerja 1.950 0rg/hr
Tukang Batu 0.975 0rg/hr
Kepala Tukang 0.098 0rg/hr
Mandor 0.098 0rg/hr
55c 1 m' Pasang Marmer tangga Ukuran (slab ) setara Ujung Pandang
55c 1 m' Pasang step Marmer tangga Ukuran (slab ) setara Ujung Pandang (termasuk grooving dan b
Bahan
Marmer slab Ujungpandang 1.060 M2
PC 12.440 kg
PP 0.025 M³
Semen Warna 0.650 kg
Tenaga Kerja ( termasuk upah grooving dan bullnose )
Pekerja 3.900 0rg/hr
Tukang Batu 1.950 0rg/hr
Kepala Tukang 0.195 0rg/hr
Mandor 0.195 0rg/hr
55c 1 m' Pasang step Marmer tangga Ukuran (slab ) setara Ujung Pandang (termasuk grooving dan b
56 1 m2 Pasang dinding bata pelapis ukuran (3x7x24) cm
Bahan
Bata pelapis ukuran (3x7x24) cm 63.000 buah
PC 12.440 kg
PP 0.025 M³
Semen Warna 2.750 kg
Tenaga Kerja
Pekerja 1.000 0rg/hr
Tukang Batu 0.500 0rg/hr
Kepala Tukang 0.050 0rg/hr
Mandor 0.050 0rg/hr
1 2 3 4
59 1 m2 Pasang Vinyl setara Forbo Sarlon Sparkling 15db t=2,6mm (Harga terpasang)
Bahan
Vinyl Forbo Sarlon Sparkling 15db t=2,6mm (Harga
1.050 M2
terpasang)
Instalasi Vinyl (Harga terpasang) 1.050 M2
Pemerataan lantai 1.050 M2
59 1 m2 Pasang Vinyl setara Forbo Sarlon Sparkling 15db t=2,6mm (Harga terpasang)
60 1 m2 Pasang wall paper, lebar 50cm
Bahan
1 2 3 4
Wall paper 1.200 M'
Lem 0.200 kg
Tenaga Kerja
Pekerja 0.020 0rg/hr
Tukang Batu 0.200 0rg/hr
Kepala Tukang 0.020 0rg/hr
Mandor 0.003 0rg/hr
1 2 3 4
63 1 m' Pasang plin plin kayu Kamper Samarinda ukuran ( t=2cm x l=10 )
Bahan
Papan kayu Kamper Samarinda 0.003 M3
Sekrup+piser 0.050 kg
Tenaga Kerja
Pekerja 0.120 0rg/hr
Tukang Batu 0.120 0rg/hr
Kepala Tukang 0.012 0rg/hr
Mandor 0.006 0rg/hr
1 2 3 4
Pasir beton 0.1000 m³
Peralatan 1.0000 Ls
Tenaga Kerja
Pekerja 0.2500 org/hr
Tukang Batu 0.5000 org/hr
Kepala Tukang Batu 0.0250 org/hr
Mandor 0.0030 org/hr
1 2 3 4
1 2 3 4
1 2 3 4
70 1 m' Pasang Stair nozing Keramik Ukuran (10 x 20) cm setara Roman
Bahan
Stair nozing Keramik Ukuran (10 x 20) cm setara Roman 5.000 buah
PC 1.140 kg
PP 0.003 M³
Semen Warna 0.025 kg
Tenaga Kerja
Pekerja 0.090 0rg/hr
Tukang Batu 0.090 0rg/hr
Kepala Tukang 0.009 0rg/hr
Mandor 0.005 0rg/hr
70 1 m' Pasang Stair nozing Keramik Ukuran (10 x 20) cm setara Roman
71 1 m' Pasang Stair nozing Keramik Ukuran (10 x 30) cm setara Roman
Bahan
Stair nozing Keramik Ukuran (10 x 30) cm setara Roman 3.333 buah
PC 1.140 kg
PP 0.003 M³
Semen Warna 0.025 kg
Tenaga Kerja
Pekerja 0.090 0rg/hr
Tukang Batu 0.090 0rg/hr
Kepala Tukang 0.009 0rg/hr
Mandor 0.005 0rg/hr
71 1 m' Pasang Stair nozing Keramik Ukuran (10 x 30) cm setara Roman
72 1 m' Pasang Step tile Keramik Ukuran (30 x 30) cm setara Roman
Bahan
Step tile Keramik Ukuran (30 x 30) cm setara Roman 3.333 buah
PC 3.000 kg
PP 0.014 M³
Semen Warna 0.150 kg
Tenaga Kerja
Pekerja 0.210 0rg/hr
Tukang Batu 0.105 0rg/hr
Kepala Tukang 0.011 0rg/hr
Mandor 0.011 0rg/hr
72 1 m' Pasang Step tile Keramik Ukuran (30 x 30) cm setara Roman
73 1 M² Screeding tebal 3 cm
Bahan
Semen 0.288 zak
Pasir beton 0.039 m³
Tenaga Kerja
Tukang Batu 0.100 org/hr
Kepala Tukang 0.010 org/hr
Pekerja 0.200 org/hr
Mandor 0.010 org/hr
1 2 3 4
73 1 M² Screeding tebal 3 cm
74 1 M² Water profing coating
Bahan
Pre treatment/cleaning 1.050 m²
Curbing sudut 0.400 m'
Water profing ex. Sika Top 107 Seal ( 3 kali lapis ) 1.000 m²
Kuas 0.200 bh
Tenaga Kerja
Tukang Batu 0.200 org/hr
Kepala Tukang 0.020 org/hr
Pekerja 0.100 org/hr
Mandor 0.010 org/hr
1 2 3 4
75 1 M² Water profing Membrane ex. Sika Bituseal untuk atap dak beton
Bahan
Pre treatment/cleaning 1.050 m²
Curbing sudut 0.400 m'
Sika Bituseal T-130 SG 1.050 kg
Tenaga Kerja
Tukang Batu 0.500 org/hr
Kepala Tukang 0.050 org/hr
Pekerja 0.250 org/hr
Mandor 0.013 org/hr
75 1 M² Water profing Membrane ex. Sika Bituseal untuk atap dak beton
1 2 3 4
76 1 M² Water profing Rain tite ex. Sika
Bahan
Pre treatment/cleaning 1.050 m²
Curbing sudut 0.400 m'
Sika Bituseal T-130 SG 2.400 kg
Tenaga Kerja
Tukang Batu 0.500 org/hr
Kepala Tukang 0.050 org/hr
Pekerja 0.250 org/hr
Mandor 0.013 org/hr
1 2 3 4
a. Terpasang :
Material : Dongyang Epoxy Primer EP 118, Dongyang 1.0500 M2
Scraping Material, Dongyang Epoxy finish ET 5635 -
Selfleveling type.
1 2 3 4
70a 1 m' Pasang Stair nozing homogenous tile Ukuran (10 x 20) cm
Bahan
Stair nozing homogenous tile Ukuran (10 x 20) cm 5.000 buah
PC 1.140 kg
PP 0.003 M³
Semen Warna 0.025 kg
Tenaga Kerja
Pekerja 0.090 0rg/hr
Tukang Batu 0.090 0rg/hr
Kepala Tukang 0.009 0rg/hr
Mandor 0.005 0rg/hr
70a 1 m' Pasang Stair nozing homogenous tile Ukuran (10 x 20) cm
71a 1 m' Pasang Stair nozing homogenous tile Ukuran (10 x 30) cm
Bahan
Stair nozing homogenous tile Ukuran (10 x 30) cm 3.333 buah
PC 1.140 kg
PP 0.003 M³
Semen Warna 0.025 kg
Tenaga Kerja
Pekerja 0.090 0rg/hr
Tukang Batu 0.090 0rg/hr
Kepala Tukang 0.009 0rg/hr
Mandor 0.005 0rg/hr
71a 1 m' Pasang Stair nozing homogenous tile Ukuran (10 x 30) cm
1 2 3 4
55b 1 m' Pasang plint Marmer Ukuran (10x60) cm setara Ujung Pandang
77 1 M² Raised Floor Finish HPL "HPL Steel Panel" By Spescialist
Bahan
Raised Floor Finish HPL "HPL Steel Panel" By Spescialist 1.000 M2
Tile lifter 0.003 kg
Tenaga Kerja
Jasa pemasangan 1.000 M2
1 2 3 4
54g 1 m² Pasang Dinding Keramik Ukuran (30 x 30) cm polished setara Roman Gol. B
Bahan
Keramik Ukuran (30 x 30) cm polished setara Roman Gol. B 1.050 M2
PC 9.300 kg
PP 0.045 M³
Semen Warna 1.940 kg
Tenaga Kerja
Pekerja 0.900 0rg/hr
Tukang Batu 0.450 0rg/hr
Kepala Tukang 0.045 0rg/hr
Mandor 0.045 0rg/hr
54g 1 m² Pasang Dinding Keramik Ukuran (30 x 30) cm polished setara Roman Gol. B
54h 1 m² Pasang Dinding Keramik Ukuran (50 x 50) cm polished setara Roman Gol. B
Bahan
Keramik Ukuran (50 x 50) cm polished setara Roman Gol. B 1.050 M2
PC 9.300 kg
PP 0.045 M³
Semen Warna 1.940 kg
Tenaga Kerja
Pekerja 0.900 0rg/hr
Tukang Batu 0.450 0rg/hr
Kepala Tukang 0.045 0rg/hr
Mandor 0.045 0rg/hr
54h 1 m² Pasang Dinding Keramik Ukuran (50 x 50) cm polished setara Roman Gol. B
55 1 m² Raised floor bolted stringe steel cementitious understructure type + finis HPL
Terpasang
Raised floor bolted stringe steel cementitious understructure ty 1.050 M2
55 1 m² Raised floor bolted stringe steel cementitious understructure type + finis HPL
169,391.07
137,940.00 144,837.00
1,322.20 10,828.82
175,450.00 7,895.25
11,660.00 5,830.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 291,070.32
Overhead & keuntungan 10% : 29,107.03
Jumlah : 320,177.35
Dibulatkan : 320,100.00
204,734.07
171,600.00 180,180.00
1,322.20 10,828.82
175,450.00 7,895.25
11,660.00 5,830.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 326,413.32
Overhead & keuntungan 10% : 32,641.33
Jumlah : 359,054.65
Dibulatkan : 359,000.00
145,912.25
113,300.00 118,965.00
1,322.20 13,222.00
175,450.00 7,895.25
11,660.00 5,830.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 267,591.50
Overhead & keuntungan 10% : 26,759.15
Jumlah : 294,350.65
Dibulatkan : 294,300.00
Unpolished/Anti slip setara Roman Gol. B
177,155.08
129,690.00 138,547.83
1,322.20 13,222.00
175,450.00 7,895.25
11,660.00 17,490.00
121,679.25
89,320.00 62,524.00
A.4.4.3.Pek.Penutup lt&Ddg / HAL 272 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5.00 6.00 7.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 298,834.33
Overhead & keuntungan 10% : 29,883.43
Jumlah : 328,717.76
Unpolished/Anti slip setara Roman Gol. B Dibulatkan : 328,700.00
146,441.13
113,300.00 118,965.00
1,322.20 13,750.88
175,450.00 7,895.25
11,660.00 5,830.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 268,120.38
Overhead & keuntungan 10% : 26,812.04
Jumlah : 294,932.42
Dibulatkan : 294,900.00
153,371.13
119,900.00 125,895.00
1,322.20 13,750.88
175,450.00 7,895.25
11,660.00 5,830.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 275,050.38
Overhead & keuntungan 10% : 27,505.04
Jumlah : 302,555.42
Dibulatkan : 302,500.00
153,371.13
119,900.00 125,895.00
1,322.20 13,750.88
175,450.00 7,895.25
11,660.00 5,830.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 275,050.38
Overhead & keuntungan 10% : 27,505.04
Jumlah : 302,555.42
Dibulatkan : 302,500.00
162,994.81
122,100.00 126,984.00
1,322.20 12,957.56
175,450.00 7,895.25
11,660.00 15,158.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 284,674.06
Overhead & keuntungan 10% : 28,467.41
Jumlah : 313,141.47
Dibulatkan : 313,100.00
169,858.81
128,700.00 133,848.00
1,322.20 12,957.56
175,450.00 7,895.25
11,660.00 15,158.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 291,538.06
Overhead & keuntungan 10% : 29,153.81
Jumlah : 320,691.87
Dibulatkan : 320,600.00
194,014.81
146,300.00 158,004.00
1,322.20 12,957.56
175,450.00 7,895.25
11,660.00 15,158.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
A.4.4.3.Pek.Penutup lt&Ddg / HAL 275 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5.00 6.00 7.00
157,850.00 5,524.75
Jumlah 315,694.06
Overhead & keuntungan 10% : 31,569.41
Jumlah : 347,263.47
Dibulatkan : 347,200.00
203,518.81
155,100.00 167,508.00
1,322.20 12,957.56
175,450.00 7,895.25
11,660.00 15,158.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 325,198.06
Overhead & keuntungan 10% : 32,519.81
Jumlah : 357,717.87
Dibulatkan : 357,700.00
506,084.81
462,000.00 471,240.00
1,322.20 12,957.56
175,450.00 7,895.25
11,660.00 13,992.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
A.4.4.3.Pek.Penutup lt&Ddg / HAL 277 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5.00 6.00 7.00
157,850.00 5,524.75
Jumlah 627,764.06
Overhead & keuntungan 10% : 62,776.41
Jumlah : 690,540.47
Dibulatkan : 690,500.00
593,204.81
517,000.00 558,360.00
1,322.20 12,957.56
175,450.00 7,895.25
11,660.00 13,992.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 714,884.06
Overhead & keuntungan 10% : 71,488.41
Jumlah : 786,372.47
Dibulatkan : 786,300.00
569,444.81
495,000.00 534,600.00
1,322.20 12,957.56
175,450.00 7,895.25
11,660.00 13,992.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 691,124.06
Overhead & keuntungan 10% : 69,112.41
Jumlah : 760,236.47
Dibulatkan : 760,200.00
217,007.01
4,400.00 145,200.00
1,322.20 12,957.56
175,450.00 7,895.25
11,660.00 50,954.20
182,676.73
89,320.00 93,786.00
137,445.00 72,158.63
157,850.00 8,366.05
157,850.00 8,366.05
Jumlah 399,683.74
Overhead & keuntungan 10% : 39,968.37
Jumlah : 439,652.11
Dibulatkan : 439,600.00
13,985.16
2,200.00 11,660.00
1,322.20 1,507.31
175,450.00 526.35
11,660.00 291.50
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
Jumlah 36,603.91
Overhead & keuntungan 10% : 3,660.39
Jumlah : 40,264.30
Dibulatkan : 40,200.00
16,991.82
4,400.00 14,666.67
1,322.20 1,507.31
175,450.00 526.35
11,660.00 291.50
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
A.4.4.3.Pek.Penutup lt&Ddg / HAL 279 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5.00 6.00 7.00
Jumlah 39,610.57
Overhead & keuntungan 10% : 3,961.06
Jumlah : 43,571.63
Dibulatkan : 43,500.00
12,225.16
3,960.00 9,900.00
1,322.20 1,507.31
175,450.00 526.35
11,660.00 291.50
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
Jumlah 34,843.91
Overhead & keuntungan 10% : 3,484.39
Jumlah : 38,328.30
Dibulatkan : 38,300.00
14,241.82
7,150.00 11,916.67
1,322.20 1,507.31
175,450.00 526.35
11,660.00 291.50
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
Jumlah 36,860.57
Overhead & keuntungan 10% : 3,686.06
Jumlah : 40,546.63
Dibulatkan : 40,500.00
81,158.49
31,533.33 78,833.33
1,322.20 1,507.31
175,450.00 526.35
11,660.00 291.50
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
Jumlah 103,777.24
Overhead & keuntungan 10% : 10,377.72
Jumlah : 114,154.97
Dibulatkan : 114,100.00
85,558.49
49,940.00 83,233.33
1,322.20 1,507.31
175,450.00 526.35
11,660.00 291.50
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
A.4.4.3.Pek.Penutup lt&Ddg / HAL 281 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5.00 6.00 7.00
Jumlah 108,177.24
Overhead & keuntungan 10% : 10,817.72
Jumlah : 118,994.97
Dibulatkan : 118,900.00
emium C1 Setara ex. Ujung Pandang
953,086.51
880,000.00 932,800.00
1,322.20 10,828.82
175,450.00 7,895.25
11,660.00 1,562.44
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 1,074,765.76
Overhead & keuntungan 10% : 107,476.58
Jumlah : 1,182,242.33
Dibulatkan : 1,182,200.00
603,286.51
550,000.00 583,000.00
1,322.20 10,828.82
175,450.00 7,895.25
11,660.00 1,562.44
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 724,965.76
Overhead & keuntungan 10% : 72,496.58
Jumlah : 797,462.33
Dibulatkan : 797,400.00
3,271,669.73
3,061,666.67 3,245,366.67
1,322.20 10,828.82
175,450.00 7,895.25
11,660.00 7,579.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 3,393,348.98
Overhead & keuntungan 10% : 339,334.90
Jumlah : 3,732,683.88
Dibulatkan : 3,732,600.00
575,395.81
513,700.00 539,385.00
1,322.20 12,957.56
175,450.00 7,895.25
11,660.00 15,158.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 697,075.06
Overhead & keuntungan 10% : 69,707.51
Jumlah : 766,782.57
Dibulatkan : 766,700.00
602,365.06
539,385.00 566,354.25
1,322.20 12,957.56
175,450.00 7,895.25
11,660.00 15,158.00
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
A.4.4.3.Pek.Penutup lt&Ddg / HAL 283 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5.00 6.00 7.00
157,850.00 5,524.75
Jumlah 724,044.31
Overhead & keuntungan 10% : 72,404.43
Jumlah : 796,448.74
Dibulatkan : 796,400.00
871,151.05
807,434.10 847,805.81
66,700.70 23,345.25
42,654.15
89,320.00 15,184.40
137,445.00 23,365.65
157,850.00 2,683.45
157,850.00 1,420.65
Jumlah 913,805.20
Overhead & keuntungan 10% : 91,380.52
Jumlah : 1,005,185.72
Dibulatkan : 1,005,100.00
912,695.25
847,000.00 889,350.00
66,700.70 23,345.25
42,654.15
89,320.00 15,184.40
137,445.00 23,365.65
157,850.00 2,683.45
157,850.00 1,420.65
Jumlah 955,349.40
Overhead & keuntungan 10% : 95,534.94
Jumlah : 1,050,884.33
Dibulatkan : 1,050,800.00
102,095.25
75,000.00 78,750.00
66,700.70 23,345.25
30,053.10
89,320.00 10,718.40
137,445.00 16,493.40
157,850.00 1,894.20
157,850.00 947.10
Jumlah 132,148.35
Overhead & keuntungan 10% : 13,214.83
Jumlah : 145,363.18
Dibulatkan : 145,300.00
336,617.49
282,473.40 296,597.07
66,700.70 40,020.42
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 458,296.74
Overhead & keuntungan 10% : 45,829.67
Jumlah : 504,126.41
Dibulatkan : 504,100.00
633,227.27
564,958.90 593,206.85
66,700.70 40,020.42
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 754,906.52
Overhead & keuntungan 10% : 75,490.65
Jumlah : 830,397.17
Dibulatkan : 830,300.00
159,412.11
110,000.00 116,600.00
A.4.4.3.Pek.Penutup lt&Ddg / HAL 285 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5.00 6.00 7.00
1,322.20 12,296.46
175,450.00 7,895.25
11,660.00 22,620.40
156,444.75
89,320.00 80,388.00
137,445.00 61,850.25
157,850.00 7,103.25
157,850.00 7,103.25
Jumlah 315,856.86
Overhead & keuntungan 10% : 31,585.69
Jumlah : 347,442.55
Dibulatkan : 347,400.00
169,862.11
121,000.00 127,050.00
1,322.20 12,296.46
175,450.00 7,895.25
11,660.00 22,620.40
156,444.75
89,320.00 80,388.00
137,445.00 61,850.25
157,850.00 7,103.25
157,850.00 7,103.25
Jumlah 326,306.86
Overhead & keuntungan 10% : 32,630.69
Jumlah : 358,937.55
Dibulatkan : 358,900.00
206,822.11
156,200.00 164,010.00
1,322.20 12,296.46
175,450.00 7,895.25
11,660.00 22,620.40
156,444.75
89,320.00 80,388.00
137,445.00 61,850.25
157,850.00 7,103.25
157,850.00 7,103.25
Jumlah 363,266.86
Overhead & keuntungan 10% : 36,326.69
Jumlah : 399,593.55
Dibulatkan : 399,500.00
217,052.11
132,000.00 174,240.00
1,322.20 12,296.46
175,450.00 7,895.25
11,660.00 22,620.40
156,444.75
89,320.00 80,388.00
137,445.00 61,850.25
157,850.00 7,103.25
157,850.00 7,103.25
Jumlah 373,496.86
Overhead & keuntungan 10% : 37,349.69
Jumlah : 410,846.55
Dibulatkan : 410,800.00
446,732.11
374,000.00 403,920.00
1,322.20 12,296.46
175,450.00 7,895.25
11,660.00 22,620.40
156,444.75
89,320.00 80,388.00
137,445.00 61,850.25
157,850.00 7,103.25
446,732.11
374,000.00 403,920.00
1,322.20 12,296.46
175,450.00 7,895.25
11,660.00 22,620.40
156,444.75
89,320.00 80,388.00
137,445.00 61,850.25
157,850.00 7,103.25
157,850.00 7,103.25
Jumlah 603,176.86
Overhead & keuntungan 10% : 60,317.69
Jumlah : 663,494.55
Dibulatkan : 663,400.00
563,948.11
517,000.00 521,136.00
1,322.20 12,296.46
175,450.00 7,895.25
11,660.00 22,620.40
156,444.75
89,320.00 80,388.00
137,445.00 61,850.25
157,850.00 7,103.25
157,850.00 7,103.25
Jumlah 720,392.86
Overhead & keuntungan 10% : 72,039.29
Jumlah : 792,432.15
Dibulatkan : 792,400.00
961,213.42
880,000.00 932,800.00
1,322.20 16,448.17
175,450.00 4,386.25
11,660.00 7,579.00
225,975.75
89,320.00 116,116.00
137,445.00 89,339.25
157,850.00 10,260.25
157,850.00 10,260.25
Jumlah 1,187,189.17
Overhead & keuntungan 10% : 118,718.92
Jumlah : 1,305,908.08
Dibulatkan : 1,305,900.00
611,413.42
550,000.00 583,000.00
1,322.20 16,448.17
175,450.00 4,386.25
11,660.00 7,579.00
225,975.75
89,320.00 116,116.00
137,445.00 89,339.25
157,850.00 10,260.25
157,850.00 10,260.25
Jumlah 837,389.17
Overhead & keuntungan 10% : 83,738.92
Jumlah : 921,128.08
Dibulatkan : 921,100.00
3,273,780.08
3,061,666.67 3,245,366.67
1,322.20 16,448.17
175,450.00 4,386.25
11,660.00 7,579.00
225,975.75
89,320.00 116,116.00
137,445.00 89,339.25
157,850.00 10,260.25
961,213.42
880,000.00 932,800.00
1,322.20 16,448.17
175,450.00 4,386.25
11,660.00 7,579.00
338,963.63
89,320.00 174,174.00
137,445.00 134,008.88
157,850.00 15,390.38
157,850.00 15,390.38
Jumlah 1,300,177.04
Overhead & keuntungan 10% : 130,017.70
Jumlah : 1,430,194.75
Dibulatkan : 1,430,100.00
setara Ujung Pandang (termasuk grooving dan bullnose)
961,213.42
880,000.00 932,800.00
1,322.20 16,448.17
175,450.00 4,386.25
11,660.00 7,579.00
677,927.25
89,320.00 348,348.00
137,445.00 268,017.75
157,850.00 30,780.75
157,850.00 30,780.75
Jumlah 1,639,140.67
Overhead & keuntungan 10% : 163,914.07
Jumlah : 1,803,054.73
setara Ujung Pandang (termasuk grooving dan bullnos Dibulatkan : 1,803,000.00
210,399.42
2,500.00 157,500.00
1,322.20 16,448.17
175,450.00 4,386.25
11,660.00 32,065.00
173,827.50
89,320.00 89,320.00
137,445.00 68,722.50
157,850.00 7,892.50
157,850.00 7,892.50
Jumlah 384,226.92
Overhead & keuntungan 10% : 38,422.69
Jumlah : 422,649.61
Dibulatkan : 422,600.00
112,426.60
82,500.00 90,750.00
1,322.20 15,535.85
175,450.00 6,140.75
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 234,105.85
Overhead & keuntungan 10% : 23,410.59
Jumlah : 257,516.44
Dibulatkan : 257,500.00
330,226.60
280,500.00 308,550.00
1,322.20 15,535.85
175,450.00 6,140.75
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 451,905.85
Overhead & keuntungan 10% : 45,190.59
Jumlah : 497,096.44
Dibulatkan : 497,000.00
342,326.60
291,500.00 320,650.00
1,322.20 15,535.85
175,450.00 6,140.75
121,679.25
89,320.00 62,524.00
