PROGRAM :
KEGIATAN : PEKERJAAN PEMBANGUNAN MASJID SMK NEGERI 2
SAMARINDA - KALIMANTAN TIMUR
LOKASI : JL. A. WAHAB SYAHRANIE
i ii iii
I PEKERJAAN PENDAHULUAN Rp. 65,771,875.00
II PEKERJAAN PEMBANGUNAN MASJID
Terbilang :
I. PEKERJAAN PENDAHULUAN
1 Papan Nama Proyek 1.00 Ls 500,000.00 500,000.00
2 Pagar proyek 125.00 m1 284,175.00 35,521,875.00
3 Direksi keet 1.00 ls 12,000,000.00 12,000,000.00
4 Gudang dan alat‐alat sementara 1.00 ls 12,000,000.00 12,000,000.00
5 Penyediaan air & listrik untuk kerja 1.00 Ls 5,000,000.00 5,000,000.00
6 Administrasi dan dokumentasi 1.00 Ls 750,000.00 750,000.00
SUBTOTAL I. PEKERJAAN PENDAHULUAN 65,771,875.00
A. PEKERJAAN PERSIAPAN
C. PEKERJAAN PANCANG
1 1 M' Biaya Memancang tiang 10 x 10
0.1250 OH Pekerja 100,000.00 12,500.00 12,500.00
0.0500 OH Tukang 140,000.00 7,000.00 7,000.00
0.0050 OH Kep. Tukang 150,000.00 750.00 750.00
0.0130 OH mandor 165,000.00 2,145.00 2,145.00
Jumlah Total 22,395.00 22,395.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
2 1 Titik Memancang tiang Ulin 10x10, p = 2 m
0.0200 m3 Kayu ulin 10x10 5,000,000.00 100,000.00 100,000.00
0.0100 m3 Kalang dan sunduk 62,000.00 620.00 620.00
2.0000 m' Memancang tiang 22,395.00 44,790.00 44,790.00
Jumlah Total 100,620.00 44,790.00 145,410.00
3 1 m' Memancang Tiang Ulin 10/10 (menggunakan alat alat)
0.0750 jam Drop hammer 500,000.00 37,500.00 37,500.00
0.0170 Oh Pekerja 100,000.00 1,700.00 1,700.00
0.0170 Oh Tukang Pancang 140,000.00 2,380.00 2,380.00
0.0080 Oh Mandor 165,000.00 1,320.00 1,320.00
Jumlah Total 42,900.00 42,900.00
4 1 Titik Memancang tiang Ulin 10x10, p = 4 m
0.0370 m3 Kayu ulin 10x10 5,000,000.00 185,000.00 185,000.00
4.0000 m' Memancang tiang (menggunakan alat) 42,900.00 171,600.00 171,600.00
Jumlah Total 185,000.00 171,600.00 356,600.00
5 1 M3 Pekerjaan balok ulin 10/10
1.0500 m3 Kayu ulin 10x10 5,000,000.00 5,250,000.00 5,250,000.00
10.0000 kg Besi strip 34,000.00 340,000.00 340,000.00
0.8000 kg Paku biasa 2" ‐ 5" 20,000.00 16,000.00 16,000.00
6.0000 OH Tukang 140,000.00 840,000.00 840,000.00
1.2000 OH Kepala tukang 150,000.00 180,000.00 180,000.00
3.0000 OH Pekerja 100,000.00 300,000.00 300,000.00
0.2000 OH Mandor 165,000.00 33,000.00 33,000.00
Jumlah Total 5,606,000.00 1,353,000.00 6,959,000.00
E. PEKERJAAN BETON
1 1 M2 Pekerjaan bekisitng untuk Pondasi ‐ SNI 7394:2008
0.040 M3 Kayu Perancah 3,000,000.00 120,000.00 120,000.00
0.300 Kg Paku biasa 20,000.00 6,000.00 6,000.00
0.100 Ltr Minyak begisting 27,000.00 2,700.00 2,700.00
0.260 OH Tukang 140,000.00 36,400.00 36,400.00
0.026 OH Kepala tukang 150,000.00 3,900.00 3,900.00
