Anda di halaman 1dari 29

REKAPITULASI ANGGARAN BIAYA

PROGRAM :
KEGIATAN : PEKERJAAN PEMBANGUNAN MASJID SMK NEGERI 2
SAMARINDA - KALIMANTAN TIMUR
LOKASI : JL. A. WAHAB SYAHRANIE

No. URAIAN PEKERJAAN JUMLAH

i ii iii
I PEKERJAAN PENDAHULUAN Rp. 65,771,875.00
II PEKERJAAN PEMBANGUNAN MASJID

II.1 PEKERJAAN SUB STRUKTUR Rp. 338,107,577.26


II.2 PEKERJAAN STRUKTUR BETON Rp. 677,685,392.70
II.3 PEKERJAAN ARSITEKTUR
II.3.1 PEKERJAAN PASANGAN DINDING & LANTAI Rp. 238,676,643.32
II.3.2 PEKERJAAN KUSEN, PINTU DAN JENDELA Rp. 53,600,000.00
II.3.3 PEKERJAAN ATAP & PLAFOND Rp. 327,543,315.50
II.3.4 PEKERJAAN CAT-CATAN Rp. 55,818,462.33
II.4 PEKERJAAN MEKANIKAL ELEKTRIKAL
II.4.1 PEKERJAAN SANITAIR Rp. 36,745,545.00
II.4.2 PEKERJAAN INSTALASI LISTRIK Rp. 50,619,865.00
II.5 PEKERJAAN LAIN-LAIN Rp. 22,200,000.00

JUMLAH Rp. 1,866,768,676.11


PPN 10% Rp. 186,676,867.61
GRAND TOTAL Rp. 2,053,445,543.72

DIBULATKAN Rp. 2,053,446,000.00

Terbilang :

Samarinda, 17 September 2018


Mengetahui, Dibuat Oleh,
KOMITE Kepala SMK Negeri 2
SMK Negeri 2 Samarinda Samarinda

BUDI SUYANTO Hj. SITTI AISYAH,S.Pd. SH. MM. MH


NIP. 19690912 199802 2 004
Kegiatan : Pekerjaan Pembangunan Masjid SMK Negeri 2
Samarinda - Kalimantan Timur
Lokasi : Jl. A. Wahab Syahranie

RENCANA ANGGARAN BIAYA

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA


Rp. Rp.

I. PEKERJAAN PENDAHULUAN
1 Papan Nama Proyek 1.00 Ls 500,000.00 500,000.00
2 Pagar proyek 125.00 m1 284,175.00 35,521,875.00
3 Direksi keet 1.00 ls 12,000,000.00 12,000,000.00
4 Gudang dan alat‐alat sementara 1.00 ls 12,000,000.00 12,000,000.00
5 Penyediaan air & listrik untuk kerja 1.00 Ls 5,000,000.00 5,000,000.00
6 Administrasi dan dokumentasi 1.00 Ls 750,000.00 750,000.00
SUBTOTAL I. PEKERJAAN PENDAHULUAN 65,771,875.00

II PEKERJAAN PEMBANGUNAN MASJID


II.1 PEKERJAAN SUB STRUKTUR
II.1.1 PEKERJAAN TANAH & PASIR
1 Galian pondasi 91.53 m3 46,600.00 4,265,298.00
2 Urugan tanah kembali 37.73 m3 22,335.00 842,699.55
3 Urugan tanah peninggian lantai 20.60 m3 122,975.00 2,533,285.00
4 Urugan pasir (bawah lantai) 20.60 m3 181,650.00 3,741,990.00

II.1.2 PEKERJAAN PONDASI


1 Cor beton lantai K225 15.45 m3 1,481,815.00 22,894,041.75
2 Aanstamping batu gunung 9.25 m3 558,885.00 5,169,686.25
3 Pasangan batu gunung 1:3 30.48 m3 1,014,375.00 30,918,150.00
4 Pancang ulin 10/10 ‐ 2 m + kalang sunduk 36.00 titik 207,290.00 7,462,440.00
5 Pancang ulin 10/10 ‐ 12m 148.00 titik 1,069,800.00 158,330,400.00
6 Pondasi poer P1 (uk. 100x100x30 cm) 9.60 m3 8,771,508.00 84,206,476.80
7 Pondasi poer P2 (uk. 80x80x30 cm) 1.92 m3 9,241,203.00 17,743,109.76
Sub total III.1 338,107,577.11
II.2 PEKERJAAN STRUKTUR BETON
1  Kolom K1  Ø30 1.79 m3 14,570,154.04 26,080,575.73
2  Kolom K2 30/30 12.64 m3 14,655,475.29 185,245,207.67
3  Kolom K3 20/20 3.15 m3 14,914,391.84 46,980,334.30
4  Kolom KP 13/13 0.28 m3 12,672,747.89 3,548,369.41
5  Sloof S1 20/30 8.46 m3 12,233,762.62 103,497,631.77
6  Sloof S2 15/20 1.38 m3 13,240,058.73 18,271,281.05
7  Balok B1 20/30 6.65 m3 14,141,048.27 94,037,971.00
8  Balok B2 15/25 3.88 m3 18,513,443.19 71,832,159.58
9  Balok RB 15/20 2.69 m3 15,862,594.38 42,670,378.88
10  Talang beton 9.88 m3 6,434,304.19 63,570,925.40
11  Plat atap dak tebal 12 cm 2.88 m3 7,621,721.52 21,950,557.98
Sub total III.2 677,685,392.74
II.3 PEKERJAAN STRUKTUR
II.3.1 PEKERJAAN PASANGAN DINDING & LANTAI
1 Dinding pasangan bata camp. 1 : 4 259.71 m2 316,627.36 82,231,291.67
2 Plesteran dinding & kolom 712.71 m2 68,685.00 48,952,486.35
3 Lantai keramik 60/60 200.00 m2 368,680.00 73,736,000.00
4 Lantai keramik tile 20/20 kasar (t.wudlu & toilet) 21.00 m2 258,840.00 5,435,640.00
5 Lantai tangga keramik tile 40/40 kasar 10.98 m2 321,995.00 3,535,505.10
6 Dinding  keramik 60/60 (Mihrab) 6.00 m2 428,763.20 2,572,579.20
7 Dinding keramik tile 20/25 (t.wudlu & toilet) 66.56 m2 272,535.00 18,139,929.60
8 List dinding keramik 5/20 (t.wudlu & toilet) 32.00 m1 86,872.50 2,779,920.00
9 Lapis waterprofing plat atap dak 17.56 m2 73,650.00 1,293,294.00
Sub total III.3.1 238,676,645.92
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
Rp. Rp.
II.3.2 PEKERJAAN KUSEN, PINTU DAN JENDELA
1 Pintu type PJ1 3.00 bh 6,000,000.00 18,000,000.00
2 Pintu type P1 2.00 bh 900,000.00 1,800,000.00
3 Pintu type P2 2.00 bh 850,000.00 1,700,000.00
4 Jendela type J1 6.00 bh 2,500,000.00 15,000,000.00
5 Jendela type J2 5.00 bh 1,500,000.00 7,500,000.00
6 Jendela type J3 8.00 bh 1,000,000.00 8,000,000.00
7 Jendela BV 4.00 bh 400,000.00 1,600,000.00
Sub total III.3.2 53,600,000.00

II.3.3 PEKERJAAN ATAP & PLAFOND


1 Rangka plafond metal furing 181.00 m2 222,165.00 40,211,865.00
2 Penutup plafond gypsumboard 9 mm 160.00 m2 64,581.00 10,332,960.00
3 Penutup plafond calcyboard  21.00 m2 78,307.50 1,644,457.50
4 List plafond profil gypsum  182.20 m1 79,095.00 14,411,109.00
5 Rangka atap baja ringan 143.44 m2 255,685.00 36,675,456.40
6 Atap metal sheet 143.44 m2 97,165.00 13,937,347.60
7 Bubungan atap metal 16.00 m1 116,445.00 1,863,120.00
8 Listplank fiber cement / GRC 40.00 m1 211,675.00 8,467,000.00
9 Kubah masjid (bentuk & dimensi sesuai gambar) 1.00 Ls 200,000,000.00 200,000,000.00
- Rangka pipa galvanis
- Penutup plat galvalume finish powder coating
Sub total III.3.3 327,543,315.50
II.3.4 PEKERJAAN CAT-CATAN
1 Cat dinding eksterior / interior 712.71 m2 63,457.50 45,226,794.83
2 Cat plafond 181.00 m2 58,517.50 10,591,667.50
Sub total III.3.4 55,818,462.33
II.4 PEKERJAAN MEKANIKAL ELEKTRIKAL
II.4.1 PEKERJAAN SANITAIR
1 Pasang klosed duduk + asesories  2.00 bh 3,611,050.00 7,222,100.00
2 Pasang wastafel 2.00 bh 2,370,850.00 4,741,700.00
3 Bak mandi fiber 2.00 bh 1,271,200.00 2,542,400.00
4 Pasang kran air stainless 10.00 bh 147,450.00 1,474,500.00
5 Pasang kran air jet shower + asesories 2.00 bh 342,450.00 684,900.00
6 Pasang floor drain stainless  8.00 bh 179,325.00 1,434,600.00
7 Pasang roof drain stainless 9.00 bh 65,000.00 585,000.00
8 Pasang pipa PVC dia. 1/2" AW (air bersih)  30.00 m1 44,230.00 1,326,900.00
9 Pasang pipa PVC dia. 3" AW (air kotor cair) 25.00 m1 116,195.00 2,904,875.00
10 Pasang pipa PVC dia. 3" AW (air hujan) 34.00 m1 116,195.00 3,950,630.00
11 Pasang pipa PVC dia. 4" AW (air kotor padat) 12.00 m1 15,649,500.00 187,794,000.00
12 Biotech septictank (inc. penggalian dan pondasi) 1.00 bh 8,000,000.00 8,000,000.00
 Type Anaerob System, bahan fiberglass, vol. 1.5 m3 
Sub total II.4.1 222,661,605.00
II.4.2 PEKERJAAN INSTALASI LISTRIK
1 Kabel feeder ke panel utama  20.00 m 200,000.00 4,000,000.00
2 Instalasi penerangan, NYA 3x2,5mm2 dlm pipa conduit 29.00 titik 42,473,000.00 1,231,717,000.00
3 Instalasi kotak kontak, NYA 3x2,5mm2 dlm pipa conduit 5.00 titik 42,473,000.00 212,365,000.00
4 Stop kontak (1Ph/220‐240V/10A) 5.00 buah 8,981,500.00 44,907,500.00
5 Saklar tunggal (1Ph/220‐240V/10A) 5.00 buah 6,381,500.00 31,907,500.00
6 Saklar ganda (1Ph/220‐240V/10A) 5.00 buah 82,815.00 414,075.00
7 Lampu Downlight RD PLC 18 watt + assesories 20.00 buah 433,815.00 8,676,300.00
8 Lampu SL 18 watt + assesories 8.00 buah 108,815.00 870,520.00
9 Lampu gantung 1.00 buah 20,000,000.00 20,000,000.00
10 Box Panel + Asesories 1.00 unit 450,000.00 450,000.00
11 Grounding / Pentanahan 1.00 Ls 300,000.00 300,000.00
12 Testing Commisining  1.00 Ls 700,000.00 700,000.00
Sub total III.4.2 1,556,307,895.00
II.5 PEKERJAAN LAIN-LAIN
1 Mahkota kubah kecil 4.00 buah 1,500,000.00 6,000,000.00
2 Mahkota kubah utama 1.00 buah 3,200,000.00 3,200,000.00
3 Railing selasar 26.00 m2 500,000.00 13,000,000.00
Sub total III.5 22,200,000.00
ANALISA SATUAN PEKERJAAN
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii

A. PEKERJAAN PERSIAPAN

1 1 M' Mengukur dan Memasang Bouwplank - SNI 03-2835-2002


0.012 M3 Balok Meranti 5/7 Cm 5,500,000.00 66,000.00 66,000.00
0.007 M3 Papan Meranti 2/20 Cm 4,000,000.00 28,000.00 28,000.00
0.020 Kg Paku Biasa 20,000.00 400.00 400.00
0.100 OH Tukang 140,000.00 14,000.00 14,000.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00 1,500.00
0.100 OH Pekerja 100,000.00 10,000.00 10,000.00
0.005 OH Mandor 165,000.00 825.00 825.00
Jumlah Total 94,400.00 26,325.00 120,725.00
2 1 M' Pembuatan Pagar Sementara Dari Seng gelombang tinggi 2m (SNI.Rev.2002)
1.250 Btg Kayu Dolken dia. 8‐10/400 cm 16,900.00 21,125.00 21,125.00
2.500 Kg Semen 1,500.00 3,750.00 3,750.00
1.200 Lbr Seng Gelombang 45,000.00 54,000.00 54,000.00
0.005 M3 Pasir Pasang 150,000.00 750.00 750.00
0.009 M3 Koral Beton 450,000.00 4,050.00 4,050.00
0.025 M3 Kayu Kelas II 5,000,000.00 125,000.00 125,000.00
0.060 Kg Paku Biasa 20,000.00 1,200.00 1,200.00
0.400 OH Pekerja Biasa 100,000.00 40,000.00 40,000.00
0.200 OH Tukang Kayu 140,000.00 28,000.00 28,000.00
0.020 OH Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 OH Mandor 165,000.00 3,300.00 3,300.00
Jumlah Total 209,875.00 74,300.00 284,175.00

B. PEKERJAAN TANAH DAN PONDASI

1 1 M3 Galian Tanah Biasa - SNI 2835 : 2008


0.400 OH Pekerja 100,000.00 40,000.00 40,000.00
0.040 OH Mandor 165,000.00 6,600.00 6,600.00
Jumlah Total 46,600.00 46,600.00
2 1 M3 Urugan Tanah Kembali - SNI 2835 : 2008
0.192 OH Pekerja 100,000.00 19,200.00 19,200.00
0.019 OH Mandor 165,000.00 3,135.00 3,135.00
Jumlah Total 22,335.00 22,335.00
3 1 M3 Urugan Pasir - SNI 2835 : 2008
1.200 M3 Pasir 125,000.00 150,000.00 150,000.00
0.300 OH Pekerja 100,000.00 30,000.00 30,000.00
0.010 OH Mandor 165,000.00 1,650.00 1,650.00
Jumlah Total 150,000.00 31,650.00 181,650.00
4 1 M3 Memadatkan Tanah
0.300 OH Pekerja 100,000.00 30,000.00 30,000.00
0.040 OH Mandor 165,000.00 6,600.00 6,600.00
0.005 Jam Vibratory Roller 5 - 8 T 450,000.00 2,250.00 2,250.00
Jumlah Total 2,250.00 36,600.00 38,850.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
5 1 M3 Urugan tanah dipadatkan
1.000 M3 Tanah Urugan 55,000.00 55,000.00 55,000.00
0.250 OH Pekerja 100,000.00 25,000.00 25,000.00
0.025 OH Mandor 165,000.00 4,125.00 4,125.00
1.000 M3 Memadatkan tanah 38,850.00 38,850.00 38,850.00
Jumlah Total 55,000.00 67,975.00 122,975.00
6 1 M3 Pas. Batu aanstamping (batu gunung) - SNI 2836 : 2008
1.200 M3 Batu gunung 300,000.00 360,000.00 360,000.00
0.432 M3 Pasir Urugan 125,000.00 54,000.00 54,000.00
0.390 OH Tukang 140,000.00 54,600.00 54,600.00
0.039 OH Kepala Tukang 150,000.00 5,850.00 5,850.00
0.780 OH Pekerja 100,000.00 78,000.00 78,000.00
0.039 OH Mandor 165,000.00 6,435.00 6,435.00
Jumlah Total 414,000.00 144,885.00 558,885.00
7 1 M3 Pas. Pondasi Batu Gunung 1Pc : 3Ps SNI 2836:2008
1.200 M3 Batu gunung 300,000.00 360,000.00 360,000.00
202.000 Kg Semen PC 1,500.00 303,000.00 303,000.00
0.485 M3 Pasir Pasangan 150,000.00 72,750.00 72,750.00
0.750 OH Tukang 140,000.00 105,000.00 105,000.00
0.075 OH Kepala Tukang 150,000.00 11,250.00 11,250.00
1.500 OH Pekerja 100,000.00 150,000.00 150,000.00
0.075 OH Mandor 165,000.00 12,375.00 12,375.00
Jumlah Total 735,750.00 278,625.00 1,014,375.00
8 1 M3 Pekerjaan Agregat
0.050 OH Pekerja 100,000.00 5,000.00 5,000.00
0.007 OH Mandor 165,000.00 1,155.00 1,155.00
1.200 M3 Agregat Klas B 682,000.00 818,400.00 818,400.00
0.005 Jam Vibratory Roller 5 - 8 T 450,000.00 2,250.00 2,250.00
Jumlah Total 820,650.00 6,155.00 826,805.00
9 1 M2 Pas. paving blok 
27.0000 Bh Paving blok 3,000.00 81,000.00 81,000.00
0.1000 Kg Pasir Urug 125,000.00 12,500.00 12,500.00
0.0750 Jam Stemper duduk 32,000.00 2,400.00 2,400.00
0.5000 OH Tukang  140,000.00 70,000.00 70,000.00
0.0500 OH Kepala tukang 150,000.00 7,500.00 7,500.00
0.2500 OH Pekerja  100,000.00 25,000.00 25,000.00
0.0250 OH Mandor 165,000.00 4,125.00 4,125.00
Jumlah Total 95,900.00 106,625.00 202,525.00

C. PEKERJAAN PANCANG
1 1 M' Biaya Memancang tiang 10 x 10
0.1250 OH Pekerja 100,000.00 12,500.00 12,500.00
0.0500 OH Tukang 140,000.00 7,000.00 7,000.00
0.0050 OH Kep. Tukang 150,000.00 750.00 750.00
0.0130 OH mandor 165,000.00 2,145.00 2,145.00
Jumlah Total 22,395.00 22,395.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
2 1 Titik Memancang tiang Ulin 10x10, p = 2 m
0.0200 m3 Kayu ulin 10x10 5,000,000.00 100,000.00 100,000.00
0.0100 m3 Kalang dan sunduk 62,000.00 620.00 620.00
2.0000 m' Memancang tiang 22,395.00 44,790.00 44,790.00
Jumlah Total 100,620.00 44,790.00 145,410.00
3 1 m' Memancang Tiang Ulin 10/10 (menggunakan alat alat)
0.0750 jam Drop hammer 500,000.00 37,500.00 37,500.00
0.0170 Oh Pekerja  100,000.00 1,700.00 1,700.00
0.0170 Oh Tukang Pancang 140,000.00 2,380.00 2,380.00
0.0080 Oh Mandor 165,000.00 1,320.00 1,320.00
Jumlah Total 42,900.00 42,900.00
4 1 Titik Memancang tiang Ulin 10x10, p = 4 m
0.0370 m3 Kayu ulin 10x10 5,000,000.00 185,000.00 185,000.00
4.0000 m' Memancang tiang (menggunakan alat) 42,900.00 171,600.00 171,600.00
Jumlah Total 185,000.00 171,600.00 356,600.00
5 1 M3 Pekerjaan balok ulin 10/10
1.0500 m3 Kayu ulin 10x10 5,000,000.00 5,250,000.00 5,250,000.00
10.0000 kg Besi strip 34,000.00 340,000.00 340,000.00
0.8000 kg Paku biasa 2" ‐ 5" 20,000.00 16,000.00 16,000.00
6.0000 OH Tukang  140,000.00 840,000.00 840,000.00
1.2000 OH Kepala tukang 150,000.00 180,000.00 180,000.00
3.0000 OH Pekerja  100,000.00 300,000.00 300,000.00
0.2000 OH Mandor 165,000.00 33,000.00 33,000.00
Jumlah Total 5,606,000.00 1,353,000.00 6,959,000.00