137,445.00 48,105.75
157,850.00 5,524.75
157,850.00 5,524.75
Jumlah 464,005.85
Overhead & keuntungan 10% : 46,400.59
Jumlah : 510,406.44
Dibulatkan : 510,400.00
992,985.74
814,000.00 854,700.00
66,700.70 70,035.74
65,000.00 68,250.00
Jumlah 992,985.74
Overhead & keuntungan 10% : 99,298.57
Jumlah : 1,092,284.31
Dibulatkan : 1,092,200.00
224,357.98
30,855.00
5,610.00 28,050.00
2,805.00 2,805.00
42,724.84
89,320.00 22,508.64
137,445.00 17,318.07
157,850.00 1,932.08
157,850.00 966.04
Jumlah 73,579.84
Overhead & keuntungan 10% : 7,357.98
Jumlah : 80,937.82
Dibulatkan : 80,900.00
46,777.50
6,930.00 34,650.00
12,127.50 12,127.50
58,314.03
89,320.00 31,262.00
137,445.00 24,052.88
157,850.00 2,683.45
157,850.00 315.70
Jumlah 105,091.53
Overhead & keuntungan 10% : 10,509.15
Jumlah : 115,600.68
Dibulatkan : 115,600.00
482,882.72
271,333.33 477,546.67
66,700.70 5,336.06
20,035.40
89,320.00 7,145.60
137,445.00 10,995.60
157,850.00 1,262.80
157,850.00 631.40
Jumlah 502,918.12
Overhead & keuntungan 10% : 50,291.81
Jumlah : 553,209.93
Dibulatkan : 553,200.00
12,145.43
3,332,010.00 9,996.03
42,988.00 2,149.40
30,053.10
89,320.00 10,718.40
137,445.00 16,493.40
157,850.00 1,894.20
157,850.00 947.10
Jumlah 42,198.53
Overhead & keuntungan 10% : 4,219.85
Jumlah : 46,418.38
Dibulatkan : 46,400.00
147,620.00
115,500.00 116,655.00
A.4.4.3.Pek.Penutup lt&Ddg / HAL 294 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5.00 6.00 7.00
175,450.00 17,545.00
13,420.00 13,420.00
95,472.30
89,320.00 22,330.00
137,445.00 68,722.50
157,850.00 3,946.25
157,850.00 473.55
Jumlah 243,092.30
Overhead & keuntungan 10% : 24,309.23
Jumlah : 267,401.53
Dibulatkan : 267,400.00
172,062.00
137,500.00 138,875.00
175,450.00 17,545.00
15,642.00 15,642.00
95,472.30
89,320.00 22,330.00
137,445.00 68,722.50
157,850.00 3,946.25
157,850.00 473.55
Jumlah 267,534.30
Overhead & keuntungan 10% : 26,753.43
Jumlah : 294,287.73
Dibulatkan : 294,200.00
159,841.00
126,500.00 127,765.00
175,450.00 17,545.00
14,531.00 14,531.00
95,472.30
89,320.00 22,330.00
137,445.00 68,722.50
157,850.00 3,946.25
157,850.00 473.55
Jumlah 255,313.30
Overhead & keuntungan 10% : 25,531.33
Jumlah : 280,844.63
Dibulatkan : 280,800.00
172,062.00
137,500.00 138,875.00
175,450.00 17,545.00
15,642.00 15,642.00
95,472.30
89,320.00 22,330.00
137,445.00 68,722.50
157,850.00 3,946.25
157,850.00 473.55
Jumlah 267,534.30
Overhead & keuntungan 10% : 26,753.43
Jumlah : 294,287.73
Dibulatkan : 294,280.00
231,344.37
18,700.00 161,257.63
121,440.00 15,359.31
137,203.00 9,465.25
196,828.50 45,262.17
95,472.30
89,320.00 22,330.00
137,445.00 68,722.50
157,850.00 3,946.25
157,850.00 473.55
Jumlah 326,816.67
Overhead & keuntungan 10% : 32,681.67
A.4.4.3.Pek.Penutup lt&Ddg / HAL 296 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5.00 6.00 7.00
Jumlah : 359,498.33
Dibulatkan : 359,400.00
250,315.85
20,900.00 180,229.11
121,440.00 15,359.31
137,203.00 9,465.25
196,828.50 45,262.17
83,441.05
137,445.00 34,361.25
89,320.00 44,660.00
157,850.00 3,946.25
157,850.00 473.55
Jumlah 333,756.90
Overhead & keuntungan 10% : 33,375.69
Jumlah : 367,132.59
Dibulatkan : 367,100.00
398,325.16
79,200.00 396,000.00
1,322.20 1,507.31
175,450.00 526.35
11,660.00 291.50
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
Jumlah 420,943.91
Overhead & keuntungan 10% : 42,094.39
Jumlah : 463,038.30
Dibulatkan : 463,000.00
103,158.49
30,250.00 100,833.33
1,322.20 1,507.31
175,450.00 526.35
11,660.00 291.50
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
Jumlah 125,777.24
Overhead & keuntungan 10% : 12,577.72
Jumlah : 138,354.97
Dibulatkan : 138,300.00
272,084.18
79,200.00 264,000.00
1,322.20 3,966.60
175,450.00 2,368.58
11,660.00 1,749.00
36,503.78
89,320.00 18,757.20
137,445.00 14,431.73
157,850.00 1,657.43
157,850.00 1,657.43
Jumlah 308,587.95
Overhead & keuntungan 10% : 30,858.80
Jumlah : 339,446.75
Dibulatkan : 339,400.00
25,882.23
66,110.00 19,039.68
175,450.00 6,842.55
34,765.50
137,445.00 13,744.50
157,850.00 1,578.50
89,320.00 17,864.00
157,850.00 1,578.50
Jumlah 60,647.73
68,808.00
3,000.00 3,150.00
2,500.00 1,000.00
60,500.00 60,500.00
20,790.00 4,158.00
41,156.50
137,445.00 27,489.00
157,850.00 3,157.00
89,320.00 8,932.00
157,850.00 1,578.50
Jumlah 109,964.50
Overhead & keuntungan 10% : 10,996.45
Jumlah : 120,960.95
Dibulatkan : 120,900.00
112,142.50
3,000.00 3,150.00
2,500.00 1,000.00
102,850.00 107,992.50
100,918.13
137,445.00 68,722.50
157,850.00 7,892.50
89,320.00 22,330.00
157,850.00 1,973.13
Jumlah 213,060.63
Overhead & keuntungan 10% : 21,306.06
Jumlah : 234,366.69
Dibulatkan : 234,300.00
129,550.00
3,000.00 3,150.00
2,500.00 1,000.00
52,250.00 125,400.00
100,918.13
137,445.00 68,722.50
157,850.00 7,892.50
89,320.00 22,330.00
157,850.00 1,973.13
Jumlah 230,468.13
Overhead & keuntungan 10% : 23,046.81
Jumlah : 253,514.94
Dibulatkan : 253,500.00
963,240.24 77,059.22
14,167.34 113,338.72
438,400.60 482,240.66
3,499,755.83 3,849,731.42
133,798.50 64,223.28
61,128.23 58,683.11
Jumlah 4,645,276.40
Overhead & keuntungan 10% : 464,527.64
Jumlah : 5,109,804.04
Dibulatkan : 5,109,800.00
963,240.24 77,059.22
14,167.34 113,338.72
438,400.60 482,240.66
318,221.86 772,642.68
133,798.50 64,223.28
61,128.23 58,683.11
Jumlah 1,568,187.66
Overhead & keuntungan 10% : 156,818.77
Jumlah : 1,725,006.43
Dibulatkan : 1,725,000.00
272,283.77
16,500.00 247,500.00
66,110.00 18,643.02
175,450.00 6,140.75
167,251.70
89,320.00 3,126.20
137,445.00 48,105.75
157,850.00 110,495.00
157,850.00 5,524.75
Jumlah 439,535.47
Overhead & keuntungan 10% : 43,953.55
Jumlah : 483,489.02
Dibulatkan : 483,400.00
236,485.70 248,309.99
Jumlah 248,309.99
Overhead & keuntungan 10% : 24,831.00
Jumlah : 273,140.98
Dibulatkan : 273,100.00
297,123.20 311,979.36
Jumlah 311,979.36
Overhead & keuntungan 10% : 31,197.94
Jumlah : 343,177.30
Dibulatkan : 343,100.00
98,575.16
19,250.00 96,250.00
1,322.20 1,507.31
175,450.00 526.35
11,660.00 291.50
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
Jumlah 121,193.91
Overhead & keuntungan 10% : 12,119.39
Jumlah : 133,313.30
Dibulatkan : 133,300.00
93,991.82
27,500.00 91,666.67
1,322.20 1,507.31
175,450.00 526.35
11,660.00 291.50
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
Jumlah 116,610.57
Overhead & keuntungan 10% : 11,661.06
Jumlah : 128,271.63
Dibulatkan : 128,200.00
49,500.00
45,000.00 45,000.00
45,000.00 4,500.00
22,618.75
89,320.00 8,038.80
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 789.25
Jumlah 72,118.75
Overhead & keuntungan 10% : 7,211.88
Jumlah : 79,330.63
Dibulatkan : 79,300.00
312,700.00
280,000.00 280,000.00
20,000.00 20,000.00
3,100.00 3,100.00
9,600.00 9,600.00
53,845.14
137,445.00 29,550.68
157,850.00 3,393.78
89,320.00 19,203.80
157,850.00 1,696.89
Jumlah 366,545.14
Overhead & keuntungan 10% : 36,654.51
A.4.4.3.Pek.Penutup lt&Ddg / HAL 303 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5.00 6.00 7.00
Jumlah : 403,199.65
Dibulatkan : 403,100.00
101,902.24
550,000.00 97,166.67
1,322.20 2,741.36
175,450.00 731.04
11,660.00 1,263.17
75,325.25
89,320.00 38,705.33
137,445.00 29,779.75
157,850.00 3,420.08
157,850.00 3,420.08
Jumlah 177,227.49
Overhead & keuntungan 10% : 17,722.75
Jumlah : 194,950.23
Dibulatkan : 194,900.00
981,155.00
980,000.00 980,000.00
350,000.00 1,155.00
60,000.00
60,000.00 60,000.00
Jumlah 1,041,155.00
Overhead & keuntungan 10% : 104,115.50
Jumlah : 1,145,270.50
Dibulatkan : 1,145,200.00
161,777.11
113,300.00 118,965.00
1,322.20 12,296.46
175,450.00 7,895.25
11,660.00 22,620.40
156,444.75
89,320.00 80,388.00
137,445.00 61,850.25
157,850.00 7,103.25
157,850.00 7,103.25
Jumlah 318,221.86
Overhead & keuntungan 10% : 31,822.19
Jumlah : 350,044.05
Dibulatkan : 350,000.00
205,667.11
155,100.00 162,855.00
1,322.20 12,296.46
175,450.00 7,895.25
11,660.00 22,620.40
156,444.75
89,320.00 80,388.00
137,445.00 61,850.25
157,850.00 7,103.25
157,850.00 7,103.25
Jumlah 362,111.86
Overhead & keuntungan 10% : 36,211.19
Jumlah : 398,323.05
Dibulatkan : 398,300.00
1,848,000.00
1,760,000.00 1,848,000.00
Jumlah 1,848,000.00
Overhead & keuntungan 10% : 184,800.00
Jumlah : 2,032,800.00
Dibulatkan : 2,032,800.00
1,853,995.50
1,765,710.00 1,853,995.50
Jumlah 1,853,995.50
Overhead & keuntungan 10% : 185,399.55
Jumlah : 2,039,395.05
Dibulatkan : 2,039,300.00
1 2 3 4
A.4.5.2 PEKERJAAN PENUTUP ATAP
41a 1 m2 Pasang atap Zinc Allumunium Kiplok CB. 0.50 TCT Colorbond
a. Bahan:
Atap zincalume Kliplok CB. 0.50 TCT Colorbond 1.0500 m2
Paku hak panjang 15 cm 0.2000 kg
b. Upah:
Kepala Tukang las 0.0100 hari
Tukang las 0.1000 hari
Pekerja 0.2000 hari
Mandor 0.0100 hari
41a 1 m2 Pasang atap Zinc Allumunium Kiplok CB. 0.50 TCT Colorbond
1 2 3 4
1 2 3 4
42.b 1 m1 Longtudinat pascia capping 0.45mm TCT
1 Bahan
Longitudinal fascia Capping - 0.45 TCT colorbo 1.200 m1
Paku hak panjang 15 cm 0.040 kg
2 Tenaga
Pekerja 0.100 oh
Tukang kayu 1.000 oh
Kepala tukang 0.100 oh
Mandor 0.050 oh
a. Bahan:
Pralon Ø 1 1/2" setara AW 0.2750 btg
Sambungan Pelengkap (15% harga pralon) 0.1000 ls
Lem PVC 0.0200 kg
b. Upah:
Tukang pipa 0.0750 hari
Mandor 0.0100 hari
1 2 3 4
a. Bahan:
Pralon Ø 2" setara AW 0.2750 btg
Sambungan Pelengkap (15% harga pralon) 0.1000 ls
Lem PVC 0.0200 kg
b. Upah:
Tukang pipa 0.0750 hari
Mandor 0.0100 hari
1 2 3 4
47 1 m1 Talang Vertikal Pralon D 2 1/2"
a. Bahan:
Pralon Ø 2 1/2" setara AW 0.2750 btg
Sambungan Pelengkap (15% harga pralon) 0.1000 ls
Lem PVC 0.0200 kg
b. Upah:
Tukang pipa 0.0750 hari
Mandor 0.0100 hari
a. Bahan:
Pralon Ø 3" setara AW 0.2750 btg
Sambungan Pelengkap (15% harga pralon) 0.1000 ls
Lem PVC 0.0200 kg
b. Upah:
Tukang pipa 0.0750 hari
Mandor 0.0100 hari
a. Bahan:
Pralon Ø 4" setara AW 0.2750 btg
Sambungan Pelengkap (15% harga pralon) 0.1000 ls
Lem PVC 0.0200 kg
b. Upah:
Tukang pipa 0.0750 hari
Mandor 0.0100 hari
a. Bahan:
Pralon Ø 1 1/2" setara AW 0.0750 btg
Lem PVC 0.0010 kg
b. Upah:
Tukang pipa 0.0125 hari
Mandor 0.0006 hari
1 2 3 4
a. Bahan:
Pralon Ø 2" setara AW 0.0750 btg
Lem PVC 0.0010 kg
b. Upah:
Tukang pipa 0.0125 hari
Mandor 0.0006 hari
1 2 3 4
52 1 lobangSparing Pralon d 2 1/2"
a. Bahan:
Pralon Ø 2 1/2" setara AW 0.0750 btg
Lem PVC 0.0010 kg
b. Upah:
Tukang pipa 0.0125 hari
Mandor 0.0006 hari
a. Bahan:
Pralon f 3" setara AW 0.0750 btg
Lem PVC 0.0010 kg
b. Upah:
Tukang pipa 0.0125 hari
Mandor 0.0006 hari
a. Bahan:
Pralon f 3" setara AW 0.0750 btg
Lem PVC 0.0010 kg
b. Upah:
Tukang pipa 0.0125 hari
Mandor 0.0006 hari
a. Bahan:
zincalume t=0.50 1.1000 m1
b. Upah:
Tukang 0.1500 hari
Mandor 0.0350 hari
a. Bahan:
Baja ringan setara GIGA steel ( Terpasang ) 1.0000 m2
1 2 3 4
1 2 3 4
58 1 m2 Pasang atap asphal Bitumen tipe Marathon 20
Bahan
Asphal Bitumen tipe Marathon 20 1.0000 lbr
Plywood 4" x 8" x 9 mm 0.350 lbr
Paku biasa genting 0.040 kg
Lem 0.100 tube
Paku biasa 2" - 5" 0.030 kg
Plasing dan bubungan 0.250 m2
Tenaga Kerja
Pekerja 0.2000 org/hr
Tukang 0.3000 org/hr
Kepala Tukang 0.0030 org/hr
Mandor 0.0100 org/hr
1 2 3 4
5 6 7
269,870.59
256,495.80 269,320.59
27,500.00 550.00
47,786.20
89,320.00 893.20
137,445.00 13,744.50
157,850.00 31,570.00
157,850.00 1,578.50
Jumlah 317,656.79
Overhead & keuntungan 10% : 31,765.68
Jumlah : 349,422.47
Dibulatkan : 349,400.00
300,288.34
280,750.80 294,788.34
27,500.00 5,500.00
47,786.20
89,320.00 893.20
137,445.00 13,744.50
157,850.00 31,570.00
157,850.00 1,578.50
Jumlah 348,074.54
Overhead & keuntungan 10% : 34,807.45
Jumlah : 382,881.99
Dibulatkan : 382,800.00
605,408.49
576,055.70 604,858.49
27,500.00 550.00
118,691.65
89,320.00 13,398.00
137,445.00 103,083.75
157,850.00 1,262.80
157,850.00 947.10
Jumlah 724,100.14
Overhead & keuntungan 10% : 72,410.01
Jumlah : 796,510.15
Dibulatkan : 796,500.00
1,100.00
-
27,500.00 1,100.00
170,054.50
89,320.00 8,932.00
137,445.00 137,445.00
157,850.00 15,785.00
157,850.00 7,892.50
Jumlah 171,154.50
Overhead & keuntungan 10% : 17,115.45
A.4.5.2. Penutup Atap / HAL 316 DARI 616
N STANDARDISASI NASIONAL 2008 EDIT 2012
HARGA STUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
Jumlah : 188,269.95
Dibulatkan : 188,200.00
127,420.04
105,266.70 126,320.04
27,500.00 1,100.00
170,054.50
89,320.00 8,932.00
137,445.00 137,445.00
157,850.00 15,785.00
157,850.00 7,892.50
Jumlah 297,474.54
Overhead & keuntungan 10% : 29,747.45
Jumlah : 327,221.99
Dibulatkan : 327,200.00
5 6 7
100,787.72
83,073.10 99,687.72
27,500.00 1,100.00
170,054.50
89,320.00 8,932.00
137,445.00 137,445.00
157,850.00 15,785.00
157,850.00 7,892.50
Jumlah 270,842.22
Overhead & keuntungan 10% : 27,084.22
Jumlah : 297,926.44
Dibulatkan : 297,900.00
/sisalation Setara Primary Smart Foam 6.5 mm
162,484.25
154,746.90 162,484.25
17,856.30
89,320.00 8,932.00
137,445.00 6,872.25
157,850.00 789.25
157,850.00 1,262.80
Jumlah 180,340.55
Overhead & keuntungan 10% : 18,034.05
Jumlah : 198,374.60
/sisalation Setara Primary Smart Foam 6.5 mm Dibulatkan : 198,300.00
248,309.99
236,485.70 248,309.99
17,856.30
89,320.00 8,932.00
137,445.00 6,872.25
157,850.00 789.25
157,850.00 1,262.80
Jumlah 266,166.29
Overhead & keuntungan 10% : 26,616.63
Jumlah : 292,782.91
Dibulatkan : 292,700.00
71,975.20
242,880.00 66,792.00
36,432.00 3,643.20
77,000.00 1,540.00
11,886.88
137,445.00 10,308.38
157,850.00 1,578.50
Jumlah 83,862.08
Overhead & keuntungan 10% : 8,386.21
Jumlah : 92,248.28
Dibulatkan : 92,200.00
5 6 7
101,068.00
343,200.00 94,380.00
51,480.00 5,148.00
77,000.00 1,540.00
11,886.88
137,445.00 10,308.38
157,850.00 1,578.50
Jumlah 112,954.88
Overhead & keuntungan 10% : 11,295.49
Jumlah : 124,250.36
Dibulatkan : 124,200.00
5 6 7
142,920.80
487,520.00 134,068.00
73,128.00 7,312.80
77,000.00 1,540.00
11,886.88
137,445.00 10,308.38
157,850.00 1,578.50
Jumlah 154,807.68
Overhead & keuntungan 10% : 15,480.77
Jumlah : 170,288.44
Dibulatkan : 170,200.00
200,596.00
686,400.00 188,760.00
102,960.00 10,296.00
77,000.00 1,540.00
11,886.88
137,445.00 10,308.38
157,850.00 1,578.50
Jumlah 212,482.88
Overhead & keuntungan 10% : 21,248.29
Jumlah : 233,731.16
Dibulatkan : 233,700.00
277,666.40
952,160.00 261,844.00
142,824.00 14,282.40
77,000.00 1,540.00
11,886.88
137,445.00 10,308.38
157,850.00 1,578.50
Jumlah 289,553.28
Overhead & keuntungan 10% : 28,955.33
Jumlah : 318,508.60
Dibulatkan : 318,500.00
18,293.00
242,880.00 18,216.00
77,000.00 77.00
1,816.72
137,445.00 1,718.06
157,850.00 98.66
Jumlah 20,109.72
Overhead & keuntungan 10% : 2,010.97
Jumlah : 22,120.69
Dibulatkan : 22,100.00
5 6 7
25,817.00
343,200.00 25,740.00
77,000.00 77.00
1,816.72
137,445.00 1,718.06
157,850.00 98.66
Jumlah 27,633.72
Overhead & keuntungan 10% : 2,763.37
Jumlah : 30,397.09
Dibulatkan : 30,300.00
5 6 7
36,641.00
487,520.00 36,564.00
77,000.00 77.00
1,816.72
137,445.00 1,718.06
157,850.00 98.66
Jumlah 38,457.72
Overhead & keuntungan 10% : 3,845.77
Jumlah : 42,303.49
Dibulatkan : 42,300.00
51,557.00
686,400.00 51,480.00
77,000.00 77.00
1,816.72
137,445.00 1,718.06
157,850.00 98.66
Jumlah 53,373.72
Overhead & keuntungan 10% : 5,337.37
Jumlah : 58,711.09
Dibulatkan : 58,700.00
71,489.00
952,160.00 71,412.00
77,000.00 77.00
1,816.72
137,445.00 1,718.06
157,850.00 98.66
Jumlah 73,305.72
Overhead & keuntungan 10% : 7,330.57
Jumlah : 80,636.29
Dibulatkan : 80,600.00
82,885.00
75,350.00 82,885.00
26,141.50
137,445.00 20,616.75
157,850.00 5,524.75
Jumlah 109,026.50
Overhead & keuntungan 10% : 10,902.65
Jumlah : 119,929.15
Dibulatkan : 119,900.00
159,500.00
159,500.00 159,500.00
Jumlah 159,500.00
A.4.5.2. Penutup Atap / HAL 322 DARI 616
N STANDARDISASI NASIONAL 2008 EDIT 2012
HARGA STUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
Overhead & keuntungan 10% : 15,950.00
Jumlah : 175,450.00
Dibulatkan : 175,400.00
m calcium cilicate t=8mm rangka hollow
75,533.68
55,990.00 27,995.00
83.60 2,031.95
205,370.00 35,654.51
9,852.22 9,852.22
100,177.00
137,445.00 54,978.00
89,320.00 35,728.00
157,850.00 6,314.00
157,850.00 3,157.00
Jumlah 175,710.68
Overhead & keuntungan 10% : 17,571.07
Jumlah : 193,281.75
m calcium cilicate t=8mm rangka hollow Dibulatkan : 193,200.00
5 6 7
375,008.12
250,000.00 250,000.00
123,863.00 43,352.05
60,000.00 2,400.00
127,000.00 12,700.00
23,294.00 698.82
263,429.00 65,857.25
56,337.05
137,445.00 27,489.00
89,320.00 26,796.00
157,850.00 473.55
157,850.00 1,578.50
Jumlah 431,345.17
Overhead & keuntungan 10% : 64,336.97
Jumlah : 495,682.14
Dibulatkan : 495,600.00
173,800.00
165,000.00 173,250.00
27,500.00 550.00
47,786.20
157,850.00 31,570.00
137,445.00 13,744.50
89,320.00 893.20
157,850.00 1,578.50
Jumlah 221,586.20
Overhead & keuntungan 10% : 22,158.62
Jumlah : 243,744.82
Dibulatkan : 243,700.00
147,000.00
140,000.00 147,000.00
47,786.20
157,850.00 31,570.00
137,445.00 13,744.50
89,320.00 893.20
157,850.00 1,578.50
Jumlah 194,786.20
Overhead & keuntungan 10% : 19,478.62
Jumlah : 214,264.82
Dibulatkan : 214,200.00
107,368.80
82,500.00 86,625.00
14,806.00 15,546.30
4,950.00 5,197.50
17,856.30
89,320.00 8,932.00
137,445.00 6,872.25
157,850.00 789.25
157,850.00 1,262.80
5 6 7
Jumlah 125,225.10
Overhead & keuntungan 10% : 12,522.51
Jumlah : 137,747.61
Dibulatkan : 137,700.00
1 2 3 4
1.00 1 m³ Membuat & memasang Kusen Pintu dan Kusen Jendela.Kayu Kelas I
2 1 m³ Membuat & memasang Kusen Pintu dan Kusen Jendela. Kayu Kelas II & III
Bahan
Balok Kayu Kmape Samarinda 1.2000 m³
Paku 10 cm 1.2500 kg
Lem Kayu 1.0000 kg
Tenaga Kerja
Pekerja 6.0000 org/hr
Tukang Kayu 18.0000 org/hr
Kepala Tukang 1.8000 org/hr
Mandor 0.3000 org/hr
2 1 m³ Membuat & memasang Kusen Pintu dan Kusen Jendela. Kayu Kelas II & III
4 1 m2 Membuat & memasang Pintu Klamp sederhana. Kayu Kelas III gudang sementar
Bahan
Papan Kayu Borneo 0.0400 m³
Paku 5cm -7 cm 0.0500 kg
Tenaga Kerja
Pekerja 0.3500 org/hr
Tukang Kayu 1.0500 org/hr
Kepala Tukang 0.1050 org/hr
A.4.6.1.Pek.Kayu / HAL 326 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
KOEF SATUAN
NO. URAIAN
1 2 3 4
4 1 m2 Membuat & memasang Pintu Klamp sederhana. Kayu Kelas III gudang sementar
1 2 3 4
6a 1 m2 Membuat & memasang Pintu dan Jendela Kaca.Kayu Kamper Samarinda Kelas I
Bahan
Papan Kayu 0.0240 m³
Lem Kayu 0.3000 kg
Tenaga Kerja
Pekerja 0.8000 org/hr
Tukang Kayu 2.4000 org/hr
Kepala Tukang 0.2400 org/hr
Mandor 0.0400 org/hr
6a 1 m2 Membuat & memasang Pintu dan Jendela Kaca.Kayu Kamper Samarinda Kelas I
7 1 m2 Membuat & memasang Pintu dan Jendela Jalusi. Kayu Kelas I & II
Bahan
Papan Kayu Jati 0.0640 m³
Lem Kayu 0.5000 kg
Tenaga Kerja
Pekerja 1.0000 org/hr
Tukang Kayu 3.0000 org/hr
Kepala Tukang 0.3000 org/hr
Mandor 0.0500 org/hr
7 1 m2 Membuat & memasang Pintu dan Jendela Jalusi. Kayu Kelas I & II
7a 1 m2 Membuat & memasang Pintu dan Jendela Jalusi. Kayu Kamper Samarinda
Bahan
Papan Kayu Kamper Samarinda 0.0640 m³
