Anda di halaman 1dari 4

PEKERJAAN PERKERASAN JA

Panjang =
Lebar =

Perhitungan volume hamparan LPA Batu Pecah 2/3 Leveling = 0.1 x 4.00 x 380 =
= 15% x 152 =
=
Perhitungan volume hamparan HRS = 1 x 4.00 x 380 =
Kebutuhan Bahan, Alat dan Upah Pekerjaan Perkerasan Jalan Lingkungan dengan Konstruksi HRS
= Volume x Analisa

Pek. 1m3 LPB Batu Pecah 2/3 (menggunakan buruh) Pek. 1m2 Penghamparan lapis aspal beton (LAST
Material: Material:
Batu Pecah Mesin 2/3 = 1.0200 x 22.8 = 23.26 m3 HRS (LATASTON) =
Alat Bantu = 0.0016 x 22.8 = 0.04 set Alat Bantu =

Alat: Alat:
Mesin Gilas Tandem 6 - 10 ton = 0.0402 x 22.8 = 0.92 Jam Mesin Gilas Tandem 6 - 10 ton =

Upah: Upah:
Operator Terlatih = 0.0402 x 22.8 = 0.92 OH Mandor Lapangan =
Pembantu Operator = 0.0402 x 22.8 = 0.92 OH Operator Terlatih =
Pekerja = 0.4875 x 22.8 = 11.12 OH Pembantu Operator =

Tukang =
Pekerja =

Total Kebutuhan Bahan, Alat dan Upah untuk pe


Batu Pecah Mesin 2/3 =
HRS (LASTON) =

Alat Bantu (set @ 3 alat) =


Mesin Gilas Tandem 6 - 10 ton =

Operator Terlatih =
Pembantu Operator =
Tukang =
Pekerja =
AAN PERKERASAN JALAN LINGKUNGAN (HRS)
380 m
4.00 m

152.0 m3
22.8 m3

1,520.0 m2

is aspal beton (LASTON) t. 4 cm

0.0803 x 1,520 = 122.03 Ton


0.0004 x 1,520 = 0.65 set

0.0400 x 1,520 = 60.80 Jam

0.0009 x 1,520 = 1.35 OH


0.0089 x 1,520 = 13.51 OH
0.0089 x 1,520 = 13.51 OH

0.0111 x 1,520 = 16.84 OH


0.1108 x 1,520 = 168.42 OH

t dan Upah untuk pekerjaan Jalan ligkungan (HRS)


23.26 23.00 m3
122.03 122.00 ton

0.69 1.00 set


61.72 62.00 Jam
1 HARI
14.43 14.00 OH
14.43 14.00 OH
16.84 17.00 OH
179.53 180.00 OH
RENCANA ANGGARAN BIAYA
Propinsi : Jawa Barat No. RAB :
Kabupaten : Subang Sumber Dana : BANPROV TA. 2020
Kecamatan : Pamanukan Pagu : Rp. 200.000.000,-
Desa : Pamanukan Jenis Kegiatan : HOTMIX (LASTON T4CM)
Lokasi : Dusun Pilangsari RW 01 Volume Keg. : P X L ( 380 m X 4 m )

HARGA
JUMLAH BOBOT
NO URAIAN VOLUME SATUAN SATUAN
( Rp ) ( Rp ) (%)
A B C D E F=CXE G

1 PELAPORAN DAN SPJ


1.1 MATERAI 6000 3.00 LBR 7,500 22,500
1.2 MATERAI 3000 3.00 LBR 4,500 13,500
1.3 ATK 1.00 LS 70,000 70,000
1.4 PHOTOCOPY 50.00 LBR 200 10,000
1.5 KERTAS F4 40.00 LBR 100 4,000
1.6 DOKUMENTASI 2.00 KEG 75,000 150,000
SUB TOTAL 1 270,000 0.14%
2 PEK. HOTMIX (LASTON T4CM)
2.1 BAHAN
2.1.1 HRS 122.00 TON 1,390,000 169,580,000
2.1.2 BATU PECAH TERSARING (LPA) 23.00 M3 300,000 6,900,000
SUB TOTAL 2.1 176,480,000 88.24%
2.2 ALAT
2.2.1 ALAT BANTU (SET @3ALAT) 2.00 SET 150,000 300,000
2.2.2 MESIN GILAS TANDEM ROLLER 2.00 HARI 650,000 1,300,000
2.2.3 MOBILISASI DAN DEMOBILISAS ALAT 1.00 LS 700,000 700,000
SUB TOTAL 2.2 2,300,000 1.15%
2.3 UPAH
2.3.1 OPERATOR 14.00 HOK 150,000 2,100,000
2.3.2 PEMBANTU OPERATOR 14.00 HOK 90,000 1,260,000
2.3.3 PEKERJA 180.00 HOK 85,000 15,300,000
2.3.4 TUKANG 17.00 HOK 120,000 2,040,000
SUB TOTAL 2.3 20,700,000 10.35%
3 INFORMASI
3.1 PAPAN PROYEK 1.00 BUAH 250,000 250,000

SUB TOTAL 3 250,000 0.13%

JUMLAH RENCANA ANGGARAN BIAYA 200,000,000 100%

Subang, 23 Maret 2020


Disetujui / Mengesahkan
Kepala Desa Pamanukan, Ketua Tim Pelaksana Kegiatan
JAMALUDIN HERI SUSANTO