D. PEKERJAAN PASANGAN DAN LANTAI


1 1 m2  Pas. Batu bata camp 1 Pc : 4 Ps SNI 6897:2008
70.0000 Bh Batu bata 1,000.00 70,000.00 70,000.00
11.5000 Kg Semen PC 1,500.00 17,250.00 198,375.00
0.0430 M3 Pasir pasangan  150,000.00 6,450.00 277.35
0.1000 OH Tukang  140,000.00 14,000.00 14,000.00
0.0100 OH Kepala tukang 150,000.00 1,500.00 1,500.00
0.3000 OH Pekerja  100,000.00 30,000.00 30,000.00
0.0150 OH Mandor 165,000.00 2,475.00 2,475.00
Jumlah Total 93,700.00 47,975.00 316,627.35
2 1 M2  Pas. Batu bata camp 1 Pc : 2 Ps SNI 6897:2008
70.0000 Bh Batu bata 1,000.00 70,000.00 70,000.00
18.9500 Kg Semen PC 1,500.00 28,425.00 28,425.00
0.0380 M3 Pasir pasangan  150,000.00 5,700.00 5,700.00
0.1000 OH Tukang  140,000.00 14,000.00 14,000.00
0.0100 OH Kepala tukang 150,000.00 1,500.00 1,500.00
0.3000 OH Pekerja  100,000.00 30,000.00 30,000.00
0.0150 OH Mandor 165,000.00 2,475.00 2,475.00
Jumlah Total 104,125.00 47,975.00 152,100.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
3 1 M2 Plesteran tebal 15 mm 1 Pc : 4 Ps SNI 2837:2008
6.2400 Kg Semen Pc 1,500.00 9,360.00 9,360.00
0.0240 M3 Pasir pasangan  150,000.00 3,600.00 3,600.00
0.1500 OH Tukang  140,000.00 21,000.00 21,000.00
0.0150 OH Kepala tukang 150,000.00 2,250.00 2,250.00
0.3000 OH Pekerja  100,000.00 30,000.00 30,000.00
0.0150 OH Mandor 165,000.00 2,475.00 2,475.00
Jumlah Total 12,960.00 55,725.00 68,685.00
4 1 M2 Plesteran tebal 15 mm 1 Pc : 2 Ps SNI 2837:2008
10.2240 Kg Semen Pc 1,500.00 15,336.00 15,336.00
0.0200 M3 Pasir pasangan  150,000.00 3,000.00 3,000.00
0.1500 OH Tukang  140,000.00 21,000.00 21,000.00
0.0150 OH Kepala tukang 150,000.00 2,250.00 2,250.00
0.3000 OH Pekerja  100,000.00 30,000.00 30,000.00
0.0150 OH Mandor 165,000.00 2,475.00 2,475.00
Jumlah Total 18,336.00 55,725.00 74,061.00
5 1 M2 Acian SNI 2837:2008
3.2500 Kg Semen Pc 1,500.00 4,875.00 4,875.00
0.2000 Oh Pekerja 150,000.00 30,000.00 30,000.00
0.1000 OH Tukang 140,000.00 14,000.00 14,000.00
0.0100 OH Kepala tukang 150,000.00 1,500.00 1,500.00
0.0100 OH Mandor 165,000.00 1,650.00 1,650.00
Jumlah Total 4,875.00 47,150.00 52,025.00
6 1 M1 Pekerjaan profilan/skonengan
0.5000 Kg Semen Pc 1,500.00 750.00 750.00
0.0020 M3 Pasir pasangan  150,000.00 300.00 300.00
0.1500 OH Tukang 140,000.00 21,000.00 21,000.00
0.0100 OH Mandor 165,000.00 1,650.00 1,650.00
Jumlah Total 1,050.00 22,650.00 23,700.00
7 1 M2 Pas. Lantai keramik 20 x 20 cm SNI 7395:2008
1.0500 m2 Keramik 20x20 175,000.00 183,750.00 183,750.00
10.4000 Kg Semen Pc 1,500.00 15,600.00 15,600.00
1.6200 Kg Semen warna 1,500.00 2,430.00 2,430.00
0.0450 M3 Pasir pasangan  150,000.00 6,750.00 6,750.00
0.1350 OH Tukang  140,000.00 18,900.00 18,900.00
0.0140 OH Kepala tukang 150,000.00 2,100.00 2,100.00
0.2700 OH Pekerja  100,000.00 27,000.00 27,000.00
0.0140 OH Mandor 165,000.00 2,310.00 2,310.00
Jumlah Total 208,530.00 50,310.00 258,840.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
8 1 M2 Pas. Lantai Keramik 40 x 40 cm SNI 7395:2008
1.0500 m2 Keramik 40x40 240,000.00 252,000.00 252,000.00
9.8000 Kg Semen Pc 1,500.00 14,700.00 14,700.00
1.3000 Kg Semen warna 1,500.00 1,950.00 1,950.00
0.0450 M3 Pasir pasangan  150,000.00 6,750.00 6,750.00
0.1250 OH Tukang  140,000.00 17,500.00 17,500.00
0.0130 OH Kepala tukang 150,000.00 1,950.00 1,950.00
0.2500 OH Pekerja  100,000.00 25,000.00 25,000.00
0.0130 OH Mandor 165,000.00 2,145.00 2,145.00
Jumlah Total 275,400.00 46,595.00 321,995.00
9 1 M2 Pas. Lantai keramik 60 x 60 cm SNI 7395:2008
1.0500 m2 Keramik tile 60/60 286,000.00 300,300.00 300,300.00
9.6000 Kg Semen Pc 1,500.00 14,400.00 14,400.00
1.3000 Kg Semen warna 1,500.00 1,950.00 1,950.00
0.0450 M3 Pasir pasangan  150,000.00 6,750.00 6,750.00
0.1250 OH Tukang  140,000.00 17,500.00 17,500.00
0.0120 OH Kepala tukang 150,000.00 1,800.00 1,800.00
0.2400 OH Pekerja  100,000.00 24,000.00 24,000.00
0.0120 OH Mandor 165,000.00 1,980.00 1,980.00
Jumlah Total 323,400.00 45,280.00 368,680.00
10 1 M2 Pas. Dinding keramik 20 x 25 cm SNI 7395:2008
1.0500 m2 Keramik 20x25 136000 142,800.00 142,800.00
9.3000 Kg Semen Pc 1,500.00 13,950.00 13,950.00
1.9400 Kg Semen warna 1,500.00 2,910.00 2,910.00
0.0180 M3 Pasir pasangan  150,000.00 2,700.00 2,700.00
0.4000 OH Tukang  140,000.00 56,000.00 56,000.00
0.0450 OH Kepala tukang 150,000.00 6,750.00 6,750.00
0.4000 OH Pekerja  100,000.00 40,000.00 40,000.00
0.0450 OH Mandor 165,000.00 7,425.00 7,425.00
Jumlah Total 162,360.00 110,175.00 272,535.00
11 1 M2 Pas. Dinding keramik 60 x 60 cm SNI 7395:2008
1.3000 m2 Keramik 60/60 286,000.00 371,800.00 371,800.00
4.1666 Kg Semen Sikka @25kg 2,000.00 8,333.20 8,333.20
1.3000 Kg Semen warna 1,500.00 1,950.00 1,950.00
1.0000 Lot Alat bantu 2,100.00 2,100.00 2,100.00
0.1200 OH Tukang  140,000.00 16,800.00 16,800.00
0.0120 OH Kepala tukang 150,000.00 1,800.00 1,800.00
0.2400 OH Pekerja  100,000.00 24,000.00 24,000.00
0.0120 OH Mandor 165,000.00 1,980.00 1,980.00
Jumlah Total 384,183.20 44,580.00 428,763.20
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
12 1 M2 Pas. List keramik 5 x 20 cm SNI 7395:2008
1.0500 m1 Keramik List 5x20 58,000.00 60,900.00 60,900.00
1.1400 Kg Semen Pc 1,500.00 1,710.00 1,710.00
0.0250 Kg Semen warna 1,500.00 37.50 37.50
0.0030 M3 Pasir pasangan  150,000.00 450.00 450.00
0.0900 OH Tukang  140,000.00 12,600.00 12,600.00
0.0090 OH Kepala tukang 150,000.00 1,350.00 1,350.00
0.0900 OH Pekerja  100,000.00 9,000.00 9,000.00
0.0050 OH Mandor 165,000.00 825.00 825.00
Jumlah Total 63,097.50 23,775.00 86,872.50

