Anda di halaman 1dari 4

RENCANA ANGGARAN BIAYA

KEGIATAN : PENGEMBANGAN SEKOLAH MENENGAH KEJURUAN


PEKERJAAN : REHABILITASI RUANG KELAS 3 LOKAL
LOKASI : SMK MA'ARIF NU 02 PAGUYANGAN
TAHUN ANGGARAN : 2021

HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME TOTAL HARGA
(RP)
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pasang Bouwplank m1 30.0 500,000 15,000,000
SUBTOTAL (I) PEKERJAAN PESIAPAN 15,000,000
II PEKERJAAN TANAH DAN PASIR
1 Galian tanah pondasi m3 18.0 39,000 702,000
2 Mengurug kembali galian pondasi m3 18.0 13,000 234,000
3 Urugan pasir bawah pondasi m3 18.0 117,000 2,106,000
4 Urugan tanah peninggian lantai disiram m3 18.0 91,500 1,647,000
5 Pemadatan tanah m3 18.0 29,000 522,000
SUBTOTAL (II) PEKERJAAN TANAH DAN PASIR 5,211,000
III PEKERJAAN PASANGAN
1 Pasangan batu kosong m3 2.0 298,000 596,000
2 Pasangan pondasi batu 1 pc : 5 ps m3 2.0 518,000 1,036,000
3 Pasangan dinding 1/2 bata 1 pc : 5 ps m2 20.0 87,000 1,740,000
4 Pasangan dinding 1/2 bata 1 pc : 3 ps m2 2.0 93,000 186,000
3,558,000
IV PEKEJAAN BETON
1 Sloop 13/20 m3 - 3,500,000 -
2 Kolom 13/20 m3 0.1 5,200,000 364,000
3 Balok 13/20 m3 0.5 4,468,000 2,234,000
4 Kolom praktis 10/10 m3 - 6,900,000 -
5 Kolom struktur 15/15 (selasar) m3 0.5 4,700,000 2,350,000
6 Balok ring, geuvel 10/15 m3 1.9 6,900,000 13,110,000
SUB TOTAL (IV) PEKERJAAN BETON 18,058,000
V PEKERJAAN PLESTERAN DAN LANTAI
1 Pek. Lantai keramik 50x50 (Lt.1+Lt.2) m2 162.0 180,000 29,160,000
2 Plesteran m2 162.0 42,000 6,804,000
3 Acian plesteran m2 162.0 23,000 3,726,000
SUB TOTAL (V) PEKERJAAN PLESTERAN DAN LANTAI 39,690,000
VI PEKERJAAN KAYU DAN ALUMINIUM
1 Listplank kayu klas II m' 30.0 61,700 1,851,000
2 Kusen kayu klas II m3 0.7 6,100,000 4,270,000
3 Daun jendela kaca m2 21.0 332,000 6,972,000
4 Daun pintu panil m2 3.2 466,000 1,491,200
5 Pek. Ventilasi krepyek m2 8.0 268,000 2,144,000
6 Kaca polos 3 mm m2 14.0 138,000 1,932,000
SUB TOTAL (VI) PEKERJAAN KAYU DAN ALUMINIUM 18,660,200
VII PEKERJAAN ATAP / PLAFOND
1 Pek. Rangka baja ringan m2 224.0 225,000 50,400,000
2 Atap genteng pejaten lokal m2 224.0 61,000 13,664,000
3 Bubungan genteng pejaten m' 17.0 37,000 629,000
4 Plafond calsiboard 3,5 mm rangka kayu m2 186.0 80,600 14,991,600
5 List gifsum C7 m' 156.0 25,000 3,900,000
SUB TOTAL (VII) PEKERJAAN ATAP / PLAFOND 83,584,600
VIII PEKERJAAN BESI
1 Kunci pintu 2 slang besar bh 4.0 250,000 1,000,000
2 Engsel pintu bh 6.0 55,000 330,000
3 Engsel jendela bh 44.0 23,200 1,020,800
4 Hak angin kecil bh 44.0 27,500 1,210,000
5 Grendel kecil bh 44.0 21,500 946,000
SUB TOTAL (VIII) PEKEJAAN BESI 4,506,800
IX PEKERJAAN INSTALASI LISTRIK
1 Titik lampu + instalasi bh 8.0 173,500 1,388,000
2 Lampu SL 18 watt bh 8.0 50,000 400,000
3 Saklar dobell bh 4.0 55,000 220,000
4 Saklar tunggal bh 2.0 55,000 110,000
5 Stop kontak bh 2.0 56,000 112,000
SUB TOTAL (IX) PEKERJAAN INSTALASI LISTRIK 2,230,000
X PEKERJAAN PENGECATAN
1 Cat tembok Gln 3.0 300,000 900,000
2 Cat plapond Klg 6.0 150,000 900,000
3 Cat kayu Klg 6.0 155,000 930,000
SUB TOTAL (X) PEKERJAAN PENGECATAN 2,730,000
XI PEKERJAAN REHAB/PENGADAAN MEUBLELAIR
REHABILITASI
1 Meja belajar bh 40.0 250,000 10,000,000
2 Kursi siswa bh 80.0 100,000 8,000,000
3 Meja kerja 1/2 biro bh 2.0 350,000 700,000
4 kursi kerja bh 2.0 175,000 350,000
5 lemari kelas bh 2.0 400,000 800,000
PENGADAAN
6 Meja belajar bh 40.0 650,000 26,000,000
7 Kursi siswa bh 80.0 175,000 14,000,000
8 Meja kerja 1/2 biro bh 2.0 725,000 1,450,000
9 kursi kerja bh 2.0 250,000 500,000
10 lemari kelas bh 2.0 1,350,000 2,700,000
11 Tempat sampah bh 2.0 100,000 200,000
12 Papan tulis (whiteboard) bh 2.0 350,000 700,000

SUB TOTAL (XI) PEKERJAAN PENGADAAN MEUBLAELAIR 65,400,000


TOTAL : I + II + III + IV + V + VI + VII + VIII + IX + X + XI 258,628,600
PEMBULATAN 182,631,000