Hotmix Pilangsari
Hotmix Pilangsari
Panjang =
Lebar =
Perhitungan volume hamparan LPA Batu Pecah 2/3 Leveling = 0.1 x 4.00 x 380 =
= 15% x 152 =
=
Perhitungan volume hamparan HRS = 1 x 4.00 x 380 =
Kebutuhan Bahan, Alat dan Upah Pekerjaan Perkerasan Jalan Lingkungan dengan Konstruksi HRS
= Volume x Analisa
Pek. 1m3 LPB Batu Pecah 2/3 (menggunakan buruh) Pek. 1m2 Penghamparan lapis aspal beton (LAST
Material: Material:
Batu Pecah Mesin 2/3 = 1.0200 x 22.8 = 23.26 m3 HRS (LATASTON) =
Alat Bantu = 0.0016 x 22.8 = 0.04 set Alat Bantu =
Alat: Alat:
Mesin Gilas Tandem 6 - 10 ton = 0.0402 x 22.8 = 0.92 Jam Mesin Gilas Tandem 6 - 10 ton =
Upah: Upah:
Operator Terlatih = 0.0402 x 22.8 = 0.92 OH Mandor Lapangan =
Pembantu Operator = 0.0402 x 22.8 = 0.92 OH Operator Terlatih =
Pekerja = 0.4875 x 22.8 = 11.12 OH Pembantu Operator =
Tukang =
Pekerja =
Operator Terlatih =
Pembantu Operator =
Tukang =
Pekerja =
AAN PERKERASAN JALAN LINGKUNGAN (HRS)
380 m
4.00 m
152.0 m3
22.8 m3
1,520.0 m2
HARGA
JUMLAH BOBOT
NO URAIAN VOLUME SATUAN SATUAN
( Rp ) ( Rp ) (%)
A B C D E F=CXE G