0.520 OH Pekerja 100,000.00 52,000.00 52,000.00
0.026 OH Mandor 165,000.00 4,290.00 4,290.00
Jumlah Total 128,700.00 96,590.00 225,290.00
2 1 M2 Pekerjaan bekisitng untuk sloof ‐ SNI 7394:2008
0.045 M3 Kayu Perancah 3,000,000.00 135,000.00 135,000.00
0.300 Kg Paku biasa 20,000.00 6,000.00 6,000.00
0.100 Ltr Minyak begisting 27,000.00 2,700.00 2,700.00
0.260 OH Tukang 140,000.00 36,400.00 36,400.00
0.026 OH Kepala tukang 150,000.00 3,900.00 3,900.00
0.520 OH Pekerja 100,000.00 52,000.00 52,000.00
0.026 OH Mandor 165,000.00 4,290.00 4,290.00
Jumlah Total 143,700.00 96,590.00 240,290.00
3 1 M2 Pekerjaan bekisting untuk kolom ‐ SNI 7394:2008 SNI 7394:2008
0.040 M3 Kayu Perancah 3,000,000.00 120,000.00 120,000.00
0.400 Kg Paku biasa 20,000.00 8,000.00 8,000.00
0.200 Ltr Minyak begisting 27,000.00 5,400.00 5,400.00
0.015 m3 Balok Kayu Kelas II 5,000,000.00 75,000.00 75,000.00
0.350 Lbr Plywood 9 mm 120,000.00 42,000.00 42,000.00
2.000 btg Dolken Kayu Galam Ø 8‐10 cm, p:4 m 16,900.00 33,800.00 33,800.00
0.330 OH Tukang 140,000.00 46,200.00 46,200.00
0.033 OH Kepala tukang 150,000.00 4,950.00 4,950.00
0.660 OH Pekerja 100,000.00 66,000.00 66,000.00
0.033 OH Mandor 165,000.00 5,445.00 5,445.00
Jumlah Total 284,200.00 122,595.00 406,795.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
4 1 M2 Pekerjaan bekisitng untuk kolom Praktis
0.003 M3 Kayu Perancah 3,000,000.00 9,000.00 9,000.00
0.400 Kg Paku biasa 20,000.00 8,000.00 8,000.00
0.200 Ltr Minyak begisting 27,000.00 5,400.00 5,400.00
0.117 Lbr Plywood 9 mm 120,000.00 14,040.00 14,040.00
0.300 OH Tukang 140,000.00 42,000.00 42,000.00
0.030 OH Kepala tukang 150,000.00 4,500.00 4,500.00
0.600 OH Pekerja 100,000.00 60,000.00 60,000.00
0.030 OH Mandor 165,000.00 4,950.00 4,950.00
Jumlah Total 36,440.00 111,450.00 147,890.00
5 1 M2 Pekerjaan Begisting Balok SNI 7394:2008
0.040 M3 Kayu Perancah 3,000,000.00 120,000.00 120,000.00
0.400 Kg Paku biasa 20,000.00 8,000.00 8,000.00
0.200 Ltr Minyak begisting 27,000.00 5,400.00 5,400.00
0.018 m3 Balok Kayu Kelas II 5,000,000.00 90,000.00 90,000.00
0.350 Lbr Plywood 9 mm 120,000.00 42,000.00 42,000.00
2.000 btg Dolken Kayu Galam Ø 8‐10 cm, p:4 m 16,900.00 33,800.00 33,800.00
0.330 OH Tukang 140,000.00 46,200.00 46,200.00
0.033 OH Kepala tukang 150,000.00 4,950.00 4,950.00
0.320 OH Pekerja 100,000.00 32,000.00 32,000.00
0.006 OH Mandor 165,000.00 990.00 990.00
Jumlah Total 299,200.00 84,140.00 383,340.00
6 1 M2 Pekerjaan Begisting Lantai / Slab SNI 7394:2008
0.040 M3 Kayu Perancah 3,000,000.00 120,000.00 120,000.00
0.400 Kg Paku biasa 20,000.00 8,000.00 8,000.00