Lem Kayu 0.5000 kg
Tenaga Kerja
Pekerja 1.0000 org/hr
Tukang Kayu 3.0000 org/hr
Kepala Tukang 0.3000 org/hr
Mandor 0.0500 org/hr
7a 1 m2 Membuat & memasang Pintu dan Jendela Jalusi. Kayu Kamper Samarinda
1 2 3 4
8 1 m2 Membuat & memasang Daun Pintu Kayu Lapis (Plywood) Rangkap.Rangka Tertu
Bahan
Papan Kayu Kamper Samarinda 0.0250 m³
Paku 1 cm - 2.5 cm 0.0300 kg
Lem Kayu 0.5000 kg
Plywood Tebal 4mm Uk.90x220cm 1.0000 Lembar
Tenaga Kerja
Pekerja 0.7000 org/hr
Tukang Kayu 2.1000 org/hr
Kepala Tukang 0.2100 org/hr
Mandor 0.0350 org/hr
8 1 m2 Membuat & memasang Daun Pintu Kayu Lapis (Plywood) Rangkap.Rangka Tertu
1 2 3 4
1 2 3 4
1 2 3 4
31 1 m' Pasang dan pembuatan meja Counter Nurse station ukuran yang dihitung
2.12 10.960
1. Bahan : - Rangka multiplek 15mm meranti 17.577 lbr
- Rangka multiplek 12mm meranti 1.706 lbr
- MDF 3,5mm 21.350 lbr
- HPL 21.350 lbr
- lem kayu putih 1.913 kg
- lem kayu kuning 19.955 kg
- Paku skrup 3.515 kg
- Rel laci/Drawer Runner 4.000 bh
- Handle laci stainless steel 2.000 bh
- Surfaces 20.550 m2
- Wall bar tipe WG-5C setara Fawling 13.700 m1
- Pelat Stainless stell Hairline 1.390 m2
134,198.90
3,332,010.00 133,280.40
18,370.00 918.50
194,994.80
89,320.00 31,262.00
137,445.00 144,317.25
157,850.00 16,574.25
157,850.00 2,841.30
Jumlah 329,193.70
Overhead & keuntungan 10% : 32,919.37
Jumlah : 362,113.07
Dibulatkan : 362,100.00
157,850.00 2,841.30
Jumlah 302,683.70
Overhead & keuntungan 10% : 30,268.37
Jumlah : 332,952.07
amp sederhana. Kayu Kelas III gudang sementara Dibulatkan : 332,900.00
905,577.00
37,500,000.00 900,000.00
18,590.00 5,577.00
445,522.00
89,320.00 71,456.00
137,445.00 329,868.00
157,850.00 37,884.00
157,850.00 6,314.00
Jumlah 1,351,099.00
Overhead & keuntungan 10% : 135,109.90
Jumlah : 1,486,208.90
Dibulatkan : 1,486,200.00
2,409,295.00
37,500,000.00 2,400,000.00
18,590.00 9,295.00
556,902.50
89,320.00 89,320.00
137,445.00 412,335.00
157,850.00 47,355.00
157,850.00 7,892.50
Jumlah 2,966,197.50
Overhead & keuntungan 10% : 296,619.75
Jumlah : 3,262,817.25
Dibulatkan : 3,262,800.00
ntu Kayu Lapis (Plywood) Rangkap.Rangka Tertutup Kayu Kamper (lebar Sampai 90 cm)
236,146.35
3,332,010.00 83,300.25
18,370.00 551.10
18,590.00 9,295.00
143,000.00 143,000.00
389,831.75
89,320.00 62,524.00
137,445.00 288,634.50
157,850.00 33,148.50
157,850.00 5,524.75
Jumlah 625,978.10
Overhead & keuntungan 10% : 62,597.81
Jumlah : 688,575.91
ntu Kayu Lapis (Plywood) Rangkap.Rangka Tertutup Kayu Dibulatkan : 688,500.00
202,676.10
3,332,010.00 199,920.60
18,370.00 2,755.50
419,184.15
89,320.00 59,844.40
137,445.00 274,890.00
157,850.00 31,570.00
157,850.00 52,879.75
Jumlah 621,860.25
Overhead & keuntungan 10% : 62,186.03
Jumlah : 684,046.28
Dibulatkan : 684,000.00
Jumlah 68,318.92
A.4.6.1.Pek.Kayu / HAL 337 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
Jumlah 58,224,513.54
Overhead & keuntungan 10% : 5,822,451.35
Jumlah Harga : 64,046,964.90
Dibulatkan harga m1 : 64,046,900.00
Dibulatkan harga m1 : 4,674,900.00
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
1 1 set Kunci pintu tanam antik umum dobel slaght setara mutu menengah
2 1 set Kunci pintu tanam antik umum dobel slaght setara mutu biasa
3 1 set Kunci pintu kamar mandi
4 1 set Pemasangan 1 buah kunci silinder
4a 1 set Mortice Lock tipe Art 1490.55 + Double Cylinder Type Art
1400.60( untuk pintu engkel )
Bahan : Mortice Lock tipe Art 1490.55 ( untuk pintu engkel ) 1.0000 bh
Double Cylinder Type Art 1400.60 1.0000 bh
Upah : Pekerja 0.005 hari
Tukang kayu 0.500 hari
Kepala tukang 0.005 hari
Mandor 0.0025 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
Bahan : Lever Handle ART 306 SS 1.0000 set
Upah : Pekerja 0.015 hari
Tukang kayu 0.150 hari
Kepala tukang 0.015 hari
Mandor 0.008 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
4g 1 Psg Pull Handle tipe Art GD 9330 SS-350
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
Upah : Pekerja 0.050 hari
Tukang kayu 0.500 hari
Kepala tukang 0.050 hari
Mandor 0.0025 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
7b 1 psg Frictionstay top hung tipe 12"/MM2
Bahan : Friction stay top hung tipe 12"/2mm 1.000 psg
Upah : Pekerja 0.015 hari
Tukang kayu 0.150 hari
Kepala tukang 0.015 hari
Mandor 0.008 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
13 1 Psg Door stop Gracia tipe Art 604 ( Floor )
Bahan : Door stop Gracia tipe Art 604/40mm SS. ( Floor ) 1.0000 bh
Upah : Pekerja 0.010 hari
Tukang kayu 0.100 hari
Kepala tukang 0.010 hari
Mandor 0.0005 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
Mandor 0.008 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
14e 1 set Bracket setara Calfis BK 110
Bahan : Bracket setara Calfis BK 110 1.0000 set
Upah : Pekerja 0.0025 hari
Tukang kayu 0.0250 hari
Kepala tukang 0.0025 hari
Mandor 0.0013 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
Upah : Pekerja 0.050 hari
Tukang kayu 0.500 hari
Kepala tukang 0.005 hari
Mandor 0.003 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
15h 1 bh Anak kunci shaft door tipe Art 543
Bahan : Anak kunci shaft door tipe Art 543 1.0000 bh
Upah : Pekerja 0.050 hari
Tukang kayu 0.500 hari
Kepala tukang 0.005 hari
Mandor 0.003 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
Kepala tukang 0.015 hari
Mandor 0.00075 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
17c 1 m2 Pasang kaca clear tempered t= 5 mm
Bahan : Kacaclear tempered t= 5 mm 1.1000 m2
Upah : Pekerja 0.015 hari
Tukang kayu 0.150 hari
Kepala tukang 0.015 hari
Mandor 0.00075 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
Mandor 0.0008 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
19 1 m2 Pasang kaca polos 12 mm
Bahan : Kaca 12mm polos 1.1000 m2
Upah : Pekerja 0.025 hari
Tukang kayu 0.250 hari
Kepala tukang 0.0250 hari
Mandor 0.00125 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
Mandor 0.00075 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
24b 1 m2 Pasang kaca tinted 6 mm
Bahan : Kaca tinted 6mm 1.1000 m2
Upah : Pekerja 0.015 hari
Tukang kayu 0.150 hari
Kepala tukang 0.015 hari
Mandor 0.00075 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
Mandor 0.0008 hari
1 3 4 5
A.4.6.2 PEKERJAAN PENGGANTUNG / PERKUATAN PINTU & JENDELA
27 1 m2 Pasang kaca clear tempered t= 19 mm
Bahan : Kacaclear tempered t= 19 mm 1.1000 m2
Upah : Pekerja 0.040 hari
Tukang kayu 0.396 hari
Kepala tukang 0.0396 hari
Mandor 0.00198 hari
6 7 8
320,000.00 320,000.00 -
260,000.00 260,000.00 -
89,320.00 - 446.60
137,445.00 - 68,722.50
157,850.00 - 789.25
157,850.00 - 394.63
Jumlah : 580,000.00 70,352.98 650,352.98
Overhead & keuntungan 10% : 65,035.30
Jumlah & pembulatan : 715,300.00
1,771,000.00 1,771,000.00 -
260,000.00 260,000.00 -
89,320.00 - 446.60
137,445.00 - 68,722.50
157,850.00 - 789.25
157,850.00 - 394.63
Jumlah : 2,031,000.00 70,352.98 2,101,352.98
Overhead & keuntungan 10% : 210,135.30
Jumlah & pembulatan : 2,311,400.00
771,000.00 771,000.00 -
260,000.00 260,000.00 -
89,320.00 - 446.60
137,445.00 - 68,722.50
157,850.00 - 789.25
157,850.00 - 394.63
Jumlah : 1,031,000.00 70,352.98 1,101,352.98
Overhead & keuntungan 10% : 110,135.30
Jumlah & pembulatan : 1,211,400.00
320,000.00 320,000.00 -
144,000.00 144,000.00 -
89,320.00 - 446.60
137,445.00 - 68,722.50
157,850.00 - 789.25
157,850.00 - 394.63
Jumlah : 464,000.00 70,352.98 534,352.98
Overhead & keuntungan 10% : 53,435.30
Jumlah & pembulatan : 587,700.00
6 7 8
286,000.00 286,000.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 1,183.88
Jumlah : 286,000.00 25,508.18 311,508.18
Overhead & keuntungan 10% : 31,150.82
Jumlah & pembulatan : 342,600.00
814,000.00 814,000.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 1,183.88
Jumlah : 814,000.00 25,508.18 839,508.18
Overhead & keuntungan 10% : 83,950.82
Jumlah & pembulatan : 923,400.00
6 7 8
202,000.00 202,000.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 7,892.50
157,850.00 - 394.63
Jumlah : 202,000.00 81,475.63 283,475.63
Overhead & keuntungan 10% : 28,347.56
Jumlah & pembulatan : 311,800.00
1,317,000.00 1,317,000.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 7,892.50
157,850.00 - 394.63
Jumlah : 1,317,000.00 81,475.63 1,398,475.63
Overhead & keuntungan 10% : 139,847.56
Jumlah & pembulatan : 1,538,300.00
96,000.00 192,000.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 7,892.50
157,850.00 - 394.63
Jumlah : 192,000.00 81,475.63 273,475.63
Overhead & keuntungan 10% : 27,347.56
Jumlah & pembulatan : 300,800.00
406,000.00 812,000.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 7,892.50
157,850.00 - 394.63
Jumlah : 812,000.00 81,475.63 893,475.63
Overhead & keuntungan 10% : 89,347.56
Jumlah & pembulatan : 982,800.00
1,695,100.00 1,695,100.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 7,892.50
157,850.00 - 394.63
Jumlah : 1,695,100.00 81,475.63 1,776,575.63
Overhead & keuntungan 10% : 177,657.56
Jumlah & pembulatan : 1,954,200.00
1,303,500.00 1,303,500.00 -
A.4.6.2 Kunci & Kaca / HAL 361 DARI 616
H. SATUAN BAHAN UPAH TOTAL
Rp Rp Rp Rp
6 7 8
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 7,892.50
157,850.00 - 394.63
Jumlah : 1,303,500.00 81,475.63 1,384,975.63
Overhead & keuntungan 10% : 138,497.56
Jumlah & pembulatan : 1,523,400.00
31,000.00 31,000.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 126.28
Jumlah : 31,000.00 24,450.58 55,450.58
Overhead & keuntungan 10% : 5,545.06
Jumlah & pembulatan : 60,900.00
26,000.00 26,000.00 -
89,320.00 - 1,004.85
137,445.00 - 15,462.56
157,850.00 - 1,775.81
157,850.00 - 88.79
Jumlah : 26,000.00 18,332.02 44,332.02
Overhead & keuntungan 10% : 4,433.20
Jumlah & pembulatan : 48,700.00
78,000.00 78,000.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 1,183.88
Jumlah : 78,000.00 25,508.18 103,508.18
Overhead & keuntungan 10% : 10,350.82
Jumlah & pembulatan : 113,800.00
6 7 8
95,000.00 95,000.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 1,183.88
Jumlah : 95,000.00 25,508.18 120,508.18
Overhead & keuntungan 10% : 12,050.82
Jumlah & pembulatan : 132,500.00
172,000.00 172,000.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 1,183.88
Jumlah : 172,000.00 25,508.18 197,508.18
Overhead & keuntungan 10% : 19,750.82
Jumlah & pembulatan : 217,200.00
247,000.00 247,000.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 1,183.88
Jumlah : 247,000.00 25,508.18 272,508.18
Overhead & keuntungan 10% : 27,250.82
Jumlah & pembulatan : 299,700.00
247,500.00 247,500.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 7,892.50
157,850.00 - 473.55
Jumlah : 247,500.00 81,554.55 329,054.55
Overhead & keuntungan 10% : 32,905.46
Jumlah & pembulatan : 361,900.00
118,000.00 118,000.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 7,892.50
157,850.00 - 394.63
6 7 8
35,000.00 35,000.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 1,183.88
Jumlah : 35,000.00 25,508.18 60,508.18
Overhead & keuntungan 10% : 6,050.82
Jumlah & pembulatan : 66,500.00
35,000.00 35,000.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 1,183.88
Jumlah : 35,000.00 25,508.18 60,508.18
Overhead & keuntungan 10% : 6,050.82
Jumlah & pembulatan : 66,500.00
6 7 8
89,000.00 89,000.00 -
89,320.00 - 893.20
137,445.00 - 13,744.50
157,850.00 - 1,578.50
157,850.00 - 78.93
Jumlah : 89,000.00 16,295.13 105,295.13
Overhead & keuntungan 10% : 10,529.51
Jumlah & pembulatan : 115,800.00
44,000.00 44,000.00 -
89,320.00 - 893.20
137,445.00 - 13,744.50
157,850.00 - 1,578.50
157,850.00 - 78.93
Jumlah : 44,000.00 16,295.13 60,295.13
Overhead & keuntungan 10% : 6,029.51
Jumlah & pembulatan : 66,300.00
490,000.00 490,000.00 -
89,320.00 - 5,359.20
137,445.00 - 82,467.00
157,850.00 - 9,471.00
157,850.00 - 473.55
Jumlah : 490,000.00 97,770.75 587,770.75
Overhead & keuntungan 10% : 58,777.08
Jumlah & pembulatan : 646,500.00
185,500.00 185,500.00 -
89,320.00 - 5,359.20
137,445.00 - 82,467.00
157,850.00 - 9,471.00
157,850.00 - 473.55
Jumlah : 185,500.00 97,770.75 283,270.75
Overhead & keuntungan 10% : 28,327.08
Jumlah & pembulatan : 311,500.00
278,000.00 278,000.00 -
89,320.00 - 5,359.20
137,445.00 - 82,467.00
157,850.00 - 9,471.00
157,850.00 - 473.55
Jumlah : 278,000.00 97,770.75 375,770.75
Overhead & keuntungan 10% : 37,577.08
Jumlah & pembulatan : 413,300.00
48,500.00 48,500.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
A.4.6.2 Kunci & Kaca / HAL 365 DARI 616
H. SATUAN BAHAN UPAH TOTAL
Rp Rp Rp Rp
6 7 8
157,850.00 - 1,183.88
Jumlah : 48,500.00 25,508.18 74,008.18
Overhead & keuntungan 10% : 7,400.82
Jumlah & pembulatan : 81,400.00
72,500.00 72,500.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 1,183.88
Jumlah : 72,500.00 25,508.18 98,008.18
Overhead & keuntungan 10% : 9,800.82
Jumlah & pembulatan : 107,800.00
200,000.00 200,000.00 -
89,320.00 - 5,359.20
137,445.00 - 82,467.00
157,850.00 - 9,471.00
157,850.00 - 473.55
Jumlah : 200,000.00 97,770.75 297,770.75
Overhead & keuntungan 10% : 29,777.08
Jumlah & pembulatan : 327,500.00
6 7 8
11,800.00 11,800.00 -
89,320.00 - 223.30
137,445.00 - 3,436.13
157,850.00 - 394.63
157,850.00 - 197.31
Jumlah : 11,800.00 4,251.36 16,051.36
Overhead & keuntungan 10% : 1,605.14
Jumlah & pembulatan : 17,600.00
1,427,900.00 1,427,900.00 -
89,320.00 - 5,359.20
137,445.00 - 82,467.00
157,850.00 - 9,471.00
157,850.00 - 473.55
Jumlah : 1,427,900.00 97,770.75 1,525,670.75
Overhead & keuntungan 10% : 152,567.08
Jumlah & pembulatan : 1,678,200.00
1,913,000.00 1,913,000.00 -
89,320.00 - 5,359.20
137,445.00 - 82,467.00
157,850.00 - 9,471.00
157,850.00 - 473.55
Jumlah : 1,913,000.00 97,770.75 2,010,770.75
Overhead & keuntungan 10% : 201,077.08
Jumlah & pembulatan : 2,211,800.00
3,646,100.00 3,646,100.00
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 789.25
157,850.00 - 473.55
Jumlah : 3,646,100.00 74,451.30 3,720,551.30
Overhead & keuntungan 10% : 372,055.13
Jumlah & pembulatan : 4,092,600.00
1,749,500.00 1,749,500.00
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 789.25
157,850.00 - 473.55
Jumlah : 1,749,500.00 74,451.30 1,823,951.30
Overhead & keuntungan 10% : 182,395.13
Jumlah & pembulatan : 2,006,300.00
1,177,200.00 1,177,200.00
A.4.6.2 Kunci & Kaca / HAL 367 DARI 616
H. SATUAN BAHAN UPAH TOTAL
Rp Rp Rp Rp
6 7 8
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 789.25
157,850.00 - 473.55
Jumlah : 1,177,200.00 74,451.30 1,251,651.30
Overhead & keuntungan 10% : 125,165.13
Jumlah & pembulatan : 1,376,800.00
32,000.00 32,000.00 -
89,320.00 - 1,786.40
137,445.00 - 27,489.00
157,850.00 - 3,157.00
157,850.00 - 1,578.50
Jumlah : 32,000.00 34,010.90 66,010.90
Overhead & keuntungan 10% : 6,601.09
Jumlah & pembulatan : 72,600.00
60,000.00 60,000.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 789.25
157,850.00 - 473.55
Jumlah : 60,000.00 74,451.30 134,451.30
Overhead & keuntungan 10% : 13,445.13
Jumlah & pembulatan : 147,800.00
6 7 8
22,000.00 22,000.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 789.25
157,850.00 - 473.55
Jumlah : 22,000.00 74,451.30 96,451.30
Overhead & keuntungan 10% : 9,645.13
Jumlah & pembulatan : 106,000.00
201,000.00 201,000.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 789.25
157,850.00 - 473.55
Jumlah : 201,000.00 74,451.30 275,451.30
Overhead & keuntungan 10% : 27,545.13
Jumlah & pembulatan : 302,900.00
617,000.00 617,000.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 1,183.88
Jumlah : 617,000.00 25,508.18 642,508.18
Overhead & keuntungan 10% : 64,250.82
Jumlah & pembulatan : 706,700.00
118,000.00 118,000.00 -
89,320.00 - 4,466.00
137,445.00 - 68,722.50
157,850.00 - 7,892.50
157,850.00 - 394.63
Jumlah : 118,000.00 81,475.63 199,475.63
Overhead & keuntungan 10% : 19,947.56
Jumlah & pembulatan : 219,400.00
73,700.00 81,070.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 118.39
Jumlah : 81,070.00 24,442.69 105,512.69
Overhead & keuntungan 10% : 10,551.27
Jumlah & pembulatan : 116,000.00
112,600.00 123,860.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
A.4.6.2 Kunci & Kaca / HAL 369 DARI 616
H. SATUAN BAHAN UPAH TOTAL
Rp Rp Rp Rp
6 7 8
157,850.00 - 2,367.75
157,850.00 - 118.39
Jumlah : 123,860.00 24,442.69 148,302.69
Overhead & keuntungan 10% : 14,830.27
Jumlah & pembulatan : 163,100.00
140,800.00 154,880.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 118.39
Jumlah : 154,880.00 24,442.69 179,322.69
Overhead & keuntungan 10% : 17,932.27
Jumlah & pembulatan : 197,200.00
194,700.00 214,170.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 118.39
Jumlah : 214,170.00 24,442.69 238,612.69
Overhead & keuntungan 10% : 23,861.27
Jumlah & pembulatan : 262,400.00
6 7 8
214,700.00 236,170.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 118.39
Jumlah : 236,170.00 24,442.69 260,612.69
Overhead & keuntungan 10% : 26,061.27
Jumlah & pembulatan : 286,600.00
222,100.00 244,310.00 -
89,320.00 - 1,473.78
137,445.00 - 22,678.43
157,850.00 - 2,604.53
157,850.00 - 126.28
Jumlah : 244,310.00 26,883.01 271,193.01
Overhead & keuntungan 10% : 27,119.30
Jumlah & pembulatan : 298,300.00
382,100.00 420,310.00 -
89,320.00 - 1,473.78
137,445.00 - 22,678.43
157,850.00 - 2,604.53
157,850.00 - 126.28
Jumlah : 420,310.00 26,883.01 447,193.01
Overhead & keuntungan 10% : 44,719.30
Jumlah & pembulatan : 491,900.00
684,200.00 752,620.00 -
89,320.00 - 1,473.78
137,445.00 - 22,678.43
157,850.00 - 2,604.53
157,850.00 - 126.28
Jumlah : 752,620.00 26,883.01 779,503.01
Overhead & keuntungan 10% : 77,950.30
Jumlah & pembulatan : 857,400.00
578,900.00 636,790.00 -
89,320.00 - 1,473.78
137,445.00 - 22,678.43
157,850.00 - 2,604.53
157,850.00 - 126.28
Jumlah : 636,790.00 26,883.01 663,673.01
Overhead & keuntungan 10% : 66,367.30
Jumlah & pembulatan : 730,000.00
550,500.00 605,550.00 -
89,320.00 - 1,473.78
137,445.00 - 22,678.43
157,850.00 - 2,604.53
A.4.6.2 Kunci & Kaca / HAL 371 DARI 616
H. SATUAN BAHAN UPAH TOTAL
Rp Rp Rp Rp
6 7 8
157,850.00 - 126.28
Jumlah : 605,550.00 26,883.01 632,433.01
Overhead & keuntungan 10% : 63,243.30
Jumlah & pembulatan : 695,600.00
374,700.00 412,170.00 -
89,320.00 - 1,473.78
137,445.00 - 22,678.43
157,850.00 - 2,604.53
157,850.00 - 126.28
Jumlah : 412,170.00 26,883.01 439,053.01
Overhead & keuntungan 10% : 43,905.30
Jumlah & pembulatan : 482,900.00
6 7 8
473,700.00 521,070.00 -
89,320.00 - 2,233.00
137,445.00 - 34,361.25
157,850.00 - 3,946.25
157,850.00 - 197.31
Jumlah : 521,070.00 40,737.81 561,807.81
Overhead & keuntungan 10% : 56,180.78
Jumlah & pembulatan : 617,900.00
- - -
- - -
- - -
- - -
- - -
Jumlah : - - -
Overhead & keuntungan 10% : -
Jumlah & pembulatan : -
1,235,800.00 1,359,380.00 -
89,320.00 - 2,233.00
137,445.00 - 34,361.25
157,850.00 - 3,946.25
157,850.00 - 197.31
Jumlah : 1,359,380.00 40,737.81 1,400,117.81