E. PEKERJAAN BETON
1 1 M2 Pekerjaan bekisitng untuk Pondasi  ‐ SNI 7394:2008
0.040 M3 Kayu Perancah 3,000,000.00 120,000.00 120,000.00
0.300 Kg Paku biasa 20,000.00 6,000.00 6,000.00
0.100 Ltr Minyak begisting 27,000.00 2,700.00 2,700.00
0.260 OH Tukang  140,000.00 36,400.00 36,400.00
0.026 OH Kepala tukang 150,000.00 3,900.00 3,900.00
0.520 OH Pekerja 100,000.00 52,000.00 52,000.00
0.026 OH Mandor 165,000.00 4,290.00 4,290.00
Jumlah Total 128,700.00 96,590.00 225,290.00
2 1 M2 Pekerjaan bekisitng untuk sloof  ‐ SNI 7394:2008
0.045 M3 Kayu Perancah 3,000,000.00 135,000.00 135,000.00
0.300 Kg Paku biasa 20,000.00 6,000.00 6,000.00
0.100 Ltr Minyak begisting 27,000.00 2,700.00 2,700.00
0.260 OH Tukang  140,000.00 36,400.00 36,400.00
0.026 OH Kepala tukang 150,000.00 3,900.00 3,900.00
0.520 OH Pekerja 100,000.00 52,000.00 52,000.00
0.026 OH Mandor 165,000.00 4,290.00 4,290.00
Jumlah Total 143,700.00 96,590.00 240,290.00
3 1 M2 Pekerjaan bekisting untuk kolom ‐ SNI 7394:2008 SNI 7394:2008
0.040 M3 Kayu Perancah 3,000,000.00 120,000.00 120,000.00
0.400 Kg Paku biasa 20,000.00 8,000.00 8,000.00
0.200 Ltr Minyak begisting 27,000.00 5,400.00 5,400.00
0.015 m3 Balok Kayu Kelas II 5,000,000.00 75,000.00 75,000.00
0.350 Lbr Plywood 9 mm 120,000.00 42,000.00 42,000.00
2.000 btg Dolken Kayu Galam Ø 8‐10 cm, p:4 m 16,900.00 33,800.00 33,800.00
0.330 OH Tukang  140,000.00 46,200.00 46,200.00
0.033 OH Kepala tukang 150,000.00 4,950.00 4,950.00
0.660 OH Pekerja 100,000.00 66,000.00 66,000.00
0.033 OH Mandor 165,000.00 5,445.00 5,445.00
Jumlah Total 284,200.00 122,595.00 406,795.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
4 1 M2 Pekerjaan bekisitng untuk kolom Praktis
0.003 M3 Kayu Perancah 3,000,000.00 9,000.00 9,000.00
0.400 Kg Paku biasa 20,000.00 8,000.00 8,000.00
0.200 Ltr Minyak begisting 27,000.00 5,400.00 5,400.00
0.117 Lbr Plywood 9 mm 120,000.00 14,040.00 14,040.00
0.300 OH Tukang  140,000.00 42,000.00 42,000.00
0.030 OH Kepala tukang 150,000.00 4,500.00 4,500.00
0.600 OH Pekerja 100,000.00 60,000.00 60,000.00
0.030 OH Mandor 165,000.00 4,950.00 4,950.00
Jumlah Total 36,440.00 111,450.00 147,890.00
5 1 M2 Pekerjaan Begisting Balok SNI 7394:2008
0.040 M3 Kayu Perancah 3,000,000.00 120,000.00 120,000.00
0.400 Kg Paku biasa 20,000.00 8,000.00 8,000.00
0.200 Ltr Minyak begisting 27,000.00 5,400.00 5,400.00
0.018 m3 Balok Kayu Kelas II 5,000,000.00 90,000.00 90,000.00
0.350 Lbr Plywood 9 mm 120,000.00 42,000.00 42,000.00
2.000 btg Dolken Kayu Galam Ø 8‐10 cm, p:4 m 16,900.00 33,800.00 33,800.00
0.330 OH Tukang  140,000.00 46,200.00 46,200.00
0.033 OH Kepala tukang 150,000.00 4,950.00 4,950.00
0.320 OH Pekerja 100,000.00 32,000.00 32,000.00
0.006 OH Mandor 165,000.00 990.00 990.00
Jumlah Total 299,200.00 84,140.00 383,340.00
6 1 M2 Pekerjaan Begisting Lantai / Slab  SNI 7394:2008
0.040 M3 Kayu Perancah 3,000,000.00 120,000.00 120,000.00
0.400 Kg Paku biasa 20,000.00 8,000.00 8,000.00
0.200 Ltr Minyak begisting 27,000.00 5,400.00 5,400.00
0.015 m3 Balok Kayu Kelas II 5,000,000.00 75,000.00 75,000.00
0.350 Lbr Plywood 9 mm 120,000.00 42,000.00 42,000.00
6.000 btg Dolken Kayu Galam Ø 8‐10 cm, p:4 m 16,900.00 101,400.00 101,400.00
0.330 OH Tukang  140,000.00 46,200.00 46,200.00
0.033 OH Kepala tukang 150,000.00 4,950.00 4,950.00
0.660 OH Pekerja 100,000.00 66,000.00 66,000.00
0.033 OH Mandor 165,000.00 5,445.00 5,445.00
Jumlah Total 351,800.00 122,595.00 474,395.00
7  1 M3. Beton Lantai Kerja mutu K‐100 (fc=7,4 Mpa, 3‐6, w/c 0,87) SNI 7394:2008
0.638 m3 Pasir beton 280,000.00 178,640.00 178,640.00
0.761 m3 Koral Beton 450,000.00 342,450.00 342,450.00
230.000 kg Semen 1,500.00 345,000.00 345,000.00
200.000 Ltr Air 1,000.00 200,000.00 200,000.00
0.200 OH Tukang 140,000.00 28,000.00 28,000.00
0.020 OH Kepala Tukang 150,000.00 3,000.00 3,000.00
1.200 OH Pekerja 100,000.00 120,000.00 120,000.00
0.060 OH Mandor 165,000.00 9,900.00 9,900.00
Jumlah Total 1,066,090.00 160,900.00 1,226,990.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
8  1 M3. Beton Lantai Kerja mutu K‐175 (fc=14,5 Mpa, slump 12 ±2 cm, w/c 0,66) SNI 7394:2008
0.543 m3 Pasir beton 280,000.00 152,040.00 152,040.00
0.762 m3 Koral Beton 450,000.00 342,900.00 342,900.00
326.000 kg Semen 1,500.00 489,000.00 489,000.00
215.000 Ltr Air 1,000.00 215,000.00 215,000.00
0.275 OH Tukang 140,000.00 38,500.00 38,500.00
0.028 OH Kepala Tukang 150,000.00 4,200.00 4,200.00
1.650 OH Pekerja 100,000.00 165,000.00 165,000.00
0.083 OH Mandor 165,000.00 13,695.00 13,695.00
Jumlah Total 1,198,940.00 221,395.00 1,420,335.00
9  1 M3. Beton Lantai Kerja mutu K‐225 (fc=19,3 Mpa, slump 12 ±2 cm, w/c 0,58) SNI 7394:2008
0.499 m3 Pasir beton 280,000.00 139,720.00 139,720.00
0.776 m3 Koral Beton 0.00 - -
371.000 kg Semen 0.00 - -
215.000 Ltr Air 1,000.00 215,000.00 215,000.00
0.275 OH Tukang 140,000.00 38,500.00 38,500.00
0.028 OH Kepala Tukang 150,000.00 4,200.00 4,200.00
1.650 OH Pekerja 100,000.00 165,000.00 165,000.00
0.083 OH Mandor 165,000.00 13,695.00 13,695.00
Jumlah Total 354,720.00 221,395.00 576,115.00
10 1 Kg Pekerjaan Tulangan Beton SNI 7394:2008
1.0500 Kg Besi  0.00 - -
0.0150 Kg Kawat Bendrat 0.00 - -
0.0070 OH Tukang  0.00 - -
0.0070 OH Kepala tukang 0.00 - -
0.0070 OH Pekerja 0.00 - -
0.0004 OH Mandor 0.00 - -
Jumlah Total - - -
11 1 M3 Plat Dekker (tebal 15 cm)
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
170.448 Kg Besi - - -
4.242 M2 Bekisting 474,395.00 2,012,383.59 2,012,383.59
Jumlah Total 2,588,498.59 2,588,498.59
12 1 M3 Plat Dekker (tebal 20 cm)
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
131.769 Kg Besi - - -
2.917 M2 Bekisting 474,395.00 1,383,810.22 1,383,810.22
Jumlah Total 1,959,925.22 1,959,925.22
13 1 M3 Pondasi poer P1 (uk. 100x100x30 cm)
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
263.000 Kg Besi - - -
4.000 M2 Bekisting 225,290.00 901,160.00 901,160.00
Jumlah Total 1,477,275.00 1,477,275.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
14 1 M3 Pondasi poer P2 (uk. 80x80x30 cm)
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
276.150 Kg Besi - - -
4.667 M2 Bekisting 225,290.00 1,051,428.43 1,051,428.43
Jumlah Total 1,627,543.43 1,627,543.43
15 1 M3 Kolom K1  dia.30
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
254.371 Kg Besi - - -
16.985 M2 Bekisting 406,795.00 6,909,413.08 6,909,413.08
Jumlah Total 7,485,528.08 7,485,528.08
16 1 M3 Kolom K2  30/30
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
274.379 Kg Besi - - -
16.000 M2 Bekisting 406,795.00 6,508,720.00 6,508,720.00
Jumlah Total 7,084,835.00 7,084,835.00
17 1 M3 Kolom K3  20/20
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
218.051 Kg Besi - - -
20.000 M2 Bekisting 406,795.00 8,135,900.00 8,135,900.00
Jumlah Total 8,712,015.00 8,712,015.00
18 1 M3 Kolom KP 13/13
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
320.204 Kg Besi - - -
23.077 M2 Bekisting 147,890.00 3,412,857.53 3,412,857.53
Jumlah Total 3,988,972.53 3,988,972.53
19 1 M3 Sloof S1 20/30
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
310.739 Kg Besi - - -
13.333 M2 Bekisting 240,290.00 3,203,786.57 3,203,786.57
Jumlah Total 3,779,901.57 3,779,901.57
20 1 M3 Sloof S2 15/20
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
302.705 Kg Besi - - -
18.333 M2 Bekisting 240,290.00 4,405,236.57 4,405,236.57
Jumlah Total 4,981,351.57 4,981,351.57
21 1 M3 Balok B1 20/30
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
310.739 Kg Besi - - -
13.333 M2 Bekisting 383,340.00 5,111,072.22 5,111,072.22
Jumlah Total 5,687,187.22 5,687,187.22
22 1 M3 Balok B2 15/25
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
427.615 Kg Besi - - -
17.333 M2 Bekisting 383,340.00 6,644,432.22 6,644,432.22
Jumlah Total 7,220,547.22 7,220,547.22
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
23 1 M3 Balok RB  15/20
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
302.705 Kg Besi - - -
18.333 M2 Bekisting 383,340.00 7,027,772.22 7,027,772.22
Jumlah Total 7,603,887.22 7,603,887.22
24 1 M3 Balok Talang Beton
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
85.523 Kg Besi - - -
7.500 M2 Bekisting 383,340.00 2,875,050.00 2,875,050.00
Jumlah Total 3,451,165.00 3,451,165.00
25  1 M3 Plat atap dak tebal 12cm
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
90.024 Kg Besi - - -
8.333 M2 Bekisting 474,395.00 3,953,133.54 3,953,133.54
Jumlah Total 4,529,248.54 4,529,248.54
26 1 M3 Plat lantai pembesian wiremesh M.10
1.000 M3 Beton K.225 576,115.00 576,115.00 576,115.00
85.100 Kg Besi wiremesh M.10 0.00 - -
Jumlah Total 576,115.00 576,115.00
H. PEKERJAAN ATAP DAN PLAFOND
1 1 M2 Mengerjakan kuda‐kuda / Frame & Rangka atap baja ringan
1.440 M' Canal C 65x26 0.00 - -
3.650 M' Reng ( type U ) 0,4 TCT 0.00 - -
47.600 Pcs Screw 12‐14x20 0.00 - -
40.040 Pcs Screw 10‐16x16 0.00 - -
1.520 Pcs L Braket 0.00 - -
1.840 Pcs Dynabolt 0.00 - -
0.050 OH Tukang 0.00 - -
0.010 OH Kepala tukang 0.00 - -
0.500 OH Pekerja 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
2 1 M2 Memasang atap Genteng Metal
1.050 Lbr Genteng Metal  0.00 - -
0.200 Kg Paku Genteng  0.00 - -
0.100 OH Tukang 0.00 - -
0.010 OH Kepala tukang 0.00 - -
0.200 OH Pekerja 0.00 - -
0.001 OH Mandor 0.00 - -
Jumlah Total - - -
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
3 1 M1 Memasang Bubungan Genteng Metal
1.100 Bh Bubungan Genteng Metal 0.00 - -
0.050 Kg Paku Genteng  0.00 - -
0.150 OH Tukang 0.00 - -
0.015 OH Kepala tukang 0.00 - -
0.250 OH Pekerja 0.00 - -
0.013 OH Mandor 0.00 - -
Jumlah Total - - -
4 1 M'  listplank GRC
1.100 Lbr GRC Board 0.00 - -
0.100 Kg Paku  - - -
0.200 OH Tukang 0.00 - -
0.025 OH Kepala tukang 0.00 - -
0.100 OH Pekerja 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
5 1 M2 Rangka Plafond Hollow
3.500 m' Besi Hollow  0.00 - -
1.000 Ls Gantungan kawat 20,000.00 20,000.00 20,000.00
3.000 bh Dynabolt 0.00 - -
0.250 Oh Pekerja 0.00 - -
0.300 Oh Tukang 0.00 - -
0.050 Oh Kepala Tukang 0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total 20,000.00 - 20,000.00
6 1 M2 Memasang Plafond Gypsum ‐ SNI 2839 : 2008
0.364 M2 Gypsum board 0.00 - -
0.110 Kg Paku gypsum 0.00 - -
0.050 OH Tukang 0.00 - -
0.005 OH Kepala tukang kayu 0.00 - -
0.100 OH Pekerja 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
7 1 M2 Memasang Plafond Calsiboard ‐ SNI 03‐2838‐2002
0.3600 M2 Calsiboard 0.00 - -
0.0300 Kg Paku gypsum 0.00 - -
0.1000 OH Tukang 0.00 - -
0.0100 OH Kepala tukang kayu 0.00 - -
0.0700 OH Pekerja 0.00 - -
0.0035 OH Mandor 0.00 - -
Jumlah Total - - -
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
8 1 M' List Plafond Gypsum SNI 2839 : 2008
1.050 M2 List Gypsum 0.00 - -
0.150 Kg Tepung gypsum 0.00 - -
0.060 OH Tukang 0.00 - -
0.006 OH Kepala tukang kayu 0.00 - -
0.060 OH Pekerja 0.00 - -
0.003 OH Mandor 0.00 - -
Jumlah Total - - -

