Anda di halaman 1dari 1

Lampiran 4.

PROYEK : PEMBANGUNAN GEDUNG MERIAL TOWER RS. PELNI


BAGIAN : SISTEM SISTEM LISTRIK ARUS LEMAH
PERIHAL : DATA KEBUTUHAN PERALATAN DETEKSI KEBAKARAN
REV. / TANGGAL : 00 / 05 FEBRUARI 2020
DIBUAT OLEH : PT. DETA DECON

Junction
Detektor Asap Detektor Panas Detektor Panas Bel Titik
Box Fire Zone Jack Lampu Flow Tamper
Loop

No. Lokasi Photo Elektrik Tipe Kombinasi Suhu Tetap Lampu Indikator Tanda Panggil
Alarm Alarm Intercom Flasher Switch Switch
(Konvensional) (Konvensional) (Konvensional) Bahaya Manual
(JBFA)

1 Basement 2 1 31 15 15 - - 5 5 5 5 1 1
2 Basement 1 1 21 29 37 - - 3 3 3 3 1 1
3 Lantai 1 loop 1 1 29 66 - - 5 5 5 5 1 1
4 Lantai 2 1 22 84 - - 28 4 4 4 4 1 1
5 Lantai Mezz 1 18 28 - - - 3 3 3 3 1 1
6 Lantai 3 1 21 83 - - 28 3 3 3 3 1 1
7 Lantai 4 1 25 92 - - 19 4 4 4 4 1 1
loop 2
8 Lantai 5 1 41 70 - - 7 8 8 8 8 1 1
9 Lantai 6 1 28 77 - - - 5 5 5 5 1 1
10 Lantai 7 1 25 80 - - 30 4 4 4 4 1 1
11 Lantai 8 1 25 80 - - 30 4 4 4 4 1 1
loop 3
12 Lantai 9 1 25 77 - - 36 4 4 4 4 1 1
13 Lantai 10 1 24 57 - - - 4 4 4 4 1 1
14 Lantai Atap - - - - - - - - - - - -
TOTAL 13 335 838 52 - 178 56 56 56 56 13 13