0.200 Ltr Minyak begisting 27,000.00 5,400.00 5,400.00
0.015 m3 Balok Kayu Kelas II 5,000,000.00 75,000.00 75,000.00
0.350 Lbr Plywood 9 mm 120,000.00 42,000.00 42,000.00
6.000 btg Dolken Kayu Galam Ø 8‐10 cm, p:4 m 16,900.00 101,400.00 101,400.00
0.330 OH Tukang 140,000.00 46,200.00 46,200.00
0.033 OH Kepala tukang 150,000.00 4,950.00 4,950.00
0.660 OH Pekerja 100,000.00 66,000.00 66,000.00
0.033 OH Mandor 165,000.00 5,445.00 5,445.00
Jumlah Total 351,800.00 122,595.00 474,395.00
7 1 M3. Beton Lantai Kerja mutu K‐100 (fc=7,4 Mpa, 3‐6, w/c 0,87) SNI 7394:2008
0.638 m3 Pasir beton 280,000.00 178,640.00 178,640.00
0.761 m3 Koral Beton 450,000.00 342,450.00 342,450.00
230.000 kg Semen 1,500.00 345,000.00 345,000.00
200.000 Ltr Air 1,000.00 200,000.00 200,000.00
0.200 OH Tukang 140,000.00 28,000.00 28,000.00
0.020 OH Kepala Tukang 150,000.00 3,000.00 3,000.00
1.200 OH Pekerja 100,000.00 120,000.00 120,000.00
0.060 OH Mandor 165,000.00 9,900.00 9,900.00
Jumlah Total 1,066,090.00 160,900.00 1,226,990.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
8 1 M3. Beton Lantai Kerja mutu K‐175 (fc=14,5 Mpa, slump 12 ±2 cm, w/c 0,66) SNI 7394:2008
0.543 m3 Pasir beton 280,000.00 152,040.00 152,040.00
0.762 m3 Koral Beton 450,000.00 342,900.00 342,900.00
326.000 kg Semen 1,500.00 489,000.00 489,000.00
215.000 Ltr Air 1,000.00 215,000.00 215,000.00
0.275 OH Tukang 140,000.00 38,500.00 38,500.00
0.028 OH Kepala Tukang 150,000.00 4,200.00 4,200.00
1.650 OH Pekerja 100,000.00 165,000.00 165,000.00
0.083 OH Mandor 165,000.00 13,695.00 13,695.00
Jumlah Total 1,198,940.00 221,395.00 1,420,335.00
9 1 M3. Beton Lantai Kerja mutu K‐225 (fc=19,3 Mpa, slump 12 ±2 cm, w/c 0,58) SNI 7394:2008
0.499 m3 Pasir beton 280,000.00 139,720.00 139,720.00
0.776 m3 Koral Beton 0.00 - -
371.000 kg Semen 0.00 - -
215.000 Ltr Air 1,000.00 215,000.00 215,000.00
0.275 OH Tukang 140,000.00 38,500.00 38,500.00
0.028 OH Kepala Tukang 150,000.00 4,200.00 4,200.00
1.650 OH Pekerja 100,000.00 165,000.00 165,000.00
0.083 OH Mandor 165,000.00 13,695.00 13,695.00
Jumlah Total 354,720.00 221,395.00 576,115.00
10 1 Kg Pekerjaan Tulangan Beton SNI 7394:2008
1.0500 Kg Besi 0.00 - -
0.0150 Kg Kawat Bendrat 0.00 - -
0.0070 OH Tukang 0.00 - -
0.0070 OH Kepala tukang 0.00 - -
0.0070 OH Pekerja 0.00 - -
0.0004 OH Mandor 0.00 - -
Jumlah Total - - -
11 1 M3 Plat Dekker (tebal 15 cm)
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
170.448 Kg Besi - - -
4.242 M2 Bekisting 474,395.00 2,012,383.59 2,012,383.59
Jumlah Total 2,588,498.59 2,588,498.59
12 1 M3 Plat Dekker (tebal 20 cm)