Overhead & keuntungan 10% : 140,011.78
Jumlah & pembulatan : 1,540,100.00
540,000.00 594,000.00 -
89,320.00 - 2,233.00
137,445.00 - 34,361.25
157,850.00 - 3,946.25
157,850.00 - 197.31
Jumlah : 594,000.00 40,737.81 634,737.81
Overhead & keuntungan 10% : 63,473.78
Jumlah & pembulatan : 698,200.00
682,100.00 750,310.00 -
89,320.00 - 2,233.00
137,445.00 - 34,361.25
157,850.00 - 3,946.25
157,850.00 - 197.31
Jumlah : 750,310.00 40,737.81 791,047.81
Overhead & keuntungan 10% : 79,104.78
Jumlah & pembulatan : 870,100.00
368,400.00 405,240.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
A.4.6.2 Kunci & Kaca / HAL 373 DARI 616
H. SATUAN BAHAN UPAH TOTAL
Rp Rp Rp Rp
6 7 8
157,850.00 - 118.39
Jumlah : 405,240.00 24,442.69 429,682.69
Overhead & keuntungan 10% : 42,968.27
Jumlah & pembulatan : 472,600.00
157,900.00 173,690.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 118.39
Jumlah : 173,690.00 24,442.69 198,132.69
Overhead & keuntungan 10% : 19,813.27
Jumlah & pembulatan : 217,900.00
197,400.00 217,140.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 118.39
Jumlah : 217,140.00 24,442.69 241,582.69
Overhead & keuntungan 10% : 24,158.27
Jumlah & pembulatan : 265,700.00
6 7 8
246,300.00 270,930.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 118.39
Jumlah : 270,930.00 24,442.69 295,372.69
Overhead & keuntungan 10% : 29,537.27
Jumlah & pembulatan : 324,900.00
373,700.00 411,070.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 118.39
Jumlah : 411,070.00 24,442.69 435,512.69
Overhead & keuntungan 10% : 43,551.27
Jumlah & pembulatan : 479,000.00
286,300.00 314,930.00 -
89,320.00 - 1,339.80
137,445.00 - 20,616.75
157,850.00 - 2,367.75
157,850.00 - 118.39
Jumlah : 314,930.00 24,442.69 339,372.69
Overhead & keuntungan 10% : 33,937.27
Jumlah & pembulatan : 373,300.00
368,400.00 405,240.00 -
89,320.00 - 1,473.78
137,445.00 - 22,678.43
157,850.00 - 2,604.53
157,850.00 - 126.28
Jumlah : 405,240.00 26,883.01 432,123.01
Overhead & keuntungan 10% : 43,212.30
Jumlah & pembulatan : 475,300.00
- - -
- - -
- - -
- - -
- - -
Jumlah : - - -
Overhead & keuntungan 10% : -
Jumlah & pembulatan : -
461,100.00 507,210.00 -
89,320.00 - 1,473.78
137,445.00 - 22,678.43
157,850.00 - 2,604.53
A.4.6.2 Kunci & Kaca / HAL 375 DARI 616
H. SATUAN BAHAN UPAH TOTAL
Rp Rp Rp Rp
6 7 8
157,850.00 - 126.28
Jumlah : 507,210.00 26,883.01 534,093.01
Overhead & keuntungan 10% : 53,409.30
Jumlah & pembulatan : 587,500.00
3,842,100.00 4,226,310.00 -
89,320.00 - 2,791.25
137,445.00 - 42,951.56
157,850.00 - 4,932.81
157,850.00 - 246.64
Jumlah : 4,226,310.00 50,922.27 4,277,232.27
Overhead & keuntungan 10% : 427,723.23
Jumlah & pembulatan : 4,704,900.00
6 7 8
6,078,900.00 6,686,790.00 -
89,320.00 - 3,535.58
137,445.00 - 54,405.31
157,850.00 - 6,248.23
157,850.00 - 312.41
Jumlah : 6,686,790.00 64,501.54 6,751,291.54
Overhead & keuntungan 10% : 675,129.15
Jumlah & pembulatan : 7,426,400.00
52,500.00 57,750.00 -
80,000.00 - 80,000.00
Jumlah : 57,750.00 80,000.00 137,750.00
Overhead & keuntungan 10% : 13,775.00
Jumlah & pembulatan : 151,500.00
2,117,500.00 2,329,250.00 -
89,320.00 - 3,535.58
137,445.00 - 54,405.31
157,850.00 - 6,248.23
157,850.00 - 312.41
Jumlah : 2,329,250.00 64,501.54 2,393,751.54
Overhead & keuntungan 10% : 239,375.15
2,329,250.00 2,562,175.00 -
89,320.00 - 3,535.58
137,445.00 - 54,405.31
157,850.00 - 6,248.23
157,850.00 - 312.41
Jumlah : 2,562,175.00 64,501.54 2,626,676.54
Overhead & keuntungan 10% : 262,667.65
1 2 3 4
1 2 3 4
1 2 3 4
A.4.5.1 7b Pasang Langit-langit Gypsum water prof 120 x 240 Tebal 9 mm 1.000 m2
Pasang Langit-langit calsium cilicate 120 x 240 Tebal 6 mm termasuk rangka hollow galp
12 1 m²
termasuk gantungan
Pemasangan 1 m2 rangka besi hollow galpanis
A.4.2.1 21a 1.000 m2
1x40.40.0,35mm, modul 60 x 120 cm, untuk plapond
Pasang Langit-langit calcium cilicate Board 120 x 240 Tebal 6
A.4.5.1 7a 1.000 m2
mm
Pasang Langit-langit calsium cilicate 120 x 240 Tebal 6 mm termasuk rangka hol
12 1 m²
galpanis 40x40x0.35mm modul 6ox120 termasuk gantungan
1 2 3 4
13 1 m² Pasang Langit-langit Gypsum 120 x 240 Tebal 9 mm termasuk rangka hollow 40x40x2mm
A.4.5.1 7b Pasang Langit-langit Gypsum water prof 120 x 240 Tebal 9 mm 1.000 m2
12 1 m² Pasang Langit-langit calsium cilicate 120 x 240 Tebal 6 mm termasuk rangka hollow galp
termasuk gantungan
Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60
A.4.2.1 21 1.000 m2
x 120 cm
1 2 3 4
15 1 m² Pasang dinding partisi Gypsum Board rangkap .120 x 240 x 9 mm. Tebal 9 mm
Bahan
Gypsum Board t=9mm setara Jayaboard 0.728 Lembar
Drywall Screw 25mmX083 24.306 pc(s)
Jointing Compound UB-10/20/888/CCL 20kg/bag(s) 0.038 bag(s)
UB Tape 75m/roll(s) 0.032 roll(s)
Tenaga Kerja
Pekerja 0.200 org/hr
Tukang 0.100 org/hr
Kepala Tukang 0.010 org/hr
Mandor 0.010 org/hr
15 1 m² Pasang dinding partisi Gypsum Board rangkap .120 x 240 x 9 mm. Tebal 9 mm
1 2 3 4
17 1 m² Anti bacterial ceilling setara Bioguard 16mm + Suspension system Prelude stand
Anti bacterial ceilling setara Bioguard 16mm +
Harga terpasang Suspension system Prelude standard t=24mm setara
Armstrong 1.05
Anti bacterial ceilling setara Bioguard 16mm + Suspension system Prelude stand
17 1 m²
t=24mm setara Armstrong
18 1 m² Anti bacterial ceilling setara Bioguard 16mm + Suspension system cleanroom alu
Anti bacterial ceilling setara Bioguard 16mm +
Harga terpasang Suspension system cleanroom alumunium setara
Armstrong 1.05
1 2 3 4
19 1 m² Accustic tile ceilling setara tipe Dune 16mm + Suspension system Suprafine Grid
Accustic tile ceilling setara tipe Dune 16mm +
Harga terpasang Suspension system Suprafine Grids t=15mm setara
Armstrong 1.05
Accustic tile ceilling setara tipe Dune 16mm + Suspension system Suprafine Grid
19 1 m²
t=15mm setara Armstrong
20 1 m² Gypsum board TKA 2 jam t=13mm + Suspension system setara Prelude standard
Gypsum board TKA 2 jam setara Firestop t=16mm x 2
Harga terpasang
lapis+ rangka hollow 40x40mm t=0.35mm galvanized 1.05
Gypsum board TKA 2 jam t=13mm + Suspension system setara Prelude standard
20 1 m²
t=24mm
Overhea
1 2 3 4
Overhead &
Overhea
Perforated Accustic plaster board seamless factory pre-coated + rangka hollow 40x40mm
25 1 m²
gantungan
Pemasangan 1 m2 rangka besi hollow galpanis
A.4.2.1 21a 1.000 m2
1x40.40.0,35mm, modul 60 x 120 cm, untuk plapond
Terpasang Perforated Accustic plaster board seamless factory pre-coated 1.000 m2
Perforated Accustic plaster board seamless factory pre-coated + rangka hollow
25 1 m²
40x40mm t=0.35mm galvanized termasuk gantungan
1 2 3 4
Misalkan:
Panjang Hollow (L) = 6000 mm
Lebar Hollow (W) = 40 mm
Tinggi hollow (H) = 40 mm
Ketebalan (B) = 2 mm
Berat jenis besi = 7850 (Kg/M3)
Berat Jenis besi (BJ) = 7.85 Kg/ 1.000.000 mm3
34,479.73
84,810.00 30,870.84
83.60 1,015.97
111,026.67 2,109.51
30,213.33 483.41
17,382.75
89,320.00 8,932.00
137,445.00 6,872.25
157,850.00 789.25
157,850.00 789.25
Jumlah 51,862.48
Overhead & keuntungan 10% : 5,186.25
Jumlah : 57,048.73
Dibulatkan : 57,000.00
57,062.29
146,850.00 53,453.40
83.60 1,015.97
111,026.67 2,109.51
30,213.33 483.41
17,382.75
89,320.00 8,932.00
137,445.00 6,872.25
157,850.00 789.25
157,850.00 789.25
Jumlah 74,445.04
Overhead & keuntungan 10% : 7,444.50
Jumlah : 81,889.55
Dibulatkan : 81,800.00
45,730.97
115,720.00 42,122.08
83.60 1,015.97
111,026.67 2,109.51
30,213.33 483.41
17,382.75
89,320.00 8,932.00
137,445.00 6,872.25
A.4.5.1.Pek. Langit2 / HAL 387 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp Rp Rp
5 6 7.00
157,850.00 789.25
157,850.00 789.25
Jumlah 63,113.72
Overhead & keuntungan 10% : 6,311.37
Jumlah : 69,425.10
Dibulatkan : 69,400.00
96,325.87
35,530.00 53,295.00
1,320.00 1,372.80
5,573.33 1,463.00
4,253.33 4,423.47
28,013.33 3,734.18
49,133.33 10,917.43
7,480.00 -
14,666.67 21,120.00
125,221.25
89,320.00 44,660.00
137,445.00 68,722.50
157,850.00 7,892.50
157,850.00 3,946.25
Jumlah 221,547.12
Overhead & keuntungan 10% : 22,154.71
Jumlah : 243,701.83
Dibulatkan : 243,700.00
14,438.34
13,750.00 14,437.50
83.60 0.84
12,601.05
89,320.00 4,466.00
137,445.00 6,872.25
157,850.00 789.25
157,850.00 473.55
Jumlah 27,039.39
Overhead & keuntungan 10% : 2,703.94
Jumlah : 29,743.32
Dibulatkan : 29,700.00
16,226.93
14,630.00 15,361.50
5,769.50 865.43
15,026.55
89,320.00 5,359.20
137,445.00 8,246.70
157,850.00 947.10
157,850.00 473.55
Jumlah 31,253.48
Overhead & keuntungan 10% : 3,125.35
Jumlah : 34,378.82
Dibulatkan : 34,300.00
Tebal 9 mm termasuk rangka hollow galpanis 40x40x0.35mm modul 6ox120 termasuk
165,200.00 165,200.00
57,000.00 57,000.00
165,200.00 165,200.00
69,400.00 69,400.00
165,200.00 165,200.00
81,800.00 81,800.00
121,800.00 121,800.00
57,000.00 57,000.00
121,800.00 121,800.00
69,400.00 69,400.00
121,800.00 121,800.00
81,800.00 81,800.00
114,570.98
60,573.33 34,526.80
60,573.33 13,459.39
111,026.67 4,219.01
30,213.33 966.83
83.60 2,031.95
- -
84,810.00 59,367.00
88,954.25
137,445.00 41,233.50
137,445.00 27,489.00
89,320.00 17,864.00
157,850.00 2,367.75
Jumlah 203,525.23
Overhead & keuntungan 10% : 20,352.52
Jumlah : 223,877.76
Dibulatkan : 223,800.00
305,989.45
1,042,140.00 303,957.50
83.60 2,031.95
75,132.75
137,445.00 41,233.50
89,320.00 26,796.00
157,850.00 4,735.50
157,850.00 2,367.75
Jumlah 381,122.20
Overhead & keuntungan 10% : 38,112.22
Jumlah : 419,234.42
Dibulatkan : 419,200.00
63,773.63
84,810.00 61,741.68
83.60 2,031.95
111,026.67 4,219.01
30,213.33 966.83
34,765.50
89,320.00 17,864.00
137,445.00 13,744.50
157,850.00 1,578.50
157,850.00 1,578.50
Jumlah 98,539.13
Overhead & keuntungan 10% : 9,853.91
Jumlah : 108,393.04
Board rangkap .120 x 240 x 9 mm. Tebal 9 mm Dibulatkan : 108,300.00
419,200.00 419,200.00
108,300.00 108,300.00
28,000.00 56,000.00
Jumlah 583,500.00
Dibulatkan : 583,500.00
A.4.5.1.Pek. Langit2 / HAL 391 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp Rp Rp
5 6 7.00
363,000.00 381,150.00
Jumlah 381,150.00
Keuntungan 10% : 38,115.00
Jumlah : 419,265.00
guard 16mm + Suspension system Prelude standard
Dibulatkan :
419,200.00
572,000.00 600,600.00
Jumlah 600,600.00
Keuntungan 10% : 60,060.00
Jumlah : 660,660.00
guard 16mm + Suspension system cleanroom
Dibulatkan :
660,600.00
363,000.00 381,150.00
Jumlah 381,150.00
Keuntungan 10% : 38,115.00
Jumlah : 419,265.00
Dune 16mm + Suspension system Suprafine Grids
Dibulatkan :
419,200.00
539,442.20 566,414.31
Jumlah 566,414.31
Keuntungan 10% : 56,641.43
Jumlah : 623,055.74
m + Suspension system setara Prelude standard
Dibulatkan :
623,000.00
4,273.50
4,070.00 4,273.50
11,891.69
89,320.00 6,252.40
137,445.00 4,810.58
157,850.00 552.48
157,850.00 276.24
Jumlah 16,165.19
Overhead & keuntungan 10% : 1,616.52
Jumlah : 17,781.71
Dibulatkan : 17,700.00
221,941.24
140,274.20 147,287.91
9,331.67 37,326.67
37,326.67 37,326.67
118,691.65
89,320.00 13,398.00
137,445.00 103,083.75
157,850.00 1,262.80
157,850.00 947.10
Jumlah 340,632.89
Overhead & keuntungan 10% : 34,063.29
Jumlah : 374,696.18
Dibulatkan : 374,600.00
2,633,100.00 2,633,100.00
Jumlah 3,369,680.00
Overhead & keuntungan include : -
Jumlah : 3,369,680.00
=6mm + clear PVB laminate 1.52mm + Heat-
Dibulatkan :
m + rangka alumunium transm & mullio 3,369,600.00
851,025.00
810,500.00 851,025.00
Jumlah 851,025.00
Overhead & keuntungan 10% : 85,102.50
Jumlah : 936,127.50
Dibulatkan : 936,100.00
165,200.00 165,200.00
69,400.00 69,400.00
d seamless factory pre-coated + rangka hollow
Dibulatkan :
ermasuk gantungan 234,600.00
94,040.50
205,370.00 92,416.50
83.60 457.19
111,026.67 949.28
30,213.33 217.54
7,822.24
89,320.00 4,019.40
137,445.00 3,092.51
157,850.00 355.16
157,850.00 355.16
Jumlah 101,862.74
Overhead & keuntungan 10% : 10,186.27
Jumlah : 112,049.01
Dibulatkan : 112,000.00
2 Tenaga
Pekerja 0.150 oh 89,320.00
Tukang cat - oh 137,445.00
Kepala tukang - oh 157,850.00
Mandor 0.0025 oh 157,850.00
2 Tenaga
Pekerja 0.150 oh 89,320.00
Tukang cat - oh 137,445.00
Kepala tukang - oh 157,850.00
Mandor 0.0025 oh 157,850.00
2 Tenaga
Pekerja 0.150 oh 89,320.00
Tukang cat - oh 137,445.00
Kepala tukang - oh 157,850.00
Mandor 0.0080 oh 157,850.00
2 Tenaga
Pekerja 0.070 oh 89,320.00
Tukang cat 0.009 oh 137,445.00
Kepala tukang 0.006 oh 157,850.00
Mandor 0.0030 oh 157,850.00
4 1 m2 Pengecatan bidang kayu baru ( 1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
5 1 m2 Pengecatan bidang kayu baru ( 1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
1 Bahan
Cat meni 0.200 kg 37,180.00
Plamir 0.150 kg 31,130.00
Cat dasar 0.170 kg 57,640.00
Cat penutup 2 kali 0.350 kg 57,640.00
Kuas 0.010 bh 33,330.00
Pengencer 0.030 kg 19,800.00
Ampelas 0.200 lbr 6,021.40
2 Tenaga
Pekerja 0.070 oh 89,320.00
Tukang cat 0.105 oh 137,445.00
Kepala tukang 0.004 oh 157,850.00
Mandor 0.0030 oh 157,850.00
5 1 m2 Pengecatan bidang kayu baru ( 1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
2 Tenaga
Pekerja 0.070 oh 89,320.00
Tukang cat 0.009 oh 137,445.00
Kepala tukang 0.006 oh 157,850.00
Mandor 0.0030 oh 157,850.00
2 Tenaga
Pekerja - oh 89,320.00
Tukang politur 0.160 oh 137,445.00
Kepala tukang 0.016 oh 157,850.00
Mandor 0.0030 oh 157,850.00
2 Tenaga
Pekerja 0.160 oh 89,320.00
Tukang cat 0.160 oh 137,445.00
Kepala tukang 0.016 oh 157,850.00
Mandor 0.0025 oh 157,850.00
10 1 m2 Cat tembok Interior ICI Dulux (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
1 Bahan
Wall filler ex. ICI Dulux 0.100 kg 22,880.00
Cat dasar Interior setara Jotun 0.100 lt 31,350.00
Cat Dasar 0.260 lt 31,350.00
2 Tenaga
Pekerja 0.020 oh 89,320.00
A4.7.1. Pek-Cat / HAL 398 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
HARGA SATUAN
NO. URAIAN KOEF SATUAN
Rp.
1 2 3 4 5
10 1 m2 Cat tembok Interior ICI Dulux (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
10a 1 m2 Cat tembok exterior Weathershield ICI Dulux ( 1 lapis cat dasar, 2 lapis cat penutup )
1 Bahan
Cat jenis alkali 1 x 0.100 kg 45,430.00
Cat tembok exterior Weathershield ICI Dulux
0.100 lt 48,400.00
( Cat dasar 1 x )
Cat tembok exterior Weathershield setara Jotun
0.260 lt 48,400.00
( Cat penutup 2 x )
2 Tenaga
Pekerja 0.020 oh 89,320.00
Tukang cat 0.063 oh 137,445.00
Kepala tukang 0.0063 oh 157,850.00
Mandor 0.0025 oh 157,850.00
10a 1 m2 Cat tembok exterior Weathershield ICI Dulux ( 1 lapis cat dasar, 2 lapis cat penutup )
10b 1 m2 Pengecatan 1 m2 tembok baru interior AGE (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penu
1 Bahan
Wall filler ex. ICI Dulux 0.100 kg 22,880.00
Cat dasar ICI Dulux ( Cat dasar 1 x ) 0.100 lt 63,030.00
Cat jenis AGE setara ICI Dulux (cat penutup 2 x) 0.260 lt 63,030.00
2 Tenaga
Pekerja 0.020 oh 89,320.00
Tukang cat 0.063 oh 137,445.00
Kepala tukang 0.0063 oh 157,850.00
Mandor 0.0030 oh 157,850.00
Pengecatan 1 m2 tembok baru interior AGE (1 lapis plamuur, 1 lapis cat dasar, 2 lapis
10b 1 m2
cat penutup)
10c 1 m2 Pengecatan 1 m2 tembok baru interior Anti bakteri (1 lapis plamuur, 1 lapis cat dasar, 2 lapis ca
1 Bahan
Wall filler ex. ICI Dulux 0.100 kg 22,880.00
Cat dasar ( Cat dasar 1 x ) 0.100 lt 91,850.00
Cat jenis Anti bakteri (cat penutup 2 x) 0.260 lt 91,850.00
2 Tenaga
Pekerja 0.020 oh 89,320.00
Tukang cat 0.063 oh 137,445.00
Kepala tukang 0.0063 oh 157,850.00
Mandor 0.0030 oh 157,850.00
Pengecatan 1 m2 tembok baru interior Anti bakteri (1 lapis plamuur, 1 lapis cat dasar, 2
10c 1 m2
lapis cat penutup)
10d 1 m2 Pengecatan plafon/dak beton baru jenis AEP ( lapis cat dasar, 2 lapis cat penutup)
1 Bahan
Plamir - kg 22,880.00
Cat dasar 1 x 0.100 kg 31,350.00
Cat penutup 2 x 0.260 kg 31,350.00
2 Tenaga
Pekerja 0.025 oh 89,320.00
Tukang cat 0.065 oh 137,445.00
Kepala tukang 0.0065 oh 157,850.00
Mandor 0.0025 oh 157,850.00
10d 1 m2 Pengecatan plafon/dak beton baru jenis AEP ( lapis cat dasar, 2 lapis cat penutup)
10e 1 m2 Pengecatan plafon/dak beton baru Weathershield (1 lapis cat dasar, 2 lapis cat penutup)
1 Bahan
Plamir - kg 22,880.00
Cat dasar 1 x 0.100 kg 48,400.00
Cat penutup 2 x 0.260 kg 48,400.00
2 Tenaga
A4.7.1. Pek-Cat / HAL 400 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
HARGA SATUAN
NO. URAIAN KOEF SATUAN
Rp.
1 2 3 4 5
10e 1 m2 Pengecatan plafon/dak beton baru Weathershield (1 lapis cat dasar, 2 lapis cat penutup)
10f 1 m2 Pengecatan plafon/dak beton baru jenis cat anti bakteri (1 lapis cat dasar, 2 lapis cat penutup)
1 Bahan
Plamir - kg 22,880.00
Cat dasar 1 x 0.100 kg 91,850.00
Cat penutup 2 x 0.260 kg 91,850.00
2 Tenaga
Pekerja 0.025 oh 89,320.00
Tukang cat 0.065 oh 137,445.00
Kepala tukang 0.0065 oh 157,850.00
Mandor 0.0025 oh 157,850.00
Pengecatan plafon/dak beton baru jenis cat anti bakteri (1 lapis cat dasar, 2 lapis cat
10f 1 m2
penutup)
10g 1 m2 Pengecatan plafon/dak beton baru jenis cat AGE (1 lapis cat dasar, 2 lapis cat penutup)
1 Bahan
Plamir - kg 22,880.00
Cat dasar 1 x 0.100 kg 63,030.00
Cat penutup 2 x 0.260 kg 63,030.00
2 Tenaga
Pekerja 0.025 oh 89,320.00
Tukang cat 0.065 oh 137,445.00
Kepala tukang 0.0065 oh 157,850.00
Mandor 0.0025 oh 157,850.00
10g 1 m2 Pengecatan plafon/dak beton baru jenis cat AGE (1 lapis cat dasar, 2 lapis cat penutup)
11 1 m2 Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
1 Bahan
Wall filler ex. ICI Dulux - kg 22,880.00
Cat dasar ex. Catilax 0.120 lt 31,790.00
Cat dasar ex. Catilax jenis AEP 0.180 lt 31,790.00
2 Tenaga
Pekerja 0.028 oh 89,320.00
Tukang cat 0.042 oh 137,445.00
Kepala tukang 0.0042 oh 157,850.00
Mandor 0.0030 oh 157,850.00
2 Tenaga
Pekerja 0.028 oh 89,320.00
Tukang cat 0.042 oh 137,445.00
Kepala tukang 0.0042 oh 157,850.00
Mandor 0.0025 oh 157,850.00
2 Tenaga
Pekerja 0.150 oh 89,320.00
Tukang cat 0.001 oh 137,445.00
Kepala tukang 0.0001 oh 157,850.00
Mandor 0.0025 oh 157,850.00
A4.7.1. Pek-Cat / HAL 402 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
HARGA SATUAN
NO. URAIAN KOEF SATUAN
Rp.
1 2 3 4 5
2 Tenaga
Pekerja 0.040 oh 89,320.00
Tukang cat 0.005 oh 137,445.00
Kepala tukang 0.0005 oh 157,850.00
Mandor 0.0025 oh 157,850.00
2 Tenaga
Pekerja 0.020 oh 89,320.00
Tukang cat 0.200 oh 137,445.00
Kepala tukang 0.020 oh 157,850.00
Mandor 0.010 oh 157,850.00
2 Tenaga
Pekerja 0.250 oh 89,320.00
Tukang cat 0.225 oh 137,445.00
Kepala tukang 0.023 oh 157,850.00
Mandor 0.008 oh 157,850.00
2 Tenaga
Pekerja 0.006 oh 89,320.00
Tukang cat 0.006 oh 137,445.00
Kepala tukang 0.0225 oh 157,850.00
Mandor 0.0075 oh 157,850.00
Pengecatan permukaan baja lapis seng (galpanis) secara manual sistem 4 lapis cat
18 1 m2
konvensional dengan tebal 200 um
1 m2 Pengecatan permukaan baja lapis seng
19 (galpanis) secara manual sistem 4 lapis cat
mutakhir dengan tebal 200 um
1 Bahan
Cat 0.300 kg 75,000.00
2 Tenaga
A4.7.1. Pek-Cat / HAL 404 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
HARGA SATUAN
NO. URAIAN KOEF SATUAN
Rp.
