Anda di halaman 1dari 2

USULAN HARGA PEKERJAAN GEOTEKNIK

UNTUK DETAIL DESAIN PELABUHAN IKAN DI SAMPIT , KALSEL

No. MACAM PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


( Rp.- ) ( Rp.- )

A. MOBILISASI & DEMOBILISASI PERALATAN KALI 1 7,500,000 7,500,000

B. PEKERJAAN PEMBORAN
1 Pemboran Inti 2 titik pemboran @ 30 meter mtr 60 650,000 39,000,000
2 Moving titik bor kali 2 750,000 1,500,000
3 SPT interval 3 meter kali 30 175,000 5,250,000
4 Undisrurbed Sample interval 5 meter kali 6 250,000 1,500,000
5 Sondir Cap. 2 Ton titik 2 1,250,000 2,500,000

C. ANALYSA LABORATORIUM

Index Properties
- Moisture Content test 6 85,000 510,000
- Specific Gravity Test test 6 85,000 510,000
- Liquit Limit test 6 100,000 600,000
- Plastic Limit test 6 100,000 600,000
- Grain Size Distribution Analysis test 6 175,000 1,050,000
Engineering Properties
- Triaxial Compression Test ( Consolidated Undrain ) test 6 350,000 2,100,000
- Unconfined Compression Test test 6 300,000 1,800,000
- Consolidatin Test test 6 450,000 2,700,000
- Direct Shear Test test 6 275,000 1,650,000

D. LAPORAN & DATA ls 1 2,500,000 2,500,000

Sub- Total = 71,270,000

Catatan : Kalau Pemboran nya ada yang di laut , pasti akan ada beaya pembuatan perancah kalau kedalaman laut nya
7 meter perancah nya dari bambu sekitar 4 jt - 7 jt
KETERANGAN

Tergantung daerah nya

Anda mungkin juga menyukai