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
131.769 Kg Besi - - -
2.917 M2 Bekisting 474,395.00 1,383,810.22 1,383,810.22
Jumlah Total 1,959,925.22 1,959,925.22
13 1 M3 Pondasi poer P1 (uk. 100x100x30 cm)
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
263.000 Kg Besi - - -
4.000 M2 Bekisting 225,290.00 901,160.00 901,160.00
Jumlah Total 1,477,275.00 1,477,275.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
14 1 M3 Pondasi poer P2 (uk. 80x80x30 cm)
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
276.150 Kg Besi - - -
4.667 M2 Bekisting 225,290.00 1,051,428.43 1,051,428.43
Jumlah Total 1,627,543.43 1,627,543.43
15 1 M3 Kolom K1 dia.30
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
254.371 Kg Besi - - -
16.985 M2 Bekisting 406,795.00 6,909,413.08 6,909,413.08
Jumlah Total 7,485,528.08 7,485,528.08
16 1 M3 Kolom K2 30/30
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
274.379 Kg Besi - - -
16.000 M2 Bekisting 406,795.00 6,508,720.00 6,508,720.00
Jumlah Total 7,084,835.00 7,084,835.00
17 1 M3 Kolom K3 20/20
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
218.051 Kg Besi - - -
20.000 M2 Bekisting 406,795.00 8,135,900.00 8,135,900.00
Jumlah Total 8,712,015.00 8,712,015.00
18 1 M3 Kolom KP 13/13
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
320.204 Kg Besi - - -
23.077 M2 Bekisting 147,890.00 3,412,857.53 3,412,857.53
Jumlah Total 3,988,972.53 3,988,972.53
19 1 M3 Sloof S1 20/30
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
310.739 Kg Besi - - -
13.333 M2 Bekisting 240,290.00 3,203,786.57 3,203,786.57
Jumlah Total 3,779,901.57 3,779,901.57
20 1 M3 Sloof S2 15/20
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
302.705 Kg Besi - - -
18.333 M2 Bekisting 240,290.00 4,405,236.57 4,405,236.57
Jumlah Total 4,981,351.57 4,981,351.57
21 1 M3 Balok B1 20/30
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
310.739 Kg Besi - - -
13.333 M2 Bekisting 383,340.00 5,111,072.22 5,111,072.22
Jumlah Total 5,687,187.22 5,687,187.22
22 1 M3 Balok B2 15/25
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
427.615 Kg Besi - - -
17.333 M2 Bekisting 383,340.00 6,644,432.22 6,644,432.22
Jumlah Total 7,220,547.22 7,220,547.22
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
23 1 M3 Balok RB 15/20
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
302.705 Kg Besi - - -
18.333 M2 Bekisting 383,340.00 7,027,772.22 7,027,772.22
Jumlah Total 7,603,887.22 7,603,887.22
24 1 M3 Balok Talang Beton
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
85.523 Kg Besi - - -