I. PEKERJAAN PENGECATAN
1 1 M2 Mengecat dinding Luar SNI ‐ 2002
0.2600 Kg Cat Dinding Luar 0.00 - -
0.1000 Ltr Cat dasar 0.00 - -
0.1000 Kg Plamir 0.00 - -
1.0000 Lbr Kertas gosok 0.00 - -
0.0630 OH Tukang  0.00 - -
0.0063 OH Kepala tukang  0.00 - -
0.0200 OH Pekerja 0.00 - -
0.0025 OH Mandor 0.00 - -
Jumlah Total - - -
2 1 M2 Mengecat dinding dalam & Plafon  SNI ‐ 2002
0.2600 Kg Cat Dinding Dalam 2x 0.00 - -
0.1000 kg Cat dasar 0.00 - -
0.1000 Kg Plamir tembok 0.00 - -
1.0000 Lbr Kertas gosok 0.00 - -
0.0630 OH Tukang  0.00 - -
0.0063 OH Kepala tukang  0.00 - -
0.0200 OH Pekerja 0.00 - -
0.0025 OH Mandor 0.00 - -
Jumlah Total - - -
3  1 M2 Waterproofing atap plat beton
1.0500 m2 Waterproofing Coating ( 2 lapis @1Kg ) 0.00 - -
1.0000 m2 Screed t=1,5 cm 35,000.00 35,000.00 35,000.00
1.0000 m2 Upah mengecat 25,000.00 25,000.00 25,000.00
Jumlah Total 35,000.00 25,000.00 60,000.00

J. PEKERJAAN SANITAIR
1 1 BH Memasang Klosed Duduk SNI ‐ 2002
1.0000 Bh Kloset Duduk 0.00 - -
0.0600 Ls Perlengkapan 6% harga kloset 0.00 - -
3.3000 Oh Pekerja 0.00 - -
0.1600 Oh Mandor 0.00 - -
1.1000 Oh Tukang Batu 0.00 - -
0.0010 Oh Kepala Tukang 0.00 - -
Jumlah Total - - -
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
2 1 BH Memasang Wastafel SNI ‐ 2002
1.0000 Bh Wastafel 0.00 - -
0.0600 Ls Perlengkapan 6% harga wastafel 0.00 - -
3.3000 Oh Pekerja 0.00 - -
0.1600 Oh Mandor 0.00 - -
1.1000 Oh Tukang Batu 0.00 - -
0.0010 Oh Kepala Tukang 0.00 - -
Jumlah Total - - -
3 Memasang Satu Buah Bak Mandi Fiber
1.0000 Bh Bak mandi fiber 0.00 - -
0.0600 Bh Perlengkapan 6% harga bak  0.00 - -
1.2000 OH Pekerja Biasa 0.00 - -
1.0000 OH Tukang Batu 0.00 - -
0.7000 OH Mandor 0.00 - -
Jumlah Total - - -
4 Memasang 1 Buah Kran 
1.000 Bh Kran air 0.00 - -
0.025 Bh Seal tape 0.00 - -
0.010 OH Pekerja 0.00 - -
0.100 OH Tukang Batu 0.00 - -
0.010 OH Kepala Tukang 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
5 Memasang 1 Buah Jet shower
1.000 Bh Jet shower 0.00 - -
0.025 Bh Seal tape 0.00 - -
0.010 OH Pekerja 0.00 - -
0.100 OH Tukang Batu 0.00 - -
0.010 OH Kepala Tukang 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
6 Memasang 1 Buah Floor Drain
1.000 Bh Floor Drain 0.00 - -
0.010 OH Pekerja 0.00 - -
0.100 OH Tukang Batu 0.00 - -
0.010 OH Kepala Tukang 0.00 - -
0.005 OH Mandor 0.00 - -
Jumlah Total - - -
7 1 M' Pipa PVC AW 1/2" SNI ‐ 2002
1.200 m' Pipa PVC AW 1/2" 0.00 - -
0.350 - Perlengkapan 35 % harga Pipa 0.00 - -
0.036 Oh Pekerja 0.00 - -
0.060 Oh Tukang 0.00 - -
0.006 Oh Kepala Tukang 0.00 - -
0.002 Oh Mandor 0.00 - -
Jumlah Total - - -
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
8 1 M' Pipa PVC AW 1" SNI ‐ 2002
1.200 m' Pipa PVC AW 1" 0.00 - -
0.350 - Perlengkapan 35 % harga Pipa 0.00 - -
0.072 Oh Pekerja 0.00 - -
0.120 Oh Tukang 0.00 - -
0.012 Oh Kepala Tukang 0.00 - -
0.003 Oh Mandor 0.00 - -
Jumlah Total - - -
9 1 M' Pipa PVC AW 2" SNI ‐ 2002
1.200 m' Pipa PVC AW 2" 0.00 - -
0.350 - Perlengkapan 35 % harga Pipa 0.00 - -
0.072 Oh Pekerja 0.00 - -
0.120 Oh Tukang 0.00 - -
0.012 Oh Kepala Tukang 0.00 - -
0.003 Oh Mandor 0.00 - -
Jumlah Total - - -
10 1 M' Pipa PVC AW 3" SNI ‐ 2002
1.200 m' Pipa PVC AW 3" 0.00 - -
0.350 - Perlengkapan 35 % harga Pipa 0.00 - -
0.072 Oh Pekerja 0.00 - -
0.120 Oh Tukang 0.00 - -
0.012 Oh Kepala Tukang 0.00 - -
0.003 Oh Mandor 0.00 - -
Jumlah Total - - -
11 1 M' Pipa PVC AW 4" SNI ‐ 2002
1.200 m' Pipa PVC AW 4" 0.00 - -
0.350 - Perlengkapan 35 % harga Pipa 0.00 - -
0.072 Oh Pekerja 0.00 - -
0.120 Oh Tukang 0.00 - -
0.012 Oh Kepala Tukang 0.00 - -
0.003 Oh Mandor 0.00 - -
Jumlah Total - - -