1 2 3 4 5
Pengecatan permukaan baja lapis seng (galpanis) secara manual sistem 4 lapis cat
19 1 m2
mutakhir dengan tebal 200 um
1 m2 Pengecatan permukaan baja lapis seng
20 (galvanis) secara manual sistem 3 lapis cat
konvensional dengan tebal 200 um
1 Bahan
Cat dasar 0.110 kg 75,000.00
Cat antara 0.170 kg 75,000.00
Cat penutup 0.080 kg 75,000.00
Jumlah (1).
2 Tenaga
Pekerja 0.500 oh 89,320.00
Tukang cat 0.800 oh 137,445.00
Kepala tukang 0.300 oh 157,850.00
Mandor 0.200 oh 157,850.00
Pengecatan permukaan baja lapis seng (galvanis) secara manual sistem 3 lapis cat
20 1 m2
konvensional dengan tebal 200 um
21 1 m2 Pengecatan permukaan baja lapis seng (galvani) secara semprot (airless spray) dengan sistem
1 Bahan
Cat dasar 0.300 kg 75,000.00
2 Tenaga
Pekerja 0.400 oh 89,320.00
Tukang cat 0.700 oh 137,445.00
Kepala tukang 0.200 oh 157,850.00
Mandor 0.200 oh 157,850.00
Pengecatan permukaan baja lapis seng (galvani) secara semprot (airless spray) dengan
21 1 m2
sistem 1 lapis cat mutakhir dengan tebal 200 um
22 10 m2 Pengecatan melamik
1 Bahan
Wood filer ex. Imfra 1.500 kg 59,400.00
Wood Stend 1.500 kg 47,300.00
Sending Seller 1.500 kg 38,500.00
Clear 2.400 kg 44,000.00
Tiner Serba Guna 2.000 ltr 19,800.00
Ampelas 6.000 lbr 6,021.40
2 Tenaga
Pekerja 2.0000 oh 89,320.00
Tukang cat 12.0000 oh 137,445.00
Kepala tukang 1.2000 oh 157,850.00
Mandor 0.1000 oh 157,850.00
22 10 m2 Pengecatan melamik
22 1 m2 Pengecatan melamik
23 10 m2 Pengecatan Duco bidang kayu baru/besi ( 1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
1 Bahan
Dempul duco setara mutu tinggi 1.5000 kg 38,500.00
Meni 1.9200 kg 37,180.00
Cat kayu DUCO setara mutu tinggi 3.0000 kg 55,550.00
Hampelas 6.0000 lb 6,021.40
Thiner ( minyak cat A ) 2.0000 lt 19,800.00
2 Tenaga
Pekerja 2.0000 oh 89,320.00
Tukang cat 12.0000 oh 137,445.00
Kepala tukang 1.2000 oh 157,850.00
Mandor 0.1000 oh 157,850.00
Pengecatan Duco bidang kayu baru/besi ( 1 lapis plamir), 1 lapis cat dasar, 3 lapis cat
23 10 m2
penutup
Pengecatan Duco bidang kayu baru/besi ( 1 lapis plamir), 1 lapis cat dasar, 3 lapis cat
23 1 m2
penutup
24 1 m2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
1 Bahan
Cat dasar 0.120 kg 31,790.00
Cat penutup 2 x 0.180 kg 31,790.00
2 Tenaga
Pekerja 0.028 oh 89,320.00
Tukang cat 0.042 oh 137,445.00
Kepala tukang 0.0042 oh 157,850.00
Mandor 0.0025 oh 157,850.00
2 Tenaga
Pekerja 0.040 oh 89,320.00
Tukang cat 0.125 oh 137,445.00
Kepala tukang 0.0125 oh 157,850.00
Mandor 0.0020 oh 157,850.00
2 Tenaga
Pekerja 0.160 oh 89,320.00
Tukang cat 0.160 oh 137,445.00
Kepala tukang 0.016 oh 157,850.00
Mandor 0.0025 oh 157,850.00
1,125.00
1,125.00
13,792.63
13,398.00
-
-
394.63
Jumlah 14,917.63
Overhead & keuntungan 10% : 1,491.76
Jumlah : 16,409.39
Dibulatkan : 16,400.00
375.00
375.00
13,792.63
13,398.00
-
-
394.63
Jumlah 14,167.63
Overhead & keuntungan 10% : 1,416.76
Jumlah : 15,584.39
Dibulatkan : 15,500.00
375.00
375.00
14,660.80
13,398.00
-
-
1,262.80
Jumlah 15,035.80
Overhead & keuntungan 10% : 1,503.58
Jumlah : 16,539.38
Dibulatkan : 16,500.00
36,890.70
7,436.00
4,669.50
9,798.80
14,986.40
333.30
594.00
1,204.28
8,910.06
6,252.40
1,237.01
947.10
473.55
Jumlah 45,800.76
A4.7.1. Pek-Cat / HAL 409 DARI 616
SUB. JUMLAH JUMLAH
Rp. Rp.
6 7
42,078.30
7,436.00
4,669.50
9,798.80
20,174.00
333.30
594.00
1,204.28
21,789.08
6,252.40
14,431.73
631.40
473.55
Jumlah 63,867.38
Overhead & keuntungan 10% : 6,386.74
Jumlah : 70,254.11
Dibulatkan : 70,200.00
Err:509
Err:509
8,910.06
6,252.40
1,237.01
947.10
473.55
Jumlah Err:509
Overhead & keuntungan 10% : Err:509
Jumlah : Err:509
Dibulatkan : Err:509
23,442.80
6,750.00
4,650.00
12,042.80
24,990.35
-
21,991.20
2,525.60
473.55
Jumlah 48,433.15
Overhead & keuntungan 10% : 4,843.32
Jumlah : 53,276.47
Dibulatkan : 53,200.00
9,030.04
5,250.00
2,970.00
602.14
207.90
39,202.63
14,291.20
21,991.20
2,525.60
394.63
Jumlah 48,232.67
Overhead & keuntungan 10% : 4,823.27
Jumlah : 53,055.93
Dibulatkan : 53,000.00
13,574.00
2,288.00
3,135.00
8,151.00
11,913.44
1,786.40
A4.7.1. Pek-Cat / HAL 411 DARI 616
SUB. JUMLAH JUMLAH
Rp. Rp.
6 7
8,659.04
994.46
473.55
Jumlah 25,487.44
Overhead & keuntungan 10% : 2,548.74
Jumlah : 28,036.18
Dibulatkan :
28,000.00
21,967.00
4,543.00
4,840.00
12,584.00
11,834.52
1,786.40
8,659.04
994.46
394.63
Jumlah 33,801.52
Overhead & keuntungan 10% : 3,380.15
Jumlah : 37,181.67
Dibulatkan :
37,100.00
11,913.44
1,786.40
8,659.04
994.46
473.55
Jumlah 36,892.24
Overhead & keuntungan 10% : 3,689.22
Jumlah : 40,581.46
Dibulatkan :
40,500.00
akteri (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
35,354.00
2,288.00
9,185.00
23,881.00
11,913.44
1,786.40
8,659.04
994.46
473.55
Jumlah 47,267.44
Overhead & keuntungan 10% : 4,726.74
Jumlah : 51,994.18
Dibulatkan :
51,900.00
11,286.00
-
3,135.00
8,151.00
12,587.58
2,233.00
8,933.93
1,026.03
394.63
Jumlah 23,873.58
Overhead & keuntungan 10% : 2,387.36
Jumlah : 26,260.93
Dibulatkan : 26,200.00
17,424.00
-
4,840.00
12,584.00
12,587.58
A4.7.1. Pek-Cat / HAL 413 DARI 616
SUB. JUMLAH JUMLAH
Rp. Rp.
6 7
2,233.00
8,933.93
1,026.03
394.63
Jumlah 30,011.58
Overhead & keuntungan 10% : 3,001.16
Jumlah : 33,012.73
Dibulatkan :
33,000.00
nti bakteri (1 lapis cat dasar, 2 lapis cat penutup)
33,066.00
-
9,185.00
23,881.00
12,587.58
2,233.00
8,933.93
1,026.03
394.63
Jumlah 45,653.58
Overhead & keuntungan 10% : 4,565.36
Jumlah : 50,218.93
Dibulatkan : 50,200.00
22,690.80
-
6,303.00
16,387.80
12,587.58
2,233.00
8,933.93
1,026.03
394.63
Jumlah 35,278.38
Overhead & keuntungan 10% : 3,527.84
Jumlah : 38,806.21
Dibulatkan : 38,800.00
9,537.00
-
3,814.80
5,722.20
9,410.17
2,500.96
5,772.69
662.97
473.55
Jumlah 18,947.17
Overhead & keuntungan 10% : 1,894.72
Jumlah : 20,841.89
Dibulatkan : 20,800.00
600.00
600.00
9,331.25
2,500.96
5,772.69
662.97
394.63
Jumlah 9,931.25
Overhead & keuntungan 10% : 993.12
Jumlah : 10,924.37
Dibulatkan : 10,900.00
1,702.14
602.14
500.00
-
600.00
13,945.86
13,398.00
137.45
15.79
394.63
A4.7.1. Pek-Cat / HAL 415 DARI 616
SUB. JUMLAH JUMLAH
Rp. Rp.
6 7
Jumlah 15,648.00
Overhead & keuntungan 10% : 1,564.80
Jumlah : 17,212.79
Dibulatkan : 17,200.00
1,704.28
1,204.28
500.00
1,200.00
4,733.58
3,572.80
687.23
78.93
394.63
Jumlah 6,437.86
Overhead & keuntungan 10% : 643.79
Jumlah : 7,081.64
Dibulatkan : 7,000.00
3,925.90
3,718.00
207.90
34,010.90
1,786.40
27,489.00
3,157.00
1,578.50
Jumlah 37,936.80
Overhead & keuntungan 10% : 3,793.68
Jumlah : 41,730.48
Dibulatkan : 41,700.00
8,242.52
3,718.00
207.90
4,316.62
57,990.63
22,330.00
30,925.13
3,551.63
1,183.88
Jumlah 66,233.15
Overhead & keuntungan 10% : 6,623.31
Jumlah : 72,856.46
Dibulatkan : 72,800.00
17,514.62
3,500.00
3,500.00
3,000.00
3,000.00
198.00
4,316.62
6,096.09
535.92
824.67
3,551.63
1,183.88
Jumlah 23,610.71
Overhead & keuntungan 10% : 2,361.07
Jumlah : 25,971.78
Dibulatkan :
25,900.00
22,500.00
22,500.00
6,096.09
A4.7.1. Pek-Cat / HAL 417 DARI 616
SUB. JUMLAH JUMLAH
Rp. Rp.
6 7
535.92
824.67
3,551.63
1,183.88
Jumlah 28,596.09
Overhead & keuntungan 10% : 2,859.61
Jumlah : 31,455.70
Dibulatkan :
31,400.00
27,000.00
8,250.00
12,750.00
6,000.00
27,000.00
233,541.00
44,660.00
109,956.00
47,355.00
31,570.00
Jumlah 260,541.00
Overhead & keuntungan 10% : 26,054.10
Jumlah : 286,595.10
Dibulatkan :
286,500.00
ani) secara semprot (airless spray) dengan sistem 1 lapis cat mutakhir dengan tebal 200 um
22,500.00
22,500.00
195,079.50
35,728.00
96,211.50
31,570.00
31,570.00
Jumlah 217,579.50
Overhead & keuntungan 10% : 21,757.95
Jumlah : 239,337.45
Dibulatkan :
239,300.00
399,128.40
89,100.00
70,950.00
57,750.00
105,600.00
39,600.00
36,128.40
2,033,185.00
178,640.00
1,649,340.00
189,420.00
15,785.00
Jumlah 2,432,313.40
Overhead & keuntungan 10% : 243,231.34
Jumlah : 2,675,544.74
Dibulatkan : 2,675,500.00
Dibulatkan : 267,550.00
apis plamir), 1 lapis cat dasar, 3 lapis cat penutup
313,764.00
57,750.00
71,385.60
166,650.00
36,128.40
39,600.00
2,033,185.00
178,640.00
1,649,340.00
189,420.00
15,785.00
Jumlah 2,346,949.00
Overhead & keuntungan 10% : 234,694.90
Jumlah : 2,581,643.90
Dibulatkan :
2,581,600.00
Dibulatkan :
258,160.00
9,537.00
3,814.80
5,722.20
9,331.25
2,500.96
5,772.69
662.97
394.63
Jumlah 18,868.25
Overhead & keuntungan 10% : 1,886.82
Jumlah : 20,755.07
Dibulatkan : 20,700.00
827,750.00
827,750.00
23,042.25
3,572.80
17,180.63
1,973.13
315.70
Jumlah 850,792.25
Overhead & keuntungan 10% : 85,079.23
Jumlah : 935,871.48
Dibulatkan : 935,800.00
46,790.00
93,580.00
140,370.00
130,610.59
123,920.35
5,305.58
1,384.67
39,202.63
14,291.20
21,991.20
2,525.60
394.63
Jumlah 169,813.21
Overhead & keuntungan 10% : 16,981.32
Jumlah : 186,794.54
Dibulatkan : 186,700.00
1 2 3 4
1 1 Unit Closet duduk ex. TOTO Type CW 660 NJ / SW660J + Ecowasher TCW 03 SL
a. Bahan:
Closet duduk ex. TOTO Type CW660NJ - SW660J + Ecowa 1.000 set
Perlengkapan 0.06 %
b. Upah:
- Tukang 1.100 hari
- Pekerja 3.300 hari
- Kepala tukang 0.300 hari
- Mandor 0.160 hari
1 1 Unit Closet duduk ex. TOTO Type CW 660 NJ / SW660J + Ecowasher TCW 03 SL
1a 1 Unit Closet duduk setara TOTO Type C704L - SW784JP + Ecowasher TCW 03 SL
a. Bahan:
Closet duduk setara TOTO Type C704L - SW784JP +
Ecowasher TCW 03 SL 1.000 set
Perlengkapan 0.06 %
b. Upah:
- Tukang 1.100 hari
- Pekerja 3.300 hari
- Kepala tukang 0.300 hari
- Mandor 0.160 hari
1a 1 Unit Closet duduk setara TOTO Type C704L - SW784JP + Ecowasher TCW 03 SL
2 1 Unit Closet jongkok ex Toto type CE 9 / TV 150 NWV 12
a. Bahan:
- CE 9 1.000 bh
- Semen 0.120 zak
- Pasir pasang 0.010 m3
b. Upah:
- Tukang 1.500 hari
- Pekerja 1.000 hari
- Kepala tukang 0.300 hari
- Mandor 0.160 hari
1 2 3 4
1 2 3 4
1 2 3 4
- TL220D
Perlengkapan 12% Lot
b. Upah:
- Tukang 1.450 hari
- Pekerja 1.200 hari
- Kepala tukang 0.150 hari
- Mandor 0.075 hari
12 1 Unit Kitchen zink setara Standar Royal tipe caroline 1 lobang complete set
a. Bahan:
Kitchen zink setara Standar Royal tipe caroline 1 lobang
complete set 1.000 unit
b. Upah:
- Pekerja 0.150 hari
- Tukang 0.300 hari
- Kepala tukang 0.030 oh
- Mandor 0.0015 hari
12 1 Unit Kitchen zink setara Standar Royal tipe caroline 1 lobang complete set
1 2 3 4
12a 1 Unit Kitchen zink setara Standar Royal tipe Elizabeth 2 lobang complete set
a. Bahan:
Kitchen zink setara Standar Royal tipe Elizabeth 2 lobang
complete set 1.000 unit
b. Upah:
- Tukang 0.300 hari
- Pekerja 0.150 hari
- Kepala tukang 0.030 hari
- Mandor 0.0015 hari
12a 1 Unit Kitchen zink setara Standar Royal tipe Elizabeth 2 lobang complete set
12b 1 Unit Kitchen zink setara Standar Royal tipe angela 1 lobang complete set
a. Bahan:
Kitchen zink setara Standar Royal tipe angela 1 lobang
complete set 1.000 unit
b. Upah:
- Tukang 1.450 hari
- Pekerja 0.725 hari
- Kepala tukang 0.145 hari
- Mandor 0.073 hari
12b 1 Unit Kitchen zink setara Standar Royal tipe angela 1 lobang complete set
12c 1 Unit Laundry sink setara TOTO tipe SK322E-T30ARQ13N
a. Bahan:
Laundry sink setara TOTO tipe SK322E-T30ARQ13N 1.000 unit
b. Upah:
- Tukang 1.450 hari
- Pekerja 0.725 hari
- Kepala tukang 0.145 hari
- Mandor 0.073 hari
1 2 3 4
b. Upah:
- Tukang 1.450 hari
- Pekerja 0.725 hari
- Kepala tukang 0.145 hari
- Mandor 0.073 hari
1 2 3 4
14e 1 Unit Fixed Shower Head setara TOTO tipe TX465SMN + TX452SO
a. Bahan:
Fixed Shower Head setara TOTO tipe TX465SMN + TX452 1.000 unit
b. Upah:
- Tukang 0.150 hari
1 2 3 4
14e 1 Unit Fixed Shower Head setara TOTO tipe TX465SMN + TX452SO
1 2 3 4
1 2 3 4
1 2 3 4
14o 1 Unit Soap holder/Tempat sabun setara TOTO tipeS 156 NV1
a. Bahan:
Soap holder/Tempat sabun setara TOTO tipeS 156 NV1 1.000 bh
b. Upah:
- Tukang 0.055 hari
- Pekerja 0.028 hari
- Kepala tukang 0.010 hari
- Mandor 0.005 hari
14o 1 Unit Soap holder/Tempat sabun setara TOTO tipeS 156 NV1
14p 1 Unit Grab bar Nylon setara tipe KFS 7C
a. Bahan:
Grab bar Nylon setara tipe KFS 7C 1.000 bh
b. Upah:
- Tukang 0.100 hari
- Pekerja 0.050 hari
- Kepala tukang 0.010 hari
- Mandor 0.005 hari
1 2 3 4
b. Upah:
- Tukang 0.100 hari
- Pekerja 0.050 hari
- Kepala tukang 0.010 hari
- Mandor 0.005 hari
6,599,560.00
6,226,000.00 6,226,000.00
6,226,000.00 373,560
518,556.50
137,445.00 151,189.50
89,320.00 294,756.00
157,850.00 47,355.00
157,850.00 25,256.00
Jumlah 7,118,116.50
Overhead & keuntungan 10% : 711,811.65
Jumlah : 7,829,928.15
Dibulatkan : 7,829,900.00
8,395,200.00
7,920,000.00 7,920,000.00
7,920,000.00 475,200
518,556.50
137,445.00 151,189.50
89,320.00 294,756.00
157,850.00 47,355.00
157,850.00 25,256.00
Jumlah 8,913,756.50
Overhead & keuntungan 10% : 891,375.65
Jumlah : 9,805,132.15
Dibulatkan : 9,805,100.00
3,496,687.70
3,487,000.000 3,487,000.00
66,110.000 7,933.20
175,450.000 1,754.50
368,098.50
137,445.00 206,167.50
89,320.00 89,320.00
157,850.00 47,355.00
157,850.00 25,256.00
Jumlah 3,864,786.20
Overhead & keuntungan 10% : 386,478.62
Jumlah : 4,251,264.82
Dibulatkan : 4,251,200.00
317,687.70
308,000.000 308,000.00
66,110.000 7,933.20
175,450.000 1,754.50
368,098.50
137,445.00 206,167.50
89,320.00 89,320.00
157,850.00 47,355.00
157,850.00 25,256.00
Jumlah 685,786.20
A.5.1.1.SANITASI / HAL 434 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
6,959,487.70
5,346,000.000 5,346,000.00
66,110.000 7,933.20
175,450.000 1,754.50
5,346,000.00 1,603,800
250,442.50
137,445.00 137,445.00
89,320.00 89,320.00
157,850.00 15,785.00
157,850.00 7,892.50
Jumlah 7,209,930.20
Overhead & keuntungan 10% : 720,993.02
Jumlah : 7,930,923.22
Dibulatkan : 7,930,900.00
1,597,420.00
1,507,000.000 1,507,000.00
1,507,000.00 90,420
250,442.50
137,445.00 137,445.00
89,320.00 89,320.00
157,850.00 15,785.00
157,850.00 7,892.50
Jumlah 1,847,862.50
Overhead & keuntungan 10% : 184,786.25
Jumlah : 2,032,648.75
Dibulatkan : 2,032,600.00
3,949,623.70
3,517,800.000 3,517,800.00
66,110.000 7,933.20
175,450.000 1,754.50
3,517,800.00 422,136
339,627.75
137,445.00 199,295.25
89,320.00 107,184.00
157,850.00 23,677.50
157,850.00 9,471.00
Jumlah 4,289,251.45
Overhead & keuntungan 10% : 428,925.15
Jumlah : 4,718,176.60
Dibulatkan : 4,718,100.00
3,873,408.00
3,458,400.000 3,458,400.00
3,458,400.00 415,008
341,995.50
137,445.00 199,295.25
89,320.00 107,184.00
157,850.00 23,677.50
157,850.00 11,838.75
Jumlah 4,215,403.50
Overhead & keuntungan 10% : 421,540.35
Jumlah : 4,636,943.85
Dibulatkan : 4,636,900.00
3,617,152.00
3,229,600.000 3,229,600.00
3,229,600.00 387,552
341,995.50
137,445.00 199,295.25
89,320.00 107,184.00
157,850.00 23,677.50
157,850.00 11,838.75
Jumlah 3,959,147.50
Overhead & keuntungan 10% : 395,914.75
Jumlah : 4,355,062.25
Dibulatkan : 4,355,000.00
532,812.50
532,812.50 532,812.50
59,603.78
89,320.00 13,398.00
137,445.00 41,233.50
157,850.00 4,735.50
157,850.00 236.78
Jumlah 592,416.28
Overhead & keuntungan 10% : 59,241.63
Jumlah : 651,657.90
Dibulatkan : 651,600.00
893,750.00
893,750.00 893,750.00
59,603.78
137,445.00 41,233.50
89,320.00 13,398.00
157,850.00 4,735.50
157,850.00 236.78
Jumlah 953,353.78
Overhead & keuntungan 10% : 95,335.38
Jumlah : 1,048,689.15
Dibulatkan : 1,048,600.00
446,875.00
446,875.00 446,875.00
298,384.63
137,445.00 199,295.25
89,320.00 64,757.00
157,850.00 22,888.25
157,850.00 11,444.13
Jumlah 745,259.63
Overhead & keuntungan 10% : 74,525.96
Jumlah : 819,785.59
Dibulatkan : 819,700.00
10,692,000.00
10,692,000.00 10,692,000.00
298,384.63
137,445.00 199,295.25
89,320.00 64,757.00
157,850.00 22,888.25
157,850.00 11,444.13
Jumlah 10,990,384.63
Overhead & keuntungan 10% : 1,099,038.46
Jumlah : 12,089,423.09
Dibulatkan : 12,089,400.00
4,620,000.00
4,620,000.00 4,620,000.00
298,384.63
137,445.00 199,295.25
89,320.00 64,757.00
157,850.00 22,888.25
157,850.00 11,444.13
Jumlah 4,918,384.63
Overhead & keuntungan 10% : 491,838.46
Jumlah : 5,410,223.09
Dibulatkan : 5,410,200.00
7,953,000.00
7,953,000.00 7,953,000.00
298,384.63
137,445.00 199,295.25
89,320.00 64,757.00
157,850.00 22,888.25
157,850.00 11,444.13
Jumlah 8,251,384.63
Overhead & keuntungan 10% : 825,138.46
Jumlah : 9,076,523.09
Dibulatkan : 9,076,500.00
502,700.00
502,700.000 502,700.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 523,278.25
Overhead & keuntungan 10% : 52,327.83
Jumlah : 575,606.08
Dibulatkan : 575,600.00
464,200.00
464,200.000 464,200.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 484,778.25
Overhead & keuntungan 10% : 48,477.83
Jumlah : 533,256.08
Dibulatkan : 533,200.00
682,000.00
682,000.000 682,000.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 702,578.25
Overhead & keuntungan 10% : 70,257.83
Jumlah : 772,836.08
Dibulatkan : 772,800.00
962,500.00
962,500.000 962,500.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 983,078.25
Overhead & keuntungan 10% : 98,307.83
Jumlah : 1,081,386.08
Dibulatkan : 1,081,300.00
3,520,000.00
3,520,000.000 3,520,000.00
30,472.75
137,445.00 20,616.75
89,320.00 6,699.00
157,850.00 2,367.75
157,850.00 789.25
Jumlah 3,550,472.75
Overhead & keuntungan 10% : 355,047.28
Jumlah : 3,905,520.03
Dibulatkan : 3,905,500.00
1,962,400.00
1,962,400.000 1,962,400.00
30,472.75
137,445.00 20,616.75
89,320.00 6,699.00
157,850.00 2,367.75
157,850.00 789.25
Jumlah 1,992,872.75
Overhead & keuntungan 10% : 199,287.28
Jumlah : 2,192,160.03
Dibulatkan : 2,192,100.00
638,000.00
638,000.000 638,000.00
12,383.53
137,445.00 7,559.48
89,320.00 2,456.30
157,850.00 1,578.50
157,850.00 789.25
Jumlah 650,383.53
Overhead & keuntungan 10% : 65,038.35
Jumlah : 715,421.88
Dibulatkan : 715,400.00
1,089,000.00
1,089,000.000 1,089,000.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 1,109,578.25
Overhead & keuntungan 10% : 110,957.83
Jumlah : 1,220,536.08
Dibulatkan : 1,220,500.00
5,445,000.00