7.500 M2 Bekisting 383,340.00 2,875,050.00 2,875,050.00
Jumlah Total 3,451,165.00 3,451,165.00
25 1 M3 Plat atap dak tebal 12cm
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
90.024 Kg Besi - - -
8.333 M2 Bekisting 474,395.00 3,953,133.54 3,953,133.54
Jumlah Total 4,529,248.54 4,529,248.54
26 1 M3 Plat lantai pembesian wiremesh M.10
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
85.100 Kg Besi wiremesh M.10 0.00 - -
Jumlah Total 576,115.00 576,115.00
H. PEKERJAAN ATAP DAN PLAFOND
1 1 M2 Mengerjakan kuda‐kuda / Frame & Rangka atap baja ringan
1.440 M' Canal C 65x26 0.00 - -
3.650 M' Reng ( type U ) 0,4 TCT 0.00 - -
47.600 Pcs Screw 12‐14x20 0.00 - -
40.040 Pcs Screw 10‐16x16 0.00 - -
1.520 Pcs L Braket 0.00 - -
1.840 Pcs Dynabolt 0.00 - -
0.050 OH Tukang 0.00 - -
0.010 OH Kepala tukang 0.00 - -
0.500 OH Pekerja 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
2 1 M2 Memasang atap Genteng Metal
1.050 Lbr Genteng Metal 0.00 - -
0.200 Kg Paku Genteng 0.00 - -
0.100 OH Tukang 0.00 - -
0.010 OH Kepala tukang 0.00 - -
0.200 OH Pekerja 0.00 - -
0.001 OH Mandor 0.00 - -
Jumlah Total - - -
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
3 1 M1 Memasang Bubungan Genteng Metal
1.100 Bh Bubungan Genteng Metal 0.00 - -
0.050 Kg Paku Genteng 0.00 - -
0.150 OH Tukang 0.00 - -
0.015 OH Kepala tukang 0.00 - -
0.250 OH Pekerja 0.00 - -
0.013 OH Mandor 0.00 - -
Jumlah Total - - -
4 1 M' listplank GRC
1.100 Lbr GRC Board 0.00 - -
0.100 Kg Paku - - -
0.200 OH Tukang 0.00 - -
0.025 OH Kepala tukang 0.00 - -
0.100 OH Pekerja 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
5 1 M2 Rangka Plafond Hollow
3.500 m' Besi Hollow 0.00 - -
1.000 Ls Gantungan kawat 20,000.00 20,000.00 20,000.00
3.000 bh Dynabolt 0.00 - -
0.250 Oh Pekerja 0.00 - -
0.300 Oh Tukang 0.00 - -
0.050 Oh Kepala Tukang 0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total 20,000.00 - 20,000.00
6 1 M2 Memasang Plafond Gypsum ‐ SNI 2839 : 2008
0.364 M2 Gypsum board 0.00 - -
0.110 Kg Paku gypsum 0.00 - -
0.050 OH Tukang 0.00 - -
0.005 OH Kepala tukang kayu 0.00 - -
0.100 OH Pekerja 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
7 1 M2 Memasang Plafond Calsiboard ‐ SNI 03‐2838‐2002
0.3600 M2 Calsiboard 0.00 - -
0.0300 Kg Paku gypsum 0.00 - -
0.1000 OH Tukang 0.00 - -
0.0100 OH Kepala tukang kayu 0.00 - -
0.0700 OH Pekerja 0.00 - -
0.0035 OH Mandor 0.00 - -
Jumlah Total - - -
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
8 1 M' List Plafond Gypsum SNI 2839 : 2008
1.050 M2 List Gypsum 0.00 - -
0.150 Kg Tepung gypsum 0.00 - -
0.060 OH Tukang 0.00 - -
0.006 OH Kepala tukang kayu 0.00 - -
