HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME TOTAL HARGA
(RP)
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pasang Bouwplank m1 30.0 500,000 15,000,000
SUBTOTAL (I) PEKERJAAN PESIAPAN 15,000,000
II PEKERJAAN TANAH DAN PASIR
1 Galian tanah pondasi m3 18.0 39,000 702,000
2 Mengurug kembali galian pondasi m3 18.0 13,000 234,000
3 Urugan pasir bawah pondasi m3 18.0 117,000 2,106,000
4 Urugan tanah peninggian lantai disiram m3 18.0 91,500 1,647,000
5 Pemadatan tanah m3 18.0 29,000 522,000
SUBTOTAL (II) PEKERJAAN TANAH DAN PASIR 5,211,000
III PEKERJAAN PASANGAN
1 Pasangan batu kosong m3 2.0 298,000 596,000
2 Pasangan pondasi batu 1 pc : 5 ps m3 2.0 518,000 1,036,000
3 Pasangan dinding 1/2 bata 1 pc : 5 ps m2 20.0 87,000 1,740,000
4 Pasangan dinding 1/2 bata 1 pc : 3 ps m2 2.0 93,000 186,000
3,558,000
IV PEKEJAAN BETON
1 Sloop 13/20 m3 - 3,500,000 -
2 Kolom 13/20 m3 0.1 5,200,000 364,000
3 Balok 13/20 m3 0.5 4,468,000 2,234,000
4 Kolom praktis 10/10 m3 - 6,900,000 -
5 Kolom struktur 15/15 (selasar) m3 0.5 4,700,000 2,350,000
6 Balok ring, geuvel 10/15 m3 1.9 6,900,000 13,110,000
SUB TOTAL (IV) PEKERJAAN BETON 18,058,000
V PEKERJAAN PLESTERAN DAN LANTAI
1 Pek. Lantai keramik 50x50 (Lt.1+Lt.2) m2 162.0 180,000 29,160,000
2 Plesteran m2 162.0 42,000 6,804,000
3 Acian plesteran m2 162.0 23,000 3,726,000
SUB TOTAL (V) PEKERJAAN PLESTERAN DAN LANTAI 39,690,000
VI PEKERJAAN KAYU DAN ALUMINIUM
1 Listplank kayu klas II m' 30.0 61,700 1,851,000
2 Kusen kayu klas II m3 0.7 6,100,000 4,270,000
3 Daun jendela kaca m2 21.0 332,000 6,972,000
4 Daun pintu panil m2 3.2 466,000 1,491,200
5 Pek. Ventilasi krepyek m2 8.0 268,000 2,144,000
6 Kaca polos 3 mm m2 14.0 138,000 1,932,000
SUB TOTAL (VI) PEKERJAAN KAYU DAN ALUMINIUM 18,660,200
VII PEKERJAAN ATAP / PLAFOND
1 Pek. Rangka baja ringan m2 224.0 225,000 50,400,000
2 Atap genteng pejaten lokal m2 224.0 61,000 13,664,000
3 Bubungan genteng pejaten m' 17.0 37,000 629,000
4 Plafond calsiboard 3,5 mm rangka kayu m2 186.0 80,600 14,991,600
5 List gifsum C7 m' 156.0 25,000 3,900,000
SUB TOTAL (VII) PEKERJAAN ATAP / PLAFOND 83,584,600
VIII PEKERJAAN BESI
1 Kunci pintu 2 slang besar bh 4.0 250,000 1,000,000
2 Engsel pintu bh 6.0 55,000 330,000
3 Engsel jendela bh 44.0 23,200 1,020,800
4 Hak angin kecil bh 44.0 27,500 1,210,000
5 Grendel kecil bh 44.0 21,500 946,000
SUB TOTAL (VIII) PEKEJAAN BESI 4,506,800
IX PEKERJAAN INSTALASI LISTRIK
1 Titik lampu + instalasi bh 8.0 173,500 1,388,000
2 Lampu SL 18 watt bh 8.0 50,000 400,000
3 Saklar dobell bh 4.0 55,000 220,000
4 Saklar tunggal bh 2.0 55,000 110,000
5 Stop kontak bh 2.0 56,000 112,000
SUB TOTAL (IX) PEKERJAAN INSTALASI LISTRIK 2,230,000
X PEKERJAAN PENGECATAN
1 Cat tembok Gln 3.0 300,000 900,000
2 Cat plapond Klg 6.0 150,000 900,000
3 Cat kayu Klg 6.0 155,000 930,000
SUB TOTAL (X) PEKERJAAN PENGECATAN 2,730,000
XI PEKERJAAN REHAB/PENGADAAN MEUBLELAIR
REHABILITASI
1 Meja belajar bh 40.0 250,000 10,000,000
2 Kursi siswa bh 80.0 100,000 8,000,000
3 Meja kerja 1/2 biro bh 2.0 350,000 700,000
4 kursi kerja bh 2.0 175,000 350,000
5 lemari kelas bh 2.0 400,000 800,000
PENGADAAN
6 Meja belajar bh 40.0 650,000 26,000,000
7 Kursi siswa bh 80.0 175,000 14,000,000
8 Meja kerja 1/2 biro bh 2.0 725,000 1,450,000
9 kursi kerja bh 2.0 250,000 500,000
10 lemari kelas bh 2.0 1,350,000 2,700,000
11 Tempat sampah bh 2.0 100,000 200,000
12 Papan tulis (whiteboard) bh 2.0 350,000 700,000