5,445,000.000 5,445,000.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 5,465,578.25
Overhead & keuntungan 10% : 546,557.83
Jumlah : 6,012,136.08
Dibulatkan : 6,012,100.00
4,015,000.00
4,015,000.000 4,015,000.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 4,035,578.25
Overhead & keuntungan 10% : 403,557.83
Jumlah : 4,439,136.08
Dibulatkan : 4,439,100.00
1,815,000.00
1,815,000.000 1,815,000.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 1,835,578.25
Overhead & keuntungan 10% : 183,557.83
Jumlah : 2,019,136.08
Dibulatkan : 2,019,100.00
1,028,500.00
1,028,500.000 1,028,500.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
A.5.1.1.SANITASI / HAL 442 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
157,850.00 1,578.50
157,850.00 789.25
Jumlah 1,049,078.25
Overhead & keuntungan 10% : 104,907.83
Jumlah : 1,153,986.08
Dibulatkan : 1,153,900.00
1,996,500.00
1,996,500.000 1,996,500.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 2,017,078.25
Overhead & keuntungan 10% : 201,707.83
Jumlah : 2,218,786.08
Dibulatkan : 2,218,700.00
201,300.00
201,300.000 201,300.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 221,878.25
Overhead & keuntungan 10% : 22,187.83
Jumlah : 244,066.08
Dibulatkan : 244,000.00
1,903,000.00
1,903,000.000 1,903,000.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 1,923,578.25
Overhead & keuntungan 10% : 192,357.83
Jumlah : 2,115,936.08
Dibulatkan : 2,115,900.00
275,000.00
275,000.000 275,000.00
12,383.53
137,445.00 7,559.48
89,320.00 2,456.30
157,850.00 1,578.50
157,850.00 789.25
Jumlah 287,383.53
Overhead & keuntungan 10% : 28,738.35
Jumlah : 316,121.88
Dibulatkan : 316,100.00
2,178,000.00
2,178,000.000 2,178,000.00
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 2,198,578.25
Overhead & keuntungan 10% : 219,857.83
Jumlah : 2,418,436.08
Dibulatkan : 2,418,400.00
-
- -
20,578.25
137,445.00 13,744.50
89,320.00 4,466.00
157,850.00 1,578.50
157,850.00 789.25
Jumlah 20,578.25
Overhead & keuntungan 10% : 2,057.83
Jumlah : 22,636.08
Dibulatkan : 22,600.00
1 2 3 4
1 2 3 4
1 2 3 4
Bahan
Pipa PVC Ø 4" 1.200 m'
Perlengkapan 35% Harga Pipa 1.000 Ls
Tenaga Kerja
Pekerja 0.060 0rg/hr
Tukang Pipa 0.120 0rg/hr
Kepala Tukang 0.012 0rg/hr
Mandor 0.012 0rg/hr
1 2 3 4
5 6 7
52,034.40
32,120.00 38,544.00
13,490.40 13,490.40
12,725.02
89,320.00 3,215.52
137,445.00 8,246.70
157,850.00 947.10
157,850.00 315.70
Jumlah 64,759.42
Overhead & keuntungan 10% : 6,475.94
Jumlah : 71,235.36
Dibulatkan : 71,200.00
57,736.80
35,640.00 42,768.00
14,968.80 14,968.80
12,725.02
89,320.00 3,215.52
137,445.00 8,246.70
157,850.00 947.10
157,850.00 315.70
Jumlah 70,461.82
Overhead & keuntungan 10% : 7,046.18
Jumlah : 77,508.00
Dibulatkan : 77,500.00
76,269.60
47,080.00 56,496.00
19,773.60 19,773.60
12,725.02
89,320.00 3,215.52
137,445.00 8,246.70
157,850.00 947.10
157,850.00 315.70
Jumlah 88,994.62
Overhead & keuntungan 10% : 8,899.46
Jumlah : 97,894.08
Dibulatkan : 97,800.00
94,802.40
58,520.00 70,224.00
24,578.40 24,578.40
12,725.02
89,320.00 3,215.52
137,445.00 8,246.70
157,850.00 947.10
157,850.00 315.70
Jumlah 107,527.42
Overhead & keuntungan 10% : 10,752.74
Jumlah : 118,280.16
Dibulatkan : 118,200.00
A.5.1.1 Pek. Pemipaan / HAL 450 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
5 6 7
98,366.40
60,720.00 72,864.00
25,502.40 25,502.40
19,087.53
89,320.00 4,823.28
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 473.55
Jumlah 117,453.93
Overhead & keuntungan 10% : 11,745.39
Jumlah : 129,199.32
Dibulatkan : 129,100.00
138,996.00
85,800.00 102,960.00
36,036.00 36,036.00
19,087.53
89,320.00 4,823.28
137,445.00 12,370.05
157,850.00 1,420.65
157,850.00 473.55
Jumlah 158,083.53
Overhead & keuntungan 10% : 15,808.35
Jumlah : 173,891.88
Dibulatkan : 173,800.00
197,445.60
121,880.00 146,256.00
51,189.60 51,189.60
21,153.83
89,320.00 4,421.34
137,445.00 13,607.06
157,850.00 1,562.72
157,850.00 1,562.72
Jumlah 218,599.43
Overhead & keuntungan 10% : 21,859.94
Jumlah : 240,459.37
Dibulatkan : 240,400.00
277,992.00
171,600.00 205,920.00
72,072.00 72,072.00
23,269.21
89,320.00 4,863.47
137,445.00 14,967.76
157,850.00 1,718.99
157,850.00 1,718.99
Jumlah 301,261.21
Overhead & keuntungan 10% : 30,126.12
Jumlah : 331,387.33
Dibulatkan : 331,300.00
5 6 7
385,624.80
238,040.00 285,648.00
99,976.80 99,976.80
25,596.13
89,320.00 5,349.82
137,445.00 16,464.54
157,850.00 1,890.89
157,850.00 1,890.89
Jumlah 411,220.93
Overhead & keuntungan 10% : 41,122.09
Jumlah : 452,343.02
Dibulatkan : 452,300.00
5 6 7
768,754.80
474,540.00 569,448.00
199,306.80 199,306.80
28,155.74
89,320.00 5,884.80
137,445.00 18,110.99
157,850.00 2,079.97
157,850.00 2,079.97
Jumlah 796,910.54
Overhead & keuntungan 10% : 79,691.05
Jumlah : 876,601.60
Dibulatkan : 876,600.00
1,151,884.80
711,040.00 853,248.00
298,636.80 298,636.80
30,971.32
89,320.00 6,473.28
137,445.00 19,922.09
157,850.00 2,287.97
157,850.00 2,287.97
Jumlah 1,182,856.12
Overhead & keuntungan 10% : 118,285.61
Jumlah : 1,301,141.73
Dibulatkan : 1,301,100.00
2,102,760.00
### 1,557,600.00
545,160.00 545,160.00
34,068.45
89,320.00 7,120.61
137,445.00 21,914.30
157,850.00 2,516.77
157,850.00 2,516.77
Jumlah 2,136,828.45
Overhead & keuntungan 10% : 213,682.84
Jumlah : 2,350,511.29
Dibulatkan : 2,350,500.00
3,812,054.40
### 2,823,744.00
988,310.40 988,310.40
37,475.29
89,320.00 7,832.67
137,445.00 24,105.73
157,850.00 2,768.44
157,850.00 2,768.44
Jumlah 3,849,529.69
Overhead & keuntungan 10% : 384,952.97
Jumlah : 4,234,482.66
Dibulatkan : 4,234,400.00
1 2 3 4
1 1m' Memasang pipa penyalur air limbah jenis pipa tanah, diameter 15 cm
2 1m' Memasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm
a. Bahan
- Pipa tanah dia 1/2 20 cm 1.600 bh
- Semen portland 0.017 zak
- Pasir pasang 0.014 m3
- Pasir urug 0.014 m3
b. Tenaga
- Pekerja 0.080 oh
- Tukang batu 0.040 oh
- Kepala tukang 0.004 oh
- Mandor 0.007 oh
2 1m' Memasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm
3 1m' Memasang pipa penyalur air limbah jenis pipa beton, diameter 1/2 20 cm
a. Bahan
Pipa beton dia 1/2 20 cm 1.100 bh
Semen portland 0.017 zak
Pasir pasang 0.014 m3
Pasir urug 0.014 m3
b. Tenaga
- Pekerja 0.080 oh
- Tukang batu 0.040 oh
- Kepala tukang 0.004 oh
- Mandor 0.007 oh
3 1m' Memasang pipa penyalur air limbah jenis pipa beton, diameter 1/2 20 cm
4 1m' Memasang pipa penyalur air limbah jenis pipa beton, diameter 1/2 30 cm
a. Bahan
Pipa beton dia 1/2 30 cm 1.100 bh
Semen portland 0.078 zak
Pasir pasang 0.016 m3
Pasir urug 0.016 m3
b. Tenaga
- Pekerja 0.080 oh
- Tukang batu 0.040 oh
- Kepala tukang 0.004 oh
- Mandor 0.007 oh
A.6.1.1 SALURAN LUAR / HAL 454 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
NO. URAIAN KOEF SATUAN
1 2 3 4
4 1m' Memasang pipa penyalur air limbah jenis pipa beton, diameter 1/2 30 cm
5 1m' Memasang pipa beton, diameter 15 cm - 20 cm
a. Bahan
- Pipa beton 1.100 bh
- Batu bata 0.027 m3
- Semen portland 0.078 zak
- Pasir pasang 0.056 m3
- Pasir urug 0.024 m3
b. Tenaga
- Pekerja 0.140 oh
- Tukang batu 0.070 oh
- Kepala tukang 0.007 oh
- Mandor 0.007 oh
1 2 3 4
1 2 3 4
- Pekerja 0.567 oh
- Tukang batu 0.284 oh
- Kepala tukang 0.028 oh
- Mandor 0.028 oh
1 2 3 4
1 2 3 4
1 2 3 4
1 2 3 4
- Mandor 0.028 oh
1 2 3 4
1 2 3 4
- Pembesian 14.48 kg
- Bekisting pelat 0.70 m2
1 2 3 4
1 2 3 4
1 2 3 4
33 1bh Pembuatan bak kontrol dari beton bertulang t= 100mm uk. 50x50x100cm termasuk tutup
a. Terpasang
- Galian Tanah 0.70 m3
- Pasir urug t=5cm 0.32 m3
- Lantai kerja beton mutu fc=7,4 Mpa (K 100) 0.32 m3
- Pembesian 150kg/m3 50.70 kg
- Bekisting dinding bagian luar 2 x pakai 3.52 m2
- Bekisting dinding dan tutup 2 x pakai 3.38 m2
- Beton mutu fc=24.0 Mpa (K 275), slum (12 ± 2) cm, w/c = 0.53 0.34 m3
- Urugan kembali bekas galian 0.25 m3
- Buangan tanah kearea site 0.46 m3
33 1bh Pembuatan bak kontrol dari beton bertulang t= 100mm uk. 50x50x100cm termasuk tutup
34 1bh Pembuatan bak kontrol dari beton bertulang t= 100mm uk. 60x60x100cm termasuk tutup
a. Terpasang
- Galian Tanah 0.89 m3
- Pasir urug t=5cm 0.41 m3
- Lantai kerja beton mutu fc=7,4 Mpa (K 100) 0.41 m3
- Pembesian 150kg/m3 61.20 kg
- Bekisting dinding bagian luar 2 x pakai 3.96 m2
- Bekisting dinding dan tutup 2 x pakai 4.08 m2
- Beton mutu fc=24.0 Mpa (K 275), slum (12 ± 2) cm, w/c = 0.53 0.41 m3
- Urugan kembali bekas galian 0.31 m3
- Buangan tanah kearea site 0.58 m3
34 1bh Pembuatan bak kontrol dari beton bertulang t= 100mm uk. 60x60x100cm termasuk tutup
35 1bh Pembuatan bak kontrol dari beton bertulang t= 100mm uk. 70x70x120cm termasuk tutup
a. Terpasang
- Galian Tanah 1.57 m3
- Pasir urug t=5cm 0.59 m3
- Lantai kerja beton mutu fc=7,4 Mpa (K 100) 0.59 m3
- Pembesian 150kg/m3 96.30 kg
- Bekisting dinding bagian luar 2 x pakai 5.20 m2
- Bekisting dinding dan tutup 2 x pakai 5.35 m2
- Beton mutu fc=24.0 Mpa (K 275), slum (12 ± 2) cm, w/c = 0.53 0.64 m3
- Urugan kembali bekas galian 0.55 m3
- Buangan tanah kearea site 1.02 m3
35 1bh Pembuatan bak kontrol dari beton bertulang t= 100mm uk. 70x70x120cm termasuk tutup
36 1bh Pembuatan bak kontrol dari beton bertulang t= 120mm uk. 80x80x130cm termasuk tutup
a. Terpasang
- Galian Tanah 2.02 m3
- Pasir urug t=5cm 0.59 m3
- Lantai kerja beton mutu fc=7,4 Mpa (K 100) 0.59 m3
- Pembesian 150kg/m3 102.97 kg
- Bekisting dinding bagian luar 2 x pakai 6.27 m2
A.6.1.1 SALURAN LUAR / HAL 466 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
NO. URAIAN KOEF SATUAN
1 2 3 4
36 1bh Pembuatan bak kontrol dari beton bertulang t= 120mm uk. 80x80x130cm termasuk tutup
37 1bh Pembuatan bak kontrol dari beton bertulang t= 120mm uk. 90x90x150cm termasuk tutup
a. Terpasang
- Galian Tanah 3.33 m3
- Pasir urug t=5cm 0.65 m3
- Lantai kerja beton mutu fc=7,4 Mpa (K 100) 0.65 m3
- Pembesian 150kg/m3 156.95 kg
- Bekisting dinding bagian luar 2 x pakai 7.68 m2
- Bekisting dinding dan tutup 2 x pakai 8.72 m2
- Beton mutu fc=24.0 Mpa (K 275), slum (12 ± 2) cm, w/c = 0.53 1.05 m3
- Urugan kembali bekas galian 1.17 m3
- Buangan tanah kearea site 2.17 m3
37 1bh Pembuatan bak kontrol dari beton bertulang t= 120mm uk. 90x90x150cm termasuk tutup
1 2 3 4
38 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 100x100x200cm termasuk tutup
a. Terpasang
- Galian Tanah 4.95 m3
- Pasir urug t=5cm 0.85 m3
- Lantai kerja beton mutu fc=7,4 Mpa (K 100) 0.85 m3
- Pembesian 150kg/m3 283.05 kg
- Bekisting dinding bagian luar 2 x pakai 11.76 m2
- Bekisting dinding dan tutup 2 x pakai 15.73 m2
- Beton mutu fc=24.0 Mpa (K 275), slum (12 ± 2) cm, w/c = 0.53 1.89 m3
- Urugan kembali bekas galian 1.73 m3
- Buangan tanah kearea site 3.22 m3
38 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 100x100x200cm termasuk tutup
39 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 120x120x200cm termasuk tutup
a. Terpasang
- Galian Tanah 6.36 m3
- Pasir urug t=5cm 1.04 m3
- Lantai kerja beton mutu fc=7,4 Mpa (K 100) 1.04 m3
- Pembesian 150kg/m3 344.25 kg
- Bekisting dinding bagian luar 2 x pakai 13.44 m2
- Bekisting dinding dan tutup 2 x pakai 15.30 m2
- Beton mutu fc=24.0 Mpa (K 275), slum (12 ± 2) cm, w/c = 0.53 2.30 m3
- Urugan kembali bekas galian 2.23 m3
- Buangan tanah kearea site 4.13 m3
39 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 120x120x200cm termasuk tutup
40 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 140x140x200cm termasuk tutup
a. Terpasang
- Galian Tanah 7.94 m3
- Pasir urug t=5cm 1.45 m3
- Lantai kerja beton mutu fc=7,4 Mpa (K 100) 1.45 m3
- Pembesian 150kg/m3 409.05 kg
- Bekisting dinding bagian luar 2 x pakai 16.72 m2
- Bekisting dinding dan tutup 2 x pakai 18.18 m2
- Beton mutu fc=24.0 Mpa (K 275), slum (12 ± 2) cm, w/c = 0.53 2.73 m3
- Urugan kembali bekas galian 2.78 m3
- Buangan tanah kearea site 5.16 m3
40 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 140x140x200cm termasuk tutup
41 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 200x200x300cm termasuk tutup
a. Terpasang
- Galian Tanah 20.00 m3
- Pasir urug t=5cm 0.26 m3
- Lantai kerja beton mutu fc=7,4 Mpa (K 100) 0.26 m3
- Pembesian 150kg/m3 818.55 kg
A.6.1.1 SALURAN LUAR / HAL 468 DARI 616
ANALISA HARGA SATUAN PEKERJAAN
NO. URAIAN KOEF SATUAN
1 2 3 4
41 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 200x200x300cm termasuk tutup
1 2 3 4
1 2 3 4
b. Bahan
- Box Culvert 20x30x100 1.100 bh
c. Tenaga
- Pekerja 0.418 oh
- Tukang batu 0.209 oh
- Kepala tukang 0.021 oh
- Mandor 0.021 oh
Rp. 31,836.27
17,075.30 27,320.48
66,110.00 899.10
175,450.00 2,280.85
121,440.00 1,335.84
Rp. 10,350.73
89,320.00 5,359.20
137,445.00 4,123.35
157,850.00 473.55
157,850.00 394.63
Jumlah Rp 42,186.99
Overhead & keuntungan 10% : Rp 4,218.70
Jumlah : Rp 46,405.69
Dibulatkan : Rp 46,400.00
Rp. 46,714.29
25,879.70 41,407.52
66,110.00 1,150.31
175,450.00 2,456.30
121,440.00 1,700.16
Rp. 14,379.75
89,320.00 7,145.60
137,445.00 5,497.80
157,850.00 631.40
157,850.00 1,104.95
Jumlah Rp 61,094.04
Overhead & keuntungan 10% : Rp 6,109.40
Jumlah : Rp 67,203.45
Dibulatkan : Rp 67,200.00
Rp. 72,582.77
61,160.00 67,276.00
66,110.00 1,150.31
175,450.00 2,456.30
121,440.00 1,700.16
Rp. 14,379.75
89,320.00 7,145.60
137,445.00 5,497.80
157,850.00 631.40
157,850.00 1,104.95
Jumlah Rp 86,962.52
Overhead & keuntungan 10% : Rp 8,696.25
Jumlah : Rp 95,658.78
Dibulatkan : Rp 95,600.00
Rp. 101,651.26
83,380.00 91,718.00
66,110.00 5,183.02
175,450.00 2,807.20
121,440.00 1,943.04
Rp. 14,379.75
89,320.00 7,145.60
137,445.00 5,497.80
157,850.00 631.40
157,850.00 1,104.95
A.6.1.1 SALURAN LUAR / HAL 472 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
Jumlah Rp 116,031.01
Overhead & keuntungan 10% : Rp 11,603.10
Jumlah : Rp 127,634.12
Dibulatkan : Rp 127,600.00
Rp. 192,189.51
158,400.00 174,240.00
990.00 26.73
66,110.00 5,183.02
175,450.00 9,825.20
121,440.00 2,914.56
Rp. 24,335.85
89,320.00 12,504.80
137,445.00 9,621.15
157,850.00 1,104.95
157,850.00 1,104.95
Jumlah Rp 216,525.36
Overhead & keuntungan 10% : Rp 21,652.54
Jumlah : Rp 238,177.90
Dibulatkan : Rp 238,100.00
Rp. 265,294.27
216,700.00 238,370.00
990.00 40.10
66,110.00 7,774.54
175,450.00 14,737.80
121,440.00 4,371.84
Rp. 36,503.78
89,320.00 18,757.20
137,445.00 14,431.73
157,850.00 1,657.43
157,850.00 1,657.43
Jumlah Rp 301,798.05
Overhead & keuntungan 10% : Rp 30,179.80
Jumlah : Rp 331,977.85
Dibulatkan : Rp 331,900.00
Rp. 341,676.41
273,900.00 301,290.00
990.00 60.14
66,110.00 11,661.80
175,450.00 22,106.70
121,440.00 6,557.76
Rp. 54,755.66
89,320.00 28,135.80
137,445.00 21,647.59
157,850.00 2,486.14
157,850.00 2,486.14
Jumlah Rp 396,432.07
Overhead & keuntungan 10% : Rp 39,643.21
Jumlah : Rp 436,075.28
Dibulatkan : Rp 436,000.00
Rp. 392,244.24
301,513.30 331,664.63
990.00 90.21
66,110.00 17,492.71
175,450.00 33,160.05
121,440.00 9,836.64
Rp. 82,133.49
89,320.00 42,203.70
137,445.00 32,471.38
157,850.00 3,729.21
157,850.00 3,729.21
Jumlah Rp 474,377.73
Overhead & keuntungan 10% : Rp 47,437.77
Jumlah : Rp 521,815.51
Dibulatkan : Rp 521,800.00
Rp. 501,035.53
389,400.00 428,340.00
990.00 108.26
66,110.00 20,991.25
175,450.00 39,792.06
121,440.00 11,803.97
Rp. 98,560.19
89,320.00 50,644.44
137,445.00 38,965.66
157,850.00 4,475.05
157,850.00 4,475.05
Jumlah Rp 599,595.72
Overhead & keuntungan 10% : Rp 59,959.57
Jumlah : Rp 659,555.30
Dibulatkan : Rp 659,500.00
Rp. 584,541.45
454,300.00 499,730.00
990.00 126.30
66,110.00 24,489.79
175,450.00 46,424.07
121,440.00 13,771.30
Rp. 114,986.89
89,320.00 59,085.18
137,445.00 45,459.93
157,850.00 5,220.89
157,850.00 5,220.89
Jumlah Rp 699,528.34
Overhead & keuntungan 10% : Rp 69,952.83
Jumlah : Rp 769,481.18
Dibulatkan : Rp 769,400.00
Rp. 652,317.38
504,900.00 555,390.00
990.00 144.34
66,110.00 27,988.33
175,450.00 53,056.08
121,440.00 15,738.62
Rp. 131,413.59
89,320.00 67,525.92
137,445.00 51,954.21
157,850.00 5,966.73
157,850.00 5,966.73
Jumlah Rp 783,730.97
Overhead & keuntungan 10% : Rp 78,373.10
Jumlah : Rp 862,104.06
Dibulatkan : Rp 862,100.00
Rp. 802,389.22
619,300.00 681,230.00
990.00 180.43
66,110.00 34,985.41
175,450.00 66,320.10
121,440.00 19,673.28
Rp. 164,266.99
89,320.00 84,407.40
137,445.00 64,942.76
157,850.00 7,458.41
157,850.00 7,458.41
Jumlah Rp 966,656.21
Overhead & keuntungan 10% : Rp 96,665.62
Jumlah : Rp 1,063,321.83
Dibulatkan : Rp 1,063,300.00
Rp. 22,030.93
174,102.50 3,482.05
927,444.00 18,548.88
Rp. 170,954.45
155,413.13 170,954.45
Rp. 66,054.45
89,320.00 33,941.60
137,445.00 26,114.55
157,850.00 2,999.15
157,850.00 2,999.15
Jumlah Rp 259,039.83
Overhead & keuntungan 10% : Rp 25,903.98
Jumlah : Rp 284,943.81
Dibulatkan : Rp 284,900.00
Rp. 27,071.43
155,413.13 3,885.33
927,444.00 23,186.10
Rp. 256,431.67
233,119.70 256,431.67
Rp. 66,054.45
89,320.00 33,941.60
137,445.00 26,114.55
A.6.1.1 SALURAN LUAR / HAL 476 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
157,850.00 2,999.15
157,850.00 2,999.15
Jumlah Rp 349,557.55
Overhead & keuntungan 10% : Rp 34,955.75
Jumlah : Rp 384,513.30
Dibulatkan : Rp 384,500.00
Rp. 32,485.71
155,413.13 4,662.39
927,444.00 27,823.32
Rp. 406,109.88
369,190.80 406,109.88
Rp. 72,659.90
89,320.00 37,335.76
137,445.00 28,726.01
157,850.00 3,299.07
157,850.00 3,299.07
Jumlah Rp 511,255.49
Overhead & keuntungan 10% : Rp 51,125.55
Jumlah : Rp 562,381.04
Dibulatkan : Rp 562,300.00
Rp. 37,900.00
155,413.13 5,439.46
927,444.00 32,460.54
Rp. 501,859.60
456,236.00 501,859.60
Rp. 79,925.88
89,320.00 41,069.34
137,445.00 31,598.61
157,850.00 3,628.97
157,850.00 3,628.97
Jumlah Rp 619,685.48
Overhead & keuntungan 10% : Rp 61,968.55
Jumlah : Rp 681,654.03
Dibulatkan : Rp 681,600.00
Rp. 43,314.29
155,413.13 6,216.53
927,444.00 37,097.76