0.060 OH Pekerja 0.00 - -
0.003 OH Mandor 0.00 - -
Jumlah Total - - -
I. PEKERJAAN PENGECATAN
1 1 M2 Mengecat dinding Luar SNI ‐ 2002
0.2600 Kg Cat Dinding Luar 0.00 - -
0.1000 Ltr Cat dasar 0.00 - -
0.1000 Kg Plamir 0.00 - -
1.0000 Lbr Kertas gosok 0.00 - -
0.0630 OH Tukang 0.00 - -
0.0063 OH Kepala tukang 0.00 - -
0.0200 OH Pekerja 0.00 - -
0.0025 OH Mandor 0.00 - -
Jumlah Total - - -
2 1 M2 Mengecat dinding dalam & Plafon SNI ‐ 2002
0.2600 Kg Cat Dinding Dalam 2x 0.00 - -
0.1000 kg Cat dasar 0.00 - -
0.1000 Kg Plamir tembok 0.00 - -
1.0000 Lbr Kertas gosok 0.00 - -
0.0630 OH Tukang 0.00 - -
0.0063 OH Kepala tukang 0.00 - -
0.0200 OH Pekerja 0.00 - -
0.0025 OH Mandor 0.00 - -
Jumlah Total - - -
3 1 M2 Waterproofing atap plat beton
1.0500 m2 Waterproofing Coating ( 2 lapis @1Kg ) 0.00 - -
1.0000 m2 Screed t=1,5 cm 35,000.00 35,000.00 35,000.00
1.0000 m2 Upah mengecat 25,000.00 25,000.00 25,000.00
Jumlah Total 35,000.00 25,000.00 60,000.00
J. PEKERJAAN SANITAIR
1 1 BH Memasang Klosed Duduk SNI ‐ 2002
1.0000 Bh Kloset Duduk 0.00 - -
0.0600 Ls Perlengkapan 6% harga kloset 0.00 - -
3.3000 Oh Pekerja 0.00 - -
0.1600 Oh Mandor 0.00 - -
1.1000 Oh Tukang Batu 0.00 - -
0.0010 Oh Kepala Tukang 0.00 - -
Jumlah Total - - -
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
2 1 BH Memasang Wastafel SNI ‐ 2002
1.0000 Bh Wastafel 0.00 - -
0.0600 Ls Perlengkapan 6% harga wastafel 0.00 - -
3.3000 Oh Pekerja 0.00 - -
0.1600 Oh Mandor 0.00 - -
1.1000 Oh Tukang Batu 0.00 - -
0.0010 Oh Kepala Tukang 0.00 - -
Jumlah Total - - -
3 Memasang Satu Buah Bak Mandi Fiber
1.0000 Bh Bak mandi fiber 0.00 - -
0.0600 Bh Perlengkapan 6% harga bak 0.00 - -
1.2000 OH Pekerja Biasa 0.00 - -
1.0000 OH Tukang Batu 0.00 - -
0.7000 OH Mandor 0.00 - -
Jumlah Total - - -
4 Memasang 1 Buah Kran
1.000 Bh Kran air 0.00 - -
0.025 Bh Seal tape 0.00 - -
0.010 OH Pekerja 0.00 - -
0.100 OH Tukang Batu 0.00 - -
0.010 OH Kepala Tukang 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
5 Memasang 1 Buah Jet shower
1.000 Bh Jet shower 0.00 - -
0.025 Bh Seal tape 0.00 - -
0.010 OH Pekerja 0.00 - -
0.100 OH Tukang Batu 0.00 - -
0.010 OH Kepala Tukang 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
6 Memasang 1 Buah Floor Drain
1.000 Bh Floor Drain 0.00 - -
0.010 OH Pekerja 0.00 - -
0.100 OH Tukang Batu 0.00 - -
0.010 OH Kepala Tukang 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
7 1 M' Pipa PVC AW 1/2" SNI ‐ 2002
1.200 m' Pipa PVC AW 1/2" 0.00 - -
0.350 - Perlengkapan 35 % harga Pipa 0.00 - -
0.036 Oh Pekerja 0.00 - -
0.060 Oh Tukang 0.00 - -
0.006 Oh Kepala Tukang 0.00 - -
