3 Pekerjaan Beton Bertulang 940,223,016.70 27.721 3.465 6.930 6.930 6.930 3.465
4 Pekerjaan Dinding Dan Plesteran 201,288,357.08 5.935 0.989 0.989 1.978 1.978
6 Pekerjaan Pasangan Dinding dan Lantai Keramik 157,079,340.31 4.631 1.158 1.158 1.158 1.158
7 Pekerjaan Pintu Alumunium,Besi Dan Pagar 178,575,752.13 5.265 0.878 0.878 0.878 0.878 0.878 0.439 0.439
6 Pekerjaan Pintu Alumunium,Besi Dan Pagar 160,971,779.30 4.746 0.949 0.949 0.949 0.949 0.949
10 Pekerjaan AC 94,900,000.00 2.798 0.466 0.466 0.466 0.466 0.233 0.233 0.233 0.233
PRESTASI MENURUT RENCANA 0.000 2.846 7.214 14.320 22.395 31.304 40.213 48.337 55.658 61.965 67.752 72.495 77.097 81.015 84.830 88.472 91.745 94.570 97.058 98.801 99.473 100.000
3.943 7.100 14.977 22.164 30.250 31.501 34.717 38.258 40.240 43.946 47.554 49.567 52.426 57.180 60.630 65.439 69.536 76.784 83.005 91.288 100.00
PRESTASI MENURUT PELAKSANAAN 0.000
DEVIASI PERENCANA MENURUT PELAKSANA 0.000 1.097 -0.114 0.656 -0.231 -1.054 -8.712 -13.619 -17.400 -21.725 -23.806 -24.941 -27.530 -28.589 -27.649 -27.841 -26.306 -25.034 -20.275 -15.796 -8.185 0.003
LAPORAN KEMAJUAN PEKERJAAN (PROGRES)
PENEYLESAIAN
S/D
NO URAIAN PEKERJAAN BOBOT (% ) BIAYA (Rp) S/D MINGGU TIAP BAGIAN
S/D MINGGU LALU (Rp) MINGGU S/D MINGGU INI (Rp)
LALU (% ) PEKERJAAN (% )
INI (% )