Rp. 657,039.68
597,308.80 657,039.68
Rp. 87,918.47
89,320.00 45,176.27
137,445.00 34,758.47
157,850.00 3,991.87
157,850.00 3,991.87
Jumlah Rp 788,272.44
Overhead & keuntungan 10% : Rp 78,827.24
Jumlah : Rp 867,099.68
Dibulatkan : Rp 867,000.00
Rp. 48,728.57
155,413.13 6,993.59
927,444.00 41,734.98
Rp. 766,546.29
696,860.27 766,546.29
Rp. 96,710.32
89,320.00 49,693.90
137,445.00 38,234.31
157,850.00 4,391.06
157,850.00 4,391.06
Jumlah Rp 911,985.18
Overhead & keuntungan 10% : Rp 91,198.52
Jumlah : Rp 1,003,183.70
Dibulatkan : Rp 1,003,100.00
Rp. 54,142.86
155,413.13 7,770.66
927,444.00 46,372.20
Rp. 1,092,865.95
993,514.50 1,092,865.95
Rp. 96,710.32
89,320.00 49,693.90
137,445.00 38,234.31
157,850.00 4,391.06
157,850.00 4,391.06
Jumlah Rp 1,243,719.13
Overhead & keuntungan 10% : Rp 124,371.91
Jumlah : Rp 1,368,091.04
Dibulatkan : Rp 1,368,000.00
Rp. 64,971.43
155,413.13 9,324.79
927,444.00 55,646.64
Rp. 1,485,768.68
1,350,698.80 1,485,768.68
Rp. 106,381.35
89,320.00 54,663.29
137,445.00 42,057.74
157,850.00 4,830.16
157,850.00 4,830.16
Jumlah Rp 1,657,121.46
Overhead & keuntungan 10% : Rp 165,712.15
Jumlah : Rp 1,822,833.61
Dibulatkan : Rp 1,822,800.00
Rp. 75,800.00
155,413.13 10,878.92
927,444.00 64,921.08
Rp. 1,755,909.65
1,596,281.50 1,755,909.65
Rp. 117,019.49
89,320.00 60,129.61
137,445.00 46,263.52
157,850.00 5,313.18
157,850.00 5,313.18
Jumlah Rp 1,948,729.14
Overhead & keuntungan 10% : Rp 194,872.91
Jumlah : Rp 2,143,602.05
Dibulatkan : Rp 2,143,600.00
997,886.71 39,915.47
14,167.34 71,329.02
438,400.60 219,200.30
Jumlah Rp 330,444.78
Overhead & keuntungan 10% : Rp 33,044.48
Jumlah : Rp 363,489.26
Dibulatkan : Rp 363,400.00
997,886.71 47,898.56
14,167.34 83,847.99
438,400.60 263,040.36
Jumlah Rp 394,786.91
Overhead & keuntungan 10% : Rp 39,478.69
Jumlah : Rp 434,265.60
Dibulatkan : Rp 434,200.00
997,886.71 55,881.66
14,167.34 96,366.96
438,400.60 306,880.42
Jumlah Rp 459,129.03
Overhead & keuntungan 10% : Rp 45,912.90
Jumlah : Rp 505,041.93
Dibulatkan : Rp 505,000.00
997,886.71 79,830.94
14,167.34 184,017.21
438,400.60 350,720.48
Jumlah Rp 614,568.63
Overhead & keuntungan 10% : Rp 61,456.86
Jumlah : Rp 676,025.49
Dibulatkan : Rp 676,000.00
997,886.71 89,809.80
14,167.34 205,174.27
438,400.60 306,880.42
Jumlah Rp 601,864.50
Overhead & keuntungan 10% : Rp 60,186.45
Jumlah : Rp 662,050.95
Dibulatkan : Rp 662,000.00
997,886.71 99,788.67
14,167.34 226,331.33
438,400.60 438,400.60
Jumlah Rp 764,520.60
Overhead & keuntungan 10% : Rp 76,452.06
Jumlah : Rp 840,972.66
Dibulatkan : Rp 840,900.00
997,886.71 179,619.61
14,167.34 268,645.45
438,400.60 526,080.72
Jumlah Rp 974,345.78
Overhead & keuntungan 10% : Rp 97,434.58
Jumlah : Rp 1,071,780.36
Dibulatkan : Rp 1,071,700.00
997,886.71 209,556.21
14,167.34 310,959.57
438,400.60 613,760.84
Jumlah Rp 1,134,276.62
Overhead & keuntungan 10% : Rp 113,427.66
Jumlah : Rp 1,247,704.28
Dibulatkan : Rp 1,247,700.00
246,824.60
891,000.00 129,195.00
66,110.00 58,176.80
175,450.00 12,281.50
259,490.00 18,164.30
11,550.00 18,480.00
175,450.00 10,527.00
66,054.45
89,320.00 33,941.60
137,445.00 26,114.55
157,850.00 2,999.15
157,850.00 2,999.15
Jumlah Rp 312,879.05
Overhead & keuntungan 10% : Rp 31,287.91
Jumlah : Rp 344,166.96
Dibulatkan : Rp 344,100.00
398,378.20
891,000.00 222,750.00
66,110.00 101,809.40
175,450.00 22,808.50
259,490.00 5,189.80
11,550.00 30,030.00
175,450.00 15,790.50
210,472.19
89,320.00 126,834.40
137,445.00 65,011.49
157,850.00 7,418.95
157,850.00 11,207.35
Jumlah Rp 608,850.39
Overhead & keuntungan 10% : Rp 60,885.04
Jumlah : Rp 669,735.42
Dibulatkan : Rp 669,700.00
599,209.27
891,000.00 330,561.00
A.6.1.1 SALURAN LUAR / HAL 482 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
66,110.00 150,730.80
175,450.00 32,282.80
259,490.00 8,563.17
11,550.00 56,017.50
175,450.00 21,054.00
320,304.60
89,320.00 192,931.20
137,445.00 98,960.40
157,850.00 11,365.20
157,850.00 17,047.80
Jumlah Rp 919,513.87
Overhead & keuntungan 10% : Rp 91,951.39
Jumlah : Rp 1,011,465.26
Dibulatkan : Rp 1,011,400.00
70,936.25 49,939.12
174,102.50 55,712.80
927,444.00 296,782.08
14,167.340 718,284.14
370,166.450 1,302,985.90
370,166.450 1,251,162.60
997,886.71 337,285.71
60,935.88 15,014.60
31,054.10 14,210.36
Jumlah Rp 4,041,377.31
Overhead & keuntungan 10% : Rp 404,137.73
Jumlah : Rp 4,445,515.04
0mm uk. 50x50x100cm termasuk tutup Dibulatkan : Rp 4,445,500.00
mm uk. 60x60x100cm termasuk tutup
70,936.25 63,204.20
174,102.50 70,511.51
927,444.00 375,614.82
14,167.340 867,041.21
370,166.450 1,465,859.14
370,166.450 1,510,279.12
997,886.71 407,137.78
60,935.88 19,002.85
31,054.10 17,984.98
Jumlah Rp 4,796,635.61
Overhead & keuntungan 10% : Rp 479,663.56
Jumlah : Rp 5,276,299.17
0mm uk. 60x60x100cm termasuk tutup Dibulatkan : Rp 5,276,200.00
mm uk. 70x70x120cm termasuk tutup
70,936.25 111,582.72
174,102.50 103,425.59
927,444.00 550,948.11
14,167.340 1,364,314.84
370,166.450 1,924,865.54
370,166.450 1,980,390.51
997,886.71 640,643.27
60,935.88 33,548.25
31,054.10 31,751.26
Jumlah Rp 6,741,470.09
Overhead & keuntungan 10% : Rp 674,147.01
Jumlah : Rp 7,415,617.09
0mm uk. 70x70x120cm termasuk tutup Dibulatkan : Rp 7,415,600.00
mm uk. 80x80x130cm termasuk tutup
70,936.25 143,007.48
174,102.50 103,425.59
927,444.00 550,948.11
14,167.340 1,458,839.33
370,166.450 2,321,683.97
A.6.1.1 SALURAN LUAR / HAL 484 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
370,166.450 2,117,598.87
997,886.71 685,029.27
60,935.88 42,996.35
31,054.10 40,693.29
Jumlah Rp 7,464,222.27
Overhead & keuntungan 10% : Rp 746,422.23
Jumlah : Rp 8,210,644.50
0mm uk. 80x80x130cm termasuk tutup Dibulatkan : Rp 8,210,600.00
mm uk. 90x90x150cm termasuk tutup
70,936.25 236,359.59
174,102.50 113,131.80
927,444.00 602,653.11
14,167.340 2,223,501.68
370,166.450 2,842,878.34
370,166.450 3,227,555.31
997,886.71 1,044,092.85
60,935.88 71,063.42
31,054.10 67,256.97
Jumlah Rp 10,428,493.06
Overhead & keuntungan 10% : Rp 1,042,849.31
Jumlah : Rp 11,471,342.37
0mm uk. 90x90x150cm termasuk tutup Dibulatkan : Rp 11,471,300.00
70,936.25 351,134.44
174,102.50 147,116.61
927,444.00 783,690.18
14,167.340 4,010,065.59
370,166.450 4,353,157.45
370,166.450 5,820,867.43
997,886.71 1,883,012.22
60,935.88 105,571.40
31,054.10 99,916.57
Jumlah Rp 17,554,531.88
Overhead & keuntungan 10% : Rp 1,755,453.19
Jumlah : Rp 19,309,985.07
0mm uk. 100x100x200cm termasuk tutup Dibulatkan : Rp 19,309,900.00
mm uk. 120x120x200cm termasuk tutup
70,936.25 451,012.68
174,102.50 180,509.47
927,444.00 961,573.94
14,167.340 4,877,106.80
370,166.450 4,975,037.09
370,166.450 5,663,546.69
997,886.71 2,290,149.99
60,935.88 135,600.60
31,054.10 128,337.28
Jumlah Rp 19,662,874.53
Overhead & keuntungan 10% : Rp 1,966,287.45
Jumlah : Rp 21,629,161.98
0mm uk. 120x120x200cm termasuk tutup Dibulatkan : Rp 21,629,100.00
mm uk. 140x140x200cm termasuk tutup
70,936.25 563,375.70
174,102.50 251,578.11
927,444.00 1,340,156.58
14,167.340 5,795,150.43
370,166.450 6,189,183.04
370,166.450 6,729,626.06
997,886.71 2,721,237.05
60,935.88 169,383.45
31,054.10 160,310.58
Jumlah Rp 23,920,001.00
Overhead & keuntungan 10% : Rp 2,392,000.10
Jumlah : Rp 26,312,001.10
0mm uk. 140x140x200cm termasuk tutup Dibulatkan : Rp 26,312,000.00
mm uk. 200x200x300cm termasuk tutup
70,936.25 1,418,725.00
174,102.50 46,050.11
927,444.00 245,308.94
14,167.340 11,596,676.16
370,166.450 11,845,326.40
370,166.450 13,466,655.45
997,886.71 5,445,467.76
60,935.88 426,551.13
31,054.10 403,703.30
Jumlah Rp 44,894,464.24
Overhead & keuntungan 10% : Rp 4,489,446.42
Jumlah : Rp 49,383,910.67
0mm uk. 200x200x300cm termasuk tutup Dibulatkan : Rp 49,383,900.00
108,670.10 170,612.06
174,102.50 6,833.52
3,748,375.00 3,748,375.00
14,167.340 480,442.83
370,166.450 418,436.16
997,886.71 169,201.67
128,058.05 100,525.57
289,850.00 568,830.63
57,500.00 2,875,000.00
38,034.54 20,899.98
31,054.10 31,690.71
1,311,931.25 1,311,931.25
Jumlah Rp 9,902,779.37
Overhead & keuntungan 10% : Rp 990,277.94
Jumlah : Rp 10,893,057.31
Dibulatkan : Rp 10,893,000.00
Rp. 32,485.71
155,413.13 4,662.39
927,444.00 27,823.32
Rp. 936,100.00
851,000.00 936,100.00
Rp. 72,659.90
89,320.00 37,335.76
137,445.00 28,726.01
157,850.00 3,299.07
157,850.00 3,299.07
Jumlah Rp 1,041,245.61
Overhead & keuntungan 10% : Rp 104,124.56
Jumlah : Rp 1,145,370.17
Dibulatkan : Rp 1,145,300.00
Rp. 43,314.29
155,413.13 6,216.53
927,444.00 37,097.76
Rp. 1,533,400.00
1,394,000.00 1,533,400.00
Rp. 87,918.47
89,320.00 45,176.27
137,445.00 34,758.47
157,850.00 3,991.87
157,850.00 3,991.87
Jumlah Rp 1,664,632.76
Overhead & keuntungan 10% : Rp 166,463.28
Jumlah : Rp 1,831,096.03
Dibulatkan : Rp 1,831,000.00
Rp. 21,657.14
155,413.13 3,108.26
927,444.00 18,548.88
A.6.1.1 SALURAN LUAR / HAL 488 DARI 616
H. SATUAN SUB. JUMLAH JUMLAH
Rp. Rp. Rp.
5 6 7
Rp. 617,705.00
561,550.00 617,705.00
Rp. 72,659.90
89,320.00 37,335.76
137,445.00 28,726.01
157,850.00 3,299.07
157,850.00 3,299.07
Jumlah Rp 712,022.04
Overhead & keuntungan 10% : Rp 71,202.20
Jumlah : Rp 783,224.24
Dibulatkan : Rp 783,200.00
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
A. TENAGA
B. BAHAN
C. PERALATAN
PEKERJAAN JALAN/PERKERASAN
DIRJEN Binamarga-PERMEN PU NOMOR 28/PRT/M/2016 Edisi Penyempurnaan
P.01 1 Hr Pekerjaan Menggilas
Tenaga Kerja
Pekerja 0.250 org/hr 89,320.00
Mandor 0.025 org/hr 157,850.00
P.019 1 m³ Sub base course kelas B t=15 cm batu crop ( CBR 60% )
DIRJEN Binamarga-Panduan Analisis Satuan No 008BM2008
Bahan
Batu krop 1.20 m³ 292,327.17
Tenaga Kerja
Pekerja 0.0595 jam 17,864.00
Mandor 0.0085 jam 31,570.00
Sewa alat
Wheel Loader 0.0085 jam 467,182.34
Dump Truck 0.5043 jam 475,167.11
Motor Grader 0.0094 jam 258,500.00
Tandem roller 0.0428 jam 404,666.92
Water tank Truck 0.0141 jam 223,411.65
P.019 1 m³ Sub base course kelas B t=15 cm batu crop ( CBR 60% )
P.020 1 m³ Urug Sirtu Padat Untuk jalan ( CBR 75% ) t=40 cm
DIRJEN Binamarga-Panduan Analisis Satuan No 008BM2008
Bahan
Sirtu 1.20 m³ 151,800.00
Tenaga Kerja
Pekerja 0.0595 jam 17,864.00
Mandor 0.0085 jam 31,570.00
Sewa alat
Wheel Loader 0.0085 jam 467,182.34
Dump Truck 0.5043 jam 475,167.11
Motor Grader 0.0094 jam 258,500.00
Tandem roller 0.0428 jam 404,666.92
Water tank Truck 0.0141 jam 223,411.65
1,538,279.26
200,000.00
184,800.00
1,923,079.26
21.000 m
25.200 m²
630 m²
1.260 m²
3,052.51
1,526.25
83,942.11
62,673.60
18,216.00
3,052.51
28,374.50
26,796.00
1,578.50
Jumlah 112,316.61
Overhead & keuntungan 10% : 11,231.66
Jumlah : 123,548.27
Dibulatkan : 123,500.00
105,682.51
78,342.00
24,288.00
3,052.51
28,374.50
26,796.00
1,578.50
Jumlah 134,057.01
Overhead & keuntungan 10% : 13,405.70
Jumlah : 147,462.71
Dibulatkan : 147,400.00
121,350.91
94,010.40
24,288.00
3,052.51
28,374.50
26,796.00
1,578.50
Jumlah 149,725.41
Overhead & keuntungan 10% : 14,972.54
Jumlah : 164,697.95
Dibulatkan : 164,600.00
73,211.03
70,158.52
3,052.51
26,276.25
22,330.00
3,946.25
Jumlah 99,487.28
Overhead & keuntungan 10% : 9,948.73
Jumlah : 109,436.01
Dibulatkan : 109,400.00
19,065.88
17,539.63
1,526.25
13,138.13
11,165.00
1,973.13
Jumlah 32,204.01
Overhead & keuntungan 10% : 3,220.40
Jumlah : 35,424.41
Dibulatkan : 35,400.00
12,273.58
10,747.32
1,526.25
13,138.13
11,165.00
1,973.13
Jumlah 25,411.70
Overhead & keuntungan 10% : 2,541.17
Jumlah : 27,952.87
Dibulatkan : 27,900.00
14,279.65
12,753.40
1,526.25
19,442.50
17,864.00
1,578.50
Jumlah 33,722.15
Overhead & keuntungan 10% : 3,372.22
Jumlah : 37,094.37
Dibulatkan : 37,000.00
4,349.40
2,594.90
1,754.50
15,554.00
14,291.20
1,262.80
Jumlah 19,903.40
Overhead & keuntungan 10% : 1,990.34
Jumlah : 21,893.74
Dibulatkan : 21,800.00
61,798.17
701.80
49,846.37
11,250.00
12,627.00
10,995.60
631.40
1,000.00
Jumlah 74,425.17
Overhead & keuntungan 10% : 7,442.52
Jumlah : 81,867.68
Dibulatkan : 81,800.00
221,324.17
221,324.17
1,330.50
1,062.31
268.19
22,899.75
3,971.05
239,626.77
2,429.90
17,319.74
3,150.10
Jumlah 245,554.43
Overhead & keuntungan 10% : 24,555.44
Jumlah : 270,109.87
Dibulatkan : 270,100.00
183,165.41
183,165.41
1,330.50
6.P.Pek.Jalan / HAL 528 DARI 616
SUB. JUMLAH JUMLAH
Rp. Rp.
6 7
1,062.31
268.19
246,027.72
3,971.05
239,626.77
2,429.90
17,319.74
3,150.10
Jumlah 430,523.64
Overhead & keuntungan 10% : 43,052.36
Jumlah : 473,576.00
Dibulatkan : 473,500.00
160,269.04
160,269.04
6,652.52
5,311.55
1,340.97
246,027.72
3,971.05
239,626.77
2,429.90
17,319.74
3,150.10
Jumlah 412,949.28
Overhead & keuntungan 10% : 41,294.93
Jumlah : 454,244.21
Dibulatkan : 454,200.00
306,080.55
306,080.55
2,089.63
1,679.22
410.41
5,719.76
327.03
473.20
609.38
2,562.32
1,335.40
412.44
Jumlah 313,889.94
Overhead & keuntungan 10% : 31,388.99
Jumlah : 345,278.94
Dibulatkan : 345,200.00
176,693.64
176,693.64
1,961.27
1,661.35
299.92
20,972.58
407.47
678.30
873.49
16,306.15
989.94
1,317.70
399.53
Jumlah 199,627.49
Overhead & keuntungan 10% : 19,962.75
Jumlah : 219,590.24
Dibulatkan : 219,500.00
206,344.96
6.P.Pek.Jalan / HAL 530 DARI 616
SUB. JUMLAH JUMLAH
Rp. Rp.
6 7
206,344.96
1,044.81
839.61
205.21
5,719.76
327.03
473.20
609.38
2,562.32
1,335.40
412.44
Jumlah 213,109.54
Overhead & keuntungan 10% : 21,310.95
Jumlah : 234,420.49
Dibulatkan : 234,400.00
7,018.00
7,018.00
9,507.96
7,145.60
1,099.56
1,262.80
6,471.50
3,450.94
1,798.52
1,222.04
Jumlah 22,997.46
Overhead & keuntungan 10% : 2,299.75
Jumlah : 25,297.21
Dibulatkan : 25,200.00
66,147.57
2,594.90
1,754.50
701.80
49,846.37
11,250.00
27,181.00
10,995.60
14,291.20
1,894.20
1,526.25
1,526.25
-
Jumlah 94,854.82
Overhead & keuntungan 10% : 9,485.48
Jumlah : 104,340.30
Dibulatkan : 104,300.00
26,913.73
26,913.73
153.54
71.46
82.08
1,056.85
277.97
385.50
393.38
-
Jumlah 28,124.11
Overhead & keuntungan 10% : 2,812.41
Jumlah : 30,936.52
Dibulatkan : 30,900.00
39,147.24
39,147.24
36.81
17.86
18.94
1,056.85
6.P.Pek.Jalan / HAL 532 DARI 616
SUB. JUMLAH JUMLAH
Rp. Rp.
6 7
277.97
385.50
393.38
-
Jumlah 40,240.89
Overhead & keuntungan 10% : 4,024.09
Jumlah : 44,264.98
Dibulatkan : 44,200.00
350,792.60
350,792.60
1,330.50
1,062.31
268.19
266,497.57
3,971.05
239,626.77
2,429.90
17,319.74
3,150.10
Jumlah 618,620.68
Overhead & keuntungan 10% : 61,862.07
Jumlah : 680,482.75
Dibulatkan : 680,400.00
350,792.60
350,792.60
1,330.50
1,062.31
268.19
266,497.57
3,971.05
239,626.77
2,429.90
17,319.74
3,150.10
Jumlah 618,620.68
Overhead & keuntungan 10% : 61,862.07
Jumlah : 680,482.75
Dibulatkan : 680,400.00
182,160.00
182,160.00
1,330.50
1,062.31
268.19
266,497.57
3,971.05
239,626.77
2,429.90
17,319.74
3,150.10
Jumlah 449,988.08
Overhead & keuntungan 10% : 44,998.81
Jumlah : 494,986.88
Dibulatkan : 494,900.00
20,801.63
6,206.92
1,741.03
724.14
12,129.55
94,134.33
87,523.33
6,611.00
33,976.25
17,864.00
13,744.50
1,578.50
789.25
Jumlah 148,912.22
Overhead & keuntungan 10% : 14,891.22
Jumlah : 163,803.44
Dibulatkan : 163,800.00
183,165.41
183,165.41
1,330.50
1,062.31
268.19
Jumlah 184,495.91
Overhead & keuntungan 10% : 18,449.59
Jumlah : 202,945.50
Dibulatkan : 202,900.00
1 1 M3 Pek. Galian lubang tanam pada tanah biasa maks kedalaman 1 M'
Pekerja 0.7500 org 89,320.00
Mandor 0.0250 org 157,850.00
1 1 M3 Pek. Galian lubang tanam pada tanah biasa maks kedalaman 1 M'
2 1M3 Urugan Tanah Humus / Timbunan
Bahan :
Tanah Urug gembur 1.1000 m3 137,203.00
Tenaga :
Pekerja 0.2500 org 89,320.00
Mandor 0.0250 org 157,850.00
6 1 M2 Penyiraman Tanaman
66,990.00
3,946.25
Jumlah : 70,936.25
Overhead & keuntungan 10% : 7,093.63
Jumlah : 78,029.88
Dibulatkan : 78,000.00
150,923.30
150,923.30
26,276.25
22,330.00
3,946.25
Jumlah : 177,199.55
Overhead & keuntungan 10% : 17,719.96
Jumlah : 194,919.51
Dibulatkan : 194,900.00
44,660.00
7,892.50
Jumlah : 52,552.50
Overhead & keuntungan 10% : 5,255.25
Jumlah : 57,807.75
Dibulatkan : 57,800.00
29,475.60
1,578.50
Jumlah : 31,054.10
Overhead & keuntungan 10% : 3,105.41
Jumlah : 34,159.51
Dibulatkan : 34,100.00
15,322.23
1,608.83
7,655.02
Jumlah : 24,586.08
Overhead & keuntungan 10% : 2,458.61
Jumlah : 27,044.69
Dibulatkan : 27,000.00
675.00
675.00
2,066.53
2,009.70
56.83
411.23 411.23
Jumlah : 3,152.75
Overhead & keuntungan 10% : 315.28
Jumlah : 3,468.03
Dibulatkan : 3,400.00
1,700.00
350.00
1,350.00
7,118.50
4,019.40
2,474.01
568.26
56.83
1,322.77 1,322.77
Jumlah : 10,141.27
Overhead & keuntungan 10% : 1,014.13
Jumlah : 11,155.40
Dibulatkan : 11,100.00
312,463.03
309,129.70
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 337,817.20
Overhead & keuntungan 10% : 33,781.72
Jumlah : 371,598.92
Dibulatkan : 371,500.00
102,333.33
99,000.00
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 127,687.50
Overhead & keuntungan 10% : 12,768.75
Jumlah : 140,456.25
Dibulatkan : 140,400.00
200,161.83
196,828.50
A.7.1.1.Tanaman / HAL 562 DARI 616
SUB. JUMLAH JUMLAH
Rp.
6 7
3,333.33
- 18,957.40
10,718.40
6,597.36
1,515.36
126.28
- 6,396.77
3,073.26
2,535.32
788.19
Jumlah : 225,516.00
Overhead & keuntungan 10% : 22,551.60
Jumlah : 248,067.60
Dibulatkan : 248,000.00
110,661.43
107,328.10
3,333.33
- 18,957.40
10,718.40
6,597.36
1,515.36
126.28
- 6,396.77
3,073.26
2,535.32
788.19
Jumlah : 136,015.60
Overhead & keuntungan 10% : 13,601.56
Jumlah : 149,617.16
Dibulatkan : 149,600.00
9,357.81
8,246.70
1,111.11
- 6,635.09
3,751.44
2,309.08
530.38
44.20
- 1,934.38
929.35
766.68
238.35
Jumlah : 17,927.28
Overhead & keuntungan 10% : 1,792.73
Jumlah : 19,720.01
Dibulatkan : 19,700.00
203,679.63
200,346.30
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 229,033.80
Overhead & keuntungan 10% : 22,903.38
Jumlah : 251,937.18
Dibulatkan : 251,900.00
140,833.33
A.7.1.1.Tanaman / HAL 564 DARI 616
SUB. JUMLAH JUMLAH
Rp.