0.002 Oh Mandor 0.00 - -
Jumlah Total - - -
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
8 1 M' Pipa PVC AW 1" SNI ‐ 2002
1.200 m' Pipa PVC AW 1" 0.00 - -
0.350 - Perlengkapan 35 % harga Pipa 0.00 - -
0.072 Oh Pekerja 0.00 - -
0.120 Oh Tukang 0.00 - -
0.012 Oh Kepala Tukang 0.00 - -
0.003 Oh Mandor 0.00 - -
Jumlah Total - - -
9 1 M' Pipa PVC AW 2" SNI ‐ 2002
1.200 m' Pipa PVC AW 2" 0.00 - -
0.350 - Perlengkapan 35 % harga Pipa 0.00 - -
0.072 Oh Pekerja 0.00 - -
0.120 Oh Tukang 0.00 - -
0.012 Oh Kepala Tukang 0.00 - -
0.003 Oh Mandor 0.00 - -
Jumlah Total - - -
10 1 M' Pipa PVC AW 3" SNI ‐ 2002
1.200 m' Pipa PVC AW 3" 0.00 - -
0.350 - Perlengkapan 35 % harga Pipa 0.00 - -
0.072 Oh Pekerja 0.00 - -
0.120 Oh Tukang 0.00 - -
0.012 Oh Kepala Tukang 0.00 - -
0.003 Oh Mandor 0.00 - -
Jumlah Total - - -
11 1 M' Pipa PVC AW 4" SNI ‐ 2002
1.200 m' Pipa PVC AW 4" 0.00 - -
0.350 - Perlengkapan 35 % harga Pipa 0.00 - -
0.072 Oh Pekerja 0.00 - -
0.120 Oh Tukang 0.00 - -
0.012 Oh Kepala Tukang 0.00 - -
0.003 Oh Mandor 0.00 - -
Jumlah Total - - -
K. PEKERJAAN LISTRIK
1 1 Titik Pasang Instalasi Titik Lampu / Stop Kontak
10.000 M' Pipa PVC 1/2" protector kabel / Conduit 0.00 - -
1.000 Bh Tee Doos 3 Lubang 1,500.00 1,500.00 1,500.00
1.000 Bh Tee Doos 4 Lubang 1,600.00 1,600.00 1,600.00
10.000 M' Kabel NYM 3 x 2,5 mm2 7,500.00 75,000.00 75,000.00
3.000 Bh Sok Counduit 800.00 2,400.00 2,400.00
4.000 M' Fleksibel Pipa conduit 11,000.00 44,000.00 44,000.00
10.000 Bh Klem Pipa 1,000.00 10,000.00 10,000.00
0.550 Bh Isolasi 25,000.00 13,750.00 13,750.00
0.004 Oh Mandor 0.00 - -
0.433 Oh Tukang listrik 0.00 - -
0.152 Oh Pekerja 0.00 - -
Jumlah Total 148,250.00 - 148,250.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
2 1 Bh Pasang Saklar Tunggal
1.000 Bh Saklar TunggaL 0.00 - -
0.100 Oh Pekerja 0.00 - -
0.010 Oh Tukang 0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total - - -
3 1 Bh Pasang Saklar Ganda
1.000 Bh Saklar double 0.00 - -
0.100 Oh Pekerja 0.00 - -
0.010 Oh Tukang 0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total - - -
4 1 Bh Pasang Stop Kontak
1.000 Bh Stop kontak 0.00 - -
0.100 Oh Pekerja 0.00 - -
0.010 Oh Tukang 0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total - - -
5 1 Bh Pasang DL 18 Watt
1.000 Bh DL 18 Watt 0.00 - -
0.100 Oh Pekerja 0.00 - -
0.010 Oh Tukang 0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total - - -
6 1 Bh Pasang Lampu SL 18 Watt
1.000 Bh SL 18 Watt 0.00 - -
0.100 Oh Pekerja 0.00 - -
0.010 Oh Tukang 0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total - - -