K. PEKERJAAN LISTRIK
1 1 Titik Pasang Instalasi Titik Lampu / Stop Kontak
10.000 M' Pipa PVC 1/2" protector kabel / Conduit  0.00 - -
1.000 Bh Tee Doos 3 Lubang 1,500.00 1,500.00 1,500.00
1.000 Bh Tee Doos 4 Lubang 1,600.00 1,600.00 1,600.00
10.000 M' Kabel NYM 3 x 2,5 mm2 7,500.00 75,000.00 75,000.00
3.000 Bh Sok Counduit 800.00 2,400.00 2,400.00
4.000 M' Fleksibel Pipa conduit 11,000.00 44,000.00 44,000.00
10.000 Bh Klem Pipa  1,000.00 10,000.00 10,000.00
0.550 Bh Isolasi 25,000.00 13,750.00 13,750.00
0.004 Oh Mandor 0.00 - -
0.433 Oh Tukang listrik 0.00 - -
0.152 Oh Pekerja 0.00 - -
Jumlah Total 148,250.00 - 148,250.00
HARGA HARGA JUMLAH
KODE INDEX SAT. URAI AN SATUAN BAHAN UPAH HARGA
(Rp) (Rp) (Rp) (Rp)
i ii iii iv v vi vii viii
2 1 Bh Pasang Saklar Tunggal
1.000 Bh Saklar TunggaL 0.00 - -
0.100 Oh Pekerja 0.00 - -
0.010 Oh Tukang  0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total - - -
3 1 Bh Pasang Saklar Ganda
1.000 Bh Saklar double 0.00 - -
0.100 Oh Pekerja 0.00 - -
0.010 Oh Tukang  0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total - - -
4 1 Bh Pasang Stop Kontak
1.000 Bh Stop kontak 0.00 - -
0.100 Oh Pekerja 0.00 - -
0.010 Oh Tukang  0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total - - -
5 1 Bh Pasang DL 18 Watt
1.000 Bh DL 18 Watt 0.00 - -
0.100 Oh Pekerja 0.00 - -
0.010 Oh Tukang  0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total - - -
6 1 Bh Pasang Lampu SL 18 Watt
1.000 Bh SL 18 Watt 0.00 - -
0.100 Oh Pekerja 0.00 - -
0.010 Oh Tukang  0.00 - -
0.001 Oh Mandor 0.00 - -
Jumlah Total - - -
DAFTAR HARGA SATUAN UPAH DAN BAHAN

HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )

A HARGA BAHAN / MATERIAL


1 Perkerja OH Dilokasi
2 Tukang OH Dilokasi
3 Kepala Tukang OH Dilokasi
4 Mandor OH Dilokasi

B DAFTAR HARGA SATUAN BAHAN

I BAHAN BATU, TANAH & SEMEN


1 Pasir pasang m3 Dilokasi
2 Pasir Beton m3 Dilokasi
3 Pasir Urug m3 Dilokasi
4 Koral Beton m3 Dilokasi
5 Tanah Urug m3 Dilokasi
6 Batu Gunung m3 Dilokasi
7 Batu Bata Bh Dilokasi
8 Paving Block Bh Dilokasi
9 Agregat klas B m3 Dilokasi
10 Keramik lantai 20 x 20 setara Roman m2 Dilokasi
11 Keramik 40/40 polish m2 Dilokasi
12 Keramik 60/60 polish m2 Dilokasi
13 Keramik dinding 20 x 25 setara Roman m2 Dilokasi
14 List Keramik dinding 5 x 20 setara Roman m1 Dilokasi
15 Marmer / granit uk. 100 x 100 cm m2 Dilokasi
16 Semen Warna Kg Dilokasi
17 Semen PC Kg Dilokasi
18 Air Ltr Dilokasi
19 Tanah Humus m3 Dilokasi

II BAHAN LOGAM
1 Paku biasa Kg Dilokasi
2 Paku gypsum Kg Dilokasi
3 Paku plywood Kg Dilokasi
4 Paku Genteng Metal Kg Dilokasi
5 Besi Tulangan Kg Dilokasi
6 Kawat Bendrat Kg Dilokasi
7 Besi wiremesh M.10 Kg Dilokasi
8 Canal C75,75 m' Dilokasi
9 Reng (type U) 0,4 TCT m' Dilokasi
10 Screw 12-14 x 20 Pcs Dilokasi
11 Screw 10-16 x 16 Pcs Dilokasi
12 L Braket Pcs Dilokasi
13 Dynabolt Pcs Dilokasi
14 Besi Profil Kg Dilokasi
15 Besi Hollow 4 x 4 m' Dilokasi
16 Kusen Alumunium silver m' Dilokasi
17 Rangka Jendela Alumunium silver m' Dilokasi
18 Daun Pintu Alumunium m2 Dilokasi
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )

III BAHAN KAYU DAN PLYWOOD


1 Papan Bengkirai m3 Dilokasi
2 Balok Bengkirai m3 Dilokasi
3 Papan Ulin m3 Dilokasi
4 Balok Ulin 10/10 m3 Dilokasi
5 Balok Ulin 15/15 m3 Dilokasi
6 Papan Meranti m3 Dilokasi
7 Balok Meranti m3 Dilokasi
8 Kayu Perancah m3 Dilokasi
9 Kayu Kapur (balok) m3 Dilokasi
10 Dolken Kayu Galam Btg Dilokasi
11 Teakwood 4 mm Lbr Dilokasi
12 Plywood 9 mm Lbr Dilokasi
13 Calciboard 6 mm Lbr Dilokasi
14 Lem Kayu Kg Dilokasi
15 Gipsum 9 mm Lbr Dilokasi
16 GRC 9 mm m' Dilokasi
17 List Gypsum m' Dilokasi
18 List Profil Kayu Bengkirai m' Dilokasi
19 Tepung Gypsum Kg Dilokasi

IV BAHAN KUNCI PENGGANTUNG


1 Engsel daun pintu setara SES Bh Dilokasi
2 Engsel Casement Jendela setara SES Set Dilokasi
3 Lock Case incl Cillinder Bh Dilokasi
4 Handle Pintu Utama Set Dilokasi
5 Lever Handle Bh Dilokasi
6 Expanyolet setara SES Set Dilokasi
7 Rambucis non lokcing setara SES Bh Dilokasi
8 Kaca bening 5 mm m2 Dilokasi

V BAHAN ATAP
1 Atap Genteng Metal Lbr Dilokasi
2 Bubungan Atap Genteng Metal Bh Dilokasi
3 Seng Gelombang Lbr Dilokasi

VI BAHAN CAT - CATAN


1 Cat Interior setara Mowilex Kg Dilokasi
2 Cat Exterior setara Mowilex Kg Dilokasi
3 Cat Dasar Kg Dilokasi
4 Plamir dinding Kg Dilokasi
5 Cat Kilat Kg Dilokasi
6 Waterproof Kg Dilokasi
7 Dempul Kg Dilokasi
8 Cat dasar / meni Kg Dilokasi
9 Kuas Bh Dilokasi
10 Kertas gosok Lbr Dilokasi
11 Tinner Ltr Dilokasi
12 Minyak bekisting Ltr Dilokasi
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )

VII BAHAN SANITAIR DAN PIPA


1 Klosed Duduk TOTO - setara Bh Dilokasi
2 Bak mandi fiber Bh Dilokasi
3 Washtafel Bh Dilokasi
4 Jet Shower TOTO Bh Dilokasi
5 Kran air TOTO Bh Dilokasi
6 Seal Tape Bh Dilokasi
7 Floor drain TOTO Bh Dilokasi
8 Pipa PVC 0/5 " m' Dilokasi
9 Pipa PVC 1" m' Dilokasi
10 Pipa PVC 2" m' Dilokasi
11 Pipa PVC 3" m' Dilokasi
12 Pipa PVC 4" m' Dilokasi

VIII LISTRIK
1 Lampu TL 2x36 Watt RMI Bh Dilokasi
2 Lampu Downlight 18 Watt Bh Dilokasi
3 Lampu SL 18 Watt Bh Dilokasi
4 Lampu Pijar Bh Dilokasi
5 Stop Kontak Bh Dilokasi
6 Saklar Tunggal Bh Dilokasi
7 Saklar Ganda Bh Dilokasi

C DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA


1 Concrete Mixer 0.3 - 0.6 M3 jam
2 Dump Truck 3.5 Ton jam
3 Generator Set jam
4 Motor Grader > 100 Hp jam
5 Wheel Loader 1.0 - 1.6 M3 jam
6 Tandem Roller 6 - 8 T jam
7 Vibratory Roller 5 - 8 T jam
8 Concrete Vibrator jam
9 Water Pump 70 - 100 mm jam
10 Water Tangker 3000 - 4500 L jam
11 Stemper duduk jam
TIME SCHEDULE
Program : PENGELOLAAN RUANG TERBUKA HIJAU DAN RUANG IBADAH
Kegiatan : PEKERJAAN LANDSCAPE DAN MUSHOLLA SMP NEGERI 2
KEC. KOTA BANGUN, KAB. KUTAI KARTANEGARA-KALIMANTAN TIMUR
Lokasi : JL. AWANG LONG RT.1 DESA LIANG ULU, KEC. KOTA BANGUN
Jangka Waktu Pelaksanaan : 90 Hari kalender

BOBOT Sept Oktober November Desember


NO URAIAN PEKERJAAN
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13
100
I. PEKERJAAN PENDAHULUAN 3.52 3.523
II. PEKERJAAN SARANA INFRASTRUKTUR & LANDSCAPE 90
II.1 PEKERJAAN PEMATANGAN LAHAN & TURAP #REF! ### ### ### ### ### ### ### ### ###
II.2 PEKERJAAN DRAINASE #REF! ### ### ### ### 80
II.3 PEKERJAAN JALAN LINGKUNGAN & AREAL PARKIR #REF! ### ### ### ### ###
II.4 PEKERJAAN AREAL UPACARA #REF! ### ### ### 70
II.5 PEKERJAAN LANDSCAPE #REF! ### ### ###
III. PEKERJAAN PEMBANGUNAN MASJID 60
III.1 PEKERJAAN SUB STRUKTUR 18.11 6.037 6.037 6.037
III.2 PEKERJAAN STRUKTUR BETON 36.30 7.261 7.261 7.261 7.261 7.261 50
III.3 PEKERJAAN ARSITEKTUR
III.3.1 PEKERJAAN PASANGAN DINDING & LANTAI 12.79 4.262 4.262 4.262 40
III.3.2 PEKERJAAN KUSEN, PINTU DAN JENDELA 2.87 1.436 1.436
III.3.3 PEKERJAAN ATAP & PLAFOND 17.55 5.849 5.849 5.849 30
III.3.4 PEKERJAAN CAT-CATAN 2.99 1.495 1.495
III.4 PEKERJAAN MEKANIKAL ELEKTRIKAL 20
III.4.1 PEKERJAAN SANITAIR 1.97 0.984 0.984
III.4.2 PEKERJAAN INSTALASI LISTRIK 2.71 1.356 1.356 10
III.5 PEKERJAAN LAIN-LAIN 1.19 0.595 0.595
0

Jumlah Bobot Rencana #REF! ### ### ### ### ### ### ### ### ### ### ### ### 3.45

Kumulatif Bobot Rencana 0.00 ### ### ### ### ### ### ### ### ### ### ### ### #REF!

Jumlah Bobot Realisasi

Kumulatif Bobot Realisasi

0
0
0

0
0
DAFTAR HARGA SATUAN UPAH DAN BAHAN

HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )

A HARGA BAHAN / MATERIAL


1 Perkerja OH 70,000.00 Dilokasi
2 Tukang OH 80,000.00 Dilokasi
3 Kepala Tukang OH 110,000.00 Dilokasi
4 Mandor OH 130,000.00 Dilokasi

B DAFTAR HARGA SATUAN BAHAN

I BAHAN BATU, TANAH & SEMEN


1 Pasir pasang m3 214,000.00 Dilokasi
2 Pasir Beton m3 350,000.00 Dilokasi
3 Pasir Urug m3 135,000.00 Dilokasi
4 Koral Beton m3 690,000.00 Dilokasi
5 Tanah Urug m3 52,500.00 Dilokasi
6 Batu Gunung m3 450,000.00 Dilokasi
7 Batu Bata Bh 3,250.00 Dilokasi
8 Paving Block Bh 5,000.00 Dilokasi
9 Agregat klas B m3 525,000.00 Dilokasi
10 Keramik lantai 20 x 20 setara Roman m2 135,000.00 Dilokasi
11 Keramik 40/40 polish m2 185,000.00 Dilokasi
12 Keramik 60/60 polish m2 220,000.00 Dilokasi
13 Keramik dinding 20 x 25 setara Roman m2 105,000.00 Dilokasi
14 List Keramik dinding 5 x 20 setara Roman m1 45,000.00 Dilokasi
15 Marmer / granit uk. 100 x 100 cm m2 1,250,000.00 Dilokasi
16 Semen Warna Kg 13,000.00 Dilokasi
17 Semen PC Kg 1,700.00 Dilokasi
18 Air Ltr 145.00 Dilokasi
19 Tanah Humus m3 210,000.00 Dilokasi
-
II BAHAN LOGAM -
1 Paku biasa Kg 18,500.00 Dilokasi
2 Paku gypsum Kg 32,000.00 Dilokasi
3 Paku plywood Kg 22,500.00 Dilokasi
4 Paku Genteng Metal Kg 35,000.00 Dilokasi
5 Besi Tulangan Kg 17,500.00 Dilokasi
6 Kawat Bendrat Kg 26,000.00 Dilokasi
7 Besi wiremesh M.10 Kg 19,000.00 Dilokasi
8 Canal C75,75 m' 23,500.00 Dilokasi
9 Reng (type U) 0,4 TCT m' 17,500.00 Dilokasi
10 Screw 12-14 x 20 Pcs 500.00 Dilokasi
11 Screw 10-16 x 16 Pcs 375.00 Dilokasi
12 L Braket Pcs 6,000.00 Dilokasi
13 Dynabolt Pcs 3,000.00 Dilokasi
14 Besi Profil Kg 27,500.00 Dilokasi
15 Besi Hollow 4 x 4 m' 26,000.00 Dilokasi
16 Kusen Alumunium silver m' 170,000.00 Dilokasi
17 Rangka Jendela Alumunium silver m' 160,000.00 Dilokasi
18 Daun Pintu Alumunium m2 795,000.00 Dilokasi
-
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )
-
III BAHAN KAYU DAN PLYWOOD -
1 Papan Bengkirai m3 5,550,000.00 Dilokasi
2 Balok Bengkirai m3 5,150,000.00 Dilokasi
3 Papan Ulin m3 5,850,000.00 Dilokasi
4 Balok Ulin 10/10 m3 5,150,000.00 Dilokasi
5 Balok Ulin 15/15 m3 5,350,000.00 Dilokasi
6 Papan Meranti m3 3,350,000.00 Dilokasi
7 Balok Meranti m3 3,000,000.00 Dilokasi
8 Kayu Perancah m3 3,050,000.00 Dilokasi
9 Kayu Kapur (balok) m3 3,850,000.00 Dilokasi
10 Dolken Kayu Galam Btg 13,000.00 Dilokasi
11 Teakwood 4 mm Lbr 85,000.00 Dilokasi
12 Plywood 9 mm Lbr 115,000.00 Dilokasi
13 Calciboard 6 mm Lbr 115,000.00 Dilokasi
14 Lem Kayu Kg 15,000.00 Dilokasi
15 Gipsum 9 mm Lbr 87,500.00 Dilokasi
16 GRC 9 mm m' 75,000.00 Dilokasi
17 List Gypsum m' 38,500.00 Dilokasi
18 List Profil Kayu Bengkirai m' 25,000.00 Dilokasi
19 Tepung Gypsum Kg 55,000.00 Dilokasi
-
IV BAHAN KUNCI PENGGANTUNG -
1 Engsel daun pintu setara SES Bh 58,500.00 Dilokasi
2 Engsel Casement Jendela setara SES Set 180,000.00 Dilokasi
3 Lock Case incl Cillinder Bh 250,000.00 Dilokasi
4 Handle Pintu Utama Set 275,000.00 Dilokasi
5 Lever Handle Bh 120,000.00 Dilokasi
6 Expanyolet setara SES Set 250,000.00 Dilokasi
7 Rambucis non lokcing setara SES Bh 55,000.00 Dilokasi
8 Kaca bening 5 mm m2 135,000.00 Dilokasi
-
V BAHAN ATAP -
1 Atap Genteng Metal Lbr 62,500.00 Dilokasi
2 Bubungan Atap Genteng Metal Bh 45,000.00 Dilokasi
3 Seng Gelombang Lbr 35,000.00 Dilokasi
-
VI BAHAN CAT - CATAN -
1 Cat Interior setara Mowilex Kg 80,000.00 Dilokasi
2 Cat Exterior setara Mowilex Kg 95,000.00 Dilokasi
3 Cat Dasar Kg 60,000.00 Dilokasi
4 Plamir dinding Kg 50,000.00 Dilokasi
5 Cat Kilat Kg 56,500.00 Dilokasi
6 Waterproof Kg 10,000.00 Dilokasi
7 Dempul Kg 22,500.00 Dilokasi
8 Cat dasar / meni Kg 44,000.00 Dilokasi
9 Kuas Bh 12,500.00 Dilokasi
10 Kertas gosok Lbr 4,000.00 Dilokasi
11 Tinner Ltr 20,000.00 Dilokasi
12 Minyak bekisting Ltr 21,000.00 Dilokasi
-
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )
-
VII BAHAN SANITAIR DAN PIPA -
1 Klosed Duduk TOTO - setara Bh 2,250,000.00 Dilokasi
2 Bak mandi fiber Bh 650,000.00 Dilokasi
3 Washtafel Bh 1,350,000.00 Dilokasi
4 Jet Shower TOTO Bh 250,000.00 Dilokasi
5 Kran air TOTO Bh 100,000.00 Dilokasi
6 Seal Tape Bh 3,500.00 Dilokasi
7 Floor drain TOTO Bh 125,000.00 Dilokasi
8 Pipa PVC 0/5 " m' 15,000.00 Dilokasi
9 Pipa PVC 1" m' 21,000.00 Dilokasi
10 Pipa PVC 2" m' 27,000.00 Dilokasi
11 Pipa PVC 3" m' 45,000.00 Dilokasi
12 Pipa PVC 4" m' 65,000.00 Dilokasi
-
VIII LISTRIK -
1 Lampu TL 2x36 Watt RMI Bh 550,000.00 Dilokasi
2 Lampu Downlight 18 Watt Bh 325,000.00 Dilokasi
3 Lampu SL 18 Watt Bh 75,000.00 Dilokasi
4 Lampu Pijar Bh 35,000.00 Dilokasi
5 Stop Kontak Bh 60,000.00 Dilokasi
6 Saklar Tunggal Bh 40,000.00 Dilokasi
7 Saklar Ganda Bh 55,000.00 Dilokasi

C DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA


1 Concrete Mixer 0.3 - 0.6 M3 jam 65,000.00
2 Dump Truck 3.5 Ton jam 350,000.00
3 Generator Set jam 300,000.00
4 Motor Grader > 100 Hp jam 550,000.00
5 Wheel Loader 1.0 - 1.6 M3 jam 450,000.00
6 Tandem Roller 6 - 8 T jam 350,000.00
7 Vibratory Roller 5 - 8 T jam 450,000.00
8 Concrete Vibrator jam 60,000.00
9 Water Pump 70 - 100 mm jam 160,000.00
10 Water Tangker 3000 - 4500 L jam 330,000.00
11 Stemper duduk jam 32,000.00
DAFTAR HARGA SATUAN UPAH DAN BAHAN

HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )

A HARGA BAHAN / MATERIAL


1 Perkerja OH 100,000.00 Dilokasi
2 Tukang OH 140,000.00 Dilokasi
3 Kepala Tukang OH 150,000.00 Dilokasi
4 Mandor OH 165,000.00 Dilokasi

B DAFTAR HARGA SATUAN BAHAN

I BAHAN BATU, TANAH & SEMEN


1 Pasir pasang m3 150,000.00 Dilokasi
2 Pasir Beton m3 280,000.00 Dilokasi
3 Pasir Urug m3 125,000.00 Dilokasi
4 Koral Beton m3 450,000.00 Dilokasi
5 Tanah Urug m3 55,000.00 Dilokasi
6 Batu Gunung m3 300,000.00 Dilokasi
7 Batu Bata Bh 1,000.00 Dilokasi
8 Paving Block Bh 3,000.00 Dilokasi
9 Agregat klas B m3 682,000.00 Dilokasi
10 Keramik lantai 20 x 20 setara Roman m2 175,000.00 Dilokasi
11 Keramik 40/40 polish m2 240,000.00 Dilokasi
12 Keramik 60/60 polish m2 286,000.00 Dilokasi
13 Keramik dinding 20 x 25 setara Roman m2 136,000.00 Dilokasi
14 List Keramik dinding 5 x 20 setara Roman m1 58,000.00 Dilokasi
15 Marmer / granit uk. 100 x 100 cm m2 1,625,000.00 Dilokasi
16 Semen Warna Kg 1,500.00 Dilokasi
17 Semen PC Kg 1,500.00 Dilokasi
18 Air Ltr 1,000.00 Dilokasi
19 Tanah Humus m3 273,000.00 Dilokasi

II BAHAN LOGAM
1 Paku biasa Kg 20,000.00 Dilokasi
2 Paku gypsum Kg 41,000.00 Dilokasi
3 Paku plywood Kg 29,000.00 Dilokasi
4 Paku Genteng Metal Kg 45,000.00 Dilokasi
5 Besi Tulangan Kg 20,000.00 Dilokasi
6 Kawat Bendrat Kg 33,000.00 Dilokasi
7 Besi wiremesh M.10 Kg 24,000.00 Dilokasi
8 Canal C75,75 m' 30,000.00 Dilokasi
9 Reng (type U) 0,4 TCT m' 22,000.00 Dilokasi
10 Screw 12-14 x 20 Pcs 700.00 Dilokasi
11 Screw 10-16 x 16 Pcs 500.00 Dilokasi
12 L Braket Pcs 8,000.00 Dilokasi
13 Dynabolt Pcs 4,000.00 Dilokasi
14 Besi Profil Kg 35,000.00 Dilokasi
15 Besi Hollow 4 x 4 m' 33,000.00 Dilokasi
16 Kusen Alumunium silver m' 221,000.00 Dilokasi
17 Rangka Jendela Alumunium silver m' 208,000.00 Dilokasi
18 Daun Pintu Alumunium m2 1,033,000.00 Dilokasi
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )

III BAHAN KAYU DAN PLYWOOD


1 Papan Bengkirai m3 6,250,000.00 Dilokasi
2 Balok Bengkirai m3 5,500,000.00 Dilokasi
3 Papan Ulin m3 6,250,000.00 Dilokasi
4 Balok Ulin 10/10 m3 5,000,000.00 Dilokasi
5 Balok Ulin 15/15 m3 6,955,000.00 Dilokasi
6 Papan Meranti m3 4,000,000.00 Dilokasi
7 Balok Meranti m3 3,000,000.00 Dilokasi
8 Kayu Perancah m3 3,000,000.00 Dilokasi
9 Kayu Kapur (balok) m3 5,000,000.00 Dilokasi
10 Dolken Kayu Galam Btg 16,900.00 Dilokasi
11 Teakwood 4 mm Lbr 110,000.00 Dilokasi
12 Plywood 9 mm Lbr 120,000.00 Dilokasi
13 Calciboard 6 mm Lbr 150,000.00 Dilokasi
14 Lem Kayu Kg 20,000.00 Dilokasi
15 Gipsum 9 mm Lbr 114,000.00 Dilokasi
16 GRC 9 mm m' 150,000.00 Dilokasi
17 List Gypsum m' 50,000.00 Dilokasi
18 List Profil Kayu Bengkirai m' 32,000.00 Dilokasi
19 Tepung Gypsum Kg 72,000.00 Dilokasi

IV BAHAN KUNCI PENGGANTUNG


1 Engsel daun pintu setara SES Bh 76,000.00 Dilokasi
2 Engsel Casement Jendela setara SES Set 234,000.00 Dilokasi
3 Lock Case incl Cillinder Bh 325,000.00 Dilokasi
4 Handle Pintu Utama Set 357,000.00 Dilokasi
5 Lever Handle Bh 156,000.00 Dilokasi
6 Expanyolet setara SES Set 325,000.00 Dilokasi
7 Rambucis non lokcing setara SES Bh 71,000.00 Dilokasi
8 Kaca bening 5 mm m2 150,000.00 Dilokasi

V BAHAN ATAP
1 Atap Genteng Metal Lbr 50,000.00 Dilokasi
2 Bubungan Atap Genteng Metal Bh 58,000.00 Dilokasi
3 Seng Gelombang Lbr 45,000.00 Dilokasi

VI BAHAN CAT - CATAN


1 Cat Interior setara Mowilex Kg 104,000.00 Dilokasi
2 Cat Exterior setara Mowilex Kg 123,000.00 Dilokasi
3 Cat Dasar Kg 78,000.00 Dilokasi
4 Plamir dinding Kg 65,000.00 Dilokasi
5 Cat Kilat Kg 73,000.00 Dilokasi
6 Waterproof Kg 13,000.00 Dilokasi
7 Dempul Kg 29,000.00 Dilokasi
8 Cat dasar / meni Kg 57,000.00 Dilokasi
9 Kuas Bh 16,000.00 Dilokasi
10 Kertas gosok Lbr 5,000.00 Dilokasi
11 Tinner Ltr 26,000.00 Dilokasi
12 Minyak bekisting Ltr 27,000.00 Dilokasi
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
( Rp. )

VII BAHAN SANITAIR DAN PIPA


1 Klosed Duduk TOTO - setara Bh 2,925,000.00 Dilokasi
2 Bak mandi fiber Bh 845,000.00 Dilokasi
3 Washtafel Bh 1,755,000.00 Dilokasi
4 Jet Shower TOTO Bh 325,000.00 Dilokasi
5 Kran air TOTO Bh 130,000.00 Dilokasi
6 Seal Tape Bh 5,000.00 Dilokasi
7 Floor drain TOTO Bh 162,000.00 Dilokasi
8 Pipa PVC 0/5 " m' 20,000.00 Dilokasi
9 Pipa PVC 1" m' 27,000.00 Dilokasi
10 Pipa PVC 2" m' 35,000.00 Dilokasi
11 Pipa PVC 3" m' 58,000.00 Dilokasi
12 Pipa PVC 4" m' 84,000.00 Dilokasi

VIII LISTRIK
1 Lampu TL 2x36 Watt RMI Bh 715,000.00 Dilokasi
2 Lampu Downlight 18 Watt Bh 422,000.00 Dilokasi
3 Lampu SL 18 Watt Bh 97,000.00 Dilokasi
4 Lampu Pijar Bh 45,000.00 Dilokasi
5 Stop Kontak Bh 78,000.00 Dilokasi
6 Saklar Tunggal Bh 52,000.00 Dilokasi
7 Saklar Ganda Bh 71,000.00 Dilokasi

C DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA


1 Concrete Mixer 0.3 - 0.6 M3 jam 65,000.00
2 Dump Truck 3.5 Ton jam 350,000.00
3 Generator Set jam 300,000.00
4 Motor Grader > 100 Hp jam 550,000.00
5 Wheel Loader 1.0 - 1.6 M3 jam 450,000.00
6 Tandem Roller 6 - 8 T jam 350,000.00
7 Vibratory Roller 5 - 8 T jam 450,000.00
8 Concrete Vibrator jam 60,000.00
9 Water Pump 70 - 100 mm jam 160,000.00
10 Water Tangker 3000 - 4500 L jam 330,000.00
11 Stemper duduk jam 32,000.00