6 7
137,500.00
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 166,187.50
Overhead & keuntungan 10% : 16,618.75
Jumlah : 182,806.25
Dibulatkan : 182,800.00
44,566.83
41,233.50
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 69,921.00
Overhead & keuntungan 10% : 6,992.10
Jumlah : 76,913.10
Dibulatkan : 76,900.00
289,542.33
286,209.00
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 314,896.50
Overhead & keuntungan 10% : 31,489.65
Jumlah : 346,386.15
Dibulatkan : 346,300.00
217,989.53
214,656.20
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 243,343.70
Overhead & keuntungan 10% : 24,334.37
Jumlah : 267,678.07
Dibulatkan : 267,600.00
318,163.23
A.7.1.1.Tanaman / HAL 566 DARI 616
SUB. JUMLAH JUMLAH
Rp.
6 7
314,829.90
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 343,517.40
Overhead & keuntungan 10% : 34,351.74
Jumlah : 377,869.14
Dibulatkan : 377,800.00
184,833.33
181,500.00
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 210,187.50
Overhead & keuntungan 10% : 21,018.75
Jumlah : 231,206.25
Dibulatkan : 231,200.00
270,138.33
266,805.00
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 295,492.50
Overhead & keuntungan 10% : 29,549.25
Jumlah : 325,041.75
Dibulatkan : 325,000.00
289,542.33
286,209.00
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 314,896.50
Overhead & keuntungan 10% : 31,489.65
Jumlah : 346,386.15
Dibulatkan : 346,300.00
326,045.83
A.7.1.1.Tanaman / HAL 568 DARI 616
SUB. JUMLAH JUMLAH
Rp.
6 7
322,712.50
3,333.33
18,957.40
10,718.40
6,597.36
1,515.36
126.28
6,396.77
3,073.26
2,535.32
788.19
Jumlah : 351,400.00
Overhead & keuntungan 10% : 35,140.00
Jumlah : 386,540.00
Dibulatkan : 386,500.00
35,795.21
34,684.10
1,111.11
6,635.09
3,751.44
2,309.08
530.38
44.20
4,625.69
1,966.89
2,028.25
630.55
Jumlah : 47,055.99
Overhead & keuntungan 10% : 4,705.60
Jumlah : 51,761.59
Dibulatkan : 51,700.00
169,919.50
144,919.50
25,000.00
28,436.10
16,077.60
9,896.04
2,273.04
189.42
8,955.47
4,302.56
3,549.44
1,103.46
Jumlah : 207,311.07
Overhead & keuntungan 10% : 20,731.11
Jumlah : 228,042.18
Dibulatkan : 228,000.00
118,984.00
93,984.00
25,000.00
- 28,436.10
16,077.60
9,896.04
2,273.04
189.42
- 8,955.47
4,302.56
3,549.44
1,103.46
Jumlah : 156,375.57
Overhead & keuntungan 10% : 15,637.56
Jumlah : 172,013.13
Dibulatkan : 172,000.00
22,463.60
17,463.60
5,000.00
6,635.09
3,751.44
2,309.08
530.38
44.20
3,134.42
1,505.90
1,242.31
386.21
Jumlah : 32,233.11
Overhead & keuntungan 10% : 3,223.31
Jumlah : 35,456.42
Dibulatkan : 35,400.00
43,685.90
38,685.90
5,000.00
13,270.18
7,502.88
4,618.15
1,060.75
88.40
4,093.93
1,966.89
1,622.60
504.44
Jumlah : 61,050.01
Overhead & keuntungan 10% : 6,105.00
Jumlah : 67,155.01
Dibulatkan : 67,100.00
186,912.50
181,912.50
5,000.00
6,635.09
3,751.44
2,309.08
530.38
44.20
3,134.42
1,505.90
1,242.31
386.21
Jumlah : 196,682.01
Overhead & keuntungan 10% : 19,668.20
Jumlah : 216,350.21
Dibulatkan : 216,300.00
11,850.00
9,350.00
2,500.00
6,635.09
3,751.44
2,309.08
530.38
44.20
1,935.84
307.33
1,242.31
386.21
Jumlah : 20,420.93
Overhead & keuntungan 10% : 2,042.09
Jumlah : 22,463.03
Dibulatkan : 22,400.00
13,293.20
10,793.20
2,500.00
6,635.09
3,751.44
2,309.08
530.38
44.20
2,089.51
460.99
1,242.31
386.21
Jumlah : 22,017.80
Overhead & keuntungan 10% : 2,201.78
Jumlah : 24,219.58
Dibulatkan : 24,200.00
7,836.10
5,336.10
2,500.00
6,635.09
3,751.44
2,309.08
530.38
44.20
1,935.84
307.33
1,242.31
386.21
Jumlah : 16,407.03
Overhead & keuntungan 10% : 1,640.70
Jumlah : 18,047.74
Dibulatkan : 18,000.00
74,051.70
71,551.70
2,500.00
6,635.09
3,751.44
2,309.08
530.38
44.20
2,089.51
460.99
1,242.31
386.21
Jumlah : 82,776.30
Overhead & keuntungan 10% : 8,277.63
Jumlah : 91,053.93
Dibulatkan : 91,000.00
37,669.20
A.7.1.1.Tanaman / HAL 573 DARI 616
SUB. JUMLAH JUMLAH
Rp.
6 7
35,169.20
2,500.00
6,635.09
3,751.44
2,309.08
530.38
44.20
2,089.51
460.99
1,242.31
386.21
Jumlah : 46,393.80
Overhead & keuntungan 10% : 4,639.38
Jumlah : 51,033.18
Dibulatkan : 51,000.00
76,551.70
71,551.70
5,000.00
6,635.09
3,751.44
2,309.08
530.38
44.20
3,134.42
1,505.90
1,242.31
386.21
Jumlah : 86,321.21
Overhead & keuntungan 10% : 8,632.12
Jumlah : 94,953.33
Dibulatkan : 94,900.00
5,505,000.00
5,500,000.00
5,000.00
6,635.09
3,751.44
2,309.08
530.38
44.20
3,134.42
1,505.90
1,242.31
386.21
Jumlah : 5,514,769.51
Overhead & keuntungan 10% : 551,476.95
Jumlah : 6,066,246.46
Dibulatkan : 6,066,200.00
41,000.00
38,500.00
2,500.00
6,635.09
3,751.44
2,309.08
530.38
44.20
2,089.51
460.99
1,242.31
386.21
Jumlah : 49,724.60
Overhead & keuntungan 10% : 4,972.46
Jumlah : 54,697.06
Dibulatkan : 54,600.00
17,053.00
A.7.1.1.Tanaman / HAL 575 DARI 616
SUB. JUMLAH JUMLAH
Rp.
6 7
14,553.00
2,500.00
6,635.09
3,751.44
2,309.08
530.38
44.20
2,089.51
460.99
1,242.31
386.21
Jumlah : 25,777.60
Overhead & keuntungan 10% : 2,577.76
Jumlah : 28,355.36
Dibulatkan : 28,300.00
68,750.00
68,750.00
12,623.77
7,145.60
4,673.13
536.69
268.35
24,366.97
17,719.96
5,070.64
1,576.38
Jumlah : 105,740.73
Overhead & keuntungan 10% : 10,574.07
Jumlah : 116,314.81
Dibulatkan : 116,300.00
22,434.50
22,434.50
12,623.77
7,145.60
4,673.13
536.69
268.35
24,366.97
17,719.96
5,070.64
1,576.38
Jumlah : 59,425.23
Overhead & keuntungan 10% : 5,942.52
Jumlah : 65,367.76
Dibulatkan : 65,300.00
83,828.20
78,828.20
5,000.00
6,635.09
3,751.44
2,309.08
530.38
44.20
4,093.93
1,966.89
1,622.60
504.44
Jumlah : 94,557.22
Overhead & keuntungan 10% : 9,455.72
Jumlah : 104,012.94
Dibulatkan : 104,000.00
9,972.00
4,972.00
5,000.00
A.7.1.1.Tanaman / HAL 577 DARI 616
SUB. JUMLAH JUMLAH
Rp.
6 7
6,635.09
3,751.44
2,309.08
530.38
44.20
1,970.92
774.46
912.71
283.75
Jumlah : 18,578.01
Overhead & keuntungan 10% : 1,857.80
Jumlah : 20,435.82
Dibulatkan : 20,400.00
65,637.50
60,637.50
5,000.00
6,635.09
3,751.44
2,309.08
530.38
44.20
4,093.93
1,966.89
1,622.60
504.44
Jumlah : 76,366.52
Overhead & keuntungan 10% : 7,636.65
Jumlah : 84,003.17
Dibulatkan : 84,000.00
123,750.00
123,750.00
12,623.77
7,145.60
4,673.13
536.69
268.35
24,366.97
17,719.96
5,070.64
1,576.38
Jumlah : 160,740.73
Overhead & keuntungan 10% : 16,074.07
Jumlah : 176,814.81
Dibulatkan : 176,800.00
97,020.00
97,020.00
12,623.77
7,145.60
4,673.13
536.69
268.35
24,366.97
17,719.96
5,070.64
1,576.38
Jumlah : 134,010.73
Overhead & keuntungan 10% : 13,401.07
Jumlah : 147,411.81
Dibulatkan : 147,400.00
97,020.00
97,020.00
12,623.77
A.7.1.1.Tanaman / HAL 579 DARI 616
SUB. JUMLAH JUMLAH
Rp.
6 7
7,145.60
4,673.13
536.69
268.35
24,366.97
17,719.96
5,070.64
1,576.38
Jumlah : 134,010.73
Overhead & keuntungan 10% : 13,401.07
Jumlah : 147,411.81
Dibulatkan : 147,400.00
42,930.80
42,930.80
5,000.00
6,635.09
3,751.44
2,309.08
530.38
44.20
1,970.92
774.46
912.71
283.75
Jumlah : 51,536.81
Overhead & keuntungan 10% : 5,153.68
Jumlah : 56,690.50
Dibulatkan : 56,600.00
106,357.90
106,357.90
5,000.00
6,635.09
3,751.44
2,309.08
530.38
44.20
1,970.92
774.46
912.71
283.75
Jumlah : 114,963.91
Overhead & keuntungan 10% : 11,496.39
Jumlah : 126,460.31
Dibulatkan : 126,400.00
57,726.90
57,726.90
5,000.00
6,635.09
3,751.44
2,309.08
530.38
44.20
1,970.92
774.46
912.71
283.75
Jumlah : 66,332.91
Overhead & keuntungan 10% : 6,633.29
Jumlah : 72,966.21
Dibulatkan : 72,900.00
28,498.80
28,498.80
A.7.1.1.Tanaman / HAL 581 DARI 616
SUB. JUMLAH JUMLAH
Rp.
6 7
5,000.00
6,635.09
3,751.44
2,309.08
530.38
44.20
1,970.92
774.46
912.71
283.75
Jumlah : 37,104.81
Overhead & keuntungan 10% : 3,710.48
Jumlah : 40,815.30
Dibulatkan : 40,800.00
28,490.00
28,490.00
12,623.77
7,145.60
4,673.13
536.69
268.35
9,105.62
2,458.61
5,070.64
1,576.38
Jumlah : 50,219.39
Overhead & keuntungan 10% : 5,021.94
Jumlah : 55,241.32
Dibulatkan : 55,200.00
60,632.00
60,632.00
12,623.77
7,145.60
4,673.13
536.69
268.35
9,105.62
2,458.61
5,070.64
1,576.38
Jumlah : 82,361.39
Overhead & keuntungan 10% : 8,236.14
Jumlah : 90,597.52
Dibulatkan : 90,500.00
75,790.00
75,790.00
18,957.40
10,718.40
6,597.36
1,515.36
126.28
9,105.62
2,458.61
5,070.64
1,576.38
Jumlah : 103,853.02
Overhead & keuntungan 10% : 10,385.30
Jumlah : 114,238.32
Dibulatkan : 114,200.00
9,549.54
9,549.54
9,226.14
5,359.20
A.7.1.1.Tanaman / HAL 583 DARI 616
SUB. JUMLAH JUMLAH
Rp.
6 7
3,298.68
378.84
189.42
49,398.64
35,439.91
10,648.33
3,310.39
Jumlah : 68,174.32
Overhead & keuntungan 10% : 6,817.43
Jumlah : 74,991.75
Dibulatkan : 74,900.00
23,557.38
23,557.38
9,226.14
5,359.20
3,298.68
378.84
189.42
49,398.64
35,439.91
10,648.33
3,310.39
Jumlah : 82,182.16
Overhead & keuntungan 10% : 8,218.22
Jumlah : 90,400.37
Dibulatkan : 90,400.00
8,276.73
8,276.73
9,226.14
5,359.20
3,298.68
378.84
189.42
49,398.64
35,439.91
10,648.33
3,310.39
Jumlah : 66,901.51
Overhead & keuntungan 10% : 6,690.15
Jumlah : 73,591.66
Dibulatkan : 73,500.00
118,170.36
118,170.36
Jumlah : 118,170.36
Overhead & keuntungan 10% : 11,817.04
Jumlah : 129,987.40
Dibulatkan : 129,900.00
4,275,000.00 4,275,000.00
110,000.00 110,000.00
510,000.00 510,000.00
Jumlah : 4,895,000.00
Overhead & keuntungan 10% : 489,500.00
Jumlah : 5,384,500.00
Dibulatkan : 5,384,500.00
4,275,000.00 4,275,000.00
110,000.00 110,000.00
400,000.00 400,000.00
510,000.00 510,000.00
Jumlah : 5,295,000.00
Overhead & keuntungan 10% : 529,500.00
Jumlah : 5,824,500.00
Dibulatkan : 5,824,500.00
1,620,000.00 1,620,000.00
Jumlah : 1,620,000.00
Overhead & keuntungan 10% : 162,000.00
Jumlah : 1,782,000.00
Dibulatkan : 1,782,000.00
1 3 4
R. Harga satuan pekerjaan Signage
1 1 Unit Standing Signage tipe SS-1 & SS-2 ukuran 800x2100 mm
1 Harga terpasang
Terpasang Rangka hollow 40x40x2mm 1.10
Terpasang MDF t=12mm 1.10
Terpasang lapisan HPL 1.10
Signika Negative t=100mm terpasang stainless 20.00
Signika Negative t=50mm terpasang Stainless 185.00
Signika Negative t=30mm terpasang Stainless 45.00
Signika Negative t=20 & 15mm terpasang Stainless 854.00
Plat stainless steel t=4,5mm 1.10
Grafir pola batik 1.00
2 Alat batu dan bahan penunjang 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
3 1 Unit Ceilling hanging Signage tipe S2-1 s/d S2-6 & S2-22 s/d S2-24 ukuran 640x1200 mm
1 Harga terpasang
Terpasang Rangka hollow 40x40x2mm 0.77
Terpasang Acrylic t=10mm warna 1.54
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
1 3 4
R. Harga satuan pekerjaan Signage
Terpasang Rangka hollow 40x40x2mm 0.24
Terpasang Acrylic t=10mm warna 0.24
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
5 1 Unit Ceilling hanging Signage tipe S2-8 s/d S2-10 & S2-21 ukuran 200x1200 mm
1 Harga terpasang
Terpasang Rangka hollow 40x40x2mm 0.24
Terpasang Acrylic t=10mm warna 0.48
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
6 1 Unit Ceilling hanging Signage tipe S2-11 & S2-12 & S2-20 ukuran 200x1500 mm
1 Harga terpasang
Terpasang Rangka hollow 40x40x2mm 0.30
Terpasang Acrylic t=10mm warna 0.30
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
ANALISA HARGA SATUAN PEKERJAAN
1 3 4
R. Harga satuan pekerjaan Signage
7 1 Unit Ceilling hanging Signage tipe S2-13 ukuran 200x1800 mm
1 Harga terpasang
Terpasang Rangka hollow 40x40x2mm 0.36
Terpasang Acrylic t=10mm warna 0.36
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
8 1 Unit Ceilling hanging Signage tipe S2-14, S2-16 & S2-18 ukuran 200x600 mm
1 Harga terpasang
Terpasang Rangka hollow 40x40x2mm 0.12
Terpasang Acrylic t=10mm warna 0.12
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
9 1 Unit Ceilling hanging Signage tipe S2-15 & S2-19 ukuran 200x1200 mm
1 Harga terpasang
Terpasang Rangka hollow 40x40x2mm 0.24
Terpasang Acrylic t=10mm warna 0.24
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
ANALISA HARGA SATUAN PEKERJAAN
1 3 4
R. Harga satuan pekerjaan Signage
Overhead + Profit 10% :
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
ANALISA HARGA SATUAN PEKERJAAN
1 3 4
R. Harga satuan pekerjaan Signage
Overhead + Profit 10% :
Jumlah & pembulatan :
ANALISA HARGA SATUAN PEKERJAAN
1 3 4
R. Harga satuan pekerjaan Signage
16 1 Unit Wall Signage tipe S3-6 s/d S3-8 ukuran variabel
1 Harga terpasang
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
17 1 Unit Wall Signage tipe S3-9 s/d S3-10 ukuran 400 x 2340mm
1 Harga terpasang
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
1 3 4
R. Harga satuan pekerjaan Signage
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
23 1 Unit Wall Signage tipe S3-17 & S3-18 ukuran 2520 x 7505mm
1 Harga terpasang
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
ANALISA HARGA SATUAN PEKERJAAN
1 3 4
R. Harga satuan pekerjaan Signage
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
ANALISA HARGA SATUAN PEKERJAAN
1 3 4
R. Harga satuan pekerjaan Signage
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
ANALISA HARGA SATUAN PEKERJAAN
1 3 4
R. Harga satuan pekerjaan Signage
32 1 Unit Floor Signage tipe S6-1 ukuran Ø800
1 Harga terpasang
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
2 1 Unit Ceilling hanging Signage tipe S7-1 s/d S7-3 ukuran 200x600 mm
1 Harga terpasang
Terpasang Rangka hollow 40x40x2mm 0.12
Terpasang Acrylic t=10mm warna 0.12
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
1 3 4
R. Harga satuan pekerjaan Signage
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
3 Biaya pemasangan :
Galian + pengecoran 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
ANALISA HARGA SATUAN PEKERJAAN
1 3 4
R. Harga satuan pekerjaan Signage
7 1 Unit Wall Signage tipe S7-8 ukuran 100x700 mm
1 Harga terpasang
Plat alumunium t=3mm 0.07
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
10 1 Unit Ceilling hanging Signage tipe S7-11 & S7-12 ukuran 200x600 mm
1 Harga terpasang
Terpasang Rangka hollow 40x40x2mm 0.12
Terpasang Acrylic t=10mm warna 0.12
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
ANALISA HARGA SATUAN PEKERJAAN
1 3 4
R. Harga satuan pekerjaan Signage
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
3 Biaya pemasangan :
Galian + pengecoran 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
2 Biaya finishing
Finishing cat huruf dan Gambar 1.00
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
Jumlah :
Overhead + Profit 10% :
Jumlah & pembulatan :
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
12,748,339.74
m2 110,740.67 121,814.73
m2 164,450.00 180,895.00
m2 169,813.21 186,794.54
cm 9,450.00 189,000.00
cm 9,450.00 1,748,250.00
cm 9,450.00 425,250.00
cm 9,450.00 8,070,300.00
m2 1,335,032.25 1,468,535.47
Lot 357,500.00 357,500.00
LS 1,274,833.97 1,274,833.97 1,274,833.97
14,023,173.72
1,402,317.37
15,425,491.00
12,390,839.74
m2 110,740.67 121,814.73
m2 164,450.00 180,895.00
m2 169,813.21 186,794.54
cm 9,450.00 189,000.00
cm 9,450.00 1,748,250.00
cm 9,450.00 425,250.00
cm 9,450.00 8,070,300.00
m2 1,335,032.25 1,468,535.47
LS 1,239,083.97 1,239,083.97 1,239,083.97
13,629,923.72
1,362,992.37
14,992,916.00
uran 640x1200 mm
1,149,966.86
m2 110,740.67 85,048.83
m2 693,306.01 1,064,918.03
1,863,727.63
186,372.76
2,050,100.00
192,971.20
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
m2 110,740.67 26,577.76
m2 693,306.01 166,393.44
304,496.32
30,449.63
334,945.00
359,364.65
m2 110,740.67 26,577.76
m2 693,306.01 332,786.89
582,414.89
58,241.49
640,656.00
241,214.00
m2 110,740.67 33,222.20
m2 693,306.01 207,991.80
380,620.40
38,062.04
418,682.00
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
289,456.80
m2 110,740.67 39,866.64
m2 693,306.01 249,590.16
456,744.48
45,674.45
502,418.00
96,485.60
m2 110,740.67 13,288.88
m2 693,306.01 83,196.72
152,248.16
15,224.82
167,472.00
192,971.20
m2 110,740.67 26,577.76
m2 693,306.01 166,393.44
304,496.32
30,449.63
334,945.00
289,456.80
m2 110,740.67 39,866.64
m2 693,306.01 249,590.16
456,744.48
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
45,674.45
502,418.00
754,665.76
m2 110,740.67 55,813.30
m2 693,306.01 698,852.46
1,223,071.26
122,307.13
1,345,378.00
195,168.96
19,516.90
214,685.00
97,584.48
9,758.45
107,342.00
378,139.86
37,813.99
415,953.00
414,734.04
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
41,473.40
456,207.00
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
421,704.36
42,170.44
463,874.00
652,421.95
65,242.20
717,664.00
345,030.84
34,503.08
379,533.00
216,428.44
21,642.84
238,071.00
264,523.64
26,452.36
290,976.00
5 6 7 9
3,874,299.02
387,429.90
4,261,728.00
9,738,931.10
973,893.11
10,712,824.00
9,628,335.36
962,833.54
10,591,168.00
8,788,458.27
878,845.83
9,667,304.00
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
131,018.36
m2 110,740.67 9,689.81
m2 693,306.01 121,328.55
212,338.76
21,233.88
233,572.00
150,190.20
m2 110,740.67 14,949.99
m2 164,450.00 22,200.75
m2 169,813.21 22,924.78
m2 1,335,032.25 90,114.68
LS 31,366.44 31,366.44 31,366.44
181,556.64
18,155.66
199,712.00
28,141.63
m2 110,740.67 3,875.92
m2 693,306.01 24,265.71
44,405.71
4,440.57
48,846.00
54,273.15
m2 110,740.67 7,475.00
m2 693,306.01 46,798.16
85,639.59
8,563.96
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
94,203.00
126,000.00
cm 6,300.00 126,000.00
126,000.00
12,600.00
138,600.00
252,000.00
cm 6,300.00 252,000.00
252,000.00
25,200.00
277,200.00
105,862.82
m2 110,740.67 10,298.88
m2 164,450.00 15,293.85
m2 169,813.21 15,792.63
m2 693,306.01 64,477.46
LS 13,940.64 13,940.64 13,940.64
cm 4,725.00 189,000.00 189,000.00
308,803.46
30,880.35
339,683.00
105,000.00
cm 2,625.00 105,000.00
105,000.00
10,500.00
115,500.00
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
187,126.40
18,712.64
205,839.00
989,564.95
98,956.50
1,088,521.00
96,485.60
m2 110,740.67 13,288.88
m2 693,306.01 83,196.72
152,248.16
15,224.82
167,472.00
179,682.32
m2 110,740.67 13,288.88
m2 693,306.01 166,393.44
291,207.44
29,120.74
320,328.00
5 6 7 9
231,066.11
23,106.61
254,172.00
264,712.57
m1 271,958.56 1,514,809.15
m1 95,909.11 191,818.21
m2 303,726.50 72,894.36
478,317.69
47,831.77
526,149.00
128,647.47
m2 110,740.67 17,718.51
m2 693,306.01 110,928.96
202,997.55
20,299.75
223,297.00
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
27,731.55
m2 396,165.00 27,731.55
76,523.79
7,652.38
84,176.00
47,539.80
m2 396,165.00 47,539.80
131,183.64
13,118.36
144,302.00
40,202.33
m2 110,740.67 5,537.03
m2 693,306.01 34,665.30
63,436.73
6,343.67
69,780.00
96,485.60
m2 110,740.67 13,288.88
m2 693,306.01 83,196.72
152,248.16
15,224.82
H. SATUAN BAHAN TOTAL
SATUAN Rp Rp Rp
5 6 7 9
167,472.00
264,712.57
m1 95,909.11 191,818.21
m2 303,726.50 72,894.36
478,317.69
47,831.77
526,149.00
239,576.43
m2 110,740.67 17,718.51
m2 693,306.01 221,857.92
388,276.59
38,827.66
427,104.00
324,881.87
m2 110,740.67 16,611.10
m2 164,450.00 49,335.00
m2 169,813.21 50,943.96
m2 693,306.01 207,991.80
LS 139,406.40 139,406.40 139,406.40
464,288.27
46,428.83
510,717.00
ANALISA HARGA SATUAN PEKERJAAN
KOEF SATUAN
NO. URAIAN
1 2 3 4
S PEKERJAAN RAK SEPEDA
Jumlah 10,359,446.25
Overhead & keuntungan 10% : 1,035,944.63
Jumlah : 11,395,390.88
258,160.00 3,289,988.56 3,289,988.56
Dibulatkan : 14,685,300.00