DAFTAR HARGA SATUAN UPAH DAN BAHAN
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )
II BAHAN LOGAM
1 Paku biasa Kg Dilokasi
2 Paku gypsum Kg Dilokasi
3 Paku plywood Kg Dilokasi
4 Paku Genteng Metal Kg Dilokasi
5 Besi Tulangan Kg Dilokasi
6 Kawat Bendrat Kg Dilokasi
7 Besi wiremesh M.10 Kg Dilokasi
8 Canal C75,75 m' Dilokasi
9 Reng (type U) 0,4 TCT m' Dilokasi
10 Screw 12-14 x 20 Pcs Dilokasi
11 Screw 10-16 x 16 Pcs Dilokasi
12 L Braket Pcs Dilokasi
13 Dynabolt Pcs Dilokasi
14 Besi Profil Kg Dilokasi
15 Besi Hollow 4 x 4 m' Dilokasi
16 Kusen Alumunium silver m' Dilokasi
17 Rangka Jendela Alumunium silver m' Dilokasi
18 Daun Pintu Alumunium m2 Dilokasi
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )
V BAHAN ATAP
1 Atap Genteng Metal Lbr Dilokasi
2 Bubungan Atap Genteng Metal Bh Dilokasi
3 Seng Gelombang Lbr Dilokasi
VIII LISTRIK
1 Lampu TL 2x36 Watt RMI Bh Dilokasi
2 Lampu Downlight 18 Watt Bh Dilokasi
3 Lampu SL 18 Watt Bh Dilokasi
4 Lampu Pijar Bh Dilokasi
5 Stop Kontak Bh Dilokasi
6 Saklar Tunggal Bh Dilokasi
7 Saklar Ganda Bh Dilokasi
Jumlah Bobot Rencana #REF! ### ### ### ### ### ### ### ### ### ### ### ### 3.45
Kumulatif Bobot Rencana 0.00 ### ### ### ### ### ### ### ### ### ### ### ### #REF!
0
0
0
0
0
DAFTAR HARGA SATUAN UPAH DAN BAHAN
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )
II BAHAN LOGAM
1 Paku biasa Kg 20,000.00 Dilokasi
2 Paku gypsum Kg 41,000.00 Dilokasi
3 Paku plywood Kg 29,000.00 Dilokasi
4 Paku Genteng Metal Kg 45,000.00 Dilokasi
5 Besi Tulangan Kg 20,000.00 Dilokasi
6 Kawat Bendrat Kg 33,000.00 Dilokasi
7 Besi wiremesh M.10 Kg 24,000.00 Dilokasi
8 Canal C75,75 m' 30,000.00 Dilokasi
9 Reng (type U) 0,4 TCT m' 22,000.00 Dilokasi
10 Screw 12-14 x 20 Pcs 700.00 Dilokasi
11 Screw 10-16 x 16 Pcs 500.00 Dilokasi
12 L Braket Pcs 8,000.00 Dilokasi
13 Dynabolt Pcs 4,000.00 Dilokasi
14 Besi Profil Kg 35,000.00 Dilokasi
15 Besi Hollow 4 x 4 m' 33,000.00 Dilokasi
16 Kusen Alumunium silver m' 221,000.00 Dilokasi
17 Rangka Jendela Alumunium silver m' 208,000.00 Dilokasi
18 Daun Pintu Alumunium m2 1,033,000.00 Dilokasi
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )
V BAHAN ATAP
1 Atap Genteng Metal Lbr 50,000.00 Dilokasi
2 Bubungan Atap Genteng Metal Bh 58,000.00 Dilokasi
3 Seng Gelombang Lbr 45,000.00 Dilokasi
VIII LISTRIK
1 Lampu TL 2x36 Watt RMI Bh 715,000.00 Dilokasi
2 Lampu Downlight 18 Watt Bh 422,000.00 Dilokasi
3 Lampu SL 18 Watt Bh 97,000.00 Dilokasi
4 Lampu Pijar Bh 45,000.00 Dilokasi
5 Stop Kontak Bh 78,000.00 Dilokasi
6 Saklar Tunggal Bh 52,000.00 Dilokasi
7 Saklar Ganda Bh 71,000.